STANDARDS/STANDARD SPEC. 01-1E-0/2004 01.05.2004
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINEERING PROJECTS GROUP
ENGINEERING DIVISION
SPECIFICATION No. 01-1E
STANDARD SPECIFICATION FOR
CONTRACTOR'S DDOCUMENTS, DATA FILES AND TRANSMITTALS
MAY 2004
Prepared by: M. Ronen J. Weinstock
Checked by: J. Habuba
Approved by: Z. Eyal
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 � Page
STANDARD SPECIFICATION FOR
CONTRACTOR’S DOCUMENTS, DATA FILES AND TRANSMITTALS
TABLE OF CONTENTS
SECTION PAGE No.
1. General …………………………………………………………… 2
2. Quality Requirements …………………………………………… 5
3. Documents Transmittals ………………………………………... 6
4. Mailing of Drawing and Data …………………………………… 12
5. Attachments………………………………………………………. 13
Attachment # 1: Document Transmittal Notice………………… 14
Attachment # 2: Approval Notice ………………………………. 16
Attachment # 3: Instructions for AUTOCAD
Drawings Submitted to IEC……………………… 18
Attachment # 4: Requirements for PDMS Model
and Items to be Agreed Upon………………….. 22
Attachment # 5: Requirements for Technical Data
and Commercial Lists …………………………… 25
Attachment # 6: Software Formats and Versions…………… 52
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 � Page
STANDARD SPECIFICATION FOR
CONTRACTOR’S DOCUMENTS, DATA FILES AND TRANSMITTALS
(STANDARD 01-1E)
1. GENERAL
In accordance with the provisions of the General Conditions and
not derogating from the generalities thereof, Contractor’s
documents, such as: Drawings, Manuals and Instructions (data,
certificates, reports, calculations), Lists and Procedures, etc., shall
be submitted to the Purchaser in accordance with this Standard,
except as supplemented in or modified by the Technical
Specification (Annexure “B”).
1.1 Transmittal Notice
1.1.1 A transmittal notice (example is attached as Attachment # 1) must
accompany the Contractor's documents, as required in the
Specification, and shall include all information listed in para 3.3. All
transmittals received without a transmittal notice containing such
information will be returned to the Contractor. The documents shall
be transferred by electronic mail or digital media, as agreed upon
with the Contractor, and a note shall be made on the official
document transmittal notice. In addition, hard copies may be
submitted and sent by a special courier.
1.2 Document Review and Approval
After award of Contract, all documents shall be submitted, as
required in the Technical Specification, to the Purchaser for review
and/or approval.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 � Page
1.2.1 The Purchaser will review the documents for compliance with
Contract Technical Specifications, mark and stamp same to
indicate changes or corrections, as required. If changes or
corrections are necessary the documents, with such changes or
corrections noted, will be returned to the Contractor.
1.2.2 Submittals requiring the Purchaser’s approval will be returned to
the Contractor, marked as follows:
STATUS 1 -
NO EXCEPTION TAKEN, THE CONTRACTOR MAY
PROCEED WITH FABRICATION OR CONSTRUCTION
STATUS 2 -
THE CONTRACTOR MAY PROCEED, BASED ON
MAKING REVISIONS AS NOTED AND RESUBMIT.
STATUS 3 -
REVISE AS NOTED AND RESUBMIT - HOLD
FABRICATION.
The Contractor shall prepare the APPROVAL NOTICE, as shown in
Attachment # 2, and stamp it on each drawing and document that
requires an approval by the Purchaser according to the Contract.
The Purchaser will provide the APPROVAL NOTICE stamp on
digital media. The size and measures of the APPROVAL NOTICE
stamp should be kept without change.
1.2.3 The review and approval of engineering documents by the
Purchaser does not release the Contractor of any responsibility for
errors or omissions in the work carried out. Faulty, incorrect or
incomplete work resulting from submittal errors shall be corrected
by the Contractor, irrespective of any prior review by the Purchaser.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 � Page
1.3 Design Information
Design information shall be included on correctly identified
drawings (see para 3 for required identifying information). The fact
that such design information may later be included in instruction
and/or operating manuals does not relieve the Contractor from
compliance with this requirement.
1.4 Instructions Manuals
Instruction Manuals (Installation, Operation and Maintenance
Instructions, Erection and Execution of Work Directive and
Assembly Instructions, Storage, Preservation and Shipment
Instructions), shall be submitted in accordance with the
requirements of Annexure "B" - Technical Specification.
1.5 Contractor’s Exceptions
Any exceptions to this Standard shall be clearly indicated in the
Proposal submittal and specifically identified as an exception.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 � Page
2. QUALITY REQUIREMENTS
2.1 General
2.1.1 Documents submitted to the Purchaser shall be of such quality and
with such legibility that hard-copy reproductions may be prepared
by the Purchaser with every line, character and letter clearly legible
and usable for further reproduction.
