tc5613-6 - operation manual
TRANSCRIPT
-
8/18/2019 TC5613-6 - Operation Manual
1/109
TC5613-6 C2
TC5613-6 VERSION C2
QTZ80 (TC5613-6) Tower Crane
Operating Instructions
Changsha Zoomlion Heavy Industry Science and Technology Development Co.Ltd
-
8/18/2019 TC5613-6 - Operation Manual
2/109
Go through the instructions for correct operation and maintenance, and always keep at
hand for consultation.
Pay attention to the sentences marked with “Warning, Notice or Precautions ” in
this publication, which involves safety of construction.
Zoomlion has been devoting every effort to the perfect of her products. Therefore
they are changed without notice. If you have any questions, please don't hesitate to contact
Zoomlion for further consultation.
Shipped Date
-
8/18/2019 TC5613-6 - Operation Manual
3/109
Contents
Preface................................................................. 0-10-10
Part I Erection of Tower Crane
Erection................................................ 1.1-11.1-49
Dismantling........................................... 1.2-11.2-6
Part II Operation and Maintenance
Safety Operation of the Tower Crane.................................. 2.1-12.1-6
Operation of Mechanisms & Electrical Equipment................ 2.2-12.2-8
Safety Protection Device.................................................... 2.3-12.3-9
Maintenance.................................................................... 2.4-12.4-8
Appendix ....................................................................... 1
Editor
Fu liang
Proofreader Liu yi
Ratifier
Yingxiong Fu
-
8/18/2019 TC5613-6 - Operation Manual
4/109
Preface
Model TC5613-6 tower crane is designed and manufactured by Changsha Zoomlion
Heavy Industry Science and Technology Development Co., Ltd. according to the Chinese
standard of JG/T5037-93 “Classification of Tower Crane”.
The TC5613-6 tower crane is a self-climbing multi-purpose machine with a horizontal
jib, a trolleying mechanism and an upper slewing mechanism. Its characteristics are:
The performance parameters and technical indicator of the crane are at a leading level in
China. The Maximum working radius is 56m and the maximum hoisting height is 220m.
The crane has different working modes such as: outrigger stationary, undercarriage
stationary, mobile and inside climbing, so that it is applied in different construction
projects. The hoisting height of outrigger stationary is 40.5m and the hoist height of the
crane anchored to the building is 220m.
High working speed and good regulated speed performance make the machine working
smoothly.
The main electric elements are used world-renowned products, which service life is 3-4
times longer than China-made counterparts with less failure, simple maintenance and
reliable working.
8 sets of safety devices ensure the tower crane work reliably, and the safety devices are
mechanical or integrated mechanical-electrical products.
The design of the crane is based on the actual situations in China and on the safe-reliable
operation principles. Greatly absorb and adopt the well-established and reliable advanced
technology to enhance its overall technical level at the same time in the world.
Well-established advanced technology adopted as following:
-
8/18/2019 TC5613-6 - Operation Manual
5/109
Importing frequency transformer and realizing stepless speed regulated and frequency
altering make starting and braking smoothly without impact, running safety and reliable.
Electrics manufactured with the technology from TE, France.
Weight limier, height limiter, radius limiter, slewing limiter, slewing brake, traction
brake and similar safety guards are China-made based on the imported technology.
Carriage rope break-proof device (carriage slip-proof) and axle break-proof device;
Rope pay-off system for hoisting mechanism;
Traction rope-tensioning system;
Large-radius hoisting jib suspended by double rigid tie rods, featuring good jib rigidity,
light jib weight, small jib cross-section, small wind resistance and nice-looking
appearance and several jib lengths, it is satisfied different construction needs.
Out-hung operator cabin, featuring excellent field of view, spacious interior and
satisfactory working environment, and advanced inter-active control console, the
operator handles the mechanisms easy and services simply.
Design in complete conformity or superior to the
relevant national standards.
The crane is suitable for use in such large-sized construction projects as high-rise or
super high-rise buildings, bridge and water conservancy projects, large-span industrial buildings, large gymnasiums, and high chimneys and silos constructed with slip form.
-
8/18/2019 TC5613-6 - Operation Manual
6/109
Technical parameters of the tower crane
Technical performance parameters for the whole machine (Table 8-1)
Table 8-1
Hoisting
Slewing Mechanism Group
Trolleying
kNm
Rated hoisting moment
Fall Stationary Anchored
Max hoisting height
Maximum
Working Radius Minimum
t
Max hoisting capacity
Fall
m/min
Speed
Max. Load
kW
Power
Speed m/min Trolleying Power kW
Speed r/min
Slewing Power kW
Working
Pressure MPa Recommended Value
Speed m/min Recommended
Value
Jacking
(Erecting) mechanism
Power kW Recommended Value
Total power kW Excluding Erecting Mechanism
Counterweight
Operation Temperature
Technical parameters of the four mechanisms
-
8/18/2019 TC5613-6 - Operation Manual
7/109
Technical parameters of hoisting mechanism
QS680D(Table 8-2-1)
Table 8-2-1
Maximum traction of the rope N
Specifications
Wire rope
Maximum linear speed m/min 160
Wire
Rope Drum
Rope capacity m (6)(layers6)
Model YZTD225L2-4/8/32
Power kW 24/24/5.4
Motor Speed r/min 1440/720/160
Model YWZ3-315/45-16
Brake
Braking moment N.m 630
Reducer ratio 16.75
Technical parameters of trolleying mechanism (Table 8-2-2) Table 8-2-2
Maximum traction of the rope
Specifications
619-7.7-1550--
619-7.7-1550-- right-twist
Maximum linear speed
44mJib 88 56
50mJib 100 62
Wire rope
Length 56mJib
m
Wire rope112
Wire
rope 68
WireRope Drum
Drum Speed
Model YDEJ132S-4/8-B5
Power kW 3.3/2.2
Motor Speed r/min 1440/720
Reducer
Ratio43
Technical parameters of slewing mechanism (Table 8-2-3)
-
8/18/2019 TC5613-6 - Operation Manual
8/109
Table 8-2-3
Technical parameters of jacking mechanism (Table 8-2-4) Table 8-2-4
Hydraulic
pump
Working pressure
Cylinder /rod diameter
Maximum jacking force
Jacking
cylinder
Jacking speed
Radius and Load Capacity
m Jib’s Radius and Load Capacity
Radius (m) 2fall
Hoistin
gweight
(t)
4
fall
Radius (m)
2
fall
Hoistin
gweight(t)
4fall
Model YTW112M-4B5
Power kW 4.0
Motor Speed r/min 1440
Model
Ratio 195
Reducer
Output rotation moment N·m 10000
Modulus m 12
Number of teeth Z 16
Gear parameter at
output end
Position-changing factor X +0.5
Slewing speed r/min
Slewing ring support 011.45.1250
-
8/18/2019 TC5613-6 - Operation Manual
9/109
44m Jib’s Radius and Load Capacity
Radius (m)
2
fall
Hoisting
weight(t)
4
fall
Radius (m) 2
fall
Hoisting
weight(t)
4
fall
-
8/18/2019 TC5613-6 - Operation Manual
10/109
m Jib’s Radius and Load Capacity
Radius (m)
2fall
Hoistin
gweight
(t)
4
fall
Radius (m)
2
fall
Hoistingweight
(t)
4
fall
m Jib’s Radius and Load Capacity
Radius (m)
2fall
Hoistin
gweight
(t)
4
fall
Radius (m)
2fall
Hoistin
g
weight
(t)
4
fall
-
8/18/2019 TC5613-6 - Operation Manual
11/109
Overall dimensions of the crane
Overall dimensions of the stationary crane
Fig.1 Overall dimensions of the stationary TC5613-6 tower crane
-
8/18/2019 TC5613-6 - Operation Manual
12/109
Fig.2 Overall dimensions of TC5613-6 Stationary Tower Crane with Foundation Undercarriage
-
8/18/2019 TC5613-6 - Operation Manual
13/109
Overall dimensions of the crane anchored to the building
Fig.3 Dimensions of Stationary Crane with Foundation Anchor
-
8/18/2019 TC5613-6 - Operation Manual
14/109
Part I Installation of Tower Crane
Chapter I Erecting
Foreword
The user should go through the chapter in detail for proper and prompt erection of the
tower crane.
