tertiary treatment facilities project - regional san · tertiary treatment facilities project...
TRANSCRIPT
REGIONALSAN
Tertiary Treatment Facilities ProjectContract No. 4283
Mandatory Pre-Bid MeetingWednesday, January 24, 2018
REGIONALSAN
Meeting Objective- Agenda
Introduction of the TTF Team (District, Design Consultant, CM and
PMO)
General overview of other EchoWater Projects (BNR, RAS, CAB)
Overview of TTF Project
Contract documents and contract requirements
Clarifications/changes impacting the contract documents will be issued
as addenda, email inquiries to [email protected]
Site Visit (Optional)
REGIONALSAN
Introductions Vick Kyotani – Program Manager
Graham Calciano – PMO Project Manager
William Yu – PMO Project Engineer
Scott Mueller – PMO Engineer
John Nurmi – District Operations Rep
Chris Cleveland – Carollo, Designer
Keith Corcoran – Carollo, Onsite Rep
Ron Perkins – Construction Manager
Dan Wilson – Assistant Construction Manager
REGIONALSAN
Overview of EchoWater Project
Return Activated Sludge
Tertiary Treatment Facilities (TTF)
Flow Equalization
BNR/PEPS
TTF North
Coagulant
Storage
Feed
Facility
Main Electrical Substation Expansion
Nitrifying Sidestream Treatment
Channel Air Blower Building
Disinfection Chemical Storage
REGIONALSAN
North Area Projects
FEQNSTRASBNRCAB
Channel Air Blower Building
TTF North
Coagulant
Storage
Feed
Facility
BNR/PEPS
REGIONALSAN
TTF Project Requirements Bid and Reference Documents
Addenda Overview
Bid Form
Proposed Products Form
Substitution
Bidding Requirements
Permits
Temp Stormwater Pollution
Control
Site Access and Security
SRF Requirements
Wage Requirements
OCIP Program
Work Restrictions and Milestones
Document Technology
Scheduling Requirements
Project Controls
Commissioning Requirements
REGIONALSAN
Bid and Reference Documents
Invitation link on RegionalSan website
PDF Drawings and Specifications on Public Purchase website
Click a box on the Public Purchase website to be on “Plan Holders List”
REGIONALSAN
Bid and Reference Documents
Spec Section 00 21 13 – Instructions to Bidders
Reference Documents: https://www.dropbox.com/sh/6o2m3o08tt49qp5/AAAzBiRO3EDHEg2CpxKtVjV5a?dl=0
Including Revit, Civil 3D, NWD, and more
Related Documents
Geotech and Schedule
Structural Drawings on existing secondary effluent channels
REGIONALSAN
Addenda
Addendum No. 1 (Issued
January 18, 2018)
Targeting Addendum No. 2
on February 2, 2018
Targeting Addendum No. 3
TBD
REGIONALSAN
BID Form – Stipulated Sum 00 41 13
Description Total Bid Item
ASSIGNED DRUM SCREEN $ 2,770,508
ALLOWANCE SITE CONDITIONS $ 1,000,000
ALLOWANCE UTILITY CONFLICTS $ 500,000
Subtotal $ 4,270,508
BASE BID $ ________
SHEETING, SHORING, BRACING $ ________
Total $ ________
REGIONALSAN
Proposed Products Form
Spec section 00 43 33
Standardized Equipment List, FIPS Pumps
select from only those listed
For 25 items, select listed
manufacturer or list an “or equal”
Listed Equipment, select from list
Substitutions, if approved will be
added by addendum
Must use the SUBSTITUTION
REQUEST FORM (00 43 25)
All applications must be within 35 calendar days
of Advertisement (February 8, 2018)
REGIONALSAN
Proposed Products Form
Spec section 00 43 33
Standardized Equipment List, FIPS Pumps
select from only those listed
For 25 items, select listed
manufacturer or list an “or equal”
Listed Equipment, select from list
Substitutions, if approved will be
added by addendum
Must use the SUBSTITUTION
REQUEST FORM (00 43 25)
All applications must be within 35 calendar
days of Advertisement (February 8, 2018)
REGIONALSAN
Proposed Products Form
Spec section 00 43 33
Standardized Equipment List, FIPS Pumps
select from only those listed
For 25 items, select listed
manufacturer or list an “or equal”
Listed Equipment, select from list
Substitutions, if approved will be
added by addendum
Must use the SUBSTITUTION
REQUEST FORM (00 43 25)
All applications must be within 35 calendar
days of Advertisement (February 8, 2018)
REGIONALSAN
Substitution
• SECTION 00 43 25 - SUBSTITUTION REQUEST FORM
(DURING PROCUREMENT)
• SECTION 00 43 33 - PROPOSED PRODUCTS FORM
• SECTION 00 72 00 - GENERAL CONDITIONS
• SECTION 01 33 00 - SUBMITTAL PROCEDURES
REGIONALSAN
Bidding Requirements
Forms that are part of bid:
• BID FORM (Section 00 41 00)
• BID FORM – STIPULATED SUM (SINGLE-PRIME CONTRACT) (Section 00 41 13)
• BID SECURITY FORM (Section 00 43 13)
• PROPOSED PRODUCTS FORM (Section 00 43 33)
• PROPOSED SUBCONTRACTORS FORM (Section 00 43 36)
• BIDDER’S INFORMATION (Section 00 45 12)
• NONCOLLUSION AFFIDAVIT (Section 00 45 19)
Within 5 days from the 3 apparent low bidders
