the exploration prospect contains a development option
DESCRIPTION
The Exploration Prospect Contains a Development Option. - PowerPoint PPT PresentationTRANSCRIPT
PROBLEM #1
CALCULATE THE ECONOMIC VALUE
OF THIS EXPLORATION PROSPECT
(X) (R) (C) (P) Exploration Reserve Development Reserve Cost Size Cost Price (million) (million bbl) (per/bbl) (per/bbl)
$50 0 (pr=½) $5 $4 (pr=½) 50 (pr=¼) $8 (pr=½) 100 (pr=¼)
Expected economic value (prior to exploration) = ___________.
CALCULATE THE ECONOMIC VALUE
OF THIS EXPLORATION PROSPECT
(X) (R) (C) (P) Exploration Reserve Development Reserve Cost Size Cost Price (million) (million bbl) (per/bbl) (per/bbl)
$50 0 (pr=½) $5 $4 (pr=½) 50 (pr=¼) $8 (pr=½) 100 (pr=¼) Note: E(R) = ½0 + ¼50 + ¼100 = 37.5 million bbl E(P) = ½$4 + ½$8 = $6/bbl Thus: E() = ($6-$5)37.5 - $50 = -$12.5 million
$6.25
$25
$100
- $50
- $50
$100
- $50
$250
$100
- $50
-$100
- $50
- $50
$250
-$50
-$150
- $50
Develop
Develop
Develop
Develop
Stop
Stop
Stop
Stop
pr($8) = 1/2
pr($4) = 1/2
pr($8) = 1/2
pr($4) = 1/2
pr(R=50) = 1/4
pr(R=0) = 1/2
pr(R=100) = 1/4
Explore
The Exploration Prospect Contains a Development Option
OCS SALE 123: OPTION VALUE CORRELATIONSBASED ON EVALUATION OF 18 TRACTS
YOUR YOUR OPTION HIGH YOUR AVG HIGH AVGcorrelations: NPV EV VALUE BID BID BID XBID XBID
YOUR NPV 1.00YOUR EV 0.96 1.00
OV 0.30 0.41 1.00HIGH BID 0.25 0.36 0.42 1.00
YOUR BID -0.41 -0.23 0.53 0.27 1.00AVG BID 0.01 0.16 0.53 0.86 0.72 1.00
HIGH XBID 0.21 0.32 0.35 0.99 0.23 0.86 1.00AVG XBID 0.07 0.21 0.47 0.95 0.51 0.97 0.94 1.00
N BIDS 0.15 0.15 0.08 0.60 0.14 0.45 0.65 0.60
Analogy Between Stock Call Option
& Oil Field Development Project
Stock Call Option Oil Field Development Project Current stock price Current value of developed reserve
Variance of stock price Variance of reserve price
Exercise price Development cost
Time to expiration Relinquishment requirement
Riskless rate of interest Riskless rate of interest
Dividend Convenience yield