tscm40 - planning & manufacturing i
TRANSCRIPT
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 1/522
TSCM40Planning / Manufacturing I
SAP Supply Chain Management
Date
Training Center
Instructors
Education Website
Instructor Handbook
Course Version: 81Course Duration: 10 Day(s)
Material Number: 50090909
Owner: Frank Layer (D036000)
An SAP Compass course - use it to learn, reference it for work
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 2/522
Copyright
Copyright © 2008 SAP AG. All rights reserved.
No part of this publication may be reproduced or transmitted in any form or for any purpose
without the express permission of SAP AG. The information contained herein may be changed
without prior notice.
Some software products marketed by SAP AG and its distributors contain proprietary software
components of other software vendors.
Trademarks
Microsoft®, WINDOWS®, NT®, EXCEL®, Word®, PowerPoint® and SQL Server® are
registered trademarks of Microsoft Corporation.
• IBM®, DB2®, OS/2®, DB2/6000®, Parallel Sysplex®, MVS/ESA®, RS/6000®, AIX®,
S/390®, AS/400®, OS/390®, and OS/400® are registered trademarks of IBM Corporation.
• ORACLE® is a registered trademark of ORACLE Corporation.
• INFORMIX®-OnLine for SAP and INFORMIX® Dynamic ServerTM are registered
trademarks of Informix Software Incorporated.
• UNIX®, X/Open®, OSF/1®, and Motif® are registered trademarks of the Open Group.
• Citrix®, the Citrix logo, ICA®, Program Neighborhood®, MetaFrame®, WinFrame®,
VideoFrame®, MultiWin® and other Citrix product names referenced herein are trademarks
of Citrix Systems, Inc.
• HTML, DHTML, XML, XHTML are trademarks or registered trademarks of W3C®, World
Wide Web Consortium, Massachusetts Institute of Technology.
• JAVA® is a registered trademark of Sun Microsystems, Inc.
• JAVASCRIPT® is a registered trademark of Sun Microsystems, Inc., used under license for
technology invented and implemented by Netscape.
• SAP, SAP Logo, R/2, RIVA, R/3, SAP ArchiveLink, SAP Business Workflow, WebFlow, SAP
EarlyWatch, BAPI, SAPPHIRE, Management Cockpit, mySAP.com Logo and mySAP.com
are trademarks or registered trademarks of SAP AG in Germany and in several other countries
all over the world. All other products mentioned are trademarks or registered trademarks of
their respective companies.
Disclaimer
THESE MATERIALS ARE PROVIDED BY SAP ON AN "AS IS" BASIS, AND SAP EXPRESSLY
DISCLAIMS ANY AND ALL WARRANTIES, EXPRESS OR APPLIED, INCLUDING
WITHOUT LIMITATION WARRANTIES OF MERCHANTABILITY AND FITNESS FOR A
PARTICULAR PURPOSE, WITH RESPECT TO THESE MATERIALS AND THE SERVICE,
INFORMATION, TEXT, GRAPHICS, LINKS, OR ANY OTHER MATERIALS AND PRODUCTSCONTAINED HEREIN. IN NO EVENT SHALL SAP BE LIABLE FOR ANY DIRECT,
INDIRECT, SPECIAL, INCIDENTAL, CONSEQUENTIAL, OR PUNITIVE DAMAGES OF ANY
KIND WHATSOEVER, INCLUDING WITHOUT LIMITATION LOST REVENUES OR LOST
PROFITS, WHICH MAY RESULT FROM THE USE OF THESE MATERIALS OR INCLUDED
SOFTWARE COMPONENTS.
g200882614053
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 3/522
About This Handbook
This handbook is intended to complement the instructor-led presentation of this
course, and serve as a source of reference. It is not suitable for self-study.
Typographic Conventions
American English is the standard used in this handbook. The following
typographic conventions are also used.
Type Style Description
Example text Words or characters that appear on the screen. Theseinclude field names, screen titles, pushbuttons as well
as menu names, paths, and options.
Also used for cross-references to other documentation
both internal (in this documentation) and external (in
other locations, such as SAPNet).
Example text Emphasized words or phrases in body text, titles of
graphics, and tables
EXAMPLE TEXT Names of elements in the system. These include
report names, program names, transaction codes, tablenames, and individual key words of a programming
language, when surrounded by body text, for example
SELECT and INCLUDE.
Example text Screen output. This includes file and directory names
and their paths, messages, names of variables and
parameters, and passages of the source text of a
program.
Example text Exact user entry. These are words and characters that
you enter in the system exactly as they appear in the
documentation.
<Example text> Variable user entry. Pointed brackets indicate that you
replace these words and characters with appropriate
entries.
2008 © 2008 SAP AG. All rights reserved. iii
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 4/522
About This Handbook TSCM40
Icons in Body Text
The following icons are used in this handbook.
Icon Meaning
For more information, tips, or background
Note or further explanation of previous point
Exception or caution
Procedures
Indicates that the item is displayed in the instructor’s
presentation.
iv © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 5/522
Contents
Course Overview ........ ...... ........ ..... ........ ...... ........ ...... .. vii
Course Goals ... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .viiCourse Objectives ..................................................... ix
Unit 1: Preface ........ ...... ........ ...... ........ ...... ....... ........ ..... 1
Course Overview........................................................ 2
Unit 2: Overview of Production Planning in SAP ERP ... .. .. .. .. . 7
Overview of Supply Chain Planning .. .. .. .. ... ... .. .. .. ... .. .. ... .. .. 8
Unit 3: Demand Management ...... .. .... ... .... .... ... .... .... .... ... 29
Overview of Demand Management... .. .. .. ... ... .. .. .. ... .. .. ... .. 32Planning Make-to-Stock Production................................ 39Planning Make-to-Order Production................................ 84Enhancements for Demand Management .. .. .. .. .. .. .. .. .. .. .. .. 110
Basics of the Availability Check .. .. ... .. .. .. ... ... .. .. .. ... .. .. ... .133
Unit 4: Executing Material Requirements Planning. .. .. .. .. .. .. 157
Overview and Concept of MRP ....................................159Prerequisites for MRP ... .... .... ... .... ... ... .... .... ... .... ... .... .164Setting and Executing the MRP Run .. .. .. .. ... .. .. .. .. ... .. .. ... .172Firming .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .217
Unit 5: Technical Processes in Requirements Planning....... 241
Net Requirements Calculation ... .. ... .. .. .. ... ... .. .. .. ... .. .. ... .244Lot-Size Calculation ... ... .... .... ... .... ... ... ..... ... ... .... ... .... 272Procurement Types..................................................294
Scheduling.... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .307BOM and Routing Selection. .... ... .... ... ... ..... ... ... .... ... .... 335
Unit 6: Evaluating and Processing the MRP Results .. .. .. .. . .. 361
MRP List and Stock/Requirements List .. .. .. .. .. .. .. .. .. .. .. .. .. .363Planning Table........................................................389Exception Messages ..... .... .... ... .... ... ... ..... ... ... .... ... .... 398Additional Evaluation Aids .. .. ... .. ... .. .. .. .. ... ... .. .. .. ... .. .. ... 407
Unit 7: Overview of SAP APO-PP/DS. ... .. ... ... .. .. ... .. ... ... .. .. 427
Introduction to SAP APO-PP/DS.. ... .. .. .. .. ... .. .. .. .. ... .. .. ... .429
Master Data Overview.... .... .... ... .... ... ... ..... ... ... .... ... .... 439
2008 © 2008 SAP AG. All rights reserved. v
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 6/522
Contents TSCM40
Demand Management with APO PP/DS.......................... 461Production Planning with APO PP/DS ............................ 483
Selected Planning Tools in APO PP/DS ... .. .. .. .. .. .. .. .. .. .. .. .497
vi © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 7/522
Course Overview
This folder deals only with the content of the second week of TSCM40. The
first week is covered by the PLM114.
This course teaches you how to handle master data and planning in SAP ECC
and SAP SCM-APO.
The information is based on the release levels SAP ECC 6.0 and SAP SCM 5.1
Target Audience
This course is intended for the following audiences:
• Application consultants responsible for the implementation of planning as
part of the SAP Business Suite in SAP ERP.
Course Prerequisites
Required Knowledge
• SAP120 SAP Navigation (E-Learning)
• ERP001 Management Empowered by SAP ERP (E-Learning)
Recommended Knowledge
• None
Course Duration Details
Unit 1: Preface
Course Overview 20 Minutes
Unit 2: Overview of Production Planning in SAP ERPOverview of Supply Chain Planning 90 Minutes
Exercise 1: Production Planning Process with ECC 20 Minutes
Unit 3: Demand Management
Overview of Demand Management 30 MinutesPlanning Make-to-Stock Production 120 Minutes
Exercise 2: Sales Orders in Make-to-StockProduction 10 Minutes
Exercise 3: Planning with Final Assembly 20 Minutes
Exercise 4: Subassembly Planning 15 Minutes
Planning Make-to-Order Production 90 Minutes
Exercise 5: Planning Without Final Assembly 20 Minutes
Enhancements for Demand Management 90 Minutes
Exercise 6: Customizing 10 Minutes
2008 © 2008 SAP AG. All rights reserved. vii
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 8/522
Course Overview TSCM40
Basics of the Availability Check 60 Minutes
Exercise 7: Availability Check for Sales Order 15 Minutes
Unit 4: Executing Material Requirements Planning
Overview and Concept of MRP 30 Minutes
Prerequisites for MRP 60 Minutes
Setting and Executing the MRP Run 120 Minutes
Exercise 8: Planning File 20 Minutes
Exercise 9: Simulative MRP 20 Minutes
Firming 90 Minutes
Exercise 10: Firming 20 Minutes
Unit 5: Technical Processes in Requirements Planning
Net Requirements Calculation 90 Minutes
Exercise 11: Net Requirements Calculation and
Safety Stock 25 Minutes
Lot-Size Calculation 60 Minutes
Exercise 12: Lot-Size Calculation 15 Minutes
Procurement Types 60 Minutes
Exercise 13: Procurement Type and QuotaArrangement 15 Minutes
Scheduling 90 Minutes
Exercise 14: Scheduling 30 Minutes
BOM and Routing Selection 60 Minutes
Exercise 15: Routing and BOM Selection 10 Minutes
Unit 6: Evaluating and Processing the MRP ResultsMRP List and Stock/Requirements List 60 Minutes
Exercise 16: Functions of the Stock/Requirements
List 15 Minutes
Exercise 17: Display Filter, Selection Rule(Optional) 10 Minutes
Planning Table 30 Minutes
Exception Messages 30 Minutes
Additional Evaluation Aids 30 Minutes
Exercise 18: Collective Display of MRP Lists 10 Minutes
Exercise 19: Rescheduling Check (Optional) 15 Minutes
Unit 7: Overview of SAP APO-PP/DSIntroduction to SAP APO-PP/DS 20 Minutes
Master Data Overview 90 Minutes
Exercise 20: Master Data Overview 25 Minutes
Demand Management with APO PP/DS 75 Minutes
Exercise 21: Planning with Final Assembly inAPO-PP/DS 30 Minutes
Production Planning with APO PP/DS 75 MinutesExercise 22: Executing the Production Planning
Run (Optional) 20 Minutes
viii © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 9/522
TSCM40 Course Overview
Selected Planning Tools in APO PP/DS 90 Minutes
Course Goals
This course will prepare you to:
• To understand the positioning, integration, and functions in the area of
planning within the SAP ERP application and name the main functions in
the secondary application SAP SCM
Course Objectives
After completing this course, you will be able to:
• Evaluate, describe, and implement the options provided by SAP-basedplanning
Preparation before the start of the course
1. In SCM APO: Under Customizing for GATP: Call the check instruction for
the 050 -A combination and deactivate “Rules-based ATP and Immediate
Rule evaluation, without previous check”.
2. Before starting the course, a mass change of the production horizon must be
carried out in SCM APO: Call APO transaction MASSD, load the SCM250_I
variant, set the supply profile to “blank”, set both the SNP production
horizon and PP/DS horizon to 60 days, and save.
User name and passwords for the course participants
The standard format for user names is “the course name plus the group number”:
TSCM40-##. The initial password is INITIAL. Use transaction ZUSR to copy the
user from a reference user (into the ECC and SCM systems):
Copy template: SCM250MUSTER (if this does not exist, use your own user)
Name of the course. TSCM40
Number of exercise groups: For example, 18.
Initial password: INITIAL
To create the user, choose Execute.
In the “Uniqueness of group numbers” dialog box, choose No.
In the “Free Group Numbers Found” dialog box, choose Create.
Important note to Instructor:
2008 © 2008 SAP AG. All rights reserved. ix
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 10/522
Course Overview TSCM40
Days 1-4 cover the first 5 units of the course SCM240 (Production Planning
(ERP)). Special processes such as MRP areas or master production scheduling
are therefore not dealt with. Instead, on day 5, the last unit provides a selectionimportant content from the course SCM250 (Production Planning and Detailed
Scheduling with APO-PP/DS).
The courses SCM240 and SCM250 are therefore best suited as a means of
preparation for this course.
LOCATION FOR THE INFORMATION
XML-BASED TRAINING MATERIAL – INSTRUCTOR HANDBOOK
In the Instructor Handbook for XML based training material the most important
recommended information is also placed under the first “Instructor note” xml-entry
after the “Course Objectives” and before “Introduction” of Unit 1.
RECOMMENDED INFORMATION
HINTS ON PREPARING THIS COURSE
Remember to check for additional information not published after the course
material was finally released. For the latest information or course updates see also
the Instructor Guide/System Setup Guide or Trouble Shooting Guide on SAP
Service Marketplace under the alias /curr-info:
http://service.sap.com/curr-info .
TRAINING SYSTEM
Your training systems will be available and accessible on Sunday evening (CETtime zone) in the week the training takes place. Do not use the system or prepare
your course before that time. The system may still be in use by another course
or in the refresh procedures of the IT preparation for your course! If you need a
test/prep. system before your course takes place, see details under the section
“Test/Prep. System”.
MATERIAL REQUIRED FOR PARTICIPANTS
In this course the following training material is necessary:
• For the first week of the course: PLM114 Coll. 63
(or PLM110 Coll. 52 and PLM111 Coll. 52, if the course is held in German)• For the second week of the course: TSCM40 Coll. 81
DATA REQUIRED
For this TSCM40 course you need a training landscape consisting of an ECC 6.0
system that has been copied from XD0, and the corresponding SCM 5.1 system
that has been copied from FO7.
“Corresponding” means that CIF integration must exist and be active between
both systems.
x © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 11/522
TSCM40 Course Overview
TEST /PREP. SYSTEM
Use the system landscape T37 (ECC) and TO7 (SCM) for your course preparation.
You need to use client 800. If you do not have a user, the systems are not available,
or the systems do not work correctly, please open a CSS ticket.
Do not use T37/TO7 in your training! Otherwise an access violation fee will be
charged by KPS.
TRAINING WTS FARM
If necessary, you can work via WTS (Windows Terminal Server).
• Training at SAP training centers/Internal SAP training
The internal connectivity to the training WTS farms can only be used inside
the SAP network infrastructure.To connect to the training WTS farm use http://wts.wdf.sap.corp:1080.
Choose your home region (US, EMEA or APJ). Select the “Training Zone”
menu. Connect to “Common Training”, if no other WTS farm is named
for the training.
• Customer Onsite training / Third party training center
Customer Onsite training can only connect to SAP training WTS farm via
the SAP Citrix Secure Gateway (SAP CSG). You therefore need a CSG-User
ID. The User ID needs to have been created by the education department in
time for the training. The data (User ID and password) are delivered to you
by the education department. The instructor and participants use the samededicated CSG-User-ID and password for the training.
To connect to the training WTS farm use https://mywts.sap.com.
Enter the CSG-User ID and password. Choose your home region (US,
EMEA or APJ). Select the “Training” icon. Connect to “Common Training”,
if no other WTS farm is named for the training.
USER ID AND PASSWORDS FOR THE COURSE
• Training with Reference User IDs:
To create the participants’ users (and, if necessary, your instructor user)
directly before the course starts, log on to both training systems with the user
“Training”. The monthly changed password should be delivered by your
education department in the training information email/documentation. The
standard format for User IDs is the course ID (here: TSCM40), followed by
the group number (here: ## being the group number 00 up to max. 30).
The User IDs will thus be "TSCM40-##". The initial password is INITIAL
(capital letters!). Use transaction ZUSR to copy these User IDs from the
reference User ID (e.g. from your own user or from the user SCM250muster).
2008 © 2008 SAP AG. All rights reserved. xi
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 12/522
Course Overview TSCM40
ADDITIONAL PREPARATION IN THE SYSTEM
• Example ABAPs
none
• CATTs/eCATTS
no CATTs needed
• Switching on/off table locking in SAP systems
Call transaction SE38, run the report ZSENQOFF (Customizing is needed by
participants in parallel on the second course day).
TECHNICAL HINTS
Further activities to be carried out before the course commences:• General CIF-check: Post goods receipt - other - for T-F200: 15 pcs, storage
location 0002 in ECC (transaction MIGO) and check result in the product
view in SCM.
• Global ATP: Maintain check instructions in SCM: 050 – A: Deactivate RBA,
deactivate Start Immediately
• PP/DS: Set SNP and PP/DS horizon for the products T-F2##, T-B1##,
T-B22##, T-B3##, and T-B4## to 60 days using transaction MASSD in
SCM, variant SCM250_I
For further information please refer to XML instructor versions of SCM240 Coll.
81, SCM250 Coll. 81 or previous instructor guides (SAP corporate portal).
xii © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 13/522
Unit 11 Preface
Use this unit to present the course schedule and contents to the participants in
the form of a general preview.
Unit Overview
The course materials provide a detailed view of material requirements planning
(MRP) in ECC as well as an overview of the main functions of extended planning
in APO-PP/DS.
Unit Objectives
After completing this unit, you will be able to:
• Gain an overview of the content of this week of the course.
Unit Contents
Lesson: Course Overview ..... ... .... ... .... .... ... ... .... .... ... ... .... ... .... ..2
2008 © 2008 SAP AG. All rights reserved. 1
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 14/522
Unit 1: Preface TSCM40
Lesson:
2
Course Overview
Lesson Duration: 20 Minutes
Lesson Overview
The content of the second week of TSCM40 is presented and placed in the overall
context.
Lesson Objectives
After completing this lesson, you will be able to:
• Gain an overview of the content of this week of the course.
The course TSCM40, which constitutes the first part of the Partner Academy
“Planning & Manufacturing”, is divided into 2 parts: Master data, which is
covered in the first week with PLM, and production planning, which is dealt with
in the second week using these course materials.
Business Example
The course TSCM40 contains master data from logistics and planning aspects
from the ECC (main focus) and SCM-APO (overview) systems
Figure 1: SAP Consultant Training
2 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 15/522
TSCM40 Lesson: Course Overview
Figure 2: Content Covered in This Week of the Course
2008 © 2008 SAP AG. All rights reserved. 3
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 16/522
Unit 1: Preface TSCM40
Facilitated Discussion
Point out to the participants the main points of emphasis and objectives of the
course. If necessary, explain how these main points of emphasis are weighted
in the certification test.
Discussion Questions
Use the following questions to engage the participants in the discussion. Feel free
to use your own additional questions.
4 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 17/522
TSCM40 Lesson: Course Overview
Lesson Summary
You should now be able to:• Gain an overview of the content of this week of the course.
2008 © 2008 SAP AG. All rights reserved. 5
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 18/522
Unit Summary TSCM40
Unit Summary
You should now be able to:
• Gain an overview of the content of this week of the course.
6 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 19/522
Unit 2 7 Overview of Production Planning in
SAP ERP
Welcome the participants and introduce the course content and objectives.
Familiarize the participants with the course schedule. Ask them to introduce
themselves.
Unit Overview
Describe the content and organizational aspects of the course. It is important to
show where the course belongs in the SCM curriculum. The course operates
exclusively within SAP ECC as far as content, demonstrations, and exercises are
concerned, dealing with the production planning process in the system. The course
builds on the basics covered in SCM100.
As an introduction, put the production planning process into context: Talk about
the entire planning chain from (optional) sales and operations planning to shop
floor control. Do not go into detail about the functions. Instead, show how the
contents of the course relate to the neighboring business processes.
Unit Objectives
After completing this unit, you will be able to:
• Place the course content in the overall context
• Outline the business scenario used
• Give an overview of Supply Chain Planning in ECC
Unit Contents
Lesson: Overview of Supply Chain Planning...................................8Demonstration: Production Planning Process with ECC. .. .. .. .. .. .. .. 14
Exercise 1: Production Planning Process with ECC.................... 17
2008 © 2008 SAP AG. All rights reserved. 7
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 20/522
Unit 2: Overview of Production Planning in SAP ERP TSCM40
Lesson:
8
Overview of Supply Chain Planning
Lesson Duration: 90 Minutes
Lesson Overview
Welcome the participants and introduce the course content and objectives.
Familiarize the participants with the course schedule. Get the participants to
introduce themselves.
Lesson Objectives
After completing this lesson, you will be able to:
• Place the course content in the overall context
• Outline the business scenario used
• Give an overview of Supply Chain Planning in ECC
You should point out here that production control and capacity requirements
planning are not dealt with in this course, but in the courses SCM310 and SCM360.
This course focuses on requirements planning.
If necessary, you can go straight to unit 5 (Evaluations) after you have completed
this unit. For information about this, see the note in the description of the overview
demonstration Production Planning Process with ECC at the end of this unit.
Business Example
Your company is implementing production planning and detailed scheduling
using ECC MRP.
You use the example of the Precision Pump Company to familiarize yourself with
the functions of MRP. The Precision Pump Company offers various standard
pumps.
After you have entered future requirement quantities in demand management,
you plan production in the production plant. Externally procured or low value
materials should, if necessary, be planned using consumption-based planning.
Possible SAP Components of Supply Chain Planning
Describe the system landscape in the SAP planning environment. Explain in
particular the special characteristics of the different systems in the landscape.
8 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 21/522
TSCM40 Lesson: Overview of Supply Chain Planning
Figure 3: Possible SAP Components of Supply Chain Planning
SC planning primarily uses the following SAP components: SAP ECC (ERP
Central Component), SAP SCM (including APO, Advanced Planning and
Optimization), and SAP BW (Business Information Warehouse). The SAP
SCM system contains many components that constituted separate systems in
earlier releases. As well as APO, SCM 4.1 also includes Supply Chain Event
Management (EM) and Inventory Collaboration Hub (ICH).
The interfaces responsible for integrating ECC with BW or SCM APO are made
available using a corresponding Plug-In. The interface between ECC and SCM
APO is called the Core Interface (CIF).
Supply Chain Planning in ECC
Describe the steps in the ECC production planning process and place these in
the overall business context.
Some frequently used abbreviations:
• Sales and Operations Planning = SOP
• Material Requirements Planning = MRP
• Master Production Scheduling = MPS
• Long-Term Planning = LTP
2008 © 2008 SAP AG. All rights reserved. 9
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 22/522
Unit 2: Overview of Production Planning in SAP ERP TSCM40
Figure 4: Supply Chain Planning in ECC
Supply Chain Planning in SAP ECC can be divided into several steps: Planning
takes place in demand management. Consumption of the forecast with sales orders
is possible. Long-term planning is simulative planning. You can use it to analyze
a demand program to see how feasible it is, for example. Master production
scheduling is requirements planning for master schedule items. Non-master
schedule items are planned in material requirements planning.
Figure 5: Production Planning and Control
10 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 23/522
TSCM40 Lesson: Overview of Supply Chain Planning
Demand Management
Repeat the most important points relevant to this subject from the course SCM100.
Figure 6: Demand Management
Demand Management is the management of independent requirements. The
behavior of independent requirements in material requirements planning (for
example, whether they are effective, or whether they consume other requirements)
is determined by their requirements type or by the planning strategy.
Planned independent requirements are stock requirements that can be derived
from a forecast of future demand. In make-to-stock production, you want to start
procurement of the affected materials without waiting for specific sales orders. On
the one hand, this kind of procedure allows you to reduce delivery times, while on
the other hand, you can use forecast planning to spread the burden as evenly as
possible across your production resources.
Sales orders (customer independent requirements) are created in Sales and
Distribution. Customer requirements can enter Material Requirements Planningdirectly, depending on their requirement type. This is always desirable if you want
to plan for specific customers.
Sales orders can be used either as exclusive requirement sources, for which
procurement is then specifically triggered (make-to-order production), or they can
be grouped with planned independent requirements to create the total requirements.
Consumption is also possible with planned independent requirements.
2008 © 2008 SAP AG. All rights reserved. 11
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 24/522
Unit 2: Overview of Production Planning in SAP ERP TSCM40
MRP Procedures
Point out the differences between the two basic MRP procedures. Refer to training
course SCM525, if required.
Figure 7: MRP Procedures
If you want to plan material requirements automatically, you must define suitable
MRP and lot-sizing procedures in the material master. To do this, use the MRP
type and lot size indicators. Depending on the procedure you choose, you then
have to maintain further data in the material master. You can define different MRP
procedures for a material in different plants.
The two main planning procedures are consumption-based planning and material
requirements planning.
Consumption-based planning is based on historical consumption values and
uses forecasting or statistical procedures to determine future requirements.
Consumption-based planning is characterized by its simplicity and is mainly used
for B and C parts with a low value. One prerequisite of consumption-based
planning is efficient and constantly up-to-date inventory management.
In contrast to consumption-based planning, material requirements planning takes
current and future sales as a reference point and is executed for the whole BOM
structure. The planned requirement quantities trigger the MRP calculation. It
produces better planning results than consumption-based planning.
12 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 25/522
TSCM40 Lesson: Overview of Supply Chain Planning
The principle of MRP
Explain the basic characteristics of MRP. Go into sufficient detail, as the first
exercise on this subject follows on from your explanation.
Figure 8: The principle of MRP
In the first step for detailed planning in MRP, the procurement dates and quantities
for the required assemblies and components are determined based on the
requirements dates and quantities for the finished product (for example, a sales
order). Bills of material and routings must be exploded to do this.
Scheduling of procurement for in-house products is carried out using the routing.
The production operations to be executed and the length of the individual
operations are specified in the routing. The assemblies (from the BOM) required
for production must be available when production of the finished product is
started. Procurement of these assemblies must therefore be initiated earlier. In this
way, assuming the dependent requirements date is the availability date, the systemdetermines the order dates of the components by means of backward scheduling
using the in-house production time or planned delivery time.
2008 © 2008 SAP AG. All rights reserved. 13
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 26/522
Unit 2: Overview of Production Planning in SAP ERP TSCM40
Demonstration: Production Planning Process withECC
Purpose
Overview demo of the entire planning process
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Do the exercise in the introductory unit as a demonstration. Take account
of the fact that this may be the first time some of the participants have seen
the transactions used! If in doubt, take more time.
Material: R-F1## in plant 1000
2. Note: If you think it would be better to go into more detail about the
evaluation tools stock/requirements list and MRP list here, (for example,
because the majority of the participants are MRP controllers), go straight to
unit 5 (Evaluations).
Call the tools (transactions MD04, MD05, MD06, MD07) one after the
other. Use the slides and exercises from unit 5 to explain the basic features
and where they are used. If necessary, you can go through the whole of
unit 5 here.
If you decide to do this, go through all the exercises from unit 5 directly
after exercise 1.
The advantage: The participants can start using these evaluation tools to
evaluate their planning results right away without having to wait until the
fourth day of the course when they cover the unit about evaluations.
3. Alternative option: If you want to demonstrate the whole process (including
Demand Planning), you can use the following system demonstration.(Caution, this demonstration is suitable only for experienced trainers since
the contents exceeds the concepts covered in the course and it requires
knowledge of Demand Planning).
3.1 Generate the product group pump-## in plant 1000 [transaction MC84],
base unit of measure pc, member materials and maintain the following data:
14 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 27/522
TSCM40 Lesson: Overview of Supply Chain Planning
Material number Plant Proportional factor
T-F1## 1000 60%
R-F1## 1000 40%
3.2 Call the planning tool in change mode [transaction MC82], active
version, and maintain the following sales figures:
Period Month
+3
Month
+4
Month
+5
Month
+6
Month
+7
Month
+8
Sales 600 700 500 900 1000 1100
3.3 Now generate a synchronous to sales production plan and save it.3.4 Release the production plan [transaction MC75] and write it to the active
planned independent requirements version 00.
3.5 Check the result in the stock/requirements list [transaction MD04]
and interpret it.
3.6 If necessary, carry out material requirements planning [transaction
MD02] and interpret the results.
2008 © 2008 SAP AG. All rights reserved. 15
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 28/522
Unit 2: Overview of Production Planning in SAP ERP TSCM40
16 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 29/522
TSCM40 Lesson: Overview of Supply Chain Planning
13 Exercise 1: Production Planning Process
with ECCExercise Duration: 20 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Execute the main steps required for the production planning process in
SAP ECC.
Business Example
Precision Pumps Inc uses the make-to-stock production strategy. The
make-to-stock production strategy is used. Pumps are manufactured, put away,
and then sold.
Task 1:
In plant 1000, enter a demand program (planned independent requirements) for
material R-F1## (replace ## with your group number). Select make-to-stock
production (LSF requirements) for the first 8 weeks of your planning period.
To do this, proceed as follows:
1. Maintain the material master: In the material master for pump R-F1##, enter
strategy group 10 for plant 1000 in the MRP 3 view and save the change.
2. In Demand Management, enter the planned independent requirements
(requirement type LSF) for material R-F1## in plant 1000 (version 00).
Set the planning period to week format by entering the indicator W in the
planning period field in the initial screen for the transaction. Enter the
following planned independent requirements for pump R-F1## in plant
1000:
Current
Week + 5
Current
Week + 6
Current
Week + 7
...Current
Week + 12
25 25 25 ...25
(Total quantity: 200 pieces, the first column on the left-hand side in
transaction MD61 is the current week)
Save your entries.
3. From the MRP menu, display the stock/requirements list for material
R-F1## in plant 1000.
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 17
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 30/522
Unit 2: Overview of Production Planning in SAP ERP TSCM40
Note down the exact date of the second LSF require-
ment:______________________
Task 2:
From the MRP menu, carry out multilevel, single-item planning for pump
R-F1##. In the initial screen of the planning run, use the following creation
indicators:
Processing key NETCH
Purchase req. purchase req. 2
Scheduling agreement schedule lines
3
Create MRP list 1
Planning mode 1
Scheduling 1
Also plan unchanged components Select
Display results Do not select
Display material list Select
Simulation mode Do not select
1. In the initial screen for single-item, multilevel MRP, save the creation
indicator setting you have made for the MRP run by selecting the menu
path Settings → Save.
2. Start the MRP run by choosing Enter and confirm the system warning by
choosing Enter again.
Task 3:
Once the MRP run has been carried out successfully, the system displays the
statistics.
1. Choose the Material List pushbutton and select the row containing your
pump R-F1## by clicking on the button at the beginning of the row. Goto
the display for the current stock-/requirements list for the material and
refresh the screen (F6).You can now see the planned orders created for the
requirements.
Continued on next page
18 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 31/522
TSCM40 Lesson: Overview of Supply Chain Planning
2. Display one of the planned orders by double-clicking it and choosing Display
Element. Select the Component Overview pushbutton and compare the
order start date of the end product R-F1## with the requirements date for theassemblies R-B1##, R-B2## and R-B3##. How do you explain the date?
__________________________________________________________________
__________________________________________________________________
Then exit the display for the planned order and the stock-/requirements list
(understand that you navigated in the stock-/requirements list in display
mode).
Task 4:
Call the current stock/requirements list again and convert the first two plannedorders into production orders. Then release each production order.
1. From the MRP menu, display the current stock/requirements list for material
R-F1## in plant 1000.
2. Click on the Details of Element icon to display the statistics for the first
planned order in the list. Choose the Convert planned order into production
order function.
Release the production order and save the order
3. Repeat the operation for the second planned order.
4. Refresh the display by selecting Refresh. Make a note of the productionorder numbers.
Production order number 1
_______________________________________
Production order number 2
_______________________________________
Hint: You may have to wait a few seconds for the asynchronous
update to read the data from the queue and update it to the database.
You can call the refresh function several times until you see theproduction orders.
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 19
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 32/522
Unit 2: Overview of Production Planning in SAP ERP TSCM40
Task 5:
Now assume that you have produced the product, and can post the end product,
the pump, to stock. (We will skip completion confirmation for the purposes of
this training example)
1. Execute the goods movement (more precisely: the Goods receipt for
the order MIGO with the transaction MIGO_GO) from the Inventory
Management menu.
In this transaction, use Goods Receipt and Order, not Display, to make your
selections. Enter the order number and choose Enter to confirm your entry.
Select the Item OK field. You may have to scroll down to see this.
Take a look at the Where tab page to make sure that the movement type 101
has been defined (order to stock).
Post the goods movement.
Repeat the operation for the second order number.
2. Check the stock situation in the stock/requirements list and make a note of
the quantity of the oldest planned independent requirement:
_____________________
the date of the oldest planned independent requirement:
_____________________
the quantity available today: _____________________
20 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 33/522
TSCM40 Lesson: Overview of Supply Chain Planning
Solution 1: Production Planning Process
with ECCTask 1:
In plant 1000, enter a demand program (planned independent requirements) for
material R-F1## (replace ## with your group number). Select make-to-stock
production (LSF requirements) for the first 8 weeks of your planning period.
To do this, proceed as follows:
1. Maintain the material master: In the material master for pump R-F1##, enter
strategy group 10 for plant 1000 in the MRP 3 view and save the change.
a) Menu path: Logistics → Production → Master Data → Material
Master → Material → Change → Immediately
2. In Demand Management, enter the planned independent requirements
(requirement type LSF) for material R-F1## in plant 1000 (version 00).
Set the planning period to week format by entering the indicator W in the
planning period field in the initial screen for the transaction. Enter the
following planned independent requirements for pump R-F1## in plant
1000:
Current
Week + 5
Current
Week + 6
Current
Week + 7
...Current
Week + 12
25 25 25 ...25
(Total quantity: 200 pieces, the first column on the left-hand side in
transaction MD61 is the current week)
Save your entries.
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Planned Independent Requirements → Create
3. From the MRP menu, display the stock/requirements list for material
R-F1## in plant 1000.
Note down the exact date of the second LSF require-
ment:______________________
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Environment → Stock/Requirements List
Date of second LSF requirement: Varies
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 21
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 34/522
Unit 2: Overview of Production Planning in SAP ERP TSCM40
Task 2:
From the MRP menu, carry out multilevel, single-item planning for pump
R-F1##. In the initial screen of the planning run, use the following creation
indicators:
Processing key NETCH
Purchase req. purchase req. 2
Scheduling agreement schedule lines 3
Create MRP list 1
Planning mode 1
Scheduling 1
Also plan unchanged components Select
Display results Do not select
Display material list Select
Simulation mode Do not select
1. In the initial screen for single-item, multilevel MRP, save the creation
indicator setting you have made for the MRP run by selecting the menu
path Settings → Save.
a) Menu path: Logistics → Production → MRP → Planning →
Single-Item, Multi-Level
2. Start the MRP run by choosing Enter and confirm the system warning by
choosing Enter again.
a) Menu path: Logistics → Production → MRP → Planning →
Single-Item, Multi-Level
Continued on next page
22 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 35/522
TSCM40 Lesson: Overview of Supply Chain Planning
Task 3:
Once the MRP run has been carried out successfully, the system displays the
statistics.
1. Choose the Material List pushbutton and select the row containing your
pump R-F1## by clicking on the button at the beginning of the row. Goto
the display for the current stock-/requirements list for the material and
refresh the screen (F6).You can now see the planned orders created for the
requirements.
a) No solution required.
2. Display one of the planned orders by double-clicking it and choosing Display
Element. Select the Component Overview pushbutton and compare the
order start date of the end product R-F1## with the requirements date for the
assemblies R-B1##, R-B2## and R-B3##. How do you explain the date?
__________________________________________________________________
__________________________________________________________________
Then exit the display for the planned order and the stock-/requirements list
(understand that you navigated in the stock-/requirements list in display
mode).
a) How do you explain the date? The requirements dates for the
assemblies coincide with the order start date of the planned order
for the finished product. The assemblies are therefore available at the
start of production for the finished product.
Task 4:
Call the current stock/requirements list again and convert the first two planned
orders into production orders. Then release each production order.
1. From the MRP menu, display the current stock/requirements list for material
R-F1## in plant 1000.
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Environment → Stock/Requirements List
2. Click on the Details of Element icon to display the statistics for the firstplanned order in the list. Choose the Convert planned order into production
order function.
Release the production order and save the order
a) No solution required.
3. Repeat the operation for the second planned order.
a) No solution required.
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 23
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 36/522
Unit 2: Overview of Production Planning in SAP ERP TSCM40
4. Refresh the display by selecting Refresh. Make a note of the production
order numbers.
Production order number 1
_______________________________________
Production order number 2
_______________________________________
Hint: You may have to wait a few seconds for the asynchronous
update to read the data from the queue and update it to the database.
You can call the refresh function several times until you see the
production orders.
a) Production order number 1: Varies
Production order number 2: Varies
Task 5:
Now assume that you have produced the product, and can post the end product,
the pump, to stock. (We will skip completion confirmation for the purposes of
this training example)
1. Execute the goods movement (more precisely: the Goods receipt for
the order MIGO with the transaction MIGO_GO) from the Inventory
Management menu.
In this transaction, use Goods Receipt and Order, not Display, to make your
selections. Enter the order number and choose Enter to confirm your entry.
Select the Item OK field. You may have to scroll down to see this.
Take a look at the Where tab page to make sure that the movement type 101
has been defined (order to stock).
Post the goods movement.
Repeat the operation for the second order number.
a) Menu path: Logistics → Materials Management → Inventory Management → Goods Movement → Goods Receipt → GR for Order
(MIGO)
Alternatively, you can also use transaction MIGO (goods movement
MIGO).
2. Check the stock situation in the stock/requirements list and make a note of
Continued on next page
24 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 37/522
TSCM40 Lesson: Overview of Supply Chain Planning
the quantity of the oldest planned independent requirement:
_____________________
the date of the oldest planned independent requirement:
_____________________
the quantity available today: _____________________
a) the quantity of the oldest planned independent requirement: 25
the date of the oldest planned independent requirement: Varies
the quantity available today: 50
2008 © 2008 SAP AG. All rights reserved. 25
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 38/522
Unit 2: Overview of Production Planning in SAP ERP TSCM40
Lesson Summary
You should now be able to:• Place the course content in the overall context
• Outline the business scenario used
• Give an overview of Supply Chain Planning in ECC
26 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 39/522
TSCM40 Unit Summary
Unit Summary
You should now be able to:
• Place the course content in the overall context
• Outline the business scenario used
• Give an overview of Supply Chain Planning in ECC
2008 © 2008 SAP AG. All rights reserved. 27
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 40/522
Unit Summary TSCM40
28 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 41/522
Unit 3 25 Demand Management
Introduce the most important planning strategies for make-to-stock production and
sales order based production, which are not dealt with (in detail) in SCM100.
Discuss the strategies for assembly processing too, giving examples along theway. Conclude the unit with an explanation of types of planned independent
requirements reduction dependent on the respective strategy, and the options
available for adjusting and reorganizing planned independent requirements.
Mention the availability check in passing (but do not go into detail, as this could
side-track the discussion). Discuss the relevant Customizing settings in this
context too.
Unit Overview
Demand Management represents the first step in the planning process from the
perspective of this course. This unit (and course) does not cover the determinationof the actual level of the planned independent requirements – this is the task of
preliminary demand planning, and can be realized in the SAP system by executing
Sales and Operations Planning (or alternatively in SAP SCM (APO-DP = Demand
Planning)). Normally, the forecasting technique is used here.
Assuming that the planning figures are known, this unit deals with the issue of the
requirements type for planned independent requirements. The requirements type
is determined (or rather, can be determined) by the strategy entered in the material
master. Point out that a strategy is usually defined by a planned independent
requirement type and a customer requirement type, and the interaction between
the two.
In this course, sales orders are simulated by customer requirements (a sales order
creates a customer requirement), since you have to create a delivery in order
to cancel out a sales order (for which there is not enough time in this course).
Otherwise customer requirements behave in the same manner as sales orders.
Introduce the various strategies in detail and explain their functions. There
are strategies that take effect at finished product level, and assembly strategies
that are used for planning an assembly. The functions of planned independent
2008 © 2008 SAP AG. All rights reserved. 29
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 42/522
Unit 3: Demand Management TSCM40
requirement consumption with customer requirements or dependent requirements
and the functions of planned independent requirement reduction are important in
understanding how the strategies work.
Furthermore, this unit will look explicitly at the availability check against planning
and the availability check with ATP logic, although both these issues really come
under the area of Sales. Nevertheless, this integrated whole must be dealt with
from two perspectives: Availability checks can also play a role in production
planning (checking for available components from planned orders or production
orders). You should also point out the difference between the net requirements
calculation and the availability check.
Unit Objectives
After completing this unit, you will be able to:
• Use the planning strategy
• Explain the interplay between planned independent requirements and
customer requirements
• Use planning strategies for make-to-stock production
• Use planning strategies for make-to-order production
• Explain assembly processing
• Make demand management settings
• Make an adjustment and reduce requirements
• Carry out ATP checks for sales orders
Unit Contents
Lesson: Overview of Demand Management ................................. 32Lesson: Planning Make-to-Stock Production................................. 39
Demonstration: ECC Strategy 10 (Make-to-Stock Production), NetRequirements Planning... .... ... ... ..... ... ... .... ... .... .... ... ... .... .... 44Demonstration: ECC Strategy 30 (Production by Lot Size)............ 47
Demonstration: ECC Strategy 40 (Planning with Final Assembly): Part
1: Creating Planned Independent Requirements ....................... 49Demonstration: ECC Strategy 40 (Planning with Final Assembly): Part2: Planning, Evaluation and Independent Requirement Reduction... 52Demonstration: Subassembly Planning (70)... .. .. .. .. .. .. .. .. .. .. .. .. .. 58
Exercise 2: Sales Orders in Make-to-Stock Production .. .. .. .. .. .. .. .. 61Exercise 3: Planning with Final Assembly ............................... 67
Exercise 4: Subassembly Planning .... .. .. .. ... .. .. ... .. ... .. .. .. .. ... ... 77Lesson: Planning Make-to-Order Production ................................ 84
Demonstration: Pure Make-to-Order Production. .. .. .. .. .. .. .. .. .. .. .. . 90
Demonstration: Planning Without Final Assembly (50) .. .. .. .. .. .. .. .. 97Demonstration: Assembly Processing: Prerequisites and Settings . 100
30 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 43/522
TSCM40 Unit 3: Demand Management
Demonstration: Assembly Processing.. ... .. .. .. .. ... .. .. .. .. ... .. .. ... .101Exercise 5: Planning Without Final Assembly .. .. .. .. .. .. .. .. .. .. .. .. .. 103
Lesson: Enhancements for Demand Management .. .. .. .. .. .. .. .. .. .. .. .. 110Demonstration: Adjustment ............................................... 114Demonstration: Reorganization Compared to Adjustment, Using Data
from the Adjustment Demonstration (Optional). .. .. .. .. .. .. .. .. .. .. .. .. 117Demonstration: MRP Settings in the Material Master, MRP Group,Plant... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 119Demonstration: Customizing: Planned Independent Requirements
Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .123Exercise 6: Customizing..... ... .... .... ... .... ... ... ..... ... ... .... ... .... 127
Lesson: Basics of the Availability Check.....................................133Demonstration: Planned Order ATP (Optional)... .. .. .. .. .. .. .. .. .. .. .. 139Demonstration: Availability Check for Sales Orders .. .. .. .. .. .. .. .. .. .141Exercise 7: Availability Check for Sales Order . .. .. .. .. .. .. .. .. .. .. .. .. 145
2008 © 2008 SAP AG. All rights reserved. 31
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 44/522
Unit 3: Demand Management TSCM40
Lesson:
27
Overview of Demand Management
Lesson Duration: 30 Minutes
Lesson Overview
The fundamental concepts of demand management and the terms specific to this
area will be explained.
Lesson Objectives
After completing this lesson, you will be able to:
• Use the planning strategy
• Explain the interplay between planned independent requirements and
customer requirements
Space for notes
Business Example
You are a member of a project team in a company that manufactures pumps. The
team is responsible for the implementation of production planning, from demandmanagement to material requirements planning. The pumps are not configurable.
You want to use planning strategies for the procurement of non-configurable
pumps in Demand Management.
Overview: Requirements calculation and motivation for the planning
strategies
Explain the relationship of demand management to material requirements
planning.
Explain the different types of planned independent requirements that are
represented in the SAP system. In this context, describe the importance and
purpose of a planning strategy.
32 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 45/522
TSCM40 Lesson: Overview of Demand Management
Figure 9: Overview: Requirements Calculation
With regard to later procurement and therefore requirement coverage, it is first
useful to take an overview of the net requirements calculation for material
requirements planning. A procurement is generally necessary only if the
requirements situation exceeds the stock/receipt situation at the time of the
comparison. Here, it is important which requirements are included in the
requirements situation and how the requirements affect each other (for example,
whether they are MRP-relevant and whether they offset each other). The
respective requirements volume (and therefore the production program) also
depends on the default settings maintained in the planning or requirement strategy.
Note that, from a technical point of view, this behavior is not the same as an
availability check . The above comparison is a net requirements calculation.
This unit deals with the properties of the important ECC planning strategies and
how to use them to generate a relevant production program.
2008 © 2008 SAP AG. All rights reserved. 33
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 46/522
Unit 3: Demand Management TSCM40
Figure 10: Reasons for using planning strategies
A requirement is the quantity of a material that is required at a certain time in a
plant.
Planned independent requirements have no relation to the requirements of other
materials. In particular, planned independent requirements can be attained using
flexible planning or manual planning in the ECC system. They can also be
characterized under the general term “planning”. Together with sales orders they
form dependent requirements.
A planning strategy specifies one of a number of possible material planning
procedures.
Some planning strategies support make-to-stock production. You could, for
example, plan production or purchasing based on a forecast and then cover the
sales orders from the stock.
Some planning strategies support make-to-order production. In this case, you
may not start production or purchasing, for example, until a sales order has been
received.
Some requirements strategies support a combination of make-to-stock and
make-to-order production. You could produce the subordinate assembly based
on a forecast, for example. You would not start the final assembly until a sales
order is received.
34 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 47/522
TSCM40 Lesson: Overview of Demand Management
Spectrum of planning strategies and overview: Important planning strategies
in ECC
Outline the characteristics of and differences between the basic requirements
strategies and list the most important planning strategies for this course.
Figure 11: Spectrum of Planning Strategies
A number of options are available for planning production with the help of
planned independent requirements. The different effects that planned independent
requirements can have is controlled in ECC by the planning strategy.
If you use make-to-stock production strategies, production usually takes place
without there being sales orders for the respective material. If sales orders are then
received, these can be met by warehouse stock so that short delivery times can be
realized. With make-to-stock production, it is also possible to implement a steady
production process, independent of the current demand.
Make-to-stock production can also be executed for assemblies. In this case, the
finished products themselves are not produced to stock, but rather the necessaryassemblies are procured. A sales order for a finished product can usually be
fulfilled quickly because only final assembly remains to be carried out and the
assemblies required for this already exist.
Sales-order based production is not based on planning in the real sense; rather
a product is procured for an existing sales order. Make-to-order production is
often used in connection with subassembly planning for the components, to keep
delivery times as short as possible.
2008 © 2008 SAP AG. All rights reserved. 35
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 48/522
Unit 3: Demand Management TSCM40
Figure 12: Overview: Important Planning Strategies in ECC
The make-to-stock production strategies plan production or procurement using
planned independent requirements, which can be created from sales or forecast
figures. Sales orders are fulfilled by warehouse stock. Make-to-stock production
strategies are used in industries where demand and sales fluctuate but where
production should be kept at full capacity. Fluctuations in demand and sales are
balanced out by warehouse stock.
When working with the strategies for make-to-order production, the sales order is
the only pegged requirement. In addition to standard make-to-order production,
planning without final assembly is also possible. Various strategies for assembly
processing are also available.
36 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 49/522
TSCM40 Lesson: Overview of Demand Management
Facilitated Discussion
Discuss the term “planning strategy”.
Discussion Questions
Use the following questions to engage the participants in the discussion. Feel free
to use your own additional questions.
What setting is made with a planning strategy?
2008 © 2008 SAP AG. All rights reserved. 37
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 50/522
Unit 3: Demand Management TSCM40
Lesson Summary
You should now be able to:• Use the planning strategy
• Explain the interplay between planned independent requirements and
customer requirements
38 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 51/522
TSCM40 Lesson: Planning Make-to-Stock Production
Lesson:
32
Planning Make-to-Stock Production
Lesson Duration: 120 Minutes
Lesson Overview
Planning make-to-stock production is mainly done using planned independent
requirements. Sales orders can be taken into account too, without the need for
sales order-specific planning.
Lesson Objectives
After completing this lesson, you will be able to:
• Use planning strategies for make-to-stock production
Space for notes
Business Example
Pump production is planned independently of sales orders using planned
independent requirements.
Important Make-to-Stock Production Strategies
Emphasize some of the basic characteristics of make-to-stock production and
provide a general idea of the illustrated make-to-stock production strategies
(10, 30, 40, 70).
2008 © 2008 SAP AG. All rights reserved. 39
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 52/522
Unit 3: Demand Management TSCM40
Figure 13: Important Make-to-Stock Production Strategies
Make-to-Stock Production: Overview
Describe the basic process of make-to-stock production again and point out
that the most important make-to-stock production strategies will be looked at
individually in the section that follows.
Figure 14: Make-to-Stock Production: Overview
40 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 53/522
TSCM40 Lesson: Planning Make-to-Stock Production
Areas of use: Make-to-stock production strategies are designed for planning the
procurement of components (production or purchasing) by planning the finished
product. If it is easier for you to plan at component level, you can use planning atassembly level. Choose a make-to-stock production strategy if a) the materials do
not have to be stored separately or are assigned to a specific sales order; b) the
costs have to be visible at material level, in other words not at sales order level.
You use make-to-stock production when you produce stock independently of an
order, because you want to supply your customers with goods from this stock
later. You may want to produce goods without a sales order if you expect a
demand for them in the future. Make-to-stock strategies thus support very close
customer-supplier relationships, since their purpose is to supply the customer with
goods from stock as quickly as possible. Returns that have undergone a quality
check and other unplanned goods receipts can be used for other sales orders.
You can avoid increased warehouse stock in a make-to-stock environment bycreating planned independent requirements in advance to plan your stock. If you
do this, you can also decide whether sales orders that extend beyond your plan
can influence production. In addition, sales orders should be known at a relatively
early stage (for example, using scheduling agreements). Make-to-stock production
strategies generally consist of four phases: Generation of planned independent
requirements, procurement, receipt of sales order, goods issue for delivery and
reduction of planned independent requirements.
Make-to-Stock Production (10)
The sales order does not come into play; there is no consumption.
Figure 15: Make-to-Stock Production (10)
2008 © 2008 SAP AG. All rights reserved. 41
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 54/522
Unit 3: Demand Management TSCM40
In pure make-to-stock production (“net requirements planning” according to
strategy 10), the demand program is specified without reference to sales orders.
Sales orders are not relevant for MRP, but you can display them for information
purposes. You can make this setting in the No MRP field in Customizing for
the relevant requirements class (work step, “Define Requirements Classes” in
Customizing for Sales and Distribution).
Sales orders are fulfilled from stock. No consumption with planned independent
requirements occurs. You can carry out the availability check with ATP logic
in Sales and Distribution. Goods withdrawals against a sales order reduce the
respective sales order.
Reduction of the demand program, that is, of the planned independent
requirements, is carried out at goods issue (the PIR reduction indicator must be
set in Customizing for customer requirements class 30 if you want to reduce thedemand program by delivering to a sales order). The oldest planned independent
requirement is reduced first, in accordance with the FIFO (first in first out)
principle, using the requirement date as a basis. Future planned independent
requirements are also reduced by goods issues, providing this is allowed by the
“forward consumption period” in the material master.
Make-to-Stock Production (10): Master Data
Point out the importance of the forward consumption period in make-to-stock
production.
Figure 16: Make-to-Stock Production (10): Master Data
42 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 55/522
TSCM40 Lesson: Planning Make-to-Stock Production
Maintain the strategy group 10 in the material master (MRP 3) for the finished
product.
Make-to-Stock Production/Net Requirements Planning (10)
Explain the FIFO principle for reducing planned independent requirements.
Figure 17: Make-to-Stock Production/Net Requirements Planning (10)
The demand program is defined without reference to sales orders.
Sales orders are not relevant for MRP, but you can display them for information
purposes. You make this setting in the No MRP field in Customizing for the
relevant requirements class (work step, “Define Requirements Classes” in
Customizing for Sales and Distribution).
Sales orders are fulfilled from stock. You can carry out the availability check
with ATP logic in Sales and Distribution. Goods withdrawals against a sales
order reduce the respective sales order.
Reduction of the demand program, that is, of the planned independent
requirements, is carried out at goods issue (the PIR reduction indicator must be
set in Customizing for requirements class 30 if you want to reduce the demand
program when delivering to a sales order). The oldest planned independent
requirement is reduced first, in accordance with the FIFO (first in first out)
principle, using the requirement date as a basis. Future planned independent
requirements are also reduced by goods issues, providing the forward consumption
period in the material master allows this.
2008 © 2008 SAP AG. All rights reserved. 43
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 56/522
Unit 3: Demand Management TSCM40
First provide a short explanation of the net requirements planning logic based on a
theoretical numerical example:
1. Stock 15 pcs, planned independent requirement 10 pcs, procurement? No. The
stock is included in the net requirements calculation.
2. Goods issue of 5 pcs: Stock 15 pcs → 10 pcs, planned independent requirement
10 pcs → 5 pcs (oldest requirement is reduced).
Demonstration: ECC Strategy 10 (Make-to-StockProduction), Net Requirements Planning
Purpose
Preparing the exercise
Hint: As the instructor, you can set navigation profile SCM001
during this demo in order to call the main functions quickly from the
stock/requirements list. Refresh the stock/requirements list after each
step. Execute the goods receipt and goods issue transactions in a separate
session or define up to five favorites for the purpose.
Material R-F1##, Plant 1000
System Data
System: see weekly e-mail
Client: see weekly e-mail
User ID: Your user ID
Password: Own password
Set up instructions: Standard
1. Check the material master and make the following settings: MRP type PD,
strategy group 10 (F4 help for strategy group).
2. Create planned independent requirements (requirement type LSF): Current
week + 4 to current week + 8, each 25 pcs.
3. Execute multilevel requirements planning
4. Convert the first two planned orders into production orders.
5. Post a goods receipt for the production orders (goods receipt for order,
movement type 101, storage location 0002).
44 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 57/522
TSCM40 Lesson: Planning Make-to-Stock Production
→ The stock level increases by the amount of the posted goods receipt; the
planned independent requirements remain the same. A new MRP run does
not cause any new planned orders because the stock level that now exists istaken into account (net requirements planning!).
6. Create customer requirement: 8 pcs for today + 6 weeks
→ The customer requirement is not relevant to MRP (make-to-stock
production) (you can see this by the fact that the available quantity in the
list is not affected).
7. Post a goods issue for the customer requirement (movement type 231,
storage location 0002).
→ Reduction of the customer requirement, reduction of the warehouse
stock, reduction of the oldest planned independent requirement according
to the FIFO rule (first-in-first-out). If the amount removed was more than
the planned independent requirements in the past, then the future planned
independent requirements are also reduced if a corresponding entry exists in
the consumption period forward (although this function does not actually
have anything to do with consumption; you could also consult SAP Note
71804: Requirement reductions same as consumption logic).
You can display the subsequent documents for a customer requirement (for
example, partially processed goods issue for a customer requirement) from
the display of the requirements under Environment → Status Overview.