2.1.2 Documents submitted to the Purchaser that do not conform to the
requirements of this Specification, shall be subject to rejection by
the Purchaser and, upon request, the Contractor shall resubmit
conforming documents. If conforming submittals cannot be
obtained from source documents, such source documents shall be
retraced, redrawn or photographically restored, as may be
necessary to meet such requirements. The Contractor’s (or its
Subcontractors') failure to initially satisfy the legibility quality
requirements herein set forth, will not release the Contractor (or his
Subcontractors) from meeting the required schedule for submittal of
drawings and data.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 � Page
3. DOCUMENT TRANSMITTALS
3. 1. Document Formats:
3.1.1 Documents, excluding drawings, lists and technical data included in
the "Documents Transmittal" list, should be provided in a separate
copy, in its original size and in one of the following formats:
TIF, DOC, RTF, XLS, PDF.
3.1.2 All drawings included in the "Document Transmittal" list should be
provided in a separate copy, in its original size and in AUTOCAD
format. Drawings having VECTOR formats should be provided in
AUTODESK AUTOCAD 2000 DWG ® format that IEC is currently
utilizing. The Contractor is to be notified of any alteration and he
should then update his version accordingly.
Instructions for AUTOCAD Drawings submitted to IEC are attached
as Attachment # 3.
3.1.3 Three (3) dimension design information received on digital media
and included in the "Document Transmittal" list should be provided
in AVEVA PDMS 11.4 ® formats that IEC is currently utilizing. The
Contractor is to be notified of any alteration and he should then
update his version accordingly.
Attachment # 4 outlines the requirements for the PDMS model and
the items to be agreed upon during the meeting, in order to
facilitate the use of PDMS model.
3.1.4 Technical data and lists, as detailed in Attachment # 5, should be
provided in software programs, such as EXCEL or ACCESS
formats that IEC is currently utilizing, running on Windows XP
operating system. The Contractor is to be notified of any alteration
and he should then update his version accordingly.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 � Page
All data should be compatible with IEC's information systems. For
lists not included in Attachment # 5, the exact format and fields will
be determined between the Contractor and the Purchaser during a
meeting, after the Contract has been signed.
3.1.5 The Contractor and the Purchaser will coordinate data exchange
methods during "data exchange session" to be carried out
immediately after the Contract has been signed.
Both parties, the Contractor and the Purchaser, will designate each
one at its site, a person responsible for a smooth and timely data
exchange session.
The Contractor and the Purchaser will agree upon the type, version
and method of data exchange.
The Table in Attachment # 6 depicts the software formats and
versions that IEC is currently utilizing.
3.2 Dimensional System:
The dimensions in all submittals shall be in the metric system. The
English equivalent of principal dimensions and tolerances may be
indicated in adjacent brackets.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 � Page
3.3. Meta-Data File:
Each "Document Transmittal" should be submitted to IEC, attached
with a meta-data file in EXCEL format, including the following
inputs:
Values Size Data
Type
Description
30 String Contractor
15 String Order No.
Value = 0Drawing Value = 1 Instruction Value = 2Manual Value = 3 Other
� String Document Type (Drawing, Instruction, Manual or Other)
25 String Contractor Document/Drawing No.
25 String Sub-Contractor Doc. /Drawing No.
25 String Manufacturer Doc. /Drawing No.
Example: Sheet No.12 of 25 sheets
10 String Sheet No.__ of__ sheets
3 String Revision
90 String Title/Description
Value = M (Mechanical) Value = C (Civil) Value = E (Electrical)
2 String Department (Mechanical, Civil, Electrical)
(A=Approval, I= Information) 12 String Purpose (Approval, Information)
200 string File Name (Attachment Files)
(A0,A1,A2,A3,A4) (A,B,C,D,E,F,G)
2 String Original Size (A0, A1, A2, A3, A4), (A, B, C, D, E, F, G)
(1:1, 1:2, 1:5, 1:10, 1:25, 1:50, 1:100)
10 String Drawing Scale (1:1, 1:5, 1:100…)
15 String Manufacturer
Value = M (Main contractor)
Value = S (Sub contractor) 1 String Manufacturer type (Main Contractor,
Sub-Contractor)
2 String Sub-project
2 String Content
(Physical break-
down)
3 String
IEC W.B.S (Work breakdown
structure)
System
7 String Contract/Specification code
30 String Power Station
2 String Unit
15 String Document Transmittal Number (DT/SI)
12 String UNID (Sequence number of Manufacturer)
15 String Transmittal No.
Date Transmittal date
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 Page
3.4 Sending Documents
3.4.1 "Document Transmittal" should be sent by the following ways:
� E-Mail. Each E-Mail should not exceed the size of 3 MB.
