stephen milton [email protected] system update fac review april 2005 undulator system...
Post on 20-Dec-2015
220 views
TRANSCRIPT
Stephen Milton
[email protected] System Update
FAC Review April 2005
Undulator System Update
Facility Advisory Committee Review
April 7th and 8th 2005
Stephen Milton
Argonne National Laboratory
Advanced Photon Source
Stephen Milton
[email protected] System Update
FAC Review April 2005
Outline
Quick Overview
Project Management and Administrative Items
Organization
Plan for the next 6 months
FAC Responses
Magnet Measurement Facility
See Robert Ruland’s Talk in breakout session 1 and J. Sevilla’s breakout session 4.
Physics Topics
Magnet Support System Status
Vacuum System
Diagnostics Status
Building Topics
Controls Status
System Integration Test
Stephen Milton
[email protected] System Update
FAC Review April 2005
Undulator OrganizationUndulator System
System Manager S. Milton
Chief Engineer/Deputy G. Pile
Magnetic Measurement
R. Ruland
System Layout
TBD
SLAC Integration
B. Youngman
Magnets and Supports
M. White
Vacuum and Diagnostics
D. Walters
Controls
J. Stein
Undulator Physics
H.D. Nuhn
Global Schedule and
Integration
R. Boyce
CF Physics
J. Welch
PMCS Support
P. Mast (AIM)F. Clark (ANL)
Controls System
System Manager
B. Dalesio
Stephen Milton
[email protected] System Update
FAC Review April 2005
Faces
Geoff PileANL LCLS Chief Engineer
Responsible for overall undulator system integration and will act in the role of my Deputy
Stephen Milton
[email protected] System Update
FAC Review April 2005
Faces
Sushil SharmaFixed Supports Engineer
Will be responsible for the engineering and delivery of the undulator system fixed supports
Has already begun coordinating with Jim Welch
Stephen Milton
[email protected] System Update
FAC Review April 2005
Faces
Horst FriedsamANL/SLAC Survey and Alignment LiasonWill coordinate with Robert Ruland to ensure all survey and alignment needs of the undulator system are met
Stephen Milton
[email protected] System Update
FAC Review April 2005
New Roles
Undulator Integration Engineer (SLAC)
At SLAC Brad Youngman will oversee daily integration issue for the undulator system
Brad will report directly to Geoff Pile and myself
For administrative purposes Brad will also report to Mark, but ANL will have the final say on what Brad should be doing
Stephen Milton
[email protected] System Update
FAC Review April 2005
New Roles
ControlsBob Dalesio directs the overall LCLS Controls effort; therefore,
Josh Stein will work directly with Bob to ensure a robost integration of the overall LCLS controls system
For administrative purposes Josh will still report to me, but Bob will have final say in all controls issues
Stephen Milton
[email protected] System Update
FAC Review April 2005
6 Month Look Ahead
BPM SystemBuild cold test prototype x-band beam detectorDesign receiver boards
OTRAssemble and Test Prototype
Wire ScannerAssemble and Test Prototype
Support/Mover SystemAssemble and Test Prototype
1st Article UndulatorsMaybe receive 1st articles from assembly vendors
Fixed SupportsFinalize design and begin procurement for testing
Vacuum ChamberFinalize testing of construction methodsStart building prototype
Project ManagementIt never Ends
Stephen Milton
[email protected] System Update
FAC Review April 2005
FAC Responses
Cradle (Mover/Support) System Needs Attention
In addition to Emil Trakhtenberg an additional engineer, Jeff Collins, has been assigned to work on the Mover/Support System
All parts for the prototype have arrived and it will be assembled soon
Stephen Milton
[email protected] System Update
FAC Review April 2005
FAC Responses
Trade-offs must be considered to decide whether longer girders can improve tolerance to ground motion
An engineer with experience in girder system (Sushil Sharma) has been assigned to fully develop the fixed support strategy and engineering
He is going over all trade-offs and he is responsible to make the decision, pending review, of the support system used
Stephen Milton
[email protected] System Update
FAC Review April 2005
FAC Responses
The FAC recommends that, if the gap/period is changed, a new prototype is not necessary
We are not changing the gap or the period
Consider the use of feed-forward from temperature measurement to adjust the undulator horizontal position and control K
Although this has been discussed and the system is certainly capable of responding in such a fashion, we have not pursued it or tested it yet
Temperature readback of the undulator will be available
Stephen Milton
[email protected] System Update
FAC Review April 2005
FAC Responses
The decision has been made to NOT hire a general contractor responsible for delivering complete undulators. The consequences of this decision (plans for control of final assembly) should be presented
The magnet design and engineering has been refined with ease and simplicity of construction in mindA statement of work is being written and will include a complete description of the QA process to be followed
A QA person has been assigned to the projectA complete assembly procedure has been written and a video is being made of the assembly processTwo assembly vendors will be chosenAssembly vendors are being prequalifiedThe 1st article from each of the two vendors will be thoroughly measured and tested before we will accept additional undulatorsFrequent vendor visits will be made to the vendors to perform QA/QC checks and complete assembly travellers will be required for each undulator and component
Stephen Milton
[email protected] System Update
FAC Review April 2005
Magnet Measurement Facility
SLAC ScopeANL will act in both mentoring and consulting roles as the facility gets constructed and commissioned.
