table of contents - waste management€¦ · figure 6-32 stage 2 archaeological...
TRANSCRIPT
Draft Environmental Assessment West Carleton Environmental Centre
chapter 6. detailed impact assessment of the undertaking
T a b l e o f C o n t e n t s Page
6. Detailed Impact Assessment of the Undertaking ......................................... 6-1
6.1 Preferred Alternative Landfill Footprint Option ...................................................6-2 6.2 Facility Characteristics Report...........................................................................6-5
6.2.1 Waste Quantities and Characteristics ....................................................6-5 6.2.2 Site Entrance .........................................................................................6-5 6.2.3 Stormwater Management ......................................................................6-6 6.2.4 Leachate Management and Treatment ..................................................6-6 6.2.5 Leachate Treatment ..............................................................................6-8 6.2.6 Landfill Gas Management ......................................................................6-9 6.2.7 Landfill Development .............................................................................6-9 6.2.8 Site Materials Balance ...........................................................................6-9 6.2.9 Landfill Operations ................................................................................6-9 6.2.10 Landfill Traffic ...................................................................................... 6-10 6.2.11 Site Closure and End Use ................................................................... 6-10
6.3 Study Area ...................................................................................................... 6-11 6.4 Environmental Components ............................................................................ 6-11 6.5 Methodology ................................................................................................... 6-13 6.6 Key Issues and Design Optimization ............................................................... 6-13 6.7 Net Effects on the Environment ....................................................................... 6-15
6.7.1 Atmospheric Environment ................................................................... 6-15 6.7.1.1 Particulate Matter (Dust) ........................................................ 6-15 6.7.1.2 Combustion Emissions .......................................................... 6-22 6.7.1.3 Odour .................................................................................... 6-26 6.7.1.4 Landfill Gas ........................................................................... 6-36 6.7.1.5 Noise ..................................................................................... 6-41
6.7.2 Geology and Hydrogeology ................................................................. 6-49 6.7.2.1 Geology and Hydrogeology Methodology/Additional
Investigations ........................................................................ 6-49 6.7.2.2 Detailed Description of the Geology and Hydrogeology
Environment Potentially Affected ........................................... 6-51 6.7.2.3 Future Baseline Geology and Hydrogeology Conditions ........ 6-56 6.7.2.4 Potential Geology and Hydrogeology Effects ......................... 6-60 6.7.2.5 Geology and Hydrogeology Mitigation and/or
Compensation Measures ....................................................... 6-65 6.7.2.6 Geology and Hydrogeology Net Effects ................................. 6-68
6.7.3 Surface Water ..................................................................................... 6-68 6.7.3.1 Detailed Description of the Surface Water Environment
Potentially Affected ................................................................ 6-70 6.7.3.2 Potential Effects on Surface Water ........................................ 6-70 6.7.3.3 Surface Water Mitigation and/or Compensation Measures .... 6-71
Draft Environmental Assessment West Carleton Environmental Centre
chapter 6. detailed impact assessment of the undertaking
6.7.3.4 Surface Water Net Effects ..................................................... 6-77 6.7.4 Biology – Terrestrial and Aquatic Environment .................................... 6-77
6.7.4.1 Detailed Description of the Biology Environment
Potentially Affected ................................................................ 6-79 6.7.4.2 Potential Effects on Biology ................................................... 6-86 6.7.4.3 Biology Mitigation and/or Compensation Measures ............... 6-89 6.7.4.4 Biology Net Effects ................................................................ 6-96
6.7.5 Archaeology ........................................................................................ 6-99 6.7.5.1 Detailed Description of the Archaeology Environment
Potentially Affected ................................................................ 6-99 6.7.5.2 Net Effects on Archaeology ................................................... 6-99
6.7.6 Cultural Heritage ................................................................................. 6-99 6.7.6.1 Detailed Description of the Cultural Heritage Environment
Potentially Affected .............................................................. 6-102 6.7.6.2 Potential Effects on Cultural Heritage .................................. 6-103 6.7.6.3 Culture Heritage Mitigation and/or Compensation
Measures ............................................................................ 6-103 6.7.6.4 Culture Heritage Net Effects ................................................ 6-105
6.7.7 Transportation ................................................................................... 6-105 6.7.7.1 Transportation (Effects from Truck Traffic)........................... 6-105 6.7.7.2 Transportation (Integrated Gull Management) ..................... 6-111
6.7.8 Land Use ........................................................................................... 6-114 6.7.8.1 Detailed Description of the Land Use Environment
Potentially Affected .............................................................. 6-114 6.7.8.2 Potential Effects on Land Use .............................................. 6-116 6.7.8.3 Mitigation and/or Compensation Measures for Land Use ..... 6-118 6.7.8.4 Land Use Net Effects ........................................................... 6-118
6.7.9 Agriculture ......................................................................................... 6-119 6.7.9.1 Detailed Description of the Agriculture Environment
Potentially Affected .............................................................. 6-119 6.7.9.2 Potential Effects on Agriculture ............................................ 6-119 6.7.9.3 Mitigation and/or Compensation Measures for Agriculture ... 6-122 6.7.9.4 Net Effects on Agriculture .................................................... 6-122
6.7.10 Socio-Economic Environment ............................................................ 6-122 6.7.10.1 Socio-Economic Environment .............................................. 6-122 6.7.10.2 Visual Environment .............................................................. 6-126
6.8 Summary of Net Effects ................................................................................ 6-137 6.9 Cumulative Effects on the Environment ........................................................ 6-142
6.9.1 Cumulative Effects – Approach ......................................................... 6-142 6.9.2 Valued Ecosystem Components (VEC’s) ........................................... 6-144 6.9.3 Results .............................................................................................. 6-147
6.9.3.1 Significance Assessment ..................................................... 6-147
Draft Environmental Assessment West Carleton Environmental Centre
chapter 6. detailed impact assessment of the undertaking
List of Figures
Figure 6-1 Preferred Alternative Landfill Footprint ............................................................6-4
Figure 6-2 Typical Cross-Section of a Generic II – Double Liner System .........................6-7
Figure 6-3 Detailed Impact Assessment Generic Study Areas ....................................... 6-12
Figure 6-4 Particulate Matter Detailed Impact Assessment Sources and Receptor
Locations ...................................................................................................... 6-17
Figure 6-5 Maximum Predicted 24-Hour TSP Contours ................................................. 6-18
Figure 6-6 Maximum Predicted 24-Hour PM10 Contours ............................................... 6-19
Figure 6-7 Maximum Predicted 24-Hour PM2.5 Contours .............................................. 6-20
Figure 6-8 Combustion Emissions Detailed Impact Assessment Sources and
Receptor Locations ....................................................................................... 6-24
Figure 6-9 Odour Detailed Impact Study Area and Receptor Locations ......................... 6-28
Figure 6-10 Intermediate Operation Year – Preferred Leachate Management System
Isopleths of the Maximum Predicted Odour Concentration - 10-Minute
Average Period ............................................................................................. 6-30
