technoeconomic distribution network planning...
TRANSCRIPT
Research ArticleTechnoeconomic Distribution Network Planning Using SmartGrid Techniques with Evolutionary Self-Healing Network States
Jesus Nieto-Martin 1 Timoleon Kipouros12 Mark Savill1 Jennifer Woodruff3
and Jevgenijs Butans4
1Power and Propulsion Sciences Group Cranfield University Cranfield MK43 0AL UK2Engineering Design Centre Cambridge University Trumpington Street Cambridge CB2 1PZ UK3Western Power Distribution Innovation Pegasus Business Park Derby DE74 2TU UK4Complex System Research Centre Cranfield School of Management Cranfield MK43 0AL UK
Correspondence should be addressed to Jesus Nieto-Martin jnietomartincranfieldacuk
Received 26 January 2018 Revised 4 July 2018 Accepted 25 July 2018 Published 10 October 2018
Academic Editor Fernando Lezama
Copyright copy 2018 Jesus Nieto-Martin et al This is an open access article distributed under the Creative Commons AttributionLicense which permits unrestricted use distribution and reproduction in any medium provided the original work isproperly cited
The transition to a secure low-carbon system is raising a set of uncertainties when planning the path to a reliable decarbonisedsupply The electricity sector is committing large investments in the transmission and distribution sector upon 2050 in order toensure grid resilience The cost and limited flexibility of traditional approaches to 11 kV network reinforcement threaten toconstrain the uptake of low-carbon technologies This paper investigates the suitability and cost-effectiveness of smart gridtechniques along with traditional reinforcements for the 11 kV electricity distribution network in order to analyse expectedinvestments up to 2050 under different DECC demand scenarios The evaluation of asset planning is based on an area of studyin Milton Keynes (East Midlands United Kingdom) being composed of six 11 kV primaries To undertake this the analysisused a revolutionary new model tool for electricity distribution network planning called scenario investment model (SIM)Comprehensive comparisons of short- and long-term evolutionary investment planning strategies are presented The work helpselectricity network operators to visualise and design operational planning investments providing bottom-up decision support
1 Introduction
Distribution networks are a key enabler for a low-carbonfuture In the UK distribution network operators (DNOs)are entering a period of significant changes due to UK energytargets up to 2050 [1] By 2020 it is expected that 15 ofits total demand will be from renewable energy sourceswith a 20 reduction in greenhouse gas emissions andmoreover 80 reduction in greenhouse gas emissions by2050 The challenges presented by the transition to alow-carbon economy will directly impact the electricitydistribution network
As for an increasing connection of distributed generatorsand electrification of heat and transport new approaches todesign construct and operate networks will be required[2] A more active management of local distribution
networks interconnections storage or flexibility servicesare some of the strategic propositions that will maximisethe full potential of the digital network revolution In thatsense the UK National Infrastructure Commission the UKregulator OFGEM and the Department of Business Energyand Industrial Strategy (BEIS) are contributing to the smartflexible energy system debate [3]
In 2010 OFGEM introduced RIIO namely settingrevenue using incentives to deliver innovation and outputs[4] This new performance-based pricing framework soughtto make network operators more consumer-centric encour-aging longer-term thinking greater innovation and moreefficient delivery
The RIIO framework has been applied to both gasand electricity transmission and distribution networks Thecurrent price control (called ldquoRIIO-1rdquo) is the first generation
HindawiComplexityVolume 2018 Article ID 1543179 18 pageshttpsdoiorg10115520181543179
(2015ndash2023) of controls under this new framework As welook forward towards the discussion of defining the pricecontrol for RIIO-2 (2023ndash2031) we have to take account ofthe dramatic changes and the increased complexity that areunderway in the energy sector as well as the experienceand lessons learned from RIIO-ED1 by DNOs
In response to these challenges DNOs are evaluatingthe performance of novel intervention techniques alongwith traditional reinforcements for future network planning[5ndash7] Furthermore the deployment of these novel tech-niques is expected to improve the quality of service [8]The rising number of stakeholders in the electricity valuechain increases the complexity for asset planning Besidesthe number of decision makers the energy sector is facinga data revolution and therefore utilities of the future mustinclude in their planning capabilities the implementation ofinformation and communication technologies (ICTs)
Most network modelling tools such as IPSA PowerETAP or DINIS [9ndash11] perform power flow analysis andlook after overloads and stress points of the network Theirapproach can be considered static in the sense that theyevaluate an instantaneous view of the network at a certaingiven time However dynamic modelling like the ones imple-mented within the SIM [12] extends those static approachesmaking a series of evaluation runs adjusting future networkstates (configuration of the network) to previous fixed stateswhere the grid needed an intervention across its topology
The novel techniques under study in this researchare classified as engineering techniques automatic loadtransfer (ALT) dynamic asset rating (DAR) for cables andtransformers meshed networks and energy storage andcommercial techniques distributed generation (DG) anddemand side management (DSM) Traditional reinforce-ments (TRAD) are modelled as follows transformer replace-ment or addition cable or overhead line (OHL) replacementtransfer load to adjacent feeder and installation of new feeder[13] In addition the assets considered to be fixed duringthis assessment are the cables and transformers of thelocal 11 kV network
This study is populated with the data from the FALCON(Flexible Approaches to Low Carbon Optimised Networks)project trials using a section of Western Power Distribution(WPD) in Milton Keynes area composed of six 11 kV pri-maries In contrast with the parametric top-down represen-tation embedded in the transform model [14] the SIMaims at creating long-term strategic investment plans Thisstudy will deliver insights and scalability of these novelinterventions for asset planning of the UK distributionpower networks
There are a number of previous notable projects thataddress the uncertainty around the integration of low carbonand low-carbon technologies into the distribution grid[15ndash18] The smart distribution network operation for max-imising the integration of renewable generation project [19]performs the optimisation of network operation modes andreinforcement planning in the presence of renewable genera-tion The OFGEM smart grid forum work stream 3 whichlater became the EA technology transform model [14] isa parametric representation of the electricity distribution
network that aimed at creating long-term strategic invest-ment plans [20] It is important to note that there are certainlimitations in transform that are characteristic to all paramet-ric models The operating characteristics of devices and theirrelationship to other technologies require extensive calibra-tion to produce a qualified answer To some extent thelimitations of transform were addressed by smart grid forumwork stream 7 [21] which took four of transformrsquos paramet-ric representations of typical distribution networks andconverted them into nodal network models Other examplesinclude the energy system catapult energy path model whichtargets local energy systems [22] and the Comillas Universityreference network model (RNM) [23] which is a large-scale distribution network planning tools that can createoptimal networks
Despite the differences in their respective approaches theaforementioned models and software tools share some com-mon limitations [24] They have limited ability to captureemerging behaviour arising from the simultaneous applica-tion of multiple low-carbon and smart technologies to theelectricity distribution network Likewise it is complex toadd new technologies into the mix due to either the lack ofautomatic application of smart techniques or as in the casewith transform the parametric approach which needs infor-mation about the way different technologies compete witheach other which is difficult to obtain And finally no deci-sion support for a particular piece of distribution networkcan be provided because of either lack of automation or theparametric nature of the model The following sectionsintroduce and describe the smart techniques and the noveltechnoeconomic approach for performing dynamic networkmodelling in distribution networks and analysis in thepresence of multiple smart grid techniques It uses nodalnetwork modelling to capture the emerging behaviour andcreate localised network development plans
2 Overview of Techniques
21 Technique 1 Dynamic Asset Rating The heating effect ofcurrent passing through a metal restricts the capacity of alltransformers overhead conductors and cables on a distribu-tion network represented in Figure 1 This restriction is basedon the maximum temperature on a critical componentwithin the asset Therefore each asset will have a finitecurrent-carrying capacity rating based on assumed values ofexternal conditions which affect thermal buildup ie windspeed ambient temperature soil and humidity As the assetsin general do not have temperature monitoring the assumedvalues of the external conditions used in these calculationshave as a basis a statistically low level of the risk of the assetexceeding its critical temperature By more accurately mon-itoring metrological conditions and modelling asset ratingsin real time the capacity of the asset can be increased whilekeeping the risk of exceeding the critical temperature to aminimum Further models and algorithms will be developedas part of this second implementation to cater for theincreased information available
In addition many assets have a thermal capacity suchthat it takes time for the asset to raise its temperature
2 Complexity
(ie an increase in the current passing through the asset willnot cause a step change in the temperature of the asset) Suchassets typically have short-term current ratings which are sig-nificantly greater than their continuous current rating Theseshort-term ratings are based on specific current-carryingcurves By being able to forecast the actual current-carryingcurves the asset ratings can be further refined such that aneven greater short-term current can be supported Trans-formers and underground cables have significant thermalcapacity that can utilise this method whereas overhead linecircuits do not have significant thermal capacity
22 Technique 2 Automated Load Transfer Consumers ofelectricity on the network use energy at different rates at
different times of the day and by actively managing thenetwork connectivity the loads across connected feederscan be evenly balanced Rather than the position of normalswitching open points being determined for average networkconditions the positions can be changed automatically bythe network management system to a more optimum loca-tion based on a number of factors such as security voltagedrop capacity utilisation and load forecasts as displayedin Figure 2
23 Technique 3 Meshed Networks This technique repre-sents the process by which circuit breakers on the networkare switched in order to feed loads from multiple locationsThis approach fundamentally allows the load on each feeder
RTU
Metrologicalsensors
Alstom P341
PowerOn fusion
Communicationnetwork Asset
current ampvoltagesensors
Asset temperature(underground cables
transformers)
Asset data and metrological data
Asset temperature and sag data
Ampacity
Asset temperatureamp sag sensors
(overhead lines)
Demandforecast
DARcalculation
Figure 1 DAR trial schematic
Communication network
RTU
Substation 1
RTU
Substation 2
RTU
Substation 3
RTU
Substation 4
PowerOn fusion
Demandforecast
ALT function
Automated switch
11 kV network (which may include additional substations)
Figure 2 ALT trial schematic
3Complexity
in a meshed circuit to deviate according to the routine varia-tions in the connected load without the need for pre-existinganalysis and changes to switch states
However simply closing normal open points (NOPs)exposes more connected customers to supply interrup-tion following a network fault Therefore any plannedclosure of open points for long-term operation is routinelyaccompanied by the installation of along-the-feeder faultsensing and interruption equipment (protection relaysand circuit breakers) The installation of along-the-feederprotection devices restores and potentially reduces theprobability of customer interruption under fault conditionswith mesh operations
The aim of trialing this technique was to operate thedesignated 11 kV networks with parallel feeding arrange-ments protective device-driven autosectioning zones whileexploring potential impacts both benefits and trade-offsthat could be derived from parallel feeder configurationsand potential impact both benefits and constraints of opera-tion with autosectioning zones balanced against timeeffortand cost
24 Technique 4 Storage Energy demand in an 11 kV feedertends to occur in peaks and troughs throughout a 24-hourcycle The current supplying capacity of a feeder is limitedto the current-carrying capability of the smallest cable or
conductor in the circuit and these usually decrease incross-sectional area size further away from the primary theyare located This is acceptable when the load is spread evenlyacross a circuit but when the load occurs unevenly then theutilisation factor of the assets will also be uneven By intro-ducing energy storage devices on the network (Figure 3) theycan feed out onto the system at peak demands and rechargeduring times of low demand thus deferring the need toreplace existing assets
25 Technique 5 Distributed Generation Control A numberof industrial and commercial customers have their ownon-site generation and this number is likely to increase withthe transition to a low-carbon economy In some cases thismay be uncontrollable renewable generation (wind or solar)but the majority is in the form of either standby generatorsor controllable plants such as biomass refuse incineratorsor combined heat and power (CHP) plants If customers withcontrollable distributed generation can be incentivised toaccept instruction from a DNO to increase or decreasegeneration this can be used to reduce or increase sitedemand andor provide or remove supply from the grid asa means of rectifying network problems
26 Technique 6 Demand Side Management Similar todistributed generation DSM involves putting in place
Communication network
RTU
Substation
PowerOn fusion
Demandforecast
Energystorage
controller
Energystorage
unitLV fe
eder
sto
custo
mer
s
Substation
Energystorage
unitLV fe
eder
sto
custo
mer
s
Datacontrol connectionDistribution network connection
Volta
gec
urre
ntm
easu
rem
ents
Energystorage
unitcontroller
Operation mode-local control
Communication network
RTU
Alar
ms
indi
catio
ns
PowerOn fusion
Operation mode-remote control
Figure 3 Storage trial representation
4 Complexity
commercial agreements between the DNO and industrialand commercial customers who have the ability to controlappreciable amounts of load in a relatively short period oftime We expect demand side response to be in two formsusing the representation in Figure 4
(i) To reduce the impact of predicted peak loads
(ii) To respond to an unplanned event such as a fault
Demand side response actions can be used by the DNOto enable a change in behaviour by a customer site inresponse to an explicit signal triggering a preagreed actionThe action should be the interruption of a customerrsquosinternal electricity-consuming processes either to avoid ormore likely to defer these to a later time Its metricscapacitydelta reduction durationfrequency and OPEXare detailed in [13]
3 Methodology
To undertake the analysis of the aforementioned techniquesa revolutionary new software tool for electricity distributionnetwork planning called the scenario investment model(SIM) is used Results from evaluations using the SIM areobtained through a series of experiments that modelled thenetwork evolution under different demand scenarios pre-sented in Table 1 at short- (2015ndash2023) and long-termlookahead (2015ndash2050) to assist decision-makers in futurepower network planning
Currently electricity distribution networks have beenplanned with typically linear load growths of up to 1 perannum The expected increase in low-carbon technologieswill have a significant effect on the electricity demands onthe network which may have significant rapid sporadicincreases in the electricity demand on the 11 kV networks
[25] In addition the daily electricity load shapes may be alsoaltered significantly The networks will need to be upgradedand systems are being able to evolve and cope with newdemand profiles
There had been identified two main streams of work toconsider the use of the innovative techniques namely strate-gic and tactical planning and Design Build and OperationThe strategic and tactical planning stream will consider thenetwork planning roles while the design and operationstream will consider design build and operation roles InFigure 5 the smart grid planning framework diagram pre-sents the key elements of each stream which are displayedwith their main interactions
In order to leverage the capability of existing networkanalysis tools which are already extensively used by elec-tricity network operators the SIM is separated into twomain packages a network modelling tool which primarilyperforms the technical assessment of the application ofthe techniques and the SIM harness which manages theoverall process and perform the economic assessment andreporting functions
Demand data modelling has been based on a bottom-upapproach The methods used provide an estimate of demandfor each half-hour at each secondary substation for 18different season-day types [12]
Communication network
DGDSM
Customer site
PowerOn fusion
Demandforecast
Networkanalyser
Networkevent
DGDSMscheduler
DSMDG manager
Performancemonitor
Paymentscalculator
RTUsmartmeter
Figure 4 Commercial trials representation DGDSM
Table 1 Demand scenarios
Demand scenariosFuel
efficiencyLow-carbon
heatWall
insulation
DECC1 Medium High High
DECC2 High Medium High
DECC3 High High Low
DECC4 Low Low Medium
5Complexity
The research objective is settled to prove the suitability ofthe six novel smart interventions presented in Section 2and along with the traditional reinforcements provide anevolutionary planning insight for future power networksTo undertake this study specific experiments were selectedfor a certain power trial network under different demandscenarios and evaluation periods assessing smart tech-niques along with traditional reinforcements The approachinvolved running a set of experiments using the SIM for thesix 11 kV primaries in the FALCON trial area
31 SIM Support Algorithms The essence of the SIMapproach is its ability to take a network configuration andcorresponding load profiles in a particular year (termed asinitial network state) perform power flow and reliabilityanalysis and create derivative network states in a processknown as ldquonetwork state expansionrdquo The expansion happenseither by transitioning to the following year for networkstates without any failures or by applying intervention
techniques to resolve network issues With each new net-work state created the SIM therefore is faced with adecision as to which network state from the executionhistory to expand next The expansion can be guided bysimple depth first or breadth first algorithms which areimplemented in the SIM for verification purposes Thedepth-first algorithm always selects the newest ie themost recently created network state that is not fullyexpanded for expansion while the breadth-first algorithmalways selects the oldest network state However thosesimple heuristics are inadequate for any practical usebeyond simple test cases due to the size of the searchspace obtained by permuting all possible interventionsover a number of years To perform intelligent explorationof the search space the SIM uses a heuristic approach thatis based on an Alowast algorithm [26 27]
The baseline Alowast algorithm aims at finding the least-costpath through the search space As Alowast traverses the searchspace it builds a tree of partial paths The leaf nodes of this
Learning transfer
Key component
Systempackage conatinga set of key components
Learninganalysis of results for theimprovement of models and development ofpolicies
Smart grid planning framework
Substationmonitoring
Dynamicasset ratings
data
Automatedload transfer
dataMeshed
network data
Communication network trial
Monitoringdata collection
system
Trials data distributionmanagement system
Scenario investment model
Network modelling tool(technical Assessment)
Dynamic assetratings
techniquemodel
Automatedload transfer
techniquemodel
Batterystorage
techniquemodel
Meshednetwork
techniquemodel
Traditional reinforcement
technique model
Networktopology amp
loads
Distributedgenerationtechnique
model
Demand sidemanagement
techniquemodel
Multi-yearscheduler
Economicinvestmentassesment
Networkperformance
analysisVisualisationand reporting
SIM harness(economic assesment and
reporting)
Performance analysisamp learning
Energy modelminusmeasured data
comparison
Demand datamodelling and
scenario development
Impr
ove e
nerg
ym
odel
Design build andoperation
Strategic andtactical planning
Strategic planning supportconnections and
infrastructure planningplanning policy development
Impr
ove t
echn
ique
and
netw
ork m
odels
Batterystorage data
Distributedgeneration
trial
Demand sidemanagement
data
Design amp build learning
Impr
ove i
mpl
emen
tatio
n co
st m
odels
Figure 5 Smart grid planning framework diagram
6 Complexity
tree (failed network states) are stored in a priority queue thatis ordered using a cost function
f x = g x + h x 1
where h x is a heuristic estimate of the path cost toreach the goal and g x is the distance travelled fromthe initial node
The SIM selects network states from the priority queue toapply intervention techniques one application at a timeDeployment of a technique produces a new network statefor which a power flow analysis is performed in intact andall n minus 1 (contingency) network operation modes If allthe failures are resolved a reliability analysis comprisingcustomer minutes lost (CML) customer interruptions (CI)losses and fault level studies is performed A new networkstate is subsequently created in the next year of evaluationor if it is already the last year of evaluation the costsof interventions are calculated and the network statetogether with all its expansion history is saved to theresult store as a new result The evaluation is terminated
(Figure 6) when criteria such as the number of resultsnumber of network state evaluations or run time arereached As noted previously Alowast uses a combination ofdistance travelled so far and a heuristic estimate of thedistance to reach the endpoint
In SIM case this corresponds to g x being the totalexpenditures (TOTEX) incurred so far and h x being aheuristic estimate of TOTEX to reach the end year ofthe experiment TOTEX also referred to as the totalexpenditure comprises implementation costs (CAPEX)that occur only once when an intervention is applied tothe network operation costs (OPEX) that refer to anongoing expense of operating an asset or a scheme alongwith asset life degradation and metric costs that includeincentive payments for losses fault levels and networkreliability Referring to (2) the g x for a network statexi in year i is defined as
g xi = ci + oi + jminus1
j=1cj + oj +mj 2
Initial network state
Create new networkstate in the next year Analyse power flow
Generate and applynext intervention
technique application
Save network state tofailed network state
store
Update path costestimates
Reorder priority queue
Select top mostnetwork state from the
priority queueTermination
criteria reached
Failure present
Analyse reliabilityEnd yearreached
minus
+
minus
+
minus
+
Update solution costs
Save result
End
Figure 6 SIM evaluation flowchart
7Complexity
where ci is CAPEX in the current year oi is OPEX in thecurrent year and cj oj and mj are CAPEX OPEX andmetrics costs respectively of the ancestor network statewith no issues in year j The heuristic estimate h x ofthe cost to reach the end year is given by
h xi = cREMi +mi + n
k=i+1ck + ok +mk 3
where cREMi is the average remaining CAPEX in the cur-rent year i mi is the average metric cost in this year ckok and mk are the average CAPEX OPEX and metriccosts respectively of the descendant network state in yeark with no issues and n is the end year of evaluation Pre-seeded to a constant value c0 the average CAPEX isupdated each time a network state is expanded in a partic-ular year thus the estimated costs of fixing all issues in aparticular year progressively approach true average Settingc0 to a value greater than 0 speeds up the expansion pro-cess ie all interventions that cost less than c0 will resultin new network states that are at the top of the priorityqueue The business rationale is that DNOs are not thatinterested in optimizing interventions costing less than acertain threshold The learned averages are propagatedback to network states in the priority queue thus updatingtheir estimated effort and leading to the reordering of thequeue unlike the average CAPEX average OPEX andmetrics costs which are assumed to be 0 for years withno network states The average OPEX value for a year isobtained using
o = jToc jT jminus1 4
where j is a column vector of ones and oc is an OPEXvector of compliant network states in that year Likewisethe average metric cost is obtained according to
m = jTmc jT jminus1 5
where j is a column vector of ones and mc is a vector ofthe metric costs of compliant network states in that year
32 Conceptualising Bottom-Up Evolutionary PlanningModel-driven engineering (MDE) uses analysis constructionand development of frameworks to formulate metamodelsThose models are usually characterised using domain-specific modelling approaches [28] containing appropriatedetail abstraction of particular domain through a specificmetamodel The use of metamodels requires therefore inputsfrom domain experts which can be used to generate aggre-gated or disaggregated models Top-down and bottom-upare the conceptual definition of aggregated and disaggregatedmodels [29] These two modelling paradigms are frequentlyused to epitomise domain interactions among the operationof the energy system the econometrics related and thetechnical performance indicators [30]
From a bottom-up modelling approach [31 32] thetop-down perspective is a simplistic characterisation ofhow electrical power networks combine locational eventsand individual asset performance with high-level objectiveslike improving the CML of a certain congested area [33 34]From an engineering point of view both are still validsince outputs and strategic forecast are produced in bothHow those outcomes are calculated validated and trans-formed to strategy is presented in Figure 7 (top-down)and Figure 8 (bottom-up)
Interventiontechnique costs
Relative usage ofinterventiontechnique
Interventiontechnique installation
details
Interventiontechnique models
Validationphysical trials
Interventiontechnique operation
details
Purchase andoperation cost data
Cost model
Network data
Representativenetworks
Model network through years
Calculate intervention technique usage
Strategic forecasts
Validationsampled nodal
networks
Demand scenarios
Figure 7 Top-down conceptualisation of evolutionary power networks planning
8 Complexity
The ability of bottom-up to capture discrete locationalimpacts of technologies on the system and their disaggre-gated costs is triggering the following subsections Trade-offmethodologies are needed for planning evolutionary powersystems where observing disaggregated result strategic fore-casts are to be produced These methodologies need to beinteractive in the sense that starting from an initial stateand after a testing or learning phase the network is able toaccommodate techniques that have improved the systemproviding an exploratory set of solutions that can beexpanded or discarded as the model evolves through time
33 Experiment Characterisation To illustrate the processingof the methodology adopted we consider a typical networkscenario tree created by the tool that consists of failed (red)and compliant (green) network states in different years ofevaluation The SIM starts with a single network state inthe first year of evaluation Every year the network isevaluated for compliance in intact and n minus 1 contingencyoperation modes If failures are detected the SIM appliesintervention techniques described in Section 2 to create net-work patches that resolve the failures Each application of anintervention technique creates a new network state The toolhas to resolve all issues in the network before transitioninginto the next year DNO planners usually run power flowstudies with a single fixed load pattern In contrast the SIMchecks each network state for compliance under 18 charac-teristic day load scenarios each comprising of 48 half-hoursettlement periods All studies are performed under intactand n minus 1 contingency network operation modes The SIM
calculates patch costs using cost drivers returned by the net-work modelling tool The cost driver describes a networkintervention and consists of two parts namely the patchkey and the scaling The patch key identifies the nature ofthe modification of the network performed (removal or addi-tion of an asset and the type of the asset) Scaling data is rel-evant only to patches that can be installed in multiples of onesuch as cable upgrades and additional transformer installa-tion Scaling data structure provides a list of multipliers tothe base cost data available in the SIM database In case ofcable upgrade or replacement it enables the SIM to correctlyestimate full installation costs from per unit of length valuesFinally for postprocessing analysis the SIM also returns a listof failures by asset It was identified by DNO planners asindispensable features to help validate the system and corre-late the expansion trees to the actual assets on the networkdiagram The failure detail table contains asset ID anddescription alongside information about the number of fail-ures in intact and n minus 1 operating modes as well as absoluteand per unit thermal and voltage failure magnitude
34 Case Characterisation Two set of experiments wereperformed for this study one for comparing short-termevaluation period for RIIO-ED1 (2015ndash2023) where theRIIO-ED1 investment planning has been stylised and alonger planning period for RIIO-ED1 to RIIO-ED4 from2015 up to 2047 The other set aimed at evaluating differ-ent DECC demand scenarios Experiments evaluated twodemand scenarios DECC2 and DECC4 DECC4 representsas displayed in Table 1 the slow-progression scenario and
Purchase andoperation cost data
Cost model Nodal network model
Model network through years
Apply intervention technique to keep the network compilant
Find optimal network development options
Solutions for individual networks
Aggregate results for larger network areas
Strategic forecasts
Network data Demand scenarios
Interventiontechnique costs
Interventiontechnique installation
details
Nodal interventiontechnique models
Validation withphysical trials
Relative usage ofinterventiontechniques
Validation of powerflow and reliability
models
Interventiontechnique operation
details
Load profiles
Figure 8 Bottom-up conceptualisation of evolutionary power networks planning
9Complexity
DECC2 is with DECC3 the most challenging scenario interms of electrification and low-carbon technology integra-tion The procedure to run the experiments in the SIM isshown in Figure 6 The inputs to be sent to the SIM aredetailed in Figure 5 the selected network techniques evalu-ation period demand scenario and cost model whereas theoutputs of the SIM we obtain are techniques used failuressolved assets fixed and electrical performance indicatorsThe SIM address mentioned outputs for long-term plan-ning reinforcements to optimise investment asset planningresolving network constraints The performance criteria eval-uated were capital expenditures (CAPEX) operating expen-ditures (OPEX) utilisation of assets CMLs CIs and lossesThese parameter values are delivered by the SIM after eachsimulation In order to look for the optimal solution amongthe feasible solution pathways the SIM allows a granularitystudy of each network state
4 Results
This section presents the assessment of the six smart gridinterventions along with traditional reinforcements in thetrial area compounded by six 11 kV primaries in MiltonKeynes UK for two different evaluation periods DECC2and DECC4 Subsection 41 introduces the results for the2015ndash2023 period as short-term planning and Subsection42 presents the results for a long-term evaluation period2015ndash2047
41 Short-Term Planning This section presents the assess-ment of the six smart grid interventions along with tradi-tional reinforcements in the trial area compounded by six11 kV primaries in Milton Keynes UK for two differentdemand scenarios DECC2 and DECC4
411 DECC4 2015ndash2023 Figure 9 shows the trends ofCAPEX and OPEX Note that in the year 2015 there is aCAPEXrsquos peak due to the application of more techniquesand OPEX increments over time from 2017 to 2023
Despite the investment the increase is compensated bya benefit in the electricity distribution network with areduction in CML and CI as shown in Figure 10
The summary of the proportion of installations requiredduring this evaluation period and by capital expenditures pertechnique is presented in Table 2 for both DECC scenarios
The average yearly price of each technique implementedto fix a network state is key for future decision-makingconsiderations
Figure 11 displays the average price of each techniquedisaggregated by CAPEX and OPEX
Performance indicators are key parameters for futuredecision-making within electricity distribution planning asquantifiers due to their influence on the quality of service
Therefore as shown in Figure 12 the only smart tech-nique used in combination with traditional reinforcementsin this scenario and evaluation period that slightly influenceslightly CML and CI is meshed networks
412 DECC2 2015ndash2023 Figure 13 plots the trend ofCAPEX and OPEX over the evaluation period It is important
to highlight that there is a CAPEX peak in 2015 due to anincrease of techniques applied in this period
This CAPEX increment produces a benefit in terms ofCML and CI as observed in Figure 14
The distribution of techniques applied and capital expen-ditures per technique are shown in Table 2 The average priceof each technique implementation in this demand scenariofor this evaluation period is shown in Figure 15
As displayed in Figure 12 for DECC4rsquos simulation theonly smart grid technique that improves the quality of serviceis the meshed network In Figure 16 the contribution ofsmart techniques on CML and CI for DECC2 demandevaluation is captured
413 Comparison between DECC2 and DECC4 for 2015ndash2023 The results presented may facilitate improvementsin electricity distribution network operations and planningresulting in better-informed decision-making when upgrad-ing current electricity distribution networks The assess-ment of the six smart grid techniques discovered thatonly three of them were selected as part of optimal
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
Mill
ions
pound p
er an
num
CAPEXOPEX
442444648
55254
Figure 9 CAPEX and OPEX DECC4 2015ndash2023
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
pu
Figure 10 CML and CI DECC4 2015ndash2023
10 Complexity
solutions for DECC4 and DECC2 as described in Table 2These three techniques applied are DAR for cables andtransformers and meshed networks
Comparing the cost trends of the two assessed scenariosit is notable that in both demand scenarios DECC4 and
DECC2 the CAPEX peak occurs in 2015 (Figures 9 and13) reflecting the more difficult nature of network statesto be feasible in a demanding scenario whereas DECC2shows a higher improvement of CI and CML performanceindicators as can be seen in Figures 10 and 14
Table 2 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2023
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 15 2 14 2
DAR-transformer 7 1 5 1
ALT 0 0 0 0
Mesh 3 1 4 1
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 8 3 7 2
TRAD-cable 60 89 65 91
TRAD-transfer load 6 2 4 1
TRAD-new feeder 1 2 1 2
DAR - cable DAR -transformer
Meshednetworks
TRAD -transformer
TRAD - cable
CAPEXOPEX
0
20000
40000
60000
80000
100000
pound
Figure 11 Average cost disaggregation per technique DECC4 2015ndash2023
Figure 12 Average CML and CI improvement per technique DECC4 2015ndash2023
11Complexity
The techniques applied are the key consideration to beassessed It is necessary to analyse the number of interven-tions applied by type the effect of these techniques in theelectric grid solving failures and fixing assets Figures 11and 15 show average prices of techniques used in eachdemand scenario Smart techniques have a lower TOTEXthan traditional reinforcements These novel techniquesabove are not frequently able to fix failures and thereforeproduce feasible network states In terms of CML and CIthe only technique able to moderately contribute to theirimprovement is meshed networks as shown in Figures 12and 16 Results attribute the majority of fixes to traditionalreinforcements with a comparatively smaller number offailures being solved by smart techniques (Table 2) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention forDECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
For DECC4 the three mentioned techniques along withtraditional cable and transformer replacement are applied(Table 2) whereas for DECC2 two of them are appliedDAR for cables and meshed networks (Table 2) Comparingthe cost trends of the two assessed scenarios it is notable thatin DECC4 the CAPEX peak occurs in 2015 (Figure 7)whereas in DECC2 besides the peak in 2015 there is alsoone in 2019 (Figure 11) reflecting the more difficult natureof network states to be feasible in a demanding scenarioHowever DECC2 shows a higher improvement of electricalperformance indicators as can be seen in Figure 12
In addition traditional cable replacement DAR forcables and meshed networks are able to fix the cable whereastraditional transformer replacement and DAR for trans-formers are able to fix transformer issues (Figure 16) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention for
DECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
42 Long-Term Planning This section evaluates two experi-ments namely characterising the DECC2 and DECC4 sce-narios for 2015ndash2047 evaluation period For each demandscenario expected investments disaggregating CAPEX andOPEX are presented the evolution of electrical performanceindicators and the number of techniques applied
421 DECC4 2015ndash2047 In this experiment the mostsignificant results to analyse the suitability of each techniqueare presented
Figure 17 shows the trend of CAPEX and OPEX from2015 to 2047
There are CAPEX peaks in the year 2018 and during thebeginning of RIIO-ED2 in the years 2025 to 2026 due to theapplication of more techniques to fulfill low-carbon targets
Figure 18 indicates that upgrades on the network aredirectly related to technical performance indicators CMLand CI
In Table 3 the techniques applied and their contributionto CAPEX during the evaluation period from 2015 to 2047 bya demand scenario are shown
422 DECC2 2015ndash2047 Within this experiment the mostrelevant results to analyse the evolutionary network statesare presented
In Figure 19 the trend of CAPEX and OPEX from 2015to 2047 is shown There is a significant increase of CAPEXin the years 2024 to 2026 at the beginning of RIIO-ED2due to the necessary implementation of new techniques toreach low-carbon targets The evolution of CML and CI ispresented in Figure 20 linking larger investment years whenmajor reductions are found The contribution of each solutiontechnique is presented in Table 3
423 Comparison between DECC2 and DECC4 for 2015ndash2047 Figure 21 presents a multidimensional parallel coor-dinate representation of the feasible network statersquoscombinations that produced a 2015ndash2047 investment path-way for the evaluated area It bundles economic indicatorsie CAPEX and OPEX with technical performance indica-tors providing valuable insights on the number of traditionalreinforcements utilised to heal falling network states Resultsare also clustered by the two demand scenarios assessedduring the experiments
Solutions of DECC2 (represented in orange and green)and DECC4 (in black and blue) are clustered by the per-centage of traditional reinforcements utilised as well asthe utilisation factor
Solutions in green and in black represent those wheresmart grids were more used whereas orange and blue repre-sent the cheapest (CAPEX and OPEX) less utilised and theworst responding to the decrease of CML CI and lossesand the ones using more traditional reinforcement to fixnetwork states
Besides the fact that DECC2 smart solutions are between16 and 28 more expensive than DECC4 traditional
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
CAPEXOPEX
442444648
552
Mill
ions
pound p
er an
num
54
Figure 13 CAPEX and OPEX DECC2 2015ndash2023
12 Complexity
reinforcement solutions (green solutions versus blue solu-tions in Figure 21) DECC2 traditional solutions are in therange of costs of smart solutions of DECC4 (orange andblack solutions in Figure 21) It can also be concluded thatinvestment pathways using less smart techniques provide a
cheaper response to technical performance evaluators suchas utilisation CML CI and losses
43 Summary Experiment evaluation runs from the2015ndash2047 period present lower investment rates for the
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
PU
Figure 14 CML and CI DECC2 2015ndash2023
CAPEXOPEX
DAR -transformer
Meshednetworks
Traditional -transformer
Traditional -cable
0
20000
40000
60000
80000
100000
120000
140000
pound
Figure 15 Average cost disaggregation per technique DECC2 2015ndash2023
Figure 16 Average CML and CI improvement per technique DECC2 2015ndash2023
13Complexity
2015ndash2023 period than if the evaluation is just performedwith a 2015ndash2023 time frame This occurs as a result of thechallenging low-carbon targets up to 2047 and a myopicplanning with short-term lookahead For an evaluationperiod four times larger the CAPEX and TOTEX increasedjust 18 compared to 2015ndash2023 concluding that betweenpound52M and pound68M the evaluation area regardless of thetime horizon for the investment or the demand scenarioconsidered is required
Furthermore it can be inferred comparing Tables 2 and 3that for less smart interventions the short-term planningis used compared to the long-term horizon planningDAR-cable and DAR-transformer experienced a significantimplementation variation between the two evaluationperiods for both demand scenarios as well as CAPEX allo-cated in cable upgrades falling from 89ndash91 (2015ndash2023)to 29ndash66 in the long term 2015ndash2047 run Both technicalperformance evaluators CML and CI respond to theirrespective CAPEX curve shape Due to a more incentivisedsmart grid technique during RIIO-ED2 and ED3 the per-centages of smart techniques implemented varied notablyFor DECC4 in 2023rsquos outlook the share of techniques is
25 for smart grid interventions whereas for 2050rsquos out-look the share is increased up to 58 In the same wayfor DECC2 in 2023rsquos outlook the share of smart interven-tions is 23 whereas in 2050rsquos outlook the share increasesup to 69
Feasible solutions characterising the solution space(Figure 21) differ in the degree of investment required andtechnical performance evaluators Each of the solution pathrepresented in the multidimensional solution space inFigure 21 represents the intersection of that dimension witheach axis Parallel coordinates [35] are low complexityworking for any N-dimension In the case of Figure 21it has 8 dimensions treating every variable uniformlyEach intersection of one solution path with each axis isthe value of that solution for that axis As for axis DECC2and DECC4 it represents the feasible solutions for eachdemand scenario Making a query by the percentage oftraditional reinforcement used in that solution we have thepartition between orange and green for DECC2 and blueand black being the first solutions that use more traditionalreinforcement compared with the ones that use more smarttechniques represented in green (DECC2) and black(DECC4) From Figure 21 we can argue that solutions thatuse more smart techniques (green and blacks) are moreexpensive in terms of CAPEX and OPEX than their peers(orange and blues) when compared by a demand scenarioIt can also be stated that solutions with a higher use of tradi-tional reinforcements are the ones that decrease the mostCML CI and losses
Disaggregating results by network state of the six 11 kVprimaries and by the feeder if necessary for further granulardebugging can discern locational capacity Under bothdemand scenarios Secklow Gate was seen to be the one withgreater capacity being necessary to apply fewer techniquesover the evaluation period 2015ndash2047 On the other handNewport Pagnell exceeds the capacity as soon as 2015requiring a high number of network state evaluation to befixed that happens for each subsequent year hence the largenumber of network states is presented in Table 4
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
pound p
er an
num
Figure 17 CAPEX and OPEX DECC4 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
pu
Figure 18 CML and CI DECC4 2015ndash2047
14 Complexity
5 Conclusions
Power flow analysis using a nodal network model is essentialwhen determining the benefits of trailed smart interventions
because the interactions and implications are highly specificto a particular location and scenario
This suggests that while the bottom-up approach isonerous in terms of data handling and manipulation this isworthwhile for strategic planning and policy evaluationComparing both investment strategies investment strategyadjustments will be necessary in future regulation periodsif an over-invested network behaves as displayed in theshort-term section of this study
Traditional reinforcement will continue to be the mainmethod by which network issues are mostly resolvedfollowed by dynamic asset rating and meshed networks
The assessment of the six novel smart interventions in theFALCON 11kV primary test area in Milton Keynes hasproved the suitability of three techniques able to fix failuresimproving the quality of service and their readiness to bedeployed in the near future These techniques are DAR forcables and transformers and meshed networks Meshednetworks have been repeatedly selected as a feasible tech-nique because using it will reduce CML CI and power losses
Table 3 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2047
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 18 5 31 6
DAR-transformer 32 16 32 6
ALT 0 0 0 0
Mesh 8 3 6 3
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 25 44 9 16
TRAD-cable 15 29 20 66
TRAD-transfer load 1 1 1 1
TRAD-new feeder 1 2 1 2
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
s pound p
er an
num
Figure 19 CAPEX and OPEX DECC2 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
PU
Figure 20 CML and CI DECC2 2015ndash2047
15Complexity
improving the quality of service and the efficiency whilebeing a cost-effective solution
The initial capacity at primary substations differedsignificantly and this affected the number and complexityof interventions required by the SIM Due to the loadscenarios showing significant peak load increases DAR wasoften a temporary measure that would delay but not removethe eventual need for traditional reinforcement
Implementing DAR for cables and transformers themonitoring of assets when their peak capacity is increasedwas analysed On the other hand it was observed thattraditional reinforcements still play a key role in keepingthe electricity distribution networks free of constraintsTRAD techniques such as transformer and cable replace-ments are able to fix the majority of failures and will beessential also in the future
The comparison between traditional reinforcements andnovel smart techniques has provided a new knowledge aboutthe suitability of each technique to be applied in termsof costs electrical performance failures fixed and assetreplaced Cable replacement is the most costly techniquehowever its use is unavoidable in a number of cases Further-more the applicability of each technique regarding costsinvolved improvements on power quality and efficiency
and failures solved lead to new questions to be analysed suchas the lack of these techniques to provide flexible capacitywithin the trailed area
To sum up this study has performed a comparativeanalysis of novel smart intervention techniques providinginsights for future investments in electricity distributionplanning Further work can focus on scaling up the analysisto include a larger section of the network or a constrainedarea to evaluate national applicability of the current findings
Data Availability
Some of the data relevant to this submission is proprietaryfrom Western Power Distribution It can be accessed forresearch purposes under a signed collaboration agreement
Conflicts of Interest
The authors declare that they have no conflicts of interest
Acknowledgments
The authors would like to thank the rest of the WesternPower Distribution Innovation team particularly the other
2400
2200
2000
350
360
370
380
390
400
1400
1300
1200
1100
1000DECC 4
50
55
60
12
11
10
9
8
4400
4200
4000
3800
3600
2400
CAPEX (in kpound) OPEX (in kpound) Utilisation Traditional reinforcements () DECC 2 998796 CML 998796 CI 998796 Losses
2200
2000
1800
Figure 21 Parallel coordinate visualisation of technoeconomic performance indicators under DECC4 and DECC2
Table 4 Summary of network states and results for demand scenario DECC4 and DECC2
Primary 11 kV substation Feeders Year TechniquesResultsDECC4
NSDECC4
