table of contents - karnataka municipal data societyfinal swm dpr for kushalnagar under swachh...
TRANSCRIPT
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 1
Table of Contents
Executive Summary…………………………………………………………………………………………………………………14
1. Introduction .......................................................................................................................... 29
1.1 Report Overview ............................................................................................................ 29
1.2 Need for the Project ....................................................................................................... 29
1.3 Scope and Objective of the Project ................................................................................ 31
1.4 Structure of the report ................................................................................................... 32
2 Town Profile .......................................................................................................................... 34
2.1 History ............................................................................................................................ 34
2.2 Location and Topography ............................................................................................... 34
2.3 Demography ................................................................................................................... 35
2.3.1 Population Projection ............................................................................................. 36
2.4 Climatology ..................................................................................................................... 37
2.4.1 Rainfall .................................................................................................................... 37
2.4.2 Temperature ........................................................................................................... 38
2.5 Transportation ................................................................................................................ 40
2.6 Tourist Centers ............................................................................................................... 40
2.7 Urban Local Body ........................................................................................................... 42
2.7.1 Political Setup ......................................................................................................... 42
2.7.2 Ward and Administrative Setup.............................................................................. 43
3 Existing Status of solid waste management Infrastructure .................................................. 45
3.1 Overview of SWM in the ULBs ....................................................................................... 45
3.2 MSW Quantification ....................................................................................................... 46
3.2.1 Waste generation estimate based on generators .................................................. 47
3.2.2 Normative Estimate of Waste Generation ............................................................. 50
3.2.3 Estimation of Waste Quantity using Secondary Transportation Vehicle ............... 51
3.3 MSW Characterisation ................................................................................................... 53
3.3.1 Physical Composition .............................................................................................. 53
3.3.2 Chemical Composition ............................................................................................ 55
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 2
3.4 Organization Chart for SWM Division ............................................................................ 55
3.5 Existing MSW Practising ................................................................................................. 56
3.6 Baseline Information ...................................................................................................... 58
3.6.1 MSW Primary Collection ......................................................................................... 58
3.6.2 MSW Storage .......................................................................................................... 58
3.6.3 MSW Secondary Collection & Transportation ........................................................ 58
3.6.4 MSW Processing and Disposal Practise .................................................................. 60
3.6.5 Street Sweeping and Drain Cleaning ...................................................................... 62
3.7 Existing Tariff & Cost Recovery Methods ....................................................................... 63
3.7.1 Past Five/Ten Years Trends ..................................................................................... 63
3.7.2 Cost Recovery Method............................................................................................ 64
4 Project Definition, Concept, Scope and Detailing ................................................................. 65
4.1 Land Availability ............................................................................................................. 65
4.1.1 MSW Collection and Transportation ...................................................................... 65
4.1.2 MSW Processing and Disposal ................................................................................ 65
4.2 Waste Generation Forecast ........................................................................................... 65
4.3 Storage of waste at source ............................................................................................. 66
4.3.1 Households ............................................................................................................. 66
4.3.2 Commercial Establishments / Institutions .............................................................. 68
4.3.3 Hotels & Restaurants .............................................................................................. 68
4.3.4 Vegetable Markets .................................................................................................. 69
4.3.5 Slaughter house, Meat & Fish Markets .................................................................. 69
4.3.6 Hospitals / Clinics / Nursing Homes, etc. ................................................................ 70
4.3.7 Construction and Demolition wastes...................................................................... 71
4.4 Segregation of Recyclables/Non-degradable waste ...................................................... 72
4.5 Proposed COllection and Transporation Strategy ......................................................... 72
4.6 Primary collection of waste ............................................................................................ 74
4.6.1 Modus Operandi ..................................................................................................... 74
4.6.2 Use of small vehicles for direct collection of waste from congested areas ........... 75
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 3
4.6.3 Requirement of manpower, requirement of vehicles ............................................ 76
4.7 Street Sweeping ............................................................................................................. 78
4.7.1 Street Sweeping Frequency .................................................................................... 78
4.7.2 Vehicles, tools and equipment to be used for sweeping ....................................... 78
4.7.3 Requirement of manpower .................................................................................... 79
4.7.4 Norms of work ........................................................................................................ 81
4.7.5 Improvement and recommendations on street sweeping and drain cleaning ...... 81
4.8 Temporary waste storage depots for onward transportation of waste ........................ 81
4.9 Transportation of waste ................................................................................................. 81
4.9.1 Transportation of Municipal Solid Waste ............................................................... 81
4.9.2 Transportation of Biomedical waste from hospitals/clinic/nursing homes ........... 82
4.9.3 Transportation of Construction and demolition waste .......................................... 83
4.9.4 Workshop facility for vehicle maintenance ............................................................ 83
4.9.5 Routing of waste and trip requirement .................................................................. 84
4.9.6 Deployment plan for existing vehicles, staff and additional requirements ........... 84
4.9.7 Total requirement of tools/equipment/vehicles .................................................... 84
4.9.8 Manpower requirement for implementation of MSW strategy ............................ 85
4.10 Dry Waste Collection Centres/zero waste management centre................................ 85
4.11 Processing & Disposal options available to ULBs ....................................................... 89
4.11.1 Site profile ............................................................................................................... 89
4.11.2 Concept of IWMF .................................................................................................... 89
4.11.3 Technology Options ................................................................................................ 89
4.11.4 Thermal Processing Technologies ........................................................................... 90
4.11.5 Biological Processing Technologies......................................................................... 90
4.11.6 Physical Processing Technologies ........................................................................... 90
4.11.7 Technology Selection .............................................................................................. 91
4.12 Aerobic Process – Windrow Composting Technology ................................................ 92
4.12.1 Process flow and Material Balance ......................................................................... 92
4.12.2 Layout ...................................................................................................................... 92
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 4
4.12.3 Components of IWMF and its capacities ................................................................ 95
4.12.4 Detailed design ....................................................................................................... 98
4.12.5 Leachate from Processing Shed ............................................................................ 103
4.13 Sanitary Landfill ........................................................................................................ 103
4.13.1 Landfill Design Requirements and Standards ....................................................... 105
4.13.2 Tests and Samples during Construction of the Sealing Systems .......................... 109
4.13.3 Design &Area Requirement .................................................................................. 112
4.13.4 Leachate from Landfill .......................................................................................... 114
4.14 Leachate Treatment plant - Planted Gravel Filter .................................................... 114
4.15 Disposal of Industrial waste ...................................................................................... 116
4.16 Disposal of Biomedical waste ................................................................................... 116
4.17 Disposal of Slaughter House ..................................................................................... 116
4.18 Remediation of Existing MSW at Dumpsite ............................................................. 116
4.19 Smart Monitoring and Control of MSW Operations ................................................ 117
4.19.1 GPS (Global Positioning System) ........................................................................... 117
4.19.2 RFID, GPS, GIS and GSM technologies .................................................................. 118
4.20 Legal Aspects ............................................................................................................ 118
4.20.1 Introduction .......................................................................................................... 118
4.20.2 Proposed Provisions .............................................................................................. 119
4.21 Health Aspects .......................................................................................................... 121
4.21.1 Special Attention to Slums and Traditional Dirty Areas ....................................... 121
4.21.2 Implementation of Low Cost Sanitation Program to Prevent Open Defecation .. 122
4.21.3 Covering of Buildings under Construction ............................................................ 122
4.21.4 Cattle & Pig Nuisance ............................................................................................ 122
4.21.5 Health Monitoring for Sanitation Workers ........................................................... 123
4.21.6 Prevent In-discriminate Use of Pesticides ............................................................ 123
5 Project Cost ......................................................................................................................... 124
5.1 Cost estimate for Land Acquisition .............................................................................. 124
5.2 Capital cost estimate for Collection and Transportation ............................................. 124
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 5
5.3 Capital cost estimate for Processing Facility ................................................................ 125
5.4 Capital cost estimate for Recycling Facility .................................................................. 125
5.5 Capital cost estimate for Leachate Treatment Facility ................................................ 126
5.6 Capital cost estimate for Disposal ................................................................................ 126
5.7 Capital cost estimate for COmmon Facilities ............................................................... 126
5.8 Capital cost estimate for Public Awareness Programme ............................................. 127
5.9 Capital cost estimate for Social Forestry and Crop Demonstration............................. 128
5.10 Capital cost estimate for Dry Waste Colelction Centre ............................................ 128
5.11 Summary of Capital cost for Integrated SOlid Waste Management ........................ 128
6 Project Institution Framework ............................................................................................ 130
6.1 Roles of different institutions ...................................................................................... 130
6.1.1 Citizens .................................................................................................................. 130
6.1.2 NGO participations/Informal Sectors ................................................................... 130
6.1.3 Private Sector ........................................................................................................ 130
6.1.4 ULB SWM staffs ..................................................................................................... 130
6.2 Implementation Plan .................................................................................................... 131
6.2.1 Option 1 – Service delivery by TP ......................................................................... 131
6.2.2 Option 2 –Service delivery through private operator(s) with TP playing the role of
a facilitator .......................................................................................................................... 131
6.2.3 Implementation “Packages” for implementation of SWM activities ................... 133
7 Project Financial STructuring .............................................................................................. 134
7.1 Overall Financial Structuring of the Project ................................................................. 134
7.2 Review of OPtions ........................................................................................................ 134
7.2.1 Institutional Dept .................................................................................................. 134
8 Project Phasing.................................................................................................................... 135
8.1 Schedule for bringing in STate level and ULB level contricutions to the Porject ......... 135
8.2 Schedule for obtaining all clearances .......................................................................... 135
8.3 Schedule for Shifting Utilities ....................................................................................... 135
8.4 PERT Chart/CPM Diagram ............................................................................................ 135
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 6
8.5 Schedule for Tendering/Selection for procurement of services/Equipments/Vehicles
135
8.5.1 Tendering Schedule/Selection of Procurement of services ................................. 135
9 Project O&M ....................................................................................................................... 137
10 Project Benefits Assessment ............................................................................................... 141
10.1 Benefits from the societal perspective ..................................................................... 141
10.2 List of negative externalities ..................................................................................... 144
10.3 Economic internal rate of return .............................................................................. 145
11 Public Awareness ................................................................................................................ 146
11.1 Introduction .............................................................................................................. 146
11.2 Reduce, Reuse and recycle (R-R-R) ........................................................................... 146
11.2.1 Recycling of waste by all concerned ..................................................................... 146
11.2.2 Reuse ..................................................................................................................... 147
11.2.3 Recycling ............................................................................................................... 147
11.3 Public participation ................................................................................................... 147
11.3.1 Finding out optional solutions .............................................................................. 148
11.3.2 Consult community on options available ............................................................. 148
11.4 Public Information Education, Communication and Awareness Programs ............. 149
11.4.1 Public Education .................................................................................................... 149
11.4.2 Group Education ................................................................................................... 149
11.4.3 Mass Education ..................................................................................................... 150
A.1 Survey of Waste Generators ................................................................................................. 152
A.2 Waste Quantification Study .................................................................................................. 157
A.3. Waste Characterization Study ............................................................................................. 158
A.3.1. Physical Composition of Waste - Dumpsite.............................................................. 158
A.3.2. Chemical Characterization ........................................................................................ 160
A.4. Drawings .............................................................................................................................. 161
A.5. Detailed Estimation ............................................................................................................. 162
A.5.1. Detailed Estimation for Collection and Transportation ........................................... 162
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 7
A.5.2. Detailed Estimation for Processing Facility – Civil works ......................................... 166
A.5.3. Detailed Estimation for Processing Facility – Machineries, Tools and Equipments . 172
A.5.4. Detailed Estimation for Recycling Facility ................................................................ 175
A.5.5. Detailed Estimation for Leachate Treatment Facility – Planted Gravel Filter .......... 176
A.5.6. Detailed Estimation for Leachate Collection Tank – Windrow Pad.......................... 181
A.5.7. Detailed Estimation for Sanitary Landfill Facility ...................................................... 186
A.5.8. Detailed Estimation for Common Facility – Office building cum Weigh Bridge Room
............................................................................................................................................. 199
A.5.9. Detailed Estimation for Common Facility – Two Seater Toilet Block ....................... 213
A.5.10. Detailed Estimation for Common Facility – Septic Tank ........................................ 222
A.5.11. Detailed Estimation for Common Facility – Rain Water Harvesting ...................... 227
A.5.12. Detailed Estimation for Common Facility – Deep Burial Facility ............................ 230
A.5.13. Detailed Estimation for Common Facility – Drain .................................................. 231
A.5.14. Detailed Estimation for Common Facility – Internal Road – 5m wide ................... 234
A.5.15. Detailed Estimation for Common Facility – Compound wall ................................. 237
A.5.16. Detailed Estimation for Common Facility – Weigh Bridge Pit ................................ 241
A.5.17. Detailed Estimation for Common Facility - Tools and Equipment’s ....................... 244
A.5.17. Detailed Estimation for Awareness Programme and IEC ....................................... 245
A.5.18. Detailed Estimation for Social Forestry and Crop Demonstration ......................... 246
A.5.19. Detailed Estimation for Dry Waste Collection Centre ............................................ 247
A.5.20. Detailed Estimation of Dry Waste Collection Centre – Tools and Equipment’s..... 254
A.6. Quotations ........................................................................................................................... 255
A.6.1. List of Quotations ..................................................................................................... 255
A.7. Census of India 2011 – District Census Handbook, Kodagu ................................................ 256
A.7.1 District Primary Census Abstract ................................................................................... 256
A.7.2 Urban PCA – Town wise Primary Census Abstract ........................................................ 259
A.8. Karnataka High Court Order for Waste Segregation ........................................................... 260
A.9. TP comments from DRaft DPR of MSW under SBM ............................................................ 261
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 8
List of Exhibits
Exhibit 1: Material Balance of Processing Facility ........................................................................ 23
Exhibit 1-1: Kushalnagar Summary ............................................................................................... 30
Exhibit 1-2: Chapters of the DPR ................................................................................................... 32
Exhibit 2-1: Google Map of the Kushalnagar ................................................................................ 34
Exhibit 2-2: Topology of Kushalnagar ........................................................................................... 34
Exhibit 2-3: Population trends in Kushalnagar.............................................................................. 35
Exhibit 2-4: Ward level Population and Households of Kushalnagar in Census 2011 .................. 36
Exhibit 2-5: Projected Design Population of Kushalnagar ............................................................ 37
Exhibit 2-6: Monthly Rainfall of Kushalnagar ............................................................................... 38
Exhibit 2-7: Graphical Representation of Monthly Rainfall of Kushalnagar ................................. 38
Exhibit 2-8: Monthly Temperature of Kushalnagar ...................................................................... 39
Exhibit 2-9: Graphical Representation of Monthly Temperature of Kushalnagar ........................ 39
Exhibit 2-10: Political Chart of Kushalnagar .................................................................................. 42
Exhibit 2-11: Organization Chart of Kushalnagar .......................................................................... 43
Exhibit 2-12: Photographs of Meeting with Officials .................................................................... 44
Exhibit 3-1: Revenue payment: Revised budget estimate for 2014-15 for SWM in Budget Year
2015-16 ......................................................................................................................................... 45
Exhibit 3-2: Capital payment: Revised budget estimate for 2014-15 for SWM in Budget Year
2015-16 ......................................................................................................................................... 46
Exhibit 3-3: Estimation of Waste Quantity from Waste Generators ............................................ 48
Exhibit 3-4: Google Image for Location of Kushalnagar TP and Neighbouring Villages ............... 49
Exhibit 3-5: Distance and Waste Generation of neighbouring Villages and Kushalnagar Town .. 49
Exhibit 3-6: Graphical Representation of Waste Quantity from Waste Generators .................... 50
Exhibit 3-7: Photographs of Waste Generator Sampling Study .................................................... 50
Exhibit 3-8: Estimation of Waste Quantity from Secondary Transportation Vehicles ................. 51
Exhibit 3-9: Data on Transportation of Waste to Disposal Site .................................................... 51
Exhibit 3-10: Photographs of Waste Quantification Study ........................................................... 52
Exhibit 3-11: Physical Composition of Waste in % - Dumpsite Fresh Sample .............................. 53
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 9
Exhibit 3-12: Photographs of Physical Composition of waste – Dumpsite Sample ...................... 54
Exhibit 3-13: Chemical Composition of Waste ............................................................................. 55
Exhibit 3-14: Organization Chart for SWM Division ...................................................................... 56
Exhibit 3-15: Staffing details of Kushalnagar ................................................................................ 56
Exhibit 3-16: Process Chart for Current MSW Practices in Kushalnagar ...................................... 57
Exhibit 3-17: Flow Chart on Transportation Mechanism .............................................................. 59
Exhibit 3-18: Details of Vehicle Involved in Transportation of Waste .......................................... 59
Exhibit 3-19: Google Image of Kushalnagar Dumpsite ................................................................. 60
Exhibit 3-20: List of Existing Available Facilities at Dumpsite ....................................................... 61
Exhibit 3-21: Photographs of Existing Available Facilities at Dumpsite ........................................ 61
Exhibit 3-22: Frequency of Street Sweeping in Kushalnagar Town .............................................. 63
Exhibit 3-23: User Fee/Collection fee for SWM in 2014 ............................................................... 63
Exhibit 4-1: Estimation of Waste Generation and Projection ....................................................... 66
Exhibit 4-2: Requirement of Dust Bins and Sacks for source Segregation ................................... 67
Exhibit 4-3: Proposed Collection and Transportation System ...................................................... 73
Exhibit 4-4: Requirement of Primary Collection Vehicles ............................................................. 77
Exhibit 4-5: Manpower Requirement for Primary Collection Activities ....................................... 77
Exhibit 4-6: Tools for Street Cleaning Activities ............................................................................ 78
Exhibit 4-7: Total Number of PKs and Vehicles required for Street Sweeping ............................. 80
Exhibit 4-8: Estimation of Secondary Transportation Vehicles .................................................... 82
Exhibit 4-9: Requirement of Vehicles ........................................................................................... 84
Exhibit 4-10: Requirement of Manpower for Collection and Transportation .............................. 85
Exhibit 4-11: Handling of Dry/Inorganic Waste in Dry Waste Collection Centre ......................... 86
Exhibit 4-12: Approximate market rate of Recoverable from waste ........................................... 87
Exhibit 4-13: Dry Waste Collection Centre Model ........................................................................ 88
Exhibit 4-14: Technological Options for MSW processing in different categories ....................... 89
Exhibit 4-15: Technological Options for MSW Processing in Different Categories ...................... 92
Exhibit 4-16: Material Balance of Processing Facility ................................................................... 94
Exhibit 4-17: List of Proposed Facilities at Site ............................................................................. 95
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 10
Exhibit 4-18: List of Proposed Machineries, Tools and Equipment at Processing Facility and Dry
waste collection centre ................................................................................................................. 95
Exhibit 4-19: Details of Common Facilities Proposed at Site ........................................................ 97
Exhibit 4-20: Area Requirement of Aerobic Composting Process and Recycling unit ................ 101
Exhibit 4-21: Leachate Generation from Waste Processing & Compost Area............................ 103
Exhibit 4-22: Area Requirement for Sanitary Landfill ................................................................. 112
Exhibit 4-23: Leachate Generation from Sanitary Landfill .......................................................... 114
Exhibit 4-24: Total Leachate Generation & sizing of Leachate Collection Tank ......................... 114
Exhibit 4-25: Constructed Wetlands ........................................................................................... 115
Exhibit 4-26: Sizing of Planted Gravel filter for Leachate ........................................................... 115
Exhibit 4-27: Assessment of Existing MSW Quantity at Dumpsite ............................................. 117
Exhibit 5-1: Capital Cost Estimation for Collection and Transportation ..................................... 124
Exhibit 5-2: Capital Cost Estimation for Processing Facility ........................................................ 125
Exhibit 5-3: Capital Cost Estimation for Recycling Facility .......................................................... 126
Exhibit 5-4: Capital Cost Estimation for Leachate Treatment Facility ........................................ 126
Exhibit 5-5: Capital Cost Estimation for Sanitary Landfill Facility ............................................... 126
Exhibit 5-6: Capital Cost Estimation for Common Facility .......................................................... 127
Exhibit 5-7: Capital Cost Estimation for Public Awareness Programme ..................................... 127
Exhibit 5-8: Capital Cost Estimation for Social Forestry and Crop Demonstration .................... 128
Exhibit 5-9: Capital Cost Estimation for Dry Waste Collection Centre ....................................... 128
Exhibit 5-10: Summary of Project Cost ....................................................................................... 129
Exhibit 6-1: Options for Implementation of MSW ...................................................................... 131
Exhibit 7-1: Financial Structuring of the Project ......................................................................... 134
Exhibit 8-1: Schedule for obtaining clearances ........................................................................... 135
Exhibit 9-1: Operations and Management cost of proposed MSWM ........................................ 137
Exhibit 9-2: Revenue by sale of Compost and By-Products ........................................................ 138
Exhibit 9-3: Revenue Generation by user fee collection for the year 2017-18 .......................... 138
Exhibit 9-4: Proposed SWM user fees for next 5 years .............................................................. 139
Exhibit 9-5: Financing of O&M expenses for the MSWM services ............................................. 139
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 11
Exhibit 10-1: Social Benefits and Quantitative Impacts .............................................................. 141
Exhibit 10-2: Negative Externalities and Impacts ....................................................................... 144
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 12
Acronyms
APM Arithmetic Progression Method
BOD Biological Oxygen Demand
CLF Compact Fluorescent Lamp
COD Chemical Oxygen Demand
CPCB Central Pollution Control Board
CPHEEO Central Public Health and Environmental Engineering, Organization
DMA Directorate of Municipal Administration, Government of Karnataka
DPR Detailed Project Report
EIA Environmental Impact Assessment
FCO Fertilizer Control Order
GCL Geo synthetic Clay Liner
GIS Geographical Information System
GL Ground Level
GPM Geometric Progression Method
GPS Global Positioning System
GSM Global System Mobile
HDPE High Density Polyethylene
HF Horizontal Flow
HP Horse Power
IEC Information, Education and Communication
IIM Incremental Increase Method
IWMF Integrated Waste Management Facility
LEL Lower Explosive Limit
LS Lumpsum
MIS Management Information System
MLA Member of Legislative Assembly
MLC Member of Legislative Corporation
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 13
MP Member of Parliament
MRF Material Recovery Facility
MSW Municipal Solid Waste
MSWM Municipal Solid Waste Management
NGO Non-Government Organisation
O&M Operation and Maintenance
PGF Planted Gravel Filter
Pk Pourakarmikas
PVC Poly Vinyl Chloride
RDF Refuse Derived Fuel
RFID Radio Frequency Identification
RWA Resident Welfare Association
SBM Swachh Bharat Mission
SBM-U Swachh Bharat Mission - Urban
SLF Sanitary Landfill
SWM Solid Waste Management
TP Town Panchayat
TPD Tons per day
TPH Tones per hour
TTPL Tide Technocrats Private Limited
ULB Urban Local Body
VF Vertical Flow
WBM Water Bound Macadam
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 14
Executive Summary
1. About town
Kushalnagar is a Town Panchayat located in Kodagu District, on the banks of Kaveri River, in the
state of Karnataka, India. The town is located on Bantwal - Mysore state highway 88.
Kushalnagar is at a distance of 80Kms from Mysore and 30 Kms from Madikeri. Kushalnagar is
located at 12.47°N 75.97°E. It has an average elevation of 831 metres. The Town Panchayat of
Kushalnagar has a population of about 15,326 as per 2011 census and an area of 18.5 km². The
road length of the town is 24 km. The number of households in the town is 3,788 households.
A brief information of the town is provided in the table below
Population 2011 18,249
Population (2016) 20,042
Area in Sq. kms 18.5Sq Km
No. of wards 16 wards
Total no. of households 4,594
Total no. of commercial establishments 1,725
No. of Bulk waste generators such as Marriage halls
Markets Hotels
Institutions
06 01 119 20
Road length in Kms - A Type (< 10%) - B Type - C Type - D Type - Total Road length
6 km 10kms 12kms 20 Kms 48 km
2. Existing SWM in Kushalnagar
2.1 Waste generation and collection estimate
The total municipal waste generation as per generator based assessment (sum of waste
collected from Households, Commercial establishments, Markets and street sweeping) in
Kushalnagar town is estimated to be about 10.7 tons per day (TPD) which is quite high due to
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 15
disposal of waste generation from village namely Kudumangallore at Kushalnagar town
informally. The normative estimate is about 10.1 tons per day (Total Population * Per Capita
waste). The waste generation of 10.7 tons per day is adopted as a realistic waste generation. An
average of about 7.09 tons per day of waste is collected. The collection efficiency is about 66%.
2.2 Waste generation by generator type
About 10 major waste generators were identified for estimating quantity of waste generated in
the town. The amount of waste generated by different generators is estimated as follows.
S. No. Waste Generators No of Generators
Avg. waste per day in Kg
Total waste in Kg
Total waste in Tonnes
1 Household 2979 1.3 3783.33 3.78
2 Commercial establishments
1565 1.1 1784.10 1.78
3 Slum 1615 0.8 1211.25 1.21
4 Hotels 119 4.6 547.40 0.55
5 Meat/Chicken shops/Slaughter house
58 4.4 255.00 0.26
6 Institutions 20 3.6 72.00 0.07
7 Veg. Markets 1 30.3 30.30 0.03
8 Petty Shops 160 0.5 80.00 0.08
9 Street Sweeping
Type A 6.0 40.0 240.00 0.24
Type B 10.0 21.0 210.00 0.21
Type C 12.0 10.0 120.00 0.12
Type D 20.0 7.4 148.00 0.15
10 Miscellaneous waste 5%
333.69 0.33
Total waste generated at Kushalnagar Town 8815.07 8.82
Total waste generated at Kudumangalore Village 1895.00 1.90
Total 10710.07 10.71
C&D waste 0.69
2.3 Characterization of waste
2.3.1 Physical and Chemical properties of waste collected
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 16
S. No.
Physical Characteristics Chemical Characteristics
Components Average Components Results
1 Food Waste 9.13 Moisture Content 6.42%
2 Tree/Fruit/Flower Waste 19.68 pH of 10% Solution 8.32
3 Grass and Leaf Waste 15.94 Total Nitrogen (N) 0.28%
4 Plastic Containers & Packaging
9.03 Total Phosphates (P2O5) 0.44%
5 Paper, Cardboard & Cartons 8.82 Potash (K2O) 0.62%
6 Rubber 1.77 Organic Carbon 6.92%
7 Rags/Clothes 6.97 Carbon: Nitrogen Ratio (C : N) 24.71: 1
8 Wood 3.41 Gross Calorific Value in Cal/gm 240.00
9 Metals 0.80
10 Glass 6.35
11 Inerts 17.23
12 Electronic waste/batteries/Bulbs
0.88
13 Bio-Medical waste 0.00
Total 100.00
2.4 Present system of waste management
Estimated waste generation is about 10.7 TPD and about 7.09 TPD of waste collected is with
efficiency of about 66%. The Landfill site is about 7 acres 15 guntas located in Buvanagiri
located in 12°30'56.92"N and 75°57'21.83"E, at a distance of about 11 km from the town
center. The details of quantification study is provided as below
S. No. Type of Vehicle Number of Vehicle
Number of Trips per day
Weight in tons Average in tons 04/12/15 05/12/15 06/12/15
1 Tractor Trailer 1 2 2.32 1.73 1.86 1.97
2 Tractor Trailer 1 2 2.26 3.50 1.81 2.52
3 Tractor Trailer 1 1 0.00 4.29 3.51 2.60
Total 3 5 4.58 9.52 7.18 7.09
2.4.1 Collection infrastructure
Collection, sweeping and drain cleaning is managed by the TP through pourakarmikas and
contract workers. About 33 staffs have been deployed for sweeping, collection and drain
cleaning. Secondary transportation is managed by TP and 8 drivers have been deployed for
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 17
vehicles. The vehicles and equipment used for collection and transportation are Tractor
Trailers-3 and Auto tipper-5.
2.4.2 Transport
2.4.3 Processing and Disposing
Kushalnagar TP has set up MSW disposing site at Buvanagiri. The total area of the landfill site is
about 7 acres 12 guntas. The waste is brought to the depot by tractor trailers and auto tipper.
No front end loader is deployed to form heaps of the wastes and it is spread over the area
where the waste has been dumped. Rag pickers operate inside the site, they collect recyclable
waste like plastic covers, plastic utensils, metal pieces if any and glass bottles. These rag pickers
are not authorized but have been permitted to pick waste from dumpsite. They do not
segregate waste into degradable or non-biodegradable waste but just pick the waste can be
sold in scrap shops.
2.4.4 Bio- medical waste
Kushalnagar town has about 25 numbers of bio medical waste generators including nursing
homes and clinics. There is an existing system of waste storage, collection, transport and
processing as per the biomedical waste handling rules. Bio-medical waste generated by
Hospitals and clinics is separately collected by private agency called M/s. Shree Consultants
which has a common processing facility located at Mysore, Karnataka. The collection of
biomedical waste from Kushalnagar town will be done in weekly twice by using 4 wheeled truck
with covered body.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 18
2.4.5 Cost of waste management
The TP collects a fee of Rs. 10 per month from all household and Rs.30 per month from all the
commercial establishment waste generators from where they collect wastes. The fee collected
is used for maintenance of vehicle and to pay salaries to personnel involved.
User Fee/Collection fee for SWM in 2014-2015
S. No. Particulars No. of Units Collection Efficiency
Price / Month/ Unit
Amount Rs. Per Month
1 Household 3,788.00 70% 10.00 26,516.00
2 Commercial 1,827.00 70% 30.00 38,367.00
Total 40.00 64,883.00
2.4.6 Total expenditure incurred on SWM and total revenue generated at present.
i. Expenditure details
Activities Expenditure in lakhs
Salary for permanent Pks 32.4
Wages for outsource Pks 35.58
Wages for outsource drivers 4.50
Vehicle running & Maintenance cost 11.21
Consumables 3.00
Total 86.69 lakhs
ii. Revenue details
Particulars Amount (Rs. in lakhs)
2016-17
% of Property tax reserved towards SWM and cleaning activities 8.22
SWM Cess 7.78
Sale of compost, recyclables, RDF etc -
Components of Town planning Fee, advertisement tax, birth / death certificate fee etc towards SWM and cleaning activities
0.20
Fines and fees available for SWM and cleaning activities -
Others -
Total 16.2 lakhs
3. Proposed Plan for Management of MSW
3.1 Collection infrastructure
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 19
The proposed plan recommends 100% door to door collection system of segregated waste. The
Door to door collection systems would be collected daily through the use of auto tipper for wet
and dry waste; and wet waste collected would be transferred to compactor which shall be
transported directly to the processing facility. The dry waste, hazardous and sanitary waste is
collected through auto tipper and transported directly to dry waste collection centre. 100% of
meat/chicken/slaughter house waste would need to be covered using wet/dry waste collection
auto tipper as separate trip after 11 am. Street sweeping silt would be directly transferred to
low lying area/sanitary landfill after smart segregation on site by sweepers using tractor trailer.
Existing tractor trailers and pushcarts in use at present would be continued to use for sweeping
and C&D waste collection and five auto tippers in use at present would be continued to use for
collection and transportation.
• 2 additional auto tippers have to be purchased
• 1 compactor is to be purchased for secondary transportation
3.2 Transport
The segregated wet waste would be transported processing facility located in Buvanagiri
through compactor and the inert from the processing facility would be disposed into the
sanitary landfill. The dry waste collected would be directly transported through auto tipper to
dry waste collection centre.
The silt from street sweeping activity would be transferred to the low lying area/sanitary landfill
facility by way of tractor trailers after manual smart segregation on the streets. The tractor
trailers in use at present would be restricted to be used for street sweeping, C&D waste and at
the composting plant but not to be used for transport of municipal wastes.
Proposed Micro-planning of door-to-door collection vehicles Autotippers
Sn
Vehicle no.
Trips/day
Ward no
Street name
generators covered
Quantity of waste
Disposal centre
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 20
1 Auto tipper No.1
3 1,2
Rasool badavane, vivekananda badavane, Thiyagaraja road, Kempamma badavane, Kalamma colony, Nethaji badavane
973 2,549 Processing/DWCC
2 Auto tipper No.2
3 3,13
Singaramma badavane, Shylaja badavane, IB road right side, Chowde Gowda badavane, housing board, Thomas badavane
995 2607 Processing/DWCC
3 Auto tipper No.3
3 4,5 Dandinpet, Havabi badavane, Shanthi marga, BM road left side, Bapuji badavane, town colony
807 2114 Processing/DWCC
4 Auto tipper No.4
3 6,10
Avadhani badavane, Basappa badavane, Sai layout, Somvarpet road right side, Iyyappa temple road, Dandinpet main road, BM road left side
838 2196 Processing/DWCC
5 Auto tipper No.5
3 7,8,9
Balamuri temple full, Shivarama karanth badavane, maruthi badavane, bypass road right&left side, Dr.S.Radhakrishna badavane, Town panchayath office, Kavari badavane
935 2450 Processing/DWCC
6 Auto tipper No.6
3 11,12
Bayachanahalli, Kaveri badavane,
Raita bhavan, BM road right side 954 2499
Processing/DWCC
7 Auto tipper No.7
3 14,15,16
HRP colony quarters, Nehru
badavane, water supply board guest
house, Gandada kote road right side,
Gundurao badavane, RK layout,
Yogananda badavane, Bhavani
badavane, Nizamuddin badavane
901 2361 Processing/DWCC
100% of meat/chicken/slaughter house waste would need to be covered using wet/dry waste collection auto tipper as separate trip after 11 am. The details of the vehicles and equipment’s recommended for Kushalnagara are as below
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 21
S.N Type of Vehicles Proposed Existing no’s
To Procure
Rate Amount
C&T
1 Containers of 10 Lit capacity
8310 0 8310 160 1329600
2 HDPE Sacks 4155 0 4155 17 70635
3 Auto tippers / Mini tippers 7 5 2 520000 1040000
4 Compactor 1 0 1 2900000 2900000
5 GPS tracking system 10 0 10 15000 150000
6 Sound box, mic set 7 0 7 5180 36260
Processing Site
7 Baling machines set including bins
1 0 1 587500 587500
8 Tractor trailers 1 1 0 792000 0
9 High raised Trailers 1 0 1 250000 250000
10 Front end loader (backhoe) 1 0 1 2364000 2364000
11 Screening machines (trommel) 35 mm/ 16mm/4mm
1 0 1 6700000 6700000
12 Tools, Baskets, sieving kit etc
1 0 1 50000 50000
13 Bagging tools and Equipment’s
2 0 2 35000 70000
14 DWCC tools & equipment’s 1set 0 1 31969 31969
15 Common facilities
647495 647495
16 Crop Demonstration and social forestry
347910 347910
17 Total
1,65,75,369.00
Contingency of 3%
0 3% 4,97,261.07
Awareness
0 0 202300 2,02,300.00
Grand total
0
1,72,74,930.07
Amount in Lakhs
172.75
3.3 Processing and Disposal
3.3.1 Technology Selection
Based on the above analysis it is recommended to have aerobic windrow composting based
waste management facility. The existing vermin compost can also be used at time to time. This
would be supported by the recycling of plastics and other in organics. This technology
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 22
proposed is simple and easy to implement with potential to meet the overall objectives of
waste management elucidated above. This is cost effective.
3.3.2 Design requirement for Processing and Disposal plan
The Integrated waste management facility has been designed for a capacity of 16.9 tons per day
for the design period 2020 (Five years period) for Kushalnagar Town, Mullusoge village and
Kudumangalore village and also in consideration of direct waste disposal of Kudige village at
processing facility. Out of total waste 25 % of dry waste i.e. 4.2 TPD considered as direct
transport to dry waste collection centre and 15% of street sweeping waste about 2.5 TPD
considered as direct transport to low lying areas. The remaining 10.1 TPD of waste is considered
for plant design capacity. The processing facilities are windrow composting of 10.1 TPD and RDF
material of 3.8 TPD capacities.
Technological Options for MSW Processing in Different Categories
Particulars Unit Quantity
Design Year (Five years period) Year 2022
Projected waste for Kushalnagar and Kudumangalore TPD 14.4
Projected waste for Kudige (direct disposal at processing facility) TPD 2.5
Total Waste TPD 16.9
25% of dry waste considered as direct transport to DWC TPD 4.2
15% of Sweeping waste considered as direct transport to low lying area
TPD 2.5
Plant Design Capacity TPD 10.1
Processing Facility
Windrow Composting TPD 10.1
Material Recovery Facility
Refuse Derived Fuel Plant TPD 3.8
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 23
Exhibit 1: Material Balance of Processing Facility
RDF (3.8 TPD)
Recyclables (1.7 TPD)
SLF (1.0 + 1.2) TPD
1.0 TPD
Semi-automated Sorting
(2.5+2.3 TPD) Dry Waste
Collection Centre ( 4.2 TPD) 2.3 TPD
3.1 TPD
Weighment of MSW at site
(10.1 TPD)
6.6 TPD 3.5 TPD for 35 days Aerobic Compost
(40% moisture loss)
Designated C&D disposal
area (2.5 TPD)
1.2 TPD
11.7 TPD
16.9 TPD
Reused as culture (0.7
TPD)
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 24
3.3.3 Construction and Demolition Waste
It is the responsibility of any generator of construction and demolition debris to employ
reasonable and practical means, including source reduction, reuse or recycling, in order to
prevent construction and demolition debris from being disposed finally in low lying areas.
Municipalities may introduce permits system which enable obtaining permits with a
monetary deposit that allows for the tracking of C&D waste.
The construction debris should be disposed off in low lying areas. The TP shall identify the
dedicated low lying area/ location for dumping of construction debris. The existing tractor
trailer in the TP shall use for transportation of C & D waste.
3.3.4 Bio- medical waste
Bio-medical waste generated by Hospitals and clinics is separately collected and transported
by private agency called M/s Shree Consultants which has a common processing facility
located at Mysore, Karnataka. The collection of biomedical waste from Kushalnagar town is
done weekly twice by using 4 wheeled truck with covered body. The existing system for Bio
medical waste is adequate for the town and is recommended to be continued. TP should
ensure that all the bio medical waste generating units come under this mechanism and the
existing biomedical waste processing unit shall be made operational.
3.3.5 Capital cost for integrated solid waste management
S. No.
Description Total Estimated Amount
Contingency - 3%
Grand Total
1 Awareness and IEC ₹ 2,02,300.00 ₹ 0.00 ₹ 2,02,300.00
2 Collection & Transport ₹ 55,26,495.00 ₹ 1,65,794.85 ₹ 56,92,289.85
3 Processing Facilities ₹ 1,81,76,919.13 ₹ 5,45,307.57 ₹ 1,87,22,226.70
4 Sanitary Landfill Facilities ₹ 37,62,297.00 ₹ 1,12,868.91 ₹ 38,75,165.91
5 Recycling facilities ₹ 5,87,500.00 ₹ 17,625.00 ₹ 6,05,125.00
6 Common Facilities ₹ 62,35,545.00 ₹ 1,87,066.35 ₹ 64,22,611.35
7 Leachate Treatment Facility ₹ 4,66,725.81 ₹ 14,001.77 ₹ 4,80,727.58
8 Social Forestry and Crop Demonstration
₹ 3,47,910.00 ₹ 10,437.30 ₹ 3,58,347.30
9 Dry Waste Collection Centre ₹ 7,23,971.00 ₹ 21,719.13 ₹ 7,45,690.13
Total Estimated Amount ₹ 3,60,29,662.94 ₹ 10,74,820.89 ₹ 3,71,04,483.82
3.3.6 Operation and Management cost of proposed MSWM
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 25
S. No
Particular No. Unit cost Unit Monthly expenses
Yearly expenses
1 Man power cost Salaries for staff
Plant Operator 1 20,000.00 Nos. 20,000.00 2,40,000.00
PK at Processing Facility 6 16,105.01 Nos. 96,630.04 11,59,560.52
Drivers for backhoe & Tractor trailer
2 14,416.03 Nos. 28,832.07 3,45,984.82
Security cum weighbridge operator
1 12,512.50 Nos. 12,512.50 1,50,150.00
Drivers for Auto tipper/Mini tipper
7 13,831.39 Nos. 96,819.73 11,61,836.73
Drivers for Compactor 1 14,416.03 Nos. 14,416.03 1,72,992.41
Drivers for Tractor Trailer for street sweeping, C&D
2 13,831.39 Nos. 27,662.78 3,31,953.35
Pk at Dry waste collection centre
2 16,105.01 Nos. 32,210.01 3,86,520.17
O/S PKs for Auto tipper 4 16,105.01 Nos.
