tkp4170 – process design, projectreport: 42 appendices: 23 conclusion a pulverized coal (pc) plant...
TRANSCRIPT
NTNU Faculty of Natural Sciences and Technology Norwegian University of Department of Chemical Engineering Science and Technology
TKP4170 – Process Design, Project
Title: Considerations for a New Coal-Fired Power
Plant on Svalbard
Location: Trondheim, Norway
Date:
November
21, 2013
Authors:
Aqeel Hussain
Reza Farzad
Anders Leirpoll
Kasper Linnestad
Supervisor: Sigurd Skogestad
Number of pages: 72
Report: 42
Appendices: 23
Conclusion A pulverized coal (PC) plant was found to be the best fit for a new power plant o n
Svalbard. The technology is commercially available, and no research and development is
required. A maximum boiler temperature of 00 was assumed, together with
subcritical pressure in the steam cycle. District heating from a backpressure steam
turbine was found to be a better option than a central heat pump, both practically and
economically.
-
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
i
Abstract Different types of coal-fired power plants were considered as options for a new power plant at
Svalbard. Conventional technology was found to be the best fit, and a pulverized coal plant was
modeled in detail. As the current plant does not have any flue gas treatment, the new plant was
designed to handle CO2, sulfur, NOx, dust particle and mercury emissions. In a literature search, a
seawater scrubber and amine solution carbon capture were found to be suitable for this task.
The plant was modeled in Aspen HYSYS according to design basis and data given by
Longyearbyen Bydrift. Four cases were considered and studied in detail. The base case
generates electric power from three steam levels, and utilizes the existing district heating
network in Longyearbyen to use remaining heat from the steam cycle. In the heat pump case,
electric power is generated from two steam levels, fully condensing the steam. It was assumed
that the power could be used in a central heat pump or in consumer bought heat pumps,
consuming the power more efficiently. The last two cases consider how increasing the steam
pressure or temperature affects the plants thermal efficiency.
Economic analysis was performed on all major equipment, using order-of-magnitude scaling and
the factorial method. Variable costs, revenues and working capital were estimated together with
capital costs to perform investment analysis on the investment.
By analyzing case study data from Aspen HYSYS it was found that the base case is preferable
over the heat pump case, both in efficiency and in economic perspective. The case studies on
steam temperature and pressure confirmed that higher values will give a rise in thermal
efficiency.
Further research is recommended on optimizing the steam cycle, as number of steam levels,
steam pressure and temperature highly affect the thermal efficiency. Research and development
is recommended on amine solution carbon capture, as the expense of carbon capture and
storage is the economic bottleneck of the project.
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
ii
Preface This project was written as a part of the M.Sc. degree in Chemical Engineering at the Norwegian
University of Science and Technology in the course TKP4170 Process Design Project.
We would like to thank our supervisor, Professor Sigurd Skogestad for his invaluable help,
insight and motivation throughout the project period.
We are deeply grateful, and his support has helped us throughout the whole project, providing
knowledge we will carry on in our degree.
Declaration of Compliance
We hereby declare that this is an independent report according to the exam regulations of the
Norwegian University of Science and Technology.
Trondheim, November 21, 2013
Aqeel Hussain
Reza Farzad
Anders Leirpoll
Kasper Linnestad
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
iii
Table of Contents Abstract i
Preface ii
1 Design Basis 1
2 Introduction to Coal-Fired Power Plants 2
2.1 Conventional Coal-Fired Power Plants 2
2.1.1 Supercritical Coal Fired Power Plants 3
2.2 Integrated Gasification Combined Cycle (IGCC) Coal-Fired Power Plants 4
2.3 Oxygen-Fired Coal Combustion Power Plants (Chemical Looping Combustion) 5
3 Introduction to Flue Gas Treatment 6
3.1 CO2 Capture 6
3.1.1 Post-Combustion Capture 6
3.1.2 Pre-Combustion Capture 7
3.1.3 Oxygen-Fired Combustion 8
3.1.4 Carbon Storage 8
3.1.5 Economics of CO2 Capture 8
3.2 Flue Gas Desulphurization 10
3.2.1 Wet scrubbing 10
3.2.2 Dry Scrubbing 11
3.3 NOx Removal 12
4 Process Descriptions 12
4.1 Current Plant at Svalbard 12
4.1.1 Boiler 13
4.1.2 Steam Cycle 13
4.1.3 District Heating 13
4.1.4 Gas Treatment 13
4.2 Proposed Pulverized Coal plant with Carbon Capture and Storage (Base Case) 14
4.2.1 Pulverized Coal Boiler 14
4.2.2 Steam Cycle 14
4.2.3 Flue Gas Treatment 15
4.2.4 District Heating 15
4.3 Case Studies 15
4.3.1 Base Case 15
4.3.2 Heat Pump Case 15
5 Flowsheet Calculations 15
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
iv
5.1 Base Case 15
5.1.1 Flow diagram 15
5.1.2 Stream Data 16
5.1.3 Compositions 17
5.1.4 Summary of Key Results 19
5.1.5 Steam Temperature 19
5.1.6 Steam Cycle Pressure 20
5.2 Heat Pump Case 20
5.2.1 Flow Diagram 21
5.2.2 Stream Data 22
5.2.3 Compositions 23
5.2.4 Summary of Key Results 24
5.2.5 Coefficient of performance 24
6 Cost Estimation 25
6.1 Capital Costs of Major Equipment 25
6.1.1 Pulverized Coal boiler 25
6.1.2 Heat exchangers 26
6.1.3 Turbines 26
6.1.4 Compressors 26
6.1.5 Pumps 27
6.1.6 Flue Gas Desulfurization 27
6.1.7 Carbon Capture Facility 27
6.1.8 Heat Pump Costs 27
6.1.9 Total Equipment Costs 28
6.2 Variable Costs 29
6.2.1 Labor 29
6.2.2 Diesel Costs 30
6.2.3 Cost of Coal 30
6.2.4 Operation and Maintenance 30
6.2.5 Chemicals 31
6.2.6 Total Variable Costs 31
6.3 Revenues 31
6.4 Working Capital 31
7 Investment Analysis 31
7.1 Base Case 31
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
v
7.2 Heat Pump Case 32
8 Discussion 33
8.1 Plant Choices 33
8.1.1 Plant Type 33
8.1.2 Steam Cycle 34
8.1.3 Flue Gas Treatment 34
8.2 Case Studies 34
8.2.1 Base Case 34
8.2.2 Steam Temperature 35
8.2.3 Steam Cycle Pressure 35
8.2.4 Heat Pump Case 35
8.3 Investments 35
8.3.1 Cost estimations 35
8.3.2 Investment analyses 36
9 Conclusion and Recommendations 37
References 38
List of symbols and abbreviations 41
Appendix A - Cost estimation for the base case A-1
A.1 Cost of major equipment A-1
A.2 Variable costs A-5
A.3 Revenues A-6
A.4 Working capital A-6
Appendix B - Cost estimation for the heat pump case B-1
B.1 Major Equipment B-1
B.2 Variable Costs B-5
B.3 Revenues B-6
B.4 Working Capital B-6
Appendix C - Cost estimation for the base case without carbon capture C-1
C.1 Cost of major equipment C-1
C.2 Variable Costs C-4
C.3 Revenues C-5
C.4 Working Capital C-5
Appendix D Net Calorific Value of the Coal on Svalbard D-1
Appendix E – Composite Curves E-1
E.1 Boiler E-1
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
vi
E.2 District Heat Exchanger E-1
E.3 Vacuum Condenser E-2
E.4 CO2 Cooler E-2
E.5 LP CO2-Cooler E-3
E.6 IP CO2-Cooler E-3
Appendix F – Aspen HYSYS Flowsheets F-1
F.1 Base Case F-1
F.2 Heat Pump Case F-2
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
1
1 Design Basis The design for the new plant was based upon the current plant data. It was assumed that the
electrical energy demand would double, and that the need for district heating would increase
with 50 %. A summary of the data from the current plant and the design basis for the new plant
are listed in Table 1.1.
Table 1.1: Plant data for the current plant and design basis for the new plant.
Current plant New plant
Electrical energy 4.8 MW 9.6 MW Thermal energy (district heating)
8.0 MW 12 MW
Coal 25000 ton/year 60000 ton/year (calculated) Diesel 390 000
liters/year 307 000 liters/year (average of the last four years)
The simplifications and assumptions that are made are listed below.
The coal is assumed to be pure carbon with the same net calorific value as the coal on
Svalbard (~7300 kcal/kg), shown in Figure D.1 in Appendix C .
The boiler is modeled as a combustion reactor with a maximum temperature of 00 ,
followed by a heat exchanger.
The boiler is assumed to combust the coal completely.
The boiler is assumed to have a minimum temperature approach of 10 , this is obtained
by adjusting the flow of water in the steam cycle.
The flue gas desulfurization is not included in the model.
The carbon capture facility is modeled as a pure component splitter with a given heat
requirement for re-boiling the rich amine solution in the stripper column.
The HP steam temperature and pressure are set to 00 and 165 bar respectively.
The outlet pressure of the HP steam turbine is set to 49 bar, and is reheated to 00 .
The vacuum pressure created by the condenser is set to 0.01 bar.
The seawater is assumed to be 4 .
The district heating network is modeled as heat exchangers with an inlet temperature of
1 0 , an outlet temperature of 0 and a pressure drop of 5 bar. This is obtained by
adjusting the flow of water in the district heating network.
The compressor train for the compression of carbon dioxide for storage is modeled as
two compressors and a pump with intercooling using heat exchanger with cold seawater.
The inter-stage pressures for the compressor train are found by trial and error to
yield the lowest amount of work needed.
The adiabatic efficiencies of all the compressors and pumps are assumed to be .
The split ratio between the LP steam turbine and the IP steam turbine are chosen to
yield a total district heating of 12 MW.
The amount of air blown into the boiler is chosen to yield a maximum combustion
temperature of 800 .
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
2
The amount of heat needed to the reboiler of the stripper is based on a 90% capture,
and an amount of heat needed per kilo removed ( 4
).
The amount of electricity needed for the heat pump is found by an estimate for the heat
pumps coefficient of performance (
) [1], and a basis of 12 MW for district
heating.
The price of electricity was assumed to be 1 NOK/kWh.
The price of district heating was assumed to be 0.5 NOK/kWh.
Constant yearly costs and revenues.
Constant depreciation rate of 10%.
Constant amount of depreciation of 20%.
0% tax on Svalbard.
2 Introduction to Coal-Fired Power Plants For more than 100 years, coal-fired power plants have generated the major portion of the
worldwide electric power [2] with a current (2011) market supply share of 41.2% [3]. Coal is
the largest growing source of primary energy worldwide, despite the decline in demand among
the OECD countries, due to China’s high increase in demand [4]. The Chinese coal consumption
and production account for more than 45% of both global totals, and it has been estimated that
their share will pass 50% by 2014 because of their high demand for cheap energy [4]. This will
drastically increase the world total CO -production which will contribute greatly to the global
warming and other environmental effects such as ocean acidification [5]. It will therefore be of
great importance to develop clean and efficient coal plants which can produce electricity that
can compete with the prices of the cheap, polluting coal plants that currently exists. Some
instances of such plants have been proposed as alternatives to the conventional coal-fired power
plant and they will be given an introduction in this report.
2.1 Conventional Coal-Fired Power Plants Conventional coal-fired power plants use pulverized coal (PC) or crushed coal and air as a fuel to
the furnace. The coal is pulverized by crushing and fed to the reactor at ambient pressures and
temperatures and burned in excess of air. The excess of air is introduced to lower the furnace
temperature which makes the equipment cheaper as it does not have to withstand extreme
temperatures, and it also reduces the formation of O . O is formed at high temperatures and
is a pollutant that has a negative effect on the health of humans besides contributing to acidic
precipitation [6]. The hot flue gas from the furnace is used to heat up the boiler which produces
high pressure (HP) steam. This steam is in turn expanded in a turbine arrangement that
generate electrical power. The low pressure (LP) steam is then condensed and re-fed to the
boiler. The hot flue gas contains pollutants and aerosols which have to be removed before the
gas is vented through the stack to the atmosphere. Pollutants that have to be removed include
mercury, O and O . The nitrous oxides are usually removed using selective catalytic
reduction (SCR) where ammonia is used as a reducing agent [7]. The sulfur, mercury and other
solid matter is normally removed as solid matter by reducing the sulfurous oxide using lime and
water, and then passing the flue gas through an electrostatic precipitator or a fabric filter. The
slurry is then collected for safe deposition. Conventional coal plants operating using subcritical
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
3
(sC) conditions, which will result in low overall plant efficiency [8]. A conceptual process flow
diagram of this power plant is shown in Figure 2.1.
Figure 2.1: Simplified process flow diagram for the conventional coal plant with district heating. HRSG = heat recovery steam generator. FGT = flue gas treatment (desulfurization, mercury removal, dust removal etc.)
2.1.1 Supercritical Coal Fired Power Plants
The efficiency of the plant can be increase by using supercritical (SC) steam conditions with
higher pressure. The plant efficiency is increasing both for increasing pressure drop and
increasing temperature. There is therefore a constant development of better equipment that can
withstand higher steam pressures and temperatures [8]. Some examples of conditions are listed
in
Table 2.1. The ultra supercritical configuration is currently under development and is expected
to be available in 2015 [8]. A typical heat recovery steam generator design is shown in Figure
2.2.
Boiler
FGT
HRSG
A
T 2-
x n
As
P w
D s n
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
4
Figure 2.2: Heat recovery steam generator cycle with three pressure levels, HP, IP and LP. HP = high pressure. IP = intermediate pressure. LP = low pressure.
