A RESEARCH ON CRflu.iu. tA fURS H-IA1 INFLUENCE CONSTRUCTION PRODUCTIVITY RELATED TO HUMAN POWER IN GAMBANG AND KUANTAN
NURUL AKES BINTI MAZNT
Thesis submitted in fulfillment of the requirements for the award of the degree of Bachelor of Civil Engineering
Faculty of Civil Engineering & Earth Resources UNIVERSITI MALAYSIA PAHANG
JUNE 2013
ABSTRACT
Factors affecting the construction productivity are one of the most frequently researched topics in our country. In comparison with rapidly growing economies, we need to increase the productivity level. Our productivity level or output per employee was at 5.8% which is lower than Organisation of Economic Cooperation and Development (OECD) countries. As we know, we need to facing many challenges in order to be a develop nation but the most important is low productivity. The objective of this research is to identify factors that influence the productivity that related to human power, to identify the impact of factor influence to construction productivity and to determine the critical factors that influence the construction productivity related to human power. To achieve this objective, those factors can be identifying through a series of statistical analysis (SPSS) based on collected data of questionnaire survey. From the findings, top ten factor that influenced the productivity were identified such as worker skills, a real construction experience in construction field, change of worker (not loyal to the company), relationship between contractor and worker, communication with foreign worker, worker attitude and morale, labour absenteeism, working overtime, direct supervisor (daily interaction with labourers) and delay in responding to request for information. The most critical factor that influenced the construction productivity related to human power also identified which are worker skills. The result obtain from this research can be used as a guideline in producing the productivity rate which it can help the scheduling of construction production in order to increase our economies.
ABSTRAK
Faktor yang menjejaskan produktiviti pembinaan adalah salah satu topik yang paling kerap dikaji di negara kita. Berbanding dengan negara-negara yang pesat membangun, kita perlu meningkatkan tahap produktiviti. Tahap produktiviti bagi setiap pekerja adalah pada kadar 5.8% yang lebih rendah berbanding dengan Pertubuhan Kerjasama Ekonomi clan Pembangunan negara (OECD). Seperti yang kita tabu, kita perlu menghadapi pelbagai cabaran untuk menjadi sebuah negara membangun tetapi yang paling penting ialah penurunan kadar produktiviti. Objektif kajian mi adalah untuk mengenalpasti faktor-faktor yang mempengaruhi produktiviti yang berkaitan dengan kuasa manusia, untuk mengenal pasti kesan pengaruh faktor produktiviti pembinaan dan untuk menentukan faktor-faktor kritikal yang mempengaruhi produktiviti pembinaan yang berkaitan dengan kuasa manusia. Untuk mencapai objektif kajian mi, faktor-faktor yang boleh mengenal pasti harus melalui beberapa sirl analisis statistik (SPSS) berdasarkan data yang dikumpul daripada kajian soal selidik. Daripada penemuan ini, sepuluh faktor yang mempengaruhi produktiviti telah dikenal pasti seperti kemahiran pekerja, pengalaman pembinaan sebenar dalam bidang pembinaan, perubahan pekerja (tidak setia kepada syarikat), hubungan antara kontraktor clan pekerja, komunikasi dengan pekerja asing, sikap pekerja dan moral, ketidakhadiran pekerja, keija lebih masa, penyelia langsung (interaksi harian dengan bumh) dan kelewatan dalam bertindak balas untuk meminta maklumat. Faktor yang paling penting yang mempengaruhi produktiviti pembinaan yang berkaitan dengan kuasa manusia juga pasti yang kemahiran pekeija. Hasil danpada kajian mi boleh digunakan sebagai garis panduan dalam menghasilkan kadar produktiviti yang mana ia boleh membantu penjadualan pengeluaran pembinaan untuk meningkatkan ekonomi kita.
