the data center hybrid solution · capex and opex short and long term data center hybrid analysis....
TRANSCRIPT
Presented by:
Mark Evanko
Principal – Engineer / BRUNS-PAK
The Data Center
Hybrid Solution
The data center presentation provides a summary of data center options and
considerations associated with meeting present and future facility requirements.
Whether retrofitting an existing complex, expanding an existing facility,
consolidating multiple data center/server facilities, or relocating a data center
operation, the elements that impact size, space, cooling, reliability,
OPEX/CAPEX costs, and scalability/modularity will include:
Facility Infrastructure
Energy Efficiency
Co-Location
Cloud Internal/External
Migration/Relocation
Computer Software
Disaster Recovery
Computer Hardware/Software
Personnel
Modularity/Scalability/Reliability
Communications/Network
Service Level Agreements
CAPEX vs. Lease/OPEX
Container
Legal Repercussions
Government/Corporate/University/Non-Profit
The critical aspect is to maximize the return on investment both short and long term. 2
Agenda
3
Part I
The 2015 and “Beyond” Data Center
Solution Challenge
4
The 2015 and “Beyond”
Data Center Solution Challenge
• Reduce Data Center CAPEX/OPEX Costs While
Increasing Performance
• Leverage Available Technologies
Cloud both private and public
Co-Location
Containers
Physically owned sites
Disaster recovery
• Increasing Data/Telecommunication Uptime Performance
• Project Data Security
Critical
5
• Exceed Both Internal and External SLA Agreements
• “Just in Time” Data Processing with Corresponding Data
Center Facility Expansion
• Data Center Solutions That Provision for the Future
Technology Solutions (HPC, Chilled Water, Cloud, etc.)
• Complete and Comprehensive Disaster Recovery/Business
Continuity Planning and Execution.
• At All Costs, Protect the Enterprise Computing Operation.
• Deploy Energy Efficient Green/LEED, Modular/Scalable
Solutions.
6
The 2015 and “Beyond”
Data Center Solution Challenge
Part II
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
7
PERSONNEL (12)
CLOUD (4) Internal/
External
SERVICE LEVEL
AGREEMENTS (11)
CONTAINERS (14)
CAPEX vs. LEASE/OPEX
(13)
CO-LOCATION (6)
MIGRATION/
RELOCATION (7)
MODULARITY/SCALABILITY
/RELIABILITY (9) COMMUNICATIONS/
NETWORK (10)
COMPUTER
SOFTWARE (8)
DISASTER RECOVERY (5)
COMPUTER HARDWARE (3)
FACILITY INFRASTRUCTURE (1)
GOVERNMENT/CORPORATE/
UNIVERSITY/NON-PROFIT
(15)
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
The BRUNS-PAK Hybrid “2015 Transformation”
Efficient Data Center Elements
ENERGY EFFICIENCY (2)
LEGAL REPERCUSSIONS (16)
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
8
1) Facility Infrastructure
A. Architectural
B. Civil
C. Electrical
D. Fire Protection (EPO Code Change) – Update NEC/NFPA vs.
Factory Mutual
E. Mechanical – CFD Models
F. Security
G. Site
H. Structural
I. Geographic Regional Considerations… i.e. southwest hurricanes,
west earthquakes, etc.
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
9
2) Energy Efficiency
A. ASHRAE 9.9 – Higher Inlet Temperatures
B. Why pay for electrical consumption for mechanical cooling?
C. CFD Models
D. Heat Wheel
E. 400v AC/DC
F. DCIM
G. Virtualization of Servers
H. Higher efficiency computer equipment
I. March 14, 2014 – Federal data center efficiency legislation passes
US House of Representatives
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
10
Written to save “dollars” and be more green
Office of Management and Budget to create a strategy
DOE and EPA to study server and data center efficiency trends
New “data center energy practitioner program”
New “metrics”
Data center LEED guidelines - New
J. LEED – New data center guidelines
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
11
3) Computer Hardware
A. Higher Efficiency
B. “Flash” storage announcements
C. Virtualization
D. High performance computing impacts – All critical?
E. Scalability/Modularity/Flexibility
F. Water cooled to the chiller
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
12
4) Cloud
A. Managed services
B. Internal vs. external
C. Migration to the cloud
D. Impact of returns
E. Moves/adds/changes
F. Trouble shooting
G. True “partner” of equal financial stability – San Diego 2013 cloud
provider “30 day notice to vacate”