ResultsDECC2
NSDECC2
Fox Milne 13 2047 Smart and traditional 54 276 47 259
Newport Pagnell 9 2047 Smart and traditional 48 317 31 318
Secklow Gate 9 2047 Smart and traditional 27 29 15 16
Bletchley 19 2047 Smart and traditional 32 40 21 48
Marlborough Street 11 2047 Smart and traditional 31 52 19 37
Childs Way 17 2047 Smart and traditional 67 398 54 181
16 Complexity
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
(2015ndash2023) of controls under this new framework As welook forward towards the discussion of defining the pricecontrol for RIIO-2 (2023ndash2031) we have to take account ofthe dramatic changes and the increased complexity that areunderway in the energy sector as well as the experienceand lessons learned from RIIO-ED1 by DNOs
In response to these challenges DNOs are evaluatingthe performance of novel intervention techniques alongwith traditional reinforcements for future network planning[5ndash7] Furthermore the deployment of these novel tech-niques is expected to improve the quality of service [8]The rising number of stakeholders in the electricity valuechain increases the complexity for asset planning Besidesthe number of decision makers the energy sector is facinga data revolution and therefore utilities of the future mustinclude in their planning capabilities the implementation ofinformation and communication technologies (ICTs)
Most network modelling tools such as IPSA PowerETAP or DINIS [9ndash11] perform power flow analysis andlook after overloads and stress points of the network Theirapproach can be considered static in the sense that theyevaluate an instantaneous view of the network at a certaingiven time However dynamic modelling like the ones imple-mented within the SIM [12] extends those static approachesmaking a series of evaluation runs adjusting future networkstates (configuration of the network) to previous fixed stateswhere the grid needed an intervention across its topology
The novel techniques under study in this researchare classified as engineering techniques automatic loadtransfer (ALT) dynamic asset rating (DAR) for cables andtransformers meshed networks and energy storage andcommercial techniques distributed generation (DG) anddemand side management (DSM) Traditional reinforce-ments (TRAD) are modelled as follows transformer replace-ment or addition cable or overhead line (OHL) replacementtransfer load to adjacent feeder and installation of new feeder[13] In addition the assets considered to be fixed duringthis assessment are the cables and transformers of thelocal 11 kV network
This study is populated with the data from the FALCON(Flexible Approaches to Low Carbon Optimised Networks)project trials using a section of Western Power Distribution(WPD) in Milton Keynes area composed of six 11 kV pri-maries In contrast with the parametric top-down represen-tation embedded in the transform model [14] the SIMaims at creating long-term strategic investment plans Thisstudy will deliver insights and scalability of these novelinterventions for asset planning of the UK distributionpower networks
There are a number of previous notable projects thataddress the uncertainty around the integration of low carbonand low-carbon technologies into the distribution grid[15ndash18] The smart distribution network operation for max-imising the integration of renewable generation project [19]performs the optimisation of network operation modes andreinforcement planning in the presence of renewable genera-tion The OFGEM smart grid forum work stream 3 whichlater became the EA technology transform model [14] isa parametric representation of the electricity distribution
network that aimed at creating long-term strategic invest-ment plans [20] It is important to note that there are certainlimitations in transform that are characteristic to all paramet-ric models The operating characteristics of devices and theirrelationship to other technologies require extensive calibra-tion to produce a qualified answer To some extent thelimitations of transform were addressed by smart grid forumwork stream 7 [21] which took four of transformrsquos paramet-ric representations of typical distribution networks andconverted them into nodal network models Other examplesinclude the energy system catapult energy path model whichtargets local energy systems [22] and the Comillas Universityreference network model (RNM) [23] which is a large-scale distribution network planning tools that can createoptimal networks
Despite the differences in their respective approaches theaforementioned models and software tools share some com-mon limitations [24] They have limited ability to captureemerging behaviour arising from the simultaneous applica-tion of multiple low-carbon and smart technologies to theelectricity distribution network Likewise it is complex toadd new technologies into the mix due to either the lack ofautomatic application of smart techniques or as in the casewith transform the parametric approach which needs infor-mation about the way different technologies compete witheach other which is difficult to obtain And finally no deci-sion support for a particular piece of distribution networkcan be provided because of either lack of automation or theparametric nature of the model The following sectionsintroduce and describe the smart techniques and the noveltechnoeconomic approach for performing dynamic networkmodelling in distribution networks and analysis in thepresence of multiple smart grid techniques It uses nodalnetwork modelling to capture the emerging behaviour andcreate localised network development plans
2 Overview of Techniques
21 Technique 1 Dynamic Asset Rating The heating effect ofcurrent passing through a metal restricts the capacity of alltransformers overhead conductors and cables on a distribu-tion network represented in Figure 1 This restriction is basedon the maximum temperature on a critical componentwithin the asset Therefore each asset will have a finitecurrent-carrying capacity rating based on assumed values ofexternal conditions which affect thermal buildup ie windspeed ambient temperature soil and humidity As the assetsin general do not have temperature monitoring the assumedvalues of the external conditions used in these calculationshave as a basis a statistically low level of the risk of the assetexceeding its critical temperature By more accurately mon-itoring metrological conditions and modelling asset ratingsin real time the capacity of the asset can be increased whilekeeping the risk of exceeding the critical temperature to aminimum Further models and algorithms will be developedas part of this second implementation to cater for theincreased information available
In addition many assets have a thermal capacity suchthat it takes time for the asset to raise its temperature
2 Complexity
(ie an increase in the current passing through the asset willnot cause a step change in the temperature of the asset) Suchassets typically have short-term current ratings which are sig-nificantly greater than their continuous current rating Theseshort-term ratings are based on specific current-carryingcurves By being able to forecast the actual current-carryingcurves the asset ratings can be further refined such that aneven greater short-term current can be supported Trans-formers and underground cables have significant thermalcapacity that can utilise this method whereas overhead linecircuits do not have significant thermal capacity
22 Technique 2 Automated Load Transfer Consumers ofelectricity on the network use energy at different rates at
different times of the day and by actively managing thenetwork connectivity the loads across connected feederscan be evenly balanced Rather than the position of normalswitching open points being determined for average networkconditions the positions can be changed automatically bythe network management system to a more optimum loca-tion based on a number of factors such as security voltagedrop capacity utilisation and load forecasts as displayedin Figure 2
23 Technique 3 Meshed Networks This technique repre-sents the process by which circuit breakers on the networkare switched in order to feed loads from multiple locationsThis approach fundamentally allows the load on each feeder
RTU
Metrologicalsensors
Alstom P341
PowerOn fusion
Communicationnetwork Asset
current ampvoltagesensors
Asset temperature(underground cables
transformers)
Asset data and metrological data
Asset temperature and sag data
Ampacity
Asset temperatureamp sag sensors
(overhead lines)
Demandforecast
DARcalculation
Figure 1 DAR trial schematic
Communication network
RTU
Substation 1
RTU
Substation 2
RTU
Substation 3
RTU
Substation 4
PowerOn fusion
Demandforecast
ALT function
Automated switch
11 kV network (which may include additional substations)
Figure 2 ALT trial schematic
3Complexity
in a meshed circuit to deviate according to the routine varia-tions in the connected load without the need for pre-existinganalysis and changes to switch states
However simply closing normal open points (NOPs)exposes more connected customers to supply interrup-tion following a network fault Therefore any plannedclosure of open points for long-term operation is routinelyaccompanied by the installation of along-the-feeder faultsensing and interruption equipment (protection relaysand circuit breakers) The installation of along-the-feederprotection devices restores and potentially reduces theprobability of customer interruption under fault conditionswith mesh operations
The aim of trialing this technique was to operate thedesignated 11 kV networks with parallel feeding arrange-ments protective device-driven autosectioning zones whileexploring potential impacts both benefits and trade-offsthat could be derived from parallel feeder configurationsand potential impact both benefits and constraints of opera-tion with autosectioning zones balanced against timeeffortand cost
24 Technique 4 Storage Energy demand in an 11 kV feedertends to occur in peaks and troughs throughout a 24-hourcycle The current supplying capacity of a feeder is limitedto the current-carrying capability of the smallest cable or
conductor in the circuit and these usually decrease incross-sectional area size further away from the primary theyare located This is acceptable when the load is spread evenlyacross a circuit but when the load occurs unevenly then theutilisation factor of the assets will also be uneven By intro-ducing energy storage devices on the network (Figure 3) theycan feed out onto the system at peak demands and rechargeduring times of low demand thus deferring the need toreplace existing assets
25 Technique 5 Distributed Generation Control A numberof industrial and commercial customers have their ownon-site generation and this number is likely to increase withthe transition to a low-carbon economy In some cases thismay be uncontrollable renewable generation (wind or solar)but the majority is in the form of either standby generatorsor controllable plants such as biomass refuse incineratorsor combined heat and power (CHP) plants If customers withcontrollable distributed generation can be incentivised toaccept instruction from a DNO to increase or decreasegeneration this can be used to reduce or increase sitedemand andor provide or remove supply from the grid asa means of rectifying network problems
26 Technique 6 Demand Side Management Similar todistributed generation DSM involves putting in place
Communication network
RTU
Substation
PowerOn fusion
Demandforecast
Energystorage
controller
Energystorage
unitLV fe
eder
sto
custo
mer
s
Substation
Energystorage
unitLV fe
eder
sto
custo
mer
s
Datacontrol connectionDistribution network connection
Volta
gec
urre
ntm
easu
rem
ents
Energystorage
unitcontroller
Operation mode-local control
Communication network
RTU
Alar
ms
indi
catio
ns
PowerOn fusion
Operation mode-remote control
Figure 3 Storage trial representation
4 Complexity
commercial agreements between the DNO and industrialand commercial customers who have the ability to controlappreciable amounts of load in a relatively short period oftime We expect demand side response to be in two formsusing the representation in Figure 4
(i) To reduce the impact of predicted peak loads
(ii) To respond to an unplanned event such as a fault
Demand side response actions can be used by the DNOto enable a change in behaviour by a customer site inresponse to an explicit signal triggering a preagreed actionThe action should be the interruption of a customerrsquosinternal electricity-consuming processes either to avoid ormore likely to defer these to a later time Its metricscapacitydelta reduction durationfrequency and OPEXare detailed in [13]
3 Methodology
To undertake the analysis of the aforementioned techniquesa revolutionary new software tool for electricity distributionnetwork planning called the scenario investment model(SIM) is used Results from evaluations using the SIM areobtained through a series of experiments that modelled thenetwork evolution under different demand scenarios pre-sented in Table 1 at short- (2015ndash2023) and long-termlookahead (2015ndash2050) to assist decision-makers in futurepower network planning
Currently electricity distribution networks have beenplanned with typically linear load growths of up to 1 perannum The expected increase in low-carbon technologieswill have a significant effect on the electricity demands onthe network which may have significant rapid sporadicincreases in the electricity demand on the 11 kV networks
[25] In addition the daily electricity load shapes may be alsoaltered significantly The networks will need to be upgradedand systems are being able to evolve and cope with newdemand profiles
There had been identified two main streams of work toconsider the use of the innovative techniques namely strate-gic and tactical planning and Design Build and OperationThe strategic and tactical planning stream will consider thenetwork planning roles while the design and operationstream will consider design build and operation roles InFigure 5 the smart grid planning framework diagram pre-sents the key elements of each stream which are displayedwith their main interactions
In order to leverage the capability of existing networkanalysis tools which are already extensively used by elec-tricity network operators the SIM is separated into twomain packages a network modelling tool which primarilyperforms the technical assessment of the application ofthe techniques and the SIM harness which manages theoverall process and perform the economic assessment andreporting functions
Demand data modelling has been based on a bottom-upapproach The methods used provide an estimate of demandfor each half-hour at each secondary substation for 18different season-day types [12]
Communication network
DGDSM
Customer site
PowerOn fusion
Demandforecast
Networkanalyser
Networkevent
DGDSMscheduler
DSMDG manager
Performancemonitor
Paymentscalculator
RTUsmartmeter
Figure 4 Commercial trials representation DGDSM
Table 1 Demand scenarios
Demand scenariosFuel
efficiencyLow-carbon
heatWall
insulation
DECC1 Medium High High
DECC2 High Medium High
DECC3 High High Low
DECC4 Low Low Medium
5Complexity
The research objective is settled to prove the suitability ofthe six novel smart interventions presented in Section 2and along with the traditional reinforcements provide anevolutionary planning insight for future power networksTo undertake this study specific experiments were selectedfor a certain power trial network under different demandscenarios and evaluation periods assessing smart tech-niques along with traditional reinforcements The approachinvolved running a set of experiments using the SIM for thesix 11 kV primaries in the FALCON trial area
31 SIM Support Algorithms The essence of the SIMapproach is its ability to take a network configuration andcorresponding load profiles in a particular year (termed asinitial network state) perform power flow and reliabilityanalysis and create derivative network states in a processknown as ldquonetwork state expansionrdquo The expansion happenseither by transitioning to the following year for networkstates without any failures or by applying intervention
techniques to resolve network issues With each new net-work state created the SIM therefore is faced with adecision as to which network state from the executionhistory to expand next The expansion can be guided bysimple depth first or breadth first algorithms which areimplemented in the SIM for verification purposes Thedepth-first algorithm always selects the newest ie themost recently created network state that is not fullyexpanded for expansion while the breadth-first algorithmalways selects the oldest network state However thosesimple heuristics are inadequate for any practical usebeyond simple test cases due to the size of the searchspace obtained by permuting all possible interventionsover a number of years To perform intelligent explorationof the search space the SIM uses a heuristic approach thatis based on an Alowast algorithm [26 27]
The baseline Alowast algorithm aims at finding the least-costpath through the search space As Alowast traverses the searchspace it builds a tree of partial paths The leaf nodes of this
Learning transfer
Key component
Systempackage conatinga set of key components
Learninganalysis of results for theimprovement of models and development ofpolicies
Smart grid planning framework
Substationmonitoring
Dynamicasset ratings
data
Automatedload transfer
dataMeshed
network data
Communication network trial
Monitoringdata collection
system
Trials data distributionmanagement system
Scenario investment model
Network modelling tool(technical Assessment)
Dynamic assetratings
techniquemodel
Automatedload transfer
techniquemodel
Batterystorage
techniquemodel
Meshednetwork
techniquemodel
Traditional reinforcement
technique model
Networktopology amp
loads
Distributedgenerationtechnique
model
Demand sidemanagement
techniquemodel
Multi-yearscheduler
Economicinvestmentassesment
Networkperformance
analysisVisualisationand reporting
SIM harness(economic assesment and
reporting)
Performance analysisamp learning
Energy modelminusmeasured data
comparison
Demand datamodelling and
scenario development
Impr
ove e
nerg
ym
odel
Design build andoperation
Strategic andtactical planning
Strategic planning supportconnections and
infrastructure planningplanning policy development
Impr
ove t
echn
ique
and
netw
ork m
odels
Batterystorage data
Distributedgeneration
trial
Demand sidemanagement
data
Design amp build learning
Impr
ove i
mpl
emen
tatio
n co
st m
odels
Figure 5 Smart grid planning framework diagram
6 Complexity
tree (failed network states) are stored in a priority queue thatis ordered using a cost function
f x = g x + h x 1
where h x is a heuristic estimate of the path cost toreach the goal and g x is the distance travelled fromthe initial node
The SIM selects network states from the priority queue toapply intervention techniques one application at a timeDeployment of a technique produces a new network statefor which a power flow analysis is performed in intact andall n minus 1 (contingency) network operation modes If allthe failures are resolved a reliability analysis comprisingcustomer minutes lost (CML) customer interruptions (CI)losses and fault level studies is performed A new networkstate is subsequently created in the next year of evaluationor if it is already the last year of evaluation the costsof interventions are calculated and the network statetogether with all its expansion history is saved to theresult store as a new result The evaluation is terminated
(Figure 6) when criteria such as the number of resultsnumber of network state evaluations or run time arereached As noted previously Alowast uses a combination ofdistance travelled so far and a heuristic estimate of thedistance to reach the endpoint
In SIM case this corresponds to g x being the totalexpenditures (TOTEX) incurred so far and h x being aheuristic estimate of TOTEX to reach the end year ofthe experiment TOTEX also referred to as the totalexpenditure comprises implementation costs (CAPEX)that occur only once when an intervention is applied tothe network operation costs (OPEX) that refer to anongoing expense of operating an asset or a scheme alongwith asset life degradation and metric costs that includeincentive payments for losses fault levels and networkreliability Referring to (2) the g x for a network statexi in year i is defined as
g xi = ci + oi + jminus1
j=1cj + oj +mj 2
Initial network state
Create new networkstate in the next year Analyse power flow
Generate and applynext intervention
technique application
Save network state tofailed network state
store
Update path costestimates
Reorder priority queue
Select top mostnetwork state from the
priority queueTermination
criteria reached
Failure present
Analyse reliabilityEnd yearreached
minus
+
minus
+
minus
+
Update solution costs
Save result
End
Figure 6 SIM evaluation flowchart
7Complexity
where ci is CAPEX in the current year oi is OPEX in thecurrent year and cj oj and mj are CAPEX OPEX andmetrics costs respectively of the ancestor network statewith no issues in year j The heuristic estimate h x ofthe cost to reach the end year is given by
h xi = cREMi +mi + n
k=i+1ck + ok +mk 3
where cREMi is the average remaining CAPEX in the cur-rent year i mi is the average metric cost in this year ckok and mk are the average CAPEX OPEX and metriccosts respectively of the descendant network state in yeark with no issues and n is the end year of evaluation Pre-seeded to a constant value c0 the average CAPEX isupdated each time a network state is expanded in a partic-ular year thus the estimated costs of fixing all issues in aparticular year progressively approach true average Settingc0 to a value greater than 0 speeds up the expansion pro-cess ie all interventions that cost less than c0 will resultin new network states that are at the top of the priorityqueue The business rationale is that DNOs are not thatinterested in optimizing interventions costing less than acertain threshold The learned averages are propagatedback to network states in the priority queue thus updatingtheir estimated effort and leading to the reordering of thequeue unlike the average CAPEX average OPEX andmetrics costs which are assumed to be 0 for years withno network states The average OPEX value for a year isobtained using
o = jToc jT jminus1 4
where j is a column vector of ones and oc is an OPEXvector of compliant network states in that year Likewisethe average metric cost is obtained according to
m = jTmc jT jminus1 5
where j is a column vector of ones and mc is a vector ofthe metric costs of compliant network states in that year
32 Conceptualising Bottom-Up Evolutionary PlanningModel-driven engineering (MDE) uses analysis constructionand development of frameworks to formulate metamodelsThose models are usually characterised using domain-specific modelling approaches [28] containing appropriatedetail abstraction of particular domain through a specificmetamodel The use of metamodels requires therefore inputsfrom domain experts which can be used to generate aggre-gated or disaggregated models Top-down and bottom-upare the conceptual definition of aggregated and disaggregatedmodels [29] These two modelling paradigms are frequentlyused to epitomise domain interactions among the operationof the energy system the econometrics related and thetechnical performance indicators [30]
From a bottom-up modelling approach [31 32] thetop-down perspective is a simplistic characterisation ofhow electrical power networks combine locational eventsand individual asset performance with high-level objectiveslike improving the CML of a certain congested area [33 34]From an engineering point of view both are still validsince outputs and strategic forecast are produced in bothHow those outcomes are calculated validated and trans-formed to strategy is presented in Figure 7 (top-down)and Figure 8 (bottom-up)
Interventiontechnique costs
Relative usage ofinterventiontechnique
Interventiontechnique installation
details
Interventiontechnique models
Validationphysical trials
Interventiontechnique operation
details
Purchase andoperation cost data
Cost model
Network data
Representativenetworks
Model network through years
Calculate intervention technique usage
Strategic forecasts
Validationsampled nodal
networks
Demand scenarios
Figure 7 Top-down conceptualisation of evolutionary power networks planning
8 Complexity
The ability of bottom-up to capture discrete locationalimpacts of technologies on the system and their disaggre-gated costs is triggering the following subsections Trade-offmethodologies are needed for planning evolutionary powersystems where observing disaggregated result strategic fore-casts are to be produced These methodologies need to beinteractive in the sense that starting from an initial stateand after a testing or learning phase the network is able toaccommodate techniques that have improved the systemproviding an exploratory set of solutions that can beexpanded or discarded as the model evolves through time
33 Experiment Characterisation To illustrate the processingof the methodology adopted we consider a typical networkscenario tree created by the tool that consists of failed (red)and compliant (green) network states in different years ofevaluation The SIM starts with a single network state inthe first year of evaluation Every year the network isevaluated for compliance in intact and n minus 1 contingencyoperation modes If failures are detected the SIM appliesintervention techniques described in Section 2 to create net-work patches that resolve the failures Each application of anintervention technique creates a new network state The toolhas to resolve all issues in the network before transitioninginto the next year DNO planners usually run power flowstudies with a single fixed load pattern In contrast the SIMchecks each network state for compliance under 18 charac-teristic day load scenarios each comprising of 48 half-hoursettlement periods All studies are performed under intactand n minus 1 contingency network operation modes The SIM
calculates patch costs using cost drivers returned by the net-work modelling tool The cost driver describes a networkintervention and consists of two parts namely the patchkey and the scaling The patch key identifies the nature ofthe modification of the network performed (removal or addi-tion of an asset and the type of the asset) Scaling data is rel-evant only to patches that can be installed in multiples of onesuch as cable upgrades and additional transformer installa-tion Scaling data structure provides a list of multipliers tothe base cost data available in the SIM database In case ofcable upgrade or replacement it enables the SIM to correctlyestimate full installation costs from per unit of length valuesFinally for postprocessing analysis the SIM also returns a listof failures by asset It was identified by DNO planners asindispensable features to help validate the system and corre-late the expansion trees to the actual assets on the networkdiagram The failure detail table contains asset ID anddescription alongside information about the number of fail-ures in intact and n minus 1 operating modes as well as absoluteand per unit thermal and voltage failure magnitude
34 Case Characterisation Two set of experiments wereperformed for this study one for comparing short-termevaluation period for RIIO-ED1 (2015ndash2023) where theRIIO-ED1 investment planning has been stylised and alonger planning period for RIIO-ED1 to RIIO-ED4 from2015 up to 2047 The other set aimed at evaluating differ-ent DECC demand scenarios Experiments evaluated twodemand scenarios DECC2 and DECC4 DECC4 representsas displayed in Table 1 the slow-progression scenario and
Purchase andoperation cost data
Cost model Nodal network model
Model network through years
Apply intervention technique to keep the network compilant
Find optimal network development options
Solutions for individual networks
Aggregate results for larger network areas
Strategic forecasts
Network data Demand scenarios
Interventiontechnique costs
Interventiontechnique installation
details
Nodal interventiontechnique models
Validation withphysical trials
Relative usage ofinterventiontechniques
Validation of powerflow and reliability
models
Interventiontechnique operation
details
Load profiles
Figure 8 Bottom-up conceptualisation of evolutionary power networks planning
9Complexity
DECC2 is with DECC3 the most challenging scenario interms of electrification and low-carbon technology integra-tion The procedure to run the experiments in the SIM isshown in Figure 6 The inputs to be sent to the SIM aredetailed in Figure 5 the selected network techniques evalu-ation period demand scenario and cost model whereas theoutputs of the SIM we obtain are techniques used failuressolved assets fixed and electrical performance indicatorsThe SIM address mentioned outputs for long-term plan-ning reinforcements to optimise investment asset planningresolving network constraints The performance criteria eval-uated were capital expenditures (CAPEX) operating expen-ditures (OPEX) utilisation of assets CMLs CIs and lossesThese parameter values are delivered by the SIM after eachsimulation In order to look for the optimal solution amongthe feasible solution pathways the SIM allows a granularitystudy of each network state
4 Results
This section presents the assessment of the six smart gridinterventions along with traditional reinforcements in thetrial area compounded by six 11 kV primaries in MiltonKeynes UK for two different evaluation periods DECC2and DECC4 Subsection 41 introduces the results for the2015ndash2023 period as short-term planning and Subsection42 presents the results for a long-term evaluation period2015ndash2047
41 Short-Term Planning This section presents the assess-ment of the six smart grid interventions along with tradi-tional reinforcements in the trial area compounded by six11 kV primaries in Milton Keynes UK for two differentdemand scenarios DECC2 and DECC4
411 DECC4 2015ndash2023 Figure 9 shows the trends ofCAPEX and OPEX Note that in the year 2015 there is aCAPEXrsquos peak due to the application of more techniquesand OPEX increments over time from 2017 to 2023
Despite the investment the increase is compensated bya benefit in the electricity distribution network with areduction in CML and CI as shown in Figure 10
The summary of the proportion of installations requiredduring this evaluation period and by capital expenditures pertechnique is presented in Table 2 for both DECC scenarios
The average yearly price of each technique implementedto fix a network state is key for future decision-makingconsiderations
Figure 11 displays the average price of each techniquedisaggregated by CAPEX and OPEX
Performance indicators are key parameters for futuredecision-making within electricity distribution planning asquantifiers due to their influence on the quality of service
Therefore as shown in Figure 12 the only smart tech-nique used in combination with traditional reinforcementsin this scenario and evaluation period that slightly influenceslightly CML and CI is meshed networks
412 DECC2 2015ndash2023 Figure 13 plots the trend ofCAPEX and OPEX over the evaluation period It is important
to highlight that there is a CAPEX peak in 2015 due to anincrease of techniques applied in this period
This CAPEX increment produces a benefit in terms ofCML and CI as observed in Figure 14
The distribution of techniques applied and capital expen-ditures per technique are shown in Table 2 The average priceof each technique implementation in this demand scenariofor this evaluation period is shown in Figure 15
As displayed in Figure 12 for DECC4rsquos simulation theonly smart grid technique that improves the quality of serviceis the meshed network In Figure 16 the contribution ofsmart techniques on CML and CI for DECC2 demandevaluation is captured
413 Comparison between DECC2 and DECC4 for 2015ndash2023 The results presented may facilitate improvementsin electricity distribution network operations and planningresulting in better-informed decision-making when upgrad-ing current electricity distribution networks The assess-ment of the six smart grid techniques discovered thatonly three of them were selected as part of optimal
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
Mill
ions
pound p
er an
num
CAPEXOPEX
442444648
55254
Figure 9 CAPEX and OPEX DECC4 2015ndash2023
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
pu
Figure 10 CML and CI DECC4 2015ndash2023
10 Complexity
solutions for DECC4 and DECC2 as described in Table 2These three techniques applied are DAR for cables andtransformers and meshed networks
Comparing the cost trends of the two assessed scenariosit is notable that in both demand scenarios DECC4 and
DECC2 the CAPEX peak occurs in 2015 (Figures 9 and13) reflecting the more difficult nature of network statesto be feasible in a demanding scenario whereas DECC2shows a higher improvement of CI and CML performanceindicators as can be seen in Figures 10 and 14
Table 2 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2023
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 15 2 14 2
DAR-transformer 7 1 5 1
ALT 0 0 0 0
Mesh 3 1 4 1
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 8 3 7 2
TRAD-cable 60 89 65 91
TRAD-transfer load 6 2 4 1
TRAD-new feeder 1 2 1 2
DAR - cable DAR -transformer
Meshednetworks
TRAD -transformer
TRAD - cable
CAPEXOPEX
0
20000
40000
60000
80000
100000
pound
Figure 11 Average cost disaggregation per technique DECC4 2015ndash2023
Figure 12 Average CML and CI improvement per technique DECC4 2015ndash2023
11Complexity
The techniques applied are the key consideration to beassessed It is necessary to analyse the number of interven-tions applied by type the effect of these techniques in theelectric grid solving failures and fixing assets Figures 11and 15 show average prices of techniques used in eachdemand scenario Smart techniques have a lower TOTEXthan traditional reinforcements These novel techniquesabove are not frequently able to fix failures and thereforeproduce feasible network states In terms of CML and CIthe only technique able to moderately contribute to theirimprovement is meshed networks as shown in Figures 12and 16 Results attribute the majority of fixes to traditionalreinforcements with a comparatively smaller number offailures being solved by smart techniques (Table 2) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention forDECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
For DECC4 the three mentioned techniques along withtraditional cable and transformer replacement are applied(Table 2) whereas for DECC2 two of them are appliedDAR for cables and meshed networks (Table 2) Comparingthe cost trends of the two assessed scenarios it is notable thatin DECC4 the CAPEX peak occurs in 2015 (Figure 7)whereas in DECC2 besides the peak in 2015 there is alsoone in 2019 (Figure 11) reflecting the more difficult natureof network states to be feasible in a demanding scenarioHowever DECC2 shows a higher improvement of electricalperformance indicators as can be seen in Figure 12
In addition traditional cable replacement DAR forcables and meshed networks are able to fix the cable whereastraditional transformer replacement and DAR for trans-formers are able to fix transformer issues (Figure 16) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention for
DECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
42 Long-Term Planning This section evaluates two experi-ments namely characterising the DECC2 and DECC4 sce-narios for 2015ndash2047 evaluation period For each demandscenario expected investments disaggregating CAPEX andOPEX are presented the evolution of electrical performanceindicators and the number of techniques applied
421 DECC4 2015ndash2047 In this experiment the mostsignificant results to analyse the suitability of each techniqueare presented
Figure 17 shows the trend of CAPEX and OPEX from2015 to 2047
There are CAPEX peaks in the year 2018 and during thebeginning of RIIO-ED2 in the years 2025 to 2026 due to theapplication of more techniques to fulfill low-carbon targets
Figure 18 indicates that upgrades on the network aredirectly related to technical performance indicators CMLand CI
In Table 3 the techniques applied and their contributionto CAPEX during the evaluation period from 2015 to 2047 bya demand scenario are shown
422 DECC2 2015ndash2047 Within this experiment the mostrelevant results to analyse the evolutionary network statesare presented
In Figure 19 the trend of CAPEX and OPEX from 2015to 2047 is shown There is a significant increase of CAPEXin the years 2024 to 2026 at the beginning of RIIO-ED2due to the necessary implementation of new techniques toreach low-carbon targets The evolution of CML and CI ispresented in Figure 20 linking larger investment years whenmajor reductions are found The contribution of each solutiontechnique is presented in Table 3
423 Comparison between DECC2 and DECC4 for 2015ndash2047 Figure 21 presents a multidimensional parallel coor-dinate representation of the feasible network statersquoscombinations that produced a 2015ndash2047 investment path-way for the evaluated area It bundles economic indicatorsie CAPEX and OPEX with technical performance indica-tors providing valuable insights on the number of traditionalreinforcements utilised to heal falling network states Resultsare also clustered by the two demand scenarios assessedduring the experiments
Solutions of DECC2 (represented in orange and green)and DECC4 (in black and blue) are clustered by the per-centage of traditional reinforcements utilised as well asthe utilisation factor
Solutions in green and in black represent those wheresmart grids were more used whereas orange and blue repre-sent the cheapest (CAPEX and OPEX) less utilised and theworst responding to the decrease of CML CI and lossesand the ones using more traditional reinforcement to fixnetwork states
Besides the fact that DECC2 smart solutions are between16 and 28 more expensive than DECC4 traditional
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
CAPEXOPEX
442444648
552
Mill
ions
pound p
er an
num
54
Figure 13 CAPEX and OPEX DECC2 2015ndash2023
12 Complexity
reinforcement solutions (green solutions versus blue solu-tions in Figure 21) DECC2 traditional solutions are in therange of costs of smart solutions of DECC4 (orange andblack solutions in Figure 21) It can also be concluded thatinvestment pathways using less smart techniques provide a
cheaper response to technical performance evaluators suchas utilisation CML CI and losses
43 Summary Experiment evaluation runs from the2015ndash2047 period present lower investment rates for the
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
PU
Figure 14 CML and CI DECC2 2015ndash2023
CAPEXOPEX
DAR -transformer
Meshednetworks
Traditional -transformer
Traditional -cable
0
20000
40000
60000
80000
100000
120000
140000
pound
Figure 15 Average cost disaggregation per technique DECC2 2015ndash2023
Figure 16 Average CML and CI improvement per technique DECC2 2015ndash2023
13Complexity
2015ndash2023 period than if the evaluation is just performedwith a 2015ndash2023 time frame This occurs as a result of thechallenging low-carbon targets up to 2047 and a myopicplanning with short-term lookahead For an evaluationperiod four times larger the CAPEX and TOTEX increasedjust 18 compared to 2015ndash2023 concluding that betweenpound52M and pound68M the evaluation area regardless of thetime horizon for the investment or the demand scenarioconsidered is required
Furthermore it can be inferred comparing Tables 2 and 3that for less smart interventions the short-term planningis used compared to the long-term horizon planningDAR-cable and DAR-transformer experienced a significantimplementation variation between the two evaluationperiods for both demand scenarios as well as CAPEX allo-cated in cable upgrades falling from 89ndash91 (2015ndash2023)to 29ndash66 in the long term 2015ndash2047 run Both technicalperformance evaluators CML and CI respond to theirrespective CAPEX curve shape Due to a more incentivisedsmart grid technique during RIIO-ED2 and ED3 the per-centages of smart techniques implemented varied notablyFor DECC4 in 2023rsquos outlook the share of techniques is
25 for smart grid interventions whereas for 2050rsquos out-look the share is increased up to 58 In the same wayfor DECC2 in 2023rsquos outlook the share of smart interven-tions is 23 whereas in 2050rsquos outlook the share increasesup to 69
Feasible solutions characterising the solution space(Figure 21) differ in the degree of investment required andtechnical performance evaluators Each of the solution pathrepresented in the multidimensional solution space inFigure 21 represents the intersection of that dimension witheach axis Parallel coordinates [35] are low complexityworking for any N-dimension In the case of Figure 21it has 8 dimensions treating every variable uniformlyEach intersection of one solution path with each axis isthe value of that solution for that axis As for axis DECC2and DECC4 it represents the feasible solutions for eachdemand scenario Making a query by the percentage oftraditional reinforcement used in that solution we have thepartition between orange and green for DECC2 and blueand black being the first solutions that use more traditionalreinforcement compared with the ones that use more smarttechniques represented in green (DECC2) and black(DECC4) From Figure 21 we can argue that solutions thatuse more smart techniques (green and blacks) are moreexpensive in terms of CAPEX and OPEX than their peers(orange and blues) when compared by a demand scenarioIt can also be stated that solutions with a higher use of tradi-tional reinforcements are the ones that decrease the mostCML CI and losses
Disaggregating results by network state of the six 11 kVprimaries and by the feeder if necessary for further granulardebugging can discern locational capacity Under bothdemand scenarios Secklow Gate was seen to be the one withgreater capacity being necessary to apply fewer techniquesover the evaluation period 2015ndash2047 On the other handNewport Pagnell exceeds the capacity as soon as 2015requiring a high number of network state evaluation to befixed that happens for each subsequent year hence the largenumber of network states is presented in Table 4
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
pound p
er an
num
Figure 17 CAPEX and OPEX DECC4 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
pu
Figure 18 CML and CI DECC4 2015ndash2047
14 Complexity
5 Conclusions
Power flow analysis using a nodal network model is essentialwhen determining the benefits of trailed smart interventions
because the interactions and implications are highly specificto a particular location and scenario
This suggests that while the bottom-up approach isonerous in terms of data handling and manipulation this isworthwhile for strategic planning and policy evaluationComparing both investment strategies investment strategyadjustments will be necessary in future regulation periodsif an over-invested network behaves as displayed in theshort-term section of this study
Traditional reinforcement will continue to be the mainmethod by which network issues are mostly resolvedfollowed by dynamic asset rating and meshed networks
The assessment of the six novel smart interventions in theFALCON 11kV primary test area in Milton Keynes hasproved the suitability of three techniques able to fix failuresimproving the quality of service and their readiness to bedeployed in the near future These techniques are DAR forcables and transformers and meshed networks Meshednetworks have been repeatedly selected as a feasible tech-nique because using it will reduce CML CI and power losses
Table 3 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2047
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 18 5 31 6
DAR-transformer 32 16 32 6
ALT 0 0 0 0
Mesh 8 3 6 3
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 25 44 9 16
TRAD-cable 15 29 20 66
TRAD-transfer load 1 1 1 1
TRAD-new feeder 1 2 1 2
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
s pound p
er an
num
Figure 19 CAPEX and OPEX DECC2 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
PU
Figure 20 CML and CI DECC2 2015ndash2047
15Complexity
improving the quality of service and the efficiency whilebeing a cost-effective solution
The initial capacity at primary substations differedsignificantly and this affected the number and complexityof interventions required by the SIM Due to the loadscenarios showing significant peak load increases DAR wasoften a temporary measure that would delay but not removethe eventual need for traditional reinforcement
Implementing DAR for cables and transformers themonitoring of assets when their peak capacity is increasedwas analysed On the other hand it was observed thattraditional reinforcements still play a key role in keepingthe electricity distribution networks free of constraintsTRAD techniques such as transformer and cable replace-ments are able to fix the majority of failures and will beessential also in the future
The comparison between traditional reinforcements andnovel smart techniques has provided a new knowledge aboutthe suitability of each technique to be applied in termsof costs electrical performance failures fixed and assetreplaced Cable replacement is the most costly techniquehowever its use is unavoidable in a number of cases Further-more the applicability of each technique regarding costsinvolved improvements on power quality and efficiency
and failures solved lead to new questions to be analysed suchas the lack of these techniques to provide flexible capacitywithin the trailed area
To sum up this study has performed a comparativeanalysis of novel smart intervention techniques providinginsights for future investments in electricity distributionplanning Further work can focus on scaling up the analysisto include a larger section of the network or a constrainedarea to evaluate national applicability of the current findings
Data Availability
Some of the data relevant to this submission is proprietaryfrom Western Power Distribution It can be accessed forresearch purposes under a signed collaboration agreement
Conflicts of Interest
The authors declare that they have no conflicts of interest
Acknowledgments
The authors would like to thank the rest of the WesternPower Distribution Innovation team particularly the other
2400
2200
2000
350
360
370
380
390
400
1400
1300
1200
1100
1000DECC 4
50
55
60
12
11
10
9
8
4400
4200
4000
3800
3600
2400
CAPEX (in kpound) OPEX (in kpound) Utilisation Traditional reinforcements () DECC 2 998796 CML 998796 CI 998796 Losses
2200
2000
1800
Figure 21 Parallel coordinate visualisation of technoeconomic performance indicators under DECC4 and DECC2
Table 4 Summary of network states and results for demand scenario DECC4 and DECC2
Primary 11 kV substation Feeders Year TechniquesResultsDECC4
NSDECC4
ResultsDECC2
NSDECC2
Fox Milne 13 2047 Smart and traditional 54 276 47 259
Newport Pagnell 9 2047 Smart and traditional 48 317 31 318
Secklow Gate 9 2047 Smart and traditional 27 29 15 16
Bletchley 19 2047 Smart and traditional 32 40 21 48
Marlborough Street 11 2047 Smart and traditional 31 52 19 37
Childs Way 17 2047 Smart and traditional 67 398 54 181
16 Complexity
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
(ie an increase in the current passing through the asset willnot cause a step change in the temperature of the asset) Suchassets typically have short-term current ratings which are sig-nificantly greater than their continuous current rating Theseshort-term ratings are based on specific current-carryingcurves By being able to forecast the actual current-carryingcurves the asset ratings can be further refined such that aneven greater short-term current can be supported Trans-formers and underground cables have significant thermalcapacity that can utilise this method whereas overhead linecircuits do not have significant thermal capacity
22 Technique 2 Automated Load Transfer Consumers ofelectricity on the network use energy at different rates at
different times of the day and by actively managing thenetwork connectivity the loads across connected feederscan be evenly balanced Rather than the position of normalswitching open points being determined for average networkconditions the positions can be changed automatically bythe network management system to a more optimum loca-tion based on a number of factors such as security voltagedrop capacity utilisation and load forecasts as displayedin Figure 2
23 Technique 3 Meshed Networks This technique repre-sents the process by which circuit breakers on the networkare switched in order to feed loads from multiple locationsThis approach fundamentally allows the load on each feeder
RTU
Metrologicalsensors
Alstom P341
PowerOn fusion
Communicationnetwork Asset
current ampvoltagesensors
Asset temperature(underground cables
transformers)
Asset data and metrological data
Asset temperature and sag data
Ampacity
Asset temperatureamp sag sensors
(overhead lines)
Demandforecast
DARcalculation
Figure 1 DAR trial schematic
Communication network
RTU
Substation 1
RTU
Substation 2
RTU
Substation 3
RTU
Substation 4
PowerOn fusion
Demandforecast
ALT function
Automated switch
11 kV network (which may include additional substations)
Figure 2 ALT trial schematic
3Complexity
in a meshed circuit to deviate according to the routine varia-tions in the connected load without the need for pre-existinganalysis and changes to switch states
However simply closing normal open points (NOPs)exposes more connected customers to supply interrup-tion following a network fault Therefore any plannedclosure of open points for long-term operation is routinelyaccompanied by the installation of along-the-feeder faultsensing and interruption equipment (protection relaysand circuit breakers) The installation of along-the-feederprotection devices restores and potentially reduces theprobability of customer interruption under fault conditionswith mesh operations
The aim of trialing this technique was to operate thedesignated 11 kV networks with parallel feeding arrange-ments protective device-driven autosectioning zones whileexploring potential impacts both benefits and trade-offsthat could be derived from parallel feeder configurationsand potential impact both benefits and constraints of opera-tion with autosectioning zones balanced against timeeffortand cost