Figure 6-11 Intermediate Operation Year – Contingency Leachate Management
System Isopleths of the Maximum Predicted Odour Concentration - 10-
Minute Average Period ................................................................................. 6-31
Figure 6-12 Final Operation Year – Preferred Leachate Management System
Isopleths of the Maximum Predicted Odour Concentration – 10-Minute
Average Period ............................................................................................. 6-32
Figure 6-13 Final Operation Year – Contingency Leachate Management System
Isopleths of the Maximum Predicted Odour Concentration – 10-Minute
Average Period ............................................................................................. 6-33
Figure 6-14 Landfill Gas Detailed Impact Study Area and Receptor Locations ................ 6-38
Figure 6-15 Noise Detailed Impact Study Area and Receptor Locations .......................... 6-42
Figure 6-16 Geology and Hydrogeology Detailed Impact Assessment Study Area .......... 6-50
Figure 6-17 Modelled Groundwater Heads in the Regional Area, Future Baseline
Conditions .................................................................................................... 6-58
Figure 6-18 Modelled Groundwater Head Contours in the Site-Vicinity, Future
Baseline Conditions ...................................................................................... 6-59
Figure 6-19 Predicted Chloride Concentrations under Future Baseline Conditions .......... 6-61
Figure 6-20 Modelled Groundwater Head Contours in the Site-Vicinity, Assuming
Operation of the New Landfill Footprint and Stormwater Management
Ponds ........................................................................................................... 6-62
Draft Environmental Assessment West Carleton Environmental Centre
chapter 6. detailed impact assessment of the undertaking
Figure 6-21 Predicted Chloride Concentrations, Assuming Operation of the New
Landfill Footprint and Stormwater Management Ponds ................................. 6-64
Figure 6-22 Predicted Chloride Concentrations, Assuming Operation of the New
Landfill Footprint and Stormwater Management Ponds, and with
Mitigation Measures In-Place ........................................................................ 6-67
Figure 6-23 Surface Water Detailed Impact Assessment Study Area .............................. 6-69
Figure 6-24 Proposed Stormwater Management Ponds .................................................. 6-75
Figure 6-25 Conceptual Cross-section – Two Stage Stormwater Facility ......................... 6-76
Figure 6-26 Biology Detailed Impact Assessment Study Area ......................................... 6-78
Figure 6-27 Vegetation Communities ............................................................................... 6-80
Figure 6-28 Wildlife Observations .................................................................................... 6-82
Figure 6-29 Fish Habitat Classification ............................................................................ 6-83
Figure 6-30 Biology Net Environmental Effects ................................................................ 6-98
Figure 6-31 Archaeology Study Area ............................................................................. 6-100
Figure 6-32 Stage 2 Archaeological Assessment ........................................................... 6-101
Figure 6-33 Location of Cultural Heritage Components ................................................. 6-104
Figure 6-34 Transportation Effects from Truck Traffic Detailed Impact Assessment
Study Area .................................................................................................. 6-106
Figure 6-35 Land Use Detailed Impact Assessment Study Area .................................... 6-115
Figure 6-36 Agriculture Detailed Impact Assessment Study Area .................................. 6-120
Figure 6-37 Soils and Farm Locations ........................................................................... 6-121
Figure 6-38 Socio-Economic Detailed Impact Assessment Study Area.......................... 6-123
Figure 6-39 Socio-Economic – Visual Detailed Impact Assessment Study Area ............ 6-127
Figure 6-40 Existing Viewpoints of Preferred Alternative Landfill Footprint Site ............. 6-130
Figure 6-41 Viewpoints of Preferred Alternative Landfill Footprint .................................. 6-131
Figure 6-42 Possible Landscape Treatments to Screen from Adjacent Surrounding
Areas – View from northwest along William Mooney Road of Preferred
Landfill Footprint with no screening treatment. ............................................ 6-133
Figure 6-43 Possible Landscape Treatments to Screen from Adjacent Surrounding
Areas – View from Northwest along William Mooney Road of Preferred
Landfill Footprint with Possible Natural Landscape Screening Treatment ... 6-134
Figure 6-44 Possible Landscape Treatments to Screen from Adjacent Surrounding
Areas – View from Southeast Along Carp Road of Preferred Landfill
Footprint with No Screening Treatment ...................................................... 6-134
Figure 6-45 Possible Landscape Treatments to Screen from Adjacent Surrounding
Areas – View from Southeast Along Carp Road of Preferred Landfill
Footprint with Possible Landscape Screening Treatment ........................... 6-135
Draft Environmental Assessment West Carleton Environmental Centre
chapter 6. detailed impact assessment of the undertaking
Figure 6-46 Possible Landscape Treatments to Screen from Adjacent Surrounding
Areas – View from Northeast Along Richardson Side Road of the
Preferred Landfill Footprint with No Screening Treatment ........................... 6-135
Figure 6-47 Possible Landscape Treatments to Screen from Adjacent Surrounding
Areas – View from Northeast Along Richardson Side Road of the
Preferred Landfill Footprint with Possible Landscape Screening
Treatment ................................................................................................... 6-136
Figure 6-48 Additional WCEC Facilities ......................................................................... 6-145
List of Tables
Table 6-1 Key Design Issues Identified in the Detailed Impact Assessment ................. 6-13
Table 6-2 Modifications to the FCR .............................................................................. 6-14
Table 6-3 Potential Increase in Sound Levels over Existing Conditions –
Landfill Operations ........................................................................................ 6-47
Table 6-4 Summary of Vegetation Removed ................................................................ 6-96
Table 6-5 Interior Forest Habitat Removed ................................................................... 6-97
Table 6-6 Intersection Analysis Results ...................................................................... 6-108
Table 6-7 Summary of Predicted Net Effects on the Environment .............................. 6-137
Table 6-8 Description of Additional WCEC Facilities and Existing Projects and
Facilities ..................................................................................................... 6-143
Table 6-9 Valued Ecosystem Components ................................................................. 6-146
Table 6-10 Cumulative Effects ...................................................................................... 6-148
Table 6-11 Interaction of Residual Cumulative Effects with Other Projects and
Activities ..................................................................................................... 6-148
Table 6-12 Significance Assessment Framework ......................................................... 6-149
Table 6-13 Significance of Residual Effects .................................................................. 6-151
Draft Environmental Assessment West Carleton Environmental Centre
6-1
chapter 6. detailed impact assessment of the undertaking
6. Detailed Impact Assessment of the Undertaking
Following the confirmation of Option #2 as the Preferred Alternative Landfill Footprint and Off-
site Effluent Discharge to City of Ottawa Sanitary Sewer in combination with On-site Tree
Irrigation as the Preferred Leachate Treatment Alternative, a Detailed Impact Assessment of the
preferred alternative was undertaken. The purpose of the Detailed Impact Assessment is to
identify the potential environmental effects associated with the implementation of the Preferred
Alternative Landfill Footprint and Leachate Treatment Alternative; to develop mitigation or
compensation measures to address potential adverse environmental effects; and to determine
any remaining net effects following the application of mitigation and/or compensation measures.
The intent of the Detailed Impact Assessment is to review the mitigation measures and resultant
net effects from the Alternative Methods stage within the context of the preliminary design
developed for the Preferred Alternative Landfill Footprint. The preliminary design is presented in
the Facility Characteristic Report (FCR) and outlines the design and operations information for the
Preferred Alternative Landfill Footprint (Option #2) and provides information on the following:
site layout design;
surface water management;
leachate management;
gas management; and,
landfill development sequence and daily operations.