64420.02864
773040.3437
O/S PKs for Compactor 1 16,105.01 Nos. 16,105.01 1,93,260.09
O/S Loaders for tractors 6 16,105.01 Nos. 96,630.04 11,59,560.52
O/S PKs for street sweeping-Type A
1 16,105.01 Nos. 16,105.01 1,93,260.09
O/S PKs for street sweeping-Type B
1 16,105.01 Nos. 16,105.01 1,93,260.09
O/S PKs for street sweeping-Type C
1 16,105.01 Nos. 16,105.01 1,93,260.09
O/S PKs for street sweeping-Type D
1 16,105.01 Nos. 16,105.01 1,93,260.09
Permanent staff
Health inspector 1 20,000.00 Nos. 20,000 2,40,000.00
Supervisor 1 22,000.00 Nos. 22,000 2,64,000.00
Pks (sweeping, D2D) 12 22,500.00 Nos. 2,70,000 32,40,000
2 Fuel and power
60.00 Rs. /lit
Auto tipper 7 5.00 L/day 63,000 7,56,000.00
Compactor 1 15.00 L/day 27,000 3,24,000.00
Tractors Trailer 3 10.00 L/day 54,000 6,48,000.00
Backhoe Loader 1 25.00 L/day 45,000 5,40,000.00
3 Power
LS
10,000 1,20,000.00
4 Additives and Chemicals 14 100.00 Rs/TPD 42,000 5,04,000.00
5 Tools/Safety equipment’s
35 3,000.00 set/yr 8,750.00 1,05,000.00
6 Baggage and packing cost
2 300.00 Rs/TPD 13,770 1,65,240.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 26
7 Transportation of finished products
2.64 300.00 Rs/TPD 23,715 2,84,580.00
8 Office cost
LS Rs 10,000 1,20,000.00
9 Maintenance on civil works
17274930.07
2% on Civil cost
Rs 28,791.55 3,45,498.60
10 Maintenance on electrical & mechanical equipment’s
7467495
8% on electrical and mechanical works
Rs 49,783 5,97,399.60
11 Vehicle Maintenance Cost
6554000 5% on vehicle cost
Rs 65,540 7,86,480.00
12 Misc
LS Rs 10,000 1,20,000.00
Total 13,34,00 1,60,08,097
Estimated cost per ton of the waste
S.No Particulars Total Estimated Amount TPD Amount per
Ton
1 Capital cost 37104483.82 16.9 21,95,531.59
2 Operation and Maintenance cost 1,60,08,097.49 16.9 2595.14
3.6 Financing of O&M expenses and projected expenses for the MSWM services
3.6.1 Revenue Generation by Compost and recyclables for the year 2017-18
S. No.
Particulars Quantity in TPD
Unit Cost Amount in Rs. per month Amount in Rs. per annum
A Sales
1 Compost 1.53 2,500.00 1,14,750.00 13,77,000.00
2 Recyclables 1.1 300.00 331.50 3,978.00
3 RDF 2.5 100.00 246.50 2,958.00
Total 1,15,328.00 13,83,936.00
3.6.2 Revenue Generation by user fee collection for the year 2017-18
S.No Waste generators No of generators
Collection Percentage
Rate Amount/annum
1 Slums 1615 40% 25 193800
2 Households 2979 80% 40 1143936
3 Hotels 119 90% 200 257040
4 Institution 20 90% 200 43200
5 Market 1 90% 2000 21600
6 Shops less than 10 sqm 764 85% 110 857208
7 Shops more than 10 sqm 961 90% 130 1349244
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 27
8 Meat/chicken shops 58 95% 200 132240
9 Marriage hall 7 100% 1000 84000
10 Cinema theatre 1 100% 500 6000
11 Hospital 25 100% 200 60000
12 Street vendors 112 80% 110 118272
Total
42,66,540.00
3.6.3 Proposed SWM user fees for next 5 years
S.No Waste generators 2017 2018 2019 2020 2021
1 Slums 25 25 30 30 35
2 Households 40 40 50 50 60
3 Hotels 200 200 250 250 300
4 Institution 200 200 250 250 300
5 Market 2000 2000 1500 1500 3000
6 Shops less than 10 sqm 110 110 125 125 140
7 Shops more than 10 sqm 130 130 150 150 170
8 Meat/chicken shops 200 200 250 250 300
9 Marriage hall 1000 1000 1500 1500 2000
10 Cinema theatre 500 500 400 400 700
11 Hospital 200 200 250 250 300
12 Street vendors 110 110 125 125 140
The revenue generation from user fee collection and compost is given below in which it is
proposed to collect 35% of the operations cost from SWM services for the first year and in
next 5 year about 55% of operations cost shall be covered by revenue from SWM services.
S. N. Description Amount in Rs.per annum
1 Proposed O&M cost 160.08 168.09 176.49 185.31 194.58
2 Proposed Revenue by way of User Charges 42.67
48.15 62.97 70.81 91.54
3 Proposed Revenue by sale of compost and by-product
13.84 14.25 14.68 15.12 15.58
4 Salaries by Untied SFC 51.36 53.93 56.62 59.45 62.43
5 Salaries from SFC grants for permanent staff
37.44 39.31 41.28 43.34 45.51
6 Total revenue proposed revenue 145.30 155.64 175.56 188.73 215.05
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 28
7
Surplus or deficit (SWM) = Proposed total SWM O&M cost- Proposed total revenue generated (SWM related cess) 14.78 12.44 0.93 (3.41) (20.47)
% of cost recovered from SWM services 35% 37% 44% 46% 55%
3.7 Financing the Capital cost
SN Particulars Details
1 GoI share @ 35% of project Cost 129.87 Lakhs
2 GoK share @ 11.67% of GOI share 43.29 Lakhs
3 ULB’s contribution (14th Finance, CM Special Grants, SFC, others)
16.97 Lakhs
4 Total funds available 190.12 Lakhs
5 Deficit = Estimated DPR cost (capital cost)– total funds available
=371.04– 190.12 Lakhs =180.92 Lakhs
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 29
1. INTRODUCTION
1.1 REPORT OVERVIEW
Solid Waste Management (SWM) is one of the important obligatory functions of the urban
local bodies in India. It is also one of the primary responsibilities of the municipal
authorities. However, most of them are currently unable to fulfil their duty to ensure
environmentally sound and sustainable ways of dealing with waste generation, collection,
transport, treatment, and disposal. The failure of municipal solid waste management
(MSWM) can result in serious health problems and environmental degradation.
Furthermore, even the collected waste is disposed of in uncontrolled dumpsites or burned
openly, thus contributing to severe environmental impacts including pollution of water
resources and air.
As per the scope of work specified, TTPL has prepared a draft detailed project report (DPR)
and allied Engineering Drawings on Solid Waste Management Plan for Kushalnagar Town
Panchayat on an integrated approach in accordance with MSW Rules 2000.
The detailed project report covers an introduction to project, town profile, status of the
existing solid waste management system, proposed MSW management system, design of
waste processing plant, design of sanitary landfill, engineering drawings, incremental cost of
proposed system, operation & maintenance cost, institutional and financial framework. The
health & legal aspects of the system and provision of community participation through IEC
has also been discussed in detail in the report.
1.2 NEED FOR THE PROJECT
Ministry of Urban Development has launched Swachh Bharat Mission (SBM) on 2ndOctober,
2014. The Mission covers all 4,041 statutory towns/cities as per 2011 census. Solid waste
management is one of the admissible components under SBM.
As per Guidelines for Swachh Bharat Mission – Urban (SBM-U) component IV, ULB’s are to
prepare DPR for solid waste management of their town in consultation with state
government. The Directorate of Municipal Administration (DMA), Karnataka has directed to
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 30
Town Panchayat, Kushalnagar to prepare Detailed Project Report (DPR) on integrated solid
waste management for Kushalnagar TP under swachh Bharat Mission.
Kushalnagar: Kushalnagar is a Town Panchayat located in Kodagu District, on the banks of
Kaveri River, in the state of Karnataka, India. The town is located on Bantwal -Mysore state
highway 88. Kushalnagar is at a distance of 80Kms from Mysore and 30 Km from Madikeri.
Kushalanagar is located at 12.47°N 75.97°E. It has an average elevation of 831 metres. The
Town Panchayat of Kushalnagar has a population of 15,326 as per 2011 census and an area
of 18.5 km².
The Town Panchayat of Kushalnagar though has made a good effort to modernize its SWM
system; it still has these deficiencies in varying degrees. There is a need to make substantial
improvement in the SWM practices prevailing in the town to raise the standards of health,
sanitation and urban environment keeping pace with the rapid urbanization and growing
population. Hence there is a need for strengthening and modernization of the present
practice of MSWM in the town.
Exhibit 1-1: Kushalnagar Summary
Name of the Town Kushalnagar Town Panchayat
Population as per Census 2011 15,326
Area 18.5 Sq.km
Number of wards 16
Temperature 28°C during summer; 15°C during winter
Length of Road
A type road : 6km
B type road : 10km
C type road : 12km
D type road : 20 km
Total road length: 48km
No of houses and slums 4594 households
No. of Hotels 119
No. of Marriage Halls 06
No. of Markets 01
No. of Chicken/Mutton/Fish Stalls/
Slaughter houses 58
No. of Hospitals 25
No. of Institutions 20
No. of Temples/Churches/Mosque 15
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 31
No. of Cinema Theatres 01
No. of Bus-stands 01
No. of Railway stations Nil
No. of Petty shops 160
No. of Rice mill 39
No. of Shops 1565
1.3 SCOPE AND OBJECTIVE OF THE PROJECT
Kushalnagar TP’s objectives for the consultancy project on “Preparation of DPR on
Integrated Solid Waste Management under Swachh Bharat Mission” are to conduct detailed
study on existing SWM mechanisms and to prepare a DPR.
The detailed of scope of assignment of the project is given below:
A. SOLID WASTE COLLECTION & TRANSPORTATION PLAN
i. Conducting detailed study on the existing solid waste system in the town
ii. Conduct waste sampling for assessment of quantity and quality of waste
generated
iii. Prepare a route plan based on the GIS map for MSW collection
iv. To provide an efficient collection and transportation plan for the town
v. To provide details of additional facilities required for efficient collection
system
vi. To provide technical support to the Town Municipal Council
B. SOLID WASTE PROCESSING PLAN
i. To conduct waste character, quantity and chemical analysis on the MSW
ii. Provide Designs, maps and estimations required for setting up the processing
facility and operate the solid waste processing facility
iii. Providing solutions for carrying out processing of waste using available and
accepted technologies like aerobic composting by windrow method, vermin-
composting, bio composting using eco - friendly microbial culture and bio-
methanation etc.
iv. Carrying out disposal of only reject/inert waste in sanitary landfills
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 32
1.4 STRUCTURE OF THE REPORT
The detailed project report is organized in thirteen chapters detailed about the project
interventions, abstract of cost estimates comprising of capital, operation and maintenance
cost with BOQs for proposed components along with supporting quotations, financial
viability, benefit assessment for improving solid waste management systems. These
chapters are briefed below.
Exhibit 1-2: Chapters of the DPR
S.
No. Chapter Details
1 Introduction Presents the background, scope and objective of the
project.
2 Town Profile
Provides the understating of town profile which brings
out the nature and details of the study area such as
location, topography, demography, climate,
transportation, organization and political setup of the
town
3 Existing SWM system
Provides details of existing SWM practices, quantification
& characterization of the waste including the existing
road, door to door collection, transportation and
processing systems
4 Proposed SWM system
Presents proposed solid waste management practices
gives out details on the proposed segregation, collection,
transportation and processing plan including the
technology and processes
5 Project Cost This chapter provides capital investment of solid waste
management facility
6 Project Institutions
Framework
This chapter provides details on the administrative
resources to be increased for setting up an efficient waste
management plan
7 Project Financial
Structuring
This chapter examines the sources and composition of
funding for the project
8 Project Phasing
This chapter provides details of project plan in terms of
scheduling and phasing including pre-construction
commencement activities and covering all relevant
modules and components
9 Project O&M Cost This chapter provides Operation and Maintenance of solid
waste management facility
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 33
10 Project Benefit
Assessment
This chapters provides details on the benefits from
societal perspective (both social and economic) and
negative externalities (i.e. adverse impacts) from a
societal perspective ( both social and economic)
11 Public Awareness
This chapter provides public awareness in terms of MSW
segregation at source level and 3R concept. Also provides
Information education, communication and awareness
programmes
12 Annexures
Annexures provide additional details to the DPR like
drawings, estimates, quotations, study formats
conducted, census data of 2011, SWM rules 2000,
Karnataka State Policy and Karnataka High Court Order for
source segregation and Clients comments from Draft DPR.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 34
2 TOWN PROFILE
2.1 HISTORY
Kushalnagar is a Town Panchayat in district of Kodagu, Karnataka, India. The city is divided
into 13 wards for which elections are held every 5 years. The town is located in the east of
Kodagu district, on the banks of Kaveri River, in the state of Karnataka, India. According to
popular myth, the name was given by Hyder Ali who was camped there when he received
news of the birth of his son Tipu and called it as Kushyal nagar.
Exhibit 2-1: Google Map of the Kushalnagar
2.2 LOCATION AND TOPOGRAPHY
Exhibit 2-2: Topology of Kushalnagar
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 35
Kushalnagar is at a distance of 80Kms from Mysore and 30 Kms from Madikeri. Kushalnagar
is located at 12.47°N 75.97°E. It has an average elevation of 831 metres (2726 feet). The
Town of Kushalnagar has a population of 15,326 as per 2011 census. The area of the city is
18.5 km².
2.3 DEMOGRAPHY
The Kushalnagar Town Panchayat has population of 15,326 of which 7,742 are males while
7,584are females as per report released by Census India 2011.Population of Children with
age of 0-6 is 1,724 which is 11.25 % of total population of Kushalnagar (TP). In Kushalnagar
Town Panchayat, Female Sex Ratio is of 980 against state average of 973. Moreover Child
Sex Ratio in Kushalnagar is around 968 compared to Karnataka state average of 948. Literacy
rate of Kushalnagar town is 89.73 % higher than state average of 75.36 %. In Kushalnagar,
Male literacy is around 93.52 % while female literacy rate is 85.87 %.
Exhibit 2-3: Population trends in Kushalnagar
S. No. Census Year Population Increase Growth %
1 1971 5000 - -
2 1981 6936 1936 38.72
3 1991 9472 2536 36.56
4 2001 13186 3714 39.21
5 2011 18249 5063 38.40
Source: Census of India, 2011
Schedule Caste (SC) constitutes 13.84% while Schedule Tribe (ST) was 2.85% of total
population in Kushalnagar (TP). Out of total population, 5,525 were engaged in work or
business activity. Of this 4,360 were males while 1,165 were females. In census survey,
worker is defined as person who does business, job, service, and cultivator and labour
activity. Of total 5,525 working population, 94.17 % were engaged in Main Work while 5.83
% of total workers were engaged in Marginal Work.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 36
Exhibit 2-4: Ward level Population and Households of Kushalnagar in Census 2011
Ward No. Population Household
1 1269 312
2 1313 321
3 1461 343
4 985 242
5 888 212
6 1146 294
7 1831 447
8 1147 264
9 383 102
10 1154 241
11 1204 330
12 1085 289
13 1460 391
14 984 271
15 922 243
16 1017 292
Total 18,249 4,594
Source: Census of India, 2011
2.3.1 Population Projection
Population projection is one of the important aspects of planning or designing any urban
infrastructure. There are several methods by which population projections can be done.
Some methods are ad-hoc method while some are iterative methods. The various factors
affecting population projection are:
• Birth rates, death rates and migration trends
• Plans and Policies of the Government
• Infrastructure facilities such as housing, water supply, roads
• Employment providing potential
• Natural as well as man- made hazards
Government of India, Ministry of Urban Development has published a Manual on Municipal
Solid Waste Management which documents methods of population projection that are
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 37
widely used in planning of solid waste management. Following methods have been outlined
in the manual.
• Arithmetic Progression Method (APM)
• Geometric Progression Method (GPM)
• Varying Increment Method or Incremental Increase Method (IIM)
2.3.1.1. Design Population
Projection has been performed along similar lines for the requisite design period of the
proposed improvements to the applicable components of the MSWM system. Projection
has been performed for the present (2016), intermediate (2026) and ultimate stages (2036)
based on factors such as ward density (present), relative location of the ward, access the
town center and other facilities, present land-use pattern, potential for future change and
others. The below exhibit shows the projected population and has also been adopted as the
design population.
Exhibit 2-5: Projected Design Population of Kushalnagar
S.
No. Year
Projected Population Population
considered (Avg.
of AP, GP& II)
Arithmetic
Progression
Method
Geometric
Progression
Method
Incremental
Increase
Method
1 2016 46,318 48,469 48,578 47,788
2 2021 50,320 56,055 56,028 54,134
3 2026 54,322 65,074 64,914 61,437
4 2031 58,325 75,528 75,539 69,797
5 2036 62,327 87,414 88,273 79,338
2.4 CLIMATOLOGY
2.4.1 Rainfall
The monthly rainfall for Kushalnagar town in the year 2014 and 2015 are given in below
exhibit. The monsoon generally breaks in the district during June and lasts till September.
The total annual precipitation in the year 2014 and 2015 are 3,347mm and 2,944mm
respectively.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 38
Exhibit 2-6: Monthly Rainfall of Kushalnagar
S.No Months Monthly Rainfall in mm
2014 2015
1 January 0.00 0.00
2 February 0.00 0.00
3 March 0.00 36.00
4 April 15.00 77.00
5 May 116.00 126.00
6 June 624.00 651.00
7 July 1119.00 1033.00
8 August 951.00 464.00
9 September 316.00 230.00
10 October 147.00 231.00
11 November 21.00 96.00
12 December 38.00 -
Total 3,347.00 2,944.00
Source: Accuweather
Exhibit 2-7: Graphical Representation of Monthly Rainfall of Kushalnagar
2.4.2 Temperature
The monthly temperature for Kushalnagar in the year 2014 and 2015 are given in below
exhibit. The hottest months are in March and April and coldest months are between
November and January. The maximum temperature falls in the year 2014 and 2015 were
38°C in the month of March and 36°Cin the month of March respectively. Similarly, the
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 39
minimum temperature falls in the year 2014 and 2015 were 12°C and 9°C during January
respectively.
Exhibit 2-8: Monthly Temperature of Kushalnagar
Months Monthly Temperature °C
Max, 2014 Min, 2014 Max, 2015 Min, 2015
January 32.00 12.00 32.00 9.00
February 34.00 13.00 36.00 11.00
March 38.00 13.00 36.00 17.00
April 37.00 18.00 35.00 18.00
May 34.00 18.00 34.00 19.00
June 32.00 19.00 32.00 19.00
July 29.00 19.00 30.00 19.00
August 32.00 19.00 31.00 18.00
September 32.00 18.00 31.00 18.00
October 31.00 19.00 33.00 17.00
November 30.00 14.00 31.00 15.00
December 32.00 12.00 - -
Source: Accuweather
Exhibit 2-9: Graphical Representation of Monthly Temperature of Kushalnagar
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 40
2.5 TRANSPORTATION
By Rail
The nearest railway station to Kushalnagar is Krishnarajanagara railway station at a distance
of 63.7 km. Hassan and Mysuru are other nearest Railway stations at a distance of 80.6 km
and 87.7 km respectively. The other railway stations are Thalassery and Kannur in Kerala, at
a distance of 125 km each.
By Road
Kushalnagar is well connected by road network to Mangaluru168 km towards its west and
Mysore88 km town towards east and Bengaluru237 km town towards east. Kushalnagar is
also well connected by road with other places like Kannur, Thalassery, Iritty and Wayanad of
neighbouring state Kerala.
By Air
Mysore Airport is the nearest airport, which is about 102 km from Kushalnagar. The other
airports are Mangalore International airport, Mangalore situated at 175km distance,
Kempegowda International airport, Bangalore situated at 260 km distance and Calicut
airport, Calicut situated at 215 km distance.
2.6 TOURIST CENTERS
Dubare Forest: Dubare is known for its elephant camp,
a forest camp on the banks of the River Kaveri about
8km from Kushalnagar Town in the district
of Kodagu, Karnataka. It is an important base for the
Karnataka Forest Department's elephants.The main
Attraction is Elephant Glimpse, River View.
Harangi Reservoir: Harangi is the only Dam in
Coorg District. This Dam provides water for
agriculture to the Hassan District and some part of
Coorg District. 11000 Volt of Electricity generating
by this Dam. In the Recent years tourists not
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 41
allowed inside the dam because of safety (You can watch this dam from 400 to 500 mtr).
Kaveri Nisargadhama: Kaveri Nisargadhama is an
island formed by river Kaveri near Kushalnagar in the
district of Kodagu, Karnataka. It is approximately 3
km from Kushalanagara, off the State Highway and
30 km from Madikeri and 95 km from Mysore. It is a
64-acre island with lush foliage of
thick bamboo groves, sandalwood and teak trees.
The island is accessible through a hanging rope bridge. There aredeer, rabbits, peacocks,
and a children's playground as well as an orchidarium.
Tibetan Golden Temple: more than 50 years ago
Tibetan comes to India by the honor of mahatma
Gandhi. One of the Tibetan Settlement located in
Bylukoppe of Mysore District and border of Coorg
District. They built many Temples of Buddha with
great traditional style, this is one of the best
attractions to tourists, Thousands of lama’s praying in the temples with tradition.
Valnur fishing camp: it’s on the banks of River
Cauvery near Kushalnagar, is an ideal place for
all the fishing enthusiasts. Wide range of fishes
can be found here. Variety of birds can also be
seen.
Chikli hole: It is located near Nanjarayapattana and 18 km from kushalnagar. It is one of the
small reservoirs on the Cauvery stream. It has been overflowing. The overflow of water on
the semi-circular structure of Chikli-hole reservoir, which has no crest gates, attracts
tourists. It is surrounded by Meenukolli reserve forest on one side and coffee estates on the
other side. The reservoir is 72.6 metre high and has the capacity to store 18 TMC water and
irrigate 865 hectare farm land.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 42
2.7 URBAN LOCAL BODY
2.7.1 Political Setup
The elected members of the Kodagu district consisting of the Member of Parliament (MP),
the member of the legislative assembly (MLA) and the Member of the legislative
Corporation (MLC) are honorary members of the town municipal body. There are 13 elected
members, one for each ward. From the elected members to the TP the President and Vice
President are elected. The TP has various standing committees for different types of sector
including works, health, finance etc. to enable a smooth integration of the various inputs.
Elections were last held in the year 2013. Municipal elections were held for every five years.
Every month there is a general body meeting held in the office. The members of the
standing committee also meet before and after each meeting.
Exhibit 2-10: Political Chart of Kushalnagar
MP
MLA
President
Members
Vice President
MLC
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 43
2.7.2 Ward and Administrative Setup
Kushalnagar TP has various departments for the effective management and administration.
The Chief Officer is the chief executive of the Municipal Council. The executive power of the
Kushalnagar is vested with the Municipal Commissioner appointed by the Directorate of
Municipal Administration, Government of Karnataka. The below exhibit shows the
organisation chart of Kushalnagar TP. The Kushalnagar TP has following departments.
• Community affairs department
• Revenue Department
• Accounts department
• Administration department
• Data management department.
• Environment section
Exhibit 2-11: Organization Chart of Kushalnagar
Chief Officer
Bill Collector Jr. Health Inspector
Sanitary Supervisor
Junior EngineerFirst Garde
Revenue Inspector
First Division Assistant
Second Division Assistant
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 44
Exhibit 2-12: Photographs of Meeting with Officials
Meeting with Chief Officer Meeting with Project Director, DUDC
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 45
3 EXISTING STATUS OF SOLID WASTE MANAGEMENT INFRASTRUCTURE
3.1 OVERVIEW OF SWM IN THE ULBS
A detailed study was conducted by the consultants in Kushalnagar for understanding the
existing solid waste management infrastructure. The study was conducted in December
2015. The study included the ULB officers, executives and stakeholders in loop. This chapter
gives a detailed picture of the existing Solid Waste management system in Kushalnagar. This
chapter provides an understanding of the system prevalent in the town. The total municipal
waste generation in Kushalnagar town is estimated to be about 10.7tons per day (TPD)
which is quite higher than the towns of its size in Karnataka state due to large number of
floating population and addition of waste generation from two villages namely, Mullusoge
and Kudumangallore which is disposed at Kushalnagar town informally, of which about 7.1
tons of waste is collected and transported to the landfill site at present as per the study
details. Primary collection is conducted by door to door collection and by disposal of waste
generators in open locations.
The sweeping, collection and drain cleaning activity are handled by pourakarmikas and
contract workers managed by Kushalnagar TP. The transportation of waste from all the
sources happens with the auto tipper and tractor trailers. Street sweeping activities are
carried out by combination of pourakarmikas and contract workers. The waste is
transported to the landfill site located on buvanagiri which is located at a distance of about
11 kms and covers an area of 7 acres 15 guntas in two partition divided by road and nala.
The site is owned by Kushalnagar TP and has been allotted for treatment and disposal of
Solid waste.
Bio medical waste generated by Hospitals and clinics is separately collected by private
agency called M/s. Shree consultants which has a common processing facility located at
Mysore, Karnataka. The collection of biomedical waste from Kushalnagar will be done in
weekly twice by using 4 wheeled truck with covered body.
Exhibit 3-1: Revenue payment: Revised budget estimate for 2014-15 for SWM in Budget Year 2015-16
S. No. Particulars Amount in Rs.
1 Pay, allowances and benefits 36,36,329.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 46
2 Wages - Labour and travelling 2,66,335.00
3 Books, periodicals, printing, stationery and photocopying expenses 10,000.00
4 Power and Fuel - Diesel bill 4,06,173.00
5 Other general expenses 25,000.00
6 Safety Equipment and Uniform 28,000.00
7 Sanitary tools and equipment 5,479.00
8 Chemicals and additives 3,00,000.00
9 Repair and maintenance – Vehicles 99,347.00
10 Repair and maintenance - other fixed assets 1,25,075.00
11 Operating expenses - landfill site 5,00,000.00
12 Outsourced operating expenses - Tractor driver 2,50,000.00
13 Outsourced operating expenses – Pourakarmikas 9,71,591.00
14 Awareness Programme Expenses 1,86,599.00
Total 68,09,928.00
Exhibit 3-2: Capital payment: Revised budget estimate for 2014-15 for SWM in Budget Year 2015-16
S. No. Particulars Amount in Rs.
1 Plant and Machinery 8,72,000.00
2 Other Fixed Assets –Other 13,24,125.00
Total 21,96,125.00
3.2 MSW QUANTIFICATION
A detailed estimate of the MSW generation has been carried and presented in this section.
The estimate of MSW generation has been done by three ways. A detailed sampling was
done for the different waste generators in Kushalnagar town and by using the data on the
number of such generators from TP data; the quantity of waste generated has been
estimated.
The second approach adopted was to use a waste generation rate, Kushalnagar lies between
the population10,000 to 19,999 (class IV) as per Supreme Court Committee classification
and as per draft MSW Manual 2014, waste generation rate was found to be between 200
and 300 gm/ capita /day in small towns / cities with population below 2,00,000. A higher
number of 300 grams has been adopted as significant part of the town is spread out.
The third approach adopted was to quantify the waste collected by secondary
transportation vehicles to dumpsite. The waste collected and disposed-off in the dumpsite
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 47
was estimated based on actual measurement of the arrivals at the dumpsite over a 3 day
period. All the secondary transportation vehicles were weighed for 3 consecutive days and
the waste collected and transported was estimated.
3.2.1 Waste generation estimate based on generators
There are various source of wastes from which waste is generated namely, residential,
commercial establishment, hospital and clinics, worship, cinema theatres, education
institutions, markets, meat/chicken/slaughter house, hotels and restaurants and Street
Sweeping. To estimate the waste generated at source a sample survey was conducted by
weighing waste generated at each generator source for 3 consecutive days to arrive at the
average waste generated by waste generator.
The samples selected for survey included all types of participants of a generator type. For
examples in case of residential, the selected residential source included household, declared
slum and undeclared slum from different wards.
The following table shows number of sources and the average waste generated in each
source base on the waste estimation at Kushalnagar. About 9 sources were selected which
are major contributors for the waste generated in the Kushalnagar and 5% of miscellaneous
waste including floating population for the waste generated in Kushalnagar.
To arrive at number of sources in the town, most of the data
like population, households and street length is obtained
through secondary data collection format. Residents are taken
from the census, street length from the Kushalnagar town,
other sources such as markets, commercial establishment data
were obtained through secondary data collection.
The detailed data on the sampling and waste generators is presented in Annexure A.1. The
synopsis of the data is presented in below exhibits. The major waste generation is from
residents followed by street sweeping waste. The other sources generate lesser wastes.
9 various major contributor were selected as source for waste estimation
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 48
Exhibit 3-3: Estimation of Waste Quantity from Waste Generators
S. No. Waste Generators No of Generators
Avg. waste per day in Kg
Total waste in Kg
Total waste in Tonnes
1 Household 2979 1.3 3783.33 3.78
2 Commercial establishments
1565 1.1 1784.10 1.78
3 Slum 1615 0.8 1211.25 1.21
4 Hotels 119 4.6 547.40 0.55
5 Meat/Chicken shops/Slaughter house
58 4.4 255.00 0.26
6 Institutions 20 3.6 72.00 0.07
7 Veg. Markets 1 30.3 30.30 0.03
8 Petty Shops 160 0.5 80.00 0.08
9 Street Sweeping
Type A 6.0 40.0 240.00 0.24
Type B 10.0 21.0 210.00 0.21
Type C 12.0 10.0 120.00 0.12
Type D 20.0 7.4 148.00 0.15
10 Miscellaneous waste 5%
333.69 0.33
Total waste generated at Kushalnagar Town 8815.07 8.82
Total waste generated at Kudumangalore Village 1895.00 1.90
Total 10710.07 10.71
C&D waste 0.69
Source: Study Conducted by TTPL
The total municipal waste generation in Kushalnagar town is estimated to be about 10.7
tons per day (TPD) which is quite high due to disposal of waste generation from one village
namely Kudumangallore at Kushalnagar town informally.
Kushalnagar town has grown such a way that there is no virtual border between the
neighbouring villages of Mullosoge and Kudumangalore. Though the Kushalnagar town is
supposed to manage waste generated in the town jurisdiction, the town informally receives
waste from these 1 village in open points. Generally, it is learnt from the experience that the
waste generators of the 1 village dispose their waste in nights into the jurisdictions of
Kushalnagar TP. The Kushalnagar administration has taken actions to restrict villagers
disposing waste into TP area but have not been successful. The administration has taken a
call that it is easier to dispose the 2-3 ton of waste generated by these village than to
prevent them from disposing waste.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 49
Exhibit 3-4: Google Image for Location of Kushalnagar TP and Neighbouring Villages
The landfill site of Kushalnagar is located in a village called Kudige, since the landfill site is
located in Kudige village, the waste generated in Kudige is also disposed in to the landfill site
of Kushalnagar. The Waste generated in Kudige is about 1.1 TPD.
Exhibit 3-5: Distance and Waste Generation of neighbouring Villages and Kushalnagar Town
Name of the Place Distance (to Kushalnagar)
in km Waste Generation in TPD
Kushalnagar - 8.82
Kudumangalore 3.9 1.90
Kudige 4.5 1.10
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 50
Exhibit 3-6: Graphical Representation of Waste Quantity from Waste Generators
Exhibit 3-7: Photographs of Waste Generator Sampling Study
Collecting sample from Household
Collecting waste from Commercial Establishments and Petty Shops
3.2.2 Normative Estimate of Waste Generation
The population of Kushalnagar and Kudumangalore in 2011 are 18249 and 9,346
respectively. Floating population of Kushalnagar including tourist is estimated to be about
3.78
1.78
1.21
0.55
0.26
0.07
0.030.08
0
0.24 0.21
0.120.15 0.33 Household
Commerical establishments
Slum
Hotels
Meat/Chicken shops/SalughterhouseInstitutions
Veg. Markets
Petty Shops
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 51
6,130 i.e. 40% of total population due to tourist attraction. Based on waste generation of
300 grams per capita for Kushalnagar and 200 grams per capita for Kudumangalore village,
the estimated waste generation per day is about 10.1 tons per day. This number is lesser
than the estimated waste generation of 10.7 tons of waste. The estimated waste generation
of 10.7 tons is considered as actual waste generation in these towns town which is inclusive
of waste generated by floating population.
3.2.3 Estimation of Waste Quantity using Secondary Transportation Vehicle
A survey of all the vehicles reaching the dumpsite for 3 days from 4thDecember to
6thDecember 2015 was undertaken. All the MSW collected from the town is regularly
transported and dumped in dumpsite.
Three Tractor trailer which carries waste to dumpsite, were
weighed at an adjacent weigh bridge called Anugraha coffee
curing works Weigh Bridge located on Avadani layout,
Kushalnagar for all trips prior to dumping at dumpsite. In weigh
bridge weighment, both load and tare weights of the vehicles
were obtained. The data by vehicle is presented in Annexure A.2.
The consolidate data is presented in below exhibit.
Exhibit 3-8: Estimation of Waste Quantity from Secondary Transportation Vehicles
S. No. Sample date Quantity of waste in TPD
1 04/12/2015 4.58
2 05/12/2015 9.52
3 06/12/2015 7.18
Average waste per day 7.09
Source: Field Study conducted by TTPL
Based on the study conducted by TTPL, it is noted that Kushalnagar town and
Kudumangalore village’s waste disposal site receives an average quantity of waste at about
7.1 TPD.
An analysis of the transportation of waste by tractor trailer are presented below. Tractor
trailer transport an average of 1.4tons of waste in single trip a day.
Exhibit 3-9: Data on Transportation of Waste to Disposal Site
Weighment of vehicles were done in M/s. Anugaraha coffee curing works weigh bridge, Kushalnagar
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 52
S. No. Type of Vehicle
Number
of
Vehicle
Number
of Trips
per day
Weight in tons Average
in tons 04/12/15 05/12/15 06/12/15
1 Tractor Trailer 1 2 2.32 1.73 1.86 1.97
2 Tractor Trailer 1 2 2.26 3.50 1.81 2.52
3 Tractor Trailer 1 1 0.00 4.29 3.51 2.60
Total 3 5 4.58 9.52 7.18 7.09
Source: Field Study conducted by TTPL
3.2.3.1 Timings of waste disposal
Collection and Transportation of waste in Kushalnagar town happens in two rounds. The
first round starts from morning 6.00 AM and ends at 10.00 AM and the second round of
collection starts from 11 AM and ends at 1.30 PM in the afternoon. Tractor trailer collects
waste from respective locations which have to be loaded manually. Tractor trailer arrive in
dumpsite at about 9.00 AM. They keep arriving at dumpsite till around 2.00 PM.
Exhibit 3-10: Photographs of Waste Quantification Study
Weighing the truck quantity at weigh Bridge
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 53
Weighment Slip
3.3 MSW CHARACTERISATION
3.3.1 Physical Composition
An analysis of the physical composition of the fresh waste was conducted for 3 days at the
dumpsite as well as waste generators. Based on the analysis, the waste composition is
presented in below exhibits. The details are given as annexure A.3.1 and A.3.2.
3.3.3.1 Physical Composition of Waste from Dumpsite Fresh Sample
The data shows an organic content in the waste of 44.7%, 37.1% recyclable materials, 17.2%
of slit and stones and 0.8% special waste. The quantity of silt and stone is high because of
collection of waste from roads while sweeping. The waste is amenable to composting;
recycling and preparation of refuse derive fuel.
Exhibit 3-11: Physical Composition of Waste in % - Dumpsite Fresh Sample
S. No.
Components Composition in %
Day 1 Day 2 Day 3 Average
1
Wet
Was
te Food Waste 8.89 8.93 9.57 9.13
2 Tree/Fruit/Flower Waste
31.39 13.89 13.76 19.68
3 Grass and Leaf Waste 12.77 16.48 18.56 15.94
Sub-Total
44.75
4
Dry
Was
te
Plastic Containers & Packaging
8.93 9.17 8.98 9.03
5 Paper, Cardboard & Cartons
6.50 10.40 9.55 8.82
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 54
6 Rubber 0.00 2.91 2.39 1.77
7 Rags/Clothes 7.13 6.77 6.99 6.97
8 Wood 2.99 4.37 2.87 3.41
9 Metals 1.28 0.63 0.50 0.80
10 Glass 6.20 6.49 6.36 6.35
11 Inerts 13.31 19.00 19.40 17.23
Sub-Total
54.37
12
Spec
ial
Was
te Electronic
waste/batteries/Bulbs 0.61 0.95 1.07 0.88
13 Bio-Medical waste 0.00 0.00 0.00 0.00
Sub-Total
0.88
Total 100.00 100.00 100.00 100.00
Source: Field Study conducted by TTPL
Exhibit 3-12: Photographs of Physical Composition of waste – Dumpsite Sample
Segregation of dumpsite Waste
Weighing of Segregated Waste
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 55
Segregated Waste
3.3.2 Chemical Composition
The chemical characteristics of MSW samples are analysed and then compared with MSW
(M&H) Rules, 2000 for Compost quality and Fertilizer (Control) Order, 2009 as presented in
below exhibit and the analysis laboratory reports are given in annexure A.3.3.
Exhibit 3-13: Chemical Composition of Waste
S.
No. Parameters Results
Compost Standards
As per MSW Rules -
2000 conc limits
(Heavy Metals) for
Compost (mg/kg,
dry basis)
As per
Fertilizer
Control Order
(FCO) (mg/kg,
dry basis)
1 Moisture Content 6.42% 15-25
2 pH of 10% Solution 8.32 5.5-8.5 6.5-7.5
3 Total Nitrogen (N) 0.28% 0.8
4 Total Phosphates (P2O5) 0.44%
5 Potash (K2O) 0.62%
6 Organic Carbon 6.92% 12
7 Carbon: Nitrogen Ratio (C : N) 24.71: 1 <20
8 Gross Calorific Value in Cal/gm 240.00
Source: Field Study conducted by TTPL
3.4 ORGANIZATION CHART FOR SWM DIVISION
The MSW management activities in the Kushalnagar town are supervised by the health
department of TP, which is headed by a Chief Officer and the organization structure of the
department is set out in the exhibits below.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 56
The Chief Officer is assisted by a Junior Health Inspector and Sanitary Supervisor. Junior
Health Inspector is responsible for management of MSW activities in a set of wards and is
assisted by Conservancy / Dafedar who in turn is responsible for supervision of
Pourakarmikas (PKs) and the contract workers. The staffing pattern of the department is set
out in the exhibit below.
Exhibit 3-14: Organization Chart for SWM Division
Exhibit 3-15: Staffing details of Kushalnagar
S. No. Details of staff Manpower in Nos.
1 Chief Officer 1
2 Health Inspector 1
3 Sanitary Supervisors 1
4 Pourakarmikas (PKs)– Permanent 12
5 Drivers – Contract 8
6 Pourakarmikas (PKs) –Contract 24
Source: Data collected from TP by TTPL
3.5 EXISTING MSW PRACTISING
The current MSW management practice in the town is set out in the exhibit below.
Chief Officer
Jr. Health Inspector
Sanitary Supervisor
Drivers PourakarmikasDrivers & Pourakarmikas
(Contract)
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 57
Exhibit 3-16: Process Chart for Current MSW Practices in Kushalnagar
Source: Data collected from TP by TTPL
Tractor trailer Tractor trailer Tractor trailer Tractor trailer Tractor trailer
Households and Slums
Commercial Establishment
s
Hotels and Restaurants
Street Sweeping
Construction Debris & Drain
Cleaning
Auto tipper Tractor trailer
Disposed at
Dumpsite
Slaughter House
Vegetable Market
D to D
collection
Tractor trailer
Kudige Village Direct Disposal
at Dumpsite
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 58
3.6 BASELINE INFORMATION
3.6.1 MSW Primary Collection
Existing system of MSW collection and transportation is performed by the ULB with the help
of auto tippers and tractor trailers. Waste collected through auto tipper and tractor trailer is
directly transported to dumpsite. About 7.09 tons of waste is collected on a daily basis
based on survey conducted by TTPL.