24 Technique 4 Storage Energy demand in an 11 kV feedertends to occur in peaks and troughs throughout a 24-hourcycle The current supplying capacity of a feeder is limitedto the current-carrying capability of the smallest cable or
conductor in the circuit and these usually decrease incross-sectional area size further away from the primary theyare located This is acceptable when the load is spread evenlyacross a circuit but when the load occurs unevenly then theutilisation factor of the assets will also be uneven By intro-ducing energy storage devices on the network (Figure 3) theycan feed out onto the system at peak demands and rechargeduring times of low demand thus deferring the need toreplace existing assets
25 Technique 5 Distributed Generation Control A numberof industrial and commercial customers have their ownon-site generation and this number is likely to increase withthe transition to a low-carbon economy In some cases thismay be uncontrollable renewable generation (wind or solar)but the majority is in the form of either standby generatorsor controllable plants such as biomass refuse incineratorsor combined heat and power (CHP) plants If customers withcontrollable distributed generation can be incentivised toaccept instruction from a DNO to increase or decreasegeneration this can be used to reduce or increase sitedemand andor provide or remove supply from the grid asa means of rectifying network problems
26 Technique 6 Demand Side Management Similar todistributed generation DSM involves putting in place
Communication network
RTU
Substation
PowerOn fusion
Demandforecast
Energystorage
controller
Energystorage
unitLV fe
eder
sto
custo
mer
s
Substation
Energystorage
unitLV fe
eder
sto
custo
mer
s
Datacontrol connectionDistribution network connection
Volta
gec
urre
ntm
easu
rem
ents
Energystorage
unitcontroller
Operation mode-local control
Communication network
RTU
Alar
ms
indi
catio
ns
PowerOn fusion
Operation mode-remote control
Figure 3 Storage trial representation
4 Complexity
commercial agreements between the DNO and industrialand commercial customers who have the ability to controlappreciable amounts of load in a relatively short period oftime We expect demand side response to be in two formsusing the representation in Figure 4
(i) To reduce the impact of predicted peak loads
(ii) To respond to an unplanned event such as a fault
Demand side response actions can be used by the DNOto enable a change in behaviour by a customer site inresponse to an explicit signal triggering a preagreed actionThe action should be the interruption of a customerrsquosinternal electricity-consuming processes either to avoid ormore likely to defer these to a later time Its metricscapacitydelta reduction durationfrequency and OPEXare detailed in [13]
3 Methodology
To undertake the analysis of the aforementioned techniquesa revolutionary new software tool for electricity distributionnetwork planning called the scenario investment model(SIM) is used Results from evaluations using the SIM areobtained through a series of experiments that modelled thenetwork evolution under different demand scenarios pre-sented in Table 1 at short- (2015ndash2023) and long-termlookahead (2015ndash2050) to assist decision-makers in futurepower network planning
Currently electricity distribution networks have beenplanned with typically linear load growths of up to 1 perannum The expected increase in low-carbon technologieswill have a significant effect on the electricity demands onthe network which may have significant rapid sporadicincreases in the electricity demand on the 11 kV networks
[25] In addition the daily electricity load shapes may be alsoaltered significantly The networks will need to be upgradedand systems are being able to evolve and cope with newdemand profiles
There had been identified two main streams of work toconsider the use of the innovative techniques namely strate-gic and tactical planning and Design Build and OperationThe strategic and tactical planning stream will consider thenetwork planning roles while the design and operationstream will consider design build and operation roles InFigure 5 the smart grid planning framework diagram pre-sents the key elements of each stream which are displayedwith their main interactions
In order to leverage the capability of existing networkanalysis tools which are already extensively used by elec-tricity network operators the SIM is separated into twomain packages a network modelling tool which primarilyperforms the technical assessment of the application ofthe techniques and the SIM harness which manages theoverall process and perform the economic assessment andreporting functions
Demand data modelling has been based on a bottom-upapproach The methods used provide an estimate of demandfor each half-hour at each secondary substation for 18different season-day types [12]
Communication network
DGDSM
Customer site
PowerOn fusion
Demandforecast
Networkanalyser
Networkevent
DGDSMscheduler
DSMDG manager
Performancemonitor
Paymentscalculator
RTUsmartmeter
Figure 4 Commercial trials representation DGDSM
Table 1 Demand scenarios
Demand scenariosFuel
efficiencyLow-carbon
heatWall
insulation
DECC1 Medium High High
DECC2 High Medium High
DECC3 High High Low
DECC4 Low Low Medium
5Complexity
The research objective is settled to prove the suitability ofthe six novel smart interventions presented in Section 2and along with the traditional reinforcements provide anevolutionary planning insight for future power networksTo undertake this study specific experiments were selectedfor a certain power trial network under different demandscenarios and evaluation periods assessing smart tech-niques along with traditional reinforcements The approachinvolved running a set of experiments using the SIM for thesix 11 kV primaries in the FALCON trial area
31 SIM Support Algorithms The essence of the SIMapproach is its ability to take a network configuration andcorresponding load profiles in a particular year (termed asinitial network state) perform power flow and reliabilityanalysis and create derivative network states in a processknown as ldquonetwork state expansionrdquo The expansion happenseither by transitioning to the following year for networkstates without any failures or by applying intervention
techniques to resolve network issues With each new net-work state created the SIM therefore is faced with adecision as to which network state from the executionhistory to expand next The expansion can be guided bysimple depth first or breadth first algorithms which areimplemented in the SIM for verification purposes Thedepth-first algorithm always selects the newest ie themost recently created network state that is not fullyexpanded for expansion while the breadth-first algorithmalways selects the oldest network state However thosesimple heuristics are inadequate for any practical usebeyond simple test cases due to the size of the searchspace obtained by permuting all possible interventionsover a number of years To perform intelligent explorationof the search space the SIM uses a heuristic approach thatis based on an Alowast algorithm [26 27]
The baseline Alowast algorithm aims at finding the least-costpath through the search space As Alowast traverses the searchspace it builds a tree of partial paths The leaf nodes of this
Learning transfer
Key component
Systempackage conatinga set of key components
Learninganalysis of results for theimprovement of models and development ofpolicies
Smart grid planning framework
Substationmonitoring
Dynamicasset ratings
data
Automatedload transfer
dataMeshed
network data
Communication network trial
Monitoringdata collection
system
Trials data distributionmanagement system
Scenario investment model
Network modelling tool(technical Assessment)
Dynamic assetratings
techniquemodel
Automatedload transfer
techniquemodel
Batterystorage
techniquemodel
Meshednetwork
techniquemodel
Traditional reinforcement
technique model
Networktopology amp
loads
Distributedgenerationtechnique
model
Demand sidemanagement
techniquemodel
Multi-yearscheduler
Economicinvestmentassesment
Networkperformance
analysisVisualisationand reporting
SIM harness(economic assesment and
reporting)
Performance analysisamp learning
Energy modelminusmeasured data
comparison
Demand datamodelling and
scenario development
Impr
ove e
nerg
ym
odel
Design build andoperation
Strategic andtactical planning
Strategic planning supportconnections and
infrastructure planningplanning policy development
Impr
ove t
echn
ique
and
netw
ork m
odels
Batterystorage data
Distributedgeneration
trial
Demand sidemanagement
data
Design amp build learning
Impr
ove i
mpl
emen
tatio
n co
st m
odels
Figure 5 Smart grid planning framework diagram
6 Complexity
tree (failed network states) are stored in a priority queue thatis ordered using a cost function
f x = g x + h x 1
where h x is a heuristic estimate of the path cost toreach the goal and g x is the distance travelled fromthe initial node
The SIM selects network states from the priority queue toapply intervention techniques one application at a timeDeployment of a technique produces a new network statefor which a power flow analysis is performed in intact andall n minus 1 (contingency) network operation modes If allthe failures are resolved a reliability analysis comprisingcustomer minutes lost (CML) customer interruptions (CI)losses and fault level studies is performed A new networkstate is subsequently created in the next year of evaluationor if it is already the last year of evaluation the costsof interventions are calculated and the network statetogether with all its expansion history is saved to theresult store as a new result The evaluation is terminated
(Figure 6) when criteria such as the number of resultsnumber of network state evaluations or run time arereached As noted previously Alowast uses a combination ofdistance travelled so far and a heuristic estimate of thedistance to reach the endpoint
In SIM case this corresponds to g x being the totalexpenditures (TOTEX) incurred so far and h x being aheuristic estimate of TOTEX to reach the end year ofthe experiment TOTEX also referred to as the totalexpenditure comprises implementation costs (CAPEX)that occur only once when an intervention is applied tothe network operation costs (OPEX) that refer to anongoing expense of operating an asset or a scheme alongwith asset life degradation and metric costs that includeincentive payments for losses fault levels and networkreliability Referring to (2) the g x for a network statexi in year i is defined as
g xi = ci + oi + jminus1
j=1cj + oj +mj 2
Initial network state
Create new networkstate in the next year Analyse power flow
Generate and applynext intervention
technique application
Save network state tofailed network state
store
Update path costestimates
Reorder priority queue
Select top mostnetwork state from the
priority queueTermination
criteria reached
Failure present
Analyse reliabilityEnd yearreached
minus
+
minus
+
minus
+
Update solution costs
Save result
End
Figure 6 SIM evaluation flowchart
7Complexity
where ci is CAPEX in the current year oi is OPEX in thecurrent year and cj oj and mj are CAPEX OPEX andmetrics costs respectively of the ancestor network statewith no issues in year j The heuristic estimate h x ofthe cost to reach the end year is given by
h xi = cREMi +mi + n
k=i+1ck + ok +mk 3
where cREMi is the average remaining CAPEX in the cur-rent year i mi is the average metric cost in this year ckok and mk are the average CAPEX OPEX and metriccosts respectively of the descendant network state in yeark with no issues and n is the end year of evaluation Pre-seeded to a constant value c0 the average CAPEX isupdated each time a network state is expanded in a partic-ular year thus the estimated costs of fixing all issues in aparticular year progressively approach true average Settingc0 to a value greater than 0 speeds up the expansion pro-cess ie all interventions that cost less than c0 will resultin new network states that are at the top of the priorityqueue The business rationale is that DNOs are not thatinterested in optimizing interventions costing less than acertain threshold The learned averages are propagatedback to network states in the priority queue thus updatingtheir estimated effort and leading to the reordering of thequeue unlike the average CAPEX average OPEX andmetrics costs which are assumed to be 0 for years withno network states The average OPEX value for a year isobtained using
o = jToc jT jminus1 4
where j is a column vector of ones and oc is an OPEXvector of compliant network states in that year Likewisethe average metric cost is obtained according to
m = jTmc jT jminus1 5
where j is a column vector of ones and mc is a vector ofthe metric costs of compliant network states in that year
32 Conceptualising Bottom-Up Evolutionary PlanningModel-driven engineering (MDE) uses analysis constructionand development of frameworks to formulate metamodelsThose models are usually characterised using domain-specific modelling approaches [28] containing appropriatedetail abstraction of particular domain through a specificmetamodel The use of metamodels requires therefore inputsfrom domain experts which can be used to generate aggre-gated or disaggregated models Top-down and bottom-upare the conceptual definition of aggregated and disaggregatedmodels [29] These two modelling paradigms are frequentlyused to epitomise domain interactions among the operationof the energy system the econometrics related and thetechnical performance indicators [30]
From a bottom-up modelling approach [31 32] thetop-down perspective is a simplistic characterisation ofhow electrical power networks combine locational eventsand individual asset performance with high-level objectiveslike improving the CML of a certain congested area [33 34]From an engineering point of view both are still validsince outputs and strategic forecast are produced in bothHow those outcomes are calculated validated and trans-formed to strategy is presented in Figure 7 (top-down)and Figure 8 (bottom-up)
Interventiontechnique costs
Relative usage ofinterventiontechnique
Interventiontechnique installation
details
Interventiontechnique models
Validationphysical trials
Interventiontechnique operation
details
Purchase andoperation cost data
Cost model
Network data
Representativenetworks
Model network through years
Calculate intervention technique usage
Strategic forecasts
Validationsampled nodal
networks
Demand scenarios
Figure 7 Top-down conceptualisation of evolutionary power networks planning
8 Complexity
The ability of bottom-up to capture discrete locationalimpacts of technologies on the system and their disaggre-gated costs is triggering the following subsections Trade-offmethodologies are needed for planning evolutionary powersystems where observing disaggregated result strategic fore-casts are to be produced These methodologies need to beinteractive in the sense that starting from an initial stateand after a testing or learning phase the network is able toaccommodate techniques that have improved the systemproviding an exploratory set of solutions that can beexpanded or discarded as the model evolves through time
33 Experiment Characterisation To illustrate the processingof the methodology adopted we consider a typical networkscenario tree created by the tool that consists of failed (red)and compliant (green) network states in different years ofevaluation The SIM starts with a single network state inthe first year of evaluation Every year the network isevaluated for compliance in intact and n minus 1 contingencyoperation modes If failures are detected the SIM appliesintervention techniques described in Section 2 to create net-work patches that resolve the failures Each application of anintervention technique creates a new network state The toolhas to resolve all issues in the network before transitioninginto the next year DNO planners usually run power flowstudies with a single fixed load pattern In contrast the SIMchecks each network state for compliance under 18 charac-teristic day load scenarios each comprising of 48 half-hoursettlement periods All studies are performed under intactand n minus 1 contingency network operation modes The SIM
calculates patch costs using cost drivers returned by the net-work modelling tool The cost driver describes a networkintervention and consists of two parts namely the patchkey and the scaling The patch key identifies the nature ofthe modification of the network performed (removal or addi-tion of an asset and the type of the asset) Scaling data is rel-evant only to patches that can be installed in multiples of onesuch as cable upgrades and additional transformer installa-tion Scaling data structure provides a list of multipliers tothe base cost data available in the SIM database In case ofcable upgrade or replacement it enables the SIM to correctlyestimate full installation costs from per unit of length valuesFinally for postprocessing analysis the SIM also returns a listof failures by asset It was identified by DNO planners asindispensable features to help validate the system and corre-late the expansion trees to the actual assets on the networkdiagram The failure detail table contains asset ID anddescription alongside information about the number of fail-ures in intact and n minus 1 operating modes as well as absoluteand per unit thermal and voltage failure magnitude
34 Case Characterisation Two set of experiments wereperformed for this study one for comparing short-termevaluation period for RIIO-ED1 (2015ndash2023) where theRIIO-ED1 investment planning has been stylised and alonger planning period for RIIO-ED1 to RIIO-ED4 from2015 up to 2047 The other set aimed at evaluating differ-ent DECC demand scenarios Experiments evaluated twodemand scenarios DECC2 and DECC4 DECC4 representsas displayed in Table 1 the slow-progression scenario and
Purchase andoperation cost data
Cost model Nodal network model
Model network through years
Apply intervention technique to keep the network compilant
Find optimal network development options
Solutions for individual networks
Aggregate results for larger network areas
Strategic forecasts
Network data Demand scenarios
Interventiontechnique costs
Interventiontechnique installation
details
Nodal interventiontechnique models
Validation withphysical trials
Relative usage ofinterventiontechniques
Validation of powerflow and reliability
models
Interventiontechnique operation
details
Load profiles
Figure 8 Bottom-up conceptualisation of evolutionary power networks planning
9Complexity
DECC2 is with DECC3 the most challenging scenario interms of electrification and low-carbon technology integra-tion The procedure to run the experiments in the SIM isshown in Figure 6 The inputs to be sent to the SIM aredetailed in Figure 5 the selected network techniques evalu-ation period demand scenario and cost model whereas theoutputs of the SIM we obtain are techniques used failuressolved assets fixed and electrical performance indicatorsThe SIM address mentioned outputs for long-term plan-ning reinforcements to optimise investment asset planningresolving network constraints The performance criteria eval-uated were capital expenditures (CAPEX) operating expen-ditures (OPEX) utilisation of assets CMLs CIs and lossesThese parameter values are delivered by the SIM after eachsimulation In order to look for the optimal solution amongthe feasible solution pathways the SIM allows a granularitystudy of each network state
4 Results
This section presents the assessment of the six smart gridinterventions along with traditional reinforcements in thetrial area compounded by six 11 kV primaries in MiltonKeynes UK for two different evaluation periods DECC2and DECC4 Subsection 41 introduces the results for the2015ndash2023 period as short-term planning and Subsection42 presents the results for a long-term evaluation period2015ndash2047
41 Short-Term Planning This section presents the assess-ment of the six smart grid interventions along with tradi-tional reinforcements in the trial area compounded by six11 kV primaries in Milton Keynes UK for two differentdemand scenarios DECC2 and DECC4
411 DECC4 2015ndash2023 Figure 9 shows the trends ofCAPEX and OPEX Note that in the year 2015 there is aCAPEXrsquos peak due to the application of more techniquesand OPEX increments over time from 2017 to 2023
Despite the investment the increase is compensated bya benefit in the electricity distribution network with areduction in CML and CI as shown in Figure 10
The summary of the proportion of installations requiredduring this evaluation period and by capital expenditures pertechnique is presented in Table 2 for both DECC scenarios
The average yearly price of each technique implementedto fix a network state is key for future decision-makingconsiderations
Figure 11 displays the average price of each techniquedisaggregated by CAPEX and OPEX
Performance indicators are key parameters for futuredecision-making within electricity distribution planning asquantifiers due to their influence on the quality of service
Therefore as shown in Figure 12 the only smart tech-nique used in combination with traditional reinforcementsin this scenario and evaluation period that slightly influenceslightly CML and CI is meshed networks
412 DECC2 2015ndash2023 Figure 13 plots the trend ofCAPEX and OPEX over the evaluation period It is important
to highlight that there is a CAPEX peak in 2015 due to anincrease of techniques applied in this period
This CAPEX increment produces a benefit in terms ofCML and CI as observed in Figure 14
The distribution of techniques applied and capital expen-ditures per technique are shown in Table 2 The average priceof each technique implementation in this demand scenariofor this evaluation period is shown in Figure 15
As displayed in Figure 12 for DECC4rsquos simulation theonly smart grid technique that improves the quality of serviceis the meshed network In Figure 16 the contribution ofsmart techniques on CML and CI for DECC2 demandevaluation is captured
413 Comparison between DECC2 and DECC4 for 2015ndash2023 The results presented may facilitate improvementsin electricity distribution network operations and planningresulting in better-informed decision-making when upgrad-ing current electricity distribution networks The assess-ment of the six smart grid techniques discovered thatonly three of them were selected as part of optimal
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
Mill
ions
pound p
er an
num
CAPEXOPEX
442444648
55254
Figure 9 CAPEX and OPEX DECC4 2015ndash2023
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
pu
Figure 10 CML and CI DECC4 2015ndash2023
10 Complexity
solutions for DECC4 and DECC2 as described in Table 2These three techniques applied are DAR for cables andtransformers and meshed networks
Comparing the cost trends of the two assessed scenariosit is notable that in both demand scenarios DECC4 and
DECC2 the CAPEX peak occurs in 2015 (Figures 9 and13) reflecting the more difficult nature of network statesto be feasible in a demanding scenario whereas DECC2shows a higher improvement of CI and CML performanceindicators as can be seen in Figures 10 and 14
Table 2 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2023
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 15 2 14 2
DAR-transformer 7 1 5 1
ALT 0 0 0 0
Mesh 3 1 4 1
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 8 3 7 2
TRAD-cable 60 89 65 91
TRAD-transfer load 6 2 4 1
TRAD-new feeder 1 2 1 2
DAR - cable DAR -transformer
Meshednetworks
TRAD -transformer
TRAD - cable
CAPEXOPEX
0
20000
40000
60000
80000
100000
pound
Figure 11 Average cost disaggregation per technique DECC4 2015ndash2023
Figure 12 Average CML and CI improvement per technique DECC4 2015ndash2023
11Complexity
The techniques applied are the key consideration to beassessed It is necessary to analyse the number of interven-tions applied by type the effect of these techniques in theelectric grid solving failures and fixing assets Figures 11and 15 show average prices of techniques used in eachdemand scenario Smart techniques have a lower TOTEXthan traditional reinforcements These novel techniquesabove are not frequently able to fix failures and thereforeproduce feasible network states In terms of CML and CIthe only technique able to moderately contribute to theirimprovement is meshed networks as shown in Figures 12and 16 Results attribute the majority of fixes to traditionalreinforcements with a comparatively smaller number offailures being solved by smart techniques (Table 2) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention forDECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
For DECC4 the three mentioned techniques along withtraditional cable and transformer replacement are applied(Table 2) whereas for DECC2 two of them are appliedDAR for cables and meshed networks (Table 2) Comparingthe cost trends of the two assessed scenarios it is notable thatin DECC4 the CAPEX peak occurs in 2015 (Figure 7)whereas in DECC2 besides the peak in 2015 there is alsoone in 2019 (Figure 11) reflecting the more difficult natureof network states to be feasible in a demanding scenarioHowever DECC2 shows a higher improvement of electricalperformance indicators as can be seen in Figure 12
In addition traditional cable replacement DAR forcables and meshed networks are able to fix the cable whereastraditional transformer replacement and DAR for trans-formers are able to fix transformer issues (Figure 16) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention for
DECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
42 Long-Term Planning This section evaluates two experi-ments namely characterising the DECC2 and DECC4 sce-narios for 2015ndash2047 evaluation period For each demandscenario expected investments disaggregating CAPEX andOPEX are presented the evolution of electrical performanceindicators and the number of techniques applied
421 DECC4 2015ndash2047 In this experiment the mostsignificant results to analyse the suitability of each techniqueare presented
Figure 17 shows the trend of CAPEX and OPEX from2015 to 2047
There are CAPEX peaks in the year 2018 and during thebeginning of RIIO-ED2 in the years 2025 to 2026 due to theapplication of more techniques to fulfill low-carbon targets
Figure 18 indicates that upgrades on the network aredirectly related to technical performance indicators CMLand CI
In Table 3 the techniques applied and their contributionto CAPEX during the evaluation period from 2015 to 2047 bya demand scenario are shown
422 DECC2 2015ndash2047 Within this experiment the mostrelevant results to analyse the evolutionary network statesare presented
In Figure 19 the trend of CAPEX and OPEX from 2015to 2047 is shown There is a significant increase of CAPEXin the years 2024 to 2026 at the beginning of RIIO-ED2due to the necessary implementation of new techniques toreach low-carbon targets The evolution of CML and CI ispresented in Figure 20 linking larger investment years whenmajor reductions are found The contribution of each solutiontechnique is presented in Table 3
423 Comparison between DECC2 and DECC4 for 2015ndash2047 Figure 21 presents a multidimensional parallel coor-dinate representation of the feasible network statersquoscombinations that produced a 2015ndash2047 investment path-way for the evaluated area It bundles economic indicatorsie CAPEX and OPEX with technical performance indica-tors providing valuable insights on the number of traditionalreinforcements utilised to heal falling network states Resultsare also clustered by the two demand scenarios assessedduring the experiments
Solutions of DECC2 (represented in orange and green)and DECC4 (in black and blue) are clustered by the per-centage of traditional reinforcements utilised as well asthe utilisation factor
Solutions in green and in black represent those wheresmart grids were more used whereas orange and blue repre-sent the cheapest (CAPEX and OPEX) less utilised and theworst responding to the decrease of CML CI and lossesand the ones using more traditional reinforcement to fixnetwork states
Besides the fact that DECC2 smart solutions are between16 and 28 more expensive than DECC4 traditional
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
CAPEXOPEX
442444648
552
Mill
ions
pound p
er an
num
54
Figure 13 CAPEX and OPEX DECC2 2015ndash2023
12 Complexity
reinforcement solutions (green solutions versus blue solu-tions in Figure 21) DECC2 traditional solutions are in therange of costs of smart solutions of DECC4 (orange andblack solutions in Figure 21) It can also be concluded thatinvestment pathways using less smart techniques provide a
cheaper response to technical performance evaluators suchas utilisation CML CI and losses
43 Summary Experiment evaluation runs from the2015ndash2047 period present lower investment rates for the
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
PU
Figure 14 CML and CI DECC2 2015ndash2023
CAPEXOPEX
DAR -transformer
Meshednetworks
Traditional -transformer
Traditional -cable
0
20000
40000
60000
80000
100000
120000
140000
pound
Figure 15 Average cost disaggregation per technique DECC2 2015ndash2023
Figure 16 Average CML and CI improvement per technique DECC2 2015ndash2023
13Complexity
2015ndash2023 period than if the evaluation is just performedwith a 2015ndash2023 time frame This occurs as a result of thechallenging low-carbon targets up to 2047 and a myopicplanning with short-term lookahead For an evaluationperiod four times larger the CAPEX and TOTEX increasedjust 18 compared to 2015ndash2023 concluding that betweenpound52M and pound68M the evaluation area regardless of thetime horizon for the investment or the demand scenarioconsidered is required
Furthermore it can be inferred comparing Tables 2 and 3that for less smart interventions the short-term planningis used compared to the long-term horizon planningDAR-cable and DAR-transformer experienced a significantimplementation variation between the two evaluationperiods for both demand scenarios as well as CAPEX allo-cated in cable upgrades falling from 89ndash91 (2015ndash2023)to 29ndash66 in the long term 2015ndash2047 run Both technicalperformance evaluators CML and CI respond to theirrespective CAPEX curve shape Due to a more incentivisedsmart grid technique during RIIO-ED2 and ED3 the per-centages of smart techniques implemented varied notablyFor DECC4 in 2023rsquos outlook the share of techniques is
25 for smart grid interventions whereas for 2050rsquos out-look the share is increased up to 58 In the same wayfor DECC2 in 2023rsquos outlook the share of smart interven-tions is 23 whereas in 2050rsquos outlook the share increasesup to 69
Feasible solutions characterising the solution space(Figure 21) differ in the degree of investment required andtechnical performance evaluators Each of the solution pathrepresented in the multidimensional solution space inFigure 21 represents the intersection of that dimension witheach axis Parallel coordinates [35] are low complexityworking for any N-dimension In the case of Figure 21it has 8 dimensions treating every variable uniformlyEach intersection of one solution path with each axis isthe value of that solution for that axis As for axis DECC2and DECC4 it represents the feasible solutions for eachdemand scenario Making a query by the percentage oftraditional reinforcement used in that solution we have thepartition between orange and green for DECC2 and blueand black being the first solutions that use more traditionalreinforcement compared with the ones that use more smarttechniques represented in green (DECC2) and black(DECC4) From Figure 21 we can argue that solutions thatuse more smart techniques (green and blacks) are moreexpensive in terms of CAPEX and OPEX than their peers(orange and blues) when compared by a demand scenarioIt can also be stated that solutions with a higher use of tradi-tional reinforcements are the ones that decrease the mostCML CI and losses
Disaggregating results by network state of the six 11 kVprimaries and by the feeder if necessary for further granulardebugging can discern locational capacity Under bothdemand scenarios Secklow Gate was seen to be the one withgreater capacity being necessary to apply fewer techniquesover the evaluation period 2015ndash2047 On the other handNewport Pagnell exceeds the capacity as soon as 2015requiring a high number of network state evaluation to befixed that happens for each subsequent year hence the largenumber of network states is presented in Table 4
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
pound p
er an
num
Figure 17 CAPEX and OPEX DECC4 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
pu
Figure 18 CML and CI DECC4 2015ndash2047
14 Complexity
5 Conclusions
Power flow analysis using a nodal network model is essentialwhen determining the benefits of trailed smart interventions
because the interactions and implications are highly specificto a particular location and scenario
This suggests that while the bottom-up approach isonerous in terms of data handling and manipulation this isworthwhile for strategic planning and policy evaluationComparing both investment strategies investment strategyadjustments will be necessary in future regulation periodsif an over-invested network behaves as displayed in theshort-term section of this study
Traditional reinforcement will continue to be the mainmethod by which network issues are mostly resolvedfollowed by dynamic asset rating and meshed networks
The assessment of the six novel smart interventions in theFALCON 11kV primary test area in Milton Keynes hasproved the suitability of three techniques able to fix failuresimproving the quality of service and their readiness to bedeployed in the near future These techniques are DAR forcables and transformers and meshed networks Meshednetworks have been repeatedly selected as a feasible tech-nique because using it will reduce CML CI and power losses
Table 3 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2047
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 18 5 31 6
DAR-transformer 32 16 32 6
ALT 0 0 0 0
Mesh 8 3 6 3
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 25 44 9 16
TRAD-cable 15 29 20 66
TRAD-transfer load 1 1 1 1
TRAD-new feeder 1 2 1 2
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
s pound p
er an
num
Figure 19 CAPEX and OPEX DECC2 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
PU
Figure 20 CML and CI DECC2 2015ndash2047
15Complexity
improving the quality of service and the efficiency whilebeing a cost-effective solution
The initial capacity at primary substations differedsignificantly and this affected the number and complexityof interventions required by the SIM Due to the loadscenarios showing significant peak load increases DAR wasoften a temporary measure that would delay but not removethe eventual need for traditional reinforcement
Implementing DAR for cables and transformers themonitoring of assets when their peak capacity is increasedwas analysed On the other hand it was observed thattraditional reinforcements still play a key role in keepingthe electricity distribution networks free of constraintsTRAD techniques such as transformer and cable replace-ments are able to fix the majority of failures and will beessential also in the future
The comparison between traditional reinforcements andnovel smart techniques has provided a new knowledge aboutthe suitability of each technique to be applied in termsof costs electrical performance failures fixed and assetreplaced Cable replacement is the most costly techniquehowever its use is unavoidable in a number of cases Further-more the applicability of each technique regarding costsinvolved improvements on power quality and efficiency
and failures solved lead to new questions to be analysed suchas the lack of these techniques to provide flexible capacitywithin the trailed area
To sum up this study has performed a comparativeanalysis of novel smart intervention techniques providinginsights for future investments in electricity distributionplanning Further work can focus on scaling up the analysisto include a larger section of the network or a constrainedarea to evaluate national applicability of the current findings
Data Availability
Some of the data relevant to this submission is proprietaryfrom Western Power Distribution It can be accessed forresearch purposes under a signed collaboration agreement
Conflicts of Interest
The authors declare that they have no conflicts of interest
Acknowledgments
The authors would like to thank the rest of the WesternPower Distribution Innovation team particularly the other
2400
2200
2000
350
360
370
380
390
400
1400
1300
1200
1100
1000DECC 4
50
55
60
12
11
10
9
8
4400
4200
4000
3800
3600
2400
CAPEX (in kpound) OPEX (in kpound) Utilisation Traditional reinforcements () DECC 2 998796 CML 998796 CI 998796 Losses
2200
2000
1800
Figure 21 Parallel coordinate visualisation of technoeconomic performance indicators under DECC4 and DECC2
Table 4 Summary of network states and results for demand scenario DECC4 and DECC2
Primary 11 kV substation Feeders Year TechniquesResultsDECC4
NSDECC4
ResultsDECC2
NSDECC2
Fox Milne 13 2047 Smart and traditional 54 276 47 259
Newport Pagnell 9 2047 Smart and traditional 48 317 31 318
Secklow Gate 9 2047 Smart and traditional 27 29 15 16
Bletchley 19 2047 Smart and traditional 32 40 21 48
Marlborough Street 11 2047 Smart and traditional 31 52 19 37
Childs Way 17 2047 Smart and traditional 67 398 54 181
16 Complexity
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
in a meshed circuit to deviate according to the routine varia-tions in the connected load without the need for pre-existinganalysis and changes to switch states
However simply closing normal open points (NOPs)exposes more connected customers to supply interrup-tion following a network fault Therefore any plannedclosure of open points for long-term operation is routinelyaccompanied by the installation of along-the-feeder faultsensing and interruption equipment (protection relaysand circuit breakers) The installation of along-the-feederprotection devices restores and potentially reduces theprobability of customer interruption under fault conditionswith mesh operations
The aim of trialing this technique was to operate thedesignated 11 kV networks with parallel feeding arrange-ments protective device-driven autosectioning zones whileexploring potential impacts both benefits and trade-offsthat could be derived from parallel feeder configurationsand potential impact both benefits and constraints of opera-tion with autosectioning zones balanced against timeeffortand cost
24 Technique 4 Storage Energy demand in an 11 kV feedertends to occur in peaks and troughs throughout a 24-hourcycle The current supplying capacity of a feeder is limitedto the current-carrying capability of the smallest cable or
conductor in the circuit and these usually decrease incross-sectional area size further away from the primary theyare located This is acceptable when the load is spread evenlyacross a circuit but when the load occurs unevenly then theutilisation factor of the assets will also be uneven By intro-ducing energy storage devices on the network (Figure 3) theycan feed out onto the system at peak demands and rechargeduring times of low demand thus deferring the need toreplace existing assets
25 Technique 5 Distributed Generation Control A numberof industrial and commercial customers have their ownon-site generation and this number is likely to increase withthe transition to a low-carbon economy In some cases thismay be uncontrollable renewable generation (wind or solar)but the majority is in the form of either standby generatorsor controllable plants such as biomass refuse incineratorsor combined heat and power (CHP) plants If customers withcontrollable distributed generation can be incentivised toaccept instruction from a DNO to increase or decreasegeneration this can be used to reduce or increase sitedemand andor provide or remove supply from the grid asa means of rectifying network problems
26 Technique 6 Demand Side Management Similar todistributed generation DSM involves putting in place
Communication network
RTU
Substation
PowerOn fusion
Demandforecast
Energystorage
controller
Energystorage
unitLV fe
eder
sto
custo
mer
s
Substation
Energystorage
unitLV fe
eder
sto
custo
mer
s
Datacontrol connectionDistribution network connection
Volta
gec
urre
ntm
easu
rem
ents
Energystorage
unitcontroller
Operation mode-local control
Communication network
RTU
Alar
ms
indi
catio
ns
PowerOn fusion
Operation mode-remote control
Figure 3 Storage trial representation
4 Complexity
commercial agreements between the DNO and industrialand commercial customers who have the ability to controlappreciable amounts of load in a relatively short period oftime We expect demand side response to be in two formsusing the representation in Figure 4
(i) To reduce the impact of predicted peak loads
(ii) To respond to an unplanned event such as a fault
Demand side response actions can be used by the DNOto enable a change in behaviour by a customer site inresponse to an explicit signal triggering a preagreed actionThe action should be the interruption of a customerrsquosinternal electricity-consuming processes either to avoid ormore likely to defer these to a later time Its metricscapacitydelta reduction durationfrequency and OPEXare detailed in [13]
3 Methodology
To undertake the analysis of the aforementioned techniquesa revolutionary new software tool for electricity distributionnetwork planning called the scenario investment model(SIM) is used Results from evaluations using the SIM areobtained through a series of experiments that modelled thenetwork evolution under different demand scenarios pre-sented in Table 1 at short- (2015ndash2023) and long-termlookahead (2015ndash2050) to assist decision-makers in futurepower network planning
Currently electricity distribution networks have beenplanned with typically linear load growths of up to 1 perannum The expected increase in low-carbon technologieswill have a significant effect on the electricity demands onthe network which may have significant rapid sporadicincreases in the electricity demand on the 11 kV networks
[25] In addition the daily electricity load shapes may be alsoaltered significantly The networks will need to be upgradedand systems are being able to evolve and cope with newdemand profiles
There had been identified two main streams of work toconsider the use of the innovative techniques namely strate-gic and tactical planning and Design Build and OperationThe strategic and tactical planning stream will consider thenetwork planning roles while the design and operationstream will consider design build and operation roles InFigure 5 the smart grid planning framework diagram pre-sents the key elements of each stream which are displayedwith their main interactions
In order to leverage the capability of existing networkanalysis tools which are already extensively used by elec-tricity network operators the SIM is separated into twomain packages a network modelling tool which primarilyperforms the technical assessment of the application ofthe techniques and the SIM harness which manages theoverall process and perform the economic assessment andreporting functions
Demand data modelling has been based on a bottom-upapproach The methods used provide an estimate of demandfor each half-hour at each secondary substation for 18different season-day types [12]
Communication network
DGDSM
Customer site
PowerOn fusion
Demandforecast
Networkanalyser
Networkevent
DGDSMscheduler
DSMDG manager
Performancemonitor
Paymentscalculator
RTUsmartmeter
Figure 4 Commercial trials representation DGDSM
Table 1 Demand scenarios
Demand scenariosFuel
efficiencyLow-carbon
heatWall
insulation
DECC1 Medium High High
DECC2 High Medium High
DECC3 High High Low
DECC4 Low Low Medium
5Complexity
The research objective is settled to prove the suitability ofthe six novel smart interventions presented in Section 2and along with the traditional reinforcements provide anevolutionary planning insight for future power networksTo undertake this study specific experiments were selectedfor a certain power trial network under different demandscenarios and evaluation periods assessing smart tech-niques along with traditional reinforcements The approachinvolved running a set of experiments using the SIM for thesix 11 kV primaries in the FALCON trial area
31 SIM Support Algorithms The essence of the SIMapproach is its ability to take a network configuration andcorresponding load profiles in a particular year (termed asinitial network state) perform power flow and reliabilityanalysis and create derivative network states in a processknown as ldquonetwork state expansionrdquo The expansion happenseither by transitioning to the following year for networkstates without any failures or by applying intervention
techniques to resolve network issues With each new net-work state created the SIM therefore is faced with adecision as to which network state from the executionhistory to expand next The expansion can be guided bysimple depth first or breadth first algorithms which areimplemented in the SIM for verification purposes Thedepth-first algorithm always selects the newest ie themost recently created network state that is not fullyexpanded for expansion while the breadth-first algorithmalways selects the oldest network state However thosesimple heuristics are inadequate for any practical usebeyond simple test cases due to the size of the searchspace obtained by permuting all possible interventionsover a number of years To perform intelligent explorationof the search space the SIM uses a heuristic approach thatis based on an Alowast algorithm [26 27]
The baseline Alowast algorithm aims at finding the least-costpath through the search space As Alowast traverses the searchspace it builds a tree of partial paths The leaf nodes of this
Learning transfer
Key component
Systempackage conatinga set of key components
Learninganalysis of results for theimprovement of models and development ofpolicies
Smart grid planning framework
Substationmonitoring
Dynamicasset ratings
data
Automatedload transfer
dataMeshed
network data
Communication network trial
Monitoringdata collection
system
Trials data distributionmanagement system
Scenario investment model
Network modelling tool(technical Assessment)
Dynamic assetratings
techniquemodel
Automatedload transfer
techniquemodel
Batterystorage
techniquemodel
Meshednetwork
techniquemodel
Traditional reinforcement
technique model
Networktopology amp
loads
Distributedgenerationtechnique
model
Demand sidemanagement
techniquemodel
Multi-yearscheduler
Economicinvestmentassesment
Networkperformance
analysisVisualisationand reporting
SIM harness(economic assesment and
reporting)
Performance analysisamp learning
Energy modelminusmeasured data
comparison
Demand datamodelling and
scenario development
Impr
ove e
nerg
ym
odel
Design build andoperation
Strategic andtactical planning
Strategic planning supportconnections and
infrastructure planningplanning policy development
Impr
ove t
echn
ique
and
netw
ork m
odels
Batterystorage data
Distributedgeneration
trial
Demand sidemanagement
data
Design amp build learning
Impr
ove i
mpl
emen
tatio
n co
st m
odels
Figure 5 Smart grid planning framework diagram
6 Complexity
tree (failed network states) are stored in a priority queue thatis ordered using a cost function
f x = g x + h x 1
where h x is a heuristic estimate of the path cost toreach the goal and g x is the distance travelled fromthe initial node
The SIM selects network states from the priority queue toapply intervention techniques one application at a timeDeployment of a technique produces a new network statefor which a power flow analysis is performed in intact andall n minus 1 (contingency) network operation modes If allthe failures are resolved a reliability analysis comprisingcustomer minutes lost (CML) customer interruptions (CI)losses and fault level studies is performed A new networkstate is subsequently created in the next year of evaluationor if it is already the last year of evaluation the costsof interventions are calculated and the network statetogether with all its expansion history is saved to theresult store as a new result The evaluation is terminated
(Figure 6) when criteria such as the number of resultsnumber of network state evaluations or run time arereached As noted previously Alowast uses a combination ofdistance travelled so far and a heuristic estimate of thedistance to reach the endpoint
In SIM case this corresponds to g x being the totalexpenditures (TOTEX) incurred so far and h x being aheuristic estimate of TOTEX to reach the end year ofthe experiment TOTEX also referred to as the totalexpenditure comprises implementation costs (CAPEX)that occur only once when an intervention is applied tothe network operation costs (OPEX) that refer to anongoing expense of operating an asset or a scheme alongwith asset life degradation and metric costs that includeincentive payments for losses fault levels and networkreliability Referring to (2) the g x for a network statexi in year i is defined as
g xi = ci + oi + jminus1
j=1cj + oj +mj 2
Initial network state
Create new networkstate in the next year Analyse power flow
Generate and applynext intervention
technique application
Save network state tofailed network state
store
Update path costestimates
Reorder priority queue
Select top mostnetwork state from the
priority queueTermination
criteria reached
Failure present
Analyse reliabilityEnd yearreached
minus
+
minus
+
minus
+
Update solution costs
Save result
End
Figure 6 SIM evaluation flowchart
7Complexity
where ci is CAPEX in the current year oi is OPEX in thecurrent year and cj oj and mj are CAPEX OPEX andmetrics costs respectively of the ancestor network statewith no issues in year j The heuristic estimate h x ofthe cost to reach the end year is given by
h xi = cREMi +mi + n
k=i+1ck + ok +mk 3
where cREMi is the average remaining CAPEX in the cur-rent year i mi is the average metric cost in this year ckok and mk are the average CAPEX OPEX and metriccosts respectively of the descendant network state in yeark with no issues and n is the end year of evaluation Pre-seeded to a constant value c0 the average CAPEX isupdated each time a network state is expanded in a partic-ular year thus the estimated costs of fixing all issues in aparticular year progressively approach true average Settingc0 to a value greater than 0 speeds up the expansion pro-cess ie all interventions that cost less than c0 will resultin new network states that are at the top of the priorityqueue The business rationale is that DNOs are not thatinterested in optimizing interventions costing less than acertain threshold The learned averages are propagatedback to network states in the priority queue thus updatingtheir estimated effort and leading to the reordering of thequeue unlike the average CAPEX average OPEX andmetrics costs which are assumed to be 0 for years withno network states The average OPEX value for a year isobtained using