• ESCROW BID DOCUMENTS (Section 00 43 53)
REGIONALSAN
Within 3 business days from the
3 apparent low bidders• Listed Subcontractor’s Current Year EMR and Cal/OSHA Form 300A (Section 00 43 36)
• BIDDER’S SAFETY PERFORMANCE (Section 00 45 14)
• BIDDER’S SUBCONTRACTOR QUALIFICATIONS (Section 00 45 15)
• IRAN CONTRACTING ACT DISCLOSURE FORM (Section 00 45 41)
• CERTIFICATION OF EXCLUSION OF OCIP INSURANCE COSTS (Section 00 73 16)
• CONTRACTOR’S AMERICAN IRON AND STEEL CERTIFICATION FORM
(Section 00 73 85)
• DBE CONTRACTOR/SUBCONTRACTOR CERTIFICATION FORM (Section 00 73 38)
• DBE SELECTED PRIME CONTRACTOR/RECIPIENT FORM (Section 00 73 38)
• DBE SUBCONTRACTOR PARTICIPATION FORM (EPA Form 6100-2) (Section 00 73 38)
• DBE SUBCONTRACTOR PERFORMANCE FORM (EPA Form 6100-3) (Section 00 73 38)
• DBE SUBCONTRACTOR UTILIZATION FORM (EPA Form 6100-4) (Section 00 73 38)
• DOCUMENTATION DEMONSTRATING PERFORMANCE OF GOOD FAITH EFFORTS
(Section 00 73 38)
REGIONALSAN
Subcontractor Pre-Qualifications from
Advertisement for Bids
Contractor is responsible for the System Integrator scope.
GC needs to be clear who is scoped for this required role (GC or Sub).
40 61 13 defines the System Integrator contractual responsibilities.
REGIONALSAN
Program-Level Permits
CEQA (plus)
Echowater Project EIR (certified September 2014)
MMRPs – Appendix B to Specs
SMAQMD
Optional Concrete Batch Plant
(contractor to obtain, staff not in OCIP)
REGIONALSAN
Temporary Stormwater Pollution
Control Section 01 57 23
Water Pollution Control Plan required
BMPs required
Weekly inspections required (minimum)
Project will not require an NOI, WDID, or
use of the State SMART system
REGIONALSAN
Site Access and Security
Site Access
Access and deliveries through
Dwight Rd.
Refer to Drawings GI001, GI002,
and GC003
Security
All staff will be badged
REGIONALSAN
SRF Requirements Spec Section 00 73 85 – Clean Water State Revolving Fund Provisions
Disadvantaged Business Enterprise (DBE) regulations
Buy American requirements - Manufacturer’s AIS Compliance Cert required
with Shop Drawing
Wage Rate Requirements
DBE Good Faith Effort (GFE)
Spec Section 00 73 38 – Disadvantaged Business Enterprise Requirements
GFE started a minimum of 30 calendar days prior to bid opening date
DBE forms must be submitted within three business days after bid opening
by three apparent low bidders
REGIONALSAN
Wage Requirements Spec Section 00 21 13 – Instructions to Bidders
Pursuant to Section 1770, and following, of the California Labor Code, the
Contractor shall pay not less than the prevailing rate of per diem wages as
determined by the Director of the California Department of Industrial
Relations.
Spec Section 00 73 43 – Wage Rate Requirements
Davis Bacon Act wage rate requirements of the Clean Water SRF Program
Spec Section 00 21 13 – Instructions to Bidders
If there is any difference between the State or Federal wage rates …, it shall
be mandatory upon the Contractor and any Subcontractors to pay the higher
of the two rates.
REGIONALSAN
Owner Controlled Insurance Program
(OCIP)
OCIP covers:
Workers’ Compensation, Employers’ Liability, General Liability and Excess
District will provide Builder’s Risk and Contractor’s Pollution Liability
All contractors are required to enroll in the OCIP (unless excluded)
OCIP does not cover:
Hazardous waste abatement contractors or companies without on-site
dedicated payroll
All contractors are required to exclude insurance costs for coverages
provided by RegionalSan
REGIONALSAN
Owner Controlled Insurance Program
(OCIP)
OCIP Safety Program Key Requirements
OCIP Safety Manual
Project Orientation, Section 1.11
Drug Screening, Section 1.11 and 5.3
Full-time dedicated safety manager required for GC, Section 1.3 and 1.5
Subcontractors required to assign designated safety representative, Section
1.4 and 1.5
Return to Work Program, Section 4.2
6 ft. fall protection, Section 12
REGIONALSAN
Work Restrictions and Milestones Work Restrictions
Refer to Spec Section 01 14 00
Concurrent District Projects at SRWTP (BNR, CAB, RAS, HEMB, SCAPS)
Addendum will clarify access on the West, East,
and North Perimeter
Contract Time
Refer to Spec Section 01 14 20
Note Liquidated Damages, among them:
Completion of all SATs related to FIPS,
SFDS, DCPF, SCLS, DCB, and EOS;
August 2021
Completion of all GMF SATs; April 2022
REGIONALSAN
• Smart P&ID Drawings
– Contains Database links to Equipment and Instrument numbers and data
• Civil 3D Drawings
– Allows coordination with other projects and buried work elements. Existing utilities potholed an included with best available data.