� CD Rom in PC format.
� Other methods to be agreed upon.
3.4.2 Digital Signature
All official documents submitted to the Purchaser by E–Mail should be digitally
signed by the sender, in order to ascertain authenticity and the integrity of the
message contents.
The digital signature should utilize Public Key Infrastructure (PKI) technology
of a well-known commercial Certificate Authority (CA), preferably VeriSign.
The applied system should be supported by Microsoft Outlook 2002 ® and
subsequent versions.
The technical details should be coordinated during the "data exchange
session" (see para 3.1.5).
Digital encryption would be an option and the applicability will be decided
upon during the meeting.
3.4.3 Dates of Delivery
The date to deliver each document and data file will be according to the
Contract schedule.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
3.5 Item Identification:
Each document for a part, component, assembly, sub-assembly or
any other item supplied in accordance with the Project Specification
shall specify the location and methods for identifying the item.
Identification shall include at least the following:
- Drawing and Revision number
- Part number
- Serial number (if applicable)
- Name of Purchaser
- Name of Project
- Unit number
- Purchaser's order
- Contract number
- Name of Contractor
3.6 Drawing Changes:
Identification of changes on all drawings from the previous issue
shall be shown on each drawing.
3.8 Drawing Number:
Each separate drawing submitted to the Purchaser shall have a
discrete drawing number for correct identification. Duplicate pieces
of equipment such as valves, shall not be grouped on one drawing.
They may utilize the same reference drawing, but each valve shall
have a discrete identification number.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
3.9 Submittal Language:
All submittals shall be in English or Hebrew (option of the
Contractor).
3.10 WBS code (if applicable)
Following the first review of the documents, IEC will provide the
appropriate WBS (Work Breakdown Structure) code on digital
media for the relevant document.
The Contractor shall add the WBS code on the approval stamp.
IEC's WBS code is comprised of: Sub-Project Code, Content
(Physical Breakdown) Code and System Code. An example of how
to indicate IEC's WBS Code is given below:
02 – S22 – XX (Sub-Project – Content – System).
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
4. MAILING OF DOCUMENTS
4.1 Shipment Method
All documents in all forms, as required by this Standard and the
Technical Specification, originating outside Israel, shall be
submitted by E-mail, CD Rom in PC format or other method as
agreed upon with the Contractor. In addition, hard-copies may be
submitted and sent by a special courier shipped via Air-Mail, Air-
Express or Air-Freight, depending on the weight. For materials
originating in Israel, the manner of shipment shall be coordinated
with the Purchaser.
4.2 The documents should be provided to the Purchaser in the formats
as indicated in para 3.1 above.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
5. ATTACHMENTS
The following attachments are part of this Standard Specification.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
ATTACHMENT # 1
DOCUMENT TRANSMITTAL NOTICE
(Example)
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
DOCUMENT TRANSMITTAL NOTICE
Definition of Terms
Contractor: Contractor name (Originator of document delivery)
IEC Order No. Order number issued by IEC
Submitted by: The name of the person responsible and signature
Transmittal No.: Contractor's transmittal number
Date: Date of supplied transmittal
Subject: Power Station and Unit number
Specification: Equipment Specification / Contract code
Purpose: Submitted for your - Approval/Review and Comments – A
- Information – I
Manufacturer: Equipment manufacturer
Doc. Type: Type of document. e.g.: 0 = Drawings, 1 = instruction,
2 = manual, 3 = other.
Doc. No. Document number
Sheet No. Sheet No. __ of __ Sheets
Rev.: Revision number
Title: Document title in the following order
System name
Component name
Orig. Size: The original size of the document as submitted
File: Manufacturer's document file name
Dep. IEC's responsible Department, e.g. Mechanical, Civil, Electrical
Remarks: Manufacturer's remarks, e.g. Serial number, Sequence number, Unid,
etc.
W.B.S. IEC's W.B.S. (Work Breakdown Structure) e.g. System code, Sub-
project code, Content (Physical break down) code
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
ATTACHMENT # 2
APPROVAL NOTICE STAMP
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
THE ISRAEL ELECTRIC CORP. LTD.
Engineering Division
APPROVAL NOTICE
REVIEWED FOR
__________________ POWER STATION
UNITS: ___________________________
� Mechanical Department
� Electrical Department
� Civil Department
ST. 1 � NO EXCEPTION TAKEN,
CONTRACTOR MAY
PROCEED WITH FABRICATION
OR CONSTRUCTION.
ST. 2 � CONTRACTOR MAY PROCEED,
BASED ON MARKING REVISIONS
AS NOTED AND RESUBMIT.
ST. 3 � HOLD FABRICATION, REVISE
AS NOTED AND RESUBMIT.
