REVISION OF SPECIFICATION / STR Item Name: Micro Controller Based Governor (MCBG) for application on ALCo/DLW/ 6 Cylinder 251 Series WDS6 D-E locomotives Specification No: MP-0-1700-04 1. RDSO is reviewing the specification/STR to cater to the latest technological developments in the field, modify clauses not relevant in the present context and making them more enabling with focus on functional requirements. 2. It is requested that your comments / suggestions with regard to improvements /modifications in specification / STR of the abovementioned item may be submitted in the following format along with the justification for the changes required. Part A: Basic Information SN Particulars Information 1. Name 2. Designation 3. Professional Qualification 4. Organization / Firms Name 5. Address for Correspondence 6. Contact No. 7. Email ID 8. Whether firm is registered with RDSO for the subject item. If yes, details like date of registration, current status etc. If no, firm’s experience in manufacturing of subject item or similar item 8. Whether any technical document/Report/Study to support suggested changes is available / enclosed for better appreciation Part B: Comments / suggestions on the specification SN Clause No. of RDSO STR/ Spec Clause, as it exists in RDSO STR/ Spec Clause , as it should read after incorporation of comments /suggestions in the RDSO Spec / STR Justification for changes Comments may be sent to following address within one month from the date of publication on rdso.indianrailways.gov.in B P S Bhadoria, Joint Director/MP (EC), Mobile No.-9794863120, E-mail ID: [email protected], [email protected] Phone no. : 0522-2450020 Fax No. 0522-2453916

Upload: others

Post on 18-Dec-2021

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Specification for Revision - Indian Railways

REVISION OF SPECIFICATION / STR

Item Name: Micro Controller Based Governor (MCBG) for application on ALCo/DLW/ 6 Cylinder 251 Series WDS6 D-E locomotives

Specification No: MP-0-1700-04

1. RDSO is reviewing the specification/STR to cater to the latest technological developments in the field, modify clauses not

relevant in the present context and making them more enabling with focus on functional requirements.

2. It is requested that your comments / suggestions with regard to improvements /modifications in specification / STR of the abovementioned item may be submitted in the following format along with the justification for the changes required.

Part A: Basic Information

SN Particulars Information

1. Name

2. Designation

3. Professional Qualification

4. Organization / Firm‟s Name

5. Address for Correspondence

6. Contact No.

7. Email ID

8. Whether firm is registered with RDSO for the subject item. If yes, details like date of registration, current status etc. If no, firm’s experience in manufacturing of subject item or similar item

8. Whether any technical document/Report/Study to support suggested changes is available / enclosed for better appreciation

Part B: Comments / suggestions on the specification

SN Clause No. of

RDSO STR/ Spec Clause, as it exists in RDSO STR/ Spec

Clause , as it should read after incorporation of comments /suggestions in the RDSO Spec / STR

Justification for changes

Comments may be sent to following address within one month from the date of publication on rdso.indianrailways.gov.in

B P S Bhadoria, Joint Director/MP (EC), Mobile No.-9794863120, E-mail ID: [email protected], [email protected] Phone no. : 0522-2450020 Fax No. 0522-2453916

Page 2: Specification for Revision - Indian Railways

भा र त स र का र रे ऱ मं त्रा ऱ य

अनु सं धा न अ भिकल्ऩ और मानक संगठन

लखनऊ स्था पि त : 1 9 5 7

Government of India

Ministry of Railways

Research Designs & Standards

Organization

L U C K N O W

E S T T : 1 9 5 7

© RDSO 2020

ALCo/DLW 6 सिलेंडर 251 श्रृंखला WDS6 डी-ई इृंजन ृं

के िाथ उपय ग के सलए माइक्र कृं ट्र लर आधाररत गवननर

(MCBG)

MICRO CONTROLLER BASED GOVERNOR (MCBG) FOR APPLICATION ON MICROPROCESSOR CONTROLLED

ALCO/DLW 6 CYLINDER 251 SERIES WDS6 D-E LOCOMOTIVES

Specification Number MP.0.1700.04 Revision Number 1–final draft Date of Issue 23/10/2020

Brief Description

This document describes the requirements for the development of Microprocessor Based Control Governor for WDS6 Diesel Electric Locomotives. The complete specification details the functional requirement of the unit, scope of supply and testing of the equipment ensuring reliability and fail-safe operation

Page 3: Specification for Revision - Indian Railways

FOREWORD

This specification covers the technical requirements and general features of MCBG for ALCO/DLW 6 cylinder 251 series WDS6 diesel engine on new built or fitment on old locomotives.