o = jToc jT jminus1 4
where j is a column vector of ones and oc is an OPEXvector of compliant network states in that year Likewisethe average metric cost is obtained according to
m = jTmc jT jminus1 5
where j is a column vector of ones and mc is a vector ofthe metric costs of compliant network states in that year
32 Conceptualising Bottom-Up Evolutionary PlanningModel-driven engineering (MDE) uses analysis constructionand development of frameworks to formulate metamodelsThose models are usually characterised using domain-specific modelling approaches [28] containing appropriatedetail abstraction of particular domain through a specificmetamodel The use of metamodels requires therefore inputsfrom domain experts which can be used to generate aggre-gated or disaggregated models Top-down and bottom-upare the conceptual definition of aggregated and disaggregatedmodels [29] These two modelling paradigms are frequentlyused to epitomise domain interactions among the operationof the energy system the econometrics related and thetechnical performance indicators [30]
From a bottom-up modelling approach [31 32] thetop-down perspective is a simplistic characterisation ofhow electrical power networks combine locational eventsand individual asset performance with high-level objectiveslike improving the CML of a certain congested area [33 34]From an engineering point of view both are still validsince outputs and strategic forecast are produced in bothHow those outcomes are calculated validated and trans-formed to strategy is presented in Figure 7 (top-down)and Figure 8 (bottom-up)
Interventiontechnique costs
Relative usage ofinterventiontechnique
Interventiontechnique installation
details
Interventiontechnique models
Validationphysical trials
Interventiontechnique operation
details
Purchase andoperation cost data
Cost model
Network data
Representativenetworks
Model network through years
Calculate intervention technique usage
Strategic forecasts
Validationsampled nodal
networks
Demand scenarios
Figure 7 Top-down conceptualisation of evolutionary power networks planning
8 Complexity
The ability of bottom-up to capture discrete locationalimpacts of technologies on the system and their disaggre-gated costs is triggering the following subsections Trade-offmethodologies are needed for planning evolutionary powersystems where observing disaggregated result strategic fore-casts are to be produced These methodologies need to beinteractive in the sense that starting from an initial stateand after a testing or learning phase the network is able toaccommodate techniques that have improved the systemproviding an exploratory set of solutions that can beexpanded or discarded as the model evolves through time
33 Experiment Characterisation To illustrate the processingof the methodology adopted we consider a typical networkscenario tree created by the tool that consists of failed (red)and compliant (green) network states in different years ofevaluation The SIM starts with a single network state inthe first year of evaluation Every year the network isevaluated for compliance in intact and n minus 1 contingencyoperation modes If failures are detected the SIM appliesintervention techniques described in Section 2 to create net-work patches that resolve the failures Each application of anintervention technique creates a new network state The toolhas to resolve all issues in the network before transitioninginto the next year DNO planners usually run power flowstudies with a single fixed load pattern In contrast the SIMchecks each network state for compliance under 18 charac-teristic day load scenarios each comprising of 48 half-hoursettlement periods All studies are performed under intactand n minus 1 contingency network operation modes The SIM
calculates patch costs using cost drivers returned by the net-work modelling tool The cost driver describes a networkintervention and consists of two parts namely the patchkey and the scaling The patch key identifies the nature ofthe modification of the network performed (removal or addi-tion of an asset and the type of the asset) Scaling data is rel-evant only to patches that can be installed in multiples of onesuch as cable upgrades and additional transformer installa-tion Scaling data structure provides a list of multipliers tothe base cost data available in the SIM database In case ofcable upgrade or replacement it enables the SIM to correctlyestimate full installation costs from per unit of length valuesFinally for postprocessing analysis the SIM also returns a listof failures by asset It was identified by DNO planners asindispensable features to help validate the system and corre-late the expansion trees to the actual assets on the networkdiagram The failure detail table contains asset ID anddescription alongside information about the number of fail-ures in intact and n minus 1 operating modes as well as absoluteand per unit thermal and voltage failure magnitude
34 Case Characterisation Two set of experiments wereperformed for this study one for comparing short-termevaluation period for RIIO-ED1 (2015ndash2023) where theRIIO-ED1 investment planning has been stylised and alonger planning period for RIIO-ED1 to RIIO-ED4 from2015 up to 2047 The other set aimed at evaluating differ-ent DECC demand scenarios Experiments evaluated twodemand scenarios DECC2 and DECC4 DECC4 representsas displayed in Table 1 the slow-progression scenario and
Purchase andoperation cost data
Cost model Nodal network model
Model network through years
Apply intervention technique to keep the network compilant
Find optimal network development options
Solutions for individual networks
Aggregate results for larger network areas
Strategic forecasts
Network data Demand scenarios
Interventiontechnique costs
Interventiontechnique installation
details
Nodal interventiontechnique models
Validation withphysical trials
Relative usage ofinterventiontechniques
Validation of powerflow and reliability
models
Interventiontechnique operation
details
Load profiles
Figure 8 Bottom-up conceptualisation of evolutionary power networks planning
9Complexity
DECC2 is with DECC3 the most challenging scenario interms of electrification and low-carbon technology integra-tion The procedure to run the experiments in the SIM isshown in Figure 6 The inputs to be sent to the SIM aredetailed in Figure 5 the selected network techniques evalu-ation period demand scenario and cost model whereas theoutputs of the SIM we obtain are techniques used failuressolved assets fixed and electrical performance indicatorsThe SIM address mentioned outputs for long-term plan-ning reinforcements to optimise investment asset planningresolving network constraints The performance criteria eval-uated were capital expenditures (CAPEX) operating expen-ditures (OPEX) utilisation of assets CMLs CIs and lossesThese parameter values are delivered by the SIM after eachsimulation In order to look for the optimal solution amongthe feasible solution pathways the SIM allows a granularitystudy of each network state
4 Results
This section presents the assessment of the six smart gridinterventions along with traditional reinforcements in thetrial area compounded by six 11 kV primaries in MiltonKeynes UK for two different evaluation periods DECC2and DECC4 Subsection 41 introduces the results for the2015ndash2023 period as short-term planning and Subsection42 presents the results for a long-term evaluation period2015ndash2047
41 Short-Term Planning This section presents the assess-ment of the six smart grid interventions along with tradi-tional reinforcements in the trial area compounded by six11 kV primaries in Milton Keynes UK for two differentdemand scenarios DECC2 and DECC4
411 DECC4 2015ndash2023 Figure 9 shows the trends ofCAPEX and OPEX Note that in the year 2015 there is aCAPEXrsquos peak due to the application of more techniquesand OPEX increments over time from 2017 to 2023
Despite the investment the increase is compensated bya benefit in the electricity distribution network with areduction in CML and CI as shown in Figure 10
The summary of the proportion of installations requiredduring this evaluation period and by capital expenditures pertechnique is presented in Table 2 for both DECC scenarios
The average yearly price of each technique implementedto fix a network state is key for future decision-makingconsiderations
Figure 11 displays the average price of each techniquedisaggregated by CAPEX and OPEX
Performance indicators are key parameters for futuredecision-making within electricity distribution planning asquantifiers due to their influence on the quality of service
Therefore as shown in Figure 12 the only smart tech-nique used in combination with traditional reinforcementsin this scenario and evaluation period that slightly influenceslightly CML and CI is meshed networks
412 DECC2 2015ndash2023 Figure 13 plots the trend ofCAPEX and OPEX over the evaluation period It is important
to highlight that there is a CAPEX peak in 2015 due to anincrease of techniques applied in this period
This CAPEX increment produces a benefit in terms ofCML and CI as observed in Figure 14
The distribution of techniques applied and capital expen-ditures per technique are shown in Table 2 The average priceof each technique implementation in this demand scenariofor this evaluation period is shown in Figure 15
As displayed in Figure 12 for DECC4rsquos simulation theonly smart grid technique that improves the quality of serviceis the meshed network In Figure 16 the contribution ofsmart techniques on CML and CI for DECC2 demandevaluation is captured
413 Comparison between DECC2 and DECC4 for 2015ndash2023 The results presented may facilitate improvementsin electricity distribution network operations and planningresulting in better-informed decision-making when upgrad-ing current electricity distribution networks The assess-ment of the six smart grid techniques discovered thatonly three of them were selected as part of optimal
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
Mill
ions
pound p
er an
num
CAPEXOPEX
442444648
55254
Figure 9 CAPEX and OPEX DECC4 2015ndash2023
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
pu
Figure 10 CML and CI DECC4 2015ndash2023
10 Complexity
solutions for DECC4 and DECC2 as described in Table 2These three techniques applied are DAR for cables andtransformers and meshed networks
Comparing the cost trends of the two assessed scenariosit is notable that in both demand scenarios DECC4 and
DECC2 the CAPEX peak occurs in 2015 (Figures 9 and13) reflecting the more difficult nature of network statesto be feasible in a demanding scenario whereas DECC2shows a higher improvement of CI and CML performanceindicators as can be seen in Figures 10 and 14
Table 2 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2023
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 15 2 14 2
DAR-transformer 7 1 5 1
ALT 0 0 0 0
Mesh 3 1 4 1
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 8 3 7 2
TRAD-cable 60 89 65 91
TRAD-transfer load 6 2 4 1
TRAD-new feeder 1 2 1 2
DAR - cable DAR -transformer
Meshednetworks
TRAD -transformer
TRAD - cable
CAPEXOPEX
0
20000
40000
60000
80000
100000
pound
Figure 11 Average cost disaggregation per technique DECC4 2015ndash2023
Figure 12 Average CML and CI improvement per technique DECC4 2015ndash2023
11Complexity
The techniques applied are the key consideration to beassessed It is necessary to analyse the number of interven-tions applied by type the effect of these techniques in theelectric grid solving failures and fixing assets Figures 11and 15 show average prices of techniques used in eachdemand scenario Smart techniques have a lower TOTEXthan traditional reinforcements These novel techniquesabove are not frequently able to fix failures and thereforeproduce feasible network states In terms of CML and CIthe only technique able to moderately contribute to theirimprovement is meshed networks as shown in Figures 12and 16 Results attribute the majority of fixes to traditionalreinforcements with a comparatively smaller number offailures being solved by smart techniques (Table 2) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention forDECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
For DECC4 the three mentioned techniques along withtraditional cable and transformer replacement are applied(Table 2) whereas for DECC2 two of them are appliedDAR for cables and meshed networks (Table 2) Comparingthe cost trends of the two assessed scenarios it is notable thatin DECC4 the CAPEX peak occurs in 2015 (Figure 7)whereas in DECC2 besides the peak in 2015 there is alsoone in 2019 (Figure 11) reflecting the more difficult natureof network states to be feasible in a demanding scenarioHowever DECC2 shows a higher improvement of electricalperformance indicators as can be seen in Figure 12
In addition traditional cable replacement DAR forcables and meshed networks are able to fix the cable whereastraditional transformer replacement and DAR for trans-formers are able to fix transformer issues (Figure 16) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention for
DECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
42 Long-Term Planning This section evaluates two experi-ments namely characterising the DECC2 and DECC4 sce-narios for 2015ndash2047 evaluation period For each demandscenario expected investments disaggregating CAPEX andOPEX are presented the evolution of electrical performanceindicators and the number of techniques applied
421 DECC4 2015ndash2047 In this experiment the mostsignificant results to analyse the suitability of each techniqueare presented
Figure 17 shows the trend of CAPEX and OPEX from2015 to 2047
There are CAPEX peaks in the year 2018 and during thebeginning of RIIO-ED2 in the years 2025 to 2026 due to theapplication of more techniques to fulfill low-carbon targets
Figure 18 indicates that upgrades on the network aredirectly related to technical performance indicators CMLand CI
In Table 3 the techniques applied and their contributionto CAPEX during the evaluation period from 2015 to 2047 bya demand scenario are shown
422 DECC2 2015ndash2047 Within this experiment the mostrelevant results to analyse the evolutionary network statesare presented
In Figure 19 the trend of CAPEX and OPEX from 2015to 2047 is shown There is a significant increase of CAPEXin the years 2024 to 2026 at the beginning of RIIO-ED2due to the necessary implementation of new techniques toreach low-carbon targets The evolution of CML and CI ispresented in Figure 20 linking larger investment years whenmajor reductions are found The contribution of each solutiontechnique is presented in Table 3
423 Comparison between DECC2 and DECC4 for 2015ndash2047 Figure 21 presents a multidimensional parallel coor-dinate representation of the feasible network statersquoscombinations that produced a 2015ndash2047 investment path-way for the evaluated area It bundles economic indicatorsie CAPEX and OPEX with technical performance indica-tors providing valuable insights on the number of traditionalreinforcements utilised to heal falling network states Resultsare also clustered by the two demand scenarios assessedduring the experiments
Solutions of DECC2 (represented in orange and green)and DECC4 (in black and blue) are clustered by the per-centage of traditional reinforcements utilised as well asthe utilisation factor
Solutions in green and in black represent those wheresmart grids were more used whereas orange and blue repre-sent the cheapest (CAPEX and OPEX) less utilised and theworst responding to the decrease of CML CI and lossesand the ones using more traditional reinforcement to fixnetwork states
Besides the fact that DECC2 smart solutions are between16 and 28 more expensive than DECC4 traditional
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
CAPEXOPEX
442444648
552
Mill
ions
pound p
er an
num
54
Figure 13 CAPEX and OPEX DECC2 2015ndash2023
12 Complexity
reinforcement solutions (green solutions versus blue solu-tions in Figure 21) DECC2 traditional solutions are in therange of costs of smart solutions of DECC4 (orange andblack solutions in Figure 21) It can also be concluded thatinvestment pathways using less smart techniques provide a
cheaper response to technical performance evaluators suchas utilisation CML CI and losses
43 Summary Experiment evaluation runs from the2015ndash2047 period present lower investment rates for the
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
PU
Figure 14 CML and CI DECC2 2015ndash2023
CAPEXOPEX
DAR -transformer
Meshednetworks
Traditional -transformer
Traditional -cable
0
20000
40000
60000
80000
100000
120000
140000
pound
Figure 15 Average cost disaggregation per technique DECC2 2015ndash2023
Figure 16 Average CML and CI improvement per technique DECC2 2015ndash2023
13Complexity
2015ndash2023 period than if the evaluation is just performedwith a 2015ndash2023 time frame This occurs as a result of thechallenging low-carbon targets up to 2047 and a myopicplanning with short-term lookahead For an evaluationperiod four times larger the CAPEX and TOTEX increasedjust 18 compared to 2015ndash2023 concluding that betweenpound52M and pound68M the evaluation area regardless of thetime horizon for the investment or the demand scenarioconsidered is required
Furthermore it can be inferred comparing Tables 2 and 3that for less smart interventions the short-term planningis used compared to the long-term horizon planningDAR-cable and DAR-transformer experienced a significantimplementation variation between the two evaluationperiods for both demand scenarios as well as CAPEX allo-cated in cable upgrades falling from 89ndash91 (2015ndash2023)to 29ndash66 in the long term 2015ndash2047 run Both technicalperformance evaluators CML and CI respond to theirrespective CAPEX curve shape Due to a more incentivisedsmart grid technique during RIIO-ED2 and ED3 the per-centages of smart techniques implemented varied notablyFor DECC4 in 2023rsquos outlook the share of techniques is
25 for smart grid interventions whereas for 2050rsquos out-look the share is increased up to 58 In the same wayfor DECC2 in 2023rsquos outlook the share of smart interven-tions is 23 whereas in 2050rsquos outlook the share increasesup to 69
Feasible solutions characterising the solution space(Figure 21) differ in the degree of investment required andtechnical performance evaluators Each of the solution pathrepresented in the multidimensional solution space inFigure 21 represents the intersection of that dimension witheach axis Parallel coordinates [35] are low complexityworking for any N-dimension In the case of Figure 21it has 8 dimensions treating every variable uniformlyEach intersection of one solution path with each axis isthe value of that solution for that axis As for axis DECC2and DECC4 it represents the feasible solutions for eachdemand scenario Making a query by the percentage oftraditional reinforcement used in that solution we have thepartition between orange and green for DECC2 and blueand black being the first solutions that use more traditionalreinforcement compared with the ones that use more smarttechniques represented in green (DECC2) and black(DECC4) From Figure 21 we can argue that solutions thatuse more smart techniques (green and blacks) are moreexpensive in terms of CAPEX and OPEX than their peers(orange and blues) when compared by a demand scenarioIt can also be stated that solutions with a higher use of tradi-tional reinforcements are the ones that decrease the mostCML CI and losses
Disaggregating results by network state of the six 11 kVprimaries and by the feeder if necessary for further granulardebugging can discern locational capacity Under bothdemand scenarios Secklow Gate was seen to be the one withgreater capacity being necessary to apply fewer techniquesover the evaluation period 2015ndash2047 On the other handNewport Pagnell exceeds the capacity as soon as 2015requiring a high number of network state evaluation to befixed that happens for each subsequent year hence the largenumber of network states is presented in Table 4
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
pound p
er an
num
Figure 17 CAPEX and OPEX DECC4 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
pu
Figure 18 CML and CI DECC4 2015ndash2047
14 Complexity
5 Conclusions
Power flow analysis using a nodal network model is essentialwhen determining the benefits of trailed smart interventions
because the interactions and implications are highly specificto a particular location and scenario
This suggests that while the bottom-up approach isonerous in terms of data handling and manipulation this isworthwhile for strategic planning and policy evaluationComparing both investment strategies investment strategyadjustments will be necessary in future regulation periodsif an over-invested network behaves as displayed in theshort-term section of this study
Traditional reinforcement will continue to be the mainmethod by which network issues are mostly resolvedfollowed by dynamic asset rating and meshed networks
The assessment of the six novel smart interventions in theFALCON 11kV primary test area in Milton Keynes hasproved the suitability of three techniques able to fix failuresimproving the quality of service and their readiness to bedeployed in the near future These techniques are DAR forcables and transformers and meshed networks Meshednetworks have been repeatedly selected as a feasible tech-nique because using it will reduce CML CI and power losses
Table 3 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2047
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 18 5 31 6
DAR-transformer 32 16 32 6
ALT 0 0 0 0
Mesh 8 3 6 3
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 25 44 9 16
TRAD-cable 15 29 20 66
TRAD-transfer load 1 1 1 1
TRAD-new feeder 1 2 1 2
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
s pound p
er an
num
Figure 19 CAPEX and OPEX DECC2 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
PU
Figure 20 CML and CI DECC2 2015ndash2047
15Complexity
improving the quality of service and the efficiency whilebeing a cost-effective solution
The initial capacity at primary substations differedsignificantly and this affected the number and complexityof interventions required by the SIM Due to the loadscenarios showing significant peak load increases DAR wasoften a temporary measure that would delay but not removethe eventual need for traditional reinforcement
Implementing DAR for cables and transformers themonitoring of assets when their peak capacity is increasedwas analysed On the other hand it was observed thattraditional reinforcements still play a key role in keepingthe electricity distribution networks free of constraintsTRAD techniques such as transformer and cable replace-ments are able to fix the majority of failures and will beessential also in the future
The comparison between traditional reinforcements andnovel smart techniques has provided a new knowledge aboutthe suitability of each technique to be applied in termsof costs electrical performance failures fixed and assetreplaced Cable replacement is the most costly techniquehowever its use is unavoidable in a number of cases Further-more the applicability of each technique regarding costsinvolved improvements on power quality and efficiency
and failures solved lead to new questions to be analysed suchas the lack of these techniques to provide flexible capacitywithin the trailed area
To sum up this study has performed a comparativeanalysis of novel smart intervention techniques providinginsights for future investments in electricity distributionplanning Further work can focus on scaling up the analysisto include a larger section of the network or a constrainedarea to evaluate national applicability of the current findings
Data Availability
Some of the data relevant to this submission is proprietaryfrom Western Power Distribution It can be accessed forresearch purposes under a signed collaboration agreement
Conflicts of Interest
The authors declare that they have no conflicts of interest
Acknowledgments
The authors would like to thank the rest of the WesternPower Distribution Innovation team particularly the other
2400
2200
2000
350
360
370
380
390
400
1400
1300
1200
1100
1000DECC 4
50
55
60
12
11
10
9
8
4400
4200
4000
3800
3600
2400
CAPEX (in kpound) OPEX (in kpound) Utilisation Traditional reinforcements () DECC 2 998796 CML 998796 CI 998796 Losses
2200
2000
1800
Figure 21 Parallel coordinate visualisation of technoeconomic performance indicators under DECC4 and DECC2
Table 4 Summary of network states and results for demand scenario DECC4 and DECC2
Primary 11 kV substation Feeders Year TechniquesResultsDECC4
NSDECC4
ResultsDECC2
NSDECC2
Fox Milne 13 2047 Smart and traditional 54 276 47 259
Newport Pagnell 9 2047 Smart and traditional 48 317 31 318
Secklow Gate 9 2047 Smart and traditional 27 29 15 16
Bletchley 19 2047 Smart and traditional 32 40 21 48
Marlborough Street 11 2047 Smart and traditional 31 52 19 37
Childs Way 17 2047 Smart and traditional 67 398 54 181
16 Complexity
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
commercial agreements between the DNO and industrialand commercial customers who have the ability to controlappreciable amounts of load in a relatively short period oftime We expect demand side response to be in two formsusing the representation in Figure 4
(i) To reduce the impact of predicted peak loads
(ii) To respond to an unplanned event such as a fault
Demand side response actions can be used by the DNOto enable a change in behaviour by a customer site inresponse to an explicit signal triggering a preagreed actionThe action should be the interruption of a customerrsquosinternal electricity-consuming processes either to avoid ormore likely to defer these to a later time Its metricscapacitydelta reduction durationfrequency and OPEXare detailed in [13]
3 Methodology
To undertake the analysis of the aforementioned techniquesa revolutionary new software tool for electricity distributionnetwork planning called the scenario investment model(SIM) is used Results from evaluations using the SIM areobtained through a series of experiments that modelled thenetwork evolution under different demand scenarios pre-sented in Table 1 at short- (2015ndash2023) and long-termlookahead (2015ndash2050) to assist decision-makers in futurepower network planning
Currently electricity distribution networks have beenplanned with typically linear load growths of up to 1 perannum The expected increase in low-carbon technologieswill have a significant effect on the electricity demands onthe network which may have significant rapid sporadicincreases in the electricity demand on the 11 kV networks
[25] In addition the daily electricity load shapes may be alsoaltered significantly The networks will need to be upgradedand systems are being able to evolve and cope with newdemand profiles
There had been identified two main streams of work toconsider the use of the innovative techniques namely strate-gic and tactical planning and Design Build and OperationThe strategic and tactical planning stream will consider thenetwork planning roles while the design and operationstream will consider design build and operation roles InFigure 5 the smart grid planning framework diagram pre-sents the key elements of each stream which are displayedwith their main interactions
In order to leverage the capability of existing networkanalysis tools which are already extensively used by elec-tricity network operators the SIM is separated into twomain packages a network modelling tool which primarilyperforms the technical assessment of the application ofthe techniques and the SIM harness which manages theoverall process and perform the economic assessment andreporting functions
Demand data modelling has been based on a bottom-upapproach The methods used provide an estimate of demandfor each half-hour at each secondary substation for 18different season-day types [12]
Communication network
DGDSM
Customer site
PowerOn fusion
Demandforecast
Networkanalyser
Networkevent
DGDSMscheduler
DSMDG manager
Performancemonitor
Paymentscalculator
RTUsmartmeter
Figure 4 Commercial trials representation DGDSM
Table 1 Demand scenarios
Demand scenariosFuel
efficiencyLow-carbon
heatWall
insulation
DECC1 Medium High High
DECC2 High Medium High
DECC3 High High Low
DECC4 Low Low Medium
5Complexity
The research objective is settled to prove the suitability ofthe six novel smart interventions presented in Section 2and along with the traditional reinforcements provide anevolutionary planning insight for future power networksTo undertake this study specific experiments were selectedfor a certain power trial network under different demandscenarios and evaluation periods assessing smart tech-niques along with traditional reinforcements The approachinvolved running a set of experiments using the SIM for thesix 11 kV primaries in the FALCON trial area
31 SIM Support Algorithms The essence of the SIMapproach is its ability to take a network configuration andcorresponding load profiles in a particular year (termed asinitial network state) perform power flow and reliabilityanalysis and create derivative network states in a processknown as ldquonetwork state expansionrdquo The expansion happenseither by transitioning to the following year for networkstates without any failures or by applying intervention
techniques to resolve network issues With each new net-work state created the SIM therefore is faced with adecision as to which network state from the executionhistory to expand next The expansion can be guided bysimple depth first or breadth first algorithms which areimplemented in the SIM for verification purposes Thedepth-first algorithm always selects the newest ie themost recently created network state that is not fullyexpanded for expansion while the breadth-first algorithmalways selects the oldest network state However thosesimple heuristics are inadequate for any practical usebeyond simple test cases due to the size of the searchspace obtained by permuting all possible interventionsover a number of years To perform intelligent explorationof the search space the SIM uses a heuristic approach thatis based on an Alowast algorithm [26 27]
The baseline Alowast algorithm aims at finding the least-costpath through the search space As Alowast traverses the searchspace it builds a tree of partial paths The leaf nodes of this
Learning transfer
Key component
Systempackage conatinga set of key components
Learninganalysis of results for theimprovement of models and development ofpolicies
Smart grid planning framework
Substationmonitoring
Dynamicasset ratings
data
Automatedload transfer
dataMeshed
network data
Communication network trial
Monitoringdata collection
system
Trials data distributionmanagement system
Scenario investment model
Network modelling tool(technical Assessment)
Dynamic assetratings
techniquemodel
Automatedload transfer
techniquemodel
Batterystorage
techniquemodel
Meshednetwork
techniquemodel
Traditional reinforcement
technique model
Networktopology amp
loads
Distributedgenerationtechnique
model
Demand sidemanagement
techniquemodel
Multi-yearscheduler
Economicinvestmentassesment
Networkperformance
analysisVisualisationand reporting
SIM harness(economic assesment and
reporting)
Performance analysisamp learning
Energy modelminusmeasured data
comparison
Demand datamodelling and
scenario development
Impr
ove e
nerg
ym
odel
Design build andoperation
Strategic andtactical planning
Strategic planning supportconnections and
infrastructure planningplanning policy development
Impr
ove t
echn
ique
and
netw
ork m
odels
Batterystorage data
Distributedgeneration
trial
Demand sidemanagement
data
Design amp build learning
Impr
ove i
mpl
emen
tatio
n co
st m
odels
Figure 5 Smart grid planning framework diagram
6 Complexity
tree (failed network states) are stored in a priority queue thatis ordered using a cost function
f x = g x + h x 1
where h x is a heuristic estimate of the path cost toreach the goal and g x is the distance travelled fromthe initial node
The SIM selects network states from the priority queue toapply intervention techniques one application at a timeDeployment of a technique produces a new network statefor which a power flow analysis is performed in intact andall n minus 1 (contingency) network operation modes If allthe failures are resolved a reliability analysis comprisingcustomer minutes lost (CML) customer interruptions (CI)losses and fault level studies is performed A new networkstate is subsequently created in the next year of evaluationor if it is already the last year of evaluation the costsof interventions are calculated and the network statetogether with all its expansion history is saved to theresult store as a new result The evaluation is terminated
(Figure 6) when criteria such as the number of resultsnumber of network state evaluations or run time arereached As noted previously Alowast uses a combination ofdistance travelled so far and a heuristic estimate of thedistance to reach the endpoint
In SIM case this corresponds to g x being the totalexpenditures (TOTEX) incurred so far and h x being aheuristic estimate of TOTEX to reach the end year ofthe experiment TOTEX also referred to as the totalexpenditure comprises implementation costs (CAPEX)that occur only once when an intervention is applied tothe network operation costs (OPEX) that refer to anongoing expense of operating an asset or a scheme alongwith asset life degradation and metric costs that includeincentive payments for losses fault levels and networkreliability Referring to (2) the g x for a network statexi in year i is defined as
g xi = ci + oi + jminus1
j=1cj + oj +mj 2
Initial network state
Create new networkstate in the next year Analyse power flow
Generate and applynext intervention
technique application
Save network state tofailed network state
store
Update path costestimates
Reorder priority queue
Select top mostnetwork state from the
priority queueTermination
criteria reached
Failure present
Analyse reliabilityEnd yearreached
minus
+
minus
+
minus
+
Update solution costs
Save result
End
Figure 6 SIM evaluation flowchart
7Complexity
where ci is CAPEX in the current year oi is OPEX in thecurrent year and cj oj and mj are CAPEX OPEX andmetrics costs respectively of the ancestor network statewith no issues in year j The heuristic estimate h x ofthe cost to reach the end year is given by
h xi = cREMi +mi + n
k=i+1ck + ok +mk 3
where cREMi is the average remaining CAPEX in the cur-rent year i mi is the average metric cost in this year ckok and mk are the average CAPEX OPEX and metriccosts respectively of the descendant network state in yeark with no issues and n is the end year of evaluation Pre-seeded to a constant value c0 the average CAPEX isupdated each time a network state is expanded in a partic-ular year thus the estimated costs of fixing all issues in aparticular year progressively approach true average Settingc0 to a value greater than 0 speeds up the expansion pro-cess ie all interventions that cost less than c0 will resultin new network states that are at the top of the priorityqueue The business rationale is that DNOs are not thatinterested in optimizing interventions costing less than acertain threshold The learned averages are propagatedback to network states in the priority queue thus updatingtheir estimated effort and leading to the reordering of thequeue unlike the average CAPEX average OPEX andmetrics costs which are assumed to be 0 for years withno network states The average OPEX value for a year isobtained using
o = jToc jT jminus1 4
where j is a column vector of ones and oc is an OPEXvector of compliant network states in that year Likewisethe average metric cost is obtained according to
m = jTmc jT jminus1 5
where j is a column vector of ones and mc is a vector ofthe metric costs of compliant network states in that year
32 Conceptualising Bottom-Up Evolutionary PlanningModel-driven engineering (MDE) uses analysis constructionand development of frameworks to formulate metamodelsThose models are usually characterised using domain-specific modelling approaches [28] containing appropriatedetail abstraction of particular domain through a specificmetamodel The use of metamodels requires therefore inputsfrom domain experts which can be used to generate aggre-gated or disaggregated models Top-down and bottom-upare the conceptual definition of aggregated and disaggregatedmodels [29] These two modelling paradigms are frequentlyused to epitomise domain interactions among the operationof the energy system the econometrics related and thetechnical performance indicators [30]
From a bottom-up modelling approach [31 32] thetop-down perspective is a simplistic characterisation ofhow electrical power networks combine locational eventsand individual asset performance with high-level objectiveslike improving the CML of a certain congested area [33 34]From an engineering point of view both are still validsince outputs and strategic forecast are produced in bothHow those outcomes are calculated validated and trans-formed to strategy is presented in Figure 7 (top-down)and Figure 8 (bottom-up)
Interventiontechnique costs
Relative usage ofinterventiontechnique
Interventiontechnique installation
details
Interventiontechnique models
Validationphysical trials
Interventiontechnique operation
details
Purchase andoperation cost data
Cost model
Network data
Representativenetworks
Model network through years
Calculate intervention technique usage
Strategic forecasts
Validationsampled nodal
networks
Demand scenarios
Figure 7 Top-down conceptualisation of evolutionary power networks planning
8 Complexity
The ability of bottom-up to capture discrete locationalimpacts of technologies on the system and their disaggre-gated costs is triggering the following subsections Trade-offmethodologies are needed for planning evolutionary powersystems where observing disaggregated result strategic fore-casts are to be produced These methodologies need to beinteractive in the sense that starting from an initial stateand after a testing or learning phase the network is able toaccommodate techniques that have improved the systemproviding an exploratory set of solutions that can beexpanded or discarded as the model evolves through time
33 Experiment Characterisation To illustrate the processingof the methodology adopted we consider a typical networkscenario tree created by the tool that consists of failed (red)and compliant (green) network states in different years ofevaluation The SIM starts with a single network state inthe first year of evaluation Every year the network isevaluated for compliance in intact and n minus 1 contingencyoperation modes If failures are detected the SIM appliesintervention techniques described in Section 2 to create net-work patches that resolve the failures Each application of anintervention technique creates a new network state The toolhas to resolve all issues in the network before transitioninginto the next year DNO planners usually run power flowstudies with a single fixed load pattern In contrast the SIMchecks each network state for compliance under 18 charac-teristic day load scenarios each comprising of 48 half-hoursettlement periods All studies are performed under intactand n minus 1 contingency network operation modes The SIM
calculates patch costs using cost drivers returned by the net-work modelling tool The cost driver describes a networkintervention and consists of two parts namely the patchkey and the scaling The patch key identifies the nature ofthe modification of the network performed (removal or addi-tion of an asset and the type of the asset) Scaling data is rel-evant only to patches that can be installed in multiples of onesuch as cable upgrades and additional transformer installa-tion Scaling data structure provides a list of multipliers tothe base cost data available in the SIM database In case ofcable upgrade or replacement it enables the SIM to correctlyestimate full installation costs from per unit of length valuesFinally for postprocessing analysis the SIM also returns a listof failures by asset It was identified by DNO planners asindispensable features to help validate the system and corre-late the expansion trees to the actual assets on the networkdiagram The failure detail table contains asset ID anddescription alongside information about the number of fail-ures in intact and n minus 1 operating modes as well as absoluteand per unit thermal and voltage failure magnitude
34 Case Characterisation Two set of experiments wereperformed for this study one for comparing short-termevaluation period for RIIO-ED1 (2015ndash2023) where theRIIO-ED1 investment planning has been stylised and alonger planning period for RIIO-ED1 to RIIO-ED4 from2015 up to 2047 The other set aimed at evaluating differ-ent DECC demand scenarios Experiments evaluated twodemand scenarios DECC2 and DECC4 DECC4 representsas displayed in Table 1 the slow-progression scenario and
Purchase andoperation cost data
Cost model Nodal network model
Model network through years
Apply intervention technique to keep the network compilant
Find optimal network development options
Solutions for individual networks
Aggregate results for larger network areas
Strategic forecasts
Network data Demand scenarios
Interventiontechnique costs
Interventiontechnique installation
details
Nodal interventiontechnique models
Validation withphysical trials
Relative usage ofinterventiontechniques
Validation of powerflow and reliability
models
Interventiontechnique operation
details
Load profiles
Figure 8 Bottom-up conceptualisation of evolutionary power networks planning
9Complexity
DECC2 is with DECC3 the most challenging scenario interms of electrification and low-carbon technology integra-tion The procedure to run the experiments in the SIM isshown in Figure 6 The inputs to be sent to the SIM aredetailed in Figure 5 the selected network techniques evalu-ation period demand scenario and cost model whereas theoutputs of the SIM we obtain are techniques used failuressolved assets fixed and electrical performance indicatorsThe SIM address mentioned outputs for long-term plan-ning reinforcements to optimise investment asset planningresolving network constraints The performance criteria eval-uated were capital expenditures (CAPEX) operating expen-ditures (OPEX) utilisation of assets CMLs CIs and lossesThese parameter values are delivered by the SIM after eachsimulation In order to look for the optimal solution amongthe feasible solution pathways the SIM allows a granularitystudy of each network state
4 Results
This section presents the assessment of the six smart gridinterventions along with traditional reinforcements in thetrial area compounded by six 11 kV primaries in MiltonKeynes UK for two different evaluation periods DECC2and DECC4 Subsection 41 introduces the results for the2015ndash2023 period as short-term planning and Subsection42 presents the results for a long-term evaluation period2015ndash2047
41 Short-Term Planning This section presents the assess-ment of the six smart grid interventions along with tradi-tional reinforcements in the trial area compounded by six11 kV primaries in Milton Keynes UK for two differentdemand scenarios DECC2 and DECC4
411 DECC4 2015ndash2023 Figure 9 shows the trends ofCAPEX and OPEX Note that in the year 2015 there is aCAPEXrsquos peak due to the application of more techniquesand OPEX increments over time from 2017 to 2023
Despite the investment the increase is compensated bya benefit in the electricity distribution network with areduction in CML and CI as shown in Figure 10
The summary of the proportion of installations requiredduring this evaluation period and by capital expenditures pertechnique is presented in Table 2 for both DECC scenarios
The average yearly price of each technique implementedto fix a network state is key for future decision-makingconsiderations
Figure 11 displays the average price of each techniquedisaggregated by CAPEX and OPEX
Performance indicators are key parameters for futuredecision-making within electricity distribution planning asquantifiers due to their influence on the quality of service
Therefore as shown in Figure 12 the only smart tech-nique used in combination with traditional reinforcementsin this scenario and evaluation period that slightly influenceslightly CML and CI is meshed networks
412 DECC2 2015ndash2023 Figure 13 plots the trend ofCAPEX and OPEX over the evaluation period It is important
to highlight that there is a CAPEX peak in 2015 due to anincrease of techniques applied in this period
This CAPEX increment produces a benefit in terms ofCML and CI as observed in Figure 14
The distribution of techniques applied and capital expen-ditures per technique are shown in Table 2 The average priceof each technique implementation in this demand scenariofor this evaluation period is shown in Figure 15
As displayed in Figure 12 for DECC4rsquos simulation theonly smart grid technique that improves the quality of serviceis the meshed network In Figure 16 the contribution ofsmart techniques on CML and CI for DECC2 demandevaluation is captured
413 Comparison between DECC2 and DECC4 for 2015ndash2023 The results presented may facilitate improvementsin electricity distribution network operations and planningresulting in better-informed decision-making when upgrad-ing current electricity distribution networks The assess-ment of the six smart grid techniques discovered thatonly three of them were selected as part of optimal
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
Mill
ions
pound p
er an
num
CAPEXOPEX
442444648
55254
Figure 9 CAPEX and OPEX DECC4 2015ndash2023
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
pu
Figure 10 CML and CI DECC4 2015ndash2023
10 Complexity
solutions for DECC4 and DECC2 as described in Table 2These three techniques applied are DAR for cables andtransformers and meshed networks
Comparing the cost trends of the two assessed scenariosit is notable that in both demand scenarios DECC4 and
DECC2 the CAPEX peak occurs in 2015 (Figures 9 and13) reflecting the more difficult nature of network statesto be feasible in a demanding scenario whereas DECC2shows a higher improvement of CI and CML performanceindicators as can be seen in Figures 10 and 14
Table 2 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2023
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 15 2 14 2
DAR-transformer 7 1 5 1
ALT 0 0 0 0
Mesh 3 1 4 1
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 8 3 7 2
TRAD-cable 60 89 65 91
TRAD-transfer load 6 2 4 1
TRAD-new feeder 1 2 1 2
DAR - cable DAR -transformer
Meshednetworks
TRAD -transformer
TRAD - cable
CAPEXOPEX
0
20000
40000
60000
80000
100000
pound
Figure 11 Average cost disaggregation per technique DECC4 2015ndash2023
Figure 12 Average CML and CI improvement per technique DECC4 2015ndash2023
11Complexity
The techniques applied are the key consideration to beassessed It is necessary to analyse the number of interven-tions applied by type the effect of these techniques in theelectric grid solving failures and fixing assets Figures 11and 15 show average prices of techniques used in eachdemand scenario Smart techniques have a lower TOTEXthan traditional reinforcements These novel techniquesabove are not frequently able to fix failures and thereforeproduce feasible network states In terms of CML and CIthe only technique able to moderately contribute to theirimprovement is meshed networks as shown in Figures 12and 16 Results attribute the majority of fixes to traditionalreinforcements with a comparatively smaller number offailures being solved by smart techniques (Table 2) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention forDECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
For DECC4 the three mentioned techniques along withtraditional cable and transformer replacement are applied(Table 2) whereas for DECC2 two of them are appliedDAR for cables and meshed networks (Table 2) Comparingthe cost trends of the two assessed scenarios it is notable thatin DECC4 the CAPEX peak occurs in 2015 (Figure 7)whereas in DECC2 besides the peak in 2015 there is alsoone in 2019 (Figure 11) reflecting the more difficult natureof network states to be feasible in a demanding scenarioHowever DECC2 shows a higher improvement of electricalperformance indicators as can be seen in Figure 12
In addition traditional cable replacement DAR forcables and meshed networks are able to fix the cable whereastraditional transformer replacement and DAR for trans-formers are able to fix transformer issues (Figure 16) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention for
DECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
42 Long-Term Planning This section evaluates two experi-ments namely characterising the DECC2 and DECC4 sce-narios for 2015ndash2047 evaluation period For each demandscenario expected investments disaggregating CAPEX andOPEX are presented the evolution of electrical performanceindicators and the number of techniques applied
421 DECC4 2015ndash2047 In this experiment the mostsignificant results to analyse the suitability of each techniqueare presented
Figure 17 shows the trend of CAPEX and OPEX from2015 to 2047
There are CAPEX peaks in the year 2018 and during thebeginning of RIIO-ED2 in the years 2025 to 2026 due to theapplication of more techniques to fulfill low-carbon targets
Figure 18 indicates that upgrades on the network aredirectly related to technical performance indicators CMLand CI
In Table 3 the techniques applied and their contributionto CAPEX during the evaluation period from 2015 to 2047 bya demand scenario are shown
422 DECC2 2015ndash2047 Within this experiment the mostrelevant results to analyse the evolutionary network statesare presented
In Figure 19 the trend of CAPEX and OPEX from 2015to 2047 is shown There is a significant increase of CAPEXin the years 2024 to 2026 at the beginning of RIIO-ED2due to the necessary implementation of new techniques toreach low-carbon targets The evolution of CML and CI ispresented in Figure 20 linking larger investment years whenmajor reductions are found The contribution of each solutiontechnique is presented in Table 3