ANY ACTION SHOWN ABOVE IS SUBJECT
TO THE TERMS OF THE CONTRACT AND
DOES NOT RELEASE CONTRACTOR FROM
HIS OBLIGATIONS UNDER THE CONTRACT
INCLUDING DESIGN AND DETAILING.
SPEC. No. ___________________
SUB PROJECT No. ___________
CONTENT(PBS) _____________
SYSTEM ____________________
SIGNATURE _________________
DATE ______________________
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
ATTACHMENT # 3
INSTRUCTIONS FOR AUTOCAD DRAWINGS
SUBMITTED TO IEC
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 � Page
INSTRUCTIONS FOR AUTOCAD DRAWINGS
SUBMITTED TO IEC
1. Unicode should not be used when indicating the measures on
the drawing.
2. Standard definitions of Dimension Style and Text Style should
not be changed.
3. The size of the drawing sheet should not be less than the
minimal size according to ISO (A4).
4. The drawing will be drawn using Decimal units. The English
equivalent of principal dimensions and tolerances may be indicated
in adjacent brackets.
5. All types of dimensions used in the drawing should have a
corresponding "Dimension Style". If the dimensions have been
determined by external application (not by AUTOCAD internal work
environment), take care to define the corresponding "Dimension
Style" correctly. If the "Dimension Style" could not be defined, an
"Explode" command should be given to these dimensions.
6. Only original AUTOCAD "Shape" files should be used.
7. "True Type Fonts" in Hebrew should not be used.
8. The original path of the AUTOCAD for the text font should be
used when defining the "Fonts Style".
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
9. Only IEC's Standard Hebrew Text Fonts should be used. IEC will
provide the Hebrew Fonts for AUTOCAD to the Contractor.
10. "Mline" line types should not be used.
11. Only AUTOCAD standard line types should be used.
12. Irrelevant entities should be deleted from the drawing before
submitting it to IEC.
13. The dimensions should not be included in other Blocks.
14. If "Binding" of "Xref" is performed, the sign "$" should be
removed from all names (LayerName, TextStyle, LineStyle, etc.)
15. The following Files should be attached to each drawing:
� "Text Fonts" files, used in the drawing
� "Xref" files, if applicable.
� "Color Map" (*.pcp) files, compatible to HP printers.
� "Raster image" files, if applicable.
16. The names of the used "Color Map" should be saved in the
same drawing "Layout settings".
17. It is possible to use the following seven basic colors width
(instead para 16):
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
Color Pen Number Width (mm)
Red 1 0.2
Yellow 2 0.6
Green 3 0.4
Cyan 4 0.3
Blue 5 0.7
Violet 6 0.5
White 7 0.2 (0.1)
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
ATTACHMENT # 4
REQUIREMENTS FOR PDMS MODEL
AND
ITEMS TO BE AGREED UPON
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
ITEMS TO BE AGREED UPON DURING THE MEETING
IN ORDER TO FACILITATE THE USE OF PDMS
1. Power plant point of origin.
2. Direction of the North on the isometric drawings.
3. A naming system for the axes of the plant, used exclusively by the two
parts.
4. Type naming of PDMS’ PIPE and VALVE.
5. Terminal points for customer connections will be given by a list which
will define the following items:
� Three (3) D position of the leaving point of the nozzle.
� Three (3) D Orientation of the leaving point of the
nozzle.
� Connection size.
� Connection type.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
THE REQUIRED FORMATS ARE AS FOLLOWS:
1. Three (3) Dimensional model elements (equipment, pipes, foundations,
etc.) will be as a PDMS Databases and PDMS system Databases
with advanced numbering agreement.
2. Two (2) Dimensional drawing originating in PDMS format will be
supplied in the following formats.
� PDMS plot file format or AUTODESK AUTOCAD
2000 DXF® format.
� DRAFT plot sheet file.
3. The Contractor’s piping specification used for creating the model piping
will be supplied in PDMS PARAGON Databases and PDMS system
Databases numbering as agreed upon.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
ATTACHMENT # 5
REQUIREMENTS FOR TECHNICAL DATA AND
COMMERCIAL LISTS
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
REQUIREMENTS FOR TECHNICAL DATA AND
COMMERCIAL LISTS
The supplier should provide all types of list, each having its specific
fields, as detailed below, on a digital media such as EXCEL and
ACCESS structured files, that IEC currently utilizes so, that each field
of the list may be processed by computer programs.
The Data for each Project and Unit should be provided in separate
files.
The records in each file should have a constant structure.
Records should not be split into several records and the content of a
field should not be split into several lines.
Cancelled records should not be deleted. Additional and adjacent field
should be utilized, in order to indicate on it that this record is canceled
and not relevant any more.
Empty fields should not be deleted.