See Robert Ruland’s talk for more detailsUndulator Measurement/Fiducialization/In-Situ Alignment : Breakout session 1 4:00pm
Stephen Milton
[email protected] System Update
FAC Review April 2005
Physics Issues
Break Lengths
AC ConductivityWhat we did
What we decided
Radiation CalculationsPreliminary Results
Next Steps
AlignmentBPM Location
Undulator SectionsWire idea
Feedback
Earth’s Field Correction
Initial Basic Commission Steps
Stephen Milton
[email protected] System Update
FAC Review April 2005
Characteristic Lengths Length of Undulator Strongback (Segment):
Lseg = 3.4 m
Distance for 113 x 2 Phase Slippage:L0 = (3.668 m) 3.656 m
Distance for 2 Phase Slippage in Field Free Space:Linc = u (1+K2/2) = 0.214 m
Standard Break Lengths Used Use parameter n to characterize different phase length choices
Ln = L0 - Lseg +(n-1)Linc
Use 2 Short Breaks Followed by 1 Long Break in n-Pattern2 – 2 – 4 ([0.482 m – 0.482 m – 0.910 m]) [0.470 m – 0.470 m – 0.898
m]
Fine Tuning of Initial Break Length Suggested by N. Vinokurov based on Simulations by R. Dejus and N. Vinokurov
using Linear Simulation Code, RON
Small length increases for first 3 break lengths[0.045 m – 0.020 m – 0.005 m]
Total Undulator Length (from beginning of strongback 1 – end of strongback 33):
Lund = (131.59 m) 131.52 m
Undulator Break LengthsUndulator Break Lengths(Old Strategy)(Old Strategy) New Strategy New Strategy
Taking from HD Nuhn’s FAC Talk
Stephen Milton
[email protected] System Update
FAC Review April 2005
AC Conductivity
induced energy deviation for round chamber
induced energy deviation for flat chamber
Stephen Milton
[email protected] System Update
FAC Review April 2005
AC Conductivity
What’s been doneTheory
Bane, Stupakov, HuangSimulation
Fawley, Reiche, EmmaMeasurements
Yu, Walters
What was decidedThe beam sees AlWe use a flattened cross-sectionWe explore a variety of operating points during commissioning
There will be a much more complete description of what has been done supporting our decision during beakout session 1 of the FAC
Stephen Milton
[email protected] System Update
FAC Review April 2005
Radiation Calculations
OTR ScreensWe are concerned that the radiation produced by these screens when inserted into the beam could damage the undulatorBingxin Yang produced a set of conditions and geometries that might be encountered and provided these to the SLAC radiation physicisitAlberto Fassò chose the condition that would produce the most radiation and did simulations of it using his program FLUKA
Stephen Milton
[email protected] System Update
FAC Review April 2005
Radiation Calculations
The data in the literature seems to suggest that neutrons are most responsible for the degradation in performance of the permanent magnet blocks.
Stephen Milton
[email protected] System Update
FAC Review April 2005
Radiation Calculations
Preliminary ResultsEven with a 100 micron thick screen the simulation suggests that we could operate at 14 GeV with 1nC and at 120 Hz for 10 days before experiencing damaging demagetization
Real operationsWe intend to use foils that are only a micron or two thickWe also plan to use the OTR screens only at low repetition rates (~10 Hz) and they will never be left in while we analyze data
HoweverMagnetic fields were not included in the FLUKA simulationsA field map will be given to Fassò along with other improvements in the geometry and operating conditionsThe simulation will be done again with these improvements
Stephen Milton
[email protected] System Update
FAC Review April 2005
Undulator Alignment
Question: How do you ensure that both ends of the undulator are on the desired line?