Table 2.1: Some typical HP steam conditions [8]
Temperature
Pressure [bar]
Depleted < 500 < 115 Subcritical (sC) 500-600 115-170 Supercritical (SC) 500-600 230-265 Ultra supercritical ~730 ~345
2.2 Integrated Gasification Combined Cycle (IGCC) Coal-Fired Power Plants IGCC power plants feed compressed oxygen and a slurry of coal and water to a gasifier. The
gasifier converts the fuel to synthesis gas (syngas) which is then treated to remove sulfur,
mercury and aerosols. The syngas is then brought to a combustor with compressed air diluted
with nitrogen in a turbine. The flue gas is then used to create steam by passing it through an
HRSG. This steam is passed through a series of turbines, as with the conventional plant. The
efficiency gain this method has compared to the conventional plant is that the combustor
turbine operates at a very high temperature (~1500 ), but it also has to have an air separation
unit (ASU) to achieve reasonable conversion rates for the gasification process [9]. The IGCC
power plants require large investments because of all the advanced utilities such as a fluidized
bed reactor for gasification and an air separation unit. The IGCC power plants can achieve up to
3% higher efficiencies which can be worth the investment in the long run, especially for huge
power plants [8].
HP IP LP
nd ns
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
5
Figure 2.3: Simplified process flow diagram for the IGCC power plant.
2.3 Oxygen-Fired Coal Combustion Power Plants (Chemical Looping
Combustion) Oxygen-fired coal combustion power plants, also known as chemical looping combustion, burn
PC with pure oxygen which creates a flue gas that has a very high carbon dioxide concentration.
This has the advantage that the flue gas can be injected directly into storage after
desulfurization, and cleaning. This technology is currently under development and several pilot
plants have been built [10]. Unlike the other power plant designs, this design does not suffer a
significant loss in efficiency when carbon capture and storage (CCS) is implemented. For a
conventional power plant the loss in efficiency can be up to 14%, while the oxygen-fired power
plant only suffers losses of around 3% [8] [11]. Another advantage is that there will not be any
formation of nitrous oxides due to the lack of nitrogen in the feed, however the concentration of
sulfur oxide will increase due to the flue gas recycle. This is on the other hand not seen as a
major problem as sulfur oxide can be treated by introducing lime in the reactor. However this
technology is currently not available commercially.
Fluidized bed gasifier FGT
A HRSG P w
ASU
x n
As
S u
P w
T 2-
x n
N n
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
6
Figure 2.4: Simplified process flow diagram for the oxygen-fired coal combustion power plant.
3 Introduction to Flue Gas Treatment
3.1 CO2 Capture Energy supply from fossil fuels is associated with large emissions of CO and account for 75% of
the total CO emissions. CO emissions will have to be cut by 50% to 85% to achieve the goal of
restricting average global temperature increase to the range of to 4 [5]. Industry and
power generation have the potential to reduce the emission of greenhouse gases by 19% by
2050, by applying carbon capture and storage [12]. There are three basic systems for CO
capture.
Post-combustion capture
Pre-combustion capture
Oxygen fuelled combustion capture
3.1.1 Post-Combustion Capture
CO2 captured from flue gases produced by combustion of fossil fuel or biomass and air is
commonly referred to as post-combustion. The flue gases are passed through a separator where
CO is separated from the flue gases. There are several technologies available for post-
combustion carbon capture from the flue gases, usually by using a solvent or membrane. The
process that looks most promising with current technologies is the absorption process based on
amine solvents. It has a relatively high capture efficiency, a high selectivity of CO and the lowest
energy use and cost in comparison with other technologies. In absorption processes, CO is
captured using the reversible nature of chemical reactions of an aqueous alkali solution. Amine
solutions are most common for carbon capture. After cooling the flue gas it is brought into
contact with solvent in an absorber at temperatures of 40 to 0 . The regeneration of solvent
is carried out by heating in a stripper at elevated temperatures of 100 to 140 . This requires
a lot of heat from the process, and is the main reason why CO capture is expensive [13].
Membrane processes are used for CO capture at high pressure and higher concentration of
carbon dioxide. Therefore, membrane processes require compression of the flue gases; as a
Fluidized bed gasifier FGT
A HRSG P w
ASU
x n
As
S u
T 2-
nj n
N n
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
7
consequence this is not a feasible solution with available technology as of 2013. However, if the
combustion is carried out under high pressure, as with the IGCC process, membranes can
become a viable option once they achieve high separation of CO [14].
Figure 3.1: Conceptual process flow diagram of the absorption process. HEX = heat-exchanger used to minimize the total heat needed for separation of carbon dioxide.
3.1.2 Pre-Combustion Capture
Pre-combustion capture involves reacting fuel with oxygen or air and adding water, and
converting the carbonaceous material into synthesis gas containing carbon monoxide and
hydrogen. During the conversion of fuel into synthesis gas, CO2 is produced via water-shift
reaction. CO2 is then separated from the synthesis gas using a chemical or physical absorption
process resulting in H2 rich fuel which can be further combusted with air. Pressure swing
adsorption is commonly used for the purification of syngas to high purity of H2, however, it does
not selectively separate CO2 from the waste gas, which requires further purification of CO2 for
storage. The chemical absorption process is also used to capture CO2 from syngas at partial
pressure below 1.5 MPa. The solvent removes CO2 from the shifted syngas by mean of chemical
reaction which can be reversed by high pressure and heating. The physical absorption process is
applicable in gas streams which have higher CO2 partial pressure or total pressure and also with
higher sulfur contents. This process is used for the capturing of both H2S and CO2, and one
commercial solvent is Selexol [8].
Absorption Regenerator
F u s
HEX
n u s
R bs b n
L n bs b n
Abs b n m -up
2
nj n
R -b
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
8
Figure 3.2: Schematic drawing of an integrated gasification combined cycle plant with pre-combustion carbon caption. Th e carbon monoxide from the gasifier is converted to carbon dioxide and hydrogen by reacting it with steam in the sh ift reactor. The carbon dioxide is captured in the carbon capture unit (CC, see Figure 3.1), and pure hydrogen is b u rned with nitrogen diluted air.
3.1.3 Oxygen-Fired Combustion
In oxygen-fired coal combustion, the flue gas is almost free of nitrogen-gases and after removal
of sulfur the flue gas is 90 % CO2, rest H2O. There is no need for further CO2-capture, and the CO2
can be compressed and stored [11].
3.1.4 Carbon Storage
After the carbon dioxide has been compressed it can be injected into storage. CO is usually
stored in geological formation at depths of 1000 m or more [15]. Hence high pressures are
required before injection, which has the advantage that CO can be injected as a supercritical
fluid. This will reduce the pipeline diameter and, consequently capital cost [16]. The oil industry
is experienced with geological difficulties, and may provide expertise on the geological
formation and how they will react to carbon dioxide injection. The storage site and reservoir has
to be closely monitored to ensure that the carbon dioxide does not escape into the atmosphere
or nearby drinking water supplies. With careful design of injection and appropriate monitoring
of well pressure and local CO -concentrations, it can be ensured that the injected carbon dioxide
remains underground for thousands of years [15].
3.1.5 Economics of CO2 Capture
CO2 capture is an expensive process both in capital costs and variable costs. Post combustion
absorption by amine solution can add as high as a 29% electrical power penalty even with state
of the art CO2 capture technology [8]. The capital costs depend highly on the flow rate of flue gas,
as this increases the regenerator and compressor size. The variable costs are also increased with
higher flue gas flow, as more sorbent is required, and the cost of CO2-transport and storage will
Fluidized bed gasifier FGT
A HRSG P w
ASU
x n
As
S u
P w
T m sp
Shift reac-
tor
T 2-
nj n
CC
S m
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
9
increase [17]. Improving process configurations and solvent capacity can majorly reduce power
demand for the regenerator. Such improvements include: absorber intercooling, stripper
interheating, flashing systems and multi-pressure stripping, though all of these will come at the
expense of complexity and higher capital costs. Table 3.1 shows the development in MEA
absorption systems from year 2001 to 2006 [18].
Table 3.1: Economics of CO2 capture by MEA scrubbing [18].
Year of design 2001 2006 MEA [weight percent] 20 30 Power used [MWh/ton] 0.51 0.37 @ $ 80/MWh [$/ton CO2 removed] 41 29 Capital cost [$/ton CO2 removed per year] 186 106 @ 16%/year [$/ton CO2 removed] 30 17 Operating and maintenance cost [$/ton CO2 removed] 6 6 Total cost [$/ton CO2 removed] 77 52 Net CO2 removal with power replaced by gas [%] 72 74
The environmental impact is commonly expressed as cost per pollutant removed or cost per
pollutant avoided. Cost of CO2 per tom removed is different from cost of CO2 avoided and cost of
CO2 avoided is given as [19] :
cost o CO a oided ( tonne⁄ ) ( h⁄ ) ( h⁄ )
(tonne CO h⁄ ) (tonne CO h⁄ ) (1)
Table 3.2 shows the cost variability and representative cost values for power generation and CO2
capture, for the three fuel systems respectively. The cost of electricity is lowest for the NGCC,
regardless of CO2 capture. Pulverized Coal plant has lower capital cost without capture while
IGCC plant has lower cost when current CO2 capture is added in the system.
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
10
Table 3.2: Summary of reported CO2 emissions and costs for a new electric power plant with and without CO2 capture b ase don current technology (excluding CO2 transport and storage costs) [20].
MWref = reference plant net output Rep . value = representative value NGCC = natural gas combined cycle plant.
Cost and Performance Measures
PC Plant IGCC Plant NGCC Plant
Range low-high
Rep. value
Range low-high
Rep. value
Range low-high
Rep. value
Emission rate w/o capture [kg CO2/MWh]
722-941 795 682-846 757 344-364
358
Emission rate with capture [kg CO2/MWh]
59-148 116 70-152 113 40-63 50
Percent CO2 reduction per kWh [%]
80-93 85 81-91 85 83-88 87
Capital cost w/o capture [$/kW]
1100-1490
1260 1170-1590
1380 447-690
560
Capital cost with capture [$/kW]
1940-2580
2210 1410-2380
1880 820-2020
1190
Percent increase in capital cost [%]
67-87 77 19-66 36 37-190 110
Cost of CO2 avoided [$/t CO2]
42-55 47 13-37 26 35-74 47
Cost of CO2 captured [$/t CO2]
29-44 34 11-32 22 28-57 41
Power penalty for capture [% MWref]
22-29 27 12-20 16 14-16 15
Thermal efficiency w/o capture [8]
36.8%-39.3%
38.1% 39.0%-42.1%
40.2% 50.2% 50.2%
Thermal efficiency w/ capture [8]
26.2%-28.4%
27.3% 31.0%-32.6%
31.6% 42.8% 42.8%
3.2 Flue Gas Desulphurization SO2 has a harmful effect both on humans and the environment. Exposure to higher
concentrations of SO2 is the cause of many harmful diseases. SO2 affects the environment by
reacting into acids and is a major source of acid rain [21]. Combustion of sulfur-containing
compounds such as coal is a major source of SO2 generation. Removal of sulfur from solid fuels is
not practical, so the sulfur is removed from the flue gas after combustion of coal. The removal of
sulfur oxide from the flue gasses is achieved by physical or chemical absorption process [22].
There are two commonly used industrial processes for the desulphurization of flue gasses [23],
wet and dry scrubbing.
3.2.1 Wet scrubbing
In wet scrubbing, a solvent is used for the absorption of SO2. Typically water is considered to be
the cheapest sol ent It’s washing capacity howe er is ery limited and huge quantity of water
has to be used. Approximately 75 tons of water is used per ton of flue gas, and even then 5% of
SO2 remains [22].
In advanced processes, flue gas is treated with an alkaline slurry in an absorber, where SO2 is
captured, shown in Figure 3.3. The most commonly used slurry is composed of limestone, which
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
11
reacts with the sulfur. The sulfur removal efficiency is 98 % for wet slurry scrubbing processes.
Carbon dioxide removal units include a polishing scrubber which lowers flue gas SO2 content
from 44 ppmv to 10 ppmv [8].
Figure 3.3: Flue gas desulfurization via wet scrubbing using limestone slurry [24].
Wet scrubbing process is mostly used with higher sulfur contents with economic efficiency of 95
to 98%. The main disadvantage of wet scrubbing is acidic environment which can be corrosive.
Therefore, corrosion resistant material is required for the construction which increases capital
cost of the plant. The other disadvantage includes consumption of large quantity of water for the
process.
3.2.2 Dry Scrubbing
Dry scrubbing is useful for coal with lower sulfur content. It also has the major advantage of
maintaining a higher temperature of the emission gasses, while wet scrubbing decreases the
temperature to that of water used [21]. Lime is normally used as sorbent-agent during the dry
scrubbing process. The dry sorbent reacts with the flue gas at 1000 to remove SO2. In dry
scrubbing adiabatic saturation approach is normally applied. Adiabatic saturation is required to
achieve high SO2 removal, thereby carefully controlling the amount of water [21].
Figure 3.4: Flue gas desulfurization via dry scrubbing using limestone [24].
Flue Gas
Lime + Water
Oxidation Air Solids for
Dewatering
Wet Desulfurized
Flue Gas
Flue Gas
Desulfurisation
Scrubber
Flue Gas
Lime + Water
Solids for
Disposal
Desulfurized
Flue Gas Flue Gas
Desulfurisation
Spray Dryer
Electrostatic
Precipitator
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
12
Relatively poor conversion is the main disadvantage of dry sorbent process, which increases the
operational costs. Dry scrubbing uses a minimal amount of water, and leaves the flue gas dry,
reducing risk of corrosion. Relatively dry calcium sulfite is obtained as by-product with fly ash
[21].