The repeating fields in the different lists in the different files, such as:
Project, Unit, Drawing No., Item No., etc. should be identical.
Any data value should be indicated in the correct field, in such a way
that only one value will be indicated in one field.
The following marks should not appear at the beginning of the fields as
they are reserved marks used for computing infrastructure:
=, @, %, #, &, <, >, etc.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
1. Commercial Lists
1.1. Equipment Shipment Schedule (ESS).
1.2. Packing List of Items.
1.3. Package Header
1.4. Package List
2. Technical Data Lists
2.1. Bill of Materials (BOM)/Parts List.
2.2. Instrument List.
2.3. Connection List
2.4. Electrical Consumer List.
2.5. Cable List
2.6. Materials and Electrical Equipment List
2.7. Motor List.
2.8. List of Input and Output Signals.
2.9. List of Tools and Equipment for Erection and Maintenance.
2.10. List of Field Work and Fabrication.
2.11. Insulation Bill of Materials.
2.12. Drawing List/Data Sheet List.
2.13. Sub-Suppliers List
2.14. List of all Components and Accessories Manufactured in Israel.
2.15. List of all Components and Accessories Manufactured in Countries
other than Israel.
2.16. List of Equipment Requiring Greasing and Lubricating Oil.
2.17. List of Pipes and Data.
2.18. Welding Points List and Data.
2.19. Supports List and Bills of Material.
2.20 Conversion List between IEC's Code and Supplier's Code.
2.21 List of Reinforcement Bar Schedule.
2.22 Embedded Parts List.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.23 Design Calculation List.
2.24 Civil Design Criteria/Load Data/Instructions, Recommendations,
Specifications, Catalog data Sheets/Erection and Construction
Instructions/Consultant Reports.
2.25 Conservation Instructions
2.26 Welding Procedures
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 � Page
DEFINITION OF THE REQUIRED FIELDS FOR EACH LIST
TYPE
The following defines the requirements of the fields for each list:
1. Commercial Lists
1.1. Equipment Shipment Schedule (ESS).
� Project
� Unit
� Item Number (In the ESS)
� Supplier's Item Code
� IEC's Catalog Number
� Description
� Quantity
� Unit of Measure
� Mode of Delivery
� Latest Date of Delivery
� Revised Latest Date of Delivery
� Related Milestone
� Manufacturer's Country of Origin
� Supplier
� Identification Code of Item for Power Plants, such as KKS
(if applicable)
� Attended by
� Remarks/Open Points
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
1.2 Package List
� Project
� Unit
� Delivery Number
� Package Number
� Description
1.3. Package Header
� Project
� Unit
� Package Number
� Contract Number
� IEC's Order Number
� Description
� Type of Package
� Storage Category
� Notes
� Gross Weight (Kg)
� Net Weight (Kg)
� Volume (m3)
� Length (cm)
� Width (cm)
� Height (cm)
� Pack Number of Sub-Supplier
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
1.4 Packing List of Items
� Project
� Unit
� Package Number
� Item Number (In the ESS)
� Supplier's Item Code
� Part Number (in the Drawing)
� Drawing Number
� Drawing revision
� Quantity
� Unit of Measure
� Description
� Designation
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2. Technical Data Lists
2.1. Bill of Materials (BOM)/Parts List
� Project
� Unit
� Order Number
� Drawing Number
� Drawing Revision
� Part Number (In the Drawing)
� Item Number (In the ESS)
� Supplier's Item Code
� Supplier's Name
� Description
� Designation
� Quantity
� Weight
� Unit of Measure (ton, kg)
� Dimensions
� Identification Code of Item for Power Station such as KKS
(if applicable)
� Conservation Code
� IEC's Catalog Number
� Material
� Material ID Number
� Characteristics
� Storage Code
� Erection Step Number
� Dangerous Good Class
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.2. Instrument List
The Instrument List/Index shall include all field instruments, such as: Control
Valves, Solenoid Valves, Limit Switches, etc., as well as all control
instruments (if any), such as: Hand Switches, Recorders, Indicators, etc.
For each Instrument, at least the following data should be included:
� Project
� Unit
� Contractor's/Manufacturer's Tag Number
� IEC's Tag Number
� Manufacturer
� Model Number
� Power Supply (if applicable)
� Enclosure Protection (IP or NEMA)
2.3. Connection List
The Contractor shall provide full data concerning instrumentation primary point
(take-off connections) including:
� Project
� Unit
� Size
� Type (SW, Flange, Screwed, etc.)
