Target Value Design How Can It Benefit You? By David Umstot, PE, CEM Umstot Project & Facilities Solutions, LLC © 2014 Umstot Project & Facilities Solutions, LLC 1

Upload: others

Post on 13-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Target Value DesignHow Can It Benefit You?

By David Umstot, PE, CEM

Umstot Project & Facilities Solutions, LLC

© 2014 Umstot Project & Facilities Solutions, LLC 1

Page 2: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

September 4, 2014

$2B OVERRUN © 2014 Umstot Project & Facilities Solutions, LLC 2

Page 3: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Target Value Design – What is it?

A management practice that drives design to deliver customer values and develops design within project constraints.

3

Page 4: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Source: Ballard

Target Value Design…

• …strives to reduce the waste and rework in the Design/Estimate/Redesign cycle.

• ...requires a fundamental shift in thinking from “expected costs” to “target costs”.

• …necessarily involves cross functional teams. No one person has all the knowledge.

• …cries out for an integrated product/process/cost model.

4

Page 5: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

The Cardinal Rule

The Target Cost Must Never Be Exceeded!!!

© 2014 Umstot Project & Facilities Solutions, LLC 5

Page 6: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Target Value Design Works Using:

• Design-Build

• EPC

• Design-Assist

• CM at Risk

• Integrated Project Delivery

© 2014 Umstot Project & Facilities Solutions, LLC 6

Page 7: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

What is of Value To You?

• Total Cost of Ownership?

• Energy Efficiency?

• Speed to Market?

• No disruption to ongoing business operations?

• Iconic design?

• Improved productivity and occupant satisfaction?

• Sustainable buildings?

© 2014 Umstot Project & Facilities Solutions, LLC 7

Page 8: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Value-Waste Nexus

• How to create value within fixed monetary constraints?

• Eliminate waste

• Enhance value with the savings from waste reduction

© 2014 Umstot Project & Facilities Solutions, LLC 8

Page 9: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Index of Construction Labor Productivity 1964-2012

From: Teicholz (2013)

Non-farm Productivity

Construction

©2014 Umstot Project and Facilities Solutions, LLC

Page 10: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Construction Waste in the U.S.

Current Manufacturing

Waste 26%Support Activity 12%

Current Construction

Waste 57%Support Activity 33%

Value Added 10%

Source: Construction Industry Institute

Value Added 62%

© 2014 Umstot Project & Facilities Solutions, LLC 10

Page 11: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Cartoon By: JC Gatlin

11

Page 12: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Cartoon By: JC Gatlin

12

Page 13: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Cartoon By: JC Gatlin13

Page 14: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Cartoon By: JC Gatlin

14

Page 15: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Cartoon By: JC Gatlin15

Page 16: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Cartoon By: JC Gatlin

16

Page 17: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Cartoon By: JC Gatlin

17

Page 18: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Typical Types of Design Waste:

• Iterative Design• Rework• Lack of Coordination Between Disciplines• Inefficient work flow• Over design of systems (diversity and factors of

safety)• Poor design that generates waste during construction• Designing over allowable budget

© 2014 Umstot Project & Facilities Solutions, LLC 18

Page 19: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Rework Costs (as % of total project costs)

Source: Robin McDonald, 201319

Page 20: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Collaborative Team Is Key

Page 21: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

21

https://www.gov.uk/government/uploads/system/uploads/

attachment_data/file/210099/bis-13-955-construction-

2025-industrial-strategy.pdf

UK Construction 2025 Goals

Page 22: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

22

UK Construction 2025 Goals

Page 23: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

THE BASICS

Target Value Design

© 2014 Umstot Project & Facilities Solutions, LLC 23

Page 24: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Business Case Evaluation (from Ballard)

1. Assess the business case (demand, revenues), taking into account the cost to own and use the facility (business operations, facility operations, facility maintenance, adaptability, durability) as well as the cost to acquire it.

2. Determine minimum acceptable ROI or maximum available funds -- set the allowable cost for the facility.

© 2014 Umstot Project & Facilities Solutions, LLC 24

Page 25: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Business Case Evaluation (from Ballard)

3. Answer: “If we had a facility with which we could achieve our specific purposes, and if we could have that facility within our constraints of cost, location and time, would we do it?”