423 Comparison between DECC2 and DECC4 for 2015ndash2047 Figure 21 presents a multidimensional parallel coor-dinate representation of the feasible network statersquoscombinations that produced a 2015ndash2047 investment path-way for the evaluated area It bundles economic indicatorsie CAPEX and OPEX with technical performance indica-tors providing valuable insights on the number of traditionalreinforcements utilised to heal falling network states Resultsare also clustered by the two demand scenarios assessedduring the experiments
Solutions of DECC2 (represented in orange and green)and DECC4 (in black and blue) are clustered by the per-centage of traditional reinforcements utilised as well asthe utilisation factor
Solutions in green and in black represent those wheresmart grids were more used whereas orange and blue repre-sent the cheapest (CAPEX and OPEX) less utilised and theworst responding to the decrease of CML CI and lossesand the ones using more traditional reinforcement to fixnetwork states
Besides the fact that DECC2 smart solutions are between16 and 28 more expensive than DECC4 traditional
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
CAPEXOPEX
442444648
552
Mill
ions
pound p
er an
num
54
Figure 13 CAPEX and OPEX DECC2 2015ndash2023
12 Complexity
reinforcement solutions (green solutions versus blue solu-tions in Figure 21) DECC2 traditional solutions are in therange of costs of smart solutions of DECC4 (orange andblack solutions in Figure 21) It can also be concluded thatinvestment pathways using less smart techniques provide a
cheaper response to technical performance evaluators suchas utilisation CML CI and losses
43 Summary Experiment evaluation runs from the2015ndash2047 period present lower investment rates for the
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
PU
Figure 14 CML and CI DECC2 2015ndash2023
CAPEXOPEX
DAR -transformer
Meshednetworks
Traditional -transformer
Traditional -cable
0
20000
40000
60000
80000
100000
120000
140000
pound
Figure 15 Average cost disaggregation per technique DECC2 2015ndash2023
Figure 16 Average CML and CI improvement per technique DECC2 2015ndash2023
13Complexity
2015ndash2023 period than if the evaluation is just performedwith a 2015ndash2023 time frame This occurs as a result of thechallenging low-carbon targets up to 2047 and a myopicplanning with short-term lookahead For an evaluationperiod four times larger the CAPEX and TOTEX increasedjust 18 compared to 2015ndash2023 concluding that betweenpound52M and pound68M the evaluation area regardless of thetime horizon for the investment or the demand scenarioconsidered is required
Furthermore it can be inferred comparing Tables 2 and 3that for less smart interventions the short-term planningis used compared to the long-term horizon planningDAR-cable and DAR-transformer experienced a significantimplementation variation between the two evaluationperiods for both demand scenarios as well as CAPEX allo-cated in cable upgrades falling from 89ndash91 (2015ndash2023)to 29ndash66 in the long term 2015ndash2047 run Both technicalperformance evaluators CML and CI respond to theirrespective CAPEX curve shape Due to a more incentivisedsmart grid technique during RIIO-ED2 and ED3 the per-centages of smart techniques implemented varied notablyFor DECC4 in 2023rsquos outlook the share of techniques is
25 for smart grid interventions whereas for 2050rsquos out-look the share is increased up to 58 In the same wayfor DECC2 in 2023rsquos outlook the share of smart interven-tions is 23 whereas in 2050rsquos outlook the share increasesup to 69
Feasible solutions characterising the solution space(Figure 21) differ in the degree of investment required andtechnical performance evaluators Each of the solution pathrepresented in the multidimensional solution space inFigure 21 represents the intersection of that dimension witheach axis Parallel coordinates [35] are low complexityworking for any N-dimension In the case of Figure 21it has 8 dimensions treating every variable uniformlyEach intersection of one solution path with each axis isthe value of that solution for that axis As for axis DECC2and DECC4 it represents the feasible solutions for eachdemand scenario Making a query by the percentage oftraditional reinforcement used in that solution we have thepartition between orange and green for DECC2 and blueand black being the first solutions that use more traditionalreinforcement compared with the ones that use more smarttechniques represented in green (DECC2) and black(DECC4) From Figure 21 we can argue that solutions thatuse more smart techniques (green and blacks) are moreexpensive in terms of CAPEX and OPEX than their peers(orange and blues) when compared by a demand scenarioIt can also be stated that solutions with a higher use of tradi-tional reinforcements are the ones that decrease the mostCML CI and losses
Disaggregating results by network state of the six 11 kVprimaries and by the feeder if necessary for further granulardebugging can discern locational capacity Under bothdemand scenarios Secklow Gate was seen to be the one withgreater capacity being necessary to apply fewer techniquesover the evaluation period 2015ndash2047 On the other handNewport Pagnell exceeds the capacity as soon as 2015requiring a high number of network state evaluation to befixed that happens for each subsequent year hence the largenumber of network states is presented in Table 4
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
pound p
er an
num
Figure 17 CAPEX and OPEX DECC4 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
pu
Figure 18 CML and CI DECC4 2015ndash2047
14 Complexity
5 Conclusions
Power flow analysis using a nodal network model is essentialwhen determining the benefits of trailed smart interventions
because the interactions and implications are highly specificto a particular location and scenario
This suggests that while the bottom-up approach isonerous in terms of data handling and manipulation this isworthwhile for strategic planning and policy evaluationComparing both investment strategies investment strategyadjustments will be necessary in future regulation periodsif an over-invested network behaves as displayed in theshort-term section of this study
Traditional reinforcement will continue to be the mainmethod by which network issues are mostly resolvedfollowed by dynamic asset rating and meshed networks
The assessment of the six novel smart interventions in theFALCON 11kV primary test area in Milton Keynes hasproved the suitability of three techniques able to fix failuresimproving the quality of service and their readiness to bedeployed in the near future These techniques are DAR forcables and transformers and meshed networks Meshednetworks have been repeatedly selected as a feasible tech-nique because using it will reduce CML CI and power losses
Table 3 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2047
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 18 5 31 6
DAR-transformer 32 16 32 6
ALT 0 0 0 0
Mesh 8 3 6 3
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 25 44 9 16
TRAD-cable 15 29 20 66
TRAD-transfer load 1 1 1 1
TRAD-new feeder 1 2 1 2
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
s pound p
er an
num
Figure 19 CAPEX and OPEX DECC2 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
PU
Figure 20 CML and CI DECC2 2015ndash2047
15Complexity
improving the quality of service and the efficiency whilebeing a cost-effective solution
The initial capacity at primary substations differedsignificantly and this affected the number and complexityof interventions required by the SIM Due to the loadscenarios showing significant peak load increases DAR wasoften a temporary measure that would delay but not removethe eventual need for traditional reinforcement
Implementing DAR for cables and transformers themonitoring of assets when their peak capacity is increasedwas analysed On the other hand it was observed thattraditional reinforcements still play a key role in keepingthe electricity distribution networks free of constraintsTRAD techniques such as transformer and cable replace-ments are able to fix the majority of failures and will beessential also in the future
The comparison between traditional reinforcements andnovel smart techniques has provided a new knowledge aboutthe suitability of each technique to be applied in termsof costs electrical performance failures fixed and assetreplaced Cable replacement is the most costly techniquehowever its use is unavoidable in a number of cases Further-more the applicability of each technique regarding costsinvolved improvements on power quality and efficiency
and failures solved lead to new questions to be analysed suchas the lack of these techniques to provide flexible capacitywithin the trailed area
To sum up this study has performed a comparativeanalysis of novel smart intervention techniques providinginsights for future investments in electricity distributionplanning Further work can focus on scaling up the analysisto include a larger section of the network or a constrainedarea to evaluate national applicability of the current findings
Data Availability
Some of the data relevant to this submission is proprietaryfrom Western Power Distribution It can be accessed forresearch purposes under a signed collaboration agreement
Conflicts of Interest
The authors declare that they have no conflicts of interest
Acknowledgments
The authors would like to thank the rest of the WesternPower Distribution Innovation team particularly the other
2400
2200
2000
350
360
370
380
390
400
1400
1300
1200
1100
1000DECC 4
50
55
60
12
11
10
9
8
4400
4200
4000
3800
3600
2400
CAPEX (in kpound) OPEX (in kpound) Utilisation Traditional reinforcements () DECC 2 998796 CML 998796 CI 998796 Losses
2200
2000
1800
Figure 21 Parallel coordinate visualisation of technoeconomic performance indicators under DECC4 and DECC2
Table 4 Summary of network states and results for demand scenario DECC4 and DECC2
Primary 11 kV substation Feeders Year TechniquesResultsDECC4
NSDECC4
ResultsDECC2
NSDECC2
Fox Milne 13 2047 Smart and traditional 54 276 47 259
Newport Pagnell 9 2047 Smart and traditional 48 317 31 318
Secklow Gate 9 2047 Smart and traditional 27 29 15 16
Bletchley 19 2047 Smart and traditional 32 40 21 48
Marlborough Street 11 2047 Smart and traditional 31 52 19 37
Childs Way 17 2047 Smart and traditional 67 398 54 181
16 Complexity
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
The research objective is settled to prove the suitability ofthe six novel smart interventions presented in Section 2and along with the traditional reinforcements provide anevolutionary planning insight for future power networksTo undertake this study specific experiments were selectedfor a certain power trial network under different demandscenarios and evaluation periods assessing smart tech-niques along with traditional reinforcements The approachinvolved running a set of experiments using the SIM for thesix 11 kV primaries in the FALCON trial area
31 SIM Support Algorithms The essence of the SIMapproach is its ability to take a network configuration andcorresponding load profiles in a particular year (termed asinitial network state) perform power flow and reliabilityanalysis and create derivative network states in a processknown as ldquonetwork state expansionrdquo The expansion happenseither by transitioning to the following year for networkstates without any failures or by applying intervention
techniques to resolve network issues With each new net-work state created the SIM therefore is faced with adecision as to which network state from the executionhistory to expand next The expansion can be guided bysimple depth first or breadth first algorithms which areimplemented in the SIM for verification purposes Thedepth-first algorithm always selects the newest ie themost recently created network state that is not fullyexpanded for expansion while the breadth-first algorithmalways selects the oldest network state However thosesimple heuristics are inadequate for any practical usebeyond simple test cases due to the size of the searchspace obtained by permuting all possible interventionsover a number of years To perform intelligent explorationof the search space the SIM uses a heuristic approach thatis based on an Alowast algorithm [26 27]
The baseline Alowast algorithm aims at finding the least-costpath through the search space As Alowast traverses the searchspace it builds a tree of partial paths The leaf nodes of this
Learning transfer
Key component
Systempackage conatinga set of key components
Learninganalysis of results for theimprovement of models and development ofpolicies
Smart grid planning framework
Substationmonitoring
Dynamicasset ratings
data
Automatedload transfer
dataMeshed
network data
Communication network trial
Monitoringdata collection
system
Trials data distributionmanagement system
Scenario investment model
Network modelling tool(technical Assessment)
Dynamic assetratings
techniquemodel
Automatedload transfer
techniquemodel
Batterystorage
techniquemodel
Meshednetwork
techniquemodel
Traditional reinforcement
technique model
Networktopology amp
loads
Distributedgenerationtechnique
model
Demand sidemanagement
techniquemodel
Multi-yearscheduler
Economicinvestmentassesment
Networkperformance
analysisVisualisationand reporting
SIM harness(economic assesment and
reporting)
Performance analysisamp learning
Energy modelminusmeasured data
comparison
Demand datamodelling and
scenario development
Impr
ove e
nerg
ym
odel
Design build andoperation
Strategic andtactical planning
Strategic planning supportconnections and
infrastructure planningplanning policy development
Impr
ove t
echn
ique
and
netw
ork m
odels
Batterystorage data
Distributedgeneration
trial
Demand sidemanagement
data
Design amp build learning
Impr
ove i
mpl
emen
tatio
n co
st m
odels
Figure 5 Smart grid planning framework diagram
6 Complexity
tree (failed network states) are stored in a priority queue thatis ordered using a cost function
f x = g x + h x 1
where h x is a heuristic estimate of the path cost toreach the goal and g x is the distance travelled fromthe initial node
The SIM selects network states from the priority queue toapply intervention techniques one application at a timeDeployment of a technique produces a new network statefor which a power flow analysis is performed in intact andall n minus 1 (contingency) network operation modes If allthe failures are resolved a reliability analysis comprisingcustomer minutes lost (CML) customer interruptions (CI)losses and fault level studies is performed A new networkstate is subsequently created in the next year of evaluationor if it is already the last year of evaluation the costsof interventions are calculated and the network statetogether with all its expansion history is saved to theresult store as a new result The evaluation is terminated
(Figure 6) when criteria such as the number of resultsnumber of network state evaluations or run time arereached As noted previously Alowast uses a combination ofdistance travelled so far and a heuristic estimate of thedistance to reach the endpoint
In SIM case this corresponds to g x being the totalexpenditures (TOTEX) incurred so far and h x being aheuristic estimate of TOTEX to reach the end year ofthe experiment TOTEX also referred to as the totalexpenditure comprises implementation costs (CAPEX)that occur only once when an intervention is applied tothe network operation costs (OPEX) that refer to anongoing expense of operating an asset or a scheme alongwith asset life degradation and metric costs that includeincentive payments for losses fault levels and networkreliability Referring to (2) the g x for a network statexi in year i is defined as
g xi = ci + oi + jminus1
j=1cj + oj +mj 2
Initial network state
Create new networkstate in the next year Analyse power flow
Generate and applynext intervention
technique application
Save network state tofailed network state
store
Update path costestimates
Reorder priority queue
Select top mostnetwork state from the
priority queueTermination
criteria reached
Failure present
Analyse reliabilityEnd yearreached
minus
+
minus
+
minus
+
Update solution costs
Save result
End
Figure 6 SIM evaluation flowchart
7Complexity
where ci is CAPEX in the current year oi is OPEX in thecurrent year and cj oj and mj are CAPEX OPEX andmetrics costs respectively of the ancestor network statewith no issues in year j The heuristic estimate h x ofthe cost to reach the end year is given by
h xi = cREMi +mi + n
k=i+1ck + ok +mk 3
where cREMi is the average remaining CAPEX in the cur-rent year i mi is the average metric cost in this year ckok and mk are the average CAPEX OPEX and metriccosts respectively of the descendant network state in yeark with no issues and n is the end year of evaluation Pre-seeded to a constant value c0 the average CAPEX isupdated each time a network state is expanded in a partic-ular year thus the estimated costs of fixing all issues in aparticular year progressively approach true average Settingc0 to a value greater than 0 speeds up the expansion pro-cess ie all interventions that cost less than c0 will resultin new network states that are at the top of the priorityqueue The business rationale is that DNOs are not thatinterested in optimizing interventions costing less than acertain threshold The learned averages are propagatedback to network states in the priority queue thus updatingtheir estimated effort and leading to the reordering of thequeue unlike the average CAPEX average OPEX andmetrics costs which are assumed to be 0 for years withno network states The average OPEX value for a year isobtained using
o = jToc jT jminus1 4
where j is a column vector of ones and oc is an OPEXvector of compliant network states in that year Likewisethe average metric cost is obtained according to
m = jTmc jT jminus1 5
where j is a column vector of ones and mc is a vector ofthe metric costs of compliant network states in that year
32 Conceptualising Bottom-Up Evolutionary PlanningModel-driven engineering (MDE) uses analysis constructionand development of frameworks to formulate metamodelsThose models are usually characterised using domain-specific modelling approaches [28] containing appropriatedetail abstraction of particular domain through a specificmetamodel The use of metamodels requires therefore inputsfrom domain experts which can be used to generate aggre-gated or disaggregated models Top-down and bottom-upare the conceptual definition of aggregated and disaggregatedmodels [29] These two modelling paradigms are frequentlyused to epitomise domain interactions among the operationof the energy system the econometrics related and thetechnical performance indicators [30]
From a bottom-up modelling approach [31 32] thetop-down perspective is a simplistic characterisation ofhow electrical power networks combine locational eventsand individual asset performance with high-level objectiveslike improving the CML of a certain congested area [33 34]From an engineering point of view both are still validsince outputs and strategic forecast are produced in bothHow those outcomes are calculated validated and trans-formed to strategy is presented in Figure 7 (top-down)and Figure 8 (bottom-up)
Interventiontechnique costs
Relative usage ofinterventiontechnique
Interventiontechnique installation
details
Interventiontechnique models
Validationphysical trials
Interventiontechnique operation
details
Purchase andoperation cost data
Cost model
Network data
Representativenetworks
Model network through years
Calculate intervention technique usage
Strategic forecasts
Validationsampled nodal
networks
Demand scenarios
Figure 7 Top-down conceptualisation of evolutionary power networks planning
8 Complexity
The ability of bottom-up to capture discrete locationalimpacts of technologies on the system and their disaggre-gated costs is triggering the following subsections Trade-offmethodologies are needed for planning evolutionary powersystems where observing disaggregated result strategic fore-casts are to be produced These methodologies need to beinteractive in the sense that starting from an initial stateand after a testing or learning phase the network is able toaccommodate techniques that have improved the systemproviding an exploratory set of solutions that can beexpanded or discarded as the model evolves through time
33 Experiment Characterisation To illustrate the processingof the methodology adopted we consider a typical networkscenario tree created by the tool that consists of failed (red)and compliant (green) network states in different years ofevaluation The SIM starts with a single network state inthe first year of evaluation Every year the network isevaluated for compliance in intact and n minus 1 contingencyoperation modes If failures are detected the SIM appliesintervention techniques described in Section 2 to create net-work patches that resolve the failures Each application of anintervention technique creates a new network state The toolhas to resolve all issues in the network before transitioninginto the next year DNO planners usually run power flowstudies with a single fixed load pattern In contrast the SIMchecks each network state for compliance under 18 charac-teristic day load scenarios each comprising of 48 half-hoursettlement periods All studies are performed under intactand n minus 1 contingency network operation modes The SIM
calculates patch costs using cost drivers returned by the net-work modelling tool The cost driver describes a networkintervention and consists of two parts namely the patchkey and the scaling The patch key identifies the nature ofthe modification of the network performed (removal or addi-tion of an asset and the type of the asset) Scaling data is rel-evant only to patches that can be installed in multiples of onesuch as cable upgrades and additional transformer installa-tion Scaling data structure provides a list of multipliers tothe base cost data available in the SIM database In case ofcable upgrade or replacement it enables the SIM to correctlyestimate full installation costs from per unit of length valuesFinally for postprocessing analysis the SIM also returns a listof failures by asset It was identified by DNO planners asindispensable features to help validate the system and corre-late the expansion trees to the actual assets on the networkdiagram The failure detail table contains asset ID anddescription alongside information about the number of fail-ures in intact and n minus 1 operating modes as well as absoluteand per unit thermal and voltage failure magnitude
34 Case Characterisation Two set of experiments wereperformed for this study one for comparing short-termevaluation period for RIIO-ED1 (2015ndash2023) where theRIIO-ED1 investment planning has been stylised and alonger planning period for RIIO-ED1 to RIIO-ED4 from2015 up to 2047 The other set aimed at evaluating differ-ent DECC demand scenarios Experiments evaluated twodemand scenarios DECC2 and DECC4 DECC4 representsas displayed in Table 1 the slow-progression scenario and
Purchase andoperation cost data
Cost model Nodal network model
Model network through years
Apply intervention technique to keep the network compilant
Find optimal network development options
Solutions for individual networks
Aggregate results for larger network areas
Strategic forecasts
Network data Demand scenarios
Interventiontechnique costs
Interventiontechnique installation
details
Nodal interventiontechnique models
Validation withphysical trials
Relative usage ofinterventiontechniques
Validation of powerflow and reliability
models
Interventiontechnique operation
details
Load profiles
Figure 8 Bottom-up conceptualisation of evolutionary power networks planning
9Complexity
DECC2 is with DECC3 the most challenging scenario interms of electrification and low-carbon technology integra-tion The procedure to run the experiments in the SIM isshown in Figure 6 The inputs to be sent to the SIM aredetailed in Figure 5 the selected network techniques evalu-ation period demand scenario and cost model whereas theoutputs of the SIM we obtain are techniques used failuressolved assets fixed and electrical performance indicatorsThe SIM address mentioned outputs for long-term plan-ning reinforcements to optimise investment asset planningresolving network constraints The performance criteria eval-uated were capital expenditures (CAPEX) operating expen-ditures (OPEX) utilisation of assets CMLs CIs and lossesThese parameter values are delivered by the SIM after eachsimulation In order to look for the optimal solution amongthe feasible solution pathways the SIM allows a granularitystudy of each network state
4 Results
This section presents the assessment of the six smart gridinterventions along with traditional reinforcements in thetrial area compounded by six 11 kV primaries in MiltonKeynes UK for two different evaluation periods DECC2and DECC4 Subsection 41 introduces the results for the2015ndash2023 period as short-term planning and Subsection42 presents the results for a long-term evaluation period2015ndash2047
41 Short-Term Planning This section presents the assess-ment of the six smart grid interventions along with tradi-tional reinforcements in the trial area compounded by six11 kV primaries in Milton Keynes UK for two differentdemand scenarios DECC2 and DECC4
411 DECC4 2015ndash2023 Figure 9 shows the trends ofCAPEX and OPEX Note that in the year 2015 there is aCAPEXrsquos peak due to the application of more techniquesand OPEX increments over time from 2017 to 2023
Despite the investment the increase is compensated bya benefit in the electricity distribution network with areduction in CML and CI as shown in Figure 10
The summary of the proportion of installations requiredduring this evaluation period and by capital expenditures pertechnique is presented in Table 2 for both DECC scenarios
The average yearly price of each technique implementedto fix a network state is key for future decision-makingconsiderations
Figure 11 displays the average price of each techniquedisaggregated by CAPEX and OPEX
Performance indicators are key parameters for futuredecision-making within electricity distribution planning asquantifiers due to their influence on the quality of service
Therefore as shown in Figure 12 the only smart tech-nique used in combination with traditional reinforcementsin this scenario and evaluation period that slightly influenceslightly CML and CI is meshed networks
412 DECC2 2015ndash2023 Figure 13 plots the trend ofCAPEX and OPEX over the evaluation period It is important
to highlight that there is a CAPEX peak in 2015 due to anincrease of techniques applied in this period
This CAPEX increment produces a benefit in terms ofCML and CI as observed in Figure 14
The distribution of techniques applied and capital expen-ditures per technique are shown in Table 2 The average priceof each technique implementation in this demand scenariofor this evaluation period is shown in Figure 15
As displayed in Figure 12 for DECC4rsquos simulation theonly smart grid technique that improves the quality of serviceis the meshed network In Figure 16 the contribution ofsmart techniques on CML and CI for DECC2 demandevaluation is captured
413 Comparison between DECC2 and DECC4 for 2015ndash2023 The results presented may facilitate improvementsin electricity distribution network operations and planningresulting in better-informed decision-making when upgrad-ing current electricity distribution networks The assess-ment of the six smart grid techniques discovered thatonly three of them were selected as part of optimal
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
Mill
ions
pound p
er an
num
CAPEXOPEX
442444648
55254
Figure 9 CAPEX and OPEX DECC4 2015ndash2023
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
pu
Figure 10 CML and CI DECC4 2015ndash2023
10 Complexity
solutions for DECC4 and DECC2 as described in Table 2These three techniques applied are DAR for cables andtransformers and meshed networks
Comparing the cost trends of the two assessed scenariosit is notable that in both demand scenarios DECC4 and
DECC2 the CAPEX peak occurs in 2015 (Figures 9 and13) reflecting the more difficult nature of network statesto be feasible in a demanding scenario whereas DECC2shows a higher improvement of CI and CML performanceindicators as can be seen in Figures 10 and 14
Table 2 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2023
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 15 2 14 2
DAR-transformer 7 1 5 1
ALT 0 0 0 0
Mesh 3 1 4 1
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 8 3 7 2
TRAD-cable 60 89 65 91
TRAD-transfer load 6 2 4 1
TRAD-new feeder 1 2 1 2
DAR - cable DAR -transformer
Meshednetworks
TRAD -transformer
TRAD - cable
CAPEXOPEX
0
20000
40000
60000
80000
100000
pound
Figure 11 Average cost disaggregation per technique DECC4 2015ndash2023
Figure 12 Average CML and CI improvement per technique DECC4 2015ndash2023
11Complexity
The techniques applied are the key consideration to beassessed It is necessary to analyse the number of interven-tions applied by type the effect of these techniques in theelectric grid solving failures and fixing assets Figures 11and 15 show average prices of techniques used in eachdemand scenario Smart techniques have a lower TOTEXthan traditional reinforcements These novel techniquesabove are not frequently able to fix failures and thereforeproduce feasible network states In terms of CML and CIthe only technique able to moderately contribute to theirimprovement is meshed networks as shown in Figures 12and 16 Results attribute the majority of fixes to traditionalreinforcements with a comparatively smaller number offailures being solved by smart techniques (Table 2) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention forDECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
For DECC4 the three mentioned techniques along withtraditional cable and transformer replacement are applied(Table 2) whereas for DECC2 two of them are appliedDAR for cables and meshed networks (Table 2) Comparingthe cost trends of the two assessed scenarios it is notable thatin DECC4 the CAPEX peak occurs in 2015 (Figure 7)whereas in DECC2 besides the peak in 2015 there is alsoone in 2019 (Figure 11) reflecting the more difficult natureof network states to be feasible in a demanding scenarioHowever DECC2 shows a higher improvement of electricalperformance indicators as can be seen in Figure 12
In addition traditional cable replacement DAR forcables and meshed networks are able to fix the cable whereastraditional transformer replacement and DAR for trans-formers are able to fix transformer issues (Figure 16) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention for
DECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
42 Long-Term Planning This section evaluates two experi-ments namely characterising the DECC2 and DECC4 sce-narios for 2015ndash2047 evaluation period For each demandscenario expected investments disaggregating CAPEX andOPEX are presented the evolution of electrical performanceindicators and the number of techniques applied
421 DECC4 2015ndash2047 In this experiment the mostsignificant results to analyse the suitability of each techniqueare presented
Figure 17 shows the trend of CAPEX and OPEX from2015 to 2047
There are CAPEX peaks in the year 2018 and during thebeginning of RIIO-ED2 in the years 2025 to 2026 due to theapplication of more techniques to fulfill low-carbon targets
Figure 18 indicates that upgrades on the network aredirectly related to technical performance indicators CMLand CI
In Table 3 the techniques applied and their contributionto CAPEX during the evaluation period from 2015 to 2047 bya demand scenario are shown
422 DECC2 2015ndash2047 Within this experiment the mostrelevant results to analyse the evolutionary network statesare presented
In Figure 19 the trend of CAPEX and OPEX from 2015to 2047 is shown There is a significant increase of CAPEXin the years 2024 to 2026 at the beginning of RIIO-ED2due to the necessary implementation of new techniques toreach low-carbon targets The evolution of CML and CI ispresented in Figure 20 linking larger investment years whenmajor reductions are found The contribution of each solutiontechnique is presented in Table 3
423 Comparison between DECC2 and DECC4 for 2015ndash2047 Figure 21 presents a multidimensional parallel coor-dinate representation of the feasible network statersquoscombinations that produced a 2015ndash2047 investment path-way for the evaluated area It bundles economic indicatorsie CAPEX and OPEX with technical performance indica-tors providing valuable insights on the number of traditionalreinforcements utilised to heal falling network states Resultsare also clustered by the two demand scenarios assessedduring the experiments
Solutions of DECC2 (represented in orange and green)and DECC4 (in black and blue) are clustered by the per-centage of traditional reinforcements utilised as well asthe utilisation factor
Solutions in green and in black represent those wheresmart grids were more used whereas orange and blue repre-sent the cheapest (CAPEX and OPEX) less utilised and theworst responding to the decrease of CML CI and lossesand the ones using more traditional reinforcement to fixnetwork states
Besides the fact that DECC2 smart solutions are between16 and 28 more expensive than DECC4 traditional
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
CAPEXOPEX
442444648
552
Mill
ions
pound p
er an
num
54
Figure 13 CAPEX and OPEX DECC2 2015ndash2023
12 Complexity
reinforcement solutions (green solutions versus blue solu-tions in Figure 21) DECC2 traditional solutions are in therange of costs of smart solutions of DECC4 (orange andblack solutions in Figure 21) It can also be concluded thatinvestment pathways using less smart techniques provide a
cheaper response to technical performance evaluators suchas utilisation CML CI and losses
43 Summary Experiment evaluation runs from the2015ndash2047 period present lower investment rates for the
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
PU
Figure 14 CML and CI DECC2 2015ndash2023
CAPEXOPEX
DAR -transformer
Meshednetworks
Traditional -transformer
Traditional -cable
0
20000
40000
60000
80000
100000
120000
140000
pound
Figure 15 Average cost disaggregation per technique DECC2 2015ndash2023
Figure 16 Average CML and CI improvement per technique DECC2 2015ndash2023
13Complexity
2015ndash2023 period than if the evaluation is just performedwith a 2015ndash2023 time frame This occurs as a result of thechallenging low-carbon targets up to 2047 and a myopicplanning with short-term lookahead For an evaluationperiod four times larger the CAPEX and TOTEX increasedjust 18 compared to 2015ndash2023 concluding that betweenpound52M and pound68M the evaluation area regardless of thetime horizon for the investment or the demand scenarioconsidered is required
Furthermore it can be inferred comparing Tables 2 and 3that for less smart interventions the short-term planningis used compared to the long-term horizon planningDAR-cable and DAR-transformer experienced a significantimplementation variation between the two evaluationperiods for both demand scenarios as well as CAPEX allo-cated in cable upgrades falling from 89ndash91 (2015ndash2023)to 29ndash66 in the long term 2015ndash2047 run Both technicalperformance evaluators CML and CI respond to theirrespective CAPEX curve shape Due to a more incentivisedsmart grid technique during RIIO-ED2 and ED3 the per-centages of smart techniques implemented varied notablyFor DECC4 in 2023rsquos outlook the share of techniques is
25 for smart grid interventions whereas for 2050rsquos out-look the share is increased up to 58 In the same wayfor DECC2 in 2023rsquos outlook the share of smart interven-tions is 23 whereas in 2050rsquos outlook the share increasesup to 69
Feasible solutions characterising the solution space(Figure 21) differ in the degree of investment required andtechnical performance evaluators Each of the solution pathrepresented in the multidimensional solution space inFigure 21 represents the intersection of that dimension witheach axis Parallel coordinates [35] are low complexityworking for any N-dimension In the case of Figure 21it has 8 dimensions treating every variable uniformlyEach intersection of one solution path with each axis isthe value of that solution for that axis As for axis DECC2and DECC4 it represents the feasible solutions for eachdemand scenario Making a query by the percentage oftraditional reinforcement used in that solution we have thepartition between orange and green for DECC2 and blueand black being the first solutions that use more traditionalreinforcement compared with the ones that use more smarttechniques represented in green (DECC2) and black(DECC4) From Figure 21 we can argue that solutions thatuse more smart techniques (green and blacks) are moreexpensive in terms of CAPEX and OPEX than their peers(orange and blues) when compared by a demand scenarioIt can also be stated that solutions with a higher use of tradi-tional reinforcements are the ones that decrease the mostCML CI and losses
Disaggregating results by network state of the six 11 kVprimaries and by the feeder if necessary for further granulardebugging can discern locational capacity Under bothdemand scenarios Secklow Gate was seen to be the one withgreater capacity being necessary to apply fewer techniquesover the evaluation period 2015ndash2047 On the other handNewport Pagnell exceeds the capacity as soon as 2015requiring a high number of network state evaluation to befixed that happens for each subsequent year hence the largenumber of network states is presented in Table 4
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
pound p
er an
num
Figure 17 CAPEX and OPEX DECC4 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
pu
Figure 18 CML and CI DECC4 2015ndash2047
14 Complexity
5 Conclusions
Power flow analysis using a nodal network model is essentialwhen determining the benefits of trailed smart interventions
because the interactions and implications are highly specificto a particular location and scenario
This suggests that while the bottom-up approach isonerous in terms of data handling and manipulation this isworthwhile for strategic planning and policy evaluationComparing both investment strategies investment strategyadjustments will be necessary in future regulation periodsif an over-invested network behaves as displayed in theshort-term section of this study
Traditional reinforcement will continue to be the mainmethod by which network issues are mostly resolvedfollowed by dynamic asset rating and meshed networks
The assessment of the six novel smart interventions in theFALCON 11kV primary test area in Milton Keynes hasproved the suitability of three techniques able to fix failuresimproving the quality of service and their readiness to bedeployed in the near future These techniques are DAR forcables and transformers and meshed networks Meshednetworks have been repeatedly selected as a feasible tech-nique because using it will reduce CML CI and power losses
Table 3 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2047
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 18 5 31 6
DAR-transformer 32 16 32 6
ALT 0 0 0 0
Mesh 8 3 6 3
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 25 44 9 16
TRAD-cable 15 29 20 66
TRAD-transfer load 1 1 1 1
TRAD-new feeder 1 2 1 2
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
s pound p
er an
num
Figure 19 CAPEX and OPEX DECC2 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
PU
Figure 20 CML and CI DECC2 2015ndash2047
15Complexity
improving the quality of service and the efficiency whilebeing a cost-effective solution
The initial capacity at primary substations differedsignificantly and this affected the number and complexityof interventions required by the SIM Due to the loadscenarios showing significant peak load increases DAR wasoften a temporary measure that would delay but not removethe eventual need for traditional reinforcement
Implementing DAR for cables and transformers themonitoring of assets when their peak capacity is increasedwas analysed On the other hand it was observed thattraditional reinforcements still play a key role in keepingthe electricity distribution networks free of constraintsTRAD techniques such as transformer and cable replace-ments are able to fix the majority of failures and will beessential also in the future
The comparison between traditional reinforcements andnovel smart techniques has provided a new knowledge aboutthe suitability of each technique to be applied in termsof costs electrical performance failures fixed and assetreplaced Cable replacement is the most costly techniquehowever its use is unavoidable in a number of cases Further-more the applicability of each technique regarding costsinvolved improvements on power quality and efficiency
and failures solved lead to new questions to be analysed suchas the lack of these techniques to provide flexible capacitywithin the trailed area
To sum up this study has performed a comparativeanalysis of novel smart intervention techniques providinginsights for future investments in electricity distributionplanning Further work can focus on scaling up the analysisto include a larger section of the network or a constrainedarea to evaluate national applicability of the current findings
Data Availability
Some of the data relevant to this submission is proprietaryfrom Western Power Distribution It can be accessed forresearch purposes under a signed collaboration agreement
Conflicts of Interest
The authors declare that they have no conflicts of interest
Acknowledgments
The authors would like to thank the rest of the WesternPower Distribution Innovation team particularly the other
2400
2200
2000
350
360
370
380
390
400
1400
1300
1200
1100
1000DECC 4
50
55
60
12
11
10
9
8
4400
4200
4000
3800
3600
2400
CAPEX (in kpound) OPEX (in kpound) Utilisation Traditional reinforcements () DECC 2 998796 CML 998796 CI 998796 Losses
2200
2000
1800
Figure 21 Parallel coordinate visualisation of technoeconomic performance indicators under DECC4 and DECC2
Table 4 Summary of network states and results for demand scenario DECC4 and DECC2
Primary 11 kV substation Feeders Year TechniquesResultsDECC4
NSDECC4
ResultsDECC2
NSDECC2
Fox Milne 13 2047 Smart and traditional 54 276 47 259
Newport Pagnell 9 2047 Smart and traditional 48 317 31 318
Secklow Gate 9 2047 Smart and traditional 27 29 15 16
Bletchley 19 2047 Smart and traditional 32 40 21 48
Marlborough Street 11 2047 Smart and traditional 31 52 19 37
Childs Way 17 2047 Smart and traditional 67 398 54 181
16 Complexity
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
tree (failed network states) are stored in a priority queue thatis ordered using a cost function
f x = g x + h x 1
where h x is a heuristic estimate of the path cost toreach the goal and g x is the distance travelled fromthe initial node
The SIM selects network states from the priority queue toapply intervention techniques one application at a timeDeployment of a technique produces a new network statefor which a power flow analysis is performed in intact andall n minus 1 (contingency) network operation modes If allthe failures are resolved a reliability analysis comprisingcustomer minutes lost (CML) customer interruptions (CI)losses and fault level studies is performed A new networkstate is subsequently created in the next year of evaluationor if it is already the last year of evaluation the costsof interventions are calculated and the network statetogether with all its expansion history is saved to theresult store as a new result The evaluation is terminated
(Figure 6) when criteria such as the number of resultsnumber of network state evaluations or run time arereached As noted previously Alowast uses a combination ofdistance travelled so far and a heuristic estimate of thedistance to reach the endpoint
In SIM case this corresponds to g x being the totalexpenditures (TOTEX) incurred so far and h x being aheuristic estimate of TOTEX to reach the end year ofthe experiment TOTEX also referred to as the totalexpenditure comprises implementation costs (CAPEX)that occur only once when an intervention is applied tothe network operation costs (OPEX) that refer to anongoing expense of operating an asset or a scheme alongwith asset life degradation and metric costs that includeincentive payments for losses fault levels and networkreliability Referring to (2) the g x for a network statexi in year i is defined as
g xi = ci + oi + jminus1
j=1cj + oj +mj 2
Initial network state
Create new networkstate in the next year Analyse power flow
Generate and applynext intervention
technique application
Save network state tofailed network state
store
Update path costestimates
Reorder priority queue
Select top mostnetwork state from the
priority queueTermination
criteria reached
Failure present
Analyse reliabilityEnd yearreached
minus
+
minus
+
minus
+
Update solution costs
Save result
End
Figure 6 SIM evaluation flowchart
7Complexity
where ci is CAPEX in the current year oi is OPEX in thecurrent year and cj oj and mj are CAPEX OPEX andmetrics costs respectively of the ancestor network statewith no issues in year j The heuristic estimate h x ofthe cost to reach the end year is given by
h xi = cREMi +mi + n
k=i+1ck + ok +mk 3
where cREMi is the average remaining CAPEX in the cur-rent year i mi is the average metric cost in this year ckok and mk are the average CAPEX OPEX and metriccosts respectively of the descendant network state in yeark with no issues and n is the end year of evaluation Pre-seeded to a constant value c0 the average CAPEX isupdated each time a network state is expanded in a partic-ular year thus the estimated costs of fixing all issues in aparticular year progressively approach true average Settingc0 to a value greater than 0 speeds up the expansion pro-cess ie all interventions that cost less than c0 will resultin new network states that are at the top of the priorityqueue The business rationale is that DNOs are not thatinterested in optimizing interventions costing less than acertain threshold The learned averages are propagatedback to network states in the priority queue thus updatingtheir estimated effort and leading to the reordering of thequeue unlike the average CAPEX average OPEX andmetrics costs which are assumed to be 0 for years withno network states The average OPEX value for a year isobtained using
o = jToc jT jminus1 4
where j is a column vector of ones and oc is an OPEXvector of compliant network states in that year Likewisethe average metric cost is obtained according to
m = jTmc jT jminus1 5
where j is a column vector of ones and mc is a vector ofthe metric costs of compliant network states in that year
32 Conceptualising Bottom-Up Evolutionary PlanningModel-driven engineering (MDE) uses analysis constructionand development of frameworks to formulate metamodelsThose models are usually characterised using domain-specific modelling approaches [28] containing appropriatedetail abstraction of particular domain through a specificmetamodel The use of metamodels requires therefore inputsfrom domain experts which can be used to generate aggre-gated or disaggregated models Top-down and bottom-upare the conceptual definition of aggregated and disaggregatedmodels [29] These two modelling paradigms are frequentlyused to epitomise domain interactions among the operationof the energy system the econometrics related and thetechnical performance indicators [30]
From a bottom-up modelling approach [31 32] thetop-down perspective is a simplistic characterisation ofhow electrical power networks combine locational eventsand individual asset performance with high-level objectiveslike improving the CML of a certain congested area [33 34]From an engineering point of view both are still validsince outputs and strategic forecast are produced in bothHow those outcomes are calculated validated and trans-formed to strategy is presented in Figure 7 (top-down)and Figure 8 (bottom-up)
Interventiontechnique costs
Relative usage ofinterventiontechnique
Interventiontechnique installation
details
Interventiontechnique models
Validationphysical trials
Interventiontechnique operation
details
Purchase andoperation cost data
Cost model
Network data
Representativenetworks
Model network through years
Calculate intervention technique usage
Strategic forecasts
Validationsampled nodal
networks
Demand scenarios
Figure 7 Top-down conceptualisation of evolutionary power networks planning
8 Complexity
The ability of bottom-up to capture discrete locationalimpacts of technologies on the system and their disaggre-gated costs is triggering the following subsections Trade-offmethodologies are needed for planning evolutionary powersystems where observing disaggregated result strategic fore-casts are to be produced These methodologies need to beinteractive in the sense that starting from an initial stateand after a testing or learning phase the network is able toaccommodate techniques that have improved the systemproviding an exploratory set of solutions that can beexpanded or discarded as the model evolves through time
33 Experiment Characterisation To illustrate the processingof the methodology adopted we consider a typical networkscenario tree created by the tool that consists of failed (red)and compliant (green) network states in different years ofevaluation The SIM starts with a single network state inthe first year of evaluation Every year the network isevaluated for compliance in intact and n minus 1 contingencyoperation modes If failures are detected the SIM appliesintervention techniques described in Section 2 to create net-work patches that resolve the failures Each application of anintervention technique creates a new network state The toolhas to resolve all issues in the network before transitioninginto the next year DNO planners usually run power flowstudies with a single fixed load pattern In contrast the SIMchecks each network state for compliance under 18 charac-teristic day load scenarios each comprising of 48 half-hoursettlement periods All studies are performed under intactand n minus 1 contingency network operation modes The SIM
