udaya gamage 15 th november 2012 project based management

47
Udaya Gamage 15 th November 2012 Project Based Management

Upload: merry-simon

Post on 26-Dec-2015

224 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Udaya Gamage 15 th November 2012 Project Based Management

Udaya Gamage15th November 2012

Project Based Management

Page 2: Udaya Gamage 15 th November 2012 Project Based Management

Description Marks out of

Weighted average

Due Date

Assignment 1 100 5 28 Nov. 2012

Assignment 2 100 30 24 Dec. 2012

Assignment 3 100 65 4 Feb. 2012

Page 3: Udaya Gamage 15 th November 2012 Project Based Management

Assignment 1

Provide the following (no mark sheet is required)

Cover sheet (showing student details, etc)

Title or name of project

Brief background of the project (100 words approximately)

Explanation of the project status. • Is the project completed?• Is it under way?• Or is it yet to start?

Page 4: Udaya Gamage 15 th November 2012 Project Based Management

This is important in terms of your critical analysis in assignments 2 and 3 (50 words)

Justification of why the selected project is suitable for analysis of the topics in assignments 2 and 3 (50 words approximately)

Confirmation that you have a PMP available for analysis in assignment 3.

Page 5: Udaya Gamage 15 th November 2012 Project Based Management

Assignment 2 Topic: The Project Business Case Word Length – 2500 approximately

The cover or title page should have the followingTitle author date student number

Executive summary 100 -200 words (does not form the part of

assignment count) Why the report was prepared How it is structured what are the important findings conclusions and recommendations

Page 6: Udaya Gamage 15 th November 2012 Project Based Management

Assignment 2

Table of contents (respective page numbers of) executive summary Introduction Main sections References Individual appendices Figures and tables

Introduction 100 Words Why the report has been prepared What project is being analyzed How the report is structured

Page 7: Udaya Gamage 15 th November 2012 Project Based Management

Assignment 2

Project Background 100 words approximately Brief background of the project context

Business case (should provide) Justification for undertaking a project Evaluating the benefits, cost and risk of

alternative options and the rationale for the preferred solution

Page 8: Udaya Gamage 15 th November 2012 Project Based Management

Provide a critical analysis of the business case for your chosen project to cover the points below.

In what ways does your project conform (or not) to the definition of a project in the literature?

Who (or what) is the ‘sponsor’ of your project?

To what extent was a ‘business case’ created for this project (or should have been)?

In what ways are the benefits, cost and risk evaluated as part of the business case (or should have been)?

In what way/s is the preferred solution justified (or should have been)?

In what way is management commitment and approval for the investment obtained (or should have been)?

Page 9: Udaya Gamage 15 th November 2012 Project Based Management

Assignment 2

Conclusions 150 words approximately Lessons learned What findings are important for the management

in future projects What represent a threat to project success

Recommendations 150 words approximately How your project (or similar future projects)

should be managed in light of what you have learned from your analysis.

Page 10: Udaya Gamage 15 th November 2012 Project Based Management

Assignment 2

List of references – (using the Harvard AGPS system)

There should be at least 15 references Use the e-Journals and eBooks available from

the library website

Appendices

Turnitin Originality Report

Page 11: Udaya Gamage 15 th November 2012 Project Based Management

Assignment 3 Topic: The Project Management Plan Word Length 3000 – 4000 approximately Consists of two parts

body of the assignment and is a critical analysis of the chosen PMP

Appendix 1 which should be a practical Project Management Plan

The cover or title page should have the following

Title author date student number

Page 12: Udaya Gamage 15 th November 2012 Project Based Management

Assignment 3 Part 1: Critical Analysis of the Project Management Plan Executive summary

200 -250 words (does not form the part of assignment count)

Why the report was prepared How it is structured what are the important findings conclusions and recommendations

Page 13: Udaya Gamage 15 th November 2012 Project Based Management

Assignment 3 Table of contents (respective page numbers of)

executive summary Introduction Main sections References Individual appendices Figures and tables

Introduction 250 Words Why the report has been prepared What project is being analyzed How the report is structured

Page 14: Udaya Gamage 15 th November 2012 Project Based Management

Assignment 3 Project Background

250 words approximately Brief background of the project context

Structure and the contents of the PMP 1000 – 1500 approximately Provide a critical analysis of who is intended to

be the main audience of the PM plan? What do they need to know? How will they use the plan? What information needs to be provided? How should that information be provided? In what sequence? What does the theory say? What alternatives exist for the structure of a PM

plan (examine and compare a range of theories and opinions here)?