The FCR also provides estimates of parameters relevant to the detailed impact assessment
including estimates of leachate generation, contaminant flux through the liner system, landfill
gas generation, and traffic levels associated with waste and construction materials haulage.
With a more detailed description of the preferred landfill footprint, a more detailed understanding
of the environment was developed by each of the Technical disciplines. The previously
identified potential effects and recommended mitigation or compensation measures associated
with the Preferred Alternative Landfill Footprint in the Comparative Evaluation phase were
reviewed to ensure their accuracy in the context of the preliminary design presented in the FCR.
Based on the review, the potential effects, mitigation or compensation measures, and net
effects associated with the Preferred Alternative Landfill Footprint were confirmed and
documented in stand-alone Detailed Impact Assessment Reports (See Supporting Document
#5). In addition to identifying mitigation or compensation measures, potential enhancement
opportunities as well as monitoring requirements associated with the preliminary design for the
Preferred Alternative Landfill Footprint were also be identified, where possible.
Draft Environmental Assessment West Carleton Environmental Centre
6-2
chapter 6. detailed impact assessment of the undertaking
In addition to assessing the impacts from the preferred landfill footprint option, the technical
disciplines also reviewed the potential impacts from the other WCEC facilities, including the
preferred leachate treatment method. As part of the approved Terms of Reference (ToR), WM
committed to undertaking an assessment of the cumulative effects of the landfill and other
WCEC components/facilities and other non-WCEC projects/activities that are existing, planned
and approved or reasonably foreseeable. The assessment of cumulative environmental effects
is not an aspect normally considered in the OEAA, but is part of the federal EA process under
the Canadian Environmental Assessment Act (CEAA). It should be noted that while the
additional assessment of effects of the non-landfill WCEC components is not required under the
OEAA, it was undertaken based on the ToR commitment and in general, good EA practice.
The technical team reviewed potential impacts on the environment from the additional WCEC
components/facilities, as well as any impacts that may arise from these facilities in tandem/
conjunction with the preferred landfill footprint.
The additional facilities include the following:
A material recycling facility;
A construction and demolition material recycling facility;
An organics processing facility;
Residential diversion facility;
Community lands for parks and recreation;
A landfill-gas-to-energy facility; and
Greenhouses.
Further, the team reviewed other projects/activities within proximity to the landfill, which may act
in a cumulative fashion.
6.1 Preferred Alternative Landfill Footprint Option
In order to undertake the Detailed Impact Assessment it was necessary to further refine the
design plans for the Preferred Alternative Landfill Footprint from the conceptual design stage, as
described in the Conceptual Design Report (CDR) (Supporting Document #2 – Alternative
Methods Evaluation – Landfill Footprint Alternatives). Refinements were based on
additional, more detailed site specific data influencing the engineered features and design of the
landfill. Stakeholder comments received during the EA process were also considered in making
refinements to the landfill footprint. The purpose of the refinements was to further avoid or
mitigate potential adverse environmental effects, as identified in the net effects analysis during
the Alternative Methods phase of the EA. These refinements are captured in the Facility
Characteristics Report (FCR), described in further detail in Section 6.2.
Draft Environmental Assessment West Carleton Environmental Centre
6-3
chapter 6. detailed impact assessment of the undertaking
The southern half of the Preferred Alternative Landfill Footprint is on WM-owned lands and the
northern half is on lands that WM has options to purchase. A 100 m buffer is maintained
between the north limit of the Preferred Footprint and the private lands to the north (e.g., lands
which front onto Richardson Side Road) in accordance with Ontario Regulation 232/98, and an
approximate 350 m buffer is maintained between the east limit of the footprint and Carp Road. A
light industrial building (e.g., the Laurysen building) is situated in the eastern portion of WM
optioned lands, which WM anticipates using for equipment storage/maintenance or waste
diversion activities in the future. An approximate 45 to 50 m buffer is maintained between the
toe of slope of the existing and new landfills, thus allowing sufficient area for a new waste haul
road to the new footprint, and for maintenance and monitoring access. The location of the west
limit of the Preferred Alternative Landfill Footprint was determined by maintaining the noted
buffers and providing the required 6,500,000 m3 capacity, while maintaining the landfill elevation
below 158 mASL (as reported in the CDR) and maintaining side slopes required by Ontario
Regulation 232/98 (e.g., varying from 4H to 1V to 5%). This results in an approximate 146 m
buffer between the west limit of the Preferred Footprint and William Mooney Road. This buffer
preserves a portion of the existing woodlot within the west part of the WM-owned lands.
The final contours of the landfill are shown in Figure 6-1 and reflect a rectangular landform with
a maximum elevation (top of final cover) of 155.7 mASL. This elevation is approximately 30.7 m
above the surrounding existing grade. By comparison, the maximum elevation of the existing
Ottawa WMF landfill is approximately 172 mASL or approximately 47 m above the surrounding
existing grade. The contours reflect maximum side slopes of 4H to 1V, and a minimum slope of
5%. The total footprint area of the new landfill is 37.8 ha.
The base grades for the landfill have been developed such that the base of the landfill liner
system will be at or above the predicted maximum shallow groundwater level.
Slope stability analyses were performed to assess the potential effect of ground motion due to
seismic activity on the slope stability of the landfill and liner system. Eastern Canada is part of
the stable interior of the North American Plate and the damage potential of an earthquake is
determined by how the ground moves. Expected ground motion can be calculated on the basis
of probability, and the expected ground motions are referred to as ‘seismic hazard’. With the
selection of appropriate liner materials, the seismic slope stability analyses results suggested
that the slope stability of the landfill and liner system can have an adequate factor of safety
under seismic condition with the peak ground acceleration. Detailed assessment of stability of
the landfill and liner system will be carried out using updated input parameters during the
detailed design of the landfill to confirm that appropriate materials are selected and to ensure
that adequate factor of safety is achieved.
Draft Environmental Assessment West Carleton Environmental Centre
6-4
chapter 6. detailed impact assessment of the undertaking
Figure 6-1 Preferred Alternative Landfill Footprint
Draft Environmental Assessment West Carleton Environmental Centre
6-5
chapter 6. detailed impact assessment of the undertaking
6.2 Facility Characteristics Report
A Facility Characteristics Report (FCR) was prepared in order to more accurately define
potential environmental effects and mitigation or compensation measures identified for the
Preferred Alternative Landfill Footprint during the Alternative Methods phase of the EA. The
FCR also describes enhancement opportunities and approval requirements associated with the
implementation of the Preferred Alternative Landfill Footprint. The FCR presents preliminary
design and operations information for the Preferred Alternative Landfill Footprint and provides
information on all main aspects of landfill design and operations.
The FCR also provides estimates of parameters relevant to the Detailed Impact Assessment
including estimates of leachate generation, contaminant flux through the liner system, landfill
gas (LFG) generation, and traffic levels associated with waste and construction materials
haulage. The FCR is included as Supporting Document #4 – Facility Characteristics Report.
Key components of the site design outlined in the FCR are summarised in the subsections
below. A description of the other WCEC facilities has been included in the Cumulative Effects
section of this Chapter.
