Page 1: The Primrose East Bridge

PRIMROSE EAST BRIDGE

Implementation of Folded Plate Technology & Geosynthetic Reinforced Soil-Integrated

Bridge System

2016 Concrete Paving WorkshopJason Volz

NDOR Construction

Page 2: The Primrose East Bridge

Primrose BridgePrimrose East Bridge:

• Constructed Fall 2014

• On a county road east of Primrose

• Contractor: Simon Contractors

• Designer: NDOR Bridge Division

Page 3: The Primrose East Bridge

Primrose BridgeNew Technologies:

• GRS Abutment• Folded Plate

Girder• Ultra-High

Performance Concrete

Page 4: The Primrose East Bridge

Geosynthetic Reinforced Soil (GRS) Integrated Abutment:

• Accelerated Construction

• No Crane/Pile Hammer

• No Specialized Labor

Page 5: The Primrose East Bridge

Folded Plate Girder:

• Developed at UNL

• Light Weight

Page 6: The Primrose East Bridge

Ultra High Performance Concrete:

• 21,000 psi at 28-days

• Narrow Joints• Minimal

Shrinkage

Page 7: The Primrose East Bridge

Primrose BridgeOther Innovative Features:

• Pre-Fabricated Bridge Elements

• Accelerated Bridge Construction (ABC)

Page 8: The Primrose East Bridge

DECK CONSTRUCTION:

• Girders Delivered July 1st

• Offsite location used for casting deck

Page 9: The Primrose East Bridge

GIRDER DELIVERY• Elevation and

Layout of Girders Matched Bridge

Page 10: The Primrose East Bridge

SHORED CONSTRUCTION• No Camber in

Girders• Required

Continuous Unyielding Support

Page 11: The Primrose East Bridge

DECK FORMING• Formed and

poured all at once

• Prevented problems with bar interference

Page 12: The Primrose East Bridge

DECK POUR• 47BD-4000• White Pigment/

Wet Burlap Cure

Page 13: The Primrose East Bridge

8” DECK JOINT• Required

exposed aggregate finish.

• Forms treated with set-retarder

• Power washed 12-24 hours after pour

Page 14: The Primrose East Bridge

LIFTING DEVICES• Orientation

required two cranes

Page 15: The Primrose East Bridge

BRIDGE SITE• Large Drainage

Area • Flooding

Overtopped Road

• Road Closed for Construction Sept 15

Page 16: The Primrose East Bridge

GRS ABUTMENT • 2’ Reinforced

Soil Foundation• 13’ GRS

Abutment• 4’ Integrated

Approach

Page 17: The Primrose East Bridge

EXCAVATION• Unsuitable

material removed and replaced with granular fill

• Layout of delivered materials

Page 18: The Primrose East Bridge

REINFORCED FOUNDATION• 2 ft thick

“Burrito” beneath abutment and wings

• Extra layer of fabric on abutment side

Page 19: The Primrose East Bridge

LEVELING COURSE• Critical to

maintaining wall alignment

• <0.5” of granular to help level

Page 20: The Primrose East Bridge

GRS Abutment• Step 1: Place

block

Page 21: The Primrose East Bridge

GRS Abutment• Step 1: Place

block• Step 2: Place

Select Granular Backfill and compact

Page 22: The Primrose East Bridge

GRS Abutment• Step 1: Place

block• Step 2: Place

Select Granular Backfill and compact

• Step 3: Place Geosynthetic Fabric

Page 23: The Primrose East Bridge

CMU BLOCK WALL• Red line at

berm elevation for scour monitoring

• Hollow vs solid block

• Split face block

Page 24: The Primrose East Bridge
Page 25: The Primrose East Bridge

LOADING GIRDERS • 4 -Flatbed

Trucks• 2-Cranes

Page 26: The Primrose East Bridge

SETTING GIRDERS• No rebar

interference problems

Page 27: The Primrose East Bridge
Page 28: The Primrose East Bridge

UHPC EQUIPMENT• 3.5 cuft mixers• Shipped to site

in advance

Page 29: The Primrose East Bridge

UHPC QUALITY CONTROL• All ingredients

are measured out

• Every batch is tested

Page 30: The Primrose East Bridge

UHPC JOINT FORMING• Formed an 1/8”

high• Chimneys at 8’

spacing

Page 31: The Primrose East Bridge
Page 32: The Primrose East Bridge

UHPC JOINT GRINDING• Grind 1/8’” to

remove voids• Hand grinders

vs bump grinder

Page 33: The Primrose East Bridge

VOIDS IN UHPC• Filled with non-

cement grout

Page 34: The Primrose East Bridge
Page 35: The Primrose East Bridge

WATER TESTING OF JOINTS• Joints were

water tight, no additional sealing required

Page 36: The Primrose East Bridge

OPEN TO TRAFFIC• November 19th

Page 37: The Primrose East Bridge
Page 38: The Primrose East Bridge

Special ThanksSimon Contractors:

• Dale Burkhead –Project Manager• Sid Smith – Project Superintendent

NDOR District 3• Steve Trosper – Project Manager• Monty Koch- Project Inspector

NDOR Bridge• Fouad Jaber – Asst. State Bridge Engineer• Steve Ferguson- Designer

Boone County• Darrel Thorin – Highway Superintendent