Page 15: Udaya Gamage 15 th November 2012 Project Based Management

Assignment 3 Provide a critical analysis of how the PM

plan has been structured relative to what theory suggests

Justify why the respective components have been included or explain why it should have been structured differently.

Contents of the PMP 1000 – 1500 words Why has a project schedule been included? Is it a meaningful document Was it prepared by the right people, does it

contain the right information, etc.?

Page 16: Udaya Gamage 15 th November 2012 Project Based Management

Assignment 3 Conclusions

250 words approximately Summarize your findings from the analysis of

your project management plan What did you find out about the project plan? Does it conform to the recognized theory? What aspects are important and are of

significance to project outcomes? What are its strengths and its weaknesses?

Page 17: Udaya Gamage 15 th November 2012 Project Based Management

Assignment 3 Recommendations

250 words approximately What are your recommendations flowing from

this analysis with regard to the PMP? What changes should be made to the PMP for

this project (or similar future projects)? Address the shortcomings identified in the

conclusions focus on recommendations related to the PMP

and not on the project itself.

List of references

Appendices

Page 18: Udaya Gamage 15 th November 2012 Project Based Management

Assignment 3 Part 2: Appendix 1 – The PMP Should include the following

project background, including an overview, brief description and a statement of objectives of the project

a summary of the management approach to be taken, who will manage the project, to whom do they report, how will project governance be achieved, etc.

detailed sections on the various aspects of the project that need to be managed (scope, time, cost, etc.)

additional information or documents to support the above

Turnitin Originality Report

Page 19: Udaya Gamage 15 th November 2012 Project Based Management

What is a project? Unique Novel Transient

How do you differentiate this with normal business?

delivering objectives with constraints of time, cost, and quality

What is a temporary organization in PM? Ex. of supertanker and flotilla of Yachts

How can we categorize projects? Runners, Repeaters, Strangers, and aliens

Page 20: Udaya Gamage 15 th November 2012 Project Based Management

What is the difference between the outcome/output of a project and the desired performance improvement? Ex, of A bridge across the Yangtze river

What do you think about the owner contractor model in a project?

Page 21: Udaya Gamage 15 th November 2012 Project Based Management

Core functions of PM (+ 2, risk and commitment of stakeholders need to be managed)

Page 22: Udaya Gamage 15 th November 2012 Project Based Management

Study table 1.2 of turner for tools and techniques of PM

Scope managed thro’ product breakdown structure Organization managed thro’ organization

breakdown structureQuality managed thro’ control techniquesCost is managed thro’ cost breakdown structure Time managed thro, networks and bar charts (CPA,

CPM, and PERT)

Page 23: Udaya Gamage 15 th November 2012 Project Based Management

Management of the project second dimension of the structured approach

The project life cycle (stages thro’ vision to reality))

The management process (management of stages Five steps of the cycle

Concept Feasibility Design Execution Close-out

Management process is derived from the ten step problem solving cycle (refer table 1.4 and figure 1.6)

Page 24: Udaya Gamage 15 th November 2012 Project Based Management

The management process (each stage of the PM to be executed)

Page 25: Udaya Gamage 15 th November 2012 Project Based Management

Project Management is Fractal management, Discuss?

