streamlined approach for environmental restoration plan 41 …...practica17 propose adm inistrative...
TRANSCRIPT
![Page 1: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/1.jpg)
NevadaEnvironmentalRestorationProject
I
Streamlined Approach forEnvironmental Restoration Planfor Corrective Action Unit 41 6,Mud Pit, Project Shoal Area
Controlled Copy No.:_
Revision No: 1
July 1997
Environmental RestorationDivision
U.S. Department of EnergyNevada Operations Office
![Page 2: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/2.jpg)
This report has been reproduced from the best available copy.
Available to DOE and DOE contractors from theOffice of Scientific and Technical Information, P.D. Box 62,Oak Ridge, TN 37831. (423) 576-8401.
Available to the public from the National Technical InformationService, U.S. Department of Commerce, 5285 Port Royal Road,Springfield, VA 22161. (703) 487-4650.
![Page 3: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/3.jpg)
DOE/NV--479UC-700
STREAMLINED APPROACH FOR ENVIRONMENTALRESTORATION PLAN FOR CORRECTIVE ACTION
UNIT 416, MUD PIT, PROJECT SHOAL AREA
DOE Nevada Operations OfficeLas Vegas, Nevada
Controlled Copy No.:_
Revision: 1
July 1997
![Page 4: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/4.jpg)
STREA:MLINED APPROACH FOR ENVIRONl\1ENTAL RESTORATIONPLAN FOR CORRECTIVE ACTION UNIT 416,
I\fUD PIT, PROJECT SHOAL AREA
APprovedbY~~~/ 10~Janet Appenzell er-Wing, Project ManagerOffsites Subproject
Date: 7/J/f){ I
SV.1C' ~~ ... ;!) fY? t I/'II.! Iv.....Stephen A. Mellington, Project ManagerNevada Environmental Restoration Project
Approved by: __-..L__----:-...:...----!......--!..-.=...:.L.!....:...:,~-=------
![Page 5: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/5.jpg)
SAFER Plan for CAU 416Section: ContentsRevision: 1Date 07/03/97Page i of iv
Table of Contents
List of Figures , ..... , , ..... , . , .... , , .. , , . , .. , . ,
List of Tables .. , , .. " , , , ,' ,
List of Acronyms and Abbreviations
1.0 Introduction , , .. , .. , , , , , .. , , , , . , .. ,
11
111
IV
2.0 Unit Description and Closure Objectives ., ,., .. , ".,.'... 4
2.1 Project Shoal Area ,.', , ,.,... . , .. , , . , . . . . . . . 4
2.2 Site Location and Description. , .. , , , , , .. , , . , . . . . . . 7
2.3 Process Knowledge , , , . , .. , , . , , , , , 7
2.4 Waste Inventory , , .. " .. , .. ,' , , , .. " .. ,.. ' . , , .. 12
2.5 Closure Standards , .. , .. , , , , , , .. , , , , 12
3.0 Field Activities , " ,., , , , 17
3.1 Constituents of Concern " , .. , , , , .. , , , . , , , , . . .. 17
3,2 Remediation , , , , .. , . , , .. , , , .. , , , . . . .. 17
3.3 Verification , .. , , , , , .. , , , . , .. , 19
3.4 Clean Closure .. , , , .. , , , , , , , , . .. 20
3.5 Site Restoration " ,' , , " ',., .. 22
3.6 Schedule,." " , ,., , , .. " " 22
4,0 Reports .,....',............'..........,.....,......, , . . . . . . . . . . ,. 23
5.0 Waste Management, , .. , , .. , , , , , , . , .. , 24
6.0 Site-Specific Health and Safety Plan .. , , , .. , , ,... 26
7.0 References ... . , . . . . . . . . . . . . , , . . , , . . . . . , . , . . . . . . . . . . . . . . . , . , . . . . . . , . .. 27
Appendix A - Response to NDEP Comments , " " .. " , 29
![Page 6: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/6.jpg)
SAF ER Plan for CAU 416Section: ContentsRevision: 1Date: 07f03/97Page ii of iv
List of Figures
Number Title
1-1 SAFER Decision Diagram, Proj ect Shoal Area, Nevada
Page
.", . , . . . -'
2-1 Project Shoal Area , , , . . . . . . . . . . . . . . . . . , . . . , , . . . . , . . . ' , . . , . . . , . . . . . .. 5
2-2 Location of Deep Borings, Project Shoal Area ...... 6
2-3 Approximate Location of Project Shoal Area Impoundment .. " , .. " 8
2-4 Shoal Mud Pit Sample Location Map with Upgradient Locations ............. 10
2-5
3-1
Shoal Mud Pit Sample Location Map
Shoal Mud Pit Area to be Excavated
........ , , , . ,. 11
, , , ,. 18
3-2 Shoal Mud Pit Verification Sample Location Map ............... , .. , , .... , 21
![Page 7: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/7.jpg)
List of Tables
Number Title
SAFER Plan for CAU 416Section: ContentsRevision: 1Date 07/03/97Page iii of iv
Page
2-1 Shoal Mud Pit Analytical Data , , . , , .... , , .... , , .. 13
3-1 Project Shoal Area Mud Pit Confirmation Sampling Requirements .. , ..... , 19
![Page 8: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/8.jpg)
List ofAcronyms and Abbreviations
SAFER Plan for CAU 416Section: ContentsRevision: 1Date 07/03/97Page iv of iv
AEC
bgs
CAS
CAU
CFR
DOE
DOEINV
DQO
EPA
FFACO
ftft3
km
mg/kg
mg/L
mr
NA
NAC
ND
NDEP
~TS
pCi/g
PPE
PSA
SAFER
TCLP
TPH
SB~'vf
yd '
u.s. Atomic Energy Commission
Below ground surface
Corrective Action Site(s)
Corrective Action Unit(s)
Code ofFederal Regulations
U.S. Department of Energy
U.S, Department of Energy, Nevada Operations Office
Data Quality Objective(s)
U,S. Environmental Protection Agency
Federal Facility Agreement and Consent Order
Foot (feet)
Cubic foot (feet)
Kilometer(s)
Meter(s)
Cubic meter(s)
J\lilligram(s) per kilogram
Milligram(s) per liter
Mile/s)
Not analyzed
Nevada Administrative Code
Not detected
Nevada Department of Environmental Quality
Nevada Test Site
PicoCurie(s) per gram
Personal protective equipment
Project Shoal Area
Streamlined Approach for Environmental Restoration
Toxicity Characteristic Leaching Procedure
Total petroleum hydrocarbon(s)
US. Bureau of Mines
Cubic yard(s)
![Page 9: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/9.jpg)
SAFER Plan for CAU 416Section: 1.0Revision: 1Date: 07/03/97Page 1 of 32
1.0 Introduction
This plan addresses the actions necessary for the restoration and closure of the Project Shoal
Area (PSA), Surface Corrective Action Unit (CAU) 416, Mud Pit (Corrective Action Site
No. 57-09-01), a pit that was used to store effluent produced during drilling of the Post-Shot
Borehole PS-1 in 1963. This plan describes the activities that will occur at the site and the steps
that will be taken to gather enough data to obtain a notice of completion from the Nevada
Division of Environmental Protection (NDEP). This plan was prepared under the Streamlined
Approach for Environmental Restoration (SAFER) concept, and it will be implemented with the
Federal Facility Agreement and Consent Order (FFACO) (FFACO, 1996) and the Industrial
Sites Quality Assurance Project Plan (DOEINV, 1994).
The SAFER process is being employed at this CAD where enough information exists about the
nature and extent of contamination to propose an appropriate corrective action without
completing a Corrective Action Decision Document and Corrective Action Plan. This process
combines elements of the Data Quality Objective (DQO) process and the observational approach
to help plan and conduct corrective actions. DQOs are used to identify the problem and define
the type and quality of data needed to complete the investigation phase of the process. This has
already been completed for the mud pit so it 'will not be repeated here. The DQOs for the mud
pit are presented in the Corrective Action Investigation Plan for Project Shoal Area,
CAU No. 416 (DOEINV, 1996). This observational approach provides a framework for
managing uncertainty and planning decision making.
