sunshine coast solar farm project

19
Sunshine Coast Solar Farm Project Business Case Summary May 2016

Upload: others

Post on 08-Nov-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Sunshine Coast Solar Farm Project

Sunshine Coast Solar Farm ProjectBusiness Case SummaryMay 2016

Page 2: Sunshine Coast Solar Farm Project

Contents

Page/s

• Policy perspective 3 - 5

• Project walk through 6 - 10

• Unique aspects of the Solar Farm project 11

• Why the Valdora site 12

• Project timeline 13

• The tender process 14

• How the Solar Farm will look 15 - 17

• Looking to the future 18

• Summary 19

2

Page 3: Sunshine Coast Solar Farm Project

Policy perspective: a mandate from the community

• 2009 ‘Regional Energy Opportunities’ Report– Externally prepared– Considered: wind, wave, tidal, biogas, gas co-generation, biomass, solar thermal, solar PV and

hydroelectric with solar PV most viable

• 2010 (June) – Council adopt ‘Climate Change & Peak Oil Strategy’*– Actions (8.3, 8.4, 8.5) include investigating the viability of alternative energy sites in rural areas

• 2010 (December) – Council adopt ‘Energy Transition Plan 2010-2020’*– Action 11: … allow renewable energy generation as a complement to primary production on

rural land– Action 5: … implement a clean energy solar program include facilitating large scale energy

production and solar power stations

*Underwent community consultation

3

Page 4: Sunshine Coast Solar Farm Project

Policy perspective: a mandate from the community

• 2011 Development Application (MCU) for 909 Yandina-Coolum Rd*– MCU for a major solar PV utility– Negotiated Decision Notice issued August 2011

• 2013 (April) – Council adopt ‘Rural Futures Strategy’*– Informed/guided by Rural Futures Background Study which identified ‘fuel farms’ may emerge

including solar … as alternative rural area land use

• 2013 (December) – Council adopt ‘Regional Economic Development Strategy 2013-2033’*– Focus on high-value industries such as ‘Clean Technology’ to generate 100,000 jobs

*Underwent community consultation

4

Page 5: Sunshine Coast Solar Farm Project

Policy perspective: summary

• Extensive supporting policy

• Policies underpinned by community support for: – Alternative energy– Renewable energy in rural areas– Identifying viable renewable energy sites

• Identified Solar PV as most viable renewable energy option– Community uptake of solar PV shows significant support (with 30,000 systems installed)

• Alternative use for Canelands, such as solar, also supported

• Economic development through Clean Technologies identified

• Council voted in on a platform of Action and Implementation

5

Page 6: Sunshine Coast Solar Farm Project

Project walk through

Page

• Financial Analysis 7

• Does solar PV make financial sense for Council? 8

• Testing our assumptions 9

• Why not rooftop solar at Council facilities? 10

6

Page 7: Sunshine Coast Solar Farm Project

Financial Analysis

Cost Component

BAU

30 Year NPV

$ millionEnergy Charges $(78.7) m

Carbon Charges -

Electricity Network Charges $(132.8) m

Service & Maintenance $(98.5) m

Other Charges $(9.4) m

TOTAL $(319.2) m

7

Page 8: Sunshine Coast Solar Farm Project

Does solar PV make financial sense for Council?

Type of Cost BAU NPV

$millions

Project NPV

$millions

Diff $millions

Energy Charges $(78.7) m $(35.4) m $43.3 m

Carbon Charges - - -

Network Charges $(132.8) m $(132.8) m -

ENERGEX Service & Maintenance $(98.5) m $(98.5) m -

Other Charges $(9.4) m $(9.4) m -

Total electricity costs $(319.2) m $(276.0) m $43.3 m

Total Project Spend - $(50.4) m $(50.4) m

Operating cost - $(10.6) m $(10.6) m

Large scale generation certificates - $22.6 m $22.6 m

Electricity Export - $12.8 m $12.8 m

Solar farm terminal value - $4.4 m $4.4 m

Total costs $(319.2) m $(297.1) m $22.1 m

8

Page 9: Sunshine Coast Solar Farm Project

$(9.0) m $(4.0) m $1.0 m $6.0 m $11.0 m $16.0 m $21.0 m $26.0 m $31.0 m $36.0 m $41.0 m $46.0 m

Freq

uenc

y

Value of Savings to Council (NPV $m)

Solar Farm Project Simulation (10,000 Trials)Testing our assumptions

SAVINGS TO COUNCIL

MORE EXPENSIVE

THAN RETAIL

FINA

NCIA

L BRE

AK E

VEN

LGCs repealed

9

Page 10: Sunshine Coast Solar Farm Project

Why not rooftop solar at Council facilities?