H. Downtime: Who Pays?
I. Security Breach: Who Pays?
J. Terms and conditions (Legal Beagles!!!) 2014+
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
13
K. Senator Menendez – New Jersey – Sponsoring new legislation
2015 - fines
L. Speed to delivery of applications
M. “Candidacy” of applications
N. The 2014 / 2015 / 2016 contract language for cloud contracts
O. Critical vs. non-critical data
P. Moves/adds/changes
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
14
5) Disaster Recovery
A. Hot or cold
B. Recovery time
C. Internal disaster recovery data centers vs. external “leased”
disaster recovery centers
D. Lease terms and conditions for availability
E. Government regulations for uptime – banking/healthcare/etc.
F. Active testing
G. Guarantee of “space” when needed?
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
15
6) Co-Location
A. Leased data center constructed space
B. Capex schedule of delivery minimized
C. ROI – see total cost of ownership – 3+?
D. Other tenants? – Impact of security
E. Downtime: Who pays?
F. Security Breach: Who pays?
G. Terms and conditions (Legal Beagles 2014!!!)
H. Senator Menendez – New Jersey sponsoring legislation 2014 and
beyond
I. Financial strength of service providers – see Cushman Wakefield
survey of “economics” 2014 report.
J. Moves/add/changes
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
16
7) Migration / Relocation
A. Move existing or buy/lease new?
B. Asset swap outs
C. General hardware life cycle ± 3-4 years?
D. Maximize uptime
E. Multiple phases
F. Consolidation strategies
G. Physical cost vs. planning costs
H. Impacts of the network
I. Move it? – Plan to migrate back? – Resume update
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
17
8) Computer Software
A. Large scale corporate “procurement” effort to leverage one (1)
massive licensing agreement vs. “two hundred” division licenses
B. Single point of failure considerations vs. mirroring
C. Impacts of hardware platforms
D. Downtime
E. Impact of licenses at cloud and/or co-location
F. Cost changes 2014 / 2015 / 2016
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
18
9) Modularity / Scalability / Reliability
A. Optimize
Computer hardware
Computer software
Telecommunication (network)
Facilities
Service level agreements
Scale with growth!
B. Defray CAPEX dollars until needed across the board
C. Scale without interruption
D. Reliability past/present/future
E. In house vs. outsource
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
19
10) Communications / Network
A. Redundant / isolated paths?
B. Multiple carriers
C. Data breach? Who pays? Significant dominant focus 2014 /
2015 / 2016
D. Data security? Who is responsible?
E. The power of the cloud – iPhone® 5S/6/6Plus – WOW!!
F. Impact of network loss
G. Who manages the network?
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
20
11) Service Level Agreements
A. Internal vs. external (client) based
B. Government imposed guidelines/performance (i.e. HIPPA, etc.)
C. Co-Location / Cloud – 2014 transformation – fine print – who
pays? – how much? – damages (Legal Beagles 2014!!)
D. What does 99.999 availability mean to me when “I go down?”
E. Moves/adds/changes without interruption!
F. New “fines/penalties” by external agencies being processed 2014
/ 2015 / 2016
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
21
12) Personnel
A. Employee vs. contract personnel
B. Mr. Snowden contract person? Who is liable?
C. Client worldwide – “as the world turns” personnel solution –
United States/Europe/Singapore – payback 18 months
D. Efficiency metrics
E. Data Breaches?
F. Banks recent statements – limited liability
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
22
13) CAPEX vs. OPEX
A. CAPEX – Capital dollars spent to build/deploy
data center across (16) elements
B. OPEX – Operating dollar “expense” to
financial statements – very attractive
C. New trend of internal “OPEX” data center
solution 2014 / 2015 / 2016
D. Cloud/co-location OPEX?
E. 2008 - 2014 economics crises worldwide leads
to bottom line
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
23
14) Containers
A. Portable
B. Speed of delivery?
C. Local zoning regulations regarding deployment of permanent
structure?
D. Pre-fabricated structure compliance with local building codes /
approvals
E. Work flow
F. Saves building addition
G. Government exempt
H. ADA compliance
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
24
15) Government/Corporate/University/Non-Profit
A. The new “data center energy efficiency” (March 2014) and
Senator Menendez Initiative
B. The cost and liability of data infringement
C. Worldwide government are experiencing the impacts of data
processing issues
D. Currently US regulations exist for banking, healthcare, financial
etc.