� Material
� Rating
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.4. Electrical Consumers List
The Contractor shall provide a list of electrical consumers sorted by type for
Motors, Actuators, Equipment, Cubicles, etc., including the following data:
� Project
� Unit
� IEC's Tag Number of Consumer
� Description
� Manufacturer
� Manufacturer's Tag Number
� Power (KW)
� Rated Voltage
� Rated Current
� Motor RPM
� Quantity/Unit
� Normal Operation Work/Stand-by
� Operation hrs/day
� Area Location
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.5. Cable List
The Contractor shall provide a list of all cables, including the following:
� Project
� Unit
� Cable Type
� Wire Size
� Number of Conductors.
� Descriptive Number
� Location of Starting and Ending Points
� Word Description
� Cable Length
� IEC's Tag Number
� Factory-Mounted or Installed and Wired by IEC
� From Tag Number
� To Tag Number
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.6. Materials and Electrical Equipment List
The Contractor shall furnish a complete list of materials and electrical
equipment with sufficient details to allow for complete identification of all
components of the assembly. The list will include the following:
� Project
� Unit
� Part Identification
� Type
� Manufacturer's Identification
� Description
� Material Specification
� Standard
� Number of Similar Parts
� General Remarks
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.7 Motor List
The Contractor should provide the following data for each motor supplied
under this Contract:
� Project
� Unit
� IEC's Tag Number of Motor/Manufacturer's Identification (type)
� Description/Name of Driven Equipment
� Manufacturer
� Manufacturer's Tag. Number
� Quantity
� Number of Phases
� Rated Horsepower (KW)
� Synchronous Speed (RPM)
� Frequency
� Rated Voltage
� Service Factor
� Power Factor at Full Speed
� Power Factor at 3/4 and 1/2 Load (for motors rated 250 HP and
above)
� Breakdown Torque (for motors rated 100 HP and above) (% of full-
load torque)
� Locked Rotor Torque (for motors rated 100 HP and above) (% of
full-load torque)
� Calculated Continuous Brake Horsepower Required by Driven
Equipment (for motors rated 100 HP and above) at :
o Design Continuous (HP)
o Maximum Capability (HP)
� Rated Current at Full Speed
� Locked Rotor Current (1% of rated current at full load)
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
� Maximum Number of Starts per Hour
� Accelerating Time at Full load under Specified Conditions (for
integrated motors)
� Permissible Stall Time (for integrated motors)
� Efficiency at Full Load (for integrate motors)
� Efficiency at 3/4 and 1/2 Load (for motors rated 250 HP and above)
� Wk2 of the Motor (for motors rated 100 HP and above) (kg/m2)
� Wk2 of the Driven Equipment (for motors rated 100 HP and above)
(kg/m2)
� Enclosure (TEFC, TEAAC, TEAO, etc.)
� Frame (NEMA, IP, IEC)
� Insulation Class
� Maximum Temperature Rise of the Winding at Rated HP
continuously in 0C :
o By resistance (for all integral motors)
o By embedded detector (for integral motors)
� Bearing Type (for all integral motors)
� Are Surge Protection capacitors Required (yes/no)
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 � Page
2.8. List of Input and Output Signals
The Contractor shall provide a list of I/O signals in MS Excel or Access file
format, including:
� Project
� Unit
For the exchange signals:
� Contractor's Tag Name
� Description
� Signal Destination (AI, DI, AO, DO)
� Generic Name of the signal
� Source/destination, field device Tag name
For the hardwired signals the following information shall also be included,
according to the signal type specification:
� Signal type: 4-20 RTD, TC's or other
� Analog signals loop/power definition
� Digital signals type
For the Linked signals:
� Signal source/destination network mode (PLC, computer) address
� Signal address with the network mode (register, bit, etc.)
� Scaling factor, for AI and AO, that has to be used when
coding/decoding the analog value to/from the corresponding digital
value
� If more than one link is used for the connection with PCMS, each
link will then get a number/name. The database will clearly indicate
for each signal to which link it belongs
Separate lists (database files) with exactly the same attributes as defined
above, will be provided for signals between DCS and field or DCS and
systems other than DCS.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.9. List of Tools and Equipment for Erection and Maintenance
The Contractor shall provide a complete list of general tools, special tool and a
separate complete list of maintenance equipment and tools including:
� Project
� Unit
� Description
� Purpose
� Part Number
� Manufacturer
2.10 List of Field Work and Fabrication
The Contractor shall provide comprehensive lists for all field work and field
fabrication work to be performed by IEC, such as:
Temporary work, Scaffolding, Blocking, Shoring, Hanging, Heating, Wiring,
Disassembling, Reassembling, Welding, Preheating, Stress relieving,
Cleaning, Checking, Inspecting, Insulating, Painting, Testing, etc, including:
� Project
� Unit
� Erection Step Number
� Description of Work/Erection Step Description
� Approximately Time for performance
� Subject
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.11. Insulation Bill of Materials
� Project
� Unit
� Supplier's Item Code
� Insulation Material
� Description
� Type of Insulation
� Insulation Purpose
� Minimum Insulation Thickness
� Heat Loss
� Specification
2.12. Drawing List/Data Sheet List
The Contractor shall provide complete list of drawings, technical data sheet,
specifications, instructions, characteristics, curves, diagrams, calculations and
any other document, for each piece of equipment from the Contractor or Sub-
Contractor, including the following data. The Contractor should indicate on the
list which items are being purchased from Sub-Contractor.