• Council explored rooftop solar– Commissioned an external report by Auzion Alliance - March 2012– Looked at 10 Council buildings/six Council land sites - extrapolated results

• In total rooftop solar only meets 5-10% of Council’s electricity requirement– With some sites being NPV negative

• Some Council facilities are simply not suitable for rooftop solar– By virtue of their consumption/layout – eg Aquatic Centres – Structural advice from Council’s Facilities Management Unit

• Council has implemented rooftop solar on 24 buildings– 158kW installed capacity

10

Page 11: Sunshine Coast Solar Farm Project

Unique aspects of Council’s project• Council is its own customer

– Removes margin and credit risk making it cheaper

• Not a selective use of capital – One way or another electricity usage is going to cost ~$60 million

• Low financing costs – Borrow at lower rates and for longer than commercial equivalents

• Long-term view– Commercial enterprise is looking for a return sooner; Council can be patient

• Social benefits– Educational benefit not realised by commercial players

• Economic benefit– Direct and indirect region specific investment benefits do not help external investors

11

Page 12: Sunshine Coast Solar Farm Project

Why the Valdora site?• 33kV line critical for connection

• Close proximity - $1m per km to connect

• Needs to connect at the ‘right point’ on the 33kV line• Network/line must have adequate capacity

to absorb power injection from farm

• Other crucial criteria• Protected land removed (eg water bodies,

conservation areas)• Urban and rural residential ‘footprint’

removed• Big enough (>30 ha) • Flat (<5% slope)• Available

• One real viable locationYandina-Coolum Rd powerline

12

Page 13: Sunshine Coast Solar Farm Project

Mar

Closed tender started

Apr

Initial business case to Council

Undertake more work

2011 2013

Project timeline

May

Developers offer

Council PPA (rejected)

Aug

MCU Approved

Mar

Developers re-approach

Council(PPA rejected)

July

Developer follow-up meeting

(PPA rejected)

Jan

Council OM Project ownership/ site value flagged.

Further work Land option agreement

July

Feb

Revised Business Case to Council

Council acquires site and project

Apr

Oct

New MCU lodged

2012 2015 20162014

Shortlisted tenderers and ETI

session held

Nov Jan

Council SM Preferred contractor

agreed and authority to enter

contract

Contract with Downer signed

Mar

QAO Audit

“No significant audit findings”

Mar

13

Page 14: Sunshine Coast Solar Farm Project

The Tender Process

EOI

ETI

Tender

2013/14 - 48 Submissions, 10 interviewed

Preferred Supplier

2014 – four Shortlisted Entities

2015 – two Final Submissions

SIGNED CONTRACT $37.5 million for ‘D&C’

Downer Utilities

14

Page 15: Sunshine Coast Solar Farm Project

How the Solar Farm will look – aerial view

15

Page 16: Sunshine Coast Solar Farm Project

Layout Plan

16

Page 17: Sunshine Coast Solar Farm Project

Ocean Vista Drive (1.9km away)

Karnu Drive (4.0km away)

17

Page 18: Sunshine Coast Solar Farm Project

Looking to the future

• Design and Construction contract is signed

• Contractor Downer has possession of the Valdora site

• Practical completion of build is expected by April 2017

• ENERGEX is fully supportive

• Electricity retailer is on board for flexible retail strategy

• Two-year Operations and Maintenance contract is signed

18

Page 19: Sunshine Coast Solar Farm Project

Summary

• Strong community and policy support

• Not a ‘selective’ use of capital– We are paying for electricity one way or another

• Extensive due diligence– Peer review and extensive industry consultation

• Staged Council decision-making approach– Numerous meetings/presentations to Council with more planned

• Significant social and economic benefits– Impact future young residents– Drive the development of new economies

• Tier 1 contractor to build and operate facility

19