E. The board or directors and trustee (university) responsibility and
liability
F. Insurance
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
25
16) Legal Repercussions
A. The most dominant theme of 2014 / 2015 / 2016 data center
optimization impacting in house vs. outsource
B. Government fines
C. Stockholder lawsuits
D. Individual lawsuits
E. Fiduciary responsibility
F. “Non-disclosed” trends
Copyright © 2014 BRUNS-PAK 2014. All Rights Reserved.
Defining the Mix of “Elements” (16)
Considered in the Data Center Solution
26
Part III
Total Cost of Ownership?
27
Total Cost of Ownership
The 2015 and beyond data center “hybrid” total cost
contributors include costs of: Facility Infrastructure
Energy Efficiency
Computer Hardware
Cloud Internal/External
Disaster Recovery
Co-location
Migration/Relocation
Computer Software
Modular/Scalability/Reliability
Computer Network
Service Level Agreement.
Personnel
CAPEX vs. Lease/OPEX
Containers
Government/Corporate/University/Non-Profit
Legal Repercussions
Total cost of ownership for all data center solutions is the
optimal value. 28
Step Process
1) Information technology understanding of existing, growth, and
uptime
2) Interpolation to hardware, software, network, and facility
requirements
3) Overall consideration of sixteen (16) element solution with total
cost of ownership
4) OPEX vs. CAPEX
Considerations / include:
1) Retrofit
2) Expansion
3) Build new
4) Cloud
29
Total Cost of Ownership
5) Co-Location
6) Container
7) Network
8) Multiple data center sites
Define
1) Day 1 CAPEX
2) Day 2 CAPEX
3) Day 1 OPEX
4) Day 2 OPEX
Return on investment.
30
Total Cost of Ownership
Energy efficiency solutions
1) Heat Wheel
2) 400v AC/DC
3) DCIM
4) ASHRAE 9.9
5) LEED
6) CFD
NOTE: Initial CAPEX and continuing OPEX considerations.
31
Total Cost of Ownership
900 kW IASE Using Rotary HXs
Part IV
Concerns of All Data Center Solutions
32
Concerns of All
Data Center Solutions
CAPEX and OPEX short and long term data center hybrid
analysis.
Impacts of down time for remote provide solutions (i.e. co-
location, cloud, etc.) Who pays? Duration? Amount?
Impacts of network security for data provisioned and/or hosted off
site? If compromised, who pays, amount?
What are the specific contract provisions for cloud/co-
location/third party suppliers?
Considerations of the financial viability of the third party
providers with guaranteed expansion rights and costs fixed?
The hybrid solution in summary encompasses a true partner
mentality. 33
Third party providers: A) Network carriers?
B) High density power?
C) Green practices?
The financial and healthcare regulations/conformance?
Should I lease vs. capitalize the data center solution?
What are the terms of any third party agreement?
Adds/changes? Future technology?
What provisions have I made associated with ever bringing
back the applications to corporate data center? What are costs?
Resume update???
