the university of hong kong librariesebook.lib.hku.hk/hkg/b3584145x.pdf · draft code of practice...
TRANSCRIPT
THE UNIVERSITY OF HONG KONGLIBRARIES
This book was receivedin accordance with the Books
Registration OrdinanceSection 4
DRAFT CODE OF PRACTICE
FOR
SITE SAFETY SUPERVISION
December 1997
BOOKS REGISTRATION ORDINANCEChapter 142
No.: HK 98393S FT
FOREWORD
In order to improve safety on or adjacent to private construction anddemolition sites in Hong Kong, a new site safety supervision plan system is introduced.This calls for the submission of a supervision plan prior to or at the time of application forconsent to commence works.
The Technical Memorandum for Supervision Plans (the TechnicalMemorandum) issued under section 39A of the Buildings Ordinance sets out the principles,requirements and operation of supervision plans, whereas detailed guidance on theapplication of the Technical Memorandum and the preparation of supervision plans are tobe provided in the Code of Practice for Site Safety Supervision (the Code).
The Code is now issued as a draft document. It will be replaced by afinalized edition when it has been reviewed through experience gained in its application.
Any enquiries or comments on the Code may be directed to the ChiefOfficer/Site Monitoring of the Buildings Department at 12/F - 18/F, Pioneer Centre, 750Nathan Road, Kowloon, Hong Kong.
December 1997Buildings Department
Contents
1 Background 1-2
2 Application and Scope 2
3 Interpretation 3
4 General Principles 3 -5
5 Management and Responsibilities 5-53
6 Assessment of Degree of Complexity 54 - 82
7 Supervision Requirements 83-100
8 Additional Safety Supervision Requirements 101 -107
9 Communication and Reports 108-110
10 Minor Deviations from a Supervision Plan 111-112
1 Background
1.1 In order to improve safety on or adjacent to private building construction
sites in Hong Kong, the Buildings (Amendment) Ordinance 1996 was
enacted. This Ordinance requires, inter alia, the preparation and adherence
to a new form of document called a supervision plan.
1.2 The supervision plan as defined in Section 2 (1) of the Buildings Ordinance
sets out a system for safety management of building works or street works.
It is to be lodged by an authorized person with the Building Authority:-
(a) prior to or at the time of application for consent to the
commencement of building works or street works; or
(b) as a result of carrying out urgent works.
1.3 The supervision plan, is to be put into operation by qualified and
experienced professional and technical personnel i.e. Technically
Competent Persons.
1.4 Safety management of building works and street works addresses two types
of supervision:
(a) Quality Supervision
This means ensuring that the building works or street works are
carried out in general accordance with the provisions of the Buildings
Ordinance and Regulations and with the plans approved in respect of
them by the Building Authority and with any order made or condition
imposed, pursuant to any provision of the Ordinance or regulations in
that behalf, by the Building Authority; and
(b) Site Safety Supervision
This means controlling hazards from building works and street works
so as to minimise the risk to :
(i) the workers on site;
(ii) all persons around the sites; and
(iii) adjoining buildings, structures and land.
1.5 The Technical Memorandum for Supervision Plan (Technical
Memorandum) sets out the principles of management for supervision, the
framework for managing site safety supervision and for the format of
supervision plans.
2 Application and Scope
2.1 This Code of Practice provides detailed guidance to the practitioners on the
application of the Technical Memorandum, addressing specifically the
following so as to assist the practitioners in the preparation of the
supervision plan:
(a) safety management structure;
(b) assessment of complexity of types of building works and street
works;
(c) safety supervision requirements; and
(d) communication and reporting requirements.
2.2 This Code of Practice is to be read in conjunction with the Technical
Memorandum. In implementing the requirements of the supervision plan,
reference should also be made to the Buildings Ordinance, the Building
Regulations, Practice Notes for Authorized Persons and Registered
Structural Engineers (PNAPs), Practice Notes for Registered Contractors
(PNRCs) and any other relevant documents issued by the Building
Authority.
2.3 In considering method statements, precautionary and protective measures,
practitioners are encouraged to consider not only the minimum standards
referred to in this Code of Practice but to consider prevalent standards and
improved measures, if relevant and practicable.
3
Unless specified otherwise, the terms and expressions used in this Code of
Practice have the same meaning as has been assigned under the Buildings
Ordinance and the Building Regulations. Any additional terms and
expressions used in this Code of Practice are explained in the text of this
Code or defined in the Technical Memorandum.
4 General Principles
Underlying Principles
4.1 The Technical Memorandum sets out the underlying principles of safety
management and the following major aspects of the supervision system:
(a) the framework and purpose of the site safety management system;
(b) the roles and responsibilities of the parties concerned;
(c) the two types of site safety supervision - routine safety supervision
and engineering safety supervision;
(d) the employment of Technically Competent Persons; and
(e) the preparation of supervision plans.
4.2 This Code of Practice explains:
(a) how to establish the degree of complexity of various types of works;
(b) how to approach method statements, precautionary and protective
measures;
(c) how to establish the class of supervision;
(d) how TCPs may best be deployed and how their duties may be
combined;
(e) the management structure within each functional stream and the
responsibilities for communication; and
(f) the specific tasks of TCPs in carrying out safety supervision.
Basic Principles for Assessing Safety Supervision Requirements
4.3 In principle, the total supervision requirements (SRT) for a particular type of
building works or street works is a function of scale (S), difficulty (D) and
risk (R), such that:
SRT = f,(S) x f2(D,R)
where:
• fj is a modifier which makes allowance for the scale of the building
works or street works;
• f2 measures the complexity of the building works or street works;
• complexity is a combination of difficulty (D) and risk (R);
4.4 The information used to assess scale, difficulty and risk (in the form of
input parameters) is measured independently for each parameter.
4.5 Both the complexity f2(D, R) and the supervision requirements SRT will be
assessed in discrete steps.
Phased Implementation
4.6 The Technical Memorandum and Code of Practice set out the qualifications
and experience of TCPs and the frequency of their site inspections. These
overall requirements will be introduced progressively on an incremental
basis over a transition period.
4.7 The length of the transition period, and the incremental arrangements will
be determined by the Building Authority and published from time to time in
the Practice Notes for Authorized Persons and Registered Structural
Engineers (PNAPs) and the Practice Notes for Registered Contractors
(PNRCs).
4.8 After the standards .set out in the Technical Memorandum and Code of
Practice have been fully attained, the Building Authority will review and
may upgrade the'required qualifications and experience of the TCPs and the
frequency of their site inspections in order to further improve the standard
of supervision, after taking into consideration the supply of TCPs, the
prevailing state of construction technology and method.
5 Management and Responsibilities
5.1 This section sets out the responsibilities of each TCP and other personnel in
the site safety management structure. This includes listing of individual
responsibilities and references to tables of specific tasks. Guidance is given
on the division of responsibility for temporary works between the
Contractor and RSE.
Chain of Responsibility
5.2 The AP, RSE and RGBC/RSC are at the head of the organizational
structure and have overall responsibility and accountability for their
respective functional streams. They will each appoint a Representative who
is the highest grade TCP within their respective supervision streams and
who is required to take the senior role in the site safety management
structure. In the chain of responsibility, therefore, the appointed
Representatives are accountable to the AP, RSE or RGBC/RSC (in the last
case through the Authorized Signatory [AS]). All other site safety
management personnel are accountable to the appointed Representative of
their respective streams.
5.3 Under normal circumstances with a full site staff complement the general
responsibilities of TCPs are as follows.
TCP Grade General Responsibilities
Tl Check on a routine basis that the work on site complies with
general site safety requirements and that the general site
safety aspects of building works or street works are properly
carried out.
T2 Check that identified specialist aspects of site work comply
with safety requirements.
T3 Monitor the activities of subordinate TCPs to ensure that
routine checks are being carried out at the frequency set out
in this Code of Practice and that reports and records are
properly prepared and filed.
T4 Check that specified aspects of site work comply with the
design requirements where these are related to site safety
and with the supervision plan including method statements,
precautionary and protective measures. Check that systems
are in place and followed, to record that site safety
supervision has been properly executed.
T5 Check that site operations and installations meet safety
requirements. For the design of temporary and/or permanent
works where safety relies on assumed conditions being
present on site, validate those assumptions by checking the
actual site conditions and taking necessary follow up action.
Direct subordinate TCPs in priorities and identify aspects of
work which require special care and supervision.
5.4 TCPs may be called on to carry out the general responsibilities of junior
positions and the duties of TCPs may be combined.
5.5 Within the safety management structure two types of site safety supervision
are identified. As defined in the Technical Memorandum these are:
a) Engineering Safety Supervision; and
b) Routine Safety Supervision.
5.6 In the check lists of specific tasks set out in Tables of 5 series, the tasks and
responsibilities of TCPs are assigned with reference to the above broad
headings but referred back also to the levels of supervision established in
the Technical Memorandum.
5.7 The responsibilities arising out of engineering safety supervision should be
discharged by TCPs of grade T4 or T5. TCPs of lower grades should not be
called on to carry out engineering safety supervision responsibilities as
these are commensurate with the qualifications and experience associated
with professionally qualified persons or the qualifications of degree holders.
5.8 Further details of the responsibilities of each stream are set out below.
AP 9s Safety Management Structure
5.9 The AP's Representative will have the duties and responsibilities listed
below.
Responsibilities
(a) The AP's Representative is accountable to the AP for the
implementation of the AP' s supervision plan.
(b) He is the formal point of contact, representing the AP in
communication with other functional streams.
(c) He is accountable to the AP with a responsibility for coordinating
and compiling reports on supervision activities including reports on
non-conformity, incorporating those reports on supervision activities
prepared by other disciplines and for forwarding them to the AP as
appropriate; (the activities include but are not confined to those in
the check list of specific tasks which is provided in this Code of
Practice).
Duties
(d) He will coordinate the submission of supervision plans for all
streams;
(e) In respect of non-conformity he will follow the procedures set out in
Section 9 of this Code of Practice.
5.10 An AP's TCP who is responsible for undertaking engineering safety
supervision will have the duties and responsibilities listed below.
Responsibilities
(a) He is accountable to the AP, through the AP's Representative, for
the implementation of the AP's supervision plan.
(b) He has the relevant responsibilities set down in the Technical
Memorandum and this Code of Practice.
Duties
(c) He is responsible for the safety supervision of the works including,
but not confined to, those specific tasks set out in the check list
provided in this Code of Practice.
(d) When necessary, he will validate conditions on site which relate to
design assumptions.
(e) He will take action in respect of non-conformity by referral to the
AP's Representative and by notifying TCPs in other streams.
5.11 An AP's TCP who is responsible for undertaking routine safety supervision
will have the duties and responsibilities listed below.
Responsibilities
(a) He is accountable to the AP through the AP's Representative.
(b) He has the relevant responsibilities set down in the Technical
Memorandum and this Code of Practice.
Duties
(c) He is responsible for site safety supervision including but not
confined to those specific tasks set out in the check list provided in
this Code of Practice.
(d) He will monitor closely the work of the Contractor's TCPs in
respect of supervision of general and minor site safety aspects of
building works or street works as identified in this Code of Practice.
(e) He will maintain on site, registers of all relevant safety supervision
plans together with all reports, documents and correspondence
relating to the particular site safety supervision plan.
(f) He will take action in respect of non-conformity by referral to the
AP's Representative and by informing TCPs in other streams.
RSE 's Safety Management Structure
5.12 The RSE's Representative will have the duties and responsibilities listed
below.
Responsibilities
(a) He is accountable to the RSE for implementing the RSE's
supervision plan, in respect of site safety aspects.
(b) He is the formal point of contact, representing the RSE in
communication with other functional streams.
(c) He has overall responsibility to check if the safety measures on
site meet with the requirements of safety supervision plans.
(d) He is accountable to the RSE for the satisfactory execution of
the specific tasks and responsibilities of junior TCPs, including
but not confined to those set out in the check list provided in
this Code of Practice.
Duties
(e) He will assist the RSE in carrying out site safety management
functions.
(f) In respect of non-conformity of structural nature, he will follow
the procedures set out in Section 9 of this Code of Practice.
5.13 An RSE's TCP who is responsible for undertaking engineering safety
supervision will have the duties and responsibilities listed below.
Responsibilities
(a) He is accountable to the RSE through the RSE's Representative,
for the implementation of the RSE's supervision plan.
(b) He has the relevant responsibilities set down in the Technical
Memorandum and this Code of Practice.
Duties
(c) He Is responsible for the engineering safety supervision of the
works including, but not confined to, those tasks set out in check
list provided in this Code of Practice.
(d) When necessary, he will validate conditions on .site which relate to
design assumptions.
(e) He will take action in respect of non-conformity by referral to the
RSE's Representative and by notifying TCPs in other streams.
5.14 An RSE's TCP who is responsible for undertaking routine safety
supervision will have the duties and responsibilities listed below.
Responsibilities
(a) He is accountable to the RSE through the RSE's Representative.
(b) He has the relevant responsibilities set down in the Technical
Memorandum and this Code of Practice.
Duties
(c) He is responsible for site safety supervision including but not
confined to the specific tasks set out in the check list provided in
this Code of Practice.
(d) He is responsible for checking that the Contractor's TCPs have
carried out their supervision tasks in areas of work including but not
confined to the specific tasks set out in check list provided in this
Code of Practice.
(e) He will take action in respect of non-conformity by referral to the
RSE's Representative and by notifying TCPs in other streams.
Contractor's Safety Management Structure
5.15 The Authorized Signatory of the Contractor (AS) will have the duties and
responsibilities listed below.
Responsibilities
(a) He has overall responsibility for safety matters regarding the project.
(b) He is responsible for ensuring that his Detailed Safety Supervision
Plans are regularly reviewed and implemented.
10
(c) He will ensure that reports of non-conformity, are immediately acted
on and that rectification is carried out forthwith.
(d) He will have delegated authority to accept instructions and advice
on behalf of the Contractor and will be given authority by the
Contractor to take necessary action.
Duties
(e) He will ensure good communication exists between his
Representative and other TCPs including the AFs and RSE's
Representatives.
(f) He will establish and maintain communication between himself and
his Representative.
5.16 The Contractor's Representative will have the duties and responsibilities
listed below.
Responsibilities
(a) He is accountable to the AS for implementing the safety supervision
plan.
(b) He is accountable to the AS for the implementation of the
contractor's supervision plan.
(c) He is the formal point of contact, representing the Contractor in
communication with other functional streams.
(d) He has sufficient delegated authority to instruct subordinates and
sub-contractors on safety related matters.
Duties
(e) He will assist the AS in carrying out his site safety management
functions
(f) He will ensure that all members of line management, including sub-
contractors and TCPs, are conversant with the Detailed Safety
Supervision Plan and the supporting documentation and have
sufficient resources to implement safety measures.
(g) He will ensure good coordination and communication exists
between his site safety management TCPs and safety officers and
safety supervisors provided under other legislation.
11
(h) In respect of non-conformity, he will report follow the procedures
set out in Section 9 of this Code of Practice.
(i) He will investigate the causes of each non-conformity and will
institute measures which will prevent further occurrence.
5.17 A Contractor's TCP who is responsible for undertaking engineering safety
supervision will have the duties and responsibilities listed below.
Responsibilities
(a) He is accountable to the AS through the Contractor's
Representative.
(b) He has the overall responsibilities detailed in the Technical
Memorandum and this Code of Practice and is also responsible for
checking that conditions and circumstances shown on the drawings
are present on site but excluding checking of the AP's and RSE's
design.
Duties
(c) He will check that where required in the Detailed Safety Supervision
Plan, design assumptions made in the design of temporary works
and method statements are validated on site.
(d) He will take action in respect of non-conformity by referral to the
Contractor's Representative, by instructing rectification and by
notifying TCPs in other streams.