6.2.1 Waste Quantities and Characteristics
WM anticipates receiving an average of 400,000 tonnes/yr of waste over a 10 year period,
consisting primarily of institutional, commercial, and industrial waste, as well as residential
waste and ‘Special’ waste. ‘Special’ waste consists primarily of impacted soils that may be used
for daily or interim cover. The composition of the waste stream is expected to vary based on
actual waste sources.
6.2.2 Site Entrance
Given the location of the Preferred Footprint relative to the existing Ottawa WMF, a new site
entrance is proposed for the WCEC. The new landfill site entrance will be located off Carp
Road, approximately 640 m south of Richardson Side Road. The entrance roadway leading to
the scale facility is approximately 400 m long and will provide truck queuing to address the
potential for queuing on Carp Road. The entrance to the existing Ottawa WMF was deemed not
ideal due to poor sight lines along Carp Road to the north, and close proximity to entrances of
industrial operations on the east side of Carp Road. The proposed entrance location improves
sight lines to the north, maintains adequate separation from the intersection of Richardson Side
Road and Carp Road, and increases distance from the intersection of Carp Road and
Highway 417.
Draft Environmental Assessment West Carleton Environmental Centre
6-6
chapter 6. detailed impact assessment of the undertaking
6.2.3 Stormwater Management
Stormwater management (SWM) for the expanded site will be achieved through integration of
an existing and proposed system of ditches, culverts, storm sewers and ponds that have been
designed to mitigate the impacts of stormwater runoff on water quantity and water quality before
discharge. The proposed SWM system for the new landfill will be similar to the system for the
existing Ottawa WMF landfill in that surface water runoff will recharge to groundwater and will
not directly discharge off-site.
Three new SWM ponds are proposed for the WCEC:
One near the northeast corner of the new landfill to accommodate flow from
the new landfill (once capped) and the maintenance/service road; and
Two near the southeast corner of the new landfill: one to accommodate flow
from the new waste haul road; and one to replace an existing SWM pond that
will be displaced by the new landfill.
Each pond will consist of two stages with flow control between the two stages:
The first stage will be lined and will function as a sedimentation pond and a
containment pond where runoff can be stored;
The second stage will be unlined to permit recharge to groundwater; and
Each stage will be designed to contain a 1:100 year storm event.
6.2.4 Leachate Management and Treatment
WM intends to design the leachate control system for the site with the Generic II – Double Liner
System as specified in Ontario Regulation 232/98, or MOE-approved equivalent. The Generic II
system consists of following components (from top down):
0.3 m thick granular/perforated pipe primary leachate collection system (lcs);
Minimum 0.75 m thick geomembrane/engineered clay composite primary liner;
0.3 m thick granular/perforated pipe secondary lcs;
0.75 m thick geomembrane/engineered clay composite secondary liner; and
1 m thick natural or constructed soil attenuation layer.
The Generic II design also includes suitable separator layers (geotextile or layer of graded
granular material) between the waste and underlying primary lcs, and between granular layers
and soil or liners. A typical cross-section through the liner system is shown in Figure 6-2.
Draft Environmental Assessment West Carleton Environmental Centre
6-7
chapter 6. detailed impact assessment of the undertaking
Figure 6-2 Typical Cross-Section of a Generic II – Double Liner System
Draft Environmental Assessment West Carleton Environmental Centre
6-8
chapter 6. detailed impact assessment of the undertaking
The landfill base grades will be sloped to the northeast toward a single low point, where a
pumping station will convey leachate to a leachate treatment system, and the final cover system
will meet the requirements of Ontario Regulation 232/98.
6.2.5 Leachate Treatment
Preferred Method
The preferred leachate treatment system for the new landfill consists of disposal of leachate
through discharge to the City of Ottawa sanitary sewer system, in tandem with disposal through
irrigation of trees. For sewer disposal, collected leachate may require pretreatment on-site using
either chemical and/or biological processes in order to meet the City’s sewer use by-law. The
leachate effluent would then be discharged to an existing forcemain at Carp Road and Highway
417. The effluent would be further treated at the City’s Robert O. Pickard Environmental Centre
(ROPEC) facility. Leachate would also be disposed through irrigation of poplar and/or willow
trees on-site. The leachate may require partial or full on-site treatment using chemical and/or
biological processes prior to irrigation. The treated leachate will be discharged to the tree
plantation during days with suitable weather conditions. No liquid effluent would leave the
WCEC site.
Contingency Method
As a contingency in the event discharge to the City’s sanitary sewer is unavailable, evaporator
technology could be utilized to dispose of leachate. Leachate from the landfill would be pumped
to an equalization tank that will provide storage to handle peaks in leachate generation. The
leachate would then be fed to the evaporator for processing. The evaporator system may utilize
landfill gas as the energy source to evaporate the leachate or waste heat from the landfill gas
co-generation facility. Depending upon the strength of the leachate and the resulting air quality
emissions, the leachate may have to be pretreated using a chemical and/or biological process
prior to evaporation.
Emergency Method
In an emergency (e.g., if the preferred method were unavailable for a period of time) leachate
could be trucked to one or more wastewater treatment plants outside Ottawa for disposal. The
collected leachate may require pretreatment using chemical and/or biological processes if
required to meet the quality parameters of the receiving wastewater treatment plant(s). The
potential options for receiving the leachate in the surrounding area are not currently known.
Draft Environmental Assessment West Carleton Environmental Centre
6-9
chapter 6. detailed impact assessment of the undertaking
6.2.6 Landfill Gas Management
The proposed LFG collection system for the new landfill will be designed in accordance with
Ontario Regulation 232/98 and will incorporate an active gas collection approach, including a
series of horizontal and vertical collectors that will convey gas to the existing utilization and
flaring facility. Active gas collection will start within several years of commencement of waste
placement to ensure that landfill odour is controlled. Perforated horizontal collectors will be
installed in the landfill as filling progresses. Vertical wells will be installed once the fill
thickness is sufficient.
6.2.7 Landfill Development
For planning purposes it has been assumed that the landfill liner system would be developed in
approximately eight (8) stages with an area of 47,250 m2 each. The size of liner development
stages may be varied during more detailed design work. The layout of the liner stages is shown
in Figure 6-1. The sequence of the proposed development of the new landfill will be as follows:
The liner system will be built in eight, equally-sized stages.
Liner Stages 1 and 2, the new site entrance and roads, scale facility, and
SWM ponds would be constructed prior to commencement of waste receipt.
Liner Stages 3 through 8 will be constructed as required by waste receipts.
Final cover construction will commence after waste filling has reached final
design contours.
6.2.8 Site Materials Balance
The new landfill construction will utilize both on-site and imported materials. It is estimated that
a net volume of 333,000 m3 of fill will need to be imported.
6.2.9 Landfill Operations
The proposed operation of the new landfill will be as follows:
The size of the working face will minimize the area of exposed waste;
The working face location will be adjusted as required to provide shelter from
prevailing winds;
Berms will be constructed as required to attenuate visual and noise impacts;
Portable litter fences will be used around the working face to capture litter;
Draft Environmental Assessment West Carleton Environmental Centre
6-10
chapter 6. detailed impact assessment of the undertaking
Waste compaction will begin immediately after placement and spreading;
Cover material will be readily available and the working face will be fully
covered at the end of each operating day; and,
A comprehensive monitoring and maintenance program will be implemented
to address all aspects of the landfill operation, including waste inspection and
monitoring of landfill odour.