Presently, collection is managed by a combination of municipal sanitary and contractual
workers. MSW collection in slums is handled by sanitary workers to a moderate extent.
About 3 numbers of tractor trailer and 5 numbers of auto tippers are utilized for the
aforementioned purpose.
In Kushalnagar. Street sweeping is done around the temple area, the core area, and some
markets and commercial areas within the town.
Efforts of collection have been made through employing of contract workers and collection
of waste from bus stand and other commercial areas.
Sanitary workers sweep and collect the streets waste and drainage waste in tractor trailer
Tractor Trailers then used to convey the waste from the collection point to the disposal site.
3.6.2 MSW Storage
There is no practice of storage of waste at domestic level in households or commercial
establishments. Few households are storing waste at source and hand it over to the
collectors while rest dispose the waste at multiple locations like front of their houses or
open points. Most of the waste from market places and commercial establishments
including hotels and restaurants, construction and demolition waste etc., are thrown on the
streets and open points which have been clearing on daily basis.
3.6.3 MSW Secondary Collection & Transportation
Transportation of the solid waste generated by the town is being done by Paurakarmikas
and contract workers. Transportation of waste could be classified into 2 types based on the
collection mechanism as follows: Primary & Secondary transportation. Primary
transportation is transporting of waste generated at source to open areas. The waste is
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 59
collected from door to door by auto tippers and transport to open areas. From open points
waste is transported by tractor trailers and then the waste is transported to dumpsite. The
following flow chart shows the transportation mechanism. Vehicle involved in
transportation of waste are presented in below exhibit.
Exhibit 3-17: Flow Chart on Transportation Mechanism
Exhibit 3-18: Details of Vehicle Involved in Transportation of Waste
S.
No
Type of
Vehicle
No. of
Vehicle
Waste
Collection
point
Disposing
Point
Owned and
Managed
by
Age of Vehicle
1 Tractor
Trailers 3
Open points/Street sweeping/Hot
els/ commercial
establishments
Disposal Site
TP
2 Nos. are seven years old and 1 no is 5 years old
2 Auto Tippers 5 Houses
Open point
(transfer point)
TP
3 Nos. are one year old &2 Nos. are two years old
Source: Field Study conducted by TTPL
Auto Tippers and Tractor trailers are managed by TP and contractor workers. A detailed
vehicle movement analysis has been carried out to estimate the quantity of waste collected
by Kushalnagar town.
Households& slums Auto Tipper
Dump
site Commercial
establishments, Hotels & restaurants,
Market, street sweeping, drain
cleaningand C&D debris
Tractor
trailer
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 60
3.6.4 MSW Processing and Disposal Practise
Kushalnagar town has set up Municipal Solid Waste disposing site on Buvanagiri which is
located in 12°30'56.92"N and 75°57'21.83"E, 11 km away from the town. The landfill site is
in two parts. Part 1 of land is 3 acres 22.9 guntas and part 2 of land is 3 acres 30.68 guntas.
The total area of the landfill site is about 7 acres 15 guntas. This site is being used for
dumping of Municipal Solid Waste generated in the town. The facility has been provided
with a gate, compound wall, goods shed and a watchman’s room. The disposal site is not
being provided with a 24 hour watch man and has no weighing bridge. There is also a water
(bore well) point. The waste brought to the depot by tractor trailer and the waste is dumped
inside the landfill site.
Rag pickers operate inside the site, they collect recyclable waste like plastic covers, plastic
utensils, metal pieces if any and glass bottles. These rag pickers are not authorized but have
been permitted to pick waste from dumpsite. They do not segregate waste into degradable
or non-biodegradable waste but just pick the waste can be sold in scrap shops.
Exhibit 3-19: Google Image of Kushalnagar Dumpsite
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 61
Exhibit 3-20: List of Existing Available Facilities at Dumpsite
S. No. List of Facilities Size Unit
A. Part 1
1 Tank -1 No. 1.1mX1m Sq.m
2 Security Shed -1 No. 4.5mX5.6m Sq.m
3 Compound Wall 513 Rm
B Part 2
1 Windrow Platform 40mx30m Sq.m
2 Storage Shed 3mx8.5m Sq.m
3 Vermi pit - 4 Nos. 4.6mX3.6m Sq.m
4 Tank -1No. 1.1mX1m Sq.m
5 Security Shed -1 No. 4.5mX5.6m Sq.m
6 Gate (2 Nos.) 6.0 M
7 Internal Road - Mud 118 Rm
8 Compound Wall 502 Rm
9 Borewell 1 No.
Source: Topography Study conducted by TTPL
Exhibit 3-21: Photographs of Existing Available Facilities at Dumpsite
Compound wall with gate Security Building
Vermi-composting pit Goods shed
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 62
Windrow Platform Borewell
3.6.5 Street Sweeping and Drain Cleaning
Street sweepings and drain cleanings are the other major components of MSW
management in Kushalnagar. The quantity of street sweeping waste generated per day has
been estimated at 0.53 tons per day based on the study conducted in the town. Street
sweeping activity in the town is carried out by the PKs and contract workers. The street
sweepings and the silt collected from the road side drains are temporarily stored is small
heaps on the road sides or are collected and transferred to tractor trailers for disposal. The
estimated road length in Kushalnagar is 24 km, which has been classified into three
categories depending upon the frequency of sweeping. The classification of roads is as
follows.
Type A: Roads of this type are located in town centres, near bus stand, commercial areas
and common areas which need daily sweeping to keep them clean.
Type B: Roads of this type are located in not so busy areas like semi residential - commercial
areas, school areas, etc, where the locality is not as densely populated like Type A roads and
would require sweeping twice a week to keep them clean.
Type C: Roads of this type are located in purely residential areas where there is considerably
less dirt and people commuting. Commercials centres are very less. These type of roads
require sweeping once in a week to keep clean.
The frequency of sweeping in three categories i.e. Type A, Type B, Type C and Type D are
given in below exhibit. Most of the non-metalled roads and gunta layouts are not
considered for street sweeping. Out of 48 km road length only 6.0 km is considered for daily
sweeping whereas other streets are swept once in 3 days or once in a week.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 63
Exhibit 3-22: Frequency of Street Sweeping in Kushalnagar Town
S.
No. Parameter
Road length
in km
Frequency of
sweeping
1 Type A (town centre, commercial areas and
important areas) 6.0 Daily
2 Type B (medium density areas and housing
colonies) 10.0
Once in three
days
3 Type C (low density areas and fringe areas) 12.0 Once in a week
4 Type D (low density areas and fringe areas) 20 Once in 15 days
Total road length 48.0
Source: Study Conducted by TTPL
3.7 EXISTING TARIFF & COST RECOVERY METHODS
The existing cost recovery scenario for the services provided by Kushalnagar town in with
respect to MSW management is discussed below.
3.7.1 Past Five/Ten Years Trends
For the services provided by TP for collection and transportation of MSW, there are a
service charges / user charges that have been collected from various generators in the past
five years. The below exhibits shows the User fee/Collection fee for SWM in last year 2014.
Exhibit 3-23: User Fee/Collection fee for SWM in 2014
S. No. Particulars Price / Month/ Unit Amount in
Rs. Per Month
1 Household 10.00 26,516.00
2 Commercial 30.00 38,367.00
Total 40.00 64,883.00
Source: Study Conducted by TTPL
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 64
3.7.2 Cost Recovery Method
In order to recover part of the service delivery costs incurred for delivery of MSW
management services, Kushalnagar had passed a resolution, specifying the user charges
payable by the citizens/bulk generators. The resolution is under implementation and the
collections of user charges from various generators have commenced from 2012-13.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 65
4 PROJECT DEFINITION, CONCEPT, SCOPE AND DETAILING
4.1 LAND AVAILABILITY
For delivering the MSW services, the primary requirement of land would be for compost
facility for treatment of MSW and sanitary landfill facility for disposal of MSW.
4.1.1 MSW Collection and Transportation
With respect to collection of MSW and its transportation to treatment facility and sanitary
landfill facility, there is no requirement of land. However, with respect to litter bins for Type
A and B roads, the same would need to be placed on the road sides, for which indicative
locations have been identified. As such lands belong to TP; hence, there is no requirement
for additional land or land acquisition for implementation of proposed collection and
transportation activities.
4.1.2 MSW Processing and Disposal
Kushalnagar Town Panchayat has developed civil structure for windrow compost facility and
security shed at Buvanagiri in Kudige grama panchayat which is located in 12°30'56.92"N
and 75°57'21.83"E, the existing dumpsite is 7 acres 15 guntas of land, located at a distance
of 11 km from the town. This existing dumpsite is proposed to be modified and used for
development of a sanitary landfill. Hence additional land would not be required.
4.2 WASTE GENERATION FORECAST
The total waste generation as per generator based assessment is about 10.7 tons per day.
The normative estimate for a class IV town like Kushalnagar with floating population and
class V town like Mullusoge and kudumangalore are also 10.1 tons per day. The waste
generation of 10.7TPD is adopted as a realistic waste generation. An average of about 7.1
tons per day is collected. The collection efficiency is about 66%.
The waste generation would increase with population and with growth in waste generation
rates. The waste generation has been estimated for a 20 year time frame at 5 year intervals
and presented in below exhibit. The waste generation rate is expected to grow at 1.3% per
annum. The waste quantities are expected to increase from the present level of 10.7 TPD to
28.5 TPD in the next 20 years. With better segregation and improvement in the waste
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 66
collection systems a decrease in waste delivered to the disposal can be achieved. The
estimation of waste generation and projection for Kushalnagar town, Mullusoge village, and
Kudumangalore village is calculated with respect to population projection of these towns
which is given in below exhibits.
Exhibit 4-1: Estimation of Waste Generation and Projection
Year Population Waste generation rate in
kg/Capita Waste quantity in TPD
2016 42,084 0.298 12.3
2020 46,932 0.314 14.4
2026 55,316 0.339 18.2
2030 61,720 0.357 21.3
2035 70,750 0.381 25.8
Source: Projection by TTPL
4.3 STORAGE OF WASTE AT SOURCE
Storage of waste in households is key aspect of establishing good SWM practices. To
conduct effective storage of waste at source, Kushalnagar town panchayat should direct and
order passed by Karnataka High Court on Dec 2015 for segregation at source level and the
same has to be implemented and requires that waste is stored at source. Segregation of
waste is mandated by the MSW Rules 2000 and the same has to be implemented and
requires that waste is stored at source. The requirements of storage of waste at source are
presented for different waste generate below.
It is essential to make mandatory that waste generators do not throw any solid waste in
their neighbouring, on the streets, open spaces and vacant plots or into drains.
4.3.1 Households
Each and every household shall keep the food waste/biodegradable and hazardous/sanitary
waste as and when generated in a separate domestic waste container and keep
dry/recyclables wastes in another container/bag or sacks.
For biodegradable waste and hazardous/sanitary waste, two dust bins/containers of 10 litre
(0.010 m3) capacity for a family of 5 members would ordinarily be adequate. Wet wastes
should preferably not be disposed of in plastic carry bags. HDPE woven sacks shall be used
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 67
for storage of dry waste. Two numbers of dust bins/containers (10 ltrs) and HDPE woven
sacks shall be provided to all the households by TP.
Exhibit 4-2: Requirement of Dust Bins and Sacks for source Segregation
S. No. Particulars Capacity Numbers of Households
(designed year for 2016)
1 Containers 10 litres 4,155
2 HDPE woven sacks HDPE woven sack
(medium sized) 4,155
They shall keep the domestic hazardous and sanitary waste and store in 10 litre bin listed
below separately and hand over to the collection staff separately.
• Aerosol cans
• Batteries from flashlights and button cells
• Bleaches and household kitchen and drain cleaning agents
• Car batteries, oil filters and car care products and consumables
• Chemicals and solvents and their empty container
• Cosmetic items, chemical based
• Insecticides and their empty containers
• Light bulbs, tube lights and compact fluorescent lamps (CFL)
• Paints, oils lubricants, glues, thinners and their empty containers
• Pesticides and herbicides and their empty containers
• Styrofoam and soft foam packaging from new equipment
• Thermometers
• Mercury containing products
Kushalnagar TP shall ensure that the above practices are practised by the households and
shall provide information and education regarding method of disposing the waste.
Kushalnagar town shall also deploy men, materials and proper mechanisms to collect the
stored waste on a daily basis from all sources. Failing which will result in households littering
waste on streets.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 68
4.3.2 Commercial Establishments / Institutions
These types of generators are dispersed in the town with a high concentration in the centre
of the town. In Kushalnagar town, there are about 1,630 commercial shops/petty shops and
20Institutions in the town. They together generate waste of around 1.8 tonnes of waste per
day. It is recommended that the following processes should be practiced to effectively
manage the waste generated. The recommendations are as below:
• They shall refrain from throwing their solid waste/sweeping etc. on the footpaths,
streets and open spaces.
• They shall keep their waste on-site as and when generated in suitable containers
until the time of doorstep collection, TP shall ensure that all shops are included in
door to door collection mechanisms.
• The size of the container for bio-degradable should be adequate to hold the waste,
they normally generate in 14-18 hours with 100% spare capacity to meet
unforeseen delay in clearance or unanticipated extra loads.
• They shall keep hazardous wastes which are mentioned as hazardous for household
waste storage. Shops which sell electronic devices shall be conscious in segregating
e-waste apart from solid waste. This hazardous waste shall be disposed off as per
directions given by the local ULB.
• The association of private commercial complexes/multi-storey buildings shall
provide suitable transportable community bins which match the waste collection
and transportation system of the local body for the storage of waste by their
members and direct them to transfer their waste into the community bin before the
prescribed time on a day-to-day basis.
4.3.3 Hotels & Restaurants
There are about 119 hotels in Kushalnagar town. They generate around 535 kg of solid
waste each day. TP shall direct all hotels and restaurants with following instructions.
• They shall refrain from throwing their dry and wet solid waste/sweeping on the
footpath, streets and open spaces or drains.
• They shall also refrain from disposal off their waste into municipal street bins or
containers.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 69
• They shall store their waste on-site in sturdy container of not more than 100 litre
(0.1 m3) capacity. The container should have appropriate handle or handles on the
top or side and rim at the bottom for ease of emptying.
• In case of large hotels and restaurants where it may not be convenient to store
waste in 100 litre or smaller size containers, they may keep larger container which
match with the primary collection and transportation system that is introduced in
the town by the ULB to avoid double handling of waste.
• Hotels and restaurants may be directed to keep hazardous wastes mentioned as
hazardous for households separately as and when produced and dispose it as per
directions of the ULB.
• The hotels and restaurants shall provide the food waste to animal husbandry.
4.3.4 Vegetable Markets
There is 1 market in the Kushalnagar town located in Ward No.1, B.M road. These markets
produce large volume of solid waste. These markets produce large volume of solid waste. In
Kushalnagar town, the collected waste from the markets is around 30 kg. There would be
about 50-100 kg of waste generated in the markets if efficiently collected. To efficiently
collect and transport the waste generated from markets in the ULBs shall take the following
steps.
• Provide 1.1 m3 compactor bins in the market for storage of waste.
• Shopkeepers may be directed that they shall not dispose of waste in front of their
shops or anywhere on the streets or in open spaces and instead shall deposit their
waste as and when generated into the container provided for storage of waste in the
market.
4.3.5 Slaughter house, Meat & Fish Markets
There are about 58 meat and fish stalls including slaughter house in the Kushalnagar town.
The estimated waste that is generated by these shops is about 255 kg per day. The following
systems have to be put into place to manage the wastes from fish and meat market and
stalls.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 70
• Shopkeepers shall not throw any waste in front of their shops or on the streets or
open spaces in any conditions.
• They shall keep within their premises sturdy containers (of size not exceeding 100
litres i.e. 0.1 m3) having lid, handle on the top or the sides and rim at the bottom of
the container with adequate spare capacity to handle expected loads.
• The waste shall be collected on daily basis separately.
4.3.6 Hospitals / Clinics / Nursing Homes, etc.
Kushalnagar town has about 25 numbers of bio medical waste generators including nursing
homes and clinics. There is an existing system of waste storage, collection, transport and
processing as per the biomedical waste handling rules. Bio-medical waste generated by
Hospitals and clinics is separately collected by private agency called M/s Shree Consultants,
which has a processing facility located in Mysore, Karnataka. The collection of biomedical
waste from Kushalnagar Town will be done in weekly twice by using 4 wheeled truck with
covered body. The existing processing unit shall be made functional. The need is to ensure
all the waste generators subscribe to this facility and medical waste does not enter the
municipal waste stream. The medical establishments need to adhere to the following rules.
• They shall refrain from throwing any bio-medical waste on the streets or open
spaces, as well as into municipal dust bins or domestic waste collection sites.
• They shall also refrain from throwing any ordinary solid waste on footpaths, streets
or open spaces. The ordinary solid waste shall be stored and handed over to the
door to door collection vehicles. In larger hospitals waste would place in 1 m3
containers to be provided by the medical facility which shall be picked up by the
special vehicle carried by biomedical waste.
• They are required to store waste in colour-coded bins or bags as per the directions of
the Govt. of India, Ministry of Environment Bio-medical Waste (Management &
Handling) Rules 1998, and follow the directions of Central Pollution Control Boards
and State Pollution Control Boards from time to time for the storage of biomedical
waste.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 71
4.3.7 Construction and Demolition wastes
It is the responsibility of any generator of construction and demolition debris to employ
reasonable and practical means, including source reduction, reuse or recycling, in order to
prevent construction and demolition debris from being disposed finally in low lying areas.
The Municipality shall introduce permits system which enable obtaining permits with a
monetary deposit that allows for the tracking of C&D waste.
For any upcoming large scale construction projects, TP
shall obtain the C & D Waste Management Plan from the
owners and ensure its compliance. The small scale waste
generator has to store the waste on site and inform the TP
for disposal of the same. No person shall dispose of
construction waste or debris on the streets, public spaces,
footpaths or pavements. A tractor trailer and a PK shall be dedicated for debris collection by
TP.
Until construction debris is taken by ULB, the waste shall be
stored only within the premises of buildings or in containers
where such facility of renting out containers is available. In
exceptional cases where storage of construction waste within
the premises is not possible, such waste producers shall take
prior permission of the local authority or the State Government
as may be applicable for temporary storage of such waste and
having obtained and paid for such permission, may store such waste in such a way that it
does not hamper the traffic, the waste does not get spread on the road and does not block
surface drains or storm water drains.
The construction debris should be disposed off in low lying areas. The TP shall identify the
dedicated low lying area/ location for dumping of construction debris. The existing tractor
trailer in the TP shall use for transportation of C & D waste.
For any upcoming large scale construction projects, TP shall obtain the C & D Waste Management Plan from the owners and ensure its compliance.
Municipalities may introduce permits system which enable obtaining permits with a monetary deposit that allows for the tracking of C&D waste.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 72
4.4 SEGREGATION OF RECYCLABLES/NON-DEGRADABLE WASTE
Segregation of waste is a basic requirement for the improving solid waste management
system. There have been many efforts at segregation around the country with mixed
success. Kushalnagar town has urban population. It would take a significant effort to get
segregation into the system. The first requirement for implementing segregation is to have
separate containers for different types of waste. This has been recommended in the last
section and has to be implemented. The success of the segregation program depends on the
ability to collect segregated, transport segregated and disposal segregated waste. These
systems need to be introduced to ensure that segregation is adopted widely. A very
important requirement of segregation is to promote the concept extensively through mass
awareness.
It is proposed that, the TP shall provide one container of 10ltr capacity and one HDPE woven
sack to each household for segregation of waste. It is assumed that the 100% segregation
happens in period of five years with 10% in 1st year of implementation, 50% in 3rd year and
100% by 5th year of implementation of management.
4.5 PROPOSED COLLECTION AND TRANSPORATION STRATEGY
Based on the guidelines set out in the MSW Rules, the implementation plan for collection
and transportation system is prepared in Kushalnagar Town. The tools and equipment are
recommended for implementation of collection & transportation system. Door to door
collection systems would be through the use of auto tippers for wet waste and then
transferred to processing facility using compactor. Similarly, the dry
waste/hazardous/sanitary waste would be collected and transported to dry waste collection
centre using auto tippers. Street sweeping silt would be directly transferred to low lying
area/sanitary landfill site using tractor trailer. The proposed MSW strategy is provided in
below exhibit.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 73
Exhibit 4-3: Proposed Collection and Transportation System
Dry and
Hazardous /
Sanitary
Waste
Wet Waste Wet Waste Dry and
Hazardous /
Sanitary
Waste
Auto tipper
Wet waste-
Compost Facility
Dry waste-Dry Waste
Collection Center
Markets
Deep
Burial Pit
Hotels, Marriage
Halls, Institutions,
Worship etc,
Commercial
Establishment Slum Non- Slum
Auto
Tipper
Meat, Chicken
& slaughter
house
Compactor for wet
waste
Low lying
areas
Tractor
Trailer
Street
Sweeping
Construction
Debris
Pushcarts
Slit/ sand
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 74
4.6 PRIMARY COLLECTION OF WASTE
It is proposed to have a segregated waste collection from source to disposal at Kushalnagar
town. The approach to this is based on the door to door collection approach for individual
generators and based on bin/container collection for community locations. The plan waste
generator wise is present in this section.
4.6.1 Modus Operandi
This modus operandi for primary waste collection by each waste generator and for the
different players in the process is presented below. The overall approach for primary
collection is centred on door to door collection.
4.6.1.1 Doorstep collection through containerized handcarts & motorized vehicles
Primary collection of MSW from non-slum areas
Door-to-door collection would be the primary mode of collection from domestic
households. Auto tippers are proposed to be deployed for primary collection of MSW. The
primary collection activity would commence at 7 am and is proposed to be completed by 11
am.
Wet (biodegradable) and dry (non-biodegradable) waste from households would be
collected daily. The wet and dry waste collected in auto tippers and the wet waste would be
transported to the compost facility through compactor and the dry waste would be
transported directly to the dry waste collection centre.
Sanitary and Hazardous waste generated in the households comprise dry cells, medicines,
tubes, paints, pesticide bottles/ cans, shoe polish, etc. The households would be required to
segregate and store the hazardous and sanitary waste separately in 10 lit bin/container. The
same shall be collected by the primary collection crew.
The hazardous waste and sanitary waste collected would not be mixed. The hazardous and
sanitary waste so collected would be taken to dry waste collection centre. Further
segregation of the hazardous and sanitary waste would be carried out to separate the
recyclables and sanitary waste. The recyclable wastes such as batteries, plastic bottles, cans,
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 75
etc, would be separated and the balance waste would be send to hazardous waste handling
facility.
Primary collection of MSW from slum areas
Auto tippers are proposed to be deployed for collection of MSW from these areas. The wet
and dry waste would be collected by the auto tipper daily by the primary collection crew.
4.6.2 Use of small vehicles for direct collection of waste from congested areas
4.6.2.1 Markets
In markets, wet and dry waste would be collected by auto tipper and then transported to
the compost facility through compactor and dry waste collection centre respectively. PKs
would sweep and collect the waste in smaller markets and store it in secondary containers.
4.6.2.2 Hotels and Restaurants
Bulk generators would need to compulsorily use waste bins/containers to store their wet
and dry waste separately, which would later be collected by the auto tipper and later wet
waste would be transferred to compactor. The wet waste collected would be transported to
processing facility through compactor. The dry waste collected would be transported to dry
waste collection centre through auto tipper.
4.6.2.3 Commercial Establishments
Shops and commercial establishments would need to compulsorily use waste bins to store
their wet and dry waste separately. The waste from these bins would be picked up by Pks.
The wet waste collected would be transferred from auto tipper and transported to the
processing facility using compactors. The dry waste collected would be transported to the
dry waste collection centre using auto tipper. The shop owners associations would be made
responsible for advocating the disposal of waste only into waste bins.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 76
4.6.2.4 Meat/Chicken/Slaughter House Waste
Meat/chicken/slaughter waste would be collected separately and then transported to deep
burial facility through wet/dry waste collection auto tipper as separate trip after 11 am.
4.6.2.5 Other Sources
The current collection system adopted by Kushalnagar would be streamlined for other
generators (large institutions, construction waste, hospitals, marriage halls etc). The
biodegradable, recyclable and domestic hazardous wastes from these premises would be
collected in separate trips on daily basis. In case there is a large waste generation, special
trips of the tractor trailer or provision of container and picked up by the compactor can be
arranged.
4.6.3 Requirement of manpower, requirement of vehicles
There is existing door to door mechanism in few wards of the town. It is proposed that the
door to door collection be extended to all the 13 wards. It is proposed auto tippers be used
for door to door collection. The waste to be handled at present is 10.7 tons per day. In a five
year period which is the normal life time of a primary collection vehicle systems the waste
generation is estimated to increase to 14.4 tons. As the waste segregation process lead to
improved local recycling the waste to be collected and transported would come down and
the system is design for the 2016 year waste generation level of 12.3 tons. Over 95 -100%
collection efficiency is targeted for the collection.
The estimate of vehicle requirement for door to door collection is
calculated based on normative standards for Municipal Solid
waste Management set by Directorate of Municipal
Administration of Karnataka. Auto tippers are proposed to be
deployed for collection of wet, dry waste and meat shop/chicken shop/slaughter house
waste from households, slums, commercial establishments and meat shop/chicken
shop/slaughter house. The requirements of auto tippers have been estimated assuming
100% coverage. The requirement of auto tippers are presented in below exhibit.
Auto tippers are proposed for D2D collection
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 77
Exhibit 4-4: Requirement of Primary Collection Vehicles
Particulars Unit Quantity
Waste generation of TP (Designed year for 2017) TPD 13
Quantity of street sweeping waste TPD 0.9
Quantity of Meat/Chicken/Slaughter house waste TPD 0.4
Quantity of waste excluding sweeping/debris waste TPD 11.0
Capacity of existing Auto tippers tonnes 0.6
No of trips of Auto tippers trips/day 3
No of trips of Auto tippers for Meat/Chicken/Slaughter house waste
trips/day 1
Coverage of Auto Tipper % 100%
No of Auto tipper required Nos. 7
Existing 1m3 Auto tippers Nos. 5
No of 1m3 Auto tipper to be procured Nos. 1
At present there are 5auto tippers used for door to door collection. It is assessed that 100%
of waste would need to be covered using auto tippers for collection of wet,
dry/hazardous/sanitary waste and meat/chicken/slaughter house waste. There is an existing
auto tipper shall be used for collection of waste at door to door level. It is proposed that 1
auto tippers are recommended to be purchased. All the auto tippers should be provided
sound box with mic and printed on the purpose of the auto tipper including the wards which
it should cover. 100% of meat/chicken/slaughter house waste would need to be covered
using wet/dry waste collection auto tipper as separate trip after 11 am. Hence, 1 number of
auto tripper is proposed for procurement. A very important requirement for Kushalnagar
town is to close all open points and to ensure that waste is not disposed in the open points.
The manpower requirement for implementation of the proposed primary collection system
is set out in the exhibit below.
Exhibit 4-5: Manpower Requirement for Primary Collection Activities
S. No. Component Proposed Driver &
PKs
Existing Driver &
PKs
Manpower
Requirement
1 Auto tipper PKs - 7 Nos.;
Drivers - 7 Nos.
PKs – 33 Nos.;
Drivers - 8 Nos.
Pks -Available;
Drivers – Available.
Total Pks 7
Drivers 7
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 78
Under the strategy, one driver &one PK are required for auto tipper. There are 36 number
of PKs and 7drivers available which includes both permanent and contract workers for SWM
activities.
4.7 STREET SWEEPING
The sweeping of street and public spaces is being done by the Kushalnagar town and it is
proposed that the existing systems continue, covering all extensions and roads. Most the
PKs would carry out the street sweeping activity and would be responsible for sweeping of
the roads, cleaning of the adjoining drains and would transfer the same to tractor trailers.
For continues collection of street sweepings, tractors trailers would be going rounds and
collecting the street sweepings from identified locations where the street sweepings would
be stored/collected in a pushcarts by the PKs. The silt, debris collected in the tractor trailer
will disposed-off in the low lying areas.
4.7.1 Street Sweeping Frequency
The streets in Kushalnagar town have been identified and classified in A, B, C and Dcategory.
Type A category roads are busy road considered for daily sweeping. About 6 km of road
length is classified as roads requiring daily sweeping. Type B category roads which are about
10 km require sweeping twice in a week. Type C category roads which are about 12 km
required sweeping once in week and Type D category roads which are about 20 km required
sweeping once in 15 days. This has been done based on the usage of the road and
scientifically done.
4.7.2 Vehicles, tools and equipment to be used for sweeping
Most of the tools used for sweeping are inefficient and out-dated and need to be replaced
by efficient tools and equipment. There is a standard specification of tools to be used by
sweepers in Karnataka. Long handled broom, metal tray and plate and basket for loading of
wastes. There are standard and routine requirements and need to be provided. As these
activities are part of the day to day operations no extra budget for the same has been
provided.
Exhibit 4-6: Tools for Street Cleaning Activities
S. Safety Safety against Specifications Picture
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 79
No. equipment
1 Face mask Protect against
dust/ infection
Standard surgical
mask
2 Full arm
Uniform
Protection
against dust
Factory wear
uniforms with TP
name
3 Safety shoes Minor wounds
while sweeping
PVC make, water
proof shoes
4 Hand gloves Protection
against infection
Standard toilet
cleaning gloves
5 Eye glasses Protection
against dust
Transparent
factory wear
6 Head cover Protection
against dust Helmet
Source: Field experience of Tide Technocrats.
The street sweepings collected would be transported in existing tractor trailer to low lying
areas.
4.7.3 Requirement of manpower
The requirement of PKs for street sweeping has been estimated based on the road
classification. The estimated manpower requirement for the same is 17 numbers including
drivers. The street sweepings (waste) would be collected in pushcarts and one pushcart
would be deployed for two PKs. The estimate of manpower and vehicle requirement for
street sweeping is calculated based on normative standards for Municipal Solid Waste
Management set by Directorate of Municipal Administration of Karnataka.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 80
Exhibit 4-7: Total Number of PKs and Vehicles required for Street Sweeping
Particulars Unit Quantit
y
Normative Standards for MSWM, DMA, Karnataka
1 no. of sweeper 1000 m of road length
2 sweeper 1 pushcart
Length of the Type A road 6 kms
Length of the Type B road 10 kms
Length of the Type C road 12 kms
Length of the Type D road 20 kms
No of sweepers required per type A road 6 Nos.
No of sweepers required per type B road 3 Nos.
No of sweepers required per type C road 2 Nos.
No of sweepers required per type D road 2 Nos.
No of sweeper required 13 Nos.
No of pushcarts required 8 Nos.
No of existing pushcarts 0 Nos.
No of Pushcarts to be procured for street sweeping 8 Nos.
Waste handled per tractor per day 3000 kg
Waste generation in street sweeping activities 720 kgs
No of Tractor Trailers required for street sweeping 1 Nos.
No of Tractor Trailers required for standby (C&D waste) 1 Nos.
No of loaders for tractors 2 Nos.
Total No. of Tractor Trailer required 2 Nos.
No of existing Tractor Trailer 3 Nos.
No of Tractor Trailer to be procured for street sweeping Nil (available) Nos.
No of drivers required 2 Nos.
No. of Drivers to be hired for street sweeping and C&D
collection 2 Nos.
Source: TTPL Estimation
There are existing 3 numbers of tractor trailers; Out of 3, 2 trailers are 7 years old and one
tractor trailers is 5 years old. All tractor trailers are in good condition of which one tractor
shall be deployed for street sweeping activities, one tractor shall be deployed for C&D waste
and remaining one shall be deployed at processing facility for material transfer. The services
of the existing PKs of total 24 members (out of 36 Pks, 8 members are allotted for primary
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 81
collection activities) shall be used for the street sweeping activity. Hence, no Pks/sweepers
are required for street sweeping activities. For tractor trailer, two drivers are proposed to
employ for street waste carrying vehicles.
4.7.4 Norms of work
The norms for street workers is that an average of 1 km road per person to be covered per
day. This is as per the norms prescribed by the state government based on the norms for
different kinds of road on which is being done. This found to be adequate.
4.7.5 Improvement and recommendations on street sweeping and drain cleaning
There is open dumping of MSW on the streets of Kushalnagar
town wherein the street sweeping system has become the
primary collection. This needs to be avoided by improving door
to door collection systems and by providing intensive
information and education.
The other major issue to be addressed is in providing appropriate tools and monitoring the
health issues of sweepers. They should be provided with metal plates, gamellas, brooms,
pushcarts, and uniform as appropriate. There should also be provision of masks and gloves
to safeguard health of street sweepers.
4.8 TEMPORARY WASTE STORAGE DEPOTS FOR ONWARD TRANSPORTATION OF WASTE
The primary collection vehicles viz., auto tippers shall transfer the wet waste to compactors
and dry waste to dry waste collection centre directly. Tractor trailers shall be used for
transportation of street sweeping waste and construction debris.
4.9 TRANSPORTATION OF WASTE
4.9.1 Transportation of Municipal Solid Waste
The wet waste collected by auto tipper would be transferred to compactor directly which
would be transported to the processing facility located Buvanagiri and the inert from the
treatment facility would be disposed into the sanitary landfill. The dry waste collected
would be directly transported through auto tipper to dry waste collection centre.
TP shall provide metal plates, gamellas, brooms, pushcarts, and uniform to all sweepers/Pks
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 82
The silt from street sweeping activity would be transferred to the low lying area/sanitary
landfill facility by way of tractor trailers. The tractor trailers in use at present would be
restricted to use for street sweeping activities and not be used for transport of municipal
wastes. The requirement of the transport vehicles is estimated in the below exhibits.
Exhibit 4-8: Estimation of Secondary Transportation Vehicles
Particulars Unit Denotation Quantity
Waste generation of TP (Designed year for 2016) TPD Q1 12.3
Quantity of street sweeping waste TPD Q2 0.9
Quantity of Meat/Chicken/Slaughter house
waste TPD Q3 0.4
Quantity of waste excluding sweeping/debris
waste TPD Q4=Q1-Q2-Q3 11.0
Percentage of wet waste % P 70%
Quantity of wet waste TPD Qw = Q4*P 7.7
Capacity per 7 m3 Compactor for wet waste tonnes C 4.2
No. of trips of 7 m3 Compactor per day for wet
waste trips/day N 2
Coverage of Compactor per day for wet waste % L 100%
Collection of wet waste (daily) days B 1
No. of Compactor required for wet waste Nos. W1=
(Qw*L)/(C*N) 1
Existing Compactors Nos. W2 0
No. of Compactor to be procured for wet waste Nos. Wc=W1-W2 1
No. of helpers/Pks required Nos. 1
Total No. of helpers/Pks to be hired for
Secondary C&T Nos. 1
No. of drivers required Nos. 1
No. of Drivers to be hired for Secondary C&T
with 10% extra Nos. 2
Source: TTPL Estimation
It is proposed for procurement of one 7 m3 compactor for wet waste. It is also proposed
that 2 drivers and 2 pks are required for Secondary collection and transportation system.
4.9.2 Transportation of Biomedical waste from hospitals/clinic/nursing homes
There is an existing system operated privately for biomedical waste in Kushalnagar town and
the same may be continued. Bio-medical waste generated by Hospitals and clinics is
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 83
separately collected and transported by private agency called M/s Shree Consultants, which
has a processing facility located adjacent to Mysore, Karnataka. The collection of biomedical
waste from Kushalnagar town will be done in weekly twice by using 4 wheeled truck with
covered body.TP should ensure that all the bio medical waste generating units come under
this mechanism.
All bio-medical waste generated in the hospitals which is hazardous shall be handled
separately as per the Bio Medical Waste (Management & Handling) Rules, 1998. TP shall
ensure that all the bio-medical waste generators make use of the present system of
handling the waste by Shree Consultants, also the waste managed effectively by Shree
Consultants.
4.9.3 Transportation of Construction and demolition waste
Construction debris generally generated at the project level. Over 90% of construction
waste are inert and are known as public fill. Public fill (low lying areas) includes debris,
rubble, earth and concrete which is suitable for land reclamation and site formation. When
properly sorted, materials such as concrete and asphalt can be recycled for use in
construction.
Part of the debris can also be used as daily cover in the landfill site thus covering the day’s
waste, and with effect of reducing nuisance, odour and exploitation by animals, birds and
insects.
Transport of construction waste and debris shall be done using existing tractor trailer. No
additional requirements are proposed. One tractor shall be dedicated only for
transportation of Construction debris. The construction debris shall be disposed off in the
low lying areas identified by TP.
4.9.4 Workshop facility for vehicle maintenance
The Kushalnagar TP does not have a workshop facility for existing vehicle maintenance. It is
proposed that Kushalnagar TP shall procure 1 auto tipper for primary transportation of
waste, 1 compactor for secondary transportation of waste and one loader for processing
facility. It is expected to maintain the 6 auto tippers, 1 compactor, 3 tractor trailers and 1
loader including existing vehicles. Setting up and maintenance of workshops for these
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 84
vehicles would not be economical, considering that, workshop requires permanent skilled
labor, tool sets and necessary equipments, which TP may not be able bear. Considering the
number of vehicles to be maintained it is recommended that the existing system of using
external maintenance facilities be continued.
4.9.5 Routing of waste and trip requirement
There is an existing routing of vehicles in operation. With addition of new vehicles, routing
for the same needs to be considered along with proposed bins. As part of the exercise the
routing shall be done as part of the micro level survey.
It is proposed to introduce a GPS based monitoring systems for the door to door collection
and transport vehicles.
4.9.6 Deployment plan for existing vehicles, staff and additional requirements
The existing 3tractor trailers in use at present would be continued to use for street
sweeping, C&D waste collection and material transfer at processing facility and not be used
for transport of municipal wastes. It is proposed to use the services of available contract
workers (existing 25 sanitary workers and 8 drivers) for primary collection and street
sweeping activities.
4.9.7 Total requirement of tools/equipment/vehicles
The total requirement of tools / equipment / vehicles for implementation of proposed MSW
management strategy is provided in below exhibit.
Exhibit 4-9: Requirement of Vehicles
S.No. Component Proposed Existing Required
A Source Segregation
1 Containers (10 lits) for households 8310 0 8310
2 HDPE woven sacks for households 4155 0 4155
B Primary Collection and Transportation
1 1m3 auto tipper 7 5 2
D Street Sweeping
1 Pushcart 8 0 8
2 Tractor Trailer 2 2 0
E Secondary Transportation
1 Compactor 1 0 1
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 85
F Processing Facility
1 Tractor Trailer 1 1 0
2 Loader 1 0 1
4.9.8 Manpower requirement for implementation of MSW strategy
The manpower requirement for implantation of the proposed MSW management strategy is
provided in below exhibit.
Exhibit 4-10: Requirement of Manpower for Collection and Transportation
S. No. Component Proposed Existing Required
A Primary Collection and Transportation
1 Pks 7
Pks – 36 Nos.
Drivers – 8 Nos.
7
2 Drivers 7 7
B Street Sweeping and C&D collection
1 Pks 13 14
2 Loaders 6 6
2 Drivers 2 2
C Secondary Transportation
1 Pks 1 1
2 Drivers 1 1
D Dry Waste Collection Centre
1 Pks 2 2
E Processing Facility
1 Pks 6 6
2 Drivers 2 2
3 Plant Operator (electrical) 1 1
5 Security guard cum weigh bridge
operator 1 1
Total (for Pks) 35 36 Nil
Total (for drivers) 12 8 4
Total (for Operator) 1 0 1
Total (for Security) 1 0 1
4.10 DRY WASTE COLLECTION CENTRES/ZERO WASTE MANAGEMENT CENTRE
Dry waste collection centers/ Zero waste management centre are the decentralized units
dedicated for collection of in organic/ dry waste in the urban cities. It is proposed to
construct in the identified CA sites recommended by Kushalnagar Town Panchayath. The dry
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 86
waste consists of the recoverable like plastic material, papers, cloth pieces, metal pieces,
glass pieces etc.
The functioning of the dry waste collection centers are related to the efficiency in door to
door collection. At present all these waste are mixed with the municipal waste and are
disposed in the land fill site. The above shown wastes are dry in nature and do not support
microbial digestion and could be stored for a longer period of time. These wastes don’t stink
and are reusable.
All these waste materials have value when segregated and sold to the scrap dealers. There is
an existing chain of scrap dealers who buy these of wastes from rag pickers and sell it to the
recycling industry. The average present market rate of these waste material are presented
below.