5.18 A Contractor's TCP who is responsible for undertaking routine safety
supervision will have the duties and responsibilities listed below.
Responsibilities
(a) He is accountable to the Contractor's Representative.
(b) He has the overall responsibilities set down in the Technical
Memorandum and this Code of Practice, including those which are
detailed in this paragraph.
12
Duties
(c) He will also check specialist aspects of work to see that it is
carried out in accordance with the method statements,
precautionary and protective measures in order to ensure that it
complies with the submitted safety supervision plans.
(d) He will take action in respect of non-conformity by referral to the
Contractor's Representative and by informing TCPs in other
streams.
(e) Where more than one TCP is appointed to carry out routine safety
supervision their responsibilities should be established in the
contractor's DSSP.
Division of responsibility between RSE and Contractor for Temporary
Works and Working Procedures
5.19 The Contractor has the sole responsibility to ensure the integrity of the
temporary structure itself and the associated fixing methods.
5.20 The division of responsibility between RSE and Contractor for temporary
works is detailed below:
Case 1 When the prescribed plans stipulate temporary works and the
sequence of construction or method statements are also shown
on prescribed plans, both the RSE and the Contractor have the
responsibility of supervising the carrying out of the works in
accordance with the approved plans.
Case 2 When the temporary works, the sequence of construction or
method statements are not required to be shown on prescribed
plans and in cases when these have no effect on the permanent
structure, the Contractor has the sole responsibility of ensuring
the integrity of temporary works and that the carrying out of
temporary works should be safe and should not endanger the
workers on site, the public and adjoining buildings.
13
Case 3 In cases when the temporary works or the sequence of
construction or method statements are not required to be shown
on the prescribed plans but have a potential effect on the
integrity or serviceability of the permanent structure whether
during construction or after completion, two different cases will
be considered:-
Case 3A Part of the permanent structure will be temporarily
overstressed due to stress redistribution in the
partially constructed structure.
CaseSB The permanent structure is affected by way of
additional imposed loading over the designed
loading.
The demarcation of responsibilities between the RSE and the
Contractor on supervision of carrying out of the temporary
works and the sequence of construction are shown in the
flowchart at Chart 5.1.
5.21 For case 3A, the plans, design information and/or method statement that is
to be lodged with the project RSE by the Contractor will be certified and
signed by a person whose name is included in the list of Registered
Structural Engineers kept by the Building Authority. The certificate for
completion of temporary works will also be signed by the same person to
certify that the temporary works have been carried out in accordance with
the plans.
5.22 For case 3B, the certificate that the permanent structure will not be
overloaded, which is to be lodged with the project RSE by the Contractor
will be signed by a person whose qualifications and experience are not
inferior to that required for a T5. The certificate for completion of
temporary works will also be signed by the same person to certify that the
works have been carried out to his satisfaction.
14
5.23 The RSE may require the Contractor to submit further calculations to
substantiate his design check.
Communication Procedures
5.24 Successful implementation of the Supervision Plan requires effective and
efficient communication within and between each stream. Within streams,
lines of communication should be established between the engineering
safety supervision level and the routine safety supervision level whereas
interstream communications should usually take place between stream
counterparts.
5.25 Lines of communication between the site safety management structure
levels are needed for reporting, instructing and information purposes.
Safety Management Statement in DSSP
5.26 In completing the DSSP, a statement is required to the effect that safety
management of the works will be carried out in the manner prescribed by
the Ordinance and Regulations. Each author in turn is required to
consider this topic under the following items of the DSSP:
Item 8 to be considered by APs; item 12 by RSEs; item 18 by RGBCs and
item 24 by RSCs.
Author's Signature
5.27 The DSSP authors are required to state and sign to the effect that the
relevant part of the DSSP has been prepared by the AP (item .9), the RSE
(item 13), the RGBC (item 19) and the RSC (item 25), and also that the
part of the DSSP which they have prepared complies with the Technical
Memorandum, Code of Practice, the Buildings Ordinance and
Regulations.
15
Chart 5.1 - Division of Responsibility Between RSE and Contractor for Temporary Works andWorking Procedures That Are Not Required To Be Shown OnPrescribed Plans But That May Affect Permanent Structure(Section 5.20 refers)
Temporary works / workingprocedures that may affectpermanent works temporarily
Case 3A
Temporary overstressing ofthe permanent structure dueto stress redistribution,e.g. Refuse chute opening
21 days before thecommencement of theTemporary Works theContractor will lodge withthe Project RSE the plansand design information forthe Temporary Works,and/or a method statement
If the Project RSE is satisfiedthat the integrity of thePermanent Works remainsunaffected he will issue a reply(copied to AP) to allow theContractor to proceed
Within 14 days after thecompletion of the TemporaryWorks; the Contractor willsubmit a certificate to theProject RSE to certify that theTemporary Works have beencarried out in accordancewith the plans
Case 3BImposing loading on thepermanent structure,e.g. temporary workingplatform, bending yardor storage
RSE to release relevantdesign information tothe Contractor on request.
21 days before thecommencement of theTemporary Works theContractor will submita certificate to the ProjectRSE to certify that thepermanent structure willnot be overloaded
Within 14 days after thecompletion of the TemporaryWorks, the person appointedby the Contractor will submita certificate to the Project RSEto-certify'that the works havebeen carried out to hissatisfaction
16
Check Lists For Specific Tasks by TCPs
Table No. Specific Tasks by
5.1.1 AP's Representative
5.1.2 AP's T4
5.1.3 AP's T3
5.2.1 RSE's Representative
5.2.2 RSE's T5
5.2.3 RSE's T4
5.2.4 RSE's T3
5.2.5 RSE's T2
5.3.1 Contractor's Representative
5.3.2 Contractor's T5
5.3.3 Contractor's T4
5.3.4 Contractor's T3
5.3.5 Contractor's T2
5.3.6 Contractor's Tl
17
Table 5.1.1 Check List of Specific Tasks For AP's Representative Sheet 1 of 2Type of Tasks : Systems and Reports
Project: Type(s) of Works :
TCP filling in this check list
Name : . Signature: Date :
Sharing duties of other TCPs : AP 's stream RSE's stream
ItemNo. Description
Satisfactory
Yes NoNot
Applicable
1 .1 .1
General
Check that an office has been established for a central registry
1.1.2
Systems
Establish systems for:- co-ordinating and compiling reports- filing of reports in central site registry- maintenance of filing systems- forwarding reports to AP in case of:
i. non-conformity and failure to take remedial measuresii. non-conformity posing immediately danger
1.1.3
1.1.4
1.1.5
1.1.6
1.1.7
1.1.8
1.1.9
Action and Reporting
Register reports of non-conformity and inform other representativesof non-conformity.
In the case of report of non-structural non-conformity, verify thatnon-conformity has occurred and instruct rectification works
If the non-conformity is considered to pose an imminent danger,report to the AP immediately
If the non-conformity is considered to be a significant risk or asource of danger and if the Contractor does not comply withinstructions, report to the AP
Inform RSE of actions taken
Notify Contractor's Representative if rectification measures areinadequate
Report to AP copied to Contractor's and RSE's Representatives whennon-conformity has been rectified
18
Table 5.1.1 Check List of Specific Tasks For AP's Representative (Cont'd) Sheet 2 of 2Type of Tasks : Systems and Reports
Project: Type(s) of Works :
TCP filling in this check list
Name : Signature : Date :
Record of Instruction of Rectification Works
Instruction given to : (Functional Stream : , Grade of TCP :.
Item No. Instruction of Rectification
Record of Referral
Item No Person Referred to Functional Stream Grade of TCP
19
Table 5.1.2 Check List of Specific Tasks For AP5s T4 Sheet I of IType of Tasks : Engineering Safety Supervision
Project: Type(s) of Works :
TCP fil
Name :
Sharing
ItemNo.
1.2.1
1.2.2
1.2.3
1.2.4
1.2.5
1.2.6
Record
Instruct
Item Nc
ling in this check list
Signature : Date :
•r dnties of other T^Ps • AP's stream RSE 's stream
DescriptionGeneral
Check that works on site comply with method statements
Check and satisfy that precautionary and protective measures are inplace to meet site conditions
Site Formation
Check that revealed conditions are compatible withpredicted/assumed conditions
Check and monitor sequence of excavation to ensure lateral supportis not removed in advance of adequate propping or restraint
Check access benches and edges for any evidence of unstable planesor wedges
Check that temporary cuttings will not cause any instability toadjoining ground and final formation
Satisfactory
Yes NoNot
Applicable
of Instruction of Rectification Works
ion given to: (Functional Stream : .Grade of TCP: ^
>. Instruction of Rectification
Record of Referral
Item No Person Referred to Functional Stream Grade of TCP
20
Table 5.1.3 Check List of Specific Tasks For AP's.TS Sheet 1 of 2Type of Tasks : Management and Co-ordination;
Routine Safety SupervisionProject: Type(s) of Works :
TCP filling in this check list ~~~~
Name : Signature: Date :
Sharing duties of other TCPs : AP 's stream RSE *s stream
ItemNo.
1.3.1
1.3.2
1.3.3
1.3.4
1.3.5
1.3.6
1.3.7
1,3.8
1.3.9
1.3.10
Description .General
Check that central record system and registry have been physicallyestablished for all streams (Contractor, AP and RSE)
Maintain registry and all relevant safety supervision plans togetherwith all relevant reports, documents and correspondence
Check and satisfy that copies of approved plans are kept on site
Check that the hoarding and/or covered walkways are erected tosecure safety of the public in accordance with the hoarding planagreed by the Building Authority
Management
Check that Contractor's T1/T2/T3 are making inspections no lessthan the required frequency and carrying out duties in accordancewith the Technical Memorandum and the Code of Practice for SiteSafety Supervision
Demolition
Check that the provision and condition of scaffolding, catch fans,matscreens and heavy duty nylon mats, as appropriate, aresatisfactory
Site Formation
Check that monitoring stations are installed when necessary and thatreadings are being taken
Check that piezometers, where required, are properly covered andmaintained and readings taken at the frequency required
Check that method statements have been prepared and are beingfollowed for installing rock anchors or soil nails
Action and Reporting on Non-Conformity
Report non-conformity to AP's Representative and to counterpartTCPs
Satisfactory
Yes NoNot
Applicable
21
Table 5.13 Check List of Specific Tasks For AP's T3. (Cont'd) Sheet 2 of 2Type of Tasks : Management and Co-ordination;
Routine Safety Supervision .•
Project: Type(s) of Works :
TCP filling in this check list ————- -
Name : '. Signature : __ Date :
Record of Instruction of Rectification Works
Instruction given to : (Functional Stream : , Grade of TCP :.
Item No. Instruction of Rectification
Record of Referral
Item No Person Referred to Functional Stream Grade of TCP
22
Table 5.2.1
Project :
Check List of Specific Tasks For RSE's RepresentativeType of Tasks : Systems and Reports
Sheet 1 of !
Type(s) of Works :
TCP filling in this check list
Name : Signature : Date :
Sharing
ItemNo.
2.1.1
2.1.2
2.1.3
2.1.4
2.1.5
2.1.6
2.1.7
2.1.8
f duties of other TCPs : AP 's stream RSE 's stream
DescriptionSystems
Set up communication systems with RSE's TCPs
Action and Reports
In the case of report of structural non-conformity, verify that non-conformity has occurred and instruct rectification works
If the non-conformity is considered to pose an imminent danger,report to the RSE
If the non-conformity is considered to cause a material concern forsafety and if the Contractor does not comply with instructions, reportto the RSE
Inform AP's Representative of actions taken
Monitor that rectification measures are properly carried out
Notify Contractor's Representative if rectification measures areinadequate
Report to the RSE, copied to the Contractor's and AP'sRepresentatives, when non-conformity has been rectified
Satisfactory
Yes NoNot
Applicable
Record of Instruction of Rectification Works
Instruction given to : (Functional Stream : . Grade of TCP : )
Item No. Instruction of Rectification
Record of Referral
Item No Person Referred to Functional Stream Grade of TCP
23
Table 5.2.2
Project:
Check List of Specific Tasks For RSE's T5Type of Tasks : Engineering Safety Supervision
Type(s) of Works :
Sheet 1 of 3
TCP filling in this check list
Name : „ __ Signature : Date :
Sharing duties of other TCPs : AP 's stream RSE 's stream
ItemNo.
2.2.1
2.2.2
2,2.3
2.2.4
2.2.5
2.2.6
2.2.7
2.2.8
2.2.9
2.2.10
2.2.11
2.2.12
DescriptionGeneral
Check that structural works on site comply with method statements
Instruct RSE's TCPs Grade T2/T3 on aspects of work which requirespecial care and consideration
For cases where plant and machinery are supported or anchoredagainst the permanent structure or supported on a temporary structurethat affects the permanent structure and in such case, the integrity ofthe permanent structure is not maintained, check that the permanentstructure is adequate for the imposed load
Demolition of Superstructure
Check that cantilever structures are removed before generaldemolition of each floor
Excavation and Lateral Support
Check that approved/agreed method statement is followed
Check that there is no risk of artesian conditions
Check that nearby buildings and ground are not adversely affected
Check that depths of sheet pile or other vertical supporting membersare consistent with those estimated at design stage
Check that sufficient layers of horizontal support are provided
Check that design of walings including packing and web stiffening isadequate
Check that design of props for deflection and acceptance of proploads is adequate
Check that raking props are adequately supported and have sufficientand reliable reaction
Satisfactory
Yes NoNot
Applicable
24
Table 5.2.2 Check List of Specific Tasks For RSE'3 T5 (Cont'd)Type of Tasks : Engineering Safety Supervision
Sheet 2 of 3
Project: Type(s) of Works :
TCP filling in this check list
Name: Signature : Date :
ItemNo. Description
Satisfactory
Yes NoNot
Applicable
2.2.13
2.2.14
Excavation and Lateral Support (Cont'd)
Check that as excavation proceeds, depth of sheet piles or similarvertical members are in place to sufficient depth to provide adequatecut off and lateral support below current depth of excavation byreference to original design, installation records and characteristicsof subsoil being excavated
Check that effect of groundwater table is consistent with design oftemporary works
2.2.15
2.2.16
2.2.17
2.2.18
2.2.19
Top Down Construction
Check that enclosing walls show no signs of defect or lack ofsoundness
Check that before excavation takes place the highest new deck levelis in place and has achieved sufficient strength to provide lateralprop forces
Check that records are in place to show that during excavation thereis no unexpected deflection on the highest deck level and subsequentnew floor levels
Check that at new deck levels adequate reinforcement or fixings arein place to locate, support and restrain floors at joints with walls andcolumns
Check that columns are adequate to accept substructure loads and areadequately braced or restrained at all times
25
Table 5.2.2 Check List of Specific Tasks For T5 (Cont'd) Sheet 3 of 3Type of Tasks : Engineering Safety Supervision
Project: Type(s) of Works :
TCP filling in this check list
Name : Signature : , Date : _____
Record of Instruction of Rectification Works
Instruction given to : (Functional Stream : , Grade of TCP
Item No. Instruction of Rectification
Record of Referral
Item No Person Referred to Functional Stream Grade of TCP
26
Table 5.2.3 Check List of Specific Tasks For RSE's T4 Sheet 1 of 3Type of Tasks : Engineering Safety Supervision
Project: Type(s) of Works :
TCP filling in this check list
Name : Signature : Date,
Sharing duties of other TCPs : AP 's stream RSE's stream
ItemNo.