4. If the answer is yes, and if project delivery is not considered risky, fund the project. If the answer is positive and project delivery is considered risky, fund a feasibility study to answer the question: Can we have the facility we have in mind, will it enable us to achieve our purposes, and can we acquire it within our constraints?

© 2014 Umstot Project & Facilities Solutions, LLC 25

Page 26: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Target Cost

Expected Cost (≥)

Allowable Cost (≥)

© 2014 Umstot Project & Facilities Solutions, LLC 26

Page 27: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Steps During Design

• Set the target cost—typically lower than the budget that assumed current best practice

• Form Target Value Design teams by building system and allocate the target cost to each team

• Use a set-based approach, evaluating sets against target values

• Provide cost and constructability guidelines for design

© 2014 Umstot Project & Facilities Solutions, LLC 27

Source: Ballard

Page 28: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Steps During Design (cont.)

• Promote collaboration: have designers get cost input before developing design options

• Do rapid estimating; hold frequent budget alignment sessions

• Use value engineering proactively

• Hold design reviews with permitting agencies

© 2014 Umstot Project & Facilities Solutions, LLC 28

Source: Ballard

Page 29: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

The Cardinal Rule

The Target Cost Must Never Be Exceeded!!!

© 2014 Umstot Project & Facilities Solutions, LLC 29

Page 30: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Applying the Cardinal Rule

• Whenever improvements in the design result in increased costs, alternative, offsetting savings have to be found elsewhere without compromising value.

• Launching projects whose costs exceed their target is not allowed.

• Refusing to add scope to the project that will exceed target cost.

• The transition from design to construction is managed carefully to ensure that the target cost is indeed achieved.

© 2014 Umstot Project & Facilities Solutions, LLC 30

Page 31: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

How Multiple Systems Interact to Target Cost

© 2014 Umstot Project & Facilities Solutions, LLC 31

Building

System 1

System 2

System 3

System 4

System 5

System 2

System 3

System 4

System 5

System 1

Target Cost Reduction

Current Cost Current Cost Target Cost

Page 32: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

EXAMPLES

Target Value Design

© 2014 Umstot Project & Facilities Solutions, LLC 32

Page 33: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

San Diego Community College District

Target Costing – Project Budget Development

Space Programming

Efficiency

Targeted Cost Per Sq. Ft.

© 2014 Umstot Project & Facilities Solutions, LLC 33

Page 34: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

© 2014 Umstot Project & Facilities Solutions, LLC 34

Page 35: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

35

Page 36: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

36

Page 37: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

THE BASICS

Set-Based Design/Concurrent Engineering

© 2014 Umstot Project & Facilities Solutions, LLC 37

Page 38: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

© 2014 Umstot Project & Facilities Solutions, LLC 38

Page 39: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

© 2014 Umstot Project & Facilities Solutions, LLC 39

Page 40: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

© 2014 Umstot Project & Facilities Solutions, LLC 40

Page 41: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Rebar Alternatives

© 2014 Umstot Project & Facilities Solutions, LLC 41

Page 42: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Set-Based Design – Connection Example

Courtesy: Tipping Mar 42

Page 43: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Set-Based Design – Connection Example

Courtesy: Tipping Mar43

Page 44: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

A3 Report for Structural System Set-Based Design

© 2014 Umstot Project & Facilities Solutions, LLC44

Page 45: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

EXPERIENCE WITH LEAN AND TVD

San Diego Community College District

© 2014 Umstot Project & Facilities Solutions, LLC 45

Page 47: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Mesa College

Social and Behavioral Sciences BuildingBudget: $36.9 million

Construction Start: December 2012

Targeted Completion: September 2014

The Social and Behavioral Sciences building

will consist of approximately 66,000 GSF of

new laboratories and classrooms for the

Behavioral Sciences and Social Sciences

programs. The building will include labs for

the Psychology and Speech programs.

Tracking LEED Gold.

