study period march to may environmental...
TRANSCRIPT
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
1 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
STUDY PERIOD MARCH TO MAY -2016 NON FOREST LAND
ENVIRONMENTAL IMPACT ASSESSMENT &
ENVIRONMENTAL MANAGEMENT PLAN
FOR
Satalkhedi-Pipakhedi Limestone (Building Stone) Mine
Lease Area– 43.24 ha., M.L. No. 55/91,
Near Village – Satalkhedi-Pipakhedi, Tehsil – Ramganj Mandi, District – Kota, State - Rajasthan
Purpose – Environment Clearance, Proposed production –3, 21,699 TPA
PROJECT COST – 80.0 Lakhs CATEGORY- ΄B΄
Tor letter No- F1 (4)/SEIAA/SEAC-Raj/Sectt/Project/Cat.1 (a) B1 (7243) /14-15/752 Dated:-
06-05-2016.
LESSEE EIA CONSULTANT SH PANKAJ KUMAR BAIRWA S/o - SH. SWAROOP CHAND, R/o -SATALKHEDI, THE -RAMGANJMANDI DIST- KOTA, RAJASTHAN-
M/S UDAIPUR MIN-TECH PVT. LTD. 206, APEKSHA COMPLEX, SEC. -11 HIRAN MAGRI, UDAIPUR (RAJ.)-313002 PH. 91-294-2489672(OFF.) +91 9414167672 Email: [email protected]
ACCREDITED BY NABET CATEGORY “A” FOR MINING SECTOR (S. No. 146)
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
2 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
3 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
4 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
LIST OF ABBREVIATIONS
AMSL Above Mean Sea Level AAQ Ambient Air Quality bgl Below Ground Level
BOD Biochemical Oxygen Demand COD Chemical Oxygen Demand TDS Total Dissolve Solid
CPCB Central Pollution Control Board CSR Corporate Social Responsibility dB Decibel DO Dissolved Oxygen EAC Expert Appraisal Committee EIA Environmental Impact Assessment EMC Environmental Management Cell EMP Environment Management Plan EPA The Environment Protection Act GLC Ground Level Concentration Ha Hectare
HFL High Flood Level JIR Joint Inspection Report
KLD Kilo litre Per Day Km Kilo Meter Leq Equivalent Noise Level LFL Low Flood Level LOS Level of Service LoI Letter of Intent
MoEF Ministry of Environment and Forest NABET National Accreditation Board for
Education and Training NH National Highway
NOC No Objection Certificate OSHA Occupational Safety and Health
Administration PCU Passenger Car Unit PFR Pre- feasibility Report PM Particulate Matter PUC Pollution Under Control QCI Quality Council of India
RBM River Bed Material RL Reduced Level
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
5 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
SH State Highway SPCB State Pollution Control Board ToR Terms of Reference TPA Tonnes Per Annum
USEPA United State Environmental Protection Agency
MT Metric tone PF/RF Protected Forest/Reserve Forest
PM10/2.5 Particulate Matter PP Project Proponent
PPE Personal Protective Equipment R & R Plan Resettlement & Rehabilitation plan
ToR Terms of Reference
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
6 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
INDEX CHAPTER-I ............................................................................................................................................... 12
INTRODUCTION .................................................................................................................................................................. 12
1.1 PURPOSE OF THE REPORT ................................................................................................................................... 12
1.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT .......................................................................................... 12
DIST- KOTA, RAJASTHAN.................................................................................................................................................................. 13
1.3 BRIEF DESCRIPTION OF NATURE, SIZE AND LOCATION OF THE PROJECT ...................................................... 13
1.5 SCOPE OF THE STUDY ................................................................................................................................................................ 14
CHAPTER - II ............................................................................................................................................ 25
PROJECT DESCRIPTION ................................................................................................................................................... 25
2.1 TYPE OF PROJECT ......................................................................................................................................................................... 25
2.2 NEED OF THE PROJECT.............................................................................................................................................................. 25
2.3 LOCATION OF THE PROJECT ................................................................................................................................................... 25
2.2 DESCRIPTION OF LEASE AREA & MINING PROCESS.................................................................................................... 29
2.4 BASIC FACILITIES ....................................................................................................................................................................... 32
2.5PROPOSED SCHEDULE FOR APPROVAL AND IMPLEMENTATION ......................................................................... 33
CHAPTER-III ............................................................................................................................................ 34
DESCRIPTION OF THE ENVIRONMENT .................................................................................................................... 34
3.1 STUDY AREA ................................................................................................................................................................................... 34
3.2 ESTABLISHMENT OF BASELINE FOR VALUED ENVIRONMENT COMPONENT ............................................. 35
3.3 WATER ENVIRONMENT ............................................................................................................................................................ 49
3.4 AMBIENT AIR ENVIRONMENT ............................................................................................................................................... 57
3.5 NOISE ENVIRONMENT ............................................................................................................................................................... 72
3.6 TRAFFIC DENSITY: ....................................................................................................................................................................... 76
3.7 BIOLOGICAL ENVIRONMENT .................................................................................................................................................. 78
3.8 SOCIO-ECONOMIC ENVIRONMENT: ..................................................................................................................................... 86
CHAPTER - IV ....................................................................................................................................... 171
ANTICIPATED IMPACTS& MITIGATION MEASURES ......................................................................................... 171
4.1INTRODUCTION ............................................................................................................................................................................ 171
4.2 IMPACT ON LAND ENVIRONMENT AND MITIGATION MEASURES ..................................................................... 171
4.3 IMPACT ON WATER ENVIRONMENT AND MITIGATION MEASURES ................................................................. 172
4.4 IMPACT ON AIR ENVIRONMENT AND MITIGATION MEASURES ......................................................................... 173
4.5 IMPACT OF NOISE / VIBRATIONS & MITIGATION MEASURES ............................................................................. 178
4.6 IMPACT ON BIOLOGICAL ENVIRONMENT & MITIGATION MEASURE ............................................................... 179
4.7 IMPACT ON SOCIO ECONOMIC CONDITIONS................................................................................................................. 180
4.8 IMPACT ON OCCUPATIONAL HEALTH & SAFETY ....................................................................................................... 181
CHAPTER – V ........................................................................................................................................ 184
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
7 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
ANALYSIS OF ALTERNATIVES .................................................................................................................................... 184
5.1SITE ALTERNATIVES ............................................................................................................................................................... 184
5.2TECHNOLOGY ALTERNATIVES ............................................................................................................................................. 184
CHAPTER – VI ....................................................................................................................................... 185
ENVIRONMENTAL MONITORING PROGRAMME ................................................................................................ 185
6.1 MONITORING SCHEDULE AND PARAMETERS ......................................................................................................... 185
6.2 ENVIRONMENT MONITORING CELL ............................................................................................................................. 186
6.3 FUNCTIONS OF THE MONITORING CELL .................................................................................................................... 187
6.4 ENVIRONMENTAL POLICY: ............................................................................................................................................... 188
CHAPTER - VII ...................................................................................................................................... 189
ADDITIONAL STUDIES ................................................................................................................................................... 189
7.1 INTRODUCTION ........................................................................................................................................................................... 189
7.2 PUBLIC CONSULTATION: ........................................................................................................................................................ 189
7.2 RISK ASSESSMENT ..................................................................................................................................................................... 192
7.3 IDENTIFICATION OF HAZARDS ............................................................................................................................................ 192
7.4 SCENARIOS CONSIDERED FOR RISK ASSESSMENT .................................................................................................... 192
7.5 DISASTER MANAGEMENT PLAN ......................................................................................................................................... 194
7.6 OUTLINE OF DISASTER MANAGEMENT PLAN.............................................................................................................. 195
7.8 SOCIAL IMPACT ASSESSMENT, R&R ACTION PLAN ................................................................................................... 195
CHAPTER - VIII .................................................................................................................................... 196
PROJECT BENEFITS ......................................................................................................................................................... 196
CHAPTER – IX ....................................................................................................................................... 197
ENVIRONMENT MANAGEMENT PLAN .................................................................................................................... 197
9.1 INTRODUCTION ........................................................................................................................................................................... 197
9.2 GREEN BELT DEVELOPMENT ............................................................................................................................................... 200
9.3 SOCIO ECONOMIC ENVIRONMENT ..................................................................................................................................... 202
9.4 OCCUPATIONAL SAFETY & HEALTH ................................................................................................................................. 203
9.5 TOP SOIL AND WASTE MANAGEMENT ............................................................................................................................ 205
CHAPTER – X ........................................................................................................................................ 207
SUMMARY & CONCLUSION ........................................................................................................................................... 207
10.1 INTRODUCTION ........................................................................................................................................................................ 207
10.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT: .................................................................................... 207
10.3 LOCATION OF PROJECT: ....................................................................................................................................................... 208
10.4 SIZE OR MAGNITUDE OF OPERATION: .......................................................................................................................... 208
10.5 MINING METHOD ..................................................................................................................................................................... 208
10.6 EMPLOYEE DETAIL: About 109 workers will be required. .................................................................................. 208
10.8 DESCRIPTION OF ENVIRONMENT ................................................................................................................................... 209
10.9 ENVIRONMENT MONITORING CELL ............................................................................................................................... 210
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
8 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
10.10 ENVIRONMENT MANAGEMENT PLAN ........................................................................................................................ 210
CHAPTER – XI ....................................................................................................................................... 212
CONSULTANTS ENGAGED ............................................................................................................................................ 212
1 ................................................................................................................................................................ 205
LIST OF TABLES
TABLE 2.1: DETAIL OF YEAR WISE PROPOSED PRODUCTION ................................................. 14
TABLE 2.1: DETAIL OF YEAR WISE PROPOSED PRODUCTION ................................................. 31
TABLE 2.2: DETAIL OF PROPOSED WASTE TO BE GENERATED FOR MINING OPERATION
31
TABLE 2.3: DETAIL OF MANPOWER REQUIRED FOR MINING OPERATION ....................... 32
TABLE 2.4: DETAIL OF MACHINERY DEPLOYED OR TO BE DEPLOYED ............................... 32
TABLE 2.5WATER REQUIREMENT ....................................................................................................... 32
TABLE 3.1: STUDY AREA AT A GLANCE .............................................................................................. 34
TABLE 3.2: LAND USE PATTERN BASED ON SATELLITE IMAGE ............................................. 36
TABLE 3.3: LAND USE PLAN FOR PRE- OPERATIONAL, OPERATIONAL & POST -
OPERATIONAL PHASES (IN HECT.) ...................................................................................................... 39
TABLE 3.4: SOIL SAMPLING LOCATIONS IN THE STUDY AREA................................................ 45
TABLE 3.5: ANALYSIS RESULTS OF SOIL SAMPLES ....................................................................... 48
TABLE 3.6: LOCATION OF WATER SAMPLING IN THE STUDY AREA ..................................... 53
TABLE 3.7: ANALYSIS RESULTS OF GROUND WATER SAMPLES ............................................. 56
TABLE 3.8: LOCATION OF AMBIENT AIR MONITORING STATIONS ...................................... 59
TABLE 3.9: PROCEDURE FOR DETERMINING VARIOUS AIR QUALITY PARAMETERS ... 62
TABLE 3.10 (A): MEAN TEMPERATURE & RELATIVE HUMIDITY ........................................... 62
Sources- IMD station Jhalawar ................................................................................................................ 62
TABLE 3.10 (B): MEAN TEMPERATURE& RELATIVE HUMIDITY AT PROJECT SITE ...... 63
TABLE 3.11: AMBIENT AIR QUALITY RESULT ................................................................................. 63
TABLE 3.12: COMPARISON OF AIR MONITORING RESULTS ...................................................... 71
TABLE 3.13: LOCATION OF NOISE MONITORING STATIONS .................................................... 72
TABLE 3.14: NOISE LEVEL WITHIN THE STUDY AREA (Unit – dBA) ..................................... 75
TABLE 3.15: CPCB NOISE STANDARD ................................................................................................. 75
TABLE 3.16: LIST OF FLORAL SPECIES OBSERVED IN CORE ZONE ........................................ 82
TABLE 3.17: LIST OF FLORAL SPECIES OBSERVED IN BUFFER ZONE................................... 82
TABLE 3.18: LIST OF FAUNA SPECIES OBSERVED IN THE CORE ZONE ................................ 84
TABLE 3.19: LIST OF FAUNAL SPECIES OBSERVED IN BUFFER ZONE .................................. 85
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
9 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
TABLE 3.20: LIST OF AVIFAUNAL SPECIES OBSERVED IN THE STUDY AREA ................... 86
TABLE 3.21 DISTRIBUTION OF POPULATION ................................................................................. 88
TABLE :- 3.22 DISTRIBUTION OF POPULATION SOCIAL STRUCTURE................................... 90
TABLE 3.23 DISTRIBUTION OF LITERATES AND LITERACY RATE ......................................... 90
TABLE 3.24 OCCUPATIONAL STRUCTURE ........................................................................................ 92
TABLE NO-4.1 PREDICTED AMBIENT AIR QUALITY CONCENTRATIONS IN OPERATION
PHASE CUMULATIVE CONCENTRATIONS (BASELINE + INCREMENTAL) FOR PM10 .. 174
TABLE 6.1: MONITORING SCHEDULE FOR ENVIRONMENTAL PARAMETERS ................ 185
TABLE 9.1: ENVIRONMENT MANAGEMENT PLAN IMPLEMENTATION ........................... 197
TABLE 9.2: COST ESTIMATES OF EMP IMPLEMENTATION .................................................... 200
TABLE 9.3: STAGE WISE PLANTATION ........................................................................................... 201
TABLE 9.4: PROPOSED PLANTATION .............................................................................................. 201
TABLE 9.5: COST OF CSR ACTIVITIES .............................................................................................. 202
TABLE 9.6: BUDGETARY PROVISION FOR WORKERS ............................................................... 204
TABLE 9.7: PROPOSED WASTE GENERATED FOR MINING ACTIVITY ............................... 205
10.7 MACHINERIES DEPLOYED: ......................................................................................................... 208
LIST OF FIGURES
FIGURE 2.1: LOCATION MAP ................................................................................................................... 26
FIGURE 2.2: KEY PLAN OF THE LEASE AREA ................................................................................... 27
FIGURE 2.3: GOOGLE IMAGE SHOWING GENERAL LOCATION OF THE LEASE AREA ..... 28
FIGURE 2.4: GOOGLE IMAGE OF THE LEASE AREA WITH BOUNDARY PILLARS .............. 28
FIGURE 3.1: LAND USE / LAND COVER MAP PATTERN OF THE STUDY AREA. ................. 37
FIGURE 3.2: SATELLITE IMAGE OF 10 KM RADIUS OF THE STUDY AREA ........................... 38
FIGURE 3.3: TOPOGRAPHY MAP OF THE STUDY AREA ............................................................... 40
FIGURE 3.4: DRAINAGE MAP OF THE STUDY AREA ...................................................................... 41
FIGURE 3.5: SURFACE GEOLOGICAL PLAN AND SECTION OF THE LEASE AREA .............. 44
FIGURE 3.6: SOIL SAMPLING LOCATIONS IN THE STUDY AREA .............................................. 46
FIGURE 3.7: PHOTOGRAPHS OF SOIL SAMPLING IN THE STUDY AREA ............................... 47
FIGURE 3.8: HYDROGEOLOGICAL MAP OF THE DISTRICT KOTA ............................................ 50
FIGURE 3.8(A): DEPTH TO WATER TABLE PRE-MONSOON ...................................................... 52
FIGURE 3.8(B): DEPTH TO WATER TABLE POST-MONSOON .................................................... 52
FIGURE 3.9: WATER SAMPLING LOCATIONS MAP IN THE STUDY AREA ............................. 54
FIGURE 3.10: PHOTOGRAPHS OF WATER SAMPLING IN THE STUDY AREA ...................... 55
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
10 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.11: WIND ROSE DIAGRAM ................................................................................................... 57
FIGURE 3.12: AMBIENT AIR SAMPLING LOCATION IN THE STUDY AREA .......................... 60
FIGURE 3.13: PHOTOGRAPHS OF AMBIENT AIR MONITORING IN THE STUDY AREA ... 61
FIGURE 3.14: NOISE MONITORING LOCATION MAP ..................................................................... 73
FIGURE 3.15: PHOTOGRAPHS OF NOISE & TRAFFIC MONITORING IN THE STUDY ARE74
FIGURE 3.16: TRANSPORTATION ROUT MAP .................................................................................. 77
FIGURE 3.17: BIOLOGICAL SAMPLING LOCATION MAP OF THE STUDY AREA .................. 80
FIG 3.18 PHOTOGRAPHS OF VEGETAION .......................................................................................... 81
FIG.NO. 3.19 .................................................................................................................................................... 89
FIG.NO.3.20 ..................................................................................................................................................... 91
FIG.NO. 3.21 .................................................................................................................................................... 92
FIGURE 3.22: SOCIO –ECONOMIC SURVEY LOCATION MAP ................................................... 170
FIGURE 4.1: GROUND LEVEL CONCENTRATION OF AAQ DURING OPERATION PHASE IN 10
KM FOR PM10............................................................................................................................................. 175
FIGURE-4.2: GROUND LEVEL CONCENTRATION OF AAQ DURING OPERATION PHASE IN 1
KM FOR PM10 ............................................................................................................................................ 176
FIGURE 6.1: ENVIRONMENT MONITORING CELL (EMC) ......................................................... 186
A. Mine site ................................................................................................................................................. 190
Total ............................................................................................................................................................... 190
Mining Lease ............................................................................................................................................... 202
Township Site ............................................................................................................................................. 202
LIST OF ANNEXURE
ANNEXURE –I: COPY OF LEASE AGREEMENT ................................................................................................................................. 212
ANNEXURE –II: COPY OF NOMINATION LETTER .......................................................................................................................... 225
ANNEXURE –III: COPY OF LEASE EXTENSION LETTER .............................................................................................................. 226
ANNEXURE IV COPY OF APPROVAL LETTER OF MINING PLAN ............................................................................................. 227
ANNEXURE –V: COPY OF KHASRA MAP, JAMABANDI& DEMARCATION ............................................................................ 228
ANNEXURE –VI: PREVIOUS Year’s PRODUCTION .......................................................................................................................... 234
ANNEXURE –VII COPY OF ARAVALI LETTER ................................................................................................................................... 236
ANNEXURE –VIII COPY OF COMPOSITE MAP .................................................................................................................................. 237
ANNEXURE –IX COPY OF NOC ................................................................................................................................................................. 238
ANNEXURE –X: COPY OF MONITORING REPORT........................................................................................................................... 239
ANNEXURE –XI: TOR LETTER ................................................................................................................................................................. 269
ANNEXURE –XII: COPY OF MINUTES OF PUBLIC HEARING ...................................................................................................... 274
ANNEXURE –XIII: PHYTOSOCIO REPORT OF STUDY AREA ....................................................................................................... 282
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
11 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
ENVIRONMENTAL IMPACT ASSESSMENT &
ENVIRONMENTAL MANAGEMENT PLAN
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
12 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
CHAPTER-I
INTRODUCTION
Mining, Environment and development have become complimentary to each other. As
a result of developmental activities visible ill-effects of the environmental degradation
are clear and give signals of the concern. Therefore a sustainable development of the
area involving extraction of mineral wealth vis-à-vis protection of environment is the
ultimate solution for betterment of mankind.
1.1 PURPOSE OF THE REPORT
The Environmental Impact Assessment has been prepared to assess the current
environmental scenario of the area and then based on the activities of mining
proposed, to carry out Environmental Management Plan. The plan will identify and
address the impacts, where these are adverse in nature, and thereafter to design
mitigation measures to manage such impacts in a manner as to conserve environment
and ecology of the area. The EMP has been prepared with a view to ultimately ensure
that the adverse impacts are minimized if these cannot be prevented altogether.
Environmental clearance is a statutory requirement for the new and old establishment
of any mining project of which EIA has to be prepared and submitted to respective
agencies of state and central level in line with EIA Notification, 1994 & 2006.
As per New EIA Notification Dated 14th Sept. 2006, Environmental Clearance is
required for all old & new mining projects / enhancement of production.
1.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT
PROJECT IDENTIFICATION
This is a mining project of Satalkhedi-Pipakhedi limestone (Building Stone) Mine, near
village - Satalkhedi-Pipakhedi, Tehsil – Ramganj Mandi, District – Kota (Rajasthan)
over 43.24 ha Pvt. land.
Originally the mining lease (Area 83.87ha.) was granted in favour of Shri Ganga Ram
Bairwa S/o Sh. Kalu Ram Bairwa vide letter No-9(4) Khan/Group/-2/92 in dated
13/04/92 for 10 years (20-01-1992 to 19-01-2002). The lease deed was executed on
30/05/1992 and registered on dated 30/06/1992
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
13 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Lease renewal order was given for 10 years on dated 20.01.1992 to 19.01.2002 after
that it has extended up to the 19.01.2012.
About 40.63 ha lease area was surrendered on dated 20.01.2001.
After the death of Ganga Ram Bairwa the lease was Nominated in favour of Shri
Pankaj kumar Bairwa S/o Shri Swaroop Chand Bairwa.
And now the lease has been renewed up to the 19.01.2022.
Mining plan with progressive mine closure plan has been approved on dated 31-12-
2013.
Project was submitted to SEIAA Raj for environment clearance and Tor was issues vide
letter No- F1/(4)/SEIAA/SEAC-Raj/Sectt/Project/Cat 1(a). B1 (7243)/14-15/752 on
dated 06/05/2016 & public hearing also conducted on dated 06/12/2016.
Ref Annexure-I Copy of lease agreement
Ref Annexure-Ii Copy of nomination letter
Ref Annexure-III Copy of lease extension letter
Ref Annexure-IV Copy of approval letter of mining plan
Ref Annexure-V Copy of khasra map & Jamabandi
Ref Annexure-XI Copy Of Tor Letter
Ref Annexure-X Minutes Of Public Hearing
IDENTIFICATION OF PROJECT PROPONENT
Sh. Pankaj Kumar Bairwa S/O - Sh. Swaroop Chand, R/O -Satalkhedi, Tehsil -Ramganjmandi
Dist- Kota, Rajasthan
1.3 BRIEF DESCRIPTION OF NATURE, SIZE AND LOCATION OF THE PROJECT
NATURE OF PROJECT:
This project is for mining of Limestone near village – Satalkhedi-Pipakhedi, Tehsil –
Ramganj Mandi, District – Kota (Rajasthan) it existing mine which produce limestone
(Building stone) from opencast method.
Previous year’s production is attached as ANNEXURE NO VI
SIZE-
The lease covers an area of 43.24 hectare and it is proposed to produce about
3, 21,699 TPA (RoM) Lime Stone (Building Stone).
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
14 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
LOCATION
The lease area is situated at near village - Satalkhedi-Pipakhedi,, Tehsil – Ramganj
Mandi, District – Kota (Rajasthan) over 43.24ha Pvt. land.
1.5 SCOPE OF THE STUDY
The point wise compliance of the Standard TOR prescribed by the committee in the
tabular form is given as under.
S. No. Description Covered in EIA as per details
1. The study area will comprise 10
km zone around the mine lease
from lease periphery and the data
contained in the EIA with respect
to mining operations such as
conceptual pit limits, waste
generation etc. should be for the
life of the mine/lease period.
The EIA study has been carried out in the 10 km radius from the periphery of the lease area. Key plan show core zone and buffer zone of 10 km radius from lease boundary Ref figure No 2.2, Data like reserves, waste generation Up to life of mine have been incorporated in Chapter II of EIA/EMP Report.
2. Location of other industries &
mines within the study area along
with their production and
pollutants generated by them,
estimated pollution load and
cumulative impact on
environment including the
proposed project should be
submitted. The same shall be
accounted for while generating
mathematical models of pollution
dispersion for preparation of the
EMP.
There are two other mining leases exists in the periphery of 500 m
of lease area. The monitoring has been carried and cumulative
impact has been estimated including the proposed project. Detail is
given in Chapter-IV.
Isopleths is given in EIA EMP report on page no-118-119, Fig No-4.1
& 4.2.
3. Year-wise production details
clearly indicating the proposed
highest production for the life of
the mine/lease period should be
submitted.
Proposed year wise production detail TABLE 2.1: DETAIL OF YEAR WISE PROPOSED PRODUCTION
Year Production
in MT (RoM)
Saleable
Mineral
tones
Waste
generated
from the total
excavation
(MT)
Sub
grade
in MT
Over burden
form OB
benches
tonnes
I 321697 225189 80424 16084 1026432
II 321697 225189 80424 16084 712800
III 321697 225189 80424 16084 712800
IV 321697 225189 80424 16084 712800
V 321697 225189 80424 16084 712800
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
15 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Total
1608485
1125945 402120 80420 3877632
As per approved mining plan.
4. Details of land to be used as the
designated dumping site for OB
dump should be selected and
proposed within the lease area as
per the approved mine plan. In no
case the overburden should be
dumped outside the lease area,
however proposal for utilization of
OB for construction or other
meaningful use to the extent
possible may be submitted.
The waste as OB in the area is top soil and fractured limestone . the
soil cover in the area varies from 3m fractured limestone varies
from 27 m. This OB will be dumped at mined out pit. This sub grade
material will be stacked at earmarked site.No external dump within
lease area will be created and no O/B will be dumped outside during
course of mining.
Detail is given in Chapter- II
5. Land use plan of the mine lease
area should be prepared to
encompass pre-operational,
operational and post operational
phases.
Land use pattern of the mine lease area of pre-operational phase,
operational phase & post operational phase is given below:
Note- About 15.9800 ha area has been already planted within
lease for full fill 33% plantation as per ToR compliance. At the
end of mine life about 20.77 ha area will be planted which
includes 3.5400 Ha area will be planted on statuary barrier
(7.5 Meter) & 17.2396 ha area will be backfill planted. About
6.4804 ha area will be converted as water storage.
Particulars Pre Operational (in Ha)
Operational (in Ha)
Post operational (in Ha)
Mining Activity
Mining pits 8.5215 10.5710 0.00
Road & building
2.3750 2.3750 0.00
Plantation on statuary barrier
0.0000 2.5500 3.5400
Mineral stack 1.5420 1.9540 0.0000
Water storage 1.2010 1.2010 6.4804
Reclamation & Backfilled Plantation
5.9800 5.9800 17.2396
Plantation on remaining lease area
15.9800 15.9800 15.9800
Remaining virgin land
7.6405 2.6290 0.000
Total 43.24 43.24 43.24
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
16 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
6. The P.P. should provide a mining
plan along-with progressive mine
closer plan and implementation
plan at the time of presentation for
the EC.
Mining Plan along with Progressive Mine Closure Plan is submitted
along with the final EIA report.
7. Based on the study and the points
raised by the people during public
hearing, the P.P. shall work out an
effective plan to address the
environmental and socio-
economic issues identified during
the process, with suitable funds
allocation for the purpose.
Public hearing was conducted on dated 06.12.2016 at the Atal Seva
Kendra Gram Panchayat Bhawan in village Satalkhedi, Tehsil –
Ramganjmandi, Dist. – Kota, Rajasthan.
8. Certificate regarding mine lease
area not falling in the Aravalli Hills
to be issued by the Mining
Engineer/ Assistant Mining
Engineer in the prescribed format,
as per the instructions contained
in the letter no.
DMG/ADM/Env/EC/F11/06/17-
76 dt. 17.01.2011 issued by the
Director, Department of Mines and
Geology, GoR, Udaipur, should be
countersigned by the Additional
Director (Mines), DMG of
concerned Region and copy be
submitted with other required
documents.