Exhibit 4-11: Handling of Dry/Inorganic Waste in Dry Waste Collection Centre
Metal pieces E waste Polythene
Wire pieces Glass bottles Rubber waste
Plastics Paper Footwear waste
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 87
Exhibit 4-12: Approximate market rate of Recoverable from waste
S. No. Dry waste type Present Market Rate Consumers
1 Metal pieces Rs.25-30 per kg Metal fabrication waste buyers
2 Plastic material Rs.15-20 per kg Plastic scrap buyers
3 Pet bottles Rs.25-30 per kg Scrap buyers
4 Polythene bags Rs.1-2 per kg Scrap buyers
5 Used papers Rs.5-6 per kg Scrap buyers
6 Electric wires Rs.8-10 per kg Scrap buyers
7 Glass bottles Rs. 1-2 per unit Bottling units
8 Rubber waste Rs. 10-15 per kg Scrap buyers
9 Footwear waste Rs.5-8 per kg Scrap buyers
10 Used milk/oil Bag Rs.5-8 per kg Scrap buyers
Source: Study conducted by TTPL
The TP may operate the dry waste collection centre by itself in association with scrap
dealers and can generate revenue by conducting this operation or may outsource to private
operators. The unit rate possible to be generated is provided in the above table. Rag pickers
shall be encouraged for the collection of recyclables who in turn will be generating the
revenue by the activity. The Kushalnagar TP C shall encourage such operations so that they
are sustainable.
The proposed efficient MSW collection and transport plan insists on conducting segregated
waste collection at door steps. The waste generators would store the dry waste and
organic/ wet waste in separate containers. The door to door collection in each ward has
been outsourced to private parties. The door to door collection staff would collect the
organic waste every day at the door steps. The dry waste would be collected once in 3 days.
It is proposed that the TP shall be involved in collection of dry waste as well. The waste
could be sold to recycling industry or processing facilities. As per the study conducted by
TTPL it is assessed that about at least 30% of the total waste generated in the town could be
sold to recycling units. It is estimated that on an average 4 TPD of such dry waste which
could be sold in the market is generated in the town for operating dry waste collection
centres.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 88
Exhibit 4-13: Dry Waste Collection Centre Model
The proposed system insists on that TP shall establish and
operate a single dry waste collection centres in Kushalnagar
town. Kiosks shall be set up in the centre for collection of
different types of recyclables. The facility would require
10mx10m area for setting up collection centre. This centres shall
be spread across the town for easy access to the generators. TP
shall identify the locations for setting up of waste collection centre.
The proposed dry waste collection centres would be set up and operated by TP. The dry
waste consists of recoverable like plastic materials, paper, metals, etc. which could generate
revenue to TP. TP shall encourage rag pickers for collection of the recyclables who in turn
will be generating revenue. It is proposed to provide 3 PKs at Dry waste collection centre.
The list of manpower requirement is provided in exhibit 4-12.
The dry waste collection centres would function as a social enterprise. The collection
centres would buy the recoverable from the waste generators and sell it to the whole sale
scrap dealers. The additional monetary benefits would be used for O&M of the facility.
Proposed for setting up of a Dry Waste Collection Centre and operated in the town for recyclables by TP.
Household
Commercial/
Establishments/
Institutions
Dry waste collection centre
Sale Rejects
Landfill
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 89
4.11 PROCESSING & DISPOSAL OPTIONS AVAILABLE TO ULBS
4.11.1 Site profile
The integrated waste management facility at Kushalnagar town is proposed to be set up at
present dumping ground located at Buvanagiri. The land available at this disposal site is
about 7 acres 15 guntas. The site is now being used as dumping ground with haphazard
dumping of wastes. There are existing pits on site that have been used for trenching type
operations. The site has been covered by walls partially and has a double entry with an
existing security building. The detailed survey of topographical survey of the landfill site is
given in Annexure 4.
4.11.2 Concept of IWMF
A state of the art waste management facility is proposed. The Kushalnagar town has
adequate available land with no major local concerns at this point of time. Since the site is
located outskirt of the town and no public objection, the site is suitable for landfill
development and waste processing. It is proposed to have a facility meeting the standards
as described below.
• The facility should meet and exceed all the environmental standards set by the CPCB.
• The facility should have no materials leaving it except as usable product.
• The facility should not have any offensive visual, sound or odour. The project would
be capable of coexisting with public facilities adjacent to it.
• The facility should maximize the recycling of the waste and limit the landfill quantity
to less than 15 % of waste receipt.
4.11.3 Technology Options
There are several MSW processing technology options, which are being followed in various
parts of the world. These technologies fall in the broad categorization of thermal processing,
biological processing and physical processing. Table below gives details the various
technology options in the above mentioned categories. These have been discussed in
subsequent section in context of technology options for Kushalnagar town.
Exhibit 4-14: Technological Options for MSW processing in different categories
Waste Processing Technology Group Waste Processing Technology
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 90
Thermal Processing Technologies
Incineration (Mass burn)
Pyrolysis
Pyrolysis / Gasification
Plasma Arc Gasification
Biological Processing Technologies
Aerobic Digestion (Composting)
Anaerobic Digestion (Bio-methanation)
Landfill as Bioreactor (Bioreactor Landfill)
Physical Processing Technologies
Refuse-Derived Fuel (RDF)
Densification / Pelletisation
Mechanical separation
Size reduction
4.11.4 Thermal Processing Technologies
Thermal technologies are those technologies that operate at temperature more than 200°C
and have higher reaction rates. They typically operate in a temperature range of 375°C to
5,500°C. Thermal technologies include advanced thermal recycling (a state-of-the-art form
of waste-to-energy facilities) and thermal conversion (a process that converts the organic
carbon based portion of the MSW waste stream into a synthetic gas which is subsequently
used to produce products such as electricity, chemicals, or green fuels). This technology
group includes incineration, pyrolysis, gasification and plasma arc technology.
4.11.5 Biological Processing Technologies
Biological technologies operate at lower temperatures and lower reaction rates. Biological
processing technologies are focused on the conversion of organics in the MSW. MSW
consists of dry matter and moisture. The dry matter further consists of organics and
minerals. The organics are biodegradable. Biological technologies can only convert
biodegradables component of the MSW. By products can vary, which include: electricity,
compost and chemicals. This technology group includes Composting, Anaerobic Digestion,
and Bioreactor Landfill.
4.11.6 Physical Processing Technologies
Physical technologies involve altering the physical characteristics of the MSW feedstock. The
MSW is subjected to various physical processes that remove various components from the
materials, reduce the size and increase its heating value. It may be densified or pelletized
into homogeneous fuel pellets and transported and combusted as a supplementary fuel in
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 91
utility boilers. This technology group includes Refused Derived Fuel, Mechanical separation
and Size reduction.
4.11.7 Technology Selection
The moisture content in Indian waste is high due to the high food and other organic content
in waste. In Kushalnagar town if the silt wastes are removed from the waste stream the
organic matter is about 45-55 %. Such high moisture contents lead to low calorific value on
as received basis. Thermal processing is difficult and would require energy addition. Further
as mixed wastes are received there is always a threat of combusting plastics which can lead
to dioxins and furans release. It is recommended that no thermal processing technologies be
adopted in Kushalnagar town.
Compost, vermin-compost and bio-methanation plants are working successfully in many
places in India. These technologies recover the organic matter and make them into compost
which is a good soil conditioner and useful for soil management. Bio-methanation has many
useful by-products like biogas, compost and potential use of the liquid as pest repellent etc.
From the agrarian environment of Kushalnagar town the adoption of organic recovery
solutions like composting and vermi-compost are the preferred options. We do not
recommend bio-methanation at present as segregation is a primary requirement for
successful operation of bio-methanation plants and this is not yet in practise. In view of
existing available infrastructure in the Kushalnagar town, existing vermin compost shed has
4 pits of size 4.6mx3.6mx1m which can hold only about 0.19 tons waste per day for 30 days
vermin compost process. While windrow composting technology, it can process fresh waste
generated in the town as well as existing waste available in dumpsite. Hence, we are
recommending the aerobic windrow composting technology. The physical processing
technologies are useful to recover some of the non-organic matter and should be integrated
into the main technology solution linked to organic waste recovery through composting. The
existing vermin compost can also be used at time to time.
Based on the above analysis it is recommended to have aerobic windrow composting based
waste management facility. This would be supported by the recycling of plastics and other in
organics. This technology proposed is simple and easy to implement with potential to meet
the overall objectives of waste management elucidated above. This is cost effective.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 92
4.12 AEROBIC PROCESS – WINDROW COMPOSTING TECHNOLOGY
The Integrated waste management facility has been designed for a capacity of 14 tons per
day for five year period for Kushalnagar Town and Kudumangalore village and also in
consideration of direct waste disposal of Kudige village at processing facility. The capacity
can be enhanced over time. As presented in the previous section the integrated facility will
contain Segregation unit, Windrow compost pad, Plastic and other recycling and Landfill.
The systems have been designed to maximize the potential revenue generation. This facility
reduces the rejects to be landfill to about 15% of the incoming wastes. The integrated
facility will have the components as listed out in the below exhibit.
Exhibit 4-15: Technological Options for MSW Processing in Different Categories
Particulars Unit Quantity
Design Year (Five years period) Year 2022
Projected waste for Kushalnagar and Kudumangalore TPD 14.4
Projected waste for Kudige (direct disposal at processing facility) TPD 2.5
Total Waste TPD 16.9
25% of dry waste considered as direct transport to DWC TPD 4.2
15% of Sweeping waste considered as direct transport to low lying area
TPD 2.5
Plant Design Capacity TPD 10.1
Processing Facility
Windrow Composting TPD 10.1
Material Recovery Facility
Refuse Derived Fuel Plant TPD 3.8
4.12.1 Process flow and Material Balance
The integrated waste management facility would consist of a waste receipt and segregation
facility, windrow composting, plastic recycling, RDF and landfill. The material flow for the
integrated waste management facility for Kushalnagar town is given exhibit 4-18.
4.12.2 Layout
The integrated facilities have been planned at waste site spread over an area of 7 acres 15
guntas. Detailed layout plan and other drawing of the waste processing and disposal facility
is given in annexure 4. The overall concept is to create and retain a green character of the
site.It proposed to place the Waste Processing facilities towards the southern side of land.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 93
The existing vermin composting shed is available in southern side of the disposal site. It is
proposed that waste segregation, composting, recycling and storage for compostable and
recyclables shall be provided. A parking area for vehicles, composting facility and leachate
treatment plant are provided. A road network around the site is provided. The security
building and admin building are available. Toilet facilities would also be provided. A green
fence around the site is proposed for a 5 m width.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 94
Exhibit 4-16: Material Balance of Processing Facility
Weighment of MSW at site
(10.1 TPD)
Semi-automated Sorting
(2.5+2.3 TPD)
6.6 TPD
3.1 TPD
3.5 TPD for 35 days Aerobic Compost
(40% moisture loss)
11.7 TPD
2.3 TPD
16.9 TPD
Dry Waste Collection Centre
( 4.2 TPD)
Designated C&D disposal
area (2.5 TPD)
4 mm sieving machine
4 mm sieving machine
Compost
2.4 TPDCompost 2.4 TPD
35 &16 mm Dual sieving machine 35 &16 mm Dual sieving machine
1.2 TPD
Recyclables (1.7 TPD)
Reused as culture (0.7
TPD)
SLF (1.0 + 1.2) TPD
1.0 TPD
RDF (3.8 TPD)
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 95
4.12.3 Components of IWMF and its capacities
The common facilities for the Integrated Waste Management includes roads at site,
entrance gate, weighbridge, security and office building, The details of the common facilities
proposed are given in below exhibit.
Exhibit 4-17: List of Proposed Facilities at Site
S.No. List of Facilities Size Unit
1
Shed for Processing Facility 50mx40m Sq.m
Waste Receipt Area 10mx10m Sq.m
Windrow Area 33mx17m Sq.m
Machinery Area - Preparatory line 1 (35 mm) 4mx22m Sq.m
Machinery Area - Preparatory line 2 (16mm) 4mx22m Sq.m
Machinery Area - Finishing line (4mm) 4mx22m Sq.m
Recycling Facility 10mX8m Sq.m
Storage of Recyclables 10mX8m Sq.m
Storage of Compostable 6mX6m Sq.m
2 Weigh bridge room cum Office building with toilet 3mX3m and
1.4mx1.5m Sq.m
3 Weigh bridge platform 9mX3m Sq.m
4 Toilet Block - 2 Seater 2mX3m Sq.m
5 Septic Tank 2.5mX1.5mx2m Cu.m
6 Rain water harvesting 5m diax4.5m (depth) Cu.m
7 SLF and Leachate collection tank (3.5m dia and 2m
height) 40mx34m Sq.m
8 Leachate Treatment -PGF 15mX15m Sq.m
9 Leachate Collection Tank for Windrow platform 1.5mx2mx1m Cu.m
10 Deep Waste Burial facility - 6 Nos. 1.5mx5mx1.5m Cu.m
11 Internal Road - 5m wide 516 Rm
12 Drain 426 Rm
13 Crop Demonstration 4683 Sq.m
14 Social Forestry 10371 Sq.m
15 Compound wall for remaining area 70 Rm
Exhibit 4-18: List of Proposed Machineries, Tools and Equipment at Processing Facility and Dry waste collection centre
S.No. List of Equipments, Tools & Machinery Size Unit
A. Processing Machinery
1 Preparatory Machinery Line 1 - 35mm
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 96
Hopper 1 No.
Belt conveyor 1mx5m Sqm
Feeding conveyor 0.8mx6m Sqm
Trommel 1.5mx4m Sqm
Under conveyor 0.8mx6m Sqm
Reject conveyor 0.8mx5m Sqm
2 Preparatory Machinery Line 2 - 16mm
Feeding conveyor 0.8mx6m Sqm
Trommel 1mx4.5m Sqm
Under conveyor 0.8mx6m Sqm
Accept conveyor 0.8mx5m Sqm
Reject conveyor 0.8mx5m Sqm
3 Finishing Machinery - 4mm
Hopper 1 No.
Belt conveyor 1mx5m Sqm
Feeding conveyor 0.8mx6m Sqm
Trommel 1mx4m Sqm
Under conveyor 0.8mx6m Sqm
Reject conveyor 0.8mx5m Sqm
4 Tools - Bagging tools, weighing machine, hand
sieving screen and basket 1 Set
B. Recycling Facility
1 Belt conveyor 1.2mx5m Sqm
2 Bailing Unit 1 No.
3 Storage Bins (1.1m3) 5 Nos.
C. Others Facilities
1 Furniture and Fixtures 2 Set
2 Security LED Light Magnet Wand Baton 3 Nos.
3 Computer appliance 2 Set
4 CCTV camera 5 Nos.
5 Fire extinguisher 7 Nos.
6 Biometric system 2 Nos.
7 GPS for all vehicles 10 Nos.
8 Walkie Talkie 5 Nos.
9 Soundbox, Mic and Advertising board for auto
tippers 7 Nos.
10 Electronic LED screen and Projector 1 set
11 Weighing machine for dry waste collection centre 1 No.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 97
(digital computing bench scale)
12 DG set (62.5 KVA) 1 No.
13 Transformer (50 KVA) 1 No.
Exhibit 4-19: Details of Common Facilities Proposed at Site
S. No. Component Details
1 Boundary Wall Partial compound Wall exists at the site. Remaining 70 m
compound wall shall be provided
2 Internal Roads It is proposed to provide 5 m wide concrete road of 213m
length and 5 m wide mud road of 303 m length at site.
3 Entrance gate Two gates are available at the entry of the facility one for
vehicle entry.
4 Weighbridge
It is proposed to have 30 tons weighbridge of
electromechanical type with 3 m x 9m loading platform at
the entry of the waste management facility. The weigh
bridge system would have a vehicle monitoring and staff
time monitoring system.
5 Security building Existing facility is retained.
6
Office building, Weigh
bridge room and
toilet block
It is proposed to provide 3mx3m size of office building cum
weighbridge room and 2-seater toilet block is also
proposed.
7 Water facilities Borewell 1 nos. is available. It is recommended that water
supply line shall be provided
8 Power facilities Transformer is proposed at processing site. It is
recommended that separate KEB line shall be provided
9 Waste water
treatment plant
The leachate generation is expected from the landfill
during the monsoon. No leachate from the treatment
facilities as expected as all of them are completely covered
and generated leachate would be reused internally. The
leachate generation may happen for about 60-90 days as
the rainfall days are limited in Kushalnagar. The facility
design has been selected to enable simple operation.
10 General Services
The general services include the lighting of the facility for
minimum 20 lux. No night operations are proposed and
hence limited lighting is adequate. Firefighting tools and
services are proposed including preparation of a fire
fighting requirement assessment and plan preparation.
11 Rainwater harvesting
It is proposed to have rainwater harvesting on all buildings
and harvesting of water from all open areas by directing to
the water different percolation pits around the site.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 98
4.12.4 Detailed design
The civil estimates have been done based on the Mangalore circle SR 2016. The SBC analysis
should be considered during construction of civil work in the SWM site. The detailed
drawings of the processing and disposal facilities have been provided in annexure 4. The
design details are provided for each of the facility below.
4.12.5.1 Waste Segregation Facility
The waste arriving at the integrated waste management facility is weighed at the gate and
data recorded. The vehicles arriving are smart segregated. The balance of the materials are
taken to the segregation facility and tipped. The segregation facility is an enclosed structure.
At the tipping floor the large contraries are removed and transferred to waste a receiving
hopper. The waste is taken through a conveyor to 2 m diameter rotary sieve of with 100 mm
holes. The materials passing are taken for aerobic composting and the oversize materials are
taken for recycling or landfill.
4.12.5.2 Aerobic composting facility
Aerobic Composting is used for stabilizing organic matter. Composting can be used for
mixed wastes and results in production of stable product- compost which depending upon
its quality can be used as soil conditioner or potting medium. In this section the detailed
design and technical specifications of the compost facility are discussed.
A. Aerobic Waste decomposition processes: an overview
Aerobic composting involves the stabilization of the organics into compost by
microorganisms, which require the oxygen in air for their survival and growth. During this
process of conversion heat is released. There are ideal limits fo\r different parameters
within which these microorganisms survive. Adequate moisture is required for the
microorganisms to survive and composting to take place. If these conditions are ensured to
be stable the compost quality and time of composting process can be controlled. In batch
conditions the composting process continues at progressively reducing rate as the oxygen
becomes a limiting factor or organics get consumed. To ensure the survival of these
organisms the availability of oxygen in the waste being composted has to be ensured
through provision of air. For economic reasons the time of composting is restricted till the
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 99
major conversion is done and subsequently compost maturing is taken up till the compost is
safe for application to plants. The organics typically have high moisture and in the compost
process this is removed. There are different possible configurations of holding waste and
providing air for aerobic composting. The selection of this is based on economics and
competence in handling technology.
The various parameters that affect the composting process and the compost quality are
organisms’ population, carbon Nitrogen ratio, temperature, aeration and moisture. The
above-mentioned controlling parameters need to be monitored in the industrial scale plant.
In large composting operations it is necessary to monitor the wastewater, which comes out
of the organic waste, called leachate. The production of this leachate has to be minimized
and whatever leachate is generated has to be collected and reused for maintaining the
moisture content of the heap and as an inoculum.
B. Design choices
There are many alternative approaches, which have been adopted for composting of
municipal solid wastes based on the broad principle of aerobic composting. The following
approach has been adopted for CMC. The waste as received is pre-sorted. The waste is
formed into windrows and aerated. Roof is proposed for the composting yard. The design is
based on a 35-day waste composting cycle with 14-day additional provision in concrete yard
for additional waste load and for management during monsoons.
C. Sizing of plant
The composting plant has been grouped into 3 parts. The inheriting part, which is the basic
composting process consisting of the wastes windrowing process including aeration so that
a stabilized material is produced. The second part is the compost segregation plant also
called the processing facility where the stabilized wastes are segregated into compost and
rejects and finally maturation and storage part. As discussed previously, the processing
facility is designed to handle 14 tons per day.
D. The process Flow
The proposed type of waste processing facility is Windrow Composting system. Turning of
windrows is done using front-end loaders and optional primary air supply is through
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 100
blowing. The step-by-step process operations are given below. The various aspects, which
come into play at each of the steps, is also given.
E. Stabilising Facility
Step 1: The waste is transferred from segregation facility to the aerobic composting yard.
Step 2: The segregated waste is sent to the windrow platform. The windrow is then sprayed
with cow dung or bio culture slurry. The cow dung or bio culture slurry is made in mixing
tank provided.
Step 3: The windrow is maintained for 7 days. The temperature is monitored to ensure that
the composting process is on-going. The leachate from the windrow comes out and is
collected in the drain. The drain is connected to the leachate tank. The leachate from
leachate tank is used for making the inoculums slurry.
Step 4: At 7thday from start the first windrow is reorganized. The waste volume would have
reduced by about 20 % compared to start with moisture reduction and degradation. While
re-forming the windrow addition of inoculums slurry and water to maintain the moisture is
done using the trailer mounted slurry tank. The temperature profile in the second windrow
is monitored. The leachate from the windrow may come out and is collected in the drain.
Step 5: At 14thdays from start the second windrow is reorganized. The waste volume would
have reduced by about 20% compared to start of windrow 2 with moisture reduction and
degradation. The balance of the waste is reformed into the third windrow. Addition of water
is undertaken if required. The temperature profile in the third windrow is monitored. No
leachate is expected from now on.
Step 6: At 21stdays from start the third windrow is reorganized. The waste volume would
have reduced by about 20% compared to start of windrow 3. The wastes are reformed into
the fourth windrow. Addition of water is undertaken if required. The temperature profile in
the fourth windrow is monitored.
Step 7: At 28thdays from start the fourth windrow is reorganized. The waste volume would
have reduced by about 5% compared to start of windrow 4. The wastes are reformed into
the fifth windrow. Addition of water is undertaken if required. The temperature profile in
the fifth windrow is monitored. This is the maturing stage of the compost.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 101
Step 8: At 35thdays the waste is now composted and it is transferred to the processing line
initial hopper.
F. Waste processing facility
Step 9: The aerobic composting waste is fed into the hopper in the processing line using a
front-end loader. The waste is drawn from the hopper using aconveyor. It is transferred to
another conveyor, which lifts it into the first rotary sieve. The rotary sieve has combination
of 35 mm 16 mm and 4 mm punched holes. The waste not passing through the sieve is the
reject, which is then transferred using the belt conveyor to the reject platform. The
materials not passing through the sieve is transferred out using a chute. The materials
passing through the sieve is transferred using a chute to a heap. The compost at the heap is
further processed with admixtures or directly bagged for sale.
The material of size between 16 mm and 4 mm is sold as grade II compost and the materials
less than 4 mm is grade I compost. Additional products with different admixtures are made
and sold as niche products. The present design does not provide the mixing and grinding
facility for compost up gradation, as this would depend on marketing plans. Space for
provision of these facilities is provided. Bagging is proposed manually.
Step 10: Materials recovery from the rejects is undertaken and the recyclables are stored in
the recyclables shed.
The reject are taken out for disposal in landfill daily. The recyclables are sold when adequate
quantity is available for transport. The compost is sold as per demand.
Exhibit 4-20: Area Requirement of Aerobic Composting Process and Recycling unit
Particulars Unit Quantity
Design Basis
Design Year (Five years period) Year 2020
Design Tonnage (after screening) TPD 13.9
Density of waste under windrow formation (in t/cum ) t /m3 0.60
Density of waste at windrow nos. 2,3,4 ( in t/cum ) t /m3 0.60
Density of waste at 5th windrow ( in t/cum ) t /m3 0.60
Movement Space to be Provided
Movement space required on periphery:
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 102
Along length m 3.00
Along breadth m 3.00
Movement space required between windrows (W/R):
Along length of windrow m 3.00
Along breadth of windrow m 4.00
7 DAY Windrow Operation
No. of days considered for the first windrow day 7.00
Unit
W/R
NO.1
W/R
NO.2
W/R
NO.3
W/R
NO.4
W/R
NO.5
Volume ( in cum ) m3 24.00 15.00 9.00 5.00 3.00
Top width ( in m ) m 2.50 2.00 2.00 2.00 2.00
Bottom width ( in m ) m 5.00 4.00 4.00 4.00 4.00
Height ( in m ) m 3.00 3.00 2.50 2.50 2.50
C/S Area ( in Sq.m ) m2 11.25 9.00 7.50 7.50 7.50
Length of W/R ( in m ) m 3.00 2.00 2.00 1.00 1.00
Total length required m 21.00 14.00 14.00 7.00 7.00
Individual Windrow area m2 105.00 56.00 56.00 28.00 28.00
Windrow area Proposed
Windrow area m2 561.00
Area for Waste Segregation 100.00
Area required for Processing Machinery m2
Pre-sorting Machinery m2 88.00
Preparatory Machinery m2 88.00
Finishing Machinery m2 88.00
Area for Recycling unit m2 80.00
Area for Storage shed - Compostable m2 36.00
Area for Storage shed - Recyclables m2 80.00
Total area required for processing facility m2 1121.00
Proposed area including movement area at twice the total
area m2 2000.00
Existing Windrow pad available at site (40m x 30m) m2 1200.00
Remaining area to be constructed for windrow pad (40m x
20m) m2 800.00
It is proposed that a waste receipt, waste segregation, processing and 35 days windrow,
recycling unit and storage for compost and recyclables shall be provided. The existing pad is
not adequate for windrow composting process of 14 tons of waste per day. It is proposed to
extend the windrow pad area by 800 sqm to accommodate the waste. The layout of the
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 103
Processing facility is given annexure 4.It is proposed to provide 10 PKs, 3 drivers for tractor
trailer and front end loader for material transfer, 1 plant supervisor and 2security guards at
processing facility. The list of vehicles requirement and manpower requirement are
provided in exhibit 4-11 and 4-12 respectively.
4.12.5 Leachate from Processing Shed
Leachate collection tanks shall be provided at waste segregation area and at the windrow
compost area. It is proposed for construction leachate collection tank next to the windrow
compost pad. The leachate tank near the windrow composting area shall collect the
leachate both from windrow compost and sanitary landfill. The leachate collected shall be
reused for spraying on the windrows. The leachate collected in the waste segregation area
and SLF shall be treated together in Planted Gravel Filter and used for plantations in the
facility.
Exhibit 4-21: Leachate Generation from Waste Processing & Compost Area
Location Quantity
(m3)
Days of
operation (days)
Leachate
Generation
Quantity of
Leachate
(m3/day)
Quantity of Waste Receipt. 23.2 1 5% 1.16
Quantity of waste in
Maturation Shed (35 days) 23.2 1 5% 1.16
Total Quantity of Leachate Generation 2.32
4.13 SANITARY LANDFILL
MSW if dumped in open pollutes all environmental components. Waste pollutes air through
gases, dust, litter and bad odour. Water passing through the waste results in leachate with
high COD, heavy metals and salts content. Leachate generated contaminate ground water,
runoff from disposed waste will result in contamination of surface water. The disposed
waste has aesthetic negative impact on the surroundings.
The term ‘landfill’ is used to describe a unit operation for final disposal of ‘MSW on land,
designed and constructed with the objective of minimum impact to the environment by
incorporating eight essential components as described by CPHEEO Manual, 2000. This term
encompasses other terms such as ‘secured landfill’ and ‘engineered landfills’ which are also
sometimes applied to MSW disposal units. The term ‘landfill’ can be treated as synonymous
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 104
to ‘sanitary landfill’ of MSW, only if the latter is designed on the principle of waste
containment and is characterized by the presence of a liner and leachate collection system
to prevent ground water contamination.
(a) Land filling will be done for the following types of waste:
(i) Comingled waste (mixed waste) not found suitable for waste processing;
(ii) Pre-processing and post-processing rejects from waste processing sites;
(iii) Non-hazardous waste not being processed or recycled.
(b) Land filling will usually not be done for the following waste streams in the MSW:
(i) Bio waste/garden waste;
(ii) Dry recyclables.
(c) Land filling of hazardous waste stream in the municipal waste will be done at a
hazardous waste landfill site; such a site will be identified by the State Government
and is likely to be operated by industries of a district/state. If such a landfill is not
available, municipal authorities will dispose the hazardous waste in a special
hazardous waste cell in the MSW landfill.
(d) Land filling of construction and demolition waste will be done in a separate landfill
where the waste can be stored and mined for future use in earthwork or road
projects. If such a landfill site is not available, the waste will be stored in a special cell
at a MSW landfill from where it can be mined for future use. Construction and
demolition waste can be used as a daily cover at MSW landfills; however only
minimum thickness of cover should be provided.
The essential components of landfill are:
(1) A liner system to protect leakage of liquids and gases to soil
(2) A leachate collection and control system for collection and extraction of leachate
from the landfill base
(3) A gas collection and treatment system for collecting gas from the top and its
utilization for energy recovery
(4) A final Cover to enhance water drainage and to support vegetation
(5) Environmental Monitoring System which periodically collects and analyse samples
from air, water, soil- gas and groundwater around the landfill site
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 105
(6) A closure and post closure plan listing measures to close and secure the landfill
site
4.13.1 Landfill Design Requirements and Standards
The design requirements for landfill are broadly divided into three components as follows;
• Earth Works
• Base sealing system
• Top sealing system
The first two components shall be designed during the construction of the landfill facility.
The top sealing system shall be carried out at the end of the useful life of the landfill which
happens after a period of around 4-5 years based on the design and usage parameters.
(a) Earth Works
The design of the layout is made in such a way that all planed areas have sufficient
inclination to guarantee an unhindered run off of leachate and storm water. The design of
the landfill has to be prepared in such a manner, that the amount of cut and fills are finally
in a balance. Required cover material need to be considered and has to be made available.
Filling and compacting must be carried out in layers of up to 40 cm maximum.
(b) Base Sealing System
i. Basic Elements
To avoid negative impact of the landfill body a surface sealing system has to be installed
after the filling of the landfill or parts of it (landfill cells) are completed. The sealing system
has to fulfil the guidelines and technical requirements as defined in the EIA and in the MSW
Rules, 2000. The surface sealing system has to fulfil the following requirements:
1) Mineral sealing layer
2) HDPE Geo-membrane layer
3) Drainage layer
4) Non woven Geo Textile layer
5) Soil layer
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 106
ii. Mineral Sealing Layer
The mineral sealing layer of 900mm depth will be installed in four layers of at least 225 mm
thickness each. A suitable binding material (suitable combination of coarse and fine
particles) should be used. This material must be installed during favourable weather
conditions. The following qualities are required:
• at least 10 mass-% of clay particles with a high adsorptive capacity,
• maximum 5 mass-% of organic substances and
• maximum 15 mass-% of carbonate.
A permeability of the mineral sealing layer of kf 1 x 10-9 m/s has to be ensured. For the
material and its installation the following requirements must be considered:
• homogenous material that has a homogenous water content and homogenous
incorporation of the material,
• proctor density (DPR) of each layer of DPR 95 %, and
• Water content (w) must be higher than the proctor water content.
• Alternatively, Geo-synthetic clay liner and may also be used along with 600mm of
native soil as the mineral sealing layer.
iii. HDPE Geo-Membrane
The second sealing liner will be a High-density polyethylene (HDPE) geo-membrane with a
minimum thickness of 1.5 mm. The geo-membrane can only be installed during favourable
weather conditions. For the constructing of the layer the following items have to be
considered:
• Welding of the HDPE layer is only possible if the sun does not shine directly on the
HDPE layer in summer time (danger of blistering),
• Water is not allowed on the landfill base of the HDPE layer,
• Before work starts the way of placing has to be defined in a plan,
• The placed HDPE layer must be fixed (e. g. sandbags),
• No equipment must drive on the welded HDPE layers (only the necessary equipment
for welding), and
• Every welding seam has to be double checked (stability, density with under pressure
method, thickness, visual inspection).
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 107
iv. Drainage (Leachate) Layer
A drainage layer, consisting of gravel with a grain size of 16/32 mm will be applied to assist
drainage of leachate. Gravel will consist of uniform sizes and be washed to ensure a high
permeability. Perforated HDPE leachate collection pipes will be embedded in the drainage
layer to further assist leachate collection. Leachate will drain towards the leachate pond.
The thickness of the drainage layer will be at least 300 mm. The gravel has to fulfil the
following quality standards:
Permeability kf 1 x 10-3 m/s and b. maximum 20 mass-% of carbonate.
v. Geo-Textile – Protection Layer
For protection of the HDPE layer, a geo-textile must be applied. A geo-textile material,
which is needle-punched and non-woven, will be used as a protection layer. For
incorporation of the layer, the following items have to be considered:
• Weight of geo-textile 2000 g/m²,
• Proof of stamp pushing through force,
• Proof of strip tensile strength,
• Static proof, and
• Proof of stability and resistance to sliding during building and final state.
Laying of the geo-textile is carried out after acceptance of the layers laying underneath. No
vehicles must drive on the geo-textile no equipment or machines should be stored on this
layer. The position of the layer must be secured by appropriate measures to prevent them
from getting lifted up (e. g. sand bags).
vi. Soil Layer
For protection of the Geotextile layer, a soil layer of 300 mm thickness must be applied. A
suitable binding material (suitable combination of coarse and fine particles) should be used.
This material must be installed during favourable weather conditions. The following
qualities are required:
• at least 10 mass-% of clay particles with a high adsorptive capacity,
• maximum 5 mass-% of organic substances and
• maximum 15 mass-% of carbonate.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 108
(c) Top Sealing System
i. General
To avoid negative impact of the landfill body a surface sealing system has to be installed
after the filling of the landfill or parts of it (landfill cells) are completed. The sealing system
has to fulfil the guidelines and technical requirements as defined in the EIA and in the MSW
Rules, 2000. The surface sealing system has to fulfil the following requirements:
1) 300 mm compensation layer
2) Composite layer
3) 450 mm vegetative layer
4) Geo coir layer
After reaching the highest level of each construction phase, as final cover, the surface
sealing system has to be placed on top of the waste body. The surface sealing system will be
constructed with a maximum slope of 33 % in the embankment area.
ii. Compensation Layer
After completing the waste filling, the waste surface will be re-profiled according to the
planned inclination of the surface sealing system. Above the waste surface, the
compensation layer made of a homogenous non-binding material will be applied. The
thickness of the layer will be 600 mm. The layer will be the foundation for the mineral-
sealing layer. Alternatively, Geo-synthetic clay liner and may also be used along with 600mm
of native soil as the mineral sealing layer.
iii. HDPE Geo-Membrane
The second sealing liner will be a High-density polyethylene (HDPE) geo-membrane with a
minimum thickness of 1.5 mm. The geo-membrane can only be installed during favourable
weather conditions. For the constructing of the layer the following items have to be
considered:
• Welding of the HDPE layer is only possible if the sun does not shine directly on
the HDPE layer in summer time (danger of blistering),
• Water is not allowed on the landfill base of the HDPE layer,
• Before work starts the way of placing has to be defined in a plan,
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 109
• The placed HDPE layer must be fixed (e. g. sandbags),
• No equipment must drive on the welded HDPE layers (only the necessary
equipment for welding), and
• Every welding seam has to be double checked (stability, density with under
pressure method, thickness, visual inspection).
.
iv. Vegetative Layer and Geocoir layer
The Geo coir layer followed by vegetative soil layer (topsoil) will be used for the final
restoration of the site. The re-cultivation layer will have a thickness of at least 450 mm.
Plants will be placed in accordance to the local flora as provided in the vicinity of the site. In
order to protect the sealing system, deep rooting plants must be avoided. The plants have
to protect the total sealing system against wind and water erosion and have to minimise
rainwater infiltration.
4.13.2 Tests and Samples during Construction of the Sealing Systems
The tests and samples during construction of the sealing system need to be agreed with the
Contracting Authority but it is likely that they will include the following items.
(a) Aptitude Test
The fundamental suitability (aptitude test) of the used materials provided for the mineral
base and surface sealing system must be proven before construction works start. The
suitability tests of the used mineral sealing material have to be approved by laboratory tests
and a test field. The following laboratory testing is required:
a) grain-size distribution
b) water content
c) consistency of material
d) water absorption of material
e) portion of organic materials
f) portion of carbonate
g) density
h) proctor density
i) water permeability
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 110
j) homogeneity
The suitability of the used drainage material has to be also approved by laboratory tests.
The following tests are required:
a) grain-size distribution
b) content of organic materials
c) content of carbonate
(b) Test Field
Within a test field the suitability of the clay must be proven under the supposed site
conditions. These test fields are the basis for all conditions stipulated for later application by
an independent supervisor.
Construction starts with 4 layers of 225 mm each and includes all above mentioned
laboratory tests and examinations required for each layer by taking some samples. Visual
tests have to be performed by trial pits. The test fields have to be performed outside of the
sealing areas. The results from the test field (including the results of the laboratory tests)
must be evaluated and documented including the following statements with regard to the
design of the mineral sealing system:
a) Compacting methods
b) Compacting equipment
c) Number of compacting transitions
d) Operation speed of compacting equipment
e) Thickness of un-compacted layers (before compaction)
f) Type of homogenisation
The test field must be at least 20 m in length, the minimum width must be 2 machine widths
plus the required ramps 1: 10 and the embankments 1: 5 as well as the distance of
acceleration and deceleration with driving tracks as wide as the equipment, which are
arranged alongside. The test fields should be located at the bottom and embankment area
of the landfill. They should represent the same slopes as landfill. After the mineral sealing
material has been tested, the application of the other sealing compounds, protection layer
and drainage layer will be tested in the test field accordingly. This will be done for the base
sealing as well as for the surface sealing.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 111
(C) Quality Assurance during Construction Works
For the quality assurance during construction works the requirements are as follows:
a) The mineral sealing layers must be built under weather conditions which are in
compliance with required conditions (water content, degree of compression,
coefficient of permeability; example: no construction during heavy rain fall)
b) The top of each completed layer of the mineral sealing system must be dewatered
sufficiently. Shrinkage cracks must be avoided by taking technical measures.
c) Soil lumps which are bigger than 32 mm shall not be used for construction the
mineral sealing.
d) The sealing material must be homogenous and show regular placement water
content. The layers must achieve a homogenous sealing mass. The layers shall
overlap.
e) After completion of each compacted layer an acceptance test must be carried out
before starting the next layer.
f) During and after incorporation the following tests and checks must be carried out
especially for the mineral-sealing layer (for re-cultivation layer, drainage layer and
compensation layer the test has to be done similar):
i. density
ii. thickness of each layer
iii. flatness of each layer
iv. grain-size distribution
v. water content
vi. consistency of material
vii. water absorption of material
viii. proctor density
ix. permeability
x. content of organic parts & carbonate
These tests should be carried according a defined scheme. The laboratory test for the
aptitude test and the quality assurance during construction works have to be carried out by
a qualified geo-technical institute.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 112
4.13.3 Design &Area Requirement
Based on the growth of population and the reduction of waste by recycling and treatment
the volume of waste to be taken to the landfill site has been calculated considering the
following assumptions:
• Waste generation as described
• 15% rejects to be landfilled in case of Compost Processing Plant
• Daily covering of waste (10% of waste volume)
• Specific weight of waste in average 0.80 t/m³
The rejects and inert materials from the processing plant shall be land filled at the
engineered sanitary landfill as per MSW Rules 2000. The actual design of the Sanitary
Landfill has been carried out by assuming that residual waste of 15% to be landfilled. This is
done in line with the general practices adopted across the country to ensure that any
unexpected fluctuations in the residual waste quantities shall not cut short the life of the
landfill below five years.