2.3.1
2.3.2
2.3.3
2.3.4
2.3.5
2.3.6
2.3.7
2.3.8
2.3.9
2.3.10
2.3.11
2.3.12
2.3.13
DescriptionGeneral
Check that structural works on site comply with method statements
Instruct RSE's TCPs Grade T2/T3 on aspects of work which requirespecial care and consideration
For cases where plant and machinery are supported or anchoredagainst the permanent structure or supported on a temporary structurethat affects the permanent structure and in such case, the integrity ofthe permanent structure is not maintained, check that the permanentstructure is adequate for the imposed load
Demolition of Superstructure
Check that cantilever structures are removed before generaldemolition of each floor
Excavation and Lateral Support
Check that approved/agreed method statement is followed
Check that survey points and other geotechnical instrumentationhave been installed and are regularly monitored and results kept onsite
Check that there is no risk of artesian conditions
Check that nearby buildings and ground are not adversely affected
Check that depths of sheet pile or other vertical supporting membersare consistent with those estimated at design stage
Check that sufficient layers of horizontal support are provided
Check that design of walings including packing and web stiffening isadequate
Check that design of props for deflection and acceptance of proploads is adequate
Check that raking props are adequately supported and have sufficientand reliable reaction
Satisfactory
Yes NoNot
Applicable
27
Table 5.23 Check List of Specific Tasks For RSE's T4 (Cont'd) Sheet 2 of 3Type of Tasks : Engineering Safety Supervision
Project: Type(s) of Works :
TCP filling in this check list
Name : Signature : Date :
ItemNo. Description
Satisfactory
Yes NoNot
Applicable
2.3.14
2.3.15
Excavation and Lateral Support (Cont'd)
Check that as excavation proceeds, depth of sheet piles or similarvertical members are in place to sufficient depth to provide adequatecut off and lateral support below current depth of excavation byreference to original design, installation records and characteristicsof subsoil being excavated
Check that effect of groundwater table is consistent with design oftemporary works
2.3.16
2.3.17
2.3.18
2.3,19
2.3.20
2.3.21
Top Down Construction
Check that enclosing walls show no signs of defect or lack ofsoundness
Check that before excavation takes place the highest new deck levelis in place and has achieved sufficient strength to provide lateralprop forces
Check that during excavation there is no unexpected deflection onthe highest deck level and subsequent new floor levels
Check that at new deck levels adequate reinforcement or fixings arein place to locate, support and restrain floors at joints with walls andcolumns
Check that excavation does not proceed below defined levels or inexcess of defined bay widths
Check that columns are adequate to accept substructure loads and areadequately braced or restrained at all times
28
Table 5.23 Check List of Specific Tasks For RSE's T4 (Cont'd) Sheet 3 of 3Type of Tasks : Engineering Safety Supervision
Project: Type(s) of Works :
TCP filling in this check list
Name : Signature : Dale :
Record of Instruction of Rectification Works
Instruction given to : (Functional Stream : , Grade of TCP : ,
Item No. Instruction of Rectification
Record of Referral
Item No Person Referred to Functional Stream Grade of TCP
Table 5.2.4
Project:
Check List of Specific Tasks For RSE's T3Type of Tasks : Routine Safety Supervision
Sheet 1 of 1
Type(s) of Works :
TCP fil
Name :
Sharing
ItemNo.
2.4.1
2.4.2
2.4.3
2.4.4
2.4.5
ling in this check list
Signature : Date .
y duties of other T^.ps • AP'x stream RSE 's stream
DescriptionGeneral
Check that Contractor's TCPs carry out Routine Safety Supervisionitems related to :- structural support for plant and machinery- temporary works and intermediate stages of building works
Excavation and Lateral Support
Check that survey points and other geotechnical instrumentationhave been installed and are regularly monitored and the results kepton site
Check that there is no over-excavation
Top Down Construction
Check that enclosing walls show no signs of defect or lack ofsoundness
Check that columns are adequate to accept substructure loads andare adequately braced or restrained at all times
Satisfactory
Yes NoNot
Applicable
Record of Instruction of Rectification Works
Instruction given to : (Functional Stream : . Grade of TCP • )
Instruction of Rectification
Record of Referral
Item No Person Referred to Functional Stream Grade of TCP
30
Table 5.2.5
Project:
Check List of Specific Tasks For RSE's T2Type of Tasks : Routine Safety Supervision
Sheet 1 of 1
Type(s) of Works :
TCP filling in this check list
Name : Signature : Date :
Sharing
ItemNo.
2.5.1
2.5.2
2.5.3
2.5.4
2.5.5
Record
Instruct
Item N<
* duties of other TCPs : AP 's stream RSE 's stream
DescriptionGeneral
Check that Contractor's TCPs carry out Routine Safety Supervisionitems related to :- structural support for plant and machinery- temporary works and intermediate stages of building works
Excavation and Lateral Support
Check that survey points and other geotechnical instrumentation havebeen installed and are regularly monitored and the results kept on site
Check that there is no over-excavation
Top Down Construction
Check that enclosing walls show no signs of defect or lack ofsoundness
Check that columns are adequate to accept substructure loads and areadequately braced or restrained at all times
Satisfactory
Yes
of Instruction of Rectification Works
:ion given to : (Functional Stream : , Grade
3. Instruction of Rectification
No
of TCP :
NotApplicable
}
Record of Referral
Item No Person Referred to Functional Stream Grade of TCP
31
Table 53.1 Check List of Specific Tasks For Contractor's RepresentativeType of Tasks : Systems and Reports
Sheet 1 of 2
Project: Type(s) of Works :
TCP filling in this check list
Name: Signature: Date:
Sharing duties of other TCPs :
ItemNo. Description
Satisfactory
Yes NoNot
Applicable
3.1,1
3.1.2
3.1.3
3.1.4
General
Check that Contractor's TCPs and sub-contractors are conversantwith DSSPs and the supporting documentation
Check that communication systems are in place with AP's and RSE'srepresentatives
Set up communication and co-ordination with safety officers andsafety supervisors
Set up procedures to check and satisfy that safety measures andsafety actions have been checked and recorded.
3.1.5
3.1.6
3.1.7
5.1.8
.1.9
Action and Reporting on Non-Conformity
Instruct subordinates and subcontractors to take action on safetyrelated matters
Instruct rectification of non-conformity
Monitor rectification measures
Report to AP's and RSE's Representatives when non-conformity hasbeen rectified
Investigate reasons for non-conformity and set up systems andprocedures to avoid future non-conformity
32
Table 53.1 Check List of Specific Tasks For Contractor's Representative (Cont'd) Sheet 2 of 2Type of Tasks : Systems and Reports
Project: Type(s) of Works :
TCP filling in this check list
Name : Signature : Date :
Record of Instruction of Rectification Works
Instruction given to : (Functional Stream : , Grade of TCP :.
Item No. Instruction of Rectification
Record of Referral
Item No Person Referred to Functional Stream Grade of TCP
33
Table 53.2
Project:
Check List of Specific Tasks For Contractor's T5Type of Tasks : Engineering Safety Supervision -
Type(s) of Works :
Sheet 1 of 4
TCP filling in this check list
Name: Signature : Date :
Sharing duties of other TCPs :
ItemNo. Description
Satisfactory
Yes NoNot
Applicable
3.2.1
3.2.2
3.2.3
General and Minor Aspects of Building Works
General Items
Check that there is adequate installation of catch fans, catchplatforms and protection screens as necessary to secure safety againstfalling objects
Liaise with AP's and RSE's T4/T5 as applicable to check and satisfythat design assumptions are being validated on site
Assess actual site conditions encountered in relation to the DSSP;direct subordinates on priorities and identify aspects of work whichrequire special care and supervision
3.2.4
Formwork for Concrete
Check that the design and supports of formwork and shoring areadequate to support all intended loads
3.2.5
3.2.6
.2.7
Structural Support for Plant and Machinery
General
For cases where plant and machinery are supported on a temporaryelevated platform without affecting the permanent structure, checkthat the supporting structure is adequate for the imposed loads
For cases where plant and machinery are supported on or anchoredagainst the permanent structure or supported on a temporary structurethat affects the permanent structure and in such case, the integrity ofthe permanent structure is maintained, check that:- the design information is given- the permanent or temporary structure is adequate for the imposed
load- fixing and supports are secure
For cases where plant and machinery is supported on or anchoredagainst the permanent structure or supported on a temporary structurethat affects the permanent structure and in such case, the intendedintegrity of the permanent structure is not maintained, check that:- fixing and supports are secure- the temporary structure, if applicable, is adequate for the imposed
load
34
Table 5.3.2 Check List of Specific Tasks For Contractor's T5 (Cont'd) Sheet 2 of 4Type of Tasks : Engineering Safety Supervision
Project: Type(s) of Works :
TCP filling in this check list
Name : Signature : Date :
ItemNo.
3.2.8
3.2.9
3.2.10
3.2.11
3.2.12
3.2.13
3.2.14
3.2.15
3.2.16
3.2.17
DescriptionCranes and Hoists
Check that crane fixing and supports are secure
Man Hoists, Goods Hoists and Gondolas
Check that towers, pulleys and supporting frames are securelyattached to the building
Check that floor mounted machinery and pulleys are adequatelyfounded and secured by proper fixings
Excavation Plant and Piling Rigs
Check that if operated on ground, state of the ground is fit for useby the plant
Check that if operated on an elevated working platform, theworking platform is adequate to support the plant
Check that rigs, masts, excavator jibs and buckets do not riskstriking members of the public or road users
Stationary Plant, e.g. Compressors and Concrete Batching Plants
Check that fixed plant is securely founded and fixed
Temporary Works and Intermediate Stages
Excavation & Lateral Support
Check that approved/agreed method statement is followed
Check that as excavation proceeds, depth of sheet piles or similarvertical members are in place to sufficient depth to provideadequate cut off and lateral support below
Check current depth of excavation by reference to original design,installation records and characteristics of subsoil being excavated.
Satisfactory
Yes NoNot
Applicable
35
Table 53.2 Check List of Specific Tasks For Contractor's T5 (Cont 5d) Sheet 3 of 4Type of Tasks : Engineering Safety Supervision
Project: Type(s) of Works :
TCP filling in this check list
Name : - Signature: Date:
ItemNo.
3.2.18
3.2.19
3.2.20
3.2.21
3.2.22
3.2.23
3.2.24
3.2.25
3.2.26
3.2.27
3.2.28
3.2.29
3.2.30
DescriptionFalsework for Elevated Structures
Check that vertical supports are adequate in section and securelyfixed for applied static and dynamic loading
Check that vertical supports are properly aligned with adequatediagonal and horizontal bracing
Check that cross members supporting deck or formwork areadequately fixed and braced to accept static and dynamic loads
Check that deck and/or formwork are adequate for applied loads
Top Down Construction
Check that approved/agreed method statement is followed
Demolition of Superstructure
Check that approved/agreed method statement is followed
Check that cantilever structures are removed before generaldemolition of each floor
Check that restraining guy ropes and/or nets are provided beforeremoval of external walls
Check that before removal of walls, beams or columns :- all loads other than self weight are removed- slot cut is carried out- restraining guy ropes or nets are provided
Check that supporting scaffolding is provided to lower floors whereappropriate
Check that there is no excessive debris on cantilever or floor slabsand that no build up occurs against external walls
Check that provision and condition of scaffolding, catch fans,matscreens and heavy duty nylon mats, as appropriate, aresatisfactory
Check that mechanical plant is operating safely and in accordancewith method statements
Satisfactory
Yes NoNot
Applicable
36
Table 53.2 Check List of Specific Tasks For Contractor's T5 (Cont'd) Sheet 4 of 4Type of Tasks : Engineering Safety Supervision
Project: Type(s) of Works :
TCP filling in this check list ~~~
Name: Signature: Date,
Item
No.
3.2.31
3.2.32
3.2.33
3.2.34
3.2.35
3.2.36
3.2.37
DescriptionSite Formation
Check that angle of cutting is within specified limits
Check that loose material or boulders are not present at the crest orintermediate benches of slopes
Check during blasting operation that protective measures are in placeand maintained
Check stability of temporary stockpiles
Check that temporary stockpiles do not surcharge slopes or retainingwalls
Check that excavation, filling or temporary stockpiles do not obstructwatercourses or drains
Inspect all boulders within 20m of crest of excavated slopes to see ifthey are stable
Satisfactory
Yes No
Not
Applicable
Record of Instruction of Rectification Works
Instruction given to :
Item No. Instruction of Rectification
(Functional Stream:. ., Grade of TCP:.
Record of Referral
Item No Person Referred to Functional Stream Grade of TCP
37
Table 533
Project:
Check List of Specific Tasks For Contractor's T4Type of Tasks : Engineering Supervision
Type(s) of Works :
Sheet 1 of 4
TCP filling in this check list
Name: Signature : Date :
Sharing duties of other TCPs :
ItemNo. Description
Satisfactory
Yes NoNot
Applicable
3.3.1
3.3.2
3.3.3
General and Minor Aspects of Building Works
General Items
Check that there is adequate installation of catch fans, catchplatforms and protection screens as necessary to secure safety againstfalling objects
Liaise with AP's and RSE's T4/T5 as applicable to check and satisfythat design assumptions are being validated on site
Assess actual site conditions encountered in relation to the DSSP;direct subordinates on priorities and identify aspects of work whichrequire special care and supervision
3.3.4
Formwork for Concrete
Check that the design and supports of formwork and shoring areadequate to support all intended loads
3.3.5
3.3.6
.3.7
Structural Support for Plant and Machinery
General
For cases where plant and machinery are supported on a temporaryelevated platform without affecting the permanent structure, checkthat the supporting structure is adequate for the imposed loads
For cases where plant and machinery are supported on or anchoredagainst the permanent structure or supported on a temporary structurethat affects the permanent structure and in such case, the integrity ofthe permanent structure is maintained, check that:- the design information is given- the permanent or temporary structure is adequate for the imposed
load- fixing and supports are secure
For cases where plant and machinery is supported on or anchoredagainst the permanent structure or supported on a temporary structurethat affects the permanent structure and in such case, the intendedintegrity of the permanent structure is not maintained, check that:- fixing and supports are secure- the temporary structure, if applicable, is adequate for the imposed
load
38
Table 5.33 Check List of Specific Tasks For Contractor's T4 (Cont'd) Sheet 2 of 4Type of Tasks : Engineering Safety Supervision
Project: Type(s) of Works :
TCP filling in this check list ' • ~~~~
Name : Signature : Date :
ItemNo,
3.3.8
3.3.9
3.3.10
3.3.11
3.3.12
3.3.13
3.3.14
3.3.15
3.3.16
3.3.17
DescriptionCranes and Hoists
Check that crane fixing and supports are secure
Man Hoists, Goods Hoists and Gondolas
Check that towers, pulleys and supporting frames are securelyattached to the building
Check that floor mounted machinery and pulleys are adequatelyfounded and secured by proper fixings
Excavation Plant and Piling Rigs
Check that if operated on ground, state of the ground is fit for useby the plant
Check that if operated on an elevated working platform, theworking platform is adequate to support the plant
Check that rigs, masts, excavator jibs and buckets do not riskstriking members of the public or road users
Stationary Plant, e.g. Compressors and Concrete Batching Plants
Check that fixed plant is securely founded and fixed
Temporary Works and Intermediate Stages
Excavation & Lateral Support
Check that approved/agreed method statement is followed
Check that as excavation proceeds, depth of sheet piles or similarvertical members are in place to sufficient depth to provideadequate cut off and lateral support below
Check current depth of excavation by reference to original design,installation records and characteristics of subsoil being excavated.
Satisfactory
Yes NoNot
Applicable
39
Table 533 Check List of Specific Tasks For Contractor's T4 (Cont'd)Type of Tasks : Engineering Safety Supervision
Project: Type(s) of Works :
TCP filling in this check list
Name:
Sheet 3 of 4
Signature: Date:
ItemNo.