TABLE OF CONTENT
Page
SUPERVISOR'S DECLARATION
STUDENT'S DECLARATION
ACKNOWLEDGEMENTS iv
DEDICATION v
ABSTRACT vi
ABSTRAK vii
TABLE OF CONTENT viii
LIST OF TABLES xi
LIST OF FIGURES xii
LIST OF GRAPHS xiii
CHAPTER 1 INTRODUCTION
1.0 Background of study 1
1.1 Problem statement 3
1.2 Research objective 5
1.3 Research question S
1.4 Scope of study 5
1.5 Significant of the proposed research 7
1.5.1 Labour performance 7 1.5.2 Factor influence 7 1. 5.3 Impact to industry 7 1.5.4 Critical factor 8
1.6 Expected outcomes 8
1.6.1 Identifying and ranked the factor influence 8 productivity 1.6.2 Revelations of factor's impact on construction 8 productivity 1.6.3 Determination of critical factor 9 1.6.4 Provide leader skills to have better worker performance
VIII
1.7 Conclusion and summary of the chapters 10
CHAPTER 2 LITER1TURE REVIEW
2.1 Introduction 11
2.2 Construction productivity 11
2.2.1 Definition of productivity 11
2.3 Factor influence construction productivity 12
2.4 Impact of low construction productivity 15
2.5 Innovation provide by the company 16
CHAPTER 3 RESEARCH METHODOLOGY
3.1 Introductions 17
3.2 Research methodology 18
3.3 Procedures 19
3.4 Research method 20
3.5 Data sampling and population 20
3.6 Research question 21
3.6.1 Research question design 22 3.6.2 Research question format 23
3.7 Data collection technique 25
3.7.1 Data collection method 25 3.7.2 Statistical Analysis 25
CHAPTER 4 RESULT & DISCUSSION
4.1 Introductions 27
4.2 Survey response rate 28
4.3 Demography profile of respondents 28
Ix
x
4.4 Reliability analysis 32
4.4.1 Reliability, analysis for factor influenced 33 the productivity related to (worker) 4.4.2 Reliability analysis for factor influenced 34 the productivity related to (Site supervisor and contractor) 4.4.3 Reliability analysis for impact of low productivity 35 4.4.4 Reliability analysis for innovation of a company 36
4.5 Normality test 36
4.5.1 Normality test for factor influence 37 of construction productivity (worker) 4.5.2 Normality test for factor influence 38 of construction productivity (Site supervisor and contractor) 4.5.3 Normality test for impaction due to 39 the low of productivity 4.5.4 Normality test for innovation of the company 40
4.6 Pearson correlation analysis 41
4.7 Frequency analysis 42
4.7.1 Analysis of factor influenced of 43 construction productivity 4.7.2 Analysis of impaction due to the low of 46 productivity 4.7.3 Analysis of innovation of the company 48
4.8 Summary 50
CHAPTER 5 1CONCLUSION AND RECOMMENDATION
5.1 Conclusions 51
5.2 Recommendations 53
5.3 Recommendations for future research 54
REFERENCES 55
APPENDICES 58
A Questionnaires 58
LIST OF TABLES
Table No. Title Page
4.1 Case processing summary of factor influenced 34
4.2 Reliability statistic of factor influenced 34
4.3 Case processing summary of factor influenced 35
4.4 Reliability statistic of factor influenced 35
4.5 Case processing summary of impact of low productivity 36
4.6 Reliability statistic of impact of low productivity 36
4.7 Case processing summary of innovation-of a company 36
4.8 Reliability statistic of innovation of a company 37
4.9 Normality test for factor influenced (Section B) 38
4.10 Normality test for factor influenced (Section C) 39
4.11 Normality test for impact due to the low productivity 40
(Section D)
4.12 Normality test for innovation of the company (Section E) 41
4.13 Correlation matrix significant of r 42
4.14 Strength of correlation coefficient 42
4.15 Statistic of factor influenced of construction productivity 44
4.16 Rankin of the factor influenced 46
4.17 Statistic of impact due to the low productivity 47
4.18 Rankin of impact due to the low productivity 48
4.19 Statistic of innovation 49
4.20 Rankin of innovation 50
XI
LIST OF FIGURES
Figure No. Title Page
1.1 Comparison of productivity growth between Malaysia and 2
selected OECD countries for year 1998-2003
1.2 Productivity performance of the construction sector 4
1.3 Research area (iambang state and Kuantan 7
1.4 Number of foreign workers by nationality 16
1.5 Process flow of research progress 20
1.6 Pahang state 21
4.1 Gender of respondent 30
4.2 Age of respondent 30
4.3 Academic qualification of respondents 31
4.4 Nationality of citizen 32
4.5 Experience in work of respondents 32
4.6 Position in company of respondents 33
4.7 Frequency bar chart of factor influenced 45
4.8 Frequency bar chart of impact due to the low productivity 48
4.9 Frequency bar chart of innovation 50
XII
LIST OF GRAPHS
Graph No. Title Page
4.1 Normal Q-Q plot of factor influenced (Section B) 38
4.2 Normal Q-Q plot of factor influenced (Section C) 39
4.3 Normal Q-Q plot of impact due to the low productivity 40
(Section D)
4.4 Normal Q-Q plot of innovation of the company (Section E) 41
XIII
CHAPTER 1
INTRODUCTION
1.0 BACKGROUND OF STUDY
There are two important groups to have effective study of construction
productivity. The first is the consistent productivity across the scheduling of project.