Beam-based alignment will be used to position the quadrupoles
The quadrupoles are “locked” to the end of the undulator with their magnetic centers aligned to the desired magnetic center of the undulatorThe determines one end of the undulator
New ideaUse a wire at the other end of the undulator that has two positions: one out and one in to a fixed stopThe in position would be accurately aligned to the desired magnetic center of the undulator
Stephen Milton
[email protected] System Update
FAC Review April 2005
Undulator AlignmentBefore any BBA or wire alignment performed
After BBA: Quad, BPM and one end of the undulator aligned
After Wire Alignment: Both ends of undulator aligned
Stephen Milton
[email protected] System Update
FAC Review April 2005
Undulator Alignment
Wire IssuesHow do you distinguish easily between the electron beam and the x-rays
The beam will create an easily seen radiation shower downstream orYou could first extract the undulators
Horizontal positioning is less critical than vertical
Would require a wire after each undulatorNew idea
Needs some time to cook
Stephen Milton
[email protected] System Update
FAC Review April 2005
BPM Location
Adjacent to the Quadrupole (SM)If we believe the BPM absolutely then it could go on the other end and be used to align the downstream end of the undulator
No need to do this if we use the wire method
Advantages of being adjacent to the quadrupoleThe quad locations are critical and the is no ambiguity with the BPM adjacent
Following BBA and following quad strength massaging one will have the offset (mechanical and electrical) of the BPM
Stephen Milton
[email protected] System Update
FAC Review April 2005
Earth Magnetic Field Compensation StrategyEarth Magnetic Field Compensation Strategy
Earth Magnetic Field along Beam Trajectory in Undulator requires compensation. Estimated strength 0.43±0.06 Gauss : (0.18±0.03, -0.38±0.07,0.08±0.05) Gauss Based on Measurements by K. Hacker. (see LCLS-TN-05-4)
Compensation Strategy: Position the Undulator on Magnetic Measurement Bench in same
direction as in Undulator Tunnel
Compensate Earth Field Component in Undulator in Shimming Process
Scheduling Issues Taken from HD Nuhn’s FAC Presentation
Stephen Milton
[email protected] System Update
FAC Review April 2005
Earth Magnetic Field CompensationEarth Magnetic Field CompensationAdjustable Shim ConceptAdjustable Shim Concept
Risk arises from the lack of precise knowledge of the earth field in the tunnel at the time of undulator segment tuning.
Considering mitigation strategy based on use of a small number of precisely adjustable shims along each undulator.
One extra shim per segment will reduce phase error by factor 4.
Shims will be installed before undulator tuning, but adjusted before undulator installation when field error has been determined.
Will not affect definition of magnetic center of undulator (Standard Undulator Axis, SUSA, [see PRD 1.4-001 4.7])
Quad Quad QuadBPMBPMUndulator Undulator
Shim Position Trajectory w/ Shim
Trajectory w/o Shim
Also Taken from HD Nuhn’s FAC Presentation
Stephen Milton
[email protected] System Update
FAC Review April 2005
Magnet and Support System Status
Undulator MagnetsLong Lead Procurements
Strong team Lead by M. WhiteTitanium Strongback
Cost increase (Commodities Price)
Magnet PolesCost Decrease (Simplification)
Magnet Blocks
Magnet Assembly
SupportsSupport Mover System
Prototype being assembledMeasurement equipment orderedExpect late May early June Testing
CAM Mover system testSliding stage measurements
Fixed Supports
Stephen Milton
[email protected] System Update
FAC Review April 2005
Und. Magnet: LLP, Ti Strongback
StatusTwo Vendors Chosen
Cost higher than expected due to very rapid increase in cost of metal commodities over the last couple of years
Stephen Milton
[email protected] System Update
FAC Review April 2005
Und. Magnet: LLP, Magnet Poles
StatusOne Vendor Chosen
Based on cost
This vendor also had experience
Cost came is less than what we originally estimated
Due to simplification of the pole designNo ears
Stephen Milton
[email protected] System Update
FAC Review April 2005
Und. Magnet: LLP, Magnet Blocks
StatusRFP Delayed
Spent additional time refining the sorting plan in the statement of work.