3.3 NOx Removal Selective catalytic reduction (SCR) approach is applied for removal of NOx, where the flue gas is
reduced with ammonia over a catalyst to nitrogen and water. The SCR has a efficiency of 80 to 90
% for NOx removal. The optimal temperature range is 0 7 0 , with vanadium and titanium
as catalyst, and the following reaction is carried out during the process:
4 4 O O 4 O (2)
Ammonia is either injected in pure form under pressure or in an aqueous solution. Instead of
ammonia, urea can also be used for the process. The main challenge of the process is full
conversion as emission of the NH3 is highly undesirable. The unreacted NH3 can also oxidize SO2
to SO3 that further reacts with NH3 to form ammonium bisulfate. Ammonium bisulfate is a sticky
solid material which can plug the equipment. The catalyst activity is very critical with SCR
because catalyst can cost up to 1 0 of the capital cost [7].
4 Process Descriptions
4.1 Current Plant at Svalbard A process flow diagram for the existing plant at Svalbard is shown in Figure 4.1.
Figure 4.1: Process flow diagram of current plant at Svalbard
Boiler
District heating
Coal
Air
Ash Main Water
Pump
Sea water Pump
Sea water
Condenser
Condensing Steam Turbine
District Heat Water Pump
Flue Gas Back Pressure Steam Turbine
𝑝 4 bar𝑇 4 0
𝑝 0 0 bar𝑇 4
𝑝 1 bar𝑇
𝑝 9 bar𝑇 0
𝑝 1 bar𝑇 1 0
𝑝 1 bar𝑇 1 0
𝑝 𝑇 ambient
𝑝 bar𝑇 0
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
13
4.1.1 Boiler
Coal is crushed and fed to the boiler along with air, where it combusts at high temperatures
forming flue gas and ash. The air is blown into the boiler by fans. Water is circulated through the
evaporator-drums in the boiler to yield pressurized steam. The flue gas is sent directly to the
stack and out to the atmosphere.
4.1.2 Steam Cycle
The hot steam from the boiler is split into two streams, one of which is sent to a condensing
steam turbine, the other to a backpressure steam turbine. The steam from the condensing steam
turbine is quenched in a condenser that is cooled with seawater; this allows the outlet pressure
from the turbine to be relatively low, depending on how much it is cooled. The backpressure
steam turbine has a relatively high backpressure, which yields moderately high temperatures in
the outlet stream. This heat is exploited by heating up cold water from the district heating
network. The two different streams are then combined, sent through a pump and back to the
boiler.
4.1.3 District Heating
The district heating water circulates Longyearbyen, and is used to heat houses and tap water,
before it is sent back to the power plant for reheating. The water is pumped to a heat exchanger
where it is reheated by the condensing steam from the backpressure steam turbine. After which
it is sent back to the district heating network.
4.1.4 Gas Treatment
The flue gas is currently not treated before it is sent trough the stack to the atmosphere.
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
14
4.2 Proposed Pulverized Coal plant with Carbon Capture and Storage (Base
Case)
Figure 4.2: Process flow diagram of the proposed design. FGT = flue gas treatment unit, and CC = carbon capture unit.
4.2.1 Pulverized Coal Boiler
Coal is pulverized and fed to the boiler along with air, where it combusts at high temperatures
forming flue gas and ash. Water is circulated through the evaporator-drums in the boiler to yield
high pressure (HP) steam, through the re-heater to re-heat the intermediate pressure (IP)
steam, while re-boiler amine solution is fed through the economizer, recovering heat from the
flue gas.
4.2.2 Steam Cycle
HP steam is run through a HP turbine, and the re-heated IP steam is run through a split to the IP
turbine or the low pressure (LP) turbine. After the LP turbine, the steam condenses using
seawater from the seawater pump. Because of the low temperature of the seawater, low
pressures are obtained. After the IP turbine, the water still has a high temperature and pressure,
which is used for district heating. Residual condensed steam from both the IP and LP turbine is
pumped back up to a high pressure and once again fed into the boiler evaporator drums.
Boiler
District heating
FGT
CC
Coal
Air
Ash Main Water
Pump Sea water
Pump
Sea water
Vacuum Condenser
Condensing Steam Turbine
Low Pressure Water Pump
Back Pressure Steam Turbine
High Pressure Turbine
District Heat Water Pump
Low Pressure 𝑪𝑶𝟐 Compressor
intermediate Pressure 𝑪𝑶𝟐 Compressor
High Pressure 𝑪𝑶𝟐 Pump
Clean
Flue Gas
Flue Gas
𝑪𝑶𝟐
𝑝 𝑇 ambient
𝑝 1 bar𝑇 0
𝑝 1 bar𝑇
𝑝 1 bar𝑇 1 0
𝑝 bar𝑇 1 0
𝑝 41 bar𝑇 1 0
𝑝 100 bar𝑇 1
𝑝 1 bar𝑇
𝑝 1 bar𝑇
𝑝 bar𝑇 0
𝑝 bar𝑇 0
𝑝 bar𝑇 1 0
𝑝 49 bar𝑇 00
𝑝 1 bar𝑇 00
𝑝 1 bar𝑇 1 0
𝑝 0 001 bar𝑇
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
15
4.2.3 Flue Gas Treatment
The flue gas out of the boiler is first desulfurized in the flue gas desulfurization unit (FGD), using
a seawater scrubber. The seawater is used to cool steam and CO2 earlier in the process, and then
fed to the seawater scrubber. As the concentration of sulfur in the water out is low, it can safely
be pumped back to the ocean. As the flue gas is quenched through seawater, dust particles and
mercury is also removed.
After FGD, the flue gas goes through the carbon capture (CC) facility, using an amine solution.
Flue gas with low CO2-content is sent out to the environment, while the captured CO2 is sent to
compression and storage. Here the CO2 is cooled with seawater and compressed two times,
before being pumped as a supercritical fluid down into geological formations.
4.2.4 District Heating
The proposed pulverized coal power plant will use the same district heating network as is
already built on Svalbard, giving a steam split-factor between IP and LP turbines. The district
heating water circulates Longyearbyen, and is used to heat houses and tap water. After being
used, the water is sent back to the power plant. The cycle introduces a pressure drop, which is
equalized by the district heating water pump.
4.3 Case Studies In the report two different cases will be studied, one using the existing district heating loop on
Svalbard, another introducing a central heat pump.
4.3.1 Base Case
The base case uses the current district heating network on Svalbard, and produces 12 MW of
district heating, with double the current electric power, giving 9.6 MW of electric energy. The
split of steam to the backpressure IP turbine for district heating and LP turbine for pure electric
generation is adjustable, and was adjusted to fit the design basis in Table 1.1, using as little coal
as possible.
4.3.2 Heat Pump Case
The heat pump case is an attempt at maximizing electric energy produced, to use the electric
energy in heat pumps instead of district heating. This model has the possibility of selling excess
electric power to the neighboring town of Barentsburg, but is highly dependent on good
coefficient of performance for the heat pump. Investment analysis is performed on both cases,
using the same amount of coal, to compare them to each other.
5 Flowsheet Calculations
5.1 Base Case The plant is modeled using Aspen HYSYS, based on the results rom the report “Cost and
Per ormance Baseline or Fossil Energy Plants” by the ational Energy Technology Laboratory
[8].
5.1.1 Flow diagram
The process flow diagram from the Aspen HYSYS model is shown in Figure 5.1, a larger figure is
shown in Appendix F .
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
16
Figure 5.1: The process flow diagram from the Aspen HYSYS model for the base case.
5.1.2 Stream Data
The important stream data for the different streams in the Aspen HYSYS model are shown in
Table 5.1.
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
17
Table 5.1: Stream data for the base case, calculated in Aspen HYSYS.
Stream name Vapor fraction
Temperature [ ]
Pressure [bar]
Mass flow [kg/s]
Air 1.00 10.00 1.0 70.4
Coal 0.00 10.00 1.0 1.90
Flue gas 1.00 799.99 1.0 72.3
Slurry 0.00 799.99 1.0 0.00
1 0.00 40.36 3.0 9.08
2 0.00 41.30 165.0 9.08
3 1.00 600.00 165.0 9.08
4 1.00 407.07 49.0 9.08
5 1.00 600.00 49.0 9.08
6 1.00 600.00 49.0 4.87
7 0.90 5.88 0.0 4.87
8 0.00 5.88 0.0 4.87
9 0.00 5.99 10.0 4.87
10 1.00 600.00 49.0 4.21
13 0.00 80.00 3.0 4.21
14 0.00 40.44 3.0 9.08
D1 0.00 80.00 3.0 63.8
D4 0.00 80.00 3.0 63.8
D2 0.00 80.04 8.0 63.8
D3 0.00 120.00 8.0 63.8
11 1.00 349.87 8.0 4.21
12 0.00 120.00 8.0 4.21
Reboiler in 0.00 120.00 2.0 9.93
Reboiler out 1.00 120.00 2.0 9.93
Cleaned Gas 1.00 79.42 1.0 65.3
CO2 for compression 1.00 79.40 1.0 6.97
MP CO2 1.00 177.95 41.0 6.97
MP CO2 liquid 0.00 6.00 41.0 6.97
HP CO2 liquid 0.00 13.31 100.0 6.97
SW 1 0.00 3.00 1.2 2560
SW 2 0.00 4.00 1.2 2560
SW 0 0.00 3.00 1.0 2560
SW5 0.00 4.39 1.2 2560
LP CO2 1.00 163.23 6.1 6.97
LP CO2 cooled 1.00 10.00 6.1 6.97
SW4 0.00 4.13 1.2 2560
Cold CO2 for compression
1.00 10.00 1.0 6.97
SW3 0.00 4.04 1.2 2560
Cooler Flue Gas 1.00 79.40 1.0 72.3
5.1.3 Compositions
The composition of each stream from the Aspen HYSYS model is shown in Table 5.2.
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
18
Table 5.2: Composition data for the base case, calculated in Aspen HYSYS, where is the mole fraction of component .
Stream name
CO O C
Air 0.000 0.000 0.210 0.790 0.000
Coal 0.000 0.000 0.000 0.000 1.000
Flue gas 0.000 0.065 0.145 0.790 0.000
Slurry 0.000 0.065 0.145 0.790 0.000
1 1.000 0.000 0.000 0.000 0.000
2 1.000 0.000 0.000 0.000 0.000
3 1.000 0.000 0.000 0.000 0.000
4 1.000 0.000 0.000 0.000 0.000
5 1.000 0.000 0.000 0.000 0.000
6 1.000 0.000 0.000 0.000 0.000
7 1.000 0.000 0.000 0.000 0.000
8 1.000 0.000 0.000 0.000 0.000
9 1.000 0.000 0.000 0.000 0.000
10 1.000 0.000 0.000 0.000 0.000
13 1.000 0.000 0.000 0.000 0.000
14 1.000 0.000 0.000 0.000 0.000
D1 1.000 0.000 0.000 0.000 0.000
D4 1.000 0.000 0.000 0.000 0.000
D2 1.000 0.000 0.000 0.000 0.000
D3 1.000 0.000 0.000 0.000 0.000
11 1.000 0.000 0.000 0.000 0.000
12 1.000 0.000 0.000 0.000 0.000
Reboiler in 1.000 0.000 0.000 0.000 0.000
Reboiler out 1.000 0.000 0.000 0.000 0.000
Cleaned Gas 0.000 0.000 0.155 0.845 0.000
CO2 for compression
0.000 1.000 0.000 0.000 0.000
MP CO2 0.000 1.000 0.000 0.000 0.000
MP CO2 liquid
0.000 1.000 0.000 0.000 0.000
HP CO2 liquid
0.000 1.000 0.000 0.000 0.000
SW 1 1.000 0.000 0.000 0.000 0.000
SW 2 1.000 0.000 0.000 0.000 0.000
SW 0 1.000 0.000 0.000 0.000 0.000
SW5 1.000 0.000 0.000 0.000 0.000
LP CO2 0.000 1.000 0.000 0.000 0.000
LP CO2 cooled
0.000 1.000 0.000 0.000 0.000
SW4 1.000 0.000 0.000 0.000 0.000
Cold CO2 for compression
0.000 1.000 0.000 0.000 0.000
SW3 1.000 0.000 0.000 0.000 0.000
Cooler Flue Gas
0.000 0.065 0.145 0.790 0.000
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
19
5.1.4 Summary of Key Results
A summary of the key results from the flowsheet calculation is shown in Table 5.3. In addition,
the composite curves for all the heat exchangers are shown in Appendix E
Table 5.3: A summary of the results from the simulation of the base case.
Object Value
District heating power output 12.0 MW Net electrical power output 9.6 MW Amount of coal needed 60000 ton/year (1.90 kg/s) Thermal efficiency 34.7% Heat needed for CO2-removal 22.6 MW
5.1.5 Steam Temperature
A case study was performed on the model in Aspen HYSYS, which studies the effect of the
temperature of the steam. The thermal efficiency is calculated as:
thermal se ul energy out
se ul energy in
electric district heat
C C (3)
Where thermal is the thermal efficiency, electric is the net electric power produced, district heat is
the power provided to district heating, C is the mass flow of coal and C is the coal’s net
calorific value. In the rest of the report, the thermal efficiency is used exclusively. The results are
shown in Figure 5.2. The steam temperature’s e ect on e iciency is highly dependent on the
boiler design, which can be seen from the composite curves in Figure 5.3.
Figure 5.2: The effect on net power output and thermal efficiency as a function of temperature in the combustion ch amber of the boiler.