The SAFER concept recognizes that technical decisions may be made based on incomplete, but
sufficient, information and the experience of the decision maker. Any uncertainties are
addressed by documented assumptions that are verified by sampling and analysis, data
evaluation, on-site observations as planned activities progress, and by contingency plans as
necessary. If, at any time during the site closure, new information is developed that changes the
conceptual site model defined during the DQO process and indicates that the closure method or
underlying assumptions should be revised, the decision maker will redirect the closure activities
with the appropriate authorization to more appropriately protect human health and the
environment. The !\lJ)EP will be notified of the changes and this plan will then be amended.
![Page 10: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/10.jpg)
SAFER Plan for CAU 416Section: 1.0Revision: 1Date: 07/03/97Page 2 of 32
Following completion of SAFER activities, a closure report will be prepared and submitted to
the NDEP.
Adequate process knowledge currently exists to propose mud removal as the corrective action
for the mud pit. The process knowledge included the review of historical records and the results
of the fall 1996 mud pit characterization activities and was used to determine the constituents of
concern and the most appropriate SAFER cleanup approach.
Corrective action at the mud pit will be achieved in three phases. The first phase will be the
excavation, hauling, and disposal of the mud in the pit which has total petroleum hydrocarbon
(TPH) levels that exceed the state regulatory level. The second phase will be the collection of
samples from under the mud pit to confirm that all of the contaminated material has been
removed. The third phase will be the recontouring of the drainage in which the mud pit is
constructed. A decision diagram for this process is presented in Figure 1-1.
This plan reflects the following assumptions:
• The volume of material to be removed from the mud pit is less than 123 cubic meters(m 3) (162 cubic yards [yd 3]),
The material will be disposed of at the Nevada Test Site (NTS) Area 6 HydrocarbonLandfill.
• The material in the old mud pit berm is not contaminated with THP and can be used torecontour the mud pit area.
If, at any time during the closure activities, information is discovered that invalidates any
assumption, this plan will be amended, if possible, depending on the nature of the new
information, and amendments will be provided to NDEP for approval. No work will be
conducted on site from the time the invalidating information is discovered to the time approval
of the am end ed SAFER PIan is received from ND EP.
![Page 11: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/11.jpg)
SAFER Plan for CAU 416Section: 10Revision: 1Date: 07/03/97Page 3 of32
NO
'YES
Is furtherexcavation
practica 17
ProposeAdm inistrative
closure
Covered in the SAFER P'an
Phase 2
C ond uctveri he a ti on
sa m piing
Phase 1
Excavate anddispose ofd rillin g m uci
R econtou r th emid pit area
,/',,,,
Closure com p lete,pre pa re cfosu re
report
Figure 1-1SAFER Decision Diagram, Project Shoal Area, Nevada
![Page 12: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/12.jpg)
SAFE R Plan for CAU 416Section: 2.0Revision: 1Date: 07/03/97Page 4 of32
2.0 Unit Description and Closure Objectives
The mud pit is located on the Project Shoal Area in the northern Sand Springs Mountain Range
in Churchill County, Nevada (Figure 2-1).
2.1 Project Shoal Area
Project Shoal, part of the Vela Uniform Program, was ajoint effort of the Department of
Defense and the Atomic Energy Commission (AEC) to study the effects of different geological
media (e.g., granite) on seismic waves produced by underground nuclear explosions and to
determine if seismic waves produced from underground nuclear explosions could be
differentiated from natural earthquakes (DR!, 1988, Section A.3 .4.2). The PSA was selected as
the tentative Project Shoal Site in 1961. After a year-long geologic exploration of the area, the
PSA was confirmed as the chosen site, and preparations for the test began in late 1962.
The Shoal event consisted of detonating a nuclear device with a 12.5-±0.5 kiloton yield on
October 26, 1963 (Gardner and Nork, 1970). The device was placed in granitic rock
369 meters (m) (1,211 feet [ftD below ground surface (bgs).
Post-shot drillback activities began on October 28, 1963 (AEC, 1970), and consisted of drilling
and sampling one post-shot vertical borehole (PS-l) into the event cavity and reopening and
sampling the U.S. Bureau of Mines (USBM) No. I borehole located approximately 135.5 m
(445 ft) from the PS-l hole. The location of the deep boreholes (P.l\1-1, PM-2, PM-3, PJ'v1-8,
ECH-A, ECH-D, PS-I, USBM No, I, and the emplacement shaft and drift) drilled for the event
are shown on Figure 2-2 (AEC, 1970).
Records of data collected from the PS-l and USBM NO.1 borehole explorations indicated that
the shot cavity collapsed, producing a rubble-filled chimney 52 m (171 ft) in diameter and
109 m (356 ft) high with an II-m (36-ft) void at the top (Korver et al., 1964, pp. 4-5). Virtually
all of the high-level radiation from Project Shoal is believed to be confined in the insoluble melt
rubble mixture at the bottom (lowest 10 m [33 ftj) of the chimney. There was no venting of
particulate debris during or after the explosion although some radionuclides, mostly gaseous,
may have been injected into fractures as far as 135 m (443 ft) from the shot point. Some short
lived gaseous radionuclides (Iodine 131, Xenon133m, and Xenon133), were brought to the surface
![Page 13: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/13.jpg)
T14N
T15N
T16N
SAFER Pion forr-~!I A1f:Section: 2.0Revision: 1Date 07f03197Page 5 of 32
............................................. , ...
2~S:
l----'-~:":":":"Iti?
Frenchman
E 580,000E 560,000E 540,000
Churc~~1 Couf2.lt
Mineral County
z
z
z
oooototo
z
z
oooocoLD
ooo.oo<0
oo~ov<0
ooociN<0
R31E R31\2E R32E R33E
o Land withdrawal boundary
• Town
1·::::.1 Maunta in ranges
Area A: Right of entryArea B: Land withdrawn
T16N, R32E, Sections 33 and 34,T15N, R32E, Sections 3 and 4.
~~="==k--+- ProjedShool Area
r-, SCALEen<,N i'-...., 0 3 5 Miles0
i ::s...., 0 5 10 Kilometers~
Land Order #2834,r-- Source: DRI, 1988; Pubiic December 196200to
Area A
Improved roadway
Unimproved roadway
Township/ range bounda ryCounty line
Section line
Figure 2-1Project Shoal Area
![Page 14: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/14.jpg)
PM 2, EI. 1,621 meters (rn) (5,317 feet [ftJ)
/ TD 395 m (1,295 ft)
--'-..0:::::
SAFER Piml toreN I <-"15Section: 2.0Revision: 1Date: 07/03/97Page 6 of 32
Shaft Q==320 m (1,050 fl)EI. 1,610 m (5,284 ft)
TO 402 m (1 ,320 tt)
GZ 8PS 1
m (5,232 tt)m (1,377 ft) ECH-D
EI, 1,595 m (5,234 ft)I .r: TD 615 m (2,018 ft)~13S
11S'S
/;) USBM 1~ EI. 1,585 m (5,201 ft)
PM 8 ~~ TO 453 m (1,486 ft)I. 1,596 m (5,238 ft)"
TO 281 m (922 ft) ~ 09
~ /;) (1,998
ft~ECH-~ PM 3EI. 1,572 m (5,159 ft) EI. 1,561 m (5,120 ft)TO 579 m (1,898 ft) TO 334 m (1,097 fl)NO 457 m (1,499 ft)
EI 1,595TO 420
PM 1EI. 1,633 m (5,358 tt)TO 407 m (1,335 tt)
o
o
SCALE
200
600
400 Meters
1,200 Feet
LEGEND
ECHEI.GZTONOPMPS
Exploratory core holeElevationGround zeroTotal depthTotal vertical depthParticle motionPost shot
.,., Drawing ana measurement information taken from' Atkinson, C,H., 1964 and Holmes and Narver, 1971.~r-oo<O,-- .=~_="'=".~~~.. _="='='=_~__=~'~K~M'_=~'__~_~ ~__~ ~_~'_==~~
Figure 2-2Location of Deep Borings, Project Shoal Area
![Page 15: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/15.jpg)
SAFER Plan for CAU 416Section: 2.0Revision: 1Date 07/03/97Page 7 of 32
through the PS-l drill rig effluent vent-line system during drillback operations (Eubank and
\Vard, 1964).
These radionuclides were trapped by filters and were subsequently mixed with clean soil and
buried in the mud pit area beneath uncontaminated soil (Gardner and Nork, 1970). All
equipment was decontaminated and/or removed from the Project Shoal Area.
