the examination of possible causes of the lack of success

107
The Examination of possible Causes of the Lack of Success in the Application of Programming Techniques to Build1ng Sites J L. F. Heineck Department of Civil Engineering University of Leeds March 1982

Upload: others

Post on 27-Dec-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The Examination of possible Causes of the Lack of Success

The Examination of possible

Causes of the Lack of Success in the

Application of Programming Techniques

to Build1ng Sites J

L. F. Heineck

Department of Civil Engineering

University of Leeds

March 1982

Page 2: The Examination of possible Causes of the Lack of Success

This work summarizes a series of studies by the author on concepts and difficulties involved in the use of prograaming techniQues in building projects, in particular on house building sites of repetitive nature. It comprises mainly a throughout reviev of the literature, wtth some contributi~ns stemming from the practical research work being undertaken at the Oepartment of Civil EngiAe~ring,

University of Leeds on acttvity•s duration and precedence, as observed on three house building sites.

The report aims to examine possible causes of the lack of success in the application of programming techniques in building companies. These possible causes of the lack of success were sought in tbe following areas:

- the difficulties associated with the implementation of programming techniques in building companies;

- the applicability of the technical concepts introduced by the programming techniques. The following concepts are critically reviewed: activity•s definition, activity's duration, precedence relationship betveen activities, sequence of work on house building sites of repetitive nature, resources reQuired by the activities, productivity modelling, est1mation of activity•s duration and resources required, trade-offs between durations and • resources reQuire~, tqtal level of resources allocated to the project, and tbe setting of objectives criteria;

- the complexities of the programming problem: the inherent complexities of ~he problem and the added complexities introduced by updating and other possibte managerial functions, like stock control, cash flow, and methods study are discussed.

The differences between the theoretical aporoach suggested by the programming techniques on the above areas, mainly in terms of the technical concepts, and the evidence obtained from the observation of the work on building projects are highlighted.

Finally, the report concludes about the relative influence that each of the aspects could have had on the lack of success in the appl1cation of programming techniques. Sug]estions are made on how to use the techniques white solutions to the problems refered to are not found. The problems related to activity•s durations and updating are singled out as the most important po~sible

causes of the lack of success in the application of program~ing techniques. Greater research effort in these areas and the exploration of the capabilities of the programming techn1ques in dealing with time-related aspects, as opposed to their use to perform other ccnstruction management fuctions, are suggested as the course for action in the near future.

Page 3: The Examination of possible Causes of the Lack of Success

1. Introduction •••••••••••••••••••••••••••••••••• 1 2. Some Causes of the lack of Succes in

The Application of Programming Techniques to Building Sites •••••••••••••••••••••••••••••••• 7 2.1 The Probtems associated with the

Implementation of Programming Techniques in Building Companies •••••••••••••••••••••••• 8

2.2 The Appl1cab1lity of so•e Technical Concepts involved in the Programming of Building Sites 2.2.1 lntroduction •••••••••••••••••••••••• 11 2.2.2 The Concepts of Activity•s Oefinitio~,

Duration, Precedence and Sequence of Work •••••••••••••••••••••••••••••••• 14

2.2.3 The Concept of Resources Required by the Activities •••••••••••••••••••••• 17

2.2.4 The Concept of Productivity Hodelling 21 2.2.5 The Concept of Estimating

Activity•s Durations and Resources required •••••••••••••••••••••••••••• 27

2.2.6 The Concept of Time/Cost Trade-off Curves •••••••••••••••••••••••••••••• 2Q

2.2.1 The Concept of the actual Level of Labour Resources available on S1te •• 34

~

2.2.8 Tpe Co~cept of Dbjective Criteria ••• 38 2.3 The Complexities of the Programming Issue

and its Relationship with other Areas of Management • 2.3.1 lntrodu~ion •••••••••••••••••••••••• 43 2.3.2 Some Examples of Research ~ork

1ncorporat1ng other Management Aspects into the Programming of Construction Sites ••••••••••••••••••••••••••••••• 51

2.3.3 The Updating Problem 2.3.3.1 The Decision of when to

update a Project •••••••••••• 54 2.3.3.2 The Relationship betveen

Updating, Site Management and the early Programming of Works 58

3. Su•aarr of Findings, Conclusions and Suggestions for further Work 3.1 Su~mary of Findings •••••••••••••••••••••••• 62 3.2 Conclusions •••••••••••••••••••••••••••••••• 64 3.3 Suggestions for further Work ••••••••••••••• 73

Bibliography

Page 4: The Examination of possible Causes of the Lack of Success

PAGE 1

The simplest of the programming technique~, that

is bar charts, were introduced at the beginning o1 this

century. It can be said that the scheduling of activities in

a project has been a welt researched area during the last 40

years. The deveto~•ent of operational research techniques

during the Second Yorld War and the advent of the network

techniques <CPM and PERT) at the end of the so•s markedly

increased the potentialities associated with project

programm ing.

The new programmin~ tools attracted a great number •

of research workers in the areas of Operaticns research,

Computing and Civil Engineering. The rapid development of

research in this area and the increased capability and

availability of computers made it possible to forecast that

the programming technlques Mould fntroduce revolutionary

approaches to almost every area of management <ptanning,

estimating, c ost contro t, bidding, bonus payment,

motivation, inventory, contractual claims, etc. <Antill and

Woodhead).

The research effort undertaken in the 60's

considered that the network planning techniques could be

Page 5: The Examination of possible Causes of the Lack of Success

PAGE 2

applied undistinctly to the ~hole industry. The Construction

Industry was not treated specifically, even in research vork

done at Civil Eng1neering Oepartments. Ouring the first

years of network use, the building process was consid~red a

good example of a deterministic approach to the planning

problem, while research projects would be a good example of

a probabilistic approach <Antill and Woodheadt.

During the 70's various papers questioned the use

of network planning techniques in the Construction Industry

and other project industries (~ehra, Oavis-1966, and ling).

The use of the.techniques was restricted to large firms, and ~ . .

mainly to the planning stage. Little use was made ot them

during the running of the p~ojects. The theoretical gr~at •

advantages of the use of network planning techniques to

manage the overall process cf construction vere not being •

used (Popescu).

The situation did not change in the late 7C 1 s. The

author decided to investigate some causes of th1s apparent

failure of the programming techniques in chamging t~e face

of management applied to the construction industry.

The author decided to study possible causes of the

lack of success in the application of program•ing techniQues

Page 6: The Examination of possible Causes of the Lack of Success

PAGE 3

to the construction industry. The causes can be sought at

various levels, involving eitber the technical aspects of

the techniques, or the managerial changes that they require.

This work summarizes a series of reports by the

author dealin~ with great part of the technical concepts and

difficult1es associated with the use of programming

techniques in building projects. It looks in particular to

house building of repetitive nature. It comprises mainly a

throughout review of the literature, with some contributions

from the practical research work being undertaken by the

author on the • production characteristics <activity's t •

duration, precedence, and resource requirementsl of three

house building sites. Data foT this latter research work has •

been gathered by the Building Research Establishment using

an activity sampling package• and kindly made available to •

the author. The BRE great contribution and encouragement to

this work is deeply acknowledged.

lt was found convenient to study possible causes

of the lack of success in the apptication of programming

techniques divided in the following areas:

- the implementation of programming techniques in

building companies;

- the technical concepts involved in programmin~;

activity•s definition, activity's duration, precedence

Page 7: The Examination of possible Causes of the Lack of Success

PAGE 4

relationship between activities, sequence of ~ork on house

building sites of repetitive nature, resources required by

the activities, productivity modelling, est1mation of

activity•s duration and r e sou r c e s requ 1 red, tra d··-o f fs

between durations and resources required by the activities,

total level of resources allocated to the projects~ and

setting of oojective criteria;

- the complexities of the plann1ng problem, and

the added complexities of the updating requirements.

Each of the above topics and their subdivisions is

planned to be treated in separate reports. For exampte, "The • . ~

Analysis of Activity•s Duration, Frecedence and Sequence of

Work- Graphical Software to 'enhance the printed Output from •

the Building Research ~stablishment Site Activity ~nalysis

Package• report issued by the author on January 1982 deals

with the analysis of durations found to be far greater tban

would be expected just considering the labour content of

activities divided by the number of men ass1gned to the job,

and the overlappinç of supposedty preceding stages of work,

as observed on three house buildiny s1tes.

The report called •so~e Causes of the Variability

of the Level of Labour Resources assigned to Building Sites

Programmes of Work•, issued on February 1982 reviews

quantitative and qualltative evidence found on the

Page 8: The Examination of possible Causes of the Lack of Success

PAGE 5

l1terature on the tosses and variability that can be

expected in the number of man-hours daily available on s1te.

These tYo reports showed that the approaches

normally used in programming techniques had not been able to

model adequately the production characteristics of some

building sites. For example, activity•s duration are

normally calculated by dividing labour content by the nurnber

of operatives assigned to the job, precedence between

activities is usually of a head and tail type, and the total

level of resources available on site is normally taken as

deterministic by the programming techniques. The reports • • • provided evidence about the lack of direct relationship

between activity•s labour content and durations, the

overlapping nature of the precedence relationship, and the

stochastic tosses that can be expected in the total level of

resources actually available on site. These discrepancies

betveen the concepts of duration estimation, precedence

definitiont and setting of total resource levels could be

causes of the lack of success in the application of

programaing techniques.

~oreover, this present report purports to show

that apart from the discrepanc1es mentioned in tbe last

paragrah, the problems associated with the implementation of

the programming techniques, the modelling inaccuracy of

Page 9: The Examination of possible Causes of the Lack of Success

PAGE 6

other technical concepts, and the complexities of the

progra•ming problem itself are all causes that could be

behind the lack of success in the application of the

scheduling techniques. The whole research project also

envisages to select and modify techniques that could solve

or accomodate the problems that nowadays are hampering

further devetopment in the application of programming tools.

The last chapter, dealing with summary of results,

conclusions and suggestions for further work, tryes to

evaluate criticalty the relative importance of all the

problems affecting the mentioned lack o f success • •

• • Recommendat1ons are made on the course of action in the

application of programming techniques while the difficulties

associated with the technical concepts are not solved.

Page 10: The Examination of possible Causes of the Lack of Success

PAGE 7

Some shortcomings o f the applicat1on o f

programming techniques that have led to the slow dovn on

research work in the area, a state of general cr1ticism• and

lack of confidence regarding their benefits are dtscussed in

this chapter.

In this analyses of the possible causes of the

•• • lack of success 1n the application of programming techniques

to building sites, a chronogical form of diGcussion is be1ng

• presented. First, management should consider the problems

associated with the implementation of the programming

techniques in the company. After that, some trial

applications of the techniques will be done to program the

work on new projects. During these first programming

experiments, management and programmers will face the

difficulties associated with the technical conce~ts, as

described in the previous sections. As these trial projects

go into constructiont the company will experience the

problems related to the updating issue. After a number of

projects, the staff in charge ~ill probably become convinced

of the complexities of the programming issue, as discussed

in the last section of this report.

Page 11: The Examination of possible Causes of the Lack of Success

PAGE 8

First of allt it can be said that the techniques

were oversold to the industry. They were considered capable

of revolutionary innovations on management without the

necessary feedback of trials exper1ments o f their

application. Building companies adopting them vere

expecting great results immediately, which were not

produced. Tne first attempts to use any new technique are

decisive. The success or failure at these initial stages ~

will command its future establishment as a company routine

Csee Popescu and Borcherding) • •

It 1s also worth of mention the difficulties with

the introduction of the programming ,concepts at the various

levels of the company. Programming techn1ques were

understood as a tool that once used would produce good

results: in fact they are a process, requiring the

involvement of a great number of participants in the

project, inside and outside the building firm. For exaapte,

the new tecnniques introduced modifications in the way in

which activities were normally carried out on site,

restricting the scope for decisions by foremen and workers.

There are some evidence that the techniques were not

Page 12: The Examination of possible Causes of the Lack of Success

PAGE 9

explained to foremen and site agents, or understood by tbem.

High levels of management did not participate 1n the

1ntroduction of the new techn1ques in the companr: in

general they were preoccup1ed only with the end results of

them.

The real interest in the techniques and tbe major

effort for their introduction were confined to the eediu•

level of management staff (site managers, production

engineers, and white collar personnel in charge of

controlling the progress of work on sitet. The techniques

really did not go to the sites, they remained to be

applied, discussed and played with at the company 1 s ma in •

office <Adrian-1974).

Generally it was felt a lack of production

information data to feed the programming models. The

programming techniques implicitly called for the parallel

application of work study, method study, and feedback of

production information from previous sites. Few c~mpanies

were able to introduce jointly both programaing techniques

and production data management information systems. Gn the

other handt there has been no great development in research

work trying to obtain more accurate sets of data to be used

in conjunction with the programming techniques. There is a

clear disparity between the capabilities of programming

Page 13: The Examination of possible Causes of the Lack of Success

P.aGE 10

techniques and the

building firm, or

organlzations.

quality of data available inside the

even gathered at bu1lding research

The successfull application of the programming

techniques tD eacb new project requires production-related

information in connection with

discussed in the next section •

the technical concepts

Page 14: The Examination of possible Causes of the Lack of Success

PAGE 11

The so called technical concepts involved in the

use of programming techniques are the definition of

activities, the estimation of activity•s durations and

resources required, the definition, or estination of the

total level of resources required at each time period, and

the settin~ of objectives to • .

construction phase of the project •

be achieved during the

The review of the literature showed that o~ly part

of the concept of resources required by the activities was

sufficiently investigated by research work, that is, only

the aspect of tbe variability in the resources required by

the activities <or complete building units) is wetl

documented in the literature (see Bishop-July 1965, Forbes,

Lemessany and Clapp, Piqott, Price, Shanley, Shipley,

Walker-1970 and 1971).

The other technical concepts introduced by the

programming techniques have been used and accepted by

Page 15: The Examination of possible Causes of the Lack of Success

PAGE 12

programmers and construction management research workers

without evidence of their applicabtlity stemming from

building sites.

The importance of challenging these concepts is

illustrated by tbe fact that when the network programming

techniques were introduced in the late so~s, building

projects were considered deterministic as far as the

duration of activities and the resources required were

concerned. The work of the authors cited above and others

showed that activity•s durati~n and resources required in

building projects • are also stochastic. The change o f

approacht from the deterministic case to the stochastic one,

made the programmin~ of building works a more reatistic •

exercise. Unfortunately the other concepts like precedence

between activities, nbjectives criteria, existence of

time/cost trade-off curves were neither challen~ed nor

investigated in great depth by practioners or research

workers in the area.

It was decided to undertake an analysis cf several

concepts invGlved on site programming. The causes of lack of

success in applying programming techniques to building sites

could be related to difficulties assnciated with the

practical aspects involved in the application of these

technicat concepts, or with the obtention of production data

to support them.

Page 16: The Examination of possible Causes of the Lack of Success

PAGE 13

This section will examine the concepts listed

below:

- definition of activities;

- activity's durations;

- precedence relationship between activities;

- sequence of work on bouse building sites of

repetitive nature;

- resources required by the activity;

- productivity modelling;

- estimation of activity•s duration and

resources required;

- trade-offs between durations and resources

reQuired by the activities; •

• - total level ~f resaurces allocated to projects

throughout the project duration; •

- settinç of objectives criteria.

As already mentioned in the introduction, each of

these aspects is treated in greater depth in separate

studies by t~e author. The ideas contained in these separate

reports are summarized here. The various concepts are

grouped according to the contents of the reports.

Page 17: The Examination of possible Causes of the Lack of Success

PAGE 14

Authors like Fine and Forbes <1977) showed the

difficuties associated with identifying activities or

operations on site. Pigott observed the discontinuity of

work in the operations; the workplaces were visited several

times by the trades concerned in order to finish particular

tasks. Forbes (1977t reported that dueto discontinuity more

than 300 operations were observed on sites where

theoretically just lOC were programmed and needed •

• •

Se~eral authors proposed to estimate activity•s •

duration by dividing their labour content by the size of the

gang assigned to the job (see, for example, Barroso-

Aguillar-1973, Butcher, Halpin and Woodhead-1972, and

Preston), or by correl~tin~ linearly the activity~s labour

content to its duration <Duff-1980). No evidence su~porting

these two approaches of correlating linearly duration to

labour content was found in some reports of productivity

studies on site dealing with a similar relationship, that

is, total cost or labour consumption and tot3l project

duration. The author did not find such direct relationship

between labour content and activity's duration on the three

housebuilding sites he is studying.

Page 18: The Examination of possible Causes of the Lack of Success

PtGE 15

It was observed on particular sites tbat the

operations Mere performed in parallel rather than in

sequence as the programmes of work uould recommend. Hall and

Ball, and R~derick reported respectively the analrses of

bridge construction and a one-off commercial buildiny where

this happened. The author observed the same phenomenon on

the three h~use building sites he is investigating at the

moment.

Apart from this parallelis•, the precedence

relationship betveen activities is not absolutely rigid. For

example, painting and floor t1ling are activities that can •

be rearranged either as preceding or suceeding in arder to

produce a better scheduling; the need for windows to proceed •

with the dry trades could be overcome by management

decisions like the use of temporary plastic cocoons. Its is

clear that this flexibility in terms of activity's

precedence should be taken into account in order to optimize

the scheduling of activities.

Finally, the various trades did not follow the

same sequence o1 work from block to block on the sites

observed by the author. For example, the dry-linings stage

of work was tackle in a different arder than the decoration

stage. The precedence relationships and the principles of

the Line of Balance rlethod (see Lumsden) would dictate that

Page 19: The Examination of possible Causes of the Lack of Success

PAGE 16

the use of the same sequence of wort by all trades is the

more rational way of progra•aing and perfor•ing the vartous

tasks of the project.

The variabtlity of activity•s duration is

discussed in the next section, since it has been associated

with the variability in the quantity of resources required

by the acttv1ties •

Page 20: The Examination of possible Causes of the Lack of Success

PAGE 17

The variability o f operatives out ~tut on

construction sites is very large. Similar activities,

undertaken by different contractors on different sites are

subject to a coefficient of variation between 30-~0 X in

terms of the amount of resources required (Gates and

Scarpa-1971, and Bishop-1965).

Variability within a construction firm should be .. •

less and it is considered to have a coefficient of var1ation

between 10 and 30 X C8ishop-1965,and Walker-1971) •

The range of resources required by similar

activit,es on a construction site is very large. Shipley

reported a range 1:10. Fine (1975) gave an example related

to pile driwing with a range also of 1:10. Bi shop ( 19 68 t

found that ranges of 1:4 were common on buildinJ sites

observed by the Building Research Establishment during the

late ~o•s and the so•s.

Carr and Brightmann, Roderickt and the author came

to the conclusion that the deployment of labour resources to

Page 21: The Examination of possible Causes of the Lack of Success

PAGE 18

the activities or stages of work followed a •s• curve.

Similar •s• curves have been used to represent the

allocation of resources to the project as a whole.

The review of the literature showed that resources

required by the activities are undoubtelty stochastic. The

variabil1ty poses complicated problems to the estimation of

resources required based on previous experience (Fine-1975):

resources required by the activities on previous projects

are only a sample of values from a distribution with a

unknown average, standard deviation, and prcbably a very

targe range of vatues • •

• If activity•s durations are obtained dividing

labour content by the number of men assigned to the job, the

high variaoility in resources required autoaatically

dictates a high variability in durations. So tar the

variability of durations has not been treated se~arately

from the variability of resources required. There are no

quantitative information about the range ot variability of

activity•s duration that can be expected other tman the

great numb~r of works dealing with the probabilistic nature

of resources required.