• Revit Building Models
– Used to coordinate locate structures and equipment to avoid conflicts
Documentation Technology (w/disclaimer)
REGIONALSAN
• 40 05 03 Common Work Results for Piping Systems –
Layout Drawings
• 40 05 07 Hangers and Supports for Process Piping –
Layout Drawings
Model Submittal Requirements
REGIONALSAN
01 33 00 Submittal Procedures
• Panel drawings including area control centers (ACC), panel
fabrication, layout and point-to-point wiring (connection diagrams).
• Elementary diagrams (control and logic).
• Electronic assembly drawings
• Terminal panels or terminal boxes
• Interconnect drawings
• Loop drawings (digital and discrete)
• Custom created concrete products specifically prepared for this
project.
• All shop drawings.
CAD Drawing Submittal Requirements
REGIONALSAN
Data ManagementSpec Sections 01 33 16 and 01 78 23
MEL Spreadsheet provided with Conformed Documents
All equipment Shop drawing submittals must identify the MEL equipment numbers included with that submittal and complete meta data equipment information forms.
MEL equipment numbers used for everything including links between shop drawings and Conformed Docs, District’s MMIS, Testing Confirmation, Lockout/Tagout, O&M Manuals and Startup.
Shop drawings without equipment ID and forms will be returned.
REGIONALSAN
Commissioning Requirements
Commissioning Plan – Appendix F
Equipment Test Plans
Site Acceptance Test (SAT) Plans (point to point checks)
Site Integration Test (SIT) Plans (clean water testing)
Reliability Acceptance Test (RAT) Plans (wastewater ops)
Roles and Responsibilities Outlined
REGIONALSAN
Commissioning Schedule
2022
January February March April May June July August September October November December
May 1,
2022
TTF
Clean Water
Testing Begins
September
30, 2022
Field
Acceptance
12/16/2022
Phase 1 SITs
Phase 2 SITs
Filter Preparation and SIT Testing
Phase 3 SIT Testing
Phase 4SIT
Complete
Installation of First
96” FE
Tie-In
(90° Elbow)
RAT
Complete
Installation of
Second 96”
FE Tie-In
All Filters
Operational
Punchlist/
Closeout
96” FE Tie-In Window
TTF
Substantial
Completion
11/1/2022
REGIONALSAN
Scheduling Requirements
Spec Section 01 32 16 – Construction Progress Schedule
The Contractor shall employ or retain the services of a full-time, onsite Senior
Project Scheduler who shall have a minimum of 10 years verifiable experience
in construction. Recommend the Scheduler be on board before NTP to be
familiar with the specifications and meet submittal deadlines.
Cost and resource loaded 180-day schedule is due within 60 days following
NTP. Full baseline is due 180 days after NTP.
Summary Schedule of Values is due 30 days after NTP.
Every activity containing labor shall be cost and resource loaded.
REGIONALSAN
Scheduling Payment Limitations
Spec Sections 01-29-76 & 01-32-16 Progress Payment
Procedures and Construction Progress Schedule
District will pay up to 0.5% of the contract amount each for the 180-Day
Schedule and Baseline Schedule Approval.
Because the value of these schedules to the District diminishes with late
schedule delivery and acceptance, the following limitations apply:
180-Day Schedule – payment amount reduced by 10% for each month beyond 95
days after NTP that schedule acceptance is received.
Baseline Schedule – payment amount reduced by 10% for each month beyond
180 days after NTP that an acceptable schedule is not received.
REGIONALSAN
Synchro Requirements
• The Contractor shall employ or retain the services of a qualified Synchro Planner who shall have demonstrated experience in developing Synchro Projects on projects of at least $100 million unless otherwise approved by the District.
• The Contractor shall utilize the Baseline Construction Schedule and Synchro Project in planning, scheduling, coordinating, and performing the work under the Contract (including all activities of Subcontractors, equipment vendors, and Suppliers).
• An updated Synchro Project linked to the current progress schedule submittal shall be submitted with the Progress Schedule update.
REGIONALSAN
Contractor Training Required
Plant Orientation
Safety (OCIP)
Environmental
PMWeb (Project Controls)
Submittals and RFIs
Access Requests
Daily Reports
Pay Requests
REGIONALSAN
Site Visit Logistics
Site tour is optional for General Contractors as part of
pre-bid meeting participation
The TTF team will take limited questions during the
site walk. If you have a question and want a
response, email [email protected]
Answers given verbally during site walk by TTF team
are not binding unless included in an addendum.