0.336
0.338
0.340
0.342
0.344
0.346
0.348
0.350
0.352
0.354
0.356
9.00
9.20
9.40
9.60
9.80
10.00
10.20
500 550 600 650 700 750
Th
erm
al
Eff
icie
ncy
Po
we
r [M
W]
Steam Temperature [
Electrical Power
Base Case ElectricalPowerEfficiency
Base Case Efficiency
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
20
Figure 5.3: Plot o hot and cold composite cur e or the pul erized coal boiler The pinch temperature is set to 10
5.1.6 Steam Cycle Pressure
A case study was performed on the model in Aspen HYSYS, which studies the effect of the
highest pressure in the steam cycle. The results are shown in Figure 5.4.
Figure 5.4: The effect on net power output and thermal efficiency as a function of maximum pressure in the steam cycle.
5.2 Heat Pump Case The heat pump case is modeled in a similar manner as the base case, but without the district
heating network and the split between the LP steam turbine and the IP steam turbine.
0
100
200
300
400
500
600
700
800
0 10 20 30 40 50 60
Te
mp
era
ture
[
Heat transfered [MW]
Cold Composite Curve
Hot Composite Curve
0.336
0.338
0.340
0.342
0.344
0.346
0.348
0.350
0.352
0.354
0.356
9.00
9.20
9.40
9.60
9.80
10.00
10.20
100 120 140 160 180 200 220 240 260 280 300 320 340
Th
erm
al
eff
icic
en
cy
Po
we
r [M
W]
Highest pressure [bar]
Electrical Power
Base Case ElectricalPowerEfficiency
Base Case Efficiency
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
21
5.2.1 Flow Diagram
The process flow diagram from the Aspen HYSYS model is shown in Figure 5.5.
Figure 5.5: The process flow diagram from the Aspen HYSYS model for the heat pump case.
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
22
5.2.2 Stream Data
The important stream data for the different streams in the Aspen HYSYS model are shown in
Table 5.4.
Table 5.4: Stream data for the heat pump case, calculated in Aspen HYSYS.
Stream name Vapor fraction
Temperature ]
Pressure [bar]
Mass flow [kg/s]
Air 1.00 10.00 1.01 70.4
Coal 0.00 10.00 1.00 1.90
Flue gas 1.00 799.99 1.00 72.3
ash 0.00 799.99 1.00 0.00
1 0.00 5.88 0.01 9.09
2 0.00 6.65 165.00 9.09
3 1.00 600.00 165.00 9.09
4 1.00 407.07 49.00 9.09
5 1.00 600.00 49.00 9.09
7 0.90 5.88 0.01 9.09
8 0.00 5.88 0.01 9.09
Flue gas cooled 1.00 60.50 1.00 72.3
Reboiler in 0.00 120.0 1.01 9.93
Reboiler out 1.00 120.0 1.01 9.93
To atmosphere 1.00 60.53 1.00 65.3
CO2 for compression 1.00 60.50 1.00 6.97
LP CO2 1.00 163.23 6.10 6.97
LP CO2 cooled 1.00 10.00 6.10 6.97
MP CO2 1.00 177.95 41.00 6.97
MP CO2 liquid 0.00 6.00 41.00 6.97
HP CO2 liquid 0.00 13.31 100.00 6.97
SW 1 0.00 3.00 1.20 3183
SW 2 0.00 4.50 1.20 3183
SW 0 0.00 3.00 1.00 3183
Cold CO2 for compression
1.00 10.00 1.00 6.97
SW 3 0.00 4.52 1.20 3183
SW 4 0.00 4.60 1.20 3183
SW 5 0.00 4.80 1.20 3183
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
23
5.2.3 Compositions
The composition of each stream from the Aspen HYSYS model is shown in Table 5.5.
Table 5.5: Stream data for the heat pump case, calculated in Aspen HYSYS, where is the mole fraction of component .
Stream name
CO O C
Air 0.000 0.000 0.210 0.790 0.000
Coal 0.000 0.000 0.000 0.000 1.000
Flue gas 0.000 0.065 0.145 0.790 0.000
ash 0.000 0.065 0.145 0.790 0.000
1 1.000 0.000 0.000 0.000 0.000
2 1.000 0.000 0.000 0.000 0.000
3 1.000 0.000 0.000 0.000 0.000
4 1.000 0.000 0.000 0.000 0.000
5 1.000 0.000 0.000 0.000 0.000
7 1.000 0.000 0.000 0.000 0.000
8 1.000 0.000 0.000 0.000 0.000
Flue gas cooled
0.000 0.065 0.145 0.790 0.000
Reboiler in 1.000 0.000 0.000 0.000 0.000
Reboiler out 1.000 0.000 0.000 0.000 0.000
To atmosphere
0.000 0.000 0.155 0.845 0.000
CO2 for compression
0.000 1.000 0.000 0.000 0.000
LP CO2 0.000 1.000 0.000 0.000 0.000
LP CO2 cooled
0.000 1.000 0.000 0.000 0.000
MP CO2 0.000 1.000 0.000 0.000 0.000
MP CO2 liquid
0.000 1.000 0.000 0.000 0.000
HP CO2 liquid
0.000 1.000 0.000 0.000 0.000
SW 1 1.000 0.000 0.000 0.000 0.000
SW 2 1.000 0.000 0.000 0.000 0.000
SW 0 1.000 0.000 0.000 0.000 0.000
Cold CO2 for compression
0.000 1.000 0.000 0.000 0.000
SW 3 1.000 0.000 0.000 0.000 0.000
SW 4 1.000 0.000 0.000 0.000 0.000
SW 5 1.000 0.000 0.000 0.000 0.000
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
24
5.2.4 Summary of Key Results
A summary of the key results from the flowsheet calculation is shown in Table 5.6. In addition,
the composite curves for all the heat exchangers are shown in Appendix E
Table 5.6: A summary of the results from the simulation of the heat pump case. A coefficient of performance of 3 was u sed to obtain these results.
Object Value District heating power output 12.0 MW Net electrical power output 9.4 MW Amount of coal needed 60000 ton/year (1.90 kg/s) Thermal efficiency 34.3% Heat needed for CO2-removal 22.6 MW
5.2.5 Coefficient of performance
The o erall thermal e iciency was calculated or di erent alues o the heat pump’s coe icient
of performance. A plot of the result is shown in Figure 5.6.
Figure 5.6: A plot o o erall thermal e iciency as a unction o the heat pump’s coe icient o per ormance
0.20
0.25
0.30
0.35
0.40
1 2 3 4 5 6 7 8 9 10
Eff
icie
ncy
Coefficient of performance
Efficiency
Base Case Efficiency
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
25
Figure 5.7: An excerpt of Figure 5.6 for comparison with Figure 5.2 and Figure 5.4.
As can be seen, a high coefficient of performance is required to compete with the base case. This
is further addressed in Section 8.2.4.
6 Cost Estimation
6.1 Capital Costs of Major Equipment Cost estimations were performed on major equipment for both the district heating case and the
heat pump case. In this section, only costs for the base case are shown, while detailed cost
estimations for both cases are shown in Appendix A and Appendix B . Cost estimations were also
performed for the base case but without district heating, this is shown in Appendix C .
6.1.1 Pulverized Coal boiler
The pulverized coal (PC) boiler cost was estimated by an order-of-magnitude scaling, using the
following equation [25]:
(
)
(
)
(4)
where is the cost of a plant with capacity , is the cost of a plant with capacity and is
the exponent, which can be assumed to be 0.67 for PC plant boilers [26]. The capacity used for
calculations was electrical power produced in MW, assuming no district heating. By using data
for a PC plant with CO2-capture [8], a cost of 07 00 (on Jan. 2013 basis by using CEPCI
[27]) was obtained. This includes costs for piping, instrumentation and equipment erection. This
0.336
0.338
0.340
0.342
0.344
0.346
0.348
0.350
0.352
0.354
0.356
2.7 2.9 3.1 3.3 3.5 3.7
Eff
icie
ncy
Coefficient of performance
Efficiency
Base Case Efficiency
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
26
cost has some uncertainty, with the original boiler being 50 times larger than the boiler
estimated.
6.1.2 Heat exchangers
The heat exchangers were assumed to be U-tube shell and tube exchangers, with the following
formula and tabulated values from Sinnott [25]:
4 000 4 (5)
where and are cost constants, the capacity parameter is the heat transfer area of the
exchanger in m and is the exponent. To calculate the required area, the overall heat transfer
coefficient was estimated from tables in Sinott [25].For given values of exchanger area,
constants and exponent, the cost of the exchangers were estimated, shown in Table 6.1. Here the
Vacuum Condenser was divided into several exchangers with capacity inside the 1000 m2 limit
of formula (5). The values are on Jan. 2013 basis by using CEPCI [27]. This does not include any
material factors, piping, instrumentation or other cost factors.
Table 6.1: Estimations of heat exchanger costs, this does not include any material factors, piping, instrumentation or other cost factors.
Heat Exchanger U [W/m2K]
Capacity [m2]
Cost [$]
Heat Exchanger for District Heating 1200 105 43 500
Four Vacuum Condensers 1200 4 9 4 977 200
CO2 Cooler 50 313 83 300 Low Pressure CO2 Cooler 100 213 63 100
Intermediate Pressure CO2 Condenser 700 108 43 900
6.1.3 Turbines
The costs of the steam turbines were estimated using the same formula as for the boiler, using
an exponent of 0.67 for steam turbines [26]. The cost of the High Pressure, Intermediate
Pressure and Low Pressure turbines were estimated, and are shown in Table 6.2 on Jan. 2013
basis by using CEPCI [27]. This does not include any material factors, piping, instrumentation or
other cost factors.
Table 6.2: Estimation of turbine cost, this does not include any material factors, piping, instrumentation or other cost f actors.
Turbines Capacity [kW]
Cost [$]
High Pressure Turbine 2991 951 300
Intermediate Pressure Turbine 2097 749 900
Low Pressure Turbine 6785 1 646 900
6.1.4 Compressors
The compressors for CO2-injection were assumed to be centrifugal and estimated from tabulated
values in Sinnott using the following formula, inserted for constants and exponent:
490 000 1 00 (6)
where is the size parameter, here compressor power in . For given values of power,
constants and exponent the cost of Low Pressure CO2 Compressor and Intermediate Pressure
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
27
CO2 Compressor were estimated to be 400 and 1 700, respectively. The values are
on a Jan. 2013 basis by using CEPCI [27], and do not include any material factors, piping or other
cost factors.
6.1.5 Pumps
In similar fashion to compressor estimations, pumps were assumed to be single-stage
centrifugal pumps, with the following formula and tabulated values from Sinnott [25]:
900 0 (7)
where the capacity parameter is liters feed per second. For given values of feed, constants and
exponent, the cost of the pumps were estimated, shown in Table 6.3. The values are on Jan. 2013
basis by using CEPCI [27]. The cost of the Seawater pump has a large uncertainty, due to it being
outside of the interval of Formula (7). This does not include any material factors, piping,
instrumentation or other cost factors.
Table 6.3: Estimations of pump costs, this does not include any material factors, piping, instrumentation or other cost f actors.
Pump Capacity [L s-1]
Cost [$]
High Pressure CO2 Pump 7.8 14 300
Main Water Pump 9.1 14 600
Low Pressure Water Pump 4.8 13 500
District Heat Water Pump 66.2 27 600
Seawater Pump 2501 421 800
6.1.6 Flue Gas Desulfurization
For flue gas desulfurization a wet scrubber was chosen, using wastewater from seawater heat
exchangers. Scaling was performed in a similar manner to that of the boiler for a flue gas wet
desulfurization unit [28]. Using plant produced electricity in MW as a scaling variable, a cost of
9 400 (on Jan. 2013 basis by using CEPCI [27]) was obtained. This includes piping,
instrumentation and other cost factors.
6.1.7 Carbon Capture Facility
Cost of the carbon capture (CC) facility was based on a plant utilizing amine solution technology.
The capital costs of the CC units were estimated as a given percentage of the capital cost of the
PC plant without carbon capture. A conservative estimate may be found in Table 3.2 as 87%.
Hence the capital cost of the CC facility was estimated to be 97 0 000 (on Jan. 2013 basis by
using CEPCI [27]). This includes piping, instrumentation and other cost factors.
6.1.8 Heat Pump Costs
For the heat pump case, heat pump costs were estimated using a cost estimate based on the
thermal output of the heat pump [29]:
14000 OK
district heating (8)
The estimated capital cost of the heat pump is OK 1 000 000, which includes installation and
other cost factors. This cost is not used in the base case.
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
28
6.1.9 Total Equipment Costs
In the total equipment costs, all equipment was modified using the following formula and factors
from Sinnott [25]:
∑ , ,
(1 ) ( ) (9)
where is the total cost of the plant, including engineering costs, , , is purchased cost of
equipment i in carbon steel, is the total number of pieces of equipment, is the installation
factor for piping, is the materical factor for exotic alloys, is the installation factor for
equipment erection, is the installation factor for electrical work, is the installation factor for
instrumentation and process control, is the installation factor for civil engineering work, is
the installation factor for structures and buildings and is the installation factor for lagging,
insulation, and paint. A typical value for the factors combined for a piece of equipment in carbon
steel is 3.2, and 3.7 for 304 stainless steel.
For equipment handling CO2 and seawater, 304 stainless steel was found to be resistant enough
[25], while other pieces of equipment were estimated as carbon steel. To calculate the total fixed
capital cost, , the following formula and factors from Sinnott were used [25]:
(1 O )(1 DE ) (10)
where O is the offsite cost, DE is design and engineering cost and is contingenacy costs. The
total fixed capital costs are summarized in Table 6.4 on U.S. Gulf Coast Jan. 2013 basis.