The lease area does not falls in Aravalli hills. Copy of Aravalli letter
Attach annexure N0-VII
9. List/details within 10 km radius of
the mine lease area, the location of
human settlement, water bodies,
Reserve Forest, National Parks,
Sanctuaries, Biosphere Reserves,
Wildlife Corridors, Tiger/Elephant
reserves (existing / proposed),
shall be clearly indicated giving
the land use. Necessary clearance,
if any, as may be applicable to such
projects due to proximity of the
ecologically sensitive areas as
mentioned above shall be obtained
from the Chief Wildlife Warden
under the Wildlife (Protection)
Act’ 1972 and submitted. This
location map should also indicate
the list and location of other mine
leases existing, if any, within 10
km radius.
The nearest human settlement is village Satalkhedi & Pipakhedi
which is distance about 0.8 & 1.0 Km from mining lease area. Three
river namely Ahu, Amjar, Psadi is flowing in study area. There is no
water body exist in lease area. Drainage map (figure No.3.4) is
enclosed in the report on page No-49.
There is no National park, Sanctuaries, Biosphere reserve wild life
corridors exist within 10 km zone of lease area.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
17 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
10. A detailed biological study for the
study area [core zone and buffer
zone (10 km radius of the
periphery of the mine lease)] shall
be carried out. Details of flora and
fauna, duly authenticated,
separately for core and buffer zone
should be furnished based on field
survey. The details regarding flora
to include information regarding
(a) trees, shrubs, grasses, (b)
frequency, density, I V I,
abundance % of species occurring
on proposed site, (c) dominant
species of trees, shrubs , grasses
(d) endemic species, (e)
threatened species, (f) rare
species, (g) endangered species
and (h) vulnerable species. The
details of fauna to include
information regarding list and
distribution clearly indicating the
Schedule of the fauna present. In
case of any scheduled-I fauna
found in the study area, the
necessary plan for their
conservation should be prepared
in consultation with State Forest
and Wildlife Department and
details furnished. Necessary
allocation of funds for
implementing the same should be
made as part of the project cost.
A detailed biological study of the core and buffer zone has been
carried out. Detail is given in Chapter-III.
No endangered flora & fauna found in core & buffer zone.
Authentication List of flora fauna is under process.
11. Collection of one season (non-monsoon) primary baseline data on ambient air quality, water quality, noise level, soil and flora and fauna. Ambient Air quality should be determined by measuring the concentration of parameters like P.M.2.5, P.M.10, SO2, NOx according to the latest standards prescribed by CPCB. Site-specific meteorological data should also be collected. The location of the monitoring stations (minimum 6) should be justified. Date wise collected baseline AAQ data should form part of EIA and EMP report. The monitoring shall be carried out by CPCB/NABL/
One season (post monsoon season) primary base line data on
ambient air quality (PM2.5, PM10, SO2 and NOx), water quality, noise
level, soil and flora and fauna has been done and Date-wise AAQ
data is given in Chapter III, Table-3.11 & page no-58
Site-specific meteorological data has been collected and the AAQ and
other data are compiled in the EIA report. All monitoring station
along with the location map of monitoring sites are given in Chapter-
III,
Analysis report is attached as Annexure No-X
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
18 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
MOEF/GoR approved laboratory and copy of the report submitted. The monitoring if any prior to submission of project to SEIAA for ToR will not be considered.
12. Air quality modeling should be
carried out for prediction of
impact of the project on the air
quality of the area. It should also
take into account the impact of
movement of vehicles for
transportation of mineral. The
details of the model used and input
parameters used for modeling
should be provided. The air
quality contours may be shown on
a location map clearly indicating
the location of the site, location of
sensitive receptors, if any and the
habitation. The wind roses
showing pre-dominant wind
direction may be indicated on
map. Wind Rose Diagram should
be representative and include
stability class and inversion
phenomenon of that area along
with the lapse rate.
Air quality modeling has been carried out by Fugitive Dust Model
(FDM) which is based on Gaussian Plume Model. Vehicular
movement for the transportation of the mineral will be limited.
Therefore much impact is not envisaged. However a detailed study
has been conducted for prediction of impact details given chapter-
IV, para-4.4,. Sampling location for Air Quality Monitoring is marked
on the Air sampling location map in Chapter III Figure No-3.12.
Location of the monitoring stations represent whole of the study
area keeping in view the pre-dominant wind direction. Wind rose is
given chapter-III figure No-3.11. Isopleths is given chapter-IV figure
No-4.1 & 4.2.
The incremental value about the project is given in below table-
Particular
Mine Site
A1
Monitored Maximum concentrations in µg/m3
(Core zone) 78.7*
Predicted incremental Maximum
concentrations in µg/m3 0.8
Resultant Maximum concentrations in µg/m3 79.5
NAAQS (dated 2009) 100
13. A surface and ground water study should be carryout, both pre-monsoon and post monsoon monitoring. Information about proposed working depth of mining area, groundwater table both in above MSL and below ground level (BGL) should be provided. Based on actual monitored data, it may clearly be shown whether mine working will intersect groundwater table or not. In case the mining activity intersects the ground water table then necessary permission from CGWA should be obtained. Impact of the project on the water quality both surface and groundwater should also be assessed and necessary safeguard measures, if any required should be provided. Further, submit
Ground water study has carryout during the survey. Detail is given
in Chapter-III. Groundwater water were taken to analyze the quality
of water in the study area detail is given in chapter-III with results.
Systematic representation diagram of site elevation, working depth,
ground water table is given below-
295 mRL (45mbgl Pre monsoon)
300mRL ( 40 mbgl Post monsoon)
WATER TABLE
303 mRL (37 mbgl)
ULTIMATE DEPTH
337 mRL (Lowest Contour)
GROUND LEVEL
Proposed working will not intersect Ground
water table.
340 mRL (Highest contour)
hiesest
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
19 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
water drainage plan of the 10 km study area.
A drainage plan of the 10.0 km study area has been prepared is
given in chapter-III (figure No. 3.4).
14. The water requirement for the project, its availability and source to be furnished. A detailed water balance should also be provided. Fresh water requirement (if any) for the project should also be indicated. Necessary clearance from the Competent Authority for drawl of requisite quantity of water for the project should be provided. Details of water conservation measures including rainwater harvesting should be provided and to be adopted in the project.
WATER REQUIREMENT
S. No Particulars Quantity KLD
1. Drinking 2.0
2. Water Sprinkling 3.0
3. Green belt 3.0
Total 8.0
Water requirement for domestic/drinking, green belt & water
sprinkling purpose will be met through water tanker from dug wells
at the nearby village. There is no proposal for drawl of water within
the lease area, hence clearance for the same is not required.
Plantation is proposed along lease boundary & backfill mine out
area. Same part of work out pit will be left for rain water storage
which can be used for irrigation & other purpose & help in
recharging of ground water in near village.
15 Consumption of diesel and its storage should be provided along with an action plan for its conservation.
Total 300 lit/d diesel will be required for mining operation, there
will be not required any storage facilities of diesel. The diesel will
be providing authorized contractor on contractual basis.
16. The Conceptual post mine land use plan and Reclamation & Rehabilitation (R&R) plan of mined out area (with plans and sections at appropriate scale as per MCDR 1988 should be submitted.
The post mine land use id given under-
Particulars Position at the End of life of the mine
(post- operational in Ha)
Mining pits 0.00 Road & building 0.00
Plantation on statuary barrier
3.5400
Mineral stack 0.00
Dump Area 0.00
Water storage 6.4804
Reclamation & Backfilled Plantation
17.2396
Plantation on reaming lease area
15.98
Total 43.24 Note- About 15.9800 ha area has been already planted within lease
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
20 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
for full fill 33% plantation as per ToR compliance. At the end of
mine life about 20.77 ha area will be planted which includes 3.5400
Ha area will be planted on statuary barrier (7.5 Meter) & 17.2396 ha
area will be backfill planted. About 6.4804 ha area will be converted
as water storage.
Conceptual mine plan is attached as plate No.5.
17. Impact on local transport and
infrastructure due to the project.
Projected increase in hauling
vehicles as a result of the project
in the present road network
(including those outside the
project area) and whether it is
capable of handling the increased
load. Arrangement for improving
the infrastructure to avoid any
conjestion especially at junctions
and mishaps throughout the route
of transportation of mineral
should be ensured and action to be
taken by other agencies such as
State Government, if any, should
be covered.
About 5-6 dumpers / day will be required for transport of mineral
from mine. Increase in truck traffic is negligible and the existing
road network is capable of handling the increased load. State govt.
conduct traffic census regularly and take action accordingly.
A detail of traffic environment is refer chapter-III, para-3.6 & page
no-89.
18. The green belt area should be developed in 33% of total lease area, provide time taken for of progressive greenbelt development, plantation and compensatory a-forestation clearly indicating the 33% area to be covered under plantation giving detail of local species, width of plantation, plantation schedule etc. along with year wise financial expenditure. The proposal for completion should be for a period of 3 years from the start of mining operation. Information regarding greenbelt development plan shall also be prepared in a tabular form, indicating the location of the area, type of tree and its number supported by a map. Further, existing mining projects should carryout plantation in 33% of lease area and thereafter come for the EC.
About 15.98 ha area is already planted & At the end of mine life
about 20.77 ha area will be planted which includes 3.5400 Ha area
will be planted on statuary barrier (7.5 Meter) & 17.2396 ha area
will be backfill planted. Details of progressive greenbelt
development program are given in Chapter-IX table no 9.3.
Plantation species already given in Chapter IX on Table No-9.4.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
21 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
19. Budgetary provision for the labors working in the Mine should be submitted for all necessary infrastructure facilities such as health facility, sanitation facility, and fuel for cooking, along with provision for safe drinking water, monthly medical camps and distribution of medicines, primary education and toilets for women, crèche for infants.
Salary will be given as per the norms & all the facilities like health
facility, sanitation facility, along with provision for safe drinking
water, periodic medical etc. will be provided to the workers.
Budgetary provision for the labours to be employed in the mine is
given as under:
Facility Provided for Labourers
Total amount per year
Drinking water By Tanker 30,000/- First Aid Box 20,000/- Rest Shelter 50,000/- Washroom 20,000/- Safety shoes 75,000/- Hand Gloves 75,000/- Dust Mask 50,000/- Ear Plugs / Muffler 30,000/- Helmet 50,000/- Insurance 1,00,000
Total 5,00,000
20. Details regarding Occupational
health impact of the project should
be provided. Health study in the
surrounding area be carried out
covering information regarding
prevailing diseases, mortality rate
etc. Health and Safety Plan should
be prepared and submitted.
Occupational health impact including -Physical hazard, fatal injury
include rock fall, fires, explosions, mobile equipment accidents, etc.
given in report.
Socio survey has been carried out during study period health study
in the surrounding areas is given in chapter-III on page no-
The mining will be done with all safety PPE (Dust mask, Safety
boots, Helmet Ear muffs.) under the supervision of Qualified Staff.
Regular Water sprinkling will be done on haul roads, regular health
check-up two times in one year of the mine workers will be done
and all mitigation measure will be adopted. Vocational training will
be provided to the workers.
Details about, Occupational Health impacts, person protective
measures, pre-placement medical examination and periodical
medical examination schedules, management plan has been
furnished in Chapter-IV, and Chapter IX.
21. The P.P. will carry out proper Socio-economic survey of the villages situated in the study area. The details of survey are given if format J. Based upon its findings and also as per public hearing issues and keeping in view the felt needs of local populations, the P.P. will provide adequate budget for carrying out CSR/ESR activities including provision for toilets for girls in nearby schools, monthly medical camps, distribution of medicines and improvement in
Socio economic survey of the villages situated within the study area
has been carried out and detail is given in Chapter – III. The mining
activity in this area will have positive impact on socio economic
condition of the area & providing employment to the local people.
Wages paid to them will increase the per capital income. Thus
project will have positive impact on the surrounding local
community.
Propose CSR activities are given in Chapter-IX .
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
22 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
educational facilities in the nearby schools. Further, existing mining projects should carryout ESR/CSR for a period of at least one year and thereafter come for the EC.
22. Measures for socio economic
influence on the local community
due to proposed project to be
provided by project proponent. As
far as possible, appropriate
quantitative dimension to be
given. Analysis of Job
requirements vis-à-vis,
employability of local population
need to be provided.
This mining project will create opportunity of direct as well as
indirect employment to the local people. There will be direct
employment opportunities in the mine and also the secondary
employment by contract jobs associated with mining works.
Proposed project will provide employment to about 109 people and
preference will be given to local people.
Propose CSR activities are given in Chapter-IX.
23. Detailed environmental
management plan to mitigate the
environmental impacts which,
should inter-alia also include the
impact due to change of land use,
due to loss of agricultural land and
grazing land, if any, besides other
impacts of the projects. The
budgetary provision (both capital
and recurring) for implementing
the proposed EMP should be
clearly spelt out.
A well laid Mitigation Plan is prepared with respect to impact of the
project (Environmental protection measures including green belt
development, water sprinkling on haul roads, regular monitoring for
air quality, and Water quality monitoring, maintenance of Noise
generating sources) on the surrounding environment. For detail
refer Chapter IV & Chapter IX. About Rs. 3.5 lac per year will be
spent for EMP.
24. The points raised during Public hearing and commitment of the project proponent on the same along with time bound action plan to implement the commitments and the necessary allocation of funds for the same to be provided.
Public hearing was conducted on dated 06.12.2016 at the Atal Seva
Kendra Gram Panchayat Bhawan in village Satalkhedi, Tehsil –
Ramganjmandi, Dist. – Kota, Rajasthan.
25. Any litigation pending against the
project and /or any direction
/order passed by any Court of Law
against the project, if so, details
thereof should be submitted.
No litigation pending against this project.
26 The P.P. should ensure compliance
of the order of the Hon’ble
Rajasthan High Court, Jodhpur, in
D. B. Civil writ petition no. 1536 of
2003 in the matter of Abdul
Rahman vs State of Rajasthan and
others and submit a brief note
regarding compliance of the court
order.
The P.P has ensured the compliance of the order of the Hon’ble
Rajasthan High Court, Jodhpur.
27. That the Project Proponent shall
not use any explosive and blasting
Controlled blasting shall be done by the blasting contractor. The
explosives will be handled by the blasting contractor hence no
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
23 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
for mining activity without proper
permissions from competent
authorities.
storage of explosives is required at site. Detail of blasting is given in
Chapter-II.
28. Provide details about
transfer/allotment of mining lease,
extension of lease period etc. along
with authenticated copies of
orders for lease allotment /
transfer / extension of validity
period.
Originally the mining lease (Area 83.87ha.) was granted in favour of
Shri Ganga Ram Bairwa S/o Sh. Kalu Ram Bairwa resident of
Satalkheri, Tehsil- Ramganj Mandi District Kota.(Rajasthan)
Lease renewal order was given for 10 years on dated 20.01.1992 to
19.01.2002 after that it has extended up to the 19.01.2012.
About 40.63 ha lease area was surrendered on dated 20.01.2001.
After the death of Ganga Ram Bairwa the lease was transfer in
favour of Shri Pankaj kumar Bairwa S/o Shri Swaroop Chand
Bairwa.
And now the lease has been renewed up to the 19.01.2022.
(Annexure-I Office Order)
29. A balance sheet certified by a
Authorized Financial Expert to
clearly indicate the provision
made / amount spent for
EMP/ERP/CSR/ESR/
Safety/Labour welfare/ Legal
Obligations etc to be enclosed.
Balance sheet will be provided after getting EC, at the time of
submitting the compliance report.
30. PP should clearly mention in the
documents whether there is any
violation of provisions of EIA
Notification and inform at the start
of presentation (to be a part of
computer presentation also).
No any violation in respect to the EIA notification.
31. Used filter papers (Air monitoring)
along with photographs of the site
showing Air / Water sampling /
monitoring activity / equipment
used at each station should be
submitted. Original copies of
analysis report of all the relevant
data referred in the documents
should be enclosed.
Filter paper will be submitted at the time presentation. Photographs of Air/water/soil are enclosed in Chapter-III.
32 The information regarding the
work order/agreement issued by
the P.P. to the consultant
(Accredited from QCI/ NABET for
proposed project Sector) should
be submitted:-
1. Dispatch No. of the work
QCI-NABET Scheme for accreditation of EIA consultant organization.
Incorporate EIA report given page no-2.
Monitoring has been start on dated 4/3/2016
Postal Address is given in front page of report.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
24 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
order/agreement. 2. Date of issue of work
order. 3. Date of start of
air/water/other monitoring work (as applicable).
4. Postal address/ Email Address/ Fax Number/ Mobile Number and Landline Number of the P.P.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
25 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
CHAPTER - II
PROJECT DESCRIPTION
2.1 TYPE OF PROJECT
The proposed project is mining unit & it is proposed to produce 3, 21,699 TPA (ROM)
Limestone (building Stone) by opencast Mechanized method of mining.
2.2 NEED OF THE PROJECT
The proposed mining project falls in the area of the district Kota, Rajasthan devoid of
sufficient agriculture activities and other industrial growth. The earning sources of the
region are limited. Mineral wealth of this region as well as state Rajasthan provides the
employment opportunity to the people of the region /state. Mining is one of the major
core sector industries which play a crucial role in the process of country economic
development. Being a decorative stone, the principle use of this lime stone (Building
stone) is in flooring and wall tiles. There is sufficient demand in this region for the
purpose.
2.3 LOCATION OF THE PROJECT
The lease area falls on survey of India Toposheet No. 45P/14 & 54 D/2 and is situated
between:
Latitude N Longitude E
24°00'00"N to 24°39'30"N 76°12'96.0"E to 75°59'55.7"E
The project site is located 1.0 km from village Satalkhedi in S direction & 0.8 Km NE
direction from Pipakhedi. Tehsil headquarter Ramganj Mandi is as distance about 8.8
Km by road & district headquarter Kota is 70.8 km in North direction connected by
road. The nearest state highway of SH-9 B about 2.0 km in South direction from the
lease area. & NH- 12, 8.0 km in NE direction. Ramganj Mandi railway station is about
4.9 km from lease area & Nearest Airport Indore is about 251 km from the lease area.
(Refer Annexure-VII, copy of Aravalli letter)
Refer Annexure –VIII Copy of composite map
(Refer figure: 2.1 and 2.2 Location map and Key Plan)
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
26 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 2.1: LOCATION MAP
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
27 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 2.2: KEY PLAN OF THE LEASE AREA
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
28 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 2.3: GOOGLE IMAGE SHOWING GENERAL LOCATION OF THE LEASE AREA
FIGURE 2.4: GOOGLE IMAGE OF THE LEASE AREA WITH BOUNDARY PILLARS.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
29 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
2.2 DESCRIPTION OF LEASE AREA & MINING PROCESS
Nature of deposit
The lime stone deposit is sedimentary deposit. Bedding of lime stone area located in
the area. The upper layer of the lime stone is hard and weathered due to sum crack
and shrinkage cracks. The soil is varying in thickness from 3.0 m located at places over
the limestone (Building stone) deposit. The useable limestone layer is about 12meter
in thickness fractured limestone varying from 27 meter located above the hard
limestone layer. The recovery seems around 70% at places in the sanctioned area in
the belt.
Reserves available for proposed mining:
As per approved mining plan the reserves available for mining is given as under:
Mineable reserves
UNFC Quantity in Tonnes
Mineable proved
mineral 111
6098022.9
Mineable probable
mineral. 121
508168.8
Total 6606191.7
Life of mine- we are considering annual production of 3, 21,699 TPA (RoM)
Anticipated life = Minable reserve (Proved + Probable)/ Annual Production
=6606191.7/321699= 21 year.
Existing Working- The mining is being started from the existing pit. The Satalkhedi-
Pipakhedi limestone mine is being developed by opencast mining mechanized with
drilling and blasting. The mineral is lying on the sub surface therefore open cast
mining is obvious choice.
The bench parameters shall be for mineral-
1. Height-6m to 9m
2. Width – more than 6m-9m.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
30 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
The bench parameters shall be for O/B/Fracture-
1. Height-1m- 9m
2. Width – More than 1-9m.
Blasting:
Blasting with low charge of holes just to loosen the rocks is proposed in upper layers
to remove the hard overburden. The blasting shall be done by the authorized
contractor on contractual basis. These contractors have their own safety explosive
container as well as Explosive License
Broad blasting Parameters:
Length of Shot Holes 9.0m
Diameter of Shot Holes 4 inches
Spacing 4 m
Burden 3 m
Stemming 30 %
Sub grade drilling 1m
Types of explosive
Special gelation, Delay Detonator, Ordinary detonator, Elect detonator safety fuse
Red yet (DTH, TLD) R-Cord
Charges per hole & Powder factor Expected Powder factor(for light blasting) 8.0 tonnes kg
Quantity of ore broken per hole
=depth × Burden × spacing × Sp. Gravity
=9 × 3 × 4 ×2.7=259 tones
Explosive required per hole 259/8= 32kg
Sp. Gel. Per cartridge 9.6 kg
A.N.F.O. Per hole 22.4 kg
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
31 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
This mine is proposed to produce Lime Stone 321699 TPA (RoM). The year wise
proposed production of mineral as per the approved mining plan is given as under:
TABLE 2.1: DETAIL OF YEAR WISE PROPOSED PRODUCTION
Year Production
in MT (RoM)
Saleable
Mineral
tones
Waste
generat
ed from
the total
excavati
on (MT)
Sub
grade
in MT
Over
burden
form OB
benches
tonnes
Over
burden+
mineral
waste
tonnes
Strippin
g ration
Mineral:
waste
I 321697 225189 80424 16084 1026432 1106856 1:4. 915
II 321697 225189 80424 16084 712800 793224 1:3.522
III 321697 225189 80424 16084 712800 793224 1:3.522
IV 321697 225189 80424 16084 712800 793224 1:3.522
V 321697 225189 80424 16084 712800 793224 1:3.522
Total 1608485 1125945 402120 80420 3877632 4279752 --
Source: Approved mining plan The waste as OB in the area is top soil and fractured limestone . The soil cover in the
area varies from 3m fractured limestone varies from 27 m. This OB will be dumped at
mined out pit. This sub grade material will be stacked at earmarked site.
The total area covered by the sub grade mineral at the end of this mining plan will be
49645 Sqm. Height 6m
TABLE 2.2: DETAIL OF PROPOSED WASTE TO BE GENERATED FOR MINING OPERATION
S. No
Year I II III IV V Total
1. Fracture + mineral waste (MT)
80424 80424 80424 80424 80424 402120
2. Over Burden(MT)
1026432 712800 712800 712800 712800 3877632
3. Total Waste (1+2) MT
1106856 1106856 793224 793224 793224 4279752
4. In Cum 461190 330510 330510 330510 330510 1370730
5. Swell volume (Cum)
553428 396612 396612 396612 396612 2139876
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
32 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Source: Approved mining plan
Manpower required for the mining operation is given in the Table-2.3.
TABLE 2.3: DETAIL OF MANPOWER REQUIRED FOR MINING OPERATION
S. No. Manpower No’s 1 Mines Manger ( As per MMR, 1996) 1 2 Mining Mate/Foreman 2 3 Watchmen 2 4 Operators 4 4 Skilled labours/operators 50 5 Un- Skilled labours 50
Total 109 Total Man Power at the mine will be required 109 Nos.
As per approved mining plan detail of the mining machinery deployed or to be deployed is given in the Table-2.4 TABLE 2.4: DETAIL OF MACHINERY DEPLOYED OR TO BE DEPLOYED
Type of Machinery
Nos. Bucket Capacity in Cum.
Motive Power
Make H.P.
Dumper 6 10 tonner Diesel Tata 119 HP Water pump 1 - Diesel Local -
Compressor 1 75 CFM - Local - Jack Hammer 2 32 mm Diesel Local -
Excavator 2 1.2 m3 Diesel Local - JCB 1 - Diesel Escort -
Jiri Cutting m/c 8 - - --- - DG Set 2 125Kva Kriloskar
2.4 BASIC FACILITIES
Rest shelter: - Rest shelter cum office is present in lease area.
Water Requirement: - About 7.0 KLD water will be required. Which will be fulfil
through water tankers & wells.
TABLE 2.5WATER REQUIREMENT
Sr. No. Particulars Quantity KLD
1 Dust Suppression 2.0
2 Drinking 2.0
3 Green Belt 3.0
Total 7.0
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
33 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Washroom: washroom will be provided separately for male & female.
First Aid Box: A well-equipped first aid box will be provided.
Electricity: - No electricity is required. Fuel will be obtained from authorize public fuel
station. About 300 lt/day HSD will be used.
2.5PROPOSED SCHEDULE FOR APPROVAL AND IMPLEMENTATION
Following key approval has been taken from the concerned departments.
Approved Mining Plan with progressive mine closure plan for Limestone (M.L. 55/91)
over an area of 43.24 hect., near village-Satalkhedi-Pipakhedi, Tehsil –Ramganj Mandi &
District – Kota(Raj.) has been approved on 31/12/2013. (Refer Annexure III)
The project has applied for environment clearance as per requirements of EIA
notification SO 1533(E) dated 14.9.2006 and amendments made thereof and will be
implemented after the environment clearance is obtained.
**********
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
34 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
CHAPTER-III
DESCRIPTION OF THE ENVIRONMENT
3.1 STUDY AREA
In order to study the environmental baseline status of the prevailing conditions,
geographic area within 10 km radius from the lease area is defined as study area,
which is comprised of core zone and Buffer zone. Core zone is the total lease area of
43.24 ha, where mining has to be carried out whereas area around the lease periphery
is Buffer zone.
TABLE 3.1: STUDY AREA AT A GLANCE
S. No. Particulars Details General Particulars
1.1 Village Satalkhedi-Pipakhedi 1.2 Tehsil & District H.Q. Ramganjmandi 1.3 Latitude 24°39'27.45"N to 24°40'02.57"N
1.4 Longitude 75°59'56.64"E to 75°00'27.81"E
1.5 Toposheet No. 45P/14 & 54D/2 Demography
2.1 Total Population Male 77390 Female 70095
2.2 Literates 56327 2.3 No. of Household 30178 2.4 No. of Villages 34
Land use pattern (area in hectare) 3.1 Built up land 481.76 3.2 Crop land 9702.28 3.3 Fallow land 8203.53 3.4 Forest 10573.97 3.5 Scrub land 5358.53 3.6 Water Bodies 625.08 3.7 Grazing land 895.45 3.8 Mining area 1107.57
Total 36947.97 Climatology
4.1 Maximum temp. °C 47.0
4.2 Minimum temp. °C 13.4
4.3 Relative humidity % 12-78%
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
35 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
3.1.1 STUDY PERIOD
The baseline environmental monitoring was carried out during summer season of year
March to May 2016
3.1.2 ENVIRONMENTAL COMPONENTS
The various environmental components which are thoroughly studied during the
study period include:
Land Environment
Water Environment
Air Environment
Noise Environment
Biological Environment
Socio- Economic Environment
3.1.3 METHODOLOGY
The methodology for collection of baseline data for different environmental
component is based on the MoEF & CC and CPCB guidelines. The baseline information
on micro meteorology, ambient air quality, water quality, noise levels, soil quality and
floristic descriptions was collected by primary sampling / field studies during study
period. However secondary data have been obtained from government agencies and
other published sources.
3.2 ESTABLISHMENT OF BASELINE FOR VALUED ENVIRONMENT COMPONENT
Land Environment-
Land is the most vital resource for sustenance of the life and degradation of land due to
industrialization, urbanization and population growth is a matter of concern.