Figure 18: Production by Lot Size (30)
2008 © 2008 SAP AG. All rights reserved. 45
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 58/522
Unit 3: Demand Management TSCM40
In production by lot size (strategy 30), the requirements for the finished product are
transferred to MRP when a sales order is processed. You can also plan additional
warehouse requirements in Demand Management. This means that in productionby lot size, sales orders as well as planned independent requirements are included
in Material Requirements Planning. Planned independent requirements are not
consumed by sales orders, however. Both requirements can then be procured in a
shared lot using a suitable lot-sizing procedure (for example, period lot-sizing)
with a common procurement element (such as a planned order).
Sales orders are fulfilled from stock. The customer requirement is reduced by the
goods issue to the customer. You can carry out the availability check with ATP
logic in Sales and Distribution.
The warehouse orders created additionally in demand management are reduced by
the goods issue to the warehouse order, for example, to a cost center (the reduction
is carried out according to the FIFO principle, just as for planning strategy 10).
You can apply this strategy when you need to map orders for major customers and
factory sales from the warehouse simultaneously, for example.
Figure 19: Production by Lot Size (30): Master Data
Production by Lot Size (30) for Sales and Stock Orders
The slide illustrates the chronological grouping of the requirements and the
common procurement elements.
Example of use: Major customers and additional direct factory sales
46 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 59/522
TSCM40 Lesson: Planning Make-to-Stock Production
Figure 20: Production by Lot Size (30) for Sales and Stock Orders
In production by lot size, the system groups the procurement quantities for
customer requirements and planned independent requirements into lots. To do
this, it uses the lot-sizing procedure defined in the material master record.
Demonstration: ECC Strategy 30 (Production by Lot
Size)
Purpose
Demonstration of strategy 30: Production by lot size
System Data
System: see weekly e-mail
Client: see weekly e-mail
User ID: Your user ID
Password: Own password
Set up instructions: Standard
1. Material master R-F1##, plant 1000, MRP 3 view: Enter strategy group 30.
2. Create a customer requirement for R-F1## for 5 pieces, for the 20th
of the following month (plant 1000), requirement type: KL (sales order
manufactured by lot size)
3. Create planned independent requirements for 10 pieces, for the 20th of
the following month.
4. Stock/requirements list for R-F1##, plant 1000: No consumption
2008 © 2008 SAP AG. All rights reserved. 47
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 60/522
Unit 3: Demand Management TSCM40
5. Multilevel planning run
6. Result in the stock/requirements list: A common procurement element
7. Cleanup the planning situation for R-F1## for subsequent demos.
Figure 21: Planning with Final Assembly (40)
Planning with final assembly (planning strategy 40) allows you to focus on
flexible and fast reaction to customer demand, whilst also aiming for a production
process that is as smooth as possible.
The procurement and production of all components and assemblies including their
final assembly should be triggered by planned independent requirements before
sales orders are received.
You set the planned independent requirements for the finished product in Demand
Management. Incoming sales orders consume these planned independent
requirements.
Planned independent requirements that have not been consumed can - periodically,
for example - be set to zero (transaction MD74).
If customer requirements exceed planned independent requirements, the system
automatically creates a planned order for the sales order, including the unplanned
quantity, in the next MRP run (sales orders that affect requirements).
The availability check can be executed from the sales order.
The consumption of planned independent requirements by customer requirements
depends on the consumption mode and the consumption periods.
48 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 61/522
TSCM40 Lesson: Planning Make-to-Stock Production
Figure 22: Planning with Final Assembly (40): Master Data
Maintain the strategy group 40 in the material master (MRP 3) for the finished
product.
The settings for the consumption of sales orders and planned independent
requirements from the material master are included in this strategy.
In the material master, an MRP group can also be used to assign the consumption
to the material. If consumption values are found both directly using the strategygroup and indirectly using the MRP group, the values from the strategy group
are taken.
Demonstration: ECC Strategy 40 (Planning with FinalAssembly): Part 1: Creating Planned IndependentRequirements
Purpose
Preparing the exercise
System Data
System: see weekly e-mail
Client: see weekly e-mail
User ID: Your user ID
Password: Own password
Set up instructions: Standard
1. In the material master for the pump, change the strategy group and create
planned independent requirements.
2008 © 2008 SAP AG. All rights reserved. 49
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 62/522
Unit 3: Demand Management TSCM40
Material R-F1##, plant 1000, MRP 3 view -> change the strategy group to
40 (planning with final assembly).
2. Create planned independent requirements (new row!!!) from current
month + 6 to current month + 11 (Use the “Split period online” option),
planned quantity 1,200 pieces, splitting indicator M.
3. Stock/requirements list for R-F1##, plant 1000.
Consumption
Customer requirements arrive. Explain the features of backward consumption,
forward consumption and backward/forward consumption. Point out that this
affects several strategies. Give details of the various possible cases based on thesubsequent three slides.
Figure 23: Consumption
You can use consumption mode to determine the direction on the time axis in
which incoming sales orders are to consume planned independent requirements.
In backward consumption (consumption mode 1), the sales order consumes
planned independent requirements that existed before the customer requirement
was created.
In forward consumption (consumption mode 3), the sales order consumes planned
independent requirements that exist after the customer requirement was created.
50 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 63/522
TSCM40 Lesson: Planning Make-to-Stock Production
You can combine backward and forward consumption provided that you take the
consumption periods into account (consumption modes 2 or 4).
You can define the consumption mode and the consumption periods either in the
material master or for each plant and MRP group. If no values have been entered,
the system uses the default setting with backward consumption for 999 days
Hint: If you do not maintain mode 1 and the backward consumption
interval, this means that only the requirements on the current day are
consumed.
In addition to the consumption mode and consumption periods, the consumption
indicator (consumption type) is also important. The consumption indicator
controls whether the planned independent requirements are consumed withcustomer requirements or with dependent requirements and order reservations, for
example. It is defined as a default value for each planned independent requirement
class in Customizing for Demand Management. The indicator can be overridden
in the item detail screen for planned independent requirements management.
Figure 24: Consumption Mode 1: Backward Consumption (I)
2008 © 2008 SAP AG. All rights reserved. 51
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 64/522
Unit 3: Demand Management TSCM40
Figure 25: Consumption Mode 1: Backward Consumption (II)
Figure 26: Consumption Mode 2: Backward/forward
Demonstration: ECC Strategy 40 (Planning withFinal Assembly): Part 2: Planning, Evaluation andIndependent Requirement Reduction
Purpose
Preparing the exercise
52 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 65/522
TSCM40 Lesson: Planning Make-to-Stock Production
System Data
System: see weekly e-mail
Client: see weekly e-mail
User ID: Your user ID
Password: Own password
Set up instructions: Standard
1. Execute a planning run, evaluate the run and demonstrate independent
requirement reduction for goods issue.
Multilevel planning run with the settings from before for the previously
used material R-F1##, plant 1000.
2. Customer requirement for 10 pieces, plant 1000, R-F1##, date: Second
planned independent requirement date + 4 days, sales order consumption.
3. Stock/requirements list: Consumption or effect on requirements
compared to strategy 10.
4. Display the consumption situation for the total requirements.
5. Goods issue to customer of 10 pieces, R-F1##, plant 1000.
6. Display the changed stock situation and the dependent requirements
reduction.
Planning at Assembly Level (70)
Strategy 70 is a strategy you can use to plan sub-assemblies instead of the end
product.
2008 © 2008 SAP AG. All rights reserved. 53
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 66/522
Unit 3: Demand Management TSCM40
Figure 27: Planning at Assembly Level (70)
It makes sense to plan at assembly level (strategy 70 + set mixed MRP indicator)
when processing variants if it is easier to specify a requirements forecast for
certain assemblies than it is for the variant diversity of the finished product.
With this planning strategy, planning for an assembly is considered separately.
The planned independent requirement is entered at assembly level and triggers
the production of the assembly.
If sales orders are received for the finished product, the BOM is exploded for the
finished product. Dependent requirements or reservations are also created for
the assembly as a result of planned orders or production orders for the finished
product. These consume the planned independent requirements of the assembly.
If, due to sales orders, planned orders, or production orders at finished product
level, the dependent requirements or reservations exceed the assembly’s planned
independent requirements, a planned order is created for the assembly during
the next planning run.
In Sales and Distribution, the system does not perform a check of the assembly
planning quantities.
In the strategy group of the material master record, you must enter strategy 70 and
the mixed MRP indicator must be set for assembly planning.
The consumption indicator in the item screen for the planned independent
requirements must allow consumption with reservations and dependent
requirements.
54 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 67/522
TSCM40 Lesson: Planning Make-to-Stock Production
Planning at Assembly Level (70): Master Data
Remind the participants briefly of the meaning of the terms consumption mode,
consumption period, consumption indicator (consumption type):
Consumption mode, consumption interval: Maintain these in the material master
(MRP 3), or in Customizing for the MRP group parameters, or
→ Customizing: Production – Production Planning – Demand Management –
Planned Independent Requirements – Maintain Consumption Mode and Period
of Adjustment
Default values for the consumption type for each requirements class: Determine
the actual requirements (customer requirement, dependent requirement,
reservations) for consumption:
→ Customizing: Production – Production Planning – Demand Management –
Planned Independent Requirements – Default Values and Presettings – Define
Default Values for Consumption Type Per Reqmts Class
Figure 28: Planning at Assembly Level (70): Master Data
You make the strategy setting in the material master for the assembly or
assemblies. Maintain the planning strategy 70 together with the set mixed MRP
indicator in the ECC material master (MRP 3) for the assembly or assemblies. In
principle, the finished product can show any strategy.
Maintain the consumption parameters (consumption mode, forward and backward
consumption periods) in the material master.
2008 © 2008 SAP AG. All rights reserved. 55
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 68/522
Unit 3: Demand Management TSCM40
The consumption indicator in the item screen for the planned independent
requirements must allow consumption with reservations and dependent
requirements.
If you map this strategy together with a final assembly that takes place in
make-to-order production, you must also set the individual/collective indicator to
“collective” in the material master of the assemblies.
Short explanation of the subassembly planning logic based on a numerical
example:
The motor assembly is to be installed in three different car models A, B, C.
Planning is executed for the motor: 1000 pcs in January, and procurement is
triggered.
Sales orders are received for the cars.
400 pcs for A, 500 pcs for B, 300 pcs for C.
The dependent requirements for the motors consume the planned independent
requirements; however, they exceed the planning quantity by 200 pcs.
This means: 1000 pcs can be fulfilled from the warehouse stock, and 200 pcs
still need to be procured.
Consumption in Subassembly Planning (70)
Strategy 70 is a strategy you can use to plan assemblies instead of the end product.
56 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 69/522
TSCM40 Lesson: Planning Make-to-Stock Production
Figure 29: Consumption in Subassembly Planning (70)
In the first step, you create the requirement quantities expected in the future for
the assembly. You do this in Demand Management.
Sales orders at finished product level are created and planned or production
orders generated.
The resulting dependent requirements or reservations (for the assembly) consume
the planned independent requirements of the assembly.
Subassembly Planning (70): Consumption Periods
The consumption periods are calculated from the dependent requirements for
this strategy.
2008 © 2008 SAP AG. All rights reserved. 57
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 70/522
Unit 3: Demand Management TSCM40
Figure 30: Subassembly Planning (70): Consumption Periods
Similar to ECC strategy 40, the consumption logic is determined by the
consumption mode and the backward and forward consumption periods. These are
defined in the material master for the assembly, or per plant and MRP group.
With this strategy, the consumption periods are calculated on the basis of the
dependent requirements or reservations.
Demonstration: Subassembly Planning (70)
Purpose
Preparing the exercise
System Data
System: see weekly e-mail
Client: see weekly e-mail
User ID: Your user ID
Password: Own passwordSet up instructions: Standard
1. Materials R-F1##, R-B1##, Plant 1000
Change the material master R-B1##:
MRP 3: Strategy group 70, consumption mode 2, consumption interval
backward and forward each 30 days, mixed MRP indicator 1
2. Create planned independent requirements: 500 pcs R-B1## for current
month + 8.
58 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 71/522
TSCM40 Lesson: Planning Make-to-Stock Production
3. Execute multilevel requirements planning for R-B1##.
→ Convertible planned order was created, procurement is triggered.
4. Ensure that strategy group 30 is entered for R-F1##.
Create customer requirement for R-F1##: 100 pcs for 10th of the current
month + 8.
5. Execute multilevel requirements planning for R-F1##.
→ Planned order was created.
6. Display stock/requirements list for R-B1##.
→ Demonstrate consumption of the planned independent requirements of
R-B1## by the dependent requirements (of R-F1##).
Optional:
Customer requirement as spare part requirement for assembly R-B1##. We
assume that these spare part requirements are taken into account in the
forecast, are contained in the planned independent requirements, and are
therefore part of the consumption. For this to happen, a suitable customer
requirement type and customer requirement class must be entered in strategy
70 (for example, KSV = sales order with consumption). The corresponding
consumption type (3 = consumption against customer requirements,
dependent requirements, and reservations) must be entered in the item details
of the planned independent requirement.
2008 © 2008 SAP AG. All rights reserved. 59
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 72/522
Unit 3: Demand Management TSCM40
60 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 73/522
TSCM40 Lesson: Planning Make-to-Stock Production
47 Exercise 2: Sales Orders in Make-to-Stock
ProductionExercise Duration: 10 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Describe the effect of a sales order in make-to-stock production.
Business Example
Precision Pumps Inc. has produced pumps to stock using make-to-stock
production. A sales order is received. The sales order should have no influence
on planning, but should be available for information purposes. The sales order
is delivered.
Task 1:
You have executed planning strategy 10 from the start. Now create a customer
requirement in make-to-stock production and examine its effect in planning.
1. In the Demand Management menu, create a customer requirement of 10
pieces for pump R-F1##. The date should appear 4 days after the second
planned independent requirements date in the stock/requirements list.
Use the following data:
Delivering plant: 1000
Required delivery date: 4 calendar days after the
second planned independent
requirements date in the
stock/requirements list
Material: R-F1##
Quantity: 10 pieces
Confirm your entry by choosing Enter and make sure that the system
automatically defines the customer requirement type KSL in the item.
Save the customer requirement.
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 61
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 74/522
Unit 3: Demand Management TSCM40
2. Call the current stock/requirements list for material R-F1## in plant 1000
(you can access the current stock/requirements list directly from the Demand
Management environment). You can see that the sales order is displayed forinformation purposes only but it is not relevant to planning (that is, it has
no effect on the available quantity).
a) Note the customer requirement number/item number:
__________________ / __________________________________
b) and the customer requirement quantity:
______________________________________________________
Task 2:
Now reduce the planned independent requirements by withdrawing stock for thecustomer requirement.
1. The customer appears at the sales desk and wants to collect the 10 pumps
ordered. The customer placed the order by telephone quite a while ago. You
created the sales order in the system and it is displayed in the evaluation for
information purposes, although the material ordered is from make-to-stock
production.
From the Inventory Management menu, post the withdrawal to the customer
in the form of an other goods issue (transaction Goods Issue MIGO). Carry
out the goods movement using the following parameters:
Material number: R-F1##
Quantity: 10 pieces
Movement Type: 231 (Consumption to sales order
from warehouse)
Plant: 1000
Storage Location: 0002
Confirm the data with Enter and then enter the customer requirement number
and item you noted above on the Account Assignment tab page. Save your
entries.
2. Call the stock/requirements list and examine the stock situation.
a) How has the stock situation changed?
______________________________________________________
b) Which independent requirements and sales orders have been reduced?
______________________________________________________
Continued on next page
62 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 75/522
TSCM40 Lesson: Planning Make-to-Stock Production
______________________________________________________
2008 © 2008 SAP AG. All rights reserved. 63
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 76/522
Unit 3: Demand Management TSCM40
Solution 2: Sales Orders in Make-to-Stock
ProductionTask 1:
You have executed planning strategy 10 from the start. Now create a customer
requirement in make-to-stock production and examine its effect in planning.
1. In the Demand Management menu, create a customer requirement of 10
pieces for pump R-F1##. The date should appear 4 days after the second
planned independent requirements date in the stock/requirements list.
Use the following data:
Delivering plant: 1000 Required delivery date: 4 calendar days after the
second planned independent
requirements date in the
stock/requirements list
Material: R-F1##
Quantity: 10 pieces
Confirm your entry by choosing Enter and make sure that the system
automatically defines the customer requirement type KSL in the item.
Save the customer requirement.
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Customer Requirements → Create
2. Call the current stock/requirements list for material R-F1## in plant 1000
(you can access the current stock/requirements list directly from the Demand
Management environment). You can see that the sales order is displayed for
information purposes only but it is not relevant to planning (that is, it has
no effect on the available quantity).
a) Note the customer requirement number/item number:
__________________ / __________________________________b) and the customer requirement quantity:
______________________________________________________
a) Sales order number/item number: Varies/10
b) Sales order quantity: 10 PC
Continued on next page
64 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 77/522
TSCM40 Lesson: Planning Make-to-Stock Production
Task 2:
Now reduce the planned independent requirements by withdrawing stock for the
customer requirement.
1. The customer appears at the sales desk and wants to collect the 10 pumps
ordered. The customer placed the order by telephone quite a while ago. You
created the sales order in the system and it is displayed in the evaluation for
information purposes, although the material ordered is from make-to-stock
production.
From the Inventory Management menu, post the withdrawal to the customer
in the form of an other goods issue (transaction Goods Issue MIGO). Carry
out the goods movement using the following parameters:
Material number: R-F1##
Quantity: 10 pieces
Movement Type: 231 (Consumption to sales order
from warehouse)
Plant: 1000
Storage Location: 0002
Confirm the data with Enter and then enter the customer requirement number
and item you noted above on the Account Assignment tab page. Save your
entries.
a) Menu path: Logistics → Materials Management → Inventory
Management → Goods Movement → Goods Issue (MIGO)
Alternatively, you can also use the transaction MIGO (goods movement
MIGO).
2. Call the stock/requirements list and examine the stock situation.
a) How has the stock situation changed?
______________________________________________________
b) Which independent requirements and sales orders have been reduced?
______________________________________________________
______________________________________________________
a) Stock reduced from 50 pieces to 40 pieces.
b) The oldest planned independent requirement has been reduced
from 25 pc to 15 pc. At the same time, the customer requirement
was reduced (from 10 pieces to 0 pieces) and no longer appears.
2008 © 2008 SAP AG. All rights reserved. 65
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 78/522
Unit 3: Demand Management TSCM40
66 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 79/522
TSCM40 Lesson: Planning Make-to-Stock Production
51 Exercise 3: Planning with Final Assembly
Exercise Duration: 20 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Describe how planning with final assembly strategy works
• Describe the effects of a sales order when using planning with final assembly
strategy
Business Example
Precision Pumps Inc. has produced pumps to stock. It now wants to change itsstrategy to planning with final assembly.
Task 1:
In plant 1000, you want to enter a demand program (planned independent
requirements) beginning in six months time and distributed over a period of six
months. For these 6 months of your planning, choose the planning with final
assembly (VSF requirements) strategy to plan the production of 1200 pumps. To
do this, follow the two steps described below:
1. Maintain the material master: In the material master for pump R-F1## enter
the strategy group 40 (planning with final assembly). To do this, call thetransaction Change material immediately from the production master data
with the following parameters:
Select view(s): MRP 3
Organizational levels: Plant 1000
In the strategy group field, enter the value 40 and save the material master.
2. Maintain planned independent requirements: From the Demand Management
menu create planned independent requirements for material R-F1## in plant
1000. Set the planning period to month format by entering the indicator M and Version 00 in the planning period field on the initial screen for the
transaction. Start the transaction.
Enter material number R-F1## and plant 1000 (field MPR area) on the table
screen in a new empty row. Select this row and go to the Schedule lines tab
page to access the schedule lines screen. Make sure the requirements type
VSF, which belongs to strategy 40, is set automatically by the system.
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 67
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 80/522
Unit 3: Demand Management TSCM40
Call the Split period online function from the edit menu to instruct the
system to automatically split the production quantity of 1200 pieces over the
6 month period. Use the following data:
From: M, current month + 6
months
To: Current month + 11
months
Planned quantity: 1200 pieces
Period indicator for automatic distribution of requirements quantity: M.
Confirm (including any potential warnings) with Enter and save the
requirements.
Task 2:
1. Display the stock/requirements list for material R-F1## in plant 1000 and
note
a) the second VSF requirements date:
_________________________________
b) and the requirement quantity:
_________________________________
Task 3:
From the MRP menu, carry out multilevel, single-item planning for pump
R-F1##. Use the same creation indicators as in the previous exercises. Make sure
the “Display Material List” indicator is selected. Start the planning by choosing
Enter twice. Once the MRP run has been carried out, the system displays the
statistics.
1. Choose the Material List function, select the row with pump R-F1## and goto
to the stock/requirements list of the material. You now see the planned ordersthat have been created for the requirements (refresh the list if necessary).
2. What is the available quantity for the second VSF requirement date?
_________________________________
3. What is the planned independent requirements quantity for the second VSF
requirements date?
_________________________________
Continued on next page
68 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 81/522
TSCM40 Lesson: Planning Make-to-Stock Production
Task 4:
Now enter a customer requirement of 10 pieces from the Demand Management
menu for material R-F1## in plant 1000.
1. Use the second VSF planned independent requirement date + 4 calendar
days (that is, the date you noted above + 4 days) as requirement date for the
customer requirement. Make sure the requirements type is KSV (sales order
with consumption) and save your entries.
Task 5:
Call the current stock/requirements list again (If necessary choose the Refresh
pushbutton after having called up the list) and analyze the behavior of the customer
requirement that you have just entered.
1. What difference do you see compared to the customer requirement you
created in make-to-stock production (previous exercise)?
______________________________________________________
2. What is the planned independent requirement quantity for the second VSF
requirements date in the stock/requirements list now?
______________________________________________________
Task 6:
In the stock/requirements list, select the second VSF planned independent
requirement and call the Details of element and Display element functions. In the
planned independent requirements table, select the row with the requirements
that were created last and examine the VSF planned independent requirement
quantities (as they appear on the database) on the schedule lines screen.
1. Note the requirements quantity on the date above:
______________________________________________________
2. Do the two quantities (i.e., the quantity in this question and the quantity in
the previous question) differ? If so, by how much?
______________________________________________________
Task 7:
Analyze the total planned independent requirements situation. To do this,
access the Display Total Requirements function in the evaluations for Demand
Management.
1. Which VSF requirements quantities were consumed by which customer
requirements quantities?
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 69
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 82/522
Unit 3: Demand Management TSCM40
______________________________________________________
2. Which planned independent requirements quantities are displayed in the
stock/requirements list?
______________________________________________________
Task 8:
10 pumps from stock are delivered to the customer. Post the other goods issue.
You must enter the customer requirement number and the item number here. You
can find this number in the stock/requirements list in the VSF planning customer
requirement (planning with final assembly). You will recognize the process of
this goods movement posting from the exercise “sales orders in make-to-stock
production”, task 2.
1. How has the stock situation changed?
______________________________________________________
2. Which planned independent requirements (customer requirements/planned
independent requirements) were reduced by the goods issue from warehouse?
(From the current stock/requirements list, look at the schedule lines of the
VSF requirements on the database.)
______________________________________________________
70 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 83/522
TSCM40 Lesson: Planning Make-to-Stock Production
Solution 3: Planning with Final Assembly
Task 1:
In plant 1000, you want to enter a demand program (planned independent
requirements) beginning in six months time and distributed over a period of six
months. For these 6 months of your planning, choose the planning with final
assembly (VSF requirements) strategy to plan the production of 1200 pumps. To
do this, follow the two steps described below:
1. Maintain the material master: In the material master for pump R-F1## enter
the strategy group 40 (planning with final assembly). To do this, call the
transaction Change material immediately from the production master data
with the following parameters:
Select view(s): MRP 3
Organizational levels: Plant 1000
In the strategy group field, enter the value 40 and save the material master.
a) Menu path: Logistics → Production → Master Data → Material
Master → Material → Change → Immediately
2. Maintain planned independent requirements: From the Demand Management
menu create planned independent requirements for material R-F1## in plant
1000. Set the planning period to month format by entering the indicator M
and Version 00 in the planning period field on the initial screen for the
transaction. Start the transaction.
Enter material number R-F1## and plant 1000 (field MPR area) on the table
screen in a new empty row. Select this row and go to the Schedule lines tab
page to access the schedule lines screen. Make sure the requirements type
VSF, which belongs to strategy 40, is set automatically by the system.
Call the Split period online function from the edit menu to instruct the
system to automatically split the production quantity of 1200 pieces over the
6 month period. Use the following data:
From: M, current month + 6 months
To: Current month + 11
months
Planned quantity: 1200 pieces
Period indicator for automatic distribution of requirements quantity: M.
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 71
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 84/522
Unit 3: Demand Management TSCM40
Confirm (including any potential warnings) with Enter and save the
requirements.
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Planned Independent Requirements → Create
Task 2:
1. Display the stock/requirements list for material R-F1## in plant 1000 and
note
a) the second VSF requirements date:
_________________________________
b) and the requirement quantity:
_________________________________
a) Varies
b) Varies
Task 3:
From the MRP menu, carry out multilevel, single-item planning for pump
R-F1##. Use the same creation indicators as in the previous exercises. Make sure
the “Display Material List” indicator is selected. Start the planning by choosing
Enter twice. Once the MRP run has been carried out, the system displays the
statistics.
1. Choose the Material List function, select the row with pump R-F1## and goto
to the stock/requirements list of the material. You now see the planned orders
that have been created for the requirements (refresh the list if necessary).
a) No solution required
2. What is the available quantity for the second VSF requirement date?
_________________________________
a) Available quantity on the second VSF requirements date: 0 pc3. What is the planned independent requirements quantity for the second VSF
requirements date?
_________________________________
a) Planned independent requirements quantity on the second VSF
requirements date: As above (see task 2)
Continued on next page
72 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 85/522
TSCM40 Lesson: Planning Make-to-Stock Production
Task 4:
Now enter a customer requirement of 10 pieces from the Demand Management
menu for material R-F1## in plant 1000.
1. Use the second VSF planned independent requirement date + 4 calendar
days (that is, the date you noted above + 4 days) as requirement date for the
customer requirement. Make sure the requirements type is KSV (sales order
with consumption) and save your entries.
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Customer Requirements → Create
Task 5:
Call the current stock/requirements list again (If necessary choose the Refreshpushbutton after having called up the list) and analyze the behavior of the customer
requirement that you have just entered.
1. What difference do you see compared to the customer requirement you
created in make-to-stock production (previous exercise)?
______________________________________________________
a) The sales order with requirements type KSV is relevant to requirements.
This means it affects the available quantity.
2. What is the planned independent requirement quantity for the second VSF
requirements date in the stock/requirements list now?
______________________________________________________
a) The planned independent requirements displayed in the current
stock/requirements list is 10 less than the original requirement you
noted above. The procurement element remains unaffected by this for
the time being; no new planning run was triggered.
Task 6:
In the stock/requirements list, select the second VSF planned independent
requirement and call the Details of element and Display element functions. In the
planned independent requirements table, select the row with the requirementsthat were created last and examine the VSF planned independent requirement
quantities (as they appear on the database) on the schedule lines screen.
1. Note the requirements quantity on the date above:
______________________________________________________
a) Varies (original quantity)
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 73
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 86/522
Unit 3: Demand Management TSCM40
2. Do the two quantities (i.e., the quantity in this question and the quantity in
the previous question) differ? If so, by how much?
______________________________________________________
a) Yes, by 10 pc.
Task 7:
Analyze the total planned independent requirements situation. To do this,
access the Display Total Requirements function in the evaluations for Demand
Management.
1. Which VSF requirements quantities were consumed by which customer
requirements quantities?
______________________________________________________
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Evaluations → Display Total Reqmts
Consumed VSF requirements quantities: The second VSF planned
independent requirement quantity is consumed by the KSV
customer requirement.
2. Which planned independent requirements quantities are displayed in the
stock/requirements list?
______________________________________________________
a) Displayed independent requirements quantities: In the currentstock/requirements list, the system displays the planned
independent requirements quantities that have not been consumed
(that is, the planned independent requirements that still exist after
consumption).
Task 8:
10 pumps from stock are delivered to the customer. Post the other goods issue.
You must enter the customer requirement number and the item number here. You
can find this number in the stock/requirements list in the VSF planning customer
requirement (planning with final assembly). You will recognize the process of this goods movement posting from the exercise “sales orders in make-to-stock
production”, task 2.
1. How has the stock situation changed?
______________________________________________________
a) New requirements situation: The available plant stock has been
reduced from 40 pieces to 30 pieces.
Continued on next page
74 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 87/522
TSCM40 Lesson: Planning Make-to-Stock Production
2. Which planned independent requirements (customer requirements/planned
independent requirements) were reduced by the goods issue from warehouse?
(From the current stock/requirements list, look at the schedule lines of theVSF requirements on the database.)
______________________________________________________
a) Planned independent requirements reduction: The customer
requirement was reduced and is no longer included in the list. The
VSF planned independent requirement was also reduced, that
is, the second VSF quantity (affected by the consumption) was
also reduced by 10 pc. These 10 pc. are recorded as a withdrawal
quantity in the planned independent requirements schedule lines.
2008 © 2008 SAP AG. All rights reserved. 75
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 88/522
Unit 3: Demand Management TSCM40
76 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 89/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 90/522
Unit 3: Demand Management TSCM40
Requirements date: Current month +2
Requirement quantity: 180 pieces
Make sure the requirements type is VSFB and the consumption indicator
is 3 in the item screen of the planned independent requirements. Save the
requirement.
Task 2:
Call the stock/requirements list for material R-B1## in plant 1000.
1. Which planned independent requirement quantity for the independent
requirement for the assembly created above is still relevant for requirements
(displayed)?______________________________________________________
2. Examine the consumption in the display of the total planned independent
requirements situation of material R-B1## in plant 1000. You can access
this screen from the Demand Management menu or directly from the
stock/requirements list. Which type of requirements consumed the VSFB
planned independent requirements and what was the quantity consumed?
______________________________________________________
3. Is the VSFB requirement covered by a procurement element?
______________________________________________________
Task 3:
Select the VSFB planned independent requirement in the current
stock/requirements list.
1. Which VSFB planned independent requirement quantity appears when you
choose Details of element and Display element ?
______________________________________________________
2. How do you explain the difference between this and the display in the list?
______________________________________________________
Task 4:
Now carry out single-item, multilevel planning for material R-B1## in plant 1000.
1. Proceed using the same transaction and settings as in the previous exercises.
Continued on next page
78 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 91/522
TSCM40 Lesson: Planning Make-to-Stock Production
Task 5:
Call the stock/requirements list for material R-B1## in plant 1000.
1. Which planned independent requirement quantity for the assembly
independent requirement created above is still relevant for requirements
(displayed)?
______________________________________________________
2. Is the requirement covered by a procurement element now?
______________________________________________________
2008 © 2008 SAP AG. All rights reserved. 79
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 92/522
Unit 3: Demand Management TSCM40
Solution 4: Subassembly Planning
Task 1:
You want to plan subassemblies in order to reduce delivery times for the pump. To
do this, you must create planned independent requirements for the assemblies for
pump R-F1## using an appropriate requirements type. We are now going to carry
out subassembly planning using assembly R-B1## in plant 1000 as an example.
1. Modify the material master for R-B1## accordingly. Enter the following
parameters in the MRP 3 view in plant 1000:
Strategy group: 70 (subassembly planning)
Consumption mode: 2 (Backward/forward)
Consumption period
Forward:
12 (working days)
Consumption period
Backward:
12 (working days)
Mixed MRP: 1 (subassembly planning)
Save the material master.
a) Menu path: Logistics → Production → Master Data → Material
Master → Material → Change → Immediately
2. Enter a planned independent requirement of 180 pieces for the month
after next for material R-B1## in plant 1000. Set the planning period to
monthly by entering the indicator M in the planning period field in the initial
screen of the transaction. Use the following data:
Requirements date: Current month +2
Requirement quantity: 180 pieces
Make sure the requirements type is VSFB and the consumption indicator
is 3 in the item screen of the planned independent requirements. Save the
requirement.
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Planned Independent Requirements → Create
Continued on next page
80 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 93/522
TSCM40 Lesson: Planning Make-to-Stock Production
Task 2:
Call the stock/requirements list for material R-B1## in plant 1000.
1. Which planned independent requirement quantity for the independent
requirement for the assembly created above is still relevant for requirements
(displayed)?
______________________________________________________
a) Planned independent requirements quantities still relevant to
requirements: varies (for example, 55 pieces)
2. Examine the consumption in the display of the total planned independent
requirements situation of material R-B1## in plant 1000. You can access
this screen from the Demand Management menu or directly from the
stock/requirements list. Which type of requirements consumed the VSFBplanned independent requirements and what was the quantity consumed?
______________________________________________________
a) Consumption with the VSFB planned independent requirement:
Varies. The dependent requirements and, if necessary, the order
reservations (each for 25 pc) within the consumption periods
consume the VSFB independent requirements.
3. Is the VSFB requirement covered by a procurement element?
______________________________________________________
a) Procurement elements for the VSFB requirements: No, there is notan appropriate procurement element available as no planning run
has been carried out yet.
Task 3:
Select the VSFB planned independent requirement in the current
stock/requirements list.
1. Which VSFB planned independent requirement quantity appears when you
choose Details of element and Display element ?
______________________________________________________
a) VSFB planned independent requirements quantity with Display
element: The complete quantity of 180 pc is displayed.
2. How do you explain the difference between this and the display in the list?
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 81
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 94/522
Unit 3: Demand Management TSCM40
______________________________________________________
a) Explanation: The system only displays the non-consumed quantity
in the list. The planned independent requirements had not yet been
reduced (by a goods receipt, for example). The complete quantity
is therefore still available on the database.
Task 4:
Now carry out single-item, multilevel planning for material R-B1## in plant 1000.
1. Proceed using the same transaction and settings as in the previous exercises.
a) Menu path: Logistics → Production → MRP → Planning →
Single-Item, Multi-Level
Task 5:
Call the stock/requirements list for material R-B1## in plant 1000.
1. Which planned independent requirement quantity for the assembly
independent requirement created above is still relevant for requirements
(displayed)?
______________________________________________________
a) Planned independent requirements quantity displayed: This varies, as
above, for example 55 pc.
2. Is the requirement covered by a procurement element now?
______________________________________________________
a) Procurement element: Yes, the requirement is now covered by a
new planned order.
82 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 95/522
TSCM40 Lesson: Planning Make-to-Stock Production
Lesson Summary
You should now be able to:• Use planning strategies for make-to-stock production
2008 © 2008 SAP AG. All rights reserved. 83
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 96/522
Unit 3: Demand Management TSCM40
Lesson:
68
Planning Make-to-Order Production
Lesson Duration: 90 Minutes
Lesson Overview
Planning make-to-order production involves specific planning for individual
sales orders.
Lesson Objectives
After completing this lesson, you will be able to:
• Use planning strategies for make-to-order production
• Explain assembly processing
Space for notes
Business Example
For some customers or sales orders, pump production planning should be
order-specific down to several BOM components.
Important make-to-order production strategies
Take a brief look at the most important strategies for make-to-order production:
Provide a short overview of pure make-to-order production (20) and planning
without final assembly (50). Both these topics will be dealt with in the following
section.
The following section also aims to explain the characteristic of the
individual/collective indicator for determining the stocking level:
1. In the material master, MRP view 4
2. In the BOM item in the explosion type field (Basic Data tab page)
3. Final setting in the BOM explosion in the planning run, dependent on the
indicator for the subordinate material
84 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 97/522
TSCM40 Lesson: Planning Make-to-Order Production
Figure 31: Important Make-to-Order Production Strategies
Make-to-Order Production: Overview
Emphasize the most important characteristics of make-to-order production
(inventory management and so on).
Figure 32: Make-to-Order Production: Overview
2008 © 2008 SAP AG. All rights reserved. 85
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 98/522
Unit 3: Demand Management TSCM40
For make-to-order production, each sales order is planned separately and managed
in its own section in the MRP list or the current stock/requirements list.
The system does not perform a net requirements calculation between individual
sales orders or with the anonymous warehouse stock.
In make-to-order production, the lot-for-lot order quantity is used as the default
setting for the lot-sizing procedure, regardless of the entry you have made in the
material master. You define the lot-sizing procedure for make-to-order production
in ECC Customizing for MRP in the work step “Check Lot-Sizing Procedure”
in the field “Lot-Size Calculation for MTO Production”. Depending on how
the lot-size indicator is set in the material master, you can define a lot size for
make-to-order production that differs from the lot size used in make-to-stock
production.
The produced quantities cannot be exchanged between the individual sales ordersand the manufactured quantities are managed directly for the individual sales
orders (in the sales order stock).
The sales order stock and the requirement are reduced by a goods issue to the
sales order. As soon as the sales order is complete and the make-to-order stock
has been used up, the individual customer segment disappears from the current
stock/requirements list or MRP list in ECC.
Pure Make-to-Order Production (20)
The sales order is the defining element. Planning does not take place.
Figure 33: Pure Make-to-Order Production (20)
86 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 99/522
TSCM40 Lesson: Planning Make-to-Order Production
Procurement/production is triggered by the sales order when using this strategy.
Pure make-to-order production (that is, without planning of assemblies/compo-
nents) is done in ECC using strategy 20.
Pure Make-to-Order Production (20): Master Data
Together with the strategy group, the individual/collective indicator in the
assemblies is the decisive factor. The consumption parameters are irrelevant here.
Figure 34: Pure Make-to-Order Production (20): Master Data
You make the settings for this strategy in the master of the finished product
(MRP3). The individual/collective indicators for the assemblies need to be set
accordingly in the corresponding master.
Pure Make-to-Order Production (20): Example
Go through the example to present the subject of make-to-order production in a
more concrete manner.
2008 © 2008 SAP AG. All rights reserved. 87
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 100/522
Unit 3: Demand Management TSCM40
Figure 35: Pure Make-to-Order Production (20): Example
The net requirements calculation is carried out individually for every sales order.
Stock cannot be swapped back and forth between sales orders.
The procurement elements, that is, the planned orders, are created with reference
to the sales order and are managed in the individual customer segment. This direct
reference to the sales order is also retained in the production order.
The system manages the production and procurement costs specifically for eachsales order in a settlement order or project at sales order item level.
Requirements reduction (sales order) and reduction of make-to-order stock occurs
on delivery.
Individual/Collective Indicator: Example (I)
Go through the example in order to explain the importance and effect of the
individual/collective indicator.
88 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 101/522
TSCM40 Lesson: Planning Make-to-Order Production
Figure 36: Individual/Collective Indicator: Example (I)
The individual/collective requirements indicator in the material master determines
whether a component is procured for a specific customer requirement in an
individual segment.
The ECC indicator 1 for individual requirements means that the material is being
specially manufactured or procured for a sales order. An individual segment is
specially created for each requirement. An individual requirement is only created
if the higher-level material does not generate a collective requirement.
The ECC indicator 2 for collective requirements means that the material is
produced or procured for various requirements. The requirements are contained in
the net requirements segment.
The ECC indicator left blank means that the component is planned in the same
way as the higher-level assembly (if this represents the finished product produced
in make-to-order production and also has the indicator left blank, the constraint
for make-to-order production replaces the entry with 1: 1 means individual
requirements only).
In the example above, two individual segments (for sales orders A and B) are
created for the shaft.
If you want to control the material item for each BOM individually in ECC, use
the “Explosion type” field in the component’s item data (General Data view). The
setting in the ECC BOM overrides the setting in the material master.
2008 © 2008 SAP AG. All rights reserved. 89
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 102/522
Unit 3: Demand Management TSCM40
Individual/Collective Indicator: Example (II)
Go through the example to show the characteristics of the individual/collective
indicator in a more concrete manner.
Figure 37: Individual/Collective Indicator: Example (II)
All materials that appear under one material in collective requirements in the
BOM are planned as collective requirements (“inheritance”) irrespective of the
setting in the material master.
Demonstration: Pure Make-to-Order Production
Purpose
Preparation for exercise
System DataSystem: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Materials R-F1##, R-B1##, R-B3##
Change material master R-F1##:
90 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 103/522
TSCM40 Lesson: Planning Make-to-Order Production
MRP 3: Strategy group 20
MRP 1: MRP lot size FX / 200 pcs, although this is not really appropriate
for strategy 20
2. Create two customer requirements for R-F##:
20 pcs for the fifteenth day of the current month + 2
50 pcs for the first day of the current month + 3
3. Multilevel requirements planning for R-F1##. Display the result:
→ Two individual segments for R-F1## with lot-to-lot order quantities for
the planned orders
(Explanation: Display lot-sizing procedure in Customizing step “Check
Lot-Sizing Procedure”, indicator “MTO Lot Size” = blank ignores FXsetting in MRP type)
→ Dependent requirements for R-B1## in the collective segment (according
to Individual/coll. = 2),
→ Dependent requirements for R-B3## in the individual segments
(according to Individual/coll. = blank).
4. Convert first planned order for R-F1## to a production order.
Post a goods receipt for the order for 10 pcs (movement type 101, storage
location 0002):
→ Make-to-order stock is built up, goods movements only within thecorresponding customer individual segment.
Planning Without Final Assembly (50): Planning
Explain the meaning and effect of the planning segment and the planned orders.
2008 © 2008 SAP AG. All rights reserved. 91
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 104/522
Unit 3: Demand Management TSCM40
Figure 38: Planning Without Final Assembly (50): Planning
As in make-to-order production, planning without final assembly (planning
strategy 50) enables you to manufacture products specifically for a customer.
However, with this planning strategy, certain assemblies should be produced or
procured before the sales order for the finished product is received. Production
does not extend at first to the finished product level. The material is produced
at manufacturing level until the point of final assembly, in other words, the
assemblies and components are kept at the warehouse until the sales order isreceived. Final assembly is only triggered upon receipt of the sales order. This
strategy is useful if a large part of the value added process occurs at final assembly.
Planning that is independent of the sales order takes place using planned
independent requirements. These planned independent requirements are created
for the finished product. In the planning run, the system first creates planned
orders for the finished product to cover these requirements. These planned orders
cannot be converted into production orders (planned orders without a conversion
indicator and the order type VP). You can only convert these planned orders into
production orders once the sales order has been received. This then triggers final
assembly. If a material shortage exists, however, the system creates planned orders
at assembly and component levels in the planning run. These planned orders canbe converted into production orders or purchase requisitions since production and
procurement should have already been triggered for the lower production levels
before the sales order is received.
The planning without final assembly strategy enables you to reduce delivery times
(since production can access existing assemblies and components without delay)
without having to carry out final assembly for the product.
92 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 105/522
TSCM40 Lesson: Planning Make-to-Order Production
Planning Without Final Assembly (50): Sales Order
Refer to the individual customer segment and the consumption situation.
Figure 39: Planning Without Final Assembly (50): Sales Order
The receipt of the sales order triggers final assembly. The sales order appears
within an individual customer segment in which planning is performed separately
for the sales order. In the next planning run, the system creates a planned order for
the newly created sales order in the individual customer segment. This planned
order can be converted into a production order. This then allows final assembly. In
the planning segment, however, the planned order quantity for the planned order
without conversion indicator (with the order type VP) is reduced in accordance
with the new requirements situation. In this strategy, the sales order is managed
in the individual customer planning segment. If this is not desired, you can also
manage the sales order in the net requirements segment (planning strategy 52).
Should you choose this procedure, you have to work with the lot-sizing procedure
“lot-for-lot order quantity”. Neither the rounding value or rounding profile nor theminimum or maximum lot sizes should be maintained. Furthermore, stocks are
not taken into account. In ECC applications, this strategy as well as the strategy
planning with a planning material are the most commonly used strategies in a
make-to-order production environment.
Example: If a planned independent requirement of 100 pieces exists and you
receive a sales order for 40 pieces which consumes the planned independent
requirements then the sales order for 40 pieces remains in the individual customer
planning segment and a planned independent requirement for 60 pieces in the
2008 © 2008 SAP AG. All rights reserved. 93
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 106/522
Unit 3: Demand Management TSCM40
forecast segment. As soon as the product is planned again in the next planning
run, the system creates a planned order for 40 pieces in the individual customer
planning segment which you can convert into a production order. At the sametime, the system reduces the existing planned order in the planning segment from
100 pieces to 60 pieces.
Planning Without Final Assembly (50): Master Data
Refer to the individual customer segment and the consumption situation.
Figure 40: Planning Without Final Assembly (50): Master Data
Maintain the strategy group 50 (MRP 3) for the finished product and the
consumption parameters.
Maintain the individual/collective indicator 2 in the material master for the
assemblies that are to be procured and stored (supplied for storage) before the
sales order is received.
It is also possible that production, not only for the finished product, but also for
special assemblies, is only triggered upon receipt of a sales order.
Stocking Level
Explain the term and include the concept of value creation.
94 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 107/522
TSCM40 Lesson: Planning Make-to-Order Production
Figure 41: Stocking Level
If a large part of the value added process occurs at final assembly it makes sense to
use planning strategy 50 (Planning without final assembly). Here, final assembly
is not triggered until a sales order exists.
The storage level is always below the finished product level.
Flexible Determination of the Stocking Level (50)
Point out the options for “including” the stocking level in the BOM structure by
way of the individual/collective indicator.
2008 © 2008 SAP AG. All rights reserved. 95
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 108/522
Unit 3: Demand Management TSCM40
Figure 42: Flexible Determination of the Stocking Level (50)
If the stocking level (amount up to which is produced to stock) is not generally
to be directly below the finished product within the product structure, you can
move the stocking level for certain materials: If you enter the individual/collective
indicator 1 (individual requirements only) or “blank” (individual and collective
requirement) in the material master (MRP view) for the material assembly 2,
the material assembly 2 is specifically produced for the sales order once the
sales order is received, and not produced to stock in advance (planned orderwith VP status). Only the components of material assembly 2 are procured and
stored before the sales order is received. For this example, therefore, you must
set the individual/collective indicator to 2 (collective requirements only) for the
components of assembly 2 also. The strategy group is only to be entered for the
finished product.
If you do not wish to create VP planned orders in all BOMs for a particular
material, you can assign the “Planning off” explosion control indicator in the
“Basic Data” for the BOM item. You define this indicator under “Define
Explosion Types” in Customizing for BOMs.
Planned Orders in the Planning Segment (50)
Explain the purpose of VP planned orders and their characteristics.
96 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 109/522
TSCM40 Lesson: Planning Make-to-Order Production
Figure 43: Planned Orders in the Planning Segment (50)
Capacity evaluations are possible for planned orders with order type VP.
Planned orders with order type VP can be used for external procurement,
subcontracting, stock transfer or direct production.
These orders cannot be changed manually and cannot be converted into production
orders or purchase orders.
Demonstration: Planning Without Final Assembly (50)
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Materials: R-F1##, R-B1##, R-B3##, Plant 1000
Change material master R-F1##:
MRP 3: Strategy group 50, consumption mode 2, consumption period
backward and forward each 30 days
2. Create warehouse stock 10 pcs for R-F1##: Goods receipt – Other – Without
Purchase order (movement type 501, storage location 0002)
2008 © 2008 SAP AG. All rights reserved. 97
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 110/522
Unit 3: Demand Management TSCM40
3. Create planned independent requirements: 120 pcs R-F1## for current
month +2.
→ Planned independent requirements are displayed in a separate planning
segment.
4. Execute multilevel requirements planning for R-F1##.
→ R-F1##: VP planned order is created (cannot be converted to a production
order, see conversion indicator in planned order), existing warehouse stock
in the net segment is not taken into account.
→ R-B1##: Dependent requirements and convertible planned order in
collective segment (I/C=2), existing warehouse stock is taken into account.
→ R-B3##: Dependent requirement and non-convertible planned order in
planning segment (I/C=blank)
5. Create customer requirements: 11 pcs R-F1## for the fourth of the current
month + 2 and another 13 pcs for the same date.
→ Display of customer requirements in individual customer segment,
consumption with planned independent requirements.
Assembly Processing as a Special Form of Make-to-Order Production
Assembly Order
Changes in Assembly Processing
An important characteristic of assembly processing is that you can already check
the availability of the assemblies for the finished product when you create a
sales order (for make-to-order production you can only check the availability of
the finished product itself). In general, the components of the finished product
have already been manufactured.
With strategy 82, a production order is automatically created when a sales order is
created. The order type is defined in the corresponding customer requirements
class.
In the sales order, the ATP check (the determination of the quantities to beconfirmed) creates corresponding schedule lines for the order item. With strategy
82, these confirmed quantities are transferred from the production order (ATP
check of the components) to the schedule lines of the sales order.
Changes to the sales order are reflected in the assembly order, so long as these
are not partially or completely confirmed, not deleted, not blocked, and not
technically completed.
98 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 111/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 112/522
Unit 3: Demand Management TSCM40
With strategy 82, creating the sales order triggers the creation of a production
order. You do not need to carry out a separate planning run. With strategy 81,
when you create a sales orders, the system creates a planned order for repetitivemanufacturing and with strategy 83, it creates a network for engineer-to-order
production.
Order processing is carried out using the tools available in production control.
Delivery is made in Sales and Distribution.
The total confirmation date depends on the date of the component which is
available last. The confirmation quantity is derived from the available quantity of
the component with the lowest confirmed quantity on the requirements date.
Assembly processing can either be carried out statically (one assembly order
per sales order item) or dynamically (several assembly orders per sales order
item). Dynamic processing enables you to execute partial deliveries. In this case,however, the direct reference to the sales order is lost.
Figure 46: Changes in Assembly Processing
Schedule lines are automatically changed in the sales order.
Changes have an effect on the assigned production order until an operation
has been confirmed or until the order header has the status deleted, locked, or
technically completed.
Demonstration: Assembly Processing: Prerequisitesand Settings
Purpose
Preparation for the following demo
100 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 113/522
TSCM40 Lesson: Planning Make-to-Order Production
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Customer Requirements Class: Assembly Area (Important Entries):
• Assembly type: 2 = static production order
• Order type: PP04
• Availability check at component level: Yes
• Type of component check: Blank = ATP check
• Assembly dialog: 2 = Display missing parts, then edit components• Capacity check:
1. = Lead time scheduling
2. = Lead time scheduling and capacity check (capacity check only
performed if activated in the checking rules for the production
order)
• No update: Blank = Change to assembly order causes change to sales
order
2. Sales Order:
• The schedule line category in the sales order must allow requirement
creation
• (Basic date) scheduling in the assembly order and shipment scheduling
in the sales order → confirmed date = determined basic date + shipping
scheduling
3. Components:
• Define availability check by entering a corresponding checking group
in the material master for the components (can also be switched off
using the checking group “No check”).
• Set the individual/collective indicator to “collective” for the
components to be checked
Demonstration: Assembly Processing
Purpose
Illustration of the concept
2008 © 2008 SAP AG. All rights reserved. 101
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 114/522
Unit 3: Demand Management TSCM40
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Material master R-F1##: Enter strategy group 82 (MRP 3)
2. Material master of assembly R-B3## (I/C = blank): Checking group ZN
(no check)
3. Create planned orders manually (MD11) for R-B1## and R-B4##, today +
10 weeks, each 10 pcs.
4. Create sales order (VA01, order type TA): Sold-to party 1000, ship-to party1000, any purchase order number, sales organization 1000, distribution
channel 10, division 00, today + 6 weeks, R-F1##, 12 pcs.
→ The system automatically creates an assembly order (due to strategy
82 this is in fact a production order), on the basis of which the component
availability check is carried out. Set the scheduling of the production order
to “backward” (without time ), adopt the generated total commitment date as
the finish date;
Complete delivery, “fix date” indicator not set → the sales order retains the
required date in transaction MD04 (it should still be relevant for planning).
Only the schedule line remains on the confirmed date, the production order
has a rescheduling message.
5. Postpone the order finish date of the production order by 1 week → the
schedule line of the sales order is also postponed
(Changes made to quantities or dates in the production order will only affect
the schedule lines in the sales order.)
6. Change to the sales order quantity → new availability check: Complete
delivery, “fix date” indicator set → in transaction MD04, the sales order date
is adjusted to suit the availability date of the production order, which no
longer has a rescheduling message.
102 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 115/522
TSCM40 Lesson: Planning Make-to-Order Production
81 Exercise 5: Planning Without Final
AssemblyExercise Duration: 20 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Explain the process of planning without final assembly
• Monitor consumption between planned independent requirements and
customer requirements
• Explain the purpose and the characteristics of planned orders in the planning
segment
Business Example
To enable it to respond to sales orders faster, Precision Pumps Inc. would like to
manufacture assemblies for pumps in advance and place them in stock. Only
when a sales order is received should the pumps be assembled in make-to-order
production.
Hint: Caution! In order to gain a clearer overview in the following
exercises, delete old planning data at this point:
1. Call the current stock/requirements list for material R-F1##
(transaction MD04). Choose Details of element for a planned
independent requirement and then choose Change element. In the
table for the maintenance of planned independent requirements,
select all the rows (items) you have used and choose Delete item.
Save and refresh the list.
2. Then carry out single-item, multilevel planning for material
R-F1## in plant 1000 (transaction MD02).
3. Check the current stock/requirements list again, by calling it for
material R-F1## and, if necessary, refreshing it. Only plant stock
should be available.
2008 © 2008 SAP AG. All rights reserved. 103
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 116/522
Unit 3: Demand Management TSCM40
Task 1:
In plant 1000, you want to create a demand program that will plan a monthly
quantity of 100 pieces in three months time. First of all, choose the planning
strategy planning without final assembly for the pump (VSE requirements,
planning without final assembly). To do this, proceed as follows:
1. Maintaining the material master: In the material master for pump R-F1## in
plant 1000, enter strategy group 50 (planning without final assembly). As
in the preceding exercises, call MRP3 view using the transaction Change
material immediately. Make the change in the corresponding field and save
the change.
2. Creating the planned independent requirements: Use the transaction Create
Planned Independent Requirements again from the Demand Management
menu for the material R-F1## in plant 1000. On the initial screen for thetransaction, set the indicator M for monthly format in the planning period
field.
On the Table screen in the row with material R-F1## in the month current
month + 3, enter a planned independent requirements quantity of 100 pieces.
Select the row and proceed to the Delivery Schedule tab page. Note the
requirements type VSE.
In the Allocation Indicator field, enter W for week quantities and confirm
this using Enter so that the allocation takes effect. Save the planned
independent requirements.
Task 2:
Carry out a planning run for material R-F1## in the form of multilevel
single-item planning.
1. Use the creation indicator that you used in the preceding exercises. Start the
planning run by confirming twice using Enter .
Task 3:
Look at the planning results in the stock/requirements list.
1. Call the stock/requirements list for material R-F1## (plant 1000). Makesure that the planned independent requirements quantities and the planned
orders they belong to are listed in a separate planning segment.
Double-click (Additional data for element) to check whether these planned
orders can be converted into production orders and explain this:
_____________________________________________________
_____________________________________________________
Continued on next page
104 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 117/522
TSCM40 Lesson: Planning Make-to-Order Production
2. Look at the current stock/requirements list for assembly R-B2## (the
flywheel) in plant 1000.
Are these planned orders also taken up in a planning segment? Are they
convertible? (Give a reason)
______________________________________________________
______________________________________________________
______________________________________________________
Task 4:
A customer requirement with the desired date 3 days later than the date of the
second planned independent requirement SU is received for the finished product.
1. Now enter a customer requirement of 10 pieces for material R-F1## in plant
1000 from the Demand Management menu. Make sure the requirements type
is KEV (make-to-order production with consumption) and save your entries.
Task 5:
Carry out a new MRP run for material R-F1##, plant 1000 in the form of
multilevel single-item planning.
1. Use the creation indicator that you used in the preceding exercises. Start the
planning run by confirming twice using Enter .
Task 6:
Call the current stock/requirements list for material R-F1## in plant 1000 and,
if necessary, refresh the list.