DISCLAIMER

This specification is based on the studies and trials conducted by RDSO. Although every care is taken in specifying details adequately and unambiguously, RDSO shall not liable for any kind of damages / losses incurred by any and all due to errors or omissions in this document. When using the information described herein, the user is ultimately responsible for their own actions, as well as the actions of subordinates and assistants, and the consequences arising there from.

This document may mention numerous commercial and proprietary trade names, registered trademarks and the like (not necessarily marked as such), patents, production and manufacturing procedures, registered designs, and designations. RDSO wishes to point out very clearly that the present legal situation in respect of these names or designations or trademarks must be carefully examined before making any commercial use of the same.

Names of industrially produced apparatus and equipment may be included to a necessarily restricted extent only and any exclusion of products not mentioned in this document does not imply that any such exclusion has been based on quality criteria or any other qualifying consideration.

COPYRIGHT

RDSO has the copyright of all its publications. No part of these publications may be reproduced in any form without the prior permission of RDSO. Enquires relating to the copyright should be addressed to Executive Director (Administration), RDSO.

ADDRESS FOR COMMUNICATION

Government of India - Ministry of Railways, Research Designs & Standards Organization Manak Nagar Lucknow Uttar Pradesh India Pin: 226 011 Fax: +91 (522) 2458500 Phone: +91 (522) 2451200 (PBX) +91 (522) 2450115 (DID) Website: www.rdso.indianrailways.gov.in

Page 4: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued: 23/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 1 of 28

LIST OF AMENDMENTS

S. No.

Amendment Date

Revision

Details

1. 1 October 2008

0 First issue

2. October 2020

1 Cl. 11 Make of connectors deleted.

Cl. 14, Ambient temperature updated as 0 to 55 Deg C instead of 5 to 55 Deg C.

Clause 15 Inspection and Testing updated. Annexure-5 Methodology for inspection and testing of MCBG incorporated. Test Protocol format for Prototype test and Acceptance test along with Acceptance criteria are incorporated in Annexure 5 of the specification.

Cl 16.Performance feedback format added in heading of Field Trial. RDSO Document no. MP-8.1-1 is referred for field trials Quantity and Quality.

Cl.17 Heading of Approval replaced with heading of Bulk Supply after MCBG becoming Annexure item (Items which can be procured through Open Tender) in Vendor directory

Clause no. 25, “Vendor changes in approved status” reference of ISO document no. has been incorporated.

Clause 26 & 27 for IPR and Confidentiality has been incorporated.

Make in India Policy has been incorporated at Clause no. 28.

Page 5: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued: 23/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 2 of 28

CONTENTS

PARA NO.

DESCRIPTION PAGE NO.

1 INTRODUCTION 3

2 SCOPE OF SPECIFICATION 3

3 SCOPE OF SUPPLY 3

4 BASIC FUNCTIONS 3

5 AUXILIARY FEATURES 5

6 SAFETY FEATURES/DEVICES 7

7 DIAGNOSTIC AND FAULT LOGGING SYSTEM 8

8 ADJUSTMENT OF VARIOUS ENGINE PARAMETERS 8

9 GOVERNOR OUTPUT SHAFT AND LINKAGE 8

10 MOUNTING ARRANGEMENT 9

11 CONNECTORS 9

12 CABLES 10

13 POWER SUPPLY 10

14 SERVICE CONDITIONS 10

15 INSPECTION AND TESTING 11

16 FIELD TRIALS 11

17 BULK SUPPLY 11

18 WARRANTY 11

19 LITERATURE AND MAINTENANCE INSTRUCTINS 11

20 GOVERNOR TESTING AND CALIBRATION FACILITIES 12

21 INFRASTRUCTURE 12

22 TRAINING 13

23 MAINTENANCE SPARES 13

24 QUALITY ASSURANCE PLAN (QAP) 13

25 VENDOR CHANGES IN APPROVED STATUS 13

26 UNDERTAKING BY EQUIPMENT MANUFACTURER 13

27 DECLARATION OF CONFIDENTIALITY OF SUBMITTED DOCUMENTS BY MANUFACTURERS

14

28 PREFERENCE TO MAKE IN INDIA 14

List of Annexures

Annexure no. Description Page no.