Therefore, it is necessary to establish the existing land use pattern to optimize land use
as well as minimize degradation due to development activities. The basic idea of land
use classification for the purpose of EIA study is to define the distribution of the
existing land according to its actual use. The land use pattern use indicated the manner
in which different part of land in the study area is being utilized and un-utilized. It is an
important indicator of environmental health and human activity.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
36 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
(A) Land use of study area (buffer zone)
The existing land use pattern in the study area has been studied through satellite
imagery and is divided into following categories:-
TABLE 3.2: LAND USE PATTERN BASED ON SATELLITE IMAGE
S. No. Class Names Area (Ha.) % (Area) i Built up land 481.76 1.31 ii Crop land 9702.08 26.26 iii Fallow land 8203.53 22.21 iv Forest 10573.97 28.62 v Scrub land 5358.53 14.51 Vi Water Bodies 625.08 1.68 vii Grazing land 895.45 2.42 Viii Mining area 1107.57 2.99
Total 36947.97 100 Refer Figure 3.1: Land Use / Land Cover Map Pattern of the Study Area.
Refer Figure 3.2: Satellite Image of 10 km Radius of the Study Area
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
37 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.1: LAND USE / LAND COVER MAP PATTERN OF THE STUDY AREA.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
38 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.2: SATELLITE IMAGE OF 10 KM RADIUS OF THE STUDY AREA
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
39 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
(B) Land use of lease area (Core Zone)
The detail of present land use of the lease area and proposed utilization for different
purpose of mining during operational and post operational phase is given in the table
below.
TABLE 3.3: LAND USE PLAN FOR PRE- OPERATIONAL, OPERATIONAL & POST -
OPERATIONAL PHASES (IN HECT.)
Note- About 15.9800 ha area has been already planted within lease for full fill 33%
plantation as per ToR compliance. At the end of mine life about 20.77 ha area will be
planted which includes 3.5400 Ha area will be planted on statuary barrier (7.5 Meter)
& 17.2396 ha area will be backfill planted. About 6.4804 ha area will be converted as
water storage.
(C) Topography& Drainage:
The area is having flat topography highest elevation of the area is 340 mRL and lowest
is 337 mRL. There is no river/nallah exist within the lease area. However general
drainage in the study area is defined by the Amjar Nadi- 9.3 km in NE direction, Ahu
Nadi-6.4 km in SE direction & Psadi Nadi 7.5 km in SW direction from mine site.
S. No. Particulars Pre Operational
(In Ha)
Operational (In Ha)
Post operational
(In Ha) A) Mining Activity 1 Mining pits 8.5215 10.5710 0.00 2 Road & building 2.3750 2.3750 0.00
3 Plantation on statuary barrier
0.0000 2.5500 3.5400
4 Mineral stack 1.5420 1.9540 0.0000 5 Water storage 1.2010 1.2010 6.4804
6 Reclamation & Backfilled Plantation
5.9800 5.9800 17.2396
7 Plantation on remaining lease area
15.9800 15.9800 15.9800
B) Remaining virgin land
7.6405 2.6290 0.000
Total 43.24 43.24 43.24
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
40 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.3: TOPOGRAPHY MAP OF THE STUDY AREA
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
41 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.4: DRAINAGE MAP OF THE STUDY AREA
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
42 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
(D) Regional Geology
The area from part of Kota & Chittorgarh district of Rajasthan. The NH-12 passes
through Mandana & Suket in the eastern part of the area & western Railway main line
also runs parallel with NH-12 Satalkhedi Village is connected to railhead at
Ramganjmandi.
Era/period Geological
Cycle
Group Sub
Group
Formation Litho logy
Meso
Neo-
Proterozoic
Vindhya
Super group
Lower Bhander
(Lakheri-Singoli)
Limestone formation
Limestone
(Dolomitic)
Ganurgarh Shale
Formation upper Rewa
(Taragarh fort-Umar)
Sandstone
Shale with
Limestone
Bands
Formation Quartzitic
Sandstone
Sandstone with
gritty &
conglomerate
bands
Rewa
Group
Jhiri (Ratangarh) Shale Shale with
Limestone
Kaimpur
Group
Chittaurgarh fort
(Dicken) Sandstone
formation
Quartzitic
Sandstone
Semi
Group
Suket shale formation Shale,
Limestone
interbeds,
Sandstone
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
43 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
The temperature falls below 100 C in winter while it reached 450 C in the summer.
The Vindhya Super group of Meso to Neo-Proterozoic age, represented by its four
group is exposed in the area. The oldest Semri Group is subdivided into the Khorip
sub-group, and is represented by the Suket Shale Formation, which is an assemblage of
shale with interbeds of lime stone.
The Rewa group, represented by the Jhiri Shale (Ratangarh Shale) and the upper Rewa
Sandstone (=Taragharh Fort Sandstone) Formations, Conformably overlies the kaimur
Sandstone.
The Jhiri/Ratangar Shale is thinly bedded to laminate splintery in nature and pale
yellow to khaki greeincolour. It contains thin bands and lenses of clay and dolomitic
Limestone. The limestone is often stromatolitic in pokets.
Local Geology: Bedding of lime stone area located in the area. The upper layer of the
lime stone is hard and weathered due to sum crack and shrinkage cracks. The soil is
varying in thickness from 3.0 m located at places over the limestone (Building stone)
deposit. The useable limestone layer is about 12meter in thickness fractured limestone
varying from 27 meter located above the hard limestone layer.
Local Geological succession for the area may be summarized -
Recent Group Litho logy
Lower Vindhyan Group Khorip Group
(Semri Group)
Upper Jhalrapatan (Suket) Shale/
limestone.
Source- Approved Mining Plan
(Refer figure3.5: surface geological plan and section of the lease area).
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
44 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.5: SURFACE GEOLOGICAL PLAN AND SECTION OF THE LEASE AREA
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
45 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
(e) Soil quality
The soils of the district are alluvial in nature. The soils in the district have been
classified as deep black clayey soils, deep brown clayey soils, deep brown loamy soils,
medium black clayey soils.
Methodology for soil monitoring
Soil samples from depth (0-15 cm) were collected from different sites in the study area
for estimation of the physicochemical characteristics of soil. Air-dried and Sieved
samples have been used for determination of physical properties of soil. Standard
methods were followed for the analysis of soil samples. Soil sampling location is given
in the table below.
TABLE 3.4: SOIL SAMPLING LOCATIONS IN THE STUDY AREA
S. No. Station Code. Station Name
1 S1 Pipakheri
2 S2 Satalkheri
3 S3 Suket
4 S4 Naharsingh
5 S5 Khairabad
6 S6 Savad khurd.
Refer Figure 3.6: Soil Sampling Location map of the study area.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
46 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.6: SOIL SAMPLING LOCATIONS IN THE STUDY AREA
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
47 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.7: PHOTOGRAPHS OF SOIL SAMPLING IN THE STUDY AREA
Pipakhedi Village
Naharsingh Village
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
48 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Soil Analysis Results
Soil analysis was carried out and the results are given in table below.
TABLE 3.5: ANALYSIS RESULTS OF SOIL SAMPLES
S. No
Parameters unit S1 S2 S3 S4 S5
S6
1 pH (1:2.5) -- 7.94 8.21 7.69 7.82 7.91 8.04
2
Electrical Conductivity of Saturation Extract (1:2)
µmhos/cm
317 293 241 329 314 286
3 Bulk Density gm/cc 1.15 1.24 1.34 1.42 1.23 1.21
4 Organic Matter
% 0.23 0.31 0.14 0.18 0.21 0.13
5 Available Nitrogen
Kg/Hect.
15.0
8 13.13 12.12 15.77
13.5
6 11.45
6 Available Phosphorus
Kg/Hect.
23.4
2 18.98 24.03 20.56
20.3
6 19.31
7 Available Potassium
Kg/Hect.
19.1
6 20.07 27.78 21.34
23.3
4 17.03
STANDARD SOIL CLASSIFICATION
S.NO. Parameter Classification 1. PH <4.5 extremely acidic
4.51-5.0 very strong acidic 5.01-5.5 strongly acidic 5.51-6.0 slightly acidic 6.51-7.3 Neutral 7.31-7.8 slightly alkaline 7.81-8.5 moderately alkaline 8.51-9.0 strongly alkaline >9.0 Very strongly alkaline
2. Salinity Electrical conductivity (mho/cm)
1 mho/cm=640 ppm
Up to 1.0 average 1-2 harmful to germination 2-3 harmful to crops
3. Nitrogen (Kg/ha) Up to 50 very less 51-100 less 110-150 good 151-300 better >300 sufficient
4. Phosphorus (kg/ha) Up to 15very less 15-30 less 31-50medium 51-65 on average sufficient 66-80 sufficient
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
49 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
>80 more than sufficient 5. Potassium (kg/ha) 0-120 very less
120-180 less 180-240 medium 241-300 average 301-360 better >360 more than sufficient
Results:
The result shows that soil is moderately alkaline in nature and less fertile.
3.3 WATER ENVIRONMENT
The assessment of present status of water quality within the study area was conducted
by collecting water from ground water & surface water sources during the period of
March 16 to May ’16. There is no perennial source of surface water body in the core
zone, however two rivers flows in study area. (Refer in drainage map of the study
area).
Surface Water- proposed waste rock dump sites are away from any seasonal water
stream. Thus there will be no impact of the mining in the natural flow of water and
drainage system in the existing area. The lessee shall make garland drain, retaining
walls, setting tank all around the pits and dumps. The rain water shall be utilized by
harvesting techniques.
Ground water- the water table in the area is 40m (in rainy season) 45m (in dry
season). Mining will be not intersecting in ultimate pit limit (303 mRL). The ground
water in the area is not likely to be effected at all.
HYDROGEOLOGY- Occurrence of ground water depends upon topography, physio
graphy and structural features of the geological formations. In Kota district, ground
water occurs in mainly four hydro geological formations. These hydro geological
formations are alluvium, sandstone, shale and limestone and among these formations
alluvium is the most important formation as it covers the maximum area and also it is
the most potential among different hydro-geological formations.
Source: CGWB Kota District Rajasthan
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
50 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.8: HYDROGEOLOGICAL MAP OF THE DISTRICT KOTA
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
51 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Depth to Water Level (Pre & Post Monsoon)
The ground water level of the mine is much below the level of the working thus,
groundwater table will not be intersected till reach to ultimate depth of working. The
ground water table in the lease area is 40m (in rainy season) to 45m (in dry season) &
highest elevation of the lease area 340 mRL and lowest elevation of the lease area is
337 mRL. The ground water in the area is not likely to be affected at all.
295 mRL (45mbgl Pre monsoon)
300mRL ( 40 mbgl Post monsoon)
WATER TABLE
303 mRL (37 mbgl)
ULTIMATE DEPTH
337 mRL (Lowest Contour)
GROUND LEVEL
Proposed working will not intersect Ground
water table.
340 mRL (Highest contour)
hiesest
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
52 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.8(A): DEPTH TO WATER TABLE PRE-MONSOON
FIGURE 3.8(B): DEPTH TO WATER TABLE POST-MONSOON
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
53 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
3.5.1 Ground water monitoring methodology
The quality of groundwater near the lease area and within the 10 km radius was
established. Six ground water samples were collected during the winter season and
characterized for physico-chemical parameters. The samples were taken as grab
sample and were analysed for various parameters and compared with standards IS:
10500. The locations of water sampling stations are given in table below.
TABLE 3.6: LOCATION OF WATER SAMPLING IN THE STUDY AREA
Station Code Location Remarks
GW1 Pipakhedi Ground Water GW2 Satalkhedi Ground Water GW3 Suket Ground Water GW4 Naharsinghi Ground Water GW5 Khairabad Ground Water GW6 Saavad khurd Ground Water
Refer Figure 3.9: Water sampling locations in the study area
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
54 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.9: WATER SAMPLING LOCATIONS MAP IN THE STUDY AREA
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
55 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.10: PHOTOGRAPHS OF WATER SAMPLING IN THE STUDY AREA
Pipakhedi Village
Naharsinghi Village
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
56 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
3.5.2 Analysis Report of Water Quality
TABLE 3.7: ANALYSIS RESULTS OF GROUND WATER SAMPLES
S. No. Parameter Unit IS Standard 10500
GW1 GW2 GW3 GW4 GW5 GW6 Acceptable Permissible
1 Color -- <5 <5 <5 <5 <5 <5 5 15
2 Odour -- Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable
3 Turbidity NTU <2 <2 <2 <2 <2 <2 1 5
4 pH value -- 7.35 7.28 7.36 7.67 7.59 7.55 6.5-8.5 No relaxation
5 Total Hardness (as CaCO3)
mg/l
314 276 312 348 286 334 200
600
6 Total Dissolved solids
mg/l
928 840 1048 1240 904 1068 500
2000
7 Alkalinity mg/l 230 220 250 320 180 229 200 600
8 Chlorides (as Cl)
mg/l 119.54 149.3 179.07 164.71 213.4 199.34 250 1000
9 Calcium (as Ca)
mg/l 67.38 67.42 112.12 122.49 64.37 87.16 75 200
10 Magnesium (as Mg)
mg/l 23.07 32.56 26.47 26.76 22.81 32.55 30 100
11 Sulphate (So4)
mg/l 45.27 60.87 51.19 41.38 47.26 66.08 200 400
12 Iron (as Fe) mg/l BDL BDL 0.34 BDL BDL BDL 0.3 No relaxation
13 Nitrate (as NO3)
mg/l 33.19 40.18 32.56 34.09 30.54 33.6 45 No relaxation
14 Fluoride (as F)
mg/l 0.45 0.13 0.57 0.67 0.78 1.04 1.0 1.5
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
57 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Conclusion:
Analysis of samples revels that water parameter like total hardness, TDS , calcium
magnesium, sulphate, nitrate, fluoride are within acceptable limit.
3.4 AMBIENT AIR ENVIRONMENT
3.4.1 Meteorology -Meteorological factors such as wind speed, direction variation in
temperature, humidity etc. play a direct role in dispersion of pollutants atmospheric
pressure, rainfall and cloud cover also govern this activity. In order to establish the
prevailing climatic condition, a meteorological monitoring station was installed in the
study area during the study period. Based on the site meteorological information
gathered during the monitoring period, wind rose diagram was generated to
understand the prevailing wind direction so as to anticipate the dispersion of
pollutants in the wind direction. Refer Figure 3.11: Wind Rose Diagram
FIGURE 3.11: WIND ROSE DIAGRAM
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
58 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
3.4.2 Climatology
Climate of the district can be classified as semi arid type. Normal rainfall in the district
for the period 1951- 2000 is 807.9 mm. However, average annual rainfall for the
period 2001 to 2011 is 652.17 mm.The summers are hot and dry and winters are cold.
The cold season prevails from December to February followed by hot season from
March to mid of June. After summers the rainy season starts with the onset of
monsoon rains lasting till the end of September. The period September to November
constitutes post monsoon period. . January is the coldest month with mean daily
maximum temperature at 24.3°C and a mean daily minimum temperature at 10.6°C.
Mean daily maximum temperature during summers is 43°C to 47 °C and mean daily
minimum temperature is 25°C to 29 °C & 2°C to 5°C in winter. The average rainfall is
900 mm most of the rain falls during the period of July to September.
3.4.3 Seismicity of the area:-
Many parts of the Indian Subcontinent have historically high Seismicity. Seven
catastrophic earth quakes of magnitude greater than 8 (Richter scale) have occurred in
the western, northern and eastern parts of India and adjacent countries in the past 100
years.
The mine site as well as study area lies in Zone –II of Seismic Zoning Map, and thus can
be said to be located in an area of low seismic hazard by national standards. Hence the
risk of earthquake at the site is minimal and so the site is safe.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
59 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
3.4.4 Ambient air quality monitoring
Ambient air quality monitoring was carried out during the study period (March to May
2016) to establish the ambient air quality. Sampling was carried out with the help of
reparable particulate matter Sampler “Reparable Dust Sampler” (RDS). The data
generated by M/s Udaipur Min-Tech Pvt. Ltd. for ambient air quality status within 10
km. radius of the lease area has been compiled along with meteorological conditions.
3.4.5 Location of Ambient Air Sampling Stations
Sampling locations were established for ambient air monitoring in and around the core
zone within a radius of 10.0 km, to study the present quality of the air. The monitoring
locations are marked in the map presented as fig.3.12. Location of sampling points
along with distance and direction with respect to lease area are given as under:
TABLE 3.8: LOCATION OF AMBIENT AIR MONITORING STATIONS
Station Code.
Station Name
Location with respect to Site
Distance (Km)
Direction
A1 Near Mine Site -- --
A2 500 D/w -- --
A3 Pipakhedi 0.8km NE
A4 Satalkhedi 1.0 km
S
A5 Suket 5.0 km
SE
A6 Naharsinghi 8.5 km
SE
A7 Khairabad 6.0 km SW
A8 Salvad khurd 5.5km NE
Refer Figure 3.12: Ambient air sampling location in the study area.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
60 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.12: AMBIENT AIR SAMPLING LOCATION IN THE STUDY AREA
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
61 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.13: PHOTOGRAPHS OF AMBIENT AIR MONITORING IN THE STUDY AREA
Naharsinghi Village
Satalkhedi Village
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
62 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
3.4.5 Sampling Schedule
Sampling was done 24/8 hourly from each station round the clock, twice a week for
continuous three month (Study period).
3.5.4. Air quality parameter
The following parameters were analysed for each sample.
- Particulate Matter (PM2.5)
- Particulate Matter (PM10)
- Sulphur dioxide (SO2)
- Nitrogen dioxide (NO2)
The sampling and testing of ambient air quality parameters were carried out as
per relevant parts of IS 5182. The brief details of testing method are given in below
table.
TABLE 3.9: PROCEDURE FOR DETERMINING VARIOUS AIR QUALITY PARAMETERS
Parameters Testing method
PM2.5 Lab SOP UM-A-10
PM10 IS: 5182 (P-23) 2006 RA 2012
SO2 IS: 5182 (P-2) 2006 (DL=3μg/m3 )
NO2 IS: 5182 (P-6) 1975 RA 2006
The detailed results of ambient air quality are given in table below:
TABLE 3.10 (A): MEAN TEMPERATURE & RELATIVE HUMIDITY
Month
Temperature
(°C)
Relative Humidity
(%)
Wind speed
Max. Min. Max. Min. Max. Min.
March, 16 38.2 13.0 78.0 20.0 16 0.2
April, 16 44.6 19.0 76.0 16.0 22 0.4
May, 16 46.6 24.2 74.0 14.0 32 0.6
Sources- IMD station Jhalawar
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
63 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
TABLE 3.10 (B): MEAN TEMPERATURE& RELATIVE HUMIDITY AT PROJECT SITE
Month
Temperature (°C)
Relative Humidity (%)
Wind Speed (m/hr.)
Max. Min. Max. Min. Max. Min.
March, 16 40.0 13.4 78.0 18.0 18 0.2 April, 16 44.0 18.0 74.0 16.0 21 0.1 May, 16 47.0 25.0 72.0 12.0 34 0.6
TABLE 3.11: AMBIENT AIR QUALITY RESULT
Result for Test parameter PM10/ PM2.5/ SO2/ NO2 A1) Near Mine Site S.No. Date PM2.5
(µg/m3 ) PM10 (µg/m3) SO2 (µg/m3) NO2 (µg/m3)
1. 02.03.16 23.51 61.11 3.0 5.17 2. 03.03.16 22.18 64.95 3.84 4.23 3. 10.03.16 20.23 58.49 4.11 5.18 4. 11.03.16 22.73 70.51 4.3 4.62 5. 18.03.16 24.48 71.03 4.08 5.31 6. 19.03.16 23.66 70.72 4.58 6.99 7. 26.03.16 25.84 67.67 3.19 4.75 8. 27.03.16 21.93 74.45 4.08 3.83 9. 03.04.16 21.02 69.29 3.18 4.02 10. 04.04.16 23.61 74.13 3.66 4.78 11. 11.04.16 23.84 62.18 4.43 6.53 12. 12.04.16 23.85 65.03 3.93 4.09 13. 19.04.16 25.52 68.08 3.07 7.14 14. 20.04.16 23.71 66.06 BDL 3.19 15. 27.04.16 22.64 78.7 5.05 6.25 16. 28.04.16 21.25 67.16 4.18 4.81 17. 01.05.16 21.77 76.2 3.32 3.93 18. 02.05.16 23.89 64.98 3.52 7.1 19. 10.05.16 20.32 68.44 4.22 6.39 20. 11.05.16 23.47 71.24 BDL 6.89 21. 18.05.16 24.61 66.81 4.74 6.1 22. 19.05.16 22.67 65.88 4.91 5.7 23. 26.05.16 25.61 73.88 3.74 4.1 24. 27.05.16 23.09 66.69 3.52 6.47
Min. 20.23 58.49 BDL 3.19 Max. 25.84 78.7 5.05 7.14 Avg. 23.14 68.49 3.82 5.32
Method
Reference Lab-SOP UM-
A-10 IS: 5182 (P-23)
2006 IS: 5182 (P-2)
2001 ( DL=3.0 µg/m3)
IS: 5182 (P-6) 2006
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
64 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Result for Test parameter PM10/ PM2.5/ SO2/ NO2 A2) 500 m D/w S.No. Date PM2.5
(µg/m3 ) PM10 (µg/m3) SO2 (µg/m3) NO2 (µg/m3)
1. 02.03.16 23.73 71.21 BDL 4.72 2. 03.03.16 22.56 69.51 3.85 5.13 3. 10.03.16 23.09 72.45 3.19 4.9 4. 11.03.16 21.35 69.72 4.23 5.03 5. 18.03.16 20.28 62.76 4.07 3.83 6. 19.03.16 21.31 58.8 4.02 4.98 7. 26.03.16 25.05 74.49 3.47 4.92 8. 27.03.16 25.73 63.37 4.84 5.97 9. 03.04.16 24.55 70.53 3.03 3.23 10. 04.04.16 23.96 59.65 4.43 4.69 11. 11.04.16 21.03 68.32 3.11 5.23 12. 12.04.16 20.05 63.67 4.04 4.84 13. 19.04.16 24.47 62.08 BDL 6.04 14. 20.04.16 25.96 68.9 4.33 4.58 15. 27.04.16 20.79 74.94 3.8 5.82 16. 28.04.16 23.21 63.84 4.23 4.09 17. 05.05.16 22.48 69.62 3.11 3.35 18. 06.05.16 19.75 59.67 3.08 4.16 19. 13.05.16 23.13 67.04 4.27 4.36 20. 14.05.16 21.04 64.88 BDL 3.05 21. 21.05.16 22.13 63.98 4.38 4.04 22. 22.05.16 25.21 61.47 4.43 4.52 23. 29.05.16 20.89 66.78 3.04 5.14 24. 30.05.16 23.44 65.19 4.51 6.37
Min. 19.75 58.8 BDL 3.05 Max. 25.96 74.94 4.84 6.37 Avg. 22.72 66.37 3.75 4.71
Method Reference
Lab-SOP UM-A-10
IS: 5182 (P-23) 2006
IS: 5182 (P-2) 2001
( DL=3.0 µg/m3)
IS: 5182 (P-6) 2006
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
65 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Result for Test parameter PM10/ PM2.5/ SO2/ NO2 A3) “ Pipakhedi Village” S.No. Date PM2.5
(µg/m3 ) PM10 (µg/m3) SO2 (µg/m3) NO2 (µg/m3)
1. 01.03.16 24.54 69.65 3.03 4.03 2. 02.03.16 22.63 69.05 BDL 6.19 3. 09.03.16 24.96 75.47 BDL 5.45 4. 10.03.16 20.87 69.11 3.64 7.91 5. 17.03.16 24.93 68.84 4.18 4.98 6. 18.03.16 19.48 59.54 4.69 5.01 7. 25.03.16 23.85 67.41 3.73 4.28 8. 26.03.16 21.84 65.91 4.25 3.10 9. 02.04.16 24.7 67.28 4.33 5.98 10. 03.04.16 25.11 74.68 BDL 4.49 11. 10.04.16 22.95 66.01 4.18 6.35 12. 11.04.16 21.99 67.06 3.57 3.29 13. 18.04.16 23.6 68.78 BDL 7.01 14. 19.04.16 22.85 65.36 4.49 4.75 15. 26.04.16 20.22 60.08 3.00 5.58 16. 27.04.16 23.67 65.22 5.08 6.35 17. 03.05.16 24.65 70.81 4.27 7.10 18. 04.05.16 22.37 68.38 BDL 3.61 19. 10.05.16 23.88 65.25 3.52 5.62 20. 11.05.16 24.73 74.06 BDL 3.12 21. 17.05.16 20.59 66.74 4.91 4.46 22. 18.05.16 20.05 60.43 5.15 5.33 23. 25.05.16 22.13 67.52 4.79 6.17 24. 26.05.16 23.28 65.73 3.52 4.57
Min. 19.48 59.54 BDL 3.1 Max. 25.11 75.47 5.15 7.91 Avg. 22.91 67.43 3.74 5.20
Method Reference
Lab-SOP UM-A-10
IS: 5182 (P-23) 2006
IS: 5182 (P-2) 2001
( DL=3.0 µg/m3)
IS: 5182 (P-6) 2006
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
66 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Result for Test parameter PM10/ PM2.5/ SO2/ NO2 A4) “Satalkhedi Village ” S.No. Date PM2.5
(µg/m3) PM10 (µg/m3) SO2 (µg/m3) NO2 (µg/m3)
1. 04.03.16 26.05 62.18 BDL 3.13 2. 05.03.16 23.79 66.25 3.39 4.74 3. 12.03.16 25.06 65.53 4.10 3.99 4 13.03.16 19.9 62.53 BDL 6.96 5 20.03.16 24.24 70.51 4.26 4.56 6 21.03.16 25.3 70.71 3.35 6.04 7 28.03.16 23.61 68.61 BDL 5.57 8 29.03.16 25.06 66.47 3.51 5.04 9 02.04.16 23.67 63.93 3.11 5.16
10 03.04.16 20.37 62.71 4.54 6.90 11 10.04.16 24.46 70.27 3.03 3.02 12 11.04.16 21.72 68.45 BDL 7.20 13 18.04.16 23.82 64.21 3.80 5.78 14 19.04.16 25.06 77.47 4.23 7.98 15 26.04.16 25.62 69.16 3.80 6.20 16 27.04.16 23.09 70.47 BDL 5.98 17 06.05.16 26.09 69.49 3.61 5.33 18 07.05.16 23.09 67.09 4.17 4.46 19 13.05.16 20.19 64.66 BDL 6.54 20 14.05.16 24.59 67.08 4.79 5.36 21 2105.16 22.69 70.48 3.57 3.13 22 22.05.16 25.31 75.37 4.91 4.46 23 29.05.16 21.03 66.66 BDL 7.10 24 30.05.16 19.67 62.18 3.44 5.70
Min. 19.67 77.47 BDL 3.02 Max. 26.09 67.76 4.91 7.98 Avg. 23.48 3.46 5.43
Method Reference
Lab-SOP UM-A-10
IS: 5182 (P-23) 2006
IS: 5182 (P-2) 2001
