The PV Policy Group Project
SECOND THEMATIC WORKING GROUP MEETING
Friday 05 May 2006- in Athenes, Greece
Presentation
Monitoring European Position Paper and Action PlanF. JUQUOIS, C. URBSCHAT, A. VEIGEL, I. WEISS
Intelligent Energy Europe (EIE) / PV Policy Group –
EIE/04/058/S07.38564
• Who are the relevant users of a European wide PV monitoring system and therefore which are the relevant key data to be monitored?
• If target groups and key data are defined: What are best data collection methods to get the respective data?
• If data collection methods are designed: Who is suitable to be in charge managing the whole monitoring system nationally and at European level?
• data interpretation and communicationPV Policy Group – 2nd Thematic Working Group Meeting
European Position Paper – Key question
European Position Paper – Target groups and key datas
PV Policy Group – 2nd Thematic Working Group Meeting
Key information Relevance of data for target groups (low, medium, high)
Data about the development of National PV support schemes and National legal frameworks for PV installations (“PV Policy Monitoring”)
Policy makers: highAdministrative bodies: highIndustry: highPublic: high
Data about the development of National PV market segments and type of systems used (“PV Market monitoring”)
Policy makers: mediumAdministrative bodies: mediumIndustry: highPublic: low
Data about the National PV sector developments like capacities, turnovers, employment etc. (“PV Sector Monitoring”)
Policy makers: highAdministrative bodies: highIndustry: mediumPublic: low
Data about the development of system performance, technical evolutions and quality aspects (“PV System Monitoring”)
Policy makers: mediumAdministrative bodies: highIndustry: mediumPublic: high
PV Policy Group – 2nd Thematic Working Group Meeting
European Position Paper – Target groups and key datas
Input (= Efficiency)
Output (= Effectiveness)
PV regulatory framework
PV support schemes
PV monitoring
systems
Market Development
Industry Development
PV Price Development
Nat
ion
al
PV
Po
licy
Fra
mew
ork N
ation
al P
V S
ector
Develo
pm
ent
Objective: to measure & compare the performance of national PV policy frameworks
PV Image & Acceptance
Input (= Efficiency)
Output (= Effectiveness)
PV regulatory framework
PV regulatory framework
PV support schemes
PV support schemes
PV monitoring
systems
PV monitoring
systems
Market Development
Industry Development
PV Price Development
Nat
ion
al
PV
Po
licy
Fra
mew
ork
Nat
ion
al
PV
Po
licy
Fra
mew
ork N
ation
al P
V S
ector
Develo
pm
ent
Objective: to measure & compare the performance of national PV policy frameworks
PV Image & Acceptance
PV Policy Group – 2nd Thematic Working Group Meeting
European Position Paper – key data for policy monitoring
Key data Measurement in
Yearly new installed capacity and total installed capacity reached by the end of the ye
MW per anno / MW total
Yearly new installed plants and total number of plants by the end of the year
Numbers per anno / Numbers total
Yearly new PV electricity produced by all new installed systems and total electricity production produced by all systems in the respective year
MWh per anno /MWh total
Yearly amount of national budget spent for PV support schemes
Euro per anno
Yearly amount of national budget spent on monitoring
Euro per anno
Yearly amount of budget spent through feed in tariff or other legislative acts
Euro per anno
PV Policy Group – 2nd Thematic Working Group Meeting
European Position Paper –key data for Market Monitoring
Key data Measurement in
Regional market penetration MW per region per anno
Market segmentation regarding on grid / off grid percentage on grid / off grid per anno
Market segmentation regarding building integration type Percentage free land installation / roof on top /roof integrated / façade per anno
Module type installed Percentage silicon based / thin film per anno
PV system price development Euro per kWp and Euro per kWh
PV module price development Euro per kWp and Euro per kWh
PV Policy Group – 2nd Thematic Working Group Meeting
European Position Paper –key data PV Sector monitoring
Key data about industry Production capacity and yearly production measured by
Employment measured by
Turnover measured by
Import/export relation measured by
Ingots Tons per anno numbers Euro percentage
Wafers MW per anno numbers Euro percentage
Cells MW per anno numbers Euro percentage
Modules MW per anno numbers Euro percentage
Inverters Numbers and MW per anno
numbers Euro percentage
Batteries Numbers and Ah per anno
numbers Euro percentage
Charge regulators Numbers and MW per anno
numbers Euro percentage
Planners MW per anno numbers Euro percentage
wholesalers MW per anno numbers Euro percentage
installers MW per anno numbers Euro percentage
PV Policy Group – 2nd Thematic Working Group Meeting
European Position Paper – data collection (germany)
Key data General available sources
Best Source Data collection method
Motivation to provide data by data source? (high, medium, low)
Possibility to oblige data source to provide data? (yes/no)
Costs for best source implementation? (high, medium, low)
Regional market penetration Investor, Solar industry association BSW, grid operators
Investor register low to be investigated
high
Market segmentation on grid / off grid
BSW + Investors
BSW + Investor
Survey (off grid) + register (on grid)
low to be investigated
medium
Market segmentation by building type
Investor Investor register low to be investigated
high
Module type installed Investor Investor register low to be investigated
high
PV system price development
Investor, service providers
Investor register low to be investigated
high
PV module price development
Service providers
Service providers
Survey low to be investigated
Low/medium
PV Policy Group – 2nd Thematic Working Group Meeting
European Position Paper – data management
•who will be the national administrative body running the monitoring system nationally and
collect/serve the national target groups with data?