Annexure-1 Fuel Limit Table 15

Annexure-2 Layout of cutout for mounting controller unit in the short hood side wall of driver’s cab

16

Annexure-3 & 4 Input & output cable details of MCBG 17-18

Annexure-5 Methodology for inspection and testing of MCBG 19-27

Reference: MP.TP-15 (PERFORMANCE TEST PROCEDURE AND ACCEPTANCE

CRITERIA FOR MICRO CONTROLLER BASED GOVERNOR)

Page 6: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued: 23/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 3 of 28

MICRO CONTROLLER BASED GOVERNOR (MCBG) FOR APPLICATION ON MICROPROCESSOR CONTROLLED

ALCO/DLW 6 CYLINDER 251 SERIES WDS6 D-E LOCOMOTIVES 1. INTRODUCTION:

The Function of the MCBG is notch wise speed control of the Engine and load control and provides other safety feature for satisfactory performance of Engine. 2. SCOPE OF SPECIFICATION:

This specification covers the technical requirements and general features of MCBG for ALCO/DLW 6 cylinder 251 series diesel engine fitted on microprocessor controlled WDS6 locomotives on new built or fitment on old locomotives. 3. SCOPE OF SUPPLY:

The deliverables to this specification for MCBG shall include:

i. Controller cum display unit ii. Actuator unit iii. Interconnecting cables with connectors as per Annexure-3 and 4. iv. Engine Speed Sensor with mounting bracket and interconnecting cables with

connector (Optional): If MCBG is compatible with Microprocessor based loco controller this item is not required. The Engine Speed signal from Micro Processor system is in the form of square wave and frequency output signal (No. of Teeth x RPM x Gear ratio) /60 and amplitude of 12 Volts. The interfacing of this Engine Speed signal to MCBG is Open collector NPN transistor, maximum 20mA with galvanic isolation.

v. Kit for fitment of the controller unit. 4. BASIC FUNCTIONS: 4.1 Speed Control: The MCBG shall maintain eight engine speed steps commonly, called notches based on input from throttle handle position which generates 4 digital outputs in a particular sequence as shown in as inputs to MCBG. The notch position, corresponding energized wire numbers and engine speed to be maintained is listed in the Table-1. It shall have provision of facility to alter any notch speed, if so required from fuel economy or engine performance considerations. Dropout voltage of relays if provided, at notch input signals should be within 15-18 Volts & pickup Voltage should be above 30 Volts.

Page 7: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued: 23/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 4 of 28

TABLE-1

NOTCH POSITION

WIRES ENERGISED ENGINE SPEED (RPM)

SHUTDOWN 3A 0

Low Idle 15A, 3A 350

Idle/1 - 400

2 15A 500

3 7C 600

4 15A, 7C 700

5 12A, 7C, 3A 800

6 15A, 12A, 7C, 3A 900

7 12A, 7C 1000

8 15A, 12A, 7C 1100

4.2 Speed Stability: MCBG is required to maintain stable engine speed i.e. free from hunting at each notch position in both conditions - with or without load. 4.3 Governor Response: Time taken for speed adjustment from IDLE to FULL speed shall be of the order of 15-20 seconds. For intermediate notch positions, the time taken to adjust engine rpm shall be in the same proportion. 4.4 Load Control: The resistance of the Load Control Rheostat (LCR) resistor or its equivalent for interfacing with microprocessor based control system to latest version of RDSO specification shall be 30.5 ohms. LCP output voltage from MCBG to excitation system shall be 24.4-68.8 VDC for locomotive with microprocessor control system. The characteristics of existing LCR on hydraulic governor are as under:

LCR CHRACTERISTICS

Wiring Lugs Number of Steps Ohms per Step Ohms per Group

1-11 10 0.178 1.78

11-18 7 0.272 1.90

18-21 3 0.272 0.82

21-26 5 0.40 2.00

26-31 5 0.56 2.80

31-36 5 0.72 3.60

36-41 5 0.82 4.10

41-46 5 0.90 4.50

46-54 8 1.125 9.00

Total 30.50

Page 8: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued: 23/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 5 of 28