( DL=3.0 µg/m3)
IS: 5182 (P-6) 2006
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
67 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Result for Test parameter PM10/ PM2.5/ SO2/ NO2 A5) “Suket ”
S.No. Date PM2.5
(µg/m3) PM10 (µg/m3) SO2 (µg/m3) NO2 (µg/m3)
1. 02.03.16 23.64 72.83 BDL 5.74 2. 03.03.16 25.06 78.78 4.07 4.89 3. 10.03.16 21.87 68.62 3.10 7.52 4 11.03.16 24.24 71.51 4.95 3.02 5 18.03.16 22.82 69.55 3.27 6.19 6 19.03.16 20.32 62.59 BDL 5.55 7 26.03.16 21.94 66.25 4.18 3.92 8 27.03.16 24.36 64.30 3.43 4.86 9 03.04.16 21.76 75.89 3.11 3.30
10 04.04.16 22.85 66.44 BDL 5.18 11 11.04.16 23.89 67.60 4.23 6.23 12 12.04.16 24.91 67.73 4.33 4.38 13 19.04.16 20.11 68.79 3.11 8.06 14 20.04.16 19.86 61.56 2.28 4.87 15 27.04.16 24.61 68.65 3.00 7.97 16 28.04.16 19.03 62.63 4.23 3.11 17 05.05.16 19.94 63.04 4.17 3.85 18 06.05.16 24.13 65.36 BDL 7.18 19 13.05.16 23.44 65.52 4.17 4.46 20 14.05.16 25.06 73.93 BDL 3.13 21 21.05.16 21.91 66.68 3.36 4.96 22 22.05.16 22.09 65.15 3.48 6.80 23 29.05.16 24.32 67.93 BDL 3.85 24 30.05.16 20.55 64.49 4.03 5.90
Max. 19.03 61.56 BDL 3.02 Min. 25.06 78.78 4.95 8.06 Avg. 22.61 67.74 3.39 5.21 Method
Reference Lab-SOP UM-
A-10 IS: 5182 (P-23)
2006 IS: 5182 (P-2)
2001 ( DL=3.0 µg/m3)
IS: 5182 (P-6) 2006
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
68 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Result for Test parameter PM10/ PM2.5/ SO2/ NO2 A6) “Naharsinghi ” S. No. Date PM2.5
(µg/m3) PM10 (µg/m3) SO2 (µg/m3) NO2 (µg/m3)
1. 04.03.16 22.51 69.17 3.05 3.06 2. 05.03.16 25.18 67.27 3.22 4.89 3. 12.03.16 24.1 67.35 4.08 4.13 4 13.03.16 25.17 75.48 4.10 5.70 5 20.03.16 25.68 66.63 5.01 5.10 6 21.03.16 19.62 62.00 3.03 8.06 7 28.03.16 25.17 67.82 4.91 4.58 8 29.03.16 23.83 67.66 BDL 4.46 9 02.04.16 22.38 67.28 3.03 3.23
10 03.04.16 25.25 62.78 BDL 4.81 11 10.04.16 26.01 69.82 4.60 7.20 12 11.04.16 23.69 70.95 BDL 3.89 13 18.04.16 22.85 69.37 5.05 6.45 14 19.04.16 21.18 67.28 3.07 4.10 15 26.04.16 24.66 62.60 4.49 4.75 16 27.04.16 20.14 60.92 BDL 6.89 17 01.05.16 23.88 62.83 BDL 4.05 18 02.05.16 25.4 61.83 4.27 6.89 19 09.05.16 22.43 62.78 3.44 3.02 20 10.05.16 25.67 80.77 4.08 4.16 21 17.05.16 19.68 62.72 3.32 5.69 22 18.05.16 25.81 65.72 4.22 8.26 23 25.05.16 22.95 63.80 3.84 7.49 24 26.05.16 24.94 59.45 4.33 6.54
Min. 19.62 59.45 BDL 3.02 Max. 26.01 80.77 5.05 8.26 Avg. 23.67 66.43 3.68 5.28 Method
Reference Lab-SOP UM-
A-10 IS: 5182 (P-23)
2006 IS: 5182 (P-2)
2001 ( DL=3.0 µg/m3)
IS: 5182 (P-6) 2006
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
69 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Result for test parameter PM10/ PM2.5/ SO2/ NO2 A7) “Khairabad ” S. No. Date PM2.5
(µg/m3) PM10 (µg/m3) SO2 (µg/m3) NO2 (µg/m3)
1 02.03.16 24.65 62.07 3.24 3.56 2 03.03.16 22.37 66.24 3.39 4.74 3 10.03.16 23.88 68.04 4.10 3.99 4 11.03.16 24.73 73.45 BDL 6.96 5 18.03.16 20.59 64.83 4.26 4.56 6 19.03.16 20.05 64.58 3.35 6.04 7 26.03.16 22.13 64.28 BDL 5.57 8 27.03.16 23.28 65.69 3.51 5.04 9 01.04.16 22.38 64.49 3.09 3.25
10 02.04.16 25.25 69.70 4.18 4.43 11 9.04.16 26.01 68.00 3.22 6.88 12 10.04.16 23.69 67.08 3.30 4.07 13 17.04.16 22.85 70.48 5.02 6.19 14 18.04.16 21.18 75.37 BDL 5.16 15 25.04.16 24.66 66.66 4.23 5.50 16 26.04.16 20.14 65.68 3.10 5.31
17 03.05.16 24.54 62.98 3.09 3.35 18 04.05.16 22.63 61.72 3.61 4.23 19 11.05.16 24.96 64.97 3.17 4.81 20 12.05.16 20.87 68.07 3.81 5.20 21 18.05.16 24.93 65.46 4.79 3.89 22 19.05.16 19.48 76.65 3.57 5.45 23 26.05.16 23.85 65.31 4.41 5.10 24 27.05.16 21.84 66.53 3.02 4.75
Min. 19.48 61.72 BDL 3.25 Max. 26.01 76.65 5.02 6.96 Avg. 22.96 67.01 3.46 4.94
Method
Reference Lab-SOP UM-
A-10 IS: 5182 (P-23)
2006 IS: 5182 (P-2)
2001 ( DL=3.0 µg/m3)
IS: 5182 (P-6) 2006
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
70 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Result for Test parameter PM10/ PM2.5/ SO2/ NO2 A8) “Salvad khurd” S. No. Date PM2.5
(µg/m3) PM10 (µg/m3) SO2 (µg/m3) NO2 (µg/m3)
1. 04.03.16 21.73 65.21 3.57 4.72 2. 05.03.16 22.56 62.51 3.85 5.13 3. 12.03.16 23.09 62.45 3.19 4.9 4 13.03.16 21.35 69.72 4.23 7.03 5 20.03.16 20.28 62.76 3.07 3.83 6 21.03.16 21.31 58.8 4.02 4.98 7 28.03.16 25.05 74.49 BDL 4.92 8 29.03.16 25.73 63.37 4.84 5.97 9 02.04.16 24.55 70.53 3.03 3.23
10 03.04.16 23.96 59.65 4.43 4.69 11 10.04.16 21.03 68.32 3.11 7.23 12 11.04.16 20.05 63.67 4.04 4.84 13 18.04.16 24.47 62.08 BDL 6.04 14 19.04.16 25.96 68.9 4.33 4.58 15 26.04.16 20.79 74.94 3.8 6.82 16 27.04.16 23.21 63.84 3.23 4.09 17 06.05.16 22.48 69.62 3.11 3.35 18 07.05.16 19.75 59.67 3.08 4.16 19 13.05.16 23.13 67.04 4.27 4.36 20 14.05.16 21.04 64.88 BDL 8.05 21 2105.16 22.13 63.98 3.38 4.04 22 22.05.16 25.21 71.47 4.43 4.52 23 29.05.16 20.89 66.78 3.04 5.14 24 30.05.16 23.44 65.19 4.51 6.37
Min. 19.75 58.8 BDL 3.23 Max. 25.96 74.94 5.07 8.05
Avg. 22.63 65.83 3.66 5.12 Method
Reference Lab-SOP UM-
A-10 IS: 5182 (P-23)
2006 IS: 5182 (P-2)
2001 ( DL=3.0 µg/m3)
IS: 5182 (P-6) 2006
Source: M/S Udaipur Min- Tech Pvt. Ltd. (Analytical & Testing division NABL approved Lab T-3257)
The observed range of various parameters recorded, have been compared with the
National Ambient Quality Standards laid down by the Central Pollution Control Board.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
71 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
TABLE 3.12: COMPARISON OF AIR MONITORING RESULTS
S. No
Result A1 A2 A3 A4 A5 A6 A7 A8
PM2.5 1 Minimum 20.23 19.75 19.48 19.67 19.03 19.62 19.48 19.75 2 Maximum 25.84 25.96 25.11 26.09 25.06 26.01 26.01 25.96 3 Average 23.14 22.72 22.91 23.48 22.61 23.67 22.96 22.63 4 98% 25.34 25.44 24.60 25.56 24.55 25.48 25.48 25.44
PM10 1 Minimum 58.49 58.80 59.54 62.18 61.56 59.45 61.72 58.8 2 Maximum 78.70 74.94 75.47 77.47 78.78 80.77 76.65 74.94 3 Average 68.49 66.37 67.43 67.76 67.74 66.43 67.01 65.83 4 98% 77.12 73.44 73.96 75.92 77.20 79.15 75.11 73.44
SO2 1 Minimum BDL BDL BDL BDL BDL BDL BDL BDL 2 Maximum 5.05 4.84 5.15 4.91 4.95 5.05 5.05 5.07 3 Average 3.82 3.75 3.74 3.46 3.39 3.68 3.46 3.66 4 98% 4.94 4.74 5.04 4.81 4.85 4.94 4.94 4.96
NO2 1 Minimum 3.19 3.05 3.1 3.02 3.02 3.02 3.25 3.23 2 Maximum 7.14 6.37 7.91 7.98 8.06 8.26 6.96 8.05 3 Average 5.32 4.71 5.20 5.43 5.21 5.28 4.94 5.12 4 98% 6.99 6.24 7.75 7.82 7.89 8.09 6.82 7.88
3.4.6 Interpretation of Ambient Air quality.
PM10 level in the study area:
The minimum value of PM10 recorded in the core zone is 58.49µg/m3 and maximum
80.77 µg/m3 at Naharsinghi village in buffer zone.
PM2.5 level in the study area:
The minimum value of PM2.5 recorded in the core zone is 19.03 µg/m3 at Suket village
and maximum 26.09µg/m3 in buffer zone at Satalkhedi village.
SO2 level in the study area:
During study period, the concentration of sulphur dioxide is BDL & maximum 5.15
µg/m3 at Pipakhedi village.
NO2 level in the study area:
The concentration of nitrogen dioxide recorded in core zone ranges between 3.02
µg/m3 & 8.26 µg/m3 Naharsinghi village.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
72 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
3.5 NOISE ENVIRONMENT
The noise level monitoring in the study area was done at the ambient air monitoring
locations. Monitoring was done as per the CPCB guideline. The noise monitoring
results were compared with the Ambient Noise Quality Standard notified under
Environment (Protection) Act, 1986.
3.5.1 Monitoring Methodology of Noise Level
Noise standards have been designated for different types of land use, i.e. residential,
commercial, industrial and silence zones, as per ‘The Noise Pollution (Regulation and
Control) Rules, 2000, Notified by the Ministry of Environment and Forests, New Delhi
on February 14, 2000’. Different standards have been stipulated during day time (6 am
to 10 pm) and night time (10 pm to 6 am). The noise analysis within the study area
was recorded using Lutron sound level meter.
The noise rating method as Leq i.e. equivalent sound pressure level has been adopted
for the measurement of noise level in various selected sampling locations of this
region. It is the energy means of the noise level over a specified period and is
expressed in terms of decibels.
3.5.2 Location of noise monitoring stations
The location of Noise level monitoring is presented in below table.
TABLE 3.13: LOCATION OF NOISE MONITORING STATIONS
Station Code.
Station Name Location with respect to Site Distance (Km) Direction
N1 Near Mine Site -- -- N2 500 D/w -- -- N3 Pipakhedi 0.8km NE N4 Satalkhedi 1.0 km S N5 Suket 5.0 km SE N6 Naharsinghi 8.5 km SE N7 Khairabad 6.0 km SW N8 Salvad khurd 5.5km NE
Refer Figure 3.14: Map for noise monitoring& traffic density station in the study
Area.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
73 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.14: NOISE MONITORING LOCATION MAP
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
74 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.15: PHOTOGRAPHS OF NOISE & TRAFFIC MONITORING IN THE STUDY ARE
Satalkhedi Village
Naharsinghi Village
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
75 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
3.5.3 Noise Level Results
The noise monitoring within the study area was recorded using sound level meter
and results are given in the table below:
TABLE 3.14: NOISE LEVEL WITHIN THE STUDY AREA (Unit – dBA)
Source: M/S Udaipur Min-Tech Pvt. Ltd. TABLE 3.15: CPCB NOISE STANDARD
Category of Zones Leq in dB (A) Day Night
Industrial 75 70 Commercial 65 55 Residential 55 45
Silence Zone 50 40 a. Day time is from 6.00 Am to 10.00PM. b. Night time is reckoned between 10.00 PM to 6.00AM c. Silence zone is defined as an area up to 100m around premises of hospitals, educational institution and courts. Use of vehicle horn, loudspeaker and bursting of crackers is banned in these zones. Note: Mixed categories of areas be declared as one of the four above mentioned categories by the competent Authority and the corresponding standards shall apply.
Conclusion
During the study period ambient noise level were monitored and observed maximum
level was: 53.7dB at Suket village during day time & minimum was 41.9 at Khairabad
during night time.
All monitoring reports are attached as ANNEXURE-X
S. No
Location Average Day noise level (dBA)
Average Night noise level (dBA)
A1 Near Mine Site 50.6 42.8 A2 500 D/w 49.3 41.5 A3 Pipakhedi 51.5 42.7 A4 Satalkhedi 52.2 43.1 A5 Suket 53.7 44.3 A6 Naharsinghi 51.8 43.5 A7 Khairabad 52.4 41.9 A8 Salvad khurd 51.6 42.6
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
76 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
3.6 TRAFFIC DENSITY:
One route shall be taken for transported the material from mine site.
EXISTING TRAFFIC SCENARIO & LOS S. No.
Road V C Existing V/C
Ratio LOS
1 Satalkhedi 450 3,000 0.15 A
2 SH 9B to NH-12 1500 8,000 0.15 A
V= Volume of Vehicles in PCU’s/day & C = Capacity of Highway in PCU’s/ day.
V/C LOS Performance 0.0 - 0.2 A Excellent 0.2 - 0.4 B Very Good 0.4 - 0.6 C Good / Average / Fair 0.6 - 0.8 D Poor 0.8 - 1.0 E Very Poor
Note: Capacity as per IRC: 64-199
DURING MINE OPERATION Particulars Details Proposed Capacity of mine/annum 3,21,699TPA No. of working days 300 Proposed Capacity of mine/day 1072 TPD Dumper Capacity 10 Tones No. of dumper deployed/day 6 No of trips 17 Considering both loaded & empty tractor trolleys Increase in PCU/day will be
102PCUs
MODIFIED TRAFFIC SCENARIO & LOS
Road V C Modified V/C Ratio
LOS
Chechat 552 3,000 0.18 A SH 9B to NH-12 1602 8,000 0.2 A
From the above analysis it can be seen that the V/C ratio is likely to change to 0.18 & 0.2
with LOS being A’’ which is Excellent, as per classification. So the additional load on the
carrying capacity of the concerned roads is not likely to have any adverse effect.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
77 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.16: TRANSPORTATION ROUT MAP
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
78 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
3.7 BIOLOGICAL ENVIRONMENT
The biological study of the area has been conducted in order to understand the
ecological status of the existing flora and fauna to generate baseline information and
evaluate the probable impacts on the biological environment.
The objectives of this study were as follows:
To conduct detail study for floral/faunal/avifaunal elements in the study area of proposed project site.
To assess scheduled species in the proposed site. (Rare, endangered, critically
endangered, endemic and vulnerable).
To identify locations and features of ecological significance
To collect Baseline data for the study area along with a description of the existing terrestrial, wetland and aquatic vegetation.
Type of forest in area- Mixed Miscellaneous Forests is found in regions. The main
species found in this kind of forest are Anogeissus pendula, Anogeissus latifolia,
Terminalia tomentosa, Terminalia arjuna, Terminalia chebula, Albizia lebbeck,
Dalbergia paniculata etc. and its associates.
FOREST WITHIN 10 KM RADIUS
Sr. NO.
RESERVED & PROTECTED
FOREST
DIRECTION DISTANCE
1. Kuttepur PF NW 6.1 KM. 3. Suket RF E 7.0KM 4. Salvad RF NE 3.9KM 2. Basyaheri PF SE 5.3 Km
Flora: The floral study is done by quadrate method. In core zone 5 quadrate is taken
and in buffer zone 25 quadrate depending upon density, frequency and abundance of
trees, shrubs etc. Further the percentage values of relative frequency, density and
abundance are summed up together and this value is designates as IVI.
The present study on the floral assessment for the proposed project activity is based
on extensive field survey of the area. The study has been conducted in winter season.
The plant species were identified with the help of taxonomists of related fields and
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
79 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
nearby Institutions. Besides the collection of plant species, information was also
collected with vernacular names of plant species made by local inhabitants. In this
process the whole study area was divided into different sections to get the maximum
diversity of plant species. The sampling sites were selected based on land use pattern,
topography and floristic composition of the study area. Data on forest type legal
status and their extent in the study area has been collected from forest department.
The other relevant data on bio-diversity, like economically important plant species
and medicinal plant, Rare and endangered species in the study area have been
collected from secondary sources like forest and wild life departments.
In the core zone vegetation is dominated by Calotropis Procera, Zizyphus nummularia
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
80 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIGURE 3.17: BIOLOGICAL SAMPLING LOCATION MAP OF THE STUDY AREA
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
81 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
FIG 3.18 PHOTOGRAPHS OF VEGETAION
Calotropis procera
Accacia nilotica
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
82 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
TABLE 3.16: LIST OF FLORAL SPECIES OBSERVED IN CORE ZONE
S. No BOTANICAL NAME COMMON NAME FAMILY
1 Prosopis juliflora Babool Fabaceae 2 Zizyphus nummularia Bor Rhamnaceae 3 Calotropis procera Akdo Asclepiadaceae 4 Echinops echinatus Untkantili Asterales 5 Acacia nilotica Desi babool Fabaceae 6 Azadirachta indica Neem Meliaceae
Source: By Field Expert during study period.
TABLE 3.17: LIST OF FLORAL SPECIES OBSERVED IN BUFFER ZONE
S. No BOTANICAL NAME COMMON NAME FAMILY
Trees 1. Acacia leucophloea Harmo Fabaceae 2. Acacia nilotica Desi baval Fabaceae 3. Aegle marmelos Bel patra Rutaceae 4. Ailanthus excels Arduso Simaroubaceae 5. Albizia lebbeck Siras Fabaceae 6. Albizia procera Kala Siras Fabaceae 7. Anogeissus latifolia Dhavdo Combretaceae 8. Azadirachta indica Limdo Meliaceae 9. Bauhinia racemosa Asitaro Fabaceae 10. Bombax ceiba Simlo Bombacaceae 11. Cassia fistula Garmalo Caesalpiniaceae 12. Cassia siamea Kesia Fabaceae 13. Dalbergia sissoo Shisham Fabaceae 14. Emblica officinalis Amla Euphorbiaceae 15. Ficus benghalensis Vad Moraceae 16. Ficus religiosa Piplo Moraceae 17. Mangifera indica Aam Anacardiaceae 18. Polyalthia longifolia Ashoka Annonaceae 19. Prosopis juliflora Gandobaval Fabaceae 20. Syzygium cumini Jambun Myrtaceae 21. Tamarindus indica Khati Amli Fabaceae 22. Zizyphus mauritiana Bor Rhamnaceae 23. Phoenix sylvestris Khajur Arecaceae 24. Butea monosperma Khakhra Fabaceae
Shrubs 25. Annona squamosa Sitafal Annonaceae 26. Argemone Mexicana Pila Dhatura Papaveraceae 27. Calotropis gigantean Shivark, Akdo Apocynaceae 28. Calotropis procera Mudar Asclepiadaceae
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
83 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
S. No BOTANICAL NAME COMMON NAME FAMILY
29. Ipomoea fistulosa Beshram Convolvulaceae 30. Jatropha curcas Ratanjyot Euphorbiaceae
31. Lantana camara Lantana Verbenaceae
32. Bougainvillea spectabilis Nyctaginaceae Boganvel
Herbs 33. Cassia tora Puwad, Panwar Fabaceae 34. Datura inoxia Dhatura Solanaceae 35. Parthenium hysterophorus Gajar Ghaas Asteraceae 36. Tribulus terrestris Gokharu Zygophyllaceae 37. Tridax procumbens Kumru Asteraceae 38. Zizyphus nummulaira Ber Rhamnaceae 39. Echinops echinatus Untkantili Asterales
Grass 40. Cymbopogon martini Lemon grass Poaceae 41. Cynodon dactylon Dub Poaceae 42. Sida cordifolia Bala Malvaceae 43. Cenchrus ciliaris Jhino dhamramnu Poaceae
Fauna: The study of fauna takes substantial amount of time to understand the specific
faunal characteristics of the area. The assessment of fauna have been done on the bases
secondary data collected from different government offices like forest department,
wildlife department etc. The presence of wildlife was also confirmed from the local
inhabitants depending on the animal sightings and the frequency of their visits in the
project area. In addition review of secondary data was another source of information
for studying the fauna of the area. In addition the following sources were also used.
Sighting during ecological studies
Animal call
Foot mark and excreta
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
84 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
TABLE 3.18: LIST OF FAUNA SPECIES OBSERVED IN THE CORE ZONE
S. No. Scientific
Name
Common
Name Family
Status in
Wildlife
Protection
Act-1972
Status in
IUCN
Category
1. Funambulus
pennanti
Five Striped
Palm Squirrel
Sciuridae Schedule IV Least Concern
2. Herpestes
edwardsi
Mongoose Herpestidae Schedule II Least Concern
3. Lepus nigricollis Indian Hare Leporidae Schedule IV Least Concern
4. Hanuman langur Semnopithecu
s entellus
Cercopithecid
ae
Schedule II Least Concern
5. Rattus rattus Black Rat Muridae Schedule V Least Concern
6. Rousettus
leschenaulti
Chamgadar Pteropodidae Schedule V Least Concern
7. Hemidactylus
brooki gray
House lizard Gekkonidae Not Enlisted Not Evaluated
8. Hemidactylus
maculates
Rock gaeko Gekkonidae Not Enlisted Not Evaluated
09. Acridotheres
ginginianus
Bank Myna Sturnidae Schedule IV Least Concern
10
Acridotheres
tristis
Common Myna Sturnidae Schedule IV Least Concern
11. Corvus
macrorhynchos
Jungle Crow Corvidae Not Enlisted Least Concern
12. Columba livia Blue Rock
Pigeon
Columbidae Not Enlisted Least Concern
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
85 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
TABLE 3.19: LIST OF FAUNAL SPECIES OBSERVED IN BUFFER ZONE
S.
No. Scientific Name
Common
Name Family
Status in
Wildlife
Protection
Act-1972
Status in
IUCN
Category
1. Boselaphus
tragocamelus
Nilgai Bovidae Schedule III Least Concern
2. Canis aureus Jackal Canidae Schedule III Least Concern
3. Funambulus
pennanti
Five Striped
Palm Squirrel
Sciuridae Schedule IV Least Concern
4. Herpestes
edwardsi
Mongoose Herpestidae Schedule II Least Concern
5. Lepus nigricollis Indian Hare Leporidae Schedule IV Least Concern
6. Hanuman langur Semnopithecu
s entellus
Cercopithecid
ae
Schedule II Least Concern
7. Rattus rattus Black Rat Muridae Schedule V Least Concern
8. Rousettus
leschenaulti
Chamgadar Pteropodidae Schedule V Least Concern
9. Sus scrofa Wild boar Suidae Schedule III Least Concern
11. Hemidactylus
brooki gray
House lizard Gekkonidae Not Enlisted Not Evaluated
12 Bufo bufo Toad Bufonidae Not Enlisted Least Concern
13 Ptyas mucosus Common Rat
Snake
Colubridae Schedule IV Not Evaluated
Avifauna
During Birds survey actual counts of birds were made following the standard survey
technique. Observations were made during a walk through in the chosen transect for
sighting birds. The number of birds observed in each sampling location was directly
counted and listing was made. Birds were noted, counted and identified with the help of
8X40 “Optima Zenith” binocular and standard field identification guides
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
86 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
TABLE 3.20: LIST OF AVIFAUNAL SPECIES OBSERVED IN THE STUDY AREA
S. No. Scientific Name Common Name
Conservation Status as Per WL(P)A1972
Birds
1. Passer domesticus indicus
Indian House-Sparrow Sch. IV
2. Columba livia Rock Pigeon Sch. IV 3. Sturnia pagodarum Brahminy Starling Sch. IV 4. Bubulcus ibis Cattle Egret Sch. IV 5. Acridotheres tristis Common Myna Sch. IV 6. Centropus sinensis Greater Coucal Sch. IV 7. Francolinus
pondicerianus Grey Francolin Sch. IV
8. Upupa epops Hoopoe Sch. IV 9. Streptopelia decaocto Collared Dove Sch. IV 10. Vanellus indicus Red-wattled Lapwing Sch. IV 11. Psittacula krameri Rose-ringed Parakeet Sch. IV 12. Athene brama Spotted Owlet Sch. IV 13. Ardeola grayii Paddy bird Sch. IV
Source: Field expert during study period consultation with concern state forest officials, Secondary sources and also discussed with local people.
3.8 SOCIO-ECONOMIC ENVIRONMENT:
Introduction
Under Clause 6 of S.O.1533 of Environment Impact Assessment Notification, 2006)
The study is aimed to identify & predication likely impacts on socio-economic and
parameters of human interest due to proposed project. Socio-economic study of the
study area comprising of 10km. buffer zone. It shall be collect primary data through
air, soil, water, Biology & Biodiversity (Flora &Fauna) wild life, socioeconomic status
etc. it is main component of the project. The project of Satalkhedi Pipakhedi
Limestone mine area 43.24 hect. M.L. No. 55/91 Tehsil Ramganj Mandi Dist. Kota
RAJ.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
87 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Socio-Economic Profile
Demography & Socio-Economics: The growths of mining and industrial sectors
and infrastructure developments in and around the agriculture dominant areas,
villages and towns are bound to create its impact on the Socio-Economic aspects of
the local population of the area experiencing development. The impacts may be
positive or negative depending upon the developmental activity. To assess the
anticipated impacts of the mining and industrial growth on the socio-economic
aspects of people, it is necessary to study the existing socio-economic status of the
local population, which will be helpful for making efforts to further improve the
quality of life in the area under study. For assessing the prevailing Socio-Economic
aspects of people in the study area around the existing mine, the required data has
been collected from various secondary sources and analyzed.
Methodology Adopted for the Study: The methodology adopted for the study is
based on the following points:-
Review of Secondary Data, such as District Primary Census Statistical Hand Book of
Kota district, 2011 within the study area around the mine lease area:
Conducting Focus Group Discussions school, local person in the villages for eliciting
the general information of the study area, to support or supplement the information
collected through secondary and primary surveys.
Review of Demographic and Socio-Economic Profile - 2011
The sociological aspects of this study include human settlements, demography, social
structure such as Scheduled Castes and Scheduled Tribes and literacy levels besides
infrastructure facilities available in the study area. The economic aspects include
occupational structure of workers. The information on socio-economic aspects of the
study area has been collected from secondary sources, which mainly include District
Primary Census Handbook 2011 Kota Districts.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
88 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
The village-wise Provisional demographic data as per Census 2011. The salient
features of the demographic and Socio-Economic aspects of the study area are
described in the following sections.
Demographic Aspects: The study area total population consisted of 30178 people.
