time and work 2 sessions
TRANSCRIPT
Agenda 2 Sessions
Time and Work
• Assumptions
•Man Days Concept
•Unit Work
•Work Units – Collaboration
•Alternative Working
•Efficiencies
•Negative Work
• Pipes & Cisterns
Assumptions – T&W
Every person does the same amount of work!
Every day the same amount of work is done!
1. 10 men can do complete a work in 15 days. How many men are
required to complete the same work in 10 days?
2. 7 men working 8 hours a day can do a piece of work in 15 days.
How long will 21 men working 10 hrs a day take to finish the same
piece of work?
(1) 6 days (2) 9 days (3) 8 days (4) 4 days
3. 4 boys or 6 girls can do a piece of work in 18 days. How long will 2
boys and 9 girls take to complete the same piece of work?
(1) 12 days (2) 6 days (3) 9 days (4) 15 days
4. 8 men and 15 women can do some work in 6 days. 15 men and 18
women can do the same work in 4 days. How long would 3 men and 9
women take to complete the same work?
(1) 6 days (2) 12 days (3) 24days (4) 18 days
5. Vijay and Sujay can complete a piece of work in 40 and 50 days
respectively. If they complete the work together and get paid Rs 1,800
then what is Vijay’s share?
(1) Rs 800 (2) Rs 1,000 (3) Rs 900 (4) Rs 850
6. Sita can do a piece of work in 20 days and Gita can do the same
work in 30 days. How long will they take to complete the work if they
are working together?
(1) 12 days (2) 15 days (3) 20 days (4) 16 days
7. A can do a piece of work in 20 days and B can do the same piece
of work in 30 days. If A and B work on alternate days starting from A,
In how many days would the work get completed.
(1) 20 days (2) 60 days (3) 24 days (4) 36 days
8. A can do a piece of work in 8 days and B can do the same piece of
work in 10 days. If A and B work on alternate days starting from A, In
how many days would the work get completed.
(1) 4 (4/9) days (2) 8 (8/9) days (3) 8 (4/5) days (4) 9 days
9. A can do a piece of work in 8 days and B can do the same piece of
work in 10 days. If A and B work on alternate days starting from B, In
how many days would the work get completed.
(1) 4 (4/9) days (2) 8 (8/9) days (3) 8 (4/5) days (4) 9 days
10. Praveen and Biju can do a piece work together in 24 days. They
start the work together and Praveen quits after 16 days. Biju
completes the remaining work in 20 days. How long would it take for
Praveen alone to complete the work?
(1) 40 days (2) 60 days (3) 30 days (4) 36 days
11. Anu and Bhanu working together can finish a job in D days,
whereas if Anu is working alone she will take D+60 days to finish the
job, and if Bhanu is working alone she will take D+15 days to do the
same. What is the value of D?
(1) 75 (2) 60 (3) 30 (4) 45
12. Arun and Barun together can do a piece work in 24 days. Barun
and Karun together can do the same work in 40 days and Arun and
Karun take 30 days to complete the same work working together. How
long will Arun alone take to complete the work?
(1) 30 days (2) 40 days (3) 50 days (4) 36 days
13. Alok and Bimal can do a piece of work together in 24 days. Bimal
and Chandra can do the same work together in 30 days. Alok started
the work alone and quit after 8 days. Then, Bimal took up the work
and worked for 18 days after which he had to quit. Finally Chandra
completed the remaining work alone in 30 days. How long would
Chandra have taken to complete the work alone?
(1) 40 days (2) 36 days (3) 60 days (4) 54 days
14. Chetan and Chandan can complete a piece of work in 20 days
and 30 days respectively. Both work for 10 days and quit after which
Chintan completes the work in 8 more days. If they together get paid
Rs 3,600 find the share of Chintan?
(1) Rs 600 (2) Rs 1,000 (3) Rs 900 (4) Rs 800
Efficiency ConceptIf A can do a piece of work in 10 days and B can do the same work in 15
days , then Efficiency of A is greater than B !
If A can do a piece of work in 60 days at 100% efficiency.
Then,
at 50% efficiency he will take 120 days.
at 75% efficiency he will take 80 days
at 125% efficiency he will take 48 days
Efficiency ConceptA can do a piece of work in 20 days (say). And let’s say that you are given
efficiencies of 50%, 75%, 125% type of questions , then
You can assume that a can do Per Day, A can do say 4 units of work
at 50% efficiency he will do 2 units of work per day
at 75% efficiency he will take 3 units of work per day
at 125% efficiency he will take 5 units of work per day!