6.2.10 Landfill Traffic
Truck traffic associated with the landfill construction and operation includes trucks hauling waste
and haulage of construction materials for base grading earthworks, liner, leachate collection
system and final cover construction. The traffic analysis used 2005 operating conditions at the
existing Ottawa WMF, which reflected peak activity at the site (i.e., 50 trips per hour - 25 in, 25
out) and was considered to be conservative relative to the new landfill operation. Traffic will also
be generated by importing construction materials.
The proposed site development sequence results in the following traffic scenarios:
Site Preparation Prior to Landfilling: ............................ up to 45 trips/hour
Routine Phase 1 Operations: ...................................... up to 73 trips/hour
Routine Phase 2 Operations: ...................................... up to 50 trips/hour
Phase 2 Operations Approaching Closure: ................. up to 63 trips/hour
6.2.11 Site Closure and End Use
Site closure will follow the completion of the landfill to the approved final contours. Closure
activities include final cover construction, removal of roads and waste receipt facilities that are
not required in the post closure period, and implementation of a long-term monitoring and
maintenance program. The closure plan will be developed as part of EPA-level work. Site end
use will be determined by WM in consultation with the local community and other stakeholders.
Potential end uses may include public open space (e.g., park) that could accommodate various
passive or active recreational activities, or a restricted access open space. Ongoing landfill
monitoring and maintenance requirements will need to be incorporated into End Use planning.
Draft Environmental Assessment West Carleton Environmental Centre
6-11
chapter 6. detailed impact assessment of the undertaking
6.3 Study Area
The general On-Site, Site-Vicinity, and Regional study areas for the Preferred Alternative
Landfill Footprint at the WCEC are shown in Figure 6-3 and listed below:
On-Site ............. the lands required for the Preferred Alternative Landfill
Footprint;
Site-Vicinity ...... the lands in the vicinity of the Preferred Alternative Landfill
Footprint, extending about 500 m in all directions; and,
Regional ........... the lands within approximately 3 to 5 km of the Site and the
Preferred Alternative Landfill Footprint for those disciplines that
require a larger analysis area (i.e., socio-economic, odour,
etc.).
These generic Study Areas were modified during the Detailed Impact Assessment to suit the
requirements of each individual environmental component and to incorporate the Preferred
Leachate Treatment Alternative.
6.4 Environmental Components
Detailed Impact Assessment Reports were prepared for the following disciplines:
Atmospheric (Air Quality,
Combustion Emissions, Odour,
Landfill Gas and Noise)
Geology and Hydrogeology
Surface Water
Biology
Archaeology
Cultural Heritage
Transportation (Effects from Truck Traffic
and Integrated Gull Management)
Land Use
Agriculture
Socio-Economic (including Visual)
A summary of the findings of the Detailed Impact Assessment in relation to each of the
environmental components listed above is provided in the following subsections. The individual
Detailed Impact Assessment reports can be found in Supporting Document #5 – Detailed
Impact Assessment Reports.
Draft Environmental Assessment West Carleton Environmental Centre
6-12
chapter 6. detailed impact assessment of the undertaking
Figure 6-3 Detailed Impact Assessment Generic Study Areas
Draft Environmental Assessment West Carleton Environmental Centre
6-13
chapter 6. detailed impact assessment of the undertaking
6.5 Methodology
The discipline-specific Detailed Impact Assessments were based, in part, on the findings of the
existing conditions investigations and comparative evaluation exercise completed during the
previous stages of the EA. The net effects associated with the four Alternative Landfill Footprint
Options identified during the Alternative Methods phase of the EA were based on conceptual
designs. These effects were reviewed within the context of the preliminary design plans
developed for the Preferred Alternative Landfill Footprint, as identified in the FCR, to determine
the type and extent of any additional investigations required for each discipline to ensure a
comprehensive assessment of net effects.
The previously identified potential effects and recommended mitigation or compensation
measures associated with the Preferred Alternative Landfill Footprint documented in Chapter 5
– Alternative Methods of Carrying out the Undertaking and further in Supporting
Document #2 – Alternative Methods Evaluation – Landfill Footprint Options were reviewed
to ensure their accuracy in the context of the preliminary design for the Preferred Alternative
Landfill Footprint, or updated based on additional investigations carried out during the Detailed
Impact Assessment phase of the EA.
Following this exercise, the requirements for monitoring in relation to net effects were identified
for each discipline, where appropriate. Finally, any approvals required as part of the
implementation of the Preferred Alternative Landfill Footprint were identified.
6.6 Key Issues and Design Optimization
The preliminary results of the Detailed Impact Assessment revealed some key issues in relation
to the proposed design of the Preferred Alternative Landfill Footprint. These key issues, as well
as the recommended mitigation measures through design optimization, are summarized in
Table 6-1 below.
Table 6-1 Key Design Issues Identified in the Detailed Impact Assessment
No. Issue & Explanation Alternative Solutions Recommended Mitigation/
Design Change
1 Groundwater Contamination
from Existing Landfill Groundwater modelling for
existing landfill footprint shows predicted exceedances of
Reasonable Use Guideline B-7 at the northern property line within
10+ years.
Place purge wells between
existing and new landfill footprints Place purge wells on north side
of new landfill footprint Move location of stormwater
ponds to avoid infiltration to groundwater in eastern portion of
the site
Place purge wells between
existing and new landfill footprint
Draft Environmental Assessment West Carleton Environmental Centre
6-14
chapter 6. detailed impact assessment of the undertaking
Table 6-1 Key Design Issues Identified in the Detailed Impact Assessment
No. Issue & Explanation Alternative Solutions Recommended Mitigation/
Design Change
2 Landfill Liner Base Grades/
Groundwater Levels
Infiltration of stormwater through
ponds to groundwater causes
localized changes in predicted
maximum shallow groundwater
level. Separation of liner base
and groundwater levels required
as per regulation 232/98.
Move location of stormwater
ponds to minimize effects on
groundwater levels in eastern
portion of the site.
Change stormwater management
from groundwater infiltration to
surface discharge off-site.
Raise base of landfill liner to
maintain separation distance
from predicted maximum shallow
groundwater levels.
Raise base of landfill liner to
maintain separation distance
from predicted maximum shallow
groundwater levels.
2 Landfill Operation on Noise
Atmospheric (noise) modelling
shows a predicted exceedance at
northeast corner of proposed new
landfill footprint. Issues caused
by proximity of a sensitive
receptor (residence immediately
to the north on land not owned or
optioned by WM), height of
landfill and dispersion of
operational related noise.
Build temporary earth berm
(approx. 7 m high x 100 m long)
along the landfill working face for
each lift
Build waste berm with interim
cover and use as an attenuation
measure until each lift is
complete and covered with final
cover
Build waste berm with interim
cover and use as an attenuation
measure until each lift is
complete and covered with final
cover (Stage 1 and part of Stage
3 only)
3 Site Entrance Impact on Noise
Atmospheric (noise) modelling
shows a predicted exceedance at
northern boundary of proposed
new entrance and access road
for new landfill footprint. Issues
caused by proximity of a sensitive
receptor (residence immediately
to the north on land not owned or
optioned by WM) and dispersion
of related traffic noise at entrance
and along on-site haul road.