Page 22: The Examination of possible Causes of the Lack of Success

PAGE 19

The fact that productivity on some projects is

variable and its prediction is innacurate, as it will be

seen later, led to development of stochastic programming

models. These models, like P~RT and simulation modets, are

able to predict the most likely completion times of the

project and the probabilities of overrun, once final

completion dates are set. Their major shortcoming is that

they provide only information about the completion date of a

project, wit~out giving any guidance about tbe timing of

intermediate milestones. 1n other words, it is not possible

to decide upon the dates of intermediate milestones with the

information provided by these stochastic models: once

intermediate milestones dates are decided upon by the ~

• programmer, the constraints within which the model was

originally run are not valid any longer. Usually, P~RT and •

simutation models do not have constraints related to the

intermediate due dates.

Britney, for example, showed that the project

programmer should take the activity•s durations greater than

the most likely one, if the cost incurred in achieving also

intermediate milestones is to be minimized. FERT uses the

most ltkely duration as the activity•s duration. Jewell

indicated that the optimal scheduling of activities in an

stochastic environment depends not only on the variability

of activity•s duration, but also on the amount of extra

effort that is necessary to input to the project to recover

Page 23: The Examination of possible Causes of the Lack of Success

PAGE 20

from scheduling deviations, making sure that intermediate

due dates are reached. The simultaneous accomplishment of

intermediate and final due dates is part of the complexity

of the programming issue, that will be dealt with in a

further section of this report.

The problem o f defining the intermediate

milestones is of particular importance in the construction

industry, relying on a great number o f externa L

participants, like subcontractors, materials suppliers,

public authority connecting services, etc •• Conwelt

su9gested that at the strategic tevet, management should be , •

preoccupied only with the definition of the intermediate

milestones of a project. Detailed planning of works and the

use of programming techniques should be confined to the

tactical and operational levets of management. Further

discussion on the importance of defining correctty the

intermediate due dates will be found in the section dealing

with the com~lexities of the planning problem.

Page 24: The Examination of possible Causes of the Lack of Success

PAG:: 21

The variabil1ty usually found in the .activity 1 s

durationt in the amount of resources required, and in the

level of resources available on site could theoretically be

modelled by factors affecting productivity like weather,

size of contracts, workmanship, a•ount of supervision

availablet incentive schemes, motivation, etc" ••

Some factors were already exhaustively

investigated in the titerature, as it is the case of the )

weather (see Benjamin and GreenwGtd, Clapp-1966, Grimm and

Wagner, and Smith and Rawtingst. Oifficulties associated

with the use of factors to model productivity are given

betow.

It is relatively easy to quantify the influence of

weather on productivity, but Clapp (1966t showed that it

should be looked at in five different angles (decreased

productivity, increased absenteism, decreased number of

hours in the working week, increased time spent on repair

workt and decreased productivity on alternative jobs while

external work is disrupted by bad weathert.

Page 25: The Examination of possible Causes of the Lack of Success

PAGE 22

The so called Learning Phenomenon requires

specific conditions on site in order that it could develop.

Forbes (1977-l)t Gates and Scarpa (1972), and the Committee

on Housing, Building and Planning, ONU, said that te~rning

would occur only in the presence of good management on site,

continuity of work, and a sufficientty large number of

repetitions.

The influence of the number of hcurs spent on

supervision had been the object of worts by Walker (1972),

and Logcher and Cotlins, but no undisputed statistical

evidence was found, due to th~ relatively smalt amount of , supervision b~urs spent on various sites. Prcbably it will

never be possible to get •ore than qual1tative evidence

about the lewel of supervision to be used a project and its

influence on productivity.

In general, studies about factors affecting

productivity are not conclusive, there is little information

published, and results obtained by different others are

hardty comparable. It is doubtful if a sufficiently large

number of cases could ever be obtained to draw statistically

significant conctusions about the influence of particular

factors. Different factors affectin9 productivity can occur

simultaneousty, introducing additional complications in the

statistical analysis. For exampte, repair work can be caused

Page 26: The Examination of possible Causes of the Lack of Success

PAGE 23

by bad weather, lack of supervision, lack of skill, high

level of work•anship required by the client, or purely by

accident.

Some of the factors affecting productivity can be

related directly to individual crews or operations. It is

the case of the use of equipment, operatives training and

skilts, subsoil conditions, overtime and incentive schemes.

Others can be related ~nly to productivity as a whote, like

absenteism, labour turnover, safety, the disruptive effect

of constant variation orders, repair work, etc. Weather

influentes t~e progress of work on site both at the level of ,

the activity's productivity and at the level of prod~ctivity

associated with the whole site <Clapp-1966).

Factors affecting productivity can influence

different participants of the construction process. For

example, the influence of supervision and motivation can be

considered at the operative levet, at the foreman level, at

the site engineer level, up to the client and construction

company managerial level. likewise, financial constraints

;mposed by government action will be felt by the building

company itself, by the client, suppliers, designers and

subcontractors.

Page 27: The Examination of possible Causes of the Lack of Success

PAGE 2~

Difficult site access and subsoil conditions,

repair work, and variation orders tend to increase the

labour content of activities. Other factors affecting

productivity like incentive schemes, motivat1on, and

training may increase the output of operatives. Weather,

absenteism, and unbalanced crews can be expected to decrease

the operatives' output. Architect•s and authority•s

approvals, labour and materials supply, and lack of good

programming of ~orks tend to delay the building process,

without necessarily increasin~ the cost of the project, if

management could succesfully oeviate resources to other

projects. The modell;n~ of productivity is made more

complex by these different ways in which some factors , !

influence the building process. 1 ~)

Carr developed a simulation •odel capable of

" incorporating the influence o f factors affecting )

productivity in the calculation of activity's durations. lhe

crux of the matter is the obtent1on of reliable quantitative

values to be used as the factors modifying the activity•s

durations in order to •ake the simulations realistic.

Kellog introduced the concept of hierarchy of

factors affectin~ productlvity. His approach is designed to

look at the construction industry productivity ~n a broad i

macro-economic sense, but it could easily be extended to the I

Page 28: The Examination of possible Causes of the Lack of Success

PAGE 25

modelling of productivity on site. The •terarchical approach

seems to be a sensible way of dealin9 with the great number

of factors affecting productivity and their relative

importance. It could be suggested that only the most

important factors affecting productivity should be

investigated and used in production modelling, accepting the

fact that a good part of the variability of productivity on

site. which would be caused by minor factors, cannot be

adequately eKplained due to the lack of statistical feedback

information.

Variations in productivity can be controlled or }

reduced using the knowledge derived from the study of

factors atfecting it. Nevertheless, in practice there will

• be always a residual variability represented by partially

uncontrollable factors like weathert client variation

orders, and subsoil conditions.

Baldwin investigated the ranlcinç given by

architects, contractors, and engineers to several causes of

delay 1n the c ons truct i on industry. Attendance o f

subcontractors, weather, and labour industrial relations

problems were given the three top ranking pcsitions. No

other classification of factors affecting productivity or

causing delays was found in the literature.

Page 29: The Examination of possible Causes of the Lack of Success

PAGE 26

Several authors sbowed that •good •anagement• is

the reason behind tbe correlation of some site indexes and

productivity. Low non-productive time, develop•ent of the ~

learning phenomenon, good safety re cords, 11orlcer 1 s

motivation, the successfull application of incentive

schemes, the witlingness to work under bad weather

conditionst good quality of worlc and prompt re)air of

defects, the use of improved methods of construction, and

the successfull use of programming techniques were observ~d

to occur simultaneously with good management practices. In l·! this sense, good management would occupy one of the top

posit ions in the hierarchy o f factors affect ing

productivity. lt )

went without saying the difficutties of

defining what is understood by good management, and how a

good management factor could be established to model •

product ivity.

The learning phenomenon could represent a set of

factors affecting productiv1ty that are related to the

continuity of work on site, lik~ bad weather, labour

turnover and absenteism, materials shortage, equlpment

failure, and subcontractors attendance.

Page 30: The Examination of possible Causes of the Lack of Success

PAGE 27

The process of estimat1ng durations and resources

required was found to be innacurate by some research

workers. The review of the literature points out case in

whi ch:

- activity•s durations were underestimated by 20

to 50 x, that is, real durations are between 25 and 100 %

greater than initially estimated (Kidd and Morgan, K1ng and )

Wilson, King et allit and qoderick);

resources required by the activities Mere

underest imated by 20 to 50 % (Ashworth-April 19BOt and

Roderick);

apart from those biases, it was found that

estimating techniques were not able to predict actual

resource content of activities with a coefficient of

variation oetter than 20 % (~shworth-Apri l 1970., Fine

(1970), and ~cCaffert. These coefficients of variation were

obtained using normal analytical estimating techniques by

Ashworth and historical methods by McCaffer;

Page 31: The Examination of possible Causes of the Lack of Success

PAGE 28

Fleming and Ashuorth (March 1980» found that

labour constants published in estimating books were not

reliable sources of infor•ation on resources required by the

activities. Fleming showed that despite the technicat

evolution of the construction industry during the years, the

labour const3nts published in estimating books books did not

change systematically during the tast century. lshworth

<March 1980J compared the information produced by some

estiaating books and pointed out

given to identical tasks by

information.

the different

the different

unit rates

sources of

Page 32: The Examination of possible Causes of the Lack of Success

PAGE 29

Problems associated with activity•s durations and

resources required <costs) were investigated in the previous

sections. Now it is worthwhile to examine the concept of

time/cost trade-off curves, that calls for the estimation of

several pa1rs of act1vity•s duration and asscciated costs.

These curves are represented by convex decreasing functions

relating direct costs to perform one operaticn to the !

correspondin~ durations. Sometimes a convex increasing part

of the curve is added to represent increased costs vitn

large durations. lhe time/cost relationship could also be J

represented oy isolated points rather than curves •

When first introduced, the Critical Path Method

had two major advantages over traditional programming

techniques like the Gantt Chart:

a) the technical precedence relaticnsnip between

activities could be displayed graphically in an easily

understandaole form. The precedence relationship betveen

activities also provided a suitable algorithm for the

calculation of project total duration, activity•s start and

finish dates, and activity 1 s floats;

Page 33: The Examination of possible Causes of the Lack of Success

?AGE 30

bt the ti•e/cost trade-off curves vould be able to

summarize tbe influence of several important decisions

influencing the construction process. like the choice of

method of construction, number of crews assigned tn each

operationt o~ertime work, etc. The curves also provided the

mathematical relationships needed to optimize the sc~eduling

o f opera ti ons.

The review of the literature showed that research

work done so far failed to investigate the real nature and

shape of the time/cost trade-off curves on building sites

and other projects in general. This view is shared 3y Davis t

(1966t: up to 1966 he did not find any research work dealing

with the practical aspects and the proof of existence of

these curves. Elvers (1971) doubted that companies would

ever prepare these curves; the preparation of single cost

and duration estimates is a major task in itself. and

several accurate estimates would be necessary to produce

each activity•s time/cost trade-off curve.

The author investigated the literature deating

with the followin~ aspects associated with the coacept of

time/cost trade-off curves:

- changes in the method of construction;

different crew sizes and crew compositions;

- overtime work;

- incentive schemes;

Page 34: The Examination of possible Causes of the Lack of Success

PAGE 31

- use of subcontractors;

- resource mobilization costs;

resource idleness costs;

, I

lhe review of the literature concluded that only

under speciat circumstances it is possible to draw

activity•s time/cost trade-off curves. Some of the

interesting points raised by different authors supporting

this view are reported in the next paragraphs.

lhe building company would be able to consider •

different methods of construction only if 1t is fully

acquainted with them, otherwise it would incur the costs of

becoming familiar with a neu technique. The costs involved

in the use of a new technique are not really kno~n until

some experience is obtained with their use on site.

Pigott showed one example where only a restricted

number of crew compositions and sizes produced shorter

durations with greater number of •en assigned to the job.

Some large crews were totally unproductive, costing •ore and

apparently taking more time to complete the operations than

smaller crews.

Page 35: The Examination of possible Causes of the Lack of Success

PAGE 32

Kappaz and McNally reported the contraproductive

effects of overcrowding the work place in the cases tn which

a greater or •ultiple crews are e•ployed to decrease the

duration of a job.

Blough and ~cGlaum emphas1zed tbe lack of net

production gains in some projects where overtime vas used

continuously for more than 7 days. Moreover, they stressed

that due to the problems associated with industrial

relations on site, it is not possivel to put only some

trades and activities on overtime work.

Incentives schemes in fact originate increasing •

cost/time relationships, that is, decreased durations would

be theoreticalty obtained w1th decreased costs. !f this is

true in practice, incentive schemes are not able to produce

the classical decreasing curves generally associat~d with

time/cost relationsbip. Again, incentive schemes cannot be

used only with particular trades and activities 1 if labour-

related problems are to be avoided.

The true costs of subcontracting are not easily

calcutated due to the difficulty of enforcing prices and

durations agreed upon in the contractual documents, if any.

Variation orders, which are the rule in the construction

Page 36: The Examination of possible Causes of the Lack of Success

PAGE 33

industry• not the exception, help to decrease the lauful

implications of prices and durations set on contracts.

Pigott showed that subcontractors were undoubtelly more

productive than the maio contractor own labour on three

sites analysed. ~owever, they were responsible for the

discontinuity of work on site, making irrelevant, tiaewisely

speakinQ, the productive gains in terms of •an-hours.

TiMe/cost trade-off curves obtained fro• the

consideration of resource mobilization costs (Cullingford

and Prideaux), or resource idleness (Danoont Fine 1977-lt

fine 1977-2t and Kauffotd) can only be applied to th~ whole )

process of construction, not to individual activities •

As a conclusion, it can be said that the

difficulties in applying the concept of time/cost trade-off

curves to the programming issue are related to the problem

of calculating accurately the real costs and durations

associated with the factors tisted above, like change in the

production methodst use of different crew sizes, overtime

work, etc ••

Page 37: The Examination of possible Causes of the Lack of Success

PAGE 3~

Once the site programmer decides about ~robable

activity•s duration and resources required, the next step is

the definition of the total level of resources to be made

available on site. The required level of resource on site

can be obtained in two different vays. It could be set as a

function of the already scheduled activities and their

resource re~uirements, or it can be imposed by external

considerations. Cullingford and Prideaux proposed a model to

optimize the resource profile of a project before actually l

scheduling the activities and defining their durations and

resource requirements. Gates and Scarpa (1976t suggested to •

define the resource profile based on practical experience

and past records.

Resource Scheduling techniques are used to

allocate a limited quantity of resources to competing

activities, thus defining their start and finish dates <see

Rickard, and ICL-PertOisc). Resource Levelling is used to

smooth peaks and valleys in the resource histogram

previously Dbtained by just aggregating the resources

required by individual activities. Optimization techniques

call for the simultaneous use of Resource Scheduling,

Resource Levelling and Time/Cost Trade-off techniques <see

Kauffold).

Page 38: The Examination of possible Causes of the Lack of Success

PAGE 35

Up to now, research work has been considering the

resource levets associated with building projects as

deterministic parameters. Any variability in the actual

level of resources available on site was theoretically

modelled by the variability in activity•s duration or

resources required. The author proposed in his report about

resource le~els on building sites to separate this two

causes of variability: causes of productivity variation

related to resource fluctuation should be separated from

causes of productivity variation intrinsic to the nature of

the activities.

The author ident1fied labour absenteism and labour

turnover as two causes of variability in the actuat tevel of

resources available on site. The review of the literature

showed that very littte is know ;n quantitative terms about

these two cGmmon features of building sites. Staggering

figures were presented by some authors; for example, Bishop

<1968) stated that the tabour force could be 50 % larger or

smaller than in the day before. Average tosses in the

number of man-hours available due to absenteism was found to

be as high as 8 % in some projects.

Barroso-Aguiltar (1973) cons1dered that the

magnitude of absenteism deserved the application of a linear

pro9ramming technique to allocate the variable nu~ber of

workers that turn up daity.

Page 39: The Examination of possible Causes of the Lack of Success

PAGE 36

Two other absenteism-related problems were

1dentified. Firstly, Pigott concluded that the discontinuity

of work on site was caused by subcontractors working

simuttaneously on various sites, always loo~ing for •snags-

free runs of work' and •oving from site to site as soon as

production difficutties were presented.

Secondty, a NEDO report (1976) dealing with

industrial plant construction showed tnat on average 10 % of

the daily work1ng day was lost due to late arrivals and

early departures to and from the work place <not necessarily

to and from the sitet. The author found some similar )

qualitative evidence on the sites he studied. His

observations also suggested that the distribution of

resource availability during the day followed a comJlicated

pattern. The existing evidence indicates that resouces

shoutd not be considered ayailable on a ccnstant basis

throughout the working day.

Another source of variation in the actual level of

resources available on site is the non-productive time found

on building operations. Non-productive time was

consistently found to be in the region of 20-50 t

<Forbes-1365, 1971, 1977-1, 1977-2, Logcher and Collins, the

NEDO report-1976, and Stewart and Torrancet. Obviously non-

productive time could be 1ncluded in the estimates of the

Page 40: The Examination of possible Causes of the Lack of Success

PAGE 37

tabour constants, but Forbes (1977-2t suggested that it

shoutd be treated as a global figure, as a particular

characteristic of building s1tes or building companies. !f

this is the case, non-productive time would be better

considered at the tevel of an aggregate figure, Lt~e the

total level of resources avaitable on site. Oespite the

evidence that non-productive time is a characteristic of

each particular site, Benttey showed that non-productive

time varied with different types of activities within a

site. It could also be expected to vary throughout the

project durationt daily, wee~ly, rnonthly, or according to

the season of the year <Clapp-1966 and Pigott).

) ~

' j

Page 41: The Examination of possible Causes of the Lack of Success

PAGE 38

Construction sites prcgrammes of work ran be

obtained by several different methods, ranging from network

techniques to simple· contractual arrangements between the

participants of the building process. Schedules of work can

be differentiate by the attainment of certain management

objectives. These management goals are the objective

criteria used to compare different schedules.

The objective criteria are generally related to J

quantifiable measures of the construction process, but there

is no theoreticat problem to extent their evaluatio~ to the , whote lifecycle of a project, fro• des1gn to utilization.

Subjective and qualitative measures can also be introduced

as the objective criteria.

Some objectives are not easy to transform in

monetarr values. It is the case, for exaaple, of the policy

commitment of some building companies of handing over the

projects they undertake alvays on due dates, whatever the

difficulties they might face. This go~d completion record

that the com~any could offer to prospective clients probably

would be associated with a higher markup margin at the

tendering stage. Complex risk analyses would be called in

Page 42: The Examination of possible Causes of the Lack of Success

PAGE 39

to help transform this subjective criteria of handtng over

projects always on t1me 1n quantifiable measures. To the

best of the autbor•s knowledge this approach was not yet

tryed successfully by research work.

According to Fendley, the most co~mon objective

criteria are the ones related to:

- project duration (deterministic and

probabilistic view);

- resource utilization; level of resources

required to undertake the project, fluctuation

in resource requirements, and resource , idleness;

- number of projects or activities being

undertaken simultaneousty.

lichtenberg stated that all this measures of the

quality of projects are genuinely correct, but that they are

in fact sub-objectives to be attained during the

construction phase. He said that up to now one of these

sub-objectives has been taken as the more important one, and

the others abandoned. lhe real objective vould be a weighted

measure of alt sub-objectives. Some other authors also

proposed this weighting technique but without solving the

problems associated with tbe subjectiveness of how to set

the weights to. the various objective criteria being

considered simultaneously.