� Project
� Unit
� Contractor's Drawing Number
� Sub-Contractor's Drawing Number
� Revision
� Title
� Drawn By
� Drawn Date
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.13. Sub-Suppliers List
� Project
� Unit
� Sub-Supplier's Name
� Type of Equipment Supplied
� Address of Sub-Supplier
2.14. List of all Components and Accessories Manufactured in Israel
� Project
� Unit
� Component/Accessory Description
� Purpose
� Part Number
� Manufacturer
2.15. List of all Components and Accessories Manufactured in Countries
other than Israel
� Project
� Unit
� Component/Accessory Description
� Purpose
� Part Number
� Manufacturer
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.16 List of Equipment Requiring Greasing and/or Lubricating Oil
The Contractor should indicate the following data required for storage,
erection, start-up, and/or maintenance:
� Project
� Unit
� Equipment Description
� IEC's Tag Number (of equipment)
� Manufacturer's Tag No. (of equipment)
� Grease/Oil Specification
� Quantity of grease/Lubricant
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.17 Pipes List and Data
� Project
� Unit
� Identification of Item Code for Power Station such as KKS
� Area
� Description
� Pipe Size
� Pipe Schedule
� Material
� Max Flow (t/hr) at operating condition
� Max Flow (m3/hr) at operating condition
� Pressure at operating condition
� Specific Volume at operating conditions
� Calculated Velocity at operating conditions
� Design Temperature
� Design Pressure
� Design Code
� Required Minimum Valve or Flange Rating
� Piping Code
� Insulation Material
� Type of Insulation
� Insulation Purpose
� Cladding Thickness
� Ambient Temperature
� Minimum Insulation Thickness
� Surface Temperature
� Heat Loss
� Piping Drawing
� Revision
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.18 Welding Points List and Data
� Project
� Unit
� Weld Number
� Pipe Number Identification (KKS)
� NDE ASME Requirements
� Radiation
� Furnace Gases
� Water or Steam
� Location of Weld
� Drawing Number
� Pipe Size
� Outer Diameter
� Minimum Weight
� Nominal Weight
� Weld Size
� DN
� SCH
� Ring Type and Number or Fillet Size
� Material Specification
� Maximum Carbon Content
� Type of Joint
� Jurisdiction
� BP, BEP, NBEP
� Design Temperature
� Design Pressure
� Weld Reference Drawing Number
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.19 Supports List and Bill of Materials
� Project
� Unit
� Drawing Number
� Revision
� Item Number
� Quantity
� IEC's Tag Number
� Supplier's Item Code
� Description
� Type
� Material
� Remarks
2.20 Conversion List between IEC's Codes and Supplier's Code
� Equipment Identification
� IEC's Code
� Supplier's Code
� Sub–Part Description
� Type No. Drawing Number
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.21 Reinforcement Bar Schedule List
� Project
� Unit
� Document Number
� Title
� Revision
� Date
� Contractor
� Manufacturer
� Manufacturer Type (M=Main Contractor, S=Sub-contractor)
� Language
� Document Format (PDF, RTF, XLS)
� Page Size (A4, A3)
� Number of Pages
� Contract Code
� Transmittal Number
� Mode of Delivery
� Remarks/Open Points
� Reinforcement Grade
� Total Mass
� Reference Drawing Number
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.22 Embedded Parts List
� Project
� Unit
� Document Number
� Title
� Rev.