Construct berm along northern
property boundary (9 m high x
345 m long) to mitigate noise
effect
Move site entrance to just north
of Laurysen building and
construct berm next to entrance
road (7 m high x 330 m long) to
mitigate noise effect
Move site entrance to just south
of Laurysen building (no berm
required) to mitigate noise effect
Move site entrance to just south
of Laurysen building to mitigate
noise effect
The incorporation of the recommended mitigation measures through design optimization, as
summarized above, required revisions to the FCR. The key differences between the original
FCR and the amended version are outlined in Table 6-2 below.
Table 6-2 Modifications to the FCR
No. Characteristic Original FCR Revised FCR
1 Site Entrance Location Along northern boundary of site South of Laurysen building
2 Landfill Height (due to further refinements of liner level)
156 mASL 155.7 mASL
Draft Environmental Assessment West Carleton Environmental Centre
6-15
chapter 6. detailed impact assessment of the undertaking
The revisions outlined in Table 6-2 are captured in the FCR included as Supporting
Document #4 – Facility Characteristics Report of the EA Report.
The changes made to the FCR based on the preliminary results of the Detailed Impact
Assessment, in turn, required the revision of some of the discipline-specific Detailed Impact
Assessment Reports. The Detailed Impact Assessment Reports that were affected by the
implementation of mitigation measures through design optimization include the following:
Transportation (redesign of left-hand turn lane based on new site entrance
location, change in traffic levels to the site during construction)
Atmospheric – Noise (remodelling of noise contours based on new site
entrance location and berming at the working face)
Geology and Hydrogeology (remodelling groundwater flow and quantity
based on the addition of purge wells along the northern boundary of the
existing landfill)
Biology (recalculation of amount of vegetation and wildlife habitat lost based
on new site entrance location)
The findings of the Detailed Impact Assessment are summarized in the following sections.
6.7 Net Effects on the Environment
6.7.1 Atmospheric Environment
6.7.1.1 Particulate Matter (Dust)
The Particulate Matter Detailed Impact Assessment included the generic On-Site, Site-Vicinity,
and Regional study areas, as shown in Figure 6-3 and described below:
On-Site ............. the lands required for the Preferred Alternative Landfill Footprint;
Site-Vicinity ...... the lands in the vicinity of the Preferred Alternative Landfill
Footprint, extending about 500 m in all directions; and,
Regional ........... the lands within approximately 3 to 5 km of the Site and the
Preferred Alternative Landfill Footprint.
The Dust Detailed Impact Assessment included emissions from construction, landfilling activities,
and on-site traffic. Potential dust sources were grouped into five general categories including:
On-site roadway sources;
Idling sources;
Draft Environmental Assessment West Carleton Environmental Centre
6-16
chapter 6. detailed impact assessment of the undertaking
Material handling and processing sources;
Wind erosion sources; and
Stack emission sources.
The evaluation considered the potential impacts from the site sources, including the Preferred
Alternative Landfill Footprint, at 24 discrete receptor locations, representing receptors of interest
in the Site-Vicinity and Regional study areas (refer to Figure 6-4). The discrete receptor
locations considered in the dispersion model include nearby residences, schools, businesses,
and other sensitive receptor locations. For all cases, humans were assumed to be present at
these receptors for 24 hours per day. Further details on particulate matter sources, receptors,
and dispersion modelling are found in the Atmospheric (Particulate Matter) Detailed Impact
Assessment Report in Supporting Document #5 – Detailed Impact Assessment.
Particulate Matter Methodology/Additional Investigations
The worst case future build scenario assessed was the first operating year scenario, as it
includes the highest traffic volumes and the scenario places both the landfill and construction
working faces in the worst case locations, in close proximity to the property boundary as well as
discrete sensitive receptors. The future build scenario was assessed by determining the dust
emissions from the significant emission sources and determining the potential off-site impacts
through dispersion modelling. In addition to the first operating year scenario, two proposed
leachate management methods used to treat the leachate were assessed: the preferred method
(excluding leachate evaporator) and the contingency method (including leachate evaporator);
however, as the results were found to be essentially identical, only the results from the more
conservative contingency method are expressed.
No additional Particulate Matter monitoring programs were undertaken as part of the Detailed
Impact Assessment.
Detailed Description of the Environment Potentially Affected by Particulate Matter
On-Site and Site-Vicinity
The maximum predicted off-site particulate matter concentrations associated with the
construction and operation of the Preferred Alternative Landfill Footprint including the
contingency leachate management system is predicted to occur near the property line, north of
the landfill development Stages 1 and 3. The maximum predicted concentration of TSP is
heavily influenced by the close proximity of the bulldozing operations at the construction working
face (in Stage 3) and the exposed areas subject to wind erosion. Contour plots showing the 24-
hour averaged concentrations for TSP, PM 10 and PM 2.5 for the future build scenario are
presented in Figures 6-5 through 6-7.
Draft Environmental Assessment West Carleton Environmental Centre
6-17
chapter 6. detailed impact assessment of the undertaking
Figure 6-4 Particulate Matter Detailed Impact Assessment Sources and Receptor Locations
Draft Environmental Assessment West Carleton Environmental Centre
6-18
chapter 6. detailed impact assessment of the undertaking
Figure 6-5 Maximum Predicted 24-Hour TSP Contours
Draft Environmental Assessment West Carleton Environmental Centre
6-19
chapter 6. detailed impact assessment of the undertaking
Figure 6-6 Maximum Predicted 24-Hour PM10 Contours
Draft Environmental Assessment West Carleton Environmental Centre
6-20
chapter 6. detailed impact assessment of the undertaking
Figure 6-7 Maximum Predicted 24-Hour PM2.5 Contours
Draft Environmental Assessment West Carleton Environmental Centre
6-21
chapter 6. detailed impact assessment of the undertaking
Discrete Receptors
The results of the dispersion modelling indicate that predicted 24-hour TSP, PM10 and PM2.5
concentrations did not exceed the air quality criteria at any of the receptors. Maximum
concentrations for TSP, PM10 and PM2.5 are predicted to occur at Receptor 1 (northeast
corner of the WCEC facility) in the future build scenario.
Potential Effects from Particulate Matter
Predicted concentrations at the discrete receptors do not exceed the Ambient Air Quality
Criteria (AAQC) or Canada Wide Standards (CWS) Limits with the implementation of the
mitigation measures incorporated into the particulate modelling and described in the following
subsection. Consequently, the impact of the expansion is considered low at all discrete
receptors for all future build scenarios.
There are however, particulate matter exceedances at the WCEC property line. These results
assume that the worst-case operations are occurring in the same locations for a five-year
period. In reality, the landfill operations will move to various Stages in the landfill and the
construction operation will only last 6 to 12 months of the modelled period. The impact from the
bulldozing and wind erosion sources will be lessened as the distance between these sources
and the property line increases.
Mitigation and/or Compensation Measures for Particulate Matter
The following mitigation measures were incorporated into the modelling conducted for the
Particulate Matter Detailed Impact Assessment:
Paving internal main haul routes;
Watering and sweeping on all internal haul routes;
Watering suppressants on ancillary sources (crushing activities); and
Installation of water spray on the impact crusher (for C&D waste processing).