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
29
Table 6.4: Total estimated equipment costs, with material factors, piping and other cost factors included.
The total equipment cost was calculated from $ U.S. Gulf Coast Jan. 2013 basis into Norwegian
Krone 2013 basis (NOK) [30], yielding NOK 1 977 964 700 as total equipment costs. The
corresponding estimate without a carbon capture facility was estimated as NOK 799 069 800.
For the heat pump case, the total equipment cost was estimated to be NOK 2 798 851 400.
6.2 Variable Costs
6.2.1 Labor
Number of required operators per shift is given by [31]:
( 9 0 ) (11)
where is number of process units at the plant. With 12 process units, it yields 4 operators
per shift.
Equipment Cost [$]
Pulverized Coal Boiler 40 569 200
Heat Exchanger for District Heating 139 200
Vacuum Condenser 3 126 900
CO2 Cooler 306 400
Low Pressure CO2 Cooler 232 300
Intermediate Pressure CO2 Condenser 161 600
Total Exchanger Costs 3 966 500
High Pressure Turbine 3 044 200
Intermediate Pressure Turbine 2 399 700
Low Pressure Turbine 5 270 100
Total Turbine Costs 10 714 000
Low Pressure CO2 Compressor 9 760 700
Intermediate Pressure CO2 Compressor 9 868 800
Total Compressor Costs 19 629 500
High Pressure CO2 Pump 52 500
Main Water Pump 46 800
Low Pressure Water Pump 43 100
District Heat Water Pump 88 300
Seawater Pump 1 552 100
Total Pump Costs 1 782 800
Wet Flue Gas Desulfurization 5 896 400
Carbon Capture Facility 97 900 000
Total Fixed Capital Costs 341 028 400
Total Fixed Capital Costs [NOK] 1 977 964 700
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
30
Table 6.5: Estimation of the labor costs.
Labor
Number of units 20
Number of operators 4
Shifts per day 6
Employed operators 24
Salary per year NOK 433 000
Labor costs per year NOK 10 392 000
6.2.2 Diesel Costs
Diesel is burned to generate power and district heating when the coal plant is down for
maintenance and for peak loads. Yearly diesel costs are shown in Table 6.6.
Table 6.6: Estimated yearly diesel costs [32].
Diesel consumption
Diesel consumption in 2012 [l] 390417
Diesel consumption in 2011 [l] 530287
Diesel consumption in 2010 [l] 72907
Diesel consumption in 2009 [l] 236728
Mean diesel consumption [l] 307585
Price of diesel [NOK/l] NOK 12.00
Diesel costs per year NOK 3 691 000
6.2.3 Cost of Coal
Yearly amount of coal burned was used together with price of coal. The coal price was found by
matching Svalbard quality of coal with similar coal reserves [33]. This is used to calculate yearly
cost of coal, shown in Table 6.7.
Table 6.7: Estimated yearly cost of coal.
Coal consumption
Coal price [$/short ton] 65.5
Coal price [$/ton] 72.2
Coal consumption [ton/year] 60000
Coal costs per year $ 4 332 000
Coal costs per year NOK 25 125 700
6.2.4 Operation and Maintenance
Yearly operation and maintenance costs were calculated using statistical analysis of financial
performance of earlier power plants [34], giving the estimated costs in Table 6.8.
Table 6.8: Estimated yearly costs of operation and maintenance.
Operations and Maintenance costs
O&M [$/kW] 71 electric [kW] 13421.5
Total O&M costs [$/year] $ 952 900
Total O&M costs [NOK/year] NOK 5 527 000
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
31
6.2.5 Chemicals
The estimation of yearly costs for chemicals was obtained by scaling of a PC plant with a carbon
capture facility [8]. The results are summarized in Table 6.9.
Table 6.9: Estimated yearly costs of chemicals. This includes carbon, MEA solvent, lye, corrosion inhibitor, ammonia and other chemicals.
Cost of Chemicals
Chemicals [$/kWh] $ 0.00359 electric [kW] 13421.5
W [kWh] 117572753
Total O&M costs [$/year] $ 422 100
Total O&M costs [NOK/year] NOK 2 448 100
6.2.6 Total Variable Costs
By adding all the variable costs, the total yearly variable cost is estimated to be OK 47 1 00.
6.3 Revenues It is assumed that the price of electricity on Svalbard is 1.00 NOK/kWh, and that the price of
district heating is 0.50 NOK/kWh. The revenue is estimated in Table 6.10.
Table 6.10: Estimated yearly revenues.
Revenue
Price of electricity [NOK/kWh] [35] NOK 1.00
Price of district heating [NOK/kWh] [35] NOK 0.50
Total amount of electricity per year [kWh] 84 034 680
Total amount of district heating per year [kWh] 105 120 000
Revenue from electricity NOK 84 034 700
Revenue from district heating NOK 52 560 000
Total yearly revenue NOK 136 594 700
6.4 Working Capital The working capital was estimated as the cost of 60 days of raw material (coal and chemicals)
for production and 2% of the total fixed investment cost (for spare parts), as recommended by
NETL [8]. This estimation results in a working capital of NOK 40 673 800.
7 Investment Analysis The investment analysis was done by estimating net present value (NPV) and internal rate of
return (IRR) for each of the two cases (heat pump versus district heating). NPV was estimated
using the following formula [25]:
P FC ∑
(1 )
(12)
where is the cash flow in year , is the project life in years and is the interest rate in
percent/100. The IRR was calculated by setting equation (12) equal to zero, and solving for .
7.1 Base Case Figure 7.1 shows the estimated NPV as a function of years after investment, using the estimated
capital cost, variable costs, revenues and working capital: It has been assumed constant yearly
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
32
costs, a constant depreciation rate of 10%, a constant 20% amount depreciation and 0% tax on
Svalbard.
Figure 7.1: A plot showing the base case’s net present value as a function of years after investment with and without carbon capture and storage.
The IRR of the base case project was calculated to be 3.8% with carbon capture, and 11.1%
without carbon capture.
7.2 Heat Pump Case Figure 7.2 shows the estimated NPV as a function of years after investment using the estimated
capital cost, variable costs, revenues and working capital: It has been assumed constant yearly
costs, a constant depreciation rate of 10%, a constant 20% amount depreciation and 0% tax on
Svalbard.
-2500
-1500
-500
500
1500
2500
3500
4500
-1 2 5 8 11 14 17 20 23 26 29 32 35 38 41 44 47 50
Ne
t P
rese
nt
Va
lue
[M
NO
K]
Years after investment
Without Carbon Capture
With Carbon Capture
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
33
Figure 7.2: A plot showing the heat pump case’s net present alue as a unction o years a ter in estment
The IRR of the project was calculated to be 1.9%.
The IRR was also estimated for a case where no district heating is produced, and yielded an IRR
of 2.2% (which assumes that all the consumers will have to obtain their own heat pumps, or
some other form of heating).
8 Discussion
8.1 Plant Choices Many considerations have to be done regarding choice of plant. Weighing the high efficiency of
Integrated Gasification Combined Cycle (IGCC) plants against the in-development Chemical
Looping (CL) plants with simple carbon capture and storage (CCS) opportunities, or the already
conventional pulverized coal (PC) plant. Choice of steam cycle is also important, as number of
turbines and pressure levels highly affect the efficiency. Lastly, flue gas treatment has to be
discussed, where the different options are available at different prices.
8.1.1 Plant Type
While IGCC and CL plants were considered in the beginning, they were found unsuitable for the
planned project at Svalbard. These plants take advantage of size, as the air separation unit (ASU)
and catalyzed reactors come at a large capital and variable cost. If, however, the plant is large
enough, the ASU and reactor can repay themselves many-fold with the increased efficiency of the
plant [8]. Both options also put strains on equipment, especially so with pre-combustion
capture, where high purity hydrogen is combusted inside the turbine, yielding high
temperatures. Using a gas turbine for combined cycle puts a lot of strain on gas treatment, as the
turbines are sensitive to sulfur and carbon dioxide contents.
-3000
-2500
-2000
-1500
-1000
-500
500
1000
1500
-1 2 5 8 11 14 17 20 23 26 29 32 35 38 41 44 47 50
Net
Pre
sen
t V
alu
e [M
NO
K]
Years after investment
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
34
With its remote location, a power plant at Svalbard can easily find itself for long periods of time
without spare parts, making well-developed technology the preferred choice. Instead of in-
development technology, state of the art conventional technology was found to be the best fit. PC
plants fit this choice well, as the idea of burning coal to yield steam is over 200 years old [36]. In
a PC plant, the same principle applies, but the coal is pulverized into coal dust that burns more
efficiently. In Appendix E composite curves for the boiler are shown, proving that the design is
within the constraints of utilizable energy.
Steam turbine technology is well developed for PC plants, no gas turbine or reactor is required,
and air is blown into the boiler, without need for compression or cryogenic distillation. All of
these factors help keep the capital and variable costs low, giving a better investment perspective.
8.1.2 Steam Cycle
The current plant has a steam cycle design with two turbines, one of which is a condensing
turbine, and the other is a backpressure turbine used to produce district heating. The proposed
design has an extra turbine because they have a much higher steam pressure, as the current
technology has a maximum allowable pressure drop. It also permits for reheating in between
pressure levels which increases the efficiency [8]. A higher steam pressure also improves the
overall efficiency, which is evident in Figure 5.4.
The efficiency may be further improved by allowing a higher maximum pressure, but due to
support limitations on Svalbard, a more robust design was chosen. A higher steam temperature
may also have a positive effect, as can be seen in Figure 5.2.
8.1.3 Flue Gas Treatment
The plant has to be within Norwegian emission regulations, putting requirements on the dust
particles, sulfur, mercury and carbon dioxide output of the plant. As Svalbard already has plans
for a Flue Gas Desulfurization unit (FGD) using seawater, a seawater scrubber was used in the
design. A seawater scrubber is cheaper; both in capital cost, as the scrubber itself is cheap, and in
variable costs as seawater is considered to be free [21]. A seawater scrubber would also deal
with the mercury [23] and dust particles [8], which is harder to achieve using a dry scrubber
[21]. Alternatively an electrostatic filter could be used to remove dust particles and mercury
derivatives.
Svalbard also takes part in a project [37], aiming at a CO2-free Svalbard by 2025, which requires
the plant to have carbon dioxide capture and storage. As geological formations for storage exist
in close vicinity of Longyearbyen, the plan is feasible. At atmospheric pressure, amine solution is
preferred for capture, but puts further strain on the capital costs, as well as using heat from the
boiler as re-boiler duty. During economic evaluation, CSS capital costs were estimated as a worst
case scenario from Table 3.2, to be as much as 87% of the PC plant itself, with an electric power
penalty of up to 29%.
8.2 Case Studies
8.2.1 Base Case
In the base case, it is assumed that the current district heating network on Svalbard can be used,
which will reduce the capital cost significantly. District heating has the advantage of yielding
high overall plant efficiency, because most of this heat is not feasible for production of electrical
power. The current power plant was calculated, by Equation (4), to have an efficiency of 48.3%
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
35
(including diesel generators). The proposed design has an efficiency of 34.8%, which is quite
high considering that it includes carbon capture.
8.2.2 Steam Temperature
A case study was performed on the model in Aspen HYSYS, yielding results which point towards
a correlation that higher steam temperatures yield a higher power generation, and consequently
a higher thermal efficiency. These results apply only for the power plant modeled, and may vary
with varying steam cycles, boiler choices and plant size. Temperature considerations will have to
be done, as the higher temperature will lead to higher heat exchanger area in the boiler and
increased corrosion of the steam turbines [8]. Safety of the employees is also of concern, and risk
analysis is important for choosing a desired design.
8.2.3 Steam Cycle Pressure
A case study was performed on the model in Aspen HYSYS, yielding results which point towards
a correlation that higher pressure in the steam cycle gives a higher power generation, and
consequently a higher thermal efficiency. These results apply only for the power plant modeled,
and may vary with varying steam cycles, boiler choices and plant size. For the plant to use
supercritical and ultra-supercritical pressure, equipment and safety considerations will have to
be done. The increased capital cost from materials and complexity will have to be assessed. This
is especially true as ultra-supercritical steam generation is still under development, and not
available commercially [8]. It is still possible to build a pilot plant, but this will require a lot of
expertise and support, which might not be suitable at a remote location such as Svalbard.
8.2.4 Heat Pump Case
In the heat pump case, a central heat pump at the plant was considered. The heat pump would
provide hot water for the district heat network, and obtaining heat from the ocean. However,
since Svalbard has a cold climate, a seawater heat pump would not be viable. Nevertheless, this
option could become sustainable if geothermal heat is used instead of seawater. The efficiency of
the design with seawater as the heat source is calculated to be 34.3% which is lower than the
base case. In Figure 5.6, the efficiency is plotted against the coefficient of performance, and it is
apparent that even a high performance heat pump would yield rather low efficiency. Although,
higher than the base case with a sufficiently effective heat pump.
8.3 Investments
8.3.1 Cost estimations
In cost estimation of the PC boiler, it was assumed that capacity scaling was sufficient, as no
price for a boiler in the right capacity range was found. The boiler used for scaling was almost 50
times larger, which results in a high uncertainty. The steam turbine costs were estimated in an
equivalent manner, but with the scaling capacity much closer to the estimated steam turbine
capacities. The FGD and heat pump costs were also estimated using the aforementioned method,
and were assumed to moderately accurate, being inside a given capacity range.
Heat exchanger, compressor and pump costs were estimated using a slightly more accurate
method, as described earlier. However, the seawater pump were larger than the stated interval,
hence its cost estimation will be somewhat inaccurate.
