transmission project sponsors big tent meeting november 19, 2008 portland, oregon welcome

89
Order 2004 Sensitive 1 Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome Darrell Gerrard - PacifiCorp

Upload: kevlyn

Post on 12-Jan-2016

23 views

Category:

Documents


1 download

DESCRIPTION

Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome Darrell Gerrard - PacifiCorp. Big Tent Meeting November 19, 2008 Embassy Suites Hotel – Portland, Oregon 9:00 a.m. – 12:00 noon Agenda. 9:00Welcome – Darrell Gerrard - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Order 2004 Sensitive 1

Transmission Project Sponsors

Big Tent Meeting

November 19, 2008

Portland, Oregon

Welcome

Darrell Gerrard - PacifiCorp

Page 2: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

2

Big Tent MeetingNovember 19, 2008

Embassy Suites Hotel – Portland, Oregon9:00 a.m. – 12:00 noon

Agenda

9:00 Welcome – Darrell Gerrard

Background from July 2008 Session

Goals Supporting Coordination

9:15 TCWG Work Plan- What has been accomplished

since July 2008 – Ben Morris

9:30 Individual Project Updates (By Project Sponsor)

11:30 Next Steps – Darrell Gerrard

11:45 Inputs and Commentary – Sponsor Panel

Order 2004 Sensitive

Page 3: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

3

Goals Supporting Coordination

Develop ideas to ensure robust proposals brought to sub-regional & regional engagement

Avoid duplication of study work and facilities constructed

Ensure efficient use of resources, siting, permitting, environmental

Regional view of transmission requirements necessary long term

NW Transmission Hub concept formulated

Optimize current expansion plans from commercial as well as technical views

Open and transparent FERC Order 890 compliant planning

Improved certainty of project Phase 2 ratings expected via WECC process

Order 2004 Sensitive

Page 4: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

4

Background

Purpose: status update for several proposed projects significant to Northwest

All projects currently in or will be in WECC Phase 1 Rating Process

Began January 2008 with Transmission Coordinated Work Group (TCWG)

Goal is submission of Phase 1 reports in Q4

Sponsors are reasonably on schedule

Each project sponsor will be submitting an individual Project Phase 1 Rating report to WECC

Expectations are that projects enter Phase 2 relatively close together in the fourth quarter of 2008 or Q1 2009

Order 2004 Sensitive

Page 5: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Order 2004 Sensitive 5

WECC Phase 1 and Phase 2 Coordination

Ben Morris - PG&E Consultant

Page 6: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

6

Coordination A number of project sponsors are planning construction in the Northwest

in the 2010-2015 period and the study work is being coordinated. Their projects have the following characteristics: Currently in (or soon to be in) WECC Phase 1 Rating process Planning to submit their Comprehensive Progress Reports in 4Q, 2008 and

1Q, 2009 Agree to use a common study methodology

Projects that meet such characteristics include: Walla Walla-McNary (PacifiCorp) Hemingway-Captain Jack (PacifiCorp) West of McNary Project (BPA) I-5 Corridor Reinforcement BPA) Idaho-Northwest Project (Idaho Power and Others) Southern Crossing Project (PGE) Canada-Northwest-California (CNC) Project (PG&E and Others) CNC Project - Devil’s Gap Interconnection (Avista) Dry Creek-Coyote (Avista) Northern Lights Project (TransCanada) West Coast Cable (Sea Breeze)

The project sponsors have formed the Transmission Coordination Work Group (TCWG).

Order 2004 Sensitive

Page 7: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

New Transmission Projects Being Planned in Coordination Planned Operation: 2010 – 2015

Legend:

PG&E (AC or DC)

PacifiCorp (500 or 230kV)

PGE (500kV)

Idaho Power (500kV)

Avista Corp (230kV)

BPA (500 kV)

NorthernLights (DC)

Sea Breeze WCC (DC)

To SF Bay Area

Selkirk Sub

Spokane Area Sub and

Converter

Idaho PowerHemingway Boardman

PacifiCorpHemingway Capt.

Jack

PG&E, et. al CNC Project

PGESouthern Crossing

PG&E et. al CNC Project

BPA West of McNary Generation

Integration Project

Midpoint

Capt. Jack

Hemingway

Borah

PacifiCorp/IdahoGateway West

PacifiCorpWalla Walla

McNary

Big Eddy

BPA I-5 Corridor

Station X

To Edmonton/Heartland

Station Z

NorthernLights DC

NEO Station

Sea BreezeWCC

To SF Bay Area

Order 2004 Sensitive

7

Page 8: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

8

Transmission Projects in Regional Planning and/or Phase 1Planned Operation: 2010 – 2015

Sponsor/ Participants

Project Name Online Date Voltage Capacity WECC Milestones *

PacifiCorp Walla Walla to McNary 2010 Single 230kV AC 400 MW RP Initiated – 11/2007Ph 1 Initiated -- 10/2008

PacifiCorp Hemingway to Capt. Jack (part of Gateway West)