Exhibit 4-22: Area Requirement for Sanitary Landfill
Design Year Year 2016
Total Waste Generation TPD 12.3
Landfillable Waste TPD 1.8
Density of Landfill Waste T/ m3 0.8
Design Life
Active Period Yrs 15
Closure and Post Closure Period Yrs 5
Total Height of the Landfill m 6
Height below ground level m 3
Height above ground level m 3
Side Slope to be maintained above ground level 1:4 0.25
Side Slope to be maintained below ground level 1:1 1
Landfill Capacity, Height and
Area Phase 1 Phase 2 Phase 3 Phase 4 Phase 5
Start Year 2016 2019 2022 2025 2028
Till Year 2018 2021 2024 2027 2030
Cum. Landfill waste till
(TPY) 2,411.26 2,690.47 3,012.30 3,355.86 3,750.33
Cum. Landfill waste till 3,014.08 3,363.08 3,765.38 4,194.82 4,687.91
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 113
(m3)
Total Volume of daily
cover 15% 452.11 504.46 564.81 629.22 703.19
Total Volume required
for components-Liner
and Cover system
50% 1507.04 1681.54 1882.69 2097.41 2343.96
Total Capacity of
Landfill cu.m 4,973.23 5,549.09 6,212.88 6,921.46 7,735.06
Total Capacity of Landfill for active period cum 16,735.20
Area of the Landfill for active period Sq.m 5578.40
Area of the Landfill for active period Acre 1.38
Shape of Landfill Rectangular Shape
Landfill Phases
Phase 1 Phase 2 Phase 3 Phase 4 Phase 5
Active life period yrs 15 15 15 15 15
Duration of one phase yrs 3 3 3 3 3
Number of Phases
(each phase extends
from base to final
cover)
1 1 1 1 1
Volume of one phase Cum 4,973.23 5,549.09 6,212.88 6,921.46 7,735.06
Additional 10% of
Land is required for
infrastructure facilities
Cum 497.32 554.91 621.29 692.15 773.51
Total Volume of the
Landfill Cum 5,470.56 6,104.00 6,834.17 7,613.60 8,508.56
It is estimated that area required for active life of landfill is 1.38 acres for 15 years
implemented in five phases of each three years. However, in line with the existing practices,
it is proposed to implement the first phase initially. The subsequent phases could be
constructed as and when the existing landfill reaches towards the end of its useful life.
Accordingly, the detailed estimate of the initial phase of the sanitary landfill is provided
below:
Phase Size of the Landfill Sq.m 40mx34m
Width at GL m 34
Length at GL m 40
Width at Bottom of the landfill (-2m) m 28
Length at Bottom of the landfill (-2m) m 34
Width at Top of the landfill (+3m) m 10
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 114
Width at Top of the landfill (+3m) m 16
Landfill Volume below GL cu.m 3450.00
Landfill Volume above GL cu.m 1992.00
Volume of SLF cu.m 5442.00
Area of the SLF Sq.m 1360.00
Area of the SLF acre 0.34
4.13.4 Leachate from Landfill
The leachate from the landfill is mainly due to the rain water. Therefore the leachate
depends on the rainfall in the town. Annual peak precipitation in Kushalnagar is 1033 mm.
Exhibit 4-23: Leachate Generation from Sanitary Landfill
Particulars Quantity Unit
Annual Peak Precipitation in Kushalnagar 1033 Mm
Area of the Land fill 1360 sq. m
Monsoon duration 90 Days
Leachate Generate from the SLF 15.61 m3/day
Leachate from the Waste processing, composting and SLF shall be collected & treated
together in Planted Gravel Filter.
Exhibit 4-24: Total Leachate Generation & sizing of Leachate Collection Tank
Particulars Quantity Unit
Leachate Generate from the SLF 15.61 m3/day
Leachate from Windrow & Waste processing area 2.3 m3/day
Total Volume of Leachate Generation 17.93 m3/day
Dimension of leachate collection tank for Processing area 1.5mx2mx1m
Dimension of leachate collection tank for Sanitary
Landfill Facility 3.5m diax2m ht
4.14 LEACHATE TREATMENT PLANT - PLANTED GRAVEL FILTER
Planted Gravel Filter (also known as Constructed Wetlands) is a biological wastewater
treatment technology designed to mimic processes found in natural wetland ecosystems. It
is a shallow basin filled with filter material (substrate), usually sand or gravel, and planted
with vegetation tolerant of saturated conditions. Wastewater is introduced into the basin
and flows over the surface (horizontal flow) or through the substrate (vertical flow), and is
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 115
discharged out of the basin through a structure which controls thedepth of the wastewater
in the filter.
Exhibit 4-25: Constructed Wetlands
Research studies have shown that Planted Gravel Filters (PGFs) have great potential in
controlling water pollution from domestic, industrial and non-point source contaminants.
The technology is receiving increasing attention for wastewater treatment and recycling due
to the following major advantages:
• use of natural processes
• simple construction (can be constructed with local materials)
• simple operation and maintenance
• cost-effectiveness (low construction and operation costs)
• process stability
There are mainly two types of flow directions used in PGFs. These are horizontal flow (HF)
and vertical flow (VF). It is proposed to have HF PGF for capacity of 18 m3 leachate.
Exhibit 4-26: Sizing of Planted Gravel filter for Leachate
S.No. Parameters Size Unit Remarks
Plated Gravel Filter
1 Area of bed - HF 467.69 m2 • Inlet BOD 5 Concentration: 550
mg/l
• K for HF: 0.15 2 Width (HF) 15 m
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 116
3 Length(HF) 15 m
• Area as per kickuth
• Width as per Darcy’s Law
Assume depth as 0.4 m
4.15 DISPOSAL OF INDUSTRIAL WASTE
Kushalnagar town does not have significant industrial wastes and especially of the
hazardous type. Any specific industrial waste requiring special treatment shall not be taken
into the municipal waste facility and linked to the industrial waste treatment and disposal
facility.
4.16 DISPOSAL OF BIOMEDICAL WASTE
At present, Bio Medical Waste generated is being managed Shree Consultants for the
Kushalnagar town. This is privately managed and the same should continue. However TP
shall ensure the system is being working effectively and no bio- medical waste shall be
mixed with municipal solid waste. No new facility is proposed
4.17 DISPOSAL OF SLAUGHTER HOUSE
The present practise is meat waste (chicken, meat, fish, etc) waste is collected in auto tipper
and disposed in the dumpsite. The existing practise of collecting the meat waste separately
shall be continued. It is proposed to dispose of the meat waste in Deep Burial pits in IWMF.
The concept of Deep Burial is, the waste will be disposed and lime will be sprinkled on the
waste and will be covered by soil on daily basis. The same practise shall be followed. It is
proposed 6 nos. of pits for deep burial facility. Each pit shall be of the dimension
1.5mx5mx1.5m.
4.18 REMEDIATION OF EXISTING MSW AT DUMPSITE
Based on the topographical survey conducted in November, 2015 and considering quantity
of MSW being received presently at the dumpsite, the total quantity of MSW accumulated
at the dumpsite has been calculated. The future quantity of waste that is expected to be
received at the dumpsite till its rehabilitation has also been considered to arrive at the
quantity of MSW that has to be dealt with. The below exhibit shows the MSW quantity at
site. It is proposed that the existing waste shall be processed and recovered the inorganic
materials through 35mm rotary screen proposed at waste processing facility. The remaining
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 117
waste shall be tested according to FAO quality and sold to locally or else it can be filled in
sanitary landfill if compost standard not meet.
Exhibit 4-27: Assessment of Existing MSW Quantity at Dumpsite
S.No. Description MSW Quantity
Remark Cum. Ton
1 Quantity of MSW accumulated
at dumpsite 5489 3294 Density of MSW @ 0.6 T/Cum
2
Assuming, MSW receipt up to
January 2017(from December
2015 to June 2016), the
quantity of waste to be
accumulated
4500 2700
Assuming site rehabilitation
works start in October, 2016
and complete in January, 2017
Total 9989 5994
About 5,994 tons of unprocessed waste is accumulated in the existing landfill site. The same
has to be processed for recovering inorganic components.
4.19 SMART MONITORING AND CONTROL OF MSW OPERATIONS
4.19.1 GPS (Global Positioning System)
The transportation vehicles involved in transferring the waste from the collection points to
the treatment and disposal sites would be performing multiple trips in a day. Monitoring
and tracking these vehicles is a vital activity which cannot be carried out by manual
methods. Therefore, a GPS based vehicle tracking and management system is proposed for
monitoring these MSW transportation vehicles. Each of the transportation vehicles would
be fitted with a GPS device and operations would be centrally controlled at Kushalnagar
town. The system would help optimize vehicle routes and improve the efficiency of the
transportation system, thereby reducing the overall cost of the SWM system. The key
benefits of using the GIS system are set out below.
i. Possible to continuously monitor and track the transportation vehicles.
ii. Useful to identify the deviations in operations.
iii. Useful to identify the vehicles idling during operation.
iv. Helpful in computing the kilometers operated by the private transportation vehicles.
v. Helpful in route optimization – shortest path from the collection point to the
treatment & disposal facility.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 118
4.19.2 RFID, GPS, GIS and GSM technologies
The objectives of this model are real time monitoring of status of bins, estimation of amount
of waste in and around bins, surveillance for monitoring the movement of vehicles,
optimization of routes and reallocation of bins according to the estimated waste, availability
of management information system (MIS) reports for effective planning of resources
schedule, and providing transparency in civic administration. It consists of a garbage truck
equipped with an RFID reader, GPS and GPRS module.
Each container is equipped with an RFID label having a unique identification code. Low
frequency passive tags are proposed because they offer long term low cost solutions and
are operational in extreme conditions resistant to environment hazards. Geo-coding of
containers is done manually through field visits and by noting the locations using a GPS
receiver. When the container gets loaded onto the truck, the reader reads the serial number
of the tag on the container. At the same time, the GPS receiver on the truck calculates its
location using satellite data. The serial number of the tag, location, date and time are
transmitted real time via the GSM network to the communication gateway of the control
server. After data processing, it is transferred to the GIS terminal.
This system can be used for:
• Point to point collection monitoring and control
• Monitoring of fleet status
• Real time management of missed collection points
• Calculation of contractor payment
• Management information system (MIS)
• Management of civilian complaints
• Transparency in civic administration
4.20 LEGAL ASPECTS
4.20.1 Introduction
The legal framework for solid waste management stems from the Municipality Act, the state
policy on solid waste management and the MSW rules 2000 and associates rules. It is
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 119
advisable to incorporate in the responsibilities of the various stakeholders to enable
enforcement of proper solid waste management.
4.20.2 Proposed Provisions
The following legal provisions may be incorporated in the Kushalnagar town.
a. Prohibition against littering the streets, deposition of solid waste on the streets, Open Defecation etc;
No person shall litter on public places or deposit or cause or permit to be deposited or
thrown upon or along any public street, public place land belonging to the TP.
b. Duty of household not to mix recyclable/non-biodegradable waste and domestic hazardous waste with food waste etc.
To ensure that the recyclable waste as well as non-biodegradable waste generated at the
said premises does not get mixed up with the food/biodegradable waste and stored
separately.
c. Duty of Societies/Associations/Management of Commercial complexes to clean their premises and to provide community bins
Management of societies, Associations of residents, commercial establishments,
institutional, markets and like to arrange for daily cleaning of their internal streets, common
spaces etc., and provide community bins of appropriate size. A separate community bin may
be provided for the storage of recyclable waste where door to door collection of recyclable
waste is not practiced.
d. Community bins to be kept in good condition
In all the times community bins to be kept in good condition, regularly maintained and shall
be provided in such a number and at such places as may be considered adequate and
appropriate to contain the waste produced by citizens supposed to be served by the
community bins
e. Duty of occupiers to deposit solid waste in community bins
Occupiers of all premises for whom community bins have provided that all segregated
domestic waste, trade waste, institutional waste from their respective premises to be
deposited in the appropriate community bins.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 120
f. Duty of Kushalnagar town to provide and maintain “Waste Storage Depots”
• Provide and hygienically maintain adequate Waste Storage Depots in the TP and
place large mobile receptacles at such places for the temporary storage of waste
collected from households, shops and establishments as well as from streets and
public spaces until the waste is transported to processing and disposal sites.
• Make adequate provision for closed containers in various parts of the town for the
deposition by citizens of domestic hazardous/toxic waste material adhering to the
provisions of hazardous waste rules of Government of India.
g. Duty of Occupier of households/shops/commercial establishments to hand over the recyclable material/non-biodegradable waste to the waste collectors
It shall be incumbent on households/shops/establishments to handover their segregated
recyclable waste/non-biodegradable waste to the collectors of waste purchaser or recyclers
as may be convenient or as may be notified by the local body from time to time. Such waste
shall not be disposed-off on the streets or in municipal bins or open spaces along with the
organic/food/bio-degradable waste.
h. Duty of Kushalnagar town to collect waste from community bins and to deposit it at waste storage depots for onward transport
It shall be incumbent for local bodies to remove all solid waste deposited in community bins
on a daily basis and transfer it to the waste storage depots/containers identified in the town
and arrange for its expeditious transport to processing or disposal sites.
i. Duty of local bodies to clean all public streets, open public spaces and slum areas
It shall be incumbent on local bodies to arrange for cleaning of all public streets having
habitation on both or either side, and all slums on all days of the year including Sundays and
public holidays.
j. Duty of local body to arrange for processing of food/biodegradable waste through appropriate technology and disposal of rejects
It shall be incumbent for the local bodies to arrange for the processing of
food/organic/biodegradable waste produced in the town and dispose of the rejects and
non- biodegradable waste in an environmentally acceptable manner.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 121
k. Prohibition against deposition of building rubbish
No person shall deposit or cause or permit to be deposited any building rubbish in or along
any street, public space or open land except at a place designated for the purpose or in
conformity with conditions laid down by the Kushalnagar town.
l. Prohibition on disposal of carcasses etc.,
No person shall deposit or otherwise dispose of the carcass or parts of any dead animal at a
place not provided or appointed for this purpose.
m. Punishment for littering on streets and depositing or throwing any solid waste in contravention of the provisions of this act
Whosoever litters the street /or public places or deposits or throws or causes or permits to
be deposited or thrown any solid waste or construction debris at any place in contravention
of the provisions of this Act permits the flow of any filthy matters from his premises shall be
punished on the spot with a fine not less than Rs.50/- as may be prescribed under the rules
framed by the State Govt. from time to time. Such spot fines may be collected by officers
authorized by the Kushalnagar town, not below the rank of sanitary inspector. The amount
of fine imposed shall be recoverable as arrears of property taxes. The amount of fine shall
be kept higher for repeat offences so that the areas can also remain neat and clean.
4.21 HEALTH ASPECTS
4.21.1 Special Attention to Slums and Traditional Dirty Areas
There are about 3 slums in Kushalnagar town which include about 4,380 households. The
slums and traditionally dirty areas and have to be given special attention in terms of
creating awareness, collection of waste from the generators.
Collection of municipal waste from these slums is recommended to be conducted daily. The
waste shall be collected using pushcarts as it is not possible to collect waste using vehicles
from these areas. The details of the required number of pushcarts and other details are
provided in chapter 4 of this DPR.
It is recommended that Collection and transportation of Municipal Solid Waste should be
done on all the days including holidays and Sundays for the effective solid waste
management in the slums and traditional dirty areas. Awareness should be created among
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 122
the slum residents to store the waste and hand it over to the door to door collection points
or dump into container bins rather than throwing it into open points.
4.21.2 Implementation of Low Cost Sanitation Program to Prevent Open Defecation
Open defecation is still observed in Kushalnagar town to some extent. There is a need to
promote low costs sanitation and public toilets to ensure that this practise is stopped. The
health and sanitation department of TP is doing lot of work in this regard. The maintenance
of these public toilets is conducted frequently as a part of sweeping operations. There is
further effort required to ensure that this happens effectively. Levy and charges shall be
imposed for open defecation in the town and awareness about town sanitation should be
created among the people of the town.
The other important issue in sanitation is the open defecation near the construction sites.
Lot of construction activity in the town is happening in the non-core area. Basic facilities like
toilets and urinals to prevent open defecation at the construction sites. The TP does not
insist on provision of temporary toilets at construction sites. This should be included as part
of permission to construct and implementation needs to be monitored and ensured.
4.21.3 Covering of Buildings under Construction
It is necessary to cover the construction sites especially in the core areas. This would avoid
movement of dust and debris and ensure proper site management and debris control. TP
should make it mandatory to cover the dust during the construction and demolition of
buildings and other infrastructures.
4.21.4 Cattle & Pig Nuisance
The nuisance created by pigs and dogs in the town is high. The nuisance is due to the
number of open points in the town. The proposed SWM system is expected to control the
number of open points in the town. The reduced number of open points would decrease the
nuisance created by cattle and pig.
The cattle are seen more near them market area. The market traders should be informed to
not dispose the market waste on streets but dispose only in the compactor/container bins
provided. The bins should not have any holes as stray animals try to enter container bins for
food. It is essential to curb the movement of stray cattles within the town. Owners of these
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 123
animals should be suitably charged an administration charge for the any infringement and
disposal of such trade waste in the municipal system.
4.21.5 Health Monitoring for Sanitation Workers
The solid waste management activities are not hygienic. There are large number of ULB
employees involved in town sanitation maintenance, cleaning the solid waste and
underground drainage system. The health and hygiene of these staff is not checked
regularly at present. The TP should insist on annual medical examination and monitoring,
health education and free medical treatment for the solid waste management and
sanitation staff. It should become a standard practise to conduct medical examination of
employees bi-annually. The same shall be included in the contracts signed with the private
sector and community based organization. A group insurance for health coverage is also to
be taken. The TP should ensure that following measures are compulsorily practiced.
a. Sanitation workers should compulsorily take a weekly off
b. The workers should compulsorily wear all safety equipments
c. The workers should immediately report to health inspectors in case of any accidents
d. Sanitation workers duty should never be stretched for more than 8 hours including
breaks and attendance period
e. The staff should be checked with basic medical tests once in 3 months.
4.21.6 Prevent In-discriminate Use of Pesticides
Pesticides are in use for various pests. Indiscriminate use of pesticides, insecticides etc., at
the dustbins as well as the waste disposal sites shall be stopped. Such use may be made only
under the expert advice of the health authorities in exceptional circumstances.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 124
5 PROJECT COST
5.1 COST ESTIMATE FOR LAND ACQUISITION
Land required for storage of MSW from primary collection, compost facility and landfill
facility for disposal of MSW has been identified and the same has been in possession of TP.
Hence the cost for land acquisition is not considered in estimation of the services delivered
for MSW activities.
5.2 CAPITAL COST ESTIMATE FOR COLLECTION AND TRANSPORTATION
The cost for physical infrastructure components in the collection and transportation services
includes procurement of following tools/equipments/vehicles:
a. Dustbins and HDPE woven sacks for source segregation of slums and non-slum areas
b. Auto tipper for primary collection
c. Compactor for secondary transportation
d. Pushcarts, tractor trailers and other street sweeping equipment like (long handle
brooms, small brooms, gloves, boots, etc.) for street sweeping activities
The total cost for procurement of the tools/equipments/vehicles is provided in below
exhibits.
Exhibit 5-1: Capital Cost Estimation for Collection and Transportation
S.
No. Description Quantity Unit Price Amount in Rs.
A Source Segregation
1 Containers 8310 160.00 13,29,600.00
2 HDPE woven sacks 4155 17.00 70,635.00
B Secondary Collection
1 Auto Tippers 2 5,20,000.00 10,40,000.00
D Secondary Collection & Transportation
1 Compactor 1 29,00,000.00 29,00,000.00
F GPS Tracking device
1 Auto Tippers, Compactor & Tractor
Trailer 10 15,000.00 1,50,000.00
G Others
1 Sound Box, mic set and 2nos for each 7.00 5,180.00 36,260.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 125
vehicles
Total 55,26,495.00
The detailed cost estimation for each of the components described above is given in
Annexure A.5.1.
5.3 CAPITAL COST ESTIMATE FOR PROCESSING FACILITY
For setting up a processing facility, the infrastructure required includes civil works,
machinery and electrical works. The lists of facilities are proposed and their cost for physical
infrastructure components includes procurement of following civil structure/
machinery/equipments/vehicles:
a. Waste Processing facility (Aerobic compost process)
b. Tools and equipment required for processing facility
c. Machinery for processing facility
d. Vehicles required for processing facility and
The estimated cost for procuring the above is set out in the exhibit below.
Exhibit 5-2: Capital Cost Estimation for Processing Facility
S. No. Description Amount in Rs.
1 Construction of Waste Processing facility 87,42,919.93
2 Vehicle at processing facility 26,14,000.00
3 Tools and equipment required for processing facility 1,20,000.00
4 Machinery for processing facility 67,00,000.00
Total 181,76,919.13
The detailed cost estimation for each of the components described above are given in
Annexure A.5.2 and A.5.3.
5.4 CAPITAL COST ESTIMATE FOR RECYCLING FACILITY
For setting up a recycling facility, the infrastructure required includes civil works, machinery
and electrical works. The lists of facilities are proposed and their cost for physical
infrastructure components includes procurement of following civil structure/
machinery/equipments/vehicles:
a. Machinery required for recycling facility
b. Storage bins for recycled items
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 126
The estimated cost for procuring the above is set out in the exhibit below.
Exhibit 5-3: Capital Cost Estimation for Recycling Facility
S. No. Description Amount in Rs.
1 Machinery Storage bins for Recycling facility 5,87,500.00
Total 5,87,500.00
The detailed cost estimation for each of the components described above is given in
Annexure A.5.4.
5.5 CAPITAL COST ESTIMATE FOR LEACHATE TREATMENT FACILITY
The cost of physical infrastructure components for Leachate treatment facility would include
the following exhibit.
Exhibit 5-4: Capital Cost Estimation for Leachate Treatment Facility
S. No. Description Amount in Rs.
1 Construction of Planted gravel filter 4,36,666.00
1 Leachate tank foe windrow platform 30,058.86
Total 4,66,725.81
The detailed cost estimation for each of the components described above are given in
Annexure A.5.5 and A.5.6.
5.6 CAPITAL COST ESTIMATE FOR DISPOSAL
The cost of physical infrastructure components for development of landfill facility would
include the following exhibit.
Exhibit 5-5: Capital Cost Estimation for Sanitary Landfill Facility
S. No. Description Amount in Rs.
1 Construction of SLF 37,62,296.93
Total 37,62,296.93
The detailed cost estimation for each of the components described above is given in
Annexure A.5.7.
5.7 CAPITAL COST ESTIMATE FOR COMMON FACILITIES
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 127
The cost of physical infrastructure components for development of landfill facility would
include the following exhibit.
Exhibit 5-6: Capital Cost Estimation for Common Facility
S. No. Description Amount in Rs.
1 Weigh bridge room cum Office building with toilet 2,51,009.12
2 Toilet Block - 2 Seater 1,41,552.47
3 Septic Tank 47,998.00
4 Rain Water Harvesting 1,29,564.26
5 Deep Burial Facility 21,588.75
6 Drain 11,23,399.06
7 Internal Concrete Road - 5m wide 31,64,499.00
8 Compound Wall 5,41,994.06
9 Weigh bridge pit 1,66,445.08
9 Weigh Bridge Platform 4,94,000.00
10 Furniture and Fixtures 50,000.00
11 Security LED Light Magnet Wand Baton 900.00
12 Computer appliance 40,000.00
13 ABC type 9 kg dry fire extinguisher 17,595.00
14 CCTV camera - 4 nos. 40,000.00
15 Biometric System 5,000.00
Total 62,35,545.00
The detailed cost estimation for each of the components described above are given in
Annexure A.5.8 and A.5.16.
5.8 CAPITAL COST ESTIMATE FOR PUBLIC AWARENESS PROGRAMME
The cost of public awareness programme conducted by Kushalnagar town solid waste
management would include the following exhibit.
Exhibit 5-7: Capital Cost Estimation for Public Awareness Programme
S. No. Description Amount in Rs.
1 Awareness campaign (providing phamplets) - household,
commercial establishments and institutions 1,12,300.00
2 Awareness campaign (one day programme) - Schools,
Colleges and important places 90,000.00
Total 2,02,300.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 128
The detailed cost estimation for each of the components described above is given in
Annexure A.5.17.
5.9 CAPITAL COST ESTIMATE FOR SOCIAL FORESTRY AND CROP DEMONSTRATION
The cost of plant saplings and drip irrigation for social forestry and crop demonstration
would include the following exhibit.
Exhibit 5-8: Capital Cost Estimation for Social Forestry and Crop Demonstration
S. No. Description Amount in Rs.
1 Social Forestry and Crop Demonstration 3,47,910.00
Total 3,47,910.00
The detailed cost estimation for each of the components described above is given in
Annexure A.5.18.
5.10 CAPITAL COST ESTIMATE FOR DRY WASTE COLELCTION CENTRE
For setting up a dry waste collection centre, the infrastructure required includes civil works,
machinery and electrical works. The lists of facilities are proposed and their cost for physical
infrastructure components includes procurement of following civil structure/
machinery/equipments/vehicles:
a. Dry waste collection building
b. Tools and equipment required for Dry waste collection centre
The estimated cost for procuring the above is set out in the exhibit below.
Exhibit 5-9: Capital Cost Estimation for Dry Waste Collection Centre
S. No. Description Amount in Rs.
1 Construction of Dry Waste collection centre 6,92,001.16
2 Tools and equipment 31,969.00
Total 7,23,971.00
The detailed cost estimation for each of the components described above are given in
Annexure A.5.19 and A.5.20.
5.11 SUMMARY OF CAPITAL COST FOR INTEGRATED SOLID WASTE MANAGEMENT
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 129
The summary of the cost for implementation of Integrated Solid Waste Management
services is provided in the below exhibit.
Exhibit 5-10: Summary of Project Cost
S. No.
Description Total Estimated Amount
Contingency - 3%
Grand Total
1 Awareness and IEC ₹ 2,02,300.00 ₹ 0.00 ₹ 2,02,300.00
2 Collection & Transport ₹ 55,26,495.00 ₹ 1,65,794.85 ₹ 56,92,289.85
3 Processing Facilities ₹ 1,81,76,919.13 ₹ 5,45,307.57 ₹ 1,87,22,226.70
4 Sanitary Landfill Facilities ₹ 37,62,297.00 ₹ 1,12,868.91 ₹ 38,75,165.91
5 Recycling facilities ₹ 5,87,500.00 ₹ 17,625.00 ₹ 6,05,125.00
6 Common Facilities ₹ 62,35,545.00 ₹ 1,87,066.35 ₹ 64,22,611.35
7 Leachate Treatment Facility ₹ 4,66,725.81 ₹ 14,001.77 ₹ 4,80,727.58
8 Social Forestry and Crop Demonstration
₹ 3,47,910.00 ₹ 10,437.30 ₹ 3,58,347.30
9 Dry Waste Collection Centre ₹ 7,23,971.00 ₹ 21,719.13 ₹ 7,45,690.13
Total Estimated Amount ₹ 3,60,29,662.94 ₹ 10,74,820.89 ₹ 3,71,04,483.82
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 130
6 PROJECT INSTITUTION FRAMEWORK
6.1 ROLES OF DIFFERENT INSTITUTIONS
Effective provision of MSW management services would require co-ordinated effort by
various stakeholders. The stakeholders in the project comprise RWAs (Resident Welfare
Association), ULBs, citizens, and private operators. The roles of each stakeholder are
presented in below.
6.1.1 Citizens
• Carry out segregation of waste at household level
• Handover the segregated waste to the primary collection crew at the pre-notified
time
• Pay user fee for the door-to-door collection service offered
• Avoid throwing of waste on streets
6.1.2 NGO participations/Informal Sectors
• Inform the residents about the proposed MSW Management Plan
• Ensure that the residents co-operate and follow all the principles
• Appoint primary collection crew for door-to-door collection service
• Monitor performance of service providers, wherever required
6.1.3 Private Sector
• Carry out their roles and responsibilities as per the contractual arrangement
between them and TP
• Ensure that the MSW is handled in the manner set out in the contractual
arrangement and is not disposed in any other manner whatsoever
• Obtain compliance certificate from the authorities concerned
6.1.4 ULB SWM staffs
• Set out MSW Management Plan
• Monitor the works being performed by the private operator
• Ensure compliance by RWAs and citizens
• Make payments to the private operator
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 131
6.2 IMPLEMENTATION PLAN
The provision of MSW management services in the town could be carried out under any of
the two options set out below.
Exhibit 6-1: Options for Implementation of MSW
6.2.1 Option 1 – Service delivery by TP
Under this option, the two distinct activities, with respect to collection & transportation of
MSW and treatment & disposal of MSW, would need to be undertaken by TP in the
following manner.
6.2.1.1 Collection and transportation of MSW
• Procure tools / equipment and vehicles such as auto tippers, pushcarts, secondary
containers, dumper placers and etc. for collection and transportation of MSW
• Hire manpower for carrying out the activities envisaged
6.2.1.2 Treatment and disposal of MSW
• Select a contractor to undertake rehabilitation of the compost facility and develop
the landfill facility
• Hire skilled manpower for carrying out the operations and management of the
developed facilities
6.2.2 Option 2 –Service delivery through private operator(s) with TP playing the role of a facilitator
In this option, implementation of MSWM would be undertaken by private operator(s). The
private operator(s) would need to carry out their roles and responsibilities as per the
MSW
Management
Option1
Service delivery by TP
Option 2
Service delivery by private operator
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 132
contractual agreement signed with TP. The involvement of private operator(s) in various
stages in the MSW management chain is detailed below.
6.2.2.1 Primary Collection
Primary Collection of MSW from the households would be carried out by Private Operator.
The private operator could either utilize the services of Self Help Groups or select private
operator(s) for collection of MSW. The private operator would be responsible for door to
door collection of waste from the households and transferring the same to the secondary
containers from where it would be transported to the treatment/ disposal facility. The
private operator would be responsible for identification of collection crew, procurement of
tools/ equipment/ vehicles by utilizing the funds provided by TP and operation &
maintenance of the same. The private operator would be required to collect the user
charges from the households for provision of door to door collection services and would be
required to meet the O&M expenses within the revenue generated from user charges.
6.2.2.2 Secondary Collection and transportation of MSW
TP would identify private operator(s) for carrying out this activity. The secondary containers,
transportation vehicles and other equipment would be procured by the private operator(s)
who would also be responsible for O&M of the same. The funds required for procurement
would be provided by TP and the duration of service agreement (between TP and the
private operator) would be co-terminus with the age of the vehicles. The private operator
would also be required to make arrangements for parking its vehicles.
6.2.2.3 Treatment and landfill facility
TP would identify private operator(s) for rehabilitation of the existing compost facility and
development of landfill facility. The project could be implemented on a BOT concession
framework. The operator would be responsible for mobilization of finances for development
of these facilities (capital expenditure) and also O&M of these facilities in accordance with
design, construction and O&M specifications provided by TP.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 133
6.2.3 Implementation “Packages” for implementation of SWM activities
The various packages envisaged for MSWM services from collection, secondary storage,
transportation and disposal of MSW is set out below.
6.2.3.1 Collection and transportation
For collection and transportation of MSW from various generators and street sweeping, the
wards would be designed into packages based on the area and quantum of waste
generated. Each package would have designated primary collection crew responsible for
collection and transportation of MSW. The collection and transportation would be operated
and maintained by TP. No privatization/ private operator involvement of collection and
transportation would be recommended by selecting a private operator(s) based on a
competitive bidding process.
6.2.3.2 Treatment and disposal facility
The compost facility and landfill facility would be operated and maintained by TP. The Town
Panchayat would be responsible for rehabilitation of the existing compost facility,
construction of landfill facility and operating & maintaining the compost and landfill facility.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 134
7 PROJECT FINANCIAL STRUCTURING
7.1 OVERALL FINANCIAL STRUCTURING OF THE PROJECT
The financial structuring is proposed as per the details given in following exhibit. Other than
grants from both State and Central government, the project cost is being funded from the
internal resources of TP. The proposed financial structuring for the project is as set in the
below exhibit.
Exhibit 7-1: Financial Structuring of the Project
SN Particulars Details
1 GoI share @ 35% of project Cost 129.87 Lakhs
2 GoK share @ 11.67% of GOI share 43.29 Lakhs
3 ULB’s contribution (14th Finance, CM Special Grants, SFC, others)
16.97 Lakhs
4 Total funds available 190.12 Lakhs
5 Deficit = Estimated DPR cost (capital cost)– total funds available
=371.04– 190.12 Lakhs =180.92 Lakhs
7.2 REVIEW OF OPTIONS
7.2.1 Institutional Dept
For any infrastructure project, use of debt would enable development of more number of
projects for given amount of equity source. However, while it is beneficial to use debt
funding for the project from the project/promoter’s point of view, the decision of the
lender/debt financier to provide fund to the project depends on the project cash flows and
the debt service coverage provided. In case the project’s cash flows do not comfortably
support the debt servicing then tying up of debt funds for the project may not be possible.
As MSWM projects have limited / no returns, the project is envisaged to be developed
through grants from central and state government.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 135
8 PROJECT PHASING
8.1 SCHEDULE FOR BRINGING IN STATE LEVEL AND ULB LEVEL CONTRICUTIONS TO THE
PORJECT
It is expected that the DPR submitted to SBM would be finalized within 10 days from the
date of submission. Funds by SBM will be released to the state within 15 days of finalization
of the DPR and subsequently the state share of funds would be released.
8.2 SCHEDULE FOR OBTAINING ALL CLEARANCES
The clearances from the Karnataka State Pollution Control Board and MoEF are the
important clearances that would be required for implementation of the project which is
expected to be obtained within 45 days of receiving the final project approval from SBM.
Simultaneously, internal approvals required for project implementation will be obtained by
TP. The schedule for obtaining these clearances is given in the below exhibit.
Exhibit 8-1: Schedule for obtaining clearances
S.No. Activity Duration
1 KSPCB and MoEF 45 days
2 Local body approval for construction 30 days
8.3 SCHEDULE FOR SHIFTING UTILITIES
No shifting of utilities is envisaged during implementation of various components of the
project.
8.4 PERT CHART/CPM DIAGRAM
Not Applicable as the Total Project cost is less than Rs.25 crores (Rupees twenty five crores).
8.5 SCHEDULE FOR TENDERING/SELECTION FOR PROCUREMENT OF
SERVICES/EQUIPMENTS/VEHICLES
8.5.1 Tendering Schedule/Selection of Procurement of services
The tendering process which includes notice inviting tender, issue of tender documents,
pre-tender meeting and subsequent issue of clarifications to bidders is expected to be
completed in a month. The bids that are received by the proposal due date will be evaluated
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 136
as per the terms and conditions set out in the tender document and the preferred bidder
would be selected. A Letter of Acceptance would be issued to the preferred bidder by TP.
The selection of the preferred bidder and the agreement formalities are expected to be
completed within 15 days from the proposal due date.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 137
9 PROJECT O&M
It is recommended that the TP shall dedicate a separate budget for Operations and
management of the solid waste management system. An estimate of the proposed
Operations and management is provided below for smooth operations of the solid waste
management system.
Exhibit 9-1: Operations and Management cost of proposed MSWM
S. No
Particular No. Unit cost Unit Monthly expenses
Yearly expenses
1 Man power cost Salaries for staff
Plant Operator 1 20,000.00 Nos. 20,000.00 2,40,000.00
PK at Processing Facility 6 16,105.01 Nos. 96,630.04 11,59,560.52
Drivers for backhoe & Tractor trailer
2 14,416.03 Nos. 28,832.07 3,45,984.82
Security cum weighbridge operator
1 12,512.50 Nos. 12,512.50 1,50,150.00
Drivers for Auto tipper/Mini tipper
7 13,831.39 Nos. 96,819.73 11,61,836.73
Drivers for Compactor 1 14,416.03 Nos. 14,416.03 1,72,992.41
Drivers for Tractor Trailer for street sweeping, C&D
2 13,831.39 Nos. 27,662.78 3,31,953.35
Pk at Dry waste collection centre
2 16,105.01 Nos. 32,210.01 3,86,520.17
O/S PKs for Auto tipper 4 16,105.01 Nos.
64420.02864
773040.3437
O/S PKs for Compactor 1 16,105.01 Nos. 16,105.01 1,93,260.09
O/S Loaders for tractors 6 16,105.01 Nos. 96,630.04 11,59,560.52
O/S PKs for street sweeping-Type A
1 16,105.01 Nos. 16,105.01 1,93,260.09
O/S PKs for street sweeping-Type B
1 16,105.01 Nos. 16,105.01 1,93,260.09
O/S PKs for street sweeping-Type C
1 16,105.01 Nos. 16,105.01 1,93,260.09
O/S PKs for street sweeping-Type D
1 16,105.01 Nos. 16,105.01 1,93,260.09
Permanent staff
Health inspector 1 20,000.00 Nos. 20,000 2,40,000.00
Supervisor 1 22,000.00 Nos. 22,000 2,64,000.00
Pks (sweeping, D2D) 12 22,500.00 Nos. 2,70,000 32,40,000
2 Fuel and power
60.00 Rs. /lit
Auto tipper 7 5.00 L/day 63,000 7,56,000.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 138
Compactor 1 15.00 L/day 27,000 3,24,000.00
Tractors Trailer 3 10.00 L/day 54,000 6,48,000.00
Backhoe Loader 1 25.00 L/day 45,000 5,40,000.00
3 Power
LS
10,000 1,20,000.00
4 Additives and Chemicals 14 100.00 Rs/TPD 42,000 5,04,000.00
5 Tools/Safety equipment’s
35 3,000.00 set/yr 8,750.00 1,05,000.00
6 Baggage and packing cost
2 300.00 Rs/TPD 13,770 1,65,240.00
7 Transportation of finished products
2.64 300.00 Rs/TPD 23,715 2,84,580.00
8 Office cost
LS Rs 10,000 1,20,000.00
9 Maintenance on civil works
17274930.07
2% on Civil cost
Rs 28,791.55 3,45,498.60
10 Maintenance on electrical & mechanical equipment’s
7467495
8% on electrical and mechanical works
Rs 49,783 5,97,399.60
11 Vehicle Maintenance Cost
6554000 5% on vehicle cost
Rs 65,540 7,86,480.00
12 Misc
LS Rs 10,000 1,20,000.00
Total 13,34,00 1,60,08,097
Source: Urban Local Bodies/Town and Village Panchayats, Notification No. KAE 152 MW
208, dated 21.2.2011, published in Gazette dated 17.03.2011, minimum wages with effect
from 17.03.2011
Exhibit 9-2: Revenue by sale of Compost and By-Products
S. No.
Particulars Quantity in TPD
Unit Cost Amount in Rs. per month Amount in Rs. per annum
A Sales
1 Compost 1.53 2,500.00 1,14,750.00 13,77,000.00
2 Recyclables 1.1 300.00 331.50 3,978.00
3 RDF 2.5 100.00 246.50 2,958.00
Total 1,15,328.00 13,83,936.00
Exhibit 9-3: Revenue Generation by user fee collection for the year 2017-18
S.No Waste generators No of generators
Collection Percentage
Rate Amount/annum
1 Slums 1615 40% 25 193800
2 Households 2979 80% 40 1143936
3 Hotels 119 90% 200 257040
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 139
4 Institution 20 90% 200 43200
5 Market 1 90% 2000 21600
6 Shops less than 10 sqm 764 85% 110 857208
7 Shops more than 10 sqm 961 90% 130 1349244
8 Meat/chicken shops 58 95% 200 132240
9 Marriage hall 7 100% 1000 84000
10 Cinema theatre 1 100% 500 6000
11 Hospital 25 100% 200 60000
12 Street vendors 112 80% 110 118272
Total
42,66,540.00
Exhibit 9-4: Proposed SWM user fees for next 5 years
S.No Waste generators 2017 2018 2019 2020 2021
1 Slums 25 25 30 30 35
2 Households 40 40 50 50 60
3 Hotels 200 200 250 250 300
4 Institution 200 200 250 250 300
5 Market 2000 2000 1500 1500 3000
6 Shops less than 10 sqm 110 110 125 125 140
7 Shops more than 10 sqm 130 130 150 150 170
8 Meat/chicken shops 200 200 250 250 300
9 Marriage hall 1000 1000 1500 1500 2000
10 Cinema theatre 500 500 400 400 700
11 Hospital 200 200 250 250 300
12 Street vendors 110 110 125 125 140
The revenue generation from user fee collection and compost is given below in which it is
proposed to collect 35% of the operations cost from SWM services for the first year and in
next 5 year about 55% of operations cost shall be covered by revenue from SWM services.
