the landfill directive & its implications for remediation · 2005. 6. 30. · the requirements that...

29
The Landfill Directive & its implications for Remediation Jan Gronow Science Manager - Waste & Remediation

Upload: others

Post on 13-Feb-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

  • The Landfill Directive & its implications for Remediation

    Jan GronowScience Manager - Waste & Remediation

  • Contents▪ Requirements & implications of LFD▪ Classification of LF sites▪ Treatment & sorting▪ WAC development▪ The testing hierarchy ▪ Sampling▪ Characterisation▪ Compliance testing▪ Monolithic wastes

  • Acknowledgements

    ▪ Remediation in the context of the LFD Steve Gibbs & colleagues at Atkins Design, Environment Engineering

    ▪ Sampling & Testing:Kathy Lewin, Jane Turrell & Julian Ellis at WRc

    ▪ WACs David Hall & colleagues at Golder Associates (UK) f

  • The Landfill Directive

    ▪ The Landfill Directive & its associated decision document has a significant impact in those parts of Europe that do not have a waste management infrastructure based on incineration.

    ▪ Planning for the required changes gives an opportunity to review:▪ the cost; & ▪ the sustainability of the measures put in place.

  • The requirements that most affect remediation

    ▪ the classification of LFs and the end of the co-disposal of haz with non-haz wastes;

    ▪ prohibition of certain waste types from LF;▪ pre-treatment of wastes before LF; ▪ the general characterisation and testing of waste to

    be landfilled ▪ the setting of waste acceptance criteria for the

    deposit of waste in inert sites and the landfilling of hazardous waste.

  • Waste Acceptance Criteria▪ most waste to be treated prior to Landfillng▪ inert waste sites -limit values define inert waste▪ non-haz sites - demonstrate waste is not haz▪ limit values apply only to SNRHW & wastes co-

    disposed with them ▪ they define SNRHW & ∴treatment objectives for haz

    waste going to non-haz sites▪ others set by permit

    ▪ haz waste sites - defined by EWC & HWD▪ limit values set upper limits for the landfilling of Haz

    waste

  • Hazardous Waste Sites▪ Haz waste defined by new EWC & HWD - not by

    WACs

    ▪ Ban on co-deposit of haz & non-haz wastes,▪ Requirement to treat wastes prior to disposal.▪ Stringent nature of WAC for haz waste sites (TOC

    6% or 10% LOI)

    ▪ even more stringent criteria for the placement of SNRHW (TOC 5%)

  • New categories for soil wereestablished by the revised EWC.17 05 soil (including excavated soil from

    contaminated sites), stones & dredging spoil

    17 05 03* soil and stones containing dangerous substances

    17 05 04 soils and stones other than those mentioned in 17 05 03

    17 05 05* dredging spoil containing dangerous substances

    17 05 06 dredging spoil other than those mentioned in 17 05 05.

  • to landfill a contaminated soil

    ▪ it must have been treated;▪ the resultant product must not be a prohibited

    waste;

    ▪ the product must be characterised ▪ it must be assessed as to whether it is haz or non-

    haz;

    ▪ the product must comply with the WAC for the most appropriate class of landfill.

  • What is Treatment?A physical, thermal, chemical, or biological process (including sorting) that changes the characteristics of waste in order to:▪ reduce its quantity;▪ reduce its hazardous nature; ▪ facilitate its handling (in the LF); or ▪ enhance recovery. Dilution via mixing with uncontaminated media to meet WACs is not acceptable; nor is:▪ bagging▪ wetting▪ compaction

  • Sorting

    ▪ This appears to have potential in the short term for remediation of soils.

    ▪ The segregation of haz soils from non-haz is required & is likely to have economic benefits.

    ▪ If sorting is to be regarded as a treatment, not all of the resulting fractions can be landfilled - one fraction at least must be diverted from landfill.

  • WAC Development

    ▪ A procedure based on GW modelling to establish a relationship between: ▪ the behaviour of inorganic contaminants released by

    leaching from waste in a LF; & ▪ the risk these contaminants pose to GW.

    ▪ Used back-calculation: ▪ from GW quality criteria at specific compliance points

    downstream of the LF;▪ to corresponding limit values for the results of leaching

    tests on the waste ▪ assessed sensitivity to assumptions made & to account for

    this when limit values were set.

  • A Scenario for mobile contaminants

    POC1 POC2

    GWF

    B Concentration at points of compliance

    Waste

    GWL

    C C

    Time Time

    Percolation test data

    1

    10

    100

    1000

    10000

    0.1 1 10L/S (l/kg)

    Con

    cent

    ratio

    n (m

    g/l)

    Time(y)10 100 1000

    100

    1000

    10000

    0.1 1 10L/S (l/kg)Cum

    ulat

    ive

    leac

    hed

    amt (

    mg/

    kg)

    Wash-out

    Time(y)10 100 1000

    POC1

    GWQPOC2

    C

  • Scenario for retarded contaminantsA

    POC1 POC2

    GWF

    Waste

    GWL

    B Concentration at targets

    C

    Time

    Percolation test data

    POC1

    C

    0.001

    0.01

    0.1

    1

    10

    0.1 1 10L/S (l/kg)

    Cum

    ulat

    ive

    leac

    hed

    amou

    nt(m

    g/kg

    )

    Time(y)10 100 1000

    0.001

    0.01

    0.1

    1

    10

    0.1 1 10L/S (l/kg)

    Con

    cent

    ratio

    n (m

    g/l)

    Time(y)10 100 10

    GWQ

  • Three Tier Hierarchy of Testing

    ▪ Level 1 - Characterisation- the responsibility of the person sending the

    waste to landfill

    ▪ Level 2 - Compliance Checking- the responsibility of the operator

    ▪ Level 3 - on-site verification of every load- the responsibility of the operator

  • Sampling

    ▪ There is absolutely no point in doing any testing unless the sample has been chosen correctly

    ▪ For the sampling of waste, a sampling plan shall be developed according to part 1 of the standard (prEN 14899:2004)

    ▪ The plan should include everything from the sampling objectives to the toolbox of appropriate methods for the site specific situation.