Rating: Voltage.............................. 72 + 1 V DC Current range..................... 1.75 Amp. Tolerance on resistance value of LCR: Each section + 10% (1-18), (18-36), (36-54) 4.4.1 Load Control Timing: * Load control timing from max. to min. field position change shall be 8.5-11 sec. * Load control timing from min. to max. field position change shall be 25-35 sec. 5. AUXILIARY FEATURES: The MCBG offered shall cater for the following auxiliary features:- 5.1 Air Manifold Pressure Bias Fuel Limiter: The MCBG shall regulate the movement of fuel control shaft as a function of absolute air manifold pressure (boost air pressure). The MCBG shall satisfy the load limit requirements indicated in “Fuel Limit Table” placed as Annexure-1. The system shall however, have the facility of fuel limit adjustment to any other fuel limit curve, if required.The signal for boost air shall be taken from Locomotive Microprocessor control system. In case of no BAP signal to MCBG shall bypass manifold air pressure bias fuel limiting feature and the event shall get recorded in the error log of MCBG and a message stating `fuel limit feature by passed' shall appear on the display. A switch shall be available on the front panel of MCBG to manually bypass the manifold air pressure bias fuel-limiting feature in case erroneous input BAP reading due to some fault. 5.1.1 Boost air pressure (BAP) transducer: Requirements for boost air pressure transducer will be: Working range: 0 to 5 kg/cm2 gauge Temperature of boost air: 1200C max. 5.2 Engine Over Speed Trip Facility: MCBG shall shut down the engine in the event of engine rpm increase beyond a 1241-1250 RPM. 5.2.1 Mechanical and Electronic Engine Over Speed Trip-Test Facility: MCBG shall have facility to slowly increase the engine speed above its rated speed for checking the setting of the mechanical over speed trip mechanism over speed trip function of MCBG. It shall be possible to easily revert back to the normal setting of engine speeds.

Page 9: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued: 23/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 6 of 28

5.3 Status Display of Engine Parameters:

An industrial robust display shall be provided on the controller unit. The display shall be such that it is clearly visible under day and night conditions from a distance of 2 metres. USB port: (Specification 1.1. Device using Type B connection)

Vibration: Operational 5 to 8 Hz, 0.8"(p-p), 8 to 500 Hz, in X,Y,Z direction, duration: 1hour, 3g

Shock: Operational 40g, 9 msec in 3 directions. The display shall either be a) A bluish green vacuum fluorescent display (VFD) with four lines of 20 characters of 5 mm each. or b) Graphic colour LCD operator interface terminal with QVGA display and touch screen to the following specification • Typical power 8W • Battery: Lithium coin cell. Typical lifetime of 10 years • LCD Display:

Size/Type 5.7 inch/STN

Colours/ Pixels 256/320X240

Brightness/ Backlight 165 cd/m2/20,000 hr typ.

• 5-key keypad: for on-screen menus, Resistive analog touchscreen. On board user memory: 4 MB non-volatile flash memory The display shall be in the format given below: LOP (kg/cm2) FOP (kg/cm2) BAP (kg/cm2)

L . L F . F B . B

N S S S S R R . R H H : M M

NOTCH ENGINE FUEL LCP (hrs:minutes) SPEED (rpm) RACK (mm) 5.4 Fuel Oil Pressure (FOP) Transducer: Requirements of fuel oil pressure transducer will be as under: Working range: 0 to 5 Kg/cm2 gauge Temperature of fuel oil: 55ºC max. 5.5 Lube Oil Pressure (LOP) Transducer: Requirements of lube oil pressure transducer will be as under: Working range: 0 to 10 kg/cm2 gauge Temperature of engine lubricating oil: 125º C max.

Page 10: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued: 23/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 7 of 28

6. SAFETY FEATURES/DEVICES: Provision shall be kept for the following safety features/devices in the MCBG being offered. 6.1 Low Lube Oil Pressure Shut-Down (LOPS): A safety feature to protect the engine in the event of low lube oil pressure shall be provided to shut down the engine, whenever the lube oil pressure falls below the following stipulated limits:

Notch Engine low LOP settings (kg/sq. cm)

Low Idle 1.1 1.1

Idle/1 1.3 1.3

2 1.5

3 1.9

4 2.3

5 2.8

6 3.2

7 3.7

8 4.1

LOPS setting values are tentative and shall be user settable. It shall be possible to delay the operation of this device at each notch position. The governor shall also have a provision of adjustment of the LOPS setting values independently at each notch position. 6.1.1 Time Delay Feature: A time delay of 40-45 seconds shall be provided in low oil pressure shutdown system at idle/notch-1 speed steps to enable the engine driven lube oil pump to build up the requisite lube oil system pressure while starting the engine. It shall be possible to provide time delay facility at other notches as well. This time delay can be different for different notches. A manual button, which would have to be reset after an LOPS shutdown has occurred must be provided. 6.2 Fail-safe Feature: The MCBG shall be provided with fail-safe feature so as to cause shut-down of the diesel engine by pulling the fuel racks to “NO FUEL” position in case of malfunctioning of the governing equipment. 6.3 Multiple Unit (MU) Operation: All WDS6 locomotives provided with MCBG shall be capable of working in single Unit (SU) and Multiple Unit(MU) consist upto 4 locomotives with existing WDS6 equipped with Woodward or micro controller based governors of any make.