The levels, third and final dimension the integrative level, (project definition report,

functional design, and flow chart) The strategic and administrative level

(milestones, responsibilities, and the system design)

The tactical or operational level ( activity schedule, responsibility chart, and detailed design)

Read on project management as sailing a Yacht Micro-level Macro-level

Page 26: Udaya Gamage 15 th November 2012 Project Based Management

Objectives

Define the steps and processes necessary to move the project forward from a conceptual idea to a meaningful change management project

Develop an initial project charter for sponsor decision-making so that more detailed investigations can be undertaken

Develop business cases necessary to ensure the project is consistent with the sponsor’s objectives and goals

Define the scope and nature of the proposed project to allow more detailed planning to take place for sponsor commitment.

Page 27: Udaya Gamage 15 th November 2012 Project Based Management

Figure 3.1: Project management process interactions(Source: PMI 2008, p. 42)

Page 28: Udaya Gamage 15 th November 2012 Project Based Management

The project charter

The three Ws – why, what and when The three Hs – how much, hazards

and how The four Cs – critical success factors,

communication plan, collection of knowledge and commitment.

 

Page 29: Udaya Gamage 15 th November 2012 Project Based Management

The business case

What the project is

Why it should be done

What options have been considered?

How much will it cost?

How will it be done?

What are the risks?

Page 30: Udaya Gamage 15 th November 2012 Project Based Management

Gambles (2009) provides some clear guidelines on the purpose of a business case and how to go about it.

Confirm that the business case is robust – that is, in principle it meets business need, is affordable, achievable, with appropriate options explored and likely to achieve value for money.

Establish that the feasibility study has been completed satisfactorily and that there is a preferred way forward

Ensure that there is internal and external authority, if required, and support for the project.

Page 31: Udaya Gamage 15 th November 2012 Project Based Management

Establish that quality plans for the project and its products are in place

Page 32: Udaya Gamage 15 th November 2012 Project Based Management

Ensure that the major risks have been identified and outline risk management plans have been developed.

Establish that the project is likely to deliver its business goals and that it supports wider business change, where applicable.

Confirm that the scope and requirements specifications are realistic, clear and unambiguous.

Ensure that the full scale, intended outcomes, timescales and impact of relevant external issues have been considered.Ensure that there are plans for the next stage.

Confirm planning assumptions and that the project team can deliver the next stage.

Confirm that overarching and internal business and technical strategies have been taken into account.

Page 33: Udaya Gamage 15 th November 2012 Project Based Management

Stephen Wearne’s life cycle for industrial projects

Several versions of the project life cycle set the project within the life cycle of the product

Refer fig. 11.1 and table 11.1 project life cycle used by the World Bank

Harold Kerzner

Proposes a model addressing the life cycle of the product produced by the new asset – classical marketing view

Refer fig. 11.2

Page 34: Udaya Gamage 15 th November 2012 Project Based Management

Where are we now? The Business Case completed

Articulated the project brief or Charter to key sponsors

Developed guidelines and constraints (risks)

What is next? Firm expectations of the key sponsors will result on

What the outcome will be When it will be delivered How it will be delivered Who will deliver it What resources will be consumed What benefits will be delivered

So the next stage is to plan to deliver the Business Case

Page 35: Udaya Gamage 15 th November 2012 Project Based Management

What should we do in the planning stage?

Define organizational unit that have project responsibility

What finances that organization can afford

What processes will take place to ensure that the project happens with the least fuss and the least exposure to risk How the end benefits will be measured to demonstrate project success or failure

Page 36: Udaya Gamage 15 th November 2012 Project Based Management

PMP

Inputs required to create a comprehensive project management plan (PMP)

What processes must be undertaken

What the outcomes provide for further decision-making and implementation purposes

What is planning phase? Initiating a good idea into a final out come

Page 37: Udaya Gamage 15 th November 2012 Project Based Management

Project integration steps – a scalable methodology guide (Planning Inputs)

Area ( major investment, significant investment, moderate investment, minor investment)

Project Charter (define responsibilities, describe specific objectives, express commitments of staffing, etc.)