2014 Single 500kV AC 1,500 MW RP Initiated – 11/2007

BPA West of McNary Generation Integration Project

2012- 2013

Single 500kV AC and 500kV Sub/ Single 500kV AC

1,500 MW each

RP Completed – 02/2008Ph 1 Pending

BPA I-5 Corridor Reinforcement Project

2015 500kV Sub/Single 500kV AC

1,500 MW RP Completed – 03/2008Ph 1 Pending

Idaho Power and Others

Hemingway-Boardman 2013 Single 500kV AC 1,300 MW RP Completed – 05/2008Ph 1 Initiated – 02/2008

PGE Southern Crossing 2013- 2014

Single 500kV AC 1,500 MW RP submitted -- 10/2008 Ph 1 submitted – 10/2008

PG&E and Others Canada – Northwest - California (CNC)

2015 Double 500kV AC and HV DC

3,000 MW RP Completed – 11/2008Ph 1 Initiated – 10/2007

Avista Corp Avista Interconnection to CNC - Spokane Area Upgrades

2015 500kV Sub and local 230kV upgrades

500 MW RP Submitted – 11/2007Ph 1 Initiated – 11/2007

Avista Corp Dry Creek -Coyote 230 kV 2015 230 kV 500 MW RP and Ph 1 Initiated in 01/08

TransCanada NorthernLights 2015 +/- 500 kV DC 2,000 MW RP Completed – 01/2008Ph 1 Initiated – 01/2008

Sea Breeze West Coast Cable (WCC) 2015 +/- 600 kV DC 1,600 MW Ph 1 - Initiated –    12/2006

* RP = WECC Regional Planning Process Ph 1 = WECC Rating Process: Phase 1

Order 2004 Sensitive

Page 9: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

9

Transmission Coordination Work Group (TCWG) Group formed to

Establish consistent assumptions/methods for Project Sponsors Provide feedback on the Project Sponsor study work Explore opportunities for synergies among projects

Activities Develop consistent assumptions, study scenarios, base cases

Identify and establish consistent assumptions for the analysis of Hubs Review and comment on Project Sponsor study plans, assumptions,

study results and Comprehensive Progress Report Monthly meetings through study completion

Met monthly since January 2008 (next meeting: December 9 conference call)

Participation – Approximately 30 meeting attendees and more than 80 on the correspondence list Representatives from Phase 1 projects Other stakeholders with interest in providing feedback on technical

studies Other parties interested in the development of the projects

Order 2004 Sensitive

Page 10: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

System Parameters

2015 HS Regional Gen/Loads

Projects coordinated within the TCWG are designed to access resources in BC, Alberta, Montana, the PNW and Northeastern CA/NV

10

Region Gen (MW)

Demand(MW)

Alberta 9433 9535

BC 11576 8341

PNW 31818 26305

Idaho 4904 3771

Montana 3252 1843

No. Ca 25479 28521

+4500 MW

+1500 MW

+3000 MW

+3000 MW

+2000 MW

Order 2004 Sensitive

Page 11: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

11

Project Sponsor/TCWG Phase 1 Accomplishments Developed Study Plan

Developed Study Assumptions Identified the location and capacity of new incremental generation to

be accessed with the proposed projects Listed major paths to be monitored and their target flows Identified the projects in the WECC Phase II Rating process to be

modeled in the cases Established set of critical contingencies to be studied

Developed Base Cases: Seasonal cases:

2015 Heavy Summer (North-South Flow) 2017 Heavy Winter (South-North Flow) 2011 Light Spring (East-West Flow) 2010 Light Autumn (East-West Flow)

Reviewed and adjusted Load and Generation balance as necessary

Order 2004 Sensitive

Page 12: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

12

Project Sponsor/TCWG Phase 1 Accomplishments (cont’d)

Conducted Studies without and with Project Power flow Transient Stability Voltage Stability

A number of transmission projects converge in northeast Oregon Evaluated the technical merits of substation where these projects

could potentially terminate New Substation – NEO Station

Preliminary NEO Station arrangements have been developed and will evolve during WECC Phase 2

Communicated Study Progress and Results Each of the Projects has presented the results of their non-

simultaneous rating study work at the TCWG Meeting Participated in joint Big Tent meetings

Order 2004 Sensitive

Page 13: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

TCWG Phase 2 Coordination

Project Sponsors have agreed that TCWG will function as the Phase 2 Project Review Group No need to have separate review teams for individual projects Separate Phase 2 meetings can be held at the Project Sponsors’

discretion

Entities who are not part of the TCWG and have interest in any of the TCWG projects should contact the Project Sponsor to become part of TCWG

Coordination Activities Consistent assumptions Discuss study results involving system interactions

13

Order 2004 Sensitive

Page 14: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

TCWG Phase 2 Coordination

Meetings Regular monthly meetings

January 21 February 18

TCWG is envisioned to function until the last project completes Phase 2

14

Order 2004 Sensitive

Page 15: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Walla Walla – Mc Nary

Tom Tjoelker - PacifiCorp

Page 16: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Project Overview

Conceptual Major Project Elements Walla Walla – Wallula 230 kV Line Wallula – Mc Nary 230 kV Line

Potential Bidirectional rating: 400 MW East-to-West 400 MW West-to-East

Project Operating Date: Late 2010

Project Website:

www.pacificpower.net/energygateway. 

