Public ForumJanuary 13, 2015
THE SOUTHERNGATEWAY
-
8/10/2019 The Southern Gateway Power Point
2/23
Agenda
1. Regional HOV/Managed Lane Approach
2. Project History and Overview
3. Corridor Section Review
4. Noise Wall Implementation
5. Current Status
6. Path Forward
7. Jefferson-Memorial Project Update
8. Questions & Answers
1
-
8/10/2019 The Southern Gateway Power Point
3/23
1. Regional Managed Lane Approach
2
What are HOV lanes?
Existing High Occupancy Vehicle lanes in the DFW Region in which
motorists can travel for free as long as there are two or more occupants
in the vehicle.
TYPICAL HOV CROSS SECTION
-
8/10/2019 The Southern Gateway Power Point
4/23
1. Regional Managed Lane Approach
3
-
8/10/2019 The Southern Gateway Power Point
5/23
1. Regional Managed Lane Approach
4
What are Managed Lanes?
Managed lanes (MLs) also known as express lanes, TEXpress lanes are tolled lanes
that offer variable alternatives to single-occupant vehicle (SOV) use and increase
throughput using variable pricing, which ensure free-flow service.
Does Managed Lanes take away existing General Purpose Lanes?
No. Managed lanes (MLs) are additional capacities added to the existing corridor.
RTC Policy and State Law do not allow free lanes to be converted to tolled lanes.
-
8/10/2019 The Southern Gateway Power Point
6/23
1. Regional Managed Lane Approach
5
Regional Transportation Council (RTC), the transportation policy board
for the Metropolitan Planning Organization (MPO) comprised of 44 members
(local elected or appointed officials) established the Regional Managed Lane
Policies.
TxDOT implements the policies set by the RTC.
-
8/10/2019 The Southern Gateway Power Point
7/23
1. Regional Managed Lane Approach
6
-
8/10/2019 The Southern Gateway Power Point
8/23
1. Regional Managed Lane Approach
7
-
8/10/2019 The Southern Gateway Power Point
9/23
1. Regional Managed Lane Approach
8
-
8/10/2019 The Southern Gateway Power Point
10/23
2. Southern Gateway Project History
Began in 2001 as a Major Investment Study, Schematic, and Environmental Assessment (EA) Study limits
o IH 35E from IH 20 to 8th St. (8.6 miles)
o US 67 from FM 1382 to IH 35E (9.4 miles)
Southern Gateway Total Reconstruction Project Original Scopes;
o Total Reconstructiono Additional General Purpose (GP) capacity
o Reversible HOV in center median
o Slip ramps, direct connect ramps, frontage roads, and x-streets
Fully directional interchanges at IH 20 for IH 35E and US 67
Estimated Cost of Total Reconstruction of IH 35E and US 67 - $2 Billion
Policy, staff and community work groups held on regular basis
Five-day Value Engineering (VE) Study completed
Public Involvement
o Three series of public meetings
o Three newsletterso Aesthetics Concept Plan
o Project website (www.thesoutherngateway.org)
o Series of public hearings were held in August 2005
Finding of No Significant Impact (FONSI) obtained June 2006
9
-
8/10/2019 The Southern Gateway Power Point
11/23
2. Project Overview
10Template with layouts
The Southern Gateway (TSG)Managed Lane ProjectSegments
Segment 1 IH 35E from US
67 to Reunion Boulevard Segment 2 US 67 from FM
1382 to IH 35E Segment 3 IH 35E from IH
20 To US 67
Adjacent Projects
Dallas Horseshoe (Blue)
-
8/10/2019 The Southern Gateway Power Point
12/23
2. Project Overview
Managed Lanes Project
Focus on reconstruction of IH 35E from north of the IH 35E/US 67 split to Colorado Blvd.
Improve safety by flattening the Zang Curve on IH 35E
Add managed lane capacity south of the IH35E/US67 split utilizing existing pavement.
