Steinar Stapnes, LHCC June 2004 1 The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels Whole ID sits inside bore of LAr calorimeter cryostat (6m long, 1.1 m radius) TRT straw tube tracker, silicon strips (SCT) and PIXELs Services run along cryostat bore and out along cryostat flange Installed in sections: barrel (SCT+TRT), inner endcap (TRT A+B,SCT), outer endcap (TRT C-currently staged) and pixels (inside pixel support tube PST with beampipe)

Upload: adria-jensen

Post on 31-Dec-2015

26 views

Category:

Documents


0 download

DESCRIPTION

The ATLAS inner detector. Whole ID sits inside bore of LAr calorimeter cryostat (6m long, 1.1 m radius) TRT straw tube tracker, silicon strips (SCT) and PIXELs Services run along cryostat bore and out along cryostat flange - PowerPoint PPT Presentation

TRANSCRIPT

Steinar Stapnes, LHCC June 2004 1

The ATLAS inner detector

TRT endcap A+B TRT endcap CTRT barrel

SCT barrel SCT endcap

Pixels

Whole ID sits inside bore of LAr calorimeter cryostat (6m long, 1.1 m radius) TRT straw tube tracker, silicon strips (SCT) and PIXELs

Services run along cryostat bore and out along cryostat flange Installed in sections: barrel (SCT+TRT), inner endcap (TRT A+B,SCT), outer endcap

(TRT C-currently staged) and pixels (inside pixel support tube PST with beampipe)

Steinar Stapnes, LHCC June 2004 2

Pixel status

The rad-hard electronics being out of the list of the critical parts, we now face the challenge to produce the large number of modules needed with the necessary yield and in 15 months.

According to our schedule (in part validated by prototype mounting of modules on stave and sectors) the critical part is now the module fabrication and qualification, not the mounting on the local support neither the local support fabrication (that has started long ago). The module fabrication is just starting up (see picture below of module).

We obviously have to also look carefully at all the mechanical compatibilities between parts coming from many sources, that’s why we plan 2 dry tests (one in Cern and 1 in LBNL) to check all parts before the end of the year.

Other issues are : • Patch panels are quite complex, design is well underway and all the necessary tests and mock-ups has been

done, but fabrication should to be followed with attention. In particular the optoboards on PP0 are close to the critical path and we are only at the preproduction phase (we did implement a close follow-up of this item at last steering group)

• Optical fibre bundles have been ordered, cables order will be done soon (need to know the final length calculation).

• Off detector parts (RODs, powersupplies, etc) are making good progress

Let’s see now where we are with the module fabrication(all plots updated on May 31st).

Disk module

Steinar Stapnes, LHCC June 2004 3

Overview bistave with pigtail and type 0 cable bundle

Steinar Stapnes, LHCC June 2004 4

Loading…

Shown below is a source scan of a module on a stave (see components and also some detail of the flex circuit, but no bump damage due to the mounting process).

We plan to start loading of production modules to production stave and sectors before the end of July.

Steinar Stapnes, LHCC June 2004 5

Complete Solid Models of ATLAS Pixels

10 cm radius, Mid SVT

88 cm, ~2 times SVT

Steinar Stapnes, LHCC June 2004 6

Cost of SVT replacement with ATLAS Pixel Modules

Cost of ATLAS Pixel Modules $1000 or $3000 Area of ATLAS Pixel Modules 18 mm 62 mm Area of SVT ~0.8 m2

2.1M$ @ 3k$/module

Steinar Stapnes, LHCC June 2004 7

Sensors

Production of sensors are now proceeding well, including new delivery (90 sensor tiles) of On Semiconductor much better than the 1st one and now fully tested. A 3rd delivery (~300 tiles) is on their way to the labs and should finally confirm production quality.

good tiles tested

0

500

1000

1500

2000

2500

Mar-02

J ul-02

Nov-02

Mar-03

J ul-03

Nov-03

Mar-04

J ul-04

Nov-04

Mar-05

J ul-05

Nov-05

Mar-06

time

tile

s

Total integral

needed for 2-layer completion

needed for 3-layer completion

Test labs:

Dortmund

New Mexico,

Prague,

Udine

Steinar Stapnes, LHCC June 2004 8

Front-end electronics

102 8” wafers already delivered (out of 246 ordered) and 54 tested. 48 wafer deliveries are scheduled each 2 months and therefore expect to have all in hand before the end of the year. Testing speed (LBNL+Bonn) very rapidly at cruise speed and agrees with schedule

good dies on wafer

0

5000

10000

15000

20000

25000

30000

35000

40000

45000

Mar-02

Jul-02

Nov-02

Mar-03

Jul-03

Nov-03

Mar-04

Jul-04

Nov-04

Mar-05

Jul-05

Nov-05

Mar-06

month

die

s

Total chips

needed for 2-layer completion

needed for 3-layer completion

Steinar Stapnes, LHCC June 2004 9

Flex hybrids

Two batches of >1000 flexes delivered and most of them populated with components.

Flex hybrids

0

500

1000

1500

2000

2500

3000

Mar-02

Jul-02

Nov-02

Mar-03

Jul-03

Nov-03

Mar-04

Jul-04

Nov-04

Mar-05

Jul-05

Nov-05

Mar-06

time

nu

mb

er

of

hy

bri

ds

hybrid produced

2-layer

3-layer

hybrid loaded

Steinar Stapnes, LHCC June 2004 10

Modules (qualified and ready to go on the experiment)

We have qualified 3 sites for the module production (Bonn, Genova, LBNL) and three more will shortly follow.

The bumping start-up has been a bit longer than hoped for due to a the need for a key machine repair (now done) in one of the 2 bump vendors.

The production of pixel modules still in the learning curve. We must work on this issue and have the curve ramp-up in the next couple of months.

Flex modules

0

250

500

750

1000

1250

1500

1750

2000

Mar-02

Jul-02

Nov-02

Mar-03

Jul-03

Nov-03

Mar-04

Jul-04

Nov-04

Mar-05

Jul-05

Nov-05

Mar-06

time

nu

mb

er

of

mo

du

les

flex done

flex trahed

2-layer

3-layer

Steinar Stapnes, LHCC June 2004 11

Thinning, dicing and bare modules

0

20

40

60

80

100

120

140

Dec-03 Jan-04 Feb-04 Mar-04 Apr-04 May-04Month

Bar

e M

od

ule

s (c

um

ula

tive

)All Reworked + bad bad FE-I3/16

Thinning and dicing under control.

Settled on 220um including photoresist, agreed with bumping companies

Repeatable and fast turn-around, even for multi-wafer batches.

No yield loss from this. Even cracked wafers thinned and diced OK. Only chips lost were those originally cracked.

Furthermore, chip electrical probing yield = 99.4% +/- 0.1%

Do not have to probe all chips => not a rate-limiting step

Bare-module rates on the right

(yields promising) :

Steinar Stapnes, LHCC June 2004 12

PIXEL schedule

Being lowered with beampipe in July 2006. Component stock is building up and preliminary yield are

promising The critical parameter is module production we have to see

how this turns on …