Cautions of erecting tower
The maximum wind speed atop should be less than 14m/s during crane erecting.
Strictly follow the procedures of crane erecting.
Select a proper mobile crane and slings in accordance with items shown in Table 1-1.
1-1 Table 1-1 Component weight and height
No.
Designation
(kg)
Weight
Traveling
Driving Bogie
Driven Bogie
Total Beam Semi-Beam
Tie Rod of Bottom Frame
Base Section &
Tower Strut
Ballast (1)
Ballast (2)
EQBase Tower Section EQ
EQ7
Tower section EQ
Climbing Frame
Slewing Assembly
Operator Cab
Tower Head
Counter Jib assembly
-
8/18/2019 TC5613-6 - Operation Manual
15/109
First
Block Counterweight
38m Jib assembly
44m Jib assembly
50m Jib assembly
56m Jib assembly
Counterweight of 38 m
Jib
Counterweight of 44 mJib
Counterweight of 50 m
Jib
Counterweight of 56 m
Jib
20a 20b 20c
Note20a, 20b, 20c are the remaining counterweights after mounting a counterweight.
The dismountable pins, connecting bolts and nuts for the slewing rings and tower sections of
the tower crane are special-made, which shall not be replaced freely.
Stairs, platform and protecting fence should be installed for safe operation.
The quantity of counterweight blocks shall be provided in accordance with the jib length
(refer to relevant chapter). Jib must be installed after placing one 2.25t counter-weight on
the counter-jib. It is prohibited to place two pieces or more counter-weight on the
counter-jib before installing jib.
After jib installation, it is prohibited to hoist any load before placing specified
counter-weight on the counter-jib.
At the erection position of the tower crane, it must be no less than 1.5m distance between
the widest slewing part of the crane and around buildings, and the safe distance between any
-
8/18/2019 TC5613-6 - Operation Manual
16/109
parts of the crane and overhead power lines shall comply with the stipulations as shown in
Table 1.2-1.
Auxiliary hoist equipment, sleepers, cables, rope clips and other ordinary tools should be
provided before hand.
Reference size for tower crane erecting site is shown as Fig. 1.2-1.
Drive the trolley to the balance position
before jacking. Slew the jib to the right front of the in-let beam and thenlock the
slewing of tower crane by slewing brake.
It is prohibited to slewing the jib, move the trolley or make the hoist hook up and down
movement during jacking operation.
General layout of tower crane
Assembly relation of main components for
stationary crane (Fig.1.3-1)
-
8/18/2019 TC5613-6 - Operation Manual
17/109
Fig.1.3-1 Assembly relation of main components
1. Foundation
2. Tower Section (a-Section EQ, b-Mast Section EQ,)
3. Climbing frame
4. Slewing ring support
5. Slewing ring
6. Upper support
7. Operator cab
8. Tower head
9. Counter-jib
10. Jib (a=38m, b=44m, c=50m, d=56m)
11. Counter-weight (a=9.85t, b=11.25t, c=13.5t, d=15.3t)
12. Base frame (or undercarriage)
13. Foundation With Undercarriage
The TC 5613-6 tower crane, with embedded anchors or with an
undercarriage, independent hoisting height is 40.5m. 2-fall or 4-fall wire ropes may be used
for hoisting purpose. The tower sections are integral construction of square shaped steel
tube structure. The base section of tower body or the undercarriage is connected to the
foundation.
The lower end of the slewing ring support is the climbing frame, which surrounds the
tower body. According to the construction needs, jacking mechanism can jack the upper
structure of the tower body to let in mast sections for increasing tower crane height.
-
8/18/2019 TC5613-6 - Operation Manual
18/109
Anchored State (shown as Fig.3 and Fig.4)
The maximum hook height can reach 40.5m when crane is stationary with embedded
anchors and 220m when anchored if it is fastened with tie-in onto the building and mast tie
frame. When the height is 110m, hoisting can be done with 2-fall or 4-fall, but if the
height is >110m, only 2-fall can do the job. The required distance between slewing center of
tower and the building is 3.5 meters. As for unusual conditions, please contact Zoomlion for
further consultation
1.3.3.2.1 and 1.3.3.2.2 give consideration to project construction requirements and
force-applied situations of the tower body and anchored frames. They specify the distance
between anchored frame and foundation plane, distance between anchored frames and
suspension height limit above anchored frame. Item 1.3.3.2.3 and 1.3.3.2.3 can satisfy both
ordinary construction needs and facilitate prefabrication of anchored frames most
economically to lower the cost of the tower crane.
With one anchored attachment (Shown as Fig.1.3-2)
The
h1 is the distance from first anchor point to the
foundation surface.
The quantity of tower sections in h1 is:
The height of tower above the anchor point is h0
The quantity of tower sections in h0 is:
Fig.1.3-2
anchored frames or more
-
8/18/2019 TC5613-6 - Operation Manual
19/109
The distance h2 between two anchor points:
The quantity of
tower sections between 2 anchor points is
The height h0of tower above the highest anchor point is
When hook height h is less than100mh0 is the same shown in
1.3.2.1(2).
When hook height h is 100mnamely:n011.5
Fig1.3-3
The least number of anchored frames for the tower crane with embedded anchors (shown as
Fig.3)
With 1 anchored frame, h036.55m, h 68.5m, there are 24 tower sections totally.
With 2 anchored frames, h0m, h 93.7m, there are 33 tower sections totally.
With 3 anchored frames, h0m, h m, there are 41 tower sections
totally.
With 4 anchored frames, h0m, h 141.3m, there are 50 tower sections totally.
With 5 anchored frames, h0m, h 163.7m, there are 58 tower sections totally.
With 6 anchored frames, h0m, h 183.3m, there are 65 tower sections totally.
With 7 anchored frames, h0m, h 202.9m, there are 72 tower sections totally
-
8/18/2019 TC5613-6 - Operation Manual
20/109
With 8 anchored frames, h0m, h 220m, there are 78 tower sections totally
The least number of anchored frames for the tower crane with undercarriage (shown as
Fig.4)
With 1 anchored frame, h036.86m, h 68.8m, there are 22 tower sections totally.
With 2 anchored frames, h035.06m, h 94m, there are 31 tower sections totally.
With 3 anchored frames, h034.26m, h 119.2m, there are 40 tower sections totally.
With 4 anchored frames, h030.66 m, h 141.6m, there are 48 tower sections totally.
With 5 anchored frames, h0m, h 163.7m, there are 56 tower sections totally.
With 6 anchored frames, h0m, h 183.3m, there are 63 tower sections totally.
With 7 anchored frames, h0m, h 202.9m, there are 70 tower sections totally
With 8 anchored frames, h0m, h 220m, there are 76 tower sections totally
Foundation & Counterweight
Loads on Foundation with embedded anchorsshown
as Table1-3Fig.1.4-1
Fig.1.4-1 Load schematic diagram on the foundation
Fv(kN) Fh(kN) M(kN.m) T(kN.m)
In operation
Out of operation
-
8/18/2019 TC5613-6 - Operation Manual
21/109
Foundation with embedded anchors
Reinforced concrete foundations must be adopted. Basic requirements for the
foundation with embedded anchors as following:
1.4.2.1
The concrete strength grade must not be lower than C35. The ground base must
hard ground and the earth endurance must not be less than the specifications as shown in the
table 1-4
Table1-4 1-4
L
Reinforcing steel bar
of upper layer
Reinforcing steel bar
of lower layer
Earth
endurance
Concrete
Weight
Vertical
reinforcing
steel bar
5300
24-
Lengthwise and
crosswise
Lengthwise and
crosswise
5500
Lengthwise and
crosswise
Lengthwise and
crosswise
The depth of the concrete foundation should be more than 1000mm
Adjust the level of the anchors upper surface to ensure that the planeness tolerance is 1/500.