The males and females constitute varies from 53.15 to 52.47 % and 46.84 to 52.47
% of the study area population respectively. The distribution of population in study area
is presented in Table-3.21
TABLE 3.21 DISTRIBUTION OF POPULATION
Particulars 0-3km. 3-7 km. 7-10 km. 0-10 km. Name of Village 1-Pipakheri
2-Salwadkhurd 3-Kudala 4-Umedpura 5-Satalkheri 6-Mayla 7-Durjanpura
1-Nimana 2-Amarpura 3-Sandpur 4-Suket 5-Kumbhkot 6-Chousala 7-Hiriyakheri 8-Atraliya 9-Kalyakui 10-Semalkheri 11-Nalodiya 12-Parli 13-Charyakheri
1-Deoli 2-Barodiya Antri 3-Lahariya 4-Udpura 5-Modak 6-Naharsinghi 7-Nayagaon 8-Jamunya 9-Jhalara 10-Basyaheri 11-Julmi 12-Bhavpura 13-Khairabad 14-Ramganjmandi
No. of Household 5771 8679 15728 30178 Male Population 14178 21880 41332 77390 Female Population 12497 19800 37798 70095 Total Population 26675 41680 79130 147485 Male Population (0-6 Year) 2189 3559 5676 11424 Female Population (0-6 Year) 2002 3138 5119 10259 Total Population (0-6 Year) 4191 6697 10795 21683 % of Average household size TP 5 5 6 5 % of male to total Population 53.15 52.49 52.23 52.47 % of female to total Population 46.84 47.50 47.76 52.47 Sex Ratio (M:F) 1000:881 1000:904 1000:914 1000:905
NOHH=Number Of Household
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
89 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
TP=Total Population
TM=Total Male, Female
SC=Schedule Caste
ST=Schedule Tribe
FIG.NO. 3.19
Average Household Size: The average household size varies from 5 to 6 the low
family size could be attributed to a high degree of urbanization with migration of
people with higher literacy levels who generally for smaller family size and family
welfare measures.
Sex Ratio: The Sex Ratio of Male and Female indicates that the males constitute to
about 52.47% and females 52.7% of the total population. The sex ratio i.e. the number
of females 905 males per 1000 indirectly reveals certain sociological aspects in
relation with female births, infant mortality among female children and single person
family structure, a resultant of migration of industrial workers. The study area on an
average has 1000 females per 1000 males. high female in 0-6 year’s age groups is
alarming and indicate the impact of urban population
Social Structure: Various religion groups consisting of Hindus, Muslim and
Christians inhabit the study area. The percentage of Schedule Caste population varies
between 28.70 % in study area. The highest percentage of Schedule Caste population
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
90 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
recorded in 0-3km.radius and lowest in 7-10 Km. radius. The percentage of Schedule
Tribe population varies between0- 8% in study area. The highest percentage of
Schedule Tribe population recorded in 0-3km. radius and lowest in 3-7 km. radius.
The distribution of population by caste and tribe is shown in Table3.22
TABLE :- 3.22 DISTRIBUTION OF POPULATION SOCIAL STRUCTURE
Particulars 0-3km. 3-7 km 7-10 km 0-10 km
Schedule Caste 13988 11964 16377
42329
% of SC to total population 52.43 28.70 20.69 28.70 Schedule Tribes
2762 2351 6598
11711 % of ST to total population 10.35 6.12% 8.33 8% Total SC & ST Population 16750 14315 22975
54040
% to total
population 62.79 34.34 29.03 36.64
Literacy Levels: The study area experiences a considerably medium literacy rate
of 38.19%. The level of literacy near mining area in general quite low and female
literacy in particular is below state and National literacy level. The distribution of
literate and literacy rate in the study area is given in Table3.23
TABLE 3.23 DISTRIBUTION OF LITERATES AND LITERACY RATE
Particulars O-3km. 3-7 km. 7-10 km. 0-10 km.
Male Literates 4642
7171 10228 22041
Female Literates 7185 10652 16449 34286
Total Literate 11827 17823 26677 56327
Total Literacy Rate of TP
(%) 44.33 42.76 33.71 38.19
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
91 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Male Literacy Rate of TP (%) 17.40% 17.20% 12.92% 15%
Female Literacy Rate of TP (%) 26.93 25.55 20.78 23.24
TL=Total Literate, Male, Female
FIG.NO.3.20
Occupational Structure: The occupational structure of residents in the study area
is studied with reference to main workers, marginal workers and non-workers. The
main workers include 10 categories of workers defined by the Census Department
consisting of cultivators, agricultural labours, those engaged in livestock, forestry,
mining and quarrying; manufacturing, processing and repairs in household
industry; and other than household industry, construction, trade and commerce,
transport and communication and other services.
The marginal workers are those workers engaged in some work for a period of less
than six months during the reference year prior to the census survey. The non-
workers include those engaged in unpaid household duties, students, retired
persons, dependents, beggars, vagrants etc; institutional inmates or all other non-
workers who do not fall under the above categories.
Together the Main Workers work out to be 31.22% of the total population. The
Marginal workers 8 % and Non-workers constitute 60.78% of the total population
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
92 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
respectively. The distribution of workers by occupation indicates that the non-
workers are the predominant population. The occupational distribution of the
population of study area is shown in Table –3.24
TABLE 3.24 OCCUPATIONAL STRUCTURE
Particulars 0-3km 3-7 km 7-10 km 0-10 km
Total Population 26675 41680 79130 147485
Total Workers 11233 17270 29336 57839
Total Main workers 9111 12663 24279 46053
% of MW to TP 34.15 30.38 30.68 31.22
Marginal worker 2122 4607 5057 11786
% of MRW to TP 8% 11.05% 6.39% 8%
Non-workers 15442 24410 49794 89646
% of NW to TP 57.88 58.56 62.92 60.78
FIG.NO. 3.21
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
93 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine
Base line Data of Study Area:
Base line data are collected and prepared by conducting a survey by Team Members.
Minimum 20%of the villages under Buffer zone have been surveyed by proportional
random sampling method, multi household survey conducted by our team.
preferably the village falling from the Core Zone to 3 Km, secondly of the villages
falling 3 to 7 km and 7-10 km of buffer zone.
Study Village Pipakhedi
Pipakhedi is a medium size large village located in Ramganj Mandi of Kota District,
Rajasthan. With total 324 families residing. The Pipakhedi village has population of
1747 of which 922 are males while 825 are females as per population census 2011.
In Pipakhedi village population of children with age, 0-6 is 265, which makes up
15.17% of total population of village. Average sex ratio of Pipakhedi village is 895,
which is lower than Rajasthan state average of 928. Child Sex ratio for the Pipakhedi
as per census is 920 higher than Rajasthan average of 888.
Pipakhedi village has lower literacy rate compared to Rajasthan .in 2011, literacy
rate of Pipakhedi village was 64.37% Compared to 66.11% of Rajasthan. In
Pipakhedi Male literacy stands at 80.10% while female literacy rate was 46.70%.
Work Profile
In Pipakhedi village out of total population, 725 were engaged in work activities.
91.45% of workers describe their work as Main Work (Employment or Earning
more than 6 Months) while 8.55% were involved in Marginal activity providing
livelihood for less than 6 months. of 725 workers engaged in Main Work, 186 were
cultivators (owner or co-owner) while 24 was Agricultural labour.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
FIGURE 3.22: SOCIO –ECONOMIC SURVEY LOCATION MAP
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
CHAPTER - IV
ANTICIPATED IMPACTS& MITIGATION MEASURES
4.1INTRODUCTION
Environmental impacts due to open cast mining and allied activities are very
common which degrade the quality of environment to a considerable arial extent
from the source. In this chapter the likely impacts on different environmental
components are identified and mitigation measures are proposed accordingly.
4.2 IMPACT ON LAND ENVIRONMENT AND MITIGATION MEASURES
Topography and Drainage
Anticipated Impacts: The existing mining is change the topography and drainage
pattern of the mining lease area in the form of pits. However, mining operation
confined to the core zone of 43.24 ha, hence no impact is anticipated on the
topography and drainage pattern of the buffer zone.
Mitigation measures: To minimise the impact on the drainage pattern garland
drain is proposed to be made around the working pit so as to prevent the flow of
water into the pit. Garland drain routed through adequately sized sumps for
settling of suspended particles and the runoff thus collected is being used for
afforestation.
Land use in core and buffer zone.
Anticipated Impacts: No adverse impact is anticipated on land use of buffer
zone due to the existing mining operations, as all the related activities is
being confined to the core zone. The land use of the core zone is being undergone
considerable change as arising from:
- Excavations
- Establishment of facilities in the area.
The summarized detail of land use plan for pre-operational, operational and post
operational phase as per the approved mining plan is given as under:
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Note- About 15.9800 ha area has been already planted within lease for full fill
33% plantation as per ToR compliance. At the end of mine life about 20.77 ha area
will be planted which includes 3.5400 Ha area will be planted on statuary barrier
(7.5 Meter) & 17.2396 ha area will be backfill planted. About 6.4804 ha area will
be converted as water storage.
4.3 IMPACT ON WATER ENVIRONMENT AND MITIGATION MEASURES
Anticipated Impacts on ground water source: There is no proposal for
abstraction of groundwater for the limestone mining. Also there is no any source
of ground water in the lease area. The mining will not intersect the water table of
the area as the ultimate depth of mining will be 303 mRL and general water table
of the area is 300 mRL (40mbgl) to 295 mRL (45mbgl) as per the information
furnished in the approved mining plan.
The excavation of limestone further does not add to any harmful ingredients that
could leach down to the water table. The composition of limestone is mainly CaO
and MgO. Thus the mine workings will not affect the ground water quality.
Anticipated Impacts on ground water source including hydrogeology: There
is no abstraction of surface water. The sources of pollution generally are run-off
from waste dump and mining area.
S. No. Particulars Pre Operational
(In Ha)
Operational (In Ha)
Post operational
(In Ha) A) Mining Activity 1 Mining pits 8.5215 10.5710 0.00 2 Road & building 2.3750 2.3750 0.00
3 Plantation on statuary barrier
0.0000 2.5500 3.5400
4 Mineral stack 1.5420 1.9540 0.0000 5 Water storage 1.2010 1.2010 6.4804
6 Reclamation & Backfilled Plantation
5.9800 5.9800 17.2396
7 Plantation on remaining lease area
15.9800 15.9800 15.9800
B) Remaining virgin land
7.6405 2.6290 0.000
Total 43.24 43.24 43.24
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
There is no any surface water body exists in the lease area or any river/nallah
flowing adjoining to the lease area which could get affected. However general
drainage in the study area is defined by the Ahu river which is flowing at a
distance of 6.4 km SE direction & Amjar Nadi at 9.3km in NE & Psadi Nadi is
flowing 7.5 Km in SW direction from the lease area. Hence the proposed mining
will not pollute the surface water.
Mitigation measures to minimize impacts on water environment: Garland
drains will be constructed on all side of quarries. All the garland drains will be
routed through settling pits to remove suspended solids from flowing into storm
water. The water collected in the pit, after settling of the suspensions, will be
used for plantation. The details are given in EMP.
4.4 IMPACT ON AIR ENVIRONMENT AND MITIGATION MEASURES
The sources of air pollution are dust generated due to excavation, blasting, loading
and unloading of material and movement of dumpers/trucks. The blasting is
carried out by using low explosives by making drill hole with compressed air
operated jackhammer drills. The dust liberated in mining and other related
operations is injurious to heath if inhaled in sufficient quantity.
The baseline data on air quality is presented in Chapter-3. The maximum values of
PM10 and PM2.5 levels during the study period are below the 24-hour NAAQ
Standard 2009 (Figure-4.1). The gases SO2 and NO2 are also well below the NAAQS
2009.
Anticipated Impacts: The impact of the operation on the air quality has been
predicated using Fugitive Dust Model (FDM), which is a computerized air
quality model specifically designed for computing concentration and
deposition impacts from fugitive dust sources. The sources may be point, line or
area sources. The model has not been designed to compute the impacts of
buoyant point sources, thus it contains no plume rise algorithm. The model is
generally based on the well-known Gaussian Plume formulation for computing
concentrations, but the model has been specifically adapted to incorporate an
improved gradient transfer deposition algorithm. Emissions for each source
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
are apportioned by the user into a series of particle size classes. A
gravitational setting velocity and a deposition velocity are calculated by FDM
for each class. Dust emission rate from the mining area, based on the following
empirical formula.
Pa x 23.6
Dust émission (DE) = ---------------------- Wd x Wh x 1000
DE = Dust emission in kg/hr Pa = Annual Excavation in Tonnes Wd = No. of days of operation in a year
Wh = Effective working hrs in a day
About 23.6 Quantity of dust emitted in kg/for 1000 tonnes of excavation
Dust emission rate= (321699 x 23.6)/ 300x 8 x1000) = 3.16kg/hr.
The above mentioned emission rate is without adoption of dust control measures
of each blocks. The literature suggests that dust control measures reduce the
emissions and effective emission rate is one third of the computed emission i.e.
3.16/3= 1.05 kg/hr and the same is taken for modeling to compute the following:
The 24 hourly averaged incremental concentration with hourly data.
The identification of grid point having peak concentration for the
incremental values.
Preparation of isopleths of for various pollutants.
TABLE NO-4.1 PREDICTED AMBIENT AIR QUALITY CONCENTRATIONS IN OPERATION
PHASE CUMULATIVE CONCENTRATIONS (BASELINE + INCREMENTAL) FOR PM10
S. No.
Particular Mining lease
area
1. Monitored Maximum concentrations in µg/m3 78.7
2. Predicted incremental Maximum concentrations in µg/m3
0.8
3. Resultant Maximum concentrations in µg/m3 79.5 4. NAAQS (dated 2009) 100
Resultant maximum concentration with in permissible limit
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
FIGURE 4.1: GROUND LEVEL CONCENTRATION OF AAQ DURING OPERATION
PHASE IN 10 KM FOR PM10.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
FIGURE-4.2: GROUND LEVEL CONCENTRATION OF AAQ DURING OPERATION
PHASE IN 1 KM FOR PM10
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Mitigation Measures to Minimize Air Pollution
Main source of air pollution is dust from the movement of dumpers/trucks.
The road is metalled except that inside the connecting link. Paving of road is
proposed to be done this will reduce the dust level from the movement of
vehicles to a large extent.
The sprinkling of water is being done undertaken as and when required on
roads as well as stockpile.
The dust may also generate due to low level blasting. It will be very limited
to the explosion site within 100 m. It will be minimized by plantation around
the mine boundary.
Further while manual lifting of the material and dumping into truck or by
using excavator in this case being lime stone pieces, the dust generated will
be minimum. However, drivers will be trained to drop the material from
minimum height.
Proper maintenance of vehicles is being done to minimize the pollutants;
Pollution under Control certificates will be maintained for the trucks and
drivers are instructed to drive at slow speed and proper supervision is
maintained.
The trucks are being covered while moving the material and care is being
taken so that loading will be done without spillage of material during the
movement.
Effective traffic management is being done by ensuring that there are no
traffic jams on mine route by deputing manpower and by planning truck
movement.
Effective mine closure plan or post mining land use.
Ambient Air Quality Monitoring will be conducted on regular basis to assess
the quality of ambient air as per the proposed monitoring plan in Chapter-5
to have a watchful eye on dust levels and to assess the effectiveness of
mitigation measures.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
4.5 IMPACT OF NOISE / VIBRATIONS & MITIGATION MEASURES
There is no habitation in and around the core zone and the nearest villages
Satalkhedi & Pipakhedi is 0.8 & 1.0 km from lease area. The main source of noise
pollution and vibrations will be (i) movement of trucks (ii) Operation of excavator
(iii) Drilling of holes for blasting and (iv) Blasting itself.
Anticipated Impacts: There is no habitation in immediate vicinity. The nearest population is in village
Satalkhedi is at about 0.8 Km from the mine site. Therefore from mining activity
there will no impact on the population of the area.
Noise generated from the proposed machinery ranges between 58 to 101dB (A)
(during drill holes). The exposure time for the maximum noise level of 101dB (A)
is one hour as per the Indian Bureau of Mines. Noise levels beyond the prescribed
standards can have an impact on workers. These can have also impact, on fauna.
Mitigation measures
In order to reduce the effect of noise pollution, ear plugs /earmuffs is being
provided to workers.
The compressor used for drilling holes is being provided with proper enclosures.
The workers will not be allowed to work more than one hour in noise prone
area, and will be shifted to other places.
Plantation is being carried in mining lease in form of garden. The greenbelt
minimizes propagation of noise.
Proper maintenance of vehicles is being done.
Mine operations Proper maintenance of vehicles is being done.
limited to day time i.e. 9AM to 6 PM
Power Horns will not be allowed in trucks. Drivers will be further instructed not
to use music systems at high volumes.
The blasting is being of low impact type with a maximum impact area of 500 m
The excavator use for limited hours with breaks at regular intervals. The
excavator will be regularly serviced.
By carefully designing a blast hole using experience and deciding drilling pattern
or blast geometry with appropriate burden distance, spacing as holes, hole size,
hole depth, and stemming height, and powder factor.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Ambient and Source Noise level Monitoring will be conducted on regular basis to
assess the quality of ambient air w.r.t noise as per the proposed monitoring
plan in Chapter-5 to have a watchful eye on noise levels and to assess the
effectiveness of mitigation measures.
4.6 IMPACT ON BIOLOGICAL ENVIRONMENT & MITIGATION MEASURE
The lease area of 43.24 ha is Pvt. Land and there is no forest land within the lease
area. There is no interference with any first order streams. There is no release of
any effluent.
Impact on Flora and Fauna: The dust is the only major pollutant which will be
generated from different activities of mining. The effect of particulate matter on
vegetation is in the form of incrustation, plugging of stomata, and loss of
chlorophyll and reduction of photosynthesis process. Disturbance in plant
metabolism due to deposition of dust particles on foliar surfaces leads to
reduction in plant growth. The activities such as blasting including drilling holes,
operation of machinery as excavator and movement of dumpers/trucks can have
impact in terms of disturbance due to noise; interference in movement etc.
Mitigation Measures:
During setting up and operation phase of mine following measures will be taken
up to mitigate impacts on surrounding biodiversity:
Mining activities will be restricted to day time so that fauna will not disturb
at night.
Tar road is being used for transportation to minimise fugitive emissions.
Material is being covered during transportation.
Plantation is being taken up in consultation with Forest department and
species local to the area shall be planted as per findings during baseline
environment which help maintain the regional ecological balance, soil and
hydrological conditions.
Water sprinkling is being done on haul roads to control fugitive emissions.
Hedge of sturdy woody shrubs along the lease area will be created.
The removal or picking of any protected/unprotected plant will not be
permitted.
Fencing around the pit mouth to prevent fall of animal.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
If wild life is noticed crossing the area, they will not be distributed at all.
Worker will be made aware of the importance of the wild life.
Educational and awareness programmes for mine workers will be
arranged.
4.7 IMPACT ON SOCIO ECONOMIC CONDITIONS
Mining activity has positive as well as negative environmental impacts related to
socio economic in the study area.
Positive Impacts
Mining activity will generate employment opportunity both direct and indirect
in the study area.
Increase in business opportunity with contract works, employment through
contractors, running of dumper, trucks, tractors and buses on hire basis,
running canteens, different kind of shops and other associated jobs.
Improvement in the general living standards and knowledge sharing.
Improvement in the economic growth in the region
Improvement in the general living standards and knowledge sharing.
Development of the region.
Other facilities will be provided under CSR activity.
Thus the local people will enjoy the economic upliftment. The following activities
will be followed: -
i. Rural/village & Community welfare.
ii. Healthcare of local population.
iii. Free medical camps.
iv. Literacy awareness, supports to schools etc.
v. Environment protection and Environment awareness activities like Environment awareness camps, plantation etc.
Thus the socio-economic status of the area will be improved.
Negative impacts
Dust generated from the mining activity can have negative impact on the health of the workers.
Approach roads can be damaged by the movement of trucks/dumpers.
Nearby agricultural field can also be affected by the dust generation.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Mitigation measures
Adequate measures will be adopted to control dust generation like water
sprinkling on unpaved road, working sites and wheel & truck wash facility at
applied site.
Construction and maintenance of approach roads.
Material will be covered during transportation.
Paving of unpaved roads.
4.8 IMPACT ON OCCUPATIONAL HEALTH & SAFETY
Healthy and safe working conditions are among the first expectations for
sustainability, i.e. the expectation that risks in mining will not deprive workers of
their livelihoods or of their quality of life. Occupational injuries and ill-health have
huge social and economic implications for individuals, their families and their
communities. They also have an adverse impact on the economy of the society as a
whole.
Occupational accidents and health hazards can also affect public health and safety,
and the environment. The effect on the health and safety of people, costs to the
economy and impacts the environment. Efforts will be made to address
occupational health and safety with broader social agenda for sustainable
development.
Hazards, which are associated with poor engineering design, contribute to
increased safety risks.
Although health risks can be avoided by implementing controls at source in the
work environment, designing such controls for mining environment presents
considerable challenges because dust and noise are generated by mining itself. A
range of control measures that act together to reduce exposure to such risks is
therefore necessary. These could include methods for minimizing dust levels by
reducing dust generation and methods for dilution, suppression, capture, and
containment.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
While significant uncertainties remain in controlling dust exposures and
maintaining the effectiveness of controls, the use of appropriate personal
protective equipment (PPE) is important.
Exposure to Dust
Exposure to fine particulates is associated with work in most of the dust-
generating stages notably from drilling and blasting, mineral handling, and
transportation.
Methods to prevent and control exposure to dust include the following:
Control of dust through water spraying,
Use of PPE, as appropriate (e.g. masks and respirators) to address residual
exposures.
Physical hazards
Injuries during Project operation are typically related to slips and falls contact
with falling / moving objects and lifting / over-exertion. Other injuries may occur
due to contact with, or capture in, moving machinery (e.g. trucks). In case of any
accident immediate & proper first –aid medical care shall be provided at the mine
site.
Pre-placement medical examination and periodical medical examination
schedules
The fresh employees when taken are thoroughly medically examined under initial
medical examination and thereafter during continuation of employment; the
periodic medical examination is being done as suggested by DGMS.
Measures to Control Occupational Health Hazard & Safety
The working in the lease area will be done with all safety measures under the
supervision of qualified staff. The workers will be provided dust mask, safety boot,
helmet and other safety equipment. A well-equipped first aid box will be
maintained at site.
For mitigating the aspect the following measures will be implemented:
Regular water sprinkling on haul roads.
Dust mask is being provided to the workers.
Periodical medical examinations will be carried out for the workers as per
Norms.
Medical records are being maintained.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Medical facilities to the workers.
Any early symptom of diseases, if observed, such workers will be taken off from
the dusty atmosphere and will be employed at other suitable place.
Personal Protective Equipment’s is being provided to the workers.
Vocational Training will be provided to the workers.
Safety of the employee during mining will be taken care as per Mine
Regulations
Details of Infrastructural Facilities for Worker
Water for drinking & other purpose will be arranged.
All the safety equipment’s such as helmets, safety shoes, goggles, dust masks etc.
A well-equipped first aid facilities,
Periodic medical health check-ups,
Rest shelter, washrooms etc. is being provided near the working blocks.
*********
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
CHAPTER – V
ANALYSIS OF ALTERNATIVES
5.1SITE ALTERNATIVES
Mineral deposit is site specific. The lime stone deposit is sedimentary deposit.
There for as per the nature of mineral deposit and proposed rate of production the
technology chosen is suitable for mining.
5.2TECHNOLOGY ALTERNATIVES
Limestone is exposed in the area and depending upon the availability of mineral.
The usable lime stone varying in thickness from 6m located below the hard
limestone layer. Moreover small scale drilling and blasting will also be done for
excavation and loading and transportation will be carried out by excavator &
dumpers respectively. Therefore as per the nature of mineral deposit and
proposed rate of production the technology chosen is suitable for mining. Proper
use of waste generated by mining will be backfill into exhausted pit up to ground
level, leaving reaming mined out pit for water reserve and plantation on back
filled area.
=====******=====
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
CHAPTER – VI
ENVIRONMENTAL MONITORING PROGRAMME
6.1 MONITORING SCHEDULE AND PARAMETERS
Environmental monitoring programme will be taken up after the grant of EC and
half yearly compliance report in respect of the terms and condition stipulated in
the EC letter will be submitted to the regulatory authorities.
For the present working mine good practices of EMP and monitoring schedules
are ensured to keep all the environmental parameter of the projects within
statutory levels in respects of ambient air quality, water quality, soil quality,
socio-economic improvement, noise level standard. Regular monitoring of the
environment will be done and for that an environment monitoring cell will be
formed for conduction and supervision of entire monitoring programme. The
monitoring schedule along with monitoring parameters, monitoring frequencies
and duration is given in the below table.
TABLE 6.1: MONITORING SCHEDULE FOR ENVIRONMENTAL PARAMETERS
Particulars Monitoring
Frequencies
Duration of Station
Important Monitoring Parameters
Surface water/ Ground water Sampling
Twice in a year
Grab
pH, TDS, Iron, Hardness, Alkalinity, Chlorides, Calcium, magnesium, Nitrates, Sulphate & Fluorides.
Ambient air quality monitoring
Twice in a year.
24/8 hr. PM2.5 PM10, SO2 and NO2.
Noise Monitoring Twice in a
year. 8/1 hr. Level in dB (A).
Soil Sampling Twice in a
year Grab
PH, Conductivity, organic matter permeability, water holding capacity, Alkalinity & texture.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
6.2 ENVIRONMENT MONITORING CELL
The monitoring will be taken up by the supervisory officers of the mine. Mine
manager will be in charge of the environment cell and will be responsible for the
effective functioning of the monitoring programme. The environmental data will
be monitored initially by using an outside agency and later an in house
monitoring cell will be developed.
FIGURE 6.1: ENVIRONMENT MONITORING CELL (EMC)
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
6.3 FUNCTIONS OF THE MONITORING CELL
1. To carry out the environment monitoring for environmental parameters
given in the table 6.1 by an outside agency or through monitoring cell that
will be formed by the mines management. The monitoring programme
will be focused to ensure the environmental status of the core and buffer
zone will be preserved in good status as per rules.
2. To observe the effectiveness of mitigation measures.
3. Regular visit of the working site to examine the slope stability, mine faces
and waste dump.
4. Regular checking of garland drain for any blockage due to silting or
accumulation of the loose materials.
5. To ensure the green belt development in a time bound manner and also
regular monitoring of planted species for survival rate.
6. Regular water monitoring for the parameters prescribed in the consent
conditions of SPCB.
7. Monitoring of ambient air quality at the desired monitoring location
covering both up wind and downwind directions and also to make sure
that control measures are effectively implemented.
8. Health check-up of the workers is being conducted regularly for
Occupational health and safety and also concentration of reparable dust
in the workplace will be regularly measured as laid down by DGMS.
9. The information regarding the health status of the workers will be
maintained.
10. Conducting safety week programmes to create safety awareness amongst
the workers and other staff. This will educate the workers to work safely
in mine lease with different equipment along with all PPE’s.
11. To make sure that CSR activities are taken up in the proposed villages.
12. Coordinating the environment related activities within the project as well
as with outside agencies.
13. To comply with all the EC conditions effectively.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
6.4 ENVIRONMENTAL POLICY:
Proponent is committed to providing a quality service in a manner to ensure a
safe and healthy workplace for employees and minimize potential impact on the
environment. They will operate in compliance with all relevant environmental
legislation and strive to use pollution prevention and environmental best
practices.
To achieve this will will endeavor to-
To integrate the policy with all stages of project and activities.
Minimize the impact on various components of the environment, particularly on
Air,water,Land and Natural resources through conscious and corrected efforts.
Compliance with the applicable environmental legislation & regulations.
Continual improvement of our environmental performance through the use of
most appropriate economically viable technologies, voluntary involvement of our
employees and participation of business associates.