3.3.18
3.3.19
3.3.20
3.3.21
3.3.22
3.3.23
3.3.24
3.3.25
3.3.26
3.3.27
3.3.28
3.3.29
3.3.30
DescriptionFalsework for Elevated Structures
Check that vertical supports are adequate in section and securelyfixed for applied static and dynamic loading
Check that vertical supports are properly aligned with adequatediagonal and horizontal bracing
Check that cross members supporting deck or formwork areadequately fixed and braced to accept static and dynamic loads
Check that deck and/or formwork are adequate for applied loads
Top Down Construction
Check that approved/agreed method statement is followed
Demolition of Superstructure
Check that approved/agreed method statement is followed
Check that cantilever structures are removed before generaldemolition of each floor
Check that restraining guy ropes and/or nets are provided beforeremoval of external walls
Check that before removal of walls, beams or columns :- all loads other than self weight are removed- slot cut is carried out- restraining guy ropes or nets are provided
Check that supporting scaffolding is provided to lower floors whereappropriate
Check that there is no excessive debris on cantilever or floor slabsand that no build up occurs against external walls
Check that provision and condition of scaffolding, catch fans,matscreens and heavy duty nylon mats, as appropriate, aresatisfactory
Check that mechanical plant is operating safely and in accordancewith method statements
Satisfactory
Yes NoNot
Applicable
40
Table 53.3 Check List of Specific Tasks For Contractor's T4 (Cont'd) Sheet 4 of 4Type of Tasks : Engineering Safety Supervision
Project: Type(s) of Works :
TCP filling in this check list ~~~"~
Name: Signature, Date :
Item
No.
3.3.31
3.3.32
3.3.33
3.3.34
3.3.35
3.3.36
3.3.37
DescriptionSite Formation
Check that angle of cutting is within specified limit
Check that loose material or boulders are not present at the crest orintermediate benches of slopes
Check during blasting operation that protective measures are in placeand maintained
Check stability of temporary stockpiles
Check that temporary stockpiles do not surcharge slopes or retainingwalls
Check that excavation, filling or temporary stockpiles do not obstructwatercourses or drains
Inspect all boulders within 20m of crest of excavated slopes to see ifthey are stable
Satisfactory
Yes No
Not
Applicable
Record of Instruction of Rectification Works
Instruction given to :
Item No. Instruction of Rectification
(Functional Stream:. ., Grade of TCP :.
Record of Referral
Item No Person Referred to Functional Stream Grade of TCP
41
Table 53.4
Project :
Check List Of Specific Tasks For Contractor's T3Type of Tasks : Management and Co-ordination;
Routine Safety Supervision
Type(s) of Works
Sheet 1 of 2
TCP filling in this check list
Name: _ Signature: Date:
Sharing duties of other TCPs :
ItemNo. Description
Satisfactory
Yes NoNot
Applicable
3.4.1
3.4.2
Management
Check that T1/T2 are carrying out their duties in accordance with theTechnical Memorandum and the Code of Practice for Site SafetySupervision
Check that records are properly kept
3.4.3
General
Check that there is adequate installation of catch fans, catchplatforms and protection screens as necessary to secure safety againstfalling objects
3.4.4
3.4.5
3.4.6
3.4.7
3.4.8
Excavation and Lateral Support
Check that the approved method statement is in place
Check that survey points and other geotechnical instrumentationhave been installed and are regularly monitored and the results kepton site
Check that plans of services and adjoining foundations are available
Check that services have been located
Check that, for top down construction and before excavation takesplace, the highest new deck level is in place and has achievedsufficient strength to provide lateral prop forces
3.4.9
3,4.10
3.4.11
Site Formation
Check that prior to forecast heavy rainstorm and during rainfallevents, slopes and temporary drainage have been inspected
Check that when blasting is to be planned, all concerned havereceived adequate instructions and training and understand relevantlegislation and approved working procedures
Check that method statements have been prepared and are beingfollowed for installing rock anchors or soil nails
42
Table 5.3.4 Check List Of Specific Tasks For Contractor's T3 (Cont'd) Sheet 2 of 2Type of Tasks : Management and Co-ordination;
Routine Safety Supervision
Project: Type(s) of Works :
TCP filling in this check list ~~~~~~~ —
Name : Signature : Date :
Sharing duties of other TCPs :
Record of Instruction of Rectification Works
Instruction given to : (Functional Stream : , Grade of TCP :.
Item No. Instruction of Rectification
Record of Referral
Item No Person Referred to Functional Stream Grade of TCP
43
Table 5.3.5
Project:
Check List of Specific Tasks For Contractor's T2Type of Tasks : Routine Safety Supervision
Type(s) of Works :
Sheet 1 of 5
TCP filling in this check list
Name: ... Signature : Date :
Sharing duties of other TCPs :„
ItemNo.
3.5.1
3.5.2
3.5.3
3.5.4
3.5.5
3.5.6
3.5.7
3,5.8
3.5.9
DescriptionGeneral and Minor Safety Aspects
Check that there are arrangements for access and egress of vehicleswhich are satisfactory and do not endanger the public or other roadusers
Check that scaffolding is adequately secured to the building toprevent collapse
Check that the erection of hoarding and/or covered walkways hasbeen erected to secure safety of the public in accordance with thehoarding plan agreed by the Building Authority
Check that there is adequate installation of catch fans, catchplatforms and protection screens as necessary to secure safetyagainst falling objects
Formworkfor Concrete
Check that formwork for concrete is inspected by a competent personbefore pouring of concrete
Structural Erection
Check that suitable anchorage points are provided for the attachmentof safety harnesses and lifelines or a safety net is installed where thedistance of fall exceeds two meters
Check that safety lines are used to prevent any dangerous swing ofsteel works being raised or lowered by crane
Structural Support for Plant and Machinery
Check that fixing and supports for plant and machinery are secure
Cranes and Hoists
Check that crane fixing and supports are secure
Satisfactory
Yes No•Not
Applicable
44
Table 5.3.5 Check List of Specific Tasks For Contractor's T2 (Cont'd) Sheet 2 of 5Type of Tasks : Routine Safety Supervision
Project: Type(s) of Works :
TCP filling in this check list ' ~~~~~~
Name : Signature : Date :
ItemNo. Description
Satisfactory
Yes NoNot
Applicable
3.5.10
3.5.11
3.5.12
Man Hoists, Goods Hoists and Gondolas
Check that towers, pulleys and supporting frames are securelyattached to the building
Check that there is free or uninterrupted passage provided forgondolas before they are moved
Check that floor mounted machinery and pulleys are adequatelyfounded and secured by proper fixings
3.5.13
3.5.14
3.5.15
Excavation Plant & Piling Rigs
Check that if operated on ground, state of the ground is fit for use bythe plant
Check that if operated on an elevated working platform, the workingplatform is adequate to support the plant
Check that rigs, masts, excavator jibs and buckets do not risk strikingmembers of the public or road users
3.5.16
Stationary Plant, e.g. Compressors and Concrete Batching Plants
Check that fixed plant is securely founded and fixed
3.5.17
3.5.18
3.5.19
3.5.20
3.5.21
Demolition of Superstructure
Check that the approved/agreed method statement is followed
Check that cantilever structures are removed before generaldemolition of each floor
Check that all columns/walls are removed at each floor level beforedemolition of lower floor
Check that restraining guy ropes and/or nets are provided beforeremoval of external walls
Check that before removal of walls, beams or columns, all loadsother than self weight are removed, slot cut is carried out andrestraining guy ropes are provided, where necessary
45
Table 5.3.5 Check List of Specific Tasks For Contractor's T2 (Cont'd) Sheet 3 of 5Type of Tasks : RoutiEe Safety Supervision
Project: Type(s) of Works :
TCP filling in this check list
Name : . _ .— Signature: Date :
ItemNo.
3.5.22
3,5.23
3.5.24
3.5.25
3.5.26
3.5.27
3.5.28
3.5.29
3.5.30
3.5.31
3.5.32
3.5.33
3.5.34
3.5.35
3.5.36
DescriptionDemolition of Superstructure (Cont'd)
Check that supporting scaffolding is provided to lower floors whereappropriate
Check that there is no excessive debris on cantilever or floor slabsand that no build up occurs against external walls
Check that adequate watering is provided
Check that refuse chute or refuse openings are properly located
Check that provision and condition of scaffolding, catch fans,matscreens and heavy duty nylon mats are satisfactory
Check that mechanical plant is operating safely and in accordancewith method statements
Excavation and Lateral Support
Check that the approved/agreed method statement is followed
Check that survey points and other geotechnical instrumentationhave been installed and are regularly monitored and the results kepton site
Check that nearby buildings and ground are not adversely affected
Check that positions of sheet piling or other supports does notconflict with services or adjoining foundations
Check that sheet piles or other vertical members are adequatelysupported prior to and during driving
Check that sufficient layers of horizontal support are provided
Check that pre-loading is in place, where specified
Check that king posts to lateral support systems are provided, ifrequired
Check that raking props are adequately supported and have sufficientand reliable reaction
Satisfactory
Yes NoNot
Applicable
46
Table 53.5 Check List of Specific Tasks For Contractor's T2 (Cont'd) Sheet 4 of 5Type of Tasks : Routine Safety Supervision
Project: Type(s) of Works :
TCP filling in this check list ~~Name: Signature: Date :
ItemNo. Description
Satisfactory
Yes NoNot
Applicable
3.5.37
3.5.38
3.5.39
Excavation and Lateral Support (Contd)
Check that there is no over-excavation
Check that as excavation proceeds, depth of sheet piles or similarvertical members are in place to sufficient depth to provide adequatecut off and lateral support below current depth of excavation byreference to original design, installation records and characteristics ofsubsoil being excavated
Check that there is no instability of temporary cuttings duringintermediate stages
3.5.40
3.5.41
3.5.42
Falsework for Elevated Structures
Check that the size and arrangement of falsework members are inaccordance with the drawings, if any
Check that base plates are adequate
Check that falsework is free of risk of impact by vehicles or siteplant
3.5.43
3.5.44
3.5.45
3.5.46
3.5.47
3.5.48
3.5.49
Top Down Construction
Check that the approved/agreed method statement is followed
Check that enclosing walls show no signs of defect or lack ofsoundness
Check that before excavation takes place that the highest new decklevel is in place and has achieved sufficient strength to provide lateralprop forces
Check that during excavation there is no unexpected deflection on thehighest deck level and subsequent new floor levels
Check that at new deck levels adequate reinforcement or fixtures arein place to locate, support and restrain floors at joints with walls andcolumns
Check that excavation does not proceed below defined levels or inexcess of defined bay widths
Check that columns are adequate to accept substructure loads and areadequately braced or restrained at all times
47
Table 53.5 Check List of Specific Tasks For Contractor's T2 (Cont'd) Sheet 5 of 5Type of Tasks : Routine Safety Supervision
Project: Type(s) of Works :
TCP filling in this check list
Name: Signature: Date :
Item
No.
3.5.50
3.5.51
3.5.52
3.5.53
3.5.54
3.5.55
3.5.56
DescriptionSite Formation
Check that existing nullahs and watercourses are properly diverted
Check that monitoring stations are installed when necessary and thatthe readings are taken
Check that piezometers, where required, are properly covered andmaintained and readings taken at the frequency required
Check that angle of cutting is within specified limits
Check that loose material or boulders are not present at the crest orintermediate benches of slopes
Prior to forecast heavy rainstorms and during rainfall events, inspectslopes to check that temporary drainage is adequate and thatunexpected channels or conduits do not develop
Check that access scaffolding for slope works is secure andperiodically maintained
Satisfactory
Yes NoNot
Applicable
Record of Instruction of Rectification Works
Instruction given to : __ (Functional Stream:. ., Grade of TCP:.
Item No. Instruction of Rectification
Record of Referral
Item No Person Referred tn Functional Stream Grade of TCP
48
Table 53.6
Project:
Check List of Specific Tasks For Contractor's TlType of Tasks : Routine Safety Supervision
Sheet 1 of 5
Type(s) of Works :
TCP filling in this check list
Name : Signature : Date :
Sharing duties of other TCPs :_
ItemNo,
3.6.1
3.6.2
3.6.3
3.6.4
3.6.5
3.6.6
3.6.7
3.6.8
3.6.9
DescriptionGeneral and Minor Safety Aspects
Check that there are arrangements for access and egress of vehicleswhich are satisfactory and do not endanger the public or other roadusers
Check that scaffolding is adequately secured to the building toprevent collapse
Check that the erection of hoarding and/or covered walkways hasbeen erected to secure safety of the public in accordance with thehoarding plan agreed by the Building Authority
Check that there is adequate installation of catch fans, catchplatforms and protection screens as necessary to secure safetyagainst falling objects
Formworkfor Concrete
Check that formwork for concrete is inspected by a competentperson before pouring of concrete
Structural Erection
Check that suitable anchorage points are provided for theattachment of safety harnesses and lifelines or a safety net isinstalled where the distance of fall exceeds two meters
Check that safety lines are used to prevent any dangerous swing ofsteel works being raised or lowered by crane
Structural Support for Plant and Machinery
Check that fixing and supports for plant and machinery are secure
Cranes and Hoists
Check that crane fixing and supports are secure
Satisfactory
Yes NoNot
AppJicabSe
49
Table 5.3.6 Check List of Specific Tasks For Contractor's Tl (Cont'd) Sheet 2 of 5Type of Tasks : Routine Safety Supervision
Project: Type(s) of Works :
TCP fil
Name :
ItemNo.
3.6.10
3.6.11
3.6.12
3.6.13
3.6.14
3.6.15
3.5.16
3.6.17
3.6.18
3.6.19
3.6.20
3.6.21
ling in this check list
Sisnntur^: Date :
DescriptionMan Hoists, Goods Hoists and Gondolas
Check that towers, pulleys and supporting frames are securelyattached to the building
Check that there is free or uninterrupted passage provided forgondolas before they are moved
Check that floor mounted machinery and pulleys are adequatelyfounded and secured by proper fixings
Excavation Plant & Piling Rigs
Check that if operated on ground, state of the ground is fit for useby the plant
Check that if operated on an elevated working platform, theworking platform is adequate to support the plant
Check that rigs, masts, excavator jibs and buckets do not riskstriking members of the public or road users
Stationary Plant, e.g. Compressors and Concrete Batching Plants
Check that fixed plant is securely founded and fixed
Demolition of Superstructure
Check that the approved/agreed method statement is followed
Check that cantilever structures are removed before generaldemolition of each floor
Check that all columns/walls are removed at each floor level beforedemolition of lower floor
Check that restraining guy ropes and/or nets are provided beforeremoval of external walls
Check that before removal of walls, beams or columns, all loadsother than self weight are removed, slot cut is carried out andrestraining guy ropes are provided, where necessary
Satisfactory
Yes NoNot
\pplicable
50
Table 53.6 Check List of Specific Tasks For Contractor's Tl (Cont'd) Sheet 3 of 5Type of Tasks i Routine Safety Supervision
Project: Type(s) of Works :
TCP filling in this check list
Name : Signature : , Date :
ItemNo.