Embedded Anchors Foundation ouring cncrete diagram of embedded anchors
-
8/18/2019 TC5613-6 - Operation Manual
22/109
Install the embedded Anchors
The installation of the embedded anchors is very important, please install them as
following:
Fasten 4 anchors and the base section together with 12 high-tensile bolts (strength rating
10.9).
According to the construction convenience and the progress of binding rebar, hoist the
whole piece of anchors assembled with the base section into rebar net.
Be sure that the number of re-bars around anchors must not be reduced or cut off.
If it is difficult to pass through the anchor, the main reinforcing rod can be turned aside.
EQ
EQ EQ
Gently hoist the whole piece of anchors assembled with the base section EQ so that it is in a
vertical position before placing concrete. Hang plumb lines along the centerline in 2
directions of the base section EQ to ensure that the perpendicularity of the embedded base
section centerline and horizontal plane is less than 1.5/1000.
Concrete filling rate around the embedded anchors must be over 95%.
Installation diagram is shown as Fig.1.4-3.
Foundation Anchor bears the greatest pressure and pull, which should be equipped by the
factory, otherwise the contractor is responsible for the damage caused by incorrectly
prepared foundation anchor or by neglecting the foundation site conditions.
The embedded anchors bear all loads of the crane, so they should be purchased
from our company. Otherwise if the users supply the embedded anchors, you are
responsible for the damage caused by anchors.
It is allowed that the anchors are used one time, and it is forbidden to dig them
out and use again.
(
1.4-4)
Foundation with embedded bolts
Reinforced concrete foundations must be adopted. Basic requirements for the
-
8/18/2019 TC5613-6 - Operation Manual
23/109
foundation with embedded bolts as following:
Dig the foundation to the hard earth (Bearing load should reach the value shown as
Table 1-4), make it level, and then backfill 100mm gravel, after slip-formwork or laying
bricks for the side walls, pour concrete into pre-made reinforced rod net. The concrete block
surface should be 100mm higher than neighboring ground for the drainage of storm water,
then removal the formwork and backfill the neighboring ground with gravels.
Concrete filling rate under pallet should be more than 95%. The upper plane of the four
pallets should be within the same level plane and the pallet are allowed to be inserted into
concrete for 5-6mm.
Fig 1.4-4 Foundation with embedded bolts
-
8/18/2019 TC5613-6 - Operation Manual
24/109
The relative position of the 4 sets of embedded bolts must be correct, and the length
tolerance of the diagonal line should be no more than 2mm after assembling, ensuring the
mounting of the base tower section.
It is allowed to insert pads but no more than 2 pads into the intervals of the base tower
section and the packings. The area of pad should be more than 90% area of the pallet to
ensure that the planeness tolerance is less than 1/750 after installing the base tower section,
and vertical tolerance of central line with level plane is within 1.5/1000.
The embedded bolts should be connected with the reinforcement of lower layer
The bearing load, dimensions L and arrangement of reinforcing rods are shown as
Table 1-3 and Table1-4.
When screwing the embedded bolts, it is prohibitten to knock the wrench with a
sledgehammer.
It is allowed that the embedded bolts are used one time, and it is forbidden to dig
them out and use again. Because the embedded bolts are important parts which bear
the great mass of loads of the crane, we suggest that the bolts should be purchased
from our company. Users fabricate the bolts yourselves, the bolts must conform to the
requirements of drawing. But you are responsible for any damage caused by bolts, if
the bolts are supplied by yourselves.
Foundation for Undercarriage
The ground foundation is the precondition to ensure safe operation of the crane. This
foundation must closely comply with the regulations for different geological conditions. It is
built of 4-blocks as base ballast, made of reinforced concrete. Basic requirements as
follows:
The concrete strength grade shall be no less than C35. The ground under the foundation
-
8/18/2019 TC5613-6 - Operation Manual
25/109
should be solid with the bearing load value specified in the Table 1.4-5. The curing
duration of concrete is more than 15 days
The depth of concrete should be more than 800mm.
The contact level plane between concrete foundation and frame beam should be
calibrated. The level tolerance of four pallets is 1/750.
Dig a pit (1300mm × 1300mm × 400mm) with water drains in the middle part of
4-block foundation for the installing the frame girder.
The relative positions of 4-group embedded bolts shall be accurate to ensure proper
installation.
Hang plumb lines along the centerline in 2 directions of the base section to ensure that
the perpendicularity of the embedded base section centerline and horizontal plane is less
than 1.5/1000.
Concrete filling rate around the four pallets should be over 95.
-
8/18/2019 TC5613-6 - Operation Manual
26/109
Fig.1.4-5 Foundation for Undercarriage
lightning protection
Notes: Not connected with the steel reinforcement of the building foundation.
Counterweight
The counter-weight has two specifications; both are cast with reinforced concrete. For
specific dimensions, refer to Fig. 1.4-6. Basic requirements are as following:
Weigh the counter-weight cast with reinforced concrete. Permitted weight deviation is 2%,
concrete grade no less than C18.
Counterweight should be equipped according to the length change of jib (shown as Table
1-5).
Length change is allowed to change the weight of counterweight, but the weight accuracy of
2% should be secured.
-
8/18/2019 TC5613-6 - Operation Manual
27/109
Fig. Counterweight
-
8/18/2019 TC5613-6 - Operation Manual
28/109
Fig. Counterweight
(Table) 1-5
×
×
Counterweight
Counterweight
××
Counterweight
Counterweight
Erecting
The erection of tower crane shall be conducted only after the concrete strength of
foundation reaches the designed value of 70%.
Erecting sequence shall be conducted in according to Fig. 1.5-1
-
8/18/2019 TC5613-6 - Operation Manual
29/109
1) Tower section 2) Climbing frame 3) Slewing ring
assembly 4) Tower head assembly 5) Counter-jib assembly
6) Counter-jib con-rod 7) 2.250t A block of 2.250t
counterweight 8) operator cab 9) Jib assembly 10)
Jib con-rod 11) () Equip the remaining counterweights
Fig. 1.5-1Installation sequence of stationary crane with embedded anchors
Tower Section Erecting
Structure description
13 EQ7
There are, totally, 14 tower
sections when the hook height is
40.5m, including one base tower
section EQ, 13 tower sections EQ7.
There are a ladder and a platform
in each tower section.
1.5.1-1 EQ7
Fig1.5.1-1 Tower Section EQ7
EQ7 3
There are three bolt joints on the upper and lower ends of each chord of tower section
EQ7,
EQ EQ EQ
EQ 3 EQ 3
Base tower section EQ is divided into the section connected with pre-buried
foundation anchor, which is respectively equipped with three bolt joints on upper and lower
-
8/18/2019 TC5613-6 - Operation Manual
30/109
end of chord, and the section connected the foundation with fang bolts, which is equipped
with three bolt joints at upper end of chord, and a flange at lower end.
,
Be sure that the climbing lugs on the base section are placed perpendicularly to
the building in order to conveniently installing and dismantling the whole tower crane.
Erect two tower sections
1.5.1-2
Fig.1.5.1-2 Erect tower section
EQ7
Hoist a tower section EQ7 (shown as Fig. 1.5.1-2), it is forbidden to hoist on the horizontal
bar. on base tower section EQ7 and screw them together with 12 pieces high-tensile bolts
strength rating 10.9
2) EQ
Hoist a tower section EQ7 onto the base tower section EQ and screw it together with 12
pieces high-tensile boltsstrength rating 10.9
EQ EQ7
Hoist a tower section EQ7 onto the tower section EQ and screw it together with 12 pieces
high-tensile boltsstrength rating 10.9. There are a base tower section EQ, two tower sectin EQ7 onthe foundation.
·
-
8/18/2019 TC5613-6 - Operation Manual
31/109
Tighten all high-tensile bolts with torque up to 1400N·mand each bolt should be equipped
with a washer and two nuts. The loose-proof nut the upper nutshould be fastened
with torque equal to or a little more than 1400N
m
Check the verticality with a theodolitem or a plumb line. The verticality around the main
chord should be within the tolerance of 1.5/1000.
Hoist Climbing Frame
Fig 1.5.2-1 Climbing frame
Structure description(shown as Fig1.5.2-1)
Climbing frame consists of climbing frame structure, platform, climbing stairs,
hydraulic jack system and let-in device for tower section. Its function is jacking and
lowering the tower crane.