  • Basic Characterisation▪ source & origin of the waste;▪ process producing the waste ▪ appearance; ∗ EWC code; ∗ relevant hazard properties; ▪ whether the waste can be recycled or recovered;▪ waste treatment applied (Reg 10(1)) ∗ composition, other characteristic properties & where relevant,

    leaching test values;▪ demonstrate the waste is not prohibited under Reg 9;▪ LF class at which the waste may be accepted;∗ likely behaviour in a LF (& if relevant, leaching behaviour) & any

    precautions to be taken at the landfill; ∗ key variables

  • Characterisation Testing (1)▪ If hazardous - any testing to demonstrate which

    hazard etc. ▪ Composition ▪ there are standard methods for:▪ sample preparation▪ sample digestion▪ analysis of digestate

    ▪ To inform compliance testing▪ key variables▪ variability

  • Characterisation Testing (2)

    ▪ total availability EA NEN 7371:2004▪ pH dependence prEN 14997:2004 or

    prCEN/TS 14429:2003▪ Leaching characteristics▪ upflow percolation prCEN/TS 14405:2003▪ standard leaching ▪ granular BS EN 12457:2002▪monolithic EA NEN 7375:2004

  • CEN TC 292 Model

  • Compliance Testing▪ When waste has been deemed acceptable for LF it

    shall be subject to compliance testing.

    ▪ Compliance testing is to check that the waste complies with the basic characterisation

    ▪ The parameters to be tested are determined by the basic characterisation.

    ▪ The compliance tests used shall be one or more of those used in the basic characterisation.

    ▪ Compliance testing shall be carried out at least once a year at the frequency determined by the basic characterisation.

  • Regularly Generated Wastesderived from a process with well-defined inputs that generates waste with consistent characteristics & constituents within known boundaries▪ requires infrequent characterisation but more stringent

    compliance testing a more inconsistent waste produced regularly as a result of variable inputs &/or a variable ‘recipe’ (e.g. merchant treatment plant, aggregate recovery plant or waste transfer plant). ▪ requires frequent characterisation

    Both types require compliance testing

  • One-off Wastes▪ Compliance testing is required for all wastes

    except ‘one-off’ consignments:▪ Q these are characterised immediately before

    arriving at site;▪ they are individual wastes that exist & where

    all of the waste is available to be sampled for characterisation;

    ▪ characterisation is representative of the whole consignment which might be several loads delivered over several days.

  • Monolithic Wastes

    Generally non-granular, deliberately produced waste forms

    Monolithic WACs produced to provide the same degree of environmental

    protection as the granular ones

  • Characterisation of plant output

    ▪ Wastes entering waste-forming plant must meet TOC or LOI limits

    ▪ plant should provide appropriate number of monolithic testing samples at start-up & whenever the feed to the plant or the ‘recipe’ changes

    ▪ >40mm in any direction ▪ Compressive Strength of 1.5 MPa or greater

    depending on site conditions.

  • Characterisation of wastes for a site risk assessment (1)▪ 8 stage 64 day EA NEN 7375:2004 tank test gives

    long term diffusive leaching from the waste product. ▪ Cumulative data should meet full 64 day leaching

    limit values for monolithic wastes.▪ If a cementaceous binder is used the waste forms

    should cure for 28d, as the test also indicates the longevity of the waste form.

    ▪ The test is to demonstrate that emissions result from diffusion & not from advection or a solubility controlled mechanism

  • Characterisation of wastes for a site risk assessment (2)▪ The following tests on the ground monolith are used

    for LF site risk assessments to:▪ quantify the source term; and ▪ to predict changes in leachability should the

    monolith be overlain by waste of different pH & buffering capacity.

    ▪ max availability for leaching (EA NEN 7371:2004); ▪ pH dependent leaching (prCEN/TS 14429:2003); and▪ calculation of ANC/BNC

  • Compliance testing at the LF

    ▪ A shortened version of the standard 64 day tank test (EA NEN 7375:2004).

    ▪ Cumulative leaching from the first 4 steps of the test is the benchmark for periodic compliance testing.

    ▪ Samples must be >40mm in any direction.▪ There is no requirement to cure the sample ▪ WAC for monolithic wastes are ¼ of the values given

    for Level 1 characterisation.

    ▪ No need to determine EC at compliance.

  • Conclusions

    ▪ The LFD introduces a raft of measures with considerable implications for the remediation of contaminated soils.

    ▪ These measures entail: ▪ increased responsibilities for waste holders to

    characterise their wastes, ▪ a significant increase in the cost of landfilling ▪ a reduction in the number of landfill sites.

    ▪ it is time to invest in treatment technologies that reduce reliance on landfilling.