time management 641 topic 03 activity sequencing
TRANSCRIPT
TIME MANAGEMENT 641
Topic 03
Activity Sequencing
• Assemble project scope, historical data, WBS
and identify constraints & assumptions;
• Create an Activity List, document supporting
detail and update WBS;
SUMMARY TO DATE
TIME MANAGEMENT PROCESS
• Definition of activities;
• Sequencing of activities;
• Estimating duration of activities;
• Schedule development;
• Monitor and control of schedule;
2. - ACTIVTY SEQUENCING
• Armed with the Activity Definitions we can move
onto the Activity Sequencing Phase of the
process:
Step 2 - Activity Sequencing
• Identifies and documents activities’
dependencies upon each other.
Activity Sequencing
• performed on paper or computer software;
• purpose is logical planning only;
• an understanding is achieved through a manual
process - remember the software is only a tool;
• manual process is useful where little detail exists
or for small projects;
Activity Sequencing - Inputs
EXERCISE No. 3
• Activity Sequencing is step 2 in the process of
Time Management and again requires certain
inputs and outputs.
• Attempt to identify those Inputs are.
Activity Sequencing - Inputs
• Activity List;
• Constraints & Assumptions;
• Product Description;
• Mandatory Dependencies;
• Discretionary Dependencies;
• External Dependencies;
Activity List:
• This is the activity list is derived from the first phase of the process.
Constraints & Assumptions:
• These are the Constraints & Assumptions derived from the first phase of the process.
Activity Sequencing - Inputs
Product Description:
• documents characteristics of the project;
• in construction this is normally contained within drawings, specifications and related documentation;
• project characteristics determine the actions e.g layout of a gold mine;
• effects may be apparent through activity list but should be confirmed at this point for accuracy;
Activity Sequencing - Inputs
Dependencies:
• a dependency is reliance by one activity on
another:
• activities or parts of activities cannot be done until
another activity or part of activity is done;
• requires asking “which activities depend on others
for completion?”
• in a dependency the first activity is a predecessor
followed by a successor;
Activity Sequencing - Inputs
Mandatory Dependencies:
• a Mandatory Dependency is one inherent to the
construction method or sequence;
• they usually involve physical limitations - eg brick
wall cannot be started until footings are placed
and cured;
• mandatory dependencies are referred to as
“Hard Logic”;
Activity Sequencing - Inputs
Discretionary Dependencies:
• referred to as “Soft Logic”;
• these dependencies are defined by the team;
• must be documented - no rules to govern them;
• must be used carefully - may restrict you later;
• are usually based on project manager’s
discretion based on “Best Practices” or available
alternatives;
Activity Sequencing - Inputs
External Dependencies:
• are factors outside the project that affect activity
sequencing of activities e.g. outcome of
Environmental Impact Studies prior to project
commencing;
Activity Sequencing - Inputs
Activity Sequencing - Inputs
The logic of a dependency occurs in 1 of 4 ways:
1 Finish to Start - predecessor must finish before
successor can start e.g. place reinforcement
before concrete pour;
2 Start to Start - predecessor must start before
successor can start e.g. site clearance before
topsoil removal;
Activity Sequencing - Inputs
3 Finish to Finish - predecessor must finish before
successor finishes, similar to Start - Start eg site
clearance must finish before topsoil removal can
finish;
4 Start to Finish - predecessor must start before
successor finishes eg electrical cable installation
must start before a pump installation can be
finished;
Activity Sequencing - Inputs
• finish-to-start is most common type of logic;
• start-to-finish rarely used, only by professional
scheduling engineers;
• start-to-start, finish-to-finish, or start-to-finish
relationships with project management software
can produce unexpected results since they are
not consistently implemented.
Activity Sequencing - Inputs
“LAG”:
• Lag is an appreciation of activity relationships;
• Site Clearance & Topsoil with a Start - Start
dependency is typical;
• lags are similar to discretionary dependencies;
• they are subjective and must be fully
documented and substantiated;
Activity Sequencing - Tools
• We have now identified our activities through the
WBS and Activity Definition Process:
• We should now be able to determine their
relationship and use a diagramming tool to
display them.
Activity Sequencing - Tools
EXERCISE No. 4
• The noise wall activities were identified through
the WBS and Activity Definition Process:
• We should now be able to determine their logical
relationship and use a diagramming tool to
display them. Nominate, for each activity, what
it’s predecessor is.
1.01 Contract Award
2.01 Site Preparation
2.02 Excavate Footings
3.01 Order/Deliver Bricks
3.02 Order/Deliver Concrete
4.01 Pour footings (S/C)
4.02 Concrete curing
4.03 Erect walls
4.04 Hang gate
5.01 Practical Completion
Activity ListPredecessor
-
1.01
2.01
1.01
1.01
2.02 & 3.02
4.01
4.02
4.03
4.04
Diagrammatic Representation
There are two principal ways of showing this
information:
• Network Diagrams;
• Bar “Gantt” Charts;
Gantt charts are part of Schedule Development.
Statistical Programming Techniques:
• for use in sophisticated programming situations
only;
• known as PERT and GERT;
• Program (Graphical) Evaluation & Review
Techniques;
• rely on probability analysis of activity durations
and likelihood of achieving them;
Diagrammatic Representation
Network Diagrams;
• organisation of activities and relationships in a
diagrammatic form;
• highlights important relationships;
• allows analysis and review;
• is most common form in software packages;
• known as activity on node;
Diagrammatic Representation
Network Diagrams;
Diagrammatic Representation
Repair Walls
Buy Paint & Grout
Sand & Clean
Remove Grout
Paint Walls
Regrout
Install Fittings
EXERCISE No. 5
• Prepare a Network Diagram (activity on node) for
the brick security wall as per the actvity list
developed.
Diagrammatic Representation
Security Wall Network Diagram
Diagrammatic Representation
Award
Site Prep
Order Concrete
Excavate
Order Bricks
Pour Concrete
Erect Walls
Hang Gate
Curing
PC
Diagrammatic Representation
• network diagrams show paths & dependence
of activities;
• demonstrates how delay in one affects a
successor;
• ultimately after further development it helps
define the CRITICAL PATH;
• this is the path of activities that take the
longest time to complete;
• this is the path where a delay in an activity will
delay the project by the same amount;
• it also shows the path where time can be saved
because acceleration of those activities will lead
to earlier completion;
• the network diagram is consequently an
important communication tool for discussion with
project participants.
Diagrammatic Representation
Our outputs for the Activity Sequencing step are:
• Network Diagram
• Updated Activity List
Activity Sequencing - Outputs
Network Diagram:
• schematic display of project activities and
relationships;
• produced manually or by computer;
• maybe detailed by summary or detail activities;
• provide a narrative summary to accompany
diagram;
• is NOT a PERT or GERT;
Activity Sequencing - Outputs
Updated Activity List:
• similar to WBS update during Activity Definition;
• sequencing phase identifies activities not
previously listed or detailed;
• list is updated to accommodate new or redefined
activities;
Activity Sequencing - Outputs
• Assemble project scope, historical data, WBS
and identify constraints & assumptions;
• Create an Activity List, document supporting
detail and update WBS;
• Identify logic and relationships between activities
to develop into a network diagram;
• Evaluate & analyse network - refine where
possible;
SUMMARY TO DATE
TIME MANAGEMENT PROCESS
• Definition of activities;
• Sequencing of activities;
• Estimating duration of activities;
• Schedule development;
• Monitor and control of schedule;