The Path To A Single Project Controls System With A Primavera Core

Doug Marr Downer Australia

24th April 2012

Overview

• Company Overview• Why Change?• Moving Forward• The Integrated System• Staging the Implementation• The Primavera Core• The Roll Out• Building Stakeholder Confidence• Managing the Life Cycle

Downer Australia – Company Overview

• On 22 February, 2011 Downer announced that its Australian Works, Engineering, Emerging Sectors and CPG Resources businesses would be combined into one division, Downer Australia.

• Downer Australia provides integrated solutions to support the critical infrastructure needs of our customers in the core markets of Minerals & Metals, Oil & Gas, Power, Transport Infrastructure, Water, Communications, Social Infrastructure and Property.

• Downer Australia employs more than 7,000 people and is one of Australia’s largest engineering and infrastructure service providers.

• Downer Australia is committed to Downer Group’s aim of achieving a Zero Harm environment.

PETRO CHEMICAL PLANTS WIND FARMS

Why Change?

• Due to the amalgamation of the different divisions there were separate applications and systems being used.

• Separate system, policies and tools meant– A lack of consistency between divisions– Reporting was inconsistent– Clients received different formatted reports from different areas

of the same business– Inefficiencies could be created internally.

Why Change?

• The decision was made to move to a standardized system that could be able to increase visibility whilst improving quality.

• Stakeholders needed to see quality reports that could make any project transparent and stand up to internal audits and scrutiny.

• Increase stakeholder confidence.

Why Change – The Old System?

6

FinancialSchedulingLabour Database

Document Control

Reporting

PCS RATPAC

Human Resource

Asset Control

Contract Management

Estimating

FAST TRACK

Moving Forward

• Making sense of the existing system by splitting the new Project Controls system into Streams that would align with the main business principles.

Schedule

LabourHours

Estimate

QuantityProgress

Cost

Quality

Document Management

Change Management

Consistency Transparency Repeatability

The Integrated System

SchedulingPlanningReporting

SchedulingPlanningReporting

LabourHoursActual

Earned.

LabourHoursActual

Earned.

EstimatesTimeCost

EstimatesTimeCost

QuantityInstalled

RemainingProductivity

QuantityInstalled

RemainingProductivity

CostBudget

Forecast

CostBudget

Forecast

QualityQA

Handover

QualityQA

Handover

DocumentsDrawingsNotices

Transmittals

DocumentsDrawingsNotices

Transmittals

ChangeVariations

Delays

ChangeVariations

Delays Integrated Project

Controls System

Integrated Project

Controls System

• Applications split into Primary applications and then supporting applications

• Primary Applications were the applications where we performed most of our business functions.

• Supporting applications included Microsoft Office and Adobe Acrobat.

• The framework for the Primary Applications formed the Integrated Project Controls System

Staging the Implementation

Due to the diversity of the business we needed to review all current applications used

With the short list we needed to see what tool aligned with both the business requirements and our clients requirements.

Once the system was designed it was rolled out to a pilot implementation. This pilot program allowed users to ‘test and stress’ the new system to find its limitations.

A full assessment of the capabilities required by each business unit was undertaken. This allowed us to cut applications from the selection process

Once the tool was selected it needed to be added to the design architecture of the overall solution to see if it could be integrated. Also the required hardware could be spec’d.

After successful pilot scheme a staged rollout was implemented.

The Primavera Core

SolutionSchedules and

Planning

SolutionSchedules and

Planning

• Reports for clients• Project Initiation and Execution• Cross divisional communication

Standardisation

• Integration with overall solution• Company wide access to all.• Network architecture required to

support the solution

Access / Integration

• Project Management Initiative subset• Procedures created prior• Policies and Procedures rolled out• Strict guidelines

Systems• Training of key personnel in P6• Corporate Buy In• Field Supervision Buy In

People

The Roll Out

ManagementWithout full management support the project will never gain any momentum. Management directs and guides the separate teams

across the multiple divisions.

The IT department in conjunction with Oracle consultants review, assess, monitor and implement the direction from management. .

Technical Development

Stage 5Stage 5

Management OversightPlan

Project Review and selectionData review and assessment

Divisional RolloutTest

SupportRollout

• Learning's and outcomes of the pilot program are reviewed

Stage 5 Review

• Stage 5 system performance is assessed

Assessment• Data migration plan• Data backup

Stage 6 Initiation

• Project selection• Division selection• Project categorisation

Stage 6 Initiation

• Divisional champions empowered to drive the initiative.

• Continual training and support.Stage 6 Rollout

• Selected projects migrated.

• New projects initiated in new system

Stage 6 Tech

The Rollout

• Divisional Champions assigned to drive the initiative in each area.• Existing projects remain on their current system to maintain continuity.• New Projects commenced on new system.• Continual training and support for all divisions through divisional

champion.

Building Stakeholder Confidence

• Demonstrating consistency, transparency and repeatability on all projects through:– Accurate reports– Clear and concise reports– Dashboards– Minimal time between request and read.– Reduced costs– Improving level of communication

Building Stakeholder Confidence

The only way to truly build stakeholder confidence is to consistently demonstrate project excellence with a standardised system of controls that meets and exceeds client requirements.

Managing the Life Cycle - Initiation

Project WBS created in Estimating tool and

Primavera P6RFT Received.

Completed Estimate handed to Scheduling

Sanity Check made between Schedule and

Budget

Estimate sent to Project Manager to create

budgets in line with original WBS

Managing the Life Cycle - Execution

PCS RATPACActual Hours and

Installed Quantities Entered

Dashboards and Reports

Costs and Accruals entered to financial

system.

Managing the Life Cycle - Closeout

PCS RATPAC

Outputs fed back to Estimating Team

Cost review and assessment.

Budgeted v Actual

Quantity review and assessment

Budgeted v Actual

Schedule review and assessment

Budgeted v Actual