During the 83rd Legislature, the Southern Gateway project was granted the authority tobe developed as a Public-Private Partnership project. The project is proceeding with theintent to develop the partnerships and a financial package for a procurement that istentatively expected to be complete during the 84th Legislature in 2015.
11Template with layouts
-
8/10/2019 The Southern Gateway Power Point
13/23
2. Project Overview
TSG Goals
Improve mobility in Southern DallasCounty
Improve safety on IH 35E and US 67
Bring dilapidated facility condition up tocurrent standards.
Minimize negative EnvironmentalImpacts
Provide affordable, cost effectivetransportation solutions
12Template with layouts
Provide uniform connectivity with adjacent projects such as the Horseshoe Identify options for delivery of the ultimate corridor improvements Utilize public private partnership delivery to accelerate scheduled
improvements Identify long term delivery options. Provide a design that is sensitive to needs of different neighborhoods,
promote walkable & bicycle communities by ensuring that major cross streetsat frontage roads include crosswalks and wide outside share lanes.
-
8/10/2019 The Southern Gateway Power Point
14/23
3. Corridor Section Review
I-35E/US67 TO MARSALIS
MARSALIS TO COLORADO
FULL RECONSTRUCTION WITH MANAGED LANES
FULL RECONSTRUCTION WITH MANAGED LANES
13
-
8/10/2019 The Southern Gateway Power Point
15/23
3. Corridor Section Review
MANAGED LANES IMPLEMENTATION
PROPOPOSED FULL RECONSTRUCTION
14
-
8/10/2019 The Southern Gateway Power Point
16/23
-
8/10/2019 The Southern Gateway Power Point
17/23
3. Corridor Section Review
PROPOSED FULL RECONSTRUCTION
MANAGED LANES IMPLEMENTATION
16
-
8/10/2019 The Southern Gateway Power Point
18/23
4. Noise Wall Implementation
17Template with layouts
2006 Schematic/EA
established initial
noise wall location
based on FullReconstruction.
TSG Managed Lanes
Project will provide
corridor wide noise
wall implementation.
-
8/10/2019 The Southern Gateway Power Point
19/23
4. Noise Wall Implementation
18Template with layouts
I-35E North Section - Full Reconstruction
US 67 South Section - Managed Lane Implementation
Noise wall
Noise wall
-
8/10/2019 The Southern Gateway Power Point
20/23
5. Current Status
Dallas District Advance Planning is working on two phased project scope
Southern Gateway Managed Lanes Project
Design schematic, Interstate Access Justification Report, Design Exceptions approval by Spring
2015 Anticipated Public Hearing Spring 2015
Anticipated environmental clearance by Summer 2015
Full Reconstruction of IH35E and US 67
Updating of the 2006 Finding of No Significant Impact (FONSI)
Estimated environmental clearance by Fall 2016
Strategic Project Division coordinating feasibility Working on construction and Operation & Maintenance costs
Working on Traffic & Revenue projections
Working on Financial Analysis Working on recommendations for project delivery
19Template with layouts
-
8/10/2019 The Southern Gateway Power Point
21/23
THE SOUTHERN GATEWAY PROJECT SCHEDULE
Task Anticipated Duration
ROW Mapping/Utility Survey Investigation Summer/Fall 2013
Develop/Evaluate Alternatives Summer/Fall 2013
Public Meeting (March 27) Spring 2014
Develop Managed LaneSchematic/Environmental Document
Summer 2014 Spring 2015
Issue Request for Qualifications Spring 2015
Public Hearing Spring 2015
FONSI Summer 2015
Selection and Award Spring 2016
Construction begins Fall 2016
Service Commencement Fall 2019
Note: All dates are subject to change
6. Path Forward
20
-
8/10/2019 The Southern Gateway Power Point
22/23
7. Jefferson-Memorial Project Update
21Template with layouts
Overview Provides direct access
to/from I-35E to TrinityParkway and Downtown
Central Business District
Current Status Feasibility study that
considers four build
conceptualalternatives havebeen developed andare under evaluationalong with the No-Build alternative.
-
8/10/2019 The Southern Gateway Power Point
23/23
8. Questions & Answers