Climbing jack is mounted on the beam of rear side of climbing frame (e.g. at the side
of pre-assembled counter jib shown as Fig. 1.5.2-1). Hydraulic pump station is placed on the
platform at one side of jack. 16 wheels are equipped inside of climbing frame. The wheels
support the outside of chord of tower during jack.
For the purpose of safety jack, platforms are provided at the top of and in the middle ofthe climbing frame, including platform on the inlet beam. The worker standing on the
platform during jack can control hydraulic system, inlet tower section and fasten the bolts.
-
8/18/2019 TC5613-6 - Operation Manual
32/109
Hoisting
After pre-assembling the
climbing frame (shown as
1.5.2-2), hoist the frame.
It should be noted that
climbing jack is mounted
at the same side of the
climbing lugs on section.
Enclose the climbing
frame on the outer side of
the mast section slowly
Fig.1.5.2-2 Hoisting Climbing Frame
Place the frame over two tower sections and lower it until the pawl is supported by the
upper climbing lugs of the second tower section (count down up).
,
Fix the jacking cylinder and hoist the hydraulic pump station to one corner of the
platform, connect oil tubes, and check the hydraulic system for normal operation.
Install the Assembly of Slewing Ring
Structure description
The assembly of slewing ring consists of the slewing ring support, slewing ring, upper
support and slewing mechanism. Shown as Fig 1.5.3-1
The lower portion of the ring support is connected to the tower section and the
climbing frame. It is connected to the outer ring of the slewing ring by high-strength bolt at
the upper.
There are flange and platform on one side for the installation of slewing mechanism. On the other side of working platform is welded with a support lug for connection of the
operator cab. There is a support for the installation of slewing limiter on the forepart.
-
8/18/2019 TC5613-6 - Operation Manual
33/109
Fig.1.5.3-1 Slewing Assembly
Hoist and install the assembly of slewing rings
·
·
Check if the torque of M24 high-tensile bolts strength rating 8.8reaches up to
640N.m, and the torque of loose-proof nutsthe upper nutshould be a little more than
or equal to 640N·m.
-
8/18/2019 TC5613-6 - Operation Manual
34/109
Fig. 1.5.3-2hoist the assembly of slewing rings
Shown as Fig. 1.5.3-2hoist the assembly of slewing ring by hooking the four
connecting ears (shoe) at the slewing ring platform.
Put the assembly of slewing ring support on the top of tower. Four-corner marks on slewing
ring support and climbing frame should be aligned during the connection of them.
·
·
Screw them together with 8 pieces high-tensile boltsstrength rating 10.9, and equipping each
bolt with a washer and two nuts. Tightening all the bolts with torque up to 1800N·mthe
loose-proof nut
the upper nut
should be fastened with torque equal to or a little
more than 1800N
m.
Operation of jack system: Jack the climbing frame until it is high enough to be pined
to the slewing ring support with four pins.
-
8/18/2019 TC5613-6 - Operation Manual
35/109
-
8/18/2019 TC5613-6 - Operation Manual
36/109
Shown as Fig. 1.5.4-2hoist the tower head onto the upper support. It should be noted that
the vertical side be faced to the direction of jib. (Shown as Fig.1.5.3-1, 1.5.4-1)
Connect the tower head to the upper support with four pieces of 55 pins.
Install Counter-jib
Structure description(shown as Fig.1.5.5-1)
Fig.1.5.5-1 Counter-jib assembly
The counter-jib is welded structure of channel steel and angle steel. There are banisters,
passage and operating platform on it. The counter-jib consists of two sections. The front end
is connected to the tower head with two pins, and the other end to upper of the tower head
with two stiff con-rods.
Its tail section is equipped with the counter-weight, hoisting mechanism. The resistance box
and the electric control cabinet are arranged at the root of the front section. The hoist
mechanism and its own base frame are fixed on the counter-jib by four bolts.
Hoist counter-jib assembly
-
8/18/2019 TC5613-6 - Operation Manual
37/109
Assemble the two sections of the
counter-jib with banisters, passage
and operating platform on the
ground. And fix the hoisting
mechanism, the electric control
cabinet, the resistance box andcounter-jib con-robs onto the
counter-jib. Connect the slewing
mechanism to the temporary
power supply, and slew the portion
above
slewing ring to a position for
convenient mount of the
counter-jib.
Shown as Fig. 1.5.5-2hoist the
counter-jib (Four mounting ears
are equipped on the counter-jib).
Fig.1.5.5-2 Hoist counter-jib assembly
Fig.1.5.5-3 Counter-jib con-rods assembly
Connect the front end of counter-jib to the tower head with pins.
-
8/18/2019 TC5613-6 - Operation Manual
38/109
Shown as 1.5.5-3 for the counter-jib
con-rod schematic diagram, lift up the
counter-jib slowly to a proper position
for smooth connection of the counter-jib
con-rod to those on the tower head.
Connect the con-rods by pins, insert and
open up cotter pins. (Shown as
Fig.1.5.5-4)
Lay down the counter-jib slowly. Lift a
piece of 2.25T counter-weight at the
furthest position of the counter-jib,
shown as Fig.1.5.5-5.
Fig.1.5.5-4 Install counter-jib con-rod
Special Notice:
Be sure of mounting the baffle of the
counter-weight pins against the
counter-weight.
Be sure of mounting the end face of the
counter-weight pin exceeding
the triangle plate.
Fig.1.5.5-5 Hoisting one piece of 2.25T counter-weight
-
8/18/2019 TC5613-6 - Operation Manual
39/109
Structure description (shown as Fig.1.5.6-1)
The cab is a sheet structure, offset at the front
on the upper support right side platform. There
are large big glass windows on the four sides of
the cab. The upper window in front can be
opened to obtain a wide field of view. The cab
is nice-looking and comfortable, equipped with
inter-active control console.
1.5.6-1
Fig.1.5.6-1 Operator cab
collocation of control console
1.5.6-2
No.
ico
designation
functions explanation
1
star/ring button
Electronic control system start-control-button
Ring-button.
-
8/18/2019 TC5613-6 - Operation Manual
40/109
2
emergency stop button
In abnormal conditions,urgently cut off power of
control system. At the same time,the button can
be used in normal-stop. The button is anto-lock
only when be pressed down,the machine can run.
3
exceed 100% of working
momentalarm-light
When load-moment exceeds100% of working
moment ,the alarm-light is on.
4
exceed 90% of working
momentalarm-light
When load-moment exceeds 90% of workingmoment ,the alarm-light is on.
5
exceed 100% of working
load alarm-light
When load exceeds 100% of working load ,the
alarm-light is on.
6
exceed 50% of working
load alarm-light
When load exceeds 50% of working load ,the
alarm-light is on.
7
operating indication of the
hook raising
When the handle of right collocation of control
console is at this direction, the hook is running
up.
8
operating indication of the
hook falling
When the handle of right collocation of control
console is at this direction, the hook is running
down.
9
operating indication of
running ahead
When the handle of collocation of control
console is at this direction, the trolley is running
ahead.
10
operating indication of
running back
When the handle of collocation of control
console is at this direction, the trolley is running
back.
-
8/18/2019 TC5613-6 - Operation Manual
41/109
11
slewing/braking button
When the button is turn left ,the slewing brake is
off,jib can slew;when the button is turn right, the
slewing brake is on, jib can´t slew.
12
bypass-button
When changing fall or running trollry inside,
pressing down the button, control-system is out
of the control of position-limiter, hoisting or
trolley-radius-changing can run continuesly.
13
start-indicator light
When the electronic control system is start or run
state, the button is on.
14
operating indication of
turning left
When the handle of left collocation of control
console is at this direction, the slewing is turning
left.
15
operating indication of
turning right
When the handle of left collocation of control
console is at this direction, the slewing is turning
right.
16
operating indication of
trolley-radius-changing
outside
When the handle of left collocation of control
console is at this direction, the
trolley-radius-changing is running outside
17
operating indication of
trolley-radius-changing
inside
When the handle of left collocation of control
console is at this direction, the
trolley-radius-changing is running inside
80
The nosie in operator cab is below 80db when the tower crane in working.