calculates patch costs using cost drivers returned by the net-work modelling tool The cost driver describes a networkintervention and consists of two parts namely the patchkey and the scaling The patch key identifies the nature ofthe modification of the network performed (removal or addi-tion of an asset and the type of the asset) Scaling data is rel-evant only to patches that can be installed in multiples of onesuch as cable upgrades and additional transformer installa-tion Scaling data structure provides a list of multipliers tothe base cost data available in the SIM database In case ofcable upgrade or replacement it enables the SIM to correctlyestimate full installation costs from per unit of length valuesFinally for postprocessing analysis the SIM also returns a listof failures by asset It was identified by DNO planners asindispensable features to help validate the system and corre-late the expansion trees to the actual assets on the networkdiagram The failure detail table contains asset ID anddescription alongside information about the number of fail-ures in intact and n minus 1 operating modes as well as absoluteand per unit thermal and voltage failure magnitude
34 Case Characterisation Two set of experiments wereperformed for this study one for comparing short-termevaluation period for RIIO-ED1 (2015ndash2023) where theRIIO-ED1 investment planning has been stylised and alonger planning period for RIIO-ED1 to RIIO-ED4 from2015 up to 2047 The other set aimed at evaluating differ-ent DECC demand scenarios Experiments evaluated twodemand scenarios DECC2 and DECC4 DECC4 representsas displayed in Table 1 the slow-progression scenario and
Purchase andoperation cost data
Cost model Nodal network model
Model network through years
Apply intervention technique to keep the network compilant
Find optimal network development options
Solutions for individual networks
Aggregate results for larger network areas
Strategic forecasts
Network data Demand scenarios
Interventiontechnique costs
Interventiontechnique installation
details
Nodal interventiontechnique models
Validation withphysical trials
Relative usage ofinterventiontechniques
Validation of powerflow and reliability
models
Interventiontechnique operation
details
Load profiles
Figure 8 Bottom-up conceptualisation of evolutionary power networks planning
9Complexity
DECC2 is with DECC3 the most challenging scenario interms of electrification and low-carbon technology integra-tion The procedure to run the experiments in the SIM isshown in Figure 6 The inputs to be sent to the SIM aredetailed in Figure 5 the selected network techniques evalu-ation period demand scenario and cost model whereas theoutputs of the SIM we obtain are techniques used failuressolved assets fixed and electrical performance indicatorsThe SIM address mentioned outputs for long-term plan-ning reinforcements to optimise investment asset planningresolving network constraints The performance criteria eval-uated were capital expenditures (CAPEX) operating expen-ditures (OPEX) utilisation of assets CMLs CIs and lossesThese parameter values are delivered by the SIM after eachsimulation In order to look for the optimal solution amongthe feasible solution pathways the SIM allows a granularitystudy of each network state
4 Results
This section presents the assessment of the six smart gridinterventions along with traditional reinforcements in thetrial area compounded by six 11 kV primaries in MiltonKeynes UK for two different evaluation periods DECC2and DECC4 Subsection 41 introduces the results for the2015ndash2023 period as short-term planning and Subsection42 presents the results for a long-term evaluation period2015ndash2047
41 Short-Term Planning This section presents the assess-ment of the six smart grid interventions along with tradi-tional reinforcements in the trial area compounded by six11 kV primaries in Milton Keynes UK for two differentdemand scenarios DECC2 and DECC4
411 DECC4 2015ndash2023 Figure 9 shows the trends ofCAPEX and OPEX Note that in the year 2015 there is aCAPEXrsquos peak due to the application of more techniquesand OPEX increments over time from 2017 to 2023
Despite the investment the increase is compensated bya benefit in the electricity distribution network with areduction in CML and CI as shown in Figure 10
The summary of the proportion of installations requiredduring this evaluation period and by capital expenditures pertechnique is presented in Table 2 for both DECC scenarios
The average yearly price of each technique implementedto fix a network state is key for future decision-makingconsiderations
Figure 11 displays the average price of each techniquedisaggregated by CAPEX and OPEX
Performance indicators are key parameters for futuredecision-making within electricity distribution planning asquantifiers due to their influence on the quality of service
Therefore as shown in Figure 12 the only smart tech-nique used in combination with traditional reinforcementsin this scenario and evaluation period that slightly influenceslightly CML and CI is meshed networks
412 DECC2 2015ndash2023 Figure 13 plots the trend ofCAPEX and OPEX over the evaluation period It is important
to highlight that there is a CAPEX peak in 2015 due to anincrease of techniques applied in this period
This CAPEX increment produces a benefit in terms ofCML and CI as observed in Figure 14
The distribution of techniques applied and capital expen-ditures per technique are shown in Table 2 The average priceof each technique implementation in this demand scenariofor this evaluation period is shown in Figure 15
As displayed in Figure 12 for DECC4rsquos simulation theonly smart grid technique that improves the quality of serviceis the meshed network In Figure 16 the contribution ofsmart techniques on CML and CI for DECC2 demandevaluation is captured
413 Comparison between DECC2 and DECC4 for 2015ndash2023 The results presented may facilitate improvementsin electricity distribution network operations and planningresulting in better-informed decision-making when upgrad-ing current electricity distribution networks The assess-ment of the six smart grid techniques discovered thatonly three of them were selected as part of optimal
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
Mill
ions
pound p
er an
num
CAPEXOPEX
442444648
55254
Figure 9 CAPEX and OPEX DECC4 2015ndash2023
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
pu
Figure 10 CML and CI DECC4 2015ndash2023
10 Complexity
solutions for DECC4 and DECC2 as described in Table 2These three techniques applied are DAR for cables andtransformers and meshed networks
Comparing the cost trends of the two assessed scenariosit is notable that in both demand scenarios DECC4 and
DECC2 the CAPEX peak occurs in 2015 (Figures 9 and13) reflecting the more difficult nature of network statesto be feasible in a demanding scenario whereas DECC2shows a higher improvement of CI and CML performanceindicators as can be seen in Figures 10 and 14
Table 2 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2023
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 15 2 14 2
DAR-transformer 7 1 5 1
ALT 0 0 0 0
Mesh 3 1 4 1
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 8 3 7 2
TRAD-cable 60 89 65 91
TRAD-transfer load 6 2 4 1
TRAD-new feeder 1 2 1 2
DAR - cable DAR -transformer
Meshednetworks
TRAD -transformer
TRAD - cable
CAPEXOPEX
0
20000
40000
60000
80000
100000
pound
Figure 11 Average cost disaggregation per technique DECC4 2015ndash2023
Figure 12 Average CML and CI improvement per technique DECC4 2015ndash2023
11Complexity
The techniques applied are the key consideration to beassessed It is necessary to analyse the number of interven-tions applied by type the effect of these techniques in theelectric grid solving failures and fixing assets Figures 11and 15 show average prices of techniques used in eachdemand scenario Smart techniques have a lower TOTEXthan traditional reinforcements These novel techniquesabove are not frequently able to fix failures and thereforeproduce feasible network states In terms of CML and CIthe only technique able to moderately contribute to theirimprovement is meshed networks as shown in Figures 12and 16 Results attribute the majority of fixes to traditionalreinforcements with a comparatively smaller number offailures being solved by smart techniques (Table 2) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention forDECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
For DECC4 the three mentioned techniques along withtraditional cable and transformer replacement are applied(Table 2) whereas for DECC2 two of them are appliedDAR for cables and meshed networks (Table 2) Comparingthe cost trends of the two assessed scenarios it is notable thatin DECC4 the CAPEX peak occurs in 2015 (Figure 7)whereas in DECC2 besides the peak in 2015 there is alsoone in 2019 (Figure 11) reflecting the more difficult natureof network states to be feasible in a demanding scenarioHowever DECC2 shows a higher improvement of electricalperformance indicators as can be seen in Figure 12
In addition traditional cable replacement DAR forcables and meshed networks are able to fix the cable whereastraditional transformer replacement and DAR for trans-formers are able to fix transformer issues (Figure 16) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention for
DECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
42 Long-Term Planning This section evaluates two experi-ments namely characterising the DECC2 and DECC4 sce-narios for 2015ndash2047 evaluation period For each demandscenario expected investments disaggregating CAPEX andOPEX are presented the evolution of electrical performanceindicators and the number of techniques applied
421 DECC4 2015ndash2047 In this experiment the mostsignificant results to analyse the suitability of each techniqueare presented
Figure 17 shows the trend of CAPEX and OPEX from2015 to 2047
There are CAPEX peaks in the year 2018 and during thebeginning of RIIO-ED2 in the years 2025 to 2026 due to theapplication of more techniques to fulfill low-carbon targets
Figure 18 indicates that upgrades on the network aredirectly related to technical performance indicators CMLand CI
In Table 3 the techniques applied and their contributionto CAPEX during the evaluation period from 2015 to 2047 bya demand scenario are shown
422 DECC2 2015ndash2047 Within this experiment the mostrelevant results to analyse the evolutionary network statesare presented
In Figure 19 the trend of CAPEX and OPEX from 2015to 2047 is shown There is a significant increase of CAPEXin the years 2024 to 2026 at the beginning of RIIO-ED2due to the necessary implementation of new techniques toreach low-carbon targets The evolution of CML and CI ispresented in Figure 20 linking larger investment years whenmajor reductions are found The contribution of each solutiontechnique is presented in Table 3
423 Comparison between DECC2 and DECC4 for 2015ndash2047 Figure 21 presents a multidimensional parallel coor-dinate representation of the feasible network statersquoscombinations that produced a 2015ndash2047 investment path-way for the evaluated area It bundles economic indicatorsie CAPEX and OPEX with technical performance indica-tors providing valuable insights on the number of traditionalreinforcements utilised to heal falling network states Resultsare also clustered by the two demand scenarios assessedduring the experiments
Solutions of DECC2 (represented in orange and green)and DECC4 (in black and blue) are clustered by the per-centage of traditional reinforcements utilised as well asthe utilisation factor
Solutions in green and in black represent those wheresmart grids were more used whereas orange and blue repre-sent the cheapest (CAPEX and OPEX) less utilised and theworst responding to the decrease of CML CI and lossesand the ones using more traditional reinforcement to fixnetwork states
Besides the fact that DECC2 smart solutions are between16 and 28 more expensive than DECC4 traditional
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
CAPEXOPEX
442444648
552
Mill
ions
pound p
er an
num
54
Figure 13 CAPEX and OPEX DECC2 2015ndash2023
12 Complexity
reinforcement solutions (green solutions versus blue solu-tions in Figure 21) DECC2 traditional solutions are in therange of costs of smart solutions of DECC4 (orange andblack solutions in Figure 21) It can also be concluded thatinvestment pathways using less smart techniques provide a
cheaper response to technical performance evaluators suchas utilisation CML CI and losses
43 Summary Experiment evaluation runs from the2015ndash2047 period present lower investment rates for the
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
PU
Figure 14 CML and CI DECC2 2015ndash2023
CAPEXOPEX
DAR -transformer
Meshednetworks
Traditional -transformer
Traditional -cable
0
20000
40000
60000
80000
100000
120000
140000
pound
Figure 15 Average cost disaggregation per technique DECC2 2015ndash2023
Figure 16 Average CML and CI improvement per technique DECC2 2015ndash2023
13Complexity
2015ndash2023 period than if the evaluation is just performedwith a 2015ndash2023 time frame This occurs as a result of thechallenging low-carbon targets up to 2047 and a myopicplanning with short-term lookahead For an evaluationperiod four times larger the CAPEX and TOTEX increasedjust 18 compared to 2015ndash2023 concluding that betweenpound52M and pound68M the evaluation area regardless of thetime horizon for the investment or the demand scenarioconsidered is required
Furthermore it can be inferred comparing Tables 2 and 3that for less smart interventions the short-term planningis used compared to the long-term horizon planningDAR-cable and DAR-transformer experienced a significantimplementation variation between the two evaluationperiods for both demand scenarios as well as CAPEX allo-cated in cable upgrades falling from 89ndash91 (2015ndash2023)to 29ndash66 in the long term 2015ndash2047 run Both technicalperformance evaluators CML and CI respond to theirrespective CAPEX curve shape Due to a more incentivisedsmart grid technique during RIIO-ED2 and ED3 the per-centages of smart techniques implemented varied notablyFor DECC4 in 2023rsquos outlook the share of techniques is
25 for smart grid interventions whereas for 2050rsquos out-look the share is increased up to 58 In the same wayfor DECC2 in 2023rsquos outlook the share of smart interven-tions is 23 whereas in 2050rsquos outlook the share increasesup to 69
Feasible solutions characterising the solution space(Figure 21) differ in the degree of investment required andtechnical performance evaluators Each of the solution pathrepresented in the multidimensional solution space inFigure 21 represents the intersection of that dimension witheach axis Parallel coordinates [35] are low complexityworking for any N-dimension In the case of Figure 21it has 8 dimensions treating every variable uniformlyEach intersection of one solution path with each axis isthe value of that solution for that axis As for axis DECC2and DECC4 it represents the feasible solutions for eachdemand scenario Making a query by the percentage oftraditional reinforcement used in that solution we have thepartition between orange and green for DECC2 and blueand black being the first solutions that use more traditionalreinforcement compared with the ones that use more smarttechniques represented in green (DECC2) and black(DECC4) From Figure 21 we can argue that solutions thatuse more smart techniques (green and blacks) are moreexpensive in terms of CAPEX and OPEX than their peers(orange and blues) when compared by a demand scenarioIt can also be stated that solutions with a higher use of tradi-tional reinforcements are the ones that decrease the mostCML CI and losses
Disaggregating results by network state of the six 11 kVprimaries and by the feeder if necessary for further granulardebugging can discern locational capacity Under bothdemand scenarios Secklow Gate was seen to be the one withgreater capacity being necessary to apply fewer techniquesover the evaluation period 2015ndash2047 On the other handNewport Pagnell exceeds the capacity as soon as 2015requiring a high number of network state evaluation to befixed that happens for each subsequent year hence the largenumber of network states is presented in Table 4
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
pound p
er an
num
Figure 17 CAPEX and OPEX DECC4 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
pu
Figure 18 CML and CI DECC4 2015ndash2047
14 Complexity
5 Conclusions
Power flow analysis using a nodal network model is essentialwhen determining the benefits of trailed smart interventions
because the interactions and implications are highly specificto a particular location and scenario
This suggests that while the bottom-up approach isonerous in terms of data handling and manipulation this isworthwhile for strategic planning and policy evaluationComparing both investment strategies investment strategyadjustments will be necessary in future regulation periodsif an over-invested network behaves as displayed in theshort-term section of this study
Traditional reinforcement will continue to be the mainmethod by which network issues are mostly resolvedfollowed by dynamic asset rating and meshed networks
The assessment of the six novel smart interventions in theFALCON 11kV primary test area in Milton Keynes hasproved the suitability of three techniques able to fix failuresimproving the quality of service and their readiness to bedeployed in the near future These techniques are DAR forcables and transformers and meshed networks Meshednetworks have been repeatedly selected as a feasible tech-nique because using it will reduce CML CI and power losses
Table 3 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2047
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 18 5 31 6
DAR-transformer 32 16 32 6
ALT 0 0 0 0
Mesh 8 3 6 3
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 25 44 9 16
TRAD-cable 15 29 20 66
TRAD-transfer load 1 1 1 1
TRAD-new feeder 1 2 1 2
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
s pound p
er an
num
Figure 19 CAPEX and OPEX DECC2 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
PU
Figure 20 CML and CI DECC2 2015ndash2047
15Complexity
improving the quality of service and the efficiency whilebeing a cost-effective solution
The initial capacity at primary substations differedsignificantly and this affected the number and complexityof interventions required by the SIM Due to the loadscenarios showing significant peak load increases DAR wasoften a temporary measure that would delay but not removethe eventual need for traditional reinforcement
Implementing DAR for cables and transformers themonitoring of assets when their peak capacity is increasedwas analysed On the other hand it was observed thattraditional reinforcements still play a key role in keepingthe electricity distribution networks free of constraintsTRAD techniques such as transformer and cable replace-ments are able to fix the majority of failures and will beessential also in the future
The comparison between traditional reinforcements andnovel smart techniques has provided a new knowledge aboutthe suitability of each technique to be applied in termsof costs electrical performance failures fixed and assetreplaced Cable replacement is the most costly techniquehowever its use is unavoidable in a number of cases Further-more the applicability of each technique regarding costsinvolved improvements on power quality and efficiency
and failures solved lead to new questions to be analysed suchas the lack of these techniques to provide flexible capacitywithin the trailed area
To sum up this study has performed a comparativeanalysis of novel smart intervention techniques providinginsights for future investments in electricity distributionplanning Further work can focus on scaling up the analysisto include a larger section of the network or a constrainedarea to evaluate national applicability of the current findings
Data Availability
Some of the data relevant to this submission is proprietaryfrom Western Power Distribution It can be accessed forresearch purposes under a signed collaboration agreement
Conflicts of Interest
The authors declare that they have no conflicts of interest
Acknowledgments
The authors would like to thank the rest of the WesternPower Distribution Innovation team particularly the other
2400
2200
2000
350
360
370
380
390
400
1400
1300
1200
1100
1000DECC 4
50
55
60
12
11
10
9
8
4400
4200
4000
3800
3600
2400
CAPEX (in kpound) OPEX (in kpound) Utilisation Traditional reinforcements () DECC 2 998796 CML 998796 CI 998796 Losses
2200
2000
1800
Figure 21 Parallel coordinate visualisation of technoeconomic performance indicators under DECC4 and DECC2
Table 4 Summary of network states and results for demand scenario DECC4 and DECC2
Primary 11 kV substation Feeders Year TechniquesResultsDECC4
NSDECC4
ResultsDECC2
NSDECC2
Fox Milne 13 2047 Smart and traditional 54 276 47 259
Newport Pagnell 9 2047 Smart and traditional 48 317 31 318
Secklow Gate 9 2047 Smart and traditional 27 29 15 16
Bletchley 19 2047 Smart and traditional 32 40 21 48
Marlborough Street 11 2047 Smart and traditional 31 52 19 37
Childs Way 17 2047 Smart and traditional 67 398 54 181
16 Complexity
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
where ci is CAPEX in the current year oi is OPEX in thecurrent year and cj oj and mj are CAPEX OPEX andmetrics costs respectively of the ancestor network statewith no issues in year j The heuristic estimate h x ofthe cost to reach the end year is given by
h xi = cREMi +mi + n
k=i+1ck + ok +mk 3
where cREMi is the average remaining CAPEX in the cur-rent year i mi is the average metric cost in this year ckok and mk are the average CAPEX OPEX and metriccosts respectively of the descendant network state in yeark with no issues and n is the end year of evaluation Pre-seeded to a constant value c0 the average CAPEX isupdated each time a network state is expanded in a partic-ular year thus the estimated costs of fixing all issues in aparticular year progressively approach true average Settingc0 to a value greater than 0 speeds up the expansion pro-cess ie all interventions that cost less than c0 will resultin new network states that are at the top of the priorityqueue The business rationale is that DNOs are not thatinterested in optimizing interventions costing less than acertain threshold The learned averages are propagatedback to network states in the priority queue thus updatingtheir estimated effort and leading to the reordering of thequeue unlike the average CAPEX average OPEX andmetrics costs which are assumed to be 0 for years withno network states The average OPEX value for a year isobtained using
o = jToc jT jminus1 4
where j is a column vector of ones and oc is an OPEXvector of compliant network states in that year Likewisethe average metric cost is obtained according to
m = jTmc jT jminus1 5
where j is a column vector of ones and mc is a vector ofthe metric costs of compliant network states in that year
32 Conceptualising Bottom-Up Evolutionary PlanningModel-driven engineering (MDE) uses analysis constructionand development of frameworks to formulate metamodelsThose models are usually characterised using domain-specific modelling approaches [28] containing appropriatedetail abstraction of particular domain through a specificmetamodel The use of metamodels requires therefore inputsfrom domain experts which can be used to generate aggre-gated or disaggregated models Top-down and bottom-upare the conceptual definition of aggregated and disaggregatedmodels [29] These two modelling paradigms are frequentlyused to epitomise domain interactions among the operationof the energy system the econometrics related and thetechnical performance indicators [30]
From a bottom-up modelling approach [31 32] thetop-down perspective is a simplistic characterisation ofhow electrical power networks combine locational eventsand individual asset performance with high-level objectiveslike improving the CML of a certain congested area [33 34]From an engineering point of view both are still validsince outputs and strategic forecast are produced in bothHow those outcomes are calculated validated and trans-formed to strategy is presented in Figure 7 (top-down)and Figure 8 (bottom-up)
Interventiontechnique costs
Relative usage ofinterventiontechnique
Interventiontechnique installation
details
Interventiontechnique models
Validationphysical trials
Interventiontechnique operation
details
Purchase andoperation cost data
Cost model
Network data
Representativenetworks
Model network through years
Calculate intervention technique usage
Strategic forecasts
Validationsampled nodal
networks
Demand scenarios
Figure 7 Top-down conceptualisation of evolutionary power networks planning
8 Complexity
The ability of bottom-up to capture discrete locationalimpacts of technologies on the system and their disaggre-gated costs is triggering the following subsections Trade-offmethodologies are needed for planning evolutionary powersystems where observing disaggregated result strategic fore-casts are to be produced These methodologies need to beinteractive in the sense that starting from an initial stateand after a testing or learning phase the network is able toaccommodate techniques that have improved the systemproviding an exploratory set of solutions that can beexpanded or discarded as the model evolves through time
33 Experiment Characterisation To illustrate the processingof the methodology adopted we consider a typical networkscenario tree created by the tool that consists of failed (red)and compliant (green) network states in different years ofevaluation The SIM starts with a single network state inthe first year of evaluation Every year the network isevaluated for compliance in intact and n minus 1 contingencyoperation modes If failures are detected the SIM appliesintervention techniques described in Section 2 to create net-work patches that resolve the failures Each application of anintervention technique creates a new network state The toolhas to resolve all issues in the network before transitioninginto the next year DNO planners usually run power flowstudies with a single fixed load pattern In contrast the SIMchecks each network state for compliance under 18 charac-teristic day load scenarios each comprising of 48 half-hoursettlement periods All studies are performed under intactand n minus 1 contingency network operation modes The SIM
calculates patch costs using cost drivers returned by the net-work modelling tool The cost driver describes a networkintervention and consists of two parts namely the patchkey and the scaling The patch key identifies the nature ofthe modification of the network performed (removal or addi-tion of an asset and the type of the asset) Scaling data is rel-evant only to patches that can be installed in multiples of onesuch as cable upgrades and additional transformer installa-tion Scaling data structure provides a list of multipliers tothe base cost data available in the SIM database In case ofcable upgrade or replacement it enables the SIM to correctlyestimate full installation costs from per unit of length valuesFinally for postprocessing analysis the SIM also returns a listof failures by asset It was identified by DNO planners asindispensable features to help validate the system and corre-late the expansion trees to the actual assets on the networkdiagram The failure detail table contains asset ID anddescription alongside information about the number of fail-ures in intact and n minus 1 operating modes as well as absoluteand per unit thermal and voltage failure magnitude
34 Case Characterisation Two set of experiments wereperformed for this study one for comparing short-termevaluation period for RIIO-ED1 (2015ndash2023) where theRIIO-ED1 investment planning has been stylised and alonger planning period for RIIO-ED1 to RIIO-ED4 from2015 up to 2047 The other set aimed at evaluating differ-ent DECC demand scenarios Experiments evaluated twodemand scenarios DECC2 and DECC4 DECC4 representsas displayed in Table 1 the slow-progression scenario and
Purchase andoperation cost data
Cost model Nodal network model
Model network through years
Apply intervention technique to keep the network compilant
Find optimal network development options
Solutions for individual networks
Aggregate results for larger network areas
Strategic forecasts
Network data Demand scenarios
Interventiontechnique costs
Interventiontechnique installation
details
Nodal interventiontechnique models
Validation withphysical trials
Relative usage ofinterventiontechniques
Validation of powerflow and reliability
models
Interventiontechnique operation
details
Load profiles
Figure 8 Bottom-up conceptualisation of evolutionary power networks planning
9Complexity
DECC2 is with DECC3 the most challenging scenario interms of electrification and low-carbon technology integra-tion The procedure to run the experiments in the SIM isshown in Figure 6 The inputs to be sent to the SIM aredetailed in Figure 5 the selected network techniques evalu-ation period demand scenario and cost model whereas theoutputs of the SIM we obtain are techniques used failuressolved assets fixed and electrical performance indicatorsThe SIM address mentioned outputs for long-term plan-ning reinforcements to optimise investment asset planningresolving network constraints The performance criteria eval-uated were capital expenditures (CAPEX) operating expen-ditures (OPEX) utilisation of assets CMLs CIs and lossesThese parameter values are delivered by the SIM after eachsimulation In order to look for the optimal solution amongthe feasible solution pathways the SIM allows a granularitystudy of each network state
4 Results
This section presents the assessment of the six smart gridinterventions along with traditional reinforcements in thetrial area compounded by six 11 kV primaries in MiltonKeynes UK for two different evaluation periods DECC2and DECC4 Subsection 41 introduces the results for the2015ndash2023 period as short-term planning and Subsection42 presents the results for a long-term evaluation period2015ndash2047
41 Short-Term Planning This section presents the assess-ment of the six smart grid interventions along with tradi-tional reinforcements in the trial area compounded by six11 kV primaries in Milton Keynes UK for two differentdemand scenarios DECC2 and DECC4
411 DECC4 2015ndash2023 Figure 9 shows the trends ofCAPEX and OPEX Note that in the year 2015 there is aCAPEXrsquos peak due to the application of more techniquesand OPEX increments over time from 2017 to 2023
Despite the investment the increase is compensated bya benefit in the electricity distribution network with areduction in CML and CI as shown in Figure 10
The summary of the proportion of installations requiredduring this evaluation period and by capital expenditures pertechnique is presented in Table 2 for both DECC scenarios
The average yearly price of each technique implementedto fix a network state is key for future decision-makingconsiderations
Figure 11 displays the average price of each techniquedisaggregated by CAPEX and OPEX
Performance indicators are key parameters for futuredecision-making within electricity distribution planning asquantifiers due to their influence on the quality of service
Therefore as shown in Figure 12 the only smart tech-nique used in combination with traditional reinforcementsin this scenario and evaluation period that slightly influenceslightly CML and CI is meshed networks
412 DECC2 2015ndash2023 Figure 13 plots the trend ofCAPEX and OPEX over the evaluation period It is important
to highlight that there is a CAPEX peak in 2015 due to anincrease of techniques applied in this period
This CAPEX increment produces a benefit in terms ofCML and CI as observed in Figure 14
The distribution of techniques applied and capital expen-ditures per technique are shown in Table 2 The average priceof each technique implementation in this demand scenariofor this evaluation period is shown in Figure 15
As displayed in Figure 12 for DECC4rsquos simulation theonly smart grid technique that improves the quality of serviceis the meshed network In Figure 16 the contribution ofsmart techniques on CML and CI for DECC2 demandevaluation is captured
413 Comparison between DECC2 and DECC4 for 2015ndash2023 The results presented may facilitate improvementsin electricity distribution network operations and planningresulting in better-informed decision-making when upgrad-ing current electricity distribution networks The assess-ment of the six smart grid techniques discovered thatonly three of them were selected as part of optimal
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
Mill
ions
pound p
er an
num
CAPEXOPEX
442444648
55254
Figure 9 CAPEX and OPEX DECC4 2015ndash2023
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
pu
Figure 10 CML and CI DECC4 2015ndash2023
10 Complexity
solutions for DECC4 and DECC2 as described in Table 2These three techniques applied are DAR for cables andtransformers and meshed networks
Comparing the cost trends of the two assessed scenariosit is notable that in both demand scenarios DECC4 and
DECC2 the CAPEX peak occurs in 2015 (Figures 9 and13) reflecting the more difficult nature of network statesto be feasible in a demanding scenario whereas DECC2shows a higher improvement of CI and CML performanceindicators as can be seen in Figures 10 and 14
Table 2 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2023
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 15 2 14 2
DAR-transformer 7 1 5 1
ALT 0 0 0 0
Mesh 3 1 4 1
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 8 3 7 2
TRAD-cable 60 89 65 91
TRAD-transfer load 6 2 4 1
TRAD-new feeder 1 2 1 2
DAR - cable DAR -transformer
Meshednetworks
TRAD -transformer
TRAD - cable
CAPEXOPEX
0
20000
40000
60000
80000
100000
pound
Figure 11 Average cost disaggregation per technique DECC4 2015ndash2023
Figure 12 Average CML and CI improvement per technique DECC4 2015ndash2023
11Complexity
The techniques applied are the key consideration to beassessed It is necessary to analyse the number of interven-tions applied by type the effect of these techniques in theelectric grid solving failures and fixing assets Figures 11and 15 show average prices of techniques used in eachdemand scenario Smart techniques have a lower TOTEXthan traditional reinforcements These novel techniquesabove are not frequently able to fix failures and thereforeproduce feasible network states In terms of CML and CIthe only technique able to moderately contribute to theirimprovement is meshed networks as shown in Figures 12and 16 Results attribute the majority of fixes to traditionalreinforcements with a comparatively smaller number offailures being solved by smart techniques (Table 2) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention forDECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
For DECC4 the three mentioned techniques along withtraditional cable and transformer replacement are applied(Table 2) whereas for DECC2 two of them are appliedDAR for cables and meshed networks (Table 2) Comparingthe cost trends of the two assessed scenarios it is notable thatin DECC4 the CAPEX peak occurs in 2015 (Figure 7)whereas in DECC2 besides the peak in 2015 there is alsoone in 2019 (Figure 11) reflecting the more difficult natureof network states to be feasible in a demanding scenarioHowever DECC2 shows a higher improvement of electricalperformance indicators as can be seen in Figure 12
In addition traditional cable replacement DAR forcables and meshed networks are able to fix the cable whereastraditional transformer replacement and DAR for trans-formers are able to fix transformer issues (Figure 16) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention for
DECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
42 Long-Term Planning This section evaluates two experi-ments namely characterising the DECC2 and DECC4 sce-narios for 2015ndash2047 evaluation period For each demandscenario expected investments disaggregating CAPEX andOPEX are presented the evolution of electrical performanceindicators and the number of techniques applied
421 DECC4 2015ndash2047 In this experiment the mostsignificant results to analyse the suitability of each techniqueare presented
Figure 17 shows the trend of CAPEX and OPEX from2015 to 2047
There are CAPEX peaks in the year 2018 and during thebeginning of RIIO-ED2 in the years 2025 to 2026 due to theapplication of more techniques to fulfill low-carbon targets
Figure 18 indicates that upgrades on the network aredirectly related to technical performance indicators CMLand CI
In Table 3 the techniques applied and their contributionto CAPEX during the evaluation period from 2015 to 2047 bya demand scenario are shown
422 DECC2 2015ndash2047 Within this experiment the mostrelevant results to analyse the evolutionary network statesare presented
In Figure 19 the trend of CAPEX and OPEX from 2015to 2047 is shown There is a significant increase of CAPEXin the years 2024 to 2026 at the beginning of RIIO-ED2due to the necessary implementation of new techniques toreach low-carbon targets The evolution of CML and CI ispresented in Figure 20 linking larger investment years whenmajor reductions are found The contribution of each solutiontechnique is presented in Table 3
423 Comparison between DECC2 and DECC4 for 2015ndash2047 Figure 21 presents a multidimensional parallel coor-dinate representation of the feasible network statersquoscombinations that produced a 2015ndash2047 investment path-way for the evaluated area It bundles economic indicatorsie CAPEX and OPEX with technical performance indica-tors providing valuable insights on the number of traditionalreinforcements utilised to heal falling network states Resultsare also clustered by the two demand scenarios assessedduring the experiments
Solutions of DECC2 (represented in orange and green)and DECC4 (in black and blue) are clustered by the per-centage of traditional reinforcements utilised as well asthe utilisation factor
Solutions in green and in black represent those wheresmart grids were more used whereas orange and blue repre-sent the cheapest (CAPEX and OPEX) less utilised and theworst responding to the decrease of CML CI and lossesand the ones using more traditional reinforcement to fixnetwork states
Besides the fact that DECC2 smart solutions are between16 and 28 more expensive than DECC4 traditional
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
CAPEXOPEX
442444648
552
Mill
ions
pound p
er an
num
54
Figure 13 CAPEX and OPEX DECC2 2015ndash2023
12 Complexity
reinforcement solutions (green solutions versus blue solu-tions in Figure 21) DECC2 traditional solutions are in therange of costs of smart solutions of DECC4 (orange andblack solutions in Figure 21) It can also be concluded thatinvestment pathways using less smart techniques provide a
cheaper response to technical performance evaluators suchas utilisation CML CI and losses
43 Summary Experiment evaluation runs from the2015ndash2047 period present lower investment rates for the
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
PU
Figure 14 CML and CI DECC2 2015ndash2023
CAPEXOPEX
DAR -transformer
Meshednetworks
Traditional -transformer
Traditional -cable
0
20000
40000
60000
80000
100000
120000
140000
pound
Figure 15 Average cost disaggregation per technique DECC2 2015ndash2023
Figure 16 Average CML and CI improvement per technique DECC2 2015ndash2023
13Complexity
2015ndash2023 period than if the evaluation is just performedwith a 2015ndash2023 time frame This occurs as a result of thechallenging low-carbon targets up to 2047 and a myopicplanning with short-term lookahead For an evaluationperiod four times larger the CAPEX and TOTEX increasedjust 18 compared to 2015ndash2023 concluding that betweenpound52M and pound68M the evaluation area regardless of thetime horizon for the investment or the demand scenarioconsidered is required
Furthermore it can be inferred comparing Tables 2 and 3that for less smart interventions the short-term planningis used compared to the long-term horizon planningDAR-cable and DAR-transformer experienced a significantimplementation variation between the two evaluationperiods for both demand scenarios as well as CAPEX allo-cated in cable upgrades falling from 89ndash91 (2015ndash2023)to 29ndash66 in the long term 2015ndash2047 run Both technicalperformance evaluators CML and CI respond to theirrespective CAPEX curve shape Due to a more incentivisedsmart grid technique during RIIO-ED2 and ED3 the per-centages of smart techniques implemented varied notablyFor DECC4 in 2023rsquos outlook the share of techniques is
25 for smart grid interventions whereas for 2050rsquos out-look the share is increased up to 58 In the same wayfor DECC2 in 2023rsquos outlook the share of smart interven-tions is 23 whereas in 2050rsquos outlook the share increasesup to 69
Feasible solutions characterising the solution space(Figure 21) differ in the degree of investment required andtechnical performance evaluators Each of the solution pathrepresented in the multidimensional solution space inFigure 21 represents the intersection of that dimension witheach axis Parallel coordinates [35] are low complexityworking for any N-dimension In the case of Figure 21it has 8 dimensions treating every variable uniformlyEach intersection of one solution path with each axis isthe value of that solution for that axis As for axis DECC2and DECC4 it represents the feasible solutions for eachdemand scenario Making a query by the percentage oftraditional reinforcement used in that solution we have thepartition between orange and green for DECC2 and blueand black being the first solutions that use more traditionalreinforcement compared with the ones that use more smarttechniques represented in green (DECC2) and black(DECC4) From Figure 21 we can argue that solutions thatuse more smart techniques (green and blacks) are moreexpensive in terms of CAPEX and OPEX than their peers(orange and blues) when compared by a demand scenarioIt can also be stated that solutions with a higher use of tradi-tional reinforcements are the ones that decrease the mostCML CI and losses
Disaggregating results by network state of the six 11 kVprimaries and by the feeder if necessary for further granulardebugging can discern locational capacity Under bothdemand scenarios Secklow Gate was seen to be the one withgreater capacity being necessary to apply fewer techniquesover the evaluation period 2015ndash2047 On the other handNewport Pagnell exceeds the capacity as soon as 2015requiring a high number of network state evaluation to befixed that happens for each subsequent year hence the largenumber of network states is presented in Table 4
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
pound p
er an
num
Figure 17 CAPEX and OPEX DECC4 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
pu
Figure 18 CML and CI DECC4 2015ndash2047
14 Complexity
5 Conclusions
Power flow analysis using a nodal network model is essentialwhen determining the benefits of trailed smart interventions
because the interactions and implications are highly specificto a particular location and scenario
This suggests that while the bottom-up approach isonerous in terms of data handling and manipulation this isworthwhile for strategic planning and policy evaluationComparing both investment strategies investment strategyadjustments will be necessary in future regulation periodsif an over-invested network behaves as displayed in theshort-term section of this study
Traditional reinforcement will continue to be the mainmethod by which network issues are mostly resolvedfollowed by dynamic asset rating and meshed networks
The assessment of the six novel smart interventions in theFALCON 11kV primary test area in Milton Keynes hasproved the suitability of three techniques able to fix failuresimproving the quality of service and their readiness to bedeployed in the near future These techniques are DAR forcables and transformers and meshed networks Meshednetworks have been repeatedly selected as a feasible tech-nique because using it will reduce CML CI and power losses
Table 3 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2047
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 18 5 31 6
DAR-transformer 32 16 32 6
ALT 0 0 0 0
Mesh 8 3 6 3
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 25 44 9 16
TRAD-cable 15 29 20 66
TRAD-transfer load 1 1 1 1
TRAD-new feeder 1 2 1 2
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
s pound p
er an
num
Figure 19 CAPEX and OPEX DECC2 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
PU
Figure 20 CML and CI DECC2 2015ndash2047
15Complexity
improving the quality of service and the efficiency whilebeing a cost-effective solution
The initial capacity at primary substations differedsignificantly and this affected the number and complexityof interventions required by the SIM Due to the loadscenarios showing significant peak load increases DAR wasoften a temporary measure that would delay but not removethe eventual need for traditional reinforcement
Implementing DAR for cables and transformers themonitoring of assets when their peak capacity is increasedwas analysed On the other hand it was observed thattraditional reinforcements still play a key role in keepingthe electricity distribution networks free of constraintsTRAD techniques such as transformer and cable replace-ments are able to fix the majority of failures and will beessential also in the future
The comparison between traditional reinforcements andnovel smart techniques has provided a new knowledge aboutthe suitability of each technique to be applied in termsof costs electrical performance failures fixed and assetreplaced Cable replacement is the most costly techniquehowever its use is unavoidable in a number of cases Further-more the applicability of each technique regarding costsinvolved improvements on power quality and efficiency
and failures solved lead to new questions to be analysed suchas the lack of these techniques to provide flexible capacitywithin the trailed area
To sum up this study has performed a comparativeanalysis of novel smart intervention techniques providinginsights for future investments in electricity distributionplanning Further work can focus on scaling up the analysisto include a larger section of the network or a constrainedarea to evaluate national applicability of the current findings
Data Availability
Some of the data relevant to this submission is proprietaryfrom Western Power Distribution It can be accessed forresearch purposes under a signed collaboration agreement
Conflicts of Interest
The authors declare that they have no conflicts of interest
Acknowledgments
The authors would like to thank the rest of the WesternPower Distribution Innovation team particularly the other
2400
2200
2000
350
360
370
380
390
400
1400
1300
1200
1100
1000DECC 4
50
55
60
12
11
10
9
8
4400
4200
4000
3800
3600
2400
CAPEX (in kpound) OPEX (in kpound) Utilisation Traditional reinforcements () DECC 2 998796 CML 998796 CI 998796 Losses
2200
2000
1800
Figure 21 Parallel coordinate visualisation of technoeconomic performance indicators under DECC4 and DECC2
Table 4 Summary of network states and results for demand scenario DECC4 and DECC2
Primary 11 kV substation Feeders Year TechniquesResultsDECC4
NSDECC4
ResultsDECC2
NSDECC2
Fox Milne 13 2047 Smart and traditional 54 276 47 259
Newport Pagnell 9 2047 Smart and traditional 48 317 31 318
Secklow Gate 9 2047 Smart and traditional 27 29 15 16
Bletchley 19 2047 Smart and traditional 32 40 21 48
Marlborough Street 11 2047 Smart and traditional 31 52 19 37
Childs Way 17 2047 Smart and traditional 67 398 54 181
16 Complexity
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
The ability of bottom-up to capture discrete locationalimpacts of technologies on the system and their disaggre-gated costs is triggering the following subsections Trade-offmethodologies are needed for planning evolutionary powersystems where observing disaggregated result strategic fore-casts are to be produced These methodologies need to beinteractive in the sense that starting from an initial stateand after a testing or learning phase the network is able toaccommodate techniques that have improved the systemproviding an exploratory set of solutions that can beexpanded or discarded as the model evolves through time
33 Experiment Characterisation To illustrate the processingof the methodology adopted we consider a typical networkscenario tree created by the tool that consists of failed (red)and compliant (green) network states in different years ofevaluation The SIM starts with a single network state inthe first year of evaluation Every year the network isevaluated for compliance in intact and n minus 1 contingencyoperation modes If failures are detected the SIM appliesintervention techniques described in Section 2 to create net-work patches that resolve the failures Each application of anintervention technique creates a new network state The toolhas to resolve all issues in the network before transitioninginto the next year DNO planners usually run power flowstudies with a single fixed load pattern In contrast the SIMchecks each network state for compliance under 18 charac-teristic day load scenarios each comprising of 48 half-hoursettlement periods All studies are performed under intactand n minus 1 contingency network operation modes The SIM
calculates patch costs using cost drivers returned by the net-work modelling tool The cost driver describes a networkintervention and consists of two parts namely the patchkey and the scaling The patch key identifies the nature ofthe modification of the network performed (removal or addi-tion of an asset and the type of the asset) Scaling data is rel-evant only to patches that can be installed in multiples of onesuch as cable upgrades and additional transformer installa-tion Scaling data structure provides a list of multipliers tothe base cost data available in the SIM database In case ofcable upgrade or replacement it enables the SIM to correctlyestimate full installation costs from per unit of length valuesFinally for postprocessing analysis the SIM also returns a listof failures by asset It was identified by DNO planners asindispensable features to help validate the system and corre-late the expansion trees to the actual assets on the networkdiagram The failure detail table contains asset ID anddescription alongside information about the number of fail-ures in intact and n minus 1 operating modes as well as absoluteand per unit thermal and voltage failure magnitude