Deactivation of the site commenced on October 28, 1963. All vehicles, equipment, and surface
structures, except for the head frame of the emplacement shaft, were removed by
January 31, 1964, and the site was placed on "caretaker standby" status. The shaft was covered
with a concrete slab, and all exploratory boreholes leading to the cavity were sealed with grout
or sand and abandoned. In July 1964, the site was placed in an "unattended standby" status
with no surface structural or radiological safety hazards (Giller, 1970).
2.2 Site Location and Description
Historical documentation indicates there is one mud pit (CAS 57-09-01) at the Project Shoal
Area. One document describes the location as being, "... at the head of the creek at the east edge
of the GZ (Ground Zero) pad" (Gardner and Nork, 1970). This location matches the locale of
the "post-shot mud pit site" that was sampled in Fauver's 1986, Hazardous Waste Installation
Assessment Report (Fauver, 1986), which describes the site as being located "north of the
Rad-Safe facility" (Figure 2-3).
The estimated volume of material in the mud pit is approximately 123 m 3 (162 yd'). The
volume was estimated by averaging the depth of the mud pit, 0.5 m (1.5 ft) (as encountered in
the borings) and multiplying by 246 square meters (2,700 square feet), the estimated surface
area of the mud pit.
2.3 Process Knowledge
Process knowledge is based on the review of pre-event site characterizations, operations, closure
reports, aerial photos, and the mud pit characterization activities conducted in the fall of 1996.
All process knowledge records are available for review at the IT Corporation offices in
Las Vegas. The historical records used to compile process knowledge are listed in Section 7.0,
"References," of this plan.
![Page 16: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/16.jpg)
SAfTR Plan for"~.j: .,1 1 RSection: 2.0Revision: 1Date 07/03/97Page 8 of 32
~I
{
I
Ground zeroaccess road
•~ Rod-safe
facilityRod-safe mobilelab and 10 undry
\0-Approximate location ofGroundl Shoal impoundment
zero \
~---.------~~ \
/-Instrumenttrailer pork
Servic e rood-- Control point access rood
"'-'--.
<,
~------'-- ./
Escape road
- Control point area
areas
SCHEMATICNOT TO SCALE
co~ Source: Fauver, 1986aa<DL.. ~ ......I
Figure 2-3Approximate Location of Project Shoal Area Impoundment
![Page 17: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/17.jpg)
SAFER Plan for CAU 416Section: 2.0Revision: 1Date: 07/03/97Page 9 of32
The PSA mud pit was used to store drilling effluent that was produced during drilling of the
post-shot borehole PS-l. Since the PS-l borehole was drilled into the event cavity, radiological
contaminants produced from the test were the primary concern. A daily log for the post-shot
borehole drilling operation is contained in the Project Manager's Report Project Shoal
(AEC, 1964, Appendix C). The drilling log indicates that the fluids used to drill PS-l were
bentonite drilling mud, air, and air-mist. The daily log does not indicate the use of any diesel or
other drilling mud additives except for loss-of-circulation materials. The types of lost
circulation materials used were cotton seed husks and cane fibers. Based on the information
contained in the daily log, contamination of the drilling mud by TPH or other substances such
as barium (from barite) or chromium (from chrome lignosulfonate) was not expected. However,
diesel, barite, and chromium lignosulfonate additives have been used in drilling mud at other
U.S. Department of Energy (DOE) sites such as the Central Nevada Test Area.
The drilling log indicates that air was used to drill through rock (prior to the circulation loss),
from 30.5 to 183 ill (l00 to 600 £1) bgs, and air-mist (a mixture of air, water, and detergent) was
used to drill from 183 m (600 £1) bgs to the bottom of the PS-l hole at approximately 424 ill
(1,391 £1) bgs. All contaminated soil and cuttings resulting from the post-shot drilling activities
were reportedly combined with clean soil and buried in the mud pit.
In the fall of 1996, the mud pit was characterized. Ten soil borings were completed in the pit;
three were completed downgradient from the pit; three were completed upgradient; one was
completed east; and one was completed west of the mud pit (Figures 2-4 and 2-5).
One or two soil samples were collected from each soil boring; 16 samples were collected from
the mud pit (four of which were waste characterization samples); and nine samples were
collected from outside the mud pit. The samples were analyzed for gross alpha, gross beta,
total barium, total chromium, tritium, gamma spectroscopy, and TPH except for the waste
characterization samples which were analyzed for Toxicity Characteristic Leaching Procedure
(TCLP) metals instead of total barium and total chromium. The results of the mud pit sampling
are presented in Table 2-1. Several of the samples from inside the mud pit exceeded thebTevada
Administrative Code 459 (NAC) Action Level for TPH; however, the results for the gross alpha,
gross beta, tritium, and gamma spectroscopy are within expected values for a granitic terrain and
the total barium, and total chromium are well below the proposed Subpart S action levels.
![Page 18: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/18.jpg)
6007a07 03/20/97
DP-17DP-16DP-15-
SCALE
Shoal Mud Pit ~"'" '"'0_'0
~r'8 OP-lOOf-6 -OP-S - OP-9
OP·3 ·OP.2 - OP-7~OP-4
OP-1DP-11 _
Retention Dam
HO Dam Crest
SAFER Plan for~.l\U ,~1r:.
Section: 2.0Revision: 1Date 07/03/97Page 10 of 32
, .~~_......'.,
I Io 50 100 200 Feet
Figure 2-4Shoal Mud Pit Sample Location Map with Upgradient Locations
![Page 19: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/19.jpg)
6007a04 03/20/97
SCALE
Shoal Mud Pit
DP-18.
DP-6.
DP-3l.
DP-1.
DP-12 •
Dam Crest
Retention Dam
SAFER Plan foreN...' ·~1SSection: 2.0Revision: 1Date 07/03/97Page 11 of 32
o 20 40 80 Feet
Figure 2-5Shoal Mud Pit Sample Location Map
![Page 20: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/20.jpg)
SAFER Plan for CAU 416Section: 2.0Revision: 1Date: 07103/97Page 12 of 32
During drilling of the monitoring wells, samples of the effluent being discharged in the sumps
were sampled and analyzed. No chemical or radiological contaminants were found in any of the
samples.
2.4 Waste Inventory
Based on the results of the recent mud pit characterization, the entire 123 m 3 (162 yd') of mud in
the pit is assumed to be contaminated with TPH. Values for TPH in the pit ranged from non
detect to 900 milligrams per kilogram (mg/kg). The radionuclides reported to have been buried
in the pit Iodine!", Xenon 133m, and Xenon!" all had half lives ofless than 10 days and have
decayed to below Minimum Detectable Activity.