Hoist and install the operator cab
-
8/18/2019 TC5613-6 - Operation Manual
42/109
Mount the electric equipment in the cab and then hoist the cab to the front near right
platform of the upper support (Fig.1.5.6-2). Align it with the hole-position of ear-plate and
connect them with three pins and insert cotter pins.
Alternatively assemble on the ground the cab and slewing ring assembly and hoist the
whole piece once for all.
Fig.1.5.6-2 Hoist operator cab
Install jib assembly
Structure description (shown as Fig.1.5.7-1)
The whole jib is a varied cross-section triangle spatial structure, consisting of ten
sections. Section-to-section is connected by pins for the purpose of convenient installing and
dismantling. The root of the first jib section is connected to the tower head by pins. The
second and seventh sections are provided with two hook lugs, through which jib con-rods
are connected to the tower head. The trolley mechanism is mounted in the 2nd section;
maintenance cage is set at the side of trolley for tower crane installation and maintenance.
-
8/18/2019 TC5613-6 - Operation Manual
43/109
Fig 1.5.7-1 Jib structure
Jib sections should be assembled strictly according to the series number marked on each
section, and the jib may be assembled with various jib lengths of 56m, 50m and 44m
according to the construction requirements. Dismantling the 9th section, the jib length is
50m, and dismantling 5th and 9th sections, the jib length is 44m, and dismantling 5th and
8th and 9th sections, the jib length is 38m, shown as Fig. 1.5.7-2.
Fig.1.5.7-2 Jib assembly
Hoist and install jib assembly
Assemble the jib on the flat sleepers (or supports) near the tower crane. No matter how
many the jib length is, the trolley must at first be mounted on the guide rail on the jib lower
chord.
-
8/18/2019 TC5613-6 - Operation Manual
44/109
Mount the maintenance cage to the trolley and move the trolley as close to the
minimum radius point of jib root (foot) as possible.
Mount the traveling mechanism at the jib root section, let two wire ropes from the wire
drum and let one of them pass over the guide pulley at the jib root, and then fix it at the back
of the trolley. Let the other rope pass over the guide pulley at the middle of jib and head
portions and then fix it at the front of the trolley, as shown in Fig. 1.5.7-3. At the rear of the
trolley is provided with three rope clips. And rope clip compression plates must be on the
side of ropes with force applied. The rope clip interval is 6~9 times of the wire rope
diameter. At the front end of the trolley is provided with tensioning devices. If the traction
rope has become loosened, adjust tensioning devices to tension the rope. The jib root section
is provided with another set of rope tensioning devices. Any loosened rope during its
operation can be tensioned by this tensioning set.
Fig. 1.5.7-3 Trolley Wire Rope Layout Plan
After assembling jib con-rods shown as Fig.1.5.7-4, connect it to the jib hook lugson the upper chord of jib with pins, insert cotter pins, then place jib con-rods on the
bracket of upper chord on the jib.
Check and perfect the circuit connection on the jib. Switch on the temporary power
supply of the slewing mechanism to slew the tower crane superstructure to a position for
convenient installation of the jib.
-
8/18/2019 TC5613-6 - Operation Manual
45/109
Fig. 1.5.7-4 Jib pull rod Diagram
Hang up ropes shown as Fig. 1.5.7-5. Try the ropes for balance. In case of improper
balance, move properly the trolley position. Lift the jib assembly to the mount height. Use
the axle-positioning frame and pins to connect the slewing tower body to the root section of
jib and then fasten the connection shown as Fig. 1.5.7-6. Attention: record the jib lifting
point for reference during tower dismantling.
1.5.7-5
Fig.1.5.7-5 position of hoisting the jib
56
56m Jib
50
50m Jib
44
44m Jib
38
38m Jib
-
8/18/2019 TC5613-6 - Operation Manual
46/109
As for the position of center of gravity during jibs installation with different
lengths (incl. long and short tie rods, traveling mechanism, anti-drop device, and
trolley at the minimum radius), refer to the Table below.
2
8
l
20
When hoisting, 8m
L
20m.
The assembled jib should be supported on the ground by at least 5 supports
during winding wire rope.
Fig. 1.5.7-6 Install jib assembly
Fig.1.5.7-7 Hoisting rope layout for installing jib con-rods
-
8/18/2019 TC5613-6 - Operation Manual
47/109
Reeve the hoisting wire rope according to Fig. 1.5.7-7start hoisting winch while
lifting the jib slowly with a mobile crane till jib-tie reaches hauling plate, then fasten short
and long jib-ties to the Plate I and II at the cat head with pins shown as Fig. 1.5.7-8 and Fig.
1.5.7-9, insert split pin, let off wire rope of hoisting winch and lay down jib slowly.
Fig. 1.5.7-8 Tower head structure at the joint of jib con-rod Fig. 1.5.7-9 Joint structure
After connecting jib con-rods to tower head, dismantle the hoisting rope.
Assemble counter-weight
The weight of counter-weight varies in
proportional to the jib length (Table 1-5).
The counter-weight is hoisted
according to the jib length used.
The counter-weight configuration and
mounting position are strictly acted on the
requirements of four jib-length conditions.
Special Notice:
Be sure of mounting the baffle of the counter-weight Fig.1.5.5-5 Hoisting counter-weight
pins against the counter-weight.
-
8/18/2019 TC5613-6 - Operation Manual
48/109
Be sure of mounting the end face of the counter-weight pin exceeding the triangle plate.
Rope-winding system of hoist
mechanism
Fig.1.6-1 Hoisting rope layout
After installation, wind hoisting ropes. As shown in Fig.1.6-1, the hoisting rope is
released from the wire rope drum, passing through the rope discharging pulley, going
through the guide pulley on tower head, going down into the pulley of overload limiter in
the tower head, runing further to the trolley and hook pulley block. It is finally fixed on the
anti-torsion device at the jib tip by rope clips.
Power on and Trial operation
After the installation of the whole crane according to the above steps, check the
verticality of tower body axis at no wind conditions. The verticality tolerance is 4/1000.
Switch on power to all electric circuits according to the electric circuit diagram and start all
mechanisms for test run. Check mechanism for proper operations (details, refer to relevant
instructions). At the same time, check wire ropes at different locations for normal working
and for any friction with structure member. Remove all abnormal cases. If the tower craneneeds to be put into service immediately after the installation, the safety device must be
adjusted as specified in section3.
-
8/18/2019 TC5613-6 - Operation Manual
49/109
-
8/18/2019 TC5613-6 - Operation Manual
50/109
-
8/18/2019 TC5613-6 - Operation Manual
51/109
-
8/18/2019 TC5613-6 - Operation Manual
52/109
Before keeping the tower crane in balance, hoist one tower section EQ7 onto the
introduction platform and then move the trolley to the reference balance position shown as
Fig. 1.8-1. Hoist one mast section or other weights (The trolley position in table is an
approximate value, which must be adjusted according to the actual situation in jacking).
Then remove all the bolts connecting outriggers of the slewing ring support to tower section
EQ7.
Push the operation handle of the hydraulic jacking system to to jack
the climbing frame to a position where the legs of slewing ring support are just disengaged
from the main chord rod of the tower body.
Check if the outrigger of slewing ring support is on the same vertical line with the chord of
the tower section. Check 16 guide rollers on the climbing frame and tower body main chord
rod to make sure that they have the same clearance. This serves to determine whether or not
the tower crane is in balance. If not, adjust the balance position of the trolley until balance is
achieved so as to drop the center of gravity of the upper tower crane onto the position of
jacking cylinder beams.
Record the balance position of the trolley for the convenience of dismantling. This mark
position varies with different jib lengths.
Operate the hydraulic system to lower down the sleeve frame. Connect the slewing ring
support to tower sections with bolts. Jacking operation (shown as Fig. 1.8-2)
Hoist a tower section EQ7 to the top of inlet platform of climbing frame, install four inlet
rolls at the lower end of tower section EQ7, lower the hook slowly so that the inlet wheels
are seated onto the inlet beam properly, Then remove the hook.