The second is the identification of the critical factors that influence the productivity.
Improvement of productivity in construction of our country has been a major industry
challenge, given its high impact on project schedule and results (Rivas, R., Borcherding,
J., Gonzalez, V., and Alarcon, L. 2011).
The aim of this research is to investigate the factors influenced the construction
productivity in Malaysia in order to increase the productivity rate. Productivity is one of
the factors that affect our competitive position. The more productive we are the better
we are able to fight on world markets (Roubini and Backus, 1998). Industry Minister
Datuk Seri Mustapa Mohamed (2012) said that productivity was a gauge of
performance which measured the output per employee.
Labour cost is regarded as one of the project components carrying the most risk
(Hanna 2001). Construction labour productivity is perceived in the United States as an
economic variable that has gradually declined since the 1960s (Dai et al. 2009). In
Malaysia, our construction productivity level or output per employee was at 5.8% which
is US$13,577.
1
The productivity growth at the USA is 2.2%, Japan is 1.2%, Canada 1.1%, the
UK is 1.3, Germany is 0.9%, France is 1.0% and last but not least Italy the lowest is
0.1% has been shown in Figure 1.1. Although our productivity growth was higher than
Organisation of Economic Cooperation and Development (OECD) which is the average
is at 2.3% but our output per employee was lower than OECD countries. In Japan, the
US and the UK, output per employee were at US$80,307, US$80,284, US$59,276
which were about four to six times that of Malaysia (Mustafa, 2011).
2.52.2
2 - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - I
•1.2 -- - -----------
CL
.2 • a .. ' C-)
^. (.2 U.
U 1998-2003
Figure 1.1: Comparison of productivity growth between Malaysia and selected
OECD countries for year 1998-2003
Source: national Productivity Corporation (2003)
The evidence seems to show the labour construction performance in our country.
Identifying and implementing management actions to improve construction labour is
not desirable but also necessary (Rivas, R., Borcherding, J., Gonzalez, V., and Alarcon,
L. 2011) to increase the construction productivity and identifying the factor influence
and impact to the industry is the first step in finding opportunities for human power
Improvement.
There are some primary groups such as management, technological and human
power. From this primary group, the factor influenced productivity will be identifying.
The factor of construction productivity is importance because it can affect the project
3
cost and time overruns (CIDB, 2005). In most countries, labor cost comprises 30 to 50%
of the overall project's cost, and thus is regarded as a true reflection of the economic
success of the operation (Jarkas, A. and Bitar, 2012).
This research focus more on the factors that influence the productivity related to
human power in Gambang state and Kuantan. At the end of this research, the critical
factor that influenced will be identifying. The identifying critical factors can be used as
a guideline in producing the productivity rate to avoid delays in a project. After the
factor have been identify, the contractor can effectively act upon them to lower costs,
enhance scheduling, and eventually obtain a more accurate productivity prediction when
estimating construction costs (Borcherding and Alarcon 1991; Edmondson 1974).
1.1 PROBLEM STATEMENT
Data that we computed from Economic Report of Productivity Growth (2011),
Ministry of Finance, Malaysia shows that construction industry has growth 3.51%
which is lower than agriculture 4.78%, manufacturing 5.33% and services 4.30%. For
the example in this situation when there was a slight delay because of the contractor's
poor handling of the project on the progress of the second phase of the East Coast
Highway, it had been scheduled to be completed in 2011 but was only expected to be
completed in 2012 (Shaziman, 2010). The factor influences the productivity play a main
role in increasing the productivity growth. Figure 1.2 proved that the lower productivity
performance of civil engineering compare with residential and non residential of
construction sector.
