transformer short-circuit testing -...

25
DNV GL © 2014 Ungraded 16 July 2016 DNV GL © 2014 Ungraded Transformer short-circuit testing KEMA Laboratories’ experience 1 Shankar Subramany IEEE Transformer Committee Meeting Vancouver, October 2016

Upload: trannhi

Post on 21-Mar-2018

229 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016DNV GL © 2014

Ungraded

Transformer short-circuit testing

KEMA Laboratories’ experience

1

Shankar Subramany

IEEE Transformer Committee Meeting

Vancouver, October 2016

Page 2: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

Testing at KEMA, Netherlands

2

Page 3: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

High Power Laboratory, Arnhem

3

high-voltage

laboratory

new UHV

synthetic

installation

MV test labextension of

generator hall

power

transformer

test site

Page 4: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

KEMA Lab expansion: prepared for UHV transformers

4

2 new generators installed

UHV synthetic installation

testing of test

transformer 1/4

Page 5: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

Preparing an 800 kV transformer for a short-circuit test

5

Page 6: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

features of the test circuit

� source can be kept on floating

potential

� pre-set test method preferred

� 1,5 phase method preferred

� Very fast master breaker

Page 7: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

Power transfer source to test-object

7

Page 8: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

The 1.5 phase method results in similar mechanical stresses as full 3-phase testing at the critical instant of asymmetrical current peak.

Leading laboratories use the 1.5 or 3-phase method to realize internal stresses as in service

current in 1.5 phase test

current in 1.5 phase test

current in three-phase test

current in three-phase test

full asymm. current in one phase moment ofmaximum stress

I

½I

½I

Transformer under test

Make switch

Supply

1,5Uphase

Page 9: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

Up to 800 kV class transformers

9

0

100

200

300

400

500

600

700

800

900

0 200 400 600 800 1000 1200

vo

lta

ge

(k

V)

power (MVA)

1 phase

1.5 phase

3 phase

tested

2008-2014

after extension

acceptance test of a new 400 kV test transformerExtension project: from 4 to 6 generators

from 6 to 10 short-circuit transformers

Page 10: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

Short-circuit testing in grid- and generator supplied labs

10

must be very fast in order to prevent test

transformer from destruction at a defect

must be very accurate in order

to apply adequate asymmetry

special design: 6 ms

special design: 3 deg

switching

at high-

voltage

switching at

medium-

voltage

moderate inrush current

high inrush current

Page 11: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

Testing

� IEC 60076-5

� three-phase transformer tested with

9 short-circuit applications of 0.25 s

� Criterion is impedance change before → after short-circuit current application

� ∆X ≤ 1% for transformers ≥ 100 MVA +

Pass routine tests and visual inspection

after test

� Testing is not destructive

11

Page 12: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

Some discussions in the IEC Maintenance team

� Impedance change trend during testing

� Number of short-circuits in normal service life?

� Life of transformer after short-circuit tests – testing is not destructive

� How best to test the tertiary windings?

� When and how mock-up transformers can be made and tested?

� What design review can show and what it cannot?

12

Page 13: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

What to learn from test results?

� Possibility to assess 'winding status' through evolution of reactance

measurement

� Hidden damage to voltage regulation winding

Page 14: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

0 1 2 3 4 5 6

0

0

0

TAP 5 TAP 3 TAP 1Isc=82% Isc=100% Isc=118%

Phase U Phase V Phase Wunder test under test under test

new

Sho

rt c

ircu

it im

peda

nce

(0.