MAP

16

Order 2004 Sensitive

Page 17: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Objectives

Provides up to 400 MW of new transmission capacity both East-to-West and West-to-East

Improves transmission reliability to Wallula area

Provides transmission capacity for new wind resources in Walla Walla area

Facilitates future interconnection of other regional transmission projects such as proposed by Avista

17

Order 2004 Sensitive

Page 18: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Conceptual One-Line

18

Order 2004 Sensitive

Page 19: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

WECC PHASE Rating Process

Complete Phase I Proposed Rating Report – Feb. 2009

Initiate Phase II Planned Rating - Apr. 2009

Complete Phase II Planned Rating – June 2009

19

Order 2004 Sensitive

Page 20: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Project Update (since July, 2008)

Regional Planning Report issued October 6, 2008

Phase I WECC Rating Process initiated October 9, 2008

Single-circuit performs well

Working with Avista & BPA on potential regional transmission projects

Double-circuit may be built as part of joint project with Avista

RAS needed for higher wind penetrations

20

Order 2004 Sensitive

Page 21: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Project implementation Schedule

WECC rating studies 2008 - 2009

Permitting and Land acquisition 2008 - 2009

Engineering 2008 - 2009

Construction Late 2009

Operations Late 2010

21

Order 2004 Sensitive

Page 22: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Hemingway – Capt. Jack

Tom Tjoelker - PacifiCorp

Page 23: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Project Overview

Conceptual Major Project Elements Hemingway – Capt. Jack 500 kV

Line

Potential Bidirectional rating: 1500 MW East-to-West 1500 MW West-to-East

Project Operating Date: 2014

Project Website:

www.pacificpower.net/energygateway. 

MAP

23

Order 2004 Sensitive

Page 24: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

CONCEPTUAL ONE-LINE

HEMINGWAY – CAPT JACK

24

Order 2004 Sensitive

Page 25: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Objectives

Support West side load growth

Address renewable portfolio standards

Potentially facilitates future interconnection of other regional transmission projects

25

Order 2004 Sensitive

Page 26: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Project implementation Schedule

WECC rating studies 2009

Permitting and Land acquisition 2010 - 2011

Engineering 2010 - 2011

Construction Late 2013

Operations Late 2014

26

Order 2004 Sensitive

Page 27: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

27

West of McNary Generation Integration Project

(WOMGIP)

Kyle Kohne - BPA

Page 28: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

28

Project Overview

Major Elements

Part 1: Construct a new McNary – John Day 500 kV transmission line (~79 mi)

Part 2: Construct a new 500 kV substation (“Station Z”) near Goldendale, WA, and a 500 kV line from Station Z to BPA’s Big Eddy substation near The Dalles, OR. (~30 mi)

Planned Rating:

West of McNary: 4500MW

West of Slatt: 5500MW

West of John Day: 3450MW

Proposed Project Operating Date

Part 1: 2012

Part 2: 2013

Project Website:

http://www.columbiagrid.org/WMRP-overview.cfm

Order 2004 Sensitive

Page 29: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

29

Objectives

Enable BPA to meet Network customer load growth from new resources and serve point-to-point transmission requests across multiple congested east-west transmission paths along the Washington – Oregon border.

Enable BPA to interconnect additional wind generation in Eastern Washington and Eastern Oregon.

Increase system reliability to serve Portland area load.

Order 2004 Sensitive

Page 30: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

30

Project Update (since July 2008)

Regional Planning Completed (February 2008)

BPA plans to initiate the WECC Phase One Rating Process in January 2009.

Funds approved to begin preliminary design and NEPA work.

Public Involvement effort reinitiated for Part 1 (McNary – John Day).

Both parts of the project will be included in BPA’s Network Open Season (NOS) process.

Order 2004 Sensitive

Page 31: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

3131

Project Implementation Schedule

McNary-John Day 500-kV

Project will take approximately 3.5 years from start to energization

Environmental Process / Design – 0.5 years

Material Procurement / Construction – Additional 3 years

Big Eddy-Station Z 500-kV (includes Station Z)

Project will take approximately 5 years from start to energization

Environmental Process / Design – 2 years

Material Procurement / Construction – Additional 3 years

Order 2004 Sensitive

Page 32: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

32

I-5 Corridor Reinforcement

Kyle Kohne - BPA

Page 33: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

33

Project Overview Major Project Elements

Construct a new 500 kV Substation near Castle Rock, WA.

Develop a 500 kV yard at the existing Troutdale Substation in Troutdale, OR.

Construct a new 500 kV transmission line between these substations (approximately 70 miles).

Alternative: Construct new 500 kV line between new Castle Rock substation and Pearl substation instead

Planned Rating

South of Allston: Approximately 1300 MW increase

Proposed Operating Date

2015

Project Website:

http://www.columbiagrid.org/I5CRP-overview.cfm

Order 2004 Sensitive

Page 34: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

34

Objectives

Relieve congestion along the I-5 corridor transmission path south of Paul Substation.

Enable BPA to meet Network customer load growth from new resources and serve point-to-point transmission service requests which impact this path.

Enable BPA to interconnect additional new resources which are being planned along the I-5 Corridor.

Maintain reliable service to growing loads in Portland and vicinity.

Reduce dependence on existing RAS while maintaining transmission system reliability.