4
Output of the Construction Sub-sectors 2007-2010 at 2000 Constant Price
100
9.0
]A-RaSUMU
1.0Bqnea"
2ft7 2U8 2009 2110
- -
Cowtnicln GOP Gmwtl% 07-2010
VA
15A 4
- wtd$
P,oductMty Lirv & Growth ofthe Ccns1nxon Sector. 2001-2010
'L1LIIrLE' IM no
---9'-
Figure 1.2: Productivity performance of the construction sector
Source: Economic Report Ministry of Finance Malaysia
Productivity in the construction industry in Malaysia is not only influenced by
labour, but also influenced by other factor such as equipment or machineries, materials
and construction methods. However, most researches and construction practices to date
has primarily concentrated on workers' productivity (Alwi, 2003). If we observe the
trends in construction management it has shown a very mixed picture of labour,
equipment or machineries, materials and construction methods and indeed they solely
depend on labourer's performance to increase construction productivity (Alwi, 1995).
The use of new technology and innovative methods has made great
improvement in construction productivity. The improvement of labour productivity and
quality of material should be a major and continual concern of those who are
responsible for cost control of construction productivity.
5
Productivity in construction is defined as output per labour hour. Labour is a
major part of construction project cost and the quantity of labour hours in performing a
work in construction is main influence to management. Since labour is a major part, we
need to know its characteristic in improving the factors. The labour characteristic
include the age, skill, leadership, motivation and the most important is experience of
workforce: The contractor needs to observe and measure the workers quality or
performances over a period of time in avoid the worse impact to the productivity.
1.2 RESEARCH OBJECTIVE
i. To identify factors that influence the construction productivity related to
human power
ii. To identify the impact of factor influence to construction productivity
iii. To determine the critical factors that influenced the construction
productivity estimation related to human power in Gambang 'state and
Kuantan.
1.3 RESEARCH QUESTION
i. What are the factors that influence the construction productivity
estimation related to human power
ii. What are the impact factor influence to construction productivity
iv. What are the critical factors that influenced the construction productivity
estimation related to human power in Gambang state and Kuantan.
1.4 SCOPE OF STUDY
In order to have a detail result of my research, a bunch of effort has been made
to systematically identify and determine the critical factor that influence the
construction productivity estimation related to human power in Gambang and Kuantan.
Source from Pusat Khidmat Kontraktor,Kementerian Kerja Raya Malaysia mention that
there are 50 registered Malay contractor class A in Kuantan. Civil engineering conquers
this contractor field with 42 numbers of contractor and 8 contractors from electrical.
The scope of my research will cover the mining projects with class A contractor's.
It shown in this situation how important the factors influence the construction
productivity estimation and their impact to future when there was a slight delay because
of the contractor's poor handling of the project on the progress of the second phase of
the East Coast Highway, it had been scheduled to be completed in 2011 but was only
expected to be completed in 2012 (Shaziman, 2010).
It can be stated that the literature generally defines "leaders" as persons who
recognize the need for and implement change, establish direction, align people,
motivate and inspire, give away as opposed to hoard power, communicate a vision of
where the organization is headed, build teams and share decision making, mentor and
coach subordinates, and demonstrate a high degree of integrity in their professional
interactions (Zenger and Folkman 2002; Bass 1990; Tichy and Devanna 1990; Kouzes
and Posner 2002). Structured questionnaire will be distributed to the top management
level in organization, the worker, site supervisor and the contractors as well at least
three existing or on schedule projects at Gambang state and Küantan, at different
location and with different features.
Figure 1.3: Research area Gambang state and Kuantan
Source: Google Map
7
With the result obtain from this research it will fill a gap in knowledge in
determination of critical factors affecting the construction productivity related to human
power in engineering industry. This critical factor also can be used by industry
practitioners to develop a wider and deeper perspective of the factor influencing and
also provide guidance to construction manager to improve the labour productivity in
achieving a reasonable level of competitiveness and cost-effective operation (Jarkas, A
and Bitar, C, 2012).
1.5 SIGNIFICANT OF THE PROPOSED RESEARCH
1.5.1 Labour performance
To know what is the level of labour performance including the contractor's
performance and how their limited skill use in industry in improving the construction
productivity.