********
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
CHAPTER - VII
ADDITIONAL STUDIES
7.1 INTRODUCTION
The additional studies carried out for the Satalkhedi –Pipakhedi Limestone
(Building Stone) Mine, near village- Satalkhedi-Pipakhedi, Tehsil – Ramganj Mandi,
District- Kota (Rajasthan), for the proposed production capacity 3, 21,699 TPA
(RoM) Lime stone.
7.2 PUBLIC CONSULTATION:
As per EIA Notification, 2006 Public hearing was conducted on dated 06.12.2016
at the Atal Seva Kendra Gram Panchayat Bhawan in village Satalkhedi, Tehsil –
Ramganjmandi, Dist. – Kota, Rajasthan. Notices regarding this public hearing have
been published in news paper named Dainek Bhaskar on dated 05/11/2016 &
Jabaaz Patrika on dated 04/11/2016. The public hearing had been chaired by
Miss. Sunita Dang, Additional District Collector in the presence of Sh. Amit Sharma
Regional Officer of Rajasthan State Pollution Control Board, Kota & local people.
During the process suggestion, objections were invited from the local people
regarding the project. During the public consultation, no objection regarding the
project has been received. However people are happy with the mining project as
they have been get employment and other facilities. Minutes of public hearing is
attached as Annexure No-XII.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Photographs of public hearing
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
7.2 RISK ASSESSMENT
The anticipated risks in the mining operations are mentioned below:
Hazard identification and risk analysis: This deal with the hazards associated
with various mining works during operation of the mine and can happen due to
excavation, handling of material, machinery breakdown electric failures and
natural calamities.
It also presents the calculated frequencies of occurrence of different accident
scenarios for the identified potential hazard occurrence.
Risk Reducing Measures based on the calculated frequencies and consequences.
7.3 IDENTIFICATION OF HAZARDS
Technological Hazards
Technological hazards may be due to intense noise during excavation / loading,
transportation, drilling & blasting etc. fire in the excavator, and road mishap.
Structural failure
Structural failure is associated with the failure of slope, it can be bench fall, slope
failure due to undercutting and fall of machinery and workers due to fall of
bench/slope, any of the said activity can cause major injury and fatalities.
7.4 SCENARIOS CONSIDERED FOR RISK ASSESSMENT
Knowledge of work
The application of risk assessment depends upon full understanding of all aspects
of the job being undertaken. In carrying out a risk assessment in relation to a
particular task, the evaluation must include a review of the knowledge, experience
and training of those persons carrying out the work.
Personal Competence
It follows that the knowledge, experience and training of personnel involved in
work is critical to evaluate any risk assessment. A knowledgeable, experienced
well-trained and competently supervised workforce will be at a lower risk of
accidents occurring than a poorly trained and badly supervised workforce.
Co-ordination
It is essential that the coordinator ensures that everyone engaged in the work is
capable and understands the role of others and their responsibility for each other.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Health hazards
Health hazards are associated with the dust and noise, it is necessary to quantify
the key pollutants during surface mining operations that may result into health
hazard.
Inundation
The nearest water body is Amjar river which is flowing at a distance of 9.3 km in
the NE direction, Ahu Nadi at 6.4 km in SE direction & Psadi Nadi 7.5 km in SW
direction from the lease area. There is no possibility of inundation of mine due to
this river.
Noise
Noise is considered as a common occupational hazard in mine environment.
Prolonged exposure to noise over a period of years may cause permanent damage
to auditory nerves and its sensory components (Noise Induced Hearing Loss). In
order to avoid Noise Induced Hearing Loss (NIHL) to the operators of the HEMMs,
the cabins of these machines will be made sound proof. Also, the operators and
other workers working in the high noise generating areas are being provided with
ear plugs/ ear muffs to protect their hearing. No worker will be allowed to enter
high noise generating areas without wearing proper protection equipment’s.
Surface Fire
There are no ignitable materials in limestone deposit. However, the excavator to
be deployed in the mine may catch fire. All precautionary measures will be taken
to prevent the occurrence of such activity.
Loading
There will be no risk associated with the activity. However, precautions will be
required to be taken to remove workers away from the loading operations, to
avoid any fall of material on persons. Also, the loading operations will be
supervised by a site supervisor for properly guiding the loading machine operator.
Pit Slope Failure
The sides of the mine benches will be suitably sloped to avoid bench failure. The
bench height is planned to be kept 6 to 9m with width more than 6m to 9m of the
bench. The bench sides and edges will be regularly inspected for any signs of
failure, development of cracks, etc. Due precautionary measures will be adopted to
avoid any bench or pit slope failure.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Heavy Vehicles
Proper care will be taken while loading and transportation of mineral and
overburden. Good maintenance and regular testing will be done to avoid any
mishap.
Personal Protective Equipment (PPE)
The PPE should be of good construction, where ever possible ISI certified, suitable
for the hazard e.g. a dust respirator fitted with the correct filter to capture the
particular hazardous dust and maintained to recommended standards.
Traffic Movement
The mining operation will be of small scale and the machinery proposed to be
used for mining is less in number, therefore there will be no risk of accidents due
to the traffic movement. However, haulage roads will be properly maintained and
the speed limits shall be implied on the vehicles plying for mineral transport to
avoid accidents.
7.5 DISASTER MANAGEMENT PLAN
The complete mining operation will be carried out under the management
control and direction of qualified Mines Manager. The Directorate General of
Mines Safety (DGMS), Dhanbad have issued a number of standing orders,
model standing orders and circulars to be followed by the mine management:
Checking and regular maintenance of garland drains and earthen
bunds to avoid any inflow of surface water in the mine pit.
Provision of pumps for pumping out water from the mining pit.
Entry of unauthorized persons will be prohibited.
Fire fighting and first aid provision shall be kept in the mines office
complex and mining area.
Safety equipment such as safety boots, helmets, goggles etc. will be made
available to the employees and regular checked for their use.
Training and refresher courses for all the workers.
Working of mine as per approved scheme and regular updating for the
same.
Regular cleaning of mine faces.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Regular maintenance and testing of all mining equipment as per
manufacture’s guidelines.
Suppression of dust on the haulage roads.
Increasing the awareness of safe practices through competitions,
posters and other similar drive.
7.6 OUTLINE OF DISASTER MANAGEMENT PLAN
The purpose of disaster management plan is to restore the normalcy for early
resumption of mining operation due to an unexpected, sudden occurrence
resulting to abnormalities in the course of mining activity leading to a serious
danger to workers or any machinery or the environment. The main objectives of
preparing a disaster management plan in mining project include:
• To protect workers in mine from accident.
• To prevent or reduce the incidence and severity of injury during mining
Operations.
• To respond immediately and adequately in case of a serious accident.
First Aid & medical facilities
The mine management will provide first aid facilities for use in emergency
situation. All casualties would be registered and will be given first aid. The mine
management will provide all facilities to evacuate the injured person from the
accident site to the nearby hospital.
Care and maintenance during temporary discontinuance
In case of any temporarily discontinuance or if mine closes temporarily, then the
mining working will be in the watch of a watchman. Before reopen of the mine
maintenance working will be provide to all the machineries deployed at mine site.
Before entering the labourers into the mine working/faces the workings and faces
are proposed to be inspected by manager for safety purposes as Mines Act.
7.8 SOCIAL IMPACT ASSESSMENT, R&R ACTION PLAN
There will be the positive impact on the villagers of the nearby villages in the form
of employment. There is no human settlement in the lease area. Thus there is no
impact on the human settlement and thus no R & R plan is required.
========**************========
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
CHAPTER - VIII
PROJECT BENEFITS
There are various aspects of this project and allied activities that are beneficial to
the locality, region and nation.
The mineral Limestone production from this mine.
There is sufficient demand in this region for the purpose. The use of this
lime stone (Building Stone) in is flooring and walls tiles.
The production of lime stone from the proposed project will benefit the
state government by the way of revenue.
At present there are 109 employers in the mine & local people will also be
preferred for contract jobs during operational stages of the project.
Improvement in the physical & social infrastructure is another benefit that
will arise from this mining project. People in the adjoining area will be
helped through the CSR activities and other funds allocation especially for
the development of the area.
Tangible benefits like improved standard of living, health and education.
This project is beneficial at all levels providing benefits to the industry, local
inhabitants and state government.
========**************========
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
CHAPTER – IX
ENVIRONMENT MANAGEMENT PLAN
9.1 INTRODUCTION
The environmental management plan has been formulated in keeping view the
process of mine planning so that ecological balance of the area will be maintained
and identified adverse impacts that are likely to arise will be mitigated. Mitigation
measures for identified environmental impacts have already been discussed
earlier in Chapter-IV.
The main objective of environmental management plan is implementation of all
environment pollution controlling system effectively to maintain the ecological
balance of the area and also to promote the sustainable development during the
operational and post operational phase in the area.
TABLE 9.1: ENVIRONMENT MANAGEMENT PLAN IMPLEMENTATION
Environmental Issue
Mitigation measures Implementation
Air pollution Paving of road. The sprinkling of water is being undertaken as
and when required on roads as well as stockpile.
Plantation will be done around the mine lease & backfill area. Wet drilling system will be adopted. Training to driver for unloading the material
from safe height to prevent dust generation. The dumper is being covered while moving the
material and care is being taken so that loading will be done without spillage of material during the movement.
Traffic management to ensuring that there are no traffic jams on mine route by deputing manpower and by planning dumper movement.
Proper management of waste dump yard. Effective mine closure plan or post mining land
use.
Project authorities through Regular monitoring of the roads, plantation sites, random checking of equipment.
Noise pollution Plantation along mining lease area the greenbelt minimizes propagation of noise.
Proper maintenance of vehicles is being done. Mine operations is being limited to day time. Power Horns will not be allowed in dumper.
Project authorities through Regular monitoring.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Drivers will be further instructed not to use music systems at high volumes.
The excavator use will be for limited hours with breaks at regular intervals. The excavator will be regularly serviced.
In order to reduce the effect of noise pollution, ear plugs /earmuffs will be provided to workers.
The compressor used for drilling holes is being provided with proper enclosures.
The blasting is being of low impact type with a maximum impact area of 500 m
Ambient and Source Noise level Monitoring will be conducted on regular basis to assess the quality of ambient air w.r.t noise as per the proposed monitoring plan to have a watchful eye on noise levels and to assess the effectiveness of mitigation measures.
Water pollution Garland drains are will be constructed on all side of quarries. All the garland drains will be routed through settling pits to remove suspended solids from flowing into storm water. The water collected in the pit, after settling of the suspensions, will be used for plantation. Plantation shall further help to reduce surface water pollution.
Project authorities
through regular
monitoring.
Land degradation
Garland drain will be constructed around the excavation to prevent the inflow of water into the pit. Sumps will be made for settling of suspended particles if any. A well laid out closure plan is given in the mining plan and approved from the authorities. Detail is given for reclamation of the degraded mine lease area to the maximum possible extent by backfilling of the worked out pit and plantation in the statutory boundary barrier and over backfilled part of the lease At the end of mine life about 20.77 ha area will be planted which includes 3.5400 Ha area will be planted on statuary barrier (7.5 Meter) & 17.2396 ha area will be backfill planted. About 6.4804 ha area will be converted as water storage. At present about 15.98 Ha area already planted within lease area.
Project authorities
through regular
monitoring.
Biological Environment
Mining activities is being restricted to day time so that fauna will not disturb at night.
Tar road is being used for transportation to minimise fugitive emissions.
Project authorities
through regular
monitoring.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Material is being covered with tarpaulin during transportation. Plantation will be taken up in consultation with Forest department and species local to the area shall be planted as per findings during baseline environment which help maintain the regional ecological balance, soil and hydrological conditions. Water sprinkling is being done on haul roads to control fugitive emissions. Hedge of sturdy woody shrubs along the mine will be created. The removal or picking of any protected/unprotected plant will not be permitted. Proper traffic management including ban on use of pressure horns; restriction on use of music in vehicles at high volume as well as regular maintenance of vehicles shall be insisted to minimize disturbance from vehicular movement. Educational and awareness programmes for mine workers will be arranged.
Occupational health & safety & public health & safety.
Regular water sprinkling on haul roads. Dust mask is being provided to the workers. Periodical medical examinations will be carried out for the workers as per Norms. Medical records are being keep maintained. Medical facilities to the workers. Any early symptom of diseases, if observed, such workers will be taken off in the dusty atmosphere and suitable employed elsewhere. Personal Protective Equipment’s will be provided to the workers. Vocational Training will be provided to the workers. Safety of the employee during mining is being taken care as per Mine Regulations.
Vocational Training will be provided to the workers. A well-equipped first aid facility will be made available round the clock in ML area. By Project authority.
Waste management
Waste generated from the mining will be backfilled to the worked out pit
Regular monitoring by project authorities.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
TABLE 9.2: COST ESTIMATES OF EMP IMPLEMENTATION
The below table give overall investment on the environmental safeguards and
recurring expenditure for successful monitoring and implementation of control
measures.
(Investment and recurring cost)
S. No. Capital cost (in Rs.) Annual recurring cost (in Rs.)
Existing Proposed Existing Proposed 1 Pollution Control
(Garland Drain, Water sprinkler, Wet drilling)
- 3,00,000 - 1,00,000
2 Pollution Monitoring (Air, soil, Water, Noise)
- 5,00,000 - 1,00,000
3 Occupational Health - 5,00,000 - 1,00,000
4 Green Belt - 2,50,000 - 50,000
Total 15,50,000 3,50,000
Total investment on environmental improvement works is envisaged Rs.
15,50,000 and recurring expenditure during the stage of production is Rs.
3,50,000 per year.
9.2 GREEN BELT DEVELOPMENT
Green belt development is the most effective pollution control measures. Trees play
vital role in keeping the ground level concentration in control within the project and
its surrounding premises and also in preventing the horizontal dispersion of the
pollutants to the surrounding areas. They are very effective in trapping the pollution
causing agents viz. dust and gaseous pollutants. The green belt is being proposed for
following objectives.
Arresting of fugitive dust emission.
Noise pollution control.
Prevention of soil erosion.
Balancing eco environment.
Aesthetics.
The action plan for green belt development is given in the following table:
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
TABLE 9.3: STAGE WISE PLANTATION
Year
Plantation barrier
Backfilled area Plantation in
lease area Dump area Total
Area (Hect.)
Trees Area
(Hect.) Trees
Area (Hect.)
Trees Area (Ha.)
Trees Area
(Hect.)
Existing -- -- - - 15.98 -- - - 15.98
I 0.051 51 - -
- - - -
II 0.051 51 - - - - - -
III 0.051 51 - -
- - - -
IV 0.051 51 - - - - - -
V 0.051 51 - -
- - - -
Up to 5th year
2.5500 255 - -
- - - - 2.550
End of life of mine
0.99 99 17.23 --
- - - - 18.22
Total 3.540 3540 17.23 --
15.98 - - - 36.75
The yearly financial expenditure for green belt development is given in the table 9.2. It
is evident that at the end of plan period green belt will be developed in 84 % of the total
lease area.
Protection of Plantation Sites
Plants will be protected from diseases by the application of proper pesticides. Soil
workings, manuring etc. will be done whenever necessary. Plants will be protected by
providing fencing and proper watch and ward.
About 15.98 ha area has already planted within lease area.
TABLE 9.4: PROPOSED PLANTATION
S. No
.
SPECIES SCIENTIFIC NAME
LOCAL NAME
1 Azadirachta indica Neem 2 Dalbargia sisso Shisham 3 Cassia fistula Amaltas 4 Accacia nilotica Babbol
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
9.3 SOCIO ECONOMIC ENVIRONMENT
Based on the findings of the socioeconomic study, CSR proposal has been made by the
PP and it is aimed at the socio-economic up liftmen of the area. The provisions made are
particularly in the area of habitat, health and education, training programme of rural
women & men provide the kit for employment generation. The proposal also contains
budgetary provision of washroom facilities for girls in nearby schools.
Based on findings Pipakhedi village has been taken for CSR activities.
TABLE 9.5: COST OF CSR ACTIVITIES
S.No Activity Detail of Educational Institute
Facilities provided CSR Fund
1 Education Facility in
Pipakhedi village
(within 5 km)
Distance 1.0 Km.
Primary school in Pipakhedi *Washroom for girls.
*Schools shoes & stationery distribute for the poor student. *Provide drinking water
facility
Rs 75,000.
Activity Proposed Detail Training Fund
2 Skill Development\
Youth
Sport camp organization for youth
at Hathiya kheri Village ( Football,
Cricket match, volleyball,)
Rs. 50,000
Health & Sanitation
(within 5 km from the
site)
Contact person Proposed facilities CSR Fund
3 Sub Health Centre
(Distance 1.0 km.)
Smt. Mamata
(ANM)
- waste disposal facility
- Medical camp organization
-Medicine distribution
Rs. 75,000
Total 2.0 Lack
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
9.4 OCCUPATIONAL SAFETY & HEALTH
The medical histories of all employees will be maintained in a standard format.
Thereafter, the employees are subjected to medical examination on annual basis.
The said medical examination keep upgrading the database of medical history
of the employees.
Safety of employee during mining operation and maintenance of mining
equipment will be taken to avoid any adverse effect on the health of
workers.
To avoid any adverse effect on the health of workers due to dust, heat, noise
sufficient measures will be provided in the mining project. These include:
Provision of rest shelters for mine workers with amenities like
drinking water, washrooms etc.
Provision of personal protection devices to the workers.
Rotation of workers exposed to noisy areas.
Dust suppression on haul road.
First-aid facilities in the mining area.
Additionally, the health status of workers in the mine shall be regularly
monitored under an occupational surveillance programme. Under this
programme, all the employees will be subjected to a details medical
examination at the time of employment. The medical examination covers the
following tests.
General Physical Examination and Blood Pressure.
X-ray Chest and ECG.
Detailed Routine Blood and Urine examination.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
BUDGETARY PROVISION FOR MINE WORKER
PP will arrange all basic facilities including required infrastructure. First Aid box,
Toilets as per the provisions of Mines Rules shall be constructed and maintained.
There will be no residential colony proposed to be set up in the lease area.
TABLE 9.6: BUDGETARY PROVISION FOR WORKERS
Facility Provided for
Labourers
Total amount per year
Drinking water By Tanker 30,000/-
First Aid Box 20,000/-
Rest Shelter 50,000/-
Washroom 20,000/-
Safety shoes 75,000/-
Hand Gloves 75,000/-
Dust Mask 50,000/-
Ear Plugs / Muffler 30,000/-
Helmet 50,000/-
Insurance 1,00,000
Total 5,00,000
1) Rest shelters: Rest shelters already present there mine site. Maintenance will
be every year.
2) First Aid Box: A first aid box with proper equipment will be provided as per
mines act and Mines Rule.
3) Washroom: Washrooms will be provided separately for male and female
worker as per rule.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
4) Drinking Water: Clean potable drinking water will be provided as per Mines
Rule.
TRAINING & HUMAN RESOURCES DEVELOPMENT
The training of mine personnel will be conducted regularly with respect to
environmental protection. Training facilities will be envisaged in the mine site.
Specialized courses will be arranged for afforestation, re-vegetation,
reclamation etc. in various Institutes and organizations.
Training and human resource development is not a single time function but
a continuous requirement to up-date and improve the skills of employees.
Hence, in addition to whatever statutory training is required, the company
looks forward to continue the process by way of participative training of the
personnel in various workshops, training courses organized by manufactures
/professional agencies. Budgetary provision for occupational health and safety of
the worker is given in the table 9.2.
9.5 TOP SOIL AND WASTE MANAGEMENT
The waste as overburden in the area is top soil & fractured lime stone. The soil
cover in the area from 3.0m and fractured Limestone (Waste) varies from 27m top
soil will be spread over the backfilled area for a forestation. About 1370730 cum
of overburden & fracture waste generate will be during plan period. Waste
generated will simultaneously be used for the backfill purpose of the mine out pit.
TABLE 9.7: PROPOSED WASTE GENERATED FOR MINING ACTIVITY
S. No Year I II III IV V Total
1. Fracture +
mineral
waste (MT)
8024 8024 8024 8024 8024 402120
2. Over
Burden(MT)
1026432 712800 712800 712800 712800 3877632
3. Total Waste
(1+2) MT
1106856 1106856 793224 793224 793224 4279752
4. In Cum 461190 330510 330510 330510 330510 1370730
5. Swell
volume
(Cum)
553428 396612 396612 396612 396612 2139876
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Generation of top Soil- Top soil 3m is available shall be excavated with the
mining which shall be backfill in the pit.
Proposed to stack the sub grade material- The Sub grade mineral shall be used
in mixing with high grade to make avg. grade makeable. The generation shall be-
Year I II III IV V
Sub Grade Mineral (MT) 16084 16084 16084 16084 16084
Sub Grade Mineral M3 5957 5957 5957 5957 5957
Swell volume (M3) 7148 7148 7148 7148 7148
Avg. height of Dump 6m 6m 6m 6m 6m
***********
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
CHAPTER – X
SUMMARY & CONCLUSION
10.1 INTRODUCTION
This report is prepared to evaluate the environmental impacts of the project
namely Satalkhedi-Pipakhedi limestone mine(Building stone) over 43.24 ha Pvt.
land, near village – Satalkhedi-Pipakhedi, Tehsil – Ramganj Mandi, District – Kota
(Rajasthan) in line with the requirements of EIA notification SO 1533(E) dated
14.9.2006 and amendments made thereof.
10.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT:
This is a mining project of Satalkhedi-Pipakhedi limestone (Building Stone) Mine,
near village - Satalkhedi-Pipakhedi, Tehsil – Ramganj Mandi, District – Kota
(Rajasthan) over 43.24 ha Pvt. land.
Originally the mining lease (Area 83.87ha.) was granted in favour of Shri Ganga
Ram Bairwa S/o Sh. Kalu Ram Bairwa vide letter No-9(4) Khan/Group/-2/92 in
dated 13/04/92 for 10 years (20-01-1992 to 19-01-2002). The lease deed was
executed on 30/05/1992 and registered on dated 30/06/1992
Lease renewal order was given for 10 years on dated 20.01.1992 to 19.01.2002
after that it has extended up to the 19.01.2012.
About 40.63 ha lease area was surrendered on dated 20.01.2001.
After the death of Ganga Ram Bairwa the lease was Nominated in favour of Shri
Pankaj kumar Bairwa S/o Shri Swaroop Chand Bairwa.
And now the lease has been renewed up to the 19.01.2022.
Project proponent:
Sh. Pankaj Kumar Bairwa S/O - Sh. Swaroop Chand, R/O -Satalkhedi, Tehsil -Ramganjmandi Dist- Kota, Rajasthan
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
10.3 LOCATION OF PROJECT
State : Rajasthan
District : Kota
Tehsil : Ramganjmandi
Village : Satalkhedi, Pipakhedi
The lease area falls on survey of India Toposheet No. 45P/14 & 54 D/2 and is
situated between:
Latitude N Longitude E
24°00'00"N to 24°39'30"N 76°12'96.0"E to 75°59'55.7"E
10.4 SIZE OR MAGNITUDE OF OPERATION:
It existing mine and mineral is being proposed by opencast method. It is proposed
to produce 3, 21,699 TPA (ROM) from 43.24 ha.
10.5 MINING METHOD
Mine is being developed by opencast mining with drilling and blasting. The
mineral is lying on the sub surface therefore open cast mining is obvious choice.
The bench parameters shall be for mineral-
1. Height-6m to 9m
2. Width – more than 6m-9m.
The bench parameters shall be for O/B/Fracture-
1. Height-6m- 9m
2. Width – More than 6-9m.
10.6 EMPLOYEE DETAIL: About 109 workers will be required.
10.7 MACHINERIES DEPLOYED:
Type of Machinery
Nos. Bucket Capacity in Cum.
Motive Power
Make H.P.
Dumper 6 10 tonner Diesel Tata 119 HP Water pump 1 - Diesel Local -
Compressor 1 75 CFM - Local - Jack Hammer 2 32 mm Diesel Local - Excavator 2 1.2 m3 Diesel Local - JCB 1 - Diesel Escort - Jiri Cutting m/c 8 - - --- - DG Set 2 125Kva Kriloskar
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
10.8 DESCRIPTION OF ENVIRONMENT
TOPOGRAPHY: The area is having hilly topography. The highest elevation of the
mining lease area is 340 mRL and lowest elevation is 337 mRL. No any seasonal or
perennial nallah exist in lease area. Three river name Ahu, Amjar, Pasadi nadi
flowing in Study area.
Land use of Lease area.
Note- About 15.9800 ha area has been already planted within lease for full fill
33% plantation as per ToR compliance. At the end of mine life about 20.77 ha area
will be planted which includes 3.5400 Ha area will be planted on statuary barrier
(7.5 Meter) & 17.2396 ha area will be backfill planted. About 6.4804 ha area will
be converted as water storage.
SOIL OF THE AREA: Analysis of soil in the area show that soil of the area is
slightly alkane in nature & NPK is poor in soil.
AVAILABLE GROUND WATER IN AREA: Analysis of different Samples of ground
water shows that all parameter are well within limit.
S. No. Particulars Pre Operational
(In Ha)
Operational (In Ha)
Post operational
(In Ha) A) Mining Activity 1 Mining pits 8.5215 10.5710 0.00 2 Road & building 2.3750 2.3750 0.00
3 Plantation on statuary barrier
0.0000 2.5500 3.5400
4 Mineral stack 1.5420 1.9540 0.0000 5 Water storage 1.2010 1.2010 6.4804
6 Reclamation & Backfilled Plantation
5.9800 5.9800 17.2396
7 Plantation on remaining lease area
15.9800 15.9800 15.9800
B) Remaining virgin land
7.6405 2.6290 0.000
Total 43.24 43.24 43.24
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
AMBIENT AIR QUALITY MONITORING:
Sampling locations were established for ambient air monitoring in and around the
core zone within a radius of 10.0 km, to study the present quality of the air. From
the baseline monitoring result, it is observed that the monitored parameters
(PM10, PM2.5, SO2&NO2) are within the permissible limits as per NAAQS, 2009
during the study period.
NOISE MONITORING OF AREA: During the study period ambient noise level were
monitored and which are within CPCB Noise standard.
BIOLOGICAL ENVIRONMENT: Lease area having scattered vegetation Vilayati
babool, Babool & Aakra are mainly seen there.
SOCIO ECONOMIC ENVIRONMENT: Study has been conducted through filled survey
and results reviled that area is undeveloped, literacy rate is poor, unemployment.
Health and sanitation problems.
10.9 ENVIRONMENT MONITORING CELL
The monitoring will be taken up by the supervisory officers of the mine. Mine
manager will be in charge of the environment cell and will be responsible for the
effective functioning of the monitoring programme. The environmental data will
be monitored by an outside agency. Monitoring will be done twice in year.
10.10 ENVIRONMENT MANAGEMENT PLAN
At the end of mine 6.4804 Ha area will be used as water storage & about 17.239 ha
mine out area will used for backfill plantation.
Air pollution management:
1. Water sprinkling will be done on haul road.
2. Plantation will be done along lease boundary & with the lease area.
3. All vehicles will be regularly maintained.
4. Air quality will be regularly monitored.
Water pollution management.
1. Water conservation measures have been proposed in the project to recover
the rain water.
2. Suitable rainwater Storage is proposed at post operational phase.
3. No waste water will be generated & discharge to any water body.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Noise & vibration Pollution Management:
1. Proper plantation along road side.
2. Proper maintenance of Noise generating Machinery.
3. Provide PPE to workers (Ear muffs).
Solid waste management:
OB & Scree generated from mine site will be backfilled in pit area. Sub grade
material will be stacked at earmarked site.