Exhibit 9-5: Financing of O&M expenses for the MSWM services
S. N. Description Amount in Rs.per annum
1 Proposed O&M cost 160.08 168.09 176.49 185.31 194.58
2 Proposed Revenue by way of User Charges 42.67
48.15 62.97 70.81 91.54
3 Proposed Revenue by sale of compost and by-product
13.84 14.25 14.68 15.12 15.58
4 Salaries by Untied SFC 51.36 53.93 56.62 59.45 62.43
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 140
5 Salaries from SFC grants for permanent staff
37.44 39.31 41.28 43.34 45.51
6 Total revenue proposed revenue 145.30 155.64 175.56 188.73 215.05
7
Surplus or deficit (SWM) = Proposed total SWM O&M cost- Proposed total revenue generated (SWM related cess) 14.78 12.44 0.93 (3.41) (20.47)
% of cost recovered from SWM services 35% 37% 44% 46% 55%
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 141
10 PROJECT BENEFITS ASSESSMENT
10.1 BENEFITS FROM THE SOCIETAL PERSPECTIVE
The social benefits on 12 parameters have been enlisted and the qualitative impacts of the
same are listed in the below exhibit
Exhibit 10-1: Social Benefits and Quantitative Impacts
S. No. Benefits
Description Comments Qualitative Impacts
Underlying
Assumptions
1 Access
For collection of MSW
from non-slum areas,
auto tipper would be
used.
The collection and
transportation of the
MSW from various
generators would be
efficient
The assumption is
that, the citizens
/RWAs/ CEs think
rationally to reduce
the spread of
epidemic diseases
and also adhere to
the MSW practices.
In slum areas where
access to narrow road
is possible be auto
tipper would be used.
2 Coverage
All the areas in the
town would be
covered including
residential,
commercial and slum
areas. The strategy
integrates the
complete chain such
as collection, storage
transportation,
treatment and
disposal
MSW from
households and bulk
generators would be
substantially
covered resulting in
systematic disposal
of MSW. The exact
quantitative
assessment is very
difficult.
The assumption is
that, the citizens
/RWAs/ CEs think
rationally to reduce
the spread of
epidemic diseases
and also adhere to
the MSW practices.
3 Service
Quality
Enhanced MSW
services in collection
and transportation, as
competent private
operators would be
rendering the services
Although,
quantification is not
possible, long term,
benefits are
envisaged like
environmental
benefits, health
benefits and social
benefits. Etc.,
Involvement of the
citizens would
benefit in
improvement of
citizen’s health and
also town’s
ambience, thereby
resulting in social
and environmental
value additions
Enhanced MSW
services as the
compost facility and
landfill facility would
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 142
be operated by the
private operator
4
Income for
poorer
sections
Creation of direct and
indirect employment
for poorer section of
the society
The non-skilled
manpower would
get an opportunity
to earn their
livelihood. Value
extraction from
MSW generated
would enhance the
business opportunity
for the private
operators (for e.g
compost). This also
would generate
direct employment
for poorer sections
of the society
5 Supply
continuity
As MSW would be
generated on a daily
basis the process of
treatment and
disposal would also be
done on a daily basis.
Management of
MSW is a continues
process and when
practiced would
result in multiple
benefits
6 Safety
Implementation of the
strategy would result
in safe disposal of
MSW. And the safety
standards followed at
different levels, would
result in safe working
environment for the
PKs
Elimination of road
side disposal would
reduce the health
hazards caused due
to open
decomposition
Systematic disposal
by the citizens
would reduce the
environmental
impact. (For e.g
ground water
pollution).
Providing
protective gears to
PKs would prevent
injuries when in
contact with unsafe
waste disposed
7 Cost Savings
Due to treatment and
disposal of MSW in an
area outside the town,
air pollution and
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 143
ground water
contamination would
be prevented,
resulting in indirect
cost savings
8 Improved
Efficiency
Integrated process of
MSWM would
minimize the travel
time and improve the
efficiency at each
activity in the MSW
management chain.
(collection, storage,
transportation,
treatment and
disposal)
For example: Having
vehicle depot at
various zones of the
town reduces the
time and cost of
transportation.
Vehicle depots
would decongest the
roads rather than
parking on the road
side.
9 Time Savings
Transfer station would
reduce the time and
transportation cost of
MSW from each ward
Time saving would
improve the
efficiency of the
system
Time has monetary
value
10 Environment
Improvement
Reduced open
dumping would result
in reduced
environmental impact
In the short term
although the
improvement might
not be visible, in the
long run, lesser
pollution would
ensure cleaner
environment and
improve the
ambiance of the
town.
11 Employment
Employment
opportunity would be
generated at various
levels. eg. PKs would
be employed for MSW
collection and street
sweeping, skilled
machinery operators
would be employed
for operating the
In an indirect way,
increased disposal of
MSW would
increase the
employment
requirements at
various levels
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 144
compost and landfill
facility.
12
Improved
Quality of life
etc
Reduced air pollution,
water pollution would
result in hygienic living
standards.
10.2 LIST OF NEGATIVE EXTERNALITIES
As the project is environmental oriented, the impact and the negative externalities of the
proposed strategy has been listed in the exhibit below.
Exhibit 10-2: Negative Externalities and Impacts
S. No. Benefits Description Comments Quantitative Impacts
1
Pollution,
environmental
distortions, reduced
green cover etc
Project would reduce the
pollution levels and will not
have any adverse impact on
environmental aspects.
No pollution
2
Reduced access to
any specific user
segments
Project would not lead to
any such effect Not applicable
3
Supply interruptions
(especially during
project construction
phases etc)
Construction activity is
being planned properly to
ensure alternative plan for
regular management and
there would be no
interruption during
construction phase
No supply interruption
4 Displacement of
inhabitants
Compost facility is already
developed and is currently
maintained by TP .The
landfill facility is being
developed adjacent to the
existing compost facility
owned and possessed by
TP. No new land is being
acquired. Hence no
displacement of inhabitants
would occur
No displacement would take
place.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 145
5
Disruption of
livelihood / reduced
employment /labour
redundancy
No such effect is expected
to occur since it is expected
that more opportunities
would come up in both
direct and indirect category
of employment
Not disruption
6
Possible Haphazard
development
around/adjacent
project site areas
Since the project is being
developed on the outskirts
of the town on a barn land
area, no adjacent
development is expected.
No slum, commercial
properties (malls) ,etc
10.3 ECONOMIC INTERNAL RATE OF RETURN
Not Applicable as the Total Project cost is less than Rs. 100 crores (Rupees hundred crores).
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 146
11 PUBLIC AWARENESS
11.1 INTRODUCTION
The problems of waste disposal in the growing urban cities are a concern with the scarce
availability of land for processing and disposal of waste. The environmental remediation
measures are becoming ever more expensive. It is therefore necessary to not only think
about effective ways and means to process and dispose of the waste that the normal urban
cities generate each day, but it is also essential to seriously consider avoiding or reducing
the generation of waste in the first place and to consider ways to re-use and recycle the
waste, so that the least quantity of waste needs to be processed and disposed in the landfill
facilities.
11.2 REDUCE, REUSE AND RECYCLE (R-R-R)
There is no action on Reduce, Reuse and Recycling of waste at present in the Town. The
quantity of food waste generated per capita has increased marginally in the recent couple of
years. The quantity of packaging waste material and non-bio-degradable waste is also going
up rapidly every year. It was observed during the physical character analysis conducted in
Gajendragad Town that the plastics are up to about 13% of the municipal waste. This
increases the burden on local bodies to deal with the problem of non-biodegradable of
waste landing up at processing and disposal sites.
The TP should insist on minimal usage of plastic and other non-bio degradable wastes. The
commercial establishment owners should be included in drafting the strategy for prevention
of usage of non-bio degradable packing materials. The TP should also strictly implement the
plastic usage rules of Pollution control board (PCB).
11.2.1 Recycling of waste by all concerned
All manufacturers producing a variety of domestic and non-domestic products, food as well
as non-food should be persuaded to seriously endeavour to use re-usable packaging
materials so that after the delivery of goods, the packaging materials could be collected
back and used over and over again. They could also consider minimizing or avoiding use of
unnecessary packaging materials by innovative methods. Incentives and product discount
should be given to consumers for the return of packaging or bottling materials in good
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 147
condition, to the waste producers or retailers to promote reuse. The cost of packed articles
and article without the packaging material could be kept different with a choice to the
consumers to take the article without the packaging material at low cost.
11.2.2 Reuse
Efforts should be made to encourage collection of re-usable material through waste
collectors, waste producers, NGOs and private sector instead of allowing reusable waste to
land up on the disposal sites. Bottles, cans, tins, drums and cartons can be reused.
11.2.3 Recycling
In the era of excessive packaging materials being used, a lot of recyclable waste material is
generated. All-out efforts are necessary to retrieve recyclable material from the households,
shops and establishments and fed to the recycling industries through intermediaries such as
waste purchasers, waste collectors/NGOs, etc.
11.3 PUBLIC PARTICIPATION
Public participation is the basis for improving the solid waste management. This requires lot
of effort. Public participation is essential in the following activities.
• Reduce, Reuse & Recycling (R R R) of waste.
• Not to throw waste/litter on streets, drains, open spaces, water bodies, etc.
• Storage of organic/bio-degradable and recyclable waste separately at source.
• Primary collection of waste
• Community storage/collection of waste in flats, slums, societies, commercial
complexes, etc. and other waste source generators.
• Pay adequately for the services provided.
The local body should decide the methodology to be adopted for reaching the community
and seeking their cooperation and effective participation in SWM services. This is a very
difficult area of activity and unless this is done meticulously, desired results will not be
achieved.
The essential steps in this direction is to select representative samples of the community
and go through a consultative process to ascertain the perceptions of the people about the
SWM services being given to them, their expectations and extent to which they are willing
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 148
to support and participate in the process. Their choice of technological options available
also needs to be ascertained.
There is a need to interact with the community to identify problems of waste management
through site visits and consultation with local population at the time when the community is
generally available for interaction. It may either be in early morning or late evening. The
areas may be selected by following the method of drawl of representative samples.
Situation analysis may be done by the persons who know the subject reasonably well, know
local language and can communicate with local population effectively. Such persons may be
Non-Governmental Organisations, Community Based Organisations or knowledgeable
individuals. They should try to find out the prevalent situation of waste management in the
area under observation and ascertain the perceptions of the people about the services
provided. In this exercise the local councillors, local leaders, NGOs, etc., may be invited to
participate.
11.3.1 Finding out optional solutions
Having identified the deficiencies in the system and known the public perceptions, the next
essential step is to think of optional solutions to tackle the problems, workout the cost
implications and level of public participation needed.
11.3.2 Consult community on options available
There should be second round of consultative process where the options worked out may
be discussed with the community along with cost implications and their support required.
Their suggestions may be sought on each solution proposed. The community may be
encouraged to give their views. If we ask the people straight away the solutions of the
problems, they may not be able to give right kind of suggestions as they have no exposure
of various technological options. Therefore, they must be first appraised of the options
available and then asked to give their considered opinion on what will work in their area and
how much they are willing to cooperate.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 149
11.4 PUBLIC INFORMATION EDUCATION, COMMUNICATION AND AWARENESS
PROGRAMS
For the successful implementation of any program involving public at large in SWM system
is essential. Public information, education and communication are essential for success of
every endeavour in this space.
IEC approach should be
• Ensure that the people become aware of the problems of waste accumulation and
the way it affects their lives directly.
• Ensure that the people generate less waste by cutting back on waste generating
material and by following clear defined practices of waste management.
• Create public awareness against big waste generators and provide information to
monitor the performance of these sources of waste.
• Inform the people about waste management program of the government and
municipal bodies.
• Promote public participation in waste management efforts through private
partnership where feasible.
Citizens co-operation is vital to reduce, reuse and recycling of waste and in keeping garbage
off the streets, by keeping biodegradable "wet" kitchen and food wastes unmixed and
separate from recyclable "dry" wastes and other hazardous wastes. Their participation in
primary collection of waste, using community bins for storage of waste generated in multi
storied buildings, societies, commercial complexes and slums is also essential.
11.4.1 Public Education
The communication material developed should be utilised in public awareness programmes
through variety of approaches as under.
11.4.2 Group Education
This may be done through:
• Group Meetings in the community
• Workshops
• Exhibitions
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 150
• Lecture series
• Panel Discussions, etc.
11.4.3 Mass Education
This is very essential to cover the entire population as it is not possible to reach all the
people through group education programs. Mass Education programs can be planned using
following methods of communication.
11.4.3.1 Use of Cinema Halls
Slides in cinema theatres can be displayed to inform and motivate the public.
11.4.3.2 Posters
Attractive posters with good photographs and messages with a very few words, readable
from a distance, should be prepared and displayed in various parts of the Town where
awareness campaign is being taken up.
11.4.3.3 Use of Public Transport System
Brief messages can be painted on the rear of public buses or inside the bus panels. Public
and private firms having their own bus fleets may be invited to support such efforts.
11.4.3.4 Use of School Children
Children are powerful communicators. Parents who do not listen to the advice of others
often take their children seriously. Children are idealistic and would like to change their
world for better. The ULB should hold regular meetings with principals, teachers and
students to explain the need for change, and the usefulness to society of new ways to
manage waste. The message can be reinforced by holding essay, debate or drawing and
painting competitions on the subject and publicizing the winning contestants.
11.4.3.5 Resident Associations
Most citizens want a nearby facility to dispose of their waste, but nobody wants a dustbin at
their doorstep. Both needs can be met by the house-to-house collection system through
handcarts or tricycles. Neighbourhoods can be rewarded for good response to doorstep
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 151
collection of segregated waste. Groups that undertake to manage the cleaning of their own
area can be rewarded by ULBs through grants/subsidies.
11.4.3.6 Voluntary Organizations/NGO involvement
Many NGOs are committed to improve SWM practices in urban areas to protect the
environment and have been very active in this field. They have also developed good mass-
communication skills and education programs for the public. Such NGOs may be persuaded
to actively support the new strategies adopted by the local body and associate in public
awareness campaigns. Those who wish to conduct programs for sections of the public on
the new SWM strategies may be encouraged to do so and given necessary support.
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 152
A.1 SURVEY OF WASTE GENERATORS
A.1.1. Abstract of Waste Generators
S.
No. Waste Generators No of Generators
Avg. waste
per day in
Kg
Total
waste in Kg
1 Residential
Household 25.00 1.1 28.23
2 Undeclared Slum 13.00 0.7 9.65
3 Commercials
Shops/Malls/Complexes 11.00 1.1 11.66
4 Petty shops 8.00 0.5 4.34
5 Hotels 4.00 4.5 18.07
6 Veg. Markets 1.00 30.3 30.33
7 Meat/Chicken shops/Slaughter house 4.00 4.4 17.63
8 Institution 1 3.4 3.40
A.1.1.1 Waste Generation from Household Samples
Survey Location Residential (Household)
S.No.
Ward No.
Street Name Name of the respondent
Weight in kg
Day 1: 04/12/15
Day 2: 05/12/15
Day 3: 27/11/15
1 3 cauvery badavane
Mr. kalim 0.39 0.57 1.20
2 3 cauvery badavane
Ms. Devamma 1.40 1.50 0.36
3 3 cauvery badavane
Mr. Jagadish 0.50 1.50 0.62
4 3 cauvery badavane
Mr. M. Abubakar 0.54 0.68 1.20
5 3 cauvery badavane
Mr. dinesh nayak 1.00 1.43 0.37
6 3 cauvery badavane
Ms. Amrutha raj 0.00 0.71 0.97
7 1 brujana halli Ms. Sunitha 0.22 2.35 0.30
8 1 brujana halli Ms. Marry yamma 1.13 0.69 2.76
9 1 brujana halli Ms. Shifana 0.13 0.59 4.20
10 1 brujana halli Mr. Uthaiya K U 0.65 0.59 5.10
11 4 Dandina pete Mr. S A Thimmaiah 0.29 0.71 0.96
12 4 Dandina pete Mr. Anugraha 1.00 0.89 1.10
13 4 Dandina pete om prakash 0.56 1.23 2.20
14 4 Dandina pete Mr. sundra 0.70 1.56 1.32
15 4 Dandina pete Mr. D K thimmappa
1.21 0.56 1.50
16 12 Police block Mr. A S joseph 2.37 3.70 0.67
17 12 Police block Md. Saji 1.80 2.60 0.33
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 153
18 12 Police block Mr. dinakar S T 0.46 1.24 0.32
19 12 Police block Ms. Nisha P B 0.97 0.55 0.44
20 12 Police block Mr. Pramod muthappa
3.73 4.63 0.30
21 12 Police block Ms. Samitha kushalappa
0.23 1.14 0.84
22 13 Murroad Ms. Meenakshi 0.41 0.37 0.60
23 13 Murroad Mr. Baasha 1.35 0.67 0.32
24 13 Murroad Mr. H D Chamdhar 0.67 1.70 0.37
25 13 Murroad Ms. Anjanna 0.43 0.90 1.17
Total 22.12 33.04 29.52
A.1.1.2 Waste Generation from Declared Slums Samples
Survey Location Residential (Undeclared Slum)
S.No.
Ward No.
Street Name Name of the respondent
Weight in kg
Day 1: 04/12/15
Day 2: 05/12/15
Day 3: 27/11/15
1 2 Ambedkar layout
Ms. Lakshmi 1.94 0.43 0.54
2 2 Ambedkar layout
Ms. Tejaswani
0.34 0.16 0.56
3 2 Ambedkar layout
Ms. Neela 0.94 0.54 0.77
4 2 Ambedkar layout
Mr. rathan 0.20 0.80 0.63
5 2 Ambedkar layout
Ms. Latha 0.45 0.45 0.37
6 8 Dravida colony Mr. Narayana
0.70 1.30 0.64
7 8 Dravida colony Mr. Shiva 1.23 0.98 0.28
8 8 Dravida colony Mr. Manju 0.35 0.78 1.20
9 8 Dravida colony Mr. Aanand 0.81 0.53 1.50
10 8 Dravida colony Mr. Kariyappa
1.31 0.34 0.14
11 8 Dravida colony Mr. ravi 0.32 1.02 1.32
12 8 Dravida colony Mr. hemanth
1.76 0.46 0.72
13 8 Dravida colony Mr. guru 0.33 0.52 1.32
Total 10.67 8.30 9.98
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 154
A.1.1.3 Waste Generation from Shops/Malls/Complexes Samples
Survey Location Commercial Establishments (Shops/Malls/Complexes)
S. No.
Name of the Establishment
Street Name
Name of the respondent
Weight in kg
Day 1: 04/12/15
Day 2: 05/12/15
Day 3: 27/11/15
1 elite bakery B. M raod Mr. Shashi 0.28 0.96 1.37
2 Tea stall B. M raod Mr. husain 1.00 1.00 1.15
3 Shabari bakery B. M raod Mr. Pradeep 0.24 1.65 1.32
4 Nandini milk parlor
B. M raod Mr. chandrakanth
0.65 1.21 1.72
5 Cavery bakery B. M raod Mr. harindran 1.10 1.73 1.24
6 Gokul sweets B. M raod Mr. Kumar 0.87 0.93 0.38
7 Ashpka hair dresses
I. B road Mr. Aashoka 1.32 0.50 1.00
8 Cavery tiffans I. B road Mr. raju 1.26 1.74 0.90
9 Aadishakti medicals
I. B road Mr. venktesh 2.04 1.17 1.02
10 taj biriyani I. B road Mr. Abdulla 1.12 1.73 0.91
11 Uday medicals I. B road Mr. uday 0.90 0.57 0.00
10.78 13.19 11.01
A.1.1.4 Waste Generation from Petty Shops Samples
Survey Location Commercial Establishments (Petty Shops)
S.No.
Name Street Name
Name of the respondent
Weight in kg
Day 1: 04/12/15
Day 2: 05/12/15
Day 3: 27/11/15
1 S.S pan shop B.M road Mr. Shabari 0.57 1.20 1.00
2 Sukumar petty shop
B.M road Mr. Harshad 0.50 0.50 0.30
3 Muhammad pan stall
B.M road Mr. Thilak shetty
0.46 0.78 0.18
4 Mubin pan stall B.M road Mr. Mubin 0.50 0.50 0.30
5 Mudina pan stall M M Road Mr. Basha 0.78 0.40 0.23
6 Ganesh beda stall M M Road Mr. kumar 0.50 0.34 0.43
7 Pujari pan stall M M Road Mr. Krishna 0.35 0.45 0.57
8 Mahasha allah pan stall
M M Road Mr. Rafid 1.20 0.34 0.68
Total 4.85 4.50 3.68
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 155
A.1.1.5 Waste Generation from Hotel Samples
Survey Location Hotels
S.No.
Name of the Hotel Street Name
Name of the respondent
Weight in kg
Day 1: 04/12/15
Day 2: 05/12/15
Day 3: 06/12/15
1 kings way hotel B.M road
Mr. Dawud 2.20 4.71 3.54
2 top in town B.M road
Mr. k balakrishna
6.87 7.16 5.47
3 Keralapura miltary hotel
B.M road
Mr. srinavas 7.67 2.71 2.67
4 hotel Century B.M road
Mr. Momutti 0.60 2.66 4.71
5 hotel nisraga B.M road
Mr. dhanush narayan
4.50 3.13 5.16
6 Hotel ganesh bhavan
B.M road
mr. srinavas ashwat
6.16 7.77 3.61
Total 28.00 28.14 25.16
A.1.1.6 Waste Generation from Institutions Samples
Survey Location Institution (School/College/gov. organization)
S.No. Name of the
Institute Street Name
Name of the
respondent
Weight in kg
Day 1: 04/12/15
Day 2: 05/12/15
Day 3: 06/12/15
1 Government girls high school
Mysore road
Ms. Pushpa 3 2.61 4.6
Total 3.00 2.61 4.60
A.1.1.7 Waste Generation from Vegetable Market
Survey Location Vegetable Market
S.No. Ward No. Street Name Name of
the respondent
Weight in kg
Day 1: 04/12/15
Day 2: 05/12/15
Day 3: 06/12/15
1 1 B.M road Mr. Rajanna 25 30 36
Total 25.00 30.00 36.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 156
A.1.1.8 Waste Generation from Meat/Chicken/Fish Stall/Slaughter House Samples
Survey Location Meat/Chicken/Fish Stall/Slaughter House
S. No.
Name of Stall Street Name
Name of the respondent
Weight in kg
Day 1: 04/12/15
Day 2: 05/12/15
Day 3: 06/12/15
1 Mubin fresh chicken stall
market road
Mr. Mubin 1.71 2.15 4.75
2 Shuphi Chicken stall
market road
Mr. Shuphi 7.165 6.35 4.315
Total 8.88 8.50 9.07
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 157
A.2 WASTE QUANTIFICATION STUDY
A.2.1. Abstract of Waste Quantification Study
S.No
Vehicle No Vehicle
Type
04/12/2015 05/12/2015 07/12/2015
No. of trips
Waste Qty in Kg
No. of trips
Waste Qty in Kg
No. of trips
Waste Qty in Kg
1 KA12T5326 Tractor Trailer
2 2320 2 1730 2 1860
2 KA12T5328 Tractor Trailer
2 2260 2 3500 2 1810
3 KA12G709 Tractor Trailer
0 0 2 4290 2 3510
Total Quantity in kg 4580 9520 7180
Total Quantity in Ton 4.58 9.52 7.18
Date of sampling (Day 1) 04-12-2015
S.No. Vehicle No. Vehicle type Trip Gross wt in kg Tare wt in kg Net wt in kg
1 KA12T5326 Tractor Trailer 1st 4090 3260 830
2 KA12T5326 Tractor Trailer 2nd 4750 3260 1490
3 KA12T5328 Tractor Trailer 1st 3930 3220 710
4 KA12T5328 Tractor Trailer 2nd 4770 3220 1550
Total Quantity in kg 17540 12960 4580
Total Quantity in Ton 17.54 12.96 4.58
Date of sampling (Day 2) 05/12/2015
S. No. Vehicle No. Vehicle type Trip Gross wt in kg Tare wt in kg Net wt in kg
1 KA12T5326 Tractor Trailer 1st 4030 3260 770
2 KA12T5326 Tractor Trailer 2nd 4220 3260 960
3 KA12T5328 Tractor Trailer 1ST 4490 3220 1270
4 KA12T5328 Tractor Trailer 2nd 5450 3220 2230
5 KA12G709 Tractor Trailer 1st 6070 3350 2720
6 KA12G709 Tractor Trailer 2nd 4920 3350 1570
Total Quantity in kg 29180 19660 9520
Total Quantity in Ton 29.18 19.66 9.52
Date of sampling (Day 3) 06/12/2015
S.No. Vehicle No. Vehicle type Trip Gross wt in kg Tare wt in kg Net wt in kg
1 KA12T5326 Tractor Trailer 1st 4100 3260 840
2 KA12T5326 Tractor Trailer 2nd 4280 3260 1020
3 KA12T5328 Tractor Trailer 1st 4050 3220 830
4 KA12T5328 Tractor Trailer 2nd 4200 3220 980
5 KA12G709 Tractor Trailer 1st 4920 3350 1570
6 KA12G709 Tractor Trailer 2nd 5290 3350 1940
Total Quantity in kg 26840 19660 7180
Total Quantity in Ton 26.84 19.66 7.18
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 158
A.3. WASTE CHARACTERIZATION STUDY
A.3.1. Physical Composition of Waste - Dumpsite
Sampling Sources Dumpsite (Fresh)
Sampling Location Arji village
S. No. Components Weight in kg
Day 1 Day 2 Day 3 Average
1
Wet
Was
te Food Waste 4.10 3.84 4.20 4.04
2 Tree/Fruit/Flower Waste 14.48 5.97 6.04 8.83
3 Paper towels 5.89 7.08 8.15 7.04
3
Dry
Was
te
Plastic Containers and Packaging 4.12 3.94 3.94 4.00
4 Paper, Cardboard and Cartons 3.00 4.47 4.19 3.89
5 Rubber 0.00 1.25 1.05 0.77
6 Rags/Clothes 3.29 2.91 3.07 3.09
7 Wood 1.38 1.88 1.26 1.51
8 Metals 0.59 0.27 0.22 0.36
9 Glass 2.86 2.79 2.79 2.81
10 Inerts 6.14 8.17 8.51 7.61
11
Spec
ial
Was
te
Electronic waste/batteries/Bulbs 0.28 0.41 0.47 0.39
12 Bio-Medical waste 0.00 0.00 0.00 0.00
Total 46.12 42.97 43.87 44.32
Date of sampling (Day 1) 04/122015
Sampling Sources Dumpsite Samples
(Fresh waste)
Sampling Location Buvunagiri
S. No. Components Weight in kg
Sample 1 Sample 2
1
Wet
Was
te Food Waste 3.84 4.35
2 Tree/Fruit/Flower Waste 18.40 10.56
3 Paper towels 5.40 6.37
3
Dry
Was
te
Plastic Containers and Packaging 3.92 4.31
4 Paper, Cardboard and Cartons 2.44 3.56
5 Rubber 0.00 0.00
6 Rags/Clothes 3.61 2.97
7 Wood 1.20 1.56
8 Metals 0.61 0.57
9 Glass 2.51 3.21
10 Inerts 6.39 5.89
11
Spec
ial
Was
te
Electronic waste/batteries/Bulbs 0.24 0.33
12 Bio-Medical waste 0.00 0.00
Total 48.55 43.69
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 159
Date of sampling (Day 2) 05/12/2015
Sampling Sources Dumpsite Samples (Fresh waste)
Sampling Location Buvunagiri
S. No. Components Weight in kg
Sample 1 Sample 2
1
Wet
Was
te Food Waste 3.13 4.55
2 Tree/Fruit/Flower Waste 4.79 7.15
3 Paper towels 7.24 6.92
3
Dry
Was
te
Plastic Containers and Packaging 4.00 3.88
4 Paper, Cardboard and Cartons 4.72 4.22
5 Rubber 1.57 0.93
6 Rags/Clothes 2.32 3.50
7 Wood 1.65 2.10
8 Metals 0.32 0.22
9 Glass 2.40 3.17
10 Inerts 7.93 8.41
11
Spec
ial
Was
te
Electronic waste/batteries/Bulbs 0.51 0.32
12 Bio-Medical waste 0.00 0.00
Total 40.58 45.37
Date of sampling (Day 3) 06/12/2015
Sampling Sources Dumpsite Samples (Fresh waste)
Sampling Location Arji village
S. No. Components Weight in kg
Sample 1 Sample 2
1
Wet
Was
te Food Waste 4.72 3.67
2 Tree/Fruit/Flower Waste 5.31 6.76
3 Paper towels 8.43 7.87
3
Dry
Was
te
Plastic Containers and Packaging 3.71 4.16
4 Paper, Cardboard and Cartons 4.64 3.74
5 Rubber 1.21 0.88
6 Rags/Clothes 2.97 3.17
7 Wood 1.54 0.98
8 Metals 0.12 0.32
9 Glass 3.11 2.46
10 Inerts 8.94 8.07
11
Spec
ial
Was
te
Electronic waste/batteries/Bulbs 0.32 0.63
12 Bio-Medical waste 0.00 0.00
Total 45.01 42.72
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 160
A.3.2. Chemical Characterization
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 161
A.4. DRAWINGS
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 162
A.5. DETAILED ESTIMATION
A.5.1. Detailed Estimation for Collection and Transportation
Sl.
No Particulars Unit
Total
required
Currently
available L W D
Quantity
Required Rate Amount (Rs)
1
Supply of HDPE woven sac of 25 liter capacity for
storage of dry waste at houses and small
commercial shops
no 4155 0 Market
rate 4155 ₹ 17.00 ₹ 70,635.00
2 Supply of containers of 20 liter capacity for storage
of wet wastes at houses and shops no 8310 0
Market
rate 8310 ₹ 160.00 ₹ 13,29,600.00
3
Supply of Auto tipper of standard makes with four-
stroke engine fuelled by diesel with peak output
level of 9 BHP or more. The vehicle will be with
reverse gear. Diesel fuel 3 wheeler auto tipper
with a tipping container of capacity 1 cum and a
payload of 600 kgs or above. The hopper tipping
using either a mechanical or hydraulic
arrangement. The vehicle shall have factory made
cabin with provision for seating driver plus 1
person. Superior quality paint to ensure long
lasting structure suitable for use for handling raw
garbage under corrosive operations. Color shade
optional from standard colors offered by the
Supplier. Standard tool kit , spare tyre and jack.
The tenderer shall make arrangement for
No 7 5 Market
rate 2 ₹ 5,20,000.00 ₹ 10,40,000.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 163
Sl.
No Particulars Unit
Total
required
Currently
available L W D
Quantity
Required Rate Amount (Rs)
registration of the vehicle. The fees for the
registration shall be reimbursed.
4
Supply of transport vehicle with compactor used
for loading, compacting, transporting and
unloading municipal solid wastes. The equipment
shall be mounted on a reputed Indian chassis and
the compactor would be rugged and durable with
proven performance. The body would be tipping
type and having a hydraulic bin lifting
arrangement. The container would be equipped
with a compacting arrangement to deliver full
power of the engine. Wheel bases over 3600mm,
container with a minimum effective volume of
container of 7 cum. Attachment of a tackle to
handle different dimensions of bins with capacities
of upto 4500 liters. The chassis would be of a
standard make with company built cabin with all
standard fittings and control panel, equivalent to
TATA model LPT; WB-3600mm. The compacting
container shall be of high yield quality steel with
properly reinforced vertical sections provided with
continuous welding to avoid corrosion problem
The compactor would be hydraulically operated to
deliver full power from the engine. The compactor
No 1 0 Market
Rate 1 ₹ 29,00,000.00 ₹ 29,00,000.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 164
Sl.
No Particulars Unit
Total
required
Currently
available L W D
Quantity
Required Rate Amount (Rs)
plates would be sturdy and reinforced to be
capable of delivering the desired pressure with
adequate safety factor. Appropriate hydraulic
unloading mechanism. A drain plug to drain the
leachate and cleaning water shall be provided. The
hydraulic systems shall be direct engine driven
hydraulic pump or through a power take off
delivering full power from the engine with tank
mounted so as to ensure constant oil flow.
Equipped with easily visible level read-out gauge
and replaceable filter cartridge elements.
Necessary safety features to be included. The
cylinder, central valve, pump and hoses shall be of
reputed Indian of foreign make and proven
performance. A control panel will be provided and
located conveniently. All gauges levers and
switches required for operation of the unit shall be
grouped in the control panel. The tyres shall be of
heavy duty steel radials. The painting shall be of
superior quality to ensure long lasting structure
suitable for use for handling raw garbage under
corrosive conditions. Color shade optional from
standard colors offered by the Supplier. Supply
shall include Standard tool kit for each machine,
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 165
Sl.
No Particulars Unit
Total
required
Currently
available L W D
Quantity
Required Rate Amount (Rs)
spare tyre and jack.
5 Supply of GPS tracking system for collection and
transportation and street sweeping vehicles No 10 0
Market
Rate 10 ₹ 15,000.00 ₹ 1,50,000.00
6
Supply of Sound box, mic set and 2 nos. of
advertising board (3ftx4ft) in each vehicle for
collection and transportation and street sweeping
vehicles
No 7 0 Market
Rate 7 ₹ 5,180.00 ₹ 36,260.00
Total ₹ 55,26,495.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 166
A.5.2. Detailed Estimation for Processing Facility – Civil works
Sl No
Particulars Uni
t item
No
L/cum B
D
Quantity Require
d
Rate Amount (Rs) Area
1
KSRB 2-2.2: Earthwork Excavation for foundation for Buildings, water supply, sanitary lines and electrical conduits either in pits or in terches 1.50m and above in widht, in Hard soil not exeeding 1.5m. in depth including dressing the excavated soil clear from edges of excation with lead upto 50m. after breaking of clods complete as per as per specifications.specification. No. KBS 2.1(b) / 2.3.5(SL NO-2.4/PNO-5/SOR2015-2016)
cum
Earth work
24 1.1 1.1 1.1
31.94
266.50
8,513.08
2
KSRB 4-1.3 : Providing and laying in position plain cement concrete of mix 1:4:8 using 40mm and down size graded granite metal, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation and plinth, including cost of all materials, labour, HOM of machinery, curing complete as per specifications.Specification No. KBS 4.1, 4.2 (P-12/SL NO-4.3/SOR-2015-2016)
cum
pcc 24 1.1 1.1 0.1
2.90
5,202.00
15,106.61
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 167
3
KSRB 4.2.8 : Providing and laying in position reinforced cement concrete of mix 1:1.5:3 with 20mm and down size graded granite metal machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for R.C.C. beams, columns of all sizes in foundation plinth and superstructure ground floor level for roof slabs, staircase, lintles, columns, including cost of all materials, labour, HOM of machinery, curing, complete as per specifications.Specification No. KBS 4.1, 4.6(SL NO-4.13/PG NO-14/SOR-2015-2016)
cum
footing
24 0.32
7.68
6,510.00
49,996.80
column
24 0.9 0.45
0.45
4.37
6,510.00
28,474.74
4
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking, placing in position, lapping and I or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery complete as per specifications. Specification No. KBS 4.6.3 (SL NO-4.46.2/PG NO-19/SOR-2015-2016)(@80kg/cum)
t
footing
7.68 _ _
0.61
59,614.00
57,486.97
column
4.37 _ _
0.35
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 168
5
KSRB 4-6.7 :Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for sides and soffits of beams, beam haunchings, cantilever girders, bressumers and lintels not exceeding 1 m in depth including cost of all materials, labour complete as per specificaitons. Specification No. KBS 4.6.2 (SL NO-4.34/PG NO-16/SOR-2015-2016)
sqm
footing
24 0.8 _ _
19.20
217.00
4,166.40
column
24 1.62 _ _
38.88
217.00
8,436.96
6
Preparation and Surface treatment of formation by removing mud and slurry, watering to the extent needed to mainatain the desired moisture content, trimmng to reuired grade line, grade profile and rolling with 8-10 tons smooth sheeted roller complete as per specification. KSRRB M 300-39 (SL NO-19.45/PG NO-150/SOR-2015-2016)
sqm
platform
1 30 20 _
600.00
1.35
810.00
7
KSRRB 400-2 Providing,laying,spreading and compacting specified graded,gravel or any other course material 60% and crushed stone aggregates of granite/trap/basalt 40% in sub base course,close grading-1 including premixing the material at OMC in mechanical mixer,carriage of mixed material,spreading in uniform layers with motor grader on a prepared base and
cum
platform
1 30 20 0.1
60.00
1,716.00
1,02,960.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 169
compacting with power roller to achive the desired density including all materials,labour,HOM of machinery,lighting,guarding,barricading and maintenance of diversion.as per specifications.(SL NO-20.2/PG NO-159/SOR-2015-2016)
8
Providing, laying, spreading and compacting stone aggregates of specific sizes to Water Bound Macadam specification including spreading in uniform thickness, hand packing, rolling with power roller 8-10 tonnes in stages to proper grade and camber applying and brooming hard aggregates, screening materials followed by approved binding material to fill up the interstices of coarse aggregates, watering and rolling making necessary earthen bund to protect edges, lighting, guarding, barricading and maintenance of diversion road including cost of all materials, lead for metal upto 5 km loading, unloading, stacking, spreading labour charges of machinery's watering charges etc., complete. KSRRB M400-14.1 (SL NO-20.14.1/PG NO-162/SOR-2015-2016)
cum
platform
1 30 20 0.1
60.00
3,126.00
1,87,560.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 170
9
KSRB 4-1.2 : Providing and laying in position plain cement concrete of mix 1:3:6 using 40mm and down size graded granite metal, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation and plinth, including cost of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2 (PG NO-12/SL NO-4.2/2015-2016)
cum
platform
1 30 20 0.1
60.00
5,452.00
3,27,120.00
10
Providing and fixing pre engineered building for the composting recycling and waste segregation area including the necessary structural member(truss consisting of ISA ISLC,insert plate,cleat angle,other necessary structural member,side closer upto 1m aboveGL with door/window openings including skylight and turbo ventilator )including shop painting and two coats of anti-corrosive paint.Provide galvanised sheet for the roofing and walls including gutters and downtake pipes.The cost
sqm
1 50 40.00
_ _
2,000.00
3,750.00
75,00,000.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 171
includes all materials,transportation,all taxes fixing and all of lifts.(market rate)
11 Providing and fixing wind operated turbine exhaust fan on the slopping roof.
no 20 - - - - 20
9,500.00
1,90,000.00
12 Supply of electrical connections
2,62,287.57
Total Amount
87,42,919.13
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 172
A.5.3. Detailed Estimation for Processing Facility – Machineries, Tools and Equipments
Sl.
No Particulars Unit
Total
required
Currently
avaiable L W D
Quantity
Required Rate Amount (Rs)
Vehicles required for processing facility
1
Provision of a Loader with standard specification
for processing at landfill site. Fuel-efficient engine
with 4 stroke, 4 cylinder, water cooled diesel
engine, Minimum gross HP rating 90 HP (~67 kW)
at manufacturer’s rated RPM. Either 4-wheel drive
or 2 wheel drive with torque proportioning or
differential lock system. Fully synchromesh
transmission with 4 speeds forward and 4 speeds
reverse. The vehicle shall be with heavy Duty
torque proportioning system for 4 wheel drives or
torque proportioning or differential lock system for
2 wheel drive (rear axle). Front axle shall be
oscillating steer axle, and shall be capable of
serving as a drive axle for 4 wheel drive units. The
vehicle shall have full power hydrostatic steering
system with direct manual steering capabilities.
Self-adjusting, oil immersed, multi-disk,
hydraulically actuated main brakes with
independent left and right brake pedals.
No 1 0 Market
rate 1 ₹ 23,64,000.00 ₹ 23,64,000.00
2
Purchase of high raised trailers to be used for
collection of acceptables and rejects from 100 mm
size. The trailer to be moved by the existing tractor
No 1 0 Market
rate 1 ₹ 2,50,000.00 ₹ 2,50,000.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 173
Sl.
No Particulars Unit
Total
required
Currently
avaiable L W D
Quantity
Required Rate Amount (Rs)
3
Providing 50 HP or above tractor of standard make
with power steering with trailer of 5 cum capacity
and a water tanker of 5000 litre capacity. A pump
for the water tanker shall be provided with power
from the tractor PTO. Market rate
No 1 1 Market
rate 0 ₹ 7,92,998.00 ₹ 0.00
Processing Machineries
1
Complete set of machinery at the segregation at
pre sorting facility consisting of a sieve of 35 mm
holes, feeder with hopper and belt conveyor for
loading, accept and reject conveyors. The passing
material segregation line conveyor to be a
minimum of 5 m length of slow speed to enable
further segregation of useful components with a
capacity to Process 20 TPD of waste
Set 1 0 Market
rate 1
₹ 67,00,000.00 ₹ 67,00,000.00
2
Complete set of machinery at the segregation at
preparatory facility consisting combination of sieve
of 16 mm holes, feeder with hopper and belt
conveyor for loading, accept and reject conveyors.