3.6.22
3.6.23
3.6.24
3.6.25
3.6.26
3.6.27
3.6.28
3.6.29
3.6.30
3.6.31
3.6.32
3.6.33
3.6.34
3.6.35
3.6.36
DescriptionDemolition of Superstructure (Cont'd)
Check that supporting scaffolding is provided to lower floors whereappropriate
Check that there is no excessive debris on cantilever or floor slabsand that no build up occurs against external walls
Check that adequate watering is provided
Check that refuse chute or refuse openings are properly located
Check that provision and condition of scaffolding, catch fans,matscreens and heavy duty nylon mats are satisfactory
Check that mechanical plant is operating safely and in accordancewith method statements
Excavation and Lateral Support
Check that the approved/agreed method statement is followed
Check that survey points and other geotechnical instrumentationhave been installed and are regularly monitored and the results kepton site
Check that nearby buildings and ground are not adversely affected
Check that positions of sheet piling or other supports does notconflict with services or adjoining foundations
Check that sheet piles or other vertical members are adequatelysupported prior to and during driving
Check that sufficient layers of horizontal support are provided
Check that pre-loading is in place, where specified
Check that king posts to lateral support systems are provided, ifrequired
Check that raking props are adequately supported and have sufficientand reliable reaction
Satisfactory
Yes NoNot
Applicable
51
Table 5.3.6
Project:
Check List of Specific Tasks For Contractor's Tl (Cont'd) Sheet 4 of 5Type of Tasks : Routine Safety Supervision
Type(s) of Works :
TCP filling in this check listName: — Signature : Date :
ItemNo. Description
tisfactor
Yes NoNot
Applicable
3.6.37
3.6.38
3,6.39
Excavation and Lateral Support (Cont'd)
Check that there is no over-excavation
Check that as excavation proceeds, depth of sheet piles or similarvertical members are in place to sufficient depth to provide adequatecut off and lateral support below current depth of excavation byreference to original design, installation records and characteristics ofsubsoil being excavated
Check that there is no instability of temporary cuttings duringintermediate stages
3.6.40
3.6.41
3.6.42
Falsework for Elevated Structures
Check that the size and arrangement of falsework members are inaccordance with the drawings, if any
Check that base plates are adequate
Check that falsework is free of risk of impact by vehicles or siteplant
Top Down Construction
Check that the approved/agreed method statement is followed
Check that enclosing walls show no signs of defect or lack ofsoundness
Check that before excavation takes place that the highest new decklevel is in place and has achieved sufficient strength to provide lateralprop forces
Check that during excavation there is no unexpected deflection on thehighest deck level and subsequent new floor levels
Check that at new deck levels adequate reinforcement or fixtures arein place to locate, support and restrain floors at joints with walls andcolumns
Check that excavation does not proceed below defined levels or inexcess of defined bay widths
Check that columns are adequate to accept substructure loads and areadequately braced or restrained at all times
3.6.43
3.6.44
3.6.45
3.6.46
3.6.47
3.6.48
3.6.49
52
Table 5.3.6 Check List of Specific Tasks For Contractor's Tl (Cont'd) Sheet 5 of 5Type of Tasks : Routine Safety Supervision
Project : Type(s) of Works :
TCP filling in this check list
Name: Signature : Date :
ItemNo. Description
Satisfactory
Yes NoNot
Applicable
3.6.50
3.6.51
3.6.52
3.6.53
3.6.54
3.6.55
3.6.56
Site Formation
Check that existing nullahs and watercourses are properly diverted
Check that monitoring stations are installed when necessary andthat the readings are taken
Check that piezometers, where required, are properly covered, andmaintained and readings taken at the frequency required
Check that angle of cutting is within specified limits
Check that loose material or boulders are not present at the crest orintermediate benches of slopes
Prior to forecast heavy rainstorms and during rainfall events,inspect slopes to check that temporary drainage is adequate and thatunexpected channels or conduits do not develop
Check that access scaffolding for slope works is secure andperiodically maintained
Record of Instruction of Rectification Works
Instruction given to : '.
Item No. Instruction of Rectification
(Functional Stream;.. ., Grade of TCP:.
Record of Referral
Item No Person Referred to Functional Stream Grade of TCP
53
6 Assessment of Degree of Complexity
Content
6.1 This section explains how the complexity of the building works or street
works is to be dealt with and provides guidance on the descriptive parts of
the Outline Safety Supervision Plan (OSSP) and Detailed Safety
Supervision Plan (DSSP).
Site Description (OSSP)
6.2 Item 1 (i) of the OSSP requires the AP to give a general description of the
works which are to be carried out. The OSSP will be drawn up at an early
stage of the construction process and it is important that the general
description covers the whole of the works which are contemplated at the
time. If the nature of the works changes, then revised OSSPs should be
submitted.
6.3 Item l(ii) requires the AP to give the full address of the site and item l(iii)
requires the Lot Number to be identified. If only part of the site is to be
developed at that time then a reference should be made to this effect on
the Project Location Drawing which is required to be submitted in
Appendix A to the OSSP.
Special Features
6.4 Any special features associated with the site need to be identified in the
OSSP. It is not necessary to explain the significance of special features or
to give advice on how to deal with them. To assist the AP and his
professional advisors in completing the OSSP, a list of typical special
features is set out in Table 6.1 and the OSSP proforma provides a check
list which is to be completed by the AP,
54
6.5 Table 6.1 introduces the special features through a list of questions. If the
answer to any of the questions is positive then the AP with his advisors
should identify the feature and put a tick in the respective box in the
proforma.
Site Description (DSSP)
6.6 Item (1) of the DSSP requires the AP to describe the scope of the works
providing details of the address and lot number. Item l(iv) requires that
the site of the works should be shown on a Works Site Drawing enclosed
in Appendix 1.1 to the DSSP. Revised DSSPs referring to changes to the
works may be referenced to a previous Works Site Drawing.
6.7 Under item l(v), the AP is to list the type of works covered by the DSSP
together with the Type of Plans and approval dates.
6.8 As it will be the usual case that consent is sought and given for only a part
of the whole project works, it is important that Item 1 of the DSSP clearly
defines the extent of the works which are to be supervised and that
amended DSSPs clearly set out the nature and scope of the changes to the
works.
OSSP and Consent
6.9 Item 2 of the DSSP requires the AP to refer-to the OSSP which covers the
works and also that he lists the consents which have been issued to
commence other types of building works or street works within the same
site.
Appraisal of Special Hazards
6.10 The AP is required to submit with his DSSP an appraisal of special
hazards arising out of the listed features. The purposes of this list are to
prepare the grounds for the assessment of the degree of complexity of the
works and to assist TCPs in appreciating the special features of the works
55
and aspects which require special care in supervision. From this part of
the DSSP there is a prompt or reminder to the contractor to assist him in
considering the need for method statements and precautionary and
protective measures. Further details are set out below.
6.11 In respect of the site under item 3(i) of the AP's DSSP, the AP and his
professional advisers should describe in Appendix 1.2 the site in terms of:
• its area;
® approved access points;
•. right of way, if any, that have to be maintained through the site;
« presence of services through the site which have to be protected;
• presence of nullahs or watercourses which have to be maintained in
use.
6.12 In respect of adjacent buildings, slopes, streets and lanes under item 3(ii)
of the AP's DSSP, the AP and his professional advisers should describe,
in Appendix 1.2, all the surrounding features which might be affected by
the works in order to assist the contractor in drawing up precautionary and
protective measures. The description of buildings, slopes, streets and
lanes should include general notes on condition and aspects which have to
be taken into account in planning the works. This section should note the
presence of shallow foundations to adjoining buildings, if known.
6.13 The critical stages of the building works under item 3(iii) of the AP's
DSSP should also be set out in Appendix 1.2, in order that TCPs can plan
their visits and increase the frequency of inspection, if necessary, so as to
provide stringent supervision during the critical stages. The list of critical
stages of the building works and the additional supervision requirements
are set out in Section 8 of this Code of Practice.
56
6.14 The sequence of the proposed buildings works under item 3(iv) of the
AFs DSSP should be described in Appendix 1.2 with special.attention to:
• special programming requirements;
• parts or elements of the works which have to be carried out in a set
sequence;
• parts of the works or other completed works which will be occupied
while the subject works are being constructed;
© details of adjacent works which rely on the completion of the subject
works for support and which will be started during construction of the
works;
• parts of the site or existing buildings which will remain in use during
part or all of the time during which the works will be constructed;
• arrangements for phased handover of the subject works.
6.15 If the sequence of the proposed building works is detailed in prescribed
plans, referral to this plan numbers with the approval dates will be
considered acceptable.
6.16 In respect of the structural design of the building works under item 3(v) of
the AP's DSSP, the AP and his professional advisers should state the
standards, codes and any other relevant guidelines adopted in the
structural design.
Project Attributes Score Sheet
6.17 For each of the types of works listed in the Technical Memorandum, a
standard pro forma known as the Project Attributes Score Sheet (PASS) has
been produced. The PASS allows an assessment of the scale of works and
an assessment of the degree of complexity of the works by quantifying the
level of difficulty of the works and the level of risk associated with the
works. Proformas of these PASSes are provided in the Appendix to this
Section.
57
Pile wall may be part of site formation works and also part of excavation
and lateral support works. In such a case, the consent procedures will
require separate consent to commence the pile wall and then the remainder
of the works. When consent is applied for, the relevant PASS should be
used.
6.18 The AP is responsible for completing the PASS, Where appropriate, the AP
can seek advice from the RSE and other professionals such as his
geotechnical consultant. Prior to completing the relevant PASS for the
building works or street works, the AP needs to address any special features
and hazards associated with the works.
Difficulty
6.19 The criteria used to assess the level of difficulty associated with the works
are set out in the relevant PASS. These criteria can be related to the
particular form of the works, or related to installation procedures, involve
special building materials or be associated with the specified requirements
for specific items. Reference should also be made to special features and
hazards in case these contribute to difficulty as well as risk. When
completing this section of the PASS, the AP is required to select all items
relevant to the works, The individual scores associated with each selected
item are then summed to give an overall score for the level of difficulty.
Risk
6.20 The criteria used to assess the level of risk associated with the works are set
out in the relevant PASS. On-site and off-site risks need to be considered.
These risk criteria can refer to special requirements associated with
executing the works, the location of the works, specified distances or the
presence of particular features on or close to the site. When completing this
section of the PASS the AP is required to select all items relevant to the
works, and determine the sum of the individual scores to give an overall
complexity score for the level of risk.
58
Degree of Complexity of the Works
6.21 Five degrees of complexity associated with building works or street works
have been described in the Technical Memorandum as follows:
a) straightforward works are classed as degree of complexity 1;
b) moderately complex works are classed as degree of complexity 2;
c) complex works are classed as degree of complexity 3;
d) very complex works are classed as degree of complexity 4; and
e) extremely complex works are classed as degree of complexity 5.
6.22 The degree of complexity of the works is obtained from the relevant PASS
by adding together the scores for difficulty and risk. This score from the
PASS is related to the degree of complexity of the works as set out in Table
6.2.
59
Table 6.1 General list of special features
The following items should be regarded as a checklist of special features whichshould be taken into consideration when completing the outline safetysupervision plans.
1. Topography 1.1 Is there a major change in level within oracross the site?
1.2 Is there a major change in level within10m of the site boundary?
1.3 Is it expected that there will be basementstructures within the project?
1.4 Is the site on steeply sloping ground suchthat local failures or instability mighthave effects upslope or downslope
2. Geotechnical setting 2.1 Is there presence of the followingpotentially unfavorable exposures?a) fill;b) marine mud;c) abrupt weathering changes;
2.2 Is there presence of unfavorablediscontinuities in rock face?
2.3 Is the designed groundwater near theground surface?
2.4 Is the site close to or affected by anexisting water course?
2.5 Is the site affected by an upstreamcatchment area?
2.6 Will it be necessary to arrange temporaryor permanent diversion of water coursesaround or within the site?
60
6.1 Genera! list of features (Cont'd)
3. Location in scheduledareas
Is the site located in scheduled areas?
4. Presence of services Are any of the following present in the vicinityof the site and could they affect or be affectedby the works?a) Water mains exceeding 75mm in
diameter
b) Gas mains
c) Drainage pipes exceeding 200mm indiameter
d) Underground electricity cables
e) Overhead cables
5. Construction sequenceand programme
5.1 Is there any top-down method ofconstruction?
5.2 Is there any requirements for shrinkagestrip?
5.3 Is there any construction or demolition ofcantilever over street?
6. Presence of buildingsolder than 40 years inthe vicinity
Is there presence of buildings older than 40years in the vicinity of the site?
7. Adjacent buildings inpoor condition
Are there any buildings in poor conditions inthe vicinity of the site?
Are there any conditions imposed by theBuilding Authority under section 17 of theBuildings Ordinance?
8. Conditions imposed bythe Building Authorityunder section 17 of theBuildings Ordinance
61
Table 6.2 Relationship between the project attributes score and the
degree of complexity of the works
Description of
Complexity of Works
Straightforward
Moderately complex
Complex
Very complex
Extremely complex
Degree of Complexity
of Works
1
2
3
4
5
Project Attributes
Score
0-20
21-40
41-60
61-80
81-100
62
Appendix to 6
Project Attributes Score
• Demolition Works
• Ground Investigation Works
• Foundation Works
• Site Formation / Slope / Retaining Wall / Strengthening / Buried Services
Repair Works
• Excavation and Lateral Support Works
• Cap / Footing / Basement Works
• Superstructure Works
• Curtain wall / Cladding Work
• Alteration and Addition Works
® Street Works
Explanatory Notes
1. A score should be assigned to each item marked thus "O" when thecriteria listed under that item are met.
2. For some items under which several criteria are listed, only the criterionthat attracts the highest score should be selected and the correspondingscore assigned.
3. The selected scores should be circled to identify the criteria that are met.
4. Some of the term used in the Project Attributes Score Sheets are definedas follows:•' "crest of cutting" is at the intersection between the cut slope and the
natural slope.• "pile maximum linear dimension'V denoted by d, is the maximum
linear dimension along any direction measured on the pile horizontalcross section. For a circular pile, this is the diameter; for a rectangularpile, this is the diagonal; for a sheet pile, this is the width.
• "depth of excavation", denoted by e, refers to the vertical distancemeasured from the highest ground level that abuts the pile wall to theproposed lowest bulk excavation level.
63
Project Attributes Score Sheet for Demolition Works Sheet 1 of 2
If more than one item is applicable under one attribute, score will be assigned to only theitem with the highest score.
AssignedScore
1. Difficulty
O Type of construction materials
Reinforced concrete structureTimber flooring/roofMasonry structure - - -Precast / prefabricated structureComposite / steel structurePanel glass structure -Prestressed concrete structure - -
O Special structural elements
Flat slab -Waffle slab - -Beam exceeding 12m in spanWall / column exceeding 6m in storey heightJetty or alikeHanging structure or alike - - - - -Transfer structure or alikeCabled structure or alikeArch structure or alikeOil storage structure or alike - - - - -
O Demolition method
By hand held tool - -By heavy mechanical plant on floor - ~By hydraulic crusher with long arm boomBy wrecking ball - -By implosion -
2. RiskSub-total (A)
O Nearest distance of demolition works from the site boundary, sl m < s < 6 m - _Om < s < 1mProjection over street/footpath
O Height of building to be demolished, hd
10m<hd<50m50m <hd
5101015151520
555
10101515151515
510151515
51015
510
64
Project Attributes Score Sheet for Demolition Works Sheet 2 of 2
O Special element
External finCladding/curtain wall -~ ~ ~ - -Bay windowCantilever structure with span exceeding 1.5m
55
1010
O Near the site
Presence of slope at an average gradient greater than 30° andexceeding 7.5m in height within 5m of the site boundaryPresence of retaining wall greater than 6m in retained heightwithin 5m of the site boundary - - - -Presence of prewar buildings or building in poor conditionsadjoining the site -Presence of party wall structures adjoining the site - -
5
5
55
O Existing structure within the site and retaining a ground leveldifference, h
3m < h < 7.5m
Sub-total (B)
Complexity Score (A) + (B)
3. ScaleTotal floor area to be demolished, Ad (m2)
510
Scale Factor = Ad / 2000m2
AssignedScale Factor
(rounded up to one decimal point and subject to a maximum of 2)
65
Project Attributes Score Sheet for Ground Investigation Works Sheet 1 of I
If more than one item is applicable under one attribute, score will be assigned to only theitem with the highest score.
1. Difficulty
O Sinking borehole with foam as flushing media behind retainingwall within a horizontal distance equal to the height of the retainingwall.
