• £26m major engineering programme
• March 2013 contract awarded
• Programme aims:• Basic broadband for premises in programme area
• As much fibre based broadband with the funds available
• When added to commercial broadband roll-out:
• 93% fibre based broadband
• 87% superfast broadband (National target 90%)
• Milestone of build to date March 2015:
• 158 cabinets live, serving over 30,000 premises
• Average speed uplift to date – 52Mbps
• 35% of sub 2Mbps now getting faster broadband
Phase 1 BDUK Programme
![Page 3: The engineering challenge · 2015. 3. 19. · •March 2013 contract awarded •Programme aims: •Basic broadband for premises in programme area •As much fibre based broadband](https://reader033.vdocuments.mx/reader033/viewer/2022051910/5fff250ff0eaf360b85fe204/html5/thumbnails/3.jpg)
The engineering challenge
![Page 4: The engineering challenge · 2015. 3. 19. · •March 2013 contract awarded •Programme aims: •Basic broadband for premises in programme area •As much fibre based broadband](https://reader033.vdocuments.mx/reader033/viewer/2022051910/5fff250ff0eaf360b85fe204/html5/thumbnails/4.jpg)
• Feb 2014 – BDUK Phase 2 £250m investment - 95%
Superfast Broadband by 2017/Locally 90%
• Shropshire £11.38m Superfast Extension
• Ring fenced indefinitely
• Marches Local Enterprise Partnership - £5m
• EU funding - tba
• March 2014 £1.5m extra funding
• April 2014 – Shropshire Broadband Partnership
• Cabinet agreed to progress procurement for Phase 2
• Aim to finalise contract - April 2015
• Finish Phase 1 and commence Phase 2 - Winter 2016
Phase 2
![Page 5: The engineering challenge · 2015. 3. 19. · •March 2013 contract awarded •Programme aims: •Basic broadband for premises in programme area •As much fibre based broadband](https://reader033.vdocuments.mx/reader033/viewer/2022051910/5fff250ff0eaf360b85fe204/html5/thumbnails/5.jpg)
Exchange Cabinet Parish
premises
Information
Munslow Cabinet 3
Exchange
Only or
‘EO’
108 High proportion of network
rearrangement completed for EO
lines onto Munslow 3 – still in
planning.
Likely by end of 2015
Munslow 1 66 34 projected to be picked up by
additional £1.4m by end of 2016
Phase 1 Build Projections for structures serving the Parish
Munslow Parish
![Page 6: The engineering challenge · 2015. 3. 19. · •March 2013 contract awarded •Programme aims: •Basic broadband for premises in programme area •As much fibre based broadband](https://reader033.vdocuments.mx/reader033/viewer/2022051910/5fff250ff0eaf360b85fe204/html5/thumbnails/6.jpg)
Munslow Parish
![Page 7: The engineering challenge · 2015. 3. 19. · •March 2013 contract awarded •Programme aims: •Basic broadband for premises in programme area •As much fibre based broadband](https://reader033.vdocuments.mx/reader033/viewer/2022051910/5fff250ff0eaf360b85fe204/html5/thumbnails/7.jpg)
Exchange area map