2.5 Closure Standards
The site must have soil TPH concentrations below the NDEP Action Level of 100 mg/kg
![Page 21: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/21.jpg)
Table 2~1
Shoal Mud Pit Analytical Data(Page 1 of 4)
SAFER Plan for CAU 416Section: 2.0Revision: 1Date 07/03/97Page 13 of 32
Sample Sample # Depth Depth Sample Matrix II Arsenic Barium Barium Cadmium Chromium Chromium Lead Mercury Selenium
Location (meters) (feet) Date mq/l," mg/L mg/kgb mg/L mg/L mg/kg mg/L mg/L mg/L
ITCLP Listing (40 CFR 261.24) II 5.0 mg/L 1 100 mg/L 1 I 1.0 mg/L I 5.0 mg/L I I 5.0 mg/L I0.2 mg/L I 1.0 mg/L IDP-1 PSSOOO01 0-0.61 0-2 9/15/96 Soil NAc NA 234 NA NA 7.7 J NA NA NA
DP-1 PSSOOO02 0.61-1.22 2-4 9/15/96 Soil NA NA NA NA NA NA NA NA NA
DP-2 PSSOOO05 0-0.31 0-1 9/15/96 Soil 0.02 U 1.2 B NA 0.005 U 0.042 B NA 0.025 B 0.0001 U 0.028 U
DP-2 PSSOOO06 0-0.31 0-1 9/15/96 Soil 0,02 U 1.2 B NA 0005 U 0.046 B NA 0,03 B 0.0001 U 0028 U
DP-3 PSSOOO07 0-0.31 0-1 9/15/96 Soil NA NA 206 NA NA 12.6 J NA NA NA
DP-4 PSSOOO08 0-0.61 0-2 9/15/96 Soil NA NA 437 NA NA 10.9 J NA NA NA
DP-4 PSSOOO09 0.61-1.22 2-4 9/15/96 Soil NA NA NA NA NA NA NA NA NA
DP-5 PSSOO010 0-0.61 0-2 9/15/96 Soil 0.023 B 27 NA 0.0078 B 0.092 B NA 0.014 U 0.0001 U 0,028 U
DP-5 PSSOO011 0,61-091 2-3 9/15/96 Soil NA NA NA NA NA NA NA NA NA
DP-6 PSSOO013 0-0.76 0-2.5 9/15/96 Soil NA NA 240 NA NA 97J NA NA NA
DP-7 PSSOO014 0-0.61 0-2 9/15/96 Soil NA NA 710 NA NA 10,7 J NA NA NA
DP-7 PSSOO024 061-0.91 2-3 9/15/96 Soil NA NA NA NA NA NA NA NA NA
DP-8 PSSOO015 0-0.61 0-2 9/6/96 Soil 0.26 U 0.95 NA 0,013 U o11 NA 0,17U 00001 U 0.21 U
DP-9 PSSOO016 0-0.91 0-3 9/15/96 Soil NA NA 235 NA NA 79J NA NA NA
DP-10 PSSOO017 0-0.91 0-3 9/6/96 Soil NA NA NA NA NA NA NA NA NA
DP-11 PSSOO018 0-091 0-3 9/6/96 Soil NA NA NA NA NA NA NA NA NA
DP-12 PSSOO019 0-0.91 0-3 9/16/96 Soil NA NA NA NA NA NA NA NA NA
DP-13 PSSOO020 0-0.91 0.3 9/16/96 Soil NA NA NA NA NA NA NA NA NA
DP-14 PSSOO021 0-0.31 0-1 9/16/96 Soil NA NA NA NA NA NA NA NA NA
DP-15 PSSOO022 0-061 0-2 9/16/96 Soil NA NA 104 NA NA 7.4 J NA NA NA
DP-15 PSSOO023 0-0.61 0-2 9/16/96 Soil NA NA 842 NA NA 6.4 J NA NA NA
DP-16 PSSOO026 0-091 0-3 9/16/96 Soil NA NA 141 NA NA 10.2 J NA NA NA
DP-17 PSSOO027 0-091 0-3 9/16/96 Soil NA NA 103 NA NA 10,2 J NA NA NA
DP-18 PSSOO028 0-0,61 0-2 9/15/96 Soil NA NA 292 NA NA 18.5 J NA NA NA
DP-18 PSSOO029 0.61-0.70 2-23 9/15/96 Soil NA NA NA NA NA NA NA NA NA
![Page 22: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/22.jpg)
Table 2-1Shoal Mud Pit Analytical Data
(Page 2 of 4)
SAFER Plan for CAU 416Section: 2,0Revision: 1Date: 07/03/97Page 14 of 32
Sample Sample # Depth Depth Sample Matrix Silver Gross Alpha Gross Beta Bismuth-214 Cesium-137 Lead-212 Lead·214 Potassium-40
Location (meters) (feet) Date mg/L pCi/gd pCi/g pCi/g I pCi/g pCi/g pCilg pCilg
ITCLP Listing (40 CFR 261.24) II 5.0 mg/L I I I I I I I IIBackground Radiological Concentrations· II 12 - 45 I 7 - 56 I 0.41-3.47 I 0.17·3.08 I 0.86 - 2.9 I 0.30 -1.371 10.5 - 30.7 II
OP-1 PSSOOO01 0-0,61 0-2 9/15/96 Soil NA 20,1 18,9 NOt 0.21 U 0,88 1,00 253
OP-1 PSSOOO02 0.61-1,22 2-4 9/15/96 Soil NA 323 23,2 NO 0,19 U 1,2 0,68 24,5
OP-2 PSSOOO05 0-0.31 0-1 9/15/96 Soil 0,01 U 10,6 22,3 NO 0,27 U 0,96 1,22 18,5
OP-2 PSSOOO06 0-0,31 0-1 9/15/96 Soil 0,01 U 21,0 20,8 NO 0.23 U 0,78 092 23,2
OP-3 PSSOOO07 0-031 0-1 9/15/96 Soil NA 10,2 20,5 NO 0.25 U 123 0,8 268
OP-4 PSSOOO08 0-0,61 0-2 9/15/96 Soil NA 23,8 207 NO 035 U 1,23 0,99 16.4
OP-4 PSSOOO09 0,61-1,22 2-4 9/15/96 Soil NA 27.4 273 NO 0.22 U 1.48 1,21 25,1
OP-5 PSSOO010 0-0,61 0-2 9/15/96 Soil 0,01 U 27,7 18,5 NO 0.22 U 1,01 1,31 15,5
OP-5 PSSOO011 0,61-0,91 2-3 9/15/96 Soil NA 46.4 40,1 1,14 0,39 U 1,86 1,06 16,9
OP-6 PSSOO013 0-0,76 0-2,5 9/15/96 Soil NA 17.0 210 NO 0,25 U 1,11 0,83 23.8
OP-7 PSSOO014 0-0,61 0-2 9/15/96 Soil NA 30,7 240 0,67 0,24 U 0.94 0,85 24,,7
OP-7 PSSOO024 0,61-0,91 2-3 9/15/96 Soil NA 350 25,3 0,99 0.21 U 1.43 099 23,7
OP-8 PSSOO015 0-0,61 0-2 9/6/96 Soil 0016 U 33,7 207 NO 0.24 U 0,98 NO 218
OP-9 PSSOO016 0-0,91 0-3 9/15/96 Soil NA 28,1 25,1 NO 0,18 U 1.41 1,09 24,8
OP-10 PSSOO017 0-0,91 0-3 9/6/96 Soil NA 66,0 24,6 068 0,25 U 05 0,87 27,2
OP-11 PSSOO018 0-0,91 0-3 9/6/96 Soil NA 37,7 27.4 NO 038 U 2,2 NO 22,1
OP-12 PSSOO019 0-0,91 0-3 9/16/96 Soil NA 19,6 24,2 NO 0,25 U 1,12 1,03 24,8
OP-13 PSSOO020 0-0,91 0,3 9/16/96 Soil NA 406 57,9 1.26 0,20 U 134 112 27,7
OP-14 PSSOO021 0-0,31 0-1 9/16/96 Soil NA 53,9 37,7 1,33 0,24 U 2,04 1,11 20,7
OP-15 PSSOO022 0-0.61 0-2 9/16/96 Soil NA 23,9 27,1 1,03 024 U 1,01 0,95 23,2
OP-15 PSSOO023 0-061 0-2 9116/96 Soil NA 25.4 27,3 136 0,23 U 0.85 093 25.4
OP-16 PSSOO026 0-0,91 0-3 9/16/96 Soil NA 35,9 300 0,82 0.23 U 1,04 0,83 21.2
OP-17 PSSOO027 0-0,91 0-3 9/16/96 Soil NA 27,3 258 NO 0,39 U NO NO 17
OP-18 PSSOO028 0-0,61 0-2 9/15/96 Soil NA 15,3 18,5 NO 0.46 U NO 175 17,1
OP-18 PSSOO029 061-0,70 2-2,3 9/15/96 Soil NA 56,9 47,1 NO 0,24 U 1,17 0,91 18,7
![Page 23: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/23.jpg)
Table 2-1Shoal Mud Pit Analytical Data
(Page 3 of 4)
SAFER Plan for CAU 416Section: 2.0Revision: 1Date: 07/03/97Page 15 of 32
Sample Sample # Depth Depth Sample Matrix II Radium-226 Radium-228 Thallium-208 Thorium-234 Tritium Diesel Waste Oil
Location (meters) (feet) Date II pCi/g pCi/g pCi/g pCi/g pCi/g mg/kg mg/kg
INAC 459.9973 I I II I I I I I 100 ppm I 100 ppm IIBackground Radiological Concentrations II 0.89 - 2.0 I 0.67 - 2.4 I 0.94 - 3.38 I 0.5·3.5 I I I II
OP-1 PSSOOO01 0-0.61 0-2 9/15/96 Soil NO NO NO NO 0.005 25 U 180
OP-1 PSSOOO02 061-1.22 2-4 9/15/96 Soil 3.11 NO 048 NO 0.0008 NA NA
OP-2 PSSOOO05 0-0.31 0-1 9/15/96 Soil NO NO 0.31 NO 0006 25 U 130
OP-2 PSSOOO06 0-0.31 0-1 9/15/96 Soil NO 1.03 03 NO 0.005 25 U 140
OP-3 PSSOOO07 0-0.31 0-1 9/15/96 Soil NO NO 072 NO -0.006 25 U 50
OP-4 PSSOOO08 0-0.61 0-2 9/15/96 Soil NO NO 0,34 NO -0.002 25 U 300
OP-4 PSSOOO09 0.61-1.22 2-4 9/15/96 Soil NO NO 048 NO 0005 NA NA
OP-5 PSSOO010 0-061 0-2 9/15/96 Soil 523 141 0.35 NO 0.076 180 900
OP-5 PSSOO011 0.61-0.91 2-3 9/15/96 Soil NO NO NO NO 0,01 NA NA
OP-6 PSSOO013 0-0.76 0-2.5 9/15/96 Soil 3.75 1.53 044 NO 0003 40 93
OP-7 PSSOO014 0-0.61 0-2 9/15/96 Soil NO NO 0.32 194 0.003 25 U 190
OP-7 PSSOO024 0.61-0.91 2-3 9/15/96 Soil NO NO 048 NO 0.002 NA NA