SDCCD TVD Projects in Construction

© 2014 Umstot Project & Facilities Solutions, LLC 47

Page 48: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

SDCCD Completed TVD Projects

Miramar College - Fire Science/

EMT Training FacilityBudget: $16.5 million

Construction Start: July 2013

Completion: July 2014

This facility consists of approximately 22,900 SF to serve as a classroom and activetraining center for the Fire Science and EmergencyMedical Technician (EMT) programs. The facility will have labs, support space, equipment staging, classrooms, offices andan outdoor training area.

© 2014 Umstot Project & Facilities Solutions, LLC 48

Page 49: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Miramar College – Science Building ExpansionBudget: $31.7 million

Construction Start: October 2013

Targeted Completion: November 2014

The new 50,000 SF addition includesnew classrooms, faculty offices, andlaboratories for chemistry, physics,astronomy, geology, microbiology,anatomy, marine biology, biology and lab preparation rooms. The rooflevel includes a greenhouse and observatory.

SDCCD TVD Projects in Construction

© 2014 Umstot Project & Facilities Solutions, LLC 49

Page 50: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

SDCCD TVD Projects in Construction

Mesa College Fitness CenterBudget: $10.4 million

Construction Start: June 2014

Targeted Completion: June 2015

The Fitness Center will be an approximately 25,000 gross square feet facility to house Mesa College's Health Service program and Physical Conditioning program.

© 2014 Umstot Project & Facilities Solutions, LLC50

Page 51: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

City College:

M Building: $6.2M; 15k sq ft

C Building: $20.1M; 31k sq ft

A, D and T Buildings: $48M; more than 130k

sq ft in 3 separate buildings

SDCCD TVD Renovation Design/Build Projects

© 2014 Umstot Project & Facilities Solutions, LLC 51

Page 52: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Wouldn't It Be Nice If You Could...

Average Savings of $900,000 on each of 15 projects

Reduce Average Schedule Delay by 56 days

Enhance Sustainability Objectives by 44%

Reduce Facilities Maintenance Costs by 53%

© 2014 Umstot Project & Facilities Solutions, LLC 52

Page 53: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Why Did San Diego CCD Migrate to Lean?

Built Environment

(+1.6M square feet)

Operating Budgets

(-US$46M)

+ 8

0 p

erce

nt-1

6 p

ercent

© 2014 Umstot Project & Facilities Solutions, LLC 53

Page 54: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Public Owner Benefits

Reduced Waste in Project Delivery

Sustainable Buildings

Reduced Total Cost

of Ownership

Enhanced Value

© 2014 Umstot Project & Facilities Solutions, LLC 54

Page 55: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

By the Numbers – The Database

35 COMPLETED

PROJECTS

US$584M CONTRACT

VALUE

8000 CHANGE ORDERS

© 2014 Umstot Project & Facilities Solutions, LLC 55

Page 56: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Change Order Analysis

•7.73% Total COs

•2.99% E&O COsPre-Lean

•4.43% Total COs

•1.88% E&O COsPost-Lean

© 2014 Umstot Project & Facilities Solutions, LLC 56

Page 57: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Target Costing

11 Projects

Avg. Value:

US$21.8M

83% Met Target Cost; Avg. 7% Below Target Cost

© 2014 Umstot Project & Facilities Solutions, LLC 57

Page 58: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Value as Reduced Maintenance Costs

$3.93/sq.ft.

$1.91

$1.73

$1.46

Over 3 Years

© 2014 Umstot Project & Facilities Solutions, LLC 58

Page 59: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

US$34.6 Million of Waste Eliminated

US$13.6M Total Savings in Reduced COs

US$7.7M Total Savings To Date with TVD

US$13.3M Total Savings over 3 Years in

Maintenance Costs

© 2014 Umstot Project & Facilities Solutions, LLC 59

Page 60: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Lessons Learned

• Clearly define value at the beginning of the project

• Understand the business case constraints

• Specialty trade contractor involvement early is essential!

• Concurrent contemporaneous estimating is crucial!

• Report target cost status first, then design progress

© 2014 Umstot Project & Facilities Solutions, LLC 60

Page 61: Target Value Design How Can It Benefit You?9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78… · Target Value Design –What is it? A management practice that drives design

Questions?

David Umstot, PE, CEM

Umstot Project & Facilities Solutions, LLC

www.umstotsolutions.com