Page 11: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued: 23/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 8 of 28

7. DIAGNOSTIC AND FAULT LOGGING SYSTEM: 7.1 The MCBG offered shall include suitable fault diagnostic facility to carry out troubleshooting and to assist maintenance personal in the rectification of the defect/ defects. 7.2 Suitable memory to register fault messages with date and time stamp and their retrieval on a laptop personal computer shall be provided. A facility shall be provided to set the current date and time in the MCBG. 7.3 Recording of time spent on each notch for 24 hours shall be made. The sampling interval should not be more than one second. This is required for calculation of load factor of locomotives. For this purpose eight counters shall be provided in MCBG memory for cumulative time spent on each notch in seconds. There should be a provision to read these counters through a laptop personal computer any time to get the cumulative time spent on each of the 8 notches. All these counters should be capable of being reset to zero, at any time, through a laptop personal computer. 8. ADJUSTMENT OF VARIOUS ENGINE PARAMETERS: A simple arrangement shall be provided in the software to adjust the following parameters on the locomotive.

i. Notch wise engine speed ii. Notch wise minimum lube oil pressure for loco shut down. iii. Maximum permissible fuel rack at each notch. iv. Maximum permissible fuel rack in relation to boost air pressure v. Over speed trip setting vi. Gov. response vii. Load control timing from max to min. field position of LCP etc.& min. to max.

field position of LCP etc. viii. PID parameters These adjustments should be possible with a laptop personal computer running in windows environment. A provision shall be made to restrict accessibility to gov. adjustments to avoid misuse. 8.1 Software: Necessary software for adjusting the user settable parameters of the MCBG shall be provided. 9. GOVERNOR OUTPUT SHAFT AND LINKAGE: 9.1 Stroke: The governor output shaft travel shall be of a rotary or linear type. The linkages shall be designed such that the fuel racks have a max travel of 34 mm (approx.). 9.2 Work Capacity: The work capacity of the governor output shaft for actuation of fuel control shaft shall be at least 16.3 Nm (12 ft lb).

Page 12: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued: 23/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 9 of 28

10. MOUNTING ARRANGEMENT: 10.1 Controller and display unit: The dimensions of the electronic controller unit will not exceed 328mm(frontal width including hinges) x 465mm (frontal height including flanges for mounting) x225mm (depth into the nose compartment) and shall not project in the cab more than 70 mm. A cut out of the size 320mm (width) x 403 mm (height) along with 4 holes as shown in the RDSO drawing no. SK.DP-3649, Alt. 2 (Annexure 2) in the short hood sidewall of the driver’s cab will be made available to the supplier for mounting controller and display unit. The controller and display unit shall be designed for front-loading i.e. mounting from the short hood side wall of the driver’s cab. The supplier shall also supply a fitment kit including the beading, brackets for supporting weight etc. Connectors no. MS3102R-20-29-P+GP, MS3102R-12SP-10P+GP, MS3102R-20-27-P+GP and MS3102R-20-16-P+GP shall be fitted on the controller and display unit. The weight of the controller unit shall not be more than 30 kg. The fitment drawing of the controller unit shall be given by the supplier. 10.2 Actuator unit: The actuator along with base will be mounted on the engine block. The dimensions of the actuator shall not exceed 269 mm (frontal width) x 442mm x 508mm (height). Its weight shall not exceed 60 kg. The bottom face of actuator unit shall be designed to match governor base to DLW Part No. 10050796. LOP, FOP and BAP transducers, connectors no. MS 3102R-20-16-P+GP and MS 3102R-20-27-P+GP shall be fitted on the actuator unit. 10.3 Numbering: Each actuator and control unit shall contain a number plate indicating (a) Serial number (b) Date of manufacturing (c) Name of manufacturer (d) Model number. The major subassemblies going into each unit should also be numbered and recorded with the supplier for future reference. 11. CONNECTORS: 11.1 Connection scheme of connectors at the cable ends: All the connectors at the cable ends shall have one to one connection. 11.2 Connection scheme of connectors for carrying signals from the locomotive to the MCBG: MS3102R-20-29-P+GP (17 pins)

Connector Pin Loco Signal

A 15A

B 12A

C 7C

D 3A

E 43D/43E

F 29A

Page 13: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued: 23/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 10 of 28