1. What has happened?
______________________________________________________
______________________________________________________
______________________________________________________
______________________________________________________
2. Can the procurement element for the customer requirement be converted?
______________________________________________________
2008 © 2008 SAP AG. All rights reserved. 105
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 118/522
Unit 3: Demand Management TSCM40
Solution 5: Planning Without Final
AssemblyTask 1:
In plant 1000, you want to create a demand program that will plan a monthly
quantity of 100 pieces in three months time. First of all, choose the planning
strategy planning without final assembly for the pump (VSE requirements,
planning without final assembly). To do this, proceed as follows:
1. Maintaining the material master: In the material master for pump R-F1## in
plant 1000, enter strategy group 50 (planning without final assembly). As
in the preceding exercises, call MRP3 view using the transaction Change
material immediately. Make the change in the corresponding field and save
the change.
a) Menu path: Logistics → Production → Master Data → Material
Master → Material → Change → Immediately
2. Creating the planned independent requirements: Use the transaction Create
Planned Independent Requirements again from the Demand Management
menu for the material R-F1## in plant 1000. On the initial screen for the
transaction, set the indicator M for monthly format in the planning period
field.
On the Table screen in the row with material R-F1## in the month current
month + 3, enter a planned independent requirements quantity of 100 pieces.Select the row and proceed to the Delivery Schedule tab page. Note the
requirements type VSE.
In the Allocation Indicator field, enter W for week quantities and confirm
this using Enter so that the allocation takes effect. Save the planned
independent requirements.
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Planned Independent Requirements → Create
Task 2:
Carry out a planning run for material R-F1## in the form of multilevelsingle-item planning.
1. Use the creation indicator that you used in the preceding exercises. Start the
planning run by confirming twice using Enter .
a) Menu path: Logistics → Production → MRP → Planning →
Multilevel Single-Item Planning
Continued on next page
106 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 119/522
TSCM40 Lesson: Planning Make-to-Order Production
Task 3:
Look at the planning results in the stock/requirements list.
1. Call the stock/requirements list for material R-F1## (plant 1000). Make
sure that the planned independent requirements quantities and the planned
orders they belong to are listed in a separate planning segment.
Double-click (Additional data for element) to check whether these planned
orders can be converted into production orders and explain this:
_____________________________________________________
_____________________________________________________
a) Can the planned orders be converted? The planned orders in the
planning segment have the order type VP and therefore cannot
be converted or changed (there are no pushbuttons in the Detail
view for converting the planned order into a production order,
for example, and no change mode). They merely serve to create
dependent requirements at lower BOM levels.
2. Look at the current stock/requirements list for assembly R-B2## (the
flywheel) in plant 1000.
Are these planned orders also taken up in a planning segment? Are they
convertible? (Give a reason)
______________________________________________________
______________________________________________________
______________________________________________________
a) Planned orders for assembly R-B2##: Planned orders for assembly
R-B2## are not taken up in a planning segment. They have order
type LA and can be converted into production orders. The reason
for this is that the individual/collective indicator in the material
master for the assembly has been set to collective requirement. This
allows production of assemblies before a sales order is received.
Task 4:
A customer requirement with the desired date 3 days later than the date of the
second planned independent requirement SU is received for the finished product.
1. Now enter a customer requirement of 10 pieces for material R-F1## in plant
1000 from the Demand Management menu. Make sure the requirements type
is KEV (make-to-order production with consumption) and save your entries.
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Customer Requirements → Create
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 107
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 120/522
Unit 3: Demand Management TSCM40
Task 5:
Carry out a new MRP run for material R-F1##, plant 1000 in the form of
multilevel single-item planning.
1. Use the creation indicator that you used in the preceding exercises. Start the
planning run by confirming twice using Enter .
a) Menu path: Logistics → Production → MRP → Planning → Multilevel
Single-Item Planning
Task 6:
Call the current stock/requirements list for material R-F1## in plant 1000 and,
if necessary, refresh the list.
1. What has happened?
______________________________________________________
______________________________________________________
______________________________________________________
______________________________________________________
a) Menu path: Logistics → Production → MRP → Evaluations →
Stock/Requirements List
What has happened? The customer requirement received is managed
in an individual customer segment. The relevant quantity has
consumed a planned independent requirement from the planningsegment. Due to the planning run, a procurement element (planned
order) has been created. This procurement element is produced in
make-to-order production and covers the customer requirement.
In addition, the planned order quantity that belongs to the partially
consumed planned independent requirement has been adjusted.
2. Can the procurement element for the customer requirement be converted?
______________________________________________________
a) The planned order in the individual customer segment (order type
KD) can be converted into a production order.
108 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 121/522
TSCM40 Lesson: Planning Make-to-Order Production
Lesson Summary
You should now be able to:• Use planning strategies for make-to-order production
• Explain assembly processing
2008 © 2008 SAP AG. All rights reserved. 109
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 122/522
Unit 3: Demand Management TSCM40
Lesson:
88
Enhancements for Demand Management
Lesson Duration: 90 Minutes
Lesson Overview
There are a range of enhancement functions available in planned independent
requirements management to ensure that the production planning process runs
smoothly and consistently.
Lesson Objectives
After completing this lesson, you will be able to:
• Make demand management settings
• Make an adjustment and reduce requirements
Space for notes
Business Example
Most of the settings for Demand Management have already been made. You have
to execute several important functions to ensure it runs smoothly.
Overview: Several Special Planning Strategies
Point out some of the less prominent strategies that will either be dealt with if
specifically requested or ignored in this course (the contents will appear in the
appendix for the participants to study in their own time. If they request a system
demonstration of some of these special strategies and you have sufficient time
left, you can use some of the examples from the Instructor Guide for the course
SCM244 (Coll. 33)).
110 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 123/522
TSCM40 Lesson: Enhancements for Demand Management
Figure 47: Overview: Several Special Planning Strategies
Numerous other planning strategies are available for planning a material.
The “special planning strategies” mentioned above can be treated as an optional
element of the course.
Planned Independent Requirements Reduction
Explain in which step the planned independent requirements are reduced.
Figure 48: Planned Independent Requirements Reduction
2008 © 2008 SAP AG. All rights reserved. 111
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 124/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 125/522
TSCM40 Lesson: Enhancements for Demand Management
With strategy 59, the planned independent requirements are reduced by the goods
issue for the production order for the finished product. You must backflush the
material components.
With strategies 70 and 74, the assembly’s planned independent requirements are
reduced by the goods issue for a production order or cost center.
The corresponding movement type must allow the reduction of the planned
independent requirements. In addition, the system only reduces the planned
independent requirements for the requirements type that is controlled by the main
strategy of the strategy group assigned to the material. Planned independent
requirements for the requirements types of the alternative strategies are not usually
reduced by the material movements.
Adjusting the Planned Independent Requirements
Planned independent requirements are ignored for planning within the period of
adjustment, but remain on the database (in comparison with reorganization)!
Figure 50: Adjusting the Planned Independent Requirements
The period of adjustment determines a period in which planned independent
requirements are not taken into account in the requirements calculation, but
merely have an MRP-effect for customer requirements. However, the planned
independent requirements remain on the database (hide function).
2008 © 2008 SAP AG. All rights reserved. 113
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 126/522
Unit 3: Demand Management TSCM40
You maintain the period of adjustment in working days in Customizing for the
MRP group. The corresponding adjustment indicator defines whether the period
of adjustment points to the past or to the future. The adjustment indicator alsospecifies whether the adjustment is valid for planned independent requirements for
all strategies or only for planned independent requirements that are planned using
a strategy in which customer requirements and planned independent requirements
are consumed.
The adjustment can be used to eradicate “planning errors”, for example. The
period of adjustment could therefore correspond to the period in which only the
customer requirements that exist up to now are to be covered, and no new ones
are expected.
Demonstration: Adjustment
Purpose
Demonstration of adjustment
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Material: R-F1##, plant 1000
Change material master: Enter strategy group 40; MRP group 0031 should
already be entered
2. Create planned independent requirements for the current week – 4 to the
current week + 5, each for 10 pcs, either by entering them individually on
the Table tab page or using the “Split by period” function on the Schedule
Lines tab page.
3. Create customer requirements: 4 pcs for today, 7 pcs for today + 1 week, and
9 pcs for today + 2 weeks
→ Customer requirements consume the planned independent requirements.
4. The period of adjustment is set for each MRP group:
→ Customizing: Production – Material Requirements Planning – MRP
Groups – Carry Out Overall Maintenance of MRP Groups
or:
→ Customizing: Production – Production Planning – Demand Management
– Planned Independent Requirements – Maintain Consumption Mode and
Period of Adjustment
114 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 127/522
TSCM40 Lesson: Enhancements for Demand Management
Plant 1000, MRP group 0031, “Consumption/Adjustment” button, period of
adjustment: 6 (working) days, 1 = Adjustment in the future
5. Call the stock/requirements list again – it is not enough to simply refresh
it!
→ Only the customer requirements (regardless of whether they are inside
or outside the period of adjustment) and the planned orders (outside the
period of adjustment) have an effect on requirements planning. The planned
independent requirements within the period of adjustment are displayed, but
are not taken into account in planning.
6. Multilevel planning run to confirm the result
7. Remove the period of adjustment from the MRP group and then call the
stock/requirements list once more – it is not enough to simply refresh it!
Reorganizing Planned Independent Requirements
Planned independent requirements that can no longer be reduced by customer
requirements are removed with the reorganization. This takes place in 3 steps
(with 3 transactions).
Requirements adjustment that takes place in reorganization should not be
confused with adjustment according to MRP group, whereby planned independent
requirements within a period are ignored, yet are retained on the database (see
above).
The reorganization is described in detail in SAP Note 135807.
2008 © 2008 SAP AG. All rights reserved. 115
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 128/522
Unit 3: Demand Management TSCM40
Figure 51: Reorganizing Planned Independent Requirements
During the adjustment, planned independent requirements that lie within the
period of adjustment are simply ignored in material requirements planning but
remain on the database. The aim of reorganization is to delete old planned
independent requirements from the database.
The reorganization takes place in 3 steps:
1. “Adjust requirements” (transaction MD47): Quantities that have not beenassigned before the specified reorganization key date (this date can also be in
the future) are set to 0 and are flagged for reorganization.
2. Reorganize schedule lines (MD75): Schedule lines that have a quantity of 0
before the key date are deleted from the database.
3. Delete history (MD76): The history can be deleted by determining a (further)
key date.
As an alternative to the key date, you can maintain a reorganization period per
plant (in the Customizing for Demand Management). This is calculated backwards
from the current date.
We recommend that you carry out reorganization periodically, for example, oncea month.
116 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 129/522
TSCM40 Lesson: Enhancements for Demand Management
Demonstration: Reorganization Compared toAdjustment, Using Data from the AdjustmentDemonstration (Optional)
Purpose
Reorganization demo
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Setting up and carrying out reorganization:
Determine the reorganization period for each plant (number of days from
today backward, to define the reorganization date (key date)):
Customizing: Production – Production Planning – Demand Management –
Planned Independent Requirements – Define the reorganization interval
Do not maintain a reorganization interval in this demo, but rather enter the
key date for the requirements adjustment in the initial screen.
2. Adjustment (reduction) of independent requirement schedule line quantitiesat the level of the assigned (customer) requirements. If there are no
requirements assigned, the planned quantities are set to 0.
→ Logistics - Production – Production Planning – Demand Management
– Environment – Independent Requirements: Reorganization – Adjust
Requirements (MD74)
Key date: Today
Caution: Adjustment of the requirements within the reorganization
has nothing to do with the maintenance of the period of
adjustment (the adjustment simply ignores the planned independentrequirements for the net requirements calculation. These quantities
remain on the database, however. See above):
3. Deletion of all independent requirement schedule lines that have a planned
quantity of 0:
→ Logistics - Production – Production Planning – Demand Management
– Environment – Independent Requirements: Reorganization – Schedule
Lines: Reorganize (MD75)
2008 © 2008 SAP AG. All rights reserved. 117
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 130/522
Unit 3: Demand Management TSCM40
4. Delete history (by defining another key date, such as the last day of last week)
→ Logistics - Production – Production Planning – Demand Management –
Environment – Independent Requirements: Reorganization – Delete History
(MD76)
Supplement:
Defining the creation of a history for the planned independent requirement
depending on the requirements class:
Customizing: Production – Production Planning – Demand Management
– Planned Independent Requirements – Default Values and Presettings –
Define History Settings Per Reqmts Class
If the history creation was not defined using the requirements class, you
can activate the history in the independent requirements maintenanceusing the requirements parameters. If the history creation is defined for
a requirements class in Customizing, it cannot be reversed using the
requirements parameters.
Settings for Material Requirements Planning
Settings in the material master have priority over those made in the MRP group.
These in turn have priority over plant parameters. No setting appears in all three
groups.
Figure 52: Settings for Material Requirements Planning
118 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 131/522
TSCM40 Lesson: Enhancements for Demand Management
The Customizing settings for the requirements planning are basically controlled at
three levels:
• Material master
• MRP group (Customizing step Carry Out Overall Maintenance of MRP
Groups)
• Plant parameters (Customizing step Carry Out Overall Maintenance of Plant
Parameters)
The MRP group is an organizational object that is used to assign certain control
parameters for MRP to a group of materials. This includes the creation indicators
for purchase requisitions, schedule lines, the planning horizon, and so on. In
Customizing, you can define the MRP group with these specific control parameters
and assign the material to the corresponding MRP group in the material master
record (MRP 1 view).
If a setting is possible on several levels, the setting in the material master takes
priority over the setting in the MRP group to which the material is assigned. The
setting in the MRP group takes priority over the setting in the plant parameters.
Demonstration: MRP Settings in the Material Master,MRP Group, Plant
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Display material master R-F1##:
MRP 1: Explain the MRP group field
MRP 3: Display the settings for consumption (the same settings are alsopossible in the MRP group.)
2. Display MRP group 0031 in Customizing:
Consumption/adjustment: You can set up consumption in the MRP group
and you can only set up adjustment in the MRP group.
Display the planning horizon (can also be entered in the plant).
3. Display the plant parameters in Customizing:
2008 © 2008 SAP AG. All rights reserved. 119
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 132/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 133/522
TSCM40 Lesson: Enhancements for Demand Management
The strategy group enables you to combine several planning strategies.
Figure 54: Strategy Groups and Planning Strategies
You can create the strategy groups in Customizing, in the work step Define
Strategy Group. A strategy group can contain a main strategy and up to seven
alternative strategies. You can also create the strategies in the Customizing for
Demand Management.
You assign the strategy group to the material in the material master record (MRP
3 view) or the assigned MRP group.
When you create the customer requirements or the planned independent
requirements, the system uses the customer requirements type or planned
independent requirements type defined in the main strategy of the strategy group
assigned to the material. You can do this provided that the requirements type is not
defined by user parameters or manual entry when creating the planned independent
requirements or customer requirements (sales order). You can determine the
requirements types that can be used for a material in the alternative strategies.
In the sales order, you can access the customer requirements type in the sales
order item in the Procurement view.
You can also determine the customer requirements type from the item type of the
sales order if no strategy group has been assigned to the material (in Customizing
Sales and Distribution, in the work step Determination of Requirement Types
Using Transaction).
2008 © 2008 SAP AG. All rights reserved. 121
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 134/522
Unit 3: Demand Management TSCM40
Figure 55: Requirement Types and Classes
Generally, a planning strategy groups two requirements types - for planned
independent requirements and for customer requirements.
The requirements type is assigned to one specific requirements class. Therefore,
the requirements class represents a kind of “values list” for the settings of the
requirements type. This means that any changes to the requirements type are made
by way of the corresponding requirements class.
In the requirements class, you can control how the customer requirements are to
consume the planned independent requirements, for example.
The definition of the requirements class is made in the Customizing for Demand
Management for “planned independent” requirements classes and in the
Customizing for SD for “independent customer” requirements classes.
The requirements class controls functions relevant for sales order requirements
in Logistics. In the requirements class, you define the type of availability check,
whether the requirement is relevant to MRP ( No MRP field), whether consumption
is to be carried out and if so, which type ( Assignment indicator field). The exact
type of assembly processing is defined using the customer requirements type for
the corresponding sales order.
Furthermore, you can define specifications that are used in cost accounting (such
as the settlement profile for settling a requirements class).
122 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 135/522
TSCM40 Lesson: Enhancements for Demand Management
Demonstration: Customizing: Planned IndependentRequirements Management
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard1. Display and explain the following fields and functions in the Customizing
for Demand Management and Sales and Distribution:
Customizing: Production – Production Planning – Demand Management –
Planned Independent Requirements – ......
Customizing: Sales and Distribution – Basic Functions – Availability Check
and Transfer of Requirements – Transfer of Requirements - .......
Strategy: The strategy is defined by specifying a planned independent
requirement type and a customer requirement type
Customizing: Production – Production Planning – Demand Management – Planned Independent Requirements – Planning Strategy – Define Strategy
2. Strategy group:Strategy group: Definition of main and secondary strategy
Customizing: Production – Production Planning – Demand Management –
Planned Independent Requirements – Planning Strategy – Define Strategy
Group
3. Requirement types:
2008 © 2008 SAP AG. All rights reserved. 123
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 136/522
Unit 3: Demand Management TSCM40
Strategy for determining the requirements type (from documentation)
1. First the system tries to find a requirements type using the strategy
group from the material master.
2. If the strategy group in the material master has not been maintained, the
system determines it using the MRP group.
3. If the MRP group is not defined, the system uses the material type
instead of the MRP group when accessing the corresponding control
tables (according to Martin Preiss, this is no longer relevant as it is a
relic from the transition from R/2 to R/3)
4. for the customer requirement type: If the system does not find a
requirement type here either, it assumes a special rule exists and tries
to locate a requirement type with the aid of the item category and the
MRP type.
Customizing: Sales and Distribution – Basic Functions – Availability
Check and Transfer of Requirements – Transfer of Requirements –
Determination of Requirement Types Using Transaction.
5. If this is not possible, the system makes a final attempt to find a
requirements type using only the item category.
6. If the last attempt fails, the system declares that the transaction (the
sales order item) is not relevant for the availability check and the
transfer of requirements.
4. Message output for invalid requirements type:
Customizing: Production – Production Planning – Demand Management
– Planned Independent Requirements – Requirements Types/Requirements
Classes – Message Output for Invalid Requirements Type
The check occurs against the requirements types defined in the main strategy
and secondary strategies assigned to the respective strategy group.
The way in which a requirements type works is determined by assigning
a requirements class. Changes to a requirements type occur using the
corresponding requirements class.
Independent requirements type:
→
.......Requirements Types/Requirements Classes – Define RequirementsTypes and Allocate Requirements Class
Customer requirements type:
→ .......Define Requirements Types
5. Requirements classes:
Planned independent requirements class:
124 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 137/522
TSCM40 Lesson: Enhancements for Demand Management
→ ......Requirements Types/Requirements Classes – Maintain Requirements
Classes
Customer requirements class:
→ ......Define Requirements Classes
6. Consumption mode, consumption period: In material master (MRP 3) or
for each MRP group:
→ Customizing: Production – Material Requirements Planning – MRP
Groups – Carry Out Overall Maintenance of MRP Groups
or
Customizing: Production – Production Planning – Demand Management
– Planned Independent Requirements – Maintain Consumption Mode and
Period of Adjustment
Default values for the consumption type for each requirements class:
Determine the actual requirements (customer requirement, dependent
requirement, reservations) for consumption:
Customizing: Production – Production Planning – Demand Management
– Planned Independent Requirements – Default Values and Presettings –
Define Default Values for Consumption Type Per Reqmts Class
7. Period of adjustment (per MRP group):
→ Customizing: Production – Material Requirements Planning – MRP
Groups – Carry Out Overall Maintenance of MRP Groups
or
→ Customizing: Production – Production Planning – Demand Management
– Planned Independent Requirements – Maintain Consumption Mode and
Period of Adjustment
8. Reorganization interval (per plant):
Customizing: Production – Production Planning – Demand Management –
Planned Independent Requirements – Define the reorganization interval
2008 © 2008 SAP AG. All rights reserved. 125
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 138/522
Unit 3: Demand Management TSCM40
126 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 139/522
TSCM40 Lesson: Enhancements for Demand Management
97 Exercise 6: Customizing
Exercise Duration: 10 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Make and check the Customizing settings for the planning strategies
Business Example
The SAP person responsible for the project verifies the settings for strategy 50
in Customizing and checks the MRP group settings.
Task 1:
In Customizing for Demand Management, check which requirement types and
classes are assigned to strategy 50 (planning without final assembly). (You can
see these settings in Customizing, in the step Define Strategy.)
Hint: You only need display authorization to do this.
Plnd. Indep. Reqmnt Customer requirements
Requirements type
Requirements class
1. For which data object (requirements class or requirements type) do you make
the individual settings to determine how strategy 50 works.
_____________________________________________________
2. Name the Customizing paths for the work steps you need to modify this data
object. Navigate to the relevant entries.
Planned independent requirement:
______________________________________
_____________________________________________________
Customer requirements:
_________________________________________
_____________________________________________________
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 127
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 140/522
Unit 3: Demand Management TSCM40
Task 2:
When planning with strategy 50, customer requirements consume planned
independent requirements.
1. What values do the consumption or assignment indicators have in
Customizing?
Requirements class
Consumption or
assignment indicator
Task 3:1. Which planning strategies are allowed by strategy group 50 (Planning
without final assembly)?
_________________________________________
Task 4:
Finally, take a look at an MRP group. In Customizing, display the MRP group
SCM2 (Customizing step Carry Out Overall Maintenance of MRP Groups).
1. Which strategy group is maintained for plant 1000 in the MRP group SCM2?
______________________________________________________
2. Which values have been maintained for the planning horizon and the
rescheduling horizon in this MRP group?
Planning horizon: _______________________________________
_______________________________________
Rescheduling horizon: ________________________________
________________________________
128 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 141/522
TSCM40 Lesson: Enhancements for Demand Management
Solution 6: Customizing
Task 1:
In Customizing for Demand Management, check which requirement types and
classes are assigned to strategy 50 (planning without final assembly). (You can
see these settings in Customizing, in the step Define Strategy.)
Hint: You only need display authorization to do this.
Plnd. Indep. Reqmnt Customer requirements
Requirements type
Requirements class
1. For which data object (requirements class or requirements type) do you make
the individual settings to determine how strategy 50 works.
_____________________________________________________
a) Menu path Customizing: Production → Production Planning →
Demand Management → Planned Independent Requirements →
Planning Strategy → Define Strategy
Plnd. Indep.
Reqmnt
Customer requirements
Requirements type VSE KEV
Requirements class 103 045
Settings to activate strategy 50: You make the individual settings in
the requirements class. You then assign the requirements class to
the requirements type.
2. Name the Customizing paths for the work steps you need to modify this dataobject. Navigate to the relevant entries.
Planned independent requirement:
______________________________________
_____________________________________________________
Customer requirements:
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 129
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 142/522
Unit 3: Demand Management TSCM40
_________________________________________
_____________________________________________________
a) Customizing path to modify the requirements classes:
Planned independent requirement: Customizing: Production →
Production Planning → Demand Management → Planned Independent
Requirements → Requirements Types/Requirements Classes →
Maintain Requirements Classes
Customer requirements: Customizing: Sales and Distribution → Basic
Functions → Availability Check and Transfer of Requirements →
Transfer of Requirements → Define Requirements Classes
Task 2:
When planning with strategy 50, customer requirements consume planned
independent requirements.
1. What values do the consumption or assignment indicators have in
Customizing?
Requirements class
Consumption or
assignment indicator
a) Consumption indicator or assignment indicator in Customizing: You
may gather in the Customizing step Define Strategy.
Requirements class 103 045
Consumption or
assignment indicator
2 2
Task 3:
1. Which planning strategies are allowed by strategy group 50 (Planningwithout final assembly)?
Continued on next page
130 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 143/522
TSCM40 Lesson: Enhancements for Demand Management
_________________________________________
a) Planning strategies of strategy group 50:Planning strategies in
strategy group 50: As well as planning strategy 50 (standard case)
you can also use the strategies 40 and 20.
Menu path Customizing: Production → Production Planning →
Demand Management → Planned Independent Requirements →
Planning Strategy → Define Strategy Group
Task 4:
Finally, take a look at an MRP group. In Customizing, display the MRP group
SCM2 (Customizing step Carry Out Overall Maintenance of MRP Groups ).
1. Which strategy group is maintained for plant 1000 in the MRP group SCM2?______________________________________________________
a) Menu path: Customizing: Production → Material Requirements
Planning → MRP Groups → Carry Out Overall Maintenance of
MRP Groups
Strategy group for MRP group SCM2: Strategy group 40 (choose
Strategy Group in MRP group maintenance)
2. Which values have been maintained for the planning horizon and the
rescheduling horizon in this MRP group?
Planning horizon: ______________________________________________________________________________
Rescheduling horizon: ________________________________
________________________________
a) Planning horizon and rescheduling horizon:
200 working days, 200 working days (choose Planning Horizon or
Rescheduling Horizon in the MRP group maintenance screen).
2008 © 2008 SAP AG. All rights reserved. 131
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 144/522
Unit 3: Demand Management TSCM40
Lesson Summary
You should now be able to:• Make demand management settings
• Make an adjustment and reduce requirements
132 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 145/522
TSCM40 Lesson: Basics of the Availability Check
Lesson:
103
Basics of the Availability Check
Lesson Duration: 60 Minutes
Lesson Overview
The ATP check can be done from the sales order, for example. It is not directly
connected with material requirements planning, but should be set in such a way
that it corresponds with it.
Lesson Objectives
After completing this lesson, you will be able to:
• Carry out ATP checks for sales orders
Space for notes
Business Example
Sales orders were created and included in material requirements planning.
Afterwards, an availability check is carried out.
Availability check in SAP ECC
Depending on the strategy you use, you can carry out an ATP check or a check
against the planned independent requirements in SAP ECC. The corresponding
setting in the customer requirements class determines the choice of availability
check procedure. It is thus determined indirectly by way of the planning strategy
for the material.
2008 © 2008 SAP AG. All rights reserved. 133
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 146/522
Unit 3: Demand Management TSCM40
Figure 56: Availability Check in SAP ECC
The availability check can be used in a number of ways. It can be used in sales
orders (but also in production orders or during goods movements). Therefore,
when you create a sales order, for example, the system uses the ATP check to
determine whether there is enough stock available in the warehouse for the
required material. The system can also check if receipts (for example, production
orders and planned orders) have already been planned by the requested date. If
the answer is yes, the sales order can be confirmed.
As well as the availability check according to ATP, forecast planning offers
another alternative (choose in the customer requirements class).
Hint: Availability Check (intended as help for the instructor)
Summarize the most important points and the possible Customizing
settings
Availability Check Using ATP Logic
The scope of the check is determined by a combination of the
checking group (material master, MRP 4) and checking rule
(application-dependent), both of which are determined in Customizing.
The total replenishment lead-time is important: In Customizing you can
define that the availability check only has to be carried out for customer
requirements within this time period.
Availability Check with Planned Independent Requirements
134 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 147/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 148/522
Unit 3: Demand Management TSCM40
Customizing: Production – Material Requirements Planning –
Procurement Proposals – Planned Orders – Define Availability
Check for Components
(Table of checking rules: Description of checking rules (see above))
(Determine check: Corresponds to scope of check (see below))
Plant:Check rule for each plant
MRP group: Checking rule per plant and MRP group
• For shop floor control:
Customizing: Production – Shop Floor Control – Operations –
Availability Check – Define Checking Control: Checking rule
opened/released per plant, order type, and production order
Scope of check (combination of checking group and checking rule):
Stocks, receipts/issues, only within replenishment lead time, storage
location check, ...
Customizing: Sales and Distribution – Basic Functions – Availability
Check and Transfer of Requirements – Availability Check – Availability
Check with ATP Logic or Against Planning – Carry Out Control for
Availability Check
or
Customizing: Production – Material Requirements Planning –
Procurement Proposals – Planned Orders – Define Availability Check
for Components: Determine Check
or
Customizing: Production – Shop Floor Control – Operations –
Availability Check – Define Scope of Check
Availability Check Using ATP Logic
Explain the ATP concept: The check takes place against fixed receipts that haveto be defined. In this course, the check takes place for the finished product
(exception: Assembly production strategies 81, 82, 83).
The scope of the check is determined by a combination of the checking group
(material master, MRP 4) and checking rule (application-dependent), both of
which are determined in Customizing (see above).
The total replenishment lead-time is important: In Customizing you can define
that the availability check only has to be carried out for customer requirements
within this time period.
136 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 149/522
TSCM40 Lesson: Basics of the Availability Check
An ATP check occurs dynamically, but only when you create the sales order (it
is possible to execute this again). Moreover, an ATP check is also possible for
components from planned orders and production orders (also mass availabilitycheck).
At this point, you should tell the participants about the enhanced functions of
the global ATP check in SCM APO: Cross-location + rule based check, CTP,
multilevel ATP
Figure 57: Availability Check for Sales Order with ATP Logic
When performing an availability check using ATP logic (Available-to-Promise),
the system checks whether all issues are covered by existing receipts and whether
open quantities from the receipts are still available to cover newly received issues.
These open quantities that have not yet been assigned are added together to give
the ATP quantity.
In the availability check using ATP logic, the system checks whether the
requirement quantities are covered by specially defined receipt and issue elements
or by a specific stock. If you can confirm a quantity for the requirement date,this quantity is flagged as confirmed in the requirement and the ATP quantity
of the stock or receipt for the components is reduced correspondingly. In the
next availability check, you can only confirm requirements for the amount of
the remaining ATP quantity.
The ATP quantities are not calculated across planning segments and do not take
any periods into account.
2008 © 2008 SAP AG. All rights reserved. 137
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 150/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 151/522
TSCM40 Lesson: Basics of the Availability Check
Demonstration: Planned Order ATP (Optional)
Purpose
To demonstrate the availability check for planned orders
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Call the stock/requirements list for R-F1## in plant 1000 (## is the groupnumber that you used in the exercise for strategy 50).
2. Go to the details for the customer planned orders for the individual section.
3. Carry out the component availability check and interpret the result (quantities
and dates).
4. Evaluate the ATP quantities situation (transaction CO09)
5. Mention the conditions for transaction MDVP (collective availability check)
6. Undo any changes you may have made (for example, firming in the planned
order header and the components)
Settings for the ATP check in SAP ECC
The checking group and checking rule define what is checked. In the scope of the
check, you determine the elements that are to be included.
2008 © 2008 SAP AG. All rights reserved. 139
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 152/522
Unit 3: Demand Management TSCM40
Figure 59: Settings for the ATP Check in SAP ECC
The checking group that is entered in the material master (MRP3 view) enables
materials to be grouped according to checking properties (Maintenance in
Customizing for SD).
You use the checking rules, which are set in Customizing for the respective
business application, to carry out different checks depending on the area of
application (sales order, production order, for example). The check can also beleft out completely.
The connection between the checking group and the checking rules is made by
entering this into the scope of check (Customizing for the application). Here
you define the stocks, issues and receipts for which the combination is valid as
check instructions.
Availability Check with Planned Independent Requirements
The check here merely takes place against planned independent requirements and
not against fixed receipts. This kind of check takes place when using strategies
50, (52), 60.
140 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 153/522
TSCM40 Lesson: Basics of the Availability Check
Figure 60: Availability Check with Planned Independent Requirements
In the check against planned independent requirements, the system only checks
against the open planned independent requirements quantities. This means that no
ATP quantities, receipts or stocks are included in the availability check.
The check against planned independent requirement assignments determines
whether sufficient planned independent requirements have been planned to covera customer requirement.
In this check, the system uses the consumption mode (backward consumption in
the example above) and the corresponding consumption periods.
You can usually define the type of availability check to be performed in the
customer requirements class for the strategy. When using strategy 50, you can
only carry out the availability check against planned independent requirements. In
strategy 60, when you process the sales order, you can check against the planned
independent requirements for the planning material.
Demonstration: Availability Check for Sales Orders
Purpose
To demonstrate the availability check and to prepare the exercise.
Hint: The settings for the availability check are contained in Customizing.
2008 © 2008 SAP AG. All rights reserved. 141
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 154/522
Unit 3: Demand Management TSCM40
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. First of all, show the different types of availability checks using SAP ECC
strategies 40 (ATP logic) and 50 (check against planned independent
requirements):
Customizing: Production – Production Planning – Demand Management –
Planned Independent Requirements – Planning Strategy – Define Strategy
40 -> Availability check selected (-> ATP)
50 -> Availability check deselected and assignment indicator active
(-> check against planned independent requirements)
2. Demonstrate where the availability check for sales orders is set:
Customizing: Sales and Distribution – Basic Functions – Availability Check
and Transfer of Requirements – Availability Check – Availability Check with
ATP Logic or Against Planning – ...
→ ... - Define Checking Groups
The checking group is defined here and then saved in the material master
3. Show where the availability check is controlled (assignment of checkinggroup and checking rule):
→ ... - Control the availability check
Note: Checking rules are predefined for Sales and Distribution, whereas
checking rules for the component availability check can be created from
planned orders or production orders.
Control for the availability check determines which stocks are included,
whether the check will take place with or without replenishment lead-time,
and which receipts and issues are included.
4. Show the menu path for the SAP ECC availability check for components.(Note: MRP does not detect planned orders – this is a completely different
function! This will be dealt with in the next unit):
142 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 155/522
TSCM40 Lesson: Basics of the Availability Check
Customizing: Production – Material Requirements Planning – Procurement
Proposals – Planned Orders – Define Availability Check for Components
• Table of checking rules
• Define check (from the SD menu)
• Plant -> Default checking rule
• MRP group -> Checking rule for MRP group
2008 © 2008 SAP AG. All rights reserved. 143
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 156/522
Unit 3: Demand Management TSCM40
Facilitated Discussion
Explain the connection between material requirements planning and the
availability check.
Discussion Questions
Use the following questions to engage the participants in the discussion. Feel free
to use your own additional questions.
What happens when you reject a production order that was used to confirm a
warehouse order?
144 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 157/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 158/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 159/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 160/522
Unit 3: Demand Management TSCM40
Solution 7: Availability Check for Sales
OrderTask 1:
A sales employee enters a sales order for the pump (material R-F1##, plant 1000):
1. In Sales and Distribution, navigate to Sales and call the transaction for
creating a sales order.
The order is a standard order (order type OR). Enter the following
organizational data:
Sales Organization: 1000
Distribution Channel: 10
Division: 00
Sales Office: 1000
Choose Enter to call the standard order overview screen and enter the
following data here:
Sold-to party: 1000
Ship-to party: 1000
PO number: Sub_## (## = group number)
Required delivery date: 3 days later than the first VSE
planned independent requirement
for material R-F1## in plant 1000.
Material: R-F1##
Order quantity: Quantity of the VSE previous
planned independent requirement
+ 3 pc.
Choose Enter to confirm your entries and, if necessary, confirm the
information message with Enter .
a) Menu path: ECC Logistics → Sales and Distribution → Sales → Order
→ Create
2. The system displays the results of the availability check performed in the
background in a new window (if the window does not appear automatically,
you can call it yourself from the sales order using the the seventh pushbutton
from the left at the bottom of the screen).
Continued on next page
148 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 161/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 162/522
Unit 3: Demand Management TSCM40
_____________________________________________________
Do not exit the stock/requirements list.
a) Have new procurement elements been generated? No. The planned
orders for material R-F1## result from previous multi-level
requirements planning (from the last exercise). The availability
check in ECC does not itself generate new requirement coverage
elements.
5. In the first session (check dialog), ensure that the Fix date indicator is not
set. Call the F1 help for this field.
With this setting, will a sales order appear with the required delivery quantity
or the confirmed quantity in the stock/requirements list?
______________________________________________________
In the check dialog, choose Complete Delivery and then save the sales order.
a) Sales order quantity: The system displays a sales order using the
required delivery quantity and not the confirmed quantity.
6. In the second session, refresh the stock/requirements list for R-F1##, plant
1000 (F6 key). What quantity does the sales order return?
______________________________________________________
______________________________________________________
a) Stock/requirements list: The sales order returns the required
delivery quantity.
Task 2:
The customer cancels their sales order without warning.
1. Go to change mode for the sales order that you have just entered. The easiest
way to do this is to double-click the sales order in the stock/requirements list.
Make a note of the sales order number from the stock/requirements list here:
__________________________________________________
Follow the menu path: Sales Document → Delete and confirm and save
your change.
Note: You can use this simple deletion method here because there are no
follow-on documents.
a) Sales order number: This varies
2. After this deletion, are the quantities originally used in the confirmation
available for other sales orders?
Continued on next page
150 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 163/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 164/522
Unit 3: Demand Management TSCM40
Lesson Summary
You should now be able to:• Carry out ATP checks for sales orders
152 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 165/522
TSCM40 Unit Summary
Unit Summary
You should now be able to:
• Use the planning strategy
• Explain the interplay between planned independent requirements and
customer requirements
• Use planning strategies for make-to-stock production
• Use planning strategies for make-to-order production
• Explain assembly processing
• Make demand management settings
• Make an adjustment and reduce requirements
• Carry out ATP checks for sales orders
2008 © 2008 SAP AG. All rights reserved. 153
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 166/522
Unit Summary TSCM40
154 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 167/522
TSCM40 Test Your Knowledge
119Test Your Knowledge
1. Which of the following parameters are determined by the planning strategy?
Choose the correct answer(s).
□ A Planned independent requirement type
□ B Order type (production order or process order)
□ C Customer requirement type
□ D Procurement type
2. Changes to the planning situation automatically result in a new ATP
availability check .
Determine whether this statement is true or false.
□ True
□ False
2008 © 2008 SAP AG. All rights reserved. 155
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 168/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 169/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 170/522
Unit 4: Executing Material Requirements Planning TSCM40
Single-item planning affects only one particular material and is therefore suitable
for planning critical resources, for example. There are various ways in which
you can influence the planning result interactively. One of these possibilities issingle-item planning in simulation mode, which makes it possible to analyze and
execute multilevel planning for a particular material.
Finally, you need to prevent a planned result from being influenced by material
requirements planning. You can use firming to do this.
Unit Objectives
After completing this unit, you will be able to:
• Explain the principle of multilevel requirements planning
• Go through the principle of external procurement and the document flow• Make the necessary settings in Customizing
• Make the necessary settings in the master data
• Trigger single-item planning
• Trigger total planning
• Interpret the planning file
• Execute the MRP run in simulation mode
• Firm a planned order in different ways
• Use firming in requirements planning
Unit Contents
Lesson: Overview and Concept of MRP. .. .. .. .. ... .. .. ... .. ... .. .. .. .. ... ..159Lesson: Prerequisites for MRP ...............................................164
Demonstration: Prerequisites for MRP .................................. 165Demonstration: Material Status (Optional) .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. 166
Lesson: Setting and Executing the MRP Run...............................172
Demonstration: Executing the Planning Run .. .. .. .. .. .. .. .. .. .. .. .. .. .176Demonstration: Low-Level Coding ... .. .. .. .. ... .. .. ... .. ... .. .. .. .. ... ..177Demonstration: ECC Planning Horizon..................................181
Demonstration: Planning File .. .. .. ... .. .. .. .. ... .. .. ... .. ... .. .. .. .. ... ..185
Demonstration: Demonstration: Planning File Continued............. 186Demonstration: Options in Interactive Planning........................ 189Demonstration: Simulative MRP .........................................194Exercise 8: Planning File .... ... ... ..... ... ... .... ... .... .... ... ... ... ..... 197Exercise 9: Simulative MRP .. ... .... .... ... ... .... .... ... .... ... ... .... ..207
Lesson: Firming .... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .217
Demonstration: Firming Settings ... ... .. .. .. ... .. .. ... .. ... .. .. .. .. ... ..223Demonstration: Firming a Planned Order .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .224Exercise 10: Firming .......................................................227
158 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 171/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 172/522
Unit 4: Executing Material Requirements Planning TSCM40
Figure 61: Principles and Results of MRP
Material requirements planning takes current and future sales as its reference
point. The planned requirement quantities trigger the MRP calculation. In MRP,
the requirements elements include sales orders, planned independent requirements,
material reservations, the dependent requirements created by exploding the BOM,
and so on.
If the MRP run determines shortage quantities, the system creates procurement
proposals: Purchase requisitions and planned orders are internal planning elementsthat can be changed, rescheduled, or deleted at almost any time.
With in-house production, the system creates planned orders for planning the
production quantities. When planning is complete, planned orders can be
converted into production orders.
With external procurement, the system either uses a planned order or uses a
purchase requisition directly to plan the external procurement quantity. When
planning is complete, the planned order is converted into a purchase requisition,
which is subsequently converted to a purchase order. Using the creation indicator
for purchase requisitions on the initial screen of the planning run, you control
whether the system immediately creates purchase requisitions directly, or first
creates planned orders.
If a scheduling agreement exists for a material and is relevant for MRP in the
source list, you can also create schedule lines directly using MRP. You control this
using the creation indicator for scheduling agreement delivery schedule lines on
the initial screen of the planning run.
160 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 173/522
TSCM40 Lesson: Overview and Concept of MRP
The creation indicators defined on the initial screen of the planning run are
valid for single-level and multilevel single-item planning. The indicators can be
changed during total planning and are overridden, if required, by the creationindicator defined for each plant and MRP group in Customizing.
Multi-level material requirements planning
Explain the difference between single-level and multilevel (single-item) planning.
Explain the terms independent and dependent requirements. Point out that the
dependent requirements are not bound directly to the independent requirements.
Figure 62: Multi-Level Material Requirements Planning
With in-house production, the system creates planned orders for planning the
production quantities. In multilevel production, that is, when a finished product
is made up of assemblies or components, the corresponding assembly group
requirements are mapped by way of dependent requirements.
Dependent requirements enter the MRP for the assembly as requirements. This
ensures timely staging of the assemblies.When planning is complete, planned orders can be converted into production
orders. When this is done, the system transforms the dependent requirements of
the planned order into production order reservations.
2008 © 2008 SAP AG. All rights reserved. 161
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 174/522
Unit 4: Executing Material Requirements Planning TSCM40
Facilitated Discussion
Discussion Questions
Use the following questions to engage the participants in the discussion. Feel free
to use your own additional questions.
Is the use of multi-level MRP for in-house production practical? Is it practical
to use it for external procurement? Is there a case where it makes sense to use
single-level planning for in-house production?
162 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 175/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 176/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 177/522
TSCM40 Lesson: Prerequisites for MRP
Figure 63: Prerequisites for MRP
In the Customizing activity “Activate MRP and Set Up Planning File”, you can
specify for which plant an MRP run is to be carried out by activating material
requirements planning. You can only make entries in the planning file once this
indicator has been set, which means that:
• When a material that is relevant for MRP is created, the system copies the
material number to the planning file and flags it for planning,• Whenever a change relevant to MRP is made, the system flags the material
for planning.
If materials were created before the MRP run for a plant was activated, you must
create an entry in the planning file for all MRP-relevant materials in this plant.
This function can only be executed in background processing. You trigger this
function in the work step Set up planning file in the Customizing activity Activate
MRP and Set Up Planning File, which you can call directly from the MRP menu.
If these conditions are fulfilled, materials already in the planning file can be
excluded from the MRP run using the MRP type in the material master (for
example, by using the MRP type ND).In addition, you can lock a material using the material status for MRP or generate
a warning regarding materials planning.
Demonstration: Prerequisites for MRP
Purpose
Preparation for exercise
2008 © 2008 SAP AG. All rights reserved. 165
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 178/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 179/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 180/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 181/522
TSCM40 Lesson: Prerequisites for MRP
You can use this relationship, for example, when you access specific material
groups (for example, in the context of targeted planning) and for evaluations.
Controller
Display:
1. The MRP controller assignment in the material master
2. The definition of the MRP controller in Customizing for requirements
planning
2008 © 2008 SAP AG. All rights reserved. 169
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 182/522
Unit 4: Executing Material Requirements Planning TSCM40
Facilitated Discussion
Discussion Questions
Use the following questions to engage the participants in the discussion. Feel free
to use your own additional questions.
Explain the function of activating material requirements planning in Customizing
(“pure MM” can also be useful without material requirements planning).
Understand how material entries are created and updated in the planning file.
170 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 183/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 184/522
Unit 4: Executing Material Requirements Planning TSCM40
Lesson:
132
Setting and Executing the MRP Run
Lesson Duration: 120 Minutes
Lesson Overview
There are various options available for carrying out the MRP run.
Lesson Objectives
After completing this lesson, you will be able to:
• Trigger single-item planning
• Trigger total planning
• Interpret the planning file• Execute the MRP run in simulation mode
Space for notes
Business Example
You can use different methods to execute the MRP run.
Setting and Executing the MRP Run
Executing Material Requirements Planning
You can execute MRP as total planning not only at plant level, but also more
generally in the planning scope (see the following slides.) If MRP areas are
activated, plant planning means planning in the plant MRP area.
To set up the user exit in the total planning run, you can refer to SAP Note 208025.
172 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 185/522
TSCM40 Lesson: Setting and Executing the MRP Run
Figure 66: Executing Material Requirements Planning
You can execute the planning run at two levels: As total planning for a plant or
for an individual material. You can execute a total planning run for several plants
and/or MRP areas (planning scope).
You can execute a single-item planning run for one BOM level only (single-level)
or for all BOM levels (multi-level). Interactive planning of a material is also
possible.
Multilevel single-item planning can also be executed for a Sales and Operations
Planning (SOP) product group.
You can execute total planning online or as a background job.
Total planning for a plant encompasses all MRP-relevant materials for this plant
and includes the BOM explosion for materials with BOMs.
From the MRP menu, you can execute total planning online or as a background
job. To execute the total planning run as a background job, select a report variant
to restrict it to the relevant plant, and schedule the job.
You can use a user exit to restrict the total planning run to materials that fulfill
certain freely definable criteria. For example, you can select all materials for
which a particular MRP controller is responsible.
Cross-Plant Total Planning
• Planning scope as summary of plants/MRP areas in a particular planning
sequence, taking into account mutual dependencies (for example, stock
transfers).
• Planning with planning scope only with parallel processing
Refer at this point to planning with MPR areas (unit 6).
2008 © 2008 SAP AG. All rights reserved. 173
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 186/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 187/522
TSCM40 Lesson: Setting and Executing the MRP Run
Parallel Processing in the Planning Run
Customizing: Production – Material Requirements Planning – Define Parallel
Processing in MRP
or
Logistics – Production – MRP – Environment – Current Settings – Define Parallel
Processing in MRP
Division of the planning run between various sessions on an application server
or between various servers: Each low-level code is divided into work packages,
which are processed by different sessions or servers. A low-level code is only
processed once all the work packages for the previous one have been completed.
Target: Improving performance, robustness
Figure 68: Parallel Processing in the Planning Run
When planning with planning scope, you must set the Parallel Processing
indicator in the planning run.
Parallel processing means that the planning run is divided into several independent
work packages that run parallel to each other in different sessions. You define the
sessions in the Customizing activity Define Parallel Processing in MRP. You can
access this activity directly from the MRP menu.
2008 © 2008 SAP AG. All rights reserved. 175
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 188/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 189/522
TSCM40 Lesson: Setting and Executing the MRP Run
Figure 69: Low-Level Coding
The low-level code is the lowest level at which a material appears in any BOM
structure. The low-level code of a material is always higher than the low-level
code of all its predecessors in all the BOM structures.
The low-level code controls the planning sequence: The system plans the
materials with low-level code 0 first, then those with low-level code 1 and so on.
All materials are thus planned in the correct sequence in a planning run.
The low-level code is calculated and saved at client level during BOM
maintenance. You can display the low-level code in the material master from the
MRP 1 view by choosing Information on material or in the planning file entry,
provided that an entry for that material exists in the planning file.
Demonstration: Low-Level Coding
Purpose
Preparation for the exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
2008 © 2008 SAP AG. All rights reserved. 177
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 190/522
Unit 4: Executing Material Requirements Planning TSCM40
1. Display the low-level code of a material in the material master (using the
blue pushbutton, “Information on material” from one of the material master
views) and in the planning file (transaction “Planning File Entry - Display”from the MRP menu): New materials with valid MRP types are included
in the planning file and receive the low-level code 999, until they can be
included in a BOM as a header or an item.
Possible question for the participants about low-level codes: Is multi-level
planning equivalent to the sum of single-item planning? Answer: Yes, if you
follow the sequence of the low-level codes exactly.
MRP Control Parameters
The indicators for creating purchase requisitions, scheduling agreements, and MRP
lists can be defined in the initial screen for the planning run and in the MRP group.
Important note on the creation indicator for each MRP group:
Customizing: Production – Material Requirements Planning – Planning – Define
Creation Indicator
The following applies for the total planning run:
The creation indicators that are specified in the initial screen at the start of a
planning run merely serve as proposals. They are only valid if the system does not
find a creation indicator in the MRP group.
For single item planning (single-level and multi-level) the following applies
Only the settings on the initial screen apply here. The Customizing settings
have no effect. (This rule is valid for both single-level and multi-level planning,
although in the case of multi-level planning, as for total planning, several materials
are addressed in the planning run that may have settings in their MRP group.)
The planning mode that was set in the planning file for a material may be
overridden by the planning mode in the initial screen of the planning run. The
planning mode controls how procurement proposals from the previous planning
run that are not firmed should be dealt with in the next planning run.
178 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 191/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 192/522
Unit 4: Executing Material Requirements Planning TSCM40
Scope of planning run
Restricting the planning run and using the net change procedure avoids
performance problems: You should not plan more materials then necessary.
The net change planning procedure (NETCH) only takes materials that have
undergone a planning-relevant change since the last planning run. This is
controlled in the planning file.
By defining a planning horizon, you also delimit the planning scope in terms of
time (NETPL). The planning horizon should at least span the time period in which
sales orders are received, and, furthermore, contain the delivery and total lead
times for the material.
You should only choose complete planning (NEUPL) in exceptional cases or if there are data inconsistencies.
(You cannot, of course, use NEUPL in single-item planning!)
Figure 71: Scope of Planning Run
With regenerative planning, the system plans all the materials in a plant. Thisis useful for the first planning run and also during day-to-day operation of the
plant if data consistency cannot be guaranteed due to technical errors. During
the day-to-day operation of a plant, it usually makes sense (particularly with a
large number of materials) to execute MRP for only those materials which have
undergone MRP-relevant changes (for example, due to goods issues, new sales
orders or changes to the BOM structure). Due to it short runtime, net change
planning (which is used to plan only these materials), allows you to execute the
planning run at short intervals, so that you always have the current planning result.
With net change planning in the planning horizon, the system only takes into
180 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 193/522
TSCM40 Lesson: Setting and Executing the MRP Run
account changes that are within the planning horizon. The system only plans
materials to which an MRP-relevant change has been made within the planning
horizon. In addition, the materials are only planned within this horizon. You setthe planning horizon as a plant or MRP group parameter in MRP Customizing.
The planning horizon should include at least the time period in which sales orders
are received. The delivery times and total lead times for the material should also
be contained in this horizon. You specify the type of planning run to be used in the
“Processing Key” field on the initial screen. With single-item planning, you can
only choose between net change planning (NETCH) or net change planning in the
planning horizon (NETPL). With total planning, you can also select the NEUPL
key to determine that all materials in the planning file are to be planned.
Demonstration: ECC Planning Horizon
Purpose
Preparation for the exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. You can find the planning horizon in three places in SAP ECC Customizing:
For each plant:
Customizing: Production – Material Requirements Planning – Plant
Parameters – Carry Out Overall Maintenance of Plant Parameters
2. For each MRP group:
Customizing: Production – Material Requirements Planning – MRP Groups
– Carry Out Overall Maintenance of MRP Groups
or:
Customizing: Production – Material Requirements Planning – Planning – MRP Calculation – Define Planning Horizon
Hint: Take account of SAP Note 162728. This explains why the
MRP group value should not be read for performance reasons.
2008 © 2008 SAP AG. All rights reserved. 181
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 194/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 195/522
TSCM40 Lesson: Setting and Executing the MRP Run
No planning file entry is created for the following changes:
• Changes in Customizing, for example changes to the purchasing department
processing time in the plant parameters
• Changes relevant to planning in the routing (for example, a change to the
standard time, change to the component assignment); you can overcome
this functional gap by setting this indicator manually following a change to
a routing or the in-house production time, or by executing a planning run
with planning mode 2 or 3).
You can define whether to retain or delete the planning file entries following a
termination of the planning run in the following Customizing activity:
Customizing: Production – Material Requirements Planning – Planning – MRP
Calculation – Define Error Processing in the Planning Run
Figure 72: Planning File and MRP (1)
The planning file contains all of the materials relevant to MRP for each plant.
Net change planning only plans those materials that have been subject to a change
relevant to MRP. Changes relevant to MRP lead to a planning file entry being
created specific to the plant and material. Examples of MRP-relevant changes
include changes to the procurement type, changes to the operation times, and also
creation of sales orders, dependent requirements, stock changes, and so on.
The respective entries in the planning file are made automatically by the business
application of the system. They can, however, also be made manually from the
MRP menu in individual cases. (When doing this, you should remember that a
change in the routing does not automatically cause an indicator to be set in the
planning file.)
2008 © 2008 SAP AG. All rights reserved. 183
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 196/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 197/522
TSCM40 Lesson: Setting and Executing the MRP Run
The planning horizon is maintained in Customizing for MRP as a plant parameter
or for each MRP group.
You can define whether a planning entry is to be retained or deleted if a
termination should occur while planning a material. You can do this in the IMG
activity “Define Error Processing in the Planning Run” in Customizing for MRP
calculation by choosing “Del. planning flag”. This determines whether or not the
material is taken into account in the next planning run.
Demonstration: Planning File
Purpose
Preparation for the exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Material: R-F130 in plant 1000
Hint: Creating the customer requirements in this
demonstration/exercise is a prerequisite for the
demonstration/exercise for MRP in simulation mode.
Create the customer requirement outside the planning horizon: Today + 6
months, 50 pcs → NETCH set
2. Create a customer requirement within the planning horizon: Today + 1
month, 60 pcs → NETPL also set
3. Single-item, multilevel planning with processing key NETPL → NETPL
reset, planning only within the planning horizon
4. Single-item, multilevel planning with processing key NETCH → NETCH
reset, planning also beyond the planning horizon
5. BOM change: Specify “2” for R-B430 in BOM R-F130 in plant 1000;
NETCH, NETPL, Explode BOM set
6. Single-item, multilevel planning with processing key NETCH → NETCH,
NETPL, BOM explosion reset
2008 © 2008 SAP AG. All rights reserved. 185
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 198/522
Unit 4: Executing Material Requirements Planning TSCM40
7. Enter safety stock of 50 pcs in material master R-B430 → NETCH, NETPL
set in planning file for R-B430.
Demonstration: Demonstration: Planning FileContinued
Purpose
Preparation for the exercise
System Data
System: See weekly mailClient: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. You should also demonstrate and explain how to make a planning file entry
manually (transaction “Create planning file entry” in the menu for MRP).
Planning file
entry:
NETCH NETPL OP reset BOM
explosion
Set indicators individually for R-F1##:
NETCH X
NETPL X X
Reset OP X
Re-explode
BOM
X
Finally, execute single-item multilevel planning to reset the indicators.
You could also show: Material R-F1##:
Create the planned independent requirement outside the planning horizon:
Today + 12 months, 5 pcs → NETCH set, in assembly R-B1## NETCH
not set
2. Single-item, single-level planning for R-F1##
→ NETCH reset, NETCH now set in the assembly R-B1##
186 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 199/522
TSCM40 Lesson: Setting and Executing the MRP Run
In multi-level planning, the indicators on the subsequent structure levels are
not set in the MRP planning file, but dynamically in the program.
Net Change Planning in the Planning Horizon
If only NETPL is used: The drifting of a requirement into the planning horizon is
not an MRP-relevant change. Solution: Carry out NETCH (complete time-axis)
regularly in addition to NETPL (net change planning in the planning horizon);
Or: “Plan Regularly” indicator in the MRP type together with the “Maximum
MRP Period” per MRP group.
Figure 74: Net Change Planning in the Planning Horizon
You can only restrict material requirements planning to the planning horizon if it
is necessary to accelerate MRP for performance reasons. Only those requirements
within the planning horizon are then covered by goods receipts. If you onlyexecute net change planning in the planning horizon, the system does not plan
those requirements that are outside the planning horizon.
It is important to note that, as time lapses, requirements may fall into the planning
horizon that have not yet been covered by goods receipts. As long as no other
changes relevant to MRP are made, these requirements will not be covered until
the next planning run for the whole time axis (NETCH indicator). This kind of
planning run should therefore be carried out on a regular basis.