Life Cycle Phase and Milestones (define event based management, link them to final deliverables etc.)

Project Stakeholders (prepare and update a structured stakeholder analysis, quality management plan, risk management plan etc.)

The Project Plan (produce an integrated family of documents defining project activities)

Project Management Methodology (prepare PMP describing methodology, reviews, baseline controls etc.)

Page 38: Udaya Gamage 15 th November 2012 Project Based Management

Planning Process Gray and Larson (2000) provide some guidelines for the PMP development process as follows:

Important planning decisions are made when answering the following project-related questions:

How will the project plan be developed?

Who will develop the project plan, and how involved will the customer be?

What project management software package will be used, if needed?

Who on the project team will be responsible for entering the planning information?

Page 39: Udaya Gamage 15 th November 2012 Project Based Management

Who will have input on the plan?

What specifically are the roles and responsibilities of each team member?

How will team members be informed of decisions?Understanding that cost, time, and quality (performance) are all important, what are the priorities?

What are the deliverables of the project planning process?What format is appropriate for each of these deliverables (e.g., milestone charts)

Who will approve and certify at the completion of each deliverable?

Who receives each deliverable

Page 40: Udaya Gamage 15 th November 2012 Project Based Management

Planning Outcomes

Project Management Plan

PMP provides information How the project will be managed, as well as How the product or service itself will be produced

PMP is a document used to Guide project execution Document project planning assumptions Document project planning decisions Facilitate communications among stakeholders Define key management reviews as to content, extent, &

timing Provide a baseline for progress measurement & project

control.

Page 41: Udaya Gamage 15 th November 2012 Project Based Management

Contents of PMP (Barkley, 2000 suggests)

Control points, for instance, stage-gateway reviews, to ensure that management authorizes movement from one phase or stage to another

reporting and monitoring strategies, including the use of earned value to integrate cost, schedule, and quality performance, which should be made explicit

The project management processes selected by the project management team

The level of implementation of each selected process

The descriptions of the tools and techniques to be used for accomplishing those processes

Page 42: Udaya Gamage 15 th November 2012 Project Based Management

How work will be executed to accomplish the project objectives How changes will be monitored and controlled

How configuration management will be performed

How integrity of the performance measurement baselines will be maintained and used

The need and techniques for communication among stakeholders

The selected project life cycle and, for multi-phase projects, the associated project phases

Key management reviews for content, extent, and timing to facilitate addressing open issues and pending decisions.

Page 43: Udaya Gamage 15 th November 2012 Project Based Management

How the selected processes will be used to manage the specific project, including the dependencies and interactions among those processes, and the essential inputs and outputs

PMP may include in summary

Project scope management plan Schedule management plan Cost management plan Quality management plan Process improvement plan Staffing management plan Communication management plan Risk management plan Procurement management plan.

Page 44: Udaya Gamage 15 th November 2012 Project Based Management

Structure of PMP

Overview or executive summary – a brief description of the project and its deliverables, and a list of major milestones

Objectives – a detailed description of the project’s deliverables and outcomes, (Mission Statement)

General approach – where technical and managerial approaches are defined

Contractual - where the procurement process is described, and the specific legal aspects defined

Schedule – an outline of all schedules and milestones, using an action plan based on a WBS

Page 45: Udaya Gamage 15 th November 2012 Project Based Management

Resources – estimates of capital and operating expenses.

Personnel – describing the project work force, and requirements for special skills, expertise etc.

Evaluation methods – describing evaluation methods and standards for the completed project.

Potential problems – identifying any likely risk events that could adversely affect the project.

Page 46: Udaya Gamage 15 th November 2012 Project Based Management

Hard Skills of Project management

Page 47: Udaya Gamage 15 th November 2012 Project Based Management

Scope may be defined Product breakdown structure (a cascade of products, sub-products, assemblies and components)

Organization breakdown structure (a cascade of resource types, skill types or activities

Work breakdown structure (a cascade of the products and work activities),and/or

Some other form which comprehensively defines products and activities