Green belt Development:
Total plantation by the end of the mine life will be over 36.75 Ha (Total lease
area 43.24 ha) including 3.5400 ha area will be planted on statuary barrier &
17.23 ha area will be planted on mine out backfill area. At present about 15.98 ha
area has been already planted. So the total 84 % area will be planted.
Socio- Economic Environment
The proposed project would aid in the overall Social and economic development
of the region. Mine project will enhance the economic status. Apart from
employment this project shall provide medical & educational facilities to the
employees and people living within the study area.
Occupational health & safety measures
The medical histories of all employees will be maintained as per mines rules,
1955. Thereafter, the employees will be subjected to medical examination on
annual basis. Apart from that rest shelters, potable drinking water, wash room
will be provided, Personal protective devices will be provided to the workers.
Amount of Rs 3.5 lac will be spend per year for EMP
Amount of RS 2.0 lac will be spent for CSR/year
*********
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
CHAPTER – XI
CONSULTANTS ENGAGED
(RQP/UDP/354/2009/B)
The consultant engaged for the preparation of the EIA/EMP of the project is
M/s Udaipur Min-Tech Pvt. Ltd. The information about the company with
address is as follows:
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Questionnaire
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
PROFORMA FOR ENVIRONMENTAL APPRAISAL OF MINING PROJECTS
(MINING SECTOR PROJECTS)
1. General Information
(i) Name of the project : Chechat Limestone (Building Stone) Mine
Name of the proponent : Sh. Pankaj Kumar Bairwa Mailing Address : R/o -Satalkhedi, Tehsil -Ramganjmandi Dist- Kota, Rajasthan-
E-mail :
Telephone :
Fax No. :
(b) Objective of the project : Mining of Limestone (Building Stone)
Note 1: All information to be given in the form of Annex/s should be properly
numbered and form part of reply to thisproforma.
Note 2: Please enter √ in appropriate box where answer is Yes / No
Note 3: No abbreviation to be used - Not available or not applicable should be
clearly mentioned.
Note 4: Core zone is the mining lease area.
Buffer zone in case of ML area up to 25 ha.is to be considered as 5 km all
around the periphery of the core zone and for ML area above 25 ha. an
area 10 km all around the periphery of the core zone.
Note 5: Adopt Scoping process in carrying out EIA study.
Note 6: Please indicate source of data.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
(c) Location of mine (s)
Village(s) Tehsil District State
Satalkhedi-
Pipakhedi
Ramganj Mandi Kota Rajasthan
(d) Does the proposal relate to
(i) New mine Yes No
(ii) Expansion Yes No
Increase in ML area Yes No
Increase in annual
production Yes No
(iii) Renewal of ML Yes No
(iv) Modernization Yes No
(e) Site Information
(i) Geographical Location
Latitude
Longitude
Survey of India Topo sheet number
Elevation above Mean Sea Level
√
√
√
√
24°00'00"N to 24°39'30"N
√
√
76°12'96.0"E to 75°59'55.7"E
45P/14 & 54
D/2 Lowest 337 mRL- Highest 340 mRL
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Total mining lease area (in ha.)
(ii) Dominant nature of terrain
Flat Yes No
Undulated Yes No
Hilly Yes No
2. Land usage of the mining lease area (in ha.)
(a) Agricultural
(b) Forest
(c) Waste land
(d) Grazing
(e) Surface water bodies
(f) Others (Pvt. Land)
Total
Nil
√
√
√
Nil
Nil
Nil
Nil
43.24 Ha.
(Forest&govt.waste.lan
d) 43.24 Ha. (Pvt. Land)
43.24
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
3. Indicate the seismic zone in which ML area falls. In case of zone IV & V, details of
earth quakes in last 10 years.
(a) Severity (Richter scale) - Zone II
(b) Impact i.e. Damage to
Life Yes No
Property Yes No
Existing mine Yes No
√
√
√
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
4. Break-up of mining lease area (in ha.) as per approved conceptual plan:
Purpose Mining Lease Area Total Area acquired Area to be acquired
Government Private Government Private Government Private
Forest Others Agri. Others Forest Others Agri. Others Forest Others Agri. Others
1. Area to be excavated - - - - - - - - - -
2. Storage for top soil - - - - - - - - - - -
3. Overburden / Dumps - - - - - - - - - - - -
4. Mineral storage - - - - - - - - - - - -
5. Infrastructure (Workshop, Road & Building)
- - - - - - - - - - - -
6. Roads - - - - - - - - - - - -
7. Railway - - - - - - - - - - - -
8. Green Belt - - - 36.75 36.75 - - - 36.75 - - - -
9. River - - - -- -- - - - -- - - - -
10.Effluent treatment plant - - - -- -- - - - -- - - - -
12. Remaining land - - - -- -- - - - -- - - - -
13. Other (Water reserve) - - - 6.480 6.480 - - - 6.480 - - - -
TOTAL - - - 43.24 ha 43.24 ha - - - 43.24 ha - - - -
Note- About 15.9800 ha area has been already planted within lease for full fill 33% plantation as per ToR compliance. At the end of mine life about 20.77 ha
area will be planted which includes 3.5400 Ha area will be planted on statuary barrier (7.5 Meter) & 17.2396 ha area will be backfill planted. About 6.4804
ha area will be converted as water storage.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
5. Township (outside mining lease)
(a) Total area (in ha)
(b) No. of dwelling units
(c) Distance from mine site
6. Distance of water bodies (in km)
Distance
from
River Bank * Other Water
bodies *
Sea / creek / lake /
nalla etc. (specify)
Mining lease boundary
Amjar Nadi- 9.3 km in NE , Ahu Nadi-
6.4 km in SE, Psadi Nadi 7.5 km in SW
direction from mine site.
-
Ancillary facilities
-- --
[* From highest flood line / high tide line]
7. For projects falling within the Coastal Regulation Zone (CRZ) -
Whether the mineral to be mined is of rare
nature and not available outside CRZ? Yes No
if yes, annex a scaled location map showing low tide line (LTL), high tide line (HTL) duly demarcated by one
of the authorized agencies* [ *Director, Space Application Centre, Ahmedabad: Centre for Earth Sciences
Studies, Thiruvananthapuram: Institute of Remote Sensing, Anna University, Chennai: Institute of Wetland
Management & Ecological Designs, KolKata: Naval Hydrographers’s Office, Dehradun: National Institute of
Oceanography, Panjim, Goa: and National Institute of Ocean Technology, Chennai], boundary of mining
lease area, distance of ML area from LTL and HTL CRZ boundary and CRZ classification of the project area as
per the approved Coastal Zone Management Plan, and settlements, sand dunes, mangroves, forest
land/patches, turtles breeding and nesting sites etc., if any, in the project area.
-
-
-
√
Not Applicable
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
8. Indicate aerial distance from the periphery of core zone / area from the periphery
of the buffer zone to the boundary of following (up to 10 km):
S.
No.
Areas Name Aerial distance from
(in km.)
Core * Buffer*
Zone
1. National Park / Sanctuary None Not Applicable
2. Biosphere Reserve / Tiger
Reserve / Elephant Reserve
/ any other Reserve
None Not Applicable
3. Forest (RF / PF /
unclassified)
Sr.
NO.
RESERVED &
PROTECTED
FOREST
DIRECTION DISTANCE
1 Kuttepur PF NW 6.1 KM.
2 Suket RF E 7.0KM
3 Salvad RF NE 3.9KM
4. Habitat for migratory birds Not Applicable
5. Corridor for animals of
schedule I & II of the
Wildlife (Protection) Act,
1972
Not Applicable
6. Archaeological sites
* Notified * Others
None Not Applicable
7.
Defence Installation None Not Applicable
7. Industries / Thermal Power
Plants
None Not Applicable
8. Other Mines
Two Other mines present in the 500m radius in the lease
area and covered 20.859 ha area around periphery.
9. Airport Indore Airport 251 km from mine
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
site
10. Railway Lines
Ramganj Mandi 4.9 km in SW from lease
area
11. National / State Highways
SH-9 B
NH-12
2.0 km in S direction
8.0 NE direction
[* Buffer zone in case of ML area up to 25 ha. is to be considered as 5 km all around the periphery of the
core zone and for ML area above 25 ha. an area 10 km all around the periphery of the core zone].
9. Description of flora & fauna separately in the core and buffer zones.*
[* Consult the Wildlife (Protection) Act, 1972 as amended subsequently and list species with (1)
Common name (2) Scientific name and (3) under which schedule of the Wildlife (Protection) Act
the identified species fall. Get the list authenticated by an Expert in the field / credible scientific
institute / University / Chief Wildlife Warden office. Information to be based on field survey.]
A. Flora Core Zone Buffer Zone
1. Agricultural crops Ni Soybean, Maize, Black Gram,
Green Gram, Lentil, Wheat,
Jawar, Groundnut.
2. Commercial crops Nil Soybean, Oilseeds & Mustard.
3. Plantation Orange tree, Neem, babool,
Imli Trees, Shrubs & herbs
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
4. Natural vegetation /
forest type
Prosopis juliflora
Zizyphus nummularia
Calotropis procera
Echinops echinatus
Acacia nilotica
Azadirachta indica
Trees
Acacia leucophloea
Acacia nilotica
Aegle marmelos
Ailanthus excels
Albizia lebbeck
Albizia procera
Anogeissus latifolia
Azadirachta indica
Bauhinia racemosa
Bombax ceiba
Cassia fistula
Cassia siamea
Dalbergia sissoo
Emblica officinalis
Ficus benghalensis
Ficus religiosa
Mangifera indica
Polyalthia longifolia
Prosopis juliflora
Syzygium cumini
Tamarindus indica
Zizyphus mauritiana
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Phoenix sylvestris
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Butea monosperma
Shrubs
Annona squamosa
Argemone Mexicana
Calotropis gigantean
Calotropis procera
Ipomoea fistulosa
Jatropha curcas
Lantana camara
Bougainvillea spectabilis
Herbs
Cassia tora
Datura inoxia
Parthenium hysterophorus
Tribulus terrestris
Tridax procumbens
Zizyphus nummulaira
Echinops echinatus
Grass
Cymbopogon martini
Cynodon dactylon
Sida cordifolia
Cenchrus ciliaris
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
5. Grass lands None None
6. Endangered species None None
7. Endemic species None None
8. Others (Specify) None None
B. Fauna
1. Total listing of
faunal elements
Funambulus pennanti
Herpestes edwardsi
Lepus nigricollis
Hanuman langur
Rattus rattus
Rousettus leschenaulti
Hemidactylus brooki gray
Hemidactylus maculates
Acridotheres ginginianus
Acridotheres tristis
Corvus macrorhynchos
Columba livia
Boselaphus tragocamelus
Canis aureus
Funambulus pennanti
Herpestes edwardsi
Lepus nigricollis
Hanuman langur
Rattus rattus
Rousettus leschenaulti
Sus scrofa
Hemidactylus brooki gray
Bufo bufo
Ptyas mucosus
2. Endangered species None None
3. Endemic species None None
4. Migratory species None None
5. Details of aquatic
fauna, if applicable
None None
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
10. Details of mineral reserves (as per approved Mining Plan)
Quantity (in MT)
(a) Proved
(b) Indicated
(c) Inferred
(d) Mineable reserves
11. Major geological formation / disturbances in the mining lease area (a) Geological maps submitted Yes No
(b) Geological sections submitted Yes No
(c) Contour map submitted Yes No
(d) Whether the presence, if any,
Noted of
(i) Faults Yes No
(ii) Dykes Yes No
(iii) Shear Zone Yes No
(iv) Folds Yes No
(v) Other weak zones Yes No
6098022
√
-
--
6606191.7
√
√
√
√
√
√
√
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
(e) Source of data (Indicate)
12. Production of mineral(s) and life of mine
(a) Rated capacity of mine mineral wise (MT / annum)
(b) Life of mine at proposed capacity (Years)
(c) Lease period (Years)
(d) Date of expiry of lease (D /M /Y)
(e) Indicate in case of existing mines
(i) Date of opening of mine
(ii) Production in the last 5 years 1syear 5th year
from year 2010 to year 2015
in million tonnes.
(iii) Projected production for the next 1th to 5th year
5 years in million tonnes.
DETAIL OF YEAR WISE PROPOSED PRODUCTION
Year Saleable
Mineral
tones
Waste
generated from
the total
excavation
(MT)
Sub grade
in MT
Over
burden
form OB
benches
tonnes
Over
burden+
mineral
waste
tonnes
Stripping
ration
Mineral:
waste
I 225189 80424 16084 1026432 1106856 1:4. 915
II 225189 80424 16084 712800 793224 1:3.522
III 225189 80424 16084 712800 793224 1:3.522
IV 225189 80424 16084 712800 793224 1:3.522
321699 TPA
21 year
19/01/2022
30 year (20/01/1992 to 19/01/2022)
20/01/1992
By 1) Survey & Field works
32, 75,635 Sq feet 27,71,255 Sq feet
3,21,697 TPA (ROM) 3,21,697 TPA (ROM)
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
V 225189 80424 16084 712800 793224 1:3.522
Total 1125945 402120 80420 3877632 4279752
(iv) Whether mining was suspended after Yes No Opening of the mine?
If yes, details thereof including last production figure and reason for the same.
(f) Whether plans & sections provided? Yes No
13. Type and method of mining operations
TYPE METHOD
Opencast √
Manual
Underground Semi-mechanized
Both Mechanized √
14. Details of ancillary operations for mineral processing
DETAIL OF MACHINERY DEPLOYED OR TO BE DEPLOYED
Type of Machinery
Nos. Bucket Capacity in Cum.
Motive Power
Make H.P.
Dumper 6 10 tonner Diesel Tata 119 HP Water pump 1 - Diesel Local -
Compressor 1 75 CFM - Local - Jack Hammer 2 32 mm Diesel Local - Excavator 2 1.2 m3 Diesel Local - JCB 1 - Diesel Escort - Jiri Cutting m/c 8 - - --- - DG Set 2 125Kva Kriloskar
√
Not Applicable
√
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
15. Mine details
(a) Opencast mine
(i) Stripping ratio (mineral in tonnes to over burden in m3)
(ii) Ultimate working depth (in m bgl)
(iii) Indicate present working depth in case of
Existing mine (in m bgl)
(iv) Thickness of top soil (in m.)
Minimum
Maximum
Average
(v) Thickness of overburden (in m.) No-O/B Not applicable
Minimum
Maximum
Average
(vi) Mining Plan
Height and width of the bench in Overburden / waste. Height & width of the bench in ore body /
coal seam.
Proposed inclination / slope of the sides of the opencast mine (separately for overburden, coal / ore and overall slope of the pit sides) both while operating the mine as well as at the time of closure of the mine.
37mbgl
1.0
3.00
2.00
1:3.522
--
1.0
3.0
2.0
Height-6m- 9m & Width –
more than -6m- 9m.
--
450
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Whether transverse sections across the Yes No opencast mine at the end of fifth year
and at the end of the life of the mine have been submitted? (vii)Type of blasting, if any, to be adopted.
(b) Underground mine - Not applicable
(i) Seam / Ore body Min. Depth (m) Max. Depth (m) Avg. thickness (m)
Rate of dip Direction of dip
in degree
(ii) Mode of entry into the mine
Shaft
Adit
Incline
√
√
Small blasting with low charge of
holes
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
(iii) Details of machinery
On surface
At Face
For transportation
Others
(iv) Method of stopping (metalliferrous mines)
Open
Filled
Shrinkage
Caving
Combination of above
Others (Specify)
(v) Extraction method
Caving
Stowing
Partial extraction
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
(vi) Subsidence
Predicted max. subsidence (in m)
Max. value of tensile strain (in mm/m)
Max. slope change (in mm/m)
Whether identified possible subsidence Area superimposed on Surface Yes No Plan has been submitted?
Major impacts on surface features like natural drainage pattern, houses,
Buildings, water bodies, roads, forest,
etc.
Salient features of subsidence Management (monitoring and control).
16. Surface drainage pattern at mine site (Figure-3.4)
(a) Whether the pre-mining surface drainage plan Yes No
Submitted?
(b) Do you propose any modification / diversion Yes No
in the existing natural drainage pattern at any
stage? If yes, when. Provide location map
indicating contours, dimensions of water body to be
diverted, direction of flow of water and proposed
route / changes, if any i.e. realignment of river / nallah /
any other water body falling within core zone and
its impact.
√
√
√
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
17. Embankment and / or weir construction - Not applicable
(a) Do you propose, at any stage, construction of
(i) Embankment for protection against flood Yes No
(ii) Weir for water storage for the mine? Yes No
(b) If so, provide details thereof.
( C) Impact of embankment on HFL and settlement
around.
(d) Impact of weir on downstream users of water.
18. Vehicular traffic density (outside the ML area)
Type of vehicles No. of vehicles per day
(a) Existing
(b) After the proposed activity
(c) Whether the existing road Yes No
Network is adequate? If no, provide details of alternative proposal?
19. Loading, transportation and unloading of mineral and waste rocks on surface:
(a) Manual Yes No
(b) Tubs, mine cars, etc. Yes No
√
LMV/HMV
350/200
400/220 LMV/HMV
√
√
√
√
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
(c) Scraper, shovels, dumpers / trucks. Yes No
(d) Conveyors (belt, chain, etc.) Yes No
(e) Others (specify).
20. Mineral(s) transportation outside the ML area
Qty. (in TPD) Percentage (%) Length (in km)
(a) Road
(b) Rail
(c) Conveyors
(d) Rope way
(e) Water ways
(f) Pipeline
(g) Others (Specify)
Total
1072
1072
100
100
√
√
Excavator
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
21. Baseline Meteorological and Air Quality data- EIA & EMP Report enclosed
(a) Micro-meteorological data
[Continuous monitoring through autographic instrument for one full season other than monsoon]
(i) Wind rose pattern for one full season (16 points of compass i.e. N, NNE, NE, ---) based on 24-hourly data. For coastal area also furnish
day-time and night time data.
Day time- Day time wind direction max. towards N to S
Night time- 24 – hours period from N to S
(ii) Site specific monitored data
Month
Temperature (°C) Relative Humidity
(%)
Prominent wind
speed(Km./Hr.)
Max. Min. Max. Min. Max. Min.
March, 16 38.2 13.0 78.0 20.0 16 0.2
April, 16 44.6 19.0 76.0 16.0 22 0.4
May, 16 46.6 24.2 74.0 14.0 32 0.6
* 24-hour’s rainfall should be reported from 08:30 hrs. IST of previous day to 08:30 hrs.IST of the day. * Rainy day is considered when 24 hrs. rainfall is 2.5 mm.
** Visual observations of cloud cover should be recorded four times a day at regular intervals.
(iii) Indicate name and distance of the nearest IMD meteorological Station from which climatological data have been obtained for
reporting in the EIA report, if any.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
(b) Ambient air quality data* (RPM, SPM, SO2, and NOx)
[*Monitoring should be carried out covering one full season except monsoon – same season as in 21 (a) (i)]
[*Frequency of sampling: Sampling to be done twice a week for the entire season 24 hourly for SPM & RPM. For gaseous pollutants 24- hourly data be given irrespective of
the sampling period. ]
(i) Season and period for which monitoring has been carried out.-Summer season period (March to May 2016)
(ii) No. of samples collected at each monitoring station follows-
Name of monitoring equipment used
PM2.5 PM10 SO2 Nox Pb**
High volume High volume High volume -- Equipment sensitivity --
Permissible AAQ standard (CPCB) R I S
60 100 80 80 --
60 100 80 80 --
60 100 80 80 --
Monitoring Location
No. of Samples Drawn
Category* (R, I, S)
Min. Max. 98%
Min. Max. 98%
Min. Max. 98%
Min. Max. 98%
--
Core zone
24 Mining 20.23 25.84
25.34 58.49
78.70 77.12 BDL 5.05 4.94 3.19 7.14 6.99 --
Buffer zone
500 D/w 24 - 19.75 25.96 25.44 58.80 74.94 73.44 BDL 4.84 4.74 3.05 6.37 6.24 Pipakheri 24 - 19.48 25.11 24.60 59.54 75.47 73.96 BDL 5.15 5.04 3.1 7.91 7.75 --
Satalkheri 24 R 19.67 26.09 25.56 62.18 77.47 75.92 BDL 4.91 4.81 3.02 7.98 7.82 --
Suket 24 R 19.03 25.06 24.55 61.56 78.78
77.20 BDL 4.95 4.85 3.02 8.06
7.89 --
Naharsinghi 24 R 19.62 26.01 25.48 59.45 80.77 79.15 BDL 5.05 4.94 3.02 8.26 8.09 --
Khairabad 24 R 19.48 26.01 25.48 61.72 76.65 75.11 3.00 5.05 4.94 3.25 6.96 6.82 --
Salvad khurd 24 R 19.75 25.96 25.44 58.8 74.94 73.44 BDL 5.07 4.96 3.23 8.05 7.88 --
*R = Residential; I = Industrial; S = Sensitive (Source-Primary data collected by M/s Udaipur Min-Tech Pvt. Ltd)
**Pb for mineral specific sites only.# Annex a location map indicating location of AAQ stations, their direction and distance with respect to project site.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
22. Stack and emission details, if any* Not applicable
Sl.
No.
Process / unit
of operation
(e.g. DG Set,
Boiler)
Height of
stack
(m)
Internal
top dia.
(m)
Flue gas
exit
velocity
(m/sec)
Emission rate (kg/hr) Heat
emission
rate from
top of
stack
(K.cal/hr)
Exhaust / Flue gas
SPM SO2 NOx CO Temp
OC
Densit
y
Specific
Heat
Volumetric
flow rate
(m3/hr.)
23. Details of fugitive emissions during mining operations* Not applicable
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
24. Air Quality Impact Prediction (AQIP)* - Not applicable
(a) Details of model(s) used for AQIP including grid
size, terrain features, and input meteorological data
(b) Maximum incremental GLC values of pollutants based on
prediction exercise
(inμg/m3)
S. No. Pollutants
Incremental Value Ambient Air Quality Resultant Air Quality
1. PM10 0.8 78.7 79.5
2**. SO2 -- -- --
3**. NOX -- -- --
[* Question Number 22, 23 & 24 need not be filled-in for mines having ML area of 25 ha. or less.]
[**Information on item no. 2 & 3 to be provided in cases with captive power generation of 500 KVA and above]
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
25. Water requirement (m3/day)
Purpose Avg. Demand Peak Demand
A. Mine site
1. Mine operation
2. Land reclamation
3. Dust suppression
4. Drinking
5. Green Belt
6. Beneficiation
7. Washeries
8. Fire Service
9. Others (specify)
B. Township
1. Green Belt
2. Domestic
3. Other (specify)
Nil
Nil
2.0
3.0
2.0
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
2.0
3.0
2.0
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Total 7.0 7.0
26. Source of water supply*
S. No. Source m3/day
1 River (name) Nil
2 Ground water 7.0 KLD
3 Mine water (sump / pit) Nil
4 Other surface water bodies (specify) Nil
[*Annex a copy of sanction letter / permission from the concerned authority (Central Ground
Water Authority in case of ground water abstraction is from notified area / State Ground Water
Board in case of non-notified area / State Irrigation Department for surface water pumping) for
drawing water.]
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
27. Lean season flow in case of pumping from river / nalla (cumecs)
28. Ground water potential of the study area
28.1. Ground water availability
(a) Range of water table (m bgl)
(i) Pre-monsoon (April/May)
Core Zone
Buffer zone
(ii) Post-monsoon (November)
Core Zone
Buffer zone
(b) Total annual replenishable recharge (million m3/ year)
By ground water table fluctuation method
By rainfall infiltration factor method
(c) Annual draft excluding estimated draft through
mine discharge (million m3/ year)
(d) Estimated draft through mine discharge (million m3/ year)
(e) Net annual ground water availability (million m3/ year)
(f) Stage of ground water development in %
-
Not Applicable
38-40m
40-42m
40-45m
45-50m
-
-
10.38BCM
125%
-
11.56BCM
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
28.2 Water demand - Competing users of the water source
S. No. Usage Present Consumption
(m3/day)
Additional proposed
as per local plan
(m3/day)
Total
(m3/day)
Surface Ground Surface Ground Surface Ground
1 Domestic -- -- -- -- -- --
2 Plantation --- -- -- 3.0 -- 3.0
3 Industry -- -- -- -- -- --
4 Mining -- -- -- -- -- --
5 Dust
Suppression
-- -- --
2.0 -- 2.0
6 Sanitation &
Drinking --
-- -- 2.0 --
2.0
Total -- -- -- 7.0 -- 7.0
29. Water quality*
(a) Physico -chemical analysis of water at intake point **
Water quality testing is an important part of environmental monitoring. This section
details all of the physical & chemical parameters that affect the quality of water in the
environment. Physical properties of water quality include Color, Order, Turbidity and
Total Dissolved Solids. The chemical characteristics involve parameters such as pH,
Alkalinity, Chlorides, Total Hardness, Calcium, Magnesium, Sulphate, Iron, Nitrate and
Fluoride etc.
Water quality analysis result is attached as EIA/EMP report
** All parameters as per BIS 10500. Method- IS:2488.
(b) In case of existing mine, annex report on quality of water discharge
i.e. complete physico - chemical analysis** - Water quality analysis result is attached as
EIA/EMP report.
[*For non-discharging mines at least four ground water samples to be taken preferably
from downstream direction of the mine in pre-monsoon and post-monsoon periods
and analysed. For discharging mines six samples are to be analysed]
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
**All parameters as per BIS 10500. Indicate name of Methodology, Equipment used for analysis, and Detection Level (DL) for each parameter. *** Wherever any analytical parameter is below detection level, “BDL” (Below Detection Level) should be written instead of ‘NIL’.
30. Impact on ground water regime / stream / lake / springs due to mine dewatering * -
Ground water will not be intersected during the course of mining operation,
(a) Radius of influence (in m)
[To be estimated based on analysis of pumping
test data and application of empirical formula]
(b) Whether saline water ingress will take place? Yes No
(Applicable to coastal areas)
(c) Impact on stream / lake / springs
[* Provide a comprehensive hydro-geological assessment report if the average mine
dewatering is more than 100 m3/day and or going below water table in non-monsoon period.
The report should be based on preferably latest one year pre-monsoon and post-monsoon
baseline data covering information on ground water situation, aquifer characteristics, water level
conditions (April – May and November), estimate of ground water resources, predicted impact of
the project on ground water regime and detailed remedial / conservation measures such as
artificial recharge of ground water etc. The report should be based on actual field inventory out
of existing wells, at least 30 observation wells in the buffer zone with supplementary information
from secondary sources (mention name). For estimation** of ground water resource (refer
question no. 28 above) be designated study area of the buffer zone may be sub-divided into
command and non-command areas, watershed-wise (in case of hard rock / consolidated
formations) / block-wise / mandal-wise in case of alluvial / unconsolidated formations)]
[**For estimating ground water resources in the area follow the Ground Water
Estimation Committee recommendations of 1997]
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
31. Waste Water Management-Not applicable
Mine
(a) Daily average discharge (m3/day) from different sources
(i) Mine water discharge during
Lean period Monsoon period
(ii) Workshop
(iii) Domestic (mine site)
(iv) Beneficiation / Washeries
(v) Coal Handling Plant
(vi) Tailings pond
(vii) Others (Specify)
Total
(b) Waste water treatment plant; flow
sheet for treatment process attached. Yes No
(c) Quantity of water recycled / reused / to be recycled in
(i) Percentage
(ii) m3/day
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
√
Not Applicable
Not Applicable
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
(d) Point of final discharge -Not Applicable
Final Point Quantity discharged (in m3/day)
1. Surface
(i) Agricultural land
(ii) Waste land
(iii) Forest land
(iv) Green belt
Not Applicable
2. River / nallah Not Applicable
3. Lake Not Applicable
4. Sea Not Applicable
5. Others (specify) Not Applicable
Total Not Applicable
(e) Users of discharge water
(i) Human Yes No
(ii) Livestock Yes No
(iii) Irrigation Yes No
(iv) Industry Yes No
(v) Others (specify)
Details of the river / nalla, if final effluent is / will be discharged (cumecs)– Not Applicable
(i) Average flow rate
(ii) Lean season flow rate
(iii) Aquatic life
Not application
Not Applicable
Not Applicable
√
√
√
√
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
(iv) Analysis of river water 100 meters Yes No Upstream and 100 meters downstream
of discharge point submitted. Township – Not Applicable
(a) Waste water generation from
Township (m3/day) (b) Are you planning to provide sewage Yes No
treatment plant? (c) Usage of treated water 32. Attach water balance statement in the form of a flow diagram indicating source (s), consumption (Section-wise) and output.