34 Case Characterisation Two set of experiments wereperformed for this study one for comparing short-termevaluation period for RIIO-ED1 (2015ndash2023) where theRIIO-ED1 investment planning has been stylised and alonger planning period for RIIO-ED1 to RIIO-ED4 from2015 up to 2047 The other set aimed at evaluating differ-ent DECC demand scenarios Experiments evaluated twodemand scenarios DECC2 and DECC4 DECC4 representsas displayed in Table 1 the slow-progression scenario and
Purchase andoperation cost data
Cost model Nodal network model
Model network through years
Apply intervention technique to keep the network compilant
Find optimal network development options
Solutions for individual networks
Aggregate results for larger network areas
Strategic forecasts
Network data Demand scenarios
Interventiontechnique costs
Interventiontechnique installation
details
Nodal interventiontechnique models
Validation withphysical trials
Relative usage ofinterventiontechniques
Validation of powerflow and reliability
models
Interventiontechnique operation
details
Load profiles
Figure 8 Bottom-up conceptualisation of evolutionary power networks planning
9Complexity
DECC2 is with DECC3 the most challenging scenario interms of electrification and low-carbon technology integra-tion The procedure to run the experiments in the SIM isshown in Figure 6 The inputs to be sent to the SIM aredetailed in Figure 5 the selected network techniques evalu-ation period demand scenario and cost model whereas theoutputs of the SIM we obtain are techniques used failuressolved assets fixed and electrical performance indicatorsThe SIM address mentioned outputs for long-term plan-ning reinforcements to optimise investment asset planningresolving network constraints The performance criteria eval-uated were capital expenditures (CAPEX) operating expen-ditures (OPEX) utilisation of assets CMLs CIs and lossesThese parameter values are delivered by the SIM after eachsimulation In order to look for the optimal solution amongthe feasible solution pathways the SIM allows a granularitystudy of each network state
4 Results
This section presents the assessment of the six smart gridinterventions along with traditional reinforcements in thetrial area compounded by six 11 kV primaries in MiltonKeynes UK for two different evaluation periods DECC2and DECC4 Subsection 41 introduces the results for the2015ndash2023 period as short-term planning and Subsection42 presents the results for a long-term evaluation period2015ndash2047
41 Short-Term Planning This section presents the assess-ment of the six smart grid interventions along with tradi-tional reinforcements in the trial area compounded by six11 kV primaries in Milton Keynes UK for two differentdemand scenarios DECC2 and DECC4
411 DECC4 2015ndash2023 Figure 9 shows the trends ofCAPEX and OPEX Note that in the year 2015 there is aCAPEXrsquos peak due to the application of more techniquesand OPEX increments over time from 2017 to 2023
Despite the investment the increase is compensated bya benefit in the electricity distribution network with areduction in CML and CI as shown in Figure 10
The summary of the proportion of installations requiredduring this evaluation period and by capital expenditures pertechnique is presented in Table 2 for both DECC scenarios
The average yearly price of each technique implementedto fix a network state is key for future decision-makingconsiderations
Figure 11 displays the average price of each techniquedisaggregated by CAPEX and OPEX
Performance indicators are key parameters for futuredecision-making within electricity distribution planning asquantifiers due to their influence on the quality of service
Therefore as shown in Figure 12 the only smart tech-nique used in combination with traditional reinforcementsin this scenario and evaluation period that slightly influenceslightly CML and CI is meshed networks
412 DECC2 2015ndash2023 Figure 13 plots the trend ofCAPEX and OPEX over the evaluation period It is important
to highlight that there is a CAPEX peak in 2015 due to anincrease of techniques applied in this period
This CAPEX increment produces a benefit in terms ofCML and CI as observed in Figure 14
The distribution of techniques applied and capital expen-ditures per technique are shown in Table 2 The average priceof each technique implementation in this demand scenariofor this evaluation period is shown in Figure 15
As displayed in Figure 12 for DECC4rsquos simulation theonly smart grid technique that improves the quality of serviceis the meshed network In Figure 16 the contribution ofsmart techniques on CML and CI for DECC2 demandevaluation is captured
413 Comparison between DECC2 and DECC4 for 2015ndash2023 The results presented may facilitate improvementsin electricity distribution network operations and planningresulting in better-informed decision-making when upgrad-ing current electricity distribution networks The assess-ment of the six smart grid techniques discovered thatonly three of them were selected as part of optimal
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
Mill
ions
pound p
er an
num
CAPEXOPEX
442444648
55254
Figure 9 CAPEX and OPEX DECC4 2015ndash2023
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
pu
Figure 10 CML and CI DECC4 2015ndash2023
10 Complexity
solutions for DECC4 and DECC2 as described in Table 2These three techniques applied are DAR for cables andtransformers and meshed networks
Comparing the cost trends of the two assessed scenariosit is notable that in both demand scenarios DECC4 and
DECC2 the CAPEX peak occurs in 2015 (Figures 9 and13) reflecting the more difficult nature of network statesto be feasible in a demanding scenario whereas DECC2shows a higher improvement of CI and CML performanceindicators as can be seen in Figures 10 and 14
Table 2 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2023
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 15 2 14 2
DAR-transformer 7 1 5 1
ALT 0 0 0 0
Mesh 3 1 4 1
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 8 3 7 2
TRAD-cable 60 89 65 91
TRAD-transfer load 6 2 4 1
TRAD-new feeder 1 2 1 2
DAR - cable DAR -transformer
Meshednetworks
TRAD -transformer
TRAD - cable
CAPEXOPEX
0
20000
40000
60000
80000
100000
pound
Figure 11 Average cost disaggregation per technique DECC4 2015ndash2023
Figure 12 Average CML and CI improvement per technique DECC4 2015ndash2023
11Complexity
The techniques applied are the key consideration to beassessed It is necessary to analyse the number of interven-tions applied by type the effect of these techniques in theelectric grid solving failures and fixing assets Figures 11and 15 show average prices of techniques used in eachdemand scenario Smart techniques have a lower TOTEXthan traditional reinforcements These novel techniquesabove are not frequently able to fix failures and thereforeproduce feasible network states In terms of CML and CIthe only technique able to moderately contribute to theirimprovement is meshed networks as shown in Figures 12and 16 Results attribute the majority of fixes to traditionalreinforcements with a comparatively smaller number offailures being solved by smart techniques (Table 2) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention forDECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
For DECC4 the three mentioned techniques along withtraditional cable and transformer replacement are applied(Table 2) whereas for DECC2 two of them are appliedDAR for cables and meshed networks (Table 2) Comparingthe cost trends of the two assessed scenarios it is notable thatin DECC4 the CAPEX peak occurs in 2015 (Figure 7)whereas in DECC2 besides the peak in 2015 there is alsoone in 2019 (Figure 11) reflecting the more difficult natureof network states to be feasible in a demanding scenarioHowever DECC2 shows a higher improvement of electricalperformance indicators as can be seen in Figure 12
In addition traditional cable replacement DAR forcables and meshed networks are able to fix the cable whereastraditional transformer replacement and DAR for trans-formers are able to fix transformer issues (Figure 16) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention for
DECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
42 Long-Term Planning This section evaluates two experi-ments namely characterising the DECC2 and DECC4 sce-narios for 2015ndash2047 evaluation period For each demandscenario expected investments disaggregating CAPEX andOPEX are presented the evolution of electrical performanceindicators and the number of techniques applied
421 DECC4 2015ndash2047 In this experiment the mostsignificant results to analyse the suitability of each techniqueare presented
Figure 17 shows the trend of CAPEX and OPEX from2015 to 2047
There are CAPEX peaks in the year 2018 and during thebeginning of RIIO-ED2 in the years 2025 to 2026 due to theapplication of more techniques to fulfill low-carbon targets
Figure 18 indicates that upgrades on the network aredirectly related to technical performance indicators CMLand CI
In Table 3 the techniques applied and their contributionto CAPEX during the evaluation period from 2015 to 2047 bya demand scenario are shown
422 DECC2 2015ndash2047 Within this experiment the mostrelevant results to analyse the evolutionary network statesare presented
In Figure 19 the trend of CAPEX and OPEX from 2015to 2047 is shown There is a significant increase of CAPEXin the years 2024 to 2026 at the beginning of RIIO-ED2due to the necessary implementation of new techniques toreach low-carbon targets The evolution of CML and CI ispresented in Figure 20 linking larger investment years whenmajor reductions are found The contribution of each solutiontechnique is presented in Table 3
423 Comparison between DECC2 and DECC4 for 2015ndash2047 Figure 21 presents a multidimensional parallel coor-dinate representation of the feasible network statersquoscombinations that produced a 2015ndash2047 investment path-way for the evaluated area It bundles economic indicatorsie CAPEX and OPEX with technical performance indica-tors providing valuable insights on the number of traditionalreinforcements utilised to heal falling network states Resultsare also clustered by the two demand scenarios assessedduring the experiments
Solutions of DECC2 (represented in orange and green)and DECC4 (in black and blue) are clustered by the per-centage of traditional reinforcements utilised as well asthe utilisation factor
Solutions in green and in black represent those wheresmart grids were more used whereas orange and blue repre-sent the cheapest (CAPEX and OPEX) less utilised and theworst responding to the decrease of CML CI and lossesand the ones using more traditional reinforcement to fixnetwork states
Besides the fact that DECC2 smart solutions are between16 and 28 more expensive than DECC4 traditional
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
CAPEXOPEX
442444648
552
Mill
ions
pound p
er an
num
54
Figure 13 CAPEX and OPEX DECC2 2015ndash2023
12 Complexity
reinforcement solutions (green solutions versus blue solu-tions in Figure 21) DECC2 traditional solutions are in therange of costs of smart solutions of DECC4 (orange andblack solutions in Figure 21) It can also be concluded thatinvestment pathways using less smart techniques provide a
cheaper response to technical performance evaluators suchas utilisation CML CI and losses
43 Summary Experiment evaluation runs from the2015ndash2047 period present lower investment rates for the
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
PU
Figure 14 CML and CI DECC2 2015ndash2023
CAPEXOPEX
DAR -transformer
Meshednetworks
Traditional -transformer
Traditional -cable
0
20000
40000
60000
80000
100000
120000
140000
pound
Figure 15 Average cost disaggregation per technique DECC2 2015ndash2023
Figure 16 Average CML and CI improvement per technique DECC2 2015ndash2023
13Complexity
2015ndash2023 period than if the evaluation is just performedwith a 2015ndash2023 time frame This occurs as a result of thechallenging low-carbon targets up to 2047 and a myopicplanning with short-term lookahead For an evaluationperiod four times larger the CAPEX and TOTEX increasedjust 18 compared to 2015ndash2023 concluding that betweenpound52M and pound68M the evaluation area regardless of thetime horizon for the investment or the demand scenarioconsidered is required
Furthermore it can be inferred comparing Tables 2 and 3that for less smart interventions the short-term planningis used compared to the long-term horizon planningDAR-cable and DAR-transformer experienced a significantimplementation variation between the two evaluationperiods for both demand scenarios as well as CAPEX allo-cated in cable upgrades falling from 89ndash91 (2015ndash2023)to 29ndash66 in the long term 2015ndash2047 run Both technicalperformance evaluators CML and CI respond to theirrespective CAPEX curve shape Due to a more incentivisedsmart grid technique during RIIO-ED2 and ED3 the per-centages of smart techniques implemented varied notablyFor DECC4 in 2023rsquos outlook the share of techniques is
25 for smart grid interventions whereas for 2050rsquos out-look the share is increased up to 58 In the same wayfor DECC2 in 2023rsquos outlook the share of smart interven-tions is 23 whereas in 2050rsquos outlook the share increasesup to 69
Feasible solutions characterising the solution space(Figure 21) differ in the degree of investment required andtechnical performance evaluators Each of the solution pathrepresented in the multidimensional solution space inFigure 21 represents the intersection of that dimension witheach axis Parallel coordinates [35] are low complexityworking for any N-dimension In the case of Figure 21it has 8 dimensions treating every variable uniformlyEach intersection of one solution path with each axis isthe value of that solution for that axis As for axis DECC2and DECC4 it represents the feasible solutions for eachdemand scenario Making a query by the percentage oftraditional reinforcement used in that solution we have thepartition between orange and green for DECC2 and blueand black being the first solutions that use more traditionalreinforcement compared with the ones that use more smarttechniques represented in green (DECC2) and black(DECC4) From Figure 21 we can argue that solutions thatuse more smart techniques (green and blacks) are moreexpensive in terms of CAPEX and OPEX than their peers(orange and blues) when compared by a demand scenarioIt can also be stated that solutions with a higher use of tradi-tional reinforcements are the ones that decrease the mostCML CI and losses
Disaggregating results by network state of the six 11 kVprimaries and by the feeder if necessary for further granulardebugging can discern locational capacity Under bothdemand scenarios Secklow Gate was seen to be the one withgreater capacity being necessary to apply fewer techniquesover the evaluation period 2015ndash2047 On the other handNewport Pagnell exceeds the capacity as soon as 2015requiring a high number of network state evaluation to befixed that happens for each subsequent year hence the largenumber of network states is presented in Table 4
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
pound p
er an
num
Figure 17 CAPEX and OPEX DECC4 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
pu
Figure 18 CML and CI DECC4 2015ndash2047
14 Complexity
5 Conclusions
Power flow analysis using a nodal network model is essentialwhen determining the benefits of trailed smart interventions
because the interactions and implications are highly specificto a particular location and scenario
This suggests that while the bottom-up approach isonerous in terms of data handling and manipulation this isworthwhile for strategic planning and policy evaluationComparing both investment strategies investment strategyadjustments will be necessary in future regulation periodsif an over-invested network behaves as displayed in theshort-term section of this study
Traditional reinforcement will continue to be the mainmethod by which network issues are mostly resolvedfollowed by dynamic asset rating and meshed networks
The assessment of the six novel smart interventions in theFALCON 11kV primary test area in Milton Keynes hasproved the suitability of three techniques able to fix failuresimproving the quality of service and their readiness to bedeployed in the near future These techniques are DAR forcables and transformers and meshed networks Meshednetworks have been repeatedly selected as a feasible tech-nique because using it will reduce CML CI and power losses
Table 3 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2047
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 18 5 31 6
DAR-transformer 32 16 32 6
ALT 0 0 0 0
Mesh 8 3 6 3
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 25 44 9 16
TRAD-cable 15 29 20 66
TRAD-transfer load 1 1 1 1
TRAD-new feeder 1 2 1 2
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
s pound p
er an
num
Figure 19 CAPEX and OPEX DECC2 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
PU
Figure 20 CML and CI DECC2 2015ndash2047
15Complexity
improving the quality of service and the efficiency whilebeing a cost-effective solution
The initial capacity at primary substations differedsignificantly and this affected the number and complexityof interventions required by the SIM Due to the loadscenarios showing significant peak load increases DAR wasoften a temporary measure that would delay but not removethe eventual need for traditional reinforcement
Implementing DAR for cables and transformers themonitoring of assets when their peak capacity is increasedwas analysed On the other hand it was observed thattraditional reinforcements still play a key role in keepingthe electricity distribution networks free of constraintsTRAD techniques such as transformer and cable replace-ments are able to fix the majority of failures and will beessential also in the future
The comparison between traditional reinforcements andnovel smart techniques has provided a new knowledge aboutthe suitability of each technique to be applied in termsof costs electrical performance failures fixed and assetreplaced Cable replacement is the most costly techniquehowever its use is unavoidable in a number of cases Further-more the applicability of each technique regarding costsinvolved improvements on power quality and efficiency
and failures solved lead to new questions to be analysed suchas the lack of these techniques to provide flexible capacitywithin the trailed area
To sum up this study has performed a comparativeanalysis of novel smart intervention techniques providinginsights for future investments in electricity distributionplanning Further work can focus on scaling up the analysisto include a larger section of the network or a constrainedarea to evaluate national applicability of the current findings
Data Availability
Some of the data relevant to this submission is proprietaryfrom Western Power Distribution It can be accessed forresearch purposes under a signed collaboration agreement
Conflicts of Interest
The authors declare that they have no conflicts of interest
Acknowledgments
The authors would like to thank the rest of the WesternPower Distribution Innovation team particularly the other
2400
2200
2000
350
360
370
380
390
400
1400
1300
1200
1100
1000DECC 4
50
55
60
12
11
10
9
8
4400
4200
4000
3800
3600
2400
CAPEX (in kpound) OPEX (in kpound) Utilisation Traditional reinforcements () DECC 2 998796 CML 998796 CI 998796 Losses
2200
2000
1800
Figure 21 Parallel coordinate visualisation of technoeconomic performance indicators under DECC4 and DECC2
Table 4 Summary of network states and results for demand scenario DECC4 and DECC2
Primary 11 kV substation Feeders Year TechniquesResultsDECC4
NSDECC4
ResultsDECC2
NSDECC2
Fox Milne 13 2047 Smart and traditional 54 276 47 259
Newport Pagnell 9 2047 Smart and traditional 48 317 31 318
Secklow Gate 9 2047 Smart and traditional 27 29 15 16
Bletchley 19 2047 Smart and traditional 32 40 21 48
Marlborough Street 11 2047 Smart and traditional 31 52 19 37
Childs Way 17 2047 Smart and traditional 67 398 54 181
16 Complexity
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
DECC2 is with DECC3 the most challenging scenario interms of electrification and low-carbon technology integra-tion The procedure to run the experiments in the SIM isshown in Figure 6 The inputs to be sent to the SIM aredetailed in Figure 5 the selected network techniques evalu-ation period demand scenario and cost model whereas theoutputs of the SIM we obtain are techniques used failuressolved assets fixed and electrical performance indicatorsThe SIM address mentioned outputs for long-term plan-ning reinforcements to optimise investment asset planningresolving network constraints The performance criteria eval-uated were capital expenditures (CAPEX) operating expen-ditures (OPEX) utilisation of assets CMLs CIs and lossesThese parameter values are delivered by the SIM after eachsimulation In order to look for the optimal solution amongthe feasible solution pathways the SIM allows a granularitystudy of each network state
4 Results
This section presents the assessment of the six smart gridinterventions along with traditional reinforcements in thetrial area compounded by six 11 kV primaries in MiltonKeynes UK for two different evaluation periods DECC2and DECC4 Subsection 41 introduces the results for the2015ndash2023 period as short-term planning and Subsection42 presents the results for a long-term evaluation period2015ndash2047
41 Short-Term Planning This section presents the assess-ment of the six smart grid interventions along with tradi-tional reinforcements in the trial area compounded by six11 kV primaries in Milton Keynes UK for two differentdemand scenarios DECC2 and DECC4
411 DECC4 2015ndash2023 Figure 9 shows the trends ofCAPEX and OPEX Note that in the year 2015 there is aCAPEXrsquos peak due to the application of more techniquesand OPEX increments over time from 2017 to 2023
Despite the investment the increase is compensated bya benefit in the electricity distribution network with areduction in CML and CI as shown in Figure 10
The summary of the proportion of installations requiredduring this evaluation period and by capital expenditures pertechnique is presented in Table 2 for both DECC scenarios
The average yearly price of each technique implementedto fix a network state is key for future decision-makingconsiderations
Figure 11 displays the average price of each techniquedisaggregated by CAPEX and OPEX
Performance indicators are key parameters for futuredecision-making within electricity distribution planning asquantifiers due to their influence on the quality of service
Therefore as shown in Figure 12 the only smart tech-nique used in combination with traditional reinforcementsin this scenario and evaluation period that slightly influenceslightly CML and CI is meshed networks
412 DECC2 2015ndash2023 Figure 13 plots the trend ofCAPEX and OPEX over the evaluation period It is important
to highlight that there is a CAPEX peak in 2015 due to anincrease of techniques applied in this period
This CAPEX increment produces a benefit in terms ofCML and CI as observed in Figure 14
The distribution of techniques applied and capital expen-ditures per technique are shown in Table 2 The average priceof each technique implementation in this demand scenariofor this evaluation period is shown in Figure 15
As displayed in Figure 12 for DECC4rsquos simulation theonly smart grid technique that improves the quality of serviceis the meshed network In Figure 16 the contribution ofsmart techniques on CML and CI for DECC2 demandevaluation is captured
413 Comparison between DECC2 and DECC4 for 2015ndash2023 The results presented may facilitate improvementsin electricity distribution network operations and planningresulting in better-informed decision-making when upgrad-ing current electricity distribution networks The assess-ment of the six smart grid techniques discovered thatonly three of them were selected as part of optimal
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
Mill
ions
pound p
er an
num
CAPEXOPEX
442444648
55254
Figure 9 CAPEX and OPEX DECC4 2015ndash2023
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
pu
Figure 10 CML and CI DECC4 2015ndash2023
10 Complexity
solutions for DECC4 and DECC2 as described in Table 2These three techniques applied are DAR for cables andtransformers and meshed networks
Comparing the cost trends of the two assessed scenariosit is notable that in both demand scenarios DECC4 and
DECC2 the CAPEX peak occurs in 2015 (Figures 9 and13) reflecting the more difficult nature of network statesto be feasible in a demanding scenario whereas DECC2shows a higher improvement of CI and CML performanceindicators as can be seen in Figures 10 and 14
Table 2 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2023
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 15 2 14 2
DAR-transformer 7 1 5 1
ALT 0 0 0 0
Mesh 3 1 4 1
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 8 3 7 2
TRAD-cable 60 89 65 91
TRAD-transfer load 6 2 4 1
TRAD-new feeder 1 2 1 2
DAR - cable DAR -transformer
Meshednetworks
TRAD -transformer
TRAD - cable
CAPEXOPEX
0
20000
40000
60000
80000
100000
pound
Figure 11 Average cost disaggregation per technique DECC4 2015ndash2023
Figure 12 Average CML and CI improvement per technique DECC4 2015ndash2023
11Complexity
The techniques applied are the key consideration to beassessed It is necessary to analyse the number of interven-tions applied by type the effect of these techniques in theelectric grid solving failures and fixing assets Figures 11and 15 show average prices of techniques used in eachdemand scenario Smart techniques have a lower TOTEXthan traditional reinforcements These novel techniquesabove are not frequently able to fix failures and thereforeproduce feasible network states In terms of CML and CIthe only technique able to moderately contribute to theirimprovement is meshed networks as shown in Figures 12and 16 Results attribute the majority of fixes to traditionalreinforcements with a comparatively smaller number offailures being solved by smart techniques (Table 2) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention forDECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
For DECC4 the three mentioned techniques along withtraditional cable and transformer replacement are applied(Table 2) whereas for DECC2 two of them are appliedDAR for cables and meshed networks (Table 2) Comparingthe cost trends of the two assessed scenarios it is notable thatin DECC4 the CAPEX peak occurs in 2015 (Figure 7)whereas in DECC2 besides the peak in 2015 there is alsoone in 2019 (Figure 11) reflecting the more difficult natureof network states to be feasible in a demanding scenarioHowever DECC2 shows a higher improvement of electricalperformance indicators as can be seen in Figure 12
In addition traditional cable replacement DAR forcables and meshed networks are able to fix the cable whereastraditional transformer replacement and DAR for trans-formers are able to fix transformer issues (Figure 16) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention for
DECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
42 Long-Term Planning This section evaluates two experi-ments namely characterising the DECC2 and DECC4 sce-narios for 2015ndash2047 evaluation period For each demandscenario expected investments disaggregating CAPEX andOPEX are presented the evolution of electrical performanceindicators and the number of techniques applied
421 DECC4 2015ndash2047 In this experiment the mostsignificant results to analyse the suitability of each techniqueare presented
Figure 17 shows the trend of CAPEX and OPEX from2015 to 2047
There are CAPEX peaks in the year 2018 and during thebeginning of RIIO-ED2 in the years 2025 to 2026 due to theapplication of more techniques to fulfill low-carbon targets
Figure 18 indicates that upgrades on the network aredirectly related to technical performance indicators CMLand CI
In Table 3 the techniques applied and their contributionto CAPEX during the evaluation period from 2015 to 2047 bya demand scenario are shown
422 DECC2 2015ndash2047 Within this experiment the mostrelevant results to analyse the evolutionary network statesare presented
In Figure 19 the trend of CAPEX and OPEX from 2015to 2047 is shown There is a significant increase of CAPEXin the years 2024 to 2026 at the beginning of RIIO-ED2due to the necessary implementation of new techniques toreach low-carbon targets The evolution of CML and CI ispresented in Figure 20 linking larger investment years whenmajor reductions are found The contribution of each solutiontechnique is presented in Table 3
423 Comparison between DECC2 and DECC4 for 2015ndash2047 Figure 21 presents a multidimensional parallel coor-dinate representation of the feasible network statersquoscombinations that produced a 2015ndash2047 investment path-way for the evaluated area It bundles economic indicatorsie CAPEX and OPEX with technical performance indica-tors providing valuable insights on the number of traditionalreinforcements utilised to heal falling network states Resultsare also clustered by the two demand scenarios assessedduring the experiments
Solutions of DECC2 (represented in orange and green)and DECC4 (in black and blue) are clustered by the per-centage of traditional reinforcements utilised as well asthe utilisation factor
Solutions in green and in black represent those wheresmart grids were more used whereas orange and blue repre-sent the cheapest (CAPEX and OPEX) less utilised and theworst responding to the decrease of CML CI and lossesand the ones using more traditional reinforcement to fixnetwork states
Besides the fact that DECC2 smart solutions are between16 and 28 more expensive than DECC4 traditional
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
CAPEXOPEX
442444648
552
Mill
ions
pound p
er an
num
54
Figure 13 CAPEX and OPEX DECC2 2015ndash2023
12 Complexity
reinforcement solutions (green solutions versus blue solu-tions in Figure 21) DECC2 traditional solutions are in therange of costs of smart solutions of DECC4 (orange andblack solutions in Figure 21) It can also be concluded thatinvestment pathways using less smart techniques provide a
cheaper response to technical performance evaluators suchas utilisation CML CI and losses
43 Summary Experiment evaluation runs from the2015ndash2047 period present lower investment rates for the
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
PU
Figure 14 CML and CI DECC2 2015ndash2023
CAPEXOPEX
DAR -transformer
Meshednetworks
Traditional -transformer
Traditional -cable
0
20000
40000
60000
80000
100000
120000
140000
pound
Figure 15 Average cost disaggregation per technique DECC2 2015ndash2023
Figure 16 Average CML and CI improvement per technique DECC2 2015ndash2023
13Complexity
2015ndash2023 period than if the evaluation is just performedwith a 2015ndash2023 time frame This occurs as a result of thechallenging low-carbon targets up to 2047 and a myopicplanning with short-term lookahead For an evaluationperiod four times larger the CAPEX and TOTEX increasedjust 18 compared to 2015ndash2023 concluding that betweenpound52M and pound68M the evaluation area regardless of thetime horizon for the investment or the demand scenarioconsidered is required
Furthermore it can be inferred comparing Tables 2 and 3that for less smart interventions the short-term planningis used compared to the long-term horizon planningDAR-cable and DAR-transformer experienced a significantimplementation variation between the two evaluationperiods for both demand scenarios as well as CAPEX allo-cated in cable upgrades falling from 89ndash91 (2015ndash2023)to 29ndash66 in the long term 2015ndash2047 run Both technicalperformance evaluators CML and CI respond to theirrespective CAPEX curve shape Due to a more incentivisedsmart grid technique during RIIO-ED2 and ED3 the per-centages of smart techniques implemented varied notablyFor DECC4 in 2023rsquos outlook the share of techniques is
25 for smart grid interventions whereas for 2050rsquos out-look the share is increased up to 58 In the same wayfor DECC2 in 2023rsquos outlook the share of smart interven-tions is 23 whereas in 2050rsquos outlook the share increasesup to 69
Feasible solutions characterising the solution space(Figure 21) differ in the degree of investment required andtechnical performance evaluators Each of the solution pathrepresented in the multidimensional solution space inFigure 21 represents the intersection of that dimension witheach axis Parallel coordinates [35] are low complexityworking for any N-dimension In the case of Figure 21it has 8 dimensions treating every variable uniformlyEach intersection of one solution path with each axis isthe value of that solution for that axis As for axis DECC2and DECC4 it represents the feasible solutions for eachdemand scenario Making a query by the percentage oftraditional reinforcement used in that solution we have thepartition between orange and green for DECC2 and blueand black being the first solutions that use more traditionalreinforcement compared with the ones that use more smarttechniques represented in green (DECC2) and black(DECC4) From Figure 21 we can argue that solutions thatuse more smart techniques (green and blacks) are moreexpensive in terms of CAPEX and OPEX than their peers(orange and blues) when compared by a demand scenarioIt can also be stated that solutions with a higher use of tradi-tional reinforcements are the ones that decrease the mostCML CI and losses
Disaggregating results by network state of the six 11 kVprimaries and by the feeder if necessary for further granulardebugging can discern locational capacity Under bothdemand scenarios Secklow Gate was seen to be the one withgreater capacity being necessary to apply fewer techniquesover the evaluation period 2015ndash2047 On the other handNewport Pagnell exceeds the capacity as soon as 2015requiring a high number of network state evaluation to befixed that happens for each subsequent year hence the largenumber of network states is presented in Table 4
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
pound p
er an
num
Figure 17 CAPEX and OPEX DECC4 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
pu
Figure 18 CML and CI DECC4 2015ndash2047
14 Complexity
5 Conclusions
Power flow analysis using a nodal network model is essentialwhen determining the benefits of trailed smart interventions
because the interactions and implications are highly specificto a particular location and scenario
This suggests that while the bottom-up approach isonerous in terms of data handling and manipulation this isworthwhile for strategic planning and policy evaluationComparing both investment strategies investment strategyadjustments will be necessary in future regulation periodsif an over-invested network behaves as displayed in theshort-term section of this study
Traditional reinforcement will continue to be the mainmethod by which network issues are mostly resolvedfollowed by dynamic asset rating and meshed networks
The assessment of the six novel smart interventions in theFALCON 11kV primary test area in Milton Keynes hasproved the suitability of three techniques able to fix failuresimproving the quality of service and their readiness to bedeployed in the near future These techniques are DAR forcables and transformers and meshed networks Meshednetworks have been repeatedly selected as a feasible tech-nique because using it will reduce CML CI and power losses
Table 3 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2047
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 18 5 31 6
DAR-transformer 32 16 32 6
ALT 0 0 0 0
Mesh 8 3 6 3
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 25 44 9 16
TRAD-cable 15 29 20 66
TRAD-transfer load 1 1 1 1
TRAD-new feeder 1 2 1 2
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
s pound p
er an
num
Figure 19 CAPEX and OPEX DECC2 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
PU
Figure 20 CML and CI DECC2 2015ndash2047
15Complexity
improving the quality of service and the efficiency whilebeing a cost-effective solution
The initial capacity at primary substations differedsignificantly and this affected the number and complexityof interventions required by the SIM Due to the loadscenarios showing significant peak load increases DAR wasoften a temporary measure that would delay but not removethe eventual need for traditional reinforcement
Implementing DAR for cables and transformers themonitoring of assets when their peak capacity is increasedwas analysed On the other hand it was observed thattraditional reinforcements still play a key role in keepingthe electricity distribution networks free of constraintsTRAD techniques such as transformer and cable replace-ments are able to fix the majority of failures and will beessential also in the future
The comparison between traditional reinforcements andnovel smart techniques has provided a new knowledge aboutthe suitability of each technique to be applied in termsof costs electrical performance failures fixed and assetreplaced Cable replacement is the most costly techniquehowever its use is unavoidable in a number of cases Further-more the applicability of each technique regarding costsinvolved improvements on power quality and efficiency
and failures solved lead to new questions to be analysed suchas the lack of these techniques to provide flexible capacitywithin the trailed area
To sum up this study has performed a comparativeanalysis of novel smart intervention techniques providinginsights for future investments in electricity distributionplanning Further work can focus on scaling up the analysisto include a larger section of the network or a constrainedarea to evaluate national applicability of the current findings
Data Availability
Some of the data relevant to this submission is proprietaryfrom Western Power Distribution It can be accessed forresearch purposes under a signed collaboration agreement
Conflicts of Interest
The authors declare that they have no conflicts of interest
Acknowledgments
The authors would like to thank the rest of the WesternPower Distribution Innovation team particularly the other
2400
2200
2000
350
360
370
380
390
400
1400
1300
1200
1100
1000DECC 4
50
55
60
12
11
10
9
8
4400
4200
4000
3800
3600
2400
CAPEX (in kpound) OPEX (in kpound) Utilisation Traditional reinforcements () DECC 2 998796 CML 998796 CI 998796 Losses
2200
2000
1800
Figure 21 Parallel coordinate visualisation of technoeconomic performance indicators under DECC4 and DECC2
Table 4 Summary of network states and results for demand scenario DECC4 and DECC2
Primary 11 kV substation Feeders Year TechniquesResultsDECC4
NSDECC4
ResultsDECC2
NSDECC2
Fox Milne 13 2047 Smart and traditional 54 276 47 259
Newport Pagnell 9 2047 Smart and traditional 48 317 31 318
Secklow Gate 9 2047 Smart and traditional 27 29 15 16
Bletchley 19 2047 Smart and traditional 32 40 21 48
Marlborough Street 11 2047 Smart and traditional 31 52 19 37
Childs Way 17 2047 Smart and traditional 67 398 54 181
16 Complexity
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
solutions for DECC4 and DECC2 as described in Table 2These three techniques applied are DAR for cables andtransformers and meshed networks
Comparing the cost trends of the two assessed scenariosit is notable that in both demand scenarios DECC4 and
DECC2 the CAPEX peak occurs in 2015 (Figures 9 and13) reflecting the more difficult nature of network statesto be feasible in a demanding scenario whereas DECC2shows a higher improvement of CI and CML performanceindicators as can be seen in Figures 10 and 14
Table 2 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2023
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 15 2 14 2
DAR-transformer 7 1 5 1
ALT 0 0 0 0
Mesh 3 1 4 1
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 8 3 7 2
TRAD-cable 60 89 65 91
TRAD-transfer load 6 2 4 1
TRAD-new feeder 1 2 1 2
DAR - cable DAR -transformer
Meshednetworks
TRAD -transformer
TRAD - cable
CAPEXOPEX
0
20000
40000
60000
80000
100000
pound
Figure 11 Average cost disaggregation per technique DECC4 2015ndash2023
Figure 12 Average CML and CI improvement per technique DECC4 2015ndash2023
11Complexity
The techniques applied are the key consideration to beassessed It is necessary to analyse the number of interven-tions applied by type the effect of these techniques in theelectric grid solving failures and fixing assets Figures 11and 15 show average prices of techniques used in eachdemand scenario Smart techniques have a lower TOTEXthan traditional reinforcements These novel techniquesabove are not frequently able to fix failures and thereforeproduce feasible network states In terms of CML and CIthe only technique able to moderately contribute to theirimprovement is meshed networks as shown in Figures 12and 16 Results attribute the majority of fixes to traditionalreinforcements with a comparatively smaller number offailures being solved by smart techniques (Table 2) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention forDECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
For DECC4 the three mentioned techniques along withtraditional cable and transformer replacement are applied(Table 2) whereas for DECC2 two of them are appliedDAR for cables and meshed networks (Table 2) Comparingthe cost trends of the two assessed scenarios it is notable thatin DECC4 the CAPEX peak occurs in 2015 (Figure 7)whereas in DECC2 besides the peak in 2015 there is alsoone in 2019 (Figure 11) reflecting the more difficult natureof network states to be feasible in a demanding scenarioHowever DECC2 shows a higher improvement of electricalperformance indicators as can be seen in Figure 12
In addition traditional cable replacement DAR forcables and meshed networks are able to fix the cable whereastraditional transformer replacement and DAR for trans-formers are able to fix transformer issues (Figure 16) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention for
DECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
42 Long-Term Planning This section evaluates two experi-ments namely characterising the DECC2 and DECC4 sce-narios for 2015ndash2047 evaluation period For each demandscenario expected investments disaggregating CAPEX andOPEX are presented the evolution of electrical performanceindicators and the number of techniques applied
421 DECC4 2015ndash2047 In this experiment the mostsignificant results to analyse the suitability of each techniqueare presented
Figure 17 shows the trend of CAPEX and OPEX from2015 to 2047
There are CAPEX peaks in the year 2018 and during thebeginning of RIIO-ED2 in the years 2025 to 2026 due to theapplication of more techniques to fulfill low-carbon targets
Figure 18 indicates that upgrades on the network aredirectly related to technical performance indicators CMLand CI
In Table 3 the techniques applied and their contributionto CAPEX during the evaluation period from 2015 to 2047 bya demand scenario are shown
422 DECC2 2015ndash2047 Within this experiment the mostrelevant results to analyse the evolutionary network statesare presented
In Figure 19 the trend of CAPEX and OPEX from 2015to 2047 is shown There is a significant increase of CAPEXin the years 2024 to 2026 at the beginning of RIIO-ED2due to the necessary implementation of new techniques toreach low-carbon targets The evolution of CML and CI ispresented in Figure 20 linking larger investment years whenmajor reductions are found The contribution of each solutiontechnique is presented in Table 3
423 Comparison between DECC2 and DECC4 for 2015ndash2047 Figure 21 presents a multidimensional parallel coor-dinate representation of the feasible network statersquoscombinations that produced a 2015ndash2047 investment path-way for the evaluated area It bundles economic indicatorsie CAPEX and OPEX with technical performance indica-tors providing valuable insights on the number of traditionalreinforcements utilised to heal falling network states Resultsare also clustered by the two demand scenarios assessedduring the experiments
Solutions of DECC2 (represented in orange and green)and DECC4 (in black and blue) are clustered by the per-centage of traditional reinforcements utilised as well asthe utilisation factor
Solutions in green and in black represent those wheresmart grids were more used whereas orange and blue repre-sent the cheapest (CAPEX and OPEX) less utilised and theworst responding to the decrease of CML CI and lossesand the ones using more traditional reinforcement to fixnetwork states
Besides the fact that DECC2 smart solutions are between16 and 28 more expensive than DECC4 traditional
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
CAPEXOPEX
442444648
552
Mill
ions
pound p
er an
num
54
Figure 13 CAPEX and OPEX DECC2 2015ndash2023
12 Complexity
reinforcement solutions (green solutions versus blue solu-tions in Figure 21) DECC2 traditional solutions are in therange of costs of smart solutions of DECC4 (orange andblack solutions in Figure 21) It can also be concluded thatinvestment pathways using less smart techniques provide a
cheaper response to technical performance evaluators suchas utilisation CML CI and losses
43 Summary Experiment evaluation runs from the2015ndash2047 period present lower investment rates for the
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
PU
Figure 14 CML and CI DECC2 2015ndash2023
CAPEXOPEX
DAR -transformer
Meshednetworks
Traditional -transformer
Traditional -cable
0
20000
40000
60000
80000
100000
120000
140000
pound
Figure 15 Average cost disaggregation per technique DECC2 2015ndash2023
Figure 16 Average CML and CI improvement per technique DECC2 2015ndash2023
13Complexity
2015ndash2023 period than if the evaluation is just performedwith a 2015ndash2023 time frame This occurs as a result of thechallenging low-carbon targets up to 2047 and a myopicplanning with short-term lookahead For an evaluationperiod four times larger the CAPEX and TOTEX increasedjust 18 compared to 2015ndash2023 concluding that betweenpound52M and pound68M the evaluation area regardless of thetime horizon for the investment or the demand scenarioconsidered is required
Furthermore it can be inferred comparing Tables 2 and 3that for less smart interventions the short-term planningis used compared to the long-term horizon planningDAR-cable and DAR-transformer experienced a significantimplementation variation between the two evaluationperiods for both demand scenarios as well as CAPEX allo-cated in cable upgrades falling from 89ndash91 (2015ndash2023)to 29ndash66 in the long term 2015ndash2047 run Both technicalperformance evaluators CML and CI respond to theirrespective CAPEX curve shape Due to a more incentivisedsmart grid technique during RIIO-ED2 and ED3 the per-centages of smart techniques implemented varied notablyFor DECC4 in 2023rsquos outlook the share of techniques is
25 for smart grid interventions whereas for 2050rsquos out-look the share is increased up to 58 In the same wayfor DECC2 in 2023rsquos outlook the share of smart interven-tions is 23 whereas in 2050rsquos outlook the share increasesup to 69
Feasible solutions characterising the solution space(Figure 21) differ in the degree of investment required andtechnical performance evaluators Each of the solution pathrepresented in the multidimensional solution space inFigure 21 represents the intersection of that dimension witheach axis Parallel coordinates [35] are low complexityworking for any N-dimension In the case of Figure 21it has 8 dimensions treating every variable uniformlyEach intersection of one solution path with each axis isthe value of that solution for that axis As for axis DECC2and DECC4 it represents the feasible solutions for eachdemand scenario Making a query by the percentage oftraditional reinforcement used in that solution we have thepartition between orange and green for DECC2 and blueand black being the first solutions that use more traditionalreinforcement compared with the ones that use more smarttechniques represented in green (DECC2) and black(DECC4) From Figure 21 we can argue that solutions thatuse more smart techniques (green and blacks) are moreexpensive in terms of CAPEX and OPEX than their peers(orange and blues) when compared by a demand scenarioIt can also be stated that solutions with a higher use of tradi-tional reinforcements are the ones that decrease the mostCML CI and losses
Disaggregating results by network state of the six 11 kVprimaries and by the feeder if necessary for further granulardebugging can discern locational capacity Under bothdemand scenarios Secklow Gate was seen to be the one withgreater capacity being necessary to apply fewer techniquesover the evaluation period 2015ndash2047 On the other handNewport Pagnell exceeds the capacity as soon as 2015requiring a high number of network state evaluation to befixed that happens for each subsequent year hence the largenumber of network states is presented in Table 4
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
pound p
er an
num
Figure 17 CAPEX and OPEX DECC4 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
pu
Figure 18 CML and CI DECC4 2015ndash2047
14 Complexity
5 Conclusions
Power flow analysis using a nodal network model is essentialwhen determining the benefits of trailed smart interventions
because the interactions and implications are highly specificto a particular location and scenario
This suggests that while the bottom-up approach isonerous in terms of data handling and manipulation this isworthwhile for strategic planning and policy evaluationComparing both investment strategies investment strategyadjustments will be necessary in future regulation periodsif an over-invested network behaves as displayed in theshort-term section of this study
Traditional reinforcement will continue to be the mainmethod by which network issues are mostly resolvedfollowed by dynamic asset rating and meshed networks
The assessment of the six novel smart interventions in theFALCON 11kV primary test area in Milton Keynes hasproved the suitability of three techniques able to fix failuresimproving the quality of service and their readiness to bedeployed in the near future These techniques are DAR forcables and transformers and meshed networks Meshednetworks have been repeatedly selected as a feasible tech-nique because using it will reduce CML CI and power losses
Table 3 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2047
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 18 5 31 6
DAR-transformer 32 16 32 6
ALT 0 0 0 0
Mesh 8 3 6 3
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 25 44 9 16