Order 2004 Sensitive

Page 35: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

35

Project Update (since July 2008)

Regional Planning Completed (March 2008)

BPA plans to initiate the WECC Phase One Rating Process in February 2009.

Funds approved to begin preliminary design and NEPA work.

This project will be included in BPA’s Network Open Season (NOS) process.

Order 2004 Sensitive

Page 36: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

3636

Project Implementation Schedule

I-5 Corridor Reinforcement Project

Project will take approximately 6 years from start to energization for either alternative

Environmental Process / Design – 3 years

Material Procurement / Construction – Additional 3 years

Order 2004 Sensitive

Page 37: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

3737

BPA Network Open Season Update

Cluster Study results submitted to BPA Marketing on 10/31/08

153 PTSA’s submitted totaling 6,410 MW of transmission requests

WOMGIP and I-5 Corridor Reinforcement are part of the portfolio of projects for meeting the requests

BPA will host Customer Forum on 11/20/08 to present cluster study results (http://www.transmission.bpa.gov/customer_forums/)

Commercial Infrastructure Analysis to be completed by 12/31/08

Agency embedded rate determination on portfolio of projects no later than 2/16/09

Order 2004 Sensitive

Page 38: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

38

Hemingway to Boardman

Dave Angell - Idaho Power

Page 39: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

39

Project Overview

Project Elements

Single 500 kV AC circuit from Hemingway, Idaho to Boardman, Oregon

Reactive compensation at Sand Hollow station

Bidirectional rating:

1300 MW West to East

800/1400 MW East to West

Project Operating Date: Summer 2013

Project Websites:

http://www.idahopower.com/newsroom/projnews/hemingway_boardman/default.htm

http://www.boardmantohemingway.com/

Order 2004 Sensitive

Page 40: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

40

Objectives Meet transmission requirements of Idaho Power

Integrated Resource Plans (IRP)

225 MW of northwest resource import Relieve congested transmission path

Satisfy OATI obligation for transmission service requests

Connect resource centers to load centers (hub and spoke concept)

Transmission to forecasted load growth areas

Transmission to forecasted resources areas

Order 2004 Sensitive

Page 41: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

4141

Plan of Service

54 mile 500 kV line from Hemingway to Sand Hollow reactive station.

Sand Hollow – series capacitor size for 50% compensation of line reactance

254 mile 500 kV line from Sand Hollow to Boardman Power Plant

Boardman Power Plant – shunt capacitor bank

Order 2004 Sensitive

Page 42: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

42

Project Update (since July, 2008) Permitting

Oregon Energy Facility Siting Council Notice of Intent 8/27/2008 BLM Notice of Intent (NEPA process) 9/11/2008

Comprehensive Progress Report West to East

Hemingway – Boardman 1300 MW Idaho to Northwest Path 758 MW

East to West independent of other northwest projects Hemingway – Boardman 838 MW Idaho to Northwest Path 1766 MW

East to West with Gateway West, WOMGIP, Southern Crossing Hemingway – Boardman 1400 MW Idaho to Northwest Path 2417 MW

Order 2004 Sensitive

Page 43: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

4343

Project Implementation Schedule

WECC Regional Planning 7/2007 – 5/2008

WECC Phase 1 Rating 2/2008 – 12/2008

WECC Phase 2 Rating 1/2009 – 12/2009

Permitting and Land acquisition 1/2008 – 2011

Engineering 1/2008 – 2011

Construction 2011 – 5/2013

Operation 5/2013

Order 2004 Sensitive

Page 44: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Southern Crossing

Philip Augustin - Portland General Electric

Page 45: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Project Overview

Conceptual Major Project Elements 500kV transmission line (215 miles) 500/230 kV substations

Potential rating: 1500 MW (East to West )winter 1400 MW (East to West )summer

Project Operating Date: 2013 2013-2014 if staged

Project Website: http://www.oatioasis.com/pge/index.html http://www.nwpp.org/tcwg/

Order 2004 Sensitive

Page 46: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Objectives

The Project was initiated in response to Generation Interconnection Requests for network service.

The Project will increase transmission capacity to PGE’s service territory by increasing the East to West transfer capability of the PNW grid

The Project is designed to integrate existing PGE generation resources (i.e., Boardman and Coyote Springs) and up to 800 MW of additional renewable and other resources.

46

Order 2004 Sensitive

Page 47: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

O lallieProposed W ind

Bethel

Boardm an

M cNary

Coyote Springs

Coyote PG E Coyote Av ista

Slatt

Pelton / Round Butte

PORT L A N D GE N E RA L E L E C T RIC C O. SOU T H E RN C ROSSIN G

ON E L IN E D IA GRA M

500 kV230 kV

Conceptual Plan of Service: HVAC facilities from Boardman to

Coyote Springs HVAC facilities from Boardman to

Olallie HVAC facilities for Bethel to Olallie Series compensation between

Boardman to Olallie, and between Bethel to Olallie

47

Order 2004 Sensitive

Page 48: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Project Update (since July, 2008) Submitted Regional Planning Project Report to WECC Planning

Coordination Committee and Technical Studies Subcommittee on October 30th for 30 day review.