G 50

H 4

MS3102R-12SP-10P+GP

Connector Pin Signal

A ESS signal 1

B GND

C Spare

D ESS signal 2

12. CABLES: 12.1 Specification: 1) Insulation grade: EE (1000VAC,RMS) 2) Inner insulation: PTFE 3) Outer insulation: FRLS (Fire retarded low smoke) 4) Inner conductors: Tin plated copper 5) Shield: Wire mesh with 85% coverage (min) 6) Wire size (no of strands in cores): 15(19/28)AWG-(1.5 mm²) 7) No. of twists per meter per pair: 30 nos. min. 8) Capacitance between conductors in a pair: 20 pF per foot max. 9) Dielectric strength 2.5 kVAC, 50 Hz H.V. for 1 min. between cores, core and shield and shield and outer insulation. 13 POWER SUPPLY: The MCBG shall be suitable to work with power supply available on the locomotive as per details given below: BATTERY VOLTAGE: 64 to 50 V DC REGULATED: 72 + 1V DC (Aux. Generator) MINIMUM: During cranking the engine battery voltage may drop to

around 22 V DC for about 0.8 second. 14. SERVICE CONDITIONS: The equipment offered shall be capable of working satisfactorily up to an altitude of 1000 meters above mean sea level, ambient temperature 0 to 55 deg.C (the air temperature inside the engine compartment may reach up to 70 deg.C.), relative humidity up to 95 %. The equipment shall be capable of working satisfactorily in spite of dust, mist, rains, heavy sand storms, presence of oil vapours and radiant heat etc., to which rolling stock is normally exposed in service. The equipment shall be designed to withstand, without damage, vibrations and shock encountered in loco.

Page 14: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued: 23/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 11 of 28

15. INSPECTION AND TESTING: Refer to Annexure-5. 16. FIELD TRIALS: After successful completion of type tests, required nos. of the equipment shall be

subjected to field trials for specified time period. The Quantity and Period for field

trials shall be governed by RDSO Document no. MP-M-8.1-1. Feedback shall be

furnished by User Railways as per prescribed format as follows:

S.

N.

Loco

No./Type

MCBG

make

Date of

commissionin

g of MCBG

Date of

failure (if

failed)

Date of

rectification (if

failed)

Feedback/Remark

incl. comments on

issues related to

actuator/control units etc., if

any.

1.

2.

3.

During this period, the performance of governor shall be closely monitored and

evaluated by RDSO for:

Operational performance.

Reliability in service under actual environmental operating conditions.

Practical evaluation of maintainability/accessibility of components.

Modifications found necessary as a result of the tests and trials shall be carried out

by the vendor at his own cost, after the relevant modifications have been approved

by RDSO. The duration of field trials can be increased or curtailed at the discretion of

RDSO.

17. BULK SUPPLY: Field trials clearance as applicable for new sources as per RDSO Document no.

MP-M-8.1-1 is prerequisite for bulk supply unless otherwise not specified.

18. WARRANTY: The supplier shall provide a warranty for the satisfactory performance for a period of 2 years for all the components of the governor from the date of commissioning. 19. LITERATURE AND MAINTENANCE INSTRUCTIONS: The supplier shall supply sufficient copies of operating instructions, maintenance manual with methods of adjustments and calibration, manufacturing/installation drawings and troubleshooting manual for the complete governor.

Page 15: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued: 23/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 12 of 28

20. GOVERNOR TESTING AND CALIBRATION FACILITIES: Detailed procedure for overhauling and subsequent testing/calibration shall be specified by the supplier. Periodicity of schedule maintenance shall clearly be indicated. It may be noted that governor is required to give trouble free service for a period of 4 years without any maintenance. 21. INFRASTRUCTURE: The supplier shall have:

i. Dust Free, Air Conditioned and ESD protected environment for PCB Assembly and PCB level Testing.

ii. Component Lead Forming machines / fixtures for PCB Assembly. iii. SMT Assembly Line for SMD components Assembly consisting of Solder

Paste Printer, Automatic Pick and Place Machine and Reflow Soldering Machine.

iv. Temperature Controlled Wave Soldering Machine with Auto Fluxing Facility for Leaded components Soldering.