1.5.2 Factor influence
To know and explore the factor influence the construction productivity
estimation related to human power and produces the statistical result.
1.5.3 Impact to industry
To know the impact of all these factor to our industry and we should hang on in
the hope that with the finding of the factor influence will be guidance to our local
contractor in improving the productivity and no need to conquer by foreign contractor.
The World Bank's Report (1984) in the book" The Construction Industry" conclude
that due to the limited skills and resources on developing countries, a large amount of
projects were won by foreign contractor.
8
1.5.4 Critical factor
To determine the critical factor that can help to improve the labour's
performance to increase the construction productivity. They solely depend on labourer's
performance to increase construction productivity (AIwi, 1995).
1.6 EXPECTED OUTCOMES
1.6.1 identifying and ranked the factor influence productivity
The relationship between influencing factors and productivity for estimating
purposes is very important in industry and a number of modelling techniques have been
introduced. I hope at the end of this research, all the factor influence construction
productivity estimation related human power will be identifying. So that the respondent
can rank these following factors and it will help companies gain operational inight and
thus improve productivity and profitability (Chang,A And Lbbs,W ,2006).
1.6.2 Revelations of factor's impact on construction productivity
There are many causes and factor that can affect the construction productivity
estimation, including the difficulty in predicting the future and the uniqueness of each
project. Direct labour cost of the project may be increase and make the project slow in
progress, the schedule delay and increasing overhead costs thus make the project cost
may subsequently be increase. And since the workers comprises different backgrounds
and thus, different working methods which may affect the performance and construction
productivity level of the respective trade among the various nationalities surveyed, and
therefore the perceived important of the factor explored (Jarkas,A and Radosavljevic,
M, 2012), it becomes necessary to normalize such an influence by collecting a large,
yet balance and sample of respondent's feedback (Jarkas, 2012).
9
This situation can reduce or eliminating the contractor's profitability and
impairing the owner's return on investment or project utility (Lbbs, W, 2012). So in
achieve the second objective, at the end of this research we can see the effect of the
factor influenced on the construction workforce.
1.6.3 Determination of critical factor
Measuring productivity for construction project is a complex problem (Alwi,S
2003). Each project is different in terms of delivery methods, administration, design
specifications, and participants. If the critical factor influencing in any contracting
organisation are identified, then measure can be taken to apply them in order to upgrade
the contractors' performance (Ofri and Chan, 2001).
After the first objective achieve which is explore, identify and rank the factor
influence the construction productivity estimation related to human power th critical
factor will determining. At the end of this research, alternatives solution are provided to
assist construction managers or contractor to achieve better productivity performance by
providing them information on which factors they need to focus.
1.6.4 Provide leader skills to have better worker performance
Hanna et a!, 2005 investigated the schedule acceleration problem, studied the
impact of change orders on labour productivity and focusing on the effect of shift work
on labour productivity. The impact of management practices related to reliability on
labour productivity planning has also been studied as a relevant factor (Gonzalez et al.
2008; Liu and Ballard 2008). A good understanding of the factor affecting labour
productivity can be obtained through the viewpoint of those factors related on- site
production in construction projects. This also can enable site managers or contractor to
make decisions more effectively to improve labour performance (Dai et a!, 2009).
10
Although so many researchers have been done, there is a lack of detailed
research on the factors influence the construction productivity related to human power
in our industry. Leader skills will be provided to have a better worker performance
when analyzed these entire factor.
1.7 CONCLUSION AND SUMMARY OF THE CHAPTERS
This research consists of five (5) chapter and need to be completed. Introduction
is the first chapter; in this first chapter it describes the background of the study, the
research objectives and question, scope of study, the significant of the proposed
research, expected outcomes and the summary of the chapters. The second chapter
which is chapter two discuss on the literature review for the factor of influence
productivity of construction, the impact that affect the productivity and the critical
factor influence the construction productivity estimation related to human power and
last but not least the literature review for the leader skills for labour improvement.
In chapter three I will represents a research methodology applied in this
research consists of the collection of data, data sampling techniques, tools to collect
data, all the respondents and method to analysis all the data of collected questionnaire.