OP-8 PSSOO015 0-061 0-2 9/6/96 Soil NO NO 0,37 NO 0.011 300 U 300 U
OP-9 PSSOO016 0-091 0-3 9/15/96 Soil NO 1.59 072 NO -0.002 25 U 25 U
OP-1o PSSOO017 0-091 0-3 9/6/96 Soil NO NO 034 NO -0.004 NA NA
OP-11 PSSOO018 0-0.91 0-3 9/6/96 Soil NO NO NO NO 0.013 NA NA
OP-12 PSSOO019 0-0.91 0-3 9/16/96 Soil 5.78 NO 0.36 NO -0003 NA NA
OP-13 PSSOO02O 0-0.91 0.3 9/16/96 Soil NO 1.76 0.57 NO -0.009 NA NA
OP-14 PSSOO021 0-0.31 0-1 9/16/96 Soil NO NO 0.39 NO -0.005 NA NA
OP-15 PSSoo022 0-0.61 0-2 9/16/96 Soil 2.84 123 0.36 NO NO NA NA
![Page 24: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/24.jpg)
Table 2-1Shoal Mud Pit Analytical Data
(Page 4 of 4)
SAFER Plan for CAU 416Section 2.0Revision: 1Date: 07/03/97Page 16 of 32
...
Sample Sample # Depth Dept~, ::,,;1 mple Matrix II Radium-226 Radium-228 Thallium-208 Thorium-234 Tritium Diesel Waste Oil
location (meters) (feet) Date II pCi/g pCi/g pCi/g pCi/g pCi/g mg/kg mg/kg
INAC 459.9973 I I II I I I I 1100 ppm I 100 ppm IIBackground Radiological Concentrations II 0.89 - 2.0 I 0.67 - 2.4 I 0.94 - 3.38 I 0.5 - 3.5 I I I II
OP-15 PSSOO023 0~0,61 0-2 9/16/96 Soil NO NO 0.42 NO NO NA NA
OP-16 PSSOO026 0-091 0-3 9/16/96 Soil 3.43 NO 0.31 187 NO NA NA
OP-17 PSSOO027 0-091 0-3 9/16/96 Soil ND NO 0.74 NO NO NA NA
OP-18 PSSOO028 0-0.61 0-2 9/15/96 Soil ND NO 106 NO -0,003 110 890
OP-18 PSSOO029 0,61-0.70 2-2.3 9/15/96 Soil NO NO 0,37 NO 0005 NA NA
a Milligrams per liter
b Milligrams per kilogram
C Not analyzed
d PicoCuries per gram
e This is backgroundfor soil; radioactivity in igneous rocks is generally higher than in sedimentary rocks; igneous rocks with higher silica content
(ie, granite) have higher radioactivity levels than those with a lower silica content.
I Not detected; no minimum detectable activity given.
J = Reported result is quantitatively estimated.
U= Compound/elementwas analyzed for but not detected.
B = The reported value is below the Contract-Required Detection Limit, but above the Instrument Detection Limit
![Page 25: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/25.jpg)
SAFER Plan for CAU 416Section: 3.0Revision: 1Date: 07/03/97Page 17 of 32
3.0 Field Activities
The approach for the remedial action to be conducted under this SAFER Plan is to excavate the
mud pit material, load it into trucks, transport it to a permitted disposal facility for disposal,
conduct post-excavation sampling and analysis to verify that all contamination has been
removed, re-grade and restore the pit location, and prepare a Closure Report.
3.1 Constituents of Concern
Based on process knowledge, the only Constituent of Concern is total petroleum hydrocarbon.
No other Constituents of Concern were identified in the historical data or during the mud pit
characterization process.
3.2 Remediation
Total Petroleum Hydrocarbon results for Sample Points DP-l, DP-2, DP-4, DP-5, DP-7, DP-S,
and DP-lS ranged from 110 to 300 mg/kg as diesel and 130 to 900 mg/kg as waste oil. All
other sample points were below the 1OO-mg/kg TPH Action Level for cleanup listed in the
Nevada Administrative Code 459 (NAC, 1995). Impacted soils exceeding the 100-mg/kg TPH
Action Level in the mud pit will be excavated using a front end-loader and/or backhoe. The
approximate area as shown in Figure 3-1 will be excavated to an approximate depth of
0.6 ill (2 ft). The 0.6-m (2-ft) initial excavation depth was selected based on the results from the
sample points that exceeded the 100-mg/kg TPH Action Level. Requirements for the samples
are listed on Table 3-1.
Confirmational soil samples will be collected at the bottom of the excavation (as described in
Section 3.3). The soil samples will be submitted for TPH as diesel and 'waste oil analysis
(U.S. Environmental Protection Agency Method 8015, Modified) (EPA, 1996) to determine if
the soils exceeding the Action Level were removed. If sample results indicate soils are still
present that exceed the Action Level, an additional 15 centimeters (6 inches) of soil will be
excavated followed by additional confirmation sampling and analysis of the soil. This activity
will be repeated until TPH analytical results in the confirmation samples are evaluated to be
below the 100 mg/kg Action Level or until the excavation encounters bedrock. If the TPH
concentration in the bedrock still exceeds the 100 mg/kg Action Level, an administrative closure
will be requested from the state.
![Page 26: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/26.jpg)
6007a02 03/20/97
P-3
•
o
DP-6
•
DP-11
•
SCALE
20 40 Feet
Shoal Mud Pit
DP-10•DP-9
• 25.0
,..
DP-12
•
Figure 3-1Shoal Mud Pit Area to be Excavated
DP-13•
DP-14
•
LEGEND
~DP.13
•300
SAFER Plan for_ C"'\~".: ,,:~ '1 p.
I Section 3.0Revision: 1Date 07/03/97
~~=,1.8,,~::~
Proposed areaof excavation
Sample location withTPH concentrationin mg/kg
![Page 27: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/27.jpg)
SAFER Plan for CAU 416Section: 3.0Revision: 1Date: 07/03/97Page 19 of 32
Table 3-1Project Shoal Area Mud Pit Confirmation Sampling Requirements
ijContainer
Preservative II
III Sample Number of Constituent Analytical Type and
Location SamplesSample Type
of Concern Method VolumeIiRequired !
Mud Pit 8 Soil TPH 8015 Waste 8-ounce glass Cool4'Cj
Gila with poly linedcap
;1
Mud Pit 8 Soil TPH 8015 Waste 8-ounce glass Coo14'CGila with poly lined
cap
aEPA SW-846, Test Method for Evaluating Solid Waste, 3rd Edition (EPA, 1996)
Excavated materials will be temporarily stockpiled on 20-mil plastic (or equivalent) near the
excavation area. At the end of each work day, the excavated soil will be covered with plastic
weighted on the edges to prevent precipitation and/or aerial spread. An alternative to soil
stockpiling that may be used at the site is containerization of the excavated soil in flexible bulk
containers. Flexible bulk containers ("super sacks") are constructed of woven polyester and/or
polypropylene. The super sacks proposed for use at the site will have an approximate capacity
of 1.1 m 3 (40 cubic feet [fe]) and will be able to be tied shut to eliminate the need to place a tarp
on the load during transport. The super sacks will be stockpiled on a 20-mil plastic liner
(or equivalent) until loaded and secured on an end-dump or flatbed trailer.