Hoist another tower section EQ7 and drive the trolley to the position for balance.
Use the brake on the slewing mechanism to hold the tower superstructure at a slewing
braking status, thus ensuring no slewing movements.
-
8/18/2019 TC5613-6 - Operation Manual
53/109
Remove the eight bolts connecting tower section to slewing ring support.
Fig1.8-2 Operation of Climbing
·
Start hydraulic jack system; extrude the piston of the cylinder place the pins of both
ends of the jack beam into the cradle of the climbing lugs on tower section nearest to the
beam (It should be checked by a specially- designed watchdog). Erect the climbing frame
and the upper part until it reaches the height of 1050mm. Check if there are any strange
sounds, deformation, any self-retreat of piston rod etc, after confirmation, go on to erect
until it reaches the height of half the tower section, the support latches on the climbing
frame pass through a pair of climbing lugs and resets automatically, then retreat the jack to
let the support latches stay at the upper climbing lugs, confirm that the two support latches press the top of climbing lugs and bear the weight of climbing frame and the upper part
without any strange sound and deformation, retreat the piston completely, lift jack beam so
as to support the cradle of climbing lugs. Erect the upper part of tower crane to a height of a
little more than half the tower section so that the space is fit for a tower section, drag the
tower section EQ7 on the inlet platform of climbing frame into upper part of tower, retreat
the jack slightly so that the new tower section EQ7 alight at the top of tower and conduct
proper alignment, remove the inlet wheels, fasten the upper and lower sections with 12
pieces of M30 bolts with torque of 1400kN·m, each bolt must be equipped with two nuts.
-
8/18/2019 TC5613-6 - Operation Manual
54/109
Retreat the jack once more to let the lower of slewing ring support alight at the top of
new mast and conduct proper alignment, then fasten ring support to tower section with eight
pieces of M30 high-tensile bolts, each bolt must be equipped with two nuts. Then a tower
section is mounted. If several sections are to be mounted, just repeat procedures mentioned
aboveAs for proper alignment of slewing ring support with connecting bolt holes, insert
four guiding rods into four bolt holes at the corners of slewing ring support before retreat
the jack.
General Notices of Jacking Operation
Jacking operation is prohibited when the wind speed at the highest top exceeding 14m/s.
Keep the jib in the same direction as the in-let mast section during jacking operation. Stop
the jib with the slewing mechanism brake be sure of the trolley stopping at the
jack-balanced position.
If several tower sections are to be mounted, after mounting a section, all the chords of the
section must be fastened with 8 M30 bolts before hooking another section.
Keep the climbing lugs on the newly added tower section in alignment with those on the
existed sections.
It is prohibited to slew, change work-radius and hoist load without connection of the
slewing ring support to the tower body by 8 M30 bolts.
If the jacking hydraulic system has become abnormal in the course of jacking, stop
immediately the jacking operation, retract the oil cylinder, lower the slewing ring support
onto the top of tower body and use 8 M30 bolts to connect the slewing ring support to the
tower body before removing troubles from the hydraulic system.
When tower section reaches the desired working height, turn the jib to different directions,check if all the joints of the tower section, bolts for foundation are fastened sufficiently with
two nuts.
-
8/18/2019 TC5613-6 - Operation Manual
55/109
Tower anchored onto the building
When the working height of the tower
crane has to be exceeded to its
stand-alone height, the tower body shall
be anchored.
Fig. 1.9-1 Schematic Diagram of Tie Frame
The anchoring devices consist of 4 sets of mast-tie-frames and 4 inner ties. The 4 tie-frames
are fastened into anchoring frames by 24 sets of M20 bolts (strength rating 8.8), nuts and
washers (bolt pre-tensioned moment 370Nm). Anchoring frames are articulated with 3tie-rods on 3 top points. The 3 brace rods shall be kept at the same horizontal level.
Adjusting bolts can be used to push inner tie rods tightly against the 4 chord rods on the
tower body (shown as 1.9-1).
Load on anchoring points
Table 1.9-1 shows the arrangement of tie rod and the load value of anchored points on
the building under certain position condition of tower crane in Fig. 1.9-1. The customers
should decide how to tie their cranes to the building and conduct necessary partial
modifications according to the load value, specific tie locations, local load capacity on the
building etc.
Notice: Load values at anchoring points vary to a great extent with the relative
positions of the tower crane to the building, tie rod layout and size, height of the tower
-
8/18/2019 TC5613-6 - Operation Manual
56/109
body suspension section over body. If the tower crane is anchored at the position
different from Fig. 1.9-1, including different arrangement of tie rods or different
dimensions, please contact our company for further consultation, avoiding major
accident.
±
±
±
±
Fig. 1.9-2 Load on the anchored point
Put on the tie frame on the tower section, push the 4 inner tie rods to the 4 chords on the
tower, connect one end of anchored tie rod to the tie frame with pins, and the other end to
the building.
E
3 sets of anchoring tie rods on each frame shall be kept at the same horizontal plane. If they
are interfered with some positions of the tower section E during mounting of anchoring
frames and inner tie rods, the height of frames will properly be raised or lowered.
The walkway for personnel passage from the building to tower crane can be placed on the
anchoring tie rod, however no stockpiling of heavy objects on it.
During the mount of anchoring device, use the theodolite to check the axis of tower body for
verticality. Its deviation shall not be greater than 4/1000 of the total tower crane height. This
deviation can be achieved by adjusting the length of tie rod.
The connection of tie rods to tie frames, foundation and tie frames to the tower body and
inner tie rod shall be reliable. The inner tie rods shall reliably be pressed against the mainchord rod of the tower body and also be clamped tightly to the web rod of the tower body.
All connection bolts shall be fastened. Adjusting bolts, when properly adjusted, shall be
-
8/18/2019 TC5613-6 - Operation Manual
57/109
tightened by nut. Cotter pins shall be opened as specified. After operation they shall be
frequently checked for looseness. Timely adjustments shall be made just in case.
Notice: No matter how many anchoring is conducted, only the topmost anchoring
tie frame can install the inner tie rod. Namely after each new attachment, the inner tie
rod has to be removed into the newly-anchored frame
Preparations before operation
The pre-operation preparations of the tower crane aim are ensuring its correct control
and smooth operation at safe conditions. Main preparations are to check tower crane
components and to test-run safety devices.
Parts and Components Checking
In order to ensuring the correct erection of tower crane and its safe operation, a series
of test-runs and overall checks of tower crane components shall be conducted.
Check component-to-component connections.
Check the installation of supporting platform and fences.
Check wire ropes for correct
winding, avoiding interference and
friction with other parts.
Check power cables for smooth
and proper routing.
Check if the counter-weights onthe counter-jib are properly fixed.
Clear the lumber on platforms in
order to prevent them from falling
and avoid injuring persons during
tower crane operation.
Fig.1.10-1The mounting positions of whole crane safety devices
Check lubrication surfaces and points.
Test-run for the safety device
-
8/18/2019 TC5613-6 - Operation Manual
58/109
-Safety devices for the tower crane mainly include the travel limiter and load limiter.
The travel limiter includes the hoisting height limiter, slewing limiter and working
radius limiter.
The load limiter includes the hoisting moment limiter and hoisting weight limiter,
otherwise anemometer. Debugging is shown in the Chapter 3 of the Part 2. The mounting
positions of whole crane safety guards are shown in Fig.1.10-1.
Items-checking after tower erection (Table 1.10-2)
1.10-2 table1.10-2
Item
Contents
Foundation
Check if the foot bolts are fastened
Check safety distance between the surrounding power lines and tower crane.
Check power cable for smooth routing to avoid damage.
Tower
section
Check the bolt connection of tower sections
Climbing
frame
Check its connection to slewing ring support
Check if the guide wheels, latches, pin-bolt-connected parts move smoothly
Check if the walkway and fence are fastened
Upper
support,
slewing ring
support and
operator cab
Check if the bolts connecting slewing ring is properly fixed.
Check power cable for smooth passage
Check if the platform and fence are fastened
Check the connection for operator cab
No storage of
lubrication oils, oil cotton yarns and combustible materials in the cab.