2008 © 2008 SAP AG. All rights reserved. 187
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 200/522
Unit 4: Executing Material Requirements Planning TSCM40
A further possibility for dealing with the problem shown in the slide is to set the
Regular MRP indicator in Customizing for the MRP type of the material and to
also maintain the maximum MRP interval in the MRP group. An entry for the nextplanning date is generated automatically in the planning file. The material is
automatically included in MRP by the time the MRP date has been reached at the
latest, irrespective of the other settings in the planning file.
In order to be able to plan the changes outside the planning horizon, you must
carry out net change planning at larger intervals.
Figure 75: Executing the Planning Run Single-Item, Single-Level
During single-item, multilevel planning, the system explodes the material’s
BOM and creates and plans the dependent requirements of the assemblies and
components. If the components also have BOMs, these are also exploded and
the components are planned. This is repeated until all BOM levels have been
exploded. All materials are planned according to the parameters entered in the
initial screen of single-item, multilevel planning. Planning is carried out as
top-down planning. During multilevel planning, the MRP controller has the
option of displaying and manually changing the planning result of assemblies or
components before planning is resumed.
During single-item, single-level planning, the system generates dependent
requirements for materials at the next BOM level. “Single-item, interactive
planning” is available as a variant in which the system displays the current
planning situation before the planning run can be triggered manually.
You can check and process planning results for single-item, single-level, or
multilevel planning before saving them ( Display results before they are saved
indicator in the initial screen). The MRP controller is able to create, change,
delete, and reschedule procurement proposals before planning is resumed.
188 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 201/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 202/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 203/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 204/522
Unit 4: Executing Material Requirements Planning TSCM40
You can use the evaluation tools to easily identify the procurement proposal which
caused the time delay or exception message.
You initiate simulative planning by selecting the Simulation mode field in addition
to the usual parameters on the initial screen for single-item, multilevel planning
and choosing Enter twice.
In simulative MRP, the system stores all of the procurement proposals from the
whole BOM structure in the main memory. The planning results can be checked
and changed by the MRP controller. You also have the option of carrying out
planning again without having to leave and re-enter the transaction.
Figure 79: MRP in Simulation Mode (3)
You can analyze scheduling problems in simulative MRP by looking at the delay.
The delay for planned order 3 of the finished product shows the number of days by
which the procurement chain must be moved into the future, so that the start dates
of all the planned orders for the assemblies and components do not lie in the past.
The delays are calculated for each element as the time that the element is behind
with regards to the start date of the superior element in the BOM. The delay forthe procurement chain is the total of these individual delays. In our example,
the delay is 8 days.
Delays stemming from the planned order for the finished product are not taken
into account. These delays only come about if the correct start date for the planned
order, in relation to the requirements date, already falls in the past and there is
already a corresponding exception message for this order.
192 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 205/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 206/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 207/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 208/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 209/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 210/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 211/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 212/522
Unit 4: Executing Material Requirements Planning TSCM40
Planning indicator NETCH ____
Planning indicator NETPL ____
BOM explosion ____
Task 3:
Analyze the effect of an MRP-relevant change to the material master. In the last
step, you executed a multilevel planning run. You have therefore planned all
the components.
1. Now select the planning file entry for assembly R-B4## in the plant. Which
of the following indicators are set?
Planning indicator NETCH ____
Planning indicator NETPL ____
BOM explosion ____
2. Change the material master for the material R-B4## in plant 1000 by
entering 50 pcs as safety stock in the view MRP 2. Save the material master.
Then select the planning file entry for R-B4## in plant 1000. Which of the
following indicators are set?
Planning indicator NETCH ____
Planning indicator NETPL ____
BOM explosion ____
200 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 213/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 214/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 215/522
TSCM40 Lesson: Setting and Executing the MRP Run
Planning indicator NETCH ____ Planning indicator NETPL ____
BOM explosion ____
a) Menu path: Logistics → Production → MRP → Planning →
Single-Item, Multi-Level
Indicators set:
Planning indicator NETCH No Planning indicator NETPL No
BOM explosion No
4. Enter an additional customer requirement as follows:
Material: R-F1##
Plant: 1000
Requirements date: Today +1 month (date in day format)
Quantity: 60 pieces
Then select the planning file entry for R-F1## in plant 1000. Which of the
following indicators are set now?
Planning indicator NETCH ____ Planning indicator NETPL ____
BOM explosion ____
a) Indicators set:
Planning indicator NETCH Yes Planning indicator NETPL Yes
BOM explosion No
5. Execute multi-level requirements planning as net change planning for
material R-F1## in plant 1000. Use processing key NETPL. Then select
the planning file entry for R-F1## in plant 1000.
Which of the following indicators are set now?
Planning indicator NETCH ____ Planning indicator NETPL ____
BOM explosion ____
Give a reason for the result:
______________________________________________________
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 203
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 216/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 217/522
TSCM40 Lesson: Setting and Executing the MRP Run
Confirm with Enter. Save the BOM changes.
a) Logistics → Production → Master Data → Bills of Material → Bill of
Material → Material BOM → Change
2. Check the effect of this change to the BOM on the planning file entry.
Which of the following indicators are set now?
Planning indicator NETCH ____
Planning indicator NETPL ____
BOM explosion ____
a) Indicators set:
Planning indicator NETCH Yes
Planning indicator NETPL Yes
BOM explosion Yes
3. Carry out multilevel requirements planning for material R-F1## in plant
1000 again with the processing key NETCH and check the result again in
the planning file.
Planning indicator NETCH ____
Planning indicator NETPL ____
BOM explosion ____
a) Indicators set:
Planning indicator NETCH No
Planning indicator NETPL No
BOM explosion No
Task 3:
Analyze the effect of an MRP-relevant change to the material master. In the last
step, you executed a multilevel planning run. You have therefore planned all
the components.
1. Now select the planning file entry for assembly R-B4## in the plant. Which
of the following indicators are set?
Planning indicator NETCH ____
Planning indicator NETPL ____
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 205
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 218/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 219/522
TSCM40 Lesson: Setting and Executing the MRP Run
159 Exercise 9: Simulative MRP
Exercise Duration: 20 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Execute the MRP run in simulation mode
• In particular, analyze situations with scheduling problems due to the delay
and implement measures to correct the problem in simulation mode.
Business Example
As a member of the project team, you familiarize yourself with the functions of simulative material requirements planning.
Task 1:
In the previous exercise, you created and planned a customer requirement of 60
pieces of the pump R-F1## for the date today + 1 month. This means that you
fulfilled the requirement with a planned order.
Hint: If you did not carry out the previous exercise on the planning file
entry, create the above mentioned customer requirement now (make sure
that the requirement type is KEV) and then execute multi-level planning.
Note the change in the stock/requirements list:
1. Make a note of the customer requirement number:
______________________________________________________
2. Write down the number of the corresponding planned order:
______________________________________________________
Task 2:
Analyze the planned order as far as the dates are concerned.
1. Was the planned order for the customer requirement created on time?
______________________________________________________
(Note that the availability date of a planned order always falls on a working
day, which is not necessarily the case for the customer requirements date.)
2. What is the start date of this planned order?
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 207
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 220/522
Unit 4: Executing Material Requirements Planning TSCM40
______________________________________________________
What consequences does this have for procuring the components for this
planned order?
_____________________________________________________
3. Execute the order report function from the stock/requirements list for
this planned order. Based on this evaluation, do you foresee problems in
fulfilling the sales order?
_____________________________________________________
Task 3:
Now execute single-item, multi-level planning in simulation mode for material
R-F1## in plant 1000. To do this, select the Simulation mode indicator in theMRP initial screen.
1. Make sure that the indicator Also Plan Unchanged Components is set, and
that you use planning mode 3 in this case.
Start the planning run by choosing Enter twice.
Hint: Do not exit the transaction.
Task 4:
Evaluate the planning results: After you have executed multilevel requirements
planning, display the planning results on the material overview screen.
Select the planning result for finished product R-F1## by choosing the function
1st material.
1. Examine the planned order in the individual customer segment that you
already analyzed above. Is a delay displayed for this planned order?
______________________________________________________
By how many working days is the planned order delayed due to the lower
level assemblies and components?
____________________________________________ working days
2. Select the planned order and click on the order structure button. Select the
planned order and choose the Expand Subtree button. Note down the two
procurement elements that cause the longest delays in the following table:
Continued on next page
208 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 221/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 222/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 223/522
TSCM40 Lesson: Setting and Executing the MRP Run
Solution 9: Simulative MRP
Task 1:
In the previous exercise, you created and planned a customer requirement of 60
pieces of the pump R-F1## for the date today + 1 month. This means that you
fulfilled the requirement with a planned order.
Hint: If you did not carry out the previous exercise on the planning file
entry, create the above mentioned customer requirement now (make sure
that the requirement type is KEV) and then execute multi-level planning.
Note the change in the stock/requirements list:
1. Make a note of the customer requirement number:
______________________________________________________
a) Customer requirement number: Varies
2. Write down the number of the corresponding planned order:
______________________________________________________
a) Planned order number: Varies
Task 2:
Analyze the planned order as far as the dates are concerned.
1. Was the planned order for the customer requirement created on time?
______________________________________________________
(Note that the availability date of a planned order always falls on a working
day, which is not necessarily the case for the customer requirements date.)
a) Planned order on time: Yes, the planned order was created on time.
If the customer requirements date lands on a holiday or a weekend,
the planned order will have an availability date that is before the
customer requirements date.
2. What is the start date of this planned order?
______________________________________________________
What consequences does this have for procuring the components for this
planned order?
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 211
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 224/522
Unit 4: Executing Material Requirements Planning TSCM40
_____________________________________________________
a) Planned order start date: Varies, about one week after the current
date.
Consequences for procuring the components: The time available for
procuring the components is very tight. If the components are not
already in stock, there could be problems meeting the order date.
3. Execute the order report function from the stock/requirements list for
this planned order. Based on this evaluation, do you foresee problems in
fulfilling the sales order?
_____________________________________________________
a) Problems foreseen: Yes, problems can be expected.
Procurement of the subordinate components occurs with
procurement elements that contain exception messages.
Task 3:
Now execute single-item, multi-level planning in simulation mode for material
R-F1## in plant 1000. To do this, select the Simulation mode indicator in the
MRP initial screen.
1. Make sure that the indicator Also Plan Unchanged Components is set, and
that you use planning mode 3 in this case.
Start the planning run by choosing Enter twice.
Hint: Do not exit the transaction.
a) Menu path: Logistics → Production → MRP → Planning →
Single-Item, Multi-Level
Task 4:
Evaluate the planning results: After you have executed multilevel requirements
planning, display the planning results on the material overview screen.
Select the planning result for finished product R-F1## by choosing the function
1st material.
1. Examine the planned order in the individual customer segment that you
already analyzed above. Is a delay displayed for this planned order?
______________________________________________________
By how many working days is the planned order delayed due to the lower
level assemblies and components?
Continued on next page
212 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 225/522
TSCM40 Lesson: Setting and Executing the MRP Run
____________________________________________ working days
a) Delay: Yes, a delay is displayed.
Length of the total delay of the planned order: Varies, around 15
working days.
2. Select the planned order and click on the order structure button. Select the
planned order and choose the Expand Subtree button. Note down the two
procurement elements that cause the longest delays in the following table:
MRP element Number of MRP
element
Material Delay (working
days)
Return to the display of the Planning results: Individual lines for material
R-F1##.
Hint: Do not leave the transaction.
a) Longest delay:
MRP element Number of
MRP element
Material Delay (working
days)
PLOrd Varies R-B3## Varies, around15 days
PLOrd Varies R-B4## Varies, around
11 days
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 213
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 226/522
Unit 4: Executing Material Requirements Planning TSCM40
Task 5:
Now reschedule the planned order into the future: Select the planned order you
examined and choose the Reschedule procurement proposal button. Using the
displayed (availability) date of the planned order, postpone the planned order
by the number of working days that was displayed as the delay time for the
planned order (see above). Enter the appropriate new order finish date for the
planned order in the new field.
Hint: To help you do this, you can use F4 and the plant calendar in the
ReschDate field. The new end date is calculated as previous end date +
delay time of planned order, calculated in working days.
Make sure that you do not use the current date as the starting point for
rescheduling by mistake.
1. Make sure that the planned order is firmed. To do this, display the detail
screen for the relevant planned order by calling it from the list. Check
whether the indicator is set in the Firmed field. Return to the list by choosing
the Copy procurement proposal button.
Hint: Do not leave the transaction.
a) No solution required
Task 6:
Display the stock/requirements list for material R-F1## in plant 1000 in a
parallel session.
1. Is the changed end date displayed for the planned order that you have just
edited?
________________________________________________________
Give a reason for the result:
________________________________________________________
a) Modified end date: No, the new date is not displayed.
Reason: Simulative requirements planning occurs in the main
memory. As long as the planning run is not saved, the data in the
database remains unchanged.
Continued on next page
214 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 227/522
TSCM40 Lesson: Setting and Executing the MRP Run
Task 7:
You should now execute planning for the planned order again: The assemblies
and components that lie below the planned order that you have rescheduled, have
not yet been planned.
Return to the session with the simulation results. Select the planned order that you
have just processed and choose Execute planning run.
1. By how many working days is the planned order now delayed due to the
assemblies and components?
____________________________________________ working days
a) Total delay now: 0 working days
2. Save the planning result (and exit the transaction).
a) No solution required
Task 8:
Call up the stock/requirements list for material R-F1## in plant 1000 again
(if necessary, refresh the list).
1. Is the modified end date now displayed for the planned order you just edited?
____________________________________________________________
Give a reason for the result:
____________________________________________________________
____________________________________________________________
a) Modified end date now displayed: Yes, the modified end date is now
displayed.
Reason: When you save the planning run, the planning results are
saved to the database.
Task 9:
Then call the stock/requirements list for R-F1##, plant 1000 and execute the
“order report” function for this planned order.
1. Do the assemblies and components still show rescheduling messages?
____________________________________________________________
a) Rescheduling messages for assemblies and components: No
(Only the exception message “Opening date in the past” appears)
2008 © 2008 SAP AG. All rights reserved. 215
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 228/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 229/522
TSCM40 Lesson: Firming
Lesson:
169
Firming
Lesson Duration: 90 Minutes
Lesson Overview
When you firm planned orders you can protect a master production schedule from
changes that are made automatically during material requirements planning.
Lesson Objectives
After completing this lesson, you will be able to:
• Firm a planned order in different ways
• Use firming in requirements planning
Space for notes
Business Example
No more planning is to take place in the short term. To ensure this, the planned
orders are firmed.
Firming
Firming: Philosophy
Firming is possible for both MRP parts (P MRP type) and for master schedule
items (M MRP type).
Mention that master schedule items will be dealt with in the last chapter.
2008 © 2008 SAP AG. All rights reserved. 217
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 230/522
Unit 4: Executing Material Requirements Planning TSCM40
Figure 82: Firming: Philosophy
You can use the firming period to protect the master production schedule for
master schedule items (in the MPS run) and for non-master schedule items (in the
MRP run) from being changed automatically in the near future and therefore
stabilize planning. Within the firming period, which is defined individually for
each material, procurement proposals are no longer changed automatically during
the MRP run.
You should define the firming period on the basis of the total lead time of the
material.
In the above example, the order finish date of the planned order, E1, lies one day
before the end of the firming period. The system therefore treats it as firmed
and does not automatically reschedule it. The master production schedule for
the components is therefore stabilized.
You can define the firming period using the planning time fence or a manual
firming date. Planned orders can also be firmed and unfirmed manually.
The system will draw your attention to any possible changes to the masterproduction schedule in the form of an exception message in the MRP list. It is
then up to the MRP controller to process these changes.
218 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 231/522
TSCM40 Lesson: Firming
Figure 83: Firming a Planned Order
If a planned order is changed manually, the system automatically sets the firmed
indicator for this planned order. This means that the header data of the planned
order will remain unchanged in the next planning run.
If a component in a planned order is changed manually, the system also sets the
firmed indicator for the components. This means that the components of the
planned order will not be changed in the next planning run.The firming indicators for the planned order or the components of the planned
order can be changed manually.
If the planned orders are flagged as firmed through the definition of a firming
period in the stock/requirements list and the MRP list, this occurs independently
of the firming indicator for the planned order or its components.
By resetting the conversion indicator in the planned order, you can prevent the
planned order being converted into a production order or purchase requisition.
2008 © 2008 SAP AG. All rights reserved. 219
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 232/522
Unit 4: Executing Material Requirements Planning TSCM40
Figure 84: Firming Period and Firming Types
The firming type determines how the procurement proposals (especially planned
orders and purchase requisitions) are to be firmed for the planning run and in
which order they are to be scheduled within the firming period.
You specify the firming procedure to be used for each material using the the MRP
type. The firming type is defined in Customizing for the MRP type.
You can use firming for materials planned with both master production scheduling
and material requirements planning. Corresponding MRP types are available
for this in the standard system.
220 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 233/522
TSCM40 Lesson: Firming
Figure 85: Overview of Firming Types
• With firming type “0”, no firming period is effective.
• With firming types “1” and “2”, “automatically firmed” indicates that
any procurement proposals inside the firming period will now be firmed
automatically. They can therefore no longer be changed by the planning run,
only manually. Likewise, all procurement proposals that are moved into the
planning time fence are firmed automatically.
• Firming type “1”: The planning run covers all new shortages that haveoccurred within the planning time fence at the end of the firming period.
• Firming type “2”: The planning run does not cover any new shortages that
have occurred within the planning time fence.
• Firming type “3”: All procurement proposals that have not been manually
firmed within the planning time fence are moved to the end of the firming
period. If new shortages occur within the firming period, they are covered at
the end of the firming period.
• Firming type “4”: All procurement proposals that have not been manually
firmed within the planning time fence are deleted. If new shortages occur
within the firming period, they are not covered.
Planning time fence
Manual firming date
In contrast to the planning time fence, the manual firming date is also effective for
materials with MRP types with firming type 0, or without a firming type.
2008 © 2008 SAP AG. All rights reserved. 221
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 234/522
Unit 4: Executing Material Requirements Planning TSCM40
Figure 86: Planning Time Fence
You can use the firming period to protect the master production schedule for
a material from being automatically changed in the near future. Procurement
proposals within the firming period are no longer changed automatically during the
MRP run. You can define the firming period using the planning time fence. The
system calculates the finish date of the firming period on the basis of the MRP date.
You can specify the planning time fence either for each material in the materialmaster record or using the MRP group assigned to the material master. The length
of the planning time fence (in working days) should be based on the total lead time
of the material. The planning time fence is only effective in connection with
an MRP type that has a firming type.
The firming type determines how the procurement proposals are firmed for the
planning run and how the dates are set within the planning time fence. Existing
procurement proposals which slip into the planning time fence are firmed
automatically with firming type 1, as shown in the graphic, as soon as the date
of the procurement proposal falls at least one day before the end date of the
planning time fence.
The date for new purchase requisitions that were created within the planning time
fence and not created manually, is postponed to the final date of the planning time
fence with firming type 1. This means that these new procurement proposals
are not firmed.
222 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 235/522
TSCM40 Lesson: Firming
Figure 87: Manual Firming Date
You can also define the firming period by manually entering a date lying in
the future - that is, the “manual firming date”. The manual firming date causes
automatic firming of the procurement proposals for materials with firming types 1
and 2 and lie before the manual firming date.
Unlike the planning time fence, materials without a firming type (firming type 0)are treated like materials with firming type 1 as far as the manual firming date is
concerned. This means that the procurement proposals that lie before the manual
firming date are firmed, and new procurement proposals are moved to the manual
firming date. If you have set a manual firming date and a planning time fence is
active, the firming period is determined by the end of the planning time fence,
providing this date is later than the manual firming date. If the manual firming
date is the later of the two dates, then this defines the firming period. You set and
reset the manual firming date in the stock/requirements list, in the planning results,
or in interactive single-item planning. You can apply this function in material
requirements planning, master production scheduling, or long-term planning.
Demonstration: Firming Settings
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
2008 © 2008 SAP AG. All rights reserved. 223
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 236/522
Unit 4: Executing Material Requirements Planning TSCM40
User ID: Own user ID
Password: Own password
Set up instructions: Standard1. Display the Customizing for MRP types:
Customizing: Production – Material Requirements Planning – Master Data
– Check MRP Types
• Explain the firming type field and the difference between the
characteristics PD, P1, P2, and so on.
2. Display the planning time fence in the material master of R-F2## (MRP 1)
3. Show how it is possible to define a planning time fence in Customizing
for the MRP groups.
Customizing: Production – Material Requirements Planning – MRP Groups – Carry Out Overall Maintenance of MRP Groups
or
Customizing: Production – Material Requirements Planning – Planning –
MRP Calculation – Define Planning Time Fence and Roll Forward Period
Demonstration: Firming a Planned Order
PurposePreparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Demonstrate (at least) the content of the exercise on firming.
Roll Forward Period
You use the roll forward period to delete firmed but out-of-date planned orders in
order to clean up or update planning.
You activate the function in Customizing for the MRP type.
Customizing: Production – Material Requirements Planning – Master Data –
Check MRP Types
224 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 237/522
TSCM40 Lesson: Firming
You define the start and the length of the roll forward period in Customizing for
the MRP group:
Customizing: Production – Material Requirements Planning – MRP Groups –
Carry Out Overall Maintenance of MRP Groups → Planning Time Fence
or
Customizing: Production – Material Requirements Planning – Planning – MRP
Calculation – Define Planning Time Fence and Roll Forward Period
Figure 88: Roll Forward Period
As well as the planning time fence, you can also maintain the roll forward period
in the MRP group. You can use the roll forward period to delete firmed but
out-of-date planned orders in order to automatically update the production master
schedule.
The Roll Forward indicator in Customizing for the MRP type controls whether or
not the roll forward mechanism is applied for a material.
All firmed planned orders with an end date within the roll forward period are
deleted in the planning run and either new planned orders are created with suitable
dates or, if the corresponding firming type applies, they are moved to the end of
the planning time fence.
2008 © 2008 SAP AG. All rights reserved. 225
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 238/522
Unit 4: Executing Material Requirements Planning TSCM40
226 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 239/522
TSCM40 Lesson: Firming
177 Exercise 10: Firming
Exercise Duration: 20 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Use firming to restrict requirements planning
Business Example
Since some end products including pump R-F2## are frequently ordered by
customers at short notice, you want to use firming to stabilize requirements
planning in the short term. New customer requirements do not automatically leadto new (on time) procurement elements.
Hint: In this exercise, you will work with material R-F2## in plant 1000,
and not with R-F1##.
Task 1:
In material R-F2## in plant 1000 on the MRP views 1 and 3, maintain a firming
horizon of 20 (working) days and the strategy group 40 and save your changes.
1. Ignoring any previous entries that have been made from the demand
management menu for material R-F2## in plant 1000 create the following
active VSF planned independent requirements in planned requirements
version 00 (use W (week) for the planning period):
Current
week + 1
Current
week + 2
Current
week + 3
Current
week + +4
Current
week + 5
20 10 10 10 10
Confirm any warning messages that may appear with Enter and save the
requirements.
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 227
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 240/522
Unit 4: Executing Material Requirements Planning TSCM40
Task 2:
Execute single-item, single-level planning (and not multi-level planning) using
the preset parameters for material R-F2## in plant 1000 and call up the current
stock/requirements list for this material.
Menu path: Logistics → Production → Production Planning → MPS → MPS
→ Single-Item, Single-Level
1. Is a planning time fence active for this material (does the system display a
corresponding time fence)? Why (not)?
______________________________________________________
2. Check that a planning time fence has been entered in the material
master R-F2## for the plant 1000. Why is no firming active?
______________________________________________________
Task 3:
Convert the material using the MRP type to planned MRP with fixing type 1 in
order to satisfy the production demands: To do this, go the the view MRP 1 of the
material master R-F2## in plant 1000 and change the value of the field MRP type
to P1. Save your changes. Take another look at the (refreshed) stock/requirements
list for material R-F2## in plant 1000.
1. Does the system display a planning time fence? _____________________
2. To which date is the end of the planning time fence set?
______________________________________________________
Why are the planned orders within the planning time fence flagged as firmed?
______________________________________________________
3. Choose Display Element to display the header screen of a firmed planned
order inside the planning time fence. Is the firming indicator for planned
order set?_________________
Task 4:
A sales order is received for 100 pieces of material R-F2##, delivering plant 1000.Requirements date is today’s date + 3 weeks.
1. From the demand management menu, create a corresponding customer
requirement (use the data specified for this customer requirement) and then
save it.
2. Now call the stock/requirements list and analyze the (consumption) situation.
For which date is there a material shortage, in other words, on which date
does the quantity available for planning fall below zero?
Continued on next page
228 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 241/522
TSCM40 Lesson: Firming
______________________________________________________
Task 5:Execute interactive single-item planning for material R-F2## in plant 1000.
1. Call the transaction. When planning is called, the system reads the current
planning situation. You have to trigger planning manually by choosing
Execute Planning. After you have executed this function, you can see the
planning results that have, at this point in time, not yet been saved to the
database.
2. On which date is the material shortage corrected, in other words, on which
date is a planned order created so that the available quantity is greater than
or equal to zero?
________________________________
What is the number of this planned order?
_________________
3. Why is the shortage situation determined above not covered on time?
______________________________________________________
4. Select the planned order, and display the exceptions by choosing Element
details (to the very left of the planned order row).
Go back, select the planned order and execute the function Reschedule Proc.
Proposal (button to the bottom left).
What is the receipt due date for the planned order now?
______________________________________________________
Save the planning results.
Task 6:
Call the stock/requirements list for material R-F2## in plant 1000.
1. View the planned order that you have rescheduled, the number of which you
have noted. Is the firming indicator set in this planned order?____________
Give a reason for your result:
___________________________________________________
2. In the stock/requirements list, set the manual firming date for 3 working
days later than the end of the planning time fence . Refresh the list.
Which firming date takes effect?
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 229
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 242/522
Unit 4: Executing Material Requirements Planning TSCM40
__________________
Task 7:
1. Increase the customer requirement that you created before by 15 pieces.
Save and then execute single-item, single-level planning again. Analyze
the planning result: When has an additional procurement element for the
increased quantity of the sales order been scheduled?
__________________________________________________________
2. Then clean up material R-F2## as described at the beginning of exercise
5. Note that first you must reverse the firmings (for the material in the
stock/requirements list - you may have to do this manually).
230 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 243/522
TSCM40 Lesson: Firming
Solution 10: Firming
Task 1:
In material R-F2## in plant 1000 on the MRP views 1 and 3, maintain a firming
horizon of 20 (working) days and the strategy group 40 and save your changes.
1. Ignoring any previous entries that have been made from the demand
management menu for material R-F2## in plant 1000 create the following
active VSF planned independent requirements in planned requirements
version 00 (use W (week) for the planning period):
Current
week + 1
Current
week + 2
Current
week + 3
Current
week + +4
Current
week + 5
20 10 10 10 10
Confirm any warning messages that may appear with Enter and save the
requirements.
a) Menu path: Logistics → Production → Master Data → Material
Master → Material → Change → Immediately
Menu path: Logistics → Production → Production Planning →
Demand Management → Planned Independent Requirements → Create
Task 2:Execute single-item, single-level planning (and not multi-level planning) using
the preset parameters for material R-F2## in plant 1000 and call up the current
stock/requirements list for this material.
Menu path: Logistics → Production → Production Planning → MPS → MPS
→ Single-Item, Single-Level
1. Is a planning time fence active for this material (does the system display a
corresponding time fence)? Why (not)?
______________________________________________________
a) Planning time fence active: No2. Check that a planning time fence has been entered in the material
master R-F2## for the plant 1000. Why is no firming active?
______________________________________________________
a) Reason: The effect of the planning time fence is controlled by
the MRP type in the material master. The MRP type PD in the
material master R-F2## determines that no automatic firming is
to take place.
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 231
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 244/522
Unit 4: Executing Material Requirements Planning TSCM40
Task 3:
Convert the material using the MRP type to planned MRP with fixing type 1 in
order to satisfy the production demands: To do this, go the the view MRP 1 of the
material master R-F2## in plant 1000 and change the value of the field MRP type
to P1. Save your changes. Take another look at the (refreshed) stock/requirements
list for material R-F2## in plant 1000.
1. Does the system display a planning time fence? _____________________
a) Planning time fence displayed: Yes
2. To which date is the end of the planning time fence set?
______________________________________________________
Why are the planned orders within the planning time fence flagged as firmed?
______________________________________________________
a) End of the planning time fence: Varies (Today + 20 working days)
Planned orders within the planning time fence firmed: The planned
orders within the planning time fence are flagged as firmed,
because the MRP type P1, which you have entered in the material
master, defines that procurement proposals that fall within the
planning time fence are firmed automatically.
3. Choose Display Element to display the header screen of a firmed planned
order inside the planning time fence. Is the firming indicator for planned
order set?_________________
a) Indicator for firming planned order: No
Task 4:
A sales order is received for 100 pieces of material R-F2##, delivering plant 1000.
Requirements date is today’s date + 3 weeks.
1. From the demand management menu, create a corresponding customer
requirement (use the data specified for this customer requirement) and then
save it.
a) Menu path: Logistics→
Production→
Production Planning→
Demand Management → Customer Requirements → Create
2. Now call the stock/requirements list and analyze the (consumption) situation.
For which date is there a material shortage, in other words, on which date
does the quantity available for planning fall below zero?
Continued on next page
232 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 245/522
TSCM40 Lesson: Firming
______________________________________________________
a) Date quantity available for planning below zero: The available
quantity falls below zero on the requirements date of the customer
requirement.
Task 5:
Execute interactive single-item planning for material R-F2## in plant 1000.
1. Call the transaction. When planning is called, the system reads the current
planning situation. You have to trigger planning manually by choosing
Execute Planning. After you have executed this function, you can see the
planning results that have, at this point in time, not yet been saved to the
database.
a) No solution is required.
2. On which date is the material shortage corrected, in other words, on which
date is a planned order created so that the available quantity is greater than
or equal to zero?
________________________________
What is the number of this planned order?
_________________
a) Available quantity greater than or equal to zero: The available
quantity is greater than or equal to zero at the end of the planningtime fence.
Planned order number: This varies
3. Why is the shortage situation determined above not covered on time?
______________________________________________________
a) Why not on time: Behind the MRP type P1 is the firming type 1.
For firming type 1, recent shortage situations within the planning
time fence are not covered with a new procurement element until
the end of the planning time fence. You can perform rescheduling
manually at a later stage.
4. Select the planned order, and display the exceptions by choosing Element
details (to the very left of the planned order row).
Go back, select the planned order and execute the function Reschedule Proc.
Proposal (button to the bottom left).
What is the receipt due date for the planned order now?
______________________________________________________
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 233
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 246/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 247/522
TSCM40 Lesson: Firming
__________________________________________________________
a) Menu path: Logistics → Production → MRP → Planning →
Single-Item, Single-Level
When an additional procurement element is scheduled: The date
varies. The additional procurement element is scheduled for the
end of the effective planning time fence, that is, on the manual
firming date that you entered previously.
2. Then clean up material R-F2## as described at the beginning of exercise
5. Note that first you must reverse the firmings (for the material in the
stock/requirements list - you may have to do this manually).
a) No solution required.
2008 © 2008 SAP AG. All rights reserved. 235
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 248/522
Unit 4: Executing Material Requirements Planning TSCM40
Lesson Summary
You should now be able to:• Firm a planned order in different ways
• Use firming in requirements planning
236 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 249/522
TSCM40 Unit Summary
Unit Summary
You should now be able to:
• Explain the principle of multilevel requirements planning
• Go through the principle of external procurement and the document flow
• Make the necessary settings in Customizing
• Make the necessary settings in the master data
• Trigger single-item planning
• Trigger total planning
• Interpret the planning file
• Execute the MRP run in simulation mode
• Firm a planned order in different ways
• Use firming in requirements planning
2008 © 2008 SAP AG. All rights reserved. 237
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 250/522
Unit Summary TSCM40
238 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 251/522
TSCM40 Test Your Knowledge
189Test Your Knowledge
1. In material requirements planning you can calculate the dates for multi-level
production automatically.
Determine whether this statement is true or false.
□ True
□ False
2. Which of the following settings have to be made in order to execute a
material requirements planning run for a material?
Choose the correct answer(s).
□ A MRP activated in general
□ B Material status allows MRP
□ C MRP views have been created
2008 © 2008 SAP AG. All rights reserved. 239
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 252/522
Test Your Knowledge TSCM40
190Answers
1. In material requirements planning you can calculate the dates for multi-level
production automatically.
Answer: True
Material requirements planning for multi-level production is done by means
of backward scheduling. This determines when the respective assemblies
and components have to be available so that the deadline for the finished
product can be met.
2. Which of the following settings have to be made in order to execute a
material requirements planning run for a material?
Answer: A, B, C
MRP must be activated in Customizing in general (for each plant). The
material status can block a material for requirements planning globally or on
a plant-by-plant basis. When you create MRP views the system generates
an entry in the planning file.
240 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 253/522
Unit 5 191 Technical Processes in Requirements
Planning
Discuss the individual steps of the MRP run in detail: Net requirements
calculation, lot-size calculation, procurement types, scheduling, BOM explosion
and routing selection. Look at the relevant control parameters and the
corresponding Customizing settings.
Unit Overview
The MRP run consists of a number of individual steps that take place in the
system one after the other. The planning result depends on the various settings
for these different steps.
The first step is the net requirements calculation. This determines if a shortage will
occur for a certain material and if so, when. As well as the requirements, safetytime and quantity buffers can be included in the net requirements calculation.
In the next step, the lot-size is calculated: The lot size for the procurement
element is determined on the basis of the shortage quantity. You define the lot-size
procedure in Customizing and assign it to a material in the material master record.
Since materials produced in-house are scheduled differently to those procured
externally, you must determine the procurement type before scheduling begins.
Scheduling itself is more complicated for materials produced in-house than for
those procured externally, since two scheduling types – basic date scheduling and
lead time scheduling – have to be coordinated.
The final step is to explode the BOM. First, however, you need to determine the
BOM and the change status of the BOM to be exploded. The selection of BOM and
routing is usually controlled by selection IDs. These are defined in Customizing.
Unit Objectives
After completing this unit, you will be able to:
• Understand the net requirements calculation
• Work with safety stocks
2008 © 2008 SAP AG. All rights reserved. 241
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 254/522
Unit 5: Technical Processes in Requirements Planning TSCM40
• Use the dynamic safety stock
• Use the safety time
• Use static lot-sizing procedures
• Use lot-sizing by period
• Use optimizing lot-sizing procedures
• Make corresponding settings in Customizing
• Use the procurement type for in-house production
• Use the procurement type for external procurement
• Use the quota arrangement
• Describe scheduling for in-house production
• Describe scheduling for external procurement
• Understand multilevel backward scheduling• Make corresponding settings in Customizing
• Set the parameters for selecting the BOM
• Set the parameters for selecting the routing
• Make corresponding settings in Customizing
Unit Contents
Lesson: Net Requirements Calculation ... .. .. .. .. ... .. .. ... ... .. .. .. .. ... ... 244Demonstration: Definition of the Net Stock . .. .. .. .. .. .. .. .. .. .. .. .. .. .. 246Demonstration: Rescheduling Horizon ..................................247
Demonstration: Safety Stock Partially Available .......................250Demonstration: Dynamic Safety Stock .. .. .. ... .. ... .. ... .. .. .. .. ... ... 254Demonstration: Safety Time ..............................................258
Exercise 11: Net Requirements Calculation and Safety Stock . . .. . .. 261Lesson: Lot-Size Calculation .... ... ... ..... ... ... .... ... .... .... ... ... ... ..... 272
Demonstration: Settings for Lot-Sizing Procedure .. .. .. .. .. .. .. .. .. .. 273
Demonstration: Planning Calendar ... .. .. .. .. ... .. .. ... ... .. .. .. .. ... .. .277Demonstration: Rounding ... ... ... ..... ... ... .... ... .... .... ... ... .... ... 281Demonstration: Special Lot-Sizing Procedures ........................282
Exercise 12: Lot-Size Calculation ... ... .. .. .. ... .. .. ... .. ... .. .. .. .. ... ..287Lesson: Procurement Types .... ... ... ..... ... ... .... ... .... .... ... ... ... .... .294
Demonstration: Quota Arrangement .. .. .. .. ... .. .. ... .. ... .. .. .. .. ... ..297Exercise 13: Procurement Type and Quota Arrangement ............ 299
Lesson: Scheduling.............................................................307Demonstration: Basic Scheduling ... .. .. .. .. ... .. .. ... .. ... .. .. .. .. ... .. 311
Demonstration: Lead Time Scheduling. .. .. .. ... .. ... .. ... .. .. .. .. ... ... 315
Demonstration: Reduction and Scheduling Adjustment .. .. .. .. .. .. .. 318Demonstration: Order Dates with Lead Time Scheduling andPostponing the Dependent Requirement Dates .. .. .. .. .. .. .. .. .. .. .. .321Exercise 14: Scheduling.. .... ... ... ..... ... ... .... ... .... .... ... ... .... ... 323
Lesson: BOM and Routing Selection... ... .. .. .. .. ... .. ... .. ... .. .. .. .. ... ... 335
242 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 255/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 256/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Lesson:
193
Net Requirements Calculation
Lesson Duration: 90 Minutes
Lesson Overview
The net requirements calculation is the first step that is carried out in material
requirements planning. Various buffers are available to work round unexpected
bottlenecks.
Lesson Objectives
After completing this lesson, you will be able to:
• Understand the net requirements calculation
• Work with safety stocks
• Use the dynamic safety stock
• Use the safety time
Space for notes
Business ExampleThe net requirements calculation is provided with safety stocks and safety times in
order to work round unexpected bottlenecks.
244 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 257/522
TSCM40 Lesson: Net Requirements Calculation
Figure 89: Overview: Net Requirements Calculation
The net requirements calculation is the first step in the material requirements
planning run and is executed at plant level or at MRP area level. During this
process, the system checks whether the requirements can be covered by the
available warehouse stock and fixed dispatched receipts. If shortages exist, the
system creates a procurement proposal.
Net Requirements Calculation
As well as the stock, the firmed receipts within the rescheduling horizon flow
into the net requirements calculation. The rescheduling horizon is defined for
each plant or MRP group and is calculated based on the end of the replenishment
lead time (for materials with lot size dependent in-house production times, the
replenishment lead time is determined on the basis of the base quantity.
2008 © 2008 SAP AG. All rights reserved. 245
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 258/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Figure 90: Net requirements calculation
In MRP, a net requirements calculation is executed in the planning run to determine
whether a material shortage exists for a certain material. In addition, stock and
fixed receipts that currently exist within the rescheduling horizon (purchase
orders, production orders, fixed purchase requisitions, and planned orders...) are
compared with the safety stock and requirements. The result of this comparison
is the quantity available for planning.
The stock available for planning combines the following stock from all storage
locations that belong to this plant or MRP area and are not excluded from
MRP or planned separately: unrestricted-use stock, stock in quality inspection,
unrestricted-use consignment stock and consignment stock in quality inspection.
In the Customizing activity Define Availability of Stock in Transfer/Blocked
Stock/Unrestricted Stock you can define for each plant whether the stock in
transfer from plant-to-plant stock transfers is included in the plant stock available
for planning without stock transport orders, or the blocked stock, or the restricted
stock for batches.
If the quantity available for MRP is less than zero, a material shortage exists. MRP
reacts to material shortages by creating new procurement proposals, that is, by
creating purchase requisitions or planned orders, depending on the procurement
type. The proposed procurement quantity results from the lot-sizing procedurethat is set in the material master.
Demonstration: Definition of the Net Stock
Purpose
Preparation for exercise
246 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 259/522
TSCM40 Lesson: Net Requirements Calculation
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Show where net stock is defined/configured.
Customizing: Production – Material Requirements Planning – Planning –
MRP Calculation –.Stocks – Define Availability of Stock in Transfer/Blocked
Stock/Restricted Stock
Demonstration: Rescheduling Horizon
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Display the definition of the rescheduling horizon in Customizing at plant
or MRP group level
or
Customizing: Production – Material Requirements Planning – Planning –
MRP Calculation – Define Rescheduling Check
and explain its significance.
Hint: The rescheduling check is dealt with in more detail in the unit
on processing the MRP results.
Net Requirements Calculation Time Line
Explain the net calculation time line and point out how this is represented in the
stock/requirements list.
2008 © 2008 SAP AG. All rights reserved. 247
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 260/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Figure 91: Net Requirements Calculation Time Line
The quantity available for planning consists of stock available for planning and the
fixed receipts (purchase orders, production orders, firmed planned orders, firmed
purchase requisitions, and so on) minus the safety stock and the requirements.
This is calculated for every requirements date along the time axis. If the quantity
available for planning is less than zero, a material shortage exists.
If there is a material shortage, the system determines the net requirement (shortagequantity).
The lot-size calculation is executed on the basis of the net requirements and
a calculation is made for a procurement proposal (planned order, purchase
requisition, or schedule lines).
Overview: Quantity and Time Buffers
• Safety stock
• Safety stock partially available
• Dynamic safety stock
• Safety time
There are two types of buffer that you can plan in order to take into account
uncertainties in the development of demands:
• Quantity buffer: Safety stock, partially available safety stock, dynamic
safety stock
• Time buffer: Safety time
248 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 261/522
TSCM40 Lesson: Net Requirements Calculation
Safety stock
A safety stock that was entered in the material master can be used as a requirement
element and included in the next MRP run.
Figure 92: Safety Stock
For every requirement for which the available stock for planning is insufficient,the system creates a procurement element in order to procure (at least) the quantity
that the available stock for planning is unable to cover.
You can define the safety stock level per plant in the MRP 2 view of the material
master or per MRP area in the MRP area segment. Safety stock reduces the stock
available for planning.
When the inventory is lower than the defined safety stock level, the system
replenishes the safety stock during the planning run. Note that this is also the case
if the safety stock is only slightly below the defined safety stock level.
This type of safety stock is independent of the requirement quantities and is
therefore static.
The safety stock is displayed in a separate line in the stock/requirements list and in
the MRP list.
Safety Stock Partially Available
Making safety stock partially available avoids the need for frequent, small quantity
procurement transactions, particularly if the shortfalls are usually only minimal.
2008 © 2008 SAP AG. All rights reserved. 249
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 262/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Figure 93: Safety Stock Partially Available
You can define the proportion of safety stock that is available for planning for
each MRP group in the Customizing activity Define Safety Stock Availability. It is
defined as a percentage of the safety stock level that is specified in the material
master.
A new order proposal is not created until stock falls below the available portion of
safety stock. This order proposal replenishes stock up to (at least) the safety stock
level. This means that no individual order proposals are created for very smallmaterial shortages. This reduces the amount of administrative work and planning.
Demonstration: Safety Stock Partially Available
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mailUser ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Change material R-F1##: Enter safety stock 10 pcs (MRP 2), lot-sizing
procedure exact.
2. Enter warehouse stock: 20 pieces
3. Call the stock/requirements list for material R-F1##:
250 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 263/522
TSCM40 Lesson: Net Requirements Calculation
→ The safety stock is displayed and is entered as a requirement element
in the net requirements calculation.
4. Enter planning requirements, beginning with the current week + 2: 2, 4, 6,
1, 1, 1, 1, 1 pcs
5. Execute material requirements planning for R-F1##. Display the result:
→ Every time the requirements exceed the safety stock level, the system
generates a receipt element to cover the amount of the shortfall.
6. Definition of partially available safety stock in the Customizing for MRP
groups
or:
Customizing: Production – Material Requirements Planning – Planning –
MRP Calculation – Stocks – Define Safety Stock Availability
Enter 50%, and execute the planning run again. A new receipt element is
created up to the amount of the safety stock only when there is a shortfall in
the partially available safety stock. No further planning is executed.
7. Remove the setting in Customizing.
Figure 94: Dynamic Safety Stock (1)
Using the range of coverage calculation, you can determine a dynamic level of
safety stock that is oriented to requirements.
During every planning run, the system checks whether the available quantity is
below the minimum stock level. If this is the case, the system creates an order
proposal in order to increase the available quantity to at least the target stock
level (dynamic safety stock).
2008 © 2008 SAP AG. All rights reserved. 251
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 264/522
Unit 5: Technical Processes in Requirements Planning TSCM40
If the maximum stock level is exceeded, the quantity is adjusted as long as a
firmed procurement proposal is not involved. The system issues an exception
message for firmed procurement proposals.
Any additional defined static safety stock and the dynamic safety stock are added
together.
Figure 95: Dynamic Safety Stock (2)
The dynamic safety stock is calculated on the basis of the average dailyrequirements and therefore automatically adjusts itself to changes in demand. The
dynamic safety stock is calculated using the following formula: average daily
requirements x target range of coverage.
In the Customizing activity Define Range of Coverage Profile (Dynamic Safety
Stock) you can define the periodicity (week, month, or period according to
the planning calendar) and the number of periods for which the average daily
requirements are to be determined. The average daily requirement is calculated for
each period.
In Customizing, you enter the minimum and target range of coverage as the
number of days in which a material must still be available or should still be
available. You can also specify a maximum range of coverage. Multiplying the
average daily requirements by the values for the minimum, target, and maximum
range of coverage defined in Customizing results in the minimum, target, and
maximum stock.
During the planning run, the system checks whether the range of coverage
(available quantity divided by average daily requirement) is below the minimum
range of coverage or above the maximum range of coverage.
252 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 265/522
TSCM40 Lesson: Net Requirements Calculation
Figure 96: Dynamic Safety Stock (3)
You can enter the ranges of coverage (minimum, target, and maximum ranges
of coverage) for up to three periods and you can maintain different ranges of
coverage for each period. If you have only maintained one period, the range of
coverage is unlimited.
The values adopted by the individual parameters of the dynamic safety stock can
either be checked directly after single-item planning in the planning results or inthe stock/requirements list. In both evaluations, the dynamic safety stock data is
contained in the period totals display.
The following data is displayed: target range of coverage, minimum range of
coverage, maximum range of coverage, target stock (dynamic safety stock),
minimum stock.
The parameters for calculating the dynamic safety stock are stored in a range
of coverage profile in Customizing for MRP, in the activity Define Range of
Coverage Profile (Dynamic Safety Stock). You can access this activity directly
from the MRP menu under Environment - Current Settings.
The range of coverage profile is assigned to the material in the material masterrecord (MRP data screen 2 or MRP area segment).
Dynamic Safety Stock (4)
You can define a period profile with deviating ranges of coverage for each range
of coverage profile.
2008 © 2008 SAP AG. All rights reserved. 253
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 266/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 267/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 268/522
Unit 5: Technical Processes in Requirements Planning TSCM40
12. Execute planning run, only one planned order is created for the 14th of
the current month + 2 and replenished to the target stock level. No more
planning is executed.
Conclusion: The minimum range of coverage for the dynamic safety stock
has the same function as the amount of the static safety stock that is not
available for planning.
Safety time
Safety time is a float after production. Do not confuse the safety time with the
negative and positive lead times from the BOM item, which have a completely
different function.
Figure 98: Safety Time
The safety time is a float after production (in contrast to the positive/negative lead
time in the component data of a BOM item). It is used to avoid material shortages
caused, for example, by an unreliable vendor.
The order proposals are brought forward by the number of working days specified
in the safety time. The actual requirements dates are not changed.
You define the safety time for each plant in the material master in the MRP 2 view
or for each MRP area in the MRP area segment.
256 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 269/522
TSCM40 Lesson: Net Requirements Calculation
Figure 99: Safety Time in Multi-Level Production
If a safety time has been defined at finished product level and also at assembly
level, these two times are added together when planning the assembly. This may
not be desired. You can therefore determine for each material whether the safety
time is valid for all requirements or only for planned independent requirements
(such as sales orders).
The safety time indicator is used in the MRP 2 view for the material for each
plant, or for each MRP area in the MRP area segment to determine whether the
safety time
• should not to be taken into account (indicator = blank),
• should only to be taken into account for independent requirements (indicator
= 1),
• should be taken into account for all requirements (indicator = 2).
2008 © 2008 SAP AG. All rights reserved. 257
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 270/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Figure 100: Period Profile for the Safety Time
You define the safety time in the material master for each plant (MRP 2 view) or
for each MRP area (in the MRP area segment). In addition, you can assign a
safety time period profile to a material for each plant (MRP 2 view). You can use
the period profile to determine user-defined deviating safety times for particular
periods. These could be periods when a special marketing campaign is being
used, for example.
You define safety time period profiles in the Customizing activity Define Period
Profile for Safety Time/Actual Range of Coverage. You can access this activity
directly from the MRP menu under Environment - Current Settings.
You first create a period profile, to which you can then assign as many periods
with different safety times as you wish.
As of release ECC 5.0 you can define safety times with decimal fractions too. For
example, you enter a figure of 3.1 days using 3 days safety time and 10% lead
time (%). This means that 90% of the daily requirement quantity is deferred by 3
days and the remaining 10% by 4 days.
Demonstration: Safety Time
Purpose
Preparation for exercise
System Data
System: See weekly mail
258 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 271/522
TSCM40 Lesson: Net Requirements Calculation
Client: See weekly mail
User ID: Own user ID
Password: Own passwordSet up instructions: Standard
1. Material master – MRP 2: R-F1##, plant 1000:
Safety time indicator. This can, for example, be restricted to planned
independent requirements in multi-level planning (so that addition of times
does not occur).
Safety time/Actual range of coverage (field for the number of days of
the safety time),
Period profile for safety time (profile used to define deviant actual ranges
of coverage, for example, seasonal ranges of coverage. This is defined in
Customizing for Material Requirements Planning:)
2. Customizing of the profile:
Customizing: Production – Material Requirements Planning – Planning –
MRP Calculation – Define Period Profile for Safety Time/Actual Range
of Coverage
or:
→ Logistics – Production – MRP – Environment – Current Settings – Define
Period Profile for Safety Time/Actual Range of Coverage
(This is an alternative to making the entry in the material master: This is
done in the MRP area segment.)
Create profile P00: Period: 1st day of current month + 6 to last day of current
month + 7, safety time 3 working days. Enter period profile P00 and safety
time indicator 1 in the material master. Execute the planning run and show
the effects. Finally, reset the range of coverage profile and the safety time
indicator and execute the planning run.
2008 © 2008 SAP AG. All rights reserved. 259
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 272/522
Unit 5: Technical Processes in Requirements Planning TSCM40
260 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 273/522
TSCM40 Lesson: Net Requirements Calculation
205 Exercise 11: Net Requirements Calculation
and Safety StockExercise Duration: 25 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Use dynamic safety stock as a quantity buffer and the safety time as a time
buffer.
Business Example
Following the production phase-in period, it appears that pump R-F1## will
be sold in larger quantities. In future, the pump will be planned, assembled,
and put into storage so that sales orders can be fulfilled as quickly as possible.
Uncertainties in planning are to be covered by using dynamic safety stock. Any
delivery delays on the part of production caused by reorganizational measures
should be intercepted using the safety time.
Caution: In this exercise, you will be working with pump R-F1## and
not with R-F2##
Task 1:
First, change the material master for pump R-F1## in plant 1000, if required:
1. In the MRP 3 view, enter strategy group 40, consumption mode 2 and 30
days for both the forward and backward consumption periods.
Task 2:
Call the transaction for creating planned independent requirements for the
material R-F1##, plant 1000, version 00.
1. First, delete the row with the planned independent requirements that remain
from the test phase for strategy 50. To do this, select the relevant row and
delete the item. Save your change and exit from the table.
2. Call the same transaction again and enter the following planned independent
requirements for the pump R-F1## in plant 1000:
Current month
+ 3
Current month
+ 4
Current month
+ 5
Current month
+ 6
90 70 120 100
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 261
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 274/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Verify the requirements type VSF. Save your entries.
Task 3:Execute single-item, multilevel planning for pump R-F1## in plant 1000.
1. In the initial screen of the planning run, check the creation indicators:
Processing key NETCH
Create purchase requisition 2
Scheduling agreement schedule
lines
3
Create MRP list 1
Planning mode 1
Scheduling 1
Also plan unchanged components Select
Display results before they are saved Do not select
Display material list Select
Simulation mode Do not select
To start the planning run, press Enter twice.
2. Display or refresh the stock/requirements list for material R-F1## in plant1000. What is the available quantity at the end of the net planning segment
(this is the planning segment that contains the plant stock).
______________________________________________________
Task 4:
Test the effectiveness of a static safety stock.
1. Add a safety stock of 80 pieces to the material master for R-F1## in plant
1000 in the MRP 2 view and save this change.
2. Refresh the stock/requirements list. What is the available quantity at the
end of the net planning segment (plant segment)?
______________________________________________________
Explain this shortage:
______________________________________________________
______________________________________________________
Continued on next page
262 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 275/522
TSCM40 Lesson: Net Requirements Calculation
3. Execute multilevel requirements planning once more using the
above settings and explain the result after you have refreshed the
stock/requirements list again.
_____________________________________________________
______________________________________________________
Task 5:
Due to fluctuating demand, the definition of static safety stock does not seem
practical. Rather, the safety stock should adapt itself to the requirements situation.
The range of coverage of the safety stock should be 5 days.
1. Change the material master R-F1## in plant 1000 as follows:
Delete the safety stock and enter the coverage profile 002 instead. Savethe change.
2. Open another session and check the coverage profile 002 in plant 1000 in
Customizing for MRP. What are the parameters for determining the average
daily requirement and what values do these parameters have?
_______________________________________ _________
_______________________________________ _________
_______________________________________ _________
3. Execute single-item, multilevel planning using the settings listed above.
Call the stock/requirements list again. Go to the Period totals display
(using the totals symbol on the left margin of the stock/requirements list)
and go to the “Months” tab page.
You notice that the available quantity differs from month to month.
What is the available quantity in the month current month + 4?
______________________________________________________
Use the table entries and your documents to reconstruct the way the
calculation was made:
______________________________________________________
______________________________________________________
______________________________________________________
______________________________________________________
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 263
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 276/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Task 6:
During the months current month + 5 and current month + 6 there are likely
to be delivery delays on the part of production due to various reorganization
measures.
1. In the Customizing for MRP, enter the period profile P## for plant 1000 for
the safety time with the description “Period profile group ##” for the period
first day of current month + 5 to last day of current month + 6 with a
safety time of 3 working days. Save your entries.
2. Enter the new period profile P## in the material master for R-F1## in plant
1000 in the MRP 2 view. Which additional entry is necessary to activate the
period profile for planned independent requirements?
______________________________________________________
Enter safety time indicator 1.
3. Execute multi-level planning for material R-F1## in plant 1000 and then
refresh the stock/requirements list.
In the two critical months, do the availability dates correspond to the
requirements dates?
______________________________________________________
Explain the new situation:
______________________________________________________
______________________________________________________
Hint: To make the following exercises clearer, delete the entries
in the Coverage Profile and Safety Time Indicator fields in the
material master for R-F1## in plant 1000 in the MRP 2 view. Save
the material master. Then execute single-item, multilevel planning
for material R-F1## in plant 1000. Call the stock/requirements
list from the menu tree again. The availability dates should now
correspond to the requirements dates and the available quantity in
the period totals display/Month tab page should be zero again.
264 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 277/522
TSCM40 Lesson: Net Requirements Calculation
Solution 11: Net Requirements Calculation
and Safety StockTask 1:
First, change the material master for pump R-F1## in plant 1000, if required:
1. In the MRP 3 view, enter strategy group 40, consumption mode 2 and 30
days for both the forward and backward consumption periods.
a) Change the material master from the stock/requirements list via
Environment → Change Material or via
Menu path: Logistics → Production → Master Data → Material
Master → Material → Change → Immediately
Task 2:
Call the transaction for creating planned independent requirements for the
material R-F1##, plant 1000, version 00.
1. First, delete the row with the planned independent requirements that remain
from the test phase for strategy 50. To do this, select the relevant row and
delete the item. Save your change and exit from the table.
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Planned Independent Requirements → Create
2. Call the same transaction again and enter the following planned independent
requirements for the pump R-F1## in plant 1000:
Current month
+ 3
Current month
+ 4
Current month
+ 5
Current month
+ 6
90 70 120 100
Verify the requirements type VSF. Save your entries.