The cost of the carbon capture facility was estimated as 87% of the total capital cost of the whole
plant (without carbon capture), the worst case scenario from Table 3.2. This estimate might be
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
36
too large, as there is a lot of ongoing research into improving the cost of carbon capture by
amine absorption.
The total fixed capital cost of the plant was calculated the factorial method presented earlier.
The factors were obtained from Sinnott [25], and might have some degree of uncertainty as the
expenses will be higher on a remote location such as Svalbard.
The cost of labor was estimated from the number of units on the plant. Only operators were
considered, and all other cost for other personnel (administrative, maintenance etc.) are not
included. This is fairly inaccurate, and the total labor cost will probably be higher.
The usage of diesel was assumed to be constant, which might be wrong as the new plant may
experience some difficulties during startup which will increase the need for backup power, and
consequently diesel.
It is assumed that the coal have to be bought at a relatively high price because the net calorific
value of the coal on Svalbard is high.
The cost of chemicals was estimated by scaling chemical requirements from a PC plant with CO2
capture, and might have some uncertainty associated with it, due to the fact that the plant used
for scaling is 50 times larger.
For the estimation of revenues it is assumed that the plant is operating at maximum capacity and
that all the electricity and heating produced will be bought by the consumers. This assumption is
inaccurate, as the electricity needed at Svalbard will not automatically double as soon as the new
plant is installed.
The working capital is estimated as 60 days of coal supply, and 2% of the total plant cost for
spare part etc. The National Energy Technology Laboratory recommends that only 0.5% of the
total plant cost is needed for spare parts, however, Svalbard is a remote location and it was
consequently assumed that it will need four times the amount of spare parts.
8.3.2 Investment analyses
The net present value (NPV) was estimated by assuming that the yearly expenses and revenues
are constant throughout the whole lifetime of the project. This is incorrect, but yields a good
indication o the project’s alue or comparing to other projects In Figure 7.1 and Figure 7.2 it is
evident that the base case has a larger NPV than the heat pump case, and will therefore be a
better investment. In Figure 7.1, the NPV for the base case without district heating is shown, and
it has a much higher NPV than the base case. This indicates that CCS is the economic bottleneck,
and it might be worthwhile to wait for more efficient technology to become readily available.
The base case has a higher internal rate of return than the heat pump case, which is also an
indication that it is the better investment. When it is assumed that the consumers obtain their
heat by some other form than district heating, a higher IRR is obtained, but this is still lower
than the base case. However, both cases have a huge NPV in the 50 year horizon-perspective,
and if a sufficiently efficient heat pump is developed, it may be worth the extra investment.
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
37
9 Conclusion and Recommendations A pulverized coal (PC) plant was found to be the best fit for a new power plant on Svalbard. The
technology is commercially available, and no research and development is required. Oxygen-
fired combustion is a lucrative option, as the carbon capture is more efficient, but it will have to
be developed further before being implemented at a secluded location as Svalbard.
A maximum boiler temperature of 00 was assumed, together with subcritical pressure in the
steam cycle. It is recommended to do further studies, as it was shown that increased
temperature and pressure gives higher efficiency. Supercritical pressures are already
conventional, but a plant at Svalbard needs to consider its isolated location. The boiler has been
greatly simplified; hence further studies are needed for obtaining actual combustion
temperature and heat exchanging possibilities.
District heating from a backpressure steam turbine was found to be a better option than a
central heat pump, both practically and economically. Even if consumers obtain their own heat
pumps, the base case is preferable.
Carbon capture and storage (CCS) is also a field largely in development. Price of equipment is
expected to fall, and efficiency is expected to rise. CCS is the bottleneck in both economical and
efficiency-wise for the power plant, and was studied further in another project.
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
38
References
[1] Heat Pump & Thermal Storage Technology Center of Japan, "Data Book on Heat Pump &
Thermal Storage Systems 2011-2012," HPTCJ, 2011.
[2] H. Termuehlen and W. Emsperger, Clean and Efficient Coal-Fired Power Plants, New York:
ASME Press, 2003, pp. 1-2.
[3] International Energy Agency, "Key World Energy Statistics," 2013. [Online]. Available:
http://www.iea.org/publications/freepublications/publication/KeyWorld2013_FINAL_WEB.p
df. [Accessed 18 October 2013].
[4] International Energy Agency, "Medium-Term Coal Market Report 2012," IEA Publications,
Paris, 2012.
[5] Intergovernmental Panel on Climate Change, "Climate Change 2013: The Physical Science Basis:
Headline Statements from the Summary for Policymakers," 27 September 2013. [Online].
Available: http://www.ipcc.ch/news_and_events/docs/ar5/ar5_wg1_headlines.pdf. [Accessed
19 October 2013].
[6] Clean Air Technology Center, "Nitrogen Oxides (NOx), Why and How They Are Controlled,"
United States Environmental Protection Agency, Durham, 1999.
[7] J. U. Watts, A. N. Mann and D. L. Russel Sr., "An Overview of NOx Control Technologies
Demonstrated under the Department o Energy’s Clean Coal Technology Program," National
Energy Technology Laboratory, Pittsburg, 2000.
[8] National Energy Technology Laboratory, "Cost and Performance Baseline for Fossil Energy
Plants," Pittsburgh, 2013.
[9] O. Maurstad, "An Overview of Coal Based Integrated Gasification Combined Cycle (IGCC)
Technology," Cambridge, 2005.
[10] B. J. P. Buhre, L. K. Elliott, C. D. Sheng, R. P. Gupta and T. F. Wall, "Oxy-fuel combustion
technology for coal-fired power generation," Progress in Energy and Combustion Science, vol.
31, no. 4, pp. 283-307, 2005.
[11] Y. Oki, J. Inumaru, S. Hara, M. Kobayashi, H. Watanabe, S. Umemoto and H. Makino,
"Development of oxy-fuel IGCC system with CO2 recirculation for CO2 capture," Energy
Procedia, vol. 4, pp. 1066-1073, 2011.
[12] International Energy Agency, "CO2 Capture and Storage," OECD, 2008.
[13] D. Berstad, R. Anantharaman and P. Nekså, "Low-temperature CO2 capture technologies -
Applications and potential," International Journal of Refrigeration, vol. 36, no. 5, pp. 1403-1416,
2013.
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
39
[14] H. Zhai and E. S. Rubin, "Membrane-based CO2 Capture Systems for Coal-fired Power Plants,"
National Energy Technology Laboratory, Pittsburgh, 2012.
[15] M. Blunt, "Carbon Dioxide Storage," Imperial College of London, London, 2010.
[16] E. S. Rubin, C. Chen and A. B. Rao, "Cost and Performance of Fossil Fuel Power Plants with CO2
Capture and Storage," Energy Policy, vol. 35, no. 9, pp. 4444-4454, 2007.
[17] E. S. Rubin and A. B. Rao, "A Technical, Economic and Environmental Assessment of Amine-
Based CO2 Capture Technology for Power Plant Greenhouse Gas Control," Environmental
Science & Technology, vol. 36, no. 20, pp. 4467-4475, 2002.
[18] G. T. Rochelle, "Amine Scrubbing for CO2 Capture," Science, vol. 325, no. 5948, pp. 1652-1654,
25 September 2009.
[19] R. K. Varagani, F. Châtel-Pélage, P. Pranda, M. Rostam-Abadi, Y. Lu and A. C. Bose, "Performance
Simulation and Cost Assessment of Oxy-Combustion Process for CO2 Capture from Coal-Fired
Power Plants," in Fourth Annual Conference on Carbon Sequestration, Alexandria, 2005.
[20] E. S. Rubin, C. Chen and A. B. Rao, "Comparative Assessment of Fossil Fuel Power Plants with
CO2 Capture and Storage," in Proceedings of 7th Internation Conference on Greenhouse Gas
Control Technologies, Vancouver, 2005.
[21] R. K. Srivastava, J. Wojciech and C. Singer, "SO2 Scrubbing Technologies: A Review,"
Environmental Progress, vol. 20, no. 4, pp. 219-228, December 2001.
[22] H. Kettner, "The Removal of Sulfur Dioxide from Flue Gases," Bulletin of The World Health
Organization, vol. 32, no. 3, p. 421, 1965.
[23] C. E. Miller, T. J. Feeley, III, W. W. Aljoe, B. W. Lani, K. T. Schroeder, C. Kairies, A. T. McNemar, A.
P. Jones and J. T. Murphy, "Mercury Capture and Fate Using Wet FGD at Coal-Fired Power
Plants," U.S. Department of Energy, Pittsburgh, 2006.
[24] Power Technology, "Power Technology - A future for coal power," [Online]. Available:
http://www.power-technology.com/. [Accessed 17 November 2013].
[25] R. Sinnott and G. Towler, Chemical Engineering Design, 5th ed., Burlington, Massachusetts:
Elsevier, 2009, pp. 301, 313, 819, 1101.
[26] M. Sciazko and T. Chmielniak, "Chapter 10: Cost Estimates of Coal Gasification for Chemicals
and Motor Fuels," in Gasification for Practical Applications, 2012, p. 263.
[27] Chemical Engineering, "Economic Indicators," Chemical Engineering, pp. 71-72, April 2013.
[28] U.S. Enviromental Protection Agency, "Air Pollution Control Technology Fact Sheet," U.S.
Enviromental Protection Agency, 2002.
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
40
[29] The International Renewable Energy Agency, "Heat Pumps: Technology Brief," IRENA, 2013.
[30] XE Currency, "USD/NOK-kart," November 2013. [Online]. Available:
http://www.xe.com/currencycharts/?from=USD&to=NOK&view=1Y. [Accessed November
2013].
[31] R. Turton, R. C. Bailie, W. B. Whiting and J. A. Shaewitz, Analysis, Synthesis and Design for
Chemical Processes, 2nd ed., Hamilton in Castleton, New York: Prentice Hall, 2002, p. 193.
[32] Norsk Petroleumsinstitutt, "Statistikk," 24 June 2013. [Online]. Available:
http://www.np.no/priser/. [Accessed 10 November 2013].
[33] U.S. Energy Information Administration, "Coal News and Markets Report," 4 November 2013.
[Online]. Available: http://www.eia.gov/coal/news_markets/. [Accessed 10 November 2013].
[34] L. Giorgio and M. Mauro, "Small–medium sized nuclear coal and gas power plant: A
probabilistic analysis of their financial performances and influence of CO2 cost," Energy Policy,
p. 6360–6374, 2010.
[35] R. Blomstrand, Interviewee, Longyearbyen Board Member. [Interview]. 28 10 2013.
[36] H. Termuehlen and W. Emsperger, Clean and Efficient Coal-Fired Power Plants: Development
Toward Advanced Technologies, 1st ed., New York, New York: The American Society of
Mechanical Engineers, 2003, pp. 5-25.
[37] Nordic Network for Sustainable Energy Systems in Isolated Locations, "NordSESIL.net," 2006.
[Online]. Available: http://nordsesil.wikispaces.com/CO2+free+Svalbard+by+2025.
[Accessed 16 November 2013].
[38] F. Holland, F. Watson and J. Wilkinson, Perry's Handbook, 6th ed., New York: McGraw Hill,,
1984.
[39] Statistisk Sentralbyrå, "Earnings in electricity supply," 14 March 2013. [Online]. Available:
http://www.ssb.no/en/arbeid-og-lonn/statistikker/lonnkraft/aar/2013-03-14. [Accessed 9
November 2013].
[40] U.S. Department Of Labor, "Consumer Price Index," October 30 2013. [Online]. Available:
ftp://ftp.bls.gov/pub/special.requests/cpi/cpiai.txt. [Accessed 9 November 2013].
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
41
List of symbols and abbreviations Symbol Unit Description ASU Air Separation Unit $ Constant for Cost Estimation Constant for Cost Estimation $ Cost , , $ Purchased Cost of Equipment in Carbon Steel $ Total Fixed Capital Cost $ Cost of Plant with Capacity $ Cost of Plant with Capacity CC Carbon Capture CCS Carbon Capture and Storage CEPCI Chemical Engineering Plant Cost Index CL Chemical Looping COP Cost of Electricity DE $ Design and Engineering Cost FGD Flue Gas Desulfurization FGT Flue Gas Treatment Installation Factor for Civil Engineering Work Installation Factor for Electrical Work Installation Factor for Equipment Erection Installation Factor for Instrumentation and Process Control Installation Factor for Lagging, Insulation and Paint Installation Factor for Exotic Alloys Installation Factor for Piping Installation Factor for Structures and Buildings HEX Heat Exchanger HRSG Heat Recovery System Generator HP High Pressure IGCC Integrated Gasification Combined Cycle IP Intermediate Pressure IRR Internal Rate of Return LP Low Pressure Total Number of Pieces of Equipment MEA Monoethanolamine C g s Mass flow of Coal Number of Operators
Number of Units NCV cal g Net Colorific Value NGCC Natural Gas Combined Cycle NOK Norwegian Krone P MNOK Net Present Value Exponent Factor for Order of Magnitude OECD Organization for Economic Co-operation and Development O $ Offsite Costs O&M Operation and Maintenance Cost PC Pulverized Coal district heat MW Power provided to District Heating Capacity of Plant with Cost Capacity of Plant with Cost sC Subcritical SC Supercritical
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
42
Symbol Unit Description SCR Selective Catalytic Reduction U m K Overall Heat Transfer Coefficient electric MW Net Electric Power Produced X $ Contingency Cost i Mole Fraction of Component thermal Thermal Efficiency
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
A-1
Appendix A - Cost estimation for the base case
A.1 Cost of major equipment
The cost estimation of the major equipment is shown in Table A.1.