Tower head
Check tie rods of jib and counter-jib tie rods for proper installation.
Check ladders, platforms and protection rails.
-
8/18/2019 TC5613-6 - Operation Manual
59/109
Secure that the hoisting rope is properly wired and arranged
Jib
Check connection pins, washers and cotter pins for correct mounting.
Check if the trolley is properly installed and operates smoothly, check
maintenance cage for fixing.
Check hoisting and radius-changing ropes for winding and fixing
Counter-jib
Check counter-jib for fixing
Check protection rails of the counter-jib and walkway. Ensure no foreign
substances on the walkway
Hook
Check rope off-proof devices of the hook and fall-changing device for safety
and reliability
Check hoist hook group for defects influencing operation
Check specifications and models of hoist ropes and radius-changing ropes for
compliance with requirements.
Check wire ropes for wear.
Mechanism
Check mechanism for installation and operation
Check mechanism brakes for correct clearance adjustment
When trolley has moved to its minimum and maximum trolley
radius-changing locations respectively, make sure if steel ropes on wire drum
have over 3 lays for safety.
Check if the ends of steel ropes are loosened or improper compressed.
Safety
device
Check safety device for proper adjustment as specified in the Instructions
Check all ladders, protection rails and rest platforms for properly fastened.
Lubrication
Check lubrication conditions according to the operation instructions.
-
8/18/2019 TC5613-6 - Operation Manual
60/109
Conduct the following tests
after the erection of tower crane (The following test must be done every time when the
tower crane shifts to a new construction site)
No-load test
Conduct operation tests of each mechanism several times. After that, conduct
combined operation tests three times. No abnormal incidents occur from all mechanisms
during these tests. Brakes, operation systems, control systems, interlocking devices and
limiters shall all act accurately and reliably. In case of any trouble occurrence, remove it
immediately.
On-load test
Hoist the loads corresponding respectively to 25%, 50%, 75% and 100% of the rated hoist
load at the maximum working radius for tests. No incidents happen during these tests.
Brakes, operation systems, control systems, interlocking devices and limiters shall all act
accurately and reliably.
Stationary tower crane with
undercarriage installed according to the procedures shown as Fig. 1.10-2
Installation of Undercarriage Assembly
Other assembling procedures are the same as tower crane with embedded anchors.
Fig.1.10-2 Installation sequence of stationary tower crane with undercarriage
-
8/18/2019 TC5613-6 - Operation Manual
61/109
Undercarriage installation
Assembly of
undercarriage
Support cross beam assembly (shown
as Fig.1.10-3)fasten it to the foundation
with embedded bolts and channel steel.
Installation of Undercarriage tower
section1 and 2( shown as Fig.1.10-4)
Fig.1.10-3 Assembly of Undercarriage
Install the tower strut
Fig.1.10-4 Assembly of base tower section and strut
Mount the Base Ballast 1,2. The total weigh is 41.5t (shown as Fig.1.10-5)
-
8/18/2019 TC5613-6 - Operation Manual
62/109
-
8/18/2019 TC5613-6 - Operation Manual
63/109
Chapter Dismantling
Precautions for tower crane dismantle
Conduct maintenance and test-run for the jacking mechanism before moving the tower
crane out of the construction site.
Check limiters, slewing mechanism brakes and similar devices for reliability during test-run.
It is prohibited to use the slewing mechanism, trolleying mechanism and hosting mechanism
before the tower crane mast sections have been dismantled and the slewing ring support has
not been connected to the tower body by 8 M30 high-tensile bolts.
Check frequently the main stressed parts of the jacking mechanism, as the tower crane
dismantling is a heavy and continuous work for the jacking mechanism.
While the jacking mechanism is working, all operating personnel are required to focus their
attention on observing the relative positions of moving parts for being normal (e.g. between
rollers and main chord rods, between climbing frame and tower body.).
Carry out dismantling when the wind speed is lower than 14m/s at the highest point. Take
care of the stockpile location of dismantled parts because the building has been constructedand working site space is limited during tower crane dismantling. No carelessness in this
operation, otherwise personal safety accidents will be likely.
Procedures of Tower dismantling
Special caution: tower dismantling is a highly technical work, especially thedismantling of the mast sections of tower body, counter-weight, counter-jib and jib.
Any slight neglect will cause machine damage, personal injury or death. End-users are
-
8/18/2019 TC5613-6 - Operation Manual
64/109
therefore required to strictly follow the Instructions-specified rules to dismantle these
components. Tower operators shall have been trained and with certificates.
Notice
Pay great attention to the two climbing latches during inlet or dismantle of
tower section EQ7. Inspect if the latches are still in proper level condition.
Move the tower crane to the
dismantling area where there shall beno obstacles influencing the operation.
Carry out tower crane dismantling
according to the sequence as shown in
Fig.2.2-1. Its steps are in opposition to
the steps of tower crane erection.
Strictly follow the Instructions
specified rules in all cases.
Lower down the tower sections
(dismantle anchored devices if any).
Fig.2.2-1 Dismantle of the tower crane
Dismantle counter-weights from counter-jib. (Keep one piece of 2.25t counter-weight).
Dismantle the jib.
Dismantle the last counter-weight.
Dismantle the counter-jib.
Dismantle the operator cab (or dismantle it together with the slewing assembly).
Dismantle the tower head.
Dismantle the slewing ring assembly.
Dismantle the climbing frame and the remanent tower sections.
-
8/18/2019 TC5613-6 - Operation Manual
65/109
Dismantle the tower sections(shown as Fig. 2.2.1-1)
Slewing the jib to the direction for the let-in section (i.e. the opening side of climbing frame)
and place the slewing brake at a braking status, make the tower crane at a balanced jacking
status, and the trolley staying at the balanced position (i.e. in conformity to the balanced
position of the trolley when additional sections are jacked during tower crane erection)
;
Remove the upper and lower bolts connecting of the top tower section EQ7, connect inlet
wheels on the below section.
;,
Extend the jacking cylinder to place the pin bolts onto the slot of the 4th lug counting from
up down. Insert safety pins, jack the superstructure until the bottom of the trolley is movedto 20~50mm away from the top of the section.
-
8/18/2019 TC5613-6 - Operation Manual
66/109
-
8/18/2019 TC5613-6 - Operation Manual
67/109
Hoist the jib lightly and fix the ropes onto pins on the tower head. Start up the hoist
mechanism slowly to make the head of con-rod close to the tower head. Remove the pins
connecting con-rod frame with the tower head, lower con-rods onto the jib and fix them.
Remove wire ropes, remove pins connecting jib with slewing tower body.
Lower the jib and lay it down on the sleeper-cushioned support.
Dismantle counter-jib
Hoist down the last counter-weight. Hoist the counter-jib through 4 hook lugs on the
counter-jib to make the jib tie rod at a loosened status. Remove connecting pins of tie rod
and then dismantle the connections between counter-jib and slewing tower body. Hook the
counter-jib down onto the ground.
Dismantle operator cab
Dismantle tower head
Before dismantling, check the tower head to see if component-to-component is still
connected by power cable.
Dismantle slewing assembly
,
Support the lug changing rods of climbing frames on the tower body and then
dismantle the connection of the slewing ring support with the climbing frame and tower body. Hoist the slewing assembly for dismantling.
Dismantle the climbing frame and tower sections
Slowly hoist the climbing frames out along the mast section main chord rod and place them
down onto the ground.
Hook down the tower sections one by one.
Dismantle of the Undercarriage Assembly
-
8/18/2019 TC5613-6 - Operation Manual
68/109
Dismantle the undercarriage assembly in reversed way of installation.
Attention after tower crane dismantling
The dismantled crane needs to be checked and maintained by technical personnel and
trained maintenance personnel.
Check main stressed structural members for metal fatigue; weld fissure, structural
deformation, etc. Check tower crane parts for damage or collision injury.
After completion of checks, repair the defects found and defects potential. Carry out rust
removing and painting.
-
8/18/2019 TC5613-6 - Operation Manual
69/109
Chapter
Safety Operation
Crane operator and hoist man
The trained crane operators and hoist men are required to strictly follow the regulations as
specified in The Operating Instructions for Tower Crane.