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Planned Independent Requirements → Create
Task 3:
Execute single-item, multilevel planning for pump R-F1## in plant 1000.
1. In the initial screen of the planning run, check the creation indicators:
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 265
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 278/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Processing key NETCH
Create purchase requisition 2
Scheduling agreement schedule
lines
3
Create MRP list 1
Planning mode 1
Scheduling 1
Also plan unchanged components Select
Display results before they are saved Do not select
Display material list Select
Simulation mode Do not select
To start the planning run, press Enter twice.
a) Menu path: Logistics → Production → MRP → Planning →
Single-Item, Multi-Level
2. Display or refresh the stock/requirements list for material R-F1## in plant
1000. What is the available quantity at the end of the net planning segment
(this is the planning segment that contains the plant stock).
______________________________________________________
a) Quantity available at the end of the net requirements planning segment:0 pcs
Task 4:
Test the effectiveness of a static safety stock.
1. Add a safety stock of 80 pieces to the material master for R-F1## in plant
1000 in the MRP 2 view and save this change.
a) No solution required
2. Refresh the stock/requirements list. What is the available quantity at the
end of the net planning segment (plant segment)?
______________________________________________________
Explain this shortage:
______________________________________________________
Continued on next page
266 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 279/522
TSCM40 Lesson: Net Requirements Calculation
______________________________________________________
a) Quantity available for planning at the end of the net requirements
planning segment: Minus 80 pcs.
Reason: The newly created safety stock flows into the net
requirements calculation as a requirement.
3. Execute multilevel requirements planning once more using the
above settings and explain the result after you have refreshed the
stock/requirements list again.
_____________________________________________________
______________________________________________________
a) The available quantity at the end of the net requirements planning
segment is once again 0 pieces. The requirement from the safety
stock was fulfilled through requirements planning.
Task 5:
Due to fluctuating demand, the definition of static safety stock does not seem
practical. Rather, the safety stock should adapt itself to the requirements situation.
The range of coverage of the safety stock should be 5 days.
1. Change the material master R-F1## in plant 1000 as follows:
Delete the safety stock and enter the coverage profile 002 instead. Save
the change.
a) No solution required
2. Open another session and check the coverage profile 002 in plant 1000 in
Customizing for MRP. What are the parameters for determining the average
daily requirement and what values do these parameters have?
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 267
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 280/522
Unit 5: Technical Processes in Requirements Planning TSCM40
_______________________________________ _________
_______________________________________ _________
_______________________________________ _________
a) Menu path: Customizing: Production → Material Requirements
Planning → Planning → MRP Calculation → Define Range of
Coverage Profile (Dynamic Safety Stock)
Parameters for determining the average daily requirement:
Number of periods 3
Type of period length 3 (standard days)
Days per period 20
3. Execute single-item, multilevel planning using the settings listed above.
Call the stock/requirements list again. Go to the Period totals display
(using the totals symbol on the left margin of the stock/requirements list)
and go to the “Months” tab page.
You notice that the available quantity differs from month to month.
What is the available quantity in the month current month + 4?
______________________________________________________
Use the table entries and your documents to reconstruct the way thecalculation was made:
______________________________________________________
______________________________________________________
______________________________________________________
Continued on next page
268 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 281/522
TSCM40 Lesson: Net Requirements Calculation
______________________________________________________
a) Available quantity in the month current month + 4: 25 pcs
Calculation method (example):
Planned independent requirements from 3
periods:
Period 1: Current month + 4: 70 pcs
Period 2: Current month + 5: 120 pcs
Period 3: Current month + 6: 100 pcs
Total: 290 pcs
290 pieces divided by 3 x 20 days = 4.83
pc/day
4.83 pc/day x coverage range 5 days = 24.16
pc
24.16 pc rounds up to 25 pc.
Task 6:
During the months current month + 5 and current month + 6 there are likely
to be delivery delays on the part of production due to various reorganization
measures.
1. In the Customizing for MRP, enter the period profile P## for plant 1000 for
the safety time with the description “Period profile group ##” for the period
first day of current month + 5 to last day of current month + 6 with a
safety time of 3 working days. Save your entries.
a) Menu path: Customizing: Production → Material Requirements
Planning → Planning → MRP Calculation → Define Period Profile
for Safety Time/Actual Range of Coverage
2. Enter the new period profile P## in the material master for R-F1## in plant
1000 in the MRP 2 view. Which additional entry is necessary to activate the
period profile for planned independent requirements?
______________________________________________________
Enter safety time indicator 1.
a) Additional entry necessary: Safety time indicator
3. Execute multi-level planning for material R-F1## in plant 1000 and then
refresh the stock/requirements list.
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 269
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 282/522
Unit 5: Technical Processes in Requirements Planning TSCM40
In the two critical months, do the availability dates correspond to the
requirements dates?
______________________________________________________
Explain the new situation:
______________________________________________________
______________________________________________________
Hint: To make the following exercises clearer, delete the entries
in the Coverage Profile and Safety Time Indicator fields in the
material master for R-F1## in plant 1000 in the MRP 2 view. Save
the material master. Then execute single-item, multilevel planning
for material R-F1## in plant 1000. Call the stock/requirementslist from the menu tree again. The availability dates should now
correspond to the requirements dates and the available quantity in
the period totals display/Month tab page should be zero again.
a) In the two critical months, do the availability dates correspond to the
requirements dates? No
Reason: Due to the period profile you entered with a safety time of
3 working days, the availability dates are 3 working days before the
requirements dates in the defined period.
270 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 283/522
TSCM40 Lesson: Net Requirements Calculation
Lesson Summary
You should now be able to:• Understand the net requirements calculation
• Work with safety stocks
• Use the dynamic safety stock
• Use the safety time
2008 © 2008 SAP AG. All rights reserved. 271
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 284/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Lesson:
216
Lot-Size Calculation
Lesson Duration: 60 Minutes
Lesson Overview
The lot.size calculation follows on from the net requirements calculation. A range
of different methods are available for this.
Lesson Objectives
After completing this lesson, you will be able to:
• Use static lot-sizing procedures
• Use lot-sizing by period
• Use optimizing lot-sizing procedures
• Make corresponding settings in Customizing
Space for notes
Business Example
You should set the lot-sizing procedures in such a way that the correct procurementquantities are scheduled at the correct times.
Lot-Size Calculation
In the net requirements calculation, the system determines the shortage quantities
on the respective requirements dates. These shortage quantities must be covered
by receipt elements. The system specifies the number of receipts during a planning
run in the lot-size calculation.
You can define how the lot sizes are calculated by selecting a lot-sizing procedure
when maintaining the material master record (MRP 1).
The result of the lot-size calculation is the quantity to be produced or procured,
which you can change and display in the order proposal.
272 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 285/522
TSCM40 Lesson: Lot-Size Calculation
Figure 101: Overview of Lot-Sizing Procedures
There are three different groups of procedures in the lot-size calculation: static
lot-sizing procedures, period lot-sizing procedures and optimum lot-sizing
procedures.
You can also enter restrictions in material master maintenance that the system
takes into account when forming the lot sizes:
• Minimum lot size (minimum procurement quantity below which the lot
size is not allowed to fall)
• Maximum lot size (maximum procurement quantity for each lot)
• Rounding value (the system rounds up to a multiple of the rounding value)
• Rounding profile (used to create scaled rounding)
You define the different lot-sizing procedures in the Customizing activity “Check
Lot-Sizing Procedure”. You assign the procedure to a material on a plant basis
in the material master (MRP 1) or per MRP area in the MRP area segment of
the material.
Demonstration: Settings for Lot-Sizing Procedure
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
2008 © 2008 SAP AG. All rights reserved. 273
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 286/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Password: Own password
Set up instructions: Standard
1. You make the entry in the material master, MRP 1 view.
2. You configure the lot-sizing procedure under
Customizing: Production – Material Requirements Planning – Planning –
Lot-Size Calculation – Check Lot-Sizing Procedure
Static Lot-Sizing Procedures
Due to its simplicity, the “lot for lot” procedure is often used. However, this can
lead to a planned order every day, which is not desirable. Conversely, the “firmed
lot size” of 10 pieces in the case of a shortage of 95 pieces can lead to 10 different
procurement elements on the same day. If the storage capacity represents the
critical element, it may be practical to make use of the “Replenish up to max.
stock level” option
Figure 102: Static Lot-Sizing Procedures
If you select the lot-for-lot order quantity, an order proposal is created for the
shortage quantity. If several requirements exist on one day that cannot be covered,
the ECC system still only creates one order proposal covering the total shortage
quantity on this particular day.
274 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 287/522
TSCM40 Lesson: Lot-Size Calculation
If you use the the fixed/firmed lot size procedure, the system creates an order
proposal for the amount of the fixed lot size should material shortages occur.
If this order proposal does not cover the requirements sufficiently, the systemcreates as many additional order proposals for the same date, in this lot size, as
are needed to cover the requirements.
When replenishing to the maximum stock level, if a material shortage occurs, a
procurement proposal is created for the amount defined in the material master
record as the maximum stock level. However, if the shortage quantity for one day
is larger than the maximum stock level, the lot size is the same as the shortage
quantity. A balanced stock/requirements situation has priority over the lot-sizing
procedure. The system can also order an amount that replenishes stock up to
the maximum level and covers all requirements (when defining the lot-sizing
procedure in transaction OMI4, enter the indicator 1 in the field Max. Stock Level).
Lot-Sizing by Period
Periodic procedures are set if requirements emerge in recurring intervals (weekly,
every 3 weeks...). In this way, different materials (A-, B-, C--) can be produced in
different intervals taking stockholding and availability into consideration.
Figure 103: Lot-Sizing by Period
In the period lot-sizing procedure, the system groups together the procurement
of requirements quantities within a period in one lot size. The period lengths can
be days, weeks, months or user-defined periods in accordance with the planning
calendar.
2008 © 2008 SAP AG. All rights reserved. 275
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 288/522
Unit 5: Technical Processes in Requirements Planning TSCM40
You can choose the number of periods within which the procurement quantities are
to be grouped together. If the number is to be larger than 1, the number is entered
in the No. of periods field for the lot-sizing procedure in the ECC Customizingstep “Check Lot-Sizing Procedure” for the lot-sizing procedure selected in the
material master.
You can place the resulting receipt at the period start, period finish, or on the date
of the first requirement, by maintaining the relevant value in the “Scheduling”
field in the ECC Customizing step Check Lot-Sizing Procedure.
If you have defined in Customizing that the availability date is at the start or finish
of the period, the date of the planned order that is generated is moved accordingly.
Lot Size According to Planning Calendar
This is a variant of periodic lot sizes. Use an example that underlines that this
method is suited to heavy seasonal production (for example, to barbecue sauce
manufacturers).
Figure 104: Lot Size According to Planning Calendar
In the period lot-sizing procedure according to the planning calendar, the system
groups together the procurement of the requirements quantities within a period
defined by the planning calendar in one lot.
You assign a planning calendar to a material on a plant basis in the material master
(MRP 2) or per MRP area in the MRP area segment.
276 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 289/522
TSCM40 Lesson: Lot-Size Calculation
You maintain a planning calendar (period division) in SAP ECC in the master
data in the MRP menu or in the Customizing IMG activity “Maintain Planning
Calendar”.
Demonstration: Planning Calendar
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. You can find the planning calendar under
Customizing: Production – Material Requirements Planning – Master Data
– Maintain Planning Calendar
Otherwise, refer to the documentation:
Optimizing Lot-Sizing Procedures
The ordering costs for materials procured externally are the costs of ordering and
the setup costs for materials produced in-house. You enter the storage cost rates in
Customizing for lot-sizing procedures.
The starting point is the first shortage date determined by the net requirements
calculation. The shortage quantity that exists at this time is the minimum
procurement quantity. The system then adds the next shortage quantity to this
lot size until, based on the cost criteria, the optimum cost at the source of the
procedure is reached.
2008 © 2008 SAP AG. All rights reserved. 277
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 290/522
Unit 5: Technical Processes in Requirements Planning TSCM40
The various optimizing lot-sizing procedures differ only by the type of the
minimum cost. The following procedures exist:
• Part period balancing:
In the part period balancing procedure, the system groups together successive
requirements quantities, starting from the shortage date, until such time
as the total storage costs equal the order costs (balance between the
quantity-independent and quantity/time-dependent costs).
• Least unit cost procedure:
With the least unit cost procedure, the system groups together successive
requirement quantities into a lot size, starting from the shortage date, until
the total costs per piece create a minimum. The total costs are the sum of
the order costs and the total storage costs.• Dynamic lot size creation:
In dynamic lot size creation, the system groups together requirements
quantities in one lot, starting from the shortage date, until the additional
storage costs are larger than the order costs.
• Groff reorder procedure:
The system groups together requirements quantities in one lot, starting from
the shortage date, until the rise in the average storage costs per period is
greater than the reduction in the order costs per period.
Figure 105: Optimizing Lot-Sizing Procedures
278 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 291/522
TSCM40 Lesson: Lot-Size Calculation
Optimizing lot-sizing procedures optimize the total costs resulting from ordering
(order and setup costs) and storage costs.
You enter the ordering costs in the material master (MRP 1) or, where applicable,
in the MRP area segment.
The system determines the storage costs based on the storage costs indicator,
which you define in the Customizing activity “Check Lot-Sizing Procedure” by
entering a storage cost interest rate. You assign the storage costs indicator to the
material master (for each MRP area, if necessary). The formula for calculating
storage costs is then:
Storage costs = Requirement x Price x Storage cost interest rate x Time in storage
/ 100 / 365.
Based on the first material shortage date determined in the net requirements
planning, the system groups together requirements until the optimum cost has
been reached. The optimizing lot size procedures differ only by the type of the
minimum cost:
Part period balancing: Sum of storage costs equals ordering costs
Least unit cost procedure: Minimum total costs per piece
Groff reorder procedure: Groups together requirements quantities in one lot until
the rise in the average storage costs per period is greater than the reduction in the
order costs per period.
Dynamic lot size creation:Dynamic planning invoice: Groups together the
requirement quantities in one lot until the additional storage costs are greaterthan the lot size fixed costs.
Figure 106: Minimum Lot Size / Maximum Lot Size
2008 © 2008 SAP AG. All rights reserved. 279
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 292/522
Unit 5: Technical Processes in Requirements Planning TSCM40
You can influence the grouping of requirements into a lot by entering additional
restrictions in the material master record. For example, you can define limiting
values (minimum lot size, maximum lot size). During lot-size calculation, thesystem takes into account these limiting values. That is, the lot size is either
rounded up to the minimum lot size, or the system prevents the grouping of
requirements to form more than the maximum lot size.
Rounding
You can use rounding to create a multiple of an order unit.
Figure 107: Rounding
You can influence the grouping of requirements into a lot by entering additional
restrictions in the material master record. By specifying a rounding value, for
example, the system will determine during lot-size calculation that the lot size
quantity is a multiple of an order unit (for example, pallet size, if the materialis only delivered in complete pallets).
In addition to that, you can use rounding profiles. A rounding profile is used to
define settings for rounding up or rounding down the order proposal quantity
into deliverable units.
280 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 293/522
TSCM40 Lesson: Lot-Size Calculation
You define the rounding profiles in Customizing. A rounding profile consists
of the threshold value and the rounding value. The threshold value is the value
from which the system rounds up to the value of the next deliverable unit. Therounding value is the value to which the system should round up as soon as the
threshold value is exceeded.
You can define several combinations of threshold and rounding values for a
rounding profile.
A simulation is available for checking the rounding profile Customizing settings.
Demonstration: Rounding
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Rounding value in the material master (MRP 1) by a multiple of which the
procurement quantity is to be rounded up.
2. Rounding profile, comprising the threshold value and rounding value; create
new staticrounding profile:
Rounding profile 0002 in plant 1000:
Level 1: Threshold value 2, rounding value 5
Level 2: Threshold value 32, rounding value 40;
Demonstrate how the rounding profile works using a simulation (from 1 to
200), exit without saving.
Dynamic rounding profiles and quantity addition/subtraction profiles are
not used in material requirements planning, but rather in areas such aspurchasing.
Special Lot-Sizing Procedures
Explain what is meant by “takt time” here and emphasize the different between
the takt time for takt-based production.
2008 © 2008 SAP AG. All rights reserved. 281
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 294/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Figure 108: Special Lot-Sizing Procedures
You can control the choice of lot-size procedure especially for make-to-order
production (lot-for-lot order quantity, lot-for-lot order quantity with rounding
values, lot-sizing for short-term area).
By setting the splitting quota indicator in the Customizing for lot-size procedures,
you can distribute the procurement quantity across various sources. To do this,
you must set the quota arrangement usage indicator in the material master record
(Purchasing or MRP 2 view). You maintain the portions of the various sources inthe quota arrangement in the master data for Purchasing.
You can set the Overlapping indicator for all lot-sizing procedures in Customizing
in order to distribute the order quantity into partial quantities. These quantities
are not produced at the same time, but rather in regular, overlapping intervals.
Procurement proposals can overlap in the future and in the past. You also maintain
the takt time and, depending on the lot-size procedure, the maximum lot size
or the rounding value.
Demonstration: Special Lot-Sizing Procedures
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
282 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 295/522
TSCM40 Lesson: Lot-Size Calculation
Set up instructions: Standard
1. Each lot-sizing procedure is defined specially for make-to-order
production. Explain this in Customizing using lot-sizing procedures FXand FK.
2. Lot-size with splitting quota: Splitting the lot across various sources
according to the quota arrangement in the master data for purchasing;
you must also set the “Splitting Quota” indicator in Customizing for the
lot-size procedure and the quota arrangement usage indicator in the material
master (Purchasing or MRP 2 views). Do not confuse this with the quota
arrangement in the “procurement types” segment, with which the individual
lots are to be drawn alternately from various sources.
3. Lot-size with overlapping: Forward or backward overlapping (in time) of
partial quantities of an order; possible demonstration based on the lot-sizingprocedure FS, showing it first in Customizing, setting overlapping to “-”, and
then entering it in the material master R-F1## (MRP 1), which was used for
the demonstration of safety stock; enter a fixed lot size (120 pcs), takt time
(1 AT), and a rounding value (40 pcs), and remove any range of coverage
profile that may exist (MRP 2); execute material requirements planning and
explain the results; finally, reset the settings.
Long-Term Lot Size
The purpose of the long-term lot size is to gain a clear, advanced view theprocurement proposals in the future. Procurement is executed on the basis of
the short-term lot size.
Note here: The maximum MRP period (Customizing of the MRP group) and the
“Plan Regularly” indicator in the MRP type.
2008 © 2008 SAP AG. All rights reserved. 283
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 296/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Figure 109: Long-Term Lot Size
The purpose of the long-term lot size is to divide the time axis for MRP into a
short-term and a long-term area, enabling the lot-size calculation to be carried out
using different lot-sizing procedures in these two areas. Creating larger lots in the
long-term area has a particularly positive effect on performance.
It is therefore possible to receive a rough preview of the future master production
schedule in the long-term area and to have a more precise analysis in the
short-term area.
You maintain the settings for the long-term lot size, just as for the other lot-sizing
procedures, in Customizing for MRP in the IMG activity “Check Lot-Sizing
Procedures”. You can define the lot size that is to be used in the short-term
period and the lot size that is to be used in the long-term period, as well as the
end of the short-term/beginning of the long-term periods using the key of the
lot-sizing procedure. You defined the length of the short-term area by entering the
periodicity (for example, month, week) and the number of periods.
If a material is planned with short-term and long-term lot sizes, the period of
validity of both lot-sizing procedures is determined during the planning run. The
order quantities in the short-term horizon are calculated using the lot size in the
short-term area. The system switches to the long-term lot size on the date from
which the long-term lot size is valid. To calculate this date, the system always
rounds up to the beginning of the next full long-term period.
Under certain circumstances, there is the danger that a material planned using
long-term lot size may not be changed and may therefore not be included in new
planning when using NETCH or NETPL planning. The planning order would then
be converted in the long-term lot size. In order to prevent this from occurring,
you can set the Recurring MRP indicator in Customizing for the MRP type of
284 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 297/522
TSCM40 Lesson: Lot-Size Calculation
the material, and also maintain the Max. MRP Interval in the MRP group. The
material is then included in planning after the maximum MRP interval has been
processed and is planned with the short-term lot size, if required.
2008 © 2008 SAP AG. All rights reserved. 285
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 298/522
Unit 5: Technical Processes in Requirements Planning TSCM40
286 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 299/522
TSCM40 Lesson: Lot-Size Calculation
227 Exercise 12: Lot-Size Calculation
Exercise Duration: 15 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Make the main settings for the lot-sizing procedure
• Use the lot-sizing procedure
Business Example
Pump R-F1## is only to be planned in the short-term horizon, in which
procurement actually occurs. Taking performance issues into account, the MRPcontroller should make do with a preview at the aggregated level in the long-term
horizon.
Task 1:
First, determine which lot-sizing procedure is currently being used for planning in
the material master for pump R-F1## in plant 1000.
1. ____________________________________________________________
Is this a static, periodic or optimizing lot-sizing procedure?
____________________________________________________________
Task 2:
Now create your own lot-sizing procedure with which you can gain a summarizing
preview beyond a short-term horizon.
1. To do this, call the activity Check Lot-Sizing Procedure in Customizing
for MRP.
The MRP Lot Size field takes you to the defined lot-sizing procedures.
Call the lot-sizing procedure entered under task 1 point 1 by double-clicking
on it.Have the long-term lot size settings been maintained?
______________________________________________________
2. Choose the “Copy As...” pushbutton and enter your group number ## and
the description “Exact lot size with preview group ##” as the name for the
new procedure.
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 287
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 300/522
Unit 5: Technical Processes in Requirements Planning TSCM40
In the period indicator for the long-term lot size field, enter M, and enter
3 in the corresponding number of periods field to determine where the
short-term period ends and the long-term period begins.
Choose the lot-sizing procedure P for period lot sizing for the lot size in the
long-term horizon, 3 as the number of periods and the lot size indicator
M.
Press Enter, confirm any warning messages that may appear and then save
your new procedure.
Task 3:
Now plan your pump with the new lot-sizing procedure.
1. Call the material master for the pump R-F1##, plant 1000, and enter yournewly created lot-sizing procedure.
In addition, choose a maximum lot-size of 20 pieces and save these changes.
2. Execute a multilevel planning run using the following settings:
Processing key NETCH
Create purchase requisition 2
Scheduling agreement schedule
lines
3
Create MRP list 1
Planning mode 3
Scheduling 1
Also plan unchanged components Select
Display results before they are saved Do not select
Display material list Do not select
Simulation mode Do not select
3. Evaluate the planning result using the stock/requirements list.
How is the result in the plant segment (net segment) attained?
______________________________________________________
______________________________________________________
______________________________________________________
Why are the make-to-order segments unaffected?
______________________________________________________
Continued on next page
288 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 301/522
TSCM40 Lesson: Lot-Size Calculation
______________________________________________________
Task 4:You are, however, unsatisfied with the result and therefore call the material master
again to reverse the changes.
1. In the material master for the pump R-F1##, plant 1000 set the exact lot-size
EX again and delete the maximum lot-size of 20 pieces.
2. Execute another multilevel planning run for the pump with the settings
from task 3, point 2.
3. Verify the result by taking a look at the stock/requirements list, which you
need to call from the SAP Easy Access menu again.
2008 © 2008 SAP AG. All rights reserved. 289
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 302/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Solution 12: Lot-Size Calculation
Task 1:
First, determine which lot-sizing procedure is currently being used for planning in
the material master for pump R-F1## in plant 1000.
1. ____________________________________________________________
Is this a static, periodic or optimizing lot-sizing procedure?
____________________________________________________________
a) Lot-sizing procedure: The pump is being planned with the exact
lot size EX.
Procedure type: The exact lot size is a static lot-sizing procedure.
Task 2:
Now create your own lot-sizing procedure with which you can gain a summarizing
preview beyond a short-term horizon.
1. To do this, call the activity Check Lot-Sizing Procedure in Customizing
for MRP.
The MRP Lot Size field takes you to the defined lot-sizing procedures.
Call the lot-sizing procedure entered under task 1 point 1 by double-clicking
on it.Have the long-term lot size settings been maintained?
______________________________________________________
a) Long-term lot size maintained? No long-term lot size settings have
been maintained.
2. Choose the “Copy As...” pushbutton and enter your group number ## and
the description “Exact lot size with preview group ##” as the name for the
new procedure.
In the period indicator for the long-term lot size field, enter M, and enter
3 in the corresponding number of periods field to determine where theshort-term period ends and the long-term period begins.
Choose the lot-sizing procedure P for period lot sizing for the lot size in the
long-term horizon, 3 as the number of periods and the lot size indicator
M.
Continued on next page
290 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 303/522
TSCM40 Lesson: Lot-Size Calculation
Press Enter, confirm any warning messages that may appear and then save
your new procedure.
a) Menu path: Customizing: Production → Material Requirements
Planning → Planning → Lot-Size Calculation → Check Lot-Sizing
Procedure
Task 3:
Now plan your pump with the new lot-sizing procedure.
1. Call the material master for the pump R-F1##, plant 1000, and enter your
newly created lot-sizing procedure.
In addition, choose a maximum lot-size of 20 pieces and save these changes.
a) Menu path: Logistics → Production → Master Data → Material Master → Material → Change → Immediately, MRP 1 view
2. Execute a multilevel planning run using the following settings:
Processing key NETCH
Create purchase requisition 2
Scheduling agreement schedule
lines
3
Create MRP list 1
Planning mode 3
Scheduling 1
Also plan unchanged components Select
Display results before they are saved Do not select
Display material list Do not select
Simulation mode Do not select
a) Menu path: Logistics → Production → MRP → Planning →
Single-Item, Multi-Level
3. Evaluate the planning result using the stock/requirements list.
How is the result in the plant segment (net segment) attained?
______________________________________________________
______________________________________________________
______________________________________________________
Why are the make-to-order segments unaffected?
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 291
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 304/522
Unit 5: Technical Processes in Requirements Planning TSCM40
______________________________________________________
______________________________________________________
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Environment → Stock/Requirements List
Interpretation of the results: In the short-term horizon (up to
three months time) planning is done using the “Exact Lot-Size”
procedure, taking a maximum lot size of 20 pieces into account. In
the long-term horizon that follows on from this, the requirement
elements are grouped in blocks of 3 months each and fulfilled by
a shared procurement element (preview at aggregated level). The
availability date is the requirement date for the first requirement
element to appear.
Make-to-order segments: When you made the settings for the
lot-sizing procedure, the “make-to-order lot-size” indicator
retained the initial value “blank”. This means that the exact lot-size
is used in the make-to-order segments, regardless of the procedure
used in the net segment. Consequently, with this setting, even the
maximum lot-size has no bearing in make-to-order segments.
Task 4:
You are, however, unsatisfied with the result and therefore call the material master
again to reverse the changes.
1. In the material master for the pump R-F1##, plant 1000 set the exact lot-size
EX again and delete the maximum lot-size of 20 pieces.
a) Menu path: Logistics → Production → Master Data → Material
Master → Material → Change → Immediately, MRP 1 view
2. Execute another multilevel planning run for the pump with the settings
from task 3, point 2.
a) Menu path: Logistics → Production → MRP → Planning →
Single-Item, Multi-Level
3. Verify the result by taking a look at the stock/requirements list, which you
need to call from the SAP Easy Access menu again.
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Environment → Stock/Requirements List
292 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 305/522
TSCM40 Lesson: Lot-Size Calculation
Lesson Summary
You should now be able to:• Use static lot-sizing procedures
• Use lot-sizing by period
• Use optimizing lot-sizing procedures
• Make corresponding settings in Customizing
2008 © 2008 SAP AG. All rights reserved. 293
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 306/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 307/522
TSCM40 Lesson: Procurement Types
Figure 110: Procurement Types
The procurement type is used to determine whether a material is to be produced
in-house or procured externally.
The procurement type is predefined by the material type in Customizing for the
material master and is defined in the material master record (MRP 1, Procurement
type field).
If the procurement type permits both in-house production and externalprocurement, material requirements planning starts with in-house production.
A procurement type other than in-house production or external procurement can
be set using the special procurement key in the material master. You define
the special procurement types in the Customizing activity “Define Special
Procurement Type”; In doing so, special procurement types are assigned to a
procurement type, which defines the procurement type more precisely.
In this section, we will concentrate on in-house production.
Quota arrangement and quota maintenance
Explain the difference between this and lot-size with splitting quota.
If the participants have any questions, refer them to the appendix or go through
the appendix with them.
2008 © 2008 SAP AG. All rights reserved. 295
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 308/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Figure 111: Quota Arrangement and Quota Maintenance
If a material is obtained from various sources of supply, the individual sources of
supply can be provided with a quota arrangement. The quota arrangement specifies
how the receipts should be distributed amongst each source of supply. The
quota rating determines which source of supply is next in line. The procurement
quantities are then filled one after the other using the various sources of supply.
With a quota arrangement you can also define a preferred source of supply. Then
only the remainder of a requirement quantity that exceeds the maximum release
quantity assigned to the preferred source of supply is requested from an alternative
source of supply (see the example in the graphic). The smallest periodicity for
the maximum release quantity is a week (maximum release quantities per day can
be realized by selecting the periodicity according to planning calendar and then
creating a planning calendar with day periodicity).
Each quota arrangement applies for a specific period of time. A quota arrangement
item is created within the period for every source of supply. Only continuous
validity periods can be defined for a material.
A quota arrangement may include external procurement or in-house production, as
well as various special procurement types. A source list entry is also necessary
for external procurement, though the MRP-relevant indicator should be taken
into account.
Using the quota arrangement usage indicator in the material master (Purchasing or
MRP 2 views), you determine that a quota arrangement is used for a material. You
also specify the business application areas in which the quota arrangement is used
and determine that the quota-allocated quantity is updated. You define the quota
arrangement usage indicator in Customizing for Purchasing.
296 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 309/522
TSCM40 Lesson: Procurement Types
Demonstration: Quota Arrangement
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. To activate the quota arrangement you first have to create it in the masterdata for Purchasing or Material Requirements Planning.
2. A source list entry must exist for external procurement (including the
“MRP-relevant” indicator),
3. The quota arrangement usage indicator must be set in the material master,
4. The quota arrangement usage indicator is maintained in Customizing for
Purchasing:
Customizing: Materials Management – Purchasing – Quota Arrangement –
Define Quota Arrangement Usage.
Provide a demonstration of the exercise on procurement type and quota arrangement.
2008 © 2008 SAP AG. All rights reserved. 297
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 310/522
Unit 5: Technical Processes in Requirements Planning TSCM40
298 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 311/522
TSCM40 Lesson: Procurement Types
237 Exercise 13: Procurement Type and Quota
ArrangementExercise Duration: 15 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Classify the effect of the procurement type
• Work with quota arrangements
Business Example
In future, shaft R-B3##, plant 1000 is to be produced in-house. The amount
produced for each period will be determined by capacity restraints. Further
demand can be satisfied through external procurement. To do this, you use the
quota arrangement function.
Task 1:
Material R-B3## is to be used to test the effects of a quota arrangement in
procurement. Make the necessary settings to do this in the steps below.
1. Call the material master for the assembly R-B3##, plant 1000, and check
the procurement type. Which procurement type has been entered there and
what does this abbreviation mean?
______________________________________________________
2. Activate the quota arrangement for the material R-B3##, plant 1000 in
requirements planning by entering 3 in the Quota Arrangement Usage
field in the corresponding MRP view.
Choose Save.
Task 2:
Execute quota maintenance for the shaft from the master data menu in Material
Requirements Planning.
1. Call the transaction to access the initial screen. The quota arrangement
should be valid until 12.31. next year.
After you have done this, go to the item overview.
2. Now maintain the quota arrangement using the following constraints:
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 299
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 312/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 313/522
TSCM40 Lesson: Procurement Types
2. Call or refresh the stock/requirements list. Interpret the result by calling the
quota arrangement again (pushbutton in the stock/requirements list).
How large are the total quantities that appear in the quota arrangement
(quota allocated quantity)?
Item 1:_____________________________________________
Item 2:_____________________________________________
Which procurement elements are generated for the dependent requirements
and what is the reason for this?
______________________________________________________
______________________________________________________
______________________________________________________
3. The quota arrangement check has been completed. Deactivate the quota
arrangement for R-B3## (plant 1000) again.
2008 © 2008 SAP AG. All rights reserved. 301
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 314/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Solution 13: Procurement Type and Quota
ArrangementTask 1:
Material R-B3## is to be used to test the effects of a quota arrangement in
procurement. Make the necessary settings to do this in the steps below.
1. Call the material master for the assembly R-B3##, plant 1000, and check
the procurement type. Which procurement type has been entered there and
what does this abbreviation mean?
______________________________________________________
a) Menu path: Logistics → Production → Master Data → Material
Master → Material → Change → Immediately, View: MRP 2
Indicator entered: X
Meaning: Both procurement types (in-house production and
external procurement) are permitted.
2. Activate the quota arrangement for the material R-B3##, plant 1000 in
requirements planning by entering 3 in the Quota Arrangement Usage
field in the corresponding MRP view.
Choose Save.
a) Menu path: Logistics→
Production→
Master Data→
Material Master → Material → Change → Immediately, View: MRP 2
Task 2:
Execute quota maintenance for the shaft from the master data menu in Material
Requirements Planning.
1. Call the transaction to access the initial screen. The quota arrangement
should be valid until 12.31. next year.
After you have done this, go to the item overview.
a) Menu path: Logistics → Production → MRP → Master Data →
Quota Maintenance
Material: R-B3##
Plant: 1000
2. Now maintain the quota arrangement using the following constraints:
Continued on next page
302 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 315/522
TSCM40 Lesson: Procurement Types
Item 1:
Internal procurement – In-house
production,
Maximum release quantity: 50 PC
Number of periods for this release
quantity:
1
Periods: W (week)
Priority for this item: 1
Hint: With item 1, make sure that you actually maintain settings for
the maximum release quantity and not the maximum quantity.
Item 2:
External procurement –
Consignment.
Priority for this item: 2
Save the quota arrangement settings.
a) No solution required
Task 3:Due to the planning activities that you carried out in the previous exercises for
the finished product R-F1##, dependent requirements also exist for the assembly
R-B3##. The corresponding procurement elements are now to be generated again
using the quota arrangement.
1. Start multilevel single-item planning with the following settings:
Processing key NETCH
Create purchase requisition 1
Delivery schedules 3
Create MRP list 1
Planning mode 3
Scheduling 1
Also plan unchanged components Select
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 303
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 316/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Display results before they are saved Do not select
Display material list Do not select
Simulation mode Do not select
a) Menu path: Logistics → Production → MRP → Planning → Multilevel
Single-Item Planning
2. Call or refresh the stock/requirements list. Interpret the result by calling the
quota arrangement again (pushbutton in the stock/requirements list).
How large are the total quantities that appear in the quota arrangement
(quota allocated quantity)?
Item 1:_____________________________________________
Item 2:_____________________________________________
Which procurement elements are generated for the dependent requirements
and what is the reason for this?
______________________________________________________
______________________________________________________
______________________________________________________
a) Total quantities for items 1 and 2: Varies (for example, item 1: 370
pieces, item 2: 150 pieces)
Procurement elements: Planned orders and sometimes also purchase
requisitions are generated.
Reason: Depending on whether requirements of up to 50 pieces
or more appear in a planning interval (one week), either only
a corresponding planned order is generated (this means the
requirement can be satisfied from production alone), or a purchase
requisition is created as well to cover the requirements that exceed
the 50 pieces. The reason for this lies in the quota arrangement
settings you have defined and in the settings for the planning run
(always generate purchase requisitions for external procurement).
Continued on next page
304 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 317/522
TSCM40 Lesson: Procurement Types
3. The quota arrangement check has been completed. Deactivate the quota
arrangement for R-B3## (plant 1000) again.
a) Menu path: Logistics → Production → Master Data → Material
Master → Material → Change → Immediately, View: MRP 2
Quota arrangement usage: <blank>
Choose Save.
Hint: To deactivate the quota arrangement, all you have to do
is set the Quota arrangement usage indicator in the material
master back to blank . You do not need to delete it.
2008 © 2008 SAP AG. All rights reserved. 305
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 318/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Lesson Summary
You should now be able to:• Use the procurement type for in-house production
• Use the procurement type for external procurement
• Use the quota arrangement
306 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 319/522
TSCM40 Lesson: Scheduling
Lesson:
245
Scheduling
Lesson Duration: 90 Minutes
Lesson Overview
Scheduling takes place for materials produced in-house and procured externally
using the corresponding time elements. With products that are produced in-house,
you should take the supply planning across all BOM levels into account.
Lesson Objectives
After completing this lesson, you will be able to:
• Describe scheduling for in-house production
• Describe scheduling for external procurement
• Understand multilevel backward scheduling
• Make corresponding settings in Customizing
Space for notes
Business ExampleFor scheduling in-house production you need to ensure that basic date scheduling
and lead time scheduling run synchronously. Postponements that occur during the
conversion to a production order should be kept as small as possible.
Scheduling
During scheduling, the system calculates the start and finish dates of the
procurement elements for materials produced in-house or externally. In order
to calculate these dates, the system uses the in-house production time for parts
produced in-house and the delivery time in the material master or purchasing info
record for parts procured externally.
Scheduling Types in Production Planning
There are two different types of scheduling: Basic scheduling (through the
material master) and lead-time scheduling (through the routing); the latter always
implies the former.
2008 © 2008 SAP AG. All rights reserved. 307
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 320/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Figure 112: Scheduling Types in Production Planning
There are two methods for scheduling in production planning that are applied
differently. If material requirements planning is carried out without lead time
scheduling as shown in the upper part of the diagram, capacity requirements are
not determined for the planned orders. Production orders are always scheduled
using lead time scheduling via the operations. Lead time scheduling can also
be used to determine capacity requirements for planned orders in MRP. The
production order always has both sets of dates (basic dates and production dates).The production dates are dates relevant to production. In order to ensure smooth
material requirements planning, it is absolutely essential to schedule the routing
and to update the scheduling result in the material master.
Basic Date Scheduling Backwards for In-House Production
The following three dates are important: The opening date (the point in time
when the planned order is converted into a production order, defined using the
opening period for the planned order), the order start date (starting point of the
production order) and the order finish date (point in time by which the material
has to have been through production).
Point out the difference between lot size dependent and lot size independent
in-house production time. It could also be useful that for a blast furnace, for
example, the filling quantity would have little or no effect on the production time,
or when the production time corresponds to a quantity-independent maturation
time (beer, wine).
308 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 321/522
TSCM40 Lesson: Scheduling
Figure 113: Basic Date Scheduling Backwards for In-House Production
With materials planned using MRP, future requirements dates are known.
Backward scheduling is used. With backward scheduling, the system calculates
the order finish date by subtracting the goods receipt processing time from
the requirements date. This gives the number of workdays that are required
for checking the material and placing it in storage after the goods are received.
Backward scheduling is defined in the MRP 2 view in the material master. The
system calculates the order start date by subtracting the in-house production time
from the order finish date. The in-house production time comprises the lead time
and floats (safety time, float before production, and so on). You can maintain the
in-house production time in the material master as a value that is independent of
the lot size (MRP or Work Scheduling views) or as a lot-size-dependent value
(Work Scheduling view). If the in-house production time is independent of the lot
size, the system uses this value to determine the basic dates independent of the
order quantity. With an in-house production time that depends on the lot size, the
system determines the time based on the order lot size. The setup time and queue
time are independent of the lot size. The opening period for the planned order is
then subtracted from the order start date. This gives the opening date.
The opening period reflects the processing time that the MRP controller requires
to convert planned orders. You define the opening period as a float for the
scheduling margin key in the Customizing for MRP, in the activity “Define Floats
(Scheduling Margin Key)” for each plant, and enter the scheduling margin key inthe material master (MRP 2).
Basic Date Scheduling Forwards for In-House Production
If the order start date in backward scheduling falls in the past, “today scheduling”
without an opening period is executed. Point out that this can be repressed
technically.
2008 © 2008 SAP AG. All rights reserved. 309
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 322/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Customizing: Production – Material Requirements Planning – Planning –
Scheduling and Capacity Parameters – Parameters for Determining Basic Dates
Figure 114: Basic Date Scheduling Forwards for In-House Production
If during backward scheduling of materials planned using MRP the system
determines an order start date that is in the past, it automatically switches to
forward scheduling in order to receive realistic scheduling data. With forward
scheduling, the system sets the current date as the order start date. The in-houseproduction time is added to the current date to give the order finish date. The
goods receipt processing time is added to the order finish date in order to
determine the MRP date. The material is available from this date onwards.
There is no order creation date with forward scheduling since the opening date
calculated is in the past.
In the “Parameters for Determining the Basic Dates” activity in MRP Customizing,
you can make a setting for each plant to prevent the system from automatically
switching to forward scheduling when calculating basic dates if the order start
date is in the past. If the indicator is set, backward scheduling is always used to
determine the basic dates, even if the start date is in the past.
Basic Scheduling for External Procurement
In external procurement, the in-house production time is replaced by the sum of
the purchasing department processing time (in working days) and the planned
delivery time (in calendar days).
310 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 323/522
TSCM40 Lesson: Scheduling
Figure 115: Basic Scheduling for External Procurement
The scheduling procedure for materials procured externally is the same as for
materials produced in-house: it is merely a matter of replacing the in-house
production time with the sum of the purchasing department processing time and
the planned delivery time. You define the purchasing department processing time
in workdays as a plant parameter in Customizing. The planned delivery time
is specified in calendar days. It can be determined on a non-vendor-specific or
vendor-specific basis. You maintain the non-vendor-specific planned deliverytime in the material master in the MRP 2 view.
You enter a vendor-specific planned delivery time in the purchasing info record or
in the outline agreement. It is used in the planning run, if the Sched. info rec/agr.
(scheduling info record/agreement) indicator is maintained in Customizing as a
plant parameter or MRP group parameter and if a vendor can be uniquely assigned
as part of automatic source determination.
Demonstration: Basic Scheduling
PurposePreparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
2008 © 2008 SAP AG. All rights reserved. 311
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 324/522
Unit 5: Technical Processes in Requirements Planning TSCM40
1. Explain basic scheduling with the help of a planned order:
Call material master R-F1##, plant 1000. Display and explain the following
fields:
• Scheduling margin key (MRP 2)
• Lot-size independent in-house production time (MRP 2) and lot-size
independent (work scheduling)
• goods receipt processing time (MRP 2)
• Planned delivery time (MRP 2)
2. Display and explain the following in Customizing:
• Definition of the scheduling margin key:
Customizing: Production – Material Requirements Planning – Planning – Scheduling and Capacity Parameters – Define Floats
(Scheduling Margin Key)
• “Order Start in Past” indicator at plant level:
Customizing: Production – Material Requirements Planning –
Planning – Scheduling and Capacity Parameters – Parameters for
Determining Basic Dates
or:
Customizing: Production – Material Requirements Planning – Plant
Parameters – Carry Out Overall Maintenance of Plant Parameters
(The “order start date in the past” parameter is maintained only per
plant; the switch in the MRP group parameter cannot be bypassed)
3. Execute Material Requirements Planning for material R-F1##, plant 1000,
using planning mode 3 and scheduling indicator 1.
4. Stock/requirements list for material R-F1##, plant 1000. Double-click on a
planned order and “Change element”:
The planned order contains only the basic dates, not production dates or
capacity requirements.
Order Dates for Basic Scheduling
With basic scheduling, the dependent requirements date is derived from the order
start date of the order that caused the requirements.
312 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 325/522
TSCM40 Lesson: Scheduling
Figure 116: Order Dates for Basic Scheduling
Basic scheduling is carried out if you start the planning run with the scheduling
indicator set to 1 (basic dates will be determined for planned orders). The planning
run determines the dependent requirements for the components via the BOM
explosion. With basic scheduling, the dependent requirements date is derived from
the order start date of the planned order that caused the requirements.
Taking the dependent requirements date as the availability date, the system
determines the basic order dates of the components by means of backward
scheduling using in-house production time or planned delivery time. With basic
scheduling, no capacity requirements are calculated or dispatched for the order.
2008 © 2008 SAP AG. All rights reserved. 313
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 326/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Lead Time Scheduling
Basic scheduling is also executed first during lead time scheduling.
Hint: Point out that to adjust the results of both types of scheduling
types, it is necessary to schedule the routing and update the scheduling
results in the material master. Automatic adjustment of the order
start date is possible with different scheduling results.
• Definition of the exact production times (production start date, production
end date, operation dates, staging dates for the components)
• Determining capacity requirements
• Backward or forward scheduling
• Times from routing (queue times, setup times, personnel time, and machine
times) and floats from the scheduling margin key (float before and float
after production).
Figure 117: Lead Time Scheduling
You trigger lead time scheduling in MRP by setting the scheduling indicator to
“2” (lead time scheduling and capacity planning). During the planning run with
the scheduling indicator “2”, the order start and order finish dates are determined
for each basic scheduling. This is followed automatically by the actual lead time
scheduling which can alternatively also be executed manually for individual
planned orders (Planned order – Change – Edit – Scheduling) based on the existing
basic date scheduling with the scheduling indicator “1” (Determining basic dates
for planned orders). In lead time scheduling the precise production times (that is,
production start and finish dates) are defined for materials produced in-house and
314 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 327/522
TSCM40 Lesson: Scheduling
at the same time the capacity requirements are created. The materials staging dates
for the components are also determined. Lead time scheduling is carried out using
the times from the task list. It is executed as forward scheduling or backwardscheduling, depending on the setting you make in the “Define Scheduling
Parameters for Planned Orders” activity in Customizing. The following times are
taken into account: – Buffer times (float before production and safety time) that
are assigned to the material using the scheduling margin key – the individual time
portions from the routing: Waiting time, setup time, labor time, and machine time.
In backward scheduling, the system first works back from the order finish date
to calculate the float after production, which in turn gives the production finish
date. The individual operations of the task list are scheduled backwards, starting
from the production finish date. The start date of the first operation becomes the
production start date.
Demonstration: Lead Time Scheduling
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Tie this in with previous demonstrations or call up the details for a planned
order and “Change element” in MD04.
Execute “Schedule Planned Order” (in the Edit menu, for example) and
look at the “Header” tab page: Production dates for this one planned order
are displayed.
2. Execute a planning run for material R-F1##, plant 1000, using planning
mode 3 and scheduling indicator 2.
3. Stock/requirements list for material R-F1##, plant 1000. Double-click on adifferent planned order to the one above and “Change element”:
The planned order is scheduled using detailed scheduling and therefore only
contains production dates.
4. Compare the order start dates and the production dates using the floats from
the scheduling margin key.
5. Explain the corresponding Customizing settings:
2008 © 2008 SAP AG. All rights reserved. 315
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 328/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Customizing: Production – Material Requirements Planning – Planning –
Scheduling and Capacity Parameters – Define Scheduling Parameters for
Planned Orders
Pay particular attention to:
• Detailed scheduling
• Adjusting dates (and defining the dependent requirement dates)
• Scheduling control for detailed scheduling
• Reduction
Detailed Scheduling Horizon:
A new planned order that was generated in a planning run with a start date
that lies beyond the detailed scheduling horizon does not undergo lead time
scheduling, in spite of scheduling indicator 2
If the start date of the above planned order lies within the detailed scheduling
horizon at the time of a later planning run with the scheduling indicator 2
(and planning mode 1), the order then undergoes lead time scheduling
Reduction and Scheduling Adjustment
Explain the various possibilities for avoiding or reducing the deviations between
basic date scheduling and lead time scheduling (scheduling the routing, reducing
lead time scheduling, switching to forward scheduling, overriding Customizingsettings).
Special features in conjunction with basic date scheduling and lead time
scheduling:
• If new basic dates are set (manually) in a planned order scheduled using
detailed scheduling, the detailed scheduling data is automatically reset.
The “Start in the past” field means that in lead time scheduling, an order start date
which is a certain number of days in the past is allowed. The production start
date, however, must lie in the future.
316 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 329/522
TSCM40 Lesson: Scheduling
Figure 118: Reduction and Scheduling Adjustment
To ensure smooth interplay between basic date scheduling and lead time
scheduling, the in-house production time in the material master must match
the lead time scheduling via the routing. If basic scheduling differs from lead
time scheduling, the basic dates can be adjusted to the production dates after the
production dates have been re-determined through reduction. If the production
start date of the planned order is before the order start date, the system candetermine new production dates using reduction. Reduction can take place at two
points: 1. To reduce the float before production and the safety time, you must
set up reduction in the Customizing for the scheduling parameters for planned
orders for the plant, the planned order type, and where necessary the production
scheduler; 2.To reduce the operation times, you must assign a reduction strategy
to the operation in the routing. In the Customizing activity “Define Scheduling
Parameters for Planned Orders”, in the “Adjust Scheduling” section, you can
define whether and how the basic dates are to be adjusted to the production dates.
If there are scheduling problems, the basis for calculating basic dates switches
from backward to forward scheduling. If, based on these basic dates, detailed
scheduling occurs backward and if the times in the routing are much shorter thanthose in the material master, the following situation may arise: The calculated
production start date is further in the future than is necessary (and may still be able
to be produced on schedule.) To avoid this, Customizing is overridden. the system
schedules forward and the order finish date is adjusted (it falls on the requirements
date at the earliest). The proposed order start date remains the same.
2008 © 2008 SAP AG. All rights reserved. 317
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 330/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Demonstration: Reduction and Scheduling Adjustment
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. If the production start date is before the order start date, the system candetermine new production dates using reduction.
Demo example:
In the material master:
Reduce the processing time within lot-size dependent in-house production
time (view AV) by 10 days
Create requirement: 100 pcs for today + 5 months,
Planning run with scheduling indicator 2,
Analyze the resulting planned order:There was no reduction, the order start date was adjusted, the original order
start date can still be seen as the explosion date
In the scheduling and capacity parameters in the “Reduction” segment:
Maximum reduction level 4,
% Red. float before and after production: 50 60 70 80 90 100%
Execute planning run again with planning mode 3 and scheduling indicator
2:
New planned order: Reduced to the specified level 4, the order start date was
adjusted to the production start date that resulted from the reduction, theoriginal order start date is still visible as the explosion date.
Reduction for Forward Scheduling:
Demo example:
In the material master, enter the original processing time again manually, or
schedule the routing and update the material master,
In the scheduling and capacity parameters in the section “Reduction”: Reset
maximum reduction level to 0,
318 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 331/522
TSCM40 Lesson: Scheduling
Create requirements: 100 pcs for today + 1 week, planning run with
scheduling indicator 2, analyze generated planned order: Forward
scheduling, no reductions.
Reset maximum reduction level to 4,
Execute planning run again with planning mode 3 and scheduling indicator
2: New planned order: Reduced to specified level 4, the order start was
adjusted to the production end date that resulted from the reduction.
Staging Components in Accordance with the Operation
• Staging of the components in accordance with the operation using component
assignment
• Entry in Customizing: Dependent requirements date can also be the order
start date
Figure 119: Staging Components in Accordance with the Operation
With lead time scheduling using the routing, the dependent requirements dates can
be placed on the dates of the assigned operations. A material order appropriate for
the operation is then possible.
The standard system assumes staging of materials in accordance with the
component assignment of the BOM to the routing. The dependent requirements
date of the BOM components is set on the production start date of the operations
to which they are assigned.
2008 © 2008 SAP AG. All rights reserved. 319
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 332/522
Unit 5: Technical Processes in Requirements Planning TSCM40
If BOM components are assigned to the first operation of the routing in the default
settings or component assignment maintenance, their dependent requirements date
is set to the production start date of the first operation. With pure basic scheduling,their dependent requirements date is the order start date of the planned order that
caused the requirements.
In Customizing for MRP, in the “Adjust Scheduling” section of the IMG activity
“Define Scheduling Parameters for Planned Orders”, you can define that the
dependent requirements date is also to be placed on the order start date with lead
time scheduling (for example, if capacity requirements have to be created using
lead time scheduling).
Changing Dependent Requirement Dates
The negative/positive lead times are used to simulate the requirements dates from
lead time scheduling during basic date scheduling. These times cannot, however,
be lot size dependent.
Figure 120: Changing Dependent Requirement Dates
In the BOM explosion, the required components or assemblies are determined
for the relevant BOM.
The dependent requirement date of a particular component can be moved using
the negative lead time or positive lead time from the BOM. You maintain the
negative and positive lead times in the basic data screen of the component item.
The lead time is entered as negative lead-time offset.
320 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 333/522
TSCM40 Lesson: Scheduling
The positive lead time is not taken into account in lead time scheduling. They
are used for the simulation of component assignment in the routing during basic
date scheduling.
The negative lead time is taken into account in lead time scheduling. The
component must be available earlier by this period.
Demonstration: Order Dates with Lead TimeScheduling and Postponing the DependentRequirement Dates
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Explain the function of the negative/positive lead time and the component
assignment in both scheduling types as far as the sequencing of the dependent
requirements of the assemblies or components is concerned.
Instead of using the order report, you can also display the assembly
requirements dates in the component overview of the planned order; or with
a view to preparing the exercise, you can use the new order tree.
2008 © 2008 SAP AG. All rights reserved. 321
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 334/522
Unit 5: Technical Processes in Requirements Planning TSCM40
322 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 335/522
TSCM40 Lesson: Scheduling
255 Exercise 14: Scheduling
Exercise Duration: 30 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Describe the functions of scheduling
• Monitor the order dates in multilevel production
Business Example
Based on material R-F1## in plant 1000, the project team examines the
possibilities for staging the assemblies and components at different times inmulti-level production planning.
Task 1:
Call the current stock/requirements list for material R-F1## in plant 1000.
Select a planned order in the net segment that is not firmed and does not show
any exception messages.
1. Make a note of the number of the planned order.
______________________________________________________
2. Choose the Order Report pushbutton at the bottom left of the screen.In the order report, double-click on the respective element and select the
component materials to analyze.
With dependent requirements, always analyze the “corresponding”
requirements coverage element.
To do this, place your cursor on the line and use the Display Element
pushbutton.
R-F1## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
R-B1## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 323
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 336/522
Unit 5: Technical Processes in Requirements Planning TSCM40
R-B4## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
3. What relationship do the dates have to one another?
___________________________________________________
___________________________________________________
___________________________________________________
4. Why is there no production date?
___________________________________________________
___________________________________________________
___________________________________________________
Task 2:
The assembly electronic turbo drive R-B4## cannot be installed until assemblies
R-B1##. R-B2##, and R-B3## are assembled. Therefore the electronic turbo drive
should be made available later in the basic date scheduling.
1. Call the BOM for material R-F1## in plant 1000 and usage 1 using the
transaction Change BOM in the production master data and branch to the
item overview.
Select the item for assembly R-B4## and choose the Item button. On the
Basic Data tab page, define a positive lead time (“Lead-time offset”)
of 5 working days.
Save the change.
2. Execute multilevel planning for material R-F1## in plant 1000.
Choose planning mode 2 (re-explode BOM and routing) and scheduling
type 1 (basic date scheduling).
3. Refresh the stock/requirements list for material R-F1## in plant 1000 and
analyze the new scheduling situation for the planned order you selected.
Proceed in the same way as described in task 1 point 2.
Continued on next page
324 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 337/522
TSCM40 Lesson: Scheduling
R-F1## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
R-B1## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
R-B4## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
Compare the result with the result from task 1 point 2.
______________________________________________________
______________________________________________________
Task 3:
You should also test the effect of the positive lead time in the BOM item for lead
time scheduling.
1. Execute multilevel planning for material R-F1## in plant 1000:
Choose planning mode 2 (re-explode BOM and routing) and scheduling
type 2 (lead time scheduling).
2. Refresh the stock/requirements list for material R-F1## in plant 1000 and
analyze the new scheduling situation for the planned order you selected
previously.
R-F1## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
R-B1## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 325
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 338/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Goods receipt processing time:
R-B4## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
Do production dates exist now?
______________________________________________________
Does the positive lead time for assembly R-B4## also affect lead time
scheduling?