Chapter Four shows the details on data analysis and finding of factor that influence the
construction productivity estimation, impaction of the factor affect to industry and the
determination of the critical factor influence the productivity of construction.
Last but not least, Chapter Five would be the conclusion the overall of this
research and some recommendation for future research.
CHAPTER 2
LITERITURE REVIEW
2.1 INTRODUCTION
There are lot of reference such as conference proceedings, engineering journals,
books, the internet and newspaper to complete this chapter two, literature review. For
this research, I will provide a literature review of construction productivity, critical
factor influencing construction productivity, the impact of the critical factor influencing,
and the innovation provided by the company for productivity improvement.
In this chapter, I will convey knowledge that has been already established,
comparison of previous studies, current problems and issues in the industry.
2.2 CONSTRUCTION PRODUCTIVITY
2.2.1 Definition of productivity
Different researchers have found different meaning of productivity, such as
Paul.K (1994) said that productivity isn't everything, but in the future it is almost
everything. A country's ability and performance to improve its standard of living over
time depends almost entirely on its ability to raise its output per worker. In other
research, productivity can define as works hours divided by the equivalent quantity of
work.
In construction, productivity can be define as work quantity per man-hours (or
11
works hours) consumed to accomplish the work. Productivity is the ratio of output to all
12
or some of the resources used to produce the output (O'Grady, 2005). The productivity
can be defined as internal efficiency of the organization or other object to be measured
(Uusi-Rauvi and Hannula, 1996). A more accurate meaning of productivity is output
divide by the input that is used to generate output. Which is output consists of services
or products and input consists of material, labour, capital, energy and etc.
Productivity Output
Resources Used
Based on Thomas and Mathew (1986), no accurate standardized productivity
meaning had been established in the construction industry. It is difficult to define
precise definition of productivity because different company used different method in
their productivity measurement.
In addition, Paul.K (1994) said that productivity is analyzed is a key source of
economic growth and competitiveness. For example, the productivity data are used to
investigate the impact of product and labour market regulations on economic
performances. Productivity is one of the factors that affect our competitive position. The
more productive we are the better we are able to fight on world markets (Roubini and
Backus, 1998) and we need to accelerate our rate of productivity growth to reach this
target.
2.3 FACTOR INFLUENCE CONSTRUCTION PRODUCTIVITY
The factor of construction productivity is importance because it can affect the
project cost and time overruns (CJDB, 2005). Identifying and analysing the most critical
factor influencing construction productivity will lead to the development of more
efficient and cost effective ways and strategies to improve the productivity of future
construction operations (Markus, Janaka and George 2003). A lot of studies have been
done related to construction productivity and more specific to human factors. The factor
affected the motivation of construction factor was documented by Dozzi et a! (2000).
And he investigated more on issues that directly related to the worker during shift,
13
overstaffing, overtime, change of order and multiple shifts. The affect of overtime has
been discussed widely today for construction productivity.
Many researchers interested in project schedule delay and labour productivity. It
includes Thomas and Raynar (1997), Adrian (1988), and Henry (1991). Olgelsby et al
(1989) extensively documented the affect of many human factors and external issues
although the supporting data for the conclusion were not justifiable. A researched of the
impact of change orders on labour efficiency of electrical contractors has been done by
Hanna etal. (1999).
Lim et al. (1995) has studied that factors influencing construction productivity
in Singapore show the problems affecting productivity were difficulty with acquirement
of supervisors and workers, high rate of labour turnover, communication problems with
foreign workers and absenteeism of worker from work site. There are five specific
productivity problems in construction industry were identified such absenteeism,
rework, lack of materials and lack of equipment and tools. Olomolaiye et a! (1996) has
been done a research that factors affecting the construction productivity of craftsmen in
Indonesia. From this research it shows us the findings indicating craftsmen in this
construction industry spent 75% of their time working productively.
According to AIwi (2003), he did a research and come Out with the comparison
between the productivity problems in Indonesia with other countries in terms of factor
influencing the construction productivity such as interference, absenteeism, supervision
delay and rework. From the previous research, Kaming et a! (1997) stated that the main
craftsmen's productivity problems in Indonesia were identified such as absenteeism,
interference, lack of tools and followed by rework. Basically the main causes of rework
were found as poor instruction from supervisor or contractor. From all of this research
we can conclude that all the problems must related with workers. Mostly in a country,
absenteeism must be one of the factors influencing the construction productivity.