v. Ultrasonic Cleaning Machine for cleaning of flux residues from PCBs. vi. Customized Test Jigs / Fixtures for PCB level Functional Testing. vii. Digital / Analog IC Testers for Inspection of the Incoming material. viii. Dual Channel, 200MHz Digital Storage Oscilloscope ix. 5 ½ digit Digital Multimeter. x. Hot and Cold Chamber for Temperature Cycling Test for the PCBs xi. Pressure Pump with Calibrated Digital Pressure Indicator of minimum

accuracy of 0.05 % of Full Scale reading. xii. CNC Lathe and CNC Milling Machines for precision components

manufacturing. xiii. Gear Hobbing Machine with Microscope Attachment. xiv. Check Master – Gear Rolling Tester with Accessories, for Inspection of

Gears. xv. Digital Vernier Calipers, 0-300mm, LC0.01mm xvi. Vernier Height Gauge, 0-1000mm, L.C.0.02mm xvii. Flange Micrometer 0-25mm, 75-100mm, 100-125mm L.C. 0.01mm xviii. Test Equipment for measuring Plating, Painting and Powder Coating

Thickness. xix. Special Assembly Rig for Assembly of Rack and Pinion Box and Gear Box. xx. Custom Built Test Rig for Functional Testing of the complete MCBG System.

xxi. Custom Built Test Rig for measuring the work capacity of the Actuator Unit.

xxii. Engine Test Bed for simulated functional testing of all the functions of MCBG

in close loop in load and no load condition with speed measurement facility

through tacho generator as well as hall effect type speed sensor.

xxiii. All India service network to ensure action within 12 hours on any problem

reported by user railway.

xxiv. Permanently employed mechanical, electrical and electronics engineers with

not less than 5 years’ experience in their respective fields like electrical,

mechanical, electrical and electronics design, machine shop, fabrication etc.

Page 16: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued: 23/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 13 of 28

22. TRAINING:

The supplier of the MCBG shall impart necessary on-site training to the relevant

railway personnel, about the assembly, installation, operation, maintenance, setting

of user settable parameters and troubleshooting of the MCBG.

23. MAINTENANCE SPARES:

The supplier is also expected to supply spares, tools, testing and calibration

equipment, jigs and fixtures, which will be required for maintenance and

adjustments. The supplier shall ensure continuous availability of spares for

maintenance of the governors. Adequate warning shall be given to the purchasers

and RDSO in case some spares are at the verge of becoming obsolete and

unavailable.

24. QUALITY ASSURANCE PLAN (QAP):

A quality assurance plan (QAP) that outlines the suppliers’ quality assurance in order

to obtain a quality product shall be submitted to RDSO for approval. The QAP shall

be prepared on the lines as indicated in ISO: 9001:2000.

25. VENDOR CHANGES IN APPROVED STATUS: All the provisions contained in RDSO’s ISO procedures laid down in document no. QO-D-8.1-11, Revision latest (titled: “Vendor changes in approved status”) and subsequent versions/amendments thereof, shall be binding and applicable on the successful vendor/ vendors in the contract floated by Railways to maintain quality of products supplied to Railways.

26. UNDERTAKING BY EQUIPMENT MANUFACTURER

Vendor shall provide a signed copy of the undertaking on “INFRINGEMENT OF PATENT RIGHTS”. The undertaking shall be as under:

Indian Railways shall not be responsible for infringement of patent rights arising due to similarity in design, manufacturing process, use of similar components in the design & development of this item and any other factor not mentioned herein which may cause such a dispute. The entire responsibility to settle any such disputes/matters lies with the manufacturer/ supplier.

Details / design/documents given by them are not infringing any IPR and they are responsible in absolute and full measure instead of railways for any such violations. Data, specifications and other IP as generated out of interaction with railways shall not be unilaterally used without the consent of RDSO and right of Railways / RDSO on such IP is acceptable to them.

Page 17: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued: 23/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 14 of 28

27. DECLARATION OF CONFIDENTIALITY OF SUBMITTED DOCUMENTS BY MANUFACTURERS

While submitting a new proposal/design, manufacturer must classify their documents confidentiality declaration, such as

This document and its contents are the property of M/s XYZ(Name of the vendor) or its subsidiaries. This document contains confidential proprietary information. The reproduction, distribution, utilization or the communication of this document or any part thereof, without express authorization is strictly prohibited. Offenders will be held liable for the payment of damages. Indian Railways/RDSO is granted right to use, copy and distribute this document for the use of inspection, operation, maintenance and repair etc.

28. PREFERENCE TO MAKE IN INDIA

The Government of India policy on “Make in India” shall apply.