Damages and Claims
34
Concerns of All
Data Center Solutions
Part V
Data Center, Co-Location, Container,
and Cloud Considerations
35
Data Center, Co-Location, Container,
and Cloud Considerations
Data Center Facility
1) PLUS A. Complete ownership of hardware, software, and network
B. Self provisioned security
C. Self provisioned operations
D. Control of overall short/long term “16 element solutions”
E. Control of change management
F. Direct costs for change management
G. Self reliability
2) MINUS A. Larger CAPEX cost
B. Non-leveraged non-critical applications
C. Reliance on employee operation
D. Larger employee cost/commitment
E. Potential provisioning space/power/cooling for short term facility
solutions
36
Co-Location
1) PLUS A. Defray capital cost
B. Short schedule for availability
C. Manage your own services
D. “Others” maintain facility
2) MINUS A. Network cost
B. Shared facility with multiple tenants
C. Legal contract terms and conditions
D. SLA regarding downtime
E. Not on company owned property/facility
F. “Control” by others
37
Data Center, Co-Location, Container,
and Cloud Considerations
Containers (Physical)
1) PLUS A. Pre-packaged/pre-wired
B. Short term delivery
C. Trailer/modular building blocks
D. Minimized capital expense
E. Modular
2) MINUS A. Uniform building code acceptance
B. Planning board/zoning board
review/approval
C. “Tractor trailer” concept
D. Data center long term work flow
consideration
38
Data Center, Co-Location, Container,
and Cloud Considerations
Cloud Computing
1) PLUS A. Fast delivery of “IT” services including hardware, software, and
network
B. Decreased capital cost of computer hardware, computer software,
network, and facilities
C. “Instantaneous” increase in bandwidth planning
D. Decreased electrical utility cost and facility maintenance (assume
off site)
E. Access to latest “refresh” of technology
F. Emerging technology
G. Internal vs. external clouds
H. Many vendors
39
Data Center, Co-Location, Container,
and Cloud Considerations
2) MINUS A. Network security of information
B. Control of operation
C. Legal contract terms and conditions
D. Fees/costs associated with cloud
E. Definition of “total cost of ownership” of the cloud
40
Data Center, Co-Location, Container,
and Cloud Considerations
Part VI
Critical Considerations to be Evaluated when
Assessing Whether to Keep a Data Center
Operation “In House” or to “Outsource”
41
1) Type of data processed
2) Type of applications utilized
3) Type of computer platforms utilized across the enterprise
4) Uptime requirements both short and long term
5) Impacts to the enterprise of:
A. Downtime
B. Data security breach
C. SLA’s
D. CAPEX vs. OPEX mission
6) Impact of pending legal legislations – if it changes – can you
move back? Force existing contracts to change with
liabilities?
Critical Considerations to be Evaluated when
Assessing Whether to Keep a Data Center
Operation “In House” or to “Outsource”
42
Part VII
How to Optimize the Overall Data Center
Solution Recommendation
43
1) The BRUNS-PAK belief of the 2014 / 2015 / 2016 sixteen (16)
element data center “hybrid solution”
2) One “size” does not fit all!
3) The major components of hybrid:
How to Optimize the Overall Data
Center Solution Recommendation
A. Physical internal data center
B. Cloud – external
C. Cloud – internal
D. Co-location
E. Network
F. Disaster Recovery
G. Container
H. Internal finance – OPEX vs. CAPEX
I. Legal liability
Breach
Downtime
J. Application and hardware
“candidacy”
K. Flexibility to change based on current
legislation!! (Unless new opportunities
are sought)
44
Part VIII
What are the Recent “Trends” in the Data
Center Industry for Solutions
45
1) Outsource – no thinking required
2) Co-location vs. cloud
3) Critical data/platforms/applications staying “home”
4) Legal language/penalties/liabilities in new co-location and
cloud contracts for:
A. Downtime
B. Data breaches
C. Financial guarantees of 3rd party providers
D. Accommodation of future “unknown” legislation
5) Internal data center cloud and co-location solutions with
OPEX cost models
What are the Recent “Trends” in the
Data Center Industry for Solutions
46
6) Tremendous focus on total cost of ownership for all sixteen
(16) elements prior to decision
7) TCO considerations with risk
What are the Recent “Trends” in the
Data Center Industry for Solutions
47
Part IX
Why is Data Center Security Such a Large
Consideration for Location of Processing?
48
1) Liability, Liability, Liability
2) If corporate, what are the board of directors responsibility to
the stockholders?
3) If academic/university, what are the trustees responsibility?
4) If non-profit, what are the board members responsibility?
5) If government, what are the administration members
responsibility?
6) Hospital / healthcare:
A. Patient care records?
Why is Data Center Security Such a Large
Consideration for Location of Processing
49
7) Recent sample examples:
Anthem – 80 Million
Home Depot – 60 Million
Target – update from spring 2014 - CIO, President, and Board of
Directors removed.
JP Morgan Chase – 56 Million
Dairy Queen
Fire Department (specific)
US Government and Wiki leak – national security
The Cyber attack
Numerous other financial institutions
Apple / iPhone
50
Why is Data Center Security Such a Large
Consideration for Location of Processing
8) Reported by cyber security breach data. The attacks were
up 20.5% last year and expected to significantly grow in 2015
/ 2016 / 2017 +++ - Identity Theft Resource Center
9) Confidential examples:
A. Client co-lo
B. After seminar disclosed “in confidence” lost $56,000,000 attack. Non-
disclosed
51
Why is Data Center Security Such a Large
Consideration for Location of Processing
Thank You
52