The passing material segregation line conveyor to
be a minimum of 5 m length for 16mm trommel of
slow speed to enable further segregation of useful
components with a capacity to Process 12 TPD of
waste
Set 1 0 Market
rate 1
3 Complete set of machinery at the segregation at Set 1 0 Market 1
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 174
Sl.
No Particulars Unit
Total
required
Currently
avaiable L W D
Quantity
Required Rate Amount (Rs)
finishing facility consisting of a sieve of 4 mm
holes, feeder with hopper and belt conveyor for
loading, accept and reject conveyors. The passing
material segregation line conveyor to be a
minimum of 5 m length of slow speed to enable
further segregation of useful components with a
capacity to Process 6 TPD of waste
rate
Tools and Equipments for Processing Facility
1 Provision of tools, baskets, handsieving screens for
composting facility Set 1 0
Market
rate 1 ₹ 50,000.00 ₹ 50,000.00
2 Bagging tools, weighing machines and basic tools set 2 0 Market
rate 2 ₹ 35,000.00 ₹ 70,000.00
Total ₹ 94,34,000.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 175
A.5.4. Detailed Estimation for Recycling Facility
Sl.
No Particulars Unit
Total
Req.
Currently
available L W D QTY Rate Amount (Rs)
1
Providing a hydraulically operated baling unit complete
with the motor, the hydraulic unit, cyclinders etc and as
directed by the Engineer. Including supply, delivery,
installation and demonstration at site. Market rate.
No 1 0 Market rate 1 ₹ 4,40,000.00 ₹ 4,40,000.00
3
Supply of Recycling bins for storing of recyclables
suitable. The bins shall be made of plastic, mild steel or
galvanized iron with heavy-duty wheels. They shall be of
capacity equal to or more than the defined capacity in
volume and of adequate strength to handle the specified
weights. The lifting handles would be integrated into the
frame and be capable of the taking the loads specified.
The capacity shall be 3000 liters with capacity to handle
3000 kgs of weight. A cover with convenient opening
arrangement shall be provided. If the cover has to be
removed in operation it shall not affect the bin in any
other way. Painting Superior quality to ensure long
lasting structure.
No 5 0 Market Rate 5 ₹ 29,500.00 ₹ 1,47,500.00
Total ₹ 5,87,500.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 176
A.5.5. Detailed Estimation for Leachate Treatment Facility – Planted Gravel Filter
Sl no
Particulars Uni
t Item
No
L B D Quantity Required
Rate Amount (Rs)
1
KSRB 2-1.1: Earthwork Excavation in ordinary soilleveling lowering the ground manually (other than foundation of buildings , culvert,roads drains and trench of pipe lines and cables) and removing the excuvated stuff to a distance not exceddding 50m and lift upto 1.5m, excuvated surface levelled and neatly dressed, disposed earth to be levelled after breaking of clods and neatly dressed as per specification.Specification.No. KBS 2.1 (a)/2.3.1(sl no 2.1/pg no 5/sr 2015-2016)
cum
foundation
1
16.5
16.5
0.6
150.53
148.00
22,277.70
15.3
15
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 177
2
suppling HDPE membrane(liner) of minimum of 1.5mm thick HDPE membrane .A certificate for the thickness shall be provided .The lowest indiviual thickness shall not be less than 90% of the specified thickness.The minimum sheet density should be .94g/cc measyred as per ASTM D1055.Yeild Tensile strength shall be greater than 115 N/cm,break elongation>250%as per IS1969 (1985).The carbon black content should be between 2-3% with dispersion cat 1 or 2 as per ASTM D 5596.The cost of the liner including material ,labour for laying,cutting,jointin,etc.,complete,transportation and taxes as applicable shall be quoted by the bidder.The whole procedure of work shall be done as per the standard specifications and procedures given in section 4 of this document,laid by the pollution control board and as directed by the Engineer.This item shall be measured and paid in m2 of the finished area : Market rate
sqm
base 1 19 15 _
285.00
398.00
1,13,430.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 178
3
Providing and laying 40mm size graded coarse aggregates /pebble stones (For filter bed)as per drawing, specifications with all leads and lifts complete etc.,as directed by the Engineer.The rate includes cost of material, transportion, laying and compacting with all labour etc., (For drainage layers) : (Code No.0750,addition of 20% from the actual rate to include cost of all material, transport, labour and carriage etc.,
cum
Side 2 15 0.75
0.85
19.13
2,184.00
41,769.00
4
Providing and laying 40mm size graded coarse aggregates /pebble stones (For filter bed)as per drawing, specifications with all leads and lifts complete etc.,as directed by the Engineer.The rate includes cost of material, transportion, laying and compacting with all labour etc., (For drainage layers) : (Code No.0750,addition of 20% from the actual rate to include cost of all material, transport, labour and carriage etc.,
cum
base 1 14 15 0.2
42.00
2,184.00
91,728.00
5
Providing and laying 20mm size graded coarse aggregates /pebble stones (For filter bed)as per drawing, specifications with all leads and lifts complete etc.,as directed by the Engineer.The rate includes cost of material, transportion, laying and compacting with all labour etc., (For drainage layers) : (Code No.0749,addition of 20% from the actual rate to include cost of all material, transport,
cum
base 1 14.4
15 0.2
43.20
2,340.00
1,01,088.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 179
labour and carriage etc.,
6
KSRRB M600-1. Construction of dry lean cement concrete mix CC 1:5:10 with OPC cement @160Kgs,with 25mm and down size graded granite metal coarse aggregate at 0.86cum and fine [email protected] Sub-base over a prepared sub-grade with(course and fine aggregate confirming to IS:383)aggregate cement ratio not to exceed 15:1.Aggregate gradation after blending to be as per TAble 600-1,cement content not to be less than 160kg/cum,optimum moisture content to be determined ,concrete strength not to be less than 10Mpa at 7days finishing and curing complete as per specifications No 601(SL NO-22.1/PG NO-181/SOR-2015-2016)
cum
around 1 67 1 0.15
10.05
4,385.00
44,069.25
7
KSRB M300-8.1.Planting and Maintaining of flowering plants and shrubs-A)Planting flowering plants and shrubs in central verge MORTH Specification No.307(SL NO-19.86/PG NO-155/SOR-2015-2016)
m plants 15 15 _ _
225.00
17.00
3,825.00
8
Providing & fixing Chorinated poly venyl chloride(CPVC) pipes for inlet and outlet arrangements conforming to IS 15778,having thermal stability for hot and cold water supply including all CPVC plain and brass threaded fittings including fixing the pipe with clamp at 1.0mtr spacing.This includes jointing
m 3 14
42.00
440.00
18,480.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 180
of pipes and fittings with one step CPVC solvent cement and testing of joint complete.s(SL NO-13.85.6/PNO-69/SOR2015-2016)
Total Amount
4,36,666.95
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 181
A.5.6. Detailed Estimation for Leachate Collection Tank – Windrow Pad
Sl no Particulars Unit Item No L B D
Quantity Required
Rate Amount (Rs)
1
KSRB 2-2.2: Earthwork Excavation for foundation for Buildings, water supply, sanitary lines and electrical conduits either in pits or in terches 1.50m and above in widht, in Hard soil not exeeding 1.5m. in depth including dressing the excavated soil clear from edges of excation with lead upto 50m. after breaking of clods complete as per as per specifications.specification. No. KBS 2.1(b) / 2.3.5(SL NO-2.4/PNO-5/SOR2015-2016)
cum foundation 1.00 2.60 2.10 1.25 6.83 266.50 1,818.86
2
KSRB 4-1.3 : Providing and laying in position plain cement concrete of mix 1:4:8 using 40mm and down size graded granite metal, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation and plinth, including cost of all materials, labour, HOM of machinery, curing complete as per specifications.Specification
cum PCC base 1.00 2.60 2.10 0.10 0.55 5,202.00 2,840.29
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 182
No. KBS 4.1, 4.2 (P-12/SL NO-4.3/SOR-2015-2016)
3
KSRB 14.7-3: Providing ang laying flooring 40mm thick,with an under layer of 30mm thick M-15 cement concrete,using broken granite metal of 12.5mm nominal size and top layer of 10mm thick plaster with cement mortar 1:3,finished with floating coat of neat cement,including cost of materials,labour,curing,complete as per specifications.specificationNo.KBS 14.3(P-105/SL NO-14.10/SOR-2015-2016)
sqm flooring 1.00 2.00 1.50 _ 3.00 517.00 1,551.00
4
KSRB 5-14 : Providing and constructing precast concrete solid blocks with compressive strength not less than 35 Kg/sqm with cement mortar 1:4 masonry (quoin, Jamb, closer blocks ) with solid concrete blocks of size 40x20x20cms conforming to I.S: 2185/1965 in superstructure incuding cost of materials, labour charges, scaffolding, curing complete as per specifications.(SL NO-5.27/PNO-27/SOR2015-2016)
sqm walls 1.00 7.80 _ 1.00 7.80 854.50 6,665.10
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 183
5
KSRB15.3.6 : Providing 15mm thick cement plaster in single coat with cement mortar 1:6 to brick masonry including rounding off corners wherever required smooth rendering, : Providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications.(SL NO-15.14/PNO-116/SOR2015-2016)
sqm inside 1.00 7.00 1.00 7.00 153.00 1,071.00
6
Extra for water proofing the inside surface of tanks (OHT&UGT) applying of modified polymers soft acrylic esters coat @0.4kg/sqm in 2 coats including all labour charges tools andequipments,all complete as per the specifications.(SL NO-10.5.3/PNO-70/SOR2015-2016)
sqm
walls 1.00 7.00 _ 1.00 7.00 285.00 1,995.00
flooring 1.00 2.00 1.50 _ 3.00 285.00 855.00
7
KSRB 4.2.8 : Providing and laying in position reinforced cement concrete of mix 1:1.5:3 with 20mm and down size graded granite metal machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for R.C.C. beams, columns of all sizes in foundation plinth and superstructure ground floor level
cum Conc slab 1.00 2.40 1.90 0.15 0.68 6,510.00 4,452.84
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 184
for roof slabs, staircase, lintles, columns, including cost of all materials, labour, HOM of machinery, curing, complete as per specifications.Specification No. KBS 4.1, 4.6(SL NO-4.13/PNO-14/SOR2015-2016)
8
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking, placing in position, lapping and I or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery complete as per specifications. Specification (@80kg/m3) (PG NO-19/SL NO- 4.46.2/SOR2015-2016 )
Tonne slab 0.68 80.00kg/m3 0.05 59,614.00 3,262.08
9
KSRB2.3: Filling available excavated earth(excluding rock) in sides of foundations upto plinth in layers not exceeding 20cms.in depth,compacting each deposited layer by ramming after watering
cum around 1.00 9.00 0.10 1.15 1.04 119.50 123.68
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 185
with lead upto 50m. Including cost of all labour complete as per specification No:KBS 2.9(SL NO-2.10/PG NO-6/SOR-2015-2016)
10
Providing & Laying Perforated HDPE Pipes of 110 mm OD, of Grade PE 80, 10 Kg/M2, connected to planted gravel filter as per details, with proper fusion & slope, suitably placed in the soil, for Leachate conveying. Including excavation, proper base supports, backfilling etc complete.(Market rate)
Rm 1 12 12.00 452.00 5,424.00
Total Amount 30,058.86
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 186
A.5.7. Detailed Estimation for Sanitary Landfill Facility
Sl no
Particulars Unit No L B
D Quantity Required
Rate Amount (Rs)
Area
1 Site Clearance including carting of waste from existing site
Cum 1 43 37 0.3
477.30 90.00
42,957.00
2
KSRB 2-1.1: Earthwork Excavation in ordinary soilleveling lowering the ground manually (other than foundation of buildings , culvert,roads drains and trench of pipe lines and cables) and removing the excuvated stuff to a distance not exceddding 50m and lift upto 1.5m, excuvated surface levelled and neatly dressed, disposed earth to be levelled after breaking of clods and neatly dressed as per specification.Specification.No. KBS 2.1 (a)/2.3.1(sl no 2.1/pg no 5/sr 2015-2016)
cum 1
40 34
3
3,468.00 148.00
5,13,264.00
34 28
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 187
3
Supply & install Geo-synthetic Clay Liner laying, anchoring in trench, seaming, testing complete as given in General Specification complete to form an impervious barrier. Minimum width of the Liner shall be 4.9M. GCL must be anchored within anchor trench including excavation of trench and backfilling, compaction complete at bottom portion. Rate to include the necessary lap for jointing, wastage, and testing including bentonite powder at joints etc. complete. Measurement will be made as per finished surface area. GCL in the anchor trench will be taken in measurement.(Market rate)
sqm 1 44.5 38.5 _
1,713.25 347.00
5,94,497.75
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 188
5
Supply & installation of 1.5mm Thick. HDPE Smooth Geo-membrane Liner by Blown/Flat die cast process as per list of companies approved in the detail specifications, laying, anchoring in trench, seaming, testing complete as given per Specifications, complete to form an impervious barrier . Minimum width of the Liner shall be 5M. Geo-membrane must be anchored within anchor trench including excavation of trench and backfilling, compaction complete, at bottom portion. Rate to include the necessary lap for jointing, wastage, testing and extrusion rods complete. Measurement will be made as per finished surface area. Liner in the anchor trench will be taken in measurement.(Market rate)
sqm 1 44.5 38.5 _
1,713.25 398.00
6,81,873.50
7
Providing Sand Bedding for Drainage Layer including watering and consolidation etc., with all lead and lift, including cost of all material, transport, labour and carriage etc., complete as per specification and as directed by
cum 1 34.9 28.9 0.3
302.58 1,620.00
4,90,184.46
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 189
the Engineer : SR 15-16 code 0334, addition of 20% from the actual rate to include cost of all material, transport, labour and carriage etc.,
8
Providing and laying 20mm to 25mm size graded coarse aggregates /pebble stones (For filter bed)as per drawing, specifications with all leads and lifts complete etc.,as directed by the Engineer.The rate includes cost of material, transportion, laying and compacting with all labour etc., (For drainage layers) : SR 15-16 code 0749 (Code No.0749,addition of 20% from the actual rate to include cost of all material, transport, labour and carriage etc.,
cum 1 34.3 28.3 0.3
291.21 2,340.00
6,81,424.38
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 190
9
Supply & installation of Non-woven Geotextile (GT) of 350g/M2 made of Polypropylene of TC Mirafi (USA) / Polyfelt (Austria) / Synthetic Industries (USA) / Amoco Fabrics (USA) make or from its regional offices, as per details given in Specifications, spreading on the sand layer or Geomembrane, without damaging the Geotextile or Geomembrane. The Geotextile must be placed along the slope from bottom with an overlap of minimum 100mm. It should be stitched with HDPE thread. Geotextile must be anchored within anchor trench including excavation of trench and backfilling, compaction complete, at top and bottom portion.(Market rate)
sqm 1 34.6 28.6 _
989.56 80.00
79,164.80
11
Providing & Laying Perforated HDPE Pipes of 110 mm OD, of Grade PE 80, 10 Kg/M2, as per details, with proper fusion & slope, suitably placed in the sand layer for Leachate collection. (Market rate)
Rm 1 _ _
254.00 452.00
1,14,808.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 191
12
Providing & Laying Perforated HDPE Pipes of 160 mm OD, of Grade PE 80, 10 Kg/M2, as per details, with proper fusion & slope, suitably placed in the soil, for Leachate conveying. Including excavation, proper base supports, backfilling etc complete.(Market rate)
Rm 1 44
44.00 998.00
43,912.00
Amount
32,42,085.89
Drain
SL NO
Particulars Unit No L B D Quantity Required
Rate Amount (Rs)
1
KSRB 2-2.2: Earthwork Excavation for foundation for Buildings, water supply, sanitary lines and electrical conduits either in pits or in terches 1.50mand above in widht, in Hard soil not exeeding 1.5m. in depth including dressing the excavated soil clear from edges of excation with lead upto 50m. after breaking of clods complete as per as per specifications.specification. No. KBS 2.1(b) / 2.3.5(SL NO-2.4/PNO-5/SOR2015-2016)
cum 1 157.
8 0.85 0.8 107.304 266.5 28596.52
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 192
2
KSRB 4-1.3 : Providing and laying in position plain cement concrete of mix 1:3:6 using 40mm and down size graded granite metal, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation and plinth, including cost of all materials, labour, HOM of machinery, curing complete as per specifications.KBS 4.1,4.2 (P-12/I-4.3/SOR2015-2016 )
cum 1 157.
8 0.85 0.1 13.413 5202 69774.43
3
KSRB 4.2.2: Providing and laying in position reinforced cement concrete of design Mix M20 with OPC cement @320 kgs, with 20mm and down size graded granite metal coarse aggregates @0.69cum and fine aggregates @0.460cum, with super plasticisers @ 3 liters confirming to IS9103-1999 reafirmed-2008, machine mixed, concrete laid in layers not exceeding 15cms thick, vibrated for all works in foundation including cost for all materials, labours, HOM machinery, curing, complete but excluding cost of reinforcement as per specification.KBS 4.1,4.6
cum 1 157.
8 0.1
1.85
29.193 6372 186017.80
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 193
(P-13/I-4.11/SOR2015-2016 )
4
KSRB 4.9.1: Providing mild steel reinforcement for RCC work including straightening,cutting,bending,hooking,placing in position,lapping and/or welding wherever required,tying with binding wire and anchoring to the adjoining members whever necessary complete as per design cost of materials,labour,HOM of machinery complete as per specification.Specification No.4.6.3 (@40kg/m3) (P-18/I-4.45/SOR2015-2016 )
q 29.193
_ _ 11.6772 5622 65649.22
5
KSRB 4-6.7 :Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for sides and soffits of beams, beam haunchings, cantilever girders, bressumers and lintels not exceeding 1 m in depth including cost of all materials, labour complete as per specificaitons. Specification No. KBS 4.6.2 (PG NO-16/SL NO-4.34/SOR-2015-2016)
sqm 4 157.
8 _ 0.7 441.84 217 95879.28
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 194
Total
Amount ₹ 4,45,917.24
Leachate collection tank(3x3x2m)
Sl no
Particulars Unit Item No L B D
QuantityRequired
Rate Amount (Rs)
1
KSRB 2-2.2: Earthwork Excavation for foundation for Buildings, water supply, sanitary lines and electrical conduits either in pits or in terches 1.50mand above in widht, in Hard soil not exeeding 1.5m. in depth including dressing the excavated soil clear from edges of excation with lead upto 50m. after breaking of clods complete as per as per specifications. specification. No. KBS 2.1(b) / 2.3.5(SL NO-2.4/PNO-5/SOR2015-2016)
cum foundat
ion 1 3.6 3.6
2.25
29.16
266.50
7,771.14
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 195
2
KSRB 4-1.3 : Providing and laying in position plain cement concrete of mix 1:4:8 using 40mm and down size graded granite metal, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation and plinth, including cost of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2 (P-12/SL NO-4.3/SOR-2015-2016)
cum PCC base
1 3.6 3.6
0.10 1.30
5,202.00
6,741.79
3
KSRB 14.7-3: Providing ang laying flooring 40mm thick,with an under layer of 30mm thick M-15 cement concrete,using broken granite metal of 12.5mm nominal size and top layer of 10mm thick plaster with cement mortar 1:3,finished with floating coat of neat cement,including cost of materials,labour,curing,complete asperspecifications.specificationNo.KBS 14.3(P-105/SL NO-14.10/SOR-2015-2016)
sqm flooring 1 3 3 _ 9.00
509.00
4,581.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 196
4
KSRB 5-14: Providing and constructing precast concrete solid blocks with compressive strength not less than 35 Kg/sqm with cement mortar 1:4 masonry (quoin, Jamb, closer blocks) with solid concrete blocks of size 40x20x20cms conforming to I.S: 2185/1965 in superstructure incuding cost of materials, labour charges, scaffolding, curing complete as per specifications. (SL NO-5.27/PNO-27/SOR2015-2016)
sqm
LW 2 3.4 _
2.00 13.60
854.50
11,621.20
SW 2 3 _ 2.00
12.00 854.50
10,254.00
5
KSRB15.3.6: Providing 15mm thick cement plaster in single coat with cement mortar 1:6 to brick masonry including rounding off corners wherever required smooth rendering,: Providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications.(SL NO-15.14/PNO-116/SOR2015-2016)
sqm inside 1 12 _ 2.00
24.00 167.00
4,008.00
6 Extra for water proofing the inside surface of tanks (OHT&UGT) applying of modified
sqm walls 1 12 _
2.00 24.00
285.00
9,405.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 197
polymers soft acrylic esters coat @0.4kg/sqm in 2 coats including all labour charges tools andequipments,all complete as per the specifications. (SL NO-10.5.3/PNO-70/SOR2015-2016)
flooring 1 3 3 _ 9.00
7
KSRB 4.2.8 : Providing and laying in position reinforced cement concrete of mix 1:1.5:3 with 20mm and down size graded granite metal machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for R.C.C. beams, columns of all sizes in foundation plinth and superstructure ground floor level for roof slabs, staircase, lintles, columns, including cost of all materials, labour, HOM of machinery, curing, complete as per specifications.Specification No. KBS 4.1, 4.6(SL NO-4.13/PNO-14/SOR2015-2016)
cum Conc slab
1 3.4 3.4
0.15 1.73
6,510.00
11,288.34
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 198
8
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking, placing in position, lapping and tying with binding wire and anchoring to the adjoining members (laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery complete as per specifications. Specification (@80kg/m3) (PG NO-19/SL NO- 4.46.2/SOR2015-2016 )
Tonne
slab 1
1.73 _ _ 0.14
59,614.00
8,269.65
9
KSRB2.3: Filling available excavated earth(excluding rock) in sides of foundations upto plinth in layers not exceeding 20cms.in depth,compacting ramming after watering with lead upto 50m. Including cost of all labour complete as per specifications.specification No:KBS 2.9(SL NO-2.10/PG NO-6/SOR-2015-2016)
cum backfill 1 14 0.1
2.15 3.01
117.50
353.68
Total Amount 74,293.80
Total Amount of SLF1
37,62,296.93
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 199
A.5.8. Detailed Estimation for Common Facility – Office building cum Weigh Bridge Room
SNo
Particulars Unit Item No L B
D
QuantityRequired
Rate Amount
(Rs) AREA
1
KSRB 2-2.2: Earthwork Excavation for foundation for Buildings, water supply, sanitary lines and electrical conduits either in pits or in terches 1.50mand above in widht, in Hard soil not exeeding 1.5m. in depth including dressing the excavated soil clear from edges of excation with lead upto 50m. after breaking of clods complete as per as per specifications. specification. No. KBS 2.1(b) / 2.3.5(SL NO-2.4/PNO-5/SOR2015-2016)
cum Earth Work
1 15.39 0.80 0.75 9.23 266.50 2460.86
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 200
2
KSRB 4-1.3 : Providing and laying in position plain cement concrete of mix 1:4:8 using 40mm and down size graded granite metal, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation and plinth, including cost of all materials, labour, HOM of machinery, curing complete as per specifications.Specification No. KBS 4.1, 4.2 (P-12/SL NO-4.3/SOR-2015-2016)
cum pcc 1 15.39 0.80 0.15 1.85 5202.00 9607.05
3
KSRB 5.3-3: Providing and constructing granite/trap / basalt size stone masonry in basement with cement mortar 1:6, edges of stones chistle dressed in courses not less than 15 cms high, bond stones at two m. apart in each course including cost of materials, labour, curing complete as per specifications. Specification No KBS 5.1.13 (PG NO-23/SL NO-5.9/SOR -2015-2016)
cum step 1 1 15.39 0.60 0.60 5.54
cum step 2 1 15.39 0.45 0.35 2.42
Total Qty 7.96 5486.00 43692.29
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 201
4
KSRB 4.2.8 : Providing and laying in position reinforced cement concrete of mix 1:1.5:3 with 20mm and down size graded granite metal machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for R.C.C. beams, columns of all sizes in foundation plinth and superstructure ground floor level for roof slabs, staircase, lintles, columns, including cost of all materials, labour, HOM of machinery, curing, complete as per specifications. KBS 4.1, 4.6(SL NO-4.13/PG NO-14/SOR-2015-2016)
cum
roof 1 11.10 0.15 1.67
lintel 1 15.39 0.23 0.15 0.53
plinth 1 15.39 0.45 0.10 0.69
Total Qty 2.89 6510.00 18804.17
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 202
5
KSRB 4-6.2 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for flat surface such as suspended floors, roofs, landings, balconies and likes, thickness upto 200 mm including cost of all materials, labour complete as per specificaitons.up to 3.5m from ground level, Specification No. KBS 4.6.2,(SL NO-4.18/PG NO-15/SOR-2015-2016)
sqm roof 1 11.10 _ 11.10 266.50 2958.15
6
KSRB 4-6.7 :Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for sides and soffits of beams, beam haunchings, cantilever girders, bressumers and lintels not exceeding 1 m in depth including cost of all materials, labour complete as per specificaitons. Specification No. KBS 4.6.2 (PG NO-19/SL NO-4.34/SOR-2015-2016)
sqm lintel 2 15.39 _ 0.15 4.62 217.00 1001.89
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 203
7
KSRB 4.2.10: Providing and laying in position reinforced cement concrete of mix 1:1.5:3 (M20) with 12mm and down size graded granite metal, machine mixed, well compacted for plain chajja of 7.5 cms. average thickness, upto ground floor level, including cost of all materials, labour, HOM of machinery, finishing, curing, complete as per specifications. Specification No. KBS 4.1,4.6 (PG NO-14/SL NO-4.19/SOR-2015-2016)
sqm chajja
2 1.40 0.60 _ 1.68
1 2.50 0.60 _ 1.50
Total QTY 3.18 483.00 1535.94
8
KSRB 4-6.10 :Providing and removing centering, shuttering, strutting, propping etc., forchajjas, corbels etc., including edges including cost of all materials, labourcomplete as per specificaiton. Specification No. KBS 4.6.2 (PG NO-16/SL NO-4.37/SOR-2015-2016)
sqm chajja
2 1.40 0.60 _ 1.68
1 2.50 0.60 _ 1.50
Total QTY 3.18 233.00 740.94
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 204
9
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking, placing in position, lapping and I or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery complete as per specifications. Specification No. KBS 4.6.3 (PG NO-18/SL NO-4.46.3)
kgs
roof (1/100)*1.67*7850 131.10
lintel (1/100)*0.53*7850 41.61
chajja (1/100)*0.318*7850 24.96
Total QTY 197.67 59.61
11,783.90
10
KSRB 6-1.2: Providing and constructing burnt brick masonry with approved qualiity of non-modular brick of standard size of 3.5N/mm2 with cement mortar 1:8 including cost of materials labours, charges as per specification No.KBS 6.2 Specification No. KBS 6.2(SL NO-6.2/PG NO-29/SOR-2015-2016)
cum
Parapet 1.00
14.10
0.12 0.45 0.73
wall 1.00
14.10
0.23 3.00 9.73
deductions
door 1.00
0.90
0.23 2.10 0.43
door1 1.00
0.75
0.23 2.10 0.36
window 3.00
1.20
0.23 1.20 0.99
ventilator
1 0.9 0.23 0.6 0.12
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 205
lintel 1.00
14.10
0.23 0.15 0.49
Total Qty 8.06 5,475.00
44,114.68
11
KSRB15-3-13 : Providing 12mm thick cement plaster in single coat with cement mortar 1:3, to ceiling including rounding off corners wherever required smooth rendering, : Providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications. (PG NO-117/SL NO-15.21/SOR-2015-2016)
sqm celling 1.00
11.10 _ 11.10 180.00
1,998.00
12
KSRB15-3.6 : Providing 15mm thick cement plaster in single coat with cement mortar 1:6 to brick masonry including rounding off corners wherever required smooth rendering, : Providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications. .(SL NO-15.14/PG NO-116/SOR-2015-2016)
sqm
wall inside
1.00
13.18
_ 3.00 39.54
wall out side
1.00
15.02
_ 3.15 47.31
parapet 1.00
14.10
_ 1.13 15.93
deduction
door 1.00
0.90
_ 2.10 1.89
door1 1.00
0.75
_ 2.10 1.58
window 3 1.2 _ 1.2 4.32
ventilator
1 0.9 _ 0.6 0.54
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 206
Total Qty 94.46 153.00
14,452.53
13
KSRB 4-1.1 : Providing and laying in position plain cement concrete of mix 1:2:4 using 40mm and down size graded granite metal, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation and plinth, including cost of all materials, labour, HOM of machinery, curing complete as per specifications.Specification No. KBS 4.1, 4.2 (PG NO-12/SL NO-4.1 /SOR-2015-2016)
cum floring 1 11.10 0.1 1.11 5,610.00
6,227.10
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 207
14
KSRB 14.7-2 : Providing and laying red oxide flooring 40 mm thick, with an under layer of 30mm thick 1:2:4 cement concrete, using broken granite metal of 12.5mm nominal size and top layer of 10mm thick plaster with 1:3 cement mortar mixed with red oxide ( using 3.5 kg of red oxide per 50 kg of cement ) finished with floating coat of neat cement mixed with red oxide ( mix of same proportion ) , including cost of materials, labour, curing, complete as per specifications. Specification No. KBS 14.3(SL NO-14.9/PG NO-105/SOR-2015-2016)
sqm floring 1 11.10 _ 11.10 578.00
6,415.80
15
KSRB 15-14.1 : Providing and applying two coats with oil bound washable distemper of approved brand and shade on wall surface including priming coat with distemper primer after throughly brooming the surface free from mortar drops and other foreign matter
sqm
celling 1 11.10 _ 11.10
wall inside
1 13.18 _ 3 39.54
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 208
including preparing the surface even and sand paper smooth, cost of materials, labour, complete as per specifications.(SL NO-15.49/PG NO-116/SOR-2015-2016)
deduction
door1 1 0.75
_ 2.1 1.58
Total Qty 49.07 67.80
3,326.61
16
KSRB15-16 : Providing and finishing external walls in two coats with waterproof cement paint of approved brand and shade to give an even shade after throughly brooming the surface to remove all dirt and loose powdered material, free from mortar drops and other foreign matter cost of materials, labour, complete as per specifications.(PG NO-129/SL NO-15.53.1/SOR 2015-2016)
sqm
wall out side
1.00
15.02
_ 3.15 47.31
parapet 1.00
14.10
_ 1.13 15.93
deduction
door 1.00
0.90
_ 2.10 1.89
door1 1.00
0.75
_ 2.10 1.58
window 3 1.2 _ 1.2 4.32
ventilator
1 0.9 _ 0.6 0.54
Total Qty 54.92 56.60
3,108.53
17
KSRB 9.5-3 : Providing and fixing in position fully panelled Matti / Nandi wood shutters for doors, styles and rails of 40mm. thick with bottom and lock rails 180mm wide top rail and styles 100mm wide as per drawing and panels of 25mm
sqm
door 1 0.9 _ 2.1 1.89
door1 1 0.75 _ 2.1 1.58
window 3 1.2 _ 1.2 4.32
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 209
thick including cost of materials, labour, HOM of machineries complete as per specifications. ( excluding cost of fixtures )Specification No. KBS 9.34(SL NO-9.16/PG NO-54/SOR-2015-2016)
ventilator
1 0.9 _ 0.6 0.54
Total Qty 8.33 3,586.00
29853.45
18
KSRB 9.4-3 : Providing Matti / Nandi wood frames of doors and windows,clearystory windows,ventilators and others frames wrought,framed or assambledincluding making plaster groves(excluding cost of cement concrete and side clamps),but including cost of material,labour,HOM of machinary complete as per specifications. Specification No. KBS 9.3.(SL NO-9.12/PG NO-51/SOR-2015-2016)
cum
door 1 6.2 0.1 0.1 0.06
door1 1 5.9 0.1 0.1 0.06
window 3 5 0.1 0.1 0.15
ventilator
1 3.2 0.1 0.1 0.03
Total Qty 0.30 69,410.00
21031.23
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 210
19
KSRB 8.6-8: Providing and fixing on wall surface 2.5 Kg/Sqm HDPE rain down water pipes 110 mm outer dia aaproved make and brand with necessary specials like shoes, bends and offsets fixed with iron clamps, wall plugs screws including cost of materials, labour complete as per specifications. (PG NO-48/SL NO-8.19/SOR-2015-2016)
Rmt 2 3 _ _ 6.00 561.50
3,369.00
20
KSRB 6-1.2: Providing and constructing burnt brick masonry with approved qualiity of non-modular brick of standard size of 3.5N/mm2 with cement mortar 1:8 including cost of materials labours, charges as per specification No.KBS 6.2 No.KBS 6.2 (SL NO-6.2/PG NO-29/SOR-2015-2016)
cum
steps
1 2.1 0.6 0.15 0.189
1 2.1 0.4 0.15 0.126
1 2.1 0.2 0.15 0.063
Total Qty 0.378 5,475.00
2,069.55
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 211
21
KSRB 11-3:Providing and fixing white vitreous china clay,water closet indian type(squatting pan) of size 580mm with footrests,100mm S or P trap,(approved make)cutting and making good the wall and floor wherever required,including cost of materials,labour complete as per specifications. (SL NO-12.3/PG NO-80/SOR-2015-2016)
pan sanitary 1 _ _ _ _ 1,575.00
1,575.00
22
KSRB 13-11.1:Providing and placing on terrace,polyethylene water storage tanks as per IS 12701:1996 with manhole lid and suitable locking arrangements,making holes of suitable diameter for inlet,outlet and over flow pipes,including cost of all materials,labour,transport charges,HOM of equipments and testing complete as per specifications.(for 1000litre capacity) specification No:KBS 13.22 (SL NO-13.78/PG NO-91/SOR-2015-2016)
Nos Water tank
1 8,332.00
8,332.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 212
23 Supply of electrical connections and plumbing works
12,550.46
TOTAL COST 2,51,009.