� Date
� Contractor
� Manufacturer
� Manufacturer Type (M=Main Contractor, S=Sub-contractor)
� Language
� Document Format (PDF, RTF, XLS)
� Page Size (A4, A3)
� Number of Pages
� Contract Code
� Transmittal Number
� Mode of Delivery
� Remarks/Open Points
� Steel Grade
� Total Mass
� Corrosion Protection such as:
� Hot dip galvanized
� Painting
� Epoxy coating
� Other
� No coating
� Reference Drawing Number
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 � Page
2.23 Design Calculation List
� Project
� Unit
� Document Number
� Title
� Revision
� Date
� Contractor
� Manufacturer
� Manufacturer Type (M=Main Contractor, S=Sub-contractor)
� Language
� Document Format (PDF, RTF, XLS)
� Page Size (A4, A3)
� Number of Pages
� Contract Code
� Transmittal Number
� Mode of Delivery
� Remarks/Open Points
� Finite Element Model (Program Name)
� Analysis Type, such as:
� Static
� Model
� Harmonic Response
� Response Spectrum
� Load Combinations ( Yes/No)
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.24 Civil Design Criteria/Load Data/Instructions, Recommendations,
Specifications, Catalogue data Sheets/Erection and Construction
Instructions/Consultant Reports
� Project
� Unit
� Document Number
� Title
� Revision
� Date
� Contractor
� Manufacturer
� Manufacturer Type (M=Main Contractor, S=Sub-contractor)
� Language
� Document Format (PDF, RTF, XLS)
� Page Size (A4, A3)
� Number of Pages
� Contract Code
� Transmittal Number
� Mode of Delivery
� Remarks/Open Points
2.25. Conservation Instructions
� Project
� Unit
� Document Number
� Conservation Identification
� Description
� Frequency (Days, Months, Years)
� Remarks
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
2.26 Welding Procedures
� Project
� Unit
� Welding Identification
� Description/Weld Type (Butt/Fillet/Socket)
� WPS/PQR
� Welders Qualification
� Welding Sequence
� Welding Process
� Heat Treatment (Pre/Post)
� NDT (non-destructive Testing)
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
ATTACHMENT # 6
SOFTWARE FORMATS AND VERSIONS
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARDS/STANDARD SPEC.01-1E/2004 01.05.2004
of 53 �� Page
TABLE No. 1 - SOFTWARE FORMATS AND VERSIONS
SOFTWARE
FORMAT
VERSION
CURRENTLY
UTILIZED BY IEC
VERSION TO BE
AGREED UPON
WITH
CONTRACTOR
REMARKS
AUTODESK
AUTOCAD ®
DWG 2000
DXF 2000
AVEVA PDMS ®
11.4
MICROSOFT
EXCEL ®
OFFICE XP
MICROSOFT
ACCESS ®
OFFICE XP
ADOBE READER
(PDF)
5.0
RASTER IMAGE
TIF CCITT GROUP 4
2000dpi
– F I N A L –
Definition of Terms
From: Contractor/Subcontractor name (Originator of document
delivery)
Submitted By: The name of the responsible.
Transmittal No.: Supplier's transmittal number
Date: Date of supplier transmittal.
Subject: Project name Power Station and Unit Number.
Specification: Equipment specification.
Submitted for your: Approval/Review and Comments – A
Information – I
Manufacturer: Equipment manufacturer.
Doc. Type: Type of document. e.g.: 0 = Drawings, 1 = instruction,
2 = manual, 3 = other.
Doc. No. Document number.
Rev.: Revision number
Title: Document title in the following order:
System name.
Component name.
Orig. Size: The original size of the document as submitted.
File: Manufacturer's document file name.
Dep. IEC's responsible department, e.g. Mechanical, Civil,
Electrical
Remarks: Manufacturer's remarks e.g. Serial number., Sequence
number., Unid, etc.
W.B.S. IEC's W.B.S. (Work Breakdown Btructure) e.g. System
code, Sub project code, Physical break down (Content)
code.
For I.E.C use:
Page __ of __
CONTRACTOR:
Submitted by:
Signature:
Power Station Unit
TO: THE ISRAEL ELECTRIC CORPORATION LTD. SUBJECT:
ENGINEERING DIVISION
PROJECT MANAGER,
1 NATIV HAOR ST.,
P.O.BOX 10, HAIFA 31000 ISRAEL
OS= ORIGINAL SUBMITTAL
RS= RESUBMITTAL DUE TO CUSTOMER'S COMMENTS
RV= RESUBMITTAL DUE TO VENDOR'S CHANGES
Manufacturer Doc.
TypeDoc No. Sheet
No.__of__
Sheets
Rev. Title/Description Orig.
Size
File Remarks W.B.S.
Seq. No. Dep. St.
for IEC use:
DOCUMENT TRANSMITTAL NOTICE
I = INFORMATION
A = APPROVAL / REVIEW AND COMMENTS
ATTENTION: MR.____________________
Transmittal No.
Date:
ORDER No.:
DATE:
TRANS. No.:
CONTRACT CODE/SPECIFICATION:
Page 14- 1
Page __ of __
CONTRACTOR:
Submitted by:
OS= ORIGINAL SUBMITTAL
RS= RESUBMITTAL DUE TO CUSTOMER COMMENTS
RV= RESUBMITTAL DUE TO VENDOR CHANGES
Manufacturer Doc No. Sheet
No.__of__
Sheets
Rev. Title/Description Orig.
Size
File Remarks W.B.S.
Seq. No. Dep. St.
Transmittal No.
Purpose: Submitted for your:
DATE: Date:
A = APPROVAL / REVIEW AND COMMENTS
I = INFORMATION
ORDER No.:
TRANS. No.:
Page 14- 2