O Sinking borehole on slope at average gradient, 9 and theborehole located at more than 5m above slope toe :
15°<e<30° •30° < 9 < 45°45°<0<60°60° <e
Sub-total (A)
10
10253040
AssignedScore
2. Risk
O Sinking borehole within 5m of an existing building
O Sinking borehole within 5m of MTR structure
O Sinking borehole at the top of an existing retaining wall andwithin a distance equal to the retained height, hw:
3m< hw < 6m6m <hw
O Sinking borehole at the uphill side of slope crest and withina horizontal distance from the crest equal to the vertical height ofslope with average gradient 9 :
30°<9<45°45° < 9
Sub-total (B)
Complexity Score (A) + (B)
3. ScaleNumber of boreholes, N :
Scale Factor = N/100.
(rounded up to one decimal point and subject to a maximum of 2)
5
75
1020
510
AssignedScale Factor
66
Project Attributes Score Sheet for Pile Foundation Works Sheet 1 of 2
If more than one item is applicable under one attribute, score will be assigned to only theitem with the highest score.
1. Difficulty
O Size of pile with maximum linear dimension d,400mm<d< 750mm750mm < d < 2000mm - - ~ ~ ~ -2000mm <d
O Method of installationPercussive and without prescription of predrilling toovercome underground obstructions - - -Non-percussive with casing - - - - - -Percussive with prescription of predrilling to overcomeunderground obstructions - -Non-percussive without casing - - - - - -
O Pile foundation works at more than 5m above slope toe withmaximum linear dimension, d, on slope at an average gradient, 0,
d<400mm and 15°<9<30°d< 400mm and 30°<9<45° ~~ - - -d< 400mm and 45° < 9 - -
d> 400mm and 15°<9<30°d>400mm and 30°<9<45°d> 400mm and 45° < 9 -- «
Sub-total (A)
2. Risk
O Presence of vulnerable features within 5m of the pile foundationworks
Presence of high voltage cable -Presence of gas main - - '• - - ~- - ~ -Presence of footpathPresence of building / elevated structure on pile foundation
Presence of carriageway •Presence of watermain with diameter exceeding 75mmPresence of building / elevated structure on shallow footingPresence of MTR underground structure
O Pile foundation works with pile maximum linear dimension, d,(i) At the uphill side of slope crest and within a horizontal
distance from the crest equal to the vertical height of slopeand/or
Score
51015
55
1015
51015
101520
AssignedScore
5555
10102020
67
Project Attributes Score Sheet for Pile Foundation Works Sheet 2 of 2
(ii) At the top of retaining wall and within a horizontal distancefrom the wall equal to the retained height
d < 400mmd > 400mm
Complexity Score (A) + (B)
3. ScaleCost of the works, C :
Sub-total (B)
Scale Factor = C/$100M
(rounded up to one decimal point and subject to a maximum of 2)
1530
AssignedScale Factor
68
Project Attributes Score Sheet for Insinuating of pile wall (steelchannel planking, sheet piling, pipe piling, sollder piling, bored piling,diaphragm wall or alike and / or grouting) In Site Formation orExcavation and Lateral Support Works
Sheet 1 of 2
If more than one item is applicable under one attribute, score will be assigned to only theitem with the highest score.
1. Difficulty
O Size of pile with maximum linear dimension d,400mm < d < 750mm - - - - -750mm < d < 2000mm2000mm <d
O Method of installationPercussive and without prescription of predrilling toovercome underground obstructionsNon-percussive with casing ~ - - ~ •-»Percussive with prescription of predrilling to overcomeunderground obstructionsNon-percussive without casing
O Pile wall works at more than 5m above slope toe withmaximum linear dimension, d, on slope at an average gradient, 0,
d<400mm and 15°<9<30°30°<9<45°45° < e ' - - -15°<0<30° -30°<9<45°45° < 8
d < 400mmd < 400mmd > 400mmd > 400mmd > 400mm
andandandandand
Sub-total (A)
2. Risk
O Presence of vulnerable features within 5m of the pile wallworks
Presence of high voltage cablePresence of gas mainPresence of footpath - ~ . . - -Presence of building / elevated structure on pile foundationPresence of carriagewayPresence of waterrnain with diameter exceeding 75mmPresence of building / elevated structure on shallow footingPresence of MTR underground structure
Score
51015
55
1015
51015101520
Assigned
555510102020
69
Project Attributes Score Sheet for installing of pile wall (steel Sheet 2 of 2channel planking, sheet piling, pipe piling, solider piling, bored piling,diaphragm wall or alike and / or grouting) in Site Formation orExcavation and Lateral Support Works
O Pile wall works with pile maximum linear dimension, d,(i) At the uphill side of slope crest and within a horizontal
distance from the crest equal to the vertical height of slopeand/or
(ii) At the top of retaining wall and within a horizontal distancefrom the wall equal to the retained height
d < 400mm 75d > 400mm 30
Sub-total (B)
Complexity Score (A) + (B)
3, ScaleCost of the works, C : $
AssignedScale Factor
Scale Factor = C / $ 100M
(rounded up to one decimal point and subject to a maximum of 2)
70
Project Attributes Score Sheet for Site Formation Works, Slope / Retaining Wall /Strengthening Works or Buried Services Repair Works (excluding pile wall) Sheet 1 of 2
If more than one item is applicable under one attribute, score will be assigned to only theitem with the highest score.
Score1. Difficulty
O 1) Cutting in soil greater than 30° and height exceeding 7.5m butnot greater than 15m 5
2) Cutting in soil greater than 30° and height exceeding 15m 10
O Cutting in RockWithout blasting ~ - - 5With blasting - 10
O 1) Soil/Rock fill slope greater than 30° and height exceeding 7.5mbut not greater than 15m 5
2) Soil/Rock fill slope greater than 30° and height exceeding 15m 10
O Tie back/rock dowel in slope and/or retaining wallWithout prestress 10With prestress 20
Sub-total (A)
AssignedScore
2. Risk
O Presence of vulnerable features at the crest or the toe of a proposedcutting and within a horizontal distance from the crest or from thetoe equal to the vertical height of cutting
Presence of gas main - .- ••- - 10Presence of footpath or street 10Presence of building / elevated structure on pile foundation 10Presence of sewage tunnel 10Presence of carriageway - ~ - -.- ' . - • • ~ ~ 20Presence of slope with gradient greater than 30° and heightgreater than 7.5m 20Presence of watermain with diameter exceeding 75mm 30Presence of building / elevated structure on shallow footing 40Presence of retaining wall with height greater than 3m 30Presence of MTR underground structure 50
Sub-total (B)
Complexity Score (A) + (B)
.71-
Project Attributes Score Sheet for Site Formation Works, Slope / Wall /Strengthening Works or Buried Services Repair Works (excluding pile wall) Sheet 2 of 2
3. ScaleCost of the works, C :
AssignedScale Factor
Scale Factor = C/S100M
(rounded up to one decimal point and subject to a maximum of 2)
72
Project Attributes Score Sheet for Excavation and Lateral SupportWorks (excluding pile wall)
Sheet 1 of 2
If more than one item is applicable under one attribute, score will be assigned to only theitem with the highest score.
Score1. Difficulty
O Depth of excavation, e4.5m<e<7.5m - 57.5m<e<12m 1012m<e<18m 2018m<e 30
O Special featuresDesigned ground water level above proposed lowest bulkexcavation level - , 5Requirement for installation of lagging - - 5Requirement for pressure grouting - 10Preloading of strut 20Requirement for tie back . 20
Sub-total (A)
2. Risk
O Presence of vulnerable features at the crest or the toe of a proposedcutting and within a horizontal distance from the crest or from thetoe equal to the vertical height of cutting
Presence of gas main - 10Presence of footpath 10Presence of building / elevated structure on pile foundation 10Presence of sewage tunnel ~ - 10Presence of carriageway 20Presence of slope with gradient greater than 30° and heightgreater than 7.5m - 20Presence of watermain with diameter exceeding 75mm - - 30Presence of retaining wall with height greater than 3m 30Presence of building / elevated structure on shallow footing 40Presence of MTR underground structure 50
AssignedScore
Sub-total (B)
Complexity Score (A) + (B)
73
Project Attributes Score Sheet for Excavation and Lateral Support Sheet 2 of 2Works (excluding pile wall)
3, ScaleCost of the works, C : $ [, _
AssignedScale Factor
Scale Factor = C/S100M
(rounded up to one decimal point and subject to a maximum of 2)
Project Attributes Score Sheet for Gap, Footing or Basement Works Sheet 1 of 2
If more than one item is applicable under one attribute, score will be assigned to only theitem with the highest score.
1. Difficulty
O Depth of excavation, e4.5m < e < 7.5m7.5m<e< 12m12m<e<18m18m <e
O Special features
Designed ground water level above proposed lowest excavation
Requirement for installation of laggingPreloading of strutRequirement for pressure groutingRequirement for tie back _ - -
Sub-total (A)
2. Risk
O Presence of vulnerable features at the crest or the toe of a proposedcutting and within a horizontal distance from the crest or from thetoe equal to the vertical height of cutting
JL resence 01 gas main ""~ ~ - " '"*"* ~""Presence of footpath - -Presence of building / elevated structure on pile foundation -Presence of sewage tunnel - - - - - _ - _ _ . _Presence of carriageway - - - - - - -Presence of slope with gradient greater than 30° and heightgreater than 7.5m - - - - - - - -Presence of watermain with diameter exceeding 75mm - -Presence of retaining wall with height greater than 3mPresence of building / elevated structure on shallow footingPresence of MTR underground structure - : - - - -
Sub-total (B)
Score
5102030
510151520
1010101020
2030304050
AssignedScore
Complexity Score (A) + (B)
75
Project Attributes Score Sheet for Cap, Footing or Basement Works Sheet 2 of 2
3, ScaleCost of the works, C :
AssignedScale Factor
Scale Factor = C/S100M
(rounded up to one decimal point and subject to a maximum of 2)
76
Project Attributes Score Sheet for Superstructure Sheet 1 of 2
If more than one item is applicable under one attribute, score will be assigned to only theitem with the highest score.
1. Difficulty
O Limit state design method
O Construction MaterialsStructural steel or composite constructionConcrete grade > 45DPrestressed concreteTimber
O Structural ElementsFlat slab - - -Waffle slab, ribbed or hollow block slabCantilever structure exceeding 1.5m spanTransfer structure
Score
10101515
5101520
AssignedScore
O Span of beam, L12m<L<18m18m <L
2. Risk
Sub-total (A)
510
O Maximum building height, hb
30m <h b < 100m100m <h b < 200m200m <hb
O TopographyPresence of slope at an average gradient greater than 30° andexceeding 7.5m in height within the sitePresence of retaining wall greater than 6m in retained heightwithin the site
O Presence of vulnerable featuresPresence of building within 5m of the worksPresence of public road adjoining the works
Sub-total (B)
J1020
15
15
1515
Complexity Score (A) + (B)
77
Project Attributes Score Sheet for Superstructure Sheet 2 of 2
3. ScaleConstruction floor Area, Ac (m ) :
Scale Factor = Ac / 50000m
(rounded up to one decimal point and subject to a maximum of 2)
AssignedScale Factor
78
Project Attributes Score Sheet for Curtain Sheet 1 of 1
If more than one item is applicable under one score will be assigned to only theitem with the highest score.
1. DifficultyScore
AssignedScore
O Method of fixingFixing by cast-in anchorFixing by being welded to a structural steel memberFixing by drill-in anchor - - - ~ -Fixing by structural sealant on all sides
Sub-total (A)
2. Risk
O Nearest distance of curtain wall/cladding works from the siteboundary, s
6 m < s < 1 2 m1m < s < 6m -•• • - -•-Arm ^ o *x' 1 tvi -~UII1 _i o v* I ill '
Projection over street/footpath - - -
O Maximum installation height, hi5m < hi < 15m15m<hi<50m
Sub-total (B)
Complexity Score (A) + (B)
3. ScaleAggregate Surface Area, As (m )
5101550
5101520
5152030
AssignedScale Factor
Scale Factor = As / 10000m
(rounded up to one decimal point and subject to a maximum of 2)
79
Project Attributes Score Sheet for Alteration and Addition Works < Sheet 1 of 2
If more than one item is applicable under one attribute, score will be assigned to only the
item with the highest score.
1. Difficulty
O Type of constructionRecasting of concrete element - - ~~ -
Use of weldingUse of anchor boltUse of structural steel or other structural metal
Score
551020
AssignedScore
O Construction of special structural element
Hanging StructureTransfer StructureCantilever Structure
2. Risk
Sub-total (A)
101530
O Nearest distance of alteration and addition works from the publicarea, s
6m<s<12m1 TTI ^ ^ <?*" ^Ttt - •'-•'"•'•
O m < s < l m . . „ - . . ._ . ..... .... .„,,
Projection over street/footpath
O Demolition of Structural element^llaH nf prvntinnmiQ Qnan
Continuous beam - - - - - - - -Column -Structural wall
Sub-total (B)
Complexity Score (A) + (B) •
5101520
5102030
\ \
80
Project Attributes Score Sheet for Alteration and Addition Works Sheet 2 of 2
3, ScaleCost of the works, C :
AssignedScale Factor
Scale Factor = C/$50M
(rounded up to one decimal point and subject to a maximum of 2)
For Alteration and Addition works which are structurally independent from the existing building,the score sheet to be used will be the corresponding sheet for the appropriate type of works.
81
Project Attributes Score Sheet for Street Works Sheet 1 ofl
If more than one item is applicable under one score will be assigned to only theitem with the highest score.
1. Difficulty
•O Type of constructionRigid pavement - -Flexible pavement
O Requirement for traffic diversion
O Requirement for drainage works with pipe size, p300mm < p < 525mm - ....... - ..............p
Sub-total (A)
2. Risk
O Presence of vulnerable features within 5m of the street worksPresence of watermain with diameter exceeding 75mmPresence of gas main .....................Presence of building on shallow footingPresence of pre-war buildingPresence of MTR structure - - - ~ ......... ......
Sub-total (B)
Complexity Score (A) + (B)
3. ScaleCost of the works, C :
Scale Factor = C / $20M
(rounded up to one decimal point and subject to a maximum of 2)
Score
520
20
510
1020203050
AssignedScore
AssignedScale Factor
82
7 Supervision Requirements
Contents
7.1 This section explains how to assess the class of supervision having
determined the degree of complexity. Guidance is given on how to
combine different types of works and how to deploy staff flexibly. The
procedures are summarized in Chart 7.1.
Selecting the appropriate class of supervision
12 Six classes of supervision, denoted A to F, have been established in the
Technical Memorandum,, with class A as the lowest class of supervision and
class F as the highest class of supervision
Class of Supervision Related to Degree of Complexity
7.3 Certain types of works are known to generate more non-conformity than
others. The types of works which are considered to have similar degrees of
concern are grouped into categories as indicated in Table 7.1. A form of
stepped weighting has been introduced such that excavation and lateral
support works, by way of example, have been stepped up by three classes of
supervision to reflect their nature and the possible consequences of non-
conformity. Works which are known to be of less concern, such as ground
investigation and streetworks, have been given low classes of supervision
for the same degrees of complexity. Consequently, the class of supervision
is related not only to the degree of complexity of the works but also to the
type of building or street works.
7.4 Having assessed the degree of complexity of the works, the appropriate
class of supervision can be read directly from Table 7.1 for each type of
works.
83
Determining numbers ofTCPs and frequency of inspection visits
7.5 The initial TCP requirements for each functional stream for each class of
supervision are set out in Table 1 of the Technical Memorandum and
Table 1 also indicates the minimum frequency of inspection. Later
Sections of this Code of Practice explain how resources are to be
increased for large scale works and for critical stages of the works.