5%/d

iv)

0 1 2 3 4 5 6test number

Phase U Phase V Phase Wunder test under test under test

new

TAP 5 TAP 3 TAP 1Isc=90% Isc=100% Isc=110%

0

0

0

phase U

phase V

phase W

variation of reactance after short-circuit tests

systematic (design?) flaw particular (production?) flaw

1%

Page 15: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

Summary results

0.0

0.2

0.4

0.6

0.8

1.0

0.0

0.2

0.4

0.6

0.8

1.0

1 2 3 4 5 6 7 8 9 10 11

maximum taprated tap

maximum tap position

after test

0.0

0.2

0.4

0.6

0.8

1.0

test number

minimum tap position

rated tap position

phase 1

phase 2

phase 3

after test

phase 3

after test, SC impedance of winding excl. regulation << with regulation

increase of reactance is entirely due to regulation winding

stress on phase 1

stress on phase 2

stress on phase 3Increase of reactance of regulation winding >> 1%

Page 16: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

Results

� 1996 – 2015: 297 tests series ≥ 25 MVA

� upto to 440 MVA, 525 kV

� in 230 cases no problems

at short-circuit

� 67 cases a problem, mostly

reactance change too large

� 39 transformers re-tested

� 78 visual inspection,

7 failed in that stage

� initial failure rate 67/297 = 23%

16

Page 17: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

Test statistics ≥ 25MVA

17

0

5

10

15

20

25

30

35

40

1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015

num

ber

of te

sts

initially not OK initially OK

Page 18: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

0

10

20

30

40

50

60

70

80

90

100

110

20-100 100-200 200-300 300-400 >400

num

ber

of t

ests

kV (rated)

initially not OK

initially OK

0

10

20

30

40

50

60

70

80

90

25-50 50-100 100-200 >200

num

ber

of t

ests

MVA (rated)

initially not OK

initially OK

18

significant higher failure rate at high-end of power and voltage

Test statistics ≥ 25MVA

Page 19: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

Visible failure modes

19

Broken bushing

Oil spills

Oil spill with fire

Page 20: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

Does calculation cover all aspects of short-circuit withstand?

� Calculation method given in the Standard is only based on static forces and do not cover all

parts of the transformer. The dynamic behaviour is not considered

� Following design aspects are not/cannot be addressed fully:

– Materials are considered ideal, and do not take into account poor workmanship, inhomogeneities,

production issues

– Models consider axial and rotational symmetry, whereas failure frequently are observed at

inhomogeneity’s like transpositions, crossover locations, pitch of winding, leads etc.

– Do not take into account friction of turns in axial direction, magnetic phase to phase interaction

– cross overs of turns (inside the winding) transpositions of parallel conductors (inside the winding)

– exit leads of the windings (fixation to prevent movement and friction (wear of insulation) of exit lead)

– support of cleats and leads

– connections to OLTC

20

Page 21: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

– support of leads to bushings

– stability of the radial support of windings (for example spacers used during winding the coil (untreated,

dried, dried and oil impregnated)

– effect of varying densities of the different windings due to axial compressing forces

– dynamic movement of the oil

– Successive movement of the winding, core, clamping arrangements and leads due to accumulated stresses

during a series of short-circuit tests, leading to a failure after a certain number shots cannot be

simulated/calculated

– Many observed failure modes cannot be predicted by models, like oil spill, broken bushings, internal

winding, deformation of leads.

21

Does calculation cover all aspects of short-circuit withstand?

Page 22: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 201616 July 2016

Ungraded

22

transposition between layers

windings are not

rotational symmetric

Page 23: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 201623

The actual value is the calculated value of the transformer under review. The allowable value is the design criteria of the manufacturer (including all his experience, tests, statistics and safety margins) to meet the specification. The critical value of a certain parameter is a number, one only can determine this if there were failures. In the case of lack of test data on this parameter it is just an estimated guess.

Page 24: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

..this is what that needs to be avoided…

Page 25: Transformer short-circuit testing - grouper.ieee.orggrouper.ieee.org/groups/transformers/.../C57.164/TransformerTesting... · DNV GL © 2014 Ungraded 16 July 2016 Transformer short-circuit

DNV GL © 2014

Ungraded

16 July 2016

SAFER, SMARTER, GREENER

www.dnvgl.com

25

Thank you for your kind attention!

before test after test

[email protected]