The successful vendor will be required to sort the magnet blocks prior to shipment to the assembly vendor
Do not expect the delay to impact the assembly schedule
Stephen Milton
[email protected] System Update
FAC Review April 2005
Und. Magnet: Assembly
Plan to go with external assembly vendorsA lot of thought has gone into simplifying the assembly to the point that assembly can be done easily with simple training
How we will do itA statement of work is being written and will include a complete description of the QA process to be followed
A QA person has been assigned to the projectA complete assembly procedure is being written and a video is being made of the assembly processAssembly vendors are being prequalifiedTwo assembly vendors will be chosenThe 1st article from each of the two vendors will be thoroughly measured and tested before we will accept additional undulatorsFrequent vendor visits will be made to perform QA/QC checksComplete assembly travellers will be required for each undulator and component
Stephen Milton
[email protected] System Update
FAC Review April 2005
Und. Magnet: Support/Mover SystemPrototype parts in and assembly beginning
Testing expected in May/JuneCAM, Sliding Mechanism, etc. E. Trahktenberg and J. Collins
Stephen Milton
[email protected] System Update
FAC Review April 2005
Und. Magnet: Support/Mover System
Detail of Support/Mover System
Stephen Milton
[email protected] System Update
FAC Review April 2005
Und. Magnet: Support/Mover System
CAM Mover systemOther system reconsidered
CAM mover still found to be the method of choice
Modifications madeTotal CAM offset reduced to 1.5 mm
Better gearbox
Better bearings
Stephen Milton
[email protected] System Update
FAC Review April 2005
Und. Magnet: Fixed Supports
Recent ChangeANL takes over scope of the fixed support system
Experienced engineer assigned to the fixed supportSushil Sharma
In consultation with Jim Welch
Options being reconsideredPast thinking has been to use granite supporting 3 undulators
Other ideas are also being explored
Stephen Milton
[email protected] System Update
FAC Review April 2005
Vacuum System
ChangesBeam Sees Aluminum
Al on SSStudy of relative permeability
“Flat” cross-section Construction
Stephen Milton
[email protected] System Update
FAC Review April 2005
Vacuum System
Build chamber out of SS coated with AlWhat about the relative permeability?
Curves on the right show the effect of both linear and nonlinear permeability on the undulator field
= 1.115 mm x 5 mm chamber cross-section
Expect SS relative permeabilities of less than 1.01Looks OK but we will be doing more direct measurements to prove this is OK
Waiting for accurate, calibrated permeability meter
0.000 0.002 0.004 0.006 0.008 0.010 0.012 0.014-4.0x10-3
-3.0x10-3
-2.0x10-3
-1.0x10-3
0.0
1.0x10-3
2.0x10-3
3.0x10-3
4.0x10-3
Perturbation from 15mm (H) x 5mm aperture chamber.Constant and nonlinear permeability.
B
[T]
Z [m]
=1.1 Constant =1.1 Nonlinear
0.000 0.002 0.004 0.006 0.008 0.010 0.012 0.014
-4.0x10-4
-2.0x10-4
0.0
2.0x10-4
4.0x10-4
Perturbation from 15mm (H) x 5mm aperture chamber.Constant and nonlinear permeability.