XXXXXXXXXXX

Page 18: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued: 23/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 15 of 28

Annexure-1

FUEL LIMIT TABLE

BAP (bar) Fuel rack settings

0 17

0.2 21

0.4 23

0.6 25

0.8 26

1.0 27

1.2 28

1.4 29

1.6 Max.

1.8 Max.

Page 19: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued: 23/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 16 of 28

Annexure-2

Page 20: Specification for Revision - Indian Railways

Annexure-3

INPUT & OUTPUT CABLE BETWEEN MCBG CONTROL UNIT TO LOCO TERMINAL BOARD

SHIELD

Connector type Connector Pin no. Locomotive wire number Length of cable Connector type

MS3108F-20-29S+GP

(17 PIN)

A 15A

As per actual requirement

(10 core)

Loco TB

B 12A

C 7C

D 3A

E 43D/43E

F 29A

G 50

H 4

CABLE BETWEEN MCBG CONTROL UNIT AND ACTUATOR UNIT Two nos.

Connector type Length of cable Connector type

MS3108F-20-27S+GP (14 PIN)

As per actual requirement (14 core)

MS3108F-20-27S+GP (14 PIN)

Connector type Length of cable Connector type

MS3108F-20-16S+GP (9 PIN)

As per actual requirement (9 core)

MS3108F-20-16S+GP (9 PIN)

Page 21: Specification for Revision - Indian Railways

Annexure-4

ENGINE SPEED SIGNAL CABLE BETWEEN MCBG CONTROL UNIT AND MCBG INTERFACE OF MICROPROCESSOR

CONTROL SYSTEM

Connector type Connector Pin no. Signal Length of cable Connector type

MS3108F-12SP-10S +GP

(4 pin)

MCBG side

A ESS signal 1 As per actual requirement

(4 core)

MS3106F-16-9PX

(4 pin)

(MCBG interface side)

B GND

C Spare

D ESS signal 2

Page 22: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued 01/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 19 of 28

Annexure-5

METHODOLOGY FOR INSPECTION AND TESTING OF MCBG

Inspection and testing of the equipment to be supplied by the supplier will be carried out

in the following stages.

The supplier will provide without any extra charge, the material equipment, tools and

any other assistance which the purchaser or his nominee may consider necessary for

any test and examination which he or his nominee shall require to conduct at the

supplier’s premises and will pay all costs attendant to them.

A. Type Test Plan for Micro Controller Based Governor

(i) Following table summarizes the type test of the equipment/system as per IEC 60571(Latest)

or its equivalent to BIS:

S. No Standard Test Name Test Location Test Result/Re

marks

1.

IEC 60571 - 12.2.2 or IS equivalent

Visual Inspection At firm’s premises/NABL Labs

Pass/Fail

2. IEC 60571- 12.2.10.2 or IS equivalent

Insulation Measurement Test

At firm’s

premises/NABL Labs

Pass/Fail

3. IEC 60571 - 12.2.10.3 or IS equivalent

Voltage Withstand Test At firm’s

premises/NABL Labs

Pass/Fail

4. IEC 60571 - 7.2.6 or IS equivalent

Reverse Polarity Test At firm’s

premises/NABL Labs

Pass/Fail

5. IEC 60571 - 5.1.1.2 or IS equivalent

Voltage Variation Test At firm’s

premises/NABL Labs

Pass/Fail

Page 23: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued 01/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 20 of 28

S. No Standard Test Name Test Location Test Result/Re

marks

6. IEC 60571 - 12.2.3 or IS equivalent

Performance Test with Simulator

At firm’s

premises/NABL Labs

Pass/Fail

7. IEC 60571 - 12.2.6 or IS equivalent

Damp Heat Test At firm’s

premises/NABL Labs

Pass/Fail

8. IEC 60571 - 12.2.4 or IS equivalent

Cooling Test At firm’s

premises/NABL Labs

Pass/Fail

9. IEC 60571 - 12.2.5 or IS equivalent

Dry Heat Test At firm’s

premises/NABL Labs

Pass/Fail

10. IEC 60571-12.2.8.1 or

IS equivalent

Surge Voltage Test At firm’s

premises/NABL Labs

Pass/Fail

11. IEC 60571 – 12.2.12 & IEC61373-Cat.1-Class-B or IS equivalent

Vibration and Shock Test

At firm’s

premises/NABL Labs

Pass/Fail

12. IEC 60571 - 12.2.8.3 or IS equivalent

Transient Burst Susceptibility Test

At firm’s

premises/NABL Labs

Pass/Fail

13. IEC 60571 - 12.2.9.1 or IS equivalent

Radio Frequency Susceptibility Test

At firm’s

premises/NABL Labs

Pass/Fail

14. IEC 60571 - 12.2.9.2