TCP qualifications and experience
7.6 The minimum qualifications and experience required for each grade of
TCP are summarized in Table 2 of the Technical Memorandum. Any
persons who satisfy these qualification and experience requirements can
be employed as relevant grades of TCP for site safety supervision
purposes.
7.7 The academic qualifications specified for each grade of TCP must have
been obtained in the appropriate disciplines.
7.8 The academic qualifications that are acceptable for TCPs of grades Tl to
T3 should be in the disciplines set out in Table 7.2.
7.9 Recognition of TCPs' academic qualifications should be based on the
following principles:
(a) Diplomas and certificates must have been awarded by Technical
Institutes which are approved and/or recognized by the Vocational
Training Council.
(b) Higher diplomas and higher certificates must have been awarded
by Technical Colleges which are approved and/or recognized by
the Vocational Training Council.
(c) Bachelor degrees and higher degrees must have been awarded by
universities funded by the University Grants Committee or
recognized by the Hong Kong Institute of Architects, the Hong
Kong Institution of Engineers or the Hong Kong Institute of
Surveyors.
84
(d) For the purpose of this Code of Practice, degrees awarded by
universities or institutes other than those mentioned in (c) above
are classified as higher diplomas.
(e) For the purpose of this Code of Practice, non graduate vocational
qualifications awarded by institutions other than those mentioned
in (a) and (b) above are subject to the agreement of the Building
Authority.
7.10 For TCPs relying on professional qualifications, Table 7.3 sets out
appropriate disciplines.
7.11 In accordance with Table 2 of the Technical Memorandum, T4 may be a
degree holder in a recognized subject with total relevant working
experience of not less than 4 years. Such recognized subject means civil,
structural or geotechnical engineering.
7.12 TCP candidates who have corporate membership of the Hong Kong
Institute of Clerks of Works or the Chartered Institute of Building may be
appointed to T3 posts provided that their experience is satisfactory. A
person who is included in the list of Registered Structural Engineers kept
under the Buildings Ordinance is deemed to be acceptable to be T4 or T5.
7.13 In addition to academic and/or professional qualifications, TCPs are
required to have relevant working experience. The minimum number of
years of relevant working experience for each grade of TCP is stipulated
in Table 2 of the Technical Memorandum. Relevant working experience
is calculated as the sum of the number of years of relevant working
experience gained post qualification and half the number of years of
relevant working experience gained prior to qualification.
85
7.14 Further guidance is given below on the aggregation of relevant
experience:
for Tl -
(ii) forT2-
The relevant experience must have been
gained within the previous 5 years and at
least 1 year of experience must be local site
experience.
Similar to Tl but the experience must be
closely related to the specialist work
category concerned.
(iii) forT3- The relevant experience must have been
gained within the previous 5 years, 2 years
of experience must be local experience,
covering a minimum of 3 types of building
works, and 1 year must be on site.
(iv) forT4andT5- Similar to TL
7.15 It is recognized that at the initial stage of the implementation of the
supervision plan system there may not be sufficient qualified supervisory
personnel who have acquired the required qualifications and experience of
the various grades of TCPs. Therefore, a transitional period as described
in sections 4.6 and 4.7 will be introduced. During the transition period, for
some grades of TCP the absence of. specified qualifications may be
compensated for by extra relevant experience or the lack of sufficient
experience may be compensated for by higher qualifications :
86
Type
of
TCP
Tl
T2
T3
T4
T5
Qualifications and experience which satisfy requirements
for each type of TCP during transition period
No
Formal
Training
Academic Qualification
Certificate Diploma Higher
Certificate
Higher
Diploma
Bachelor
or Higher
Degree
Professional
Qualification
RPE
Equivalent Years of Experience
5
8
12
N/Q
N/Q
2
4
8
N/Q
N/Q
2
4
8
N/Q
N/Q
1
3
5
N/Q
N/Q
1
3
5
N/Q
N/Q
1
1
3
4
N/Q
1 *
1 *
3 *
4 *
5 *
Note:
NQ
Relevant experience obtained before the Professional
Qualification is acceptable
Not qualified
7.16 From time to time the Building Authority may give guidance on bridging
measures which allow competent persons who do not meet the set criteria
to work towards the designated standards. Proposals of acceptance and
upgrading of various levels of qualifications and experience together with
approved topping-up training requirements are to be provided in PNAPs
andPNRCs.
87
Adjustment to supervision resources
7.17 After abstracting the notional supervision resources from Table 1 of the
Technical Memorandum, it may be appropriate to make adjustments to
cover:
• the scale of the works;
© combination of TCPs;
• combination of supervision plans for more than one type of
building works.
Scale of the Works
7.18 As explained in Section 4 above, the effects of the scale of the works, are
considered separately from the complexity of the works. It is necessary to
assign characteristics which may be used to assess the scale of the works
and a list of such characteristics to be used for the assessment of the
various types of building works and streetworks is set down below:
Type of Building Works/Street Works
demolition
ground investigation
site formation
slope/retaining wall/buriedservices repairs
excavation & lateral support
foundation
cap/footing/basement
superstructure
curtain wall/cladding
addition & alteration
street works
Characteristic to be used forAssessment of Scale
maximum floor area of thebuilding to be demolished atone time
number of boreholes
cost
cost
cost
cost
cost
construction floor area
aggregated surface area
cost
cost
88
For each type of building works the appropriate Project Attributes Score
Sheet will list various values of scale factor S for various values of the
characteristics.
7.19 From time to time, the Building Authority will review and amend the
characteristic values to be adopted as benchmarks for various levels of
scale factors.
7.20 Scale factor may be defined as a ratio of the estimated value of the
characteristic chosen to assess the scale of the building works or street
works versus a scale factor of unity. The scale factors are capped at 2,
7.21 The basis of the scale assessment is that for a scale factor of unity, a full
day is expected to be devoted to inspection on each occasion that the site
is visited by a TCP except when the TCP needs to undertake Level 5 - full
time supervision.
7.22 Scale factors of more than 1 would attract extra supervision input which
would be provided by increasing the frequency of inspections or by
increasing the numbers of TCPs. Scale factors of less than 1 would allow
visits of duration less than one full day but at the same frequency. The
minimum frequency of visits as set out in the Technical Memorandum
may not be reduced.
7.23 When the scale factor exceeds unity, the scale factor may be applied in
two ways to increase the level of supervision input in addition to the base
level provided in Table 1 of the Technical Memorandum.
These are:
(a) to upgrade the level of supervision carried out for each grade of TCP
which is listed in Table 1 in the Technical Memorandum for that
class of supervision; and
89
(b) to increase the number of TCPs required to carry out full time
supervision.
7.24 The frequency levels of inspection, 1 to 5 listed in the Technical
Memorandum, can be quantified in terms of man-days per month as
shown in Table 7.4. As there is a significant difference in input between
levels 4 and 5, further guidance is give in Table 7.5 which subdivides
level 4 to take into account circumstances where more frequent
inspections are required.
7.25 The adjusted supervision input expected from a grade of TCP is the
product of the scale factor and the figures in Table 7.4. If the duties of
TCPs are not to be combined and if the supervision plan is not to be
combined with others, the process of the adjustment is best carried out
using Table 7.6 as follows:
(i) Read the required frequency level of site inspection for a grade of
TCP for the particular Class of Supervision from Table 1 of the
Technical Memorandum and enter into column (1) of Table 7.6.
(ii) Convert this figure to man-days per month, by reference to Table
7.4 and enter into column (2).
(iii) Multiply that figure by the scale factor, S, in order to calculate a
revised figure of man-days per month and enter this figure into
column (3).
(iv) Repeat this process for the other grades involved.
(v) Having calculated the scale enhanced supervision requirements in
man-days per month, take each grade of TCP in turn and with
reference to tables 7.4 and 7.5 assess the best combination in terms
of numbers of TCPs of that grade and the frequency of site visits
to fill in columns (4) and (5).
90
7.26 For full time TCPs, if the scale factor of the works does not exceed 1, full
time attendance is still required to provide continuous supervision. For
full time assignments with scale factors exceeding 1, the number of full
time TCPs is to be increased or the required supervision input extra over
that by one full time TCP is to be combined with that of other higher
grade TCPs.
Principles of Combination of Supervision Resources
7.27 It is common practice to submit, under the Buildings Ordinance, plans for
approval and consent to the commencement of works for sections or
stages of the project. Prior to or at the time of application for consent to
commencement of works, the AP has to lodge a supervision plan such
that, without further provisions to the contrary, there would need to be
many supervision plans.
7.28 In order to reduce the administrative workload and to make the best use of
supervisory resources, as many types of building works or street works as
practicable may be aggregated and covered by one supervision plan
provided that the plans for the respective building works or street works
have been approved by the Building Authority. In such cases, the
separate TCP roles for each type of building works may be combined
together into the duties of one or more persons.
7.29 The main principle of combining resources is that TCPs carrying out
combined supervision duties have to:
• satisfy the most stringent requirements for experience and
qualifications; and
« meet the individual requirements for the disciplines for all types of
works.
91
7.30 As another aid to simplify the deployment of TCPs, a higher grade TCP
may take up the duties of a junior grade TCP in his stream provided that
the requirements for qualifications and experience of the junior grade are
satisfied.
Procedure for Combining Supervision Resources
7.31 In order to combine the resources required for one or more types of
building works, or to combine the roles of junior TCPs within the duties
of a more senior TCP, the principle explained previously for application
of scale factor may be followed and Table 7.7 may be used to facilitate the
calculations.
7.32 The completed Table 7.7 should be submitted together with the
supervision plan.
7.33 It is necessary first to group the types of works under consideration into
non-concurrent and concurrent works. The remainder of the procedures
are explained in notes accompanying Table 7.7.
7.34 The AP and RSE, after calculating the supervision input in accordance
with Table 7.7, may further combine their two streams in accordance with
the same principles.
Completion ofDSSP
7.35 Having assessed the supervision input, the completed figures should be
entered into the DSSP as follows:
Item 6: AP's Representative and TCPs;
Item 10: RSE's Representative and TCPs;
Item 16: RGBC's Representative and TCPs;
Item 22: the RSC's Representative and TCPs.
92
7.36 The DSSP proforma set out in the Technical Memorandum requires an
acknowledgment over the Author's signature that the site management
structure, together with the specific duties and responsibilities of the TCPs,
specific tasks, method and timing for inspecting, reporting and rectifying
any deviations from the site safety requirements for ensuring the site safety
of works are to be in accordance with the Technical Memorandum.
This aspect is covered under the following items of the DSSP:
AP Item 7
RSE Item 11
RGBC Item 17
RSC Item 23
93
Chart 7.1 FLOW CHART FOR DETERMINATION OF THE SUPERVISIONREQUIREMENTS
Identify type of building works
Identify special features and hazardsassociated with the works
Calculate the Project Attributes Score
and the Scale Factor by filling in the
Pro]ect Attributes Score Sheet
Determine the Degree of Complexity
by referring to Table 6.2 of this Code
Determine the class of supervision by
referring to Table 7.1 of this Code
Determine the minimum supervision
requirements and inspection frequency
level by referring to Table 1 of the
Technical Memorandum
Combine supervision resources
Combination of supervision resources
by filling in Table 7.7 of this Code
Determine the required inspectionfrequency level of the corresponding
TCP by referring to Tables 7.4 and 7.5of this Code
Consider additional supervision
requirements at critical stages by
referring to Table 8.1 of this Code
Deploy suitable grades of TCP andenter their names into the
supervision plan
Adjustment of thesupervision resources bytaking the scale of works
into consideration andby filling in the
Table 7.6 of this Code
94
Table 7.1 Class of Supervision In Relation To Degree of Complexity ForVarious Types of Building Works and Street Works
Types of Works
demolitionfoundationsite formationslope / retaining wall / buried services repairspile wallexcavation and lateral support
cap / footing / basementsuperstructurecurtain wall / claddingaddition and alteration
ground investigation that is regarded asbuilding works
street works
Degree of Complexity
1
C
A
A
2
D
B
A
3
E
C
B
4
F
D
C
5
F
E
D
Table 7.2 Appropriate Disciplines for TCPs (Tl to T3 Only) Relying onAcademic Qualifications
Type of Works
ground investigation
foundation
cap / footing /basement
excavation & lateralsupport works
site formation
slope / retaining wall /buried services repairsaddition & alteration
demolition
superstructure
curtain wall/cladding
street works
TCPunder AP
Civil / Structural /Geotechnical Engineering
Building Studies
Building Surveying
Architectural Studies
Civil / Structural /Geotechnical Engineering
Building Studies
Building Surveying
Architectural Studies
TCP underRSE
Civil / Structural /GeotechnicalEngineering
Civil / Structural /GeotechnicalEngineering
TCPunder RGBC/RSC
Civil / Structural /Geotechnical Engineering
Civil / Structural /Geotechnical Engineering
Building Studies
Building Surveying
Architectural Studies
95
Table 7.3 Professional disciplines which are generally acceptable* for
qualifying as TCP of grades T4 and T5
Type of Works
ground investigation
foundation
cap / footing / basement
pile wall
excavation & lateralsupport works
site formation
slope / retaining wall /buried services repairs
addition & alteration
demolition
superstructure
curtain wall/cladding
street works
TCPtinder AP
RPE (Civil,Geotechnical orStructural)
RPE (Civil orGeotechnical)
RA
RPS(BuildingSurveying)
RPE (Civil,Building orStructural)
TCPunder RSE
RPE (Civil,Geotechnical orStructural)
RPE (Civil,Geotechnical orStructural)
RPE (Civil orStructural)
TCPunder
RGBC/RSC
RPE (Civil,Geotechnical orStructural)
RPE (Civil orGeotechnical)
RPE (Civil,Building orStructural)
* For those works, which in the opinion of the Building Authority, require specialized
engineering input, he may specify such other additional requirements he considers appropriate
for qualifying as TCP.
96
Table 7.4 Table Showing Frequency Levels of Site Inspection in Terms of
Man Days Per Month For Works of Scale Factor = 1
Level
Level 5
Level 4
Level 3
Level 2
Level 1
Description
Full time
Quarter-monthly visits
Half-monthly visits
Monthly visit
As and when required
Notional Supervision Input
(Equivalent Man-days per Month)
25
4
2
1
0.5
Table 7.5 Table Showing Adjusted Supervision Input for Works
Requiring Frequent Visits
Frequency Level of
Site Inspection
5
4.3
4.2
4.1
4
Description
Full time on site
Four visits every week
Three visits every week
Two visits every week
Quarter-monthly visits
(One visit every week)
Notional Supervision Input
(Equivalent Man-days
per Month)
25
16
12
8
4
97
Table 7.6 Adjustment to Supervision Resources
Supervision Plan Ref.
Class of Supervision
TCP
1
2
3
4
5
AP* RSB*
Scale Factor S :
Contractor *
Supervision Resources in Equivalent Man Days
Minimum Frequency. Level
of Site Inspectiond)
Notional SupervisionInput
(Man-days / month)(2 )
AdjustedSupervision Input
(Man-days/month)
( 3 )
Number ofTCP
(4)
Adjusted FrequencyLevel
of Site Inspection(5 )
Notes:
(a) * Delete as appropriate.
(b) The relationship of Notional Supervision Input to Minimum Frequency Level of Site
Inspection is shown in Table 7.4 and 7.5.
(c) The Adjusted Supervision Input is the product of the Scale Factor and the Notional
Supervision Input in terms of Man-days per month.
(d) The Adjusted Frequency Level of Site Inspection cannot be lower than the Frequency
Level directly obtained from Table 1 of the Technical Memorandum.
(e) For a part-time TCP, if the Adjusted Supervision Input is more than the Notional
Supervision Input, then by consulting Table 7.4 and 7.5 and entering the adjusted
number of man-days per month, read off the next highest level of supervision, in all
cases rounding up to the higher level.