The following are recommended additional mitigation measures that may be undertaken as part
of the Dust Best Management Plan:
Watering suppressants on working faces, unpaved interim cover area roads,
construction surfaces, etc.;
Watering suppressants on ancillary sources (Waste Transfer and Processing
Facility (WTPF) sources and other outdoor sources);
Progressive vegetation seeding on surface areas;
Limiting traffic movement on exposed surface areas; and
Speed control of on-site traffic.
Draft Environmental Assessment West Carleton Environmental Centre
6-22
chapter 6. detailed impact assessment of the undertaking
Net Effects from Particulate Matter
When the preferred leachate management system is used or the additional mitigation measures
(as listed above) for the contingency leachate management system are used the predicted
concentrations at the discrete receptors do not exceed the Point of Impingement (POI) Limit.
Consequently, the impact of the expansion is considered low at all discrete receptors for all
future build scenarios.
6.7.1.2 Combustion Emissions
The Combustion Emissions Detailed Impact Assessment included the generic On-Site, Site-
Vicinity, and Regional study areas, as shown in Figure 6-3 and described below:
On-Site ............. the lands required for the Preferred Alternative Landfill
Footprint;
Site-Vicinity ...... the lands in the vicinity of the Preferred Alternative Landfill
Footprint, extending about 500 m in all directions; and,
Regional ........... the lands within approximately 3 to 5 km of the Site and the
Preferred Alternative Landfill Footprint.
The air contaminants assessed in the Combustion Emissions Detailed Impact Assessment
include carbon monoxide (CO) and nitrogen oxide (NOx). In addition, impacts from dioxins and
furans (D&F) were assessed based on emissions from the on-site stationary combustion
sources. Predicted concentrations of CO, NOx and D&F were compared against Ontario
Regulation 337 AAQC or other available standards or criteria.
The sources of CO, NOX and D&F considered in the Combustion Emissions Detailed Impact
Assessment include:
vehicles travelling along the on-site haul routes;
idling vehicles;
the landfill gas-fired engines;
the LFG flares;
the sequencing batch reactor (SBR) emergency diesel-fired generator;
the leachate evaporator;
the impact crusher engine; and
vehicles travelling along the adjacent off-site roadways.
Draft Environmental Assessment West Carleton Environmental Centre
6-23
chapter 6. detailed impact assessment of the undertaking
The evaluation considered the potential impacts from site sources including the Preferred
Alternative Landfill Footprint footprint at 24 discrete receptor locations (refer to Figure 6-8),
representing receptors of interest in the Site-Vicinity and the Regional Study Areas. The discrete
receptor locations considered in the dispersion model include nearby residences, schools,
businesses, and other sensitive receptor locations. For all cases, humans were assumed to be
present at these receptors for 24 hours per day. Further details on sources, receptors, and
dispersion modelling are found in the Atmospheric (Combustion Emissions) Detailed Impact
Assessment Report in Supporting Document #5 – Detailed Impact Assessment.
Combustion Emissions Methodology/Additional Investigations
The worst case future build scenario assessed was the first operating year scenario as it has
the highest traffic volumes and the haul routes to the landfill and construction working faces are
positioned in worst case locations, in close proximity to the property boundary and discrete
sensitive receptors. The future build scenario was assessed by determining the combustion
emissions from the significant on-site emission sources and from the predicted 1st year of
operation off-site traffic volumes and determining the potential off-site impacts through
dispersion modelling. In addition to the first operating year scenario, two proposed leachate
management methods used to treat the leachate were assessed: the preferred method
(excluding leachate evaporator) and the contingency method (including leachate evaporator);
however, as the results were found to be essentially identical, only the results from the more
conservative contingency method are expressed.
Detailed Description of the Environment Potentially Affected by Combustion Emissions
On-Site and Site-Vicinity
Maximum predicted NOx concentrations exceed the AAQC at certain off-site locations; however,
these exceedances are driven by off-site traffic. Maximum predicted NOx concentrations from
WCEC sources are all well within the AAQC for each compound. The maximum predicted CO
and D&F concentrations are less than the AAQC when the WCEC and off-site traffic are
combined.
Discrete Receptors
CO concentrations were predicted to not exceed the 1-hour AAQC at any of the receptors for
the first year of the operation scenario. The maximum predicted 1-hour average concentration
from WCEC sources is 146 g/m3, occurring at Receptor 2. The maximum predicted 1-hour
average concentration from off-site and WCEC sources combined was 2,869 g/m3, occurring at
Receptor 4.
Draft Environmental Assessment West Carleton Environmental Centre
6-24
chapter 6. detailed impact assessment of the undertaking
Figure 6-8 Combustion Emissions Detailed Impact Assessment Sources and Receptor Locations
Draft Environmental Assessment West Carleton Environmental Centre
6-25
chapter 6. detailed impact assessment of the undertaking
CO concentrations were predicted to not exceed the 8-hour AAQC at any of the receptors for the
first year of operation scenario. The maximum predicted 8-hour average concentration from
WCEC sources is 72 g/m3, occurring at Receptor 2. The maximum predicted 1-hour average
concentration from off-site and WCEC sources combined was 937 g/m3, occurring at Receptor 4.
NOx concentrations were predicted to exceed the 1-hour AAQC at three of the receptors, based
on off-site sources. No exceedances of the 1-hour AAQC for NOx are predicted based on
WCEC sources. The maximum predicted 1-hour average NOx concentration was 577 μg/m3 at
Receptor 4. Concentrations predicted at Receptor 2 and Receptor 12 are also exceeding the 1-
hour AAQC.
It is important to note that the predicted impacts at the receptors where exceedances are
predicted are based mainly on the contribution from the off-site roadways. The WCEC sources
are contributing only a small percentage of the maximum predicted impact at these receptors.
NOX concentrations were predicted to not exceed the 24-hour AAQC at any of the receptors for
the first year of operation scenario. The maximum predicted 24-hour average concentration
from WCEC sources is 12 g/m3, occurring at both Receptor 2 and Receptor 4. The maximum
predicted 24-hour average concentration from off-site and WCEC sources combined was
97 g/m3, occurring at Receptor 4.
D&F concentrations were predicted to not exceed the 24-hour AAQC at any of the receptors.
Potential Effects from Combustion Emission
For CO and D&F the predicted impacts do not exceed the applicable AAQC at any off-site
location. The 1-hour NOX is predicted to exceed the AAQC at off-site locations, including three
of the discrete receptor locations. The 24-hour NOX is predicted to exceed the AAQC at some
off-site locations; however, it is not predicted to exceed the AAQC at any of the discrete
receptor locations.
The predicted NOX exceedances are a product of the high traffic volumes along off-site
roadways, especially Highway 417. Exceedances of the 1-hour NOX AAQC from time-to-time
are not unexpected at locations near a 400-series highway in Ontario. The contribution from
WCEC sources to the predicted NOX exceedances is low. Consequently, the impact of the
expansion is considered low at all discrete receptors for all future build scenarios.