Operators are required to understand the working principles of the tower crane and to
familiarize themselves with its structure and functions and adjustment methods for safety
guards. They are also required to master the operating methods for different performances
as well as the maintenance technique.
Operate the crane strictly according to the hoist characteristics provided in the Instructions.
No over-load operating.
Operate gently the hoist mechanism, slewing mechanism and traveling mechanism. Carry
out low speed-to-high speed conversion progressively. No violent pushing of the operation
handles from the static position (or low-speed) to the intermediate speed or high-speed
position.
It is prohibited to pull, or hoist objects in an inclined way, or hoist the staggered or squeezed
objects and or hoist the objects buried in soil or frozen on ground.
Operators and hoist men are not permitted to leave their working posts while objects are
being hung in the air.
Commanding signals, hand gestures and flag signs shall conform to the specifications.
Operators are required to carefully operate and maintain the crane, as well as to keep work
shift-changing records.
It is prohibited that the operator is drunk, ill or tired on working.
-
8/18/2019 TC5613-6 - Operation Manual
70/109
Mechanical part and others
Working environment temperature for the crane is in the range of -20~+40, wind speed
at the highest working point should be smaller than 20m/s.
All the tower safety guards shall be maintained constantly. No moving and dismantling of
them freely. No over-load operation.
The construction site shall be provided with adequate lighting facilities for night operation.
After the tower crane has been overhauled and transferred to a new site and before
re-erection, observe the following:
Check the articulations for pins cracks, rusting corrosion and damage.
Check the rigid tie rods, wire ropes, pulleys, hoist hooks, fall-changing devices, etc. for
conformity to operating conditions.
Check the metal structure members for deformations and weld fissures to make sure of their
conformity to operating conditions.
Conduct trial operation for the mechanism of hoisting, jacking, slewing,
trolley-radius-changing until they have become normal.
Switch off the main power supply when the crane operation is to be stopped for repair or
maintenance. No operation with power on.
Dispatch special persons at the ground, platform and construction work face to direct crane
operations and contact the operator. Signals hand gestures, flag signs, etc. are absolutelynecessary. Better to carry out communications by walkie-talkie.
Assure the working voltage of the tower crane at 380V±10% range, otherwise crane
electrics will be damaged easily.
Stop all hoisting operations in case of thunderstorm, heavy rain, thick mist or the top wind
speed of the crane is higher than 20m/s.
Provide a proper crane layout plan without spatial interception and interference from
another when several cranes have to work at the same construction site.
-
8/18/2019 TC5613-6 - Operation Manual
71/109
When the operator has switched on power and entered the cab, he should make overall
checks of push buttons, operation handles for non-service conditions. He is not permitted to
press the master push-button until OK confirmed.
The operator must operate the crane strictly according to its technical characteristic
diagrams and hoisting characteristic curves. No over-load operation or forced operation.
During crane working, avoid the hoisting hook touching the ground, causing rope on the
wire drum in an irregular order. If the hook has to be on the ground, pay attention to drum
rope arrangement when it rises again. Make a regular rope arrangement if necessary.
The cage fixed on the side of the trolley is for maintenance. When maintenance of some part
of the jib is necessary, the maintenance person can stand in the cage and do the maintenance
work along with the trolley. The load capacity of the cage is 100kg. No person standing in
the cage when heavy objects are being hoisted. During the assembling of the jib on the
ground and tower erection, cage-to-hoist trolley must be checked for proper connections and
reliability.
When mechanisms are required to operate in a reverse direction, it is necessary to wait for
the motor to stop its clockwise rotation before counter clockwise rotation start.
If the tower crane is found abnormal, stop the crane and switch off the power supply. Do not
operate the crane again until the troubles have been identified and removed.
After crane operation completion at each shift, lift the hoist hook higher than the height of
the highest surrounding obstacle, retract the trolley at the smallest radius and keep the
slewing brake at an open status. The operator cannot leave his post until the power supply
has been switched off.
Before work start at each shift, the operator is required to carry out routine checks of the
pins of such key components as the tower body, jib, slewing support, rigid jib tie rod,
-
8/18/2019 TC5613-6 - Operation Manual
72/109
-
8/18/2019 TC5613-6 - Operation Manual
73/109
Routine check of high-strength bolt
Preparations of high- strength bolt before tower erecting
It is necessary to check these high-strength bolts of connecting tower sections and
slewing assembly before using. And it is necessary to clean the bolts, nuts and washers with
kerosene oil. It is prohibited to use damaged bolts (including rust bolts).
Before using, it is necessary to coat the MoS2 grease on contact surfacs of the bolts,
nuts and washers to equilibrium friction.
Tighten the high-strength bolts
The tighten torque on the nuts must reach the specified torque and the torque of loose-proof
nutsthe upper nutshould be a little more than or equal the specified torque.
Check after installing
Check all bolts 2 times in a week, then one time in a week, then one time in two weeks,
and then one time in a month after erecting the tower crane. Dismantle 2-3 bolt groups each
year and check them for deformation, corrosion, rust, etc.
Repeat usage
The high-strength bolts can be used many times, but agreed with the requirements of
the above item 1.3.1 and the item 1.3.2.
Routine check of wire rope
The wire ropes used in hoisting machinery are easily-worn parts. Lack of proper
maintenance is one of the causes for their short service life.
Carry out timely cleaning of wire ropes and applying of lubrication oil or grease to them.
-
8/18/2019 TC5613-6 - Operation Manual
74/109
Watch over their visible parts as much as possible on each workday so as to find any
damages and deformations. Particularly care about the fixed ropes on machinery. When
finding any apparent changes, report to the person in charge. And such person shall carry
out checks according to item 2.4.2 in The Practical Regulations for Checking and
Rejecting of the Hoisting Machinery-Used Wire Ropes.
Watch over the wire rope on trolley and hook as much as possible on each
workday so as to find that rope is out of the pulley or not. If the rope is out of the
pulley, stop working and wind the rope again.
Chek the wire ropes one time every week.
-
8/18/2019 TC5613-6 - Operation Manual
75/109
-
8/18/2019 TC5613-6 - Operation Manual
76/109
Release the height limiter and radius limiter. Arrange the wire ropes of the trolley to match
mechanical erection.
Test-run (debugging) of hoisting mechanis:
Operate the hoisting handle to watch the hoisting operation. When pulling the handle
inwards, the hoisting hook shall move upwards. When pushing the handle outwards, the
hook shall move downwards. If not so, adjust the phase sequence of power supply of the
hoisting motor to meet the above requirements.
After completion of hoisting test-run, operate the slewing handle and
trolley-radius-changing handle respectively. When pushing the handle to the left, the jib
shall slew to the left. When pushing the handle to the right, the jib shall slew to the right.
When pulling the radius-changing handle inwards, the trolley shall travel inwards. When
pushing the handle outwards, the trolley shall travel outwards. If not so, adjust the phase
sequence of power supply of respective motor to meet the above requirements.
Notice for proper operation
After power supply to the operator cab (before pneumatic switch on), power for the aerial
light and lighting in operator cab can be supplied through switches on the control panel. The
sockets are also available for fan plugs.
Press start-button, and all operating handles shall return to zero, so as to power on the
master contactor.
To prevent reversed slewing or emergency stop from any damage to the tower crane,
electrics are provided with time-delayed devices. When the jib slews to the right (or left), it
cannot immediately slew to the left (or right) at a rated speed. Several-second delay is
necessary. After the slewing handle returned to zero, immediate braking cannot be done due
to several seconds delay.
-
8/18/2019 TC5613-6 - Operation Manual
77/109
No braking and emergency stop at revered slewing though the crane is equipped with
above-mentioned time-delay device.
Before jacking, check the rotation direction of pump station motor in conformity to your
requirements. If not, adjust the rotation to the correct direction. It is prohibited to slew, hoist
and change working radius during jacking. This aims at accident prevention and no breaking
of the power cable due to twisting.
No free adjustment of the time-delayed relay and over-current relay in the control cabinet,
they have been adjusted in the factory as specified. Any component replacements should be
conducted according to the instructions for the electrical system.
Working mechanisms of tower crane