(f) For a full-time TCP, if the Adjusted Supervision Input is more than the Notional
Supervision Input, then the number of TCPs of that grade needs to be increased
accordingly, rounding up to the nearest whole number.
(g) If the adjusted supervision input for any post exceeds 25 man-days per month, an extra
TCP is required unless the required supervision input extra over that by one full time
TCP is to be combined with the input from other higher grade TCPs.
(h) This table should not be used for supervision plans or resources which are combined.
98
Table 7.7 Combination of TCPs for one or more types of buildings works or street works under one supervision plan prepared byAP/RSE/RGBC/RSC *
Building Works / Street Works
( 1 )
Types ofBuilding works
orStreet works
( 2 )
Groupingof
works
(3 )
Degreeof
Complexity
( 4 )
Classof
Supervision
( 5 )
ScaleFactor( S )
Supervision Input Before Combination
( 6 )
TCPGrade
( 7 )
FrequencyLevel of Site
Inspection
(8)
Notional SupervisionInput
(man-day/month)
(9 )
Adjusted supervisioninput
(5) x (8)(man-day/month)
Combined Supervision Input
( 1 0 )
TCP gradesunder
combination
( i i )TCP post with
combinedduties
( 1 2 )
Summation ofsupervision input
under thecombined TCP
(13 )
No. ofcombined
TCP
(14)
RequiredFrequency
Level of SiteSupervision
Note: 1. * Delete as appropriate.2. All types of building works or street works covered by the supervision will be listed under column (1). They will be grouped in
such a way that any portion of works under one group will not be carried out concurrently with any works under other groups.3. Other notes follow on the next page.
99
Explanatory notes for filling In Table 7.7
1. The first step is to list those types of building works or street works of which supervision
resources are to be combined.
2. Types of works should then be grouped together into concurrent and non-concurrent
works.
3. The Degree of Complexity and Scale Factor for each type of works refers to the Project
Attributes Score obtained from the Project Attributes Score Sheet which is attached to this
Code of Practice.
4. The Class of Supervision refers to Table 7.1 which shows the relationship between Class
of Supervision and Degree of Complexity for various types of building works or street
works.
5. TCP grade and the Frequency Level of Site Inspection required for the required Class of
Supervision can be referred to Table 1 of the Technical Memorandum.
6. Notional Supervision Input corresponding to the Frequency Level of Site Inspection can
be found from Table 7 A.
I. The Adjusted Supervision Input is the product of the Scale Factor and the Notional
Supervision Input.
8. TCP grades that are to be combined are listed in Column 10.
9. Grades of TCP whose duties are to be combined are listed in Column 11.
10. The Supervision Input required for those TCPs who are to be combined is summed up as
the supervision input required for the combined TCP.
I1. The number of combined TCP and Frequency Level of Site Inspection required after the
combination of TCPs can be derived using tables 7.4 and 7.5 using the same technique as
used in Table 7.6.
100
8 Additional Safety Supervision Requirements
8.1 This section explains how the practitioner should deal with features which give rise to a
need for special care in preparing a supervision plan or in carrying out site safety
supervision. These are:
® critical stages of the works;
• method statements;
• precautionary and protective measures; and
• geotechnical aspects of works.
Critical Stages of the Works
8.2 Only the minimum safety supervision requirement is specified in each class of
supervision. Extra supervision resources are required for critical stages of the works.
8.3 Item (3) of the DSSP deals with an appraisal of special hazards which includes critical
stages. In item 3 (iii) of the DSSP, the AP is required to declare that the critical stages
of the works have been taken into account in the preparation of the DSSP and a list of
critical stages will be included along with an appraisal of special hazards within
Appendix 1.2 of the DSSP.
8.4 The contractor's AS should notify the AP and RSE no less than 14 days before
commencing the critical stages of the works, setting out the commencement date and
estimated time for completion of critical stages.
8.5 Additional safety supervision resources are to be allocated to critical stages of the works
based on the following principles:
(a) during critical stages of the works, increased frequency of inspections are to be
carried out;
101
8.7
(b) the extra inspections should incorporate:
(i) a record of the state of completion of the critical stage;
(ii) progress made since the previous inspection;
(iii) a record of any aspects which give rise to concern or potential concern
for safety of the works or the workers on site, or all persons around the
site or adjoining buildings, structures and land; and
(iv) a record of recommendations made and of any actions taken in
respect of (iii).
8.6 The critical stages of the works together with the additional supervision requirements
are set out in Table 8.1. This table may be reviewed from time to time and amended by
the Building Authority taking into account current good practice. In addition, the AP,
RSE or Contractor, may determine that a particular section of the works is particularly
difficult or risk prone or that the consequences of a non-conformity might be serious. In
these cases any party may notify his counterparts that he considers the section of works
to be a critical activity and include it in the DSSP.
During the period in which a TCP is carrying out supervision of critical stages, he is
required also to carry out supervision of other work as appropriate to his grade. In this
case his deployment is deemed to satisfy also the requirements of Table 1 of the
Technical Memorandum in respect of his grade.
Method Statements
8.8 The RGBC and the RSC are required to deal with method statements in Part 3 and
Part 4 respectively of the DSSP.
102
8.9 In preparing a method statement, the working procedures and sequences which are
necessary in order to. achieve the required completed form of the works need to be set
down and any hazards associated with these procedures or sequences of working
identified, together with any additional special features or hazards associated with the
site location.
8.10 There are two types of method statements which require separate action:
(a) method statements which are provided on prescribed plans or on plans that are
not prescribed plans but have to be submitted by the AP/RSE to the Building
Authority for agreement; and
(b) method statements which are provided by the Contractor to deal with a
particular aspect of the works that need not be submitted to the Building
Authority.
8.11 For case (a), the Contractor is not required to submit any further method statement
along with the supervision plan as the plans showing the method statements should
have been submitted previously to the Building Authority. For case (b), the
Contractor has to submit his method statement together with the supervision plan.
Precautionary and Protective Measures
8.12 In completing their relevant parts of the DSSP, the RGBC and the RSC are required to
submit details of precautionary and protective measures which need to be taken to
ensure site safety.
8.13 Precautionary and protective measures associated with building works and street
works are listed in Table 8.2.
103
Geotechnical Aspects of Works
.14 Supervision required for geotechnical aspect of the works may be imposed by the
Building Authority under section 17 (1) of the Buildings Ordinance. Supervision
imposed under this section of the Ordinance is of two types, part-time supervision and
full time supervision. TCPs who are deployed for site safety supervision can also
undertake the duties of the personnel undertaking supervision on geotechnical aspects
of the work or vice versa as long as their qualifications and experience are acceptable
to the Building Authority for carrying out supervision of the geotechnical aspects of
the works and providing they fulfill their obligations as required by the Technical
Memorandum and this Code of Practice.
104
Table 8.1 Additional Supervision Requirements for Critical Stages for Building Works
Type of BuildingWorks
Demolition;Addition andAlterationworks
Foundation
Excavation andlateral support;Site formation;Slope/retainingwall/buriedservices repairs
Superstructure
Dl
D2
D3F4
F5
El
E2
E3
E4
E5
SI
S2
Critical Stages of Works
Demolition of cantilever structure over street
Demolition of hanger structure
Demolition of prestressed concrete memberPiling near the crest of retaining wall within azone contained by a 45° line from the toe ofwall
Piling works within 5m of MTR structure,highway/railway structure or buildingcompleted more than 40 yearsPresence of a watermain with diameterexceeding 200mm, gas main, building onshallow footing or MTR structure within azone contained by a line measured at 60° tothe horizontal from the base of excavation
Construction of diaphragm wall/bored pilewall or installation of sheet pile/pipepile/soldier wall within 5m of MTR structure,highway / railway structure, watermain largerthan 200mm diameter / gas main larger than200mm diameter or building founded onshallow footings
Preloading of struts
Operation of recharging well
All related work when monitoring indicatesmovement of ground or building orgroundwater drawdown exceeding thatallowableConstruction of cantilever structure over street
Construction of elevated structure, likepodium deck, over street
Inspection FrequencyContractor's
T3
Full Time
Full Time
Full TimeFull Time
Full Time
Full Time
Full Time
Full Time
Full Time
Full Time
Full Time
Full Time
RSE's Stream
T43idaily
Daily
DailyBidaily
Bidaily
Bidaily
Bidaily
Bidaily
Daily
Bidaily
Daily
Daily
T2Full Time
N/A
N/AN/A
N/A
N/A
N/A
Full Time
N/A
Full Time
N/A
N/A
Notes:
1. One TCP of the appropriate grade as shown in the above table is required to supervise the critical stagesofworks.
2. For inspection frequency at Daily intervals the TCP is required to carry out site inspection at least onceevery working day.
3 . For inspection frequency at Bidaily intervals; the TCP is required to carry out site inspection at least onceevery other working day.
4. N/A means not applicable.
105
Table 8.2 Precautionary and protective measures for various types ofbuilding works and street works
Type of Building Works Typical PrecautionaryMeasures
Typical ProtectiveMeasures
Demolition;Addition and alterationworks
© Propping of floorsbeneath demolitionarea
• Tie-back• Identifying and
locating services• Warning notices• Prohibition of
working in drop zones
• Catch Fans• Hoardings• Netting
Ground investigationfoundation;Caps/footing/basement
Support to excavationProtection/support toadjoining buildingsMonitoringIndicate position of allservices includingoverhead lines withinthe works
• Fence around drillingrigs, excavations andbored pile openings
• Hoardings
Excavation and lateralsupport;Site formation;Slope/retainingwall/buried servicesrepairs
Pre-loading of strutsVertical supports topropsWelded connectionsMonitoringAdequate drainagearound excavationcrestPrecautionary worksagainst heavy rainfallBlast control
• Sealing of existingcracks
• Hoardings• Fencing
106
Table 8.2 Typical precautionary and protective measures for varioustypes of building works and street works (Cont'd)
Type of Building Works Typical PrecautionaryMeasures
Typical ProtectiveMeasures
Superstructure;Curtain wall/cladding
Fence openingsProp floors belowworking floors afterstripping of formworkRestraint to partywallsAdequate propping ofcolumns and wallsafter stripping offormworkTemporary proppingof precast elementsDefined lifting zonesTemporary supports,props or restraint tocladdingProperly designed andsecured rubbish chutes
• Catch fans• Hoardings© Netting (horizontal
and vertical)
Street works Identify and indicatepositions of servicesAdequate propping toexcavationAdequate proppingand restraint to signsand street furnitureAdequate temporarydrainageDefined loading andunloading zones
Concrete trafficbarriersAdequate temporaryfencing and trafficcontrol
107
9 Communication and Reports
Contents
9.1 This section deals with the principles of and procedures for
communication. The procedures for dealing with non-conformity are
illustrated in Chart 9.1.
Interstream Communication
9.2 The requirements for interstream communications are described in the
Technical Memorandum. Interstream communications are afforded the
same priority as within-stream communications in order to facilitate
effective safety supervision.
9.3 It is presumed that TCPs will take all reasonable and practical steps to
inform their counterparts of any aspect of the works which gives rise to
concern or which could give rise to concern on grounds of safety.
Site Safety Supervision Reports
9.4 As set out in the Technical Memorandum, site safety supervision reports
have to be completed by all TCPs whenever they carry out site safety
supervision activities. Subsequently these reports are filed and maintained
at the site office.
Non-conformity Reports
9.5 If a non-conformity arises and comes to the attention of a TCP, the
following procedures will be initiated :
(i) TCP informs the Representative of his functional stream.
(ii) The Representative informs the Representatives of other functional
streams,
(iii) The Contractor's Representative should promptly arrange the
necessary rectification works.
108
(iv) Upon the completion of the rectification works, the Contractor's
Representative will inform the AP's and RSE's Representatives.
(v) If the non-conformity is of a structural nature, the RSE's
Representative will check and satisfy that the rectification works
have been properly completed. For other cases, the AP's
Representative will check and satisfy that the rectification works
have been completed properly.
(vi) If the Contractor's Representative does not initiate the rectification
works or does not carry out the rectification works properly, the
AP's or RSE's Representative, as the case may be, will issue
instruction for proper rectification works.
(vii) If the non-conformity is considered to pose an imminent danger, the
AP's or RSE's Representatives, apart from following the above
procedures will report immediately to the AP or RSE as the case
may be. The AP or RSE upon receiving the report will issue
rectification instruction to the AS and inform the RSE or AP as the
case may be. The AP will also report the case to the Building
Authority.
(viii) If the non-conformity is considered to cause a material concern for
safety and the Contractor does not comply with instructions, the
AP's or RSE's Representative will report to the AP or RSE as the
case may be. The AP or RSE will instruct the AS to initiate action
immediately and inform the RSE or AP as the case may be. If the
Contractor still fails to comply promptly with the rectification
instruction, the AP will coordinate further action and report the case
to the Building Authority.
(ix) When the non-conformity has been rectified, the Contractor's
Representative will report to the AP's and RSE's Representatives
who will report to the AP and RSE accordingly. If the report on
non-conformity has previously been submitted to the Building
Authority, the AP will also report to the Building Authority upon
the completion of the rectification works.
109
Chart 9.1 FLOW CHART FOR DEALING WITH NON-CONFORMITY
Non-conformity event
TCP informsRepresentative
of his functional stream
Representative informsother Representatives
Contractor'sRepresentative should arrange
rectification works
Is non-conformityof structural nature?
NO
YES
RSE's Representative willcheck and satisfy adequacyof rectification works and if
necessary instruct rectification
AP's Representative willcheck and satisfy
adequacy of rectificationworks and if necessary
instruct verification
Is non-conformityconsidered to cause material concern
for safety and Contractor failsto comply with rectification
instruction?
Is non-conformityconsidered to poseimminent danger?
Contractor's Representativereports to AP and RSERepresentatives whennon-conformity has
been rectified
APs or RSE's Representativereports to AP or RSE
who will instruct AS totake action and AP will
report to Building Authority
AP's or RSE's Representativereports to AP or RSE
who will instruct AS totake action
AS acts on report ofnon-conformity andrectification process
begins forthwith
AS reports to AP andRSE when non-conformity
has been rectified
AS acts on report ofnon-conformity andrectification process
begins forthwith
AP reports toBuilding Authority
AP reportsto Building Authority
AS reports to AP andRSE when non-conformity
has been rectified
no
/ 0 Minor Deviations from a Supervision Plan
Contents
1.0.1 This section explains how to deal with minor deviations from a
supervision plan.
Absence of TCP due to personal circumstances
10.2 As provided in Section 9.1 of the Technical Memorandum, there will be
occasions when TCPs are absent because of:
® accident;
• illness; and
• emergency
10.3 A substitute TCP of equal or better qualifications and experience is
required to be posted to site within 48 hours and relevant details such as
the substitute's name, identity card number and contact telephone number
are to be entered into the site register.
Unexplained absence or other absence outside the provisions of the
Technical Memorandum or Code of Practice
10.4 Unexplained absences or absences outside the provisions of the Technical
Memorandum or Code of Practice will be addressed by the
Repres'entative(s) of the stream(s) concerned who will enter into the site
register:
(a) the period of absence;
(b) the reasons for the absence; and
(c) the action which has been taken.
111
Other Non-conformity in Supervision Arrangements
10.5 If a non-confomiity arises in supervision arrangements other than the
absence of a TCP and not being a non-conformity in the execution of the
work, method statements, precautionary or protective works, the
following procedure will be initiated:
(i) TCPs when learning of the non-conformity will report to their
respective Representative;
(ii) the respective Representative will request that the supervision
arrangements be rectified;
(iii) in case of non-compliance, the Representative will report to the AP,
RSE or AS, as the case may be; and
(iv) the AP, RSE or AS, as the case may be, will further request that the
supervision arrangements be properly complied with and if action is
not taken he will report accordingly to Building Authority.
112