Draft Environmental Assessment West Carleton Environmental Centre
6-26
chapter 6. detailed impact assessment of the undertaking
Mitigation and/or Compensation Measures for Combustion Emissions
The following measures not incorporated into the modelling may be implemented in order to
further mitigate Combustion Emission effects:
Minimizing on-site idling of vehicles;
Routine monitoring for waste vehicles arriving to the site in unfit or un-
maintained conditions; and
Proper staging and planning for internal vehicles arriving at the site and site
sequencing.
The predicted environmental impacts of CO and NOx are largely dominated by the presence of
traffic on off-site roadways; therefore, the additional mitigation measures for WCEC sources are
not expected to have a significant impact on off-site concentrations. The predicted
environmental impacts of D&F are dominated by WCEC sources; however, the maximum
predicted concentrations of D&F represent only a small percentage of the AAQC. The proposed
mitigation measures are not expected to have a significant impact on the D&F emissions from
on-site sources.
Net Effects from Combustion Emissions
The predicted concentrations at the discrete receptors do not exceed the AAQC for CO, D&F, or
24-hour NOX. Although exceedances are predicted for 1-hour NOX at three of the discrete
receptor locations, these exceedances are a result of off-site traffic, with only a minor
contribution from WCEC sources. Consequently, the impact of the expansion is considered low
at all discrete receptors for all future build scenarios.
6.7.1.3 Odour
The Odour Detailed Impact Assessment included the generic On-Site, Site-Vicinity and
Regional study areas, as shown in Figure 6-3 and described below:
On-Site ............. the lands required for the Preferred Alternative Landfill
Footprint;
Site-Vicinity ...... the lands in the vicinity of the Preferred Alternative Landfill
Footprint, extending about 500 m in all directions; and,
Regional ........... the lands within approximately 3 to 5 km of the Site and the
Preferred Alternative Landfill Footprint.
Draft Environmental Assessment West Carleton Environmental Centre
6-27
chapter 6. detailed impact assessment of the undertaking
Under normal operating conditions, solid waste landfills have the potential to produce odours
from several areas, including:
LFG and garbage odours from the landfill and waste acceptance activities:
working face, interim cover areas, final cover areas, public waste drop off
areas, installation of LFG wells, trenching activities, and cracks/fissures in the
landfill cover;
Leachate odours from the leachate management system;
Hydrocarbon odours from the use of contaminated soils as cover materials;
and,
Compost odours from the spreading of compost on the landfill mound to
encourage vegetation growth.
The evaluation considered the potential impacts from the WCEC odour sources including the
Preferred Alternative Landfill Footprint at 24 discrete receptor locations (refer to Figure 6-9),
representing receptors of interest in the Site-Vicinity and the Regional Study Areas. The discrete
receptor locations, considered in the dispersion model, include nearby residences, schools,
businesses, and other sensitive receptor locations. For all cases, humans were assumed to be
present at these receptors for 24 hours per day. In addition, the modelling was performed using
a receptor grid covering the Site-Vicinity and Regional Study Areas to produce isopleths of
predicted concentrations. Further details on odour sources, receptors, and dispersion modelling
are found in the Atmospheric (Odour) Detailed Impact Assessment Report in Supporting
Document #5 – Detailed Impact Assessment.
Odour Methodology/Additional Investigations
The potential odour impacts that would result from the construction and operation of the
Preferred Alternative Landfill Footprint were assessed at the worst case future build stages and
phases of development. The future build scenarios were assessed by determining odour
associated with the significant emission sources in each scenario and determining the potential
off-site impacts through dispersion modelling. The scenarios assessed include the intermediate
operation scenario and final operation scenario. In addition to the two operation scenarios, two
proposed leachate management methods used to treat the leachate were assessed: the
preferred method (pre-treatment with discharge to City of Ottawa sanitary sewer) and the
contingency method (pre-treatment with leachate evaporator); however, as the results were
found to be essentially identical, only the results from the more conservative contingency
method are expressed.
Draft Environmental Assessment West Carleton Environmental Centre
6-28
chapter 6. detailed impact assessment of the undertaking
Figure 6-9 Odour Detailed Impact Study Area and Receptor Locations
Draft Environmental Assessment West Carleton Environmental Centre
6-29
chapter 6. detailed impact assessment of the undertaking
The odour impacts from the WCEC operations were determined using a dispersion model and
reasonable worst-case emission rates. Dispersion modelling was performed using the U.S. EPA’s
AERMOD dispersion model (AERMOD) to predict concentrations of odour emitted from the WCEC
Preferred Alternative Landfill Footprint operations at various receptors within the Study Area.
Detailed Description of the Environment Potentially Affected by Odour
On-Site and Site-Vicinity
The combined odour impact from the site-wide WCEC operations was predicted to exceed the
recommended annoyance guideline of 3 OU/m3. For all scenarios, the exceedances were
predicted to occur near the facility property line. The maximum 10-minute averaged concentration
at any modelled receptor for 2018 conditions was predicted to be 10.0 OU/m³. The maximum 10-
minute averaged concentration at any modelled receptor for 2023 conditions was predicted to be
12.2 OU/m³. Contour plots showing the 10-minute average concentrations for odour for each
scenario are presented in Figure 6-10 through Figure 6-13. The contour plots also illustrate the
off-site area where odour impacts from the WCEC operations may exceed the 1 OU/m³ detection
threshold and the 3 OU/m³ annoyance threshold from time to time.
The maximum predicted odour concentration occurring from the landfill sources are influenced by
the close proximity of these sources to the property line. The working face was generally the most
dominant landfill source in causing off-site impacts. The working face represents the landfill
source with the highest emission flux rate (odour emissions per square metre), due to the deposit
and handling of fresh waste, reduced gas collection efficiency, and a lack of cover material in this
area. The predicted impacts from the existing landfill mound are predicted to decrease in the later
years, relative to the intermediate years, due to the reduction in LFG produced from the existing
landfill in future years. The predicted impacts from the Preferred Alternative Landfill Footprint
increased in the later years, relative to the intermediate years, as a result of increased waste
present in the Preferred Alternative Landfill Footprint in future years, which results in increased
LFG generation, and thus increased odour emissions, from this source.
The maximum predicted odour concentrations for all future build scenarios are influenced by the
SBR system. The SBR system is comprised of several tanks, which have vent exhausts with low
exit velocities and little momentum, resulting in poor dispersion from these sources. The poor
dispersion results in high concentrations at the property line. In comparison, the leachate evaporator
stack exhaust, evaluated as part of the contingency leachate management system, has a tall stack,
high exit velocity, and high momentum, resulting in good dispersion. For these reasons, the leachate
evaporator has little impact on the maximum predicted odour concentration at the property line, as
the maximum predicted concentrations between the Preferred Leachate Management System and
the Contingency Leachate Management System are relatively unchanged.
Draft Environmental Assessment West Carleton Environmental Centre
6-30
chapter 6. detailed impact assessment of the undertaking
Figure 6-10 Intermediate Operation Year – Preferred Leachate Management System Isopleths of the Maximum Predicted Odour Concentration - 10-Minute Average Period
Draft Environmental Assessment West Carleton Environmental Centre
6-31
chapter 6. detailed impact assessment of the undertaking
Figure 6-11 Intermediate Operation Year – Contingency Leachate Management System Isopleths of the Maximum Predicted Odour Concentration - 10-Minute Average Period