Studies demonstrate the Project’s effectiveness during heavy load conditions occurring either in the winter or late spring / early summer. The east – west proposed rating was determined using a WECC 2017

Heavy Winter case, and a WECC 2015 Heavy Summer case. Generation in the Northwest was dispatched to achieve 1,500 MW of flow on Southern Crossing in the winter and 1,400 MW in the summer meeting WECC Reliability Criteria.

Presented preliminary WECC Phase 1 study results to TCWG

Begun critical issues analysis work for proposed ROW

Signed a Memorandum of understanding with Idaho Power Co.

48

Order 2004 Sensitive

Page 49: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

NELWAY

SUM M ERLAKE

ALVEY

ALLSTON

KEELER

PEARL

JOHN DAY(2563 M W)

M ARION

LANE

GRIZ Z LY

BUCKLEY

THEDALLES

OSTRANDERSLATT

M cNARY(1169 M W)

BOARDM AN BOARDM AN(420 M W) (540 M W)

PAUL /CENTRALIA(1370 M W)

RAVER

M ONROE

CUSTER

ECHOLAKE

CHIEFJOE

(2447 M W)GRAND COULEE

(6850 M W)

SCHULTZ

HANFORD

ASHE(1200 M W)

VANTAGE

LOWM ON

(932M W)

LITGOOSE

(932 M W)

LOWGRANITE(932 M W)

DWORSHAK(476 M W)

BELL

DIXONVILLE

CABGORGE

(230 M W)

LOLO

HELLSCANYON(450 M W)

ROUNDUP

OXBOW(220 M W)

BROWNLEE(730 M W)

ENTERPRISE

WALLAWALLA

LAGRANDE

HATWAI

M OSCOW

BENEWAH

ROSS

ONTARIO

CALDWELLBURNS

WANETA

BOUNDARY(944 M W)

NO RT H O FHAN FO RD

IDAH O T ONO RT HW EST

W EST O F CASCADES - NO RT H

SO UT H O F RAVER

OLYM PIA

W EST O F CASCADES -SO UT H

BC - NW (W EST )

ROCKYREACH

(1240 M W)

M IDWAY

W EST O FHAT W AI

W A

OR

PDCI

SO UT H O FALLST O N

BEAVER(534 M W)

N. O F JO H N DAY (500K VO NLY)

SO UT H O F BO T H ELL

W EST O F M CN ARY

W EST O F NO XO N

BC - NW (EAST )

SO UT H O F G RIZZLY

L E G E N D:

500KV

DC

345KV

230KV

115-161KV

Upper ColumbiaGeneration

- -

Mid Columbia Generation+ +

Lower Columbia Generation+ +

I-5 cooridorGeneration

- -

Generation Dispatch Studied

49

Order 2004 Sensitive

Page 50: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Phase 1 Study Load Assumptions

Heavy Winter 2017

Name AGC Status / Area Slack Gen MW Max Gen MW Load MW

PGE   2,603 3,673 4,284

TOTAL NORTHWEST Slack output: 614 MW 30,685 48,144 33,258

Heavy Summer 2015

Name AGC Status/ Area Slack Gen MW Max Gen MW Load MW

PGE   2,451 3,673 4,330

TOTALNORTHWEST Slack output: 527 MW 32,995 48,182 30,021

50

Order 2004 Sensitive

Page 51: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Phase 1: Preliminary Impacts existing paths observed

  Winter all lines in service Summer all lines in service

Path Name and Number Pre-Project Post-Project Pre-Project Post-Project

West of Cascades South (E-W) 7814 6870 6902 5972

Pacific DC Intertie (N-S) -963 -963 2167 2167

California Oregon Intertie (N-S) -1474 -1119 3368 3329

South of Allston (N-S) -1118 -1237 1296 1149

North of John Day (N-S) -1300 -1261 6446 6528

West of Slatt (E-W) 1547 844 4185 3313

West of McNary (E-W) 1475 1159 2459 2158

51

Order 2004 Sensitive

Page 52: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Project implementation Schedule

Task Name

2008

2009 2010Finish

Start

WECC Phase 1 & Regional Review• Comprehensive Progress Report (CPR) -Identify the non-simultaneous and known interactions of the project• CPR reviewed by PCC & TSS membership• Informal reports are presented at TSS meetings• Letter to TSS and PCC requesting Phase 2 Status

WECC Phase 2 • Identify the simultaneous transfer capability for project• Address mitigations for any adverse impacts to existing system

Duration

12 monthsQ12008

Q42008

24 monthsQ12009

Q42010

Q1 Q2 Q3 Q4

Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4

52

Order 2004 Sensitive

Page 53: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Project implementation Schedule WECC Phase Rating Process

Phase 1 Comprehensive Progress Report December 2008 Phase 2 Rating Report Fourth Quarter 2010

Q1 Q2 Q3 Q4

WECC Phase 3

•Definitive commercial agreements•Preliminary Engineering•EFSC permitting process•Land Acquisition• Engineering• Procurement • Construction • Release To Operation

Task Name

2009 20142010 2011 2012 2013

FinishStartDuration

54 to 72months

Q12009

Q22013

or

2013 –Q22014

Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Q1 Q2 Q3 Q4

53

Order 2004 Sensitive

Page 54: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

54

Canada / Pacific Northwest to Northern California

Transmission Project

Stakeholder Meeting, Portland, November 19, 2008

Steve Metague - PG&E

Page 55: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

55

Project Overview

Project steering team: Avista Corp, BCTC, PacifiCorp, PG&E

Potential Bidirectional rating:

3000 MW North to South

South to North rating to be determined

Project Operating Date: late 2015

Project Website: http://www.pge.com/canada/

Today’s presentation:

Project Plan of Service.