WATER BALANCE DIAGRAM
A. WATER REQUIREMENTS FOR DUST SUPPRESSION AND PLANTATION
No out flow
No outflow No out flow
No outflow
Source: well & water tanker
Plantation-2.0 KLD Water Sprinkling 2.0 KLD
– 2KLDKLKLD
Septic tank- Soak
Drinking & sanitation-
3.0KLD
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
33.Ambient noise level leq dB (A) 1Hour Leq
Location of Sampling Stations Noise Level
Day Time Night Time
Core zone 50.6 42.8
Buffer zone
500 D/w 49.3 41.5
Pipakheri 51.5 42.7
Satalkheri 52.2 43.1
Suket 53.7 44.3
Naharsinghi 51.8 43.5
Khairabad 52.4 41.9
Salvad khurd 51.6 42.6
34. Solid Waste (a) Top soil and Solid waste quantity and quality
Name
(Lump/fines/
slurry/
Sludge/others)
Composition Quantity
(ton/year)
Method of disposal
Mining activity*
Fractured
mineral waste
and
overburden
461190
Cum/year
(Maximum)
About 1370730 cum of overburden
& fracture waste will be generated
during plan period. Waste generated
will simultaneously be used for the
backfill purpose of the mine out pit
and planted.
Effluent Treatment
Plant (sludge)
Nil Nil Nil
Total Nil 461190
Cum/year
Nil
[* Annex layout plan indicating the dump sites.]
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
(b) (i) Does waste (s) contain any
Hazardous/toxic substance/
Radioactive materials or Yes No
heavy metals?
(ii) If yes, whether details and Yes No
Precautionary measures
provided?
(c) Recovery and recycling possibilities. NO
(d) Possible user(s) of the solid waste.
(e) (i) Is the solid waste suitable for
Backfilling? Yes No
(ii) If yes, when do you propose
to start backfilling.
(in million m3)
Solid waste (s) Already
accumulated
(A)
To be generated
(B)
% of A & B to be
backfilled
A B
Over burden
Nil About 1370730 cum
(Plane period)
-- 100%
Others (specify)
Nil - -- --
√[
activi
ty*
[
a.
Top
Soil
[
b.
Over
burd
en
[
c.
Othe
rs
(spec
ify)
Mine out area will be backfill & planted.
[
a.
Top
Soil
[
b.
Over
burd
en
[
c.
Othe
rs
(spec
ify)
[
a.
Top
Soil
[
b.
Over
burd
en
[
c.
Othe
rs
(spec
ify)
√[
a.
Top
Soil
[
b.
Over
burd
en
[
c.
Othe
rs
(spec
ify)
[
a.
Top
Soil
[
b.
Over
burd
en
[
c.
Othe
rs
(spec
ify)
√
activi
ty*
[
a.
Top
Soil
[
b.
Over
burd
en
[
c.
Othe
rs
(spec
ify)
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Land reclamation Plan–
(f) In case waste is to be dumped on the ground, indicate
(i) Associated environmental problems - NO
(ii) Number & type of waste dumps
No. of external dumps
Max. projected height of dumps (in m)
No. of terraces and height of each stage
Overall slope of the dump (degree)
Proposed reclamation measures
(iii) Section of the waste dump in relation
to the adjacent ground profile attached. Yes No
35. Fuel / Energy requirements*
[*To be furnished for mines having ML area more than 25 ha. or captive power generation of
500KVA and above]
(a) Total power requirement- Not Applicable
(in MW)
S. No. Mine Site Township Others (specify) Total
1 Present
2 Proposed /
additional
Total
-
-
-
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
(b) Source of power (in MW)
S. No. SEB/Grid* Captive power plant DG Sets
1 Present
2 Proposed
Total
[* Annex a copy of the sanction letter from the concerned authority]
(c) Details of fuels
S.No. Fuel Daily Consumption
(TPD)
Calorific
value
(Kcals/kg)
% Ash % Sulphur
Existing Proposed
1
2
3
HSD
LSHS
Other
(specify)
300Lit. /
Day
350Lit. / Day
10800 0.01 0.25
36. Storage of inflammable / explosive materials
S. No. Name Number of
Storages
Consumption
(in TPD)
Maximum Quantity at
any point of time
1 Fuels -- -- -
2 Explosives - --- -
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
37. Human Settlement
Core Zone Buffer Zone
Population* Nil 147485
No. of villages Nil 34
Number of
households village-
wise
Nil 30178
[* As per 2001 census record or actual survey]
38. Rehabilitation & Resettlement (R&R) Plan*
[*Provide a comprehensive rehabilitation plan, if more than 1000 people are likely to be
displaced, other-wise a summary plan]
(a) Villages falling within the study area
Villages
Number Name
Core zone Nil Nil
500 m from the blasting site (s) Nil Nil
Buffer zone 34 List enclosed in EIA/EMP report
Township site Nil Nil
(b) Details of village(s) in the core zone- Not applicable
S.
No.
Village name
Population* Average Annual
Income Tribal Others
[*As per 2011 census / actual survey]
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
(c) Population to be displaced and / or Land oustees -Not applicable
Name of village(s) falling within Number of oustees
Land
(only)
Homestead
(only)
Land and
Homestead (both)
Mining Lease
1.
Township Site
1.
(d) Whether R&R package has been finalised?
If yes, salient features of R&R plan for oustees. Not Applicable
(i) Site details where the people are proposed to
be resettled & facilities existing / to be created.
(ii) Funds earmarked for compensation package.
(iii) Agency /Authority responsible for their
Resettlement.
(iv) Time of commencement of resettlement
of Project Affected People (PAP).
(v) Period by which resettlement of PAP will
be over.
39. Lease -wise plantation details
(a) Lease area (in ha.) -43.24 Existing mine New mine
(i) Area broken up
(ii) To be broken up
(iii) Area not to be broken-up
(b) Township area (in ha.)
8.5215 Nil
18.73 Nil
15.9800 Nil
Nil
Nil
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
(c) Area afforested and proposed (in ha.)
Peripheral Dumps Roads Township Others
(i) Existing Nil Nil Nil Nil 15.98
(Reaming land)
(ii) Proposed 3.5400 Nil Nil Nil 17.239
(Back fill planted)
(d) No. and type of trees planted and proposed
(i) Existing- Yes
When plantation was started? Month / Year
No. of plant species planted Number saplings (per ha.)
Neem, Orange Tree, Imli, --
Survival rate % ● Avg. height
(iii) Proposed
No. of plant species to be planted Number of saplings
1. Neem 2. Shisham 3. Piple, 4. Mango
-- 80%
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
40. Environmental health and safety
(a) What major health and safety hazards are anticipated? Inhalation of dust, benches failure, explosions.
(b) What provisions have been made/proposed to be made to conform to health and safety requirements?
Dust mask, noise- ear plugs, mufflers, safety shoes, helmets, hand gloves & all
necessary medical facilities provided & medical camp conduct periodically.
(c) In case of an existing mine-
i) Comprehensive report on health status
of the workers as under the Mines Act annexed Yes No
(ii) Mineralogical composition of RPM (dust)
Free silica-Not required because lime stone is not having free silica
content.
Chromium* (Total as well as Hexavalent)
Lead**
[* Only for Chromite mines]
[**Only for Base Metal mines]
(d) Information on radiation protection measures, if applicable.
√
√
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
41. Environmental Management Plan
Salient features of environmental protection measures
S. No.
Environmenta
l issues*
Already practiced, if
applicable
Proposed
1 Air pollution (1) Water spraying is
being done on haul road
existing in lease area
(2) Air monitoring will be
done once in 6 month
(3) dusk mask is being
provide to worker
engaged in mining activity
(4) Afforestation activities
for controlling of dust.
The same environmental protection
measure will continue in future.
2 Water pollution The garland drain are will
be made around the
working pit.
The water pump out from
the mine is utilized in
plantation area.
The same environmental protection
measure will continue in future.
3. Water
conservation
-- Rain water storage will be
developed at the end of mine life.
4. Noise pollution Proper maintenance of
transport vehicle are
being done to minimize
noise.
Adequate silencer should
be provided in all the
truck and tractor.
The same environmental protection
measure will continue in future.
5. Solid waste /
Tailings
No No generated any waste, mine only
generated small quantity of waste
will be used in plantation.
6. Land
degradation
Minimum Land has been
used for infrastructure
and other activities.
The same environmental protection
measure will continue in future
7. Erosion & Green Belt development
around the area
--
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Sediment minimizes the impact due
to mining actives.
8. Top soil stacked separately Top should be stacked separately
that will be used in plantation
during monsoon
9. Ground
vibration
Control Blasting with low
intensity will be practiced.
Deep hole blasting will not
be carried out.
The measure will same continue in
future.
10. Wildlife
conservation
- Not required.
11. Forest
protection
Lease area does not falls
in forest area.
Not required.
12. Others
(specify)
- --
[* As applicable]
42. Compliance with environmental safeguards (For existing units)
(a) Status of the compliance of conditions of
Environmental clearance issued by MoEF, Yes No
if any, enclosed.
(b) Status of the compliance of ‘Consent to
Operate’ issued by SPCB, if any, enclosed. Yes No
(c) Latest 'environmental statement' enclosed. Yes No
√
√
√
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
43. Scoping of EIA
Whether environmental impact assessment
of the project has been carried out b Yes No
Following scoping process
If yes, a copy of scoping of EIA yes No
Annexed.
44. Mine closure
(a) Have you planned mine closure? Yes No
(b) Submitted a conceptual mine Yes No
Closure plan.
(c) If yes, indicate estimated amount for
Implementing the same (in Rs. Lakhs)
(Mining Plan with progressive Mine closure Plan has been prepared and approved by IBM)
45. Capital cost of the project (in Rs. Lacks)
(Based on latest estimate)
80 Lacks
--
√
√
√
√
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
46. Cost of environmental protection measures
(in Rs. )
S. No. Capital cost (in Rs.) Annual recurring cost (in Rs.)
Existing Proposed Existing Proposed 1 Pollution Control
(Garland Drain, Water sprinkler, Wet drilling)
- 3,00,000 - 1,00,000
2 Pollution Monitoring (Air, soil, Water, Noise)
- 5,00,000 - 1,00,000
3 Occupational Health - 5,00,000 - 1,00,000
4 Green Belt - 2,50,000 - 50,000
Total 15,50,000 3,50,000
47. Amount earmarked for socio-economic welfare measures for the nearby villages
other than R&R plans.
S.No Activity Detail of Educational Institute
Facilities provided CSR Fund
1 Education Facility in
Pipakheri village
(within 5 km)
Distance 1.0 Km.
Primary school in Pipakhedi *Washroom for girls.
*Schools shoes & stationery distribute for the poor student. *Provide drinking water
facility
Rs 75,000.
Activity Proposed Detail Training Fund
2 Skill Development\
Youth
Sport camp organization for youth
at Hathiya kheri Village ( Football,
Cricket match, volleyball,)
Rs. 50,000
Health & Sanitation
(within 5 km from the
site)
Contact person Proposed facilities CSR Fund
3 Sub Health Centre
(Distance 1.0 km.)
Smt. Mamata
(ANM)
- waste disposal facility
- Medical camp organization
-Medicine distribution
Rs. 75,000
Total 2.0 Lack
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
48. Public Hearing
(a) Date of Advertisement
(b) Newspapers in which the advertisement appeared
(c) Date of public hearing (DD/MM/YYYY)
(d) Public Hearing Panel chaired by & members present
(e) No. of people attended the public hearing meeting
and number of people from the lease area.
(f) Summary/details of public hearing in tabular form.-
NOTE: - Copy of minutes of Public Hearing in Hindi and English is enclosed as Annexure
No.-XI
RO, District collector, Lessee,
Consultant
06/12/2016
Dainek Bhaskar & Jabaaz Patrika
49 05
05/11/16 & 04/11/2016
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
49. Whether the following approvals* (wherever applicable) have been obtained?
A. Site clearance from MOEF – Not Required
B. Consent to establishment from the SPCB Yes
C. NOC from Atomic Energy Division – Not Required
D. Letter of mining scheme/Plan - Yes (Annexure No. IV) Approved from IBM/DMG
E. Forestry clearance under FCA, 1980 Not Required
F. NOC Chief Controller of Explosives - Not Required
G. Commitment regarding availability of Not Required
Water and power from the concerned
State Authorities
H. In case of ML area falling in notified areas Not Required of the CGWA, NOC from them
* (Annex copies)
[* Annex copies of approvals and number them]
50. Was / is there any court case relating
to the project or related activities? - NO
If so, provide details present status.
Verification: The data and information given in this proforma are true to the best of my
knowledge and belief.
Date: Signature of the applicant* with full name & address
Place: [* Owner or his authorized signatory]
Given under the seal of organization on
behalf of whom the applicant is signing
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
ANNEXURE
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
ANNEXURE –I: COPY OF LEASE AGREEMENT
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
ANNEXURE –II: COPY OF NOMINATION LETTER
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
ANNEXURE –III: COPY OF LEASE EXTENSION LETTER
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
ANNEXURE IV COPY OF APPROVAL LETTER OF MINING PLAN
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
ANNEXURE –V: COPY OF KHASRA MAP, JAMABANDI& DEMARCATION
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
ANNEXURE –VI: PREVIOUS Year’s PRODUCTION
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
ANNEXURE –VII COPY OF ARAVALI LETTER
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
ANNEXURE –VIII COPY OF COMPOSITE MAP
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
ANNEXURE –IX COPY OF NOC
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
ANNEXURE –X: COPY OF MONITORING REPORT
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
ANNEXURE –XI: TOR LETTER
Secretariat of State Level Expert Appraisal Committee (SEAC) Rajasthan
4, Institutional Area, Jhalana Doongri, Jaipur-302004
Phone: 0141-5159661 ;E-mail: [email protected]
File No. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project /Cat.1(a)B1(7243) /14-15/752 Dated:-
06.05.2016
To, Sh. Pankaj Kumar Bairwa
Chechat Dist. Kota
Email: [email protected]
Sub: Submission of Application for prior Environmental Clearance (Form I along with pre
feasibility Report) of Satalkhedi Limestone Mine over an area of 43.24 hect. (ML no. 55/91) Near
Village- Satalkhedi Tehsil- Ramganjmandi & Ditrict – Kota (Raj.) in favor of Sh. Pankaj Kumar
Bairwa Production Capacity 3,21,699 TPA. (ROM) File No. 7243
Consultant – – EIA Consultant, M/s. Udaipur Mintech Pvt. Ltd. 206, Apeksha Complex, Sec. 11,
Hiram Magri, Udaipur, Rajasthan. 313002. E-mail: [email protected]
Observation of the Committee-
Keeping in view the information contained in the documents submitted and circulated to the
members by the PP, the committee. Terms of Reference including preparation of Environment
Impact Assessment Report and conduct “Public Hearing” for As above Project Name,
Proponent Name and Consultant.
1. The study area will comprise 10 km zone around the mine lease from lease periphery and the data contained in the EIA with respect to mining operations such as conceptual pit limits, waste generation etc. should be for the life of the mine/lease period.
2. Location of other industries & mines within the study area along with their production and pollutants generated by them, estimated pollution load and cumulative impact on environment including the proposed project should be submitted. The same shall be accounted for while generating mathematical models of pollution dispersion for preparation of the EMP.
3. Year-wise production details clearly indicating the proposed highest production for the life of the mine/lease period should be submitted.
4. Details of land to be used as the designated dumping site for OB dump should be selected and proposed within the lease area as per the approved mining plan. In no case the overburden should be dumped outside the lease area, however proposal for utilization of OB for construction or other meaningful use to the extent possible may be submitted and should try to work on zero waste patterns. Details regarding quantity of solid waste
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
generation to be estimated and details for its disposal and dump management are to be provided.
5. Land use plan of the mine lease area should be prepared to encompass pre-operational, operational and post operational phases.
6. The P.P. should provide a mining plan along-with progressive mine closer plan and implementation plan at the time of submission of application for the EC.
7. Based on the study and the points raised by the people during public hearing, the P.P. shall work out an effective plan to address the environmental, socio-economic and other issues identified during the process, with suitable funds allocation for the purpose. Further PP shall implement all commitments made during public hearing, while implementing the project.
8. Certificate regarding mine lease area not falling in the Aravalli Hills to be issued by the Mining Engineer/ Assistant Mining Engineer in the prescribed format, as per the instructions contained in the letter no. DMG/ADM/Env/EC/F11/06/17-76 dt. 17.01.2011 issued by the Director, Department of Mines and Geology, GoR, Udaipur, should be submitted.
9. List/details within 10 km radius of the mine lease area, the location of human settlement, water bodies, Reserve Forest, National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors, Tiger/Elephant reserves (existing / proposed), shall be clearly indicated giving the land use. Necessary clearance, if any, as may be applicable to such projects due to proximity of the ecologically sensitive areas as mentioned above shall be obtained from the Chief Wildlife Warden under the Wildlife (Protection) Act’ 1972 and submitted. This location map should also indicate the list and location of other mine leases existing, if any, within 10 km radius.
10. A detailed biological study for the study area [core zone and buffer zone (10 km radius of the periphery of the mine lease)] shall be carried out. Details of flora and fauna, duly authenticated, separately for core and buffer zone should be furnished based on field survey. The details regarding flora to include information regarding (a) trees, shrubs, grasses, (b) frequency, density, I V I, abundance % of species occurring on proposed site, (c) dominant species of trees, shrubs , grasses (d) endemic species, (e) threatened species, (f) rare species, (g) endangered species and (h) vulnerable species. The details of fauna to include information regarding list and distribution clearly indicating the Schedule of the fauna present. In case of any scheduled-I fauna found in the study area, the necessary plan for their conservation should be prepared in consultation with State Forest and Wildlife Department and details furnished. Necessary allocation of funds for implementing the same should be made as part of the project cost.
11. Collection of one season (non-monsoon) primary baseline data on ambient air quality, water quality, noise level, soil and flora and fauna. Ambient Air quality should be determined by measuring the concentration of parameters like P.M.2.5, P.M.10, SO2, NOx according to the latest standards prescribed by CPCB. Site-specific meteorological data should also be collected. The location of the monitoring stations (minimum 6) should be justified. Date wise collected baseline AAQ data should form part of EIA and EMP report. The monitoring shall be carried out by CPCB/NABL/ MOEF&CC/GoR approved laboratory and copy of the report submitted. The monitoring if any prior to submission of project to SEIAA for ToR will not be considered.
12. Air quality modeling should be carried out for prediction of impact of the project on the air quality of the area. It should also take into account the impact of movement of vehicles for transportation of mineral. The details of the model used and input parameters used for modeling should be provided. The air quality contours may be shown on a location map clearly indicating the location of the site, location of sensitive receptors, if any and the habitation. The wind roses showing pre-dominant wind direction may be indicated on map. Wind Rose Diagram should be representative and include stability class and inversion phenomenon of that area along with the lapse rate.
13. A surface and ground water study should be carryout, both pre-monsoon and post monsoon monitoring. Information about proposed working depth of mining area, groundwater table both in above MSL and below ground level (BGL) should be provided. Based on actual
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
monitored data, it may clearly be shown whether mine working will intersect groundwater table or not. In case the mining activity intersects the ground water table then necessary permission from CGWA should be obtained. Impact of the project on the water quality both surface and groundwater should also be assessed and necessary safeguard measures, if any required should be provided. Further, submit water drainage plan of the 10 km study area.
14. The water requirement for the project, its availability and source to be furnished. A detailed water balance should also be provided. Fresh water requirement (if any) for the project should also be indicated. Necessary clearance from the Competent Authority for drawl of requisite quantity of water for the project should be provided. Details of water conservation measures including rainwater harvesting should be provided and to be adopted in the project.
15. Consumption of diesel and its storage should be provided along with an action plan for its conservation.
16. The Conceptual post mine land use plan and Reclamation & Rehabilitation (R&R) plan of mined out area (with plans and sections at appropriate scale as per MCDR 1988 should be submitted.
17. Impact on local transport and infrastructure due to the project: Projected increase in hauling vehicles as a result of the project in the present road network (including those outside the project area) and whether it is capable of handling the increased load. Arrangement for improving the infrastructure to avoid any congestion especially at junctions and mishaps throughout the route of transportation of mineral should be ensured and action to be taken by other agencies such as State Government, if any, should be covered.
18. The green belt area should be developed in 33% of total lease area, provide time taken for of progressive greenbelt development, plantation and compensatory a-forestation clearly indicating the 33% area to be covered under plantation giving detail of local species, width of plantation, plantation schedule etc. along with year wise financial expenditure. The proposal for completion should be for a period of 3 years from the start of mining operation. Information regarding greenbelt development plan shall also be prepared in a tabular form, indicating the location of the area, type of tree and its number supported by a map. Further, existing mining projects should carryout plantation in 33% of lease area and thereafter come for the EC.
19. Budgetary provision for the labors working in the Mine should be submitted for all necessary infrastructure facilities such as health facility, sanitation facility, and fuel for cooking, along with provision for safe drinking water, monthly medical camps and distribution of medicines, primary education and toilets for women, crèche for infants.
20. Details regarding Occupational health impact of the project should be provided. Health study in the surrounding area be carried out covering information regarding prevailing diseases, mortality rate etc. Health and Safety Plan should be prepared and submitted.
21. The P.P. will carry out proper Socio-economic survey of the villages situated in the study area. The details of survey are given if format J. Based upon its findings and also as per public hearing issues and keeping in view the felt needs of local populations, the P.P. will provide adequate budget for carrying out CSR/ESR activities including provision for toilets for girls in nearby schools, monthly medical camps, distribution of medicines and improvement in educational facilities in the nearby schools. Further, existing mining projects should carryout ESR/CSR for a period of at least one year and thereafter come for the EC.
22. Measures for socio economic influence on the local community due to proposed project to be provided by project proponent. As far as possible, appropriate quantitative dimension to be given. Analysis of Job requirements vis-à-vis, employability of local population need to be provided.
23. Detailed environmental management plan to mitigate the environmental impacts which, should inter-alia also include the impact due to change of land use, due to loss of agricultural land and grazing land, if any, besides other impacts of the projects. The budgetary provision (both capital and recurring) for implementing the proposed EMP should be clearly spelt out.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
24. The points raised during Public hearing and commitment of the project proponent on the same along with time bound action plan to implement the commitments and the necessary allocation of funds for the same to be provided.
25. Any litigation pending against the project and /or any direction /order passed by any Court of Law against the project, if so, details thereof should be submitted.
26. The P.P. should ensure compliance of the order of the Hon’ble Rajasthan High Court, Jodhpur, in D. B. Civil writ petition no. 1536 of 2003 in the matter of Abdul Rahman vs State of Rajasthan and others and submit a brief note regarding compliance of the court order.
27. That the Project Proponent shall not use any explosive and blasting for mining activity without proper permissions from competent authorities.
28. Provide details about transfer/allotment of mining lease, extension of lease period etc. along with authenticated copies of orders for lease allotment / transfer / extension of validity period.
29. A balance sheet certified by a Authorized Financial Expert to clearly indicate the provision made / amount spent for EMP/ERP/CSR/ESR/ Safety/Labour welfare/ Legal Obligations etc to be enclosed
30. PP should clearly mention in the documents whether there is any violation of provisions of EIA Notification and inform at the start of presentation (to be a part of computer presentation also).
31. Used filter papers (Air monitoring) along with photographs of the site showing Air / Water sampling / monitoring activity / equipment used at each station should be submitted. Original copies of analysis report of all the relevant data referred in the documents should be enclosed.
32. The information regarding the work order/agreement issued by the P.P. to the consultant (Accredited from QCI/ NABET for proposed project Sector) should be submitted along with, (a) Dispatch No. of the work order/agreement, (b) Date of issue of work order (c) Date of start of air/water/other monitoring work (as applicable) and (d) Postal address/ Email Address/ Fax Number/ Mobile Number and Landline Number of the P.P.
Points included in TOR as per MoEF&CC circular no. J-11013/41/2006-IA.II(I)-Pt. dt.
19.05.2011 regarding Corporate Environmental responsibility.
1. (a) Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed in the EIA report.
(b) Does the Environment Policy prescribed for standard operating process/procedures to
bring into focus any infringement/deviation/violation of the Environmental or forest norms
/conditions? If so, it may be detailed in the EIA report.
2. What is the hierarchical system or administrative order of the company to deal with the Environmental issues and for ensuring compliance with the EC conditions? Details of this system may be given.
3. Does the company have a system of reporting of non-compliances/violations of Environmental norms to the Board of Directors of the company and /or shareholders or stakeholders at large? This reporting mechanism should be detailed in the EIA report.
4. After preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the proponent shall get the public hearing conducted (strictly following the procedure laid down in the Appendix IV of the Amendment Notification dt. 01.12.2009 and MoEF circular no. J-15012/29/2010/IA.II(M) dt. 19.04.2010). In this regard due care would be taken in (i) deciding the venue of public hearing (at the project site or in its closed proximity, to ensure widest possible public participation), (ii) forwarding the Draft EIA Reports with Executive Summary Reports and notice for hearing to various authorities / offices, specifically to Urban Local Bodies/ Panchayati Raj. Institutions (i.e Zila Parishad, Panchayat Samiti & Gram Panchayat)/ Development Authorities (i.e. U.I.T., J.D.A. etc.), (iii) adequate publicity regarding date, place and time of public hearing among local public, (iv) recording requisite “certificate” at the end of public hearing proceedings / report and (v) displaying the report in the office of Gram Panchayat, Zila Parishad, Collectorate etc. After completing the public
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
hearing process as described above, the proponent shall take further necessary action for obtaining environmental clearance in accordance with the procedure prescribed under the EIA Notification, 2006 and subsequent amendment dt. 01.12.2009.
5. A certificate should be submitted by the Regional Officer Pollution Control Board that the process followed for public hearing was adequate as required in reference to contents of MoEF O.M. no. J-15012/29/2010-IA-II(M) dt. 19.04.2010. In the final EIA /EMP report , compliance of points of ToRs should be reported point wise in
a statement of three columns as indicated below:-
Yours faithfully,
(T.S. Ranawat)
Secretary, SEAC,Rajasthan
Copy to
1. Member-Secretary, SEIAA, Rajasthan and Secretary to Government, Department of
Environment, GoR, Secretariat, Jaipur.
2 Member Secretary, RSPCB, Jaipur.
S. No Items in the letter of the ToRs Reply / Response by the PP
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
ANNEXURE –XII: COPY OF MINUTES OF PUBLIC HEARING
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
ANNEXURE –XIII: PHYTOSOCIO REPORT OF STUDY AREA
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.
Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.