______________________________________________________
Task 4:
Optional task:
To achieve staging of assemblies or components in accordance with the operation
in lead time scheduling as well, you must make a component or operation
assignment for the affected assemblies or components.
1. Call the BOM for material R-F1## in plant 1000 with usage 1 once more.
Select item R-B4## in the item overview. Choose Extras and then
Operation Assignment.
Select the operation 50 (install electronic turbo pump) in the operation
overview and choose Edit, New assignment and save.
2. Execute multilevel planning for material R-F1## in plant 1000 again.
Choose planning mode 2 (re-explode BOM and routing) and scheduling
type 2 (lead time scheduling).
3. Refresh the stock/requirements list for material R-F1## in plant 1000 and
analyze the new scheduling situation for the planned order you selected again.
R-F1## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
R-B1## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Continued on next page
326 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 339/522
TSCM40 Lesson: Scheduling
Goods receipt processing time:
R-B4## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
Compare the result with the result from task 3 point 2. Will the electronic
turbo pump assembly R-B4## now also be staged at a later date in lead
time scheduling?
______________________________________________________
Hint: The staging date for assembly R-B4## (determined using
component assignment) in lead time scheduling does not necessarily
correspond to the staging date determined in basic date scheduling,
because the positive lead time is independent of lot size.
2008 © 2008 SAP AG. All rights reserved. 327
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 340/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Solution 14: Scheduling
Task 1:
Call the current stock/requirements list for material R-F1## in plant 1000.
Select a planned order in the net segment that is not firmed and does not show
any exception messages.
1. Make a note of the number of the planned order.
______________________________________________________
a) Number of selected planned order: Varies
2. Choose the Order Report pushbutton at the bottom left of the screen.
In the order report, double-click on the respective element and select the
component materials to analyze.
With dependent requirements, always analyze the “corresponding”
requirements coverage element.
To do this, place your cursor on the line and use the Display Element
pushbutton.
R-F1## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
R-B1## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
R-B4## basic dates Production dates
Continued on next page
328 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 341/522
TSCM40 Lesson: Scheduling
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
a)
R-F1## basic dates Production dates
Finish: Varies Finish: Not available
Start: Varies Start: Not available
Goods receipt processing time: 1 day
R-B1## basic dates Production dates
Finish: Varies Finish: Not available
Start: Varies Start: Not available
Goods receipt processing time: 1 day
R-B4## basic dates Production dates
Finish: Varies Finish: Not available
Start: Varies Start: Not available
Goods receipt processing time: 1 day
3. What relationship do the dates have to one another?
___________________________________________________
___________________________________________________
___________________________________________________
a) The order start date of the finished product coincides with
the order finish dates of the assemblies plus the goods receipt
processing times of the assemblies.
4. Why is there no production date?
______________________________________________________________________________________________________
___________________________________________________
a) There are no production dates because material requirements
planning was executed first with scheduling indicator 1 (basic
date scheduling).
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 329
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 342/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Task 2:
The assembly electronic turbo drive R-B4## cannot be installed until assemblies
R-B1##. R-B2##, and R-B3## are assembled. Therefore the electronic turbo drive
should be made available later in the basic date scheduling.
1. Call the BOM for material R-F1## in plant 1000 and usage 1 using the
transaction Change BOM in the production master data and branch to the
item overview.
Select the item for assembly R-B4## and choose the Item button. On the
Basic Data tab page, define a positive lead time (“Lead-time offset”)
of 5 working days.
Save the change.
a) Menu path: Logistics → Production → Master Data → Bills of Material → Bill of Material → Material BOM → Change
2. Execute multilevel planning for material R-F1## in plant 1000.
Choose planning mode 2 (re-explode BOM and routing) and scheduling
type 1 (basic date scheduling).
a) No solution required
3. Refresh the stock/requirements list for material R-F1## in plant 1000 and
analyze the new scheduling situation for the planned order you selected.
Proceed in the same way as described in task 1 point 2.
R-F1## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
R-B1## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
R-B4## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
Compare the result with the result from task 1 point 2.
Continued on next page
330 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 343/522
TSCM40 Lesson: Scheduling
______________________________________________________
______________________________________________________
a) Due to the positive lead time of 5 days, which is set in assembly
R-B4##, the order finish date of this assembly is 5 days after the
order finish date of assembly R-B1##, which does not have positive
lead time set.
Task 3:
You should also test the effect of the positive lead time in the BOM item for lead
time scheduling.
1. Execute multilevel planning for material R-F1## in plant 1000:
Choose planning mode 2 (re-explode BOM and routing) and schedulingtype 2 (lead time scheduling).
a) No solution required
2. Refresh the stock/requirements list for material R-F1## in plant 1000 and
analyze the new scheduling situation for the planned order you selected
previously.
R-F1## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________Goods receipt processing time:
R-B1## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
R-B4## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
Do production dates exist now?
______________________________________________________
Does the positive lead time for assembly R-B4## also affect lead time
scheduling?
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 331
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 344/522
Unit 5: Technical Processes in Requirements Planning TSCM40
______________________________________________________
a) Production dates available: Yes, because requirements planning was
executed with scheduling indicator 2 (lead time scheduling).
No, the positive lead time does not have an effect in lead time
scheduling.
Task 4:
Optional task:
To achieve staging of assemblies or components in accordance with the operation
in lead time scheduling as well, you must make a component or operation
assignment for the affected assemblies or components.
1. Call the BOM for material R-F1## in plant 1000 with usage 1 once more.
Select item R-B4## in the item overview. Choose Extras and then
Operation Assignment.
Select the operation 50 (install electronic turbo pump) in the operation
overview and choose Edit, New assignment and save.
a) Menu path: Logistics → Production → Master Data → Bills of
Material → Bill of Material → Material BOM → Change
2. Execute multilevel planning for material R-F1## in plant 1000 again.
Choose planning mode 2 (re-explode BOM and routing) and scheduling
type 2 (lead time scheduling).
a) No solution required
3. Refresh the stock/requirements list for material R-F1## in plant 1000 and
analyze the new scheduling situation for the planned order you selected again.
R-F1## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
R-B1## basic dates Production dates
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
R-B4## basic dates Production dates
Continued on next page
332 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 345/522
TSCM40 Lesson: Scheduling
Finish: ________________ Finish: ________________
Start: ________________ Start: ________________
Goods receipt processing time:
Compare the result with the result from task 3 point 2. Will the electronic
turbo pump assembly R-B4## now also be staged at a later date in lead
time scheduling?
______________________________________________________
Hint: The staging date for assembly R-B4## (determined using
component assignment) in lead time scheduling does not necessarily
correspond to the staging date determined in basic date scheduling,because the positive lead time is independent of lot size.
a) Yes, the assembly R-B4## will now be staged at a later date
(primarily at the start date for operation 50 assigned to the
assembly for the finished product R-F1##. You can check this on
the Detailed Scheduling tab page in the details for the planned
order at finished product level).
2008 © 2008 SAP AG. All rights reserved. 333
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 346/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Lesson Summary
You should now be able to:• Describe scheduling for in-house production
• Describe scheduling for external procurement
• Understand multilevel backward scheduling
• Make corresponding settings in Customizing
334 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 347/522
TSCM40 Lesson: BOM and Routing Selection
Lesson:
267
BOM and Routing Selection
Lesson Duration: 60 Minutes
Lesson Overview
Planned orders for materials produced in-house are scheduled using the material
master, the routing and the BOM. You therefore need to make the corresponding
settings for selecting the routing and BOM.
Lesson Objectives
After completing this lesson, you will be able to:
• Set the parameters for selecting the BOM
• Set the parameters for selecting the routing
• Make corresponding settings in Customizing
Space for notes
Business Example
You have to select the correct BOMs and routings to schedule in-house production.
BOM Explosion
After the planning run has executed the net requirements calculation, the lot-size
calculation, and the scheduling for a material, it determines the required quantities
for assemblies produced in-house and the materials staging date for the required
components and assemblies. The system determines and explodes the valid BOM
for every new order proposal of an assembly in the planning run. In the case of
existing procurement proposals, the BOM is only re-exploded if the quantity or the
date of the procurement proposal or the BOM structure has been changed. If the
BOM structure has changed, the system creates a planning file entry with the “new
BOM explosion” indicator. If, however, you want a new BOM explosion during
the planning run, you can control this on the initial screen using the planning mode
(planning mode 2 or 3). You can view the detailed data for the BOM explosion in
the planned order on the “Master Data” screen.
2008 © 2008 SAP AG. All rights reserved. 335
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 348/522
Unit 5: Technical Processes in Requirements Planning TSCM40
BOM Explosion: Overview
Put the BOM selection and BOM explosion into context and go over the reasons
for re-exploding a BOM for procurement proposals that already exist: When
manual changes to the date or quantity of the planned order occur, the BOM in
the affected planned order and the dependent requirements are adjusted without a
new planning run; the NETCH/NETPL indicators are set in the planning file of the
affected material and components. If the BOM structure was changed, the “BOM
Explosion” indicator is set in the planning file. This relationship is shown and
explained again in the demonstration at the end of the chapter.
The detailed data for the BOM explosion is displayed in the master data
of a planned order. The production-relevant BOM items are transferred as
components to the planned order (regardless of the MRP type). In addition tothe BOM selection ID/usage, alternative selection indicator/alternative, change
status/explosion date, the BOM status is also crucial as a validity criterion.
The BOM, or all of the materials and BOMs in the complete structure must be
maintained in the corresponding plant.
Figure 121: BOM Explosion: Overview
336 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 349/522
TSCM40 Lesson: BOM and Routing Selection
During the planning run, the system explodes the BOM for every new planned
order of an assembly. The following steps are carried out to determine the valid
BOM:
• In the planning run, the system first checks which BOM usage has the highest
priority. It then checks if this usage has a valid BOM on the explosion date.
If this is not the case, the system creates an exception message.
• If there are different BOM alternatives, the system checks which alternative
corresponds to the prerequisites of the alternative selection.
• If the alternative selection requires the selection to be made in accordance
with the production version, the BOM is already determined by the
production version in which it is contained.
• The change status on the explosion date is determined for the selected BOM
alternative, if necessary.• The BOM items relevant to production are copied to the planned order for
the valid BOM. The dependent requirements quantity is determined by the
quantity factor of the BOM item.
• The dependent requirements date is determined in accordance with the
scheduling of the superior assembly: it is either derived from the basic start
date or from the production start date of the operations in the planned order
for the superior assembly.
The BOM must be maintained in the appropriate plant in order to carry out the
planning run. Furthermore, the validity of a BOM is determined by the BOM
status. To use the BOM in MRP, you must have set the BOM status in the BOM
header so that it is active for MRP.
2008 © 2008 SAP AG. All rights reserved. 337
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 350/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Figure 122: Selection of BOM Usage
With the BOM usage, it is possible to manage separate BOMs for the different
business areas (Engineering/Design, Production, Costing, and so on). The main
differences in the BOM structures result from the different tasks of the various
areas that process different item data.
You have to define which BOM usage is to be used in the planning run. Youdetermine the priority of the usages for the planning run using the selection ID
in Customizing for MRP, in the activity “Define BOM Selection” (Note: The
routing selection is not defined in this activity). You can define a sequence for the
selection of a valid BOM with the “usage” criterion.
If the system does not find a valid BOM in the selected usage, it selects the usage
with the next lowest priority and carries out the check for valid BOMs.
You define the order of priority for the BOM usage, that is, the selection ID, in
Customizing for production basic data, in the activity “Define Order of Priority
for BOM Usages”.
Demonstration: BOM Selection ID/BOM Usage
Purpose
Preparation for exercise
System Data
System: See weekly mail
338 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 351/522
TSCM40 Lesson: BOM and Routing Selection
Client: See weekly mail
User ID: Own user ID
Password: Own passwordSet up instructions: Standard
1. The BOM selection ID for MRP is defined for each plant
→ Customizing: Production – Material Requirements Planning – Planning
– BOM Explosion – Define BOM Selection
Important: Point out that you do not define the routing selection in this
Customizing activity.
2. BOM usage:
→ Customizing: Production – Basic Data – Bill of Material –General Data
– BOM Usage – Define BOM Usages→ Customizing: Production – Basic Data – Bill of Material – Alternative
Determination – Define Order of Priority for BOM Usages
The system determines the first valid usage according to the selection ID.
“Valid” means valid on the explosion date and having the BOM status active.
Hint: For long-term planning, you can use a deviating BOM
selection ID by assignment in the long-term planning scenario.
Selection of Alternative BOM
This selection is made with multiple BOMs.
2008 © 2008 SAP AG. All rights reserved. 339
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 352/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Figure 123: Selection of Alternative BOM
In the case of multiple BOMs, you have to define which alternative BOM is to be
selected during the planning run.
You can define which procedure is to be used to select the BOM in the material
master record, in the “Selection method” field for the MRP data (MRP 4).Three options are available:
• BOM selection using the order quantity (lot size): The order quantity is
based on the lot size in accordance with the selected lot-size procedure.
• Selection according to explosion date: The system uses the explosion date
to determine the valid BOM (or the valid routing) for a planned order. In
Customizing, you can define whether the order start date, order finish date,
or fixed key date of the BOM explosion number is selected.
• Selection according to production version: The production version
determines the different production methods that can be used to produce a
material. The production version therefore contains a routing and a BOM.The alternative BOM to be selected, the BOM usage, the lot-size range, and
the effectivity period of a BOM can be defined for the alternative selection.
With alternative selection indicator 3, the selection is always made according
to production version; with indicator 2 , the selection is made according to
production version when this is possible (if not, then according to lot size).
340 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 353/522
TSCM40 Lesson: BOM and Routing Selection
Selection by Order Quantity (Lot Size)
The lot-size range of the alternatives of a multiple BOM is determined in the BOM
header. If the system does not find a valid or suitable alternative for the order
quantity, it creates an exception message.
Figure 124: Selection by Order Quantity (Lot Size)
During the planning run, the system checks whether a valid alternative BOM
exists for the order quantity (lot size). You must defined the lot-size range of
an alternative in the BOM. The valid alternative is exploded and dependent
requirements are created for the corresponding components. If the system does
not find a valid or suitable alternative for the order quantity, it creates an exception
message.
Defining the Explosion Date
This setting is also valid for defining the change status of the BOM (alternative).
2008 © 2008 SAP AG. All rights reserved. 341
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 354/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Figure 125: Defining the Explosion Date
In Customizing for MRP, in the activity “Define BOM Explosion Control”, you
can define the explosion date for the BOM and routings selection at plant or MRP
group level.
The explosion date determines which BOM (or which routing) is used for the
explosion and thus for determining the dependent requirements for the planned
order. This means that the BOM that is valid on the explosion date is selected andthe system generates dependent requirements for the components entered there.
The following options are available for the explosion date:
• Order start date
• Order finish date
• BOM explosion number (gross date)
Demonstration: Explosion Date for BOM
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
342 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 355/522
TSCM40 Lesson: BOM and Routing Selection
1. → Customizing: Production – Material Requirements Planning – Planning
– BOM Explosion – Define BOM Explosion Control
Explosion According to Order Start Date
Point out that if the order start date is adjusted to the production start date,
the BOM is still exploded on the original order start date. This means that the
explosion date and the final order start date differ from one another.
Figure 126: Explosion According to Order Start Date
For BOM explosion according to date (selection method indicator = 1),
assembly-specific periods are defined, within which certain alternative BOMs are
to be used. The system then checks the defined period for the assembly during
the planning run. The system checks in which period the explosion date lies, andselects the corresponding alternative BOM. The default setting is that the order
start date is set as the BOM explosion date. The suitable alternative is exploded
and dependent requirements are created for the corresponding components.
To define the alternative BOM for each period, you choose “BOM via dates” in
the master data in the MRP menu. To define the alternative selection using dates,
enter the following parameters in the table: Material number, plant, BOM usage,
and the valid-from date, from which the alternative BOM is to be used in the
planning run, and the BOM alternative.
2008 © 2008 SAP AG. All rights reserved. 343
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 356/522
Unit 5: Technical Processes in Requirements Planning TSCM40
In order to assign several alternative BOMs with different effectivity periods to a
material, you define the beginning of the effectivity period for each alternative in
the “Valid from” field. The beginning of the validity period of the next alternativeon the time axis marks the end of the effectivity period of the previous alternative.
The system selects the BOM and explodes it as soon as the basic dates have been
determined in the scheduling, that is, in the case of lead time scheduling even
before the scheduling is carried out via the routing. If the basic date is to be
adjusted to the production date (for example, if the deadline is missed), the BOM
is still exploded on the original basic date. The BOM explosion date and the final
basic date are different in this special case.
Figure 127: Explosion Using Order Finish Date
Here you can see the BOM explosion situation if you define in Customizing that
the BOM explosion date is to be set according to the planned order finish date.
The system selects and explodes the BOM as soon as the order finish date has beendetermined in the scheduling. If, in the case of lead time scheduling, the order start
date is to be adjusted to the production dates, this does not change the order finish
date, that is, BOM explosion date and the final basic date do not differ in this case.
If the system does not find a valid or suitable alternative, the BOM with the
suitable lot size is used.
344 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 357/522
TSCM40 Lesson: BOM and Routing Selection
Explosion Using the BOM Explosion Number
You define BOM explosion numbers by entering the fixed key date in material
requirements planning.
→ Logistics – Production – MRP – Master Data – BOM Explosion Number – Edit
(When you enter a material number, the BOM explosion number can only be
used for this material.)
You can assign the BOM explosion numbers in the following places:
1. Customer requirements (item screen),
2. Planned independent requirements (schedule line screen, settings → BOM
explosion number),3. Sales order (Item detail screen: Sales A),
4. Planned order (header screen).
In the Customizing for material requirements planning, you can restrict the use
of BOM explosion numbers to make-to-order production and engineer-to-order
production.
→ Customizing: Production – Material Requirements Planning – Planning –
BOM Explosion – Define BOM Explosion Control
Figure 128: Explosion Using the BOM Explosion Number
2008 © 2008 SAP AG. All rights reserved. 345
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 358/522
Unit 5: Technical Processes in Requirements Planning TSCM40
If the order start date of the planned order is set as the explosion date for the
BOM explosion, there could be large intervals between the explosion dates of the
individual BOM structures under certain circumstances, in the case of multipleBOMs. If BOMs (alternatives) change over time due to different requirements,
the situation could occur that an assembly used several times is produced using
different BOM compositions.
If you would like to ensure for a particular production unit that the whole BOM
structure is always exploded with the same explosion date, you can assign a BOM
explosion number to the planned independent requirements or the sales order
or to a planned order.
Using the BOM explosion number, you can define a standard explosion date for
all BOM levels. This “gross date” is contained in the BOM explosion number.
The BOM is exploded for all level with this gross date.
You maintain a BOM explosion number in the MRP master data. You can define
the gross date for an alphanumeric BOM explosion number.
The BOM explosion number can be entered and pre-defined in the planned order
(header screen), in the planned independent requirement (Schedule Lines screen,
Settings -> BOM explosion number ), in customer requirements or in the sales
order (item screen Sales or item detail screen Sales A).
Selection by Production Version
With the selection “by production version” (with selection method indicator 2),
if the system cannot find a production version or one which is suitable as far as
lot size and validity period is concerned, then it selects a BOM according to the
normal logic, as thought the selection method indicator were set to “blank”.
With selection “strictly according to production version” (with the selection
method indicator set to 3), the system does not select a BOM (and does not issue
an exception message) if it does not find a suitable production version.
346 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 359/522
TSCM40 Lesson: BOM and Routing Selection
Figure 129: Selection by Production Version
There may be different BOMs according to which a material is produced. The
production of a material can also be described in various routings. The material
can be produced on different production lines (work centers). The data on the
different methods according to which a material can be produced, can be combinedin the production version and assigned as such to the material.
The production version defines the following data:
• Alternative BOMs and BOM usages for the BOM explosion
• Task list type, task list group, and group counter of the routing
• Validity period of the production version (fields “Valid from” and “Valid to”)
• Lot-size area of the production version (fields “Lot-Size from” and “Lot-Size
to”)
If the value “2” has been entered for the selection method indicator in the material
master, the BOM is selected by production version, as long as valid data isavailable. If the system does not find a production version or does not find a
production version which is suitable as far as usage, lot-size and validity period is
concerned, then the selection occurs according to lot-size in the same way as when
the selection method indicator is set to “blank”. If the indicator is set to “3”, the
selection occurs according to production version, which means that if the system
does not find any selection version or does not find any appropriate selection
version, it cannot create a production order and issues an exception message.
2008 © 2008 SAP AG. All rights reserved. 347
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 360/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Demonstration: Selection of Alternative BOM
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1.
Hint: The selection of an alternative BOM is only relevant for
multiple BOMs. You therefore create a new BOM alternative in this
demonstration (step 2).
Display and explain the selection method indicator (MRP 4).
2. Selection according to lot size: Create a new BOM alternative for material
R-F1## as a copy of the existing BOM. Copy all components, increase the
number of shafts to two, and save.
Assign the two alternatives in the lot-size range header:
Alternative 1: 1 to 10 pcs
Alternative 2: 11 to 100 pcs
Change the quantity in an existing planned order that is not firmed in the
components:
First 5 pcs, then 15 pcs, each time showing the master date and the
component overview of the planned order.
Conclusion: If the selection method indicator is blank in the material master,
the system determines the BOM alternative according to lot-size.
3. Selection according to explosion date: Set the selection method indicator 1
in the material master,
Define the temporal validity of the two alternative BOMs for R-F1##:
→ Logistics – Production – MRP – Master Data – BOM by Date
or
→ Customizing: Production – Basic Data – Bill of Material – Alternative
Determination – Define Alternative Determination for Multiple BOMs
348 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 361/522
TSCM40 Lesson: BOM and Routing Selection
Alternative 1: Valid from today
Alternative 2: Valid from today + 2 months
Conclusion: If the selection method indicator is set to 1 in the material
master, the system determines the BOM alternative according to validity
period (planning relevance).
If the system does not find a valid or suitable alternative, the BOM with
the suitable lot size is used.
4. Determining the explosion date with explosion according to date and
in consideration of the determination of the valid change status of the
(alternative) BOM.
→ Customizing: Production – Material Requirements Planning – Planning
– BOM Explosion – Define BOM Explosion Control
5. Explosion Using the BOM Explosion Number
a. Create a BOM explosion number, for example, SCM240 with a fixed key
date = today’s date, without restriction to material number.
b. Enter the BOM explosion number in a non-firmed planned order.
c. Execute single-item, multilevel planning.
d. Display the planned order, order report, open all, display the BOM
explosion number and the resulting explosion date on the master data tab
page in the planned orders of the finished product and in one assembly.
6. Call the production version of material T-SEL: Display the possibility for
defining production versions.
Change Status According to Order Start Date
Change Status According to Order Finish Date
Change Status According to BOM Explosion Number
Selection of the change status is relevant for BOMs affected by change
management (the BOM must have a change number and an associated changedate).
2008 © 2008 SAP AG. All rights reserved. 349
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 362/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Figure 130: Change Status According to Order Start Date
The BOM (or alternative BOM) can have different validity periods on the time
axis due to changes that have been made (for example in the BOM composition).
The BOM can have different compositions (statuses) at different times. Every
change status has a valid-from date and a valid-to date, defined by the valid-from
date of the next change.
The BOM status at the time of the explosion date is exploded. Whether this is the
order start or finish date, or the fixed key date of the BOM explosion number,
depends on the settings made in Customizing (Customizing activity “Define BOM
Explosion Control”).
350 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 363/522
TSCM40 Lesson: BOM and Routing Selection
Figure 131: Change Status According to Order Finish Date
Figure 132: Change Status According to BOM Explosion Number
By entering a BOM explosion number, you can explicitly define an explosion date
(fixed key date) for a BOM structure.
2008 © 2008 SAP AG. All rights reserved. 351
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 364/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Demonstration: Relationship Between BOM Explosion,Change Status, and Planning File
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard1. Change BOM with change management → the “BOM Explosion” indicator
is set in the planning file
2. Execute the planning run to reset the indicator
3. Change the order start date of the planned order so that the new change
status is called; display the components of the planned order → they now
correspond to the new status; NETCH/NETPL are set in the planning file.
Figure 133: Summary: BOM Selection
352 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 365/522
TSCM40 Lesson: BOM and Routing Selection
The BOM selection in the MRP run has three steps:
1. The BOM usage is defined by the BOM selection ID, which you assign on a
plant-by-plant basis in the Customizing activity “Define BOM Selection”.
2. The alternative BOM is determined according to the setting for the BOM
selection indicator in the material master. If the selection is to be made
according to explosion date, you should enter the date to be used in the
Customizing activity “Define BOM Explosion Control”.
3. The change status of the BOM is then determined using the explosion date.
The same Customizing setting as in step 2 is the basis for the choice of date.
Figure 134: Routing Selection
If you start the planning run with the scheduling indicator 2 (lead time scheduling
and capacity planning), the system selects the routing for each planned order. The
system calculates the dates, the staging of materials and the capacity requirements
using the routing.
The selection method indicator in the material master (MRP 4) is also crucial for
selecting the routing:
• If it has been set to value 2 or 3 (selection by production version), the routing
is also selected according to the selected production version.
• Otherwise, the selection ID of the routing selection, which is defined in
Customizing for MRP at detailed scheduling level in the activity “Define
Scheduling Parameters for Planned Orders”, decides which routing is
selected.
2008 © 2008 SAP AG. All rights reserved. 353
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 366/522
Unit 5: Technical Processes in Requirements Planning TSCM40
You define the selection ID of the routing selection in Customizing for Production
under basic data. The explosion dates of the BOM and the routing are identical.
If the planned order is managed using Engineering Change Management, thesystem uses the routing with the change status at the time of the BOM explosion
date. The task list group and the group counter for the routing as well as the
corresponding scheduling and capacity requirements can be seen on the “Detailed
Scheduling” screen for the order.
Demonstration: Routing Selection
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. The selection method indicator in the material master is also responsible for
the routing selection, as are the following two settings in Customizing:
→ Customizing: Production – Material Requirements Planning – Planning
– Scheduling and Capacity Parameters – Define Scheduling Parameters for Planned Orders
for each plant, order type and production controller:
Selection ID Detailed Scheduling
→ Customizing: Production → Basic Data → Routing → Routing Selection
→ Select Automatically:
using the selection ID: Priority sequence for task list type, usage and
status
With selection according to production version (with selection method
indicator 2 or 3), if the system cannot select a routing according to productionversion, it determines the routing using the standard logic, as if the selection
method indicator were set to blank.
(Note: For indicator 2, this is clear and identical to the BOM selection; this is
not the case for indicator 3. This can lead to problems with indicator 3 when
you convert the planned order to a production order because the production
order with standard settings requires a routing according to production
version and does not use the routing selected in the planned order.)
354 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 367/522
TSCM40 Lesson: BOM and Routing Selection
281 Exercise 15: Routing and BOM Selection
Exercise Duration: 10 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Analyze the selection of routings and BOMs in the MRP run and make the
appropriate settings in the system.
Business Example
Using material R-F1## in plant 1000, the project team investigates the technical
processes involved in selecting routings and BOMs during the planning run.
Task 1:
Call the stock/requirements list for the material R-F1## in plant 1000, then
call three existing planned orders, one after the other, in the net segment and
check which BOM was selected by looking at the Master Data tab page for
the respective planned order.
1. Have the production dates and the corresponding capacity requirements been
created on the basis of the same routing for all the planned orders?
______________________________________________________
2. Which settings in the system have caused these routings to be selected?
Individually:
What value does the selection method indicator in the material master for
material R-F1## have and what does this mean?
______________________________________________________
What Selection ID for detailed planning is set in Customizing for the
existing planned orders (you can find this selection ID in the Customizing
IMG activity Define Scheduling Parameters for Planned Orders)?
______________________________________________________
Task 2:
Evaluate the BOM explosion in the planned orders:
1. Call the stock/requirements list for material R-F1## in plant 1000 and
analyze the planned orders you looked at before. On the Master Data tab
page for the respective planned order, find out which BOM was exploded
on which date:
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 355
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 368/522
Unit 5: Technical Processes in Requirements Planning TSCM40
1. BOM: ______________
______________
Date: _____________________
_____________________
2. BOM: ______________
______________
Date: _____________________
_____________________
3. BOM: ______________
______________
Date: _____________________
2. Now analyze the detailed data for the planned orders. On which basic date
was the BOM for each planned order exploded?
______________________________________________________
3. Which indicator is responsible for selecting the alternative BOM and what
setting has been made here?
______________________________________________________
356 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 369/522
TSCM40 Lesson: BOM and Routing Selection
Solution 15: Routing and BOM Selection
Task 1:
Call the stock/requirements list for the material R-F1## in plant 1000, then
call three existing planned orders, one after the other, in the net segment and
check which BOM was selected by looking at the Master Data tab page for
the respective planned order.
1. Have the production dates and the corresponding capacity requirements been
created on the basis of the same routing for all the planned orders?
______________________________________________________
a) Same routing: Yes
2. Which settings in the system have caused these routings to be selected?
Individually:
What value does the selection method indicator in the material master for
material R-F1## have and what does this mean?
______________________________________________________
What Selection ID for detailed planning is set in Customizing for the
existing planned orders (you can find this selection ID in the Customizing
IMG activity Define Scheduling Parameters for Planned Orders)?
______________________________________________________
a) Selection method indicator in the material master: “Blank”
Meaning: The selection is made according to the order quantity.
Selection ID for the detailed planning in Customizing: (Menu
path: Customizing: Production → Material Requirements Planning
→ Planning → Scheduling and Capacity Parameters → Define
Scheduling Parameters for Planned Orders)
The selection ID detailed scheduling 01 is valid for planned orders (any
order type and production controller) in plant 1000.
Using this selection ID, the system searches for a routing with usage 1
(production) and status 4 (released general) as the highest priority (thiscan be checked using the transaction OPEB).
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 357
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 370/522
Unit 5: Technical Processes in Requirements Planning TSCM40
Task 2:
Evaluate the BOM explosion in the planned orders:
1. Call the stock/requirements list for material R-F1## in plant 1000 and
analyze the planned orders you looked at before. On the Master Data tab
page for the respective planned order, find out which BOM was exploded
on which date:
1. BOM: ______________
______________
Date: _____________________
_____________________
2. BOM: ______________
______________
Date: _____________________
_____________________
3. BOM: ______________
______________
Date: _____________________
a) BOM and date: Varies
2. Now analyze the detailed data for the planned orders. On which basic date
was the BOM for each planned order exploded?
______________________________________________________
a) Basic date: The BOMs were exploded on the respective order
start date.
3. Which indicator is responsible for selecting the alternative BOM and what
setting has been made here?
______________________________________________________
a) Criterion for the alternative BOM selection: The alternative selection
field in the material master that is responsible for controlling the
selection has the value “blank” (selection by order quantity), as
you have seen before.
358 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 371/522
TSCM40 Lesson: BOM and Routing Selection
Lesson Summary
You should now be able to:• Set the parameters for selecting the BOM
• Set the parameters for selecting the routing
• Make corresponding settings in Customizing
2008 © 2008 SAP AG. All rights reserved. 359
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 372/522
Unit Summary TSCM40
Unit Summary
You should now be able to:
• Understand the net requirements calculation
• Work with safety stocks
• Use the dynamic safety stock
• Use the safety time
• Use static lot-sizing procedures
• Use lot-sizing by period
• Use optimizing lot-sizing procedures
• Make corresponding settings in Customizing
• Use the procurement type for in-house production
• Use the procurement type for external procurement
• Use the quota arrangement
• Describe scheduling for in-house production
• Describe scheduling for external procurement
• Understand multilevel backward scheduling
• Make corresponding settings in Customizing
• Set the parameters for selecting the BOM
• Set the parameters for selecting the routing
• Make corresponding settings in Customizing
360 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 373/522
Unit 6 287 Evaluating and Processing the MRP
Results
Take a look at the functions of the MRP list and the stock/requirements list,
including the corresponding collective evaluations. Focus in particular on days’
supply and receipt days’ supply, exception messages, firming, the rescheduling
check, and the evaluation functions of the order report and pegged requirements.
If necessary, you can work through this unit directly after unit 1.
Unit Overview
The MRP results are usually processed after a total planning run. The aim is to
process problem situations that have led to the creation of exception messages
manually.
The normal tools for this manual processing are the stock/requirements list and
the MRP list with their respective collective accesses. As well as exception
messages, these lists offer a range of functions for processing the planning results:
Rescheduling data, firming, evaluation functions such as order report or pegged
requirements, stock days’ supply and receipt days’ supply.
The stock/requirements list and the MRP list are set up and used in the same
way. However, the detailed functions of the two lists differ. Both lists, with
their various functions, are used not only in operative requirements planning but
also in long-term planning. They are therefore one of the most important tools
for the MRP controller.
Unit Objectives
After completing this unit, you will be able to:
• Work with the stock/requirements list
• Use the MRP list
• Use navigation profiles
• Deploy the display filter and selection rules
• Use the collective call
2008 © 2008 SAP AG. All rights reserved. 361
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 374/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
• Use the planning table for repetitive manufacturing
• Use production versions
• Interpret exception messages
• Make corresponding settings in Customizing
• Interpret ranges of coverage
• Use the pegged requirements display
• Use the order report
Unit Contents
Lesson: MRP List and Stock/Requirements List... .. .. .. .. .. .. .. .. .. .. .. .. .363
Demonstration: Difference Between the Stock/Requirements List and
the MRP List . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .367Demonstration: Collective Access to MRP Lists andStock/Requirements Lists .... ... ... ..... ... ... .... ... .... .... ... ... .... ... 370Demonstration: Order Report/Order Tree/Pegged Requirements . .373
Exercise 16: Functions of the Stock/Requirements List. .. .. .. .. .. .. .. 377Exercise 17: Display Filter, Selection Rule (Optional) .. .. .. .. .. .. .. .. 385
Lesson: Planning Table ...... .... ... ... ..... ... ... .... ... .... .... ... ... ... .... .389Demonstration: Planning Table ..........................................393
Lesson: Exception Messages .... ... ... ..... ... ... .... ... .... .... ... ... .... ... 398
Demonstration: Exception Messages .. .. .. .. ... .. .. ... ... .. .. .. .. ... ... 401
Demonstration: Rescheduling check .. .. .. .. ... .. .. ... .. ... .. .. .. .. ... ..403Lesson: Additional Evaluation Aids.. .. ... .. .. .. .. ... .. .. ... .. ... .. .. .. .. ... ..407
Demonstration: Stock Days’ Supply and Receipt Days’ Supply .. . .. 410Exercise 18: Collective Display of MRP Lists.. .. .. .. .. .. .. .. .. .. .. .. .. .413
Exercise 19: Rescheduling Check (Optional).. .. .. .. .. .. .. .. .. .. .. .. .. .417
362 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 375/522
TSCM40 Lesson: MRP List and Stock/Requirements List
Lesson:
289
MRP List and Stock/Requirements List
Lesson Duration: 60 Minutes
Lesson Overview
You evaluate and, if necessary, process the MRP results from two central lists:
The stock/requirements list and the MRP list.
Lesson Objectives
After completing this lesson, you will be able to:
• Work with the stock/requirements list
• Use the MRP list
• Use navigation profiles
• Deploy the display filter and selection rules
• Use the collective call
Space for notes
Business ExampleA range of different functions are available in both lists for evaluating and
processing the MRP results. The MRP controller needs to know how to use these.
MRP List and Stock/Requirements List
2008 © 2008 SAP AG. All rights reserved. 363
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 376/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Figure 135: MRP List and Stock/Requirements List
You can evaluate the planning situation or the result of a planning run by using
the stock/requirements list or the MRP list. You can do this using individual
access or collective access. The current stock/requirements list is a dynamic list
that shows the current levels of stock, requirements, and receipts. You are able
to view any changes as soon as the stock/requirements list is called, or in the
stock/requirements list display screen when the elements are read in real time from
the database using the “Refresh” function. The MRP list displays the result of thelast planning run and is therefore static: Changes made after the planning run are
not displayed. You can determine whether an MRP list is to be created during the
planning run. The basic structure of both lists is the same:
• Links are in the form of a tree for the worklist of the MRP controller.
• Above the list is the header with the material number. You can display
additional information in the header details.
• The list itself contains the individual MRP elements and the corresponding
available quantities.
User-specific settings enable you to adapt the lists to your personal requirements
(see Customizing for the Evaluation of Material Requirements Planning,
“Configure MRP List / Stock/Requirements List”). You can use a customer exit
to display additional data, which you can then access using a function key (see
“Customer Exit: Program Additional Columns” in Customizing).
364 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 377/522
TSCM40 Lesson: MRP List and Stock/Requirements List
Functions of the Stock/Requirements List
Functions of the MRP List
The rescheduling check is available in both lists, but the logic in the two lists
is different: The rescheduling check in the MRP list is based on the pegging
function (connection between requirement and receipt elements). In the dynamic
stock/requirements list, there is no pegging and so the rescheduling check occurs
in the same way as the rescheduling check for firmed receipts, that is, based only
on the available quantity.
Figure 136: Functions of the Stock/Requirements List
The stock/requirements list offers several display options: You can display
different dates (the availability date or the goods receipt date, with/without safety
time). You can work with display filters and selection rules, you can work in the
period totals display, and so on. You can define the display accordingly in your
own personal settings. “Period Totals” is a display function in the MRP list andstock/requirements list evaluations that groups the planning results into periodic
buckets (for example, weekly or monthly buckets). In the “Define Period Display
for Period Totals” activity in Customizing, you define which periods are to be
shown in the “Period Totals” display. The periods you select here are shown on
various tab pages in the Period Totals display.
2008 © 2008 SAP AG. All rights reserved. 365
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 378/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
You can process individual MRP elements from the list. Alongside the standard
functions (such as search functions), you also have functions defined on a
user-specific basis that can be accessed through the “Navigation Profile” andpersonal favorites. You can also process the list with a range of user-specific
functions at a material level.
You can analyze the capacity situation from the current stock/requirements list.
For each work center and capacity category, the system displays the available
capacity, the total capacity requirements, and the capacity requirements of this
material per period. Overload situations are highlighted in color. Note that planned
orders that have not been scheduled using detailed scheduling (created by a
planning run with the scheduling indicator 1) do not create capacity requirements.
Figure 137: Functions of the MRP List
The functions in the MRP list are largely identical to the functions in the
stock/requirements list, as far as processing MRP elements or display options
is concerned, for example. Selection rules, however, are only used in the
stock/requirements list. In contrast to the stock/requirements list, you can set a
processing indicator for the MRP list. This indicator serves to highlight lists that
have already been processed by the MRP controller.
You define the display of the header details for the MRP evaluations in the
Customizing IMG activity “Define Screen Sequence for Header Details”. The
header details of the MRP list contain additional data for the planning run. In
particular, they contain the number of exception messages that have occurred
during the planning of a material.
The header details show an overview of master data and transaction data for each
material. This data is grouped together according to topic in individual screens.
The MRP type controls which screens are displayed in the requirements planning
366 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 379/522
TSCM40 Lesson: MRP List and Stock/Requirements List
evaluations. To do this, the screen sequences are provided with a key, which is
then assigned to the MRP type. It is therefore possible to display master data for
the evaluation of consumption-based materials that is different to that displayedfor MRP planned materials.
Demonstration: Difference Between theStock/Requirements List and the MRP List
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Call the stock/requirements list for material R-F1##. First display and
explain the basic structure of the list.
• Display the individual MRP elements
• Variable header
• Overview tree.
Display some special functions and (briefly) explain the following:
• Period totals display
• Displaying, changing, converting MRP elements from the list
• capacity check
• Pegged requirements and order report
2. Change the first planned order from the list, refresh the list: The changed
planned order is displayed.
3. Call up the MRP list for material R-F1##: The change made to the planned
order cannot be seen here.
Display the first planned order from the list in the Detail view: The changed
amount is displayed.
Conclusion: The MRP list is the (static) result of the last planning run.
4. Carry out material requirements planning for material R-F1##: The MRP list
is updated (when you access it again).
2008 © 2008 SAP AG. All rights reserved. 367
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 380/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Figure 138: Collective Access to Stock/Requirements List
Collective access to the stock/requirements list is possible using a large number
selection criteria. For example, you can display all of the lists for which you are
responsible as MRP controller.
Firstly, a material overview is displayed with all of the selected materials. If you
have set the “Set up Lists in Background” indicator, the following are available
for orientation: Traffic lights, various search functions in the overview and in theindividual lists, and sort functions (also for individual customer segments by
date or number). You can use the search function to select materials by certain
exception messages. You can make user-specific definitions for the display of
traffic lights according to day’s supply violations or exception groups. You can
also define user-specific sort criteria. From the overview, you can go to the
individual lists and process the materials there. For example, if you have used
the search function to select several lists for processing, you can jump from one
list directly into the next list selected.
368 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 381/522
TSCM40 Lesson: MRP List and Stock/Requirements List
Figure 139: MRP list collective display
The selection criteria for collective access in the MRP lists are not the same as
those in the stock/requirements lists. Here, for example, the MRP or processing
date and/or the processing indicator for the selection are available.
The orientation guides in the material overview correspond with those in the
stock/requirements list. It is also possible to search for processing indicators or
new exceptions.
Figure 140: Planning segments
2008 © 2008 SAP AG. All rights reserved. 369
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 382/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
The MRP list and the stock/requirements list are divided up into various planning
segments. This means that related MRP elements are also displayed together.
The individual stocks, receipts, and issues are displayed and planned within the
appropriate segment. The MRP calculation takes place within the individual
segments.
Demonstration: Collective Access to MRP Lists andStock/Requirements Lists
Purpose
Preparation for exercise
Hint: The two collective accesses have different selection screens. You
do not, however, have to explain every individual field.
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Display the collective access for the MRP lists and explain the variousselection parameters:
• MRP controller
• Product group
• MRP date
• Exception groups
• Processing indicator (only in MRP lists)
• Material data
2. Display the collective access for the stock/requirement lists and explain the
various selection parameters:
• Product group, MRP controller, production line ...
• Material dates
• Planning file entry for MRP
• The “Set up Lists in Background” indicator is necessary if the lists are
to be sorted according to certain criteria and/or the system is to search
in the individual lists.
370 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 383/522
TSCM40 Lesson: MRP List and Stock/Requirements List
Point out the settings and functions of the traffic lights and the sort and
search functions.
Material Tree
Worklist tree (you define the criteria for displaying the traffic lights from
the list).
Product groups tree
Figure 141: Material Tree
Displaying the material tree is optional (this can be set in the user settings). Press
the “Material Tree” button.
You can change the layout of the tree and display the following:
• Worklist tree: All materials in the current session are displayed (especially if
the initial access is via collective access).
• Order tree: The individual component requirements for the selected order or
requirement are displayed at several levels (see next page).
• Product group tree: All materials of a product group (only if using collective
access via a product group) are displayed.
You can display the stock/requirements list or MRP list for a material by
double-clicking on the material in the tree.
2008 © 2008 SAP AG. All rights reserved. 371
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 384/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
For the worklist tree, you can set in which order the fields are to be displayed.
User-specific definitions for the traffic lights are also possible. User-specific
sortings and groupings (for example, according to the processing indicator) arepossible. You can search for specific materials (according to exception messages,
for example).
Order Tree
Changed as of R/3 Enterprise, based on the order report
Figure 142: Order Tree
If you work with the order tree in the stock/requirements list or MRP list, the
system displays all component requirements relating to a selected order or
requirement at several levels. This function is based on the order report. If
problems occur during material requirements planning, you are notified by
exception messages.
When you navigate in the order tree, the correct stock/requirements list or MRP
list is displayed in a chart, and the cursor is positioned on the according component
requirement. This way you can quickly get an overview of the stock situations in
all levels of the order structure.
372 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 385/522
TSCM40 Lesson: MRP List and Stock/Requirements List
Demonstration: Order Report/Order Tree/PeggedRequirements
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard1. Call up the stock/requirements list of material R-F1##, and display and
explain the order report function for the first planned order.
2. Display the order tree for the first planned order (function is the same as that
of the order report).
3. Call the list of the component R-T1## from the order tree; call the pegged
requirements for the first requirement in the list; reproduce the path to the
order.
4. As of R/3 Enterprise: Direct navigation from a requirements element to its
pegged requirement.
Display Filter and Selection Rule
Explain the difference between both groups. One of the main differences between
the two filters is the influence they have on the available quantity.
As of R/3 Release 4.6C, the display filters can be assigned additional selection
criteria such as customer, vendor, ... .
→ Customizing: Production – Material Requirements Planning – Evaluation –
Filter – Define Selection Rules / Define Display Filter
2008 © 2008 SAP AG. All rights reserved. 373
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 386/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Figure 143: Display Filter and Selection Rule
You define whether selection rules and display filters are to be used when accessing
the list. This is done by choosing the indicator “With filter” in the initial screen, or
in the list itself by choosing the icon “Filter on”, or in the user-specific settings.
Display filters are used in the stock/requirements list and in the MRP list. This
is purely a display function and display filters have no influence on the MRP
elements that are used in the calculation of the available quantity. They are definedin the “Define Display Filters” activity in Customizing.
Selection rules can only be used for the current stock/requirements list. You
define which MRP elements are displayed and which of these elements are used
in the calculation of the available quantity. They enable the analysis in the
stock/requirements list of various planning situations that are different with regard
to the MRP elements that are taken into account. Selection rules have no influence
on the requirements calculation. They are defined in the “Define Selection Rules”
activity in Customizing.
Navigation profileIf you are not already working with it, show the options for using the navigation
profile to branch from the stock/requirements list to other important functions.
The navigation profile function is enhanced by the possibility of defining your own
favorites. To maintain your own favorites, see SAP Notes 312678 (Changeability
of Customizing Tables in the Production System) and 501318 (Authorization
for Maintenance of Own Favorites).
374 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 387/522
TSCM40 Lesson: MRP List and Stock/Requirements List
→ Customizing: Production – Material Requirements Planning – Evaluation
– Define Navigation Profiles
Figure 144: Navigation Profile
A navigation profile contains transaction calls for transactions that can be called
directly from the stock/requirements list, or the MRP list. The transactions areeither general, (meaning actions at material level), or they refer to a particular
MRP element.
You define a navigation profile in the Customizing activity “Define Navigation
Profiles” and you can assign yourself to a profile in the user-specific settings
(on the “General Settings” tab page).
In a navigation profile, you can determine any number of transaction calls.
However, the display in the list is limited to five general transaction calls and two
transaction calls per MRP element: The system always displays the first five or
first two transaction calls that are relevant for the context.
For each transaction call, you can pre-assign three parameters for the initial screenof the transaction. You can also connect the offering of a transaction to certain
parameters from the material master: Procurement type, material type, MRP
group, MRP type.
A function similar to the navigation profiles is available with the selection of
personal favorites, where you can also activate up to five general transaction
calls (choose “Environment - Own Favorites”). Apart from that, you can activate
two favorites per MRP element as transaction calls (choose the “*” button in the
details for the MRP element).
2008 © 2008 SAP AG. All rights reserved. 375
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 388/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Settings that can be made individually
Explain the various user-specific settings that are possible.
Summarize the options already shown and explain other settings that can be made.
New as of R/3 Enterprise: Buffered reading of order report
Figure 145: Settings That Can Be Made Individually ...
You can use your personal settings to specify a number of default display options
for the stock/requirements list and the MRP list.
Your personal settings (as well as your “Own Favorites” in Environment - Own
Favorites) determine the screen that appears when accessing the lists. From the
lists, you can change the various settings at any time - for example, you can show
or hide the overview tree.
You define the screen sequence of the header details in the Customizing for the
MRP type.
A user exit for showing user-specific categories is available.
376 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 389/522
TSCM40 Lesson: MRP List and Stock/Requirements List
299 Exercise 16: Functions of the
Stock/Requirements ListExercise Duration: 15 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Use the main functions and display options for the stock/requirements list,
• Make your own personal settings for the display.
Business Example
As a member of the project team, you want to familiarize yourself with the display
options that are available for the stock/requirements list and the MRP list.
Task 1:
You check the personal settings with which you can define the screen for the
stock/requirements list and the MRP list and, if necessary, make different settings.
1. From the MRP menu, call the stock/requirements list for material R-F1##
in plant 1000. To view the default settings that were used to access the list,
choose Settings from the menu and then Settings again. The corresponding
data is sorted thematically on several tab pages. What are the names of the
tab pages?
__________________ __________________
__________________ __________________
__________________
2. In what form are the requirements displayed with the existing settings
(Display tab page)?
__________________________________________________
__________________________________________________
3. Does the system display the availability date or the goods receipt date as the
date of an MRP element (Dates tab page)?
__________________________________________________
4. Return to the Display tab page and select the field With header details for
material. Choose Continue to return to the list. Are the header details
now displayed?
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 377
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 390/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
______________________________________________________
In the header details, find which strategy group is specified in the material
master:
______________________________________________________
Choose Collapse header details from the list.
Task 2:
You want to call frequently used transactions directly from the current
stock/requirements list. To do this, assign a navigation profile to your user.
1. In the stock/requirement list, choose Environment from the menu and then
Navigation Profile - Assign. Use the F4 help to enter the profile SCM001
in the Navigation Profile field and Copy the entry.
2. Which transaction calls are now displayed above the list header?
__________________ __________________
__________________ __________________
__________________
3. You decide to copy this setting into your personal settings. To do this,
choose Settings again and Save.
4. Exit the stock/requirements list and then call it again. Are the transactioncalls displayed?
______________________________________________________
Task 3:
In the stock/requirements list for material R-F1## (plant 1000), display the
material tree by choosing Show Overview Tree.
1. Which materials are displayed in the overview?
_________________________________________________
_________________________________________________
2. Switch to the stock/requirements list for the material R-B1## by entering
the corresponding material number in the Material field in the list header
and choose Enter.
What materials now display in the material tree?
_________________________________________________
Continued on next page
378 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 391/522
TSCM40 Lesson: MRP List and Stock/Requirements List
3. Return to material R-F1## by double-clicking on the corresponding material
number in the material tree. Note the information message in the status row:
The displayed list has the status of the given time. Refresh (F6), if necessary!
Select the first planned order in the list and switch to the order report
by executing the Order Report function in the material tree. Confirm the
information message. Which materials are displayed in the material tree?
__________________________________________________
__________________________________________________
__________________________________________________
__________________________________________________
__________________________________________________
What connects these materials?
__________________________________________________
__________________________________________________
4. If you prefer to do so, you can make the display of the material tree a
default setting for the initial view of the stock/requirements list by choosing
Settings and Save. Note that you can choose to display or hide the tree in
the list at any time.
2008 © 2008 SAP AG. All rights reserved. 379
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 392/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Solution 16: Functions of the
Stock/Requirements ListTask 1:
You check the personal settings with which you can define the screen for the
stock/requirements list and the MRP list and, if necessary, make different settings.
1. From the MRP menu, call the stock/requirements list for material R-F1##
in plant 1000. To view the default settings that were used to access the list,
choose Settings from the menu and then Settings again. The corresponding
data is sorted thematically on several tab pages. What are the names of the
tab pages?
__________________ __________________
__________________ __________________
__________________
a) Menu path: Logistics → Production → MRP → Evaluations →
Stock/Requirements List
Titles of the tab pages:
Display Period Totals
Dates Filter
General Settings
2. In what form are the requirements displayed with the existing settings
(Display tab page)?
__________________________________________________
__________________________________________________
a) Displaying requirements: The requirements are displayed
individually (and are not grouped in days).
3. Does the system display the availability date or the goods receipt date as the
date of an MRP element (Dates tab page)?
__________________________________________________
a) Availability date or goods receipt date: The availability date is
displayed.
Continued on next page
380 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 393/522
TSCM40 Lesson: MRP List and Stock/Requirements List
4. Return to the Display tab page and select the field With header details for
material. Choose Continue to return to the list. Are the header details
now displayed?
______________________________________________________
In the header details, find which strategy group is specified in the material
master:
______________________________________________________
Choose Collapse header details from the list.
a) Header details: Yes
Strategy group in the material master: Varies according to the
exercise that was carried out last (strategy group 40 or 50).
Task 2:
You want to call frequently used transactions directly from the current
stock/requirements list. To do this, assign a navigation profile to your user.
1. In the stock/requirement list, choose Environment from the menu and then
Navigation Profile - Assign. Use the F4 help to enter the profile SCM001
in the Navigation Profile field and Copy the entry.
a) Menu path: From the list display, choose Environment → Navigation
Profile → Assign
2. Which transaction calls are now displayed above the list header?
__________________ __________________
__________________ __________________
__________________
a) Displayed transaction calls:
Create PIR Interactive MRP
Create CR Planning file
Multi-Level MRP
3. You decide to copy this setting into your personal settings. To do this,
choose Settings again and Save.
a) No solution required
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 381
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 394/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
4. Exit the stock/requirements list and then call it again. Are the transaction
calls displayed?
______________________________________________________
a) Transaction calls displayed: Yes
Task 3:
In the stock/requirements list for material R-F1## (plant 1000), display the
material tree by choosing Show Overview Tree.
1. Which materials are displayed in the overview?
_________________________________________________
_________________________________________________a) Materials in material tree: Varies. All the materials that you
processed in the current session are displayed. If you access the
material tree with the material R-F1## again, only this material
is displayed.
2. Switch to the stock/requirements list for the material R-B1## by entering
the corresponding material number in the Material field in the list header
and choose Enter.
What materials now display in the material tree?
_________________________________________________
a) Materials in material tree: Material R-B1## is now displayed too.
3. Return to material R-F1## by double-clicking on the corresponding material
number in the material tree. Note the information message in the status row:
The displayed list has the status of the given time. Refresh (F6), if necessary!
Select the first planned order in the list and switch to the order report
by executing the Order Report function in the material tree. Confirm the
information message. Which materials are displayed in the material tree?
__________________________________________________
__________________________________________________
__________________________________________________
__________________________________________________
__________________________________________________
What connects these materials?
__________________________________________________
Continued on next page
382 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 395/522
TSCM40 Lesson: MRP List and Stock/Requirements List
__________________________________________________
a) Materials in the material tree: In addition to R-F1##, materials
R-B1##, R-B2##, R-B3##, R-B4##, as well as R-T0##, R-T1##,
R-T2##, R-T4##, and R-T5## are displayed.
Reason: These materials are the assemblies and components for the
finished product R-F1## (except for the finished product itself).
The system therefore displays all materials that flow into the
production of the planned order you selected.
4. If you prefer to do so, you can make the display of the material tree a
default setting for the initial view of the stock/requirements list by choosing
Settings and Save. Note that you can choose to display or hide the tree in
the list at any time.
a) No solution required
2008 © 2008 SAP AG. All rights reserved. 383
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 396/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
384 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 397/522
TSCM40 Lesson: MRP List and Stock/Requirements List
307 Exercise 17: Display Filter, Selection Rule
(Optional)Exercise Duration: 10 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Use the display filter and selection rule.
Business Example
As a member of the project team, you want to familiarize yourself with the
functions of the display filter and the selection rule.
Task:
In the stock/requirements list for material R-F1##, choose Filter on. The system
then displays two new fields in the list header where you can define a display
filter or a selection rule.
1. Call the display filter with the description SAP requirements and firmed
receipts. What changes do you see in the display of the MRP elements?
______________________________________________________
2. Do you also see changes in the available quantity that is calculated for eachMRP element?
______________________________________________________
3. Now test the effect of the display filter SAP Only receipts. Which elements
are now displayed?
______________________________________________________
4. Remove the display filter and enter the selection rule with the description
SAP Requirements and Stocks instead.
What available quantity is now displayed at the end of the net planning
segment?
______________________________________________________
Give a reason for this:
______________________________________________________
______________________________________________________
5. Now choose the Filter off button to work without a display filter or a
selection rule.
2008 © 2008 SAP AG. All rights reserved. 385
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 398/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Solution 17: Display Filter, Selection Rule
(Optional)Task:
In the stock/requirements list for material R-F1##, choose Filter on. The system
then displays two new fields in the list header where you can define a display
filter or a selection rule.
1. Call the display filter with the description SAP requirements and firmed
receipts. What changes do you see in the display of the MRP elements?
______________________________________________________
a) Changes to the display: Only requirements and firmed planned
orders (if they exist) are now displayed.