15. Akhil, Bhanu and Chandu can do a piece of work in 24, 30 and 40
days respectively. They start the work together and work for 5 days
after which Akhil quits the job and Bhanu develops a fever which
reduces his efficiency by a half. How many more days will be required
to complete the work?
(1) 20 days (2) 14 days (3) 12 days (4) 16 days
16. Rita can do some work alone at 75% efficiency in 40 days. Mita
can do the same work in 40 days if she works at 125% efficiency. Find
the time taken to complete the work if both Rita and Mita work
together at 100% efficiency.
(1) 18.125 days (2) 18.25 days (3) 18.5 days (4) 18.75 days
17. 20 men can complete building a bridge in 15 days. However
due to an illness, 10% of the men lost 10% of their efficiency, 20%
men lost 20% of their efficiency and 30% men lost 30% of their
efficiency. How much time will the bridge take to be completed?
(1) 17.24 days (2) 17.34 days (3) 17.44 days (4) 17.54 days
Let each man do 10 units per day. 20 men, 200 units per day.
Total work required to be done : 3000 units
2 men – 90 % efficiency – 9 units per day = 18 units
4 men - 80 % efficiency - 8 units per day = 32 units
6 men - 70 % efficiency - 7 units per day = 42 units
8 men - 100% efficiency - 10 units per day = 80 units
Total units per day : 172 units , Hence 3000/172 = 17.44 days!
18. Pipe A can fill a cistern in 20 mins and pipe B can fill the same
cistern in 30 mins. How long will it take to feel the cistern If both the
pipes are opened simultaneously?
(1) 15 mins (2) 25 mins (3) 12 mins (4) 10 mins
19. Tap A and tap B take 10 and 15 minutes respectively to fill a tank.
Both taps were opened together along with an emptying tap C. If the
Tank is full in 9 min, then how long will it take the emptying tap take to
empty the full Tank?
(1) 18 min (2) 25 min (3) 12 min (4) 16 min
20. A pipe can fill a tank in 10 hours. Because of the leak at the
bottom, it took 20 hours to fill the tank. In how many hours can the
leak empty a full tank?
(1) 20 hrs (2) 36hrs (3) 60 hrs (4) 30 hrs
21. Tap A can fill a tank in 20 mins and tap B can empty it in 30 mins.
Both were opened simultaneously and after some time tap B was
closed. If the tank was filled in 30 min, then what is the duration for
which tap B was open?
(1) 18 min (2) 25 min (3) 15 min (4) 20 min
22. A tank has 5 inlet pipes each of which can fill the tank in 6 hours
and 2 outlet pipes each of which can empty a full tank in 4 hours. If all
the pipes are open, how long does it take for the tank to be full?(CAT
1999)
(1) 90min (2) 120 min (3) 150 min (4) 180 min
23. A system of pipes is so designed that the capacity of the nth pipe is
equal the sum of the capacities of 1 to n-1 pipes. If P8 can fill a tank in
128 min, then how long will P11 take to fill the same tank?
(CAT 1999)
(1) 10 min (2) 4min (3) 16 min (4) 8 min
24. In a leather factory, bags and sandals are machine made.
Machine A can produce 20 bags every hour. It needs to be shut down
every 5 hours for 15 minutes. Machine B can produce 20 pairs of
sandals every hour. It needs to be shut down every 6 hours for 20
minutes. Find the number of products made in 7 days if the factory
works day and night.(count one pair of sandals as one product)?
(CAT 2004)
(1) 6360 (2) 6380 (3) 6400 (4) 6420
25. A chemical plant has four tanks (A, B, C and D), each containing
1000 litres of a chemical. The chemical is being pumped from one
tank to another as follows:
From A to B @ 20 litres/minute
From C to A @ 90 litres/minute
From A to D @ 10 litres/minute
From C to D @ 50 litres/minute
From B to C @ 100 litres/minute
From D to B @ 110 litres/minute
Which tank gets emptied first, and how long does it take (in minutes)
to get empty after pumping starts? (CAT 2005)
(1) A, 16.66 (2) C, 20 (3) D, 20 (4) D, 25