Page 43: The Examination of possible Causes of the Lack of Success

?AGE 40

Lichtemberg tried to transform into cost elements

all aspects related to a set of objective criteria. Project

duration, resouce utitization, work inventory, and other

factors like overtime, mobilization costs, etc. would be

represented by their cost implications over the project

construction. The objective criterion would become solely

the minimization of total present project cost. The main

criticism is that this technique would eventuatly require

the consideration of the whole management problem fsupply of

materials, personnel administration, client and coAtractor

relationship, cash flow analysis, site productivity, etc.t

within the programming technique. This encompassing

approacht despite the fact that ;t is theoreticaltr sound, )

will be shown unpractical later on this report.

Another major difficutty associated with the

concept of programming objective criteria is how to evaluate

their effectiveness in terrns of the inter•ediate and final

results obtained during the construction phase.

Bromilow (196~) showed that project durations were on

average 49 % greater that stated in contractual documents,

but projects using programming techniques had durations onlr

1 X greater than initially agreed. It ~as not possible to

distinguish the effectiveness of good schedules as opposed

to bad schedutes for the effectiveness of schedules capable

of attaining good and bad measures of a particular o3jective

criterion). The most important factor in order to achieve

Page 44: The Examination of possible Causes of the Lack of Success

PAGE 41

final due dates was to have a programme of workst no matter

hov it was obtained.

Studies by the Environmental Research Grou~ of the

University College - London - (1974) came to the conclusion

that building project durations were a function of the state

of the construction activity. Depressed markets led to Long

project durations, while booming aarkets led to t~e rap1d

conclusion of projects. The positive effect of programmes of

work in keeping project within the contractual pertods vas

not reported.

)

Authors like Gates anc Scarpa (1976), Handa et

alli• Kleinfeldt lemassany and Clapp, and w. N. Perry

suggested that resource profile curves could be obtained by

historical methods rather than by resource aggregation used

in conjunction with programming techniques. This means that

advantages and disadvantages associated with particular

resource profiles on site could have been achieved either by

the use of the programmimg technique itself, or by the

natural tendency of projects to follow specific resource

profile patterns.

Other objective cri teria like resource

mobilization costs and resource idleness were found to

Page 45: The Examination of possible Causes of the Lack of Success

PAGE 42

depend respectively on the state o f a ct i vi t y i n t h e

c~nstruction industry fSoeterikJ, and on the quality of

management (forbes 1977-lt Logcher and Collins, Miller-1977,

and Smith and Rawlin9s), rather than on the characteristics

of the programme of work.

The information provi ded in the preceding

paragraphs leads to the conclusion tnat the objective

criteria noraally set to programmes of work are not able to

distinguish between good and bad schedules. This could be so '!

mainly due to three reasons: firstly because it is difficult

to evaluate the influence of a particular schedule on the )

success or failure of the construction phase of a project;

secondly because some of the objective criteria are .)

influenced by a great number of outside factors, not only by

the characteristics of the schedule; and thirdly, because

generally the case is for multiple objectives and not for

single ones.

1:

Page 46: The Examination of possible Causes of the Lack of Success

PAGE 43

The programming issue has a complex mathematicat

naturet even not considering retated aspects of management

like cash flow, incentive schemes, cost estimating, etc.

<Davis - 1965). It is generalty accepted that the exact or

optimat programming techniques are of tittte use to the )

scheduling of construction work, due to the restricted

number of variables that they can handte (Butcher, Burt,

Oressler, Preston, and Shafiert. The optimtzation obtained

using these exact techniques can be considered in fact a

sub-optimizationt because a great number of variables are f teft outside the programmin~ •odets. ~

. I Great part of the research effort in network l !

program•ing techni~ues was devoted to the optimal methods

like linear programming, dynamic programming, backtracking

methods• and stochastic programmtng. The resutts of this

research eftort bear very littte relationship with the

construction programming problem.

Page 47: The Examination of possible Causes of the Lack of Success

PAGE 44

Resource Levelling and Resource Scheduling,

time/cost trade-off analysist schedul1ng to satisfy

different objective criteriat factors affecting productivity

and resource usage on site, stochastic nature of the

bu1lding process, etc. are all important aspects of the

proJramming problem that should be considered 1n a greater

or lesser extent in each particular project.

Furthermore, due to their own nature, the

programming techniques, especiatly the ones based on network

concepts, could be used to help perform several management

functions like project cash-flow, pay-roll, cost accounting,

calculation of contractual claims and the l1ke. Building

companies are in general undertaking a great number of

projects; there is no theoretical difficutty in modelling a

number of simultaneous projects.

The siaultaneous modelting of all the above

aspects results in a huge combinatorial problem, perhaps

proibitivety expense to be dealt wi th by compu ter

simulation, needless to say by the exact mathematical

methods. In practical terms, the number of variables that

can be handle is limited by the computing facitities

availablet by the objectives of each company, or by the time

taken to prepare the necessary input data. Some examples of

research t ryi ng to put together programming

Page 48: The Examination of possible Causes of the Lack of Success

PAGE 45

considerations and other aspects of •anage•ent are revieued

in the next section.

The programming problem should be hierarchized in

its strategic, tactical and operational aspects, and each

aspect should be considered on its own. Harr1s and Evans

<1977t reported soae experience Mith the management of

construction sites using programming models and strategic

and tactical decisions. Borcherding said that policy,

strategic and tactical decisions by management help to

simplify the programming problem.

)

Several examples can be given on how decisions at

a higher level might help to simplify the cornpl~x

prograrnming problem. For exampte, the implications of the

tirne/cost trade-off curves in the scheduling of activities

on site can be made sirnpler if one of the main sources of

these trade-offs, that is, ~vertime work, is ruled out by

strategic or even policy decisions. Authors like Blough and

McGlaum showed the totally detrimental effects of overtime

on productivity.

The productivity improvements caused by the

Learning Phenomenon (Gates and Scarpa-1~72, can be

disconsidered if the company decides tactically to undertake

Page 49: The Examination of possible Causes of the Lack of Success

PAGE 46

two projects in the same area, using the same poot of labour

to tackle the jobs, as it is com•on practice. The

discontinuity of work caused by the constant movement of the

operatives from one site to another would almost certa1nly

prevent any improvement in productivity due to Learning

(see the Committee on Housing, Building and Planning Report

- •Etfect of Repetition on Buitding Operations and Processes

on Site•).

Patterson, recognizing the sizeable computing cost

involved in the programming techniques, investigated methods

of previewing the performance of different schedulinç

heuristics. !nstead of applying a number of different

heuristics to a specific project and incurring the cost of

this computing exercise, he thought it would be better to

apply only the heuristic with the best chance of atta1ning

near optimal results.

The problem of costs of i•ple•entation and use of

the programming techniques remains open to discussion.

Ling, summarizin~ the work of other researches and reported

practioners experience, said that the programm1n~ costs

durinJ the pre-construction and construction phase were in

the region ot 1 to 2 % of the total project costs. ~uthors

like Lumsden, Patterson and Rickard claimed potential cost

benef1ts of the application of programming techniques in the

Page 50: The Examination of possible Causes of the Lack of Success

PAGE 47

region of 5 to 20 X. lf this is so, there is a great scope

for more and more effort to be applied to the issue of

pro~ramming the construction o f projects. The e ver

increasing awailability and capacity of computers indtcates

that the costs involved 1n programmin9 site uorks wo~ld tend

to decrease in the future. Yith this increase in co•puting

facilities, more and more of the complexities involved in

programming could be tackled in a cost effective way.

Unfortunately the experience accumulated in

schedulin] a~plied to sanufacturing industries and research

projects cannot be directly used in the construction

industry, due to the singularity of its programming problem.

Each of these areas of Qpplication of programming techniques

has special characteristics.

Research projects are totally stochastic in

nature, in general no previous experience is available on

durations and resources required. Availability of resources

is not a problem, if the prospects of the research project

are good. The total project duration is generally the most

important objective criteria to be attained.

~anufacturing industries, producing great quantity

of goods with unitary low vatues as opposed to tbe relative

Page 51: The Examination of possible Causes of the Lack of Success

PAGE ~8

high value of the construction industry product, face a more

deterministic process and a more controllable environment.

Once the production process is started, the flow of work

should be smooth, making the 1ntervention of manaqement

unnec~ssary in the short run. Resources and deadlines are

absolutely defined and should be respected. The most

important objective cr1teria is the achivement of minimum

production costs.

In the construction industry, the environment is

partly uncontrollable, some experience can be gained from

previous projects but each project is unique, and the }

process was shown to be stochastic in nature. Costs and

completion times are regulated by contracts. Theoreticalty

they should be equally important as objective criteria, but

Bromilow (FeDruary 1971) and R. Harris showed that clients

are more preoccupied with keeping the total costs vithin the

budget that with sticking to fixed project durations.

Howeverw the most important distinction between

the prograasin~ problem in the manufacturing industries and

in the construction industry is that in the latter there is

a group of personel constantly available on site, or at the

building company office, whose job is to intervene in the

construction process, correcting deviations from the

schedule. This potential use of the management presence on

Page 52: The Examination of possible Causes of the Lack of Success

PAGE IJ9

site should be explored in the initiat programming stages.

Kauffold classified the programm1ng techniques according to

their suitabititr to the various types of industries, but

did not pay attention to this particular preseuce of

management in the construction industry case.

Some research work, whi te recogn iz in g the

stochastic environment of project programming, used the

concept of •average• resutts obtained using a specific

technique in a num~er of simulations. Projects are such in

the construction industry that the contractor will not face

a sufficient number of repetitions to take advantage of

•average• results. In the manufacturing industries the

number of repetitions is larger, and the company can rely on

average simulation results to decide upon the applicability

of particular techniques. In the construction industry the

programmes of work should be sufficiently robust to overcome

problems caused by the great number of variations in

productivity, delays and deviations from schedule that could

occur. The ~rogramme should be optimized to produce a

sufficiently good resutt in terms of the objective criteria,

whatever the conditions to be faced during the project

construction.

This concept ~as firstly introduced by Fendley.

A good example is the change of objective criteria as the

Page 53: The Examination of possible Causes of the Lack of Success

PAGE 50

project is being built. At the tenderin9 stage, the

achievement of due dates is of paramount importance to the

client. As the project progresses, it could happen that the

amount of variations orders or the irregularity of pavments

by the client is such that the initial contractual

commitments in terms of due dates are meaningles, and the

contractor could change to the objective criteria of

minimizing h1s overall costs. The initial programme of

works should not impose severe constraints to the

rescheduling of site vorks taking into account this new

objective. Some programming techniques, like t~e ones

introduced by Pritsker, are able to consider a vbole range

of circumstances that could be expected to arise during the )

project construction phase. Nevertheless, these techniques

are still not able to incorporate probable changes in the

objective criteria.

After the following section, this report returns

to the examination of the robustness of the in1tial

programme of works in face of the updating of the schedule

and site management. The co•promises between dectsions at

the programminç staQe and possible updating actions are

further discussed.

Page 54: The Examination of possible Causes of the Lack of Success

PAGE 51

Abdulaajid related the programminQ of house

buitding projects to the availability of resources, like

tradesmen and bricks, at a macro-economi level. It is ctear

that the resources ava1lable as a whole in each region

should be related, among other factors, to the time taken to

built the project. In other words, the programming of

activities for each individual project should somehow

consider the present use of construction resources at the

regional levet. As a corollary, it can be said that in

vertically integrated building firms, that is, the ones

dealing also in the area of supptyiny or producing building

components, it is necessary to determ;ne at what level the

programming of works should be optimized. The progra••ing

could be considered at the whole company levet, or onlF at

the construction division levet.

Barroso-~guillar <1973) related the proble~s of

scheduling of activities and stock controt of materials on

building sites. The modelting comple•ity is great even at

this level of integration of different management functions.

Barroso-Aguillar opted for optimizing the scheduling of

activities and then, given that schedule, optimize t~e stock

Page 55: The Examination of possible Causes of the Lack of Success

PAGE 52

of materials. This approach led to the suboptimization of

th1s two aspects taken together.

Paulson (1971, 1975t tried to explore at its

fullest extent th~ capabilities of modern •an-computer

systems. The whole process of construction management,

including prDduction feedback, esti•ating and scheduling of

activities, methods improve•ent, and the analysis of the

time/cost im~lications of different metnods of work Yould be

made possible by powerful computer facilities, data storage,

and other affice equipaent. This research project was

partially abandoned in recent years, probably due to the

costs Df developinç this coaplete managerial inforaation

system.

M.oavenzadeh considered the progress simulation of

tunnel construction, taking the physical characteristics of

each section of roct bein~ drilled as stochastic variables.

The amount of computer effort, given by the number of

repetitions needed in the simulation exercise, shDwed the

practical difficulties of including more and more variables

in the programming of works on site. Moavenzadeh did not

include the trade-off between greater rock exploration costs

before the start of the project and the benefits to the

schedule of a more accurate knowledge of the rock drilling

characteristics. This trade-off between greater costs

Page 56: The Examination of possible Causes of the Lack of Success

PAGE 53

1ncurred in getting information about the s1te and improved

accuracy of the 1nformation is suggested by Bjornsson. The

consideration of this trade-off would add a neM dimension to

the programming proble••

Page 57: The Examination of possible Causes of the Lack of Success

PAGE 5~

After the analysis of the applicability of so•e

tecbnical co~cepts to the programmin9 issue, prospective new

users of the scheduling techniques should consider what sort

of problems can be expected in the updating of the

programmes of work, and in the collection of site production

feedback data.

It was already mentioned in this report that the ., application of the programming techniques to buildin1 sites

was considered a good example of a deterainisttc approach,

that is, once activities and resources are scheduled, no

substantial discrepancies between what is planned and what

will really occur on site should be expected.

lhe review of the literature showed Nutatl (1965)

as the first researcher using a stochastic approach to the

programming of building sites. From that time Ont

observations of building sites have shown that variations in

productivity, deviations from schedule, project overruns,

stoppages and breakdowns are the norm and not the exception

Page 58: The Examination of possible Causes of the Lack of Success

PAGE 55

in the building industry. Frequent updates are necessary to

bring the project back on schedule. schedules.

Streeter said that it is not always necessary to

intervene in the project at each updating if progress on

site is not matching the programme of works. lhe cost of

collecting feedback data and stopping on-going activities in

the case of resources being diverted from tbem, prevents

the use of very frequent updates and interventions. Elvers

proposed a functioo to represent the cost of intervening in

the normal flow of the project. In fact, the updating

corresponds to a new programming of works, with practically ;

the same amount of effort in terms of clerical staff,

computer time, and communication to and acceptance of the •

new schedule by the participants of the building process.

lhe type of personnel involved in the updating

effort is different from the type of personnel involved in

the initial programming. At the initial stage it is more

likely that the programming department, or the estimating

department, is in charge of applying the techniques to the

new project; as the work progresses on site, it is wiser to

let personnel directly involved with the day to day running

of the project to perform the rescheduling of activities and

resources.

Page 59: The Examination of possible Causes of the Lack of Success

PAGE 56

It is not easy to determine when the programme of

worts requires an updating. Kappaz stated that the majority

of disturbances and deviations from schedule are small and

could be individually accomodated in the floats avallabte.

!t is necessary to •easure the deviations from the schedule

on a cumulative basis to decide if a management intervention

1s needed. Critical Path Techniques, for example, ~ill not

show the disruptive effect of delays in the activities

outside the main criticat path.

Elvers and Ferdows examined the question of when

to update a project. Etvers found that for each project a

particular strategy shoutd be followed. Ferdows found that

more frequent project updating does not always improve

project performance, measured in terms of average project

completion stippage, average resource 1dleness, or average

number of projects being worked si•ultaneousty. ~esource

idleness was found to increase with more frequent updating

in the majority of cases studied.

Furthermore, t~e set of aanagement tools available

at the updating periods is notas complete as in the initiat

programming period. Thus the whole reprogramming process

becomes more constrained. Construction methods a~d site

management style are already implemented and Mould not be

easity changed. For example, incentive schemes should

Page 60: The Examination of possible Causes of the Lack of Success

P~GE 57

preferably be in force since the start of the ~roject;

overtime work requires a very careful timing and management

should face the possibility of using it until the completion

of the project, once the workers realize their barg~ining

positioni t~e employment of more labour resources should

consider the added mobilization costs and tbe matching of

old and new crew's production rates.

Any corrective action taken by management takes a

period of time to be implemented. Site aanage8ent can hardty

afford the implementation period if the project is atready

running behind schedule. )

~

Several contractual commitments are assumed dur1ng

the course of the project: for e~ample it would not be easy

to reschedule delivery dates of important components, or to

convince tne client about a tighter schedule of payments. As

the end of the project comes nearer, the scope for action

decreases (Elvers). The relationship between early

programming of works, site management, and the updating

issue is exptored further in tbe section below.

Page 61: The Examination of possible Causes of the Lack of Success

PAGE 58

Generally, it has been observed the Lack of

emphasis on the close relationship between earty proQramming

of works, site management, and the updating issue. For

example, the following aspects are not highL;ghted in the

titerature: any costs incurred to obtain feedback data to

programming modets could atso be partly allocated to the

cost of improving general management on site; more effort

altocated to programming at the pre-construction stage coutd )

determine less costly management during the p roj ect

execution. This last proposition suggests an analysis of the •

trade-offs between greater programming costs now or greater

management costs later.

A ut h o rs l i k e Barroso-Aguillar (1~73) made a

distinction between programming techniques applied to the

project before construction starts, and management

techniques used to solve the day to day allocation problems

on site. The former would be used to set the milestones, due

dates, and objectives to be achieved, while the latter would

just optimize the daily allocation of resources 1 within the

framework given by tbe previous scheduling.

Page 62: The Examination of possible Causes of the Lack of Success

PAGE 59

The milestones, due dates, and contractual

arrange•ents based on the information provided by the early

programming of works w1ll represent constraints to site

management during the construction of tbe project. It can

be suggested that all arrangements made using information

derived from the early programme of works should not

represent severe constraints to the manage•ent of the

project, whatever variations in productivity, del3ys and

deviations from the schedule CQuld reasonably occur.

Tbe scheduling techniques used at the early

programming stage can be successfully used again during the

construction stage, as part of the set of tools available to

site management to put the project back on schedule. Nutall

<1965• compared in a simutation exercise the end results of

two different styles of site management; in the first, a

programme of works was followed strictly; in the second one,

with no programae, the foreman decided which activity to

schedule next based on a heuristic rute of thumb. This

latter style of management provided better results in terms

of the achievement of due dates and smaller project

duration. The rule of thumb used by the foreman could had

been used to establish a pro~ramme, before the project

started on site. Unfortunately he did not investig3te what

would happened in the case the foremen had used the

heuristic decision rule within a previously established

schedule framework.

Page 63: The Examination of possible Causes of the Lack of Success

PAGE 60

One of the reasons preventing the consideration of

the early ~ro9ra•ming of works and site •anagement as

similar probte•s is the difference in the quality of

information at the pre-construction stage and durtng the

construction phase. It can be said that at the pre-

construction stage the uncertainity about the building

process is at its maximum, but the site program•er has a

great deal of ftexibility in terms of programming; durin9

the construction phase the certainity about the building

process increases and the scheduling flexibility decreases.