2. Do you also see changes in the available quantity that is calculated for each
MRP element?
______________________________________________________
a) Changes to the available quantity: No, the available quantity is not
changed by the display filter.Even without displaying planned
orders, the available quantity at the end of the list remains 0 pieces.
3. Now test the effect of the display filter SAP Only receipts. Which elements
are now displayed?
______________________________________________________
a) Effect of the display filter SAP Only make-to-order planning: Only
receipt elements are displayed.
4. Remove the display filter and enter the selection rule with the description
SAP Requirements and Stocks instead.
What available quantity is now displayed at the end of the net planning
segment?
______________________________________________________
Give a reason for this:______________________________________________________
Continued on next page
386 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 399/522
TSCM40 Lesson: MRP List and Stock/Requirements List
______________________________________________________
a) Quantity available for planning at the end of the net requirements
planning segment: Varies, for example, minus 350 pcs.
Reason: In contrast to display filters, selection rules have an
effect on the calculation of the available quantity. When using
the “Requirements and Stocks” selection rule, only requirements
and stocks are included in the calculation. Receipt elements are
not taken into account. In this example, the available quantity is
merely the total of all requirements and stocks.
5. Now choose the Filter off button to work without a display filter or a
selection rule.
a) No solution required
2008 © 2008 SAP AG. All rights reserved. 387
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 400/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Lesson Summary
You should now be able to:• Work with the stock/requirements list
• Use the MRP list
• Use navigation profiles
• Deploy the display filter and selection rules
• Use the collective call
388 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 401/522
TSCM40 Lesson: Planning Table
Lesson:
311
Planning Table
Lesson Duration: 30 Minutes
Lesson Overview
The planning table for repetitive manufacturing can also be used for normal
“order-based” production. It offers additional options for processing the MRP
results.
Lesson Objectives
After completing this lesson, you will be able to:
• Use the planning table for repetitive manufacturing
• Use production versions
Space for notes
Business Example
The planning table for repetitive manufacturing is particularly useful when you
want to check the capacity situation for a production plan. You therefore need tomake preparations for using this tool.
2008 © 2008 SAP AG. All rights reserved. 389
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 402/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Planning Table
Figure 146: Planning Table / Period-Based Planning
The planning table enables the work scheduler to process the master production
schedule. They can check the production quantities at a glance, change them
if required, and create new production quantities (planned orders). The work
scheduler can also determine the capacity load utilization of the production line
and the availability of the products. Pegging can also be executed by doubleclicking on the capacity requirements.
The planning table was originally developed for repetitive manufacturing. In
repetitive manufacturing, orders are generally planned according to quantity and
period, and this is reflected in the planning table display. You can choose any
planning period (shift, day, week, month, planning calendar period).
In the assignment mode, the work scheduler can assign production quantities
(planned orders) to a production version and therefore to a production line. If this
has already been executed in the MRP run, the work scheduler can also change
assignments that have already been made . Planned orders that have already been
manually assigned to a production line are classified as order type “PE” (runschedule quantities) and are usually firmed. This firming method can either be
limited to the planning time fence or completely deactivated for each material
using the repetitive manufacturing profile.
In the planning table, you can display various key figures (the range of coverage,
the available quantity, and so on) and define the display sequence.
Changes you make in the planning table are not written to the database unless
you save them.
390 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 403/522
TSCM40 Lesson: Planning Table
Figure 147: Planning in the Planning Table
The entire planning process for period-based production can be carried out
using the planning table. As well as planned orders, you can also display and
process production orders for discrete production and process orders for process
manufacturing in the planning table. Production and process orders are displayed
in a separate row - PR.ORD. You can make changes to production orders or
process orders by branching directly from the planning table to the orders usingchange mode. It is, however, not possible to execute mass change functions such
as distribution according to shifts for production and process orders.
You can convert planned orders to production orders directly using the “convert
quantities” function in the planning table. The system then shows the line
PR.ORD: , where you can view these orders. You must call the planning table
again in order to be able to make changes to these newly created orders.
In order to display production and process orders in the repetitive manufacturing
planning table you need a valid production version in the material master.
2008 © 2008 SAP AG. All rights reserved. 391
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 404/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Figure 148: Production Version for the Planning Table
To work with the planning table, there must be at least one production version
in the material master of the corresponding material. The production version
contains data relevant to production that describes a manufacturing process:
• You determine in which period the version can be used in the fields “Valid
from” and “Valid to”. You can enter a lot size range for the version in the
fields “From lot size” and “To lot size”.
• You can define a routing for detailed planning, rate-based planning, and
rough-cut planning. You enter a task list group and a group counter for
detailed planning. The routing entered is then used for capacity requirements
planning.
• You can uniquely assign a particular BOM to the version using the fields
“BOM Usage” and “Alternative BOM”.
• In the “Production Line” field, you define the work center (production line)
for the assignment of production quantities in the planning table. The system
only displays the capacity requirements for this work center in the planning
table. In order to execute capacity planning, this work center (production
line) must be contained in the routing.
Hint: Extra info on discrete manufacturing compared with repetitive
manufacturing
392 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 405/522
TSCM40 Lesson: Planning Table
The planning table is actually a tool for planning in repetitive
manufacturing. You should therefore explain at this point the differences
between discrete manufacturing and repetitive manufacturing.
• Order-based production (production in individual production orders)
Period-based production (production with certain quantities per
period)
• Products change frequently
Product produced unchanged over a longer period of time
• Varying sequence of work centers (complex routings)
Constant flow through production lines (simplified routings)
• Semifinished products often put into interim storage
Semifinished products often processed further without interim
storage
• Components staged with reference to order
Components staged at production lines periodically and
anonymously
• Status processing
Reduced control effort (no status processing)
• Completion confirmation (backflush) for individual operations ororders
Completion confirmation based on periods (final backflushing)
• Order-based cost monitoring
Period-based cost monitoring
Demonstration: Planning Table
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Material R-F1## in plant 1000, production version FV01
2008 © 2008 SAP AG. All rights reserved. 393
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 406/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Strategy group 40,
Set goods receipt processing time to 0,
Assign a production version in the MRP 4 view (“ProdVersions” button):
Version FV01 (production version 01) is valid from today and until the end
of next year.
In the detail screen:
• Lot size from 1 to 99999 pieces
• Routing: Enter standard routing for the material R-F1## in the detailed
planning row (search for number using material).
• BOM: Enter usage 1 and alternative 1.
• Production line: Work center R-F##.• Save material master
2. Create planned independent requirements for R-F1##: 40 pcs each for the
current month + 2 and the current month + 3.
3. Material requirements planning for R-F1## with scheduling indicator 1
(basic scheduling).
4. From the MRP menu, call the planning table in change mode with the
following initial parameters:
• Material R-F1## (selection by material)
• Period of examination from today until the end of the current month + 3• Period: Week
• Scheduling:
Detailed planning
Basic dates, backward scheduling,
with capacity planning
• Control: Leave blank
• MRP segments: Set all flags
Save settings and call the planning table:
Display the planned orders and explain the capacity data for work center
R-F##.
394 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 407/522
TSCM40 Lesson: Planning Table
5. Assign the planned orders to production lines, create planned orders:
• Select the row of planned orders that have not been assigned and switch
on assignment mode: From the first planned order, assign 20 pcs for
the week in which the planned order is executed and 20 pieces in the
last week on the production line R-F## (row FV01 R-F##), assign 40
pcs of the second planned order in the week it is executed.
• Switch off assignment mode. Enter 30 pcs in row FV01 R-F## three
weeks after the second planned order.
Enter --> Planned orders are scheduled and capacity data is generated.
Press save to exit the planning table.
6. Display the planning results in the stock/requirements list. Firmed and
scheduled planned orders with assigned production versions were created,
in particular:
• The first order, originally for 40 pcs, was divided into two orders
with 20 pcs each.
• An additional planned order for 30 pcs was created.
Caution: The available quantity is calculated accurately to the
day and is based on the goods receipt processing time, so that an
apparent “period shift” may appear as far as the available quantities
are concerned. It is therefore practical to set the goods receipt
processing time to 0 (see above).
2008 © 2008 SAP AG. All rights reserved. 395
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 408/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Facilitated Discussion
Discussion Questions
Use the following questions to engage the participants in the discussion. Feel free
to use your own additional questions.
Explain the advantages of using the planning table in order-based production. Use
a discussion to explain that the technical requirement of the production version
does not represent a genuine constraint (could possibly be extended later in the
direction of SAP APO).
396 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 409/522
TSCM40 Lesson: Planning Table
Lesson Summary
You should now be able to:• Use the planning table for repetitive manufacturing
• Use production versions
2008 © 2008 SAP AG. All rights reserved. 397
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 410/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Lesson:
316
Exception Messages
Lesson Duration: 30 Minutes
Lesson Overview
Exception messages draw attention to problems in planning. They therefore
constitute an important tool for the MRP controller.
Lesson Objectives
After completing this lesson, you will be able to:
• Interpret exception messages
• Make corresponding settings in Customizing
Space for notes
Business Example
The exception messages are set in such a way that the MRP controller can locate
potential problems quickly.
Exception Messages
Exception Messages
In Customizing, you can define the grouping of exception messages into exception
message groups, the priority of exception messages, the texts for exception
messages and exception message groups:
Customizing: Production – Material Requirements Planning – Evaluation –
Exception Messages
398 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 411/522
TSCM40 Lesson: Exception Messages
Figure 149: Exception Messages
You use exception messages to help monitor the MRP results. Exception messages
provide information about specific operations. They alert you to items that require
your attention (such as a start date in the past, stocks falling below the safety
level and so on). The MRP controller can then select those materials from the
planning results in order to process them manually. Exception messages generally
indicate the following: Newly created order proposals from planning, dates in the
past (for example, opening date), problems with BOM explosion or scheduling,rescheduling proposals. In the Customizing activity “Define and Group Exception
Messages”, you can determine the properties of the exception messages. This
includes the priority (should several exception messages appear), the splitting of
exception messages into exception groups for the selection, and the creation of
the MRP list depending on the exception message created. If several exception
messages apply to one MRP element, the priority assigned to these messages
determines which messages are displayed. The system displays a maximum of
two exception messages for each MRP element. If scheduling problems occur, the
system displays a relevant exception message in the stock/requirements list and
MRP list and displays a rescheduling proposal. If this proposal is accepted, you
must adjust the dates for the receipt element manually. These dates can be adjusted
automatically in the display or evaluation of the planning results (for example, ininteractive planning or when the “Display Result” indicator has been selected in
the initial screen of the planning run): You can accept the rescheduling proposal
here using the “Reschedule Order Proposal” function.
2008 © 2008 SAP AG. All rights reserved. 399
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 412/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Old/New Exception Messages
Dividing exception messages into old and new messages only works in connection
with the processing indicator. The MRP controller can select only the parts for
which exceptions have occurred. This function applies only to high priority
exceptions (you can see these in transaction MD04).
Figure 150: Old/New Exception Messages
You can differentiate between old and new exceptions in the MRP list if you
work with the processing indicator. For those materials planned in the planning
run, the system compares the exception messages in the new MRP list with the
exception messages in the old list: If one exception message appears in both
lists, it is indicated as an “old” exception message; the remaining exception
messages are considered to be new messages. In the collective list display, you
can specifically select only those lists with new exception messages. When using
collective display of the MRP lists, you can specifically select only lists with new
exceptions and even search for new and old exceptions in the individual lists.
Customizing exception messages is restricted to:
• The description of each exception message
• The priority of each exception message (high numeric value = high priority)
• The unique assignment of the message to an exception group
• Triggering the creation of an MRP list (if this is agreed in the planning run)
• The option to hide the relevant exception message
Note that these settings are valid for all clients.
400 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 413/522
TSCM40 Lesson: Exception Messages
No provision has been made for exceptions other than the predefined messages.
You can maintain your own description for the exception groups 1 to 7 (of 8).
Demonstration: Exception Messages
Purpose
Preparation for exercise
Customizing exception messages is restricted to:
• The description of each exception message
• The priority of each exception message (high numeric value = high priority)
• The unique assignment of the message to an exception group• Triggering the creation of an MRP list (if this is agreed in the planning run)
• The option to hide the relevant exception message
Note that these settings are valid for all clients.
No provision has been made for exceptions other than the predefined messages.
You can maintain your own description for the exception groups 1 to 7 (of 8).
System Data
System: See weekly mail
Client: See weekly mailUser ID: Own user ID
Password: Own password
Set up instructions: Standard
1. Today: Create a planned independent requirement of 200 pcs for today +1
month.
2. Night: Planning run, forward scheduling; a planned order is created with
exception messages 30 (plan process according to schedule) and 05 (opening
date in the past); display the exception messages: maximum of two messages
for each MRP element; call exception information.
3. Today + 1: Call MRP list using the collective access; Edit the MRP detailscreen: Bring the planned order forward to an earlier order end date that is
still later than the required date, then set the processing indicator.
4. Night + 1: MRP run
5. Night + 2: Call the collective access of the MRP list: Collective access with
the Only With New Exceptions indicator → the system does not call the
MRP list for the material because the new exceptions are the same as the old
ones.The processing indicator also remains set.
2008 © 2008 SAP AG. All rights reserved. 401
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 414/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
6. You may want to draw attention to various SAP Notes regarding the
processing indicator and exception messages (for example, SAP Note
30684).
Rescheduling Check for Firmed Receipts
Explain the purpose of the rescheduling check and the rescheduling horizon and
how they work.
Aside from the rescheduling messages, explain the special cases where the
“tolerance” period overrides the rescheduling message (no rescheduling proposal
or exception message despite too early or too late).
Figure 151: Rescheduling Check for Firmed Receipts
The planning run does not automatically reschedule firmed receipts. If the dates
of these elements no longer fall within the rescheduling horizon, the system
generates the following exception messages:
• “Reschedule in operation”, if the requirements date is before that of the
receipt element, - “reschedule out operation”, if the requirements date is after
that of the receipt element
• “Reverse operation”, when the requirement no longer exists.
Using the rescheduling horizon, you can stop the system from using receipts that
are a long time in the future to cover requirements in the near future. In this case,
the system checks within the period, which is made up of the in-house production
402 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 415/522
TSCM40 Lesson: Exception Messages
time, goods receipt processing time, and the rescheduling horizon (starting from
the planning date), to see if the existing dates for firmed receipts are still suitable
or whether firmed receipts can be rescheduled in to cover requirements. InCustomizing, you define at plant level which firmed receipts the system checks.
You can maintain the rescheduling horizon and the tolerance values for each plant
and each MRP group. If the system cannot find a receipt element within the
rescheduling horizon that can be rescheduled in or out to cover requirements, it
creates a new one. The rescheduling check of firmed elements is not restricted
to a horizon. In order to reduce the number of exception messages, you can set
tolerance values for rescheduling in and out. The system only creates an exception
message when the difference between the current receipt date and the rescheduling
date exceeds the given tolerance value.
Demonstration: Rescheduling check
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
Set up instructions: Standard1. Show the Customizing settings for the rescheduling check: Rescheduling
horizon, tolerance value, firmed elements
In the plant parameters:
→ Customizing: Production – Material Requirements Planning – Plant
Parameters – Carry Out Overall Maintenance of Plant Parameters →
Rescheduling
2. In the settings for the MRP group
→ Customizing: Production – Material Requirements Planning – MRP
Groups – Carry Out Overall Maintenance of MRP Groups→
Rescheduling Horizon
Optional demonstration: Rescheduling check
a) In material master R-F1##, plant 1000, enter strategy group 40.
b) Enter sales order: Today in 4 weeks, 10 pieces.
c) Execute planning (generated planned order satisfies requirements in
time).
2008 © 2008 SAP AG. All rights reserved. 403
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 416/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
d) Firm planned order manually.
e) Increase sales order by 90 pieces and execute planning again.
Generated planned order is too late with rescheduling proposal.
f) Reschedule the date of the planned order that is too late to 2 days
before the rescheduling date to explain the tolerance values (change
the basic date, reschedule): The rescheduling message disappears.
404 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 417/522
TSCM40 Lesson: Exception Messages
Facilitated Discussion
Discussion Questions
Use the following questions to engage the participants in the discussion. Feel free
to use your own additional questions.
Discuss the different possibilities for using exception messages when processing
MRP results (selection using exception messages, creation of MRP lists dependent
on exception messages).
2008 © 2008 SAP AG. All rights reserved. 405
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 418/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Lesson Summary
You should now be able to:• Interpret exception messages
• Make corresponding settings in Customizing
406 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 419/522
TSCM40 Lesson: Additional Evaluation Aids
Lesson:
321
Additional Evaluation Aids
Lesson Duration: 30 Minutes
Lesson Overview
With the pegged requirement and order report evaluations you can analyze
problems across all BOM levels. You can use ranges of coverage to spot potential
problems at an early stage.
Lesson Objectives
After completing this lesson, you will be able to:
• Interpret ranges of coverage
• Use the pegged requirements display
• Use the order report
Space for notes
Business Example
You need to make settings for ranges of coverage in such a way that the MRPcontroller can spot future bottlenecks at an early stage.
2008 © 2008 SAP AG. All rights reserved. 407
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 420/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Additional Evaluation Aids
Figure 152: Stock Days’ Supply
The stock days’ supply enables you to recognize potential shortages at an early
stage. It tells you when the production supply will cease if there are no more
receipts.
In the “Safety stock” field in the Customizing activity “Define Receipt Elements
for Receipt Days’ Supply” you determine for each plant whether the days’ supply
should be defined as the point where stock falls below the physical stock level
(indicator “Safety stock” = “1”) or the safety stock level (indicator = “blank”).
The days’ supply is entered in workdays and anything entered after the decimal
point indicates to what portion of the requirement can still be covered on the
shortage day (for example a days’ supply of 24.6 means that the stock can cover
the requirements for the next 24 days and on day 25 there will be enough stock to
cover 60% of the requirement). You can flag materials with critical days’ supplies
with a red traffic light in the stock/requirements list and in the MRP list.
408 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 421/522
TSCM40 Lesson: Additional Evaluation Aids
Figure 153: Receipt Days’ Supply
The receipt days’ supply provides you with information about when the production
supply will cease if certain firmed receipts are delivered. You can define two
different receipt days’ supplies that differ in terms of the selection of the firmed
receipt elements that are taken into account.
You select the firmed receipts to be taken account in the calculation for each plant
in the Customizing activity “Define Receipt Elements for Receipt Days’ Supply”.
In the “Safety Stock” field, you define whether the receipt days’ supply should be
defined as the point where stock falls below the physical stock level or the safety
stock level (see stock days’ supply).
2008 © 2008 SAP AG. All rights reserved. 409
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 422/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Figure 154: Receipt Days’ Supply 1 and 2 (Example)
You can analyze two different receipt days’ supplies (1 and 2). These two receipt
days’ supplies differ with regard to the selection of their receipt elements. The
selection is defined in the Customizing IMG activity “Define Receipt Elements
for Receipt Days’ Supply”. For different firmed receipts you determine one of
the following: That they are not taken into account (blank), that they are taken
into account for both receipt days’ supplies (“X”), that they are only taken intoaccount for receipt days’ supply 1 (“1”), that they are only taken into account for
receipt days’ supply 2 (“2”).
In the above example, production orders and firmed planned orders are included in
the calculation of receipt days’ supply 1, while the receipt days’ supply 2 provides
information on the extent of the range of coverage taking only the production
orders into account.
Demonstration: Stock Days’ Supply and Receipt Days’Supply
Purpose
Preparation for exercise
System Data
System: See weekly mail
Client: See weekly mail
User ID: Own user ID
Password: Own password
410 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 423/522
TSCM40 Lesson: Additional Evaluation Aids
Set up instructions: Standard
1. Call the stock/requirements list for material R-F1##: Display the stock days’
supply and the two receipt days’ supplies in the header details; if necessary,explain how the ranges of coverage are calculated using goods receipts and
additional planned independent requirements.
2. In Customizing, show how to define the stock days’ supply and receipt days’
supply and include safety stock:
Customizing: Production – Material Requirements Planning – Evaluation –
Define Receipt Elements for Receipt Days’ Supply
Demo example:
Enter “1” in the “Firmed Planned Orders” (FPAUF) column in Customizing,
and likewise enter “1” in the “Safety Stock” column.Warehouse stock 7 pcs; (static) safety stock 5 pcs; create planned independent
requirements: Current week + 2 weeks to current week + 6, each 10 pcs;
planning run, refresh MD04 and explain values for stock days’ supply and
receipt days’ supply (all 3 values are the same);
Convert the first planned order in a production order; fix the second planned
order manually; explain the recalculated values for both receipt days’ supply;
In Customizing, enter “blank” in the “Safety Stock” column; call up MD04
again (refreshing the screen is not enough), and explain the recalculated
value for the stock days’ supply.
Figure 155: Pegged requirement
2008 © 2008 SAP AG. All rights reserved. 411
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 424/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
You can use the “Pegged Requirements” evaluation, which you can access directly
from the stock/requirements list and MRP list, to trace from any BOM level across
other BOM levels which requirements have caused an order proposal and whichindependent requirements (particularly sales orders) are affected by the change in
date or quantity of an order proposal on a lower level.
In the stock/requirements or MRP list, you can navigate directly from the
requirements element to the pegged requirement on the level above. The system
displays the stock/requirements or MRP list of the superordinate level and
automatically positions the cursor on the line of the pegged requirement. This
makes it much easier to find pegged requirements on different MRP levels.
You can call this function from the details display of the requirements element.
The function is available for the following requirements elements: Dependent
requirements, order reservations, stock transfer requirements, stock transfer
reservations.
Figure 156: Order Report
The “Order Report” evaluation enables you to gain an overview of the status
of all BOM levels from the following MRP elements: Sales order, production
order (also collective and process order), and planned order. In this way, you
can recognize problems in the production and procurement of assemblies and
components at an early stage.
You call the transaction directly from the stock/requirements list or MRP list. The
system determines which receipt elements are planned for each MRP element. The
MRP controller is therefore able to check how the production of a certain sales
order is progressing, or if there are missing parts or scheduling problems on a
particular BOM level or for certain components.
412 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 425/522
TSCM40 Lesson: Additional Evaluation Aids
327 Exercise 18: Collective Display of MRP
ListsExercise Duration: 10 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Call MRP lists using the collective display,
• Use the processing indicator.
Business Example
You want to process the MRP lists for the materials for which you are responsible
as MRP controller, and which were created this week. You want to concentrate
in particular on situations for which rescheduling proposals exist. After having
clarified the situation in production, you change the scheduled dates of the planned
orders according to the rescheduling proposals that are in the MRP list.
Task 1:
You will now learn about an option for collective evaluation of your previous
planning activities. To do this, you use the collective display of MRP lists.
1. Starting from the Evaluation menu, call the MRP List - Collective Display.
Restrict your selection to MRP lists for materials in plant 1000, for which
you are responsible as MRP controller 0##, and for which MRP lists have
been created in the current week. To do this, enter the following in the initial
screen:
Plant: 1000
MRP controller: 0##
MRP date from: Beginning of the week to: Today
Start the selection by choosing Enter .
How many materials were selected?
______________________________________________________
2. The system displays an overview of the materials selected. In other words,
you can see all the materials for the MRP controller 0##.
Choose Select All and Display selected MRP lists in order to display the
corresponding lists in order ( Next Material button).
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 413
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 426/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Which exception messages appear in the MRP lists?
Hint: Double-click on the exception message to view the short
text in the status bar.
______________________________________________________
______________________________________________________
______________________________________________________
Task 2:
In the MRP list for the material R-B2## you notice that no further processing
is necessary.
1. You therefore set the processing indicator for this material in the MRP list.
Then exit the collective display for the MRP list and call the transaction
again. This time, select the option Only unprocessed MRP lists on the
Processing Indicator tab page in addition to the selection from task 1 point 1.
Was the material R-B2## you processed before selected too?
____________________________________________________________
414 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 427/522
TSCM40 Lesson: Additional Evaluation Aids
Solution 18: Collective Display of MRP
ListsTask 1:
You will now learn about an option for collective evaluation of your previous
planning activities. To do this, you use the collective display of MRP lists.
1. Starting from the Evaluation menu, call the MRP List - Collective Display.
Restrict your selection to MRP lists for materials in plant 1000, for which
you are responsible as MRP controller 0##, and for which MRP lists have
been created in the current week. To do this, enter the following in the initial
screen:
Plant: 1000
MRP controller: 0##
MRP date from: Beginning of the week to: Today
Start the selection by choosing Enter .
How many materials were selected?
______________________________________________________
a) Menu path: Logistics → Production → MRP → Evaluations → MRP
List - Collective DisplayNumber of materials selected: Varies, for example 12 materials
2. The system displays an overview of the materials selected. In other words,
you can see all the materials for the MRP controller 0##.
Choose Select All and Display selected MRP lists in order to display the
corresponding lists in order ( Next Material button).
Which exception messages appear in the MRP lists?
Hint: Double-click on the exception message to view the short
text in the status bar.
______________________________________________________
______________________________________________________
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 415
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 428/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
______________________________________________________
a) Which messages: Varies, for example 42, 44, 30, 10
Hint: Each planning order can contain up to 2 messages - see
details for the planning order
Task 2:
In the MRP list for the material R-B2## you notice that no further processing
is necessary.
1. You therefore set the processing indicator for this material in the MRP list.
Then exit the collective display for the MRP list and call the transaction
again. This time, select the option Only unprocessed MRP lists on the
Processing Indicator tab page in addition to the selection from task 1 point 1.
Was the material R-B2## you processed before selected too?
____________________________________________________________
a) Display the processed material: No
416 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 429/522
TSCM40 Lesson: Additional Evaluation Aids
331 Exercise 19: Rescheduling Check
(Optional)Exercise Duration: 15 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Interpret the rescheduling proposals
• Carry out the parameterization of the rescheduling check
Business Example
Pumps with the material number T-F1## (## denotes your group number) can be
planned and produced in plant 1000.
Use a small test case for pump T-F1## as an example for the rescheduling check
for delayed firmed elements and interpret the result.
Caution: Note that in this case, you are using pump T-F1##, plant 1000
and not pump R-F1##, plant 1000, which you have been using up to now.
Task 1:
Enter a customer requirement for pump T-F1## in plant 1000.1. In the program planning section, call the transaction for creating a customer
requirement.
Choose the following parameters:
Material: T-F1##
Order quantity: 2 pcs
Delivering plant: 1000
Required delivery date: Wednesday of the current week +
5 weeks
Choose Enter to confirm your entries and any information messages.
Save the customer requirement.
2. Start multilevel single-item planning for your material T-F1##, plant 1000
and interpret the result in the stock/requirements list.
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 417
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 430/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Is there an on-time requirement coverage, that is, is the requirement coverage
element able to cover the requirement on time?
____________________________________________________
3. In the stock/requirements list, define the following manual firming date:
Availability date of the planned order plus 3 working days
Refresh the list. Is the firming of the planned order visible from the list?
_____________________________________________________
Task 2:
The customer subsequently changes the requested delivery date.
1. The new requirements date is now one working day before the originalrequested delivery date.
Change the customer requirement by going to the stock/requirements list
and double-clicking to go to the details. In the item (that is, not in the field
Requested Delivery Date), change the field for the first date accordingly.
Save the customer requirement, return to the stock/requirements list and
refresh it.
Did the postponement take place?
_____________________________________________________
Are you assigned as MRP controller for this postponement, that is, does the
system issue a rescheduling message? Why (not)? To find out, display the
settings for the rescheduling check in the plant parameters (Customizing).
______________________________________________________
______________________________________________________
2. The customer wants to postpone the date by another week (7 calendar days).
Change the date of the customer requirement as before and check the new
situation in the stock/requirements list.
Are you assigned as MRP controller for this postponement, that is, does the
system issue a rescheduling message? Why (not)?
______________________________________________________
______________________________________________________
In this case, would a planning run generate a new on-time procurement ele-
ment? ______________________________________________________
Check your answer by triggering multilevel single-item planning for
T-F1##, plant 1000.
Continued on next page
418 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 431/522
TSCM40 Lesson: Additional Evaluation Aids
Task 3:
The examination of the rescheduling check for delayed firmed receipts has
terminated. Therefore, remove the test entries:
1. First delete the customer requirement (change mode: Independent
requirements → Delete.
2. In the stock/requirements list, remove the manual firming date ( Edit → Set
firming date → Delete) and refresh the list.
3. Start single item multilevel planning for T-F1##, plant 1000.
2008 © 2008 SAP AG. All rights reserved. 419
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 432/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
Solution 19: Rescheduling Check
(Optional)Task 1:
Enter a customer requirement for pump T-F1## in plant 1000.
1. In the program planning section, call the transaction for creating a customer
requirement.
Choose the following parameters:
Material: T-F1##
Order quantity: 2 pcs
Delivering plant: 1000
Required delivery date: Wednesday of the current week +
5 weeks
Choose Enter to confirm your entries and any information messages.
Save the customer requirement.
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Customer Requirements → Create
2. Start multilevel single-item planning for your material T-F1##, plant 1000and interpret the result in the stock/requirements list.
Is there an on-time requirement coverage, that is, is the requirement coverage
element able to cover the requirement on time?
____________________________________________________
a) Menu path: Logistics → Production → MRP → Planning →
Multi-Level Single-Item Planning
Menu path: Logistics → Production → MRP → Evaluations →
Stock/Requirements List
On-time requirement coverage: In general, there is an on-timerequirements coverage. Minor differences are possible, for example,
if the relevant Wednesday is a public holiday. In this case, the
requirement coverage element is made available earlier.
3. In the stock/requirements list, define the following manual firming date:
Availability date of the planned order plus 3 working days
Refresh the list. Is the firming of the planned order visible from the list?
Continued on next page
420 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 433/522
TSCM40 Lesson: Additional Evaluation Aids
_____________________________________________________
a) Menu path: Logistics → Production → MRP → Evaluations →
Stock/Requirements List
Edit → Set Firming Date
Firming: The manual firming date is displayed. The planned order
in the relevant firming interval is flagged as firmed (*).
Task 2:
The customer subsequently changes the requested delivery date.
1. The new requirements date is now one working day before the original
requested delivery date.
Change the customer requirement by going to the stock/requirements list
and double-clicking to go to the details. In the item (that is, not in the field
Requested Delivery Date), change the field for the first date accordingly.
Save the customer requirement, return to the stock/requirements list and
refresh it.
Did the postponement take place?
_____________________________________________________
Are you assigned as MRP controller for this postponement, that is, does the
system issue a rescheduling message? Why (not)? To find out, display the
settings for the rescheduling check in the plant parameters (Customizing).
______________________________________________________
______________________________________________________
a) Menu path: Logistics → Production → MRP → Evaluations →
Stock/Requirements List
Postponement: The postponement took place. However, the system
does not issue a rescheduling message in this case since the scale
of the postponement (1 working day) is still within the tolerance
interval allowed for the rescheduling check in Customizing.
Menu path: Customizing (transaction SPRO)→
F5→
Production→
Material Requirements Planning → Plant Parameters → Carry Out
Overall Maintenance of Plant Parameters
Maintain → Plant 1000 → Rescheduling
The tolerance value for bringing forward a requirement is 2
working days. Therefore, there is no need for a rescheduling
message (yet).
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 421
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 434/522
Unit 6: Evaluating and Processing the MRP Results TSCM40
2. The customer wants to postpone the date by another week (7 calendar days).
Change the date of the customer requirement as before and check the new
situation in the stock/requirements list.
Are you assigned as MRP controller for this postponement, that is, does the
system issue a rescheduling message? Why (not)?
______________________________________________________
______________________________________________________
In this case, would a planning run generate a new on-time procurement ele-
ment? ______________________________________________________
Check your answer by triggering multilevel single-item planning for
T-F1##, plant 1000.
a) You postpone the date by another week: Yes, you are assigned to the
postponement. A postponement of 8 days is no longer allowed
according to the parameterization in the plant parameters and
leads to a rescheduling message. The MRP controller can tell what
the date of the procurement proposal should be.
A new planning run does not lead to a new procurement proposal
because the two elements (requirement and delayed requirement
coverage element) belong together.
Menu path: Logistics → Production → MRP → Planning → Multilevel
Single-Item Planning
Task 3:
The examination of the rescheduling check for delayed firmed receipts has
terminated. Therefore, remove the test entries:
1. First delete the customer requirement (change mode: Independent
requirements → Delete.
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Customer Requirements → Change
2. In the stock/requirements list, remove the manual firming date ( Edit → Set
firming date→
Delete) and refresh the list.
a) Menu path: Logistics → Production → MRP → Evaluations →
Stock/Requirements List
3. Start single item multilevel planning for T-F1##, plant 1000.
a) Menu path: Logistics → Production → MRP → Planning → Multilevel
Single-Item Planning
422 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 435/522
TSCM40 Lesson: Additional Evaluation Aids
Lesson Summary
You should now be able to:• Interpret ranges of coverage
• Use the pegged requirements display
• Use the order report
2008 © 2008 SAP AG. All rights reserved. 423
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 436/522
Unit Summary TSCM40
Unit Summary
You should now be able to:
• Work with the stock/requirements list
• Use the MRP list
• Use navigation profiles
• Deploy the display filter and selection rules
• Use the collective call
• Use the planning table for repetitive manufacturing
• Use production versions
• Interpret exception messages
• Make corresponding settings in Customizing
• Interpret ranges of coverage
• Use the pegged requirements display
• Use the order report
424 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 437/522
TSCM40 Test Your Knowledge
339Test Your Knowledge
1. The planned orders that are displayed in the planning table cannot be seen in
the stock/requirements list.
Determine whether this statement is true or false.
□ True
□ False
2. Which of the following problems can be displayed using exception messages?
Choose the correct answer(s).
□ A Scheduling delays in material requirements planning
□ B Failed ATP check
□ C Unforeseen change of MRP controller
□ D Delayed arrival of production operators
2008 © 2008 SAP AG. All rights reserved. 425
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 438/522
Test Your Knowledge TSCM40
340Answers
1. The planned orders that are displayed in the planning table cannot be seen in
the stock/requirements list.
Answer: False
Like other documents, planned orders can also be processed using a number
of different transactions: Manual change, stock/requirements list, MRP list,
planning table, and so on.
2. Which of the following problems can be displayed using exception messages?
Answer: A
Exception messages point out problems in material requirements planning.
They usually refer to individual MRP elements.
426 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 439/522
Unit 7 341 Overview of SAP APO-PP/DS
In this part of the course, you work (as an exception) with the extended planning
functions in APO-PP/DS. These are used mainly when the relevant planningaspects cannot be mapped in ECC. Emphasize that this unit is merely intended
to provide an overview, and will not provide the participants with instructions
on how to set up planning in PP/DS. To learn this, they would need to attend
the customer course SCM250.
Unit Overview
While the “standard” planning functions are still available in ECC (ECC MRP),
APO-PP/DS provides additional options for Production Planning and Detailed
Scheduling in the SCM system. Planning using APO is normally executed in
cross-industry applications in ECC too, which means that the SCM-APO functionscan only be implemented practically in connection with ECC or another executing
system. The master data required for planning is also generally transferred from
ECC to APO.
Unit Objectives
After completing this unit, you will be able to:
• Name the most important basic features of PP/DS planning
• Name and characterize the master data for PP/DS planning
• Manage and characterize requirements and their behavior in DemandManagement in APO
• Describe the CTP (Capable-to-Promise) scenario
• Name the planning procedure
• Describe and implement the multilevel planning run
• Interpret pegging
• Assess the cases for using the product planning table and the detailed
scheduling planning board
• Characterize the optimizer
2008 © 2008 SAP AG. All rights reserved. 427
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 440/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Unit Contents
Lesson: Introduction to SAP APO-PP/DS ...................................429Demonstration: APO-DP, SNP and PP/DS .............................434
Lesson: Master Data Overview ...............................................439Demonstration: Master Data Overview. .. .. .. ... .. ... .. ... .. .. .. .. ... ... 443Exercise 20: Master Data Overview .. .. .. .. .. ... .. ... .. ... .. .. .. .. ... ... 445
Lesson: Demand Management with APO PP/DS ... .. .. .. .. .. .. .. .. .. .. .. .461Demonstration: Planning with Final Assembly (Strategy 20) . . . . .. . .. 464Exercise 21: Planning with Final Assembly in APO-PP/DS........... 467
Lesson: Production Planning with APO PP/DS............................. 483Exercise 22: Executing the Production Planning Run (Optional) ....489
Lesson: Selected Planning Tools in APO PP/DS .. .. .. .. .. .. .. .. .. .. .. .. .. .497Demonstration: Period-Based Planning in the Product Planning Table
(Optional) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 500
428 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 441/522
TSCM40 Lesson: Introduction to SAP APO-PP/DS
Lesson:
343
Introduction to SAP APO-PP/DS
Lesson Duration: 20 Minutes
Lesson Overview
The participants will gain an overview of planning with APO-PP/DS and its basic
features.
Lesson Objectives
After completing this lesson, you will be able to:
• Name the most important basic features of PP/DS planning
Space for notes
Business Example
Your company is implementing production planning and detailed scheduling using
APO-PP/DS. You use the example of the Precision Pump Company to familiarize
yourself with the functions.
SAP APO 3.1 and SAP SCM 4.0*
Up to Release 3.1, SAP APO was managed as an independent system. As of
Release 4.0, the functions of the APO system are integrated as a component of
the SCM system.
2008 © 2008 SAP AG. All rights reserved. 429
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 442/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Figure 157: SAP Supply Chain Planning Components
Supply Chain Planning mainly uses the following SAP components: SAP ECC,
SAP SCM (including APO, Advanced Planning and Optimization), SAP BW
(Business Information Warehouse).
The interfaces used for integrating ECC with BW or APO are provided with a
relevant plug-in. The interface between ECC and APO is called the Core Interface
(CIF).
Supply Chain Planning at a Glance
An overview of the whole Supply Chain Planning process is shown here. You can
refer to this slide to clarify how each planning function fits into the overall context.
430 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 443/522
TSCM40 Lesson: Introduction to SAP APO-PP/DS
Figure 158: Supply Chain Planning at a Glance
Supply Chain Planning is usually divided into several steps that can be executed
by various components in ECC and/or APO. It is possible and advisable to
integrate these two systems and use both for planning. System integration takes
place using the CIF interface (CIF: Core Interface).
Demand Planning (used, for example, to derive a future demand program from thedemand figures in the past) can either be executed in ECC in Flexible Planning
(with the special case of standard SOP - Sales and Operations Planning), or
in APO in Demand Planning.
Actual Demand Management takes place in ECC. However, planned independent
requirements can also be derived from APO-DP.
Sales orders are always created in the ECC system. A global ATP check of the
sales order can be performed in APO (this can also be integrated with PP/DS).
Cross-plant planning is possible with Supply Network Planning in SAP APO.
Material requirements planning and capacity planning can be executed in ECC
or APO.
Production execution, in other words, the processing of manufacturing orders
(production or process orders), takes place in Manufacturing.
2008 © 2008 SAP AG. All rights reserved. 431
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 444/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Production Planning and Detailed Scheduling at a Glance
Note that planned independent requirements can also be transferred from APO-DP
to ECC (Transfer of Planned Independent Requirements). This transfer is made
using the “Transfer of independent requirements” function from APO Demand
Planning, not the Core Interface, however.
Independent requirements are the starting point for production planning in
APO-PP/DS: Sales orders are created in the ECC system and transferred from
there to APO for planning. Planned independent requirements can be created in
ECC (Demand Management). However, they can also be derived from APO-DP.
Stock transfer requirements can be derived from cross-plant planning within
APO-SNP and then covered using PP/DS. You can also convert SNP plannedorders directly into PP/DS planned orders.
Production execution, in other words, the processing of manufacturing orders
(production or process orders), takes place in Manufacturing. Manufacturing takes
place mainly in ECC.
Figure 159: Demand Program in the Production Plant
The demand program, which has to be covered by PP/DS in the plant, is
determined using planned independent requirements, sales orders, and stock
transfer requirements.
Planned independent requirements may come from ECC Demand Management or
from APO Demand Planning. Sales orders are created in Sales and Distribution
in ECC (ECC SD) and stock transfer requirements can be derived from APO
Supply Network Planning or from ECC.
432 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 445/522
TSCM40 Lesson: Introduction to SAP APO-PP/DS
Time Relationship Between PP and DS
With in-house production, the “boundary” between PP and DS can be within the
planning time fence. In practice, however, explicit detailed scheduling is avoided
a lot of the time.
Figure 160: Time Relationship Between PP and DS
There is not only a business connection between production planning and
detailed scheduling but also a time connection. The PP/DS horizon can be used
to distinguish both areas in the short-term horizon from medium to long term
planning methods such as SNP. Within the PP/DS horizon, production planning
(PP) principally stands for lot-size-based planning in the sense of quantity-based
material requirements planning. The actual realizability/feasibility is generally
only determined during capacity loading (DS) within a short time frame (in which
production is also to be carried out), which, in many cases, can be roughly
characterized using the planning time fence. The planning time fence can
differentiate the quantity planning area of responsibility (MRP function) from theactual detailed scheduling by preventing the MRP run from changing elements
within the planning time fence. However, detailed scheduling with respect to
dates can take place.
PP planning is processed using interactive tools (such as the product view) and PP
heuristics. These calculate the net requirements and map the lot-sizing procedures.
This planning is infinite, and consequently does not take overloads on resources
into account.
2008 © 2008 SAP AG. All rights reserved. 433
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 446/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Detailed scheduling for sequencing can then take place interactively using the
detailed scheduling planning board. In addition, DS heuristics and the PP/DS
Optimizer are available as automated resources.
In the event that Detailed Scheduling with PP planning specifications does not
lead to feasible plans, iterations may be used (for example, repeating Production
Planning with different constraints, new Detailed Scheduling).
Demonstration: APO-DP, SNP and PP/DS
Purpose
Hint: This demonstration should describe a practical overall planningprocedure in APO from DP to PP/DS. This is equivalent to what the
participants would normally learn in the SCM200 course. There are
restrictions with regard to the clients that can be used in APO Demand
Planning: Certain functions (for example, data extraction from ECC) can
currently only be executed in client 800. However, this demonstration
should work in clients other than client 800 too. In this demonstration,
use a product that is not being used by any of the participants and that
will not be used in any demonstrations later in the course. Use group
number 25 as an example.
System Data
System: see weekly e-mail
Client: see weekly e-mail
User ID: Your user ID
Password: Own password
Set up instructions: Standard
1. Execute Interactive Demand Planning, select APO Product T-F225
(version 000), and explain the “Load Data” function.
2. Display and explain the historical data, and execute the forecast. Correct
the forecast: 100 pc. for current month + 3.
3. Display how the forecast data is allocated to locations 1000, 2400, 2500 (for
a better overview, select the Forecast key figure only). Then choose Save.
4. Call transaction “Release to SNP” and use the RELEASE variant to simplify
data entry. Create the following settings:
Planning area: SALES
Planning version (source): 000
Key figure: FINFOR
434 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 447/522
TSCM40 Lesson: Introduction to SAP APO-PP/DS
Planning version (target): 000
Category: Leave blank (no entry)
Horizon: From today to today + 3 months
Daily buckets profile: Delete (leave blank)
Product: T-F225
Execute the release.
Display the result of the release for location 1000 in the product view.
5. Call Interactive Supply Network Planning. Select APO location product
T-F225 and load the data for location 1000.
Explain the planned independent requirements display (forecast key figure)and point out that no receipts have been planned up to now.
6. Execute the heuristic (network).
Display the planning results in the product view for location 1000 and
explain them: In addition to the planned independent requirements, the
PP/DS horizon also contains stock transfer requirements.
7. Convert the next SNP planned order in location 1000 to a PP/DS order
(from the order).
8. Display and evaluate the capacity requirements generated by the resource
WT-L25_1000_001 in the same way as the settings on the slide “Order
and Resource Evaluations”.
Advantages of Production Planning and Detailed Scheduling in APO-PP/DS
• To-the-minute material requirements planning (hours, minutes) for
dependent requirements too
• Advanced options in capacity planning
• Multilevel make-to-order planning with CTP
• Multilevel view of material and capacity availability (pegging)
• Optimization algorithm within the limits of detailed scheduling(minimizing setup times, setup costs, date delays, alternative selection
of resources, ...)
• Dynamic exception messages (alerts)
Simultaneous material and capacity requirements planning with CTP: You
can define resources as “finite” resources in the resource master. With finite
scheduling, order operations are only created on these resources if there is
2008 © 2008 SAP AG. All rights reserved. 435
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 448/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
sufficient capacity for the order quantity on the relevant date. If insufficient
capacity is available, the system searches for a new date when the order operation
can be dispatched, taking into account the capacity situation.
To-the-minute time planning: Dependent requirements and orders are created
with time specifications.
Machine loading optimization: Orders with order sequences that are not optimal
may have been created in planning over a period of time. You can therefore change
the sequence and resource assignment of existing orders in the optimization run.
436 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 449/522
TSCM40 Lesson: Introduction to SAP APO-PP/DS
Facilitated Discussion
Discuss with the participants the advantages and disadvantages of simultaneous
quantity and capacity planning, and work towards the recommendation that these
two processes are performed separately, if possible, in APO too.
Discussion Questions
Use the following questions to engage the participants in the discussion. Feel free
to use your own additional questions.
Draw attention to the various sub-functions in APO and their transitions. Remind
the participants of the key features of APO-PP/DS and compare these with their
expectations.
2008 © 2008 SAP AG. All rights reserved. 437
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 450/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Lesson Summary
You should now be able to:• Name the most important basic features of PP/DS planning
438 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 451/522
TSCM40 Lesson: Master Data Overview
Lesson:
349
Master Data Overview
Lesson Duration: 90 Minutes
Lesson Overview
A brief overview is provided of the master data required for APO-PP/DS. For the
most part, the master data is maintained in ECC.
Lesson Objectives
After completing this lesson, you will be able to:
• Name and characterize the master data for PP/DS planning
This lesson aims merely to provide an overview (SCM200/SCM210). You should
therefore not get caught up in details or spend too much time on it.
Business Example
The master data for the use of APO-PP/DS and integration with ECC has already
been predefined and is verified.
Figure 161: MRP Type “X0” and Integration
2008 © 2008 SAP AG. All rights reserved. 439
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 452/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Planning is not necessarily executed for all materials in APO. For example,
planning for critical materials may take place in APO, while less critical materials
(such as consumption-controlled purchasing materials) may still be planned onlyin ECC.
Materials that have been planned in APO cannot be planned again in ECC – the
planning result from APO is transferred directly to ECC in the form of planning
orders or production orders. However, for materials that have a BOM, dependent
requirements can be generated in ECC for components that are not relevant for
APO. You therefore assign a special MRP type to these materials with the MRP
procedure “X” (“without MRP, with BOM explosion”). (This MRP procedure is
available as of release 4.0. If you work with earlier releases, use MRP type “P4”
with a planning time fence of 999 days).
It is also possible to use the MRP type X0 to select materials relevant for SAP
APO in the integration model. If you give materials that are to be planned in
APO a special plant-specific material status, you can use the material status to
restrict the selection further.
Master and transaction data can be transferred between ECC and SCM if there
is an active integration model for this.
An integration model is uniquely defined by its name and application. It is
possible and practical to create several integration models with the same name but
as different applications (for material masters, resources, transaction data, ATP,
and so on). As a rule, make sure that the data pools of your integration models are
not too big, since this makes error handling much easier.
Figure 162: Product Master
440 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 453/522
TSCM40 Lesson: Master Data Overview
The product master represents the mapping of information relevant for planning
from the material master. The majority of fields (for example, procurement type)
are maintained from ECC (maintenance in ECC, transfer to CIF, mapping to theAPO product master). Only fields that have no equivalent in ECC (for example,
the PP/DS horizon) are maintained in the APO product master directly.
Figure 163: Available Capacity for Planning in APO-PP/DS
ECC work centers or resources for which capacity planning is to take place in
APO-PP/DS must be included in an active integration model. The corresponding
APO resource is created the first time you activate this. As of SCM 4.0 and
Plug-in 2003.1, there are various options for defining the available capacity for
planning in APO-PP/DS:
• Option 1: You maintain the available capacity in APO. Only the header data
of the work center capacities (for which a change transfer is possible) is
transferred from ECC. Intervals of available capacity that exceed this overall
capacity are maintained in APO. With this option, you can define whether
the APO resources are to be created as single resources, multi-resources, or
mixed resources in the ECC work center capacity or in transaction CFC9.• Option 2: You maintain the available capacity entirely in ECC. Intervals of
available capacity created in ECC are therefore used for planning in APO
(“external capacity”). Any intervals of available capacity that are maintained
in APO are irrelevant for planning. However, any downtimes that may have
been defined are taken into account. Resources have to be included in an
active integration model for this procedure too. As with the case above, you
can determine whether the APO resources are to be created as single, multi
or mixed resources.
2008 © 2008 SAP AG. All rights reserved. 441
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 454/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Figure 164: ECC Production Version and APO-PPM or PDS
For the CIF transfer of routings and bills of material to APO as a production
process model (PPM) or production data structure (PDS), the material master
of the corresponding material must contain a valid production version. The
production version determines a manufacturing process by specifying a routing
and a bill of material.
Several production versions can be defined in the ECC material master (for
example, for different lot size intervals). Each of these production versions is
transferred to APO as an individual PPM/PDS.
Figure 165: Structure of a PDS or PPM
442 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 455/522
TSCM40 Lesson: Master Data Overview
Prerequisites for switching to alternative resources:
• For each activity in an operation, you have stored more than one mode with
alternative resources in PPM or PDS that can be used for carrying out the
activity.
• You have assigned the same priority to linked modes.
In general, these alternatives are not equivalent to one another. You might prefer
to operate a fast, expensive special machine to full capacity rather than the slower,
cheap alternative machine. You therefore need to assign priorities to the modes.
Priority A is the highest priority. Assign priority Z to the modes you only want to
schedule manually in the DS planning board.
When creating an order, the system automatically selects the mode in accordance
with the priority and availability date. In the case of the DS planning board, you
select the mode manually.
If a mode (such as mode 1 in the example) is deselected using Drag & Drop
during rescheduling, the other activities in the same mode are also deselected.
Demonstration: Master Data Overview
Purpose
Overview demo, master data review
Use of material/product T-F200, plant/location 1000
System Data
System: see weekly e-mail
Client: see weekly e-mail
User ID: Your user ID
Password: Own password
Set up instructions: Standard
1. In ECC, open the material master, show MRP planning type X0 and explain
the meaning
2. In ECC, open CFM2 and show the active integration model for T_PUMP0030
(or CFM5 for a filter object search)
3. In APO, open the product and display it
4. In ECC, show work center T-L25, plant 1000 and its capacities
5. In APO, open the associated resource and explain
6. In ECC, show production version 0001
7. In APO, open the production data structure and display it
2008 © 2008 SAP AG. All rights reserved. 443
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 456/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
8. Optional: Call and display production process model in APO
444 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 457/522
TSCM40 Lesson: Master Data Overview
355 Exercise 20: Master Data Overview
Exercise Duration: 25 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Name and describe the basic master data necessary for PP/DS
Business Example
Production planning and detailed scheduling are executed for pump T-F2## (## is
your group number) and its components T-B1##, T-B22##, T-B3## and T-B4##
in plant 1000 in APO-PP/DS.
APO is used in conjunction with ECC. The master data required for production
planning in APO has already been transferred from ECC.
Gain an overview of the master data structure.
Task 1:
The Core Interface (CIF) is used to integrate planning in APO and ECC. As a
representative sample, check material T-F2## (## = your group number) with
regard to the master data settings and the transfer properties.
1. First, view the material master for T-F2##, plant 1000 in ECC. Which MRP
type is entered for the view MRP 1?
2. What is the consequence of this setting?
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 445
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 458/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
3. Note the entry for the scheduling margin key for the view MRP 2. What
float before and float after production does this scheduling margin key (F4
help) provide for and why?
4. Proceed to the view MRP 4. Has a production version been defined for
the production of the end product?
5. Is a production version required in the ECC material master in order to
transfer the ECC master data for planning production to APO-PP/DS?
6. What is the result of the CIF transfer of an ECC production version to APO?
Task 2:
Use the Filter Object Search transaction in ECC, which you can start from the
Core Interface Advanced Planner and Optimizer menu. Check that the followingmaster or transaction data objects are contained in an active integration model
(select the relevant data objects after you start the transaction):
Continued on next page
446 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 459/522
TSCM40 Lesson: Master Data Overview
Material master T-F2## in plant 1000 (enter the material as a general selection
option)
Storage Loc.Stk
Plnd ind. reqmts
Planned Orders
Execute the selection. On the next screen, you see that four filter objects have
been selected.
1. Which integration models contain these filter objects (take note of the model
name and application)?
Material Master:
Storage Loc.Stk:
Planned independent
requirements:
Planned Orders:
2. Check in the same way whether material T-T3## in plant 1000, which
is in the BOM for the finished product, is contained in an active model.
(To do this, make a new selection for this filter object.) Is this material
APO-relevant?
3. What are the implications of this for planning the pump in APO and ECC?
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 447
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 460/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Task 3:
You have just established that planned independent requirements (for example)
for material T-F2## in plant 1000 (and also the material itself) are contained in
an active integration model.
1. So, would a planned independent requirement created in ECC be transferred
to APO?
2. Does this type of transaction data transfer from the ECC system have to
be triggered periodically?
Task 4:
Then display the APO product master for product T-F2##, location 1000.
1. Which PP/DS horizon is set?
2. What form of plan explosion does the product master provide for?
Continued on next page
448 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 461/522
TSCM40 Lesson: Master Data Overview
3. Which planning group does this product belong to?
4. Which lot-sizing procedure is used for this product?
5. In accordance with which requirements strategy is this product planned?
Task 5:
You have previously established that the mapping of the routing and the BOM
should not be carried out with production process models, but with productiondata structures (“Plan explosion” field in the product master). Now view the
production data structure for T-F2##, location 1000, planning version 000.
1. Which output and input products can be seen here?
2. To which activities is a setup key specifically assigned and whatdescription/meaning does this have?
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 449
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 462/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
3. What is the associated resource?
4. What is the time expenditure for the “Produce” step of this operation?
Task 6:
Then display the resources to be used to produce pump T-F2##.
Call up the Resource transaction and select these resources as follows:
Resource: WT-*##_1000* (## = your group number)
Location: 1000 1000
Planning version: 000 000
With this selection, a series of single resources, and multi-mixed resources is
displayed. These are partly used in the production of the assemblies and partlyused during the final assembly. In the following, only the resources of the final
assembly are to be taken into consideration.
1. Take note of which of the following resources are single resources and which
are multi-mixed resources.
Single/Multi
WT-M##_1000_002
WT-V##_1000_002
WT-L##_1000_001
WT-L##_1000_002
WT-E##_1000_001
WT-E##_1000_002
Continued on next page
450 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 463/522
TSCM40 Lesson: Master Data Overview
WT-F##_1000_002
WT-P##_1000_001
WT-P##_1000_002
The resources required for planning were transferred from ECC to APO.
Find the available capacity that has been defined for the resources.
To do this, first determine which basic settings have been made in the
“Change transfer for master data” Customizing step in the CIF Customizing
in ECC.
2. Are changes to work center capacities transferred online?
3. Is “external capacity” used to maintain the available capacity? Does this
apply to all resources?
4. Now examine in more detail which capacity planning settings are relevant
for planning machine capacity 001 of paint shop T-L## in plant 1000
(APO resource WTL##_1000_001) in PP/DS.
First, check whether the available capacity is defined externally for theresource in question. You have already established that the use of “external
capacity” is set for each resource (see above). Therefore, display resource
WT-L##_1000_001. Is the external capacity used?
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 451
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 464/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
5. Which standard available capacity is entered?
6. Have capacity variants (that differ from the standard available capacity)
been defined?
7. Display the relevant ECC work center capacity. Which standard available
capacity is defined here?
8. Have intervals of available capacity been defined?
9. If intervals of available capacity were defined, would they affect planning
in APO?
452 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 465/522
TSCM40 Lesson: Master Data Overview
Solution 20: Master Data Overview
Task 1:
The Core Interface (CIF) is used to integrate planning in APO and ECC. As a
representative sample, check material T-F2## (## = your group number) with
regard to the master data settings and the transfer properties.