Even though field screening of the mud pit surface and analytical results for the samples
collected and analyzed in 1996 indicated no elevated levels of radionuclides, the excavated
materials will be transported to the NTS for disposal in the Area 6 Hydrocarbon Landfill, located
approximately 480 kilometers (km) (300 miles [mij) from the site. The decision to dispose of
the TPH-impacted soil at the NTS is predominantly based on a combined disposal and
transportation cost savings of 26 to 50 percent in comparison to a private facility located
approximately 176 km (110 mi) from the site.
3.3 Verification
Excavation activities will be stopped when all of the mud pit material has been removed down
to native soil or bedrock over the entire area of the pond. To verify that the excavation has been
sufficient, the native material will be sampled and analyzed. If the analytical results meet the
![Page 28: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/28.jpg)
SAFER Plan for CAU 416Section: 3.0Revision: 1Date 07/03/97Page 20 of32
closure standards and no other constituents of concern are found, and if concurrence is obtained
from NTIEP, the site will be recontoured; no further action will be required; and the site will be
considered restored and closed. If the analytical results do not meet the closure standards,
additional material will be removed and confirmation sampling will be conducted again.
To verify that all of the contaminated material has been removed, seven verification samples will
be collected. The samples will be collected from selected locations within the mud pit
impoundment. The samples will be collected from the underlying native material at the
locations indicated on Figure 3-2 and analyzed for TPH waste oil and TPH diesel only
3.4 Clean Closure
The objective of the SAFER activities at the Project Shoal mud pit is to remove material with
TPH concentrations above the closure standard and to gather adequate data to confirm the
decision for clean closure. The nature and extent of contamination in the mud pit were defined
in the fall of 1996. The cleanup will be conducted in three phases. The first phase will include
the excavation, shipping, and disposal of the contaminated drilling mud. The second phase will
involve confirmation sampling and analysis to verify the adequacy of the remedial action. The
third phase will be the recontouring of the drainage where the mud pit is located.
Verification samples for the mud pit will be collected and analyzed to determine if additional
soil needs to be excavated and disposed of. If each sample meets the closure standard set in
Section 2.5, "Closure Standards," the site may be restored and clean-closed. If the verification
samples indicate that constituents of concern are present in the soil above the closure standard
presented in Section 2.5, additional excavation and disposal will take place as described in
Section 3.2. Additional verification samples will be collected and analyzed; this sequence may
be repeated as necessary until all areas are demonstrated to meet the closure standard presented
in Section 2.5. All samples will be collected and managed in accordance with
U.S. Environmental Protection Agency (EPA) quality control protocols as reflected in the
Resource Conservation and Recovery Act (RCRA) Industrial Sites Quality Assurance Project
Plan (DOEINV, 1994).
![Page 29: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/29.jpg)
6007a06 03/20/97
V-1 •
Shoal Mud Pit
Dam Crest
SAFER Plan for-:I,1A
Section: 3.0Revision: 1Date 07/03/97Page 21 of 32
- Retention Dam
o 20
SCALE
40 80 Feet
LEGEND
V-5
• Proposed sample location
Figure 3-2Shoal Mud Pit Verification Sample Location Map
![Page 30: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/30.jpg)
SAFER Plan for CAU 416Section: 3.0Revision: 1Date 07/03/97Page 22 of 32
The laboratory will provide Contract Laboratory Procedure-type data packages with the
analyses, and ten percent of the verification samples collected will be validated (a minimum of
one sample per analysis) by third-party data validators
3.5 Site Restoration
The mud pit will require minimal site restoration activities. After excavation and removal of the
soils exceeding the 1OO-mg/kg TPHAction Level and confirmation sampling activities,
regrading of the mud pit area will be done to reestablish the approximate original topography.
Since the mud pit was constructed in a drainage area, only minimal work will be done on the
northern area of the mud pit; however, the southern area of the mud pit and the area south of the
berm will be regraded. This wilt be accomplished by using the existing soil berm on the
southern end of the mud pit as fill for the excavated mud pit area as well as areas south of the
berm. No revegetation is planned for the area.
3.6 Schedule
After approval of the SAFER Plan, it will take approximately three weeks to complete
preparations and mobilize to the site. Removal of the mud pit material will take approximately'
two days.
Verification sampling will take approximately one day. The samples will be submitted with a
requested 24-hour turnaround on the results so that it should not take more than three days from
the beginning of verification sampling to receipt of the analytical results.
Once the results of the verification samples have proven that the excavation has gone far
enough, the area will be recontoured using the material in the mud pit berm. This will take
approximately one day.
![Page 31: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/31.jpg)
SAFER Plan for CAU 416Section: 4.0Revision: 1Date: 07/03/97Page 23 of 32
4.0 Reports
Reports during field activities and after completion of the SAFER process will be provided to
NDEP by U.S. Department of Energy, Nevada Operations Office (DOEINVj.
Daily reports offield activities will be faxed to NDEP while field activities are ongoing, In
addition, DOEINV will verbally inform NDEP as soon as is practical of any substantial changes
in scope or schedule. If it is determined that this plan requires significant amendments, :NTIEP
will be notified as soon as practical; this plan will be amended; and NDEP's concurrence of the
modified plan will be solicited.
If clean closure is achieved within six months of receipt of validated laboratory results from
final field activities, DOE/J\TV will provide a written closure report to 1\TDEP documenting that
closure was completed in accordance with this plan and will include all analytical results to
verify that clean closure did occur. Chemical laboratory analytical results, in addition to waste
characterization and disposition information, will be included in the closure report. The report
will describe the SAFER Plan activities for each unit and request a notice of completion from
NDEP,
![Page 32: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/32.jpg)
SAFER Plan for CAU 416Section: 5.0Revision: 1Date: 07/03/97Page 24 of32
5.0 Waste Management
The proposed site activities will generate the following wastes:
TPH-impacted soil
Equipment decontamination rinsate
Disposable sampling equipment (e.g., plastic, paper, aluminum foil, and samplecontainers)
Personal protective equipment (PPE)
Prior to and during excavation, radiological screening of the soil will be conducted to satisfy
radiological "green tag" requirements for disposal of soil in the Area 6 Hydrocarbon Landfill.
TPH-impacted soil will be temporarily stockpiled on 20-mil plastic (or equivalent) near the
excavation area. At the end of each workday, the excavated soil will be covered with plastic
weighted on the edges to prevent precipitation and/or aerial spread. Flexible bulk containers
("super sacks") constructed of woven polyester and/or polypropylene may be used at the site
instead of stockpiling. The flexible bulk containers, ifused, have an approximate capacity of
1.1 m' (40 ft.') and will be able to be tied shut to eliminate the need to tarp the load during
transport. The super sacks will be stockpiled on a 20-mil plastic liner (or equivalent) until
loaded and secured on an end dump or flatbed trailer. The excavated, TPH-impacted soils will
be transported to the NTS for disposal at the Area 6 Hydrocarbon Landfill (located
approximately 480 km [300 mi] from the site).
Decontamination rinsate will be generated from cleaning of the excavation equipment. The
excavation equipment will be cleaned using scrub brushes and hand-operated sprayers to
minimize the quantity ofrinsate generated. The buckets of the equipment will be cleaned using
a mixture containing Alconox and tap water followed by a tap water rinse. The rinsate will be
captured by a plastic liner below the equipment and solidified using the excavated TPH
impacted soil. The solidified rinsate will be transported with the TPH-impacted soil to the NTS
for disposal in the Area 6 Hydrocarbon Landfill.
![Page 33: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/33.jpg)
SAFER Plan for CAU 416Section: 5.0Revision: 1Date: 07/03/97Page 25 of 32
Disposable sampling equipment and PPE will be contained in either 20S-liter (55-gallon) drums
or flexible bulk containers. The sampling equipment and PPE will be transported to the NTS
and disposed of in an NTS sanitary landfill.