12
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 213
A.5.9. Detailed Estimation for Common Facility – Two Seater Toilet Block
Sl no Particulars Unit Item No L/cum B D Quantity Required
Rate Amount (Rs)
1
KSRB 2-2.2: Earthwork Excavation for foundation for Buildings, water supply, sanitary lines and electrical conduits either in pits or in terches 1.50m and above in widht, in Hard soil not exeeding 1.5m. in depth including dressing the excavated soil clear from edges of excation with lead upto 50m. after breaking of clods complete as per specification. specification. No. KBS 2.1(b) / 2.3.5(SL NO-2.4/PNO-5/SOR2015-2016)
cum
Main wall 1 9.08 1 0.7 6.356 266.50 1,693.87
partition wall
1 0.97 0.55
0.1 0.05335 266.50 14.22
2
KSRB 4-1.3 : Providing and laying in position plain cement concrete of mix 1:4:8 using 40mm and down size graded granite metal, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation and plinth, including cost of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2 (P-12/SL NO-4.3/SOR-2015-2016)
cum
Main wall 1 9.08 0.8 0.1 0.7264 5,202.00 3,778.73
partition wall
1 1.17 0.45
0.1 0.05265 5,202.00 273.89
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 214
3
KSRB 5.3-3: Providing and constructing granite/trap / basalt size stone masonry in basement with cement mortar 1:6, edges of stones chistle dressed in courses not less than 15 cms high, bond stones at two m. apart in each course including cost of materials, labour, curing complete as per specifications. Specification No KBS 5.1.13 (PG NO-23/SL NO-5.9/SOR -2015-2016)
cum
Main wall 1
9.08 0.6 0.6 3.2688 5,486.00 17,932.64
9.08 0.45
0.35 1.4301 5,486.00 7,845.53
partition wall
1 1.32 0.3 0.35 0.1386 5,486.00 760.36
4
KSRB 6-1.2: Providing and constructing burnt brick masonry with approved qualiity of non-modular brick of standard size of 3.5N/mm2 with cement mortar 1:8 including cost of materials labours, charges as per specification No.KBS 6.2 (SL NO-6.2/PG NO-29/SOR-2015-2016)
cum steps
1 2.1 0.6 0.15 0.189 5,475.00 1,034.78
1 2.1 0.4 0.15 0.126 5,475.00 689.85
1 2.1 0.2 0.15 0.063 5,475.00 344.93
5
KSRB 4-1.6 : Providing and laying in position plain cement concrete of mix 1:2:4 using 20mm and down size graded granite metal, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation and plinth, including cost of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No.KBS
cum
Plinth for main wall
1 9.08 0.45
0.1 0.4086 5,733.00 2,342.50
plinth for partition
wall 1 1.32 0.3 0.1 0.0396 5,733.00 227.03
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 215
4.1,4.2 (SL NO-4.6/PG NO-12/SOR-2015-2016)
6
KSRB 4.2.8 : Providing and laying in position reinforced cement concrete of mix 1:1.5:3 with 20mm and down size graded granite metal machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for R.C.C. beams, columns of all sizes in foundation plinth and superstructure ground floor level for roof slabs, staircase, lintles, columns, including cost of all materials, labour, HOM of machinery, curing, complete as per specifications.Specification (PG NO-14/SL NO-4.13/SOR-2015-2016)
cum
Lintel beam
1 9.08 0.23
0.15 0.31326 6,510.00 2,039.32
Roof slab 1 3 2 0.15 0.9 6,510.00 5,859.00
7
KSRB 4-6.2 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for flat surface such as suspended floors, roofs, landings, balconies and likes, thickness upto 200 mm including cost of all materials, labour complete as per specificaitons. Specification No. KBS 4.6.2(SL NO-4.29.2/PG NO-15/SOR 2015-2016)
sqm Roof slab 1 3 2 - 6 540.00 3,240.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 216
8
KSRB 4-6.7 :Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for sides and soffits of beams, beam haunchings, cantilever girders, bressumers and lintels not exceeding 1 m in depth including cost of all materials, labour complete as per specificaitons. Specification No. KBS 4.6.2 (PG NO-16/SL NO-4.34/SOR-2015-2016)
sqm Lintel for main wall
2 9.08 - 0.15 2.724 217.00 591.11
10
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking, placing in position, lapping and I or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery complete as per specifications. Specification No. KBS 4.6.3 (PG NO-17/SL NO-4.46.3/SOR 2015-2016)(@80.00kg/m3)
t
lintels for main wall
1 0.408
6 32.688 59,614.00 1,948.66
lintels for partion
wall 1
0.0396
3.168 59,614.00 188.86
roof slab 1 0.9 72 59,614.00 4,292.21
11
KSRB 5-14 : Providing and constructing precast concrete solid blocks with compressive strength not less than 35 Kg/sqm with cement
sqm
main wall 1 9.08 2.5 22.7
854.00 20,203.93 parapet 1 9.08 0.45 4.086
partition wall
1 1.54 2.5 3.85
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 217
mortar 1:4 masonry (quoin, Jamb, closer blocks ) with solid concrete blocks of size 40x20x20cms conforming to I.S: 2185/1965 in superstructure incuding cost of materials, labour charges, scaffolding, curing complete as per specifications.(SL NO-5.27/PG NO-27/SOR-2015-2016)
deductions
lintel for main wall
1 9.08 0.15 1.362
lintel for partion
wall 1 1.54 0.9 1.386
door 2 2.1 0.75 3.15
ventilators
2 0.9 0.6 1.08
23.658
12
KSRB15-3-13 : Providing 12mm thick cement plaster in single coat with cement mortar 1:3, to ceiling including rounding off corners wherever required smooth rendering, : Providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications. (PG NO-113/PG NO-15.21/SOR 2015-2016)
sqm 2 1.54 1.2 - 3.696 180.00 665.28
13
KSRB15-3.6 : Providing 15mm thick cement plaster in single coat with cement mortar 1:6 to brick masonry including rounding off corners wherever required smooth rendering, : Providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications.(SL NO-15.14/PG NO-
sqm
Inside wall
153.00 7,613.28
main wall 1 8.168 2.5 - 20.42
partition wall
2 1.54 2.5 - 7.7
Outside wall
main wall 1 10 2.65
- 26.5
Total 54.62
deduction Door 2 2.1 0.9 3.78
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 218
116/SOR-2015-2016) ventilators
2 0.9 0.6 1.08
Total 4.86
49.76
14
KSRB 14.7-2 : Providing and laying red oxide flooring 40 mm thick, with an under layer of 30mm thick 1:2:4 cement concrete, using broken granite metal of 12.5mm nominal size and top layer of 10mm thick plaster with 1:3 cement mortar mixed with red oxide ( using 3.5 kg of red oxide per 50 kg of cement ) finished with floating coat of neat cement mixed with red oxide ( mix of same proportion ) , including cost of materials, labour, curing, complete as per specifications. Specification No. KBS 14.3.(SL NO-14.9/PG NO-105/SOR-2015-2016)
sqm Floor 2 1.54 1.2 - 3.696 578.00 2,136.29
15
KSRB 15-14.1 : Providing and applying two coats with oil bound washabledistemper of approved brand and shade on wall surface including priming coat with distemper primer after throughly brooming the surface free from mortar drops and
sqm
Ceiling 2 1.54 1.2 _ 3.696
67.80 2,467.65
main wall 1 10 2.5 _ 25
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 219
other foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour, complete as per specifications.(SL NO-15.49.1/PG NO-120/SOR-2015-2016)
partition wall
2 1.54 2.5 _ 7.7
Total 36.396
16
KSRB15-16 : Providing and finishing external walls in two coats with waterproof cement paint of approved brand and shade to give an even shade after throughly brooming the surface to remove all dirt and loose powdered material, free from mortar drops and other foreign matter cost of materials, labour, complete as per specifications. (PG NO-121/SL NO-15.53.1/SOR-2015-2016) - do - with primer coat
sqm main wall 1 10 2.65
- 26.5 56.60 1,499.90
17
KSRB 9.5-3 : Providing and fixing in position fully panelled Matti / Nandi wood shutters for doors, styles and rails of 40mm. thick with bottom and lock rails 180mm wide top rail and styles 100mm wide as per drawing and panels of 25mm thick including cost of materials, labour, HOM of machineries complete as per specifications. (excluding cost of fixtures) Specification No. KBS
sqm
door 2 2.1 _ 0.9 3.78 3,586.00 13,555.08
ventilators
2 0.9 _ 0.6 1.08 3,586.00 3,872.88
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 220
9.34.(SL NO-9.16/PG NO-54/SOR-2015-2016)
18
KSRB 9.4-3 : Providing Matti / Nandi wood frames of doors and windows,clearystory windows,ventilators and others frames wrought,framed or assambledincluding making plaster groves(excluding cost of cement concrete and side clamps),but including cost of material,labour,HOM of machinary complete as per specifications. Specification No. KBS 9.3.(SL NO-9.12/PG NO-51/SOR-2015-2016)
sqm
door 2 6.2 0.1 0.1 0.124 69,410.00 8,606.84
ventilators
2 3.2 0.1 0.1 0.064 69,410.00 4,442.24
19
KSRB 11-3:Providing and fixing white vitreous china clay,water closet indian type(squatting pan) of size 580mm with footrests,100mm S or P trap,(approved make)cutting and making good the wall and floor wherever required,including cost of materials,labour complete as per specifications.(SL NO-12.3/PG NO-80/SOR-2015-2016)
pan sanitary 2 _ _ _ 2 1,575.00 3,150.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 221
20
KSRB 13-11.1:Providing and placing on terrace,polyethylene water storage tanks as per IS 12701:1996 with manhole lid and suitable locking arrangements,making holes of suitable diameter for inlet,outlet and over flow pipes,including cost of all materials,labour,transport charges,HOM of equipments and testing complete as per specifications.(for 1000litre capacity) specification No:KBS 13.22 (SL NO-13.78/PG NO-91/SOR-2015-2016)
Nos Water tank
1 _ _ _ 1 8,332.00 8,332.00
21
KSRB 8.6-6: Providing and fixing on wall surface 2.5 Kg/Sqm HDPE rain down water pipes 110 mm outer dia aaproved make and brand with necessary specials like shoes, bends and offsets fixed with iron clamps, wall plugs screws including cost of materials, labour complete as per specifications. (PG NO 47/SL NO-8.17/SOR 2015-2016)
Rmt pipes 2 3 6 472.00 2,832.00
22 Supply of electrical connections and plumbing works
7,077.62
Total Amount ₹ 1,41,552.47
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 222
A.5.10. Detailed Estimation for Common Facility – Septic Tank
Sl No
Particulars Uni
t No L B D
Quantity Required
Rate Amount (Rs)
1
KSRB 2-2.2: Earthwork Excavation for foundation for Buildings, water supply, sanitary lines and electrical conduits either in pits or in terches 1.50mand above in widht, in Hard soil not exeeding 1.5m. in depth including dressing the excavated soil clear from edges of excation with lead upto 50m. after breaking of clods complete as per as per specifications.specification. No. KBS 2.1(b) / 2.3.5(SL NO-2.4/PNO-5/SOR2015-2016)
cum foundation 1 3.11 2.11 2.25 14.76
266.50
3,934.80
2
KSRB 4-1.3 : Providing and laying in position plain cement concrete of mix 1:4:8 using 40mm and down size graded granite metal, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation and plinth, including cost of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2 (P-12/SL NO-
cum PCC 1 3.11 2.11 0.1 0.66
5,202.00
3,413.60
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 223
4.3/SOR-2015-2016)
3
KSRB 14.7-3: Providing ang laying flooring 40mm thick,with an under layer of 30mm thick M-15 cement concrete,using broken granite metal of 12.5mm nominal size and top layer of 10mm thick plaster with cement mortar 1:3,finished with floating coat of neat cement,including cost of materials,labour,curing,complete as per specifications.specificationNo.KBS 14.3Specification No. KBS 14.3(SL NO-14.10/PG NO-105/SOR-2015-2016)
sqm flooring 1 2.5 1.5 3.75
517.00
1,938.75
4
KSRB 5-14 : Providing and constructing precast concrete solid blocks with compressive strength not less than 35 Kg/sqm with cement mortar 1:4 masonry (quoin, Jamb, closer blocks ) with solid concrete blocks of size 40x20x20cms conforming to I.S: 2185/1965 in superstructure incuding cost of materials, labour charges, scaffolding, curing complete as per specifications.Specification No. KBS5.27 (SL NO-5.27/PG NO-
sqm
LW 2 2.96 2 11.84
854.00
10,111.36
SW 3 1.5 2 9.00
854.00
7,686.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 224
27/SOR-2015-2016)
5
KSRB15-3.6: Providing 15mm thick cement plaster in single coat with cement mortar 1:6 to brick masonry including rounding off corners wherever required smooth rendering, : Providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications.(SL NO-15.14/PG NO-116/SOR-2015-2016)
sqm inside 1 8 2 16.00
153.00
2,448.00
6
Extra for water proofing the inside surface of tanks (OHT&UGT) applying of modified polymers soft acrylic esters coat @0.4kg/sqm in 2 coats including all labour charges tools andequipments,all complete as per the specifications(SL NO-10.5.3/PG NO-70/SOR-2015-2016)
sqm
walls 1 8 2 16.00
285.00
5,628.75
flooring 1 2.5 1.5 3.75
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 225
7
KSRB 4.2.8 : Providing and laying in position reinforced cement concrete of mix 1:1.5:3 with 20mm and down size graded granite metal machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for R.C.C. beams, columns of all sizes in foundation plinth and superstructure ground floor level for roof slabs, staircase, lintles, columns, including cost of all materials, labour, HOM of machinery, curing, complete as per specifications.Specification No. KBS 4.1, 4.6 (SL NO-4.13/PG NO-14/SOR-2015-2016)
cum slab 1 2.96 1.96 0.15 0.87
6,510.00
5,665.26
8
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking, placing in position, lapping and I or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery complete as per
t slab 1 0.870
2 69.62
59,614.0
0
4,150.28
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 226
specifications. Specification No. KBS 4.6.3 (PG NO-19/SL NO-4.46/SOR 2015-2016)(@80.00kg/m3)
9
KSRB2.3: Filling available excavated earth(excluding rock) in sides of foundations upto plinth in layers not exceeding 20cms.in depth,compacting each deposited layer by ramming after watering with lead upto 50m. Including cost of all labour complete as per specifications.specification No. KBS 2.9 (PG NO-6/SL NO-2.10/SOR 2015-2016)(@80.00kg/m3)
cum backfill
2 0.075 1.96 2.15 0.63
119.50
189.61
2 0.075 2.96 2.15 0.95
10
KSRB 8.6-6: Providing and fixing on wall surface 2.5 Kg/Sqm HDPE pipes 110 mm outer dia aaproved make and brand with necessary specials like shoes, bends and offsets fixed with iron clamps, wall plugs screws including cost of materials, labour complete as per specifications.for inet,outlet and vent pipe connection (PG NO 47/SL NO-8.17/SOR 2015-2016)
Rmt pipes 2 3 6
472.00
2,832.00
Total Amount
₹ 47,998.42
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 227
A.5.11. Detailed Estimation for Common Facility – Rain Water Harvesting
S no Particulars Unit No Area D Quantity Required
Rate Amount (Rs)
1
KSRB 2-2.2: Earthwork Excavation for foundation for Buildings, water supply, sanitary lines and electrical conduits either in pits or in terches 1.50m and above in widht, in Hard soil not exeeding 1.5m. in depth including dressing the excavated soil clear from edges of excation with lead upto 50m. after breaking of clods complete as per as per specifications.specification. No. KBS 2.1(b) / 2.3.5(SL NO-2.4/PNO-5/SOR2015-2016)
1.00 21.23 1.45 30.78 266.50 8202.41
cum 1 13.20 3.05 40.27 266.50 10732.75
2
KSRB 4-1.3 : Providing and laying in position plain cement concrete of mix 1:4:8 using 40mm and down size graded granite metal, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation and plinth, including cost of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2 (P-12/SL NO-4.3/SOR-2015-2016)
cum 1.00 14.30 0.65 0.15 1.39 5202.00 7252.89
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 228
3
KSRRB 5.2-3:Providing and constructing granite/trap/basalt size stone masonry in foundation with cement mortar 1:6,stone hammerd dressed in courses not less than 20cms high,bond stones at 2m apart in each course including cost of materials,labour,curing complete as per specifications.KBS5.1.13 (PG NO-25/SL NO-5.6/SOR-2015-2016)
cum 1.00 14.30 0.45 1.20 7.72 4483.00 34617.73
4
KSRB 15.1.3: Providing ruled pointing to coursed stone masonry in C.M. 1:3 20mm deep after raking the joints to a depth of 20mm nicely lining including cost of all materials, labour curing etc., complete as per specification.(PG NO-116/ SL NO-15.3/SOR 2015-2016 )
sqm 1.00 13.20 _ 1.20 15.84 91.40 1447.78
5
Providing and laying boulders (For filter bed)as per drawing, specifications with all leads and lifts complete etc.,as directed by the Engineer.The rate includes cost of material, transportion, laying and compacting with all labour etc., (For drainage layers) : (Code No.0039,addition of 20% from the actual rate to include cost of all material, transport, labour and carriage etc.,
cum 1.00 13.20 1.50 19.79 1128.00 22327.38
6
Providing and laying 40mm size graded coarse aggregates /pebble stones (For filter bed)as per drawing, specifications with all leads and lifts complete etc.,as directed by the Engineer.The rate includes cost of material, transportion, laying and compacting with all labour etc., (For
cum 1.00 13.20 0.80 10.56 2184.00 23055.79
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 229
drainage layers) : (Code No.0750,addition of 20% from the actual rate to include cost of all material, transport, labour and carriage etc.,
7
Providing and laying 20mm size graded coarse aggregates /pebble stones (For filter bed)as per drawing, specifications with all leads and lifts complete etc.,as directed by the Engineer.The rate includes cost of material, transportion, laying and compacting with all labour etc., (For drainage layers) : (Code No.0749,addition of 20% from the actual rate to include cost of all material, transport, labour and carriage etc.,
cum 1.00 13.20 0.40 5.28 2340.00 12351.32
8
Providing and laying 12.5mm size graded coarse aggregates /pebble stones (For filter bed)as per drawing, specifications with all leads and lifts complete etc.,as directed by the Engineer.The rate includes cost of material, transportion, laying and compacting with all labour etc., (For drainage layers) : (Code No.0058,addition of 20% from the actual rate to include cost of all material, transport, labour and carriage etc.,
cum 1.00 13.20 0.20 2.64 2316.00 6112.32
9
Providing and laying sand /crushed sand (For filter bed)as per drawing, specifications with all leads and lifts complete etc.,as directed by the Engineer.The rate includes cost of material, transportion, laying and compacting with all labour etc, : (Code No.0731,addition of 20% from the actual rate to include cost of all material, transport, labour and carriage etc.,
cum 1.00 13.20 0.15 1.98 1750.00 3463.91
Total Amount ₹ 1,29,564.26
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 230
A.5.12. Detailed Estimation for Common Facility – Deep Burial Facility
Sl No Particulars Unit No L B D Quantity Required
Rate Amount (Rs)
1
KSRB 2-2.2: Earthwork Excavation for foundation for
Buildings, water supply, sanitary lines and electrical
conduits either in pits or in terches 1.50mand above in
widht, in Hard soil not exeeding 1.5m. in depth
including dressing the excavated soil clear from edges of
excation with lead upto 50m. after breaking of clods
complete as per as per specifications.specification.
specification. No. KBS 2.1(b) / 2.3.5(SL NO-2.4/PNO-
5/SOR2015-2016)
cum 6 5 1.5 1.5 67.5 266.50 17,988.75
2 Spreading a layer of lime for the composting purpose. cum 6 5 1.5 0.02 0.9 4,000.00 3,600.00
Total Amount 21,588.75
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 231
A.5.13. Detailed Estimation for Common Facility – Drain
SL NO
Particulars Unit No L B D Quantity Required
Rate Amount (Rs)
1
KSRB 2-2.2: Earthwork Excavation for foundation
for Buildings, water supply, sanitary lines and
electrical conduits either in pits or in terches
1.50mand above in widht, in Hard soil not
exeeding 1.5m. in depth including dressing the
excavated soil clear from edges of excation with
lead upto 50m. after breaking of clods complete as
per as per specifications.specification. No. KBS
2.1(b) / 2.3.5(SL NO-2.4/PNO-5/SOR2015-2016)
cum 1 426 0.85 0.8 289.68 266.5 77199.72
2
KSRB 4-1.3 : Providing and laying in position plain
cement concrete of mix 1:3:6 using 40mm and
down size graded granite metal, machine mixed,
concrete laid in layers not exceeding 15 cms. thick,
well compacted, in foundation and plinth, including
cost of all materials, labour, HOM of machinery,
curing complete as per specifications.KBS 4.1,4.2
(P-12/I-4.3/SOR2015-2016 )
cum 1 426 0.85 0.1 36.21 5202 188364.42
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 232
3
KSRB 4.2.2: Providing and laying in position
reinforced cement concrete of design Mix M20
with OPC cement @320 kgs, with 20mm and down
size graded granite metal coarse aggregates
@0.69cum and fine aggregates @0.460cum, with
super plasticisers @ 3 liters confirming to IS9103-
1999 reafirmed-2008, machine mixed, concrete
laid in layers not exceeding 15cms thick, vibrated
for all works in foundation including cost for all
materials, labours, HOM machinery, curing,
complete but excluding cost of reinforcement as
per specification.KBS 4.1,4.6 (P-13/I-
4.11/SOR2015-2016 )
cum 1 426 0.1 1.65 70.29 6273 440929.17
4
KSRB 4.9.1: Providing mild steel reinforcement for
RCC work including
straightening,cutting,bending,hooking,placing in
position,lapping and/or welding wherever
required,tying with binding wire and anchoring to
the adjoining members whever necessary complete
as per design cost of materials,labour,HOM of
machinery complete as per
specification.Specification No.4.6.3 (@40kg/m3)
(P-18/I-4.45/SOR2015-2016 )
q 70.29 _ _ 28.116 5622 158068.15
5
KSRB 4-6.7 :Providing and removing centering,
shuttering, strutting, propping etc., and removal
of form work for sides and soffits of beams, beam
sqm 4 426 _ 0.7 1192.8 217 258837.60
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 233
haunchings, cantilever girders, bressumers and
lintels not exceeding 1 m in depth including cost of
all materials, labour complete as per specificaitons.
Specification No. KBS 4.6.2 (PG NO-16/SL NO-
4.34/SOR-2015-2016)
Total
Amount ₹ 11,23,399.06
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 234
A.5.14. Detailed Estimation for Common Facility – Internal Road – 5m wide
Sl No Particulars Unit No L B D Quantity Required
Rate Amount (Rs)
1
KSRRB 200-8. Clearing and grubbing road land
including uprooting rank
vegetation,grass,brush,shrubs,sapling and trees
of girth upto 300mm,by manual means,in area
of light jungle,removal of stumps,disposal of
unserviceable materials,stacking of serviceable
materials labour charges complete as per
specifications.sl no:18.11/pg no:135/Sor:2015-
2016
sqm 1 516 5 _ 2580 6 15480
2
KSRRB M300-9.Execavation for roadway in all
types soil using manual means including loading
in truck for carrying of cut earth to embankment
site complete as per specifications No 301 sl
no:19./pg no:141/Sor:2015-2016
cum 1 516 5 0.15 387 137 53019
3
KSRRB M300-53.construction of embankment
with approved material gravel with all lifts and
leads,transporting to site spreading,grading to
required slope and compacting to meet
requirement complete as per
specifications,including cost of
murrum,watering charges and compaction by
vibratory roller to 95% of proctors density.sl
no:19.60/pg no:147/Sor:2015-2016
cum 1 516 5 0.15 387 564 218268
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 235
4
Providing, laying, spreading and compacting
stone aggregates of specific sizes to Water
Bound Macadam specification including
spreading in uniform thickness, hand packing,
rolling with power roller 8-10 tonnes in stages
to proper grade and camber applying and
brooming hard aggregates, screening materials
followed by approved binding material to fill up
the interstices of coarse aggregates, watering
and rolling making necessary earthen bund to
protect edges, lighting, guarding, barricading
and maintenance of diversion road including
cost of all materials, lead for metal upto 5 km
loading, unloading, stacking, spreading labour
charges of machinery's watering charges etc.,
complete. KSRRB M400-14.1 sl no:20.14.1/pg
no:156/Sor:2015-2016
cum 1 516 5 0.15 387 2106 815022
5
KSRRB 500-11.Providing and laying bituminous
macadam on prepared surface with crushed
coarse aggregates as per design mix formula for
base/binding coarse including loading of
aggregates with F.E loader,hot mixing of stone
aggregate and bitumin in hot mix
plant,transporting and mixed material in tiper to
paver and laying mixed materials with paver
finisher to the required level and grade,rolling
cum 1 516 5 0.1 258 6095 1572510
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 236
by power roller to achieve the desired density
as per specifications. sl no:21.11.1/pg
no:161/Sor:2015-2016
6
KSRRB 500-27.Providing and laying open graded
premix carpet of 20mm thick on prepared
surface in a single course as wearing course
composed of 11.2mm and 13.2mm size stone
aggregates 0.027 cum/sqm premixed with
bituminous binder at 1.46kg/sqm in mini hot
mix plant 6-10 tonne capacity laying manually
and rolling with power roller 8-10
tonne,excluding cost of tack coat,including cost
of all materials,labour,HOM of machineries
complete as per specification clause
No.511/chapter 5 sl no:21.32/pg
no:165/Sor:2015-2016
sqm 1 516 5 _ 2580 134 345720
7
KSRRB M500-39.1 and39.2.Providing and laying
seal coat for sealing the voids on bituminous
surface,laid to the specified levels,grade and
cross fall manually and rolling with power roller
8-10tonne capacity including cost of all
materials,labour,HOM of machinery complete
as per specification No.513 sl no:21.45.1/pg
no:166/Sor:2015-2016
sqm 1 516 5 _ 2580 56 144480
Total Amount ₹ 31,64,499.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 237
A.5.15. Detailed Estimation for Common Facility – Compound wall
S.No. Particulars Unit Iteam No L B D Quantity Required
Rate Amount (Rs)
1
KSRB 2-2.2 Earth work excavation for
foundation of buildings, water supply
sanitary lines and electrical conduits either in
pits or in trenches1.5m and above in width,
in Hard soil not exceeding 1.5m in depth
including dressing the bottom and the sides
of pits and trenches stacking the excavated
soil clear from edges of excavation with lead
up to 50m. after breaking of clods complete
as per specification. specification. No. KBS
2.1(b) / 2.3.5(SL NO-2.4/PNO-5/SOR2015-
2016)
cum cum 1
70.00
0.75
0.75 39.38 266.50 10,493.44
2
KSRB 4-1.3 Providing and laying in position
plain cement concrete of mix M7.5 with OPC
cement @180kgs,(1:4:8) with 40mm and
down size graded granite metal coarse
aggregates @ 0.85cum and fine aggregates
@ 0.57cum machine mixed, concrete laid in
layers not exceeding 15 Cms.thick, well
compacted in foundation and plinth,
including cost of all materials, labour,HOM of
machinery, curing etc., complete as per
specification.(PG No.12/SL No.4.3/SOR
cum cum 1
70.00
0.75
0.15 7.88 5,202.00 40,965.75
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 238
2015-206)
3
KSRB 5.2-3:Providing and constructing
granite or trap or basalt size stone masonry
stones, in foundation cement mortor 1:6
hammer dressed in courses not less than
20cms high with bond stones 2M apart in
each course including cost of materials,
labour, curing complete as per specifications.
(PG NO-25/ SL NO-5.6/SOR 2015 2016)
cum cum 1
70.00
0.60
0.60 25.20 4,483.00 1,12,971.60
4
KSRB 5.3-3:Providing and constructing
granite or trap or basalt size stone masonry
stones, in Basement cement mortor 1:6
hammer dressed in courses not less than
20cms high with bond stones 2M apart in
each course including cost of materials,
labour, curing complete as per specifications.
(PG NO-23/ SL NO-5.9/SOR 2015-2016)
cum cum 1
70.00
0.45
0.45 14.18 5,486.00 77,764.05
5
KSRB 4-1.7:Providing and laying in position
plain cement concrete of mix M10 with OPC
cement @220kgs,(1:3:6) with 20mm and
down size graded granite metal coarse
aggregates @ 0.84cum and fine aggregates
@ 0.56cum machine mixed, concrete laid in
layers not exceeding 15 Cms.thick, well
compacted in foundation and plinth,
including cost of all materials, labour,HOM of
cum
plith 1
70.00
0.45
0.10 3.15
cooping 1
70.00
0.23
0.10 1.61
Add
pillar 24
0.30
0.30
0.10 0.22
deduct
pillar 24
0.30
0.23
0.10 0.17
Total Qty 4.81 5,650.00 27,178.76
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 239
machinery, curing etc., complete as per
specification.(PG No.13 /SL No.4.7 SOR 2015-
2016)
6
KSRB 15.1.3: Providing ruled pointing to
coursed stone masonry in C.M. 1:3 20mm
deep after raking the joints to a depth of
20mm nicely lining including cost of all
materials, labour curing etc., complete as per
specification.(P112 I-15.3 )
sqm Pointing 2
70.00 _
0.45 63.00 91.40 5,758.20
7
KSRB 6-1.2: Providing and constructing burnt
brick masonry with approved qualiity of non-
modular brick of standard size of 3.5N/mm2
with cement mortar 1:8 including cost of
materials labours, charges as per
specification No.KBS 6.2 (SL NO-6.2/PG NO-
29/SOR-2015-2016)
cum Pillar 24
0.30
0.30
2.00 4.32 5,475.00 23,652.00
8
KSRB 6-1.2: Providing and constructing burnt
brick masonry with approved qualiity of non-
modular brick of standard size of 3.5N/mm2
with cement mortar 1:8 including cost of
materials labours, charges as per
specification No.KBS 6.2 (SL NO-6.2/PG NO-
29/SOR-2015-2016)
cum
wall 1
70.00
0.23
2.00 32.20
deduct
pillar 24
0.30
0.23
2.00 3.31
Total Qty 28.89 5,475.00 1,58,161.80
9
KSRB15-3.5:Providing 15mm thick cement
plastering in Single with cement mortar 1:4
to Brick masonry including rounding of all
sqm sides 2
70.00 _
2.00 280.00 172.00 48,160.00
top 1 _ 16.10 172.00 2,769.20
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 240
corners wherever required smooth
rendering, providing and removing and
scaffolding, including cost oll material,
labour, curing etc., complete as per
Specification.(PG No.116/ SL No.15.13/SOR
2015 2016)
70.00 0.23
10
KSRB 15-16.1Providing and finishing external
walls in two coats with waterproof cement
paint of approved brand and shade to give
an even shade after thoroughly brooming
the surface to remove all dirt and loose
powdered material, free from mortar drops
and other foreign matter cost of materials,
labour, complete as per specifications.(PG
No.121/SL No.15.53.1/SOR 2015-2016)
sqm
sides 2
70.00 _
2.00 280.00 56.60 15,848.00
top 1
70.00 _
0.23 16.10 56.60 911.26
11
KSRRB M800-17 Providing and fixing GI
Barbed wire Fencing 1.2m high with 1.8m
angle iron posts 40mmx40mmx6mm placed
every 3m center to center embedded in wall
2 diagonals interwoven with horizontal
wires, fixed with GI staples, turn buckles etc.
complete as per clause 800.7 as per
specification(SL NO-24.21/PNO-
190/SOR2015-2016)
rmt Fencing 1
70.00 _ _ 70.00 248.00 17,360.00
Total Amount ₹ 5,41,994.06
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 241
A.5.16. Detailed Estimation for Common Facility – Weigh Bridge Pit
Sl no Particulars Unit No L B
D Quantity Required
Rate Amount (Rs) Area
1
KSRB 2-1.1: Earthwork Excavation in ordinary
soilleveling lowering the ground manually
(other than foundation of buildings ,
culvert,roads drains and trench of pipe lines
and cables) and removing the excuvated stuff
to a distance not exceddding 50m and lift
upto 1.5m, excuvated surface levelled and
neatly dressed, disposed earth to be levelled
after breaking of clods and neatly dressed as
per specification.Specification.No. KBS 2.1
(a)/2.3.1(sl no 2.1/pg no 5/sr 2015-2016)
CUM 1 10.65 4.65 1.5 74.28 148 10,994.00
2
KSRB 4-1.3 : Providing and laying in position
plain cement concrete of mix 1:4:8 using
40mm and down size graded granite metal,
machine mixed, concrete laid in layers not
exceeding 15 cms. thick, well compacted, in
foundation and plinth, including cost of all
materials, labour, HOM of machinery, curing
complete as per specifications.Specification
No. KBS 4.1, 4.2 (P-12/SL NO-4.3/SOR-2015-
2016)
CUM
2 4.65 2.5 0.1 2.33
2 5.85 0.5 0.1 0.59
1 5.85 3.05 0.1 1.78
Total Qty 4.69 5202 24,419.49
3 KSRB 4.2.8 : Providing and laying in position CUM 2 4.45 2.3 0.4 8.19
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 242
reinforced cement concrete of mix 1:1.5:3
with 20mm and down size graded granite
metal machine mixed, concrete laid in layers
not exceeding 15 cms thick, vibrated for R.C.C.
beams, columns of all sizes in foundation
plinth and superstructure ground floor level
for roof slabs, staircase, lintles, columns,
including cost of all materials, labour, HOM of
machinery, curing, complete as per
specifications. KBS 4.1,
4.6(SL NO-4.13/PG NO-14/SOR-2015-2016)
6 0.6 0.4 0.385 0.55
Total Qty 8.74 6510 56,913.02
4
KSRB 5.3-3: Providing and constructing
granite/trap / basalt size stone masonry in
basement with cement mortar 1:6, edges of
stones chistle dressed in courses not less than
15 cms high, bond stones at two m. apart in
each course including cost of materials,
labour, curing complete as per specifications.
Specification No KBS 5.1.13 (Pg no-23/Sl no-
5.9/Sor-2015-2016)
CUM 1 25.4 0.3 1.03 7.81 5486 42,848.40
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 243
5
KSRB 4.9.2 : Providing T.M.T steel
reinforcement for R.C.C work including
straightening, cutting, bending, hooking,
placing in position, lapping and I or welding
wherever required, tying with binding wire
and anchoring to the adjoining members
wherever necessary complete as per design
(laps, hooks and wastage shall not be
measured and paid) cost of materials, labour,
HOM of machinery complete as per
specifications.
Specification No. KBS 4.6.3 (PG NO-18/SL NO-
4.46.3) (@60kg per cum of concrete)
T 8.74 0.52 59614 31,270.17
Total Amount 1,66,445.08
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 244
A.5.17. Detailed Estimation for Common Facility - Tools and Equipment’s
S.
No. Particulars Unit No. L W D Qty Rate Amount (Rs)
1 Supply of Furniture and Fixtures L.S ₹ 50,000.00
2 Supply of Security LED Light Magnet Wand Baton Nos. 2 Market rate 2 ₹ 450.00 ₹ 900.00
3 Supply of Computer appliance Nos. 1 Market rate 1 ₹ 40,000.00 ₹ 40,000.00
4 Supply of ABC type 9 kg dry fire extinguisher Nos. 5 Market rate 5 ₹ 3,519.00 ₹ 17,595.00
5 Supply, Installation and commissioning of CCTV camera Nos. 4 Market rate 4 ₹ 40,000.00 ₹ 40,000.00
6 Supply, Installation and commissioning of Biometric System No. 1 Market rate 1 ₹ 5,000.00 ₹ 5,000.00
7 Supply and erection of 30 Tons capacity digital, weigh bridge
including designs, excavation, installation and commissioning No 1 Market rate 1 ₹ 5,00,000.00 ₹ 4,94,000.00
Total ₹ 6,47,495.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 245
A.5.17. Detailed Estimation for Awareness Programme and IEC
Sl. No
Particulars Quantity Rate Amount (Rs)
Awareness, IEC and Social Forestry
1
Providing for an awareness campaign to reach about 3788 household, 1807 commercial
establishments and 20 institutions on a door to door basis using Phamplets and
procedure agreed. Market Rate
5,615 ₹ 20.00 ₹ 1,12,300.00
2
Providing for a campaign consisting of awareness days at about 20 schools, educational
institutions and other centres across the city as per forms and procedure agreed with
shown by the Engineer over a period of 3 months and asper directions of the Engineer.
Market Rate.
20 ₹ 4,500.00 ₹ 90,000.00
Total ₹ 2,02,300.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 246
A.5.18. Detailed Estimation for Social Forestry and Crop Demonstration
S. No Particulars Unit No. Quantity Rate Amount (Rs)
Area proposed under crop demonstration sqm 4683
Area proposed under Social Forestry sqm 10371
Plant density under social forestry per 1000 sqm proposed number 200
Total number of plants proposed number 2074.2
1
Planting of selected varieties of tree clumps including the preparation of the pit, supply of the plants from a recognized nursery and planting at required spacing and as per directions of the Engineer taken as a lumpsum based on market rates. The selection of the tree species shall be done the Engineer.
Number 1.00 2074.2 100 ₹ 2,07,420.00
2 Providing the first cropping demonstration of multiple crops in a area of 10000 sq m using the compost produced on site.
sqm 4683 30 ₹ 1,40,490.00
Total ₹ 3,47,910.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 247
A.5.19. Detailed Estimation for Dry Waste Collection Centre
Sl No
Particulars Uni
t item
No
L/cum B D
Quantity Required
Rate Amount (Rs) Area
1
2.24: Earth work for lowering and levelling the ground other than foundation work by mechanical means up tom 3 m depth,including providing shoring and sttuttingg remova of stumps and other deleterious matter, dressing of sides and bottom,filling back the excavation earth to the extent required including the cost of labour and HOM of machineries,as per drawing and techinical specification. (sl no-2.24/pg no :7/sor -2015-2016)
Cum
Site Clearanc
e 1 12
12.00
0.3
43.20
56.70
2,449.44
2
KSRB 2-2.2: Earthwork Excavation for foundation for Buildings, water supply, sanitary lines and electrical conduits either in pits or in terches 1.50m and above in widht, in Hard soil not exeeding 1.5m. in depth including dressing the excavated soil clear from edges of excation with lead upto 50m. after breaking of clods complete as per as per specifications.specification. No. KBS 2.1(b) / 2.3.5(SL NO-2.4/PNO-5/SOR2015-2016)
cum
Earth work
6 1.10 1.10 0.90
6.53
266.50
11,771.24
Earth work for
ssm 11 38.2 0.60 0.15
37.82
Deducion of
column 6 0.45 0.45 0.15
0.18
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 248
3
KSRB 4-1.3 : Providing and laying in position plain cement concrete of mix 1:4:8 using 40mm and down size graded granite metal, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation and plinth, including cost of all materials, labour, HOM of machinery, curing complete as per specifications.Specification No. KBS 4.1, 4.2 (P-12/SL NO-4.3/SOR-2015-2016)
cum
pcc for ssm
1 38.2 0.60 0.1
2.29
5,202.00
15,067.59
Deducion of column
6 0.45 0.45 0.1
0.12
pcc for column
6 1.1 1.10 0.1
0.73
4
KSRB 4.2.8 : Providing and laying in position reinforced cement concrete of mix 1:1.5:3 with 20mm and down size graded granite metal machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for R.C.C. beams, columns of all sizes in foundation plinth and superstructure ground floor level for roof slabs, staircase, lintles, columns, including cost of all materials, labour, HOM of machinery, curing, complete as per specifications.Specification No. KBS 4.1, 4.6(SL NO-4.13/PG NO-14/SOR-2015-2016)
cum
footing 6 0.32
1.92
6,510.00
12,499.20
column 6 0.45 0.45 0.9
1.09
6,510.00
7,118.69
5 KSRB 4.9.2: Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting,
t footing
1.92
_ _
0.15
58,920.00
14,204.43 column _ _
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 249
bending, hooking, placing in position, lapping and I or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery complete as per specifications. Specification No. KBS 4.6.3 (SL NO-4.46.2/PG NO-17/SOR-2015-2016)(@80kg/cum)
1.09 0.09
6
KSRB 4-6.7:Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for sides and soffits of beams, beam haunchings, cantilever girders, bressumers and lintels not exceeding 1 m in depth including cost of all materials, labour complete as per specificaitons. Specification No. KBS 4.6.2(SL NO-4.34/PG NO-16/SOR-2015-2016)
sqm
footing 6 0.8 _ _
4.80
217.00
1,041.60
column 6 1.62 _ _
9.72
217.00
2,109.24
7
Preparation and Surface treatment of formation by removing mud and slurry, watering to the extent needed to maintain the desired moisture content, trimming to required grade line, grade profile and rolling with 8-10 tons smooth sheeted roller
sqm platform 1 10 10.0
0 _
100.00
1.35
135.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 250
complete as per specification. KSRRB M 300-39 (SL NO-19.45/PG NO-145/SOR-2015-2016)
8
KSRB 5.3-3: Providing and constructing granite/trap / basalt size stone masonry in basement with cement mortar 1:6, edges of stones chistle dressed in courses not less than 15 cms high, bond stones at two m. apart in each course including cost of materials, labour, curing complete as per specifications. Specification No KBS 5.1.13 (PG NO-23/SL NO-5.9/SOR -2015-2016)
cum
SSM 1 38.20
0.45
0.45
7.74
5,486.00
39,437.48
Deducion of
column 6 0.45 0.45 0.45
0.55
9
KSRRB 400-2 Providing,laying,spreading and compacting specified graded,gravel or any other course material 60% and crushed stone aggregates of granite/trap/basalt 40% in sub base course,close grading-1 including premixing the material at OMC in mechanical mixer,carriage of mixed material,spreading in uniform layers with motor grader on a prepared base and compacting with power roller to achive the desired density including all materials,labour,HOM of machinery,lighting,guarding,barricading and maintenance of diversion.as
cum platform 1 9.10 9.10 0.3
24.84
1,716.00
42,630.59
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 251
per specifications.(SL NO-20.2/PG NO-154/SOR-2015-2016)
10
Providing, laying, spreading and compacting stone aggregates of specific sizes to Water Bound Macadam specification including spreading in uniform thickness, hand packing, rolling with power roller 8-10 tonnes in stages to proper grade and camber applying and brooming hard aggregates, screening materials followed by approved binding material to fill up the interstices of coarse aggregates, watering and rolling making necessary earthen bund to protect edges, lighting, guarding, barricading and maintenance of diversion road including cost of all materials, lead for metal upto 5 km loading, unloading, stacking, spreading labour charges of machinery's watering charges etc., complete. KSRRB M400-14.1 (SL NO-20.14.1/PG NO-156/SOR-2015-2016)
cum platform 1 9.10 9.10 0.1
8.28
3,126.00
25,886.41
11
KSRB 4-1.2 : Providing and laying in position plain cement concrete of mix 1:3:6 using 40mm and down size graded granite metal, machine mixed, concrete laid in layers not
cum
platform 1 10.
00 10.0
0 0.1
10.00
5,452.00
57,500.88
Deducion of
column 6 0.45 0.45 0.45
0.55
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 252
exceeding 15 cms. thick, well compacted, in foundation and plinth, including cost of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2 (PG NO-12/SL NO-4.2/2015-2016)
12
Providing and fabricating colums I Beams, purlins,base plates and bracings for main roof strucure with the 0.45 mm thick roofing sheets and with all around clading structure and sheeting,gutter,ect.The detailed scope of work and supply is enclosed (Market Price)
sqm PEB 1 10.00
10.00
_
100.00
3,750.00
3,75,000.00
13 Providing and fixing wind operated turbine exhaust fan on the slopping roof.
no 4 - - -
4.00
9,500.00
38,000.00
14 Supply and fixing of gear rolling shutters
sqm 1 1.2 _ 2.1
2.52
4,500.00
11,340.00
15
KSRB 11-3:Providing and fixing white vitreous china clay,water closet indian type(squatting pan) of size 580mm with footrests,100mm S or P trap,(approved make)cutting and making good the wall and floor wherever required,including cost of materials,labour complete as per specifications. (SL NO-12.3/PG NO-78/SOR-2015-2016)
pan sanitary 1 _ _ _ _
1,304.00
1,304.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 253
16
KSRB 13-11.1:Providing and placing on terrace,polyethylene water storage tanks as per IS 12701:1996 with manhole lid and suitable locking arrangements,making holes of suitable diameter for inlet,outlet and over flow pipes,including cost of all materials,labour,transport charges,HOM of equipments and testing complete as per specifications.(for 1000litre capacity) specification No:KBS 13.22 (SL NO-13.78/PG NO-91/SOR-2015-2016)
Nos
Water tank
1 _ _ _
1.00
8,350.00
8,350.00
Stand 1 _ _ _
1.00
6,000.00
6,000.00
6,71,845.79
17 Supply of electrical connections
20,155.37
Total Amount ₹ 6,92,001.16
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 254
A.5.20. Detailed Estimation of Dry Waste Collection Centre – Tools and Equipment’s
S.
No. Particulars Unit No. L W D Qty Rate Amount (Rs)
1 Supply of Furniture and Fixtures L.S ₹ 20,000.00
2 Supply of Security LED Light Magnet Wand Baton Nos. 1 Market rate 1 ₹ 450.00 ₹ 450.00
3 Supply of ABC type 9 kg dry fire extinguisher Nos. 1 Market rate 1 ₹ 3,519.00 ₹ 3,519.00
4 Supply, Installation and commissioning of Biometric System No. 1 Market rate 1 ₹ 5,000.00 ₹ 5,000.00
5
Supply of industrial digital price computing bench scale type TCS
electronic platform weighing scales 100 kg with big LED/LCD
display
Nos. 1 Market rate 1 ₹ 3,000.00 ₹ 3,000.00
Total ₹ 31,969.00
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 255
A.6. QUOTATIONS
A.6.1. List of Quotations
S. No. List of Quotations
1 Storage Bins (80 ltr)
2 Storage Bins (10 ltr)
3 Pushcarts
4 Auto tipper
5 Compactor
6 Front end loader
7 Bailing machine
8 Fire Extinguisher
9 DG set
10 GPS tracking system
11 Weigh Bridge
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 256
A.7. CENSUS OF INDIA 2011 – DISTRICT CENSUS HANDBOOK, KODAGU
A.7.1 DISTRICT PRIMARY CENSUS ABSTRACT
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 257
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 258
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 259
A.7.2 URBAN PCA – TOWN WISE PRIMARY CENSUS ABSTRACT
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 260
A.8. KARNATAKA HIGH COURT ORDER FOR WASTE SEGREGATION
Final SWM DPR for Kushalnagar under Swachh Bharat Mission
Tide Technocrats (P) Ltd, Bangalore 261
A.9. TP COMMENTS FROM DRAFT DPR OF MSW UNDER SBM