According to Thomas and Sanders (1991), they summaries that the types of
Interruption that can affect the progress of labour productivity such as lack of
supervision, overstaffing and rework. A research in Indonesian construction industry
14
found that poor performance of labour skills contributed 3.2% of the overall project
cost. The characteristic of contractor and supervisors include the qualifications indicate
especially small contractors. From researches that have been done, it shows that the
small contractors experienced waste more than others. The contractor plays main role in
each organization looking forward for success or failure.
The incapability of contractor's site management for organize site activities was
found to be one of the critical factor in Malaysia (M.R. Abdul Kadir, W.P. Lee, M.S.
Jaafar, S.M. Sapuan and A.A.A. Ali et al, 2005). An experience contractor is needed in
produce an efficient and effective site management team to ensure that all works is on
schedule and can completed on time proposed. Many researchers (Nima, Abdul-Kadir
et al. 2001; Abdul-Aziz 2003; CIDB 2006; Jaafar, Abdul-Aziz et al. 2007; Ibrahim, Roy
et al. 2010; Karnal and Flanagan 2012) summaries that our construction industry still
suffers with many problems and being associated with poor quality and low
productivity, unskilled workers, poor workers performance and project delays.
Country Construction Plantation Domestic help Manufacturing Services Others Total Percentage
Indonesia 92805 101521 62347 16188 2063 1125 276049 64.96
Bangladesh 26484 16416 56 40996 4743 416 89111 20.96
Philippines 1160 49 26876 1298 191 554 30128 709
Thailand 6342 10845 3818 166 1126 519 22816 5.37
Pakistan 1121 183 2 672 67 3 2048 0.48
Others 2218 460 83 660 867 574 4862 1.14
Total 130130 129474 93182 599809057
3191 425014
Percentage 30.6 30.5 21.9 14.1 2.1 0.8 100.00
Figure 1.4: Number of foreign workers by nationality
Source: Immigration Department
The Malaysian construction industry hire heavily on foreign labour especially
from Bangladesh, Indonesian, Nepal and Myanmar (Ernawati, Syarmila, Norhidayah
and Faizal Bahapjm et a! 2012). Figure 1.4 shows us the statistic of foreign workers by
nationality in our country and indicated that construction industry being the most active
15
in hiring the foreign worker. The Union of Employees in the Construction Industry
believe that we can't do without them (Hiebert, 1995).
Constructions employers in our country prefer to hired more foreign worker
because they willing to works for extra hours, flexible, willing to accept low wages and
obedient (Abdul Aziz, 2001). The wide availability and low wages of foreign worker
will give a big impact on construction productivity and quality. The advantages are the
contractors will have a little incentive to adopt and implement better quality and
performance and safer technologies (Ernawati, Syarmila, Norhidayah and Faizal
Baharum et al 2012). In another hand, this situation also can affect the contractor's
interest in hire highly skilled labour since CI1DB records shown that mostly foreign
labourers in our industry are general workers and unskilled labour (CIDB, 2006).
2.4 IMPACT OF LOW CONSTRUCTION PRODUCTIVITY
The Malaysian construction industry experiences cost overruns and time due to
various project delay factors that affect the construction productivity (A.Kadir, W.P.
Lee, M.S. Jaafar, S.M. Sapuan and A. Ali et al, 2005). It is important for us to maintain
the country's growth in productivity because it is the key determinant of long-run
growth which can lead to higher prosperity. As we know the construction industry is an
industry of main strategic importance and its productivity performance has a significant
effect on national economic growth (C.Chia , M.Skitmore, G.Runeson and A.Bridge et
a!, 2012). Hence in construction industry the productivity increases when times are
good and profit is higher and decreases when profit is lower. In the long run, there are
very small changes (Runeson, 2000).
There are three common types of indicators of performance in construction
projects which are cost, schedule and quality (McKim et a!, 2009). A research done by
Lam and Runeson (1999) and they elaborated that one of the objectives of a
construction organization is to have a complete construction projects at maximum
efficiency in terms of cost and time by optimizing the use of four resources which is
Plant, materials, manpower and management. The manpower is one of the important
resources in affecting the productivity performance.