Track Trigger Meeting 3/23/10
• Chip Schedule:– 2D wafers complete fab~ April 30 – available for single –tier
functional testing– 3D wafers complete fab ~ May 28– Diced parts and full wafers June – Sent to Ziptronix for oxide
bonding of a handle wafer, then back to Tezzaron for exposure of bottom TSVs.
– Sensor wafers available early July• Topography and flatness checked at Ziptronix• Backside protection• Test of topside tungsten deposition and CMP
• Phone conference next week with Ziptronix to discuss plans• Volunteers for chip testing work?
![Page 2: Track Trigger Meeting 3/ 23/10](https://reader030.vdocuments.mx/reader030/viewer/2022032805/5681335d550346895d9a73b9/html5/thumbnails/2.jpg)
Short Strip TierLong Strip Tier
VICTR Chip
Can be used to estimate areas needed on final chip
![Page 3: Track Trigger Meeting 3/ 23/10](https://reader030.vdocuments.mx/reader030/viewer/2022032805/5681335d550346895d9a73b9/html5/thumbnails/3.jpg)
Pad Structure
![Page 4: Track Trigger Meeting 3/ 23/10](https://reader030.vdocuments.mx/reader030/viewer/2022032805/5681335d550346895d9a73b9/html5/thumbnails/4.jpg)
Kapton-based Interposer
• A preliminary project description has been written and sent to one vendor
• The goals include:– Develop a low-mass layup which is
sufficiently planar (<100 microns bow) to allow bump bonding on both sides over the full area.
– Minimum mass, either using low mass materials or by removing unneeded material.
– Contains embedded capacitance.– Provides a flex circuit “tail” for connection
to optical drivers about 5 cm away. – Provides through vias to measure load
capacitance and crosstalk.
Approach Endicott, Compunetics Cyrexx
![Page 5: Track Trigger Meeting 3/ 23/10](https://reader030.vdocuments.mx/reader030/viewer/2022032805/5681335d550346895d9a73b9/html5/thumbnails/5.jpg)
Interposer Strategy
1. Development of a full-size technology demonstration board which would be used for mounting dummy chips and developing bump-bonding techniques. This board would provide a platform to demonstrate a low-mass interposer with the appropriate interconnectivity.– We probably need to develop a full candidate layout
of either a full or VICTR 2 interposer including bussing for vendors
– Guess at pinout and numbers of bus lines 2. Production of a direct interconnection interposer for
the VIP-1 chip. 3. Production of a direct interconnection interposer for
the VIP-2 chip.4. Final product – full sized fully functional
![Page 6: Track Trigger Meeting 3/ 23/10](https://reader030.vdocuments.mx/reader030/viewer/2022032805/5681335d550346895d9a73b9/html5/thumbnails/6.jpg)
Proposed On-chip Logic Diagram
![Page 7: Track Trigger Meeting 3/ 23/10](https://reader030.vdocuments.mx/reader030/viewer/2022032805/5681335d550346895d9a73b9/html5/thumbnails/7.jpg)
Proposal for VICTR II
![Page 8: Track Trigger Meeting 3/ 23/10](https://reader030.vdocuments.mx/reader030/viewer/2022032805/5681335d550346895d9a73b9/html5/thumbnails/8.jpg)
2nd Submission Plan
Dec 2010 ?
![Page 9: Track Trigger Meeting 3/ 23/10](https://reader030.vdocuments.mx/reader030/viewer/2022032805/5681335d550346895d9a73b9/html5/thumbnails/9.jpg)
Meetings• Upgrade Week (April 26-30) Presentations
– Simulation– Mass Budget– Module Design– Interposer?– Trigger Architecture– Mechanics and cooling
• US CMS (May 6-8)• Workshop in Elba (May 24-28) – detailed discussions of
CMS upgrade plans in light of revised machine plans.• Address issues and objections:
– Detector mass– Yield and chip size– Functionality
• Increase breadth of the collaboration