1. First, view the material master for T-F2##, plant 1000 in ECC. Which MRP
type is entered for the view MRP 1?
Answer: Menu path: Logistics → Production → Master Data → Material
Master → Material → Display → Display Current.
MRP type: The X0 MRP type is entered.
2. What is the consequence of this setting?
Answer: Effect: The X0 MRP type causes the relevant material to be
excluded from ECC planning. In contrast to the MRP type ND (no
planning), X0 allows a BOM explosion, which is particularly important
if a material is planned in APO but creates dependent requirements that
are to be planned in ECC.
3. Note the entry for the scheduling margin key for the view MRP 2. What
float before and float after production does this scheduling margin key (F4
help) provide for and why?
Answer: The scheduling margin key AP1 is entered with float before
production 0 and float after production 0. APO does not recognizethese buffer times, as a distinction is not made between basic dates and
production dates in APO. APO only recognizes production dates.
4. Proceed to the view MRP 4. Has a production version been defined for
the production of the end product?
Answer: Yes, several production versions have been defined.
5. Is a production version required in the ECC material master in order to
transfer the ECC master data for planning production to APO-PP/DS?
Answer: Yes, to be able to transfer routing and BOM as PPM
(production process model) or PDS (production data structure) to SAPAPO, they must be assigned to a production version.
6. What is the result of the CIF transfer of an ECC production version to APO?
Answer: The ECC production version can be transferred to APO as
PPM or PDS (selection to be set when creating the integration model).
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 453
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 466/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Task 2:
Use the Filter Object Search transaction in ECC, which you can start from the
Core Interface Advanced Planner and Optimizer menu. Check that the following
master or transaction data objects are contained in an active integration model
(select the relevant data objects after you start the transaction):
Material master T-F2## in plant 1000 (enter the material as a general selection
option)
Storage Loc.Stk
Plnd ind. reqmts
Planned Orders
Execute the selection. On the next screen, you see that four filter objects have
been selected.
1. Which integration models contain these filter objects (take note of the model
name and application)?
Material Master:
Storage Loc.Stk:
Planned independent
requirements:
Planned Orders:
Answer: Menu path: Logistics → Central Functions → Supply Chain
Planning Interface → Core Interface Advanced Planner and Optimizer →
Integration Model → Filter Object Search
Integration models: After selection, choose a filter object, select it,
and choose “Find Model”. Observe whether or not the models found
are actually active.
The material master is contained in the active T_PUMP0030/MD I
model, while storage location stock, planned independent requirements
and planned orders are contained in the T_PUMP0030/TD model.
2. Check in the same way whether material T-T3## in plant 1000, which
is in the BOM for the finished product, is contained in an active model.
(To do this, make a new selection for this filter object.) Is this material
APO-relevant?
Answer: No, the material is not contained in any active model and is
therefore not relevant for APO.
Continued on next page
454 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 467/522
TSCM40 Lesson: Master Data Overview
3. What are the implications of this for planning the pump in APO and ECC?
Answer: This means that this material is planned in ECC but dependent
requirements from the APO planning of the material in question are
taken into account if required.
Task 3:
You have just established that planned independent requirements (for example)
for material T-F2## in plant 1000 (and also the material itself) are contained in
an active integration model.
1. So, would a planned independent requirement created in ECC be transferred
to APO?
Answer: Are planned independent requirements created in ECCtransferred to APO? Yes, planned independent requirements created in
ECC for material T-F2## in plant 1000 are transferred to APO.
2. Does this type of transaction data transfer from the ECC system have to
be triggered periodically?
Answer: No, the transfer takes place automatically.
Task 4:
Then display the APO product master for product T-F2##, location 1000.
1. Which PP/DS horizon is set?
Answer: SCM menu path: Advanced Planning and Optimization →
Master Data → Product → Product
“PP/DS”, “Lot Size” and “Demand” tab pages
A PP/DS horizon of 60 days is entered. Note: Let your instructor know
if a different horizon is entered here. The master data will then be
adjusted according to the instructions in the trainer manual.
2. What form of plan explosion does the product master provide for?
Answer: The production data structure is used (plan explosion “5”).
3. Which planning group does this product belong to?
Answer: The planning group is ## (your group number).
4. Which lot-sizing procedure is used for this product?
Answer: The exact lot size is used.
5. In accordance with which requirements strategy is this product planned?
Answer: The planning is carried out with requirements strategy 20,
planning with final assembly, which corresponds to ECC strategy 40.
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 455
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 468/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Task 5:
You have previously established that the mapping of the routing and the BOM
should not be carried out with production process models, but with production
data structures (“Plan explosion” field in the product master). Now view the
production data structure for T-F2##, location 1000, planning version 000.
1. Which output and input products can be seen here?
Answer: SCM menu path: Advanced Planning and Optimization →
Master Data → Production Data Structure (PDS) → Display Production
Data Structures
(“Components” tab page) output: T-F2##, input: T-B1##, T-B22##,
T-B3##, T-B4##
2. To which activities is a setup key specifically assigned and whatdescription/meaning does this have?
Answer: (“Activities” tab page) A setup key 10 has been assigned to
operation 30, comprising the two activities Set up and Produce. This
describes the color that is used in this painting step (white).
3. What is the associated resource?
Answer: (Detail on activity) WT-L##_1000_001
4. What is the time expenditure for the “Produce” step of this operation?
Answer: (Detail for activity) 1200 seconds per base quantity (note: this
is in the component overview for the end product: 1 piece).
Continued on next page
456 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 469/522
TSCM40 Lesson: Master Data Overview
Task 6:
Then display the resources to be used to produce pump T-F2##.
Call up the Resource transaction and select these resources as follows:
Resource: WT-*##_1000* (## = your group number)
Location: 1000 1000
Planning version: 000 000
With this selection, a series of single resources, and multi-mixed resources is
displayed. These are partly used in the production of the assemblies and partly
used during the final assembly. In the following, only the resources of the final
assembly are to be taken into consideration.
1. Take note of which of the following resources are single resources and whichare multi-mixed resources.
Single/Multi
WT-M##_1000_002 M
WT-V##_1000_002 M
WT-L##_1000_001 S
WT-L##_1000_002 S
WT-E##_1000_001 M
WT-E##_1000_002 M
WT-F##_1000_002 M
WT-P##_1000_001 M
WT-P##_1000_002 S
The resources required for planning were transferred from ECC to APO.
Find the available capacity that has been defined for the resources.
To do this, first determine which basic settings have been made in the
“Change transfer for master data” Customizing step in the CIF Customizing
in ECC.
Answer: (See table)
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 457
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 470/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
2. Are changes to work center capacities transferred online?
Answer: Menu path: ECC Customizing: Transaction SPRO → F5 →
Integration with Other mySAP.com Components → Advanced Planning
and Optimization → Basic Settings for the Data Transfer → Change
Transfer → Change Transfer for Master Data → Configure Change
Transfer for Master Data
Yes, changes to work center capacities are transferred online because the
“Immediate transfer” indicator is set.
3. Is “external capacity” used to maintain the available capacity? Does this
apply to all resources?
Answer: The external capacity is set for each resource and therefore
must be checked separately for each individual resource.
4. Now examine in more detail which capacity planning settings are relevant
for planning machine capacity 001 of paint shop T-L## in plant 1000
(APO resource WTL##_1000_001) in PP/DS.
First, check whether the available capacity is defined externally for the
resource in question. You have already established that the use of “external
capacity” is set for each resource (see above). Therefore, display resource
WT-L##_1000_001. Is the external capacity used?
Answer: SCM menu path: Advanced Planning and Optimization →
Master Data → Resource → Resource
No, external capacity is not used.
5. Which standard available capacity is entered?
Answer: A work time of 7:00 to 15:00 with a break of 1 hour and 100%
resource utilization is set.
6. Have capacity variants (that differ from the standard available capacity)
been defined?
Answer: (Capacity Variants button) No capacity variants that differ
from the standard available capacity have been defined.
7. Display the relevant ECC work center capacity. Which standard available
capacity is defined here?Answer: Menu path: Logistics → Production → Master Data → Work
Centers → Work Center → Display
Work center T-L##, plant 1000, Capacities view, details on capacity
category 001
Standard available capacity in ECC: A working time of 7:00 to 15:00
with a break of 1 hour and a 100% rate of capacity utilization is set.
Continued on next page
458 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 471/522
TSCM40 Lesson: Master Data Overview
8. Have intervals of available capacity been defined?
Answer: (Intervals and Shifts buttons) No intervals of available capacity
that deviate from the standard have been defined.
9. If intervals of available capacity were defined, would they affect planning
in APO?
Answer: ECC intervals of available capacity would not have any effect
on the APO planning under the given circumstances. These intervals
only affect planning in APO if the external capacity is used in APO.
2008 © 2008 SAP AG. All rights reserved. 459
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 472/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Lesson Summary
You should now be able to:• Name and characterize the master data for PP/DS planning
460 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 473/522
TSCM40 Lesson: Demand Management with APO PP/DS
Lesson:
371
Demand Management with APO PP/DS
Lesson Duration: 75 Minutes
Lesson Overview
As in the ECC system, you can use planning to generate a requirement situation
before sales orders have been received. You can manage planning either in ECC
or APO, whereas sales orders are only managed in ECC. Planning with Final
Assembly in APO and the option of simultaneous quantity and capacity planning
with the CTP (Capable-to-Promise) procedure will be highlighted by way of
example.
Lesson Objectives
After completing this lesson, you will be able to:
• Manage and characterize requirements and their behavior in Demand
Management in APO
• Describe the CTP (Capable-to-Promise) scenario
This unit merely provides an exemplary and considerably restricted illustration of
Demand Management using APO-PP/DS. An example and an exercise are used to
elaborate the fundamental features of handling strategies. If required, experienced
instructors can also address the topic of APO Customizing for the requirements
strategy, the check mode and the CTP procedure.
Business Example
Products are produced in accordance with planning using make-to-stock
production, for example. From there, sales orders are delivered. In some cases
it makes sense to create a feasibility study in the availability check from within
the sales order.
2008 © 2008 SAP AG. All rights reserved. 461
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 474/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Figure 166: Planned Independent Requirements and Sales Orders
Demand Management applies to the management of independent requirements.
The way in which independent requirements behave in material requirements
planning (for example, whether they affect requirements or whether they consume
other requirements) can be determined by their requirement type or by the
requirements strategy.
Planned independent requirements are stock requirements that can be derived from
a forecast of future demand. In make-to-stock production, you want to initiate theprocurement of the materials concerned, without having to wait for actual sales
orders. This means that delivery times can be shortened. It also means that you
can use forecast planning to distribute the load across the individual production
resources as evenly as possible.
Planned independent requirements can be created in APO-DP and released to
APO-PP/DS. Alternatively, they can be created in ECC and transferred to APO
using the Core Interface (CIF).
Sales orders (customer independent requirements) are created by sales and
distribution in ECC. Customer requirements may be transferred directly to
material requirements planning, depending on the requirements type that has been
defined. This is always required for customer-specific planning. For planning in
APO PP/DS, the sales orders have to be transferred to APO using the CIF.
Sales orders can be used as exclusive requirements sources, for which procurement
is then specifically triggered (make-to-order production), or, together with planned
independent requirements, they can create the total requirement. Consumption
with planned independent requirements is also possible.
462 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 475/522
TSCM40 Lesson: Demand Management with APO PP/DS
Figure 167: Example: Planning with Final Assembly
In planning with final assembly, the emphasis is on allowing you to react flexibly
to customer requirements. The main difference between this requirements strategy
and make-to-stock production is that sales orders affect requirements.
In planning with final assembly, the planned independent requirements are entered
at finished product level too. This means that the procurement and manufacture of
the finished product is already started before the sales order is received. As soon
as a sales order is received, it consumes the planned independent requirement.
Consumption of planned independent requirements by customer requirementsdepends on the settings defined for the consumption mode and the consumption
periods.
Planned independent requirements that are not required increase the stock level in
that they are not adjusted to customer requirements. Since requirements are not
reduced according to the FIFO rule in this strategy (the delivery for a sales order
reduces this order and the planned independent requirements quantity it consumes
instead), the deletion of planned independent requirement quantities that are no
longer required has particular significance in requirements strategy 20.
In APO, you can adjust planned independent requirements created in APO using
the “Planning Adjustment” transaction (/sapapo/MD74). The planned independent
requirements that are no longer required are set to zero for the selected time period.
This function can be scheduled periodically (for example, daily). (The transaction
is similar to transaction MD74 in ECC.) If the planned independent requirements
were created in ECC, they must also be deleted in ECC (reorganization).
2008 © 2008 SAP AG. All rights reserved. 463
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 476/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Demonstration: Planning with Final Assembly(Strategy 20)
Purpose
Preparing the exercise
Hint: This demonstration serves as preparation for the exercises that
follow. Planning data should already exist for product T-F200 in plant
1000. This data must be deleted.
System Data
System: see weekly e-mail
Client: see weekly e-mail
User ID: Your user ID
Password: Own password
Set up instructions: Standard
1. Create and verify the settings for planning with final assembly in the ECC
material master (strategy group 40) and the APO product master (strategy
20) for T-F200 in plant 1000. Explain the consumption mode settings.
In the APO product master, set a PP/DS horizon of 60 days.
2. Create a goods receipt for T-F200 in plant 1000 (movement type 501):15 PC
3. Create planned independent requirements.
25 pc. for current week +2
50 pc. for current week 3
25 pc. for current week 4
25 pc. for current week 5
25 pc. for current week 6
25 pc. for current week 725 pc. for current week 8
25 pc. for current week 9
25 pc. for current week 10
Display the result in ECC (current stock/requirements list) and in APO
(product view).
464 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 477/522
TSCM40 Lesson: Demand Management with APO PP/DS
4. Create an ECC customer requirement for T-F200 (4 pc for day 4 of the
current week + 2) and explain the result in APO: The customer requirement
is relevant for requirements and is consumed.
5. Execute interactive APO planning (product heuristic) and explain the result:
The requirements are covered by corresponding procurement elements
(planned orders). Display the dependent requirement for T-B100.
Hint: Do not delete the data from the previous demonstration. It is to be
used as a basis for the following demonstrations.
Figure 168: ATP Check for Sales Orders in APO
In the Core Interface (CIF), you can specify in the integration model that the
availability check (ATP check) in the sales order is to be performed in APO rather
than in ECC. If you create a sales order in ECC, an ATP request will be sent to
APO. The system first checks whether enough stock is available for this product
and whether receipts (for example, production orders, planned orders) have
already been planned by the requested date.
In the case of non-availability, you can set the ATP check so that the system
performs an availability check for the product in a different location or for an
alternative product. Moreover, for non-availability of the product, you can specify
that the sales order triggers production directly: In this case, APO creates a
planned order for the requested quantity in PP/DS. The system can then take
capacity constraints (available capacity and even receipts that have already
been planned) into account. The component availability can also be checked.
2008 © 2008 SAP AG. All rights reserved. 465
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 478/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
If there is no longer any capacity available for the desired availability date, the
system searches for a new date on which the planned order can be created. The
availability date of the newly created planned order (finish date) is then transferredback to the ECC sales order and copied as the confirmation date.
466 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 479/522
TSCM40 Lesson: Demand Management with APO PP/DS
375 Exercise 21: Planning with Final Assembly
in APO-PP/DSExercise Duration: 30 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Create planned independent requirements and customer requirements for
planning with final assembly in APO-PP/DS
• Execute consumption
Business ExampleProduction Planning and Detailed Scheduling is executed for pump T-F2## in
plant 1000 in APO-PP/DS. Detailed scheduling is to take place within a horizon of
60 days.
Demand Management takes place in ECC: Planned independent requirements and
customer requirements are created in ECC and transferred to APO.
Hint: Make sure that the data and dates are entered correctly because the
exercise examples follow on from each other.
Task 1:
Production planning and detailed scheduling is to take place within a horizon of
60 days. The product is planned in planning with final assembly. Change or check
the APO product master for pump T-F2## accordingly:
1. Change or check the product master for:
product T-F2## in
location 1000
Go to the PP/DS tab page and check that a PP/DS Horizon of 60 days
has been entered.
Switch to the Demand tab page, and check that requirements strategy
20 (planning with final assembly) has been set. What settings are defined
for consumption?
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 467
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 480/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Consumption mode: __________________
Fwd Consumption Per.: __________________
Bwd Consumption Per.: __________________
Save the product master if required.
2. Assume that you change the PP/DS horizon in the APO product master.
Would this create an inconsistency between APO and ECC? Why (not)?
__________________________________________________
__________________________________________________
3. Would the change you made be overwritten with a change transfer from
ECC?
__________________________________________________
Task 2:
In ECC, enter stock and planned independent requirements as a basis for material
requirements planning in APO.
1. From the Inventory Management menu, start the Goods Receipt Other
(MIGO) transaction. Enter the required data (for example, on the details
screen in the lower half of the initial screen). To do so, choose “Goods
receipt” and “Other” in the selection criteria and enter:
On the “Material” tab page
Material: T-F2##
On the “Quantity” tab page
Quantity: 5 pc
On the “Where” tab page
Movement type: 501 (Goods receipt w/o PO)
Plant: 1000
Storage Location: 0002
To confirm your entries, press Enter and Post the document.
2. Is further action required in the SCM or ECC systems to transfer the stock
to APO?
Continued on next page
468 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 481/522
TSCM40 Lesson: Demand Management with APO PP/DS
____________________________________________________
3. Display the results of the stock posting in the APO product view: Access
the product view from the APO Production Planning menu: Enter the
following data on the initial screen:
Planning version:: 000
Product: T-F2##
Location: 1000
To confirm, press Enter .
Is the stock displayed?
___________________________________________________
4. Note the end of the PP/DS horizon.
_____________________________________
Why is this date set?
___________________________________________________
5. In ECC, create planned independent requirements for the pump. Use the
Create Planned Independent Requirements transaction, which you can
start from the Demand Management menu. On the initial screen of the
transaction, enter Material T-F2##, Plant 1000, and Version 00. Use weeks
as the planning period. When you choose Enter , the planning table isdisplayed. Enter the following requirements quantities:
Hint: The “current week + 3” is in three weeks’ time (fourth time
column from the left)
Current week + 3: 55 PC
Current week + 4: 25 PC
Current week + 5: 25 PC
Current week + 6: 25 PC
Current week + 7: 25 PC
Current week + 8: 25 PC
Current week + 9: 25 PC
Current week + 10: 25 PC
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 469
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 482/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
What is the ECC requirements type of these planned independent
requirements? (The requirements type is indicated on the Items tab page,
for example.)
____________________________________________________
Does this requirements type control the consumption of the planned
independent requirements in APO?
____________________________________________________
Save the planned independent requirements.
6. Display the result in the APO product view for pump T-F2## (refresh or
access it as described above).
Are the planned independent requirements displayed?
____________________________________________________
Look also at the planned independent requirements on the Forecast tab page
in the product view. Which setting controls the behavior of the planned
independent requirements in APO (for example, consumption)?
____________________________________________________
Task 3:
The stock/requirements situation for pump T-F2## has changed. Execute
interactive planning for the pump from the APO product view.
1. Proceed to the planning of product T-F2## in plant 1000 in Change in the
product view. If necessary, select the SAPALL propagation range.
Use the Product Heuristic function to execute planning. Planning is executed
after you confirm the screen by choosing Enter. Planning results in planned
orders.
Are the planned independent requirements within the PP/DS horizon covered
by planned orders?
____________________________________________________
Are the planned independent requirements outside the PP/DS horizon
covered by planned orders? Why (not)?
____________________________________________________
____________________________________________________
Save your plan.
Continued on next page
470 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 483/522
TSCM40 Lesson: Demand Management with APO PP/DS
2. Can the planned orders you just created be converted into production orders?
Is procurement of the pump initiated?
Hint: Answer the question, taking in account the conversion
indicator ready for input. However, do not carry out the conversion.
____________________________________________________
3. Go to the product view for assembly T-B1## in plant 1000. Do requirements
exist for this assembly? If so, where do they come from?
____________________________________________________
4. Are the requirements covered by planned orders?
___________________________________________________
Task 4:
A customer orders 3 pumps. Create a corresponding sales order below.
1. In ECC, start the “Create Sales Order” transaction from the Sales and
Distribution menu and create a sales order with the following parameters:
Order Type: OR
Sales Organization: 1000
Distribution Channel: 10Division: 00
Choose Enter to access the item overview. Enter the following data:
Sold-to party: 1000
Ship-to party: 1000
PO number: K##_01
Required delivery date: Thursday of the current week
plus 4 weeks
Note the current date: __________
Material: T-F2##
Order quantity: 3 PC
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 471
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 484/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Choose Enter to confirm your entries and then go to the APO ATP check for
the order (choose Check Item Availability).
Hint: If the screen shows only schedule line 0001 with a red traffic
light at this point, cancel sales order maintenance, exit the “Create
Sales Order” transaction completely (that is, do not remain on the
initial screen), and inform your course instructor.
This display indicates that the APO ATP check has not been properly
implemented, that is, it does not check the stock. The course
instructor must adjust the check instructions before you start this
exercise.
Exit the ATP check screen by choosing Continue without confirmation onthe top left of the screen. Then Save the sales order and take note of its
order number.
___________________________________________________
2. You have just created an unconfirmed sales order. Display this sales order in
the APO Product View. What date is shown for the requirement?
___________________________________________________
What is the requirement quantity, requested quantity, confirmed quantity?
___________________________________________________
3. Create a second sales order in ECC with the parameters from task 4.1 andthe differing PO number K##_02 for 1 piece of pump T-F2## and execute an
ATP check again (Check item availability button). Display the schedule line
overview on the ATP screen. What is the earliest date on which full delivery
of the customer request is possible?
___________________________________________________
In this case, confirm the sales order with full delivery and then check the
schedule line screen again to verify the confirmed quantity.
Save the changed sales order.
Display the second sales order in the Product View (which you may have torefresh). What date is shown for the requirement?
___________________________________________________
What is the requirement quantity, confirmed quantity, requested quantity?
___________________________________________________
4. Are the planned independent requirements consumed by the sales order (see
also the Forecast tab page)?
Continued on next page
472 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 485/522
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 486/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Solution 21: Planning with Final Assembly
in APO-PP/DSTask 1:
Production planning and detailed scheduling is to take place within a horizon of
60 days. The product is planned in planning with final assembly. Change or check
the APO product master for pump T-F2## accordingly:
1. Change or check the product master for:
product T-F2## in
location 1000
Go to the PP/DS tab page and check that a PP/DS Horizon of 60 dayshas been entered.
Switch to the Demand tab page, and check that requirements strategy
20 (planning with final assembly) has been set. What settings are defined
for consumption?
Consumption mode: __________________
Fwd Consumption Per.: __________________
Bwd Consumption Per.: __________________
Save the product master if required.
a) SCM menu path: Advanced Planning and Optimization → Master
Data → Product
Consumption settings:
Consumption mode: 2 (Backward/forward consumption)
Fwd Consumption Per.: 30 days
Bwd Consumption Per.: 30 days
2. Assume that you change the PP/DS horizon in the APO product master.Would this create an inconsistency between APO and ECC? Why (not)?
__________________________________________________
__________________________________________________
a) Inconsistencies between APO and ECC? No, the data would still be
consistent because the PP/DS horizon has not been copied from
ECC.
Continued on next page
474 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 487/522
TSCM40 Lesson: Demand Management with APO PP/DS
3. Would the change you made be overwritten with a change transfer from
ECC?
__________________________________________________
a) Change transfer from ECC? No, the change would not be overwritten
because only the fields that can be transferred from ECC are
affected by a change transfer.
Task 2:
In ECC, enter stock and planned independent requirements as a basis for material
requirements planning in APO.
1. From the Inventory Management menu, start the Goods Receipt Other
(MIGO) transaction. Enter the required data (for example, on the detailsscreen in the lower half of the initial screen). To do so, choose “Goods
receipt” and “Other” in the selection criteria and enter:
On the “Material” tab page
Material: T-F2##
On the “Quantity” tab page
Quantity: 5 pc
On the “Where” tab page
Movement type: 501 (Goods receipt w/o PO)
Plant: 1000
Storage Location: 0002
To confirm your entries, press Enter and Post the document.
a) Menu path: Logistics → Materials Management → Inventory
Management → Goods Movement → Goods Receipt → Other (MIGO)
2. Is further action required in the SCM or ECC systems to transfer the stock
to APO?
____________________________________________________
a) Is further action required? No, the stock is transferred automatically.
3. Display the results of the stock posting in the APO product view: Access
the product view from the APO Production Planning menu: Enter the
following data on the initial screen:
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 475
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 488/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Planning version:: 000
Product: T-F2##
Location: 1000
To confirm, press Enter .
Is the stock displayed?
___________________________________________________
a) SCM menu path: Advanced Planning and Optimization → Production
Planning → Interactive Production Planning → Product Overview
Stock displayed? Yes, the stock is displayed.
4. Note the end of the PP/DS horizon.
_____________________________________
Why is this date set?
___________________________________________________
a) End of the PP/DS horizon: This varies (current date + 2 months) .
Reason: The production horizon (of 60 days) is calculated forwards,
starting from the current date.
5. In ECC , create planned independent requirements for the pump. Use the
Create Planned Independent Requirements transaction, which you canstart from the Demand Management menu. On the initial screen of the
transaction, enter Material T-F2##, Plant 1000, and Version 00. Use weeks
as the planning period. When you choose Enter , the planning table is
displayed. Enter the following requirements quantities:
Hint: The “current week + 3” is in three weeks’ time (fourth time
column from the left)
Current week + 3: 55 PC
Current week + 4: 25 PCCurrent week + 5: 25 PC
Current week + 6: 25 PC
Current week + 7: 25 PC
Current week + 8: 25 PC
Current week + 9: 25 PC
Continued on next page
476 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 489/522
TSCM40 Lesson: Demand Management with APO PP/DS
Current week + 10: 25 PC
What is the ECC requirements type of these planned independent
requirements? (The requirements type is indicated on the Items tab page,
for example.)
____________________________________________________
Does this requirements type control the consumption of the planned
independent requirements in APO?
____________________________________________________
Save the planned independent requirements.
a) Menu path: Logistics → Production → Production Planning →
Demand Management → Planned Independent Requirements → Create
ECC requirements type: The planned independent requirements
have requirements type VSF.
b) Consumption controlled by requirements type? No. The consumption
in APO results from the requirements strategy in the product
master and the check mode in the sales order.
6. Display the result in the APO product view for pump T-F2## (refresh or
access it as described above).
Are the planned independent requirements displayed?
____________________________________________________
Look also at the planned independent requirements on the Forecast tab page
in the product view. Which setting controls the behavior of the planned
independent requirements in APO (for example, consumption)?
____________________________________________________
a) Planned independent requirements displayed? Yes.
b) Behavior of the planned independent requirements in APO: The
behavior of the planned independent requirements is defined in
APO by the requirements strategy in the product master.
Task 3:
The stock/requirements situation for pump T-F2## has changed. Execute
interactive planning for the pump from the APO product view.
1. Proceed to the planning of product T-F2## in plant 1000 in Change in the
product view. If necessary, select the SAPALL propagation range.
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 477
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 490/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Use the Product Heuristic function to execute planning. Planning is executed
after you confirm the screen by choosing Enter. Planning results in planned
orders.
Are the planned independent requirements within the PP/DS horizon covered
by planned orders?
____________________________________________________
Are the planned independent requirements outside the PP/DS horizon
covered by planned orders? Why (not)?
____________________________________________________
____________________________________________________
Save your plan.
a) Planned independent requirements within the PP/DS horizon covered?
Yes, the requirements within the PP/DS horizon are covered by
planned orders.
b) Planned independent requirements outside the PP/DS horizon covered?
No, the requirements outside the PP/DS horizon are not covered.
Outside the PP/DS horizon, planning in SNP is responsible for
covering the requirements.
2. Can the planned orders you just created be converted into production orders?
Is procurement of the pump initiated?
Hint: Answer the question, taking in account the conversion
indicator ready for input. However, do not carry out the conversion.
____________________________________________________
a) Procurement of the pump initiated? Yes, the planned orders can be
converted into production orders. Procurement of the pump is
initiated.
3. Go to the product view for assembly T-B1## in plant 1000. Do requirements
exist for this assembly? If so, where do they come from?
____________________________________________________
a) Requirements for this assembly? Yes, dependent requirements exist.
They originate in the planned orders for procuring the finished
product pump T-F2##.
4. Are the requirements covered by planned orders?
Continued on next page
478 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 491/522
TSCM40 Lesson: Demand Management with APO PP/DS
___________________________________________________
a) Requirements covered? No, the requirements are not covered.
Planning has not yet been executed for the assembly.
Task 4:
A customer orders 3 pumps. Create a corresponding sales order below.
1. In ECC, start the “Create Sales Order” transaction from the Sales and
Distribution menu and create a sales order with the following parameters:
Order Type: OR
Sales Organization: 1000
Distribution Channel: 10
Division: 00
Choose Enter to access the item overview. Enter the following data:
Sold-to party: 1000
Ship-to party: 1000
PO number: K##_01
Required delivery date: Thursday of the current week
plus 4 weeksNote the current date: __________
Material: T-F2##
Order quantity: 3 PC
Choose Enter to confirm your entries and then go to the APO ATP check for
the order (choose Check Item Availability).
Hint: If the screen shows only schedule line 0001 with a red traffic
light at this point, cancel sales order maintenance, exit the “Create
Sales Order” transaction completely (that is, do not remain on the
initial screen), and inform your course instructor.
This display indicates that the APO ATP check has not been properly
implemented, that is, it does not check the stock. The course
instructor must adjust the check instructions before you start this
exercise.
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 479
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 492/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Exit the ATP check screen by choosing Continue without confirmation on
the top left of the screen. Then Save the sales order and take note of its
order number.
___________________________________________________
a) Menu path: Logistics → Sales and Distribution → Sales → Order
→ Create
Date: Varies.
Sales order number: Varies, for example, 9835.
2. You have just created an unconfirmed sales order. Display this sales order in
the APO Product View. What date is shown for the requirement?
___________________________________________________
What is the requirement quantity, requested quantity, confirmed quantity?
___________________________________________________
a) Date of the unconfirmed sales order in APO: This varies. It is
generally the desired delivery date. However, the date of material
staging must be very early to ensure timely delivery to the customer.
b) Requirement quantity, confirmed quantity, requested quantity (without
plus or minus sign): 3, 0, 3.
3. Create a second sales order in ECC with the parameters from task 4.1 and
the differing PO number K##_02 for 1 piece of pump T-F2## and execute an
ATP check again (Check item availability button). Display the schedule line
overview on the ATP screen. What is the earliest date on which full delivery
of the customer request is possible?
___________________________________________________
In this case, confirm the sales order with full delivery and then check the
schedule line screen again to verify the confirmed quantity.
Save the changed sales order.
Display the second sales order in the Product View (which you may have to
refresh). What date is shown for the requirement?
___________________________________________________
What is the requirement quantity, confirmed quantity, requested quantity?
Continued on next page
480 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 493/522
TSCM40 Lesson: Demand Management with APO PP/DS
___________________________________________________
a) Earliest full delivery: Full delivery is possible on the requested
delivery date.
b) Requirements date in product view: This varies. Generally the
requested delivery date.
c) Requirement quantity, confirmed quantity, requested quantity (without
plus or minus sign): 1, 1, 1.
4. Are the planned independent requirements consumed by the sales order (see
also the Forecast tab page)?
____________________________________________________
a) Sales order consumption? Yes, the sales orders consume the planned
independent requirements.
2008 © 2008 SAP AG. All rights reserved. 481
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 494/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Lesson Summary
You should now be able to:• Manage and characterize requirements and their behavior in Demand
Management in APO
• Describe the CTP (Capable-to-Promise) scenario
482 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 495/522
TSCM40 Lesson: Production Planning with APO PP/DS
Lesson:
390
Production Planning with APO PP/DS
Lesson Duration: 75 Minutes
Lesson Overview
Production planning with APO PP/DS describes not only material requirements
planning but also detailed scheduling steps, where necessary. Both can take place
in the same planning run (normally arranged sequentially). Individual materials
can also have different planning procedures to “planning in planning run”.
Lesson Objectives
After completing this lesson, you will be able to:
• Name the planning procedure
• Describe and implement the multilevel planning run
This section focuses on multilevel planning. As well as material requirements
planning, which is always performed with reference to the product, this can
also mean that heuristics for the detailed scheduling of resources, or even the
optimizer, are used. You therefore need to make the difference between the MRP
run (ECC) and the production planning run (APO) clear to the participants. Try to
clarify the term “heuristic” as simply as possible, and explain that where different
business problems arise, a production planning run orientates itself towards the
heuristics that match the context and uses them to solve the problem. Place
particular emphasis on establishing the connection between the product heuristic
and the planning procedure and point out that “PP heuristics” have predefined
strategy characteristics (finite/infinite).
Turn the (optional) exercise in this unit into a kind of workshop, if necessary, by
not going into all the entries in detail.
Business Example
Different planning processes and planning runs are used depending on the
planning scenario. The production planning run that will be tested in this context
by way of an example is typical for practical applications.
2008 © 2008 SAP AG. All rights reserved. 483
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 496/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Figure 169: PP Planning Procedure
The PP planning procedure in the product master describes how a product is to
be planned. For example, you can plan a product in the planning run and write
planning file entries only if there are planning-relevant changes (this is the same
as material requirements planning in SAP ECC). Alternatively, you can carry
out immediate planning of a product in particular cases (automatic planning
immediately). The recommended default setting is “Planning in Planning Run”.
You can select from several different planning procedures that must be defined in
Customizing for PP/DS. These procedures define the system behavior in responseto different events. An heuristic is also saved here and must be used in automatic
planning.
Note that in general, settings for automatic planning always have a negative effect
on performance. You should therefore only ever choose this setting for good
business reasons (for example, as part of a CTP planning). It should be limited
to the minimum number of necessary products only.
484 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 497/522
TSCM40 Lesson: Production Planning with APO PP/DS
Figure 170: Executing the Production Planning Run
Production planning can be executed in two ways: Either as interactive single-item
planning for a product or as total planning for a group of products that can be
defined as you wish (for example, all products from a plant). Total planning can
be executed online or in background processing.
In online planning, the production planning run is executed immediately. This
procedure is ideal for low data quantities. To prevent time-consuming online
planning with data quantities that are too large from adversely affecting the
system response time, the time for executing the report is restricted: If a report
runs longer than five minutes in interactive mode, the system terminates the run
automatically. For this reason, background processing should always be used
for extensive planning.
In production planning in background processing, you use variants that contain
settings for mass planning. This function allows you to start the job immediately
or determine that it is to be started at a later point in time, so that there is no
negative effect on system performance at the wrong time. This procedure is
usually used when planning mass data.
2008 © 2008 SAP AG. All rights reserved. 485
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 498/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Figure 171: Control Parameters for the Production Planning Run (1)
You define the parameters for configuring the production planning run on the
initial screen. These can be saved using variants, and you can also execute
production planning in the background in this way.
Using the time profile, you can define the particular period for which planning
is to be carried out for a whole range of heuristics.
You use the propagation range to determine which resources and products can
be changed. You can only schedule resources and products that are within the
propagation range.
You can perform a production planning run and save its results in a simulation
version. You can then decide at a later time whether or not you want to use the
simulation in the operational planning version.
There are two different types of processing steps in the production planning run:
functions (for detailed scheduling) and heuristics (for production planning). You
cannot change functions. However, you can define heuristics in Customizing for
Production Planning and Detailed Scheduling.
Control Parameters for the Production Planning Run (2)
If the selection is carried out across several plants, the system takes dependencies
between the plants into account during planning.
486 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 499/522
TSCM40 Lesson: Production Planning with APO PP/DS
Figure 172: Control Parameters for the Production Planning Run (2)
In the production planning run, you can define several sequential processing steps
in which the system executes various heuristics and functions for the specified
objects. You can define here which objects are to be processed with which
heuristics or functions. The objects must be compatible with the selected heuristic.
For example, production planning heuristics can only plan products.
You can execute several heuristics or functions sequentially. Functions such as
optimization or scheduling can be carried out after a production planning run.
Multiple production planning runs can be performed sequentially for various
products, for example. In finite planning, the sequence of products in planning
can be defined.
For each processing step, you determine: 1. The heuristic or function to be
executed in this step; 2. The strategy profile to be used for the heuristic or
function. If you decide to use the optimization function, you have to enter an
optimization profile; 3. The objects (for example, 4 = products) for which the
heuristics/functions are to be executed; 4. If necessary, further selections that can
be used to restrict planning to specific objects.If you set the “Planning file entry” indicator on the initial screen of the production
planning run, you can limit planning to products that have had changes relevant
for planning made to them (net change planning).
2008 © 2008 SAP AG. All rights reserved. 487
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 500/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Figure 173: Example: Complete Production Planning Process
The objective of a production planning run is generally to create a “feasible”
demand program. The actual planning is normally broken down into several steps,
as shown in the process example:
• To ensure consistent planning, the stage numbering algorithm for determining
the low-level codes must be executed regularly. This algorithm may, for
example, be scheduled either at the start of a planning run or separately atregular intervals (weekly).
• Normal material requirements planning is carried out with the
SAP_MRP_001 heuristic. This planning is executed infinitely.
• In order to link the created structure of requirements and requirement
coverage elements with each other on multiple levels (and therefore to be
able to optimize on multiple levels later on), a heuristic for creating fixed
pegging is used.
• The capacity planning step can be carried out with the optimizer, which, in
addition, can carry out simultaneous sequencing with regard to setup times
or scheduling delays.
• Following optimization, the fixed pegging edges utility is removed again.
Further steps can follow. When setting up a planning run such as this, it is
recommended that a step-by-step approach be taken so that the results of the
individual planning steps can be verified in the test phase.
488 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 501/522
TSCM40 Lesson: Production Planning with APO PP/DS
395 Exercise 22: Executing the Production
Planning Run (Optional)Exercise Duration: 20 Minutes
Exercise Objectives
After completing this exercise, you will be able to:
• Use the production planning run to plan products
• Display the planning file
Business Example
Production planning and detailed scheduling are executed for pump T-F2## and
assemblies T-B1##, T-B22##, T-B3##, and T-B4## in APO-PP/DS. Requirements
(planned independent requirements and customer requirements) already exist.
Use the production planning run to plan production of the pump and its assemblies
and components.
Task 1:
Before executing production planning, you acquire an overview of the current
master and transaction data situation.
1. Display the product view for pump T-F2## in plant 1000. Do requirementsexist? Which ones?
____________________________________________________
Are the requirements covered by procurement elements?
____________________________________________________
2. Switch to the product view for casing T-B1## in plant 1000 (a pump
assembly). First, view the product master for the casing from the product
view. How does planning of this product take place when changes are made
(PP/DS tab page)?
____________________________________________________
Switch to the MRP elements display. Do requirements exist? Which ones?
____________________________________________________
Are the requirements in the PP/DS horizon covered by procurement
elements? Why (not)?
____________________________________________________
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 489
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 502/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
3. To determine whether production planning is finite or infinite, check which
heuristic is used to plan product T-F2## in a production planning run: First
call the product master for material T-F2## in plant 1000. Is a productheuristic entered explicitly on the PP/DS tab page?
____________________________________________________
What implications does this have for planning the product in the production
planning run?
____________________________________________________
4. Which planning procedure is entered in the product master?
____________________________________________________
Take a look at planning procedure “4” in PP/DS Customizing. Which
heuristic has been entered here?
____________________________________________________
5. You have found the heuristic used to plan product T-F2## as part of
production planning. Take a look at the relevant heuristic in Customizing.
Which strategy is used to carry out planning in a planning run?
____________________________________________________
6. Finally, have a look at the SAP APO planning file. Display the planning
file entries in planning version 000 in location 1000 for the production
planner 0##. Choose Execute and the relevant planning file entries are
displayed.
Are planning file entries created for assemblies T-B1##, T-B22##, T-B3##,
and T-B4## in PP/DS?
_____________________________________________________
Which low-level code do these assemblies have?
_____________________________________________________
Has a planning file entry also been created for finished product T-F2##?
Why (not)?
_____________________________________________________Which low-level code does the finished product have?
_____________________________________________________
Continued on next page
490 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 503/522
TSCM40 Lesson: Production Planning with APO PP/DS
Task 2:
Execute production planning for the finished product and its assemblies.
1. Call the Production Planning Run from the production planning menu. Enter
the following data on the initial screen:
Planning version: 000
Time profile: SAP001
Propagation range: SAPALL
Processing steps:
01 Function/heuristic: SAP_MRP_001 (Components
according to low-level code)
Objects: 4 (products)
Selection criteria for the products:
Location: 1000
Production planner: 0##
Hint: Before you execute planning, save your settings as a variant
with the name PLANNER0## and the short description “Product
planner 0##”.
Once you have saved your settings as a variant, execute the production planning run.
Were products also planned in the planning run for which a planning file
entry was not set? Why (not)?
_____________________________________________________
2. Look at the planning results in the product view using assembly T-B1##
in plant 1000 as an example. Was the product planned? (Are procurement
elements available to cover the dependent requirements?)
_____________________________________________________
2008 © 2008 SAP AG. All rights reserved. 491
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 504/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Solution 22: Executing the Production
Planning Run (Optional)Task 1:
Before executing production planning, you acquire an overview of the current
master and transaction data situation.
1. Display the product view for pump T-F2## in plant 1000. Do requirements
exist? Which ones?
____________________________________________________
Are the requirements covered by procurement elements?
____________________________________________________
a) Requirements: Yes, there are planned independent requirements
and customer requirements.
b) Requirements covered?: Yes, the requirements are covered by
planned orders.
2. Switch to the product view for casing T-B1## in plant 1000 (a pump
assembly). First, view the product master for the casing from the product
view. How does planning of this product take place when changes are made
(PP/DS tab page)?
____________________________________________________Switch to the MRP elements display. Do requirements exist? Which ones?
____________________________________________________
Are the requirements in the PP/DS horizon covered by procurement
elements? Why (not)?
____________________________________________________
a) Planning the product when there are changes: Planning takes place in
the planning run.
b) Requirements: Yes, there are dependent requirements.
c) Requirements covered in the production horizon? No, the dependent
requirements are not covered because the product has not yet been
planned. (The product heuristic that was executed in a previous
exercise for the finished product is for single-level single-item
planning.)
Continued on next page
492 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 505/522
TSCM40 Lesson: Production Planning with APO PP/DS
3. To determine whether production planning is finite or infinite, check which
heuristic is used to plan product T-F2## in a production planning run: First
call the product master for material T-F2## in plant 1000. Is a productheuristic entered explicitly on the PP/DS tab page?
____________________________________________________
What implications does this have for planning the product in the production
planning run?
____________________________________________________
a) Product heuristic in T-F2##: No, a product heuristic has not been
entered on the PP/DS tab page.
b) Significance for production planning run: Normally, the heuristic
saved in the planning procedure is used.
4. Which planning procedure is entered in the product master?
____________________________________________________
Take a look at planning procedure “4” in PP/DS Customizing. Which
heuristic has been entered here?
____________________________________________________
a) Planning procedure in the product master: Procedure 4, “Planning
in planning run”, is defined in the product master on the PP/DS
tab page.
b) Relevant Customizing:
SCM Customizing menu path: Advanced Planning and Optimization
→ Supply Chain Planning → Production Planning and Detailed
Scheduling (PP/DS) → Maintain Planning Procedures
Defined heuristic: The SAP_PP_002 heuristic is intended for
“Planning in planning run”.
5. You have found the heuristic used to plan product T-F2## as part of
production planning. Take a look at the relevant heuristic in Customizing.
Which strategy is used to carry out planning in a planning run?
____________________________________________________
a) SCM Customizing menu path: Advanced Planning and Optimization
→ Supply Chain Planning → Production Planning and Detailed
Scheduling (PP/DS) → Heuristics → Maintain Heuristics
Strategy used for planning: Planning is carried out with the strategy
defined in the heuristic, and thus with the “Infinite scheduling”
planning mode.
Continued on next page
2008 © 2008 SAP AG. All rights reserved. 493
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 506/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
6. Finally, have a look at the SAP APO planning file. Display the planning
file entries in planning version 000 in location 1000 for the production
planner 0##. Choose Execute and the relevant planning file entries aredisplayed.
Are planning file entries created for assemblies T-B1##, T-B22##, T-B3##,
and T-B4## in PP/DS?
_____________________________________________________
Which low-level code do these assemblies have?
_____________________________________________________
Has a planning file entry also been created for finished product T-F2##?
Why (not)?
_____________________________________________________
Which low-level code does the finished product have?
_____________________________________________________
a) SCM system menu path: Advanced Planning and Optimization →
Production Planning → Reporting → Display Planning File Entries
Planning file entry created for assemblies?: Yes, the assemblies are
generally marked for “Delete non-fixed receipts, reexplode new
fixed receipts”.
b) Low-level code for the assemblies: The assemblies have low-level
code 1.
c) Planning file entry created for finished product? Varies. In general,
a planning file entry is not created for the individual customer
segment, and the make-to-stock segment is marked for change
planning (“Use suitable receipts”). However, if you have executed
planning of the whole product after entering the individual
customer order (that is, you have planned the individual customer
segment and the make-to-stock segment), a planning file entry is
not created for the finished product at all since complete planning
has already been executed.
d) Low-level code for the finished product: The finished product haslow-level code 0.
Task 2:
Execute production planning for the finished product and its assemblies.
1. Call the Production Planning Run from the production planning menu. Enter
the following data on the initial screen:
Continued on next page
494 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 507/522
TSCM40 Lesson: Production Planning with APO PP/DS
Planning version: 000
Time profile: SAP001
Propagation range: SAPALL
Processing steps:
01 Function/heuristic: SAP_MRP_001 (Components
according to low-level code)
Objects: 4 (products)
Selection criteria for the products:
Location: 1000
Production planner: 0##
Hint: Before you execute planning, save your settings as a variant
with the name PLANNER0## and the short description “Product
planner 0##”.
Once you have saved your settings as a variant, execute the production
planning run.
Were products also planned in the planning run for which a planning file
entry was not set? Why (not)?
_____________________________________________________
a) SCM menu path: Advanced Planning and Optimization → Production
Planning → Automated Production Planning and Optimization →
Production Planning Run
b) Products planned without planning file entry? Yes, all products were
planned because the “Planning file entry created” indicator had
not been selected.
2. Look at the planning results in the product view using assembly T-B1##
in plant 1000 as an example. Was the product planned? (Are procurement
elements available to cover the dependent requirements?)
_____________________________________________________
a) Product planned? Yes, the assembly was planned. Planned orders
exist for procurement.
2008 © 2008 SAP AG. All rights reserved. 495
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 508/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Lesson Summary
You should now be able to:• Name the planning procedure
• Describe and implement the multilevel planning run
496 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 509/522
TSCM40 Lesson: Selected Planning Tools in APO PP/DS
Lesson:
403
Selected Planning Tools in APO PP/DS
Lesson Duration: 90 Minutes
Lesson Overview
You can use pegging relationships to create connections between requirements
and requirement coverage elements and fix them, if necessary. Enhanced planning
resources such as the product planning table and detailed scheduling planning
board enable you to examine and process planning problems, particularly in the
area of detained scheduling (scheduling and capacity planning), from various
perspectives. You can use the optimizer to improve a machine commitment
situation.
Lesson Objectives
After completing this lesson, you will be able to:
• Interpret pegging
• Assess the cases for using the product planning table and the detailed
scheduling planning board
• Characterize the optimizer
Due to the volume of material covered by this course, there is usually little time
available for this unit. You should therefore see it as an opportunity to provide the
participants with an overview of the most important tools and their features. If sufficient time happens to be available, you can use content and demonstrations
from the customer course SCM250 (see this course for details). This will provide
enough material to fill in the time, if required. You should therefore deal with this
unit at a level of detail the occasion allows. Make sure, however, that you do not
confuse the participants at the end of the course by presenting them with lots of
complex details.
Business Example
Complex planning scenarios require enhanced resources. In the area of planning
overloads and scheduling delays in particular, resources such as pegging and theoptimizer, and tools such as planning tables are used.
Pegging Relationships
Orders that have a fixed pegging relationship can no longer be deleted from
material requirements planning. They are therefore also treated as being firmed.
2008 © 2008 SAP AG. All rights reserved. 497
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 510/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
In general, it is important to note that pegging and material requirements planning
are not directly dependent on one another. For example, if a planned order in
material requirements planning is created too late (using today scheduling) for arequirements date that is too early, there may be no pegging relationship between
the requirement and the receipt under certain circumstances. However, this type
of order is still created.
Pegging relationships can play an important role in capacity planning, for example,
if rescheduling is only permitted taking pegging relationships into account.
Hint: Processes in which fixed pegging can be used to control the material
flow are only provided as of SCM 4.1 (the fixing of the pegging is retained
in the subsequent document: transitions PlOr -> PrdOrd -> Stock).
Figure 174: Pegging Relationships
Pegging establishes a link between the receipt and issue elements of a product in a
location. The system uses pegging to assign receipts to relevant requirements.
The pegging strategy defines how requirements are covered when receipts areassigned. There are two strategies that can be entered in the product.
There are two different types of pegging relationships: fixed and dynamic. Fixed
pegging enables you to fix a pegging relationship, that is, the pegging relationship
will not be changed automatically by the system during planning. You can assign
a particular quantity of a product receipt (manually or with heuristics) to a specific
requirement. You can manually fix the pegging for a receipt/requirements element
by editing the pegging structure from the product view.
498 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 511/522
TSCM40 Lesson: Selected Planning Tools in APO PP/DS
Figure 175: Product Planning Table as a Further Tool
The product planning table is a powerful tool that can be used to execute and
evaluate planning in APO-PP/DS. A wide range of charts is available for display.
You can tailor the product planning table to suit different tasks, depending on
the charts you select.
The navigation tree at the top left of the screen displays the scope of the product
planning table. Using this navigation tree, you can define which objects aredisplayed in the individual views. You can group the navigation tree according to
different categories (planner, product group, location, or resource, for example).
On the lower left of the screen, you determine which charts (for example, periodic
product view, periodic resource view, Alert Monitor, quantity graphic) you want
to display. Capacity requirements planning can also be executed in the product
planning table using corresponding charts.
The demand and availability of resources is displayed in the periodic resource
view, where their utilization of capacity is shown as a percentage.
The periodic product view displays the products, the order quantities that have to
be produced in each bucket, and detailed information about dates and quantities
for the resources.
2008 © 2008 SAP AG. All rights reserved. 499
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 512/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Demonstration: Period-Based Planning in the ProductPlanning Table (Optional)
Purpose
Preparation for optional exercise
Hint: Use planning in repetitive manufacturing as an example of how the
product planning table is used (Note: The demonstration focuses heavily
on the following optional exercise):
System Data
System: see weekly e-mail
Client: see weekly e-mail
User ID: Your user ID
Password: Own password
Set up instructions: Standard
1. Structure and key characteristics of the product planning table
2. Prerequisites for the repetitive manufacturing example: Repetitive
manufacturing indicator and profile, production version, (MRP 4 view,
Material master)
3. Create forecast in ECC in the current week + 4: Mon: 600, Tues: 500, Wed:100, Thurs: 300, Fri: 500
4. Create sales order in current week + 5, Tuesday: OR, 1000, 10.00 ->
customer 1500, material T-F1320, plant 1200, quantity 10 pieces.
5. Product master T-F1320, plant 1200: Set PP/DS Horizon to 40 days
6. Call the Product planning table for T-F1320, planning version 000, plant
1200, activate the Alert Monitor -> Analyze the situation
7. Execute manual planning (interactive with reference to exception messages)
8. Execute Automatic planning with wave algorithm and interpret the result.
500 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 513/522
TSCM40 Lesson: Selected Planning Tools in APO PP/DS
Figure 176: Detailed Scheduling Planning Board
The schedule is displayed graphically in the planning board.
The planning board is used for interactive planning, for example, for interactive
processing and resolving alerts.
You can define the layout of the planning board, for example:
• The different charts (for example, a resource chart and an order chart)• The field selection and sorting for the columns in the table section of a chart
• The format of the rows in the table section
• The objects displayed in the diagram section of a chart, for example:
– Operations or orders (graphic objects)
– Histograms (curves for warehouse stock and resource utilization)
– Network views of operations and orders that show the time and pegging
relationships between operations and orders
• The layout of operations and orders in the diagram section
2008 © 2008 SAP AG. All rights reserved. 501
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 514/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Figure 177: PP/DS Optimizer
Optimization allows you to optimize the production dates/sequences and the
resource assignment of existing operations/activities that were previously
generated by the production planning run or manual planning. The optimizer
does not create or delete orders.
The purpose of optimization is to generate feasible production plans andincrease the efficiency of production. Several optimization parameters (such as
setup times, due date violations) can be weighted in such a way that the optimized
schedule comes as close to the desired results (for example, minimum setup times)
as possible. The following parameters can be taken into account in optimization:
• Production span (from the start of the first operation to the end of the last
operation in a resource schedule within the optimization horizon). The
production span makes a statement about the compactness of the orders
within the optimization horizon.
• Sum of setup times
• Sum of setup costs
• Maximum delay costs (maximum delay of an order in relation to its
requirement date or its due date).
• Sum of delay costs (delay in relation to requirements or due dates)
• Sum of mode costs through alternative modes.
502 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 515/522
TSCM40 Lesson: Selected Planning Tools in APO PP/DS
Facilitated Discussion
Ask the participants if they have any further questions regarding SCM APO. Then
emphasize the main advantages of SCM APO again with a brief summary. If the
participants would like to know more about the topic, refer them to the course
SCM250 and the Optimizer Workshop WDSCM2.
Finally, wish the participants good luck with the certification test.
Discussion Questions
Use the following questions to engage the participants in the discussion. Feel free
to use your own additional questions.
2008 © 2008 SAP AG. All rights reserved. 503
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 516/522
Unit 7: Overview of SAP APO-PP/DS TSCM40
Lesson Summary
You should now be able to:• Interpret pegging
• Assess the cases for using the product planning table and the detailed
scheduling planning board
• Characterize the optimizer
504 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 517/522
TSCM40 Unit Summary
Unit Summary
You should now be able to:
• Name the most important basic features of PP/DS planning
• Name and characterize the master data for PP/DS planning
• Manage and characterize requirements and their behavior in Demand
Management in APO
• Describe the CTP (Capable-to-Promise) scenario
• Name the planning procedure
• Describe and implement the multilevel planning run
• Interpret pegging
• Assess the cases for using the product planning table and the detailed
scheduling planning board• Characterize the optimizer
2008 © 2008 SAP AG. All rights reserved. 505
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 518/522
Unit Summary TSCM40
506 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 519/522
TSCM40 Test Your Knowledge
409Test Your Knowledge
1. The main features of PP/DS Planning are:
Choose the correct answer(s).
□ A Sales forecasts
□ B Cross-location, period-based planning
□ C Location-related material requirements planning
□ D Location-related capacity planning
2. In some requirements strategies there is the option of absorbing planned
independent requirements from sales orders for planning. What is this
situation called and which parameters control it?
2008 © 2008 SAP AG. All rights reserved. 507
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 520/522
Test Your Knowledge TSCM40
410Answers
1. The main features of PP/DS Planning are:
Answer: C, D
PP/DS is aimed at material requirements planning and capacity planning
within the production location.
2. In some requirements strategies there is the option of absorbing planned
independent requirements from sales orders for planning. What is this
situation called and which parameters control it?
Answer: It is called consumption. It is set for a specific material usingthe consumption mode and period(s). The assignment indicator must be in
the relevant check mode and the associated requirements strategy must be
the same and not “blank”.
508 © 2008 SAP AG. All rights reserved. 2008
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 521/522
TSCM40 Course Summary
Course Summary
You should now be able to:
• Evaluate, describe, and implement the options provided by SAP-based
planning
2008 © 2008 SAP AG. All rights reserved. 509
7/25/2019 TSCM40 - Planning & Manufacturing I
http://slidepdf.com/reader/full/tscm40-planning-manufacturing-i 522/522
Course Summary TSCM40