Summary of WECC Phase 1 N-S rating results.

Schedule for S-N WECC Phase 1 and WECC Phase 2 rating.

Overall Project Schedule.

Legend:

PG&E (AC or DC)

PacifiCorp (500 or 230kV)

PGE (500kV)

Idaho Power (500kV)

Avista Corp (230kV)

BPA (500 kV)

NorthernLights (DC)

Sea Breeze WCC (DC)To SF Bay Area

Selkirk Sub

Idaho PowerHemingway Boardman

PacifiCorpHemingway Capt.

Jack

PG&E, et. al CNC Project

PGESouthern Crossing

PG&E et. al CNC Project

BPA West of McNary Generation

Integration Project

Midpoint

Capt. Jack

Hemingway

Borah

PacifiCorp/IdahoGateway West

PacifiCorpWalla Walla

McNary

Big Eddy

BPA I-5 Corridor

Station X

To Edmonton/Heartland

Station Z

NorthernLights DC

NEO Station

Sea BreezeWCC

To SF Bay Area

Cottonwood

Devil’s Gap

Order 2004 Sensitive

Page 56: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

56

Project Objectives

Enhance access to significant incremental renewable resources in Canada and the Pacific Northwest.

Improve regional transmission reliability.

Provide market participants with beneficial opportunities to use the facilities.

Use WECC’s open stakeholder planning process.

Order 2004 Sensitive

Page 57: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

5757

Plan of Service Initial Plan of Service:

HVAC facilities from Selkirk-Devil’s Gap-NEO Station

HVDC facilities from NEO Station to Collinsville with possible third terminal at Cottonwood

HVAC facilities from Collinsville to Tracy Voltage support at the interconnecting

substations Remedial Actions – tripping of generation

scheduled on the project for outages of the project facilities

Project is dependent on other projects to be installed in the 2010-2015 period. Such projects: accommodate CNC Project Sponsors’ use

of CNC, or increase AC system strength to support AC

to DC conversion at the terminal stations

Order 2004 Sensitive

Page 58: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

58

WECC Phase 1 Rating Process Update

Regional Planning Report completed and submitted – November 2007.

WECC Phase 1 has been coordinated with the Transmission Coordination Work Group (TCWG).

Three generation scenarios were developed to support delivery of 3000 MW of renewable resources in British Columbia, the Pacific Northwest, or Northern California/Nevada:

3000 MW of renewable generation from BC CNC project loaded to 3000 MW south of Selkirk

1500 MW of renewable generation from both BC and the Pacific Northwest CNC project loaded to 3000 MW south of the NEO Station

1500 MW of renewable generation from both BC and Northern California/Nevada CNC project loaded to 3000 MW south of the Cottonwood Area Substation.

2015 Heavy Summer base case has been used modeling the system with and without the CNC Project.

The WECC Phase I rating studies conducted to establish a north-to-south rating show: The initial Plan of Service is viable. Rating for the project segments is 3000 MW, N-S. Other proposed projects at Neo Station needed to support the HVDC terminal. Other proposed projects at Cottonwood needed to support the potential HVDC terminal. Generation tripping of power scheduled on CNC (up to 3000 MW) is required for CNC

facility outages.

Order 2004 Sensitive

Page 59: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

59

WECC Rating Process Next Steps Phase 1 Comprehensive Progress Report (CPR)

Project Sponsors to e-mail the draft to Stakeholders for comment by12/1/2008.

Stakeholders include TCWG members and Big Tent attendees who request a draft copy.

Stakeholder comments requested by 12/10/2008. Final CPR and request to move to Phase 2 will be submitted to WECC by

12/16/2008.

Project sponsors are scheduled to initiate the WECC Phase 1 rating process to establish a south-to-north rating in January 2009 Studies will be coordinated through the TCWG.

Project sponsors expect to initiate the WECC Phase 2 rating process 60-days after submitting the Phase 1 CPR to WECC (mid-February).

Entities wanting to participate in the WECC Phase 1 (S-N) or Phase 2 (N-S) process should join the TCWG through the Northwest Power Pool website: http://www.nwpp.org/tcwg/ Please copy Ben Morris at [email protected]

Order 2004 Sensitive

Page 60: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

WECC Rating Process Activities Previous activities

Initiated Regional Planning 12/16/2006. Submitted Regional Planning Report 11/1/2007. Completed load and resources, technical feasibility and economic screening

analysis. Reports posted on project website 11/1/2007. Initiated Phase 1 Rating Process 10/31/2007. WECC Phase 1 Rating Process Stakeholder Meetings

January 24, 2008 July 18, 2008 Today

TCWG monthly meetings.