All loads of waste transported from the site will be covered with the exception of materials that
have been contained in flexible bulk containers or equivalent.
![Page 34: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/34.jpg)
SAFER Plan for CAU 416Section: 6.0Revision: 1Date 07J03/97Page 26 of32
6.0 Site-Specific Health and Safety Plan
The health and safety protocols for the field activities related to the implementation of this
SAFER Plan will be delineated in a Site-Specific Health and Safety Plan (SSHASP). This
SSHASP, controlled separately from this SAFER Plan, is not included as part of this plan, but
will be available upon request prior to the start offield activities. The SSHASP sets forth the
specific requirements and procedures that will be followed while performing operations under
this SAFER Plan. The SSHASP includes the following information:
Engineering and administrative protective measures• Monitoring for site-specific chemical and radiological contaminants• Personal protective equipment and its use
Site controlEmergency communications
• Emergency reporting protocolDecontarnination
• Site characterizationTraining
All field activities will be performed in accordance with the applicable SSHASP, and all field
personnel involved in these activities will be familiar with requirements of the SSHASP. All
visitors to the work sites will be required to abide by these procedures.
The 0 bj ective of the SSHASP is the protection of workers during SAFER Plan activiti es, This
will be accomplished through compliance with DOE Orders, Occupational Safety and Health
Administration Regulations, and the DOEINV NV/YA1PRadiological Control Manual
(REECo, 1994), as well as the SSHASPs. Many of the operations conducted under the
DOEINV ERP are regulated under the DOE Orders and Title 29 of the Code ofFederal
Regulations.
Due to unique logistics, hazards, and site conditions, individual groups of sites and/or tasks
require the production of a SSHASP. It is considered a living document, and as new
information becomes available, changes will be made as appropriate, with concurrence and
approval of the Subproject Manager.
![Page 35: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/35.jpg)
SAFER Plan for CAU 416Section: 7.0Revision: 1Date: 07/03/97Page 27 of32
7.0 References
AEC, see U,S. Atomic Energy Commission.
Desert Research Institute, 1988. CERCLA Preliminary Assessment ofDOE's NevadaOperations Office Nuclear Weapons Testing Areas. Las Vegas, NV.
DOE, see U.S. Department of Energy.
DRI, see Desert Research Institute.
Eubank, B.F, and A. \V. Volard. 1964. On-site Health and Safety Report, VUF-10 12. Preparedfor AECINVO, Mercury, NV: Reynolds Electrical & Engineering Co., Inc.
Fauver, D.N. 1986. Hazardous Waste Installation Assessment Report. Las Vegas, NV:Reynolds Electrical & Engineering Co., Inc,
Federal Facility Agreement and Consent Order of1996, Appendix VI. Agreed to by theNevada Division of Environmental Protection, the U.S. Department of Energy, and theU.S. Department of Defense. Las Vegas, NV.
Gardner, M.e. and W.E Nork. 1970. Evaluation ofthe Project Shoal Site, Fallon, Nevada.forDisposition, Including Identification ofRestrictions, Part I, NVO-1229-105. Reportprepared for AECINVO. Las Vegas, NV.
Giller, EB., Major General, USAF, Assistant General Manager for Military Applications.U. S. Atomic Energy Commission. 1970. Letter to R.E. Miller, 31 August.Washington, DC.
Gretsky, P. IT Corporation. 1996, Letter to Bob Bangerter, DOEINV, about radionuclidelevels in groundwater monitoring well pads, 4 December.
Korver, lA, e.R. Boardman, and D.E Rawson. 1964. The Shoal Postshot Environment,SDK 65-5, Lawrence Radiation Laboratory.
Nevada Administrative Code, 1995. NAC 459, "Control of Hazardous Materials,"
REECo, see Reynolds Electrical and Engineering, Inc,
Reynolds Electrical and Engineering, Inc. 1994. NVIYA1PRadiological Control Manual,DOEINV 10630-59. Las Vegas, NV.
![Page 36: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/36.jpg)
SAFER Plan for CAU 416Section: 70Revision: 1Date: 07/03197Page 28 of 32
u.S. Atomic Energy Commission, Nevada Operations omceo 1964. Project Managers Report,Project Shoal, NVO-11. Las Vegas, NV.
U,S. Atomic Energy Commission, Nevada Operations Office. 1970. Site Disposal Report,Fallon Nuclear Test Site (Shoa!), Churchill County, Nevada, NVO-73. Las Vegas, NV.
u.s. Department of Energy, Nevada Operations Office. 1994. Resource Conservation andRecovery Act Industrial Sites Quality Assurance Project Plan, Nevada Test Site, Nevada.Prepared by IT Corporation for DOEINY Las Vegas, NY
u.s. Department of Energy, Nevada Operations Office. 1996. Corrective Action InvestigationPlanfor Project Shoal Area, CAU No. 416. Prepared by IT Corporation for DOElN\lLas Vegas, NY
u. S. Environmental Protection Agency. 1996. Test Methodsfor Evaluation, Solid Waste,Physical Chemical Methods, S\V 846, Third Edition. Washington, DC.
![Page 37: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/37.jpg)
Appendix A
Response to NDEP Comments
SAFER Plan for CAU 416Appendix ARevision: 1Date: 07/03/97Page 29 of 32
![Page 38: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/38.jpg)
NEVADA ENVIRONMENTAL RESTORATION PROJECTDOCUMENT REVIEW SHEET
SAFER Plan for CAU 416Appendix ARevision: 1Date: 07/03/97Page 30 of 32
_=z=..~= -",....=""";:::..;:=""',. . _._ .....
1. Document Title/Number Draft SAFER Plan for Project Shoal, Mud Pit 2. Document Date April 1997
3. Revision Number REV. 0 4. Orig inator/Org anization IT Corporation
5. Responsible DOE/NV ERP Project Mgr. Janet Appenzeller-Wing 6. Date Comments Due
7. Review Criteria
8. Reviewer/Organization/Phone No. Karen Beckley. NDEP 9. Reviewer's Signature-_.. ....- "'l"o::I7:I:>:r.
1O. 11. 12. 13. 14.
Comment Type" Comment Comment Response Accept
Number/
Location
Page 4 of31 "If at any time during the closure activities, information is The text was changed to read "...information is discovered
developed that invalidates any assumption, this plan will be that invalidates..." and the following was added at the end of
amended, and amendments will be provided to NDEP for the paragraph. "No work will be conducted on site from the
approval." time the invalidating information is discovered to the time
approval of the amended SAFER Plan is received from
If information is "discovered" (as apposed to developed), a NDEP"
determination needs to be made if the Plan can be amended
depending on the type of problem that is encountered. The Plan
must also clearly state that activities will stop and not proceed
without NDEP approval.
Page 180f31 "__ .are evaluated to be below the 100 mg/kg Action Level or until Added at the end of the paragraph: "If the TPH concentration
the excavation encounters bedrock." in the bedrock exceeds the 100 mg/kg Action Level, an
administrative closure will be requested from the state"
DOE needs to discuss what activities will occur if action levels
above 100 mg/kg in bedrock is encountered.
![Page 39: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/39.jpg)
SAFER Plan for CAU 416Appendix ARevision: 1Date 07/03/97Page 31 of 32
NEVADA ENVIRONMENTAL RESTORATION PROJECTDOCUMENT REVIEW SHEET
IIIUJvl 0Revision Number _----"' _Document Title/Number Draft SAFER Plan for Project Shoal, Mud Pit
Reviewer/Organization Karen Beckley. NDEP
·"',"':::I:'='I,:·,,:,-,''1:~t ='"":/":_,,"= _,J"'_""~T""-='!I:1:.
1O. 11. 12. 13. 14.
Comment Type" Comment Comment Response AcceptNumber/Location
Page 21 of 31 "Since the material in the sumps has been determined to be The analytical results from the samples collected from the
non-hazardous, confirmation sampling will not be conducted in sumps by IT in October and December 1996 and the
those areas." samples collected from the sumps by DRI in March 1997
are attached. Nothing will be done with the effluent in the
NDEP has not received and concurred with the analytical sumps until approval is received from NDEP.
results of the sampling of the sumps. The drilling effluent
sumps cannot be removed prior to NDEP review and
concurrence of the sampling results.