•and who will run the whole aggregate system on an European level?
PV Policy Group – 2nd Thematic Working Group Meeting
European Position Paper – data communication
•Centralized internet database
•Should we use a centralized internet database also to COLLECT data?
Joint Position Paper and Action Plan MonitoringWhat input do we need from National Position Papers?
* Green Power Balance group representative, which is the institution in charge of managing the promotion scheme of the Green Electricity Act.
1. Present status of national monitoring system
Based on the work already done in 2005 for National profiles the national PV Policy project partners should describe their present national PV monitoring systems in depth
• by listing all nationally researched key data
• its data collection methods and data sources
• institutions responsible for data management
• and ways of data communication.
An effective way is to fill in the following tables for taks force monitoring:
Annex of National Position Paper – present status „Policy monitoring“
* Green Power Balance group representative, which is the institution in charge of managing the promotion scheme of the Green Electricity Act.
Key data Reliable Data on national level presently available?(Yes/no and comments)
Data collection method (e.g. register, some kind of survey, estimation etc.)
Data source(industry, investors, grid operator etc.)
Institution responsible(Name, Address, contact person)
Data communication (public reports, website, internal use etc.)
Yearly new installed capacity and total installed capacity reached by the end of the ye
Yearly new installed plants and total number of plants by the end of the year
Yearly new PV electricity produced by all new installed systems and total electricity production produced by all systems in the respective year*
Yearly amount of national budget spent for PV support schemes
Yearly amount of national budget spent on monitoring
Yearly amount of budget spent through feed in tariff or other legislative acts
Annex of National Position Paper – present status „Market monitoring“
* Green Power Balance group representative, which is the institution in charge of managing the promotion scheme of the Green Electricity Act.
Key data Reliable Data on national level presently available?(Yes/no and comments)
Data collection method (e.g. register, some kind of survey, estimation etc.)
Data source(industry, investors, grid operator etc.)
Institution responsible(Name, Address, contact person)
Data communication (public reports, website, internal use etc.)
Regional market penetration
Market segmentation regarding on grid / off grid
Market segmentation regarding building integration type
Module type installed
PV system price development
PV module price development
Annex of National Position Paper – present status „Industry monitoring“
* Green Power Balance group representative, which is the institution in charge of managing the promotion scheme of the Green Electricity Act.
Key data about industry by- Production capacity and yearly
production- Employment- turnover- import/export relation for:
Reliable Data on national level presently available?(Yes/no and comments)
Data collection method (e.g. register, some kind of survey, estimation etc.)
Data source(industry, investors, grid operator etc.)
Institution responsible(Name, Address, contact person)
Data communication (public reports, website, internal use etc.)
Ingots
Wafers
Cells
Modules
Inverters
Batteries
Charge regulators
* Green Power Balance group representative, which is the institution in charge of managing the promotion scheme of the Green Electricity Act.
2. Action Plan to improve national monitoring systems
Based on the output guidelines the national PV Policy project partners should describe their national actions for improvement of national monitoring in depth by using the following structure:
1. Short description of action goals (based on National Position Paper)
2. Description of respetive working tasks for implementation
3. Description of partners for implementation and their roles
4. Timing and definition of ressources needed task by task (see 2.)
5. Aspects of financing
Joint Position Paper and Action Plan MonitoringWhat input do we need from National Action Plans?
PV Policy Group – 2nd Thematic Working Group Meeting
European Position Paper – Action plan
•Identification of the national contact responsible for the feed in contract,•Checking of the legal possibility for a mandatory European identification number,•Issuing letter of intention from those national contact,•Drafting a proposal aiming at conceiving a European monitoring database.
PV Policy Group – 2nd Thematic Working Group Meeting
European Position Paper – Action plan
• Participants: 8 Energy agency + Relevant ministry (40 000 € + 10 000 €)*16,• 1 consultant with database experience (50 000 €),• 1 developer ( 100 000 €),• 1 structure to make the database sustainable (business model), (50 000 €)• Total budget: 1 M€,• Duration: 2 years.