Planned activities WECC Phase 1 Draft Comprehensive Progress Report (CPR) out for comment –

12/1/2008. Stakeholder comments requested by 12/10/2008. Final CPR and request to move to Phase 2 to be submitted to WECC by

12/16/2008. Initiate the WECC Phase 1 rating process to establish a south-to-north rating in

January 2009. Initiate the WECC Phase 2 rating process – 2/2009. Complete WECC Phase 2 rating process – Q3/2010.

60

Order 2004 Sensitive

Page 61: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

6161

Task NameQ1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Basic Elements of Conceptual Project Schedule2014 20152010 2011 2012 2013

Note: This conceptual project schedule was prepared based on preliminary information without the benefit of route screening, preliminary engineering or other tasks necessary to finalize a detailed schedule. The timeframes set forth herein may change as the result of pre-application studies.

PROCUREMENT OF MATERIALS

RELEASE TO OPERATION

2007 2008 2009

PROJECT LAND ACQUISITION

CONSTRUCTION

2006

FEASIBILITY ANALYSIS

PROJECT PERMITTING

PROJECT DESIGN

Order 2004 Sensitive

Page 62: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Avista Corporation 500/230 kV Interconnectionwith the Proposed

Canada / Pacific Northwest to Northern California Transmission Project

Scott A. Waples - Avista Corporation

Page 63: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

63

Project Overview

Major Project Elements: 500/230 kV interconnection at

Devil’s Gap 230 kV Phase Shifting

Transformers 2-230 kV interconnections to the

Spokane Area 230 kV Grid

Potential Bidirectional rating: 500 MW

Project Operating Date: 2015

Project Website: NWPP.org/tcwg/

Devil’s Gap500-230-115 kV

PG&E-CAN500 kV Line

Beacon230-115 kV

Sunset230-115 kV

Major HighwaysExisting 230 kVProposed 230 kVExisting 115 kV

Westside230-115 kV

Order 2004 Sensitive

Page 64: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

64

Objectives and Resources

The Avista interconnection to the PG&E Canada to Northern California 500 kV Project will provide up to 500 MW of access from the “Main Stem” Project to the Avista transmission system, providing access to renewable resources in the Northwest and Canada.

The interconnection will also provide access to the “Main Stem” 500 kV Project for resources, including renewables, located within the Avista service territory.

The project may also allow Avista to integrate some of its existing thermal resources to its loads over its own transmission, and may allow for additional imports of economy energy into the Avista system.

Potential wind resources that may require export capacity from various locations on the Avista system include, but are not limited to, wind farms near Spokane, Othello and Clarkston, Washington, as well as Grangeville and Lewiston, Idaho. Avista presently has 10 pending interconnections.

Order 2004 Sensitive

Page 65: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Project Update (since July, 2008)

Avista has completed the technical study work to support the WECC Regional Planning / WECC Phase I Rating submittal as projected in July. The studies indicate that the interconnection is feasible and that there are no adverse impacts to neighboring systems from this interconnection.

Avista anticipated a joint Regional Planning / Phase I submittal for the study work, and a first draft of this report was provided to the TCWG at its October 23, 2008 meeting in Portland, Oregon. TCWG recommended that the draft report be split into two submittals. Avista has incorporated comments received at the TCWG meeting into the Regional Planning Report and has submitted that report to WECC. Comments on the report are due December 12, 2008. The Phase I report should be submitted to WECC within the next six weeks.

Avista is also working with other PG&E Project Teams (Permitting and Public Affairs) for the PG&E Canada to California project.

65

Order 2004 Sensitive

Page 66: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Project implementation Schedule

WECC Regional Planning December, 2008

WECC Phase I Rating studies December, 2008

WECC Phase II Rating studies 2009

Permitting and Land acquisition 2013-2014

Engineering 2013-2014

Construction 2014-2015

Operations 2015

66

Order 2004 Sensitive

Page 67: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Avista Corporation 230 kV Dry Creek – (Walla Walla – NEO ) –

Coyote Springs Transmission Project

Scott A. Waples - Avista Corporation

Page 68: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

68

Project Overview Major Project Elements:

Dry Creek (Walla Walla – NEO) Coyote Springs 230 kV Line

Potential Bidirectional rating: 500 MW

Project Operating Date: 2015

Project Website: NWPP.org/tcwg/

Major Highways

Proposed 230 kV

Boardman/CS II

Dry Creek

Walla Walla

WA

OR

Order 2004 Sensitive

Page 69: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

69

Objectives and Resources

The interconnection will allow Avista access to other renewable resources in the Northwest as well as in Canada.

The project may also allow Avista to integrate some of its existing thermal resources to its loads over its own transmission, and may allow for additional imports of economy energy into the Avista system.

Potential wind resources that may require export capacity from various locations on the Avista system include, but are not limited to, wind farms near Spokane, Othello and Clarkston, Washington, as well as Grangeville and Lewiston, Idaho. Avista presently has 10 pending interconnections.

Order 2004 Sensitive

Page 70: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Project Update (since July, 2008)

Avista has begun the technical study work to support the WECC Regional Planning and WECC Phase I Rating submittals. The studies that have been completed indicate that the interconnection is feasible and that there are no adverse impacts to neighboring systems from this interconnection. The project may require phase shifting transformers as well as series compensation. The project may, at a future date, also interconnect at the NEO Station.