Page 25 of31 " ..NDEP has approved the discharge of the liquid from the The analytical results from the samples collected from the
sumps to the ground surface ..." sumps by IT in October and December 1996 and the
samples collected from the sumps by DRI in March 1997
In a telephone conversation with B. Bangerter on November 25, are attached. Nothing will be done with the effluent in the
1996, and a letter to DOE from NDEP on March 4, 1997, NDEP sumps until approval is received from NDEP.
stated concern that DOE had not sent any results of well water
sampling to include the fluid pumped into the sumps. This issue
must be resolved PRIOR to any activity being conducted with
the fluid contained in the sumps.
![Page 40: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/40.jpg)
SAFER Plan for CAU 416Appendix ARevision: 1Date: 07/03/97Page 32 of32
NEVADA ENViRONMENTAL RESTORATION PROJECTDOCUMENT REVIEW SHEET
IIIIUL.I aRevision Nl· ..... h ....~~---------
Document Title/Number Draft SAFER Plan for Project Shoal. Mud Pit
Reviewer/Organization Karen Beckley. NDEP
;7'\':t.===,M'''''"",,'' =,;.".==.,,---. -1O. 11. 12. 13. 14.
Comment Typea Comment Comment Response AcceptNumberl
Location
General NDEP will not approve the SAFER Plan for Mud Pit (CAS 57-09- All references to the effluent sumps were removed from the
01) with the incorporation of the closure of the effluent sumps document.
The effluent sumps will be utilized during well development
activities. These sumps are part of the subsurface CAU and
governed by the Fluid Management Plan. Additionally, the
issues identified in the June 9, 1997 letter from NDEP to DOE
that relate to the ROC associated with these sumps, must be
addressed in documents related to CAU 447.
Page 3 of 35 The decision diagram states "Amend SAFER Plan to The diagram was changed to indicate that if the bed rock
incorporate the new information. Resume field activities under was contaminated above the 100 mglkg action level, and
revised plan" Field activities should not be conducted unless additional excavation was not feasible, an administrative
DOE has concurrence from NDEP for the revised plan. This closure would be requested.
verbiage is stated in the text of the document, however, the
diagram does not convey the same message.
Table A-1 is incomplete and needs to be revised if the The table relates to the effluent sumps and since all
Page 35 of 35 information is pertinent to the Mud Pit. The headers across the reference to the effluent sumps has been removed the table
top of the chart are missing. What constituents are the values is no longer included in the document.
representing? DOE must also compare how these values relate
to regulatory requirements."" ... .; =·_",~''''O,,...~~-: ,~. --,..- .... ...-
aComment Types: M =Mandatory, S =Suggested.
ReturnDocument Review Sheets to DOE/NVEnvironmental' Restoration DiVision, Attn: OAC,M/p-5Q?
![Page 41: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/41.jpg)
Janet Appenzeller-WingDOElNevada Operations OfficeEnvironmental Restoration DivisionP.O. Box 98518, -r..1JS 505Las Vegas, NV 89193-8518
Paul J. LiebendorferBureau of Federal FacilitiesDivision of Environmental Protection333 W. Nye Lane, Room 138Carson City, NV 89706-0851
Chuck BulikBureau of Federal FacilitiesDivision of Environmental Protection555 E. Washington, Suite 4300Las Vegas, NV 89101
Sabrina D, BonnellDOElNevada Operations OfficeEnvironmental Restoration DivisionP.O. Box 98518, MIS 505Las Vegas, NV 89193-8518
Martha DeMarreDOE Public Reading RoomP.O, Box 98521, -r..1IS NLV040Las Vegas, ~v 89193-8521
Timothy WhiteIT Corporation4330 S. Valley View, Suite 114Las Vegas, NV 89103
Rosa SilverIT Corporation4330 S, Valley View, Suite 114Las Vegas, NV 89103
Distribution List
SAFE R Plan for CAU 416Distribution ListRevision: 1Date: 07f03/97Page 1 of 2
Copies
1 (Controlled)
2 (Controlled)
1 (Controlled)
1 (Controlled)
1 (Controlled)
1 (Controlled)
2 (Controlled)
![Page 42: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/42.jpg)
Distribution List
DOElNevada Operations OfficeTechnical Information Resource CenterP.O. Box 98518, ~1IS 505Las Vegas, NV 89193-8518
u.s. Department of EnergyOffice of Scientific and Technical Information175 Oak Ridge TurnpikeP.O. Box 62Oak Ridge, Tennessee 37831
DOE Public Reading RoomP.O. Box 98521, I\1IS NLV040Las Vegas, NV 89193-8521
Dave MadsenBechtel NevadaP.O, Box 98521, WS NTS306Las Vegas, NV 89193-8521
Copies
1
2
1
1
SAFER Plan for CAU 416Distribution ListRevision: 1Date: 07/03f97Page 2 of2
![Page 43: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/43.jpg)
RECORD OF TECHNICAL CHANGE
2Page ~1,--_ of -=-_1Technical Change No.
Date 8/28/97
Project Shoal Area (CAU 416)Project/Job Name -----"-""-=='----"'-'~=-=-"""'-"=->.-'='-=-~----'--"'..><.,.L_--------
The following technical changes (including justification) are requested by:
Janet Appenzeller-\Ving(Name)
Off-Sites Sub-Project Manager(Title)
The following modification to Revision 1 of the Project Shoal Area SAFER Plan, dated July1997:
Add Corrective Action Site (CAS) CAS 57-06-01 (Muckpile) to the Streamlined Approach forEnvironmental Restoration Plan for Corrective Action Unit 416, Mud Pit, Project Shoal Area,dated July 1997.
JUSTIFICATION:
The Corrective Action Investigation Plan (CAIP) for Project Shoal Area, CAU No. 416, datedAugust 1996 stated an assumption that the muckpile would be used as backfill for the shaftclosure, however, only one third of the material was used as backfill. Enough process knowledgeexists to close the remaining two-thirds of material in place with no further action.
Process knowledge to close the muck pile in place with no further action indicates that thebroken rock material extracted from the emplacement shaft as it was constructed occurred priorto any testing of nuclear devices. The shaft was not reentered after the detonation ofthe Shoaldevice, therefore all rock materials existing as part of the muck pile may be considered nativerock. Post shot detonation investigations conducted in 1963 at a distance of approximately 1100ft east ofthe muck pile did not affect the broken rock materials comprising the muck pile.(Project Managers Report, Project Shoal, United States Atomic Energy Commission; NevadaOperations Office, May 1964)
The Project Shoal Area emplacement shaft was sunk in granitic rocks which comprise the bulk ofthe Sand Springs Range where the Project Shoal site is located. Based on the geologic rockdescriptions generated during drilling efforts near the emplacement shaft in identical rock types,it was determined that the mineralogic composition of these rocks did not contain minerals thatwould contain metals in greater than background concentrations in the area. This is supported bysoil samples collected from decomposed soil equivalents of these rocks by DOE during theSeptember 1996 surface characterization activities. The analysis of the soil samples to providechemical data regarding native background concentrations indicated no constituents in excess ofregulatory limits. (Draft Data Report Project Shoal Area Churchchill Co. Nevada, January1997). This draft data report will be finalized when it is incorporated into the subsurface (CAU447) Corrective Action Decision Document and the results pertinent to the muckpile closure willbe will be included in the Closure Report for CAU 416.
![Page 44: Streamlined Approach for Environmental Restoration Plan 41 …...practica17 Propose Adm inistrative closure Covered in the SAFER P'an Phase 2 C onduct verihe ation sa mpiing Phase](https://reader034.vdocuments.mx/reader034/viewer/2022052001/601404a763361a680637dbb2/html5/thumbnails/44.jpg)
The muck pile currently occupies an approximate surface area of 10,000 square feet. Brokenrock material has been placed on the existing gently sloping topographic surface with a.maximum relief from the natural grade along the eastern perimeter. Recontouring of the muckpile would be of minimal benefits as the surface area degraded would be significantly larger inarea and would cover areas of existing native vegetation.
The project time will be (lncreased)(Decreased)(Unchanged) by approximately adavs.
Date 1/3/f), i
cC: Approved By: Sr:8L;) !r) L I/:" ,rl.Project ManagerNevada Environmental Restoration Project
u~~·wProject Manager J
Off-Sites Subproject
Date sh /'\1