B
[T]
Z [m]
=1.1 Constant =1.1 Nonlinear
Stephen Milton
[email protected] System Update
FAC Review April 2005
Chamber Design
Start with SS FlatCoat with AlBend to Desired U shapeWeld to Vacuum Strongback
Stephen Milton
[email protected] System Update
FAC Review April 2005
Vacuum Status
Issues to addressSS permeability test
All samples in hand and parts in shops
~1 Month samples ready for measurement
Check of welding, bending, and annealing effects
Survey Market forCoating needs
Polishing needs
Fabrication
Stephen Milton
[email protected] System Update
FAC Review April 2005
Diagnostics Status
BPMsLocationPlans
OTR ScreensUseCapabilities
Based on APS Bunch Compressor DesignResolution
Prototype Timeline
Wire ScannersUse
Rethinking need and use
Undulator End Alignment Wire
Intraundulator Xray DetectorsPrototype plans
Waiting for in-vacuum motion tests
Vendor claims they will worksMust pass APS tests first
OtherCharge MonitorsCerenkov Monitors“End-Of-Undulator” Diagnostics
Stephen Milton
[email protected] System Update
FAC Review April 2005
Diagnostics Status: BPM
LocationAt the Quad
PlansUse X-Band RF BPM
Internal Dimensions SLAC responsibilityExternal ANL Responsibility
Processing ElectronicsIn-tunnel RF front end mixerGeneric RF front end
Capable for both cavity and stripline
A/D ConverterTeam determined
Stephen Milton
[email protected] System Update
FAC Review April 2005
Diagnostics Status: BPM
Prototype PlansBuild 4 cavities
Machining done externallyBrazing done at SLAC or externally
To be determined
Mount three on a rigid support and test with beam
Beam tests to occur at FFTB/SPPS
Closed in Mar. 06?Fall back location will be the APS PAR Bypass line
PC Gun beam with bunch compression
TimescaleWill need 1 year
B. Lill
Stephen Milton
[email protected] System Update
FAC Review April 2005
Diagnostics: OTR ScreensUse
Beam distribution measurement along the length of the undulator
Can be used for emittance measurement as twiss parameter checks
FeaturesCommercial 2 inch lens tube, magnification adjustable with change of lensIntegral tungsten shieldStepper driven remote focusDigital video camera, 30-fps at 1 MP, or 120 fps at VROI (250L), programmable gain.Manual iris control5 to 10 micron resolution
Based on APS Bunch Compressor OTR Success
PrototypeParts on orderTesting to occur in summer 05 BX Yang
Stephen Milton
[email protected] System Update
FAC Review April 2005
Diagnostics: Wire ScannerBased on SLAC design. Adapted for tighter space.Features
Mounted on 6-inch flangeOn-axis drive mechanism in airShare space with other diagnostics (OTR and x-ray)Wire card to adapt SLAC designTest setup is being designed
Actual use being re-examinedMight switch to the simpler 2 state end alignment wire (see earlier description)
J. Bailey, BX Yang
Stephen Milton
[email protected] System Update
FAC Review April 2005
Diagnostics: OTR and WS testingMeasure wire scanner motion accuracy
Calibrate step size and cross check encoder outputsMeasure motion error in all three directionsStudy motion error with different mounting orientation
Characterize OTR camera moduleCalibrate pixel sizeMeasure optical resolution
Status conceptual design in progressIn-Vacuum motors
Waiting for testsVendor claims goodMust pass APS standards
Stephen Milton
[email protected] System Update
FAC Review April 2005
Undulator Hall and Buildings
Equipment HallsCable Length Runs
Temperature ControlTight tolerances
20 ± 0.2 CNeeded for undulators (K value)
To minimize thermal expansion problemsMax (Min) Average power +50W/m (-50W/m)Max power fluctuations 5W/m
For more detailsGo to Welch talk at Breakout session 4 of the FAC
Stephen Milton
[email protected] System Update
FAC Review April 2005
Undulator Hall and Buildings
Equipment Halls
Maximum Cable Length < 150’
Additional Hole for future extension if needed
6 Undulators servedper drill hole
Requirements/DesiresKeep heat sources out of the tunnelKeep cable lengths to less than 150’Provide for convenient service and maintenance for all electronics
Stephen Milton
[email protected] System Update
FAC Review April 2005
Controls Status
OrganizationB. Dalesio in charge of LCLS controlsJ. Stein of ANL matrixed to Dalesio to ensure controls integration between undulator needs and the overall LCLS controls system
Undulator Equipment Halls A lot of work has been done to plan
Cable routingEquipment halls needsRack locations and needs
Major Undulator SystemsMotion Control
CAMs, Horizontal Motion, Intercepting Diagnostics Video
OTR System with up to 120 Hz frame capture rates
Controls PresentationSee J. Stein talk in breakout session 3 of the FAC for more details about the undulator controls
Stephen Milton
[email protected] System Update
FAC Review April 2005
Systems Integration Test
One Undulator Support Mover TestsPlan to assemble all major components and systems to test fit and operationsUse the 1st article undulator and prototype mover support systemUse a chamber mockup if a prototype is not availableFall 05
Multi Undulator System Integration TestsBuild up a complete system with at least 2 undulatorsUse 1st articles or prototypes for everything including fixed supportsTest overall assembly, fit, and systemsWinter 06
System Integrations Test PresentationSee M. Whites talk in breakout session 1 of the FAC for more details