Table A.1: Cost estimation of the major equipment.
Boiler C2 = C1(S2/S1)^0.67*(I2/I1)
S2 [MW] 13.42154714
C1 $ 339 189 000.00
S1 [MW] 550
I2 630.2
I1 525.4
Capital Cost of Boiler $ 33 807 637.06
HP Turbine C2 = C1(S2/S1)^0.67*(I2/I1)
S2 [MW] 2.990730163
C1 $ 834 000.00
S1 [MW] 3
I2 657.7
I1 575.4
Capital Cost of HP Turbine $ 951 313.24
IP Turbine C2 = C1(S2/S1)^0.67*(I2/I1)
S2 [MW] 2.096839296
C1 $ 834 000.00
S1 [MW] 3
I2 657.7
I1 575.4
Capital Cost of IP Turbine $ 749 896.70
LP Turbine C2 = C1(S2/S1)^0.67*(I2/I1)
S2 [MW] 6.784556249
C1 $ 834 000.00
S1 [MW] 3
I2 657.7
I1 575.4
Capital Cost of LP Turbine $ 1 646 918.71
District Heat Exchanger (24000+46*A^1.2)*(I2/I1)
UA [W/K] 126061.1955
U [W/m2 K] 1200
A [m2] 105.0509963
I2 630.2
I1 525.4
Capital Cost of District Heat Exchanger $ 43 490.90
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
A-2
CO2 Cooler (24000+46*A^1.2)*(I2/I1)
UA [W/K] 15645.45174
U [W/m2 K] 50
A [m2] 312.9090347
I2 630.2
I1 525.4
Capital Cost of CO2 Cooler $ 83 268.56
Vacuum Condensers (24000+46*A^1.2)*(I2/I1)
UA [W/K] 4724201.521
U [W/m2 K] 1200
A [m2] 3936.834601
Number of condensers 4
A per condenser [m2] 984.2086503
I2 630.2
I1 525.4
Capital Cost per Condenser $ 244 288.95
Capital Cost of Vacuum Condensers $ 977 155.79
LP CO2 Cooler (24000+46*A^1.2)*(I2/I1)
UA [W/K] 21301.19111
U [W/m2 K] 100
A [m2] 213.0119111
I2 630.2
I1 525.4
Capital Cost of LP CO2 Cooler $ 63 129.62
IP CO2 Cooler (24000+46*A^1.2)*(I2/I1)
UA [W/K] 75330.38298
U [W/m2 K] 700
A [m2] 107.6148328
I2 630.2
I1 525.4
Capital Cost of IP CO2 Cooler $ 43 922.57
LP CO2 Compressor (490000+16800*P^0.6)*(I2/I1)
P [kW] 960.7527304
I2 913.9
I1 525.4
Capital Cost of LP CO2 Compressor $ 2 652 375.18
IP CO2 Compressor (490000+16800*P^0.6)*(I2/I1)
P [kW] 987.014704
I2 913.9
I1 525.4
Capital Cost of IP CO2 Compressor $ 2 681 738.22
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
A-3
HP CO2 Pump (6900+206*V^0.9)*(I2/I1)
q [l/s ] 7.801010982
I2 913.9
I1 525.4
Capital Cost of HP CO2 Pump $ 14 278.32
Main Water Pump (6900+206*V^0.9)*(I2/I1)
q [l/s ] 9.116187496
I2 913.9
I1 525.4
Capital Cost of Main Water Pump $ 14 620.95
LP Water Pump (6900+206*V^0.9)*(I2/I1)
q [l/s ] 4.768238621
I2 913.9
I1 525.4
Capital Cost of LP Water Pump $ 13 463.61
District Heat Water Pump (6900+206*V^0.9)*(I2/I1)
q [l/s ] 66.18057501
I2 913.9
I1 525.4
Capital Cost of District Heat Water Pump $ 27 595.24
Seawater Pump (6900+206*V^0.9)*(I2/I1)
qtot [l/s ] 2500.640907
I2 913.9
I1 525.4
Capital Cost of Seawater Pump $ 421 755.00
Flue Gas Desulfurization C*P*(I2/I1)
P [kW] 13421.54714
C [$/kW] 250
I2 692.9
I1 394.3
Capital Cost of Flue Gas Desulfurization $ 5 896 392.35
CO2 Removal C = x*C1*(I2/I1)
Capital Cost Without Carbon Capture [$] $ 156 035 250.47
Percent Increase with Carbon Capture 87 %
I2 499.6
I1 692.9
Capital Cost of CO2 Removal $ 97 879 973.57
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
A-4
Installation factors
Equipment erection factor, fer 0.5
Piping factor, fp 0.6
Instrumentation and Control factor, f i 0.3
Electrical factor, fel 0.2
Civil factor, fc 0.3
Structures and Building factor, fs 0.2
Lagging and Paint factor, fl 0.1
Material, fm: Carbon steel 1
Material, fm: Stainless steal 1.3
Boiler 1.2
HP Turbine 3.2
IP Turbine 3.2
LP Turbine 3.2
District Heat Exchanger 3.2
Vacuum Condenser 3.2
CO2 Cooler 3.68
LP CO2 Cooler 3.68
IP CO2 Cooler 3.68
LP CO2 Compressor 3.68
IP CO2 Compressor 3.68
HP CO2 Pump 3.68
Main Water Pump 3.2
LP Water Pump 3.2
District Heat Water Pump 3.2
Seawater Pump 3.68
Flue Gas Desulfurization 1
CO2 Removal 1
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
A-5
Installed Capital Costs
Boiler $ 40 569 164.47
HP Turbine $ 3 044 202.35
IP Turbine $ 2 399 669.44
LP Turbine $ 5 270 139.88
District Heat Exchanger $ 139 170.88
Vacuum Condenser $ 3 126 898.52
CO2 Cooler $ 306 428.31
LP CO2 Cooler $ 232 317.02
IP CO2 Cooler $ 161 635.05
LP CO2 Compressor $ 9 760 740.66
IP CO2 Compressor $ 9 868 796.65
HP CO2 Pump $ 52 544.21
Main Water Pump $ 46 787.03
LP Water Pump $ 43 083.55
District Heat Water Pump $ 88 304.78
Seawater Pump $ 1 552 058.42
Flue Gas Desulfurization $ 5 896 392.35
Offsites 0.4
Design and Engineering 0.25
Contingency 0.1
Total fixed capital cost (without CO2 removal) $ 156 035 250.47
NOK 905 004 452.10
Total fixed capital cost (with CO2 removal) $ 341 028 400.52
NOK 1 977 964 723.00
A.2 Variable costs
The estimation of the variable costs is shown in Table A.2.
Table A.2: Estimation of the variable costs.
Labor
Number of units 20
Number of operators 4
Shifts per day 6
Employed operators 24
Salary per year NOK 433 000.00
Labor costs per year NOK 10 392 000.00
Diesel consumption
Diesel consumption in 2012 [l] 390417
Diesel consumption in 2011 [l] 530287
Diesel consumption in 2010 [l] 72907
Diesel consumption in 2009 [l] 236728
Mean diesel consumption [l] 307584.75
Price of diesel [NOK/l] NOK 12.00
Diesel costs per year NOK 3 691 017.00
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
A-6
Coal consumption
Coal price [$/short ton] 65.5
Coal price [$/ton] 72.20017637
Coal consumption [ton/year] 60000
Coal costs per year $ 4 332 010.58
Coal costs per year NOK 25 125 661.38
Operations and Maintenance costs
O&M [$/kW] 71
P [kW] 13421.54714
Total O&M costs [$/year] $ 952 929.85
Total O&M costs [NOK/year] NOK 5 526 993.11
Cost of Chemicals
Chemicals [$/kWh] $ 0.00359
P [kW] 13421.5
W [kWh] 117572753
Total O&M costs [$/year] $ 422 086.18
Total O&M costs [NOK/year] NOK 2 448 099.86
Total
Total variable costs [$/year] NOK 47 183 771.35
A.3 Revenues
The estimation of the yearly revenue is shown in Table A.3.
Table A.3: Estimation of the yearly revenue.
Revenue
Price of electricity [NOK/kWh] NOK 1.00
Price of district heating [NOK/kWh] NOK 0.50
Total amount of electricity [kWh] 84034680
Total amount of district heating [kWh] 105120000
Revenue from electricity NOK 84 034 680.00
Revenue from district heating NOK 52 560 000.00
Total revenue NOK 136 594 680.00
A.4 Working capital
The estimation of the working capital is shown in Table A.4.
Table A.4: The estimation of the working capital.
Working capital
Value of raw materials in inventory (60 days) NOK 1 114 538.70
Spare parts (2 % of total plant cost) NOK 39 849 181.64
Total Working Capital NOK 40 963 720.34
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
B-1
Appendix B - Cost estimation for the heat pump case
B.1 Major Equipment
The cost estimation of the major equipment is shown in Table B.1.
Table B.1: Cost estimation of the major equipment.
Boiler C2 = C1(S2/S1)^0.67*(I2/I1)
S2 [MW] 13.42154714
C1 $ 339 189 000.00
S1 [MW] 550
I2 630.2
I1 525.4
Capital Cost of Boiler $ 33 807 637.06
HP Turbine C2 = C1(S2/S1)^0.67*(I2/I1)
S2 [MW] 2.99386541
C1 $ 834 000.00
S1 [MW] 3
I2 657.7
I1 575.4
Capital Cost of HP Turbine $ 951 981.30
IP Turbine C2 = C1(S2/S1)^0.67*(I2/I1)
S2 [MW] 0
C1 $ 834 000.00
S1 [MW] 3
I2 657.7
I1 575.4
Capital Cost of IP Turbine $ -
LP Turbine C2 = C1(S2/S1)^0.67*(I2/I1)
S2 [MW] 12.65709666
C1 $ 834 000.00
S1 [MW] 3
I2 657.7
I1 575.4
Capital Cost of LP Turbine $ 2 501 016.97
District Heat Exchanger (24000+46*A^1.2)*(I2/I1)
UA [W/K] 0
U [W/m2 K] 1200
A [m2] 0
I2 630.2
I1 525.4
Capital Cost of District Heat Exchanger $ -
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
B-2
Vacuum Condensers (24000+46*A^1.2)*(I2/I1)
UA [W/K] 12261753.54
U [W/m2 K] 1200
A [m2] 10218.12795
Number of condensers 10
A per condenser [m2] 1021.812795
I2 630.2
I1 525.4
Capital Cost per condenser $ 254 206.86
Capital Cost of Vacuum Condensers $ 2 542 068.57
CO2 Cooler (24000+46*A^1.2)*(I2/I1)
UA [W/K] 14777.81911
U [W/m2 K] 50
A [m2] 295.5563823
I2 630.2
I1 525.4
Capital Cost of CO2 Cooler $ 79 663.40
LP CO2 Cooler (24000+46*A^1.2)*(I2/I1)
UA [W/K] 22420.49441
U [W/m2 K] 100
A [m2] 224.2049441
I2 630.2
I1 525.4
Capital Cost of LP CO2 Cooler $ 65 306.34
IP CO2 Cooler (24000+46*A^1.2)*(I2/I1)
UA [W/K] 88258.8128
U [W/m2 K] 700
A [m2] 126.0840183
I2 630.2
I1 525.4
Capital Cost of IP CO2 Cooler $ 47 090.88
LP CO2 Compressor (490000+16800*P^0.6)*(I2/I1)
P [kW] 960.7527304
I2 913.9
I1 525.4
Capital Cost of LP CO2 Compressor $ 2 652 375.18
IP CO2 Compressor (490000+16800*P^0.6)*(I2/I1)
P [kW] 960.7527304
I2 913.9
I1 525.4
Capital Cost of IP CO2 Compressor $ 2 652 375.18
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
B-3
HP CO2 Pump (6900+206*V^0.9)*(I2/I1)
q [l/s ] 7.801010982
I2 913.9
I1 525.4
Capital Cost of HP CO2 Pump $ 14 278.32
Main Water Pump (6900+206*V^0.9)*(I2/I1)
q [l/s ] 8.895505456
I2 913.9
I1 525.4
Capital Cost of Main Water Pump $ 14 563.82
LP Water Pump (6900+206*V^0.9)*(I2/I1)
q [l/s ] 0
I2 913.9
I1 525.4
Capital Cost of LP Water Pump $ -
District Heat Water Pump (6900+206*V^0.9)*(I2/I1)
q [l/s ] 0
I2 913.9
I1 525.4
Capital Cost of District Heat Water Pump $ -
Seawater Pump (6900+206*V^0.9)*(I2/I1)
qtot [l/s ] 3109.246726
I2 913.9
I1 525.4
Capital Cost of Seawater Pump $ 510 502.50
Flue Gas Desulfurization C*P*(I2/I1)
P [kW] 13421.54714
C [$/kW] 250
I2 692.9
I1 394.3
Capital Cost of Flue Gas Desulfurization $ 5 896 392.35
CO2 Removal C = x*C1*(I2/I1)
Capital Cost Without Carbon Capture [$] $ 220 792 351.45
Percent Increase with Carbon Capture 87 %
I2 499.6
I1 692.9
Capital Cost of CO2 Removal $ 138 501 713.29
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
B-4
Central heat pump
Cost per kW [NOK/kW] NOK 14 000.00
Heat provided [kW] 12000
Capital Cost of Central heat pump NOK 168 000 000.00
Installation factors
Equipment erection factor, fer 0.5
Piping factor, fp 0.6
Instrumentation and Control factor, fi 0.3
Electrical factor, fel 0.2
Civil factor, fc 0.3
Structures and Building factor, fs 0.2
Lagging and Paint factor, fl 0.1
Material, fm: Carbon steel 1
Material, fm: Stainless steal 1.3
Boiler 1.2
HP Turbine 3.2
IP Turbine 3.2
LP Turbine 3.2
District Heat Exchanger 3.2
Vacuum Condenser 3.2
CO2 Cooler 3.68
LP CO2 Cooler 3.68
IP CO2 Cooler 3.68
LP CO2 Compressor 3.68
IP CO2 Compressor 3.68
HP CO2 Pump 3.68
Main Water Pump 3.2
LP Water Pump 3.2
District Heat Water Pump 3.2
Seawater Pump 3.68
Flue Gas Desulfurization 1
CO2 Removal 1
Heat Pump 1
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
B-5
Installed Capital Costs
Boiler $ 40 569 164.47
HP Turbine $ 3 046 340.16
IP Turbine $ -
LP Turbine $ 8 003 254.32
District Heat Exchanger $ -
Vacuum Condenser $ 8 134 619.43
CO2 Cooler $ 293 161.31
LP CO2 Cooler $ 240 327.32
IP CO2 Cooler $ 173 294.44
LP CO2 Compressor $ 9 760 740.66
IP CO2 Compressor $ 9 760 740.66
HP CO2 Pump $ 52 544.21
Main Water Pump $ 46 604.22
LP Water Pump $ -
District Heat Water Pump $ -
Seawater Pump $ 1 878 649.18
Flue Gas Desulfurization $ 5 896 392.35
Heat Pump $ 28 965 517.24
Offsites 0.4
Design and Engineering 0.25
Contingency 0.1
Total fixed capital cost (without CO2 removal) $ 220 792 351.45
NOK 1 280 595 638.40
Total fixed capital cost (with CO2 removal) $ 482 560 589.57
NOK 2 798 851 419.53
B.2 Variable Costs
The estimation of the variable costs is shown in Table B.2.