Avista has formally approached PacifiCorp to see if this project and the PacifiCorp Walla Walla – McNary (NEO) project might be able to utilize a common right-of-way or common transmission structures, and the two companies are now engaged in such discussions.

Avista will be hosting a kickoff meeting for the WECC Regional Planning and Phase I Study efforts for this project in the near future. Please stay tuned!

70

Order 2004 Sensitive

Page 71: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Project implementation Schedule

WECC Regional Planning January, 2009

WECC Phase I Rating studies January, 2009

WECC Phase II Rating studies 2009

Permitting and Land acquisition 2013-2014

Engineering 2013-2014

Construction 2014-2015

Operations 2015

71

Order 2004 Sensitive

Page 72: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

NorthernLights

Connecting Alberta and the Pacific Northwest

Russ Hantho – Bill Hosie

TransCanada Corporation

Page 73: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

NorthernLights Overview

Project web site: http://www.transcanada.com/company/northernlights.html

Buckley

Edmonton

NorthernLights

AC or DC Connectors

Converter

Calgary

Spokane

BC ABSK

WA

MTID

OR

HVDC transmission line connecting the Edmonton area with northern Oregon

3000 MW line design capacity

2000 MW bidirectional capacity

900 miles

$2.2 billion (‘08$), 2000 MW initial capacity

Operational in 2015

Order 2004 Sensitive

73

Page 74: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

NorthernLights

Creates a bi-directional intertie between Alberta and the Pacific Northwest

Enhances regional resource reliability (AESO’s 2007 Market Roadmap)

Improves regional transmission reliability

Enhances regional wind capacity factors through geographic diversity

Provides market participants with beneficial opportunities to use the facilities

Provides opportunities for markets to access large scale renewable energy resources – wind, hydro, IGCC with sequestration & nuclear

Order 2004 Sensitive

74

Page 75: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Generation Potential in Alberta

Order 2004 Sensitive

75

Page 76: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

7676

Transmission Planning & WECC

Participation at NTAC, RMATS, Columbia Grid and NTTG

WECC Regional Planning Process 2007WECC Path Rating Process

BPA Interconnection Agreement

INL Study

Alberta Corridor Analysis

AESO Open Houses

NorthernLights Project Progress

Order 2004 Sensitive

76

Page 77: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Alberta Interconnection

To Buckley

Milo

Order 2004 Sensitive

77

Page 78: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Buckley Area Interconnection

“Buckley New”

Order 2004 Sensitive

78

Page 79: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Project Update (since July, 2008)

Edmonton to Calgary System Developments 40 open houses between June and December 2008 held

by the AESO with TransCanada participation

Phase 1 Comprehensive Progress Report tabled with TCWG Monday for comment Schedule to submit to the WECC December 1, 2008

Phase One Studies 2000 MW bidirectional power flow, reactive margin and

stability studies Results are all within reliability criteria standards

Order 2004 Sensitive

79

Page 80: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Project implementation Schedule

WECC rating studies 2009

Permitting and Land acquisition 2009 - 2012

Engineering 2009 - 2012

Construction 2012 - 2015

Operations 2015

Order 2004 Sensitive

80

Page 81: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

81

West Coast Cable Juan de Fuca Cable 2

Triton North CableTriton Central CableTriton South Cable

Sea Breeze Pacific - RTS Projects

Page 82: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

82

Order 2004 Sensitive

Page 83: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

83

Juan de Fuca Cable 2 2013 +/- 300 kV DC VSC 1,100 MW RP – submitted 11/2008

West Coast Cable (WCC) 2015 +/- 600 kV DC 1,600 MW Ph 1 – Initiated 12/2006

Triton Central Triton North Triton South Cables

20142016

2017/2019

+/- 300 kV DC VSC+/- 150 kV DC VSC+/- 300 kV DC VSC

2,200 MW550 MW2,200 MW

3 RP’s – submitted 11/2008

Order 2004 Sensitive

Page 84: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

84

Order 2004 Sensitive

Page 85: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

SBP-RTS Projects

West Coast Cable - In Phase 1 – Power Flow runs completed Stability runs in process

Juan de Fuca Cable 2 ▀ Triton Central Cable Triton North Cable ▀ Triton South Cables

Regional Planning reports - for all studies have been completed and are currently being submitted.

Phase 1 – Power Flow cases have been run in PowerWorld using the TCWG agreed upon 2015 HS TCWG Base Case

Have been converted to PTI format. ABB has confirmed models and has verified conversions. Models are available on the NWPP Website.

85

Order 2004 Sensitive

Page 86: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Questions?

86

Order 2004 Sensitive

Page 87: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

87

Next Steps and Timelines for TCWG

Joint Big Tent Meeting Nov 19, 2008

Submit Phase 1 CPR to PCC and TSS (Project Sponsor) Q4 2008

Phase 2 Studies (Project Sponsor and TCWG) Dec 2008 and on

TCWG will be used for Phase 2 study reviews Dec 2008 and on

Order 2004 Sensitive

Page 88: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Q & A

Order 2004 Sensitive

Page 89: Transmission Project Sponsors Big Tent Meeting November 19, 2008 Portland, Oregon Welcome

Inputs and Commentary

Sponsor Panel

89

Order 2004 Sensitive