TRAD-cable 15 29 20 66
TRAD-transfer load 1 1 1 1
TRAD-new feeder 1 2 1 2
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
s pound p
er an
num
Figure 19 CAPEX and OPEX DECC2 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
PU
Figure 20 CML and CI DECC2 2015ndash2047
15Complexity
improving the quality of service and the efficiency whilebeing a cost-effective solution
The initial capacity at primary substations differedsignificantly and this affected the number and complexityof interventions required by the SIM Due to the loadscenarios showing significant peak load increases DAR wasoften a temporary measure that would delay but not removethe eventual need for traditional reinforcement
Implementing DAR for cables and transformers themonitoring of assets when their peak capacity is increasedwas analysed On the other hand it was observed thattraditional reinforcements still play a key role in keepingthe electricity distribution networks free of constraintsTRAD techniques such as transformer and cable replace-ments are able to fix the majority of failures and will beessential also in the future
The comparison between traditional reinforcements andnovel smart techniques has provided a new knowledge aboutthe suitability of each technique to be applied in termsof costs electrical performance failures fixed and assetreplaced Cable replacement is the most costly techniquehowever its use is unavoidable in a number of cases Further-more the applicability of each technique regarding costsinvolved improvements on power quality and efficiency
and failures solved lead to new questions to be analysed suchas the lack of these techniques to provide flexible capacitywithin the trailed area
To sum up this study has performed a comparativeanalysis of novel smart intervention techniques providinginsights for future investments in electricity distributionplanning Further work can focus on scaling up the analysisto include a larger section of the network or a constrainedarea to evaluate national applicability of the current findings
Data Availability
Some of the data relevant to this submission is proprietaryfrom Western Power Distribution It can be accessed forresearch purposes under a signed collaboration agreement
Conflicts of Interest
The authors declare that they have no conflicts of interest
Acknowledgments
The authors would like to thank the rest of the WesternPower Distribution Innovation team particularly the other
2400
2200
2000
350
360
370
380
390
400
1400
1300
1200
1100
1000DECC 4
50
55
60
12
11
10
9
8
4400
4200
4000
3800
3600
2400
CAPEX (in kpound) OPEX (in kpound) Utilisation Traditional reinforcements () DECC 2 998796 CML 998796 CI 998796 Losses
2200
2000
1800
Figure 21 Parallel coordinate visualisation of technoeconomic performance indicators under DECC4 and DECC2
Table 4 Summary of network states and results for demand scenario DECC4 and DECC2
Primary 11 kV substation Feeders Year TechniquesResultsDECC4
NSDECC4
ResultsDECC2
NSDECC2
Fox Milne 13 2047 Smart and traditional 54 276 47 259
Newport Pagnell 9 2047 Smart and traditional 48 317 31 318
Secklow Gate 9 2047 Smart and traditional 27 29 15 16
Bletchley 19 2047 Smart and traditional 32 40 21 48
Marlborough Street 11 2047 Smart and traditional 31 52 19 37
Childs Way 17 2047 Smart and traditional 67 398 54 181
16 Complexity
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
The techniques applied are the key consideration to beassessed It is necessary to analyse the number of interven-tions applied by type the effect of these techniques in theelectric grid solving failures and fixing assets Figures 11and 15 show average prices of techniques used in eachdemand scenario Smart techniques have a lower TOTEXthan traditional reinforcements These novel techniquesabove are not frequently able to fix failures and thereforeproduce feasible network states In terms of CML and CIthe only technique able to moderately contribute to theirimprovement is meshed networks as shown in Figures 12and 16 Results attribute the majority of fixes to traditionalreinforcements with a comparatively smaller number offailures being solved by smart techniques (Table 2) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention forDECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
For DECC4 the three mentioned techniques along withtraditional cable and transformer replacement are applied(Table 2) whereas for DECC2 two of them are appliedDAR for cables and meshed networks (Table 2) Comparingthe cost trends of the two assessed scenarios it is notable thatin DECC4 the CAPEX peak occurs in 2015 (Figure 7)whereas in DECC2 besides the peak in 2015 there is alsoone in 2019 (Figure 11) reflecting the more difficult natureof network states to be feasible in a demanding scenarioHowever DECC2 shows a higher improvement of electricalperformance indicators as can be seen in Figure 12
In addition traditional cable replacement DAR forcables and meshed networks are able to fix the cable whereastraditional transformer replacement and DAR for trans-formers are able to fix transformer issues (Figure 16) Theresults obtained in terms of traditional reinforcement sharefor 2015ndash2023 show a 60 proportion of intervention for
DECC4 and a 65 proportion of intervention for DECC2which is close to the 59 forecasted by the transform modelfor this evaluation period
42 Long-Term Planning This section evaluates two experi-ments namely characterising the DECC2 and DECC4 sce-narios for 2015ndash2047 evaluation period For each demandscenario expected investments disaggregating CAPEX andOPEX are presented the evolution of electrical performanceindicators and the number of techniques applied
421 DECC4 2015ndash2047 In this experiment the mostsignificant results to analyse the suitability of each techniqueare presented
Figure 17 shows the trend of CAPEX and OPEX from2015 to 2047
There are CAPEX peaks in the year 2018 and during thebeginning of RIIO-ED2 in the years 2025 to 2026 due to theapplication of more techniques to fulfill low-carbon targets
Figure 18 indicates that upgrades on the network aredirectly related to technical performance indicators CMLand CI
In Table 3 the techniques applied and their contributionto CAPEX during the evaluation period from 2015 to 2047 bya demand scenario are shown
422 DECC2 2015ndash2047 Within this experiment the mostrelevant results to analyse the evolutionary network statesare presented
In Figure 19 the trend of CAPEX and OPEX from 2015to 2047 is shown There is a significant increase of CAPEXin the years 2024 to 2026 at the beginning of RIIO-ED2due to the necessary implementation of new techniques toreach low-carbon targets The evolution of CML and CI ispresented in Figure 20 linking larger investment years whenmajor reductions are found The contribution of each solutiontechnique is presented in Table 3
423 Comparison between DECC2 and DECC4 for 2015ndash2047 Figure 21 presents a multidimensional parallel coor-dinate representation of the feasible network statersquoscombinations that produced a 2015ndash2047 investment path-way for the evaluated area It bundles economic indicatorsie CAPEX and OPEX with technical performance indica-tors providing valuable insights on the number of traditionalreinforcements utilised to heal falling network states Resultsare also clustered by the two demand scenarios assessedduring the experiments
Solutions of DECC2 (represented in orange and green)and DECC4 (in black and blue) are clustered by the per-centage of traditional reinforcements utilised as well asthe utilisation factor
Solutions in green and in black represent those wheresmart grids were more used whereas orange and blue repre-sent the cheapest (CAPEX and OPEX) less utilised and theworst responding to the decrease of CML CI and lossesand the ones using more traditional reinforcement to fixnetwork states
Besides the fact that DECC2 smart solutions are between16 and 28 more expensive than DECC4 traditional
0005
01015
02025
03035
04045
05
2015 2016 2017 2018 2019 2020 2021 2022 2023
CAPEXOPEX
442444648
552
Mill
ions
pound p
er an
num
54
Figure 13 CAPEX and OPEX DECC2 2015ndash2023
12 Complexity
reinforcement solutions (green solutions versus blue solu-tions in Figure 21) DECC2 traditional solutions are in therange of costs of smart solutions of DECC4 (orange andblack solutions in Figure 21) It can also be concluded thatinvestment pathways using less smart techniques provide a
cheaper response to technical performance evaluators suchas utilisation CML CI and losses
43 Summary Experiment evaluation runs from the2015ndash2047 period present lower investment rates for the
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
PU
Figure 14 CML and CI DECC2 2015ndash2023
CAPEXOPEX
DAR -transformer
Meshednetworks
Traditional -transformer
Traditional -cable
0
20000
40000
60000
80000
100000
120000
140000
pound
Figure 15 Average cost disaggregation per technique DECC2 2015ndash2023
Figure 16 Average CML and CI improvement per technique DECC2 2015ndash2023
13Complexity
2015ndash2023 period than if the evaluation is just performedwith a 2015ndash2023 time frame This occurs as a result of thechallenging low-carbon targets up to 2047 and a myopicplanning with short-term lookahead For an evaluationperiod four times larger the CAPEX and TOTEX increasedjust 18 compared to 2015ndash2023 concluding that betweenpound52M and pound68M the evaluation area regardless of thetime horizon for the investment or the demand scenarioconsidered is required
Furthermore it can be inferred comparing Tables 2 and 3that for less smart interventions the short-term planningis used compared to the long-term horizon planningDAR-cable and DAR-transformer experienced a significantimplementation variation between the two evaluationperiods for both demand scenarios as well as CAPEX allo-cated in cable upgrades falling from 89ndash91 (2015ndash2023)to 29ndash66 in the long term 2015ndash2047 run Both technicalperformance evaluators CML and CI respond to theirrespective CAPEX curve shape Due to a more incentivisedsmart grid technique during RIIO-ED2 and ED3 the per-centages of smart techniques implemented varied notablyFor DECC4 in 2023rsquos outlook the share of techniques is
25 for smart grid interventions whereas for 2050rsquos out-look the share is increased up to 58 In the same wayfor DECC2 in 2023rsquos outlook the share of smart interven-tions is 23 whereas in 2050rsquos outlook the share increasesup to 69
Feasible solutions characterising the solution space(Figure 21) differ in the degree of investment required andtechnical performance evaluators Each of the solution pathrepresented in the multidimensional solution space inFigure 21 represents the intersection of that dimension witheach axis Parallel coordinates [35] are low complexityworking for any N-dimension In the case of Figure 21it has 8 dimensions treating every variable uniformlyEach intersection of one solution path with each axis isthe value of that solution for that axis As for axis DECC2and DECC4 it represents the feasible solutions for eachdemand scenario Making a query by the percentage oftraditional reinforcement used in that solution we have thepartition between orange and green for DECC2 and blueand black being the first solutions that use more traditionalreinforcement compared with the ones that use more smarttechniques represented in green (DECC2) and black(DECC4) From Figure 21 we can argue that solutions thatuse more smart techniques (green and blacks) are moreexpensive in terms of CAPEX and OPEX than their peers(orange and blues) when compared by a demand scenarioIt can also be stated that solutions with a higher use of tradi-tional reinforcements are the ones that decrease the mostCML CI and losses
Disaggregating results by network state of the six 11 kVprimaries and by the feeder if necessary for further granulardebugging can discern locational capacity Under bothdemand scenarios Secklow Gate was seen to be the one withgreater capacity being necessary to apply fewer techniquesover the evaluation period 2015ndash2047 On the other handNewport Pagnell exceeds the capacity as soon as 2015requiring a high number of network state evaluation to befixed that happens for each subsequent year hence the largenumber of network states is presented in Table 4
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
pound p
er an
num
Figure 17 CAPEX and OPEX DECC4 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
pu
Figure 18 CML and CI DECC4 2015ndash2047
14 Complexity
5 Conclusions
Power flow analysis using a nodal network model is essentialwhen determining the benefits of trailed smart interventions
because the interactions and implications are highly specificto a particular location and scenario
This suggests that while the bottom-up approach isonerous in terms of data handling and manipulation this isworthwhile for strategic planning and policy evaluationComparing both investment strategies investment strategyadjustments will be necessary in future regulation periodsif an over-invested network behaves as displayed in theshort-term section of this study
Traditional reinforcement will continue to be the mainmethod by which network issues are mostly resolvedfollowed by dynamic asset rating and meshed networks
The assessment of the six novel smart interventions in theFALCON 11kV primary test area in Milton Keynes hasproved the suitability of three techniques able to fix failuresimproving the quality of service and their readiness to bedeployed in the near future These techniques are DAR forcables and transformers and meshed networks Meshednetworks have been repeatedly selected as a feasible tech-nique because using it will reduce CML CI and power losses
Table 3 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2047
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 18 5 31 6
DAR-transformer 32 16 32 6
ALT 0 0 0 0
Mesh 8 3 6 3
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 25 44 9 16
TRAD-cable 15 29 20 66
TRAD-transfer load 1 1 1 1
TRAD-new feeder 1 2 1 2
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
s pound p
er an
num
Figure 19 CAPEX and OPEX DECC2 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
PU
Figure 20 CML and CI DECC2 2015ndash2047
15Complexity
improving the quality of service and the efficiency whilebeing a cost-effective solution
The initial capacity at primary substations differedsignificantly and this affected the number and complexityof interventions required by the SIM Due to the loadscenarios showing significant peak load increases DAR wasoften a temporary measure that would delay but not removethe eventual need for traditional reinforcement
Implementing DAR for cables and transformers themonitoring of assets when their peak capacity is increasedwas analysed On the other hand it was observed thattraditional reinforcements still play a key role in keepingthe electricity distribution networks free of constraintsTRAD techniques such as transformer and cable replace-ments are able to fix the majority of failures and will beessential also in the future
The comparison between traditional reinforcements andnovel smart techniques has provided a new knowledge aboutthe suitability of each technique to be applied in termsof costs electrical performance failures fixed and assetreplaced Cable replacement is the most costly techniquehowever its use is unavoidable in a number of cases Further-more the applicability of each technique regarding costsinvolved improvements on power quality and efficiency
and failures solved lead to new questions to be analysed suchas the lack of these techniques to provide flexible capacitywithin the trailed area
To sum up this study has performed a comparativeanalysis of novel smart intervention techniques providinginsights for future investments in electricity distributionplanning Further work can focus on scaling up the analysisto include a larger section of the network or a constrainedarea to evaluate national applicability of the current findings
Data Availability
Some of the data relevant to this submission is proprietaryfrom Western Power Distribution It can be accessed forresearch purposes under a signed collaboration agreement
Conflicts of Interest
The authors declare that they have no conflicts of interest
Acknowledgments
The authors would like to thank the rest of the WesternPower Distribution Innovation team particularly the other
2400
2200
2000
350
360
370
380
390
400
1400
1300
1200
1100
1000DECC 4
50
55
60
12
11
10
9
8
4400
4200
4000
3800
3600
2400
CAPEX (in kpound) OPEX (in kpound) Utilisation Traditional reinforcements () DECC 2 998796 CML 998796 CI 998796 Losses
2200
2000
1800
Figure 21 Parallel coordinate visualisation of technoeconomic performance indicators under DECC4 and DECC2
Table 4 Summary of network states and results for demand scenario DECC4 and DECC2
Primary 11 kV substation Feeders Year TechniquesResultsDECC4
NSDECC4
ResultsDECC2
NSDECC2
Fox Milne 13 2047 Smart and traditional 54 276 47 259
Newport Pagnell 9 2047 Smart and traditional 48 317 31 318
Secklow Gate 9 2047 Smart and traditional 27 29 15 16
Bletchley 19 2047 Smart and traditional 32 40 21 48
Marlborough Street 11 2047 Smart and traditional 31 52 19 37
Childs Way 17 2047 Smart and traditional 67 398 54 181
16 Complexity
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
reinforcement solutions (green solutions versus blue solu-tions in Figure 21) DECC2 traditional solutions are in therange of costs of smart solutions of DECC4 (orange andblack solutions in Figure 21) It can also be concluded thatinvestment pathways using less smart techniques provide a
cheaper response to technical performance evaluators suchas utilisation CML CI and losses
43 Summary Experiment evaluation runs from the2015ndash2047 period present lower investment rates for the
2015 2016 2017 2018 2019 2020 2021 2022 2023
CICML
0010203040506070809
PU
Figure 14 CML and CI DECC2 2015ndash2023
CAPEXOPEX
DAR -transformer
Meshednetworks
Traditional -transformer
Traditional -cable
0
20000
40000
60000
80000
100000
120000
140000
pound
Figure 15 Average cost disaggregation per technique DECC2 2015ndash2023
Figure 16 Average CML and CI improvement per technique DECC2 2015ndash2023
13Complexity
2015ndash2023 period than if the evaluation is just performedwith a 2015ndash2023 time frame This occurs as a result of thechallenging low-carbon targets up to 2047 and a myopicplanning with short-term lookahead For an evaluationperiod four times larger the CAPEX and TOTEX increasedjust 18 compared to 2015ndash2023 concluding that betweenpound52M and pound68M the evaluation area regardless of thetime horizon for the investment or the demand scenarioconsidered is required
Furthermore it can be inferred comparing Tables 2 and 3that for less smart interventions the short-term planningis used compared to the long-term horizon planningDAR-cable and DAR-transformer experienced a significantimplementation variation between the two evaluationperiods for both demand scenarios as well as CAPEX allo-cated in cable upgrades falling from 89ndash91 (2015ndash2023)to 29ndash66 in the long term 2015ndash2047 run Both technicalperformance evaluators CML and CI respond to theirrespective CAPEX curve shape Due to a more incentivisedsmart grid technique during RIIO-ED2 and ED3 the per-centages of smart techniques implemented varied notablyFor DECC4 in 2023rsquos outlook the share of techniques is
25 for smart grid interventions whereas for 2050rsquos out-look the share is increased up to 58 In the same wayfor DECC2 in 2023rsquos outlook the share of smart interven-tions is 23 whereas in 2050rsquos outlook the share increasesup to 69
Feasible solutions characterising the solution space(Figure 21) differ in the degree of investment required andtechnical performance evaluators Each of the solution pathrepresented in the multidimensional solution space inFigure 21 represents the intersection of that dimension witheach axis Parallel coordinates [35] are low complexityworking for any N-dimension In the case of Figure 21it has 8 dimensions treating every variable uniformlyEach intersection of one solution path with each axis isthe value of that solution for that axis As for axis DECC2and DECC4 it represents the feasible solutions for eachdemand scenario Making a query by the percentage oftraditional reinforcement used in that solution we have thepartition between orange and green for DECC2 and blueand black being the first solutions that use more traditionalreinforcement compared with the ones that use more smarttechniques represented in green (DECC2) and black(DECC4) From Figure 21 we can argue that solutions thatuse more smart techniques (green and blacks) are moreexpensive in terms of CAPEX and OPEX than their peers(orange and blues) when compared by a demand scenarioIt can also be stated that solutions with a higher use of tradi-tional reinforcements are the ones that decrease the mostCML CI and losses
Disaggregating results by network state of the six 11 kVprimaries and by the feeder if necessary for further granulardebugging can discern locational capacity Under bothdemand scenarios Secklow Gate was seen to be the one withgreater capacity being necessary to apply fewer techniquesover the evaluation period 2015ndash2047 On the other handNewport Pagnell exceeds the capacity as soon as 2015requiring a high number of network state evaluation to befixed that happens for each subsequent year hence the largenumber of network states is presented in Table 4
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
pound p
er an
num
Figure 17 CAPEX and OPEX DECC4 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
pu
Figure 18 CML and CI DECC4 2015ndash2047
14 Complexity
5 Conclusions
Power flow analysis using a nodal network model is essentialwhen determining the benefits of trailed smart interventions
because the interactions and implications are highly specificto a particular location and scenario
This suggests that while the bottom-up approach isonerous in terms of data handling and manipulation this isworthwhile for strategic planning and policy evaluationComparing both investment strategies investment strategyadjustments will be necessary in future regulation periodsif an over-invested network behaves as displayed in theshort-term section of this study
Traditional reinforcement will continue to be the mainmethod by which network issues are mostly resolvedfollowed by dynamic asset rating and meshed networks
The assessment of the six novel smart interventions in theFALCON 11kV primary test area in Milton Keynes hasproved the suitability of three techniques able to fix failuresimproving the quality of service and their readiness to bedeployed in the near future These techniques are DAR forcables and transformers and meshed networks Meshednetworks have been repeatedly selected as a feasible tech-nique because using it will reduce CML CI and power losses
Table 3 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2047
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 18 5 31 6
DAR-transformer 32 16 32 6
ALT 0 0 0 0
Mesh 8 3 6 3
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 25 44 9 16
TRAD-cable 15 29 20 66
TRAD-transfer load 1 1 1 1
TRAD-new feeder 1 2 1 2
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
s pound p
er an
num
Figure 19 CAPEX and OPEX DECC2 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
PU
Figure 20 CML and CI DECC2 2015ndash2047
15Complexity
improving the quality of service and the efficiency whilebeing a cost-effective solution
The initial capacity at primary substations differedsignificantly and this affected the number and complexityof interventions required by the SIM Due to the loadscenarios showing significant peak load increases DAR wasoften a temporary measure that would delay but not removethe eventual need for traditional reinforcement
Implementing DAR for cables and transformers themonitoring of assets when their peak capacity is increasedwas analysed On the other hand it was observed thattraditional reinforcements still play a key role in keepingthe electricity distribution networks free of constraintsTRAD techniques such as transformer and cable replace-ments are able to fix the majority of failures and will beessential also in the future
The comparison between traditional reinforcements andnovel smart techniques has provided a new knowledge aboutthe suitability of each technique to be applied in termsof costs electrical performance failures fixed and assetreplaced Cable replacement is the most costly techniquehowever its use is unavoidable in a number of cases Further-more the applicability of each technique regarding costsinvolved improvements on power quality and efficiency
and failures solved lead to new questions to be analysed suchas the lack of these techniques to provide flexible capacitywithin the trailed area
To sum up this study has performed a comparativeanalysis of novel smart intervention techniques providinginsights for future investments in electricity distributionplanning Further work can focus on scaling up the analysisto include a larger section of the network or a constrainedarea to evaluate national applicability of the current findings
Data Availability
Some of the data relevant to this submission is proprietaryfrom Western Power Distribution It can be accessed forresearch purposes under a signed collaboration agreement
Conflicts of Interest
The authors declare that they have no conflicts of interest
Acknowledgments
The authors would like to thank the rest of the WesternPower Distribution Innovation team particularly the other
2400
2200
2000
350
360
370
380
390
400
1400
1300
1200
1100
1000DECC 4
50
55
60
12
11
10
9
8
4400
4200
4000
3800
3600
2400
CAPEX (in kpound) OPEX (in kpound) Utilisation Traditional reinforcements () DECC 2 998796 CML 998796 CI 998796 Losses
2200
2000
1800
Figure 21 Parallel coordinate visualisation of technoeconomic performance indicators under DECC4 and DECC2
Table 4 Summary of network states and results for demand scenario DECC4 and DECC2
Primary 11 kV substation Feeders Year TechniquesResultsDECC4
NSDECC4
ResultsDECC2
NSDECC2
Fox Milne 13 2047 Smart and traditional 54 276 47 259
Newport Pagnell 9 2047 Smart and traditional 48 317 31 318
Secklow Gate 9 2047 Smart and traditional 27 29 15 16
Bletchley 19 2047 Smart and traditional 32 40 21 48
Marlborough Street 11 2047 Smart and traditional 31 52 19 37
Childs Way 17 2047 Smart and traditional 67 398 54 181
16 Complexity
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
2015ndash2023 period than if the evaluation is just performedwith a 2015ndash2023 time frame This occurs as a result of thechallenging low-carbon targets up to 2047 and a myopicplanning with short-term lookahead For an evaluationperiod four times larger the CAPEX and TOTEX increasedjust 18 compared to 2015ndash2023 concluding that betweenpound52M and pound68M the evaluation area regardless of thetime horizon for the investment or the demand scenarioconsidered is required
Furthermore it can be inferred comparing Tables 2 and 3that for less smart interventions the short-term planningis used compared to the long-term horizon planningDAR-cable and DAR-transformer experienced a significantimplementation variation between the two evaluationperiods for both demand scenarios as well as CAPEX allo-cated in cable upgrades falling from 89ndash91 (2015ndash2023)to 29ndash66 in the long term 2015ndash2047 run Both technicalperformance evaluators CML and CI respond to theirrespective CAPEX curve shape Due to a more incentivisedsmart grid technique during RIIO-ED2 and ED3 the per-centages of smart techniques implemented varied notablyFor DECC4 in 2023rsquos outlook the share of techniques is
25 for smart grid interventions whereas for 2050rsquos out-look the share is increased up to 58 In the same wayfor DECC2 in 2023rsquos outlook the share of smart interven-tions is 23 whereas in 2050rsquos outlook the share increasesup to 69
Feasible solutions characterising the solution space(Figure 21) differ in the degree of investment required andtechnical performance evaluators Each of the solution pathrepresented in the multidimensional solution space inFigure 21 represents the intersection of that dimension witheach axis Parallel coordinates [35] are low complexityworking for any N-dimension In the case of Figure 21it has 8 dimensions treating every variable uniformlyEach intersection of one solution path with each axis isthe value of that solution for that axis As for axis DECC2and DECC4 it represents the feasible solutions for eachdemand scenario Making a query by the percentage oftraditional reinforcement used in that solution we have thepartition between orange and green for DECC2 and blueand black being the first solutions that use more traditionalreinforcement compared with the ones that use more smarttechniques represented in green (DECC2) and black(DECC4) From Figure 21 we can argue that solutions thatuse more smart techniques (green and blacks) are moreexpensive in terms of CAPEX and OPEX than their peers(orange and blues) when compared by a demand scenarioIt can also be stated that solutions with a higher use of tradi-tional reinforcements are the ones that decrease the mostCML CI and losses
Disaggregating results by network state of the six 11 kVprimaries and by the feeder if necessary for further granulardebugging can discern locational capacity Under bothdemand scenarios Secklow Gate was seen to be the one withgreater capacity being necessary to apply fewer techniquesover the evaluation period 2015ndash2047 On the other handNewport Pagnell exceeds the capacity as soon as 2015requiring a high number of network state evaluation to befixed that happens for each subsequent year hence the largenumber of network states is presented in Table 4
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
pound p
er an
num
Figure 17 CAPEX and OPEX DECC4 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
pu
Figure 18 CML and CI DECC4 2015ndash2047
14 Complexity
5 Conclusions
Power flow analysis using a nodal network model is essentialwhen determining the benefits of trailed smart interventions
because the interactions and implications are highly specificto a particular location and scenario
This suggests that while the bottom-up approach isonerous in terms of data handling and manipulation this isworthwhile for strategic planning and policy evaluationComparing both investment strategies investment strategyadjustments will be necessary in future regulation periodsif an over-invested network behaves as displayed in theshort-term section of this study
Traditional reinforcement will continue to be the mainmethod by which network issues are mostly resolvedfollowed by dynamic asset rating and meshed networks
The assessment of the six novel smart interventions in theFALCON 11kV primary test area in Milton Keynes hasproved the suitability of three techniques able to fix failuresimproving the quality of service and their readiness to bedeployed in the near future These techniques are DAR forcables and transformers and meshed networks Meshednetworks have been repeatedly selected as a feasible tech-nique because using it will reduce CML CI and power losses
Table 3 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2047
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 18 5 31 6
DAR-transformer 32 16 32 6
ALT 0 0 0 0
Mesh 8 3 6 3
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 25 44 9 16
TRAD-cable 15 29 20 66
TRAD-transfer load 1 1 1 1
TRAD-new feeder 1 2 1 2
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
s pound p
er an
num
Figure 19 CAPEX and OPEX DECC2 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
PU
Figure 20 CML and CI DECC2 2015ndash2047
15Complexity
improving the quality of service and the efficiency whilebeing a cost-effective solution
The initial capacity at primary substations differedsignificantly and this affected the number and complexityof interventions required by the SIM Due to the loadscenarios showing significant peak load increases DAR wasoften a temporary measure that would delay but not removethe eventual need for traditional reinforcement
Implementing DAR for cables and transformers themonitoring of assets when their peak capacity is increasedwas analysed On the other hand it was observed thattraditional reinforcements still play a key role in keepingthe electricity distribution networks free of constraintsTRAD techniques such as transformer and cable replace-ments are able to fix the majority of failures and will beessential also in the future
The comparison between traditional reinforcements andnovel smart techniques has provided a new knowledge aboutthe suitability of each technique to be applied in termsof costs electrical performance failures fixed and assetreplaced Cable replacement is the most costly techniquehowever its use is unavoidable in a number of cases Further-more the applicability of each technique regarding costsinvolved improvements on power quality and efficiency
and failures solved lead to new questions to be analysed suchas the lack of these techniques to provide flexible capacitywithin the trailed area
To sum up this study has performed a comparativeanalysis of novel smart intervention techniques providinginsights for future investments in electricity distributionplanning Further work can focus on scaling up the analysisto include a larger section of the network or a constrainedarea to evaluate national applicability of the current findings
Data Availability
Some of the data relevant to this submission is proprietaryfrom Western Power Distribution It can be accessed forresearch purposes under a signed collaboration agreement
Conflicts of Interest
The authors declare that they have no conflicts of interest
Acknowledgments
The authors would like to thank the rest of the WesternPower Distribution Innovation team particularly the other
2400
2200
2000
350
360
370
380
390
400
1400
1300
1200
1100
1000DECC 4
50
55
60
12
11
10
9
8
4400
4200
4000
3800
3600
2400
CAPEX (in kpound) OPEX (in kpound) Utilisation Traditional reinforcements () DECC 2 998796 CML 998796 CI 998796 Losses
2200
2000
1800
Figure 21 Parallel coordinate visualisation of technoeconomic performance indicators under DECC4 and DECC2
Table 4 Summary of network states and results for demand scenario DECC4 and DECC2
Primary 11 kV substation Feeders Year TechniquesResultsDECC4
NSDECC4
ResultsDECC2
NSDECC2
Fox Milne 13 2047 Smart and traditional 54 276 47 259
Newport Pagnell 9 2047 Smart and traditional 48 317 31 318
Secklow Gate 9 2047 Smart and traditional 27 29 15 16
Bletchley 19 2047 Smart and traditional 32 40 21 48
Marlborough Street 11 2047 Smart and traditional 31 52 19 37
Childs Way 17 2047 Smart and traditional 67 398 54 181
16 Complexity
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
5 Conclusions
Power flow analysis using a nodal network model is essentialwhen determining the benefits of trailed smart interventions
because the interactions and implications are highly specificto a particular location and scenario
This suggests that while the bottom-up approach isonerous in terms of data handling and manipulation this isworthwhile for strategic planning and policy evaluationComparing both investment strategies investment strategyadjustments will be necessary in future regulation periodsif an over-invested network behaves as displayed in theshort-term section of this study
Traditional reinforcement will continue to be the mainmethod by which network issues are mostly resolvedfollowed by dynamic asset rating and meshed networks
The assessment of the six novel smart interventions in theFALCON 11kV primary test area in Milton Keynes hasproved the suitability of three techniques able to fix failuresimproving the quality of service and their readiness to bedeployed in the near future These techniques are DAR forcables and transformers and meshed networks Meshednetworks have been repeatedly selected as a feasible tech-nique because using it will reduce CML CI and power losses
Table 3 Number of interventions and CAPEX involved DECC4 and DECC2 2015ndash2047
TechniqueDECC4 DECC2
Proportion of interventions () CAPEX () Proportion of interventions () CAPEX ()
DAR-cable 18 5 31 6
DAR-transformer 32 16 32 6
ALT 0 0 0 0
Mesh 8 3 6 3
Batteries 0 0 0 0
DSM 0 0 0 0
DG 0 0 0 0
TRAD-transformer 25 44 9 16
TRAD-cable 15 29 20 66
TRAD-transfer load 1 1 1 1
TRAD-new feeder 1 2 1 2
2015 2023 2031
CAPEXOPEX
2039 20470
50
100
150
200
250
300
Thou
sand
s pound p
er an
num
Figure 19 CAPEX and OPEX DECC2 2015ndash2047
CI
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
2045
2047
CML
0010203040506070809
PU
Figure 20 CML and CI DECC2 2015ndash2047
15Complexity
improving the quality of service and the efficiency whilebeing a cost-effective solution
The initial capacity at primary substations differedsignificantly and this affected the number and complexityof interventions required by the SIM Due to the loadscenarios showing significant peak load increases DAR wasoften a temporary measure that would delay but not removethe eventual need for traditional reinforcement
Implementing DAR for cables and transformers themonitoring of assets when their peak capacity is increasedwas analysed On the other hand it was observed thattraditional reinforcements still play a key role in keepingthe electricity distribution networks free of constraintsTRAD techniques such as transformer and cable replace-ments are able to fix the majority of failures and will beessential also in the future
The comparison between traditional reinforcements andnovel smart techniques has provided a new knowledge aboutthe suitability of each technique to be applied in termsof costs electrical performance failures fixed and assetreplaced Cable replacement is the most costly techniquehowever its use is unavoidable in a number of cases Further-more the applicability of each technique regarding costsinvolved improvements on power quality and efficiency
and failures solved lead to new questions to be analysed suchas the lack of these techniques to provide flexible capacitywithin the trailed area
To sum up this study has performed a comparativeanalysis of novel smart intervention techniques providinginsights for future investments in electricity distributionplanning Further work can focus on scaling up the analysisto include a larger section of the network or a constrainedarea to evaluate national applicability of the current findings
Data Availability
Some of the data relevant to this submission is proprietaryfrom Western Power Distribution It can be accessed forresearch purposes under a signed collaboration agreement
Conflicts of Interest
The authors declare that they have no conflicts of interest
Acknowledgments
The authors would like to thank the rest of the WesternPower Distribution Innovation team particularly the other
2400
2200
2000
350
360
370
380
390
400
1400
1300
1200
1100
1000DECC 4
50
55
60
12
11
10
9
8
4400
4200
4000
3800
3600
2400
CAPEX (in kpound) OPEX (in kpound) Utilisation Traditional reinforcements () DECC 2 998796 CML 998796 CI 998796 Losses
2200
2000
1800
Figure 21 Parallel coordinate visualisation of technoeconomic performance indicators under DECC4 and DECC2
Table 4 Summary of network states and results for demand scenario DECC4 and DECC2
Primary 11 kV substation Feeders Year TechniquesResultsDECC4
NSDECC4
ResultsDECC2
NSDECC2
Fox Milne 13 2047 Smart and traditional 54 276 47 259
Newport Pagnell 9 2047 Smart and traditional 48 317 31 318
Secklow Gate 9 2047 Smart and traditional 27 29 15 16
Bletchley 19 2047 Smart and traditional 32 40 21 48
Marlborough Street 11 2047 Smart and traditional 31 52 19 37
Childs Way 17 2047 Smart and traditional 67 398 54 181
16 Complexity
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
improving the quality of service and the efficiency whilebeing a cost-effective solution
The initial capacity at primary substations differedsignificantly and this affected the number and complexityof interventions required by the SIM Due to the loadscenarios showing significant peak load increases DAR wasoften a temporary measure that would delay but not removethe eventual need for traditional reinforcement
Implementing DAR for cables and transformers themonitoring of assets when their peak capacity is increasedwas analysed On the other hand it was observed thattraditional reinforcements still play a key role in keepingthe electricity distribution networks free of constraintsTRAD techniques such as transformer and cable replace-ments are able to fix the majority of failures and will beessential also in the future
The comparison between traditional reinforcements andnovel smart techniques has provided a new knowledge aboutthe suitability of each technique to be applied in termsof costs electrical performance failures fixed and assetreplaced Cable replacement is the most costly techniquehowever its use is unavoidable in a number of cases Further-more the applicability of each technique regarding costsinvolved improvements on power quality and efficiency
and failures solved lead to new questions to be analysed suchas the lack of these techniques to provide flexible capacitywithin the trailed area
To sum up this study has performed a comparativeanalysis of novel smart intervention techniques providinginsights for future investments in electricity distributionplanning Further work can focus on scaling up the analysisto include a larger section of the network or a constrainedarea to evaluate national applicability of the current findings
Data Availability
Some of the data relevant to this submission is proprietaryfrom Western Power Distribution It can be accessed forresearch purposes under a signed collaboration agreement
Conflicts of Interest
The authors declare that they have no conflicts of interest
Acknowledgments
The authors would like to thank the rest of the WesternPower Distribution Innovation team particularly the other
2400
2200
2000
350
360
370
380
390
400
1400
1300
1200
1100
1000DECC 4
50
55
60
12
11
10
9
8
4400
4200
4000
3800
3600
2400
CAPEX (in kpound) OPEX (in kpound) Utilisation Traditional reinforcements () DECC 2 998796 CML 998796 CI 998796 Losses
2200
2000
1800
Figure 21 Parallel coordinate visualisation of technoeconomic performance indicators under DECC4 and DECC2
Table 4 Summary of network states and results for demand scenario DECC4 and DECC2
Primary 11 kV substation Feeders Year TechniquesResultsDECC4
NSDECC4
ResultsDECC2
NSDECC2
Fox Milne 13 2047 Smart and traditional 54 276 47 259
Newport Pagnell 9 2047 Smart and traditional 48 317 31 318
Secklow Gate 9 2047 Smart and traditional 27 29 15 16
Bletchley 19 2047 Smart and traditional 32 40 21 48
Marlborough Street 11 2047 Smart and traditional 31 52 19 37
Childs Way 17 2047 Smart and traditional 67 398 54 181
16 Complexity
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
members of the FALCON project as well as Paul CharletonStuart Fowler Ilja Orlovs Dan Taylor and Steve IngramAlso the authors want to acknowledge OFGEM and theLowCarbon Network Fund for funding this piece of research
References
[1] European Commission ldquoCommunication from the Commis-sion to the European Parliament the Council the EuropeanEconomic and Social Committee and the Committee of theRegionsrdquo 2011 December 2016 httpseur-lexeuropaeulegal-contentENTXTqid=1537473508968ampuri=CELEX52016PC076721
[2] F G N Li and E Trutnevyte ldquoInvestment appraisal ofcost-optimal and near-optimal pathways for the UK elec-tricity sector transition to 2050rdquo Applied Energy vol 189pp 89ndash109 2017
[3] G Strbac I Konstantelos M Pollitt and R Green DeliveringFuture-Proof Energy Infrastructure National InfrastructureCommission 2016
[4] Ofgem ldquoGB Network regulation - the RIIO modelrdquo 2010December 2014 httpswwwofgemgovuknetwork-regulation-riio-model
[5] R Poudineh and T Jamasb ldquoDistributed generation storagedemand response and energy efficiency as alternatives togrid capacity enhancementrdquo Energy Policy vol 67 pp 222ndash231 2014
[6] J Yang X Bai D Strickland L Jenkins and A M CrossldquoDynamic network rating for low carbon distribution networkoperationmdashA UK applicationrdquo IEEE Transactions on SmartGrid vol 6 no 2 pp 988ndash998 2015
[7] M Behnke W Erdman S Horgan et al ldquoSecondary net-work distribution systems background and issues relatedto the interconnection of distributed resourcesrdquo NationalRenewable Energy Laboratory (NREL) Tech Rep NRELTP-560-38079 2005
[8] J Crispim J Braz R Castro and J Esteves ldquoSmart grids in theEU with smart regulation experiences from the UK Italy andPortugalrdquo Utilities Policy vol 31 pp 85ndash93 2014
[9] Tnei ldquoIPSA Power software for power systemsrdquo March 2016httpwwwipsa-powercom
[10] ETAP ldquoETAP PSrdquo 2018 April 2016 httpsetapcomsoftwareproduct-overview-main
[11] DINIS ldquoDINIS distribution network information sys-temsrdquo 2002 March 2016 httpsetapcomsoftwareproduct-overview-main
[12] Western Power Distribution ldquoSIM final reportrdquo 2015November 2016 httpwwwwesternpowerinnovationcoukProjectsFalconaspx
[13] Western Power Distribution ldquoProject FALCONrdquo 2015November 2017 httpwwwdiniscom
[14] EA Technology ldquoTransform modelrdquo March 2016 httpwwweatechnologycomproducts-and-servicescreate-smarter-gridstransform-model
[15] L Sigrist E Lobato L Rouco M Gazzino and M CantuldquoEconomic assessment of smart grid initiatives for islandpower systemsrdquo Applied Energy vol 189 pp 403ndash415 2017
[16] J A Momoh ldquoSmart grid design for efficient and flexiblepower networks operation and controlrdquo in 2009 IEEEPESPower Systems Conference and Exposition pp 1ndash8 SeattleWA USA 2009
[17] N Good K A Ellis and P Mancarella ldquoReview and classifica-tion of barriers and enablers of demand response in the smartgridrdquo Renewable and Sustainable Energy Reviews vol 72pp 57ndash72 2017
[18] Z Yang J Xiang and Y Li ldquoDistributed consensus basedsupplyndashdemand balance algorithm for economic dispatchproblem in a smart grid with switching graphrdquo IEEE Trans-actions on Industrial Electronics vol 64 no 2 pp 1600ndash1610 2017
[19] SuSTAINABLE ldquoSmart distribution network operation formaximising the integration of renewable generationrdquo 2015March 2016 httpwwwsustainableprojecteuHomeaspx
[20] S Mohtashami D Pudjianto and G Strbac ldquoStrategic distri-bution network planning with smart grid technologiesrdquo IEEETransactions on Smart Grid vol 8 no 6 pp 2656ndash2664 2017
[21] Smart Grid Forum ldquoSmart grid forum work stream 7rdquo2015 March 2016 httpwwwsmarternetworksorgprojectnia_nget015425
[22] ETI ldquoEnergyPath networksrdquo March 2016 httpwwweticoukprojectenergypath
[23] C Mateo Domingo T Gomez San Roman Aacute Sanchez-Miralles J P Peco Gonzalez and A Candela Martinez ldquoAreference network model for large-scale distribution planningwith automatic street map generationrdquo IEEE Transactions onPower Systems vol 26 no 1 pp 190ndash197 2011
[24] R Bolton and T J Foxon ldquoInfrastructure transformation as asocio-technical process mdash implications for the governanceof energy distribution networks in the UKrdquo TechnologicalForecasting and Social Change vol 90 pp 538ndash550 2015
[25] UK Power Networks ldquoDNO guide to future Smart man-agement of distribution networks Summary reportrdquo 2014httpsinnovationukpowernetworkscoukinnovationenProjectstier-2-projectsLow-Carbon-London-(LCL)Project-DocumentsLCL20Learning20Report20-20SR20-20Summary20Report20-20DNO20Guide20to20Future20Smart20Management20of20Distribution20Networkspdf
[26] A Botea J Rintanen and D Banerjee ldquoOptimal reconfigura-tion for supply restoration with informed AlowastSearchrdquo IEEETransactions on Smart Grid vol 3 no 2 pp 583ndash593 2012
[27] T Logenthiran D Srinivasan and T Z Shun ldquoDemand sidemanagement in smart grid using heuristic optimizationrdquoIEEE Transactions on Smart Grid vol 3 no 3 pp 1244ndash1252 2012
[28] J Saacutenchez-Cuadrado J de Lara and E Guerra ldquoBottom-upmeta-modelling an interactive approachrdquo in Model DrivenEngineering Languages and Systems pp 3ndash19 Springer2012
[29] Y H Kim F J Sting and C H Loch ldquoTop-down bottom-upor both Toward an integrative perspective on operationsstrategy formationrdquo Journal of Operations Managementvol 32 no 7-8 pp 462ndash474 2014
[30] C Bohringer ldquoThe synthesis of bottom-up and top-down inenergy policy modelingrdquo Energy Economics vol 20 no 3pp 233ndash248 1998
[31] T G R Bower ldquoRepetition in human developmentrdquo Merrill-Palmer Quarterly of Behavior and Development vol 20no 4 pp 303ndash318 1974
[32] H Mintzberg and J A Waters ldquoOf strategies deliberate andemergentrdquo Strategic Management Journal vol 6 no 3pp 257ndash272 1985
17Complexity
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
[33] K Moslehi and R Kumar ldquoA reliability perspective of thesmart gridrdquo IEEE Transactions on Smart Grid vol 1 no 1pp 57ndash64 2010
[34] F Rahimi and A Ipakchi ldquoDemand response as a marketresource under the smart grid paradigmrdquo IEEE Transactionson Smart Grid vol 1 no 1 pp 82ndash88 2010
[35] A Inselberg Parallel Coordinates Visual MultidimensionalGeometry and Its Applications Springer 2009
18 Complexity
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom
Hindawiwwwhindawicom Volume 2018
MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Mathematical Problems in Engineering
Applied MathematicsJournal of
Hindawiwwwhindawicom Volume 2018
Probability and StatisticsHindawiwwwhindawicom Volume 2018
Journal of
Hindawiwwwhindawicom Volume 2018
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawiwwwhindawicom Volume 2018
OptimizationJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Engineering Mathematics
International Journal of
Hindawiwwwhindawicom Volume 2018
Operations ResearchAdvances in
Journal of
Hindawiwwwhindawicom Volume 2018
Function SpacesAbstract and Applied AnalysisHindawiwwwhindawicom Volume 2018
International Journal of Mathematics and Mathematical Sciences
Hindawiwwwhindawicom Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Hindawiwwwhindawicom Volume 2018Volume 2018
Numerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisNumerical AnalysisAdvances inAdvances in Discrete Dynamics in
Nature and SocietyHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Dierential EquationsInternational Journal of
Volume 2018
Hindawiwwwhindawicom Volume 2018
Decision SciencesAdvances in
Hindawiwwwhindawicom Volume 2018
AnalysisInternational Journal of
Hindawiwwwhindawicom Volume 2018
Stochastic AnalysisInternational Journal of
Submit your manuscripts atwwwhindawicom