The ~arly programme of works is done when the .I

information is in its worst form. More often than not, the

design is not yet concluded. Ouring the construction stage,

data used ta update the schedule could benefit from the

production feedback gathered in previous weeks.

Poreover, as already mentioned, the personnel that

usually perform the programme of works in t9e pre-

construction phase and the personnel that would be involved

in the rescheduling of activities are differenti the first

programme is done by the programming or estimating

department; the reprogramming or management of ~orks on site

should be done by personnel most directly invclved vith the

day to day running of the project.

Page 64: The Examination of possible Causes of the Lack of Success

PAGE 61

Abernathy, after findin9 that the accuracy of

estimates can improve dur1ng the construction phase of a

project. recom•ended an adaptative strategy on scheduting

and updating:

•Action taken on early information (that is, less accurate information than the 1nfor•at1on obtainabte towards the end of the project) may degrade overall project performance rather than improve it. By adaptative strategy ve mean the particular pattern of rescheduling action that is pursued over the lifecycle of a project. The objective of tbe strategy is to minimize the sum of (1» the cost of rescheduling, (2) the costs of inappropriate scheduling action result1ng from the use of poor estimates, and (3t the costs of foregone opportunities to make inexpensive corrections at an early period. It is appropriate to think in terms of strategies rather tban optimal scheduling since the derivation of optimal schedules is frustated by the presence of an unknown component of bias (optimistic bias in estimatiny, real durations are far greater than estimateda•.

This suggestion by Abernathy introduced a new

avenue for the development of research works in the area of

programming. However the matbematical formulations for such

approach are not straightforward. Biemer and Sielken, Burt,

Britney, and Jewell produced interesting introductory

research work in this area.

Page 65: The Examination of possible Causes of the Lack of Success

PAGE 62

Every aspect looked at in this research vork

shoved important discrepancies between the theoretical

approach used by the programming techniQues anc realit1es

faced on site or at the building company office. These

discrepancies went from the difficulties in accepting the

new techniques at the various levels of the participants

involved in the project. as opposed to the hopes for their

easy acceptance, formulated during the tntroduction of the

more powerful programming techniques in the Late so•s, to

the lack of evidence from building sttes supporting the

technical concepts. It should not be forgotten also the

theoretical approach used in updâting, that is, each

updating can be transformed in a totally new progr3mming

problem, while it has been shown by these report that

updating is a more constrained and complex problem.

In this sense, all difficulties associated with

programming dealt with in this report are potential causes

of the lack of success in the application cf scheduling

techniques to the building industry.

Page 66: The Examination of possible Causes of the Lack of Success

PAGE 63

It is the case now of discussing the relative

importance of the various aspects as causes of the lack of

failure in the application of programming techniques.

Page 67: The Examination of possible Causes of the Lack of Success

PAGE 6~

It has been generally accepted in the liteature

that the use of programming techniques have not been capable

of achieving the desired improvements in the management of

construction projects due to the lack of communication to

and involvement by the great number of participants in the

buitding process. The diff1culties associated with some

technical concepts, like for example the estimation of

activity•s duration, have not been made responsible for the

apparent failure of the application of pro~ramming

techniques. This view is not supported by the a~thor, that '

believes that the difficulties associated with the technical

concepts came second only to the lack of change in the

managerial structure and procedures inside the building

company as prcbable causes of failure in tne use of

scbeduling tools.

It is possible to make some distinction in the way

1n which the lack of modelling capability of the technical

concepts affects the programming problem. As it will be

discussed in the following paragraphs, the problems related

to the activity•s duration and definition, and the setting

of objectives criteria can be considered of fundamental

importance, while the problems related to precedence between

activities, variability in the resource requirements, and

Page 68: The Examination of possible Causes of the Lack of Success

?AGE 65

the variability in the total level of resources available on

site can be overcome in a number of different means using

the present progra•ming techniques.

The ove r lapp ing noted in the precedence

relationship between activities can be considered as an

extra flexibility in the schedules, to be used at an

operational or tactical levet. Strategically the schedules

can be drawn disconsidering great part of the overlapping

between activities, thus leaving some room for recovering

from schedule deviations by means of tackling simultaneousty

otherwise preceding and succeeding activities. T~is use of

overlapping is probably already practised on buildin~ sites.

by the

The problem

activit1es is

of variability in resources required

al rea dy welt documented in the

t iterature.

coefficient

Building compan1es could start using the

of variation published by various authors,

until they develop their coefficients, based on feedback

data from tneir own sites. lt is important to note that Fine

{1977-2» suggested that the reduction ot the coetficient of

variation of activity•s duration and resources required is

more important than the reduction of activity•s costs, in

terms of the cost implications ot the schedules of work.

Page 69: The Examination of possible Causes of the Lack of Success

PAGE 66

The variability in the total levet of resources

available daily on site, and the difference betveen the

programmed level and the actual level caused by, for

examplet non-productive time, can be incorporated i~ the

variability of activity•s duration and resources required,

and in the labour constants, respectively. This is believed

to be the traditional approach used so far by the

programming techniques. In bis report dealing with the

matter, the author did not recommend this approach. However,

it is sensible to say that at this moment in the developaent

of the programming techniques there are •ore i•portant

factors related to technical concepts deserving research

attention. The traditional approach can still be used. Its •

unique shortcoming is that the production characteristics of

the activities are made solely responsible for the

deviations between planned schedules of vork and the actual

progress on site, avoiding the examination of possible

causes of discrepancY at the level of the whole site, as it

would be possible if the variability in the level of total

resources available is treated separately.

Difficulties in modelling productivity should be

examined in conjunction with the variability in activity•s

duration and resources required, as far as possible causes

of the lack of success in the application of programming

techniques are concerned. In ideal circunstances, the

perfect modelling of productivity through the use of factors

Page 70: The Examination of possible Causes of the Lack of Success

PAGE 67

influencing it, would reduce yreatly the variability in

these two aspects. If it is accepted that lhe reduction in

the var1ability of activity•s duration could be related vith

greater chances of succesfull application of programming

techniques, it is recommended to follow the following course

of action. Only the more important fact~rs affecting

productivity should be used to reduce the variability in

activities duration and resources required, leaving

unexplained ]reat part of the variability caused by minar

factors. The practical difficulties in collecting and

analysing data to study the influence of minor factors

suggests that it would be better to abandon the search for

an explanation to every variation in productivity •

• Primarily, the programming techniques Mere devised

to examine the time-related aspects of the project, as final

handing over dates and intermediate start and finish dates

of activities. lhe incorporation of the consideration of

resources required, and hence costs, was made afterwards. As

the report showed, more recently some tentative research

work tried to 1ncorporate more and more aspects of

management in the programming issue. The programming

techniques are still in th~ir initial stages of development

and utilization, despite the fact that their most important

representatives, CPM and PERT, had already almost 25 years

of utilization. Therefore, it is possible to suggest that

the programming techniques should be used solely to examine

Page 71: The Examination of possible Causes of the Lack of Success

PlGE 69

the time-related aspects of the project while the co~ditions

for a more systemat1c approach to the whole management

problem are not bring about by research wor~.

In this sense the whole question of estimation of

resources required, variability in resources required, and

modelling of resources required can be ~ept outside the

programming problem. Laing introduced the idea of •one

problem, one type of toot•, after discussing how to estimate

resources required in construction projects. This idea of

separating the resource requirements from the schedule of

operations was totally opposed by Skoytes, uho tried to )

introduce the concept of •operational Estimating•. The fact

that this new approach of estimating was not accepted by the

industry could mean that the buildin~ companies were not

yet ready to consider simuttaneously activity•s duration and

resources required. Ouring the initial stages of development

in construction management, different techniques should be

used to perform different functions.

Accepting the fact that the programming techniques

shoutd be used inttially onty to investigate the tiee-

related aspects of the projects, and that average activity's

duration and their variability could be obtained, the

problems associated with the precedence relationship,

variability in resources required, variability in the total

Page 72: The Examination of possible Causes of the Lack of Success

PAGE 69

level of resources available on site, and productivfty

modelling should not in the future be related to the lack of

success in the application of programming techniques.

possible

Previouslrt it was suggested

causes of the failure

that amonç all the

of the program•ing

techniques, the difficulties in

of different objective criteria

evaluating the i•plications

choosen by the programmer

could be one of the more important sources of problem. It

was shown that tbe attainment of certain objective criteria,

l1ke minimum project duration, minimum resource idleness,

etc., are not only influenced by the characteristics of the

schedulew but by broader aspects of site management and

macro-economy. Shortsighted appraisals of the

process achievements of similar projects under

production

different

schedules would relate the objectives attained (or notJ to

the programming techniques initially used to prodace the

schedules. Failure to arrive at the optimized objective

criteria values obtained during the programming stage would

be wrongly olamed on the scheduling technique.

In fact, the whole question of how to evaluate the

cost consequences of different schedules, after the project

is completed, is much more complex. Possibly the application

of research work to the evaluation of the contribution of

different schedutes to the attainment of the ma~agement

Page 73: The Examination of possible Causes of the Lack of Success

PAGE 70

goals that can be set is beyond the capabilities of the

building research organizat1ons, dueto the great nu•ber of

projects that should be constructed under controlled

conditions.

lhe ideas presented so far showed that from the

set of proble•s associated with the so called technical

problems, only the problems related to activity•s durations

can be rationally blamed for the lack of success in the

application Df programming techniques. Some of the problerns

can be, and probably are being, overcome, like the question

of overlapping precedence. Other problems, like thp ones •

caused by the uncertainities about activity•s resource

requirements are more akin to cost estimating than to time-

related techniques. Finally, objectives criteria cannot be

rationally blamed for the lack of success in the application

of the prograrnming techniques, due to the difficulties in

correlating objective criteria, different schedules, and

results obtained.

Bishop <1968) and Bromilow t1969t claimed that the

simple existence of a schedule, independently of its

characteristics, was sufficient to improve substantially the

site organization and the attainment of objective criteria.

In order to be of any use to site management, the schedule

of works necessarily needs to have some resemblance to the

Page 74: The Examination of possible Causes of the Lack of Success

PAGE 71

way activities are being performed on site. Two aspects are

of fundamental importance to create this resemblance. First,

the progra•med activity•s durations should be such as to

adequately represent the actual durations that would occur

on site. Only in the case in which the schedule of work is

obtained externally to programming techniques, using for

example contractual arrangements, it ;s possible to drop the

requirements of accurate durations for the succesfull

application of programmes of wort.

exercises should be carried out during

project in order to bring the schedule

progress of vork on site, and vice-versa

Second, updating

the course of the

on tine with the

Therefore, the proper consideration of activity

duration and updating are directly related to the similarity

between programmes of work and actual progress, and hence to

the meaningfutness of the schedules to c onstruct ion

management. Conversely, lack of updating and activ;ty~s

durations with no relationship to the time taken to perform

tasks on site, can be blamed for the lack of meaning of

schedules of work to the running of building sites.

,.

The lack of updating and the complexity of the

updating issue were shown as potential major causes of the

lack of success in the application of pro~ramming

techniques. Usually the building companies did n~t introduce

Page 75: The Examination of possible Causes of the Lack of Success

PAGE 72

updating procedures and management feedback systems

simultaneously with the programming techniques, probably due

to the costs of th1s comprehensive package. If the economic

advantages of tbe techniques are in line uith what has been

advocated by some research workers, the change 1n

procedures, or even in the administrative organization of

building companies, would be worthwhile.

Lumsden, for example, suggested that the

application of line of Balance progra•ming techniques would

introduce such a vigorous rhythm of work on site, that it

would be better to have a material's manager at the side of

the foreman, to deal exclusively with orderinç, ins~ection,

and stock control of materials being consumed at a great

speed. This and other organizational changes could be

brought in order to accomodate the require•ents introduced

by the programming techniques.

Finally, the complexities of the programming

problem as sucht should not be appointed as one of the

causes of the lack of success in the application of the

schedulin~ techniques. :t is not possible to say that

simplistic programming techniques are bound to failure, if

the mere existence of schedules of uork. notwithstanding the

accuracy in which they were able to model the building

processt were sufficient to improve the construction of some

Page 76: The Examination of possible Causes of the Lack of Success

PAGE 73

projects, making the application of these scbedules a

succesfull exercise.

Page 77: The Examination of possible Causes of the Lack of Success

PAGE 7~

The previous section emphasized the importante of

the time-related aspects of the schedules, including

activ1ty•s duration and the updating issue, for the

succesful appl1cation of programming techniques. The

suggestion for furtber work are then concerned to these

time-related aspects.

First comes the recommendation ter a greater

emphasis on the study of activity•s duration, as observed on í

actual building sites. Great part of the research effort on

programming techniques applied to construction sites should

be devoted to the observation o f the production

characteristics of the building process. These observations

using work study, time-lapse photography, or activity

sampling could also produce a host of other useful

information, like resources required, cperative•s individual

performance, influence of factors affecting productivity,

etc •• It is suggested that regional or national centres

should be establish to gather 'nformation on the production

characteristics of building sites, imitating the succesful

example of Holland <see Van den Graaf).

Page 78: The Examination of possible Causes of the Lack of Success

PAGE 75

~ore effort should be dedicated to the study of

the intermediate milestones 1n the building process. These

m1lestones, obtained by programming methods or by other

arrangements between the participants of the building

project, are of fundamental importance in the coordination

of building construction, characterized by the great number

of participants and the long time scale of operations.

Research work so far has concentrated on the study of the

duratton of the project, on the setting of the fiAal hand

over date. Yith total durations measured in years, the

final completion dates are of littte meaning in terms of

motivating factors. The intermediate milestcnes are More

important than the final dates for a great nu•ber of

participants in the project, that, as a rule, becomes only

temporarily involved in the process.

In the tong term, it can be suggested that one of

the first issues to be tackted by research work, after the

baste technical concepts of the programming techniques are

exhaustively investigated, is the retationship betYeen the

earty programming of works, updating, and tt.e daily site

management.

The research work now bein~ undertaken by the

author at the Department of Civil Engineering, University of

Leeds will concentrate on the analysis of activity's

Page 79: The Examination of possible Causes of the Lack of Success

PAGE 76

duration, as observed on three house building sites of

repetitive nature.

Page 80: The Examination of possible Causes of the Lack of Success

, Bibliography

Page 81: The Examination of possible Causes of the Lack of Success

PAGE 1

Abdulmajid, S. A. o. ~~~~~~-For~~~sting Models ~or Private tl~~~!ng_Er~1~~1~' Phd Thesis, University of Manchester, Manchester, 1967.

Abernathy, w. s. •subjective Estimates and Scheduling Decisions• tlªn~~m~ni_â~j~o~~' Vot. 18, No. 2, October 1971, PP• 880-888.

Adrian, J. J. ~~Q~hljog_fQ!!~ir~~i120_~eth~~-ProQ~~i!~ii~• Phd Thesis, Department of Civil Engineering, University of Illinois, Urbana-C~ampaign, 1974.

Adrian, J. J.; Soyer, L. T.; •Modelling Hethod-productivity•, ~~-2!-~~~ir~~ii~n_Qi~~i~n~_Aâ~~. Vot. 102, COlt March 1976, PP• 157-168.

Ang, H. s. et alli. •Analysis of Construction Networks under Uncertainity•, ~OOYª!-ªnQ_~ªii~ª! En~ir2rr~~niª! f..Q.!!~~nii2n.~._As~[.~._~.illJ~ª~-~1iu_!::l~!!!:i.J._Qf.i2!!~!: !~Ii• Meet1ng preprint No. 2372, October 1q74.

Anthony, E. F. et alli. •Rating Project Performance by Time-Cost auality•, E~~~~~~in2~_2f_ih~_ISA-f2n!~~~n~~ ªng_~~h!biii~n.~.~iªgªrª-Eª!!~~~-!2~~~ Q~i2Q~~_!l-2~~-1~7], Proceedings published by ISAt Pittsburgh, Pa, 1977t PP• 67-74.

Antill, J. M.; Yoodhead, ~. ~. ~ritical Path Method in ~Q!!~i~~!!~_fr~ii~~' New York, London, Wiley Interscience, 2nd. ed., 1970.

Ashley, o. B. "Simulation of Repetitive Unit Construction•, ~~-2f~Qnstr~~iiQD_Q!~l~l2!!.J._!â~f, Vol. 106, C02, June 1980, PP• 185-194.

Ashvorth, A. "The Source, Nature and Comparison of published Cost Information•, ª~i!Qlng_l~~hno!Qgl_!UQ ~ªnªg~~~n!t ~arch 1980, PP• 33-37.

Ashworth, A. et alti. "An Analysis of the Accuracy of Some Bu1lder'Sstimating•, 2Y~il!I_â~!~~Y~!:• April 1980, PP• 65-70.

Attont W. S~ti!!!.2ii!!9.-~1!!.i~Q-l~-ª!!!!ding__=_!1~trj~-~Q!!.i2.!!t London, George Godwin Ltd, 1st. ed., 1967.

Bataguru, P. et alli. •cost and Time Scaled Networks: Graphtcal Modet•, ~~-Qf_the_~~n~tr!!ctlQ!!_ºivi~i~n· ~~fh• Vol. 103, C02, June 1977, PP• 179-190.

Baldwin, ~. R. et alli. •causes vf Oelay in the Construction Industry•, ~!!._.Qf_!h~ Ccn~i!:!:!.~!.!2!! Qi~i~i~n~-~â~h• Vol. 97, co2, November 1971, PP• 177-187.

Page 82: The Examination of possible Causes of the Lack of Success

PAGE 2

Barnes, N. ~.; ú1llespie, J. s. "A Computer-based Cost ~odel for Project Management•, paper at the I~!~g_!nte~n~!~~-2g~iua_gn_the_f~2~t!~at· A22~!~atiQn_Qf_f~21~~i PLªnn!n9_~-~~t~~~~ I~~~n!g~L_StQ~!b~l~L-~~~Q~~2~-!~!l• edited by ~ats Ogander, London, New York, John Wiley and Sons, 1972, PP• 37-58.

Barnes, M. •on getting paid: the right Amount•, ªg!l[irrg, Vot. 223t No. 6756, 17th November 1972, ~P· 135-136.

Barnes, N. H. "Cost Modelling - An Integrated Approach to Planning and Cost Controt•, ~ng!n~~~lng_~u~ E~2~~~~-Ec~n~mi~§• Vol. 2, 1977, PP• 45-51.

Barnes, N. M. •Human Factors in Project Cost Controt•, ~1Q_tu!ern2ii2nªl_ÇQ~1-~n9i~~ring_ÇQU9~~~~~ ~1~~~h11_19I~t PP• 224-248.

Barnes, N. M. •cost Control during Construct1on•, ÇQ~~i~~~i12n lnQ~!tr~Ç~n!~~~nf~-~~ni!~_conter~~~-~n_E!n2~al E~li~~-anQ_~~n!~~l-in_ÇQn~i~Y~i!~n_E~2i~~i~L hQnQ~nL-l~Ll~!~-~2~_i2ª[t PP• 49-54.

Barroso-Agu1llar, L. F. 3

Barroso-Aguiltar, L. F.