Table B.2: Estimation of the variable costs
Labor
Number of units 18
Number of operators 4
Shifts per day 6
Employed operators 24
Salary per year NOK 433 000.00
Labor costs per year NOK 10 392 000.00
Diesel consumption
Diesel consumption in 2012 [l] 390417
Diesel consumption in 2011 [l] 530287
Diesel consumption in 2010 [l] 72907
Diesel consumption in 2009 [l] 236728
Mean diesel consumption [l] 307584.75
Price of diesel [NOK/l] NOK 12.00
Diesel costs per year NOK 3 691 017.00
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
B-6
Coal consumption
Coal price [$/short ton] 65.5
Coal price [$/ton] 72.20017637
Coal consumption [ton/year] 60000
Coal costs per year $ 4 332 010.58
Coal costs per year NOK 25 125 661.38
Operations and Maintenance costs
O&M [$/kW] 71
P [kW] 13421.54714
Total O&M costs [$/year] $ 952 929.85
Total O&M costs [NOK/year] NOK 5 526 993.11
Cost of Chemicals
Chemicals [$/kWh] $ 0.00359
P [kW] 13421.5
W [kWh] 117572753
Total O&M costs [$/year] $ 422 086.18
Total O&M costs [NOK/year] NOK 2 448 099.86
Total
Total variable costs [NOK/year] NOK 47 183 771.35
B.3 Revenues
The estimation of the yearly revenue is shown in Table B.3.
Table B.3: Estimation of the yearly revenue.
Revenue
Price of electricity [NOK/kWh] NOK 1.00
Price of district heating [NOK/kWh] NOK 0.50
Total amount of electricity [kWh] 117412204
Total amount of district heating [kWh] 105120000
Heat pump COP 3
Electricity needed for heat pump 35040000
Available electricity 82372204
Revenue from electricity NOK 82 372 204.19
Revenue from district heating NOK 52 560 000.00
Total revenue NOK 134 932 204.19
B.4 Working Capital
The estimation of the working capital is shown in Table B.4.
Table B.4: Estimation of the working capital
Working capital
Value of raw materials in inventory (60 days) NOK 1 114 538.70
Spare parts (2 % of total plant cost) NOK 55 977 028.39
Total Working Capital NOK 57 091 567.09
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
C-1
Appendix C - Cost estimation for the base case without carbon capture
C.1 Cost of major equipment
The cost estimation of the major equipment is shown in Table C.1.
Table C.1: Cost estimation of the major equipment.
Boiler C2 = C1(S2/S1)^0.67*(I2/I1)
S2 [MW] 13.42154714
C1 $ 339 189 000.00
S1 [MW] 550
I2 630.2
I1 525.4
Capital Cost of Boiler $ 33 807 637.06
HP Turbine C2 = C1(S2/S1)^0.67*(I2/I1)
S2 [MW] 5.02153665
C1 $ 834 000.00
S1 [MW] 3
I2 657.7
I1 575.4
Capital Cost of HP Turbine $1 346 211.64
IP Turbine C2 = C1(S2/S1)^0.67*(I2/I1)
S2 [MW] 2.096839296
C1 $ 834 000.00
S1 [MW] 3
I2 657.7
I1 575.4
Capital Cost of IP Turbine $ 749 896.70
LP Turbine C2 = C1(S2/S1)^0.67*(I2/I1)
S2 [MW] 15.3701151285023
C1 $ 834 000.00
S1 [MW] 3
I2 657.7
I1 575.4
Capital Cost of LP Turbine $ 2 848 567.17
District Heat Exchanger (24000+46*A^1.2)*(I2/I1)
UA [W/K] 126061.1955
U [W/m2 K] 1200
A [m2] 105.0509963
I2 630.2
I1 525.4
Capital Cost of District Heat Exchanger $ 43 490.90
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
C-2
Vacuum Condensers (24000+46*A^1.2)*(I2/I1)
UA [W/K] 10702471.7025945
U [W/m2 K] 1200
A [m2] 8918.726419
Number of condensers 9
A per condenser [m2] 990.9696021
I2 630.2
I1 525.4
Capital Cost per Condenser $ 246 066.61
Capital Cost of Vacuum Condensers $ 2 214 599.52
Main Water Pump (6900+206*V^0.9)*(I2/I1)
q [l/s ] 15.13710685
I2 913.9
I1 525.4
Capital Cost of Main Water Pump $ 16 138.04
LP Water Pump (6900+206*V^0.9)*(I2/I1)
q [l/s ] 10.8022358
I2 913.9
I1 525.4
Capital Cost of LP Water Pump $ 15 053.08
District Heat Water Pump (6900+206*V^0.9)*(I2/I1)
q [l/s ] 66.18057501
I2 913.9
I1 525.4
Capital Cost of District Heat Water Pump $ 27 595.24
Seawater Pump (6900+206*V^0.9)*(I2/I1)
qtot [l/s ] 5665.09248
I2 913.9
I1 525.4
Capital Cost of Seawater Pump $ 867 388.10
Flue Gas Desulfurization C*P*(I2/I1)
P [kW] 13421.54714
C [$/kW] 250
I2 692.9
I1 394.3
Capital Cost of Flue Gas Desulfurization $ 5 896 392.35
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
C-3
Installation factors
Equipment erection factor, fer 0.5
Piping factor, fp 0.6
Instrumentation and Control factor, fi 0.3
Electrical factor, fel 0.2
Civil factor, fc 0.3
Structures and Building factor, fs 0.2
Lagging and Paint factor, fl 0.1
Material, fm: Carbon steel 1
Material, fm: Stainless steal 1.3
Boiler 1.2
HP Turbine 3.2
IP Turbine 3.2
LP Turbine 3.2
District Heat Exchanger 3.2
Vacuum Condenser 3.2
Main Water Pump 3.2
LP Water Pump 3.2
District Heat Water Pump 3.2
Seawater Pump 3.68
Flue Gas Desulfurization 1
Installed Capital Costs
Boiler $ 40 569 164.47
HP Turbine $ 4 307 887.24
IP Turbine $ 2 399 669.44
LP Turbine $ 9 115 414.95
District Heat Exchanger $ 139 170.88
Vacuum Condenser $ 7 086 718.48
Main Water Pump $ 51 641.72
LP Water Pump $ 48 169.87
District Heat Water Pump $ 88 304.78
Seawater Pump $ 3 191 988.22
Flue Gas Desulfurization $ 5 896 392.35
Offsites 0.4
Design and Engineering 0.25
Contingency 0.1
Total fixed capital cost (without CO2 removal) $ 137 770 641.27
NOK 799 069 719.38
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
C-4
C.2 Variable Costs
The estimation of the variable costs is shown in Table C.2.
Table C.2: Estimation of the variable costs
Labor
Number of units 10
Number of operators 3
Shifts per day 6
Employed operators 18
Salary per year NOK 433 000.00
Labor costs per year NOK 7 794 000.00
Diesel consumption
Diesel consumption in 2012 [l] 390417
Diesel consumption in 2011 [l] 530287
Diesel consumption in 2010 [l] 72907
Diesel consumption in 2009 [l] 236728
Mean diesel consumption [l] 307584.75
Price of diesel [NOK/l] NOK 12.00
Diesel costs per year NOK 3 691 017.00
Coal consumption
Coal price [$/short ton] 65.5
Coal price [$/ton] 72.20017637
Coal consumption [ton/year] 31000
Coal costs per year $ 2 238 205.47
Coal costs per year NOK 12 981 591.71
Operations and Maintenance costs
O&M [$/kW] 71
P [kW] 13421.54714
Total O&M costs [$/year] $ 952 929.85
Total O&M costs [NOK/year] NOK 5 526 993.11
Cost of Chemicals
Chemicals [$/kWh] $ 0.00359
P [kW] 13421.5
W [kWh] 117572753
Total O&M costs [$/year] $ 422 086.18
Total O&M costs [NOK/year] NOK 2 448 099.86
Total
Total variable costs [NOK/year] NOK 32 441 701.69
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
C-5
C.3 Revenues
The estimation of the yearly revenue is shown in Table C.3.
Table C.3: Estimation of the yearly revenue.
Revenue
Price of electricity [NOK/kWh] NOK 1.00
Price of district heating [NOK/kWh] NOK 0.50
Total amount of electricity [kWh] 83771908.33
Total amount of district heating [kWh] 105120000
Heat pump COP 3
Electricity needed for heat pump 35040000
Available electricity 82372204
Revenue from electricity NOK 83 771 908.33
Revenue from district heating NOK 52 560 000.00
Total revenue NOK 136 331 908.33
C.4 Working Capital
The estimation of the working capital is shown in Table C.4.
Table C.4: Estimation of the working capital
Working capital
Value of raw materials in inventory (60 days) NOK 770 351.56
Spare parts (2 % of total plant cost) NOK 15 981 394.39
Total Working Capital NOK 16 751 745.95
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
D-1
Appendix D Net Calorific Value of the Coal on Svalbard The net calorific value and contents of the coal are shown in Figure D.1.
Figure D.1: Analysis of the coal on Svalbard, received from Jørn Myrlund at Longyear Energiverk.
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
E-1
Appendix E – Composite Curves
E.1 Boiler
The hot and cold composite curves of the pulverized coal boiler in the base case are shown in
Figure E.1.
Figure E.1: Plot of hot and cold composite curve for the pulverized coal boiler. The pinch temperature is set to 10
E.2 District Heat Exchanger
The hot and cold composite curve of the district heat exchanger in the base case are shown in
Figure E.2.
Figure E.2: Plot of hot and cold composite curve for the district heat exchanger.
0
100
200
300
400
500
600
700
800
0 10 20 30 40 50 60
Te
mp
era
ture
[
Heat [MW]
Cold Composite Curve
Hot Composite Curve
0
50
100
150
200
250
300
350
400
0 1 2 3 4 5 6 7 8 9 10 11 12
Te
mp
era
ture
[
Heat [MW]
Cold Composite Curve
Hot Composite Curve
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
E-2
E.3 Vacuum Condenser
The hot and cold composite curves of the vacuum condenser in the base case are shown in
Figure E.3.
Figure E.3: Plot of hot and cold composite curve for the condenser.
E.4 CO2 Cooler
The hot and cold composite curves of the CO -Cooler in the base case are shown in Figure E.4.
Figure E.4: Plot of hot and cold composite curve for the CO -Cooler.
0
1
2
3
4
5
6
7
0 1 2 3 4 5 6 7 8 9 10 11 12
Te
mp
era
ture
[
Heat [MW]
Cold Composite Curve
Hot Composite Curve
0
10
20
30
40
50
60
70
80
90
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45
Te
mp
era
ture
[
Heat [MW]
Cold Composite Curve
Hot Composite Curve
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
E-3
E.5 LP CO2-Cooler
The hot and cold composite curves of the LP CO -Cooler in the base case are shown in Figure
E.5.
Figure E.5: Plot of hot and cold composite curve for the LP CO -Cooler.
E.6 IP CO2-Cooler
The hot and cold composite curves of the LP CO -Cooler in the base case are shown in Figure
E.6.
Figure E.6: Plot of hot and cold composite curve for the LP CO -Cooler.
0
20
40
60
80
100
120
140
160
180
0 0.2 0.4 0.6 0.8 1 1.2
Te
mp
era
ture
[
Heat [MW]
Cold Composite Curve
Hot Composite Curve
0
20
40
60
80
100
120
140
160
180
200
0 0.5 1 1.5 2 2.5 3 3.5
Te
mp
era
ture
[
Heat [MW]
Cold Composite Curve
Hot Composite Curve
TKP4170 Considerations for a New Coal-Fired Power Plant on Svalbard
F-1
Appendix F – Aspen HYSYS Flowsheets
F.1 Base Case
Figure F.1: A larger image of the Aspen HYSYS flowsheet.