Barroso-Aguiltar, L. F.

et alli. •The Construction Project Oaily Labor Allocation Problem•, paper at the Ihi~Q_ln!~~n~~-~~e~~lY!_~n_ih~ e~~~!l~2!_!Q2ti~ª!l2n_~f_E~ºi~~t f!ªnnl~-ºr_Net~Qrk_Technig~~~· ~1~~!hQ!mL-~~~Q~UL_tt2l_l21~' edited by Mats Ogander, London, ~e~ York, John Witey and Sons, 1972t Vot. 3, PP• 59-71.

et alli. "The Influence of Project Work Inventory on the Oaily Labor Allocat1on Probtem•, lni~~2i1~~1-~~m2~~i~-~n âr~1~m~~n91n~~~ing_en~-An2lt~~~L Eur~~~-~ni~~~~ii~L-1972, Vol. 2, pp.31-35.

~n_lni~~ªi~g~QQ~l!!ug_Meih~Q~log~_fg~ f~Q1~~!-~li~-~2ll29~~~nt, Phd Thes1s, Department of Civil Eng1neering, University of Ill1no1s, Urbana­-Champaign, August 1973.

Beamish, N. ~tatl~tif~-~nªl~~i~-~f_Erog~ctivit~_in_th~ ~~n~i~~~iion_lnQ~~i~t• Building Research Establishment Internal Note No. 13/78, Garston, BRE, January 1978.

Beestont O. T. •one Statiscian•s View of Estimating•, fi~}!Q}Ug ~~QU~mist, Vol. 14t No. 3, 1975, PP• 135-145.

Beeston, O. T. "Cost ~lodets•, Çhªri~~ed ~~~~~~~-ª~Í~Qillg ~ng_gyªn111r_§y~~~~ins~~ªrt~~~' Vot. 5, No. 4, Summer 1978, PP• 56-59.

Page 83: The Examination of possible Causes of the Lack of Success

PAGE 3

Benjami•t N. B.; Greenwaldt T. W. •simulating the Effects of Yeather on Construction•. ~~-Qf_th~-~Qnstr~~!!~-~!~1~!~~-~~~~, Vol. 99, CQl, .July 1973, PP• 175-190 .•

Bennet, F. L. •critical Path Resource Scheduling Algorithm•, ~~-2!-~2nst~~s!iQn_Qi~!~1Qll~-!âC:, Vot. 9~, C02t October 1968, PP• 161-180.

Bennet, .J. •operational Planning•, ~h~t~~~g_Su~~~~Q~-~~i!2ins ª~g-~~suii!z_~yr~~~1ng_q~ªrt~~!~• Vct. s, Spring 1918, PP• 50-51.

Bennet, J.; Barnes, N. M. •outline of a Theory of Measurement• ~h~i~[~Q_Qyªnii!l-~YL~~~Q~• October 1979, PP• 53-56.

Bensasson, S.; Scoinsu, O. ~2ffi~~!~~-~~g~ª~~ fo~-~Qn~t[~~!i2U ~ªn~g~~fn!~-h~ªluª!i2n_R~~2~!-~Q~_1, Jesign Office Consortium, 197~.

Bentley, M. J. E~2~~~!i2n_~nªh~~i2_Qf_~-~f~~~ªt!1_~t~~h E~ª~~-lEh-~~l_â~b2Qlt Building Research Establishment Internal Note No. 87/1959, Garston BREt August 1969.

Bertram, G. •A Fair Day•s Work is anything you want to be•, ~2~nªl_Qf Ing~~!~ial_sngin~~~Jng• Vol. 1°, No. 12, Oecember 1968, PP• 592-599.

Blemer, P. P.; Sielken .Jr., R. L. lDSQLQQ~ª!!n5_E~Ql~~i-~2~1 ~Qll~i~~ª!iQ~_!n!Q_~iQSha~!is_Per!, Institute of Statistics, Texas A&~ University, College Station, Report Themis Tr-52t November 1975.

Birrel, 6. s. •construct1on Planning - Beyond the Critical Path• ~~-Qf_~Qnst~~s!1~n_Q!~i~i2n~!â~t• Vol. 106, C03, September 1980, PP• 389-407.

Bishop, o. •Labour Requirements for House Building - Advantages of Continuity of Work and Experience•, I~~-a~!!g~~· Vol. 209t No. 6374t 16th .July 1965, PP• 150-154. <atso as Building Research Establishment Current Papers, Construction Series No. 18, Garston, BREt.

Bishop, o. •operational Bills and Cost Co••unication•, ~[~hii~~ts~~i~~~ Vol. 139, February 1966t PP• 158, 160, 162. (also as Building Research Establishment :urrent Paper, Design Series No. ss, Garston, BREt.

Bishop, o. "Arcbitects and Productivity•, Rlli~_Jo~~ª~' Vot. 73, November 1966, PP• 513-518. (also as Building Research Establishment Current Paper, Design Series No. 57t Garstont BREt 1966t.

1

. '

Page 84: The Examination of possible Causes of the Lack of Success

PA Gf 4

B1shop, o. I!~-ªª~~gr~n~_iQ_~~ªg~m~n!_~!MQ!~_Q~-ª~~' Building Research Establtshment Current P3pers No. 60/68, Garston, BRE, August 1968.

Bishop, o. R~roductivity 1n the Building Industry•, paper to tbe !!Ql.ª!._Soc!~tl:2..l!!!~Q~i!!.!!!l..-~Ql!~mber_!2l!.t ~~~i!Qiug_IecbuQ!.2g~_!n_!~~~[~~' Philosophic at Transactions No. 212, Londont Royat Society, 1972, PP• 533-563.

Bjornsson, H. c. •Learning Construction ~anagement through Computer Simulation•, lnte~natiQD~l-~QU!~~~n~ QQ_~ªngg~~~n!_Q!_R~~~ª~~h-ªnd sQ~~ªtiQn• ~~QSi2~-~Q!ªng~-~~etemQ~_!972, PP• 1-20.

Blaint B. c. R. ~QC~_st~~~-ª~-2n-ªig_to_~~!imating, 1nstitute of Building Estimating Information Service Paoer No. 30t Ascot, Berkshire, Institute of Building, Autumm 1978, 9 PP•

Blough, R. H. •Effect of Schedute Overtime on Construction ?rojects•, Am~~i~~n-~~~2~i211Qn_Qf_fQ~t-~ngin~~~~ ª~il~iin• Vol. 15, No. 5, October 1973, PP• 153-160.

Borcherding, J; Oglesby, c. •Job Dissatisfaction in :onstruction Work•, ~~-Q!_~Qn~!~~~tiQn_Q!vi~iQD~-~~~~· Vol. 101t C02t ~une 1975t PP• 415-434.

Borcherding, J. •rmprovin~ Productivity in the Construction Industry•, J._Qf_~QD~i~~ii2n_Q~J~i~U.!.._~§ç~, Vol. 102, C04, Oecember 1976, PP• 599-614.

Borcherding, J. •cost Control Simulation and Oecision ~aking•, ~~-Qf_~2fi~iLY~!!gn_Qf~1~l2ll.!..-!~~hY VBl• 103t C04, Oecember 1977, PP• 577-5~1.

Bournazos, J. M. Q~timi~ª!iQD_Qf_~21~~12i~_tlãn~l!n~-~~~tem~ ~-~S1m~i2!12n_!Q~~2~h-=' Msc. Thesis, Department of Civil Eogineering, University of Leeds, 1975.

Brett, o. •rnvisible Economics", .!!!Q!!str.i.2!.!~ed_ª!!!!.!ti!l9. ~~~i~ID~-~ng_f2m2~n~n!~· 3 October 1q66y PP• 6-9.

Brett, o. ·~here Time is Money•, fi~iiging_~~Qn~mi~!' 8th August 1969, PP• 36-37.

Britney, R. R. •sayesian Point Estimation and the Pert Scheduling of Stochastic Activities•, ~~!l2g~m~nt ~~i~!l~~t Vol. 22t No. 9, May 1976t PP• 938-948.

Brittent J. R. •computerising Resource Needs•, Bu.!lg!na• Vol. 212, No. 6457, February 1967, PP• 125-130. (also as Building Research Establishment Current Papers, Construction Series Nos. 39 and 391, Garston, BRE.

Page 85: The Examination of possible Causes of the Lack of Success

PAGE 5

Britten, J. R. Ih~-!~~~!ª~~-of_!im~-~cal~~~~twEr~~-~ng ~l~~nln~_Er~m~~' Building Research Establishment Current Papers, Construction Series No. 4lt Garston, BRE, October 1967.

Bromilow, F. J. •contract Time Performance - Expectations and Reality•, ~ui!ding_EQrYm• Vol. lt No. 3, September 1969, PP• 70-BO.

Bromilow, F. J. •The Nature and Extent of Variations to Buildin9 Contracts•, ª~!~Qi~9-I~Q~Qm!~i' Vol. 9 9 No. 3, November 1970, PP• 93-104.

Bromitowt F. J. •suitding Contract Cost Performance•, ~~!lgin~ h~QQQ~Jst, Vol. 9, No. 4t February 1971, . PP• 126-138.

Bromilow, F. J. •contracts as Yaste Generators•, ª~!hglna E2~~m' Vol. 3, No. lt ~arch 1971, PP• s-11.

Bromilow, F. J. "Performance of Building Contracts in ~astern Australia•, ª~ilQing, November 1971, PP• 18-22r 24.

Bromilow, F. J. •Measurement and Scheduling of Construction Time and Cost Performance in the Building lndustry•, ~h~~!~~~Q_BuilQ~!• Vol. 10t June/July 1974, PP• 57-65.

Bromilow, F. J.; Henderson, J. A. E!~~~Q~!~~_f~r-~~~~2ninB_ªng ~~l~ing_E~r!2~mªn~~-ot_~Yilding_~Qnt~ª~i~· Division of Building Research Report 83, 1974 Revision, ~elbourne, CSIRO, 1574t 52 PP•

Bromilow, F. J. •rhe Impact of Contract Performance Research on Building Management in Australia•, paper at the ~I~-6ih~2n~r~~~Ih~_lmQª~! of_R~~~~~~h-~n_!he ~~il! E~i~2nm~!~L-~~Qâ~2~~~~ ~yngª!~L-!~li• Vol. 2, PP• 153-158.

Bromilow, F. J. •unat is an Affordable House? Pr~QY~ti~ii~ ªng_!he_!!forgªbt~_tl2~~L-2_tran~~r!ei~2! ~-~ªe~~~-e~~~~nt~Q-2!-irr~-tl~~Jn~-I~g~~!r~ ~li~~~iai!Qn~_lltb_N~iiQ~~l_fonve~!i2~t ~~~g~rrª~-~~~irªliª~-A2ri!_!977, PP• 3-11.

Bromilow, F. J. ·~ulti-project Planning and Control in Construction Authorities•, ªui!Qi~S-h~~~Q~ist, Vol. 16t No. 4, March 1978, PP• 208-213.

Building lndustry Advisory Council of Sout~ Africa, •rimely Complet1on of Contracts•, ~~11Qing_Econ2~l~t' 13th June 1976, PP• 5-6.

Page 86: The Examination of possible Causes of the Lack of Success

PAGE 6

Building Management and Marketing Consultants Ltd •Key trend Metbod of Project Controt•, Co~~!~yctiQUt (published by the Oepartment of Environment), No. 15, September 1975, pp. 18-20.

Buildtng Research Estabtishment, E~21~~1-N~!~~~!-!nª~~~!~' Building Research Establishment Digest No. 53, 2nd Series, DecemDer 1964, reprinted with minor revisions in 1976.

Burt, J. M. "Planning and Dynamic Control of Projects under Uncertainity•, Mauªg~m~n!_â~i~n~~' Vot. 24, No. 3, November 1977, PP• 249-258.

Butchert w. •oynamic Programming for Project Cost-Time curves•, ~~-~!_i~~-~~~i~~~!12n_Qi~1~i~n~-~§~(, vot. 93, COlt March 1967, PP• 59-63.

Butler, A. J. (editor) !h~-~~~-2!-~r~ne~-~n_tov=~J~~-hig~ ~~~~itl_ind~~!r!ali!~Q_Ho~~ing, Building Research Establishment Current Paper No. 25/70t Garston, BRE, 1970.

campbelt, J. v. ~u_ln~~iiaªil2n_ªnQ_Evª!~!ion_Qf_~~~iªio ~Qmm~~~Jª!i~-~Y2!1ªh1~~2~Q~i~-E~2a~ªm~_!2~ 1h~_f2n~!~~ction_InQ~1!~' Msc. Thesis, Loughborough University of Technology, May 1970.

Campbellt J. Y. •rhe Evaluation of Certa1n Commercialty Availabte Computer Programs for NetwGrk Techniques•, paper at the lhir~_!n!~~n~i 2~~~~~-Qn_the_E~ªcti~!_!~!~ª!!~u-~! e~~l~~~Eiªnning_Q~-N~i~2rk Techn!g~~~· âi~~!hQ!m~_âM~Q~~-tlª~l~zg, edited DY Mats Ogandert London, New York, John Wiley and Sons, 1972, PP• 79-95.

Carr, R. ~~~1~~~!~_Q1_~~~~!ª!nl!~_ln~2n~!~~ctiQn_~!~rrning, Phd Thesis, Department of Civil Engineering, Stanford University, August 1971.

Carr, R. et alli. •Progress Model for Construction Activity•, J._~f_ÇQ~~tructiQU_!~ti~jiyL_ASCbt Vol. 100t COlt March 1974, PP• 59-64.

ctapp, H. A. bª~º~~-~~gyj~~~nts_fQ~~Qn~~nii2nª!_tlQ~~~~-!s~ Qg~~~Y~Q_ln_fi~-~1!~~1' Building Research Establishment Current Paper, Construction Series No. 17t Garstont BRE, July 1965.

Ctapp, M. A. •weather Conditions and Productivity- Jetailed Study of Five Buildings•, ~yj!g!n~' Vol. 2llt No. 6~39, October 1966, pn. 171t 172 9 175, 176, 179 and 180. talso as Building Research EstablishMent Current Paper, Construction Series No. 32, Garston, BRE).

Page 87: The Examination of possible Causes of the Lack of Success

PAGE 1

Clapp, ~. A. !_~i~~~-Q1_hªQQ~~_B~~Qy~ce ~~gy1re~~ni~-!~~ (~n~!~Yfii~n' unpubtished paper, 7th May 1977.

Clapp, M. A. ª~1~~h~~~~§!_~abQY!-~UQ Mai~~ªi§_=-~-âtYQY-~! R~2Yr~_!ne~i~-ªnd_Er2Qyctj~1i%t Building Research Establishment Internat Paper No. 177/78t Garstont BRE, Oecember 1978.

Clapp, M. A. •Productivity on Building Sites•, ~Y1i2iu~ ~~~~ªr~h_I~!~Q!j~h~~ni_~~~' Spring/Sum•er 198U, No. 51t PP• 17-18.

Cole, L. J. R. •Applied Flowline Technology•, ~Y!!g!ua ~~~UQ~i~1t Vot. 15, No. 4t March 1977, PP• 21a-224.

Cote, L. J. R. •vatue/Time Graphs for Building Contracts•, ~2~hQ_ÇQn~i~Y~1i2Dt Vol. 30, No. 11t November 1977, PP• 40t 42 and 43.

Committee on Housing, Building anc Planning, Economic Comission for furope, United Nations, ~!!~f!-21_R~2~iiii2D Qll_~~1iQin~_Q~rªi1QD~-ªnQ_Ero~~~~~~on_~it~~ R~~Qri_~f-~n-Ingyirr_~n~~~iak~n_Qy_!~!-f2m!iii~~ QU_tlQ~~i~g~-ªuiiging-ªn~_E!anning, New York, United Nations, 1965.

Cooke, J. E. •charting the Course of Progress•, ~Yii~ing• Vol. 239, 3 October 1980t PP• 44-45.

Cowell, A. S. T. ·~vents of Importance: So•e Com•ents on Improvements to Site Programmes•, ªY!i2ing !~~hnoloar_ªnQ_~~nªgem~nit 18th September 1980, PP• 35-36.

Crandall, K. C. •Probabilistic T1me Schedulin1"t ~~-~f-~2D~irY~!ion_Qlvisi~n~ ASCE, Vot. 102, C03, September 1976t PP• 415-423.

Crandatt, K. c. •Analysis of Schedule Simulations•, ~~-of_~QD~i!Y~i1QD_Qivi~i2~~ ASCEt Vot. 103, C03a September 1977, PP• 387-3~4.

Crawshaw, o. r. ~~~i~f!_!uf~r~ª!i2~-ªi_ih~-~~~~n~tr~~ii~n âiªa~' Building Research ~stablishmeAt Information Paper No. 27/1979, Garston, BRE, October 1979.

Cukiermant A.; Shiffer, z.; •contracting for Opt1mal Delivery Time in Long Projects•, ª~l!-~ourn~!-21_h~QU2mlf~• Vot. 7t No. lt Spring 1976, PP• 132-149.

Cullingford, G.; Prideaux, c. A. •A Variational Studr of Optimal Resource Profiles•, ~ª~ªg~m~~!~i~u~~' Vola 19t No. 9t May 1973, PP• 1067-1081.

Page 88: The Examination of possible Causes of the Lack of Success

PA GE 8

Dallast o. s. •use of Linear Regression Analysis to establish Network Time/cost relationships•, ~~Ql~~t ~~nªa~~' 2nd July 1979, PP• 2-s.

Oanoon, s. A. R. I~~-Infly~n~~_Qf_ªyffet~-~n Re~!!t!~~ Q~~~2tion~-~!!h_§i2ii~t!~~! Vari2Ql~ Q~ral!~n~' Msc. Thesis, Oepartment of Civil Engineerin~t University of Leeds, 1975.

Davidson, c. •Repetitive Operations in Building: Results of ECE/UN Studles, l!!~_fi!:!.i!.Q~!:t Vol. 210t No. 6399, 7th January 1966, PP• 9-10.

Davis, E. w. •Resource Allocation in Project Netvorks Modets; a Survey•, 4~Y~nª!_Qf_lu.Qy~!!i2!_Engin~~tin2• Vol. 17t No. 4t 1966t PP• 177-188.

Davis, E. w. •cPH use in Large Construction Firms: a Top r-'anagement Survey•, ~!!.._Q!_ç_Q.!!~!~~tiQn_Q.i~!~i~!!.!. ~~ç_~, Vot. 100, COlt ~arch 1974, PP• 39-49.

Davis, E. w.; Patterson, J. H. •A comparison of Heuristic and Optimum Solutions in P.esource-Constrained Project Scheduling•, tlª~g~~~nt S~l~n~~' Vot. 2lt No. Bt 1975, PP• 944-955.

Dean, G.; White, R. F. PrQ~!:!~i1Qn_~nªl!~i~-~~-ç_!ª~~-~t1~2!:l â~~Q.~!-~_tl2~!i~!.Q_~21!!~~-La~_Eir~!_§~h22l• Project RSM, Nottinghamshire County Council, October 1979.

Oepartment of Science and Industrial Research <Building Research) Prod~~tiv!!z_in_tlQ!:!~~-ªy!!.Qing, ~-EilQ.i_~~!Q!~_§Y!~~-i~_th~_â2~i~-S2~!_!~~-~~~1 Qf_[ng!!n~-~nd_âQYih_~~l~~L-~!:!~~941-=-Q~!~Q~!:-2~, National Buitding Studies Special Report No. 18, HMSOt 1948

Dietz, A. G. H.; L1tte, ~. A. •Education for C~nstruction"t ~~-2!_!h~-~Qnstr~~112n_Q!~!sionL-!â~~' Vol. 102t C02, June 1976, PP• 347-364.

Dover, O. R. •compact - Computer Planning and Controt Technigue•, ç_~!!~ªQ' Vol. 3, No. lt 1971, PP• 21?-34.

Doyte, R. c. "How Good is your Estimate•, !~~ri~ªn_!~~Q~i~ii2U ~f-~2~i-sns1n~~!~-ªY!l~i.in• Vot. 1?, No. 3, May/June 1977, PP• 93-97.

Dressler, J. •stochastic Scheduling of Linear Construction Sites", J.~f_!h~_con~!~uc!!Qrr_Di~!~!QUL_~â~[, Vol. lOOt C04, December 1~74, PP• 571-587.

Ouff, A. R. •control of Costs Allowances for Uncertainity", ~Y!!.Qiug_~choQ.!2S~-~ng_~~nEg~m~nt, Vol. 14, Juty/August 1976, PP• 19 and 45.

Page 89: The Examination of possible Causes of the Lack of Success

PAG[ 9

Duff, A. R. •New Look at Est1mating the Cost of Repetitive Work•, ~~!!diog, Vot. 236, 20 April 1979, PP• 56-58.

Dufft A. R. •stochastic Analysis of Activtty Ouration•, ~~~~i~~~!!~~-~ªe~~~~ Vol. 1, No. lt 1980, PP• 63-69.

Edmonds, G. A. hª~~~~ Sub~t!!~!i~~-1~-~Q~~!~~!!~n~-~-~ª~~ §!~g~-~n~!g~~1ª' Phd Thesis, Department of Civil Engineering, University of Leeds, May 1975.

Elvers, o. A. •Ptanning Mon1tor1ng Frequenc1es for CPM Projects•, ~~_g!_!h~-~Qn~t~~f!1Qn_Qi~i~iQUL-~â~(t Vol. 97t C02, November 1971, PP• 211-226.

Environmental Research Group, University College, ~!~g~-~! th~-~~11Qing~I1m~1ªhl~i_!io~l-R~2~1t UCERG -University of London Environmental Research Group, londont 1972, 121 PP•

Environmental Research Group, University College, Ih~-~~!lQ!na I1m~iªhl~~ªrt_ll_Ih~_â1gu!f!~ªn~~-~f-~~rªii~n· UCERG (University of london Environmental Research Grou~), London, February 197~, 1~ PP•

Environmental Research ~roup, University College, Ih~-~~!!Q!ng Tim~iªhle~eªrt_gl_!h~ PuQlif~f!Q~t University College Environmental Research Group, London, February 1974, 26 PP•

Eriksont c.; Boyer, L. T. •Estimating: State of the Art•, ~~-Q!_ih~Con~!~~f!i~u_Q!~i~!~n~~§~(, Vot. 102, C03, September 1976, PP• 455-464.

Evenwell, J. K. ~~Q~~ctivii~-i~_!h~_Buiig!ng_Ing~~i~[t CSIR, National Buitding Research Institute of South Africa, Report 519, Pretoria, 197~.

Calso in ~~n~!~Y~!!~n_iu_â~ythe~n-~!ci~~· Vol. 19, No. 5t 197~, PP• 131t 133, 135t 137t 139, 141t 143, 147 and 149).

Farkhondeh, N. ~~tl=~g~ Critif~l-eªth~~irrQQ_Ver~i~n-~' Report No. ~~, Centre for Computer Studies, University of Leeds, 29th October 1974.

Farkhondeh, N. Q~~!gn~2i~m~n12ii2U~n9_!2~2!!QU_Qf_~ N~i~~~~~ft~ªr~-!~~-§ch~~~!!~g-~~!!!~1~ E~~Q~~ce c~u~i~~i~~~-E~~f!~t Phd Thesis, Departrnent of Computer Studies, University of leeds, August 1976.

Fendley, L. G. •ro~ards the Development of a Complete Multi­Project Scheduling System•, ~QY~nªl-~! !ng~~trial_~ngin~~ing, Vot. 19, No. 10, October 1968, PP• 505-515.

Page 90: The Examination of possible Causes of the Lack of Success

Ferdows, K. I~t-~!f~~i~_Q!_YQQª!1ng_Qn_Mu!!!=Pr21~~i ~~h~QYi!D9t Phd Thesis, The Un1vers1ty of ~iscons1n, 1972.

PAGE 10

Fine, s., Hackemer, G. "Estimating and Bidding Estrategy•, ~Y!lgjng_I~~hD21~9l-ªng_~ªU29~m~1' SeptemGer 1970, PP• B-9.

Fine, B. "Tendering Strategy•, ~Y112.!rul• 25 October 1974, PP• 115-117, 11~ and 121.

Fine, B. "Tendering Strategy•, chapter No. 8 in !~e~~i~-~f ~~~~~~!~~-2f_f2D~irY~!i2Dt edited by n. A. Turint London, George Godwin, 1975, PP• 202-221.

Fine, B. •Randomness in Construction•, ~~~Q~siy~_QQ_~~~r~112nat !~Q~i~_Qf_ÇQn~!rYs!!ng_tlish~!-~rlg~~· Transport and Ro~d Research Laboratory, 24th June 197b•

Fine, B. Iht_~~tiii!~-~r~~~2~' Fine, Curtiss and Gross ltd. Internal Report No. 4/1977, London, February 1974.

Fine, B. "Production Management•, paper presented at the conference tlanag~~~ni_in_i~t_f~n~!~Y~!iQn_l~QY~i~l• !~~tt~~~~mber_!2I1t paper No. 6, London, P~· 51-55.

)

Fine, B. ~22~i~_Qf_ÇQ~!rY~!12n_E!2~t~~· unpublished paper presented at a Seminar for the Msc. Course in Construction, Department of Civil Engineering, University of Leeds, Leeds 1 January 19BO.

Firmstone, c. J.; Skoyles, E. R. Qe.~~!ion2!._Dr2~..!!l9~-~U~

~!!.l~-=-~~Q2~!-~f_the!r~~~n_ª_bi~t E~iect, Building Research Establishment Current Paper, Design Series No. 63, Garston, BRE.

Fleming, H. ~. "Pricing in Construction - The Relationship of Constants to Productivity•, fiyl!g!ng It~RnQlo~~-ªng_~2Uª9~ment, December 1978, PP• 5-9.

Fletcher, A. L. Ih~~f1~~!_of_NQIDlU2!ion_Q!l_Bu..!l~ing E~~gyct1v!i~-ªnd_~Q~i• Institute of Building Occasional Paper No. 12t Ascot, Berkshire, Institute of Building, 1976, 25 PP•

Forbes, W. S.; Skoyles (. R. •The Operational Bilt•, ~U~ti~r~~ ~Y!!~~R~t Vol. 95, No. Bt 1963t PP• 429-434. (also as Building Research Establishment Current Paper, Design Series No. lt Garston, 3RE).

Page 91: The Examination of possible Causes of the Lack of Success

PAGE 11

Forbes, w. s.; Cooper, H. G. •Problems encountered dur1ng the Introduct1on of Mechanical Plastering ~~1!~n21-ªYi19~r' Vol. 46, April 1965, PP• 380-382, 384 and 387· (also as Building Research Estabtish•ent Current Paper, Construction Series No. 16, Garston, BREt.

Forbes, W. s.; Stevens, A. ~. •The First Operational Assessment of V-Bricks•, E~~(, ~anuary 1966, PP• 23-30. (also as Building Research Establishment Current Paper, Construction Series No. 32, Garston, BRE».

Forbes, w. s. •some Aspects of the Measurement of Productivity in the Building Industry•, E!~~~ Vol. 1, April 1966t PP• 13-16. <also as Buitding Research Estabtishment Current Paper, Construction Series No. 28, Garston, BREt.

Forbes, W. s.; Skoyles, E. R. •A Practical Application of Operational Bilts, Part I: Preparation and Tendering Stages•, ~nªrt~~~Q-~~~~~l~r' Vol. 98, No. 9t 196&, PP• 4Bg-493. <also as Building Research Establishment Current Paper, Construction Series No. 35t Garston, BREt.

Forbes, w. s.; Mayér, ~. F. •The Output of Bricktayers•, ª~li~ing, Vol. 24, No. 6506, 26th ~an~ary 1968, PP• 137-138, 141-142 and 145-14f. (also as Building Research Establishment Current Paper No. 32/196Bt Garston, BRE, 1968t.

Forbes, w. s. ~~~~~~~-~rQg!~~~-in H~y~~ Bui!~in~' Building Research Estabtishment Current Paper No. 25/69, Garston, BRE, 1969.

Forbes, w. ·s. E12~-~h2rts_12-~2n1~Q!_PrQg~~~~n_tl2Y~ing ~jt~~' Building Research Establishment Digests, Second Series, No. 132t Garston, BRE, October 1971.

Forbes, w. s. Qim~rr~12n~!_Ql~~i~!jn~~-2nd_ihe Cy1~Yt_2f ~Li~~i2~~-=~-fas~_§tyg~-Q~-~~S._f2[Q~~~ Building Research Establishment Current Paper, No. 34/197lt Garston, BR~, November 1971.

Forbes, w. s.; Stjernstedtt R. Ih~_Einc~ªmQ~1~~Q_E!2i~~it Building Research Establishment Current Paper No. 23/1972, Garston, BRE, 1972.

Forbest w. s. •Production Cost Information•, chapter No. 7 in ~~e~~t~_irr_h~2n2~i~~-2! con~i~!i2Dt edited by o. A. Turin, London, George Godwin, 1975, PP• 186-2Dl.

Page 92: The Examination of possible Causes of the Lack of Success

PAG E 12

Forbes, w. s. ~Q~~h~~-~~!st~-ªnd_~~Q~~~i!vi!~_Re~~it~_Q! f~l!_Scale_![iai~' Building Research Establishment Current Paper No. 16/1971, Garston, BRE, 1977.

Forbes, ~. s. !~~-~~!!Qnªi!~ilon_~f_tlQY~~-~Y!!Qing, Building Research Establishment Current Paper No. 46/77, Garstont BREt 1977.

Forbes, w. s. tl~Y~~~Yi!~!ng_~~QQ~sii~itr_~!_Ladr9s1~-k~rr~~ tl!llingQQn• Building Pesearch Establishment Internat Note, Garston, BRE, March lgso.

Forbes, w. s. !h~-~et~vans~-~1-ªR~-E~QQY~!i~itl_~!~Qi~~-!Q Es!im~i~• Ruilding Research Establishment Internal Note No. ~43/80, Garstont BRE, November 1980.

Forbes, w. s. Ih~-~~s_âit~-~~!l~!!l_~na!r~i~ Pa~~ª~~' Building Research Establishment 1nternal Note No. 13/1931, Garston, BRE, 1981.

Frasert R.; ~vans, R. w. "Scottish House Building Performance", ~YiiQ!na_li~s~~b-~~iª~!!~hm~n!_N~~~· No. 54, Summer 1981t PP• 17.

,)

Gates, H.; Scarpa, A. "Bidding Contingencies and Probabitities•, ~~-Q!_!nt-~Qn~i[Y~!iorr_Q!vis!Qn~-~~~' Vol. 97, co2, November 1971, PP• 277-303.

Gates, M.; Scarpa, A. •Learning and Experience Curves"• ~~-Q!_i~~Co~![yctiQn_Qivi~QD~-AS~bt Vol. 99t C01t March 1972, PP• 79-101.

Gates, M.; Scarpa, A. •conceptual RMC/Time Synthesis•, ~~-ot_tht-~Qn~![~!!Qn_Qivis~~ ASC~, Vol. 102, C02, June 1976, PP• 301-323.

Gates, ~~., Scarpa, A. •optimum Number of Crews", ~.!.._2.!_1b.~

~~~~![~~!!Qn_Q!~!~i~n~_!â~h' Vot. 104, co2, June 1978, PP• 123-132.

Geddes, s. ~~tlmªt1~g_!~-~~11~i~9-ª~Q-~ivi!_~~gin~~~in9_~Q~~~' 2nd. Ed., london, Newnes-Butterworths, 1976.

Geisel, J. •A Method for Measurement and Analysis of Supervisory Work•, J._Q!_lnQ~~1~ig!_En~in~~[iU9t Vol. 19t No. 4t April 1968, PP• 175-185.

GDodsman, R. w. ~QQ~!!i~_ih~_ftQ~_Qf~~1_ln_~rchi!~~t~~ Qffic~, Building P.esearch ~stablishment Current Paper No. 4/1979, Garston, BRE, 1~79.

Grimmt C. T.; Wagner, N. K. "Weather Effects on Mason Productivity", J. of the Construction ~!~i~iQllt AS~[t Vol. 100t C03t September 1974, PP• 319-335.

Page 93: The Examination of possible Causes of the Lack of Success

PAGE 13

Grimmt c. T. •Estimating Real Estate Oevelopment Time Lapse•, ~~-~!-ib~n~!~Y~!ign_~ivi~ign~â~~' Vot. 103, C02t June 1977, PP• 213-226.

Hall, s. ~~~t~~gQ~l[_~~Q-~~Qn_f~~~~den~~-Net~Q~!~' Transport and Road Research Laboratory, Department of the Envlronment, TRRL Bridge Construction Divisfnn Working Paper BC,3, August 1976.

Hallt s.; Ballt s. lndust~!al_I~ªin!ns_~~~~!_=-~~QQ~l-20 !ng~~![iª~-Train!ng_~!_!n~_Tran~~~rt an~-~~ª~-R~~~ª~~b bª~Q[ª!~[~_e•2!~~1ng_~Q~l-~QQ~!~has~Q-~-~[~~~Q~n~~ Qi~~~ª~~' Sheffield, Sheffield City Polytechnic, 1978.

Hall, s. R!I~-~-~Q!~~te~~[~g[ª~-!~r-~i~la!!ng_~2n~t[~~!12n ~Q[~t Building Research Establishment Internal Note No. 52/1960, Garstont BRE, 1980.

Halpint o. w.; Woodhead, R. W. •Ftow Modelting Concepts in Construction Management•, in Nat!gnª!-~ªi~~ R~~Q~rces sng!n~r!ng_~~~ting~SCfL_~!lªn!~· Q~~[91~~ª~-a1=aª!h_Ja~y~~~~1g, Meeting preprint No. 1618.

Halpin, o. w. ~n_!~~st!gation of the Use of Simulation N~!~Q[~~-fo~_MoQ~l!ing_~gn~tryctiQn_Q~~!ªii2n~' Phd Thesis, Oepartment of Civil Engineering, University of Illinois, Urbana-Champaign, 1973.

Halpint o. w. •constructo- An Interactive Gamin9 Environment•, ~~-~f_!he~2n~!~Ys!12n~i~1~J2~Aâ~~' Vol. 102, COlt ~arch 1976~ PP• 1~5-156.

Handat v. K. et alt1. •A Cost Control and Forecast Model for Building Projects•, paper presented at the ~Iª-~th-~~ns~~~~L-~Ih~_!meª~!_Q!_B~~~ª~~h_Qrr_1he ~~!t_[nv1ron~~1~-ª~gª~~i~_tlung~~L-i2lit Vol. 2t 1974, PP• 276-280.

Handa, v. K.; Geogiades, I. F. ·~oint Venture Utilit,es and the Construction Fir••, paper presented at the ~!ª=~nd~meE~1~~-~~!in~!-2n_Qrg~ni~~tiQn_!nQ ~~n~t~Y~!i~n_Man~g~m~ni_~!_Constry~1i~~' ~lª=~~~-~gmis~jQUL_tl21!~-l~~el~-~Q~~m~~~-121ª' Session 3, PP• 3-177 to 3-198.

Harel1• M. •optimising the Eaecution Sequence in Construction Projects with Pepetitive Processes•, paper presented at the ~Iª=2nd_~~~e2~i~m_§e•in~~_gn_Q~s2ni~2!i~n ªrrQ_ÇQn~!~~cti~n-~ªn~g~m~nl-2!_fgnst~~~112n' f~ª=~~~-ComissjQU1_tl~!fª~-Is[ª~~~Q!~IDQ~C_l~I§t VGle 2t PP• 217-230.

Harris, F. c. •costing the Effects of Bad Weather•, cou~trY~!!gn <Oepartment of Environment), No. 17~ March 1976, PP• 10-13.

Page 94: The Examination of possible Causes of the Lack of Success

PI!.GE 14

Harris, F. c. •controlling Costs on Site•, ªY!!Q!n~ !~f.!!.!!!!!.~l:-!!!!Q_~!!!!~!l~!!!~ni• Vot. 14, No. 10, November 1976, PP• 5-8.

Harris, F. c.; Evans, d. B. •Road Construction - Simulat1on Game for Site Managers•, ~~_Qf_!b~~B!!~!~~~ii2n Q1~!~12n~~âÇ~, Vol. 103, C03, September 1977, PP• 405-414.

Harris, F.; Speed ~an~em~nl_~ªm~~-for y~~-!n_~~n~i[!~i12n• Institute ot Building Occasional Paper No. 15, ~scot, Berkshire, Institute of Building, 1977.

Harrist F. c. ~QQ~[n_ÇBnSi[Yf.iiB!!_tlª!!~~!!!~nl• London, Granada Publishing Company, 1977.

Harris, R. •rhe Time Element• (part 1 and ~art 2t, q~~nii!I ~~~~~l:Q~t October 1976, PP• 49-55, and November 1976t PP• 63-75.

HeinecKt L. F. !~~-~nal!~j~_Q1_!f.!i~il}:~_Qy~~!i2!!L-~~~~Q~!!f.~ !!~!.~~~n~li~.:!l1~~-~nQ_~~gy~nf.~-º!-~Q!:.~_:=­§[ª~lli~21_~Q1!~~~~-t~-~nnªn~~_..tn~-e~irri~~ Qy!.~y!._from_!.h~-ªYiiQing_R~~~arcrr_Es.t~~l!~h!!!~n1 ~ii~-~~!.ivi!.l:_An~!.l:~i~ Paf_kag~, unpublished pa~er, Oepartment of Civil Engineering, Un1versity of Leeds, Leeds, danuary 19~2.

Howenstine, ~- d. •Productivity ir. Building - lhe Universal ~nigma•, ~Y11Q1ng_R~2~Sh-2n~-~rª~tif.~= ~Batim~n!._!n!~rn~11~i' vot. 3, No. 6, November-December 1975, PP• 364-371.

Hydes, w. s. ~~ºHt~_!ii2~ª!i2n-ªUQ_!~~hnigy~~~!_s~li~!.!~g ~i!n_~~~~iaL_R~!~~~n~~-l2_tl19h~~-hnBin~~~1ng, Phd Tbesis, Department of Civil Engineering 1

University of Leeds, Leeds, 1978.

Hydes, w. s. ~º~~-~~~~~m~nt_ª!!Q_~Q~~~!.udlt handouts for the Msc. Course in Ccnstruction, Oepartment of Civil Engineering, University of Leeds, Leeds, 1979-1980 Session.

Institution of Civil Engineers fi~i!_hngin~~ring_§!.ªnQ~rQ ~~iB22-º1-~~ª~~~~m~~!t London, Institution of Civil Engineers, 1976

International Computers Limited e~~!.~[-=_Per~i!.h~Ht_l~~r~ If~-~2m2~i~r_eª~~!!9~-tlªn!:!~i~_12QQ_§~ri~~· London, Internat1onal Computers Limited (!CL), 1972.

International Computers Limited E~rl_Qi~f.-=_lÇ1_ÇQffi2~~~t Eª~~~g~ Use~~-~~llYª1~_12~[~~rie~, London, International Computers Limited {!CL), 1972.

Page 95: The Examination of possible Causes of the Lack of Success

PAGE 15

~eanes, R. E. •critical Path Hethod applied to the overatl Process of Building•, Ih~-~~jiQ~!t Vol. 205, No. 6286, 1963, PP• 957-963, and also ~~~tt~~~Q~~~~~!• Vol. 96, No. 7, 1964, PP• 339-349. (also as Building Researcb EstablishmeBt Current Paper, Design Series No. llt Garston, BR~t.

~eanes, R. ~.; Britten, ~. R. •Networks Diagrams: Some Notes on Alternative Presentations•, ~Y!!Qin~' Vol. 210, 10th June 1966, PP• 102-106. Calso as Building Research Establishment Current Papers, Construction Series No. 29, Garston, BREI.

Jewell, Y. s. •Risk taking in Criticat Path Analysis•, ~~nª~~m~ni_âf!~n~~· Vot. 11, No. 3, January 1965, PP• 438-443.

~ohnston, o. w. •Linear Scheduling Method for Highway Construction•, ~~-~f_th~-~QD~i!~!l~Q-~!~l~i2n• ~â~ht Vol. 107, C~2, ~une 1981, PP• 247-261.

Jordan, M.; Carr, R. •Education for the Professional Construction Manager•, J. of the Construction ºi~i~f2n~-~~~(, vot. 1o2;-cõ3~-s;pt;;h;~-~~76, PP• 511-519.

Kappaz, M. H. •Effect of Scope Changes on Schedule - A Systems Approach•, I~2n~2S!i~n_of_ih~-!~~1~ªn ~~~Qfiat!Qn_Qf_~Q~i-sng!n~~!~L-E!~!da_â~fii2n~ ~~mQQ~1~~-~!ª~1-ª~~fhL-E12LlQ~-~ªn~ª~r_gg=g1, American Association of Cost Engineers, Miami, 1978, PP• 106-111. (also in Am~~icªn_!~~Qfiat!Qn_of_Cost_(ngin~~~~ ~~!l~iint Vol. 9. No. 6t November-December 1977, PP• 221-224 and 237.

Kauffold, P. v. ~~iii~at_E~~Q~~E~-~!l~f~!i~n-ln~!Qfh~~i!~ E~~I~ct N~i~2L1• Phd Thesis, University of lllinois at Urbana-Champaign, December 1976.

Kello~, J. c. et alli. •Hierarchy ~odel of Construction Productivity, ~m~~i~n_â~~!~!~-~1_f1~i~-~~ain~~~~ ~2n~tnti2n_2nQ_s!e2~iii~nL-~2~i~~-~e~il_g~2~ l2I2t ASC~t 1979. <also in ~~-21_ln~_fQn~i~Y~!!~n_Qi~i~i~nL_~~~s' Vol. 107, COl, March 1981, pp.l37-152).

Kennedy, w. 3. et atti. •Ctient Time and Cost Control wtth Network Analysis•, ªYil2ing_~f2n2mi~i' Vol. q, 1970, PP• 86-92.

K1ddt J. B.; ~organ, J. R. •The Use of Subjective Probability Est1mates in Assessing Project Complet1Bn Times•, in Communications to the Editor, ~~n~g~!tnt §fi~n~~~ Vol. 16-At PP• 266-26?.

Page 96: The Examination of possible Causes of the Lack of Success

PAGE 16

King, w. R.; Wilson, T. A. •subjective Time Estimates in Critical Path Analysis - a Preliminary Analysis•, ~ªn~g~m~i_Scl~ns~' Vol. 13, No. 5, ~anuary 1967, PP• 307-320.

Kin9• w. R. et alli. •on the Analysis of Critical Path T1me Estimating Behaviour•, ~ªnªg~~~~~El~nS~• Vr·l· 1~, No. 1, September 1967, PP• 79-B~.

King. w. R.; Lu~as, P. A. •An ~xperimental Analysis of Network Planning•, ~ªuªg~men1_§~1~n~~' Vol. 1~, No. 12, August 1973, PP• 1~23-1432.

Kinninburgh, w. •comparison of Times Required to Build Walls in Building Units of Various Sizes•, ~~liQiD9• Vol. 215, No. 6543t 11th October 1969, PP• 151-152 and 155-156. <also as Building Research Estçblishment Current Paper No. 77/1968, Garston, BRE, November 1968.

Kleinfeld, I. "Manpower Use in High-rise Residential Construction•, 4~_Q1_!h~_fQn~!~il~n-~lY1~1Qn ~2~ht Vol. 102, C02t June 1976, PP• 379-383.

Klingel, A. ~. •sias in PERT Project completion Time Ca~culations for a Real Networt•, ~ªnªg~~~n! ~Si~GS~• Vol. 13, No. ~, Oecember 1766, PP• 8194-8201.

Kotiaht T. c. T.; Wallace, N. O. •Another Look at the PERT Assumptions•, ~ªaªg~m~n!_§E}~n~~· Vol. 21, No. lt September 1973, PP• 4~-~~.

Laing, w. M. ~~N~~-~eRroª~h-12-~2n~i~~si12n_~anªg~~~ai_Ih~2Y9U ~~llQing_~~ª~~~~m~!-ªng-I!m~_§igngª~g~, Lancaster, Construction Press, 1976, 213 PP•

Langiert F. J. •statistical Control of Time Standards•, ~ªnªa~meni_~si~nE~' 1963, PP• 527-541.

Latta, J. K. ~ª~~-~iYQ!~_iQ_Q~i~rmiu~ih~-~~h2Yr~-r~g~j~~g i2_~Qu~!~i-ih~_ÇQn~r~i~-E~2m~~-Q!_Iªli_~~1!Qing~ in_~~~~~E-ªng_~ini~r' Building Research Note No. 70, Division of Building Researcht ~ational Research Councilt Ottawa, Canadat May 1970.

LemessanYt J.; Clapp, M. A. R~~2~~~~-lnQ~i~_iQ_N~~ f2ni1I~si~n~_!h~-~ªQQ~r_R~g~jre~~n1~-Q!_~Q~Qiiª! ~~11Qirr9t Building Pesearch Establishment Current Paper No. 85/1975, Garston, BRE, 1975.

Lemessany, J.; Clapp, M. A. R~~Q~r~~-!n~~ts~~Qn~i~~~ii2nl !h~-~~h2Y~-~~g~iL~m~nt~_2!-tl~~~~Y!lging, Building Research Establishment Current Paper No. 76/1978, Garston, BRE, December 1978.

Page 97: The Examination of possible Causes of the Lack of Success

PAGE 17

lichtemberg, s. •Evaluation of the Effectiveness of Project Plans•, paper at the Ih1~Q_!nte~n~iL-~l!2~~1~m ~n_the Pr~fi1fªl-~2~l1cªi~n_Q1_e~~l~~i el~nnirrs_ºr_N~i~º~~-l~hn!g~es1_â!2~~hºl~t ~~~~~llL-~ªl-121~' edited by Hats Ogander, londont New York, John Wiley and Sons, 1912, PP• 219-229.

l1chtemberg, s. •rhe Principle of Sucessive Planning•, paper at the Ih1rd_!n!~rn~!~-~~m~2~1~m-~n_!h~-E~ªf!!~2l ~2~li~~t1QQ_Q1_ErQ1~~i-El2nnin~_Ql_~~t~Q~1 I~~hn!g~~~1-~!~~~b2l~L-~~~Q~nL_~ªI_!~Ig, edited by Mats Qgander, London, New York, John Wiley and Sons, 1972, Vol. 2t p~. 226-236.

Lichtemberg, s. et alti. •Graphical Evaluation of Project Schedules - A Computer Program for Interactive Man-computer Application•, paper at the EQ~~!h_ln!~~n~!~_âlm2Q~l~m_Qn_!~~-E~~ftifª1 ~22l1~~!1QQ_Qf_Pr~l~fi_Pl2nn!n~_Ql_N~t~2~! I~fhnigy~~1-f2~!~~-l211' 1974, PP· 5-16.

Linn, c. J. Ih~_!m2l~m~n!ªiiºn-ªn~_Y2~Qf_N~two~~-~n~ll2i~ l~fhn1~~~s in_2_~Qn~!~~~!1Qfi-~QID~Dlt Msc. Thesis, Department of Civil Engineering, University of Leeds, Leeds, 1976.

logcher, R.; Collins, w. •Hanagement Impacts on Labor ?roductivity•, ~~-Q!_!h~-~2n~!~~ctjQn_Q!~12iQn• A~~ht Vol. 104, C04, December 137Bt PP• 447-461.

Lumsden, P. I~~-biu~_Q!_ªªl~n~~-~~thQQt Oxtord, Pergamon ?ress Ltd, Industrial Training Divisinn, 1968, 71 PP•

Mazzetti, M. ~U-~~~~2isat_º!_Ind~2t~lali~~g-ª~i!2ina_~~i~QQlit ~se Thesist Department of Civil ~ngineering, University of Leeds, Leeds, 1977.

Mehra, K. K. !~!~~~~~in~-~~ilifªl-~ªlrr_El2nnin~_in_ª~ hU~in~~~in~_Ei~~' Msc Thesis, Univers1ty of Manchester Institute of Technology, 1~67.

Heyert ~. L.; Schaffer, L. R. •Extensions of CP~ for ~ultiform Project Time Cost Curves•, ~~-Q!_!h~-~~~~i~~~!i2n Qi~!~i~~~~~ht Vol. 91, COl, May 1967, PP• 45-67.

Meyers, o. A. •critical Path Computerized•, Th~-~~n~~!tlng hn9!U~~r' Vol. 35, No. 2, February 1971, PP• 46-47.

McCaffer, R. •some Examples of the Use of Regression Analysis as an Estimating Tool•, lh~-H~2n!J!~-â~!~~~~~ Vol. 32, No. s, December 1975, PP• 81-36.

Page 98: The Examination of possible Causes of the Lack of Success

PAGE 18

~cGlaum, w. •overtime in Construction•, A~ric~n_A~~~~i~t1Qn ~!-~Q~i_sug1n~~~-ª~!!~1in, Vol. 15t No. 5, October 1973, PP• 141-143.

HcNally, H.; Havers, J. A. •Labor Productivity in the Construction Industry•, J._Q!_!he_con~ir~~i!Qn Qi~!~!Qn~_AâÇ(_, Vol. 93, C02, September 196f, PP• 1-11.

Mitler, o. G. ~~~r~!im~i-ªng_I~rn~~~r-~!~ªre~ni~r~_!n ~~~!1~~Q-~Q-~~l!ln9lQDt BRANZt Building Researcfu Association of New Zealand technical paper P2, Wellin9ton, New Zealand, 1975, 37 PP•

Miller, D. G. Pr~~~~!ivi!~_in_~Q~~~-ª~11g1ng~!h~_Yi~~~-2f A~~!rª!iª~~ªna~er~~-â~~r~i~Q~~-ªng_Ç!r~~ni~r~' BRANZ, Building Research Association of New Zealand report P20t Wellington, New Zealand, December 1977, 31 PP•

Hoavenzadeh, F.; Markow, H. •simulation Model for Tunnel Construction Costs•, ~~-Q!_!h~_ÇQn~ir~~iiQD gi!i~ion~_Aâfb• Vol. 102, cot, Marcb 1976, PP• 51-66.

Moder, J. J.; Rodgérs, E. G. •Judgement Estimates of the Moments of PERT Type Distributions•, ~~nªg!~~n! âsi~n~~· Vot. 15, No. 2, October 1968, PP• 876-883.

Hoder, J. J.; Phillips, c. R. •Merge Event Bias Correction Procedures•, appendix No. 9-5 in PrQ~~! ~2nªg~~ent wi!h_rE~-~ng_PE~I• 2nd. Edition, London, Van Nostrand Reinholds Co., 1970, PP• 229-239.

Moodie, c. L.; Mandeville, o. E. "Project Resource Balancing by Assembly Llne Techniques•, J._Q1_!ng~~iri~i Ingin~erin9• Vol. 17, No. 1, July 1965, PP• 377-383.

Morris, o. •seasonal Effects on Building Construction•, ~~-~1-ih~_co~1~~~1ion_~i~i~i~n1_Asc~, Vol. 102, COlt March 1976t PP• 29-39.

Morrist o. •[conom1c Analysis for Accelerated Constraction• ~~-Qf_~~~-ConS![~iion_gi~iSiQ~_AS~~t Vol. 103, C02t June 1977, PP• 273-286.

Morrisont N.; Stevens, s. "A Construction Cost Data Base•, ~~ª[i~red ~~2ni!il_§Y!~~2!t June 1980, PP• 313-315.

Naaman, A. •Networking Methods for Project Planning and Controt•, J. of~1h~_rQn~!~~!i~n_Qi~l~l2GL_!~~~' Vol. 100, C03, September 1974, PP• 357-372.

Page 99: The Examination of possible Causes of the Lack of Success

PAGE 19

National Econoaic Develop•ent Office Whª!~-~~~ng_~n-~!t~ =-ª-~~~g~ªm_!~~~~2ng~, London, NEDO-National Economic Development Office, July 1971.

National Economic Development Off1ce [n9i~~ring_f~n~t~~~!12n ~~~!2rmª~~~-=-E~~Qrt_gf_!~~-f~r~~~ªt1~~-f2~~tr~~!i~n e~rf~rm2~~~-~Q~king_Eª~!lt EOC, Mechar.ical and Electrical Engineering Construction, London, NEDD­National Economic Development Office, HMSO, 1976, 88 PP•

National ~conomic Development Office Ho~_[!~~!hi~-i~ f2n~tr~~ii~o_1_A-~!yg~_2f_B~~~Y~~~~-~2-E2~t!~!eªn!~ !n_1~~-~~n~!~~~i!2n-fr2~~~~· London, NEOO-National Economic Development Office, HMSO, 1978, 90 PP•

National Electrical Contractors Association Ih~_[ff~~!-21 I~~~~rªi~[~_Qn_E~QQY~ii~i!lt National Electrical Contractors Association Peport, Washington, USA, 1974.

National Electrical Contractors Association Ih~_[ff~~t_Qf ~~lti~~!~r~_Builgins~-~n_t~Qdu~ii~i!lt National ~lectrical Contractors Association Report, Washington, USA, 1975.

Nazemt s. •Labour<s\aff) Turnover and its Effect on Productivity•, ~Y!lgins_l~~hn~i~l-ÊDQ_~ªnª~~m~n!• Vol. 7, No. 5, May 1969, PP• 114-115.

Neale, R. H. •rowards Effective Project Planning <or how to survive the Planning Whirpool)", ~Yi12ia~ I~~~!1Qh29.Lª!!Q_Man-ª.S~m~nt, February 1980, PP• ~-10.

Nowakt F. •rh~ Building Game•, ~r~hi!~i2-~2~2lt 21st Abril 1976, PP• 789-790. talso as Buildin1 Research Establish"ent Current Paper No. 49/76t Garstont BREt July 1976.

Nutall, J. F.; Jeanes, R. E. •The Critical Path Method, 1 - Its Value in Building Design and Construction; 2 - Oetailed Methods of Use•, !b~_fiYilQ~~' Vol. 204, 14th ~une and Vol. 205, 21st June 1963. talso as Building Research Establishment Current Paper, Construction Ser1es No. 3, Garston, BREt.

Nutall, J. F.; Amos, E. E. •critical Path Method Applied to Building Controt•, lh~-~Yi!Q~~' Vol. 207, No. 6327, 1964, PP• 381-392. <also as Building P.esearch Establishment Current Paper, Construction Series No. 12, Garston, BR~).

Page 100: The Examination of possible Causes of the Lack of Success

PAGE 20

Nutallt J. F. "A Study of Decision Rules for Site Control: Guidance for Foremen vhen Programme Changes•, Ih~-~uilder, Vol. 2G9, No. 6379t 20th August 1965, PP• 407-409. <also as Building Research Establishment Current Paper, Construction Series No. 19, Garston, BRE).

Nutallt J. F.; •Resource Scheduling: coping with Labour ~roblems as they occur on site•, !h~-~Yl!g~~' Vot. 210, No. 6404, 11th February 1966, PP• 311-316. «also as Building Research Establishment Current Paper 1 Construction Series No. 25, Garston, BRE).

O'brien, J. J. •voM Scheduling for High-rise Building•, ~~-~t-ih~-~~n~!~~f!iQn_oi~i~iQn~_!â~~· Vot. 101, C04, Deceaber 1975, PP• 895-965.

Oxley, R. In~~!i~~~-in_ih~_co~!!Yfi!Qn_Ingy~!~~-=-htf~~ts QQ_hª!niug~_2DQ-~2~i~• lnstitute of Building Slte Management Information Service, Paper No. 74t Ascot, Berksh1re, Institute of Building, Summer 197Bt 10 PP•

Patterson, J. H. "Project Scheduling: the Effects of Problem Structure on Heuristic Performance•, ~ª~21 &~~~ªr~h_bQ~l~!if~_Qy~~i~r!~· Vot. 23, No. 1, March 1976, PP• 95-123.

Paulson, B. ~ªn=~~m~Yt~r_~~nf~Ql~_tQr_E~Qi~f!_~2n29~!~nt• ~hd. Tbesis, Oepartment of Civil Ergineering, Stanford University, Stanfordt 1971.

Paulson, B. •Project Planning and Scheduling: unified Approach•, ~~_Qf_lh~-~Qn~!~~f!i~~-Qivi~iQn• a~~St Vol. 99, COlt March 1973, PP• 45-5B.

Paulson, B. •Estimation and Control of Construction Labor Costs•, ~~-Qf_the_~Qn~i~uction_Q!~j~i~n~-~~~~' Vol. lOlt C03t September 1975, PP• 623-633.

Paulson, B. ~~rr!in~!na_Re~~ª~fh_in_ihe º~Y~!Qe~~ni_Qt Lni~~ª~t!ye ~ªrr=f2mQ~1~~-~l~i~m~_fQr_sngin~~ting ~~~irYf1iQn_et2i~~1~• Stanford University, Department of Civil Engineering Technical Report No. 200, September 1975, 68 PP•

Paulson, B. "Concepts of Project Ptanning and ControL•, ~~-~!_ih~-~2n~!!Y~112n_Q!vi~!nnL_a~fht Vol. 102, CDlt Harch 1976, PP• 67-80.

Pautson, B. •Goals for Education and Research in Construction•, ~~-Qt_i~~~QD~l~Yf1Í2Q_Qi~i~!Qn~ ASfht Vol. 102t C03, September 1976, PP• 479-495.

Paulson, B. •Jnteractive Graphics for Simulating Construction Operations•, ~~-~!_!h~-~2~!tY~!!QD_ºiY!~iQD~-A§f(, Vol. 104t COl, March 1978t PP• 69-76.

Page 101: The Examination of possible Causes of the Lack of Success

j

~

PAGE 21

Pedersen, H. •Network Planning of Repetttive Processes in the Housing Construction Industry•, paper presented at the !~1~9-In!~rn~!~_âlm2~1um_~n_!he_E~ª~t!~at !22li~ª!!gn_Qf_E~21~f!-flann!ng_Qz_N~!~~~~ I~fhn1g~~~â12f!ho1mL_â~~Q~n~-~ªx_l21a, edited by Mats Ogander, London, New York, John Wiley and Sons, 1972, PP• 381-392.

Peert s.; Selin~er S. •cPT- New Approach to Construction Planning•, paper presented at the ~!~=~§~_E!~~! ~lm~Q~i~~-Qn_orgªni!ª1i2n_ªnd_ÇQn~tr~fiign ~ª~g~~~nt_of_ÇQu~!r~!i~nL_flª=~2~_f2mi~~i2U• Mª~uin~!~UL-YSAL-~ªl-121~, Session 4, PP• 156-163.

Pereira, G. L. ~n-~~r2i~ªl_gf_tl~m~n_Eª~12~~_!ff~E!ina Ec2Q~Eti~!tl_in_~Qn~1~~!ign, Msc. Thesis, Department of Civil Engineering, Univ~rsity of Leeds, 1978.

Perry, c; Greig, J. o. "Estimating the Mean and Variance of Subjective Oistributions in FERT and Oecision Analysis, ~ên~~m~nt_âfi~n~~' Vol. 21, No. 12, August 1975, PP• 1477-1480.

Perry, w. N. •Autdmation in Estimating Contractors~Earnings•, I~~-~ihitary_hn~in~~!' No. 410, November­December 1970, PP• 393-395.

Pigott, P. T. •som~ Factors Influencing Productivity in House Building•, paper at the CIª-6!h CQn~r~~~' ~!h~_lm~1-2f_R~~ªrfh on_th~ Bu111-~n!irQnm~ni~' ~~Qª~~~i~~~ngªr~~-!211t Vol. 2t PP• 269-274.

Pigott, P. T. ~-E~~~~~i~iii-â!~Ql_Qf~Q~~-ªuilgin~t 2nd. Impressiont Oubl1nt An Foras Forbartha - The National !nstitute for Physical Planning and Construction Research- , Decemter 1974.

Pilchert R.; Davidsont ~. •computer Based Simulation ~odels for use vith Construction Projects•, paper presented at the f!B-lng_ârmQg~iYm_~a_Q~gª~iza!i~a-ªng ç~n~ir~fiiQ~-~ª~ª~~m~a!-2!_~~~1~~tlg~ [lª~~~~-co~~~i2n~-~2i!ª~-l~~ª~lL_NQY~~~~~-!21ª' Vol. 2t PP• 295-319.

Pitcher, R.; Oxley R. •optimising Productivity and Cost in Repetitive Construction•, paper presented at the [Iª~H~~-Eir~i_§l!2~~i~~-QU_Qrgªnizª!i2U-~ng ~Qn~irYf!JQn_~ªD29~E~n!_of_~Qn~tryEii2llt ÇIB~~~2_Comj~~ÍQll~-~2~hln9iQ~_Qâh~-~ªr_!2I2t Session ~, PP• 172-195.

Page 102: The Examination of possible Causes of the Lack of Success

PAGE 22

Plant. J. J. !~âY~~~~-2n_bªbo~r_!~ª!lab!lj!~~g_B~g~!r~m~n! 2n_b2n2ºn_hº~ª1_!~!hº~iir_~ºn~ir~~!!Qn_~ii~~· Greater London Councit Research Memorandum No. RM 46B, London, Greater London Councit, 1975, 64 PP•

Popescu, C.; Borcherding, J. •oevelopments in CPM, P~RT and Network Analysis•, ~~-ºf_ig~_çQnst~~~!!~rr_Q!y1~1QDt !~~~' Vol. 101t C04, December 1975, PP• 769-784.

Popescu, c. •cPM - Cost Control by Computer•, ~~-º!_th~-~Qn~!~~~!12n_Q!v1~jQn~-A~~~' Vot. 103, C04, Oecember 1977, PP• 593-609.

Popescu, c. •CPM - Interactive Train1ng Tool"t ~~-Q!_th~-~QD~l~Y~!!QD_Qi~i~i2D~_A~~~' Vol. 104, C02, June 1978, PP• 157-166.

Poskus, K.

Preston, R.

K. lng~~triª1!~~g_~yil2in~_çºn~ir~!!Qnt!i~~L~2~i tlQQ~ii_EiL~i_QygL!~rl~-R~~Y!!~~-EY-1§• Construction Engineering Research Laboratory <CERL) Report No. CERL-IR-D-66, Urbana-Champaign Illinois, Construction Engineering Research Laboratory, April 76, 31 PP•

)

L. ~~n~g~~ni_Q!_~Qn~!r~~tiQn_B~sourc~~· Phd. Thesis, Gerg1a Institute of Technology, Georgiat 1974.

Price, K.; Horn, ~. Ind~~i~i21i~~2-I~Q=~!~~~º~~1D~• !_Erog~~tiviiX_â!~Qlt London, The National Building Agency, August 1970, 35 PP•

Pristsker, A. B.; Happ, u. W. •GERT: Grapbical Evaluation and Review Technique, Part 1: Funda•entats•, ~~~1-lnQY~iria!_~ngi~~i~• Vol. 11, No. s, ~ay 1966t PP• 267-274.

Pritsker, A. B.; Yhitehouse, b• •GERT: Graphical Evatuation and Review Technique, Part 2: Probabilistic and Industrial Engineering Applications", ~~-Q!_!ng~~!rial_~ngine~rJng, Vol. 17, No. 6t 1966t PP• 293-301.

Rabenek, A. • R e se ar c h I nt o S it e ~,anagement •, ~r c h .i!.~~!.!!!:.ª-! ~~~.iSllt Vol. 46, No. 5t 1976, PP• 275-280.

Rawclifte, J.; Rickard, P. J. •An Algoritbm for Resource Levelling", ª~i!g!ng, Vol. 212t 20th January 1967, PP• 131-136.

Reiners, w. J.; Broughton, H. F. Erºg~!.!viix_jn_~Q~~~-ª~i!21DU• ~~~QnQ_E~QQL!t National Building Studies Special Report No. 21, London, HMSO, 1g53, 37 PP•

Page 103: The Examination of possible Causes of the Lack of Success

PAGE 23

Rickard, P. J. B~~~~~~-!ii2~21!20_!o_(U9in~~~l~-t~Q~t~~~ii2U• Phd Thesist Oepartment of Civ1l Engineering, University of Leeds, Leeds, 1968.

Roderick, I. F. ·~xamination of the Use of Critical Path Methods Building•, ª~!!~log_Iec~n2!29Y-ªO~-~!uªg~m~n1• Vot. 15, March 1977, PP• 16-19. <also as Ruilding Research Establishment Current Paper No. 12/1977t Garston, BRE, 1971.

Rosso~, J. A. K.; Hoavenzadeh, F. •Management Issues in the USA Construction Industry•, ~~-21_1h~-~20~i~Y~iion ~ivi~l2ll1_A§~~' Vot. 102, C02, June 1976t PP• 277-29'+•

Russelt J. H. •Progress Function Models and Their Oeviation•, ~~-Q!_loQY~1~!ªi-1o~in~~ing, Vol. 19, No. 1, January 1968, PP• 5-10.

Salag, a.; Silberman, H. sff!~ienf~_Qf_bªQQYr_1n2~i_!n_~~~Q~~ ~~o~1rY~ii2llt National Swedish Building Research Summary R15t 1975t 2 PP•

Seeley, I. H. ª-Yi!.ç!io!l_QY2!11iil~â-(!~l2i!l~Q_:.~l_(i!iti~U• London, Macmillan Press Ltd. 1969.

' Selinger, s. •construction Planning for Linear Prcjects•,

~~-2!_ih~_f~o~1r~ct!Qu_Ql~~!Q01-~~~(, Vol. 106, C02t June 198Dt PP• 195-205.

Scheurer, r. Qgl!m~~-Er21~i_§~U~Q~!ins_yn~~r Mulii~~~-~~~QYr~ ~Qn~ir~!nt~, Phd Thesis, Oepartment of Computer Studies, University of Leeds, Leeds, 1978.

Scott, o.; Cull1ngford G. "Schedulin9 Game for Construction Industry Training•, ~~-Qf_ih~_fQn~!~~!i~~-g!~!2iQ!l• ~~~ht Vol. 99, COlw ~uly 1°73, PP• €1-92.

Schaffer, L. R. •Impact of Research on Management•, paper presented at the ~1ª=6tn_~Qll9~~~~-:I~~-lm~ª~1 Qf_Re~~EL~D-Qn_th~-ª~!!i_En~!rQn~~ni:1-ª~Q~~st, ~Yu~r~!~li• vol. 2, PP• 147-152.

Shanley, L. F.; Keaney, s. J. !n_s!ªm!n2i1QD-21_kªQQ~r-~Qn!~i in_tlQY~llS• Dublin, Ann Foras Forbartha, May 1970.

Sheppardt R. F.; Harris, F. c. •Predicting the Effect of Weather on Construction Costs•, ªYi!.Qjng_I~~hn212~X ªmL!!anª9f:!!!~ll1t Vol. 15, No.?, July/~ugust 1977t PP• 14-16.

Page 104: The Examination of possible Causes of the Lack of Success

PAGE 24

Shipley, N. !2[Íê~!!j!z_in_Q~!~~!t Operational Research Department Internal Note n. 4/71, loughbGrough Un1vers1ty of Technology, 1971.

Shippam, R. •House Building Productivity in USA•. ~Y!!giu~• Vol. 213, 15th December 1967, PP• 127-128 and 131-132. (also published as Building Research Establishment Current Paper No. 28/68, Garston, BRE, March 1968).

Skoyles, E. R. •Introduction to Operational Bilts•, g~2nl11l 2Y!~~~~~' Vol. 21t 1964, PP• 27-32. Calso as Building Research Establishment Current Paper, Oesign Series No. 32, Garston, BREt.

Skoyles, E. ~. I~~~~1~~~Qm_Q2~!ª11~n~!_Bi!!~' Building Research Estabtishment ~iscellaneous Papers No. 9, Garstont BRE.

Skoyles, E. R. E~~Q~i~-Q~~~ê!i~Dªl-ªil~• Building Research Establishment Miscellaneous Papers No. 10, Garston, BRE, June 1967.

Skoyles, E. R. !nl[QQ~in~_Bi!!~_Qf_Quantiti~~!~E~!~liQn~! EQ~~atl, Building Research Estabtishment Current Paper No. 62/6ôt Garstont BREt August 1968.

Skoyles, ~. ~. •Materials Wastage - A ~isuse of Resources•, ~Y!!ging_R~~~ª~~h-ªu~_Prê~ti~~~ July/August 1976, PP• 232-243. <also as Building Research Establisment Current Paper No. 67/76, Garston, BRE, 1976.

Smitht o. H.; Rawlings, s. Th~_I!f~~l_Qf_~~êth~r_Qn_~~i!ging PrQg~ctiviilt Construction Industry Research and Information Association - CIRIA -, Technical report No. 50t Londont CIRIA, June 191,, 25 PP•

Soeterik, F. w.; Foster, P. K. Tim~L~~i_Pe~fQ~~~n~~-~!

N~~-l~at~u~-~H11Qlns_~~utrªct~, BRANZ Technical Paper P13, Wellington, BR~NZ -Building Research Association of New Zealand -, Juty 1976, reprinted February 1979, 20 ~P·

Spooner, J. E. •Probabibistic Estimating•, ~~-Q!_ih~_ÇQn~!~~!iQn_Qi~i~i~n~-~âÇ[• vot. 100, COlt March 1974t PP• 65-77.

Stacey, N. "Estimates of Uncertainlty•, ~Yi!ding, Vol. 237, 19 October 1979, PP• 63-6~-

Stacey, N. •Assessing the Uncertainity of an Estimate•, I~~-~~2~1i!x-â~~~~~~Lt Vol. 36, June 1980, PP• 105-107.

Page 105: The Examination of possible Causes of the Lack of Success

l

1

PAGE 25

Starkt R. M. •unbalanced Bidding Models - Theory•, ~~-~!-!h~-~2n~!!~~!i2rr_Qiv!~!~nL-!§~~· Vot. 94, C02, October 1968, PP• 197-209.

Stevens, A. J. •Activity Sampling Studies a1ded by the Use of an Optical Reader•, ~~~1-§!yg~, Vol. 16, No. 1t January 1967, PP• 21-29. <also as Building Research Establishment Current Paper, Construction Series No. 38t &arston, BRE).

stevens, A. J. Af!i~j!~_§ªmQl!ng_QU_~~!lQing_§li~~l-~~~iQ~~ ~~Q~~1~n~~-!n_ih~-~~~-2f_QQ!lfª!-R~~Q~~~· Buitding Research Establ1shment Current Paper No. 16/69, Garston, BREt May 1969.

Stewart, ~. ~.; Torrance, v. 9. •An Examination of Certain Relationships between Accuracy, Productiv1ty and Site Management in the Construction of Reinforced Concrete Framed Buildings•, paper at the ~ra=~~~-§~~2nQ_§~mQQ~j~~_Qn_Q!gª~i~ªii2n_ªnQ ~Qrr~!~~!!Qn_~~nªg~m~n!_Q1_Con~!r~fi!Qn1_fiª=W6~ ~Qmi~~2n1_tl~i!~-l~~ael1_~Q~~!Q~!_!~!~· Vol. 4t PP• 311-326.

Stone, P. A. ~~ilgi~~-EcQUQID!f~~-Q~~iYnL-E!QQ~~tiQn_ãnd Q~5ªni~ªil2nL-ª_âlUQQlif-Yi~~' 2nd. Edition, Oxford, Pergamon Press, 1~76, 293 PP•

Strandellt M. •Productivity in the Construction lndustry•, ~m~~!f~n-A~~2f1ªilºn_Qf_fQ~!_~nsin~~!~-ª~!i~!ln• Vol. 20, No. 2, ~arch/April 1978, PP• 57-61.

Streeter, ~. J. •Time Thermometer•, paper presented at the ~m~~i~~n-A~~fiaii~n_of_Ç~! Eng!n~~t~_!nnY~l tl~~t1n~~-~ll~ªuk~~L-~i~~~n~j~g§=g~i~_4yng !~li• published by AAC~, Morgantown, West Virg1n1a, 1977, PP• 273-276.

Swant c. •La~or and Materiats Requirements for Housing•, ~t~~~iDJ~_Eg~~!-2U_hf2D2mi~_Aci!viil• Vol. 2t 1971t PP• 347-381.

Talbot, p. J. Eirrªnf!ª1-ln~~nii~~~-=-QQ_!h~l~~~t1' Institute of Building Occasionat Paper No. lOt Ascot, Berkshire, 1nstitute of Buildin~, 1976.

Taylor, r. E. •How Certain are you about the Uncertainity of your Estimates ?•, !m~ti~ªn_!~~Q~j~!iQ~-~! [~~i-hngl~~~~-~Y!!~iin' Vol. 19, No. 3, May/June 1977, PP• 101-102.

Page 106: The Examination of possible Causes of the Lack of Success

1 !

------~--~~ ---- .. ?~· ~-~~~---

FAGE 26

Thorpe, B. Y. •Trends in Productivity in the Housing Industry•, in ~tod~!!~!i~-ªng_th~_!ffQ~gabl~~Q~~~' 222~t-~Q~~~g-1rso~~~!~i-2!_e~ers_e~~~~~i~2 ~!_i~~-Hous1n~_ln~~~i~~~~~!at1Qn_!~~1ih N~ti~~2i-f2n~~ntion~_f2nh~tra~_!~st!ªliª' ~~ih_!977, PP• 12-15.

Tindalet P. et all1. •R<esearchJ and O<evelopment) in tow Oensity Housing: The Finchampstead Project•, f2n~~g, Vol. 2, No. 3, 1970, PP• 123-135.

Toussaint, E. •Prise in compte des Intemperies dans les Planning•, paper at the ~1~=21U-~Qn~~~~~· ~!h~_lmeª~1-Q!_R~~~~~~h-ºn-1h~-ª~111_hn~i~Qn~~nt•. ~Y~ee~~-tl~gª~~~-!21it Vol. 2t PP• 297-298.

Trimble, G.; Darlo~, M. s. A_âtUQl_!Q_Q~!~~~~~-ih~ E~~~i2i!i!X_Qf~_b!n~_2f-ªª12n~e CQm~Yi~~ E~g~ª~m~• Loughborough, Oepartmeflt of Civil Engineering, Loughborough University of Technology, February 196~.

Van den Graaf, M. P. •Richttigden voor Bouwactiviteiten•, ~yj!~1n~-I~~hn21Q9~-ªnQ~2nªg~m~ot• September 1979, PP• 8-12.

Vergara, A. J.; Soyer, L. T. •Probabil1stic Approach to Estimating and Cost Controt•, ~~-Qf_!h~-~~D~!~~i!Qn D!vi~i~DL-A~~~' Vot. 100, C04, Oecember 1974, PP• 543-552.

Vergara, A. J.; Soyer, L. T. •Portfolio Theory: Applications in Construction•, ~~-of !h~_Con~i~~~t!~n ~i~!~ion~_A§~~~ Vot. 103, C01, March 1977, PP• 23-38.

Verschuren, ?. •rhe Value of Labour Econo•Y in the Suilding Industry•, ~lª-=-H§~-~~~~ng_~~iym_QU Qtg~ni~2ti2~-ªQQ_~Qn~i~~i~n_Man2~~m~ni-2! 21_~Qn~!LY~ii2n~-~I~=~65_~2mlssiQU~_ttªif~• !~~ª~!~~Q~~mQ~~!2lª' Vol. 2t PP• 335-340.

Vahab, K. A. ·~anpower Requirements in a selected Number ~f

Housing Projects in N1ger1a•, ªuilQing_~n~!rQnm~n!• Vol. 15t PP• 33-43.

Wainwright, w. H.; Whitrod, R. ~~ª~Y~m~n!_of Bui1giu9_~~~l• London, Hutchinson Technical ~ducation, 1968.

Walker, A. ·~an-hours Requirements for conventionally can s t rue t ed Dwe lli ngs• t !hL~h.2!1~!L~Y!.!!.~l.2! • Vot. 103t No. 6t December 1970t PP• 278-297.

Walker, A. •A Study of Variation in. Output of Buildin~ Operatives•, !~~-A!.~hi!~~i~UQ_~~!vey~!t Vol. 16, November-Oecember 1971, PP• 10-13.

Page 107: The Examination of possible Causes of the Lack of Success

f

PAGE 27

Walker, A. •A Study of the Factors affecting the Level of Output on certain Bu1lding Sites•, lh~-g~ªai!i~ ~~~~~B~' November-December 1972, PP• 65-68.

Whitehead, B. •Productivity in Rricklarinç•, BuliQ!na_~~!~n~~' Vol. 8, 1973, PP• 1-10.

Uhitt, K. J. ~~!~ti~l~_!ªnªg~m~n!_!n_!h~_ÇQnstr~~i!~rr_r~~Y~!t~· Phd Tbesist Oepartment of Civil Engineering, University of Leeds, 1974.

W1lson, P. H. ~Yt~~~-of_~ini~t-~Qt~lng_~tªfi!~~in_~~~i~ªn~' Building Research Establishment Current Papers, Construction Series No. 20, Garston, B~E, September 1965.

Woodhead, w. o. •Achievable Improvements in Housebuilding Productiv1ty•, paper presented at Ih~-~Q~~jn~ Lnª~~i~2-~~~2fia!l2n~-llih_~ªiJQnªi-~2~~~n!1Qn ~~~!i_!2Ilt paper No. 3, Canberra, Australia, PP• 16-24.

Young, s. M. ·~isapplications of the Learning Curve Concept•, ~~-21-~ndu~!~iª!-sngju~~rin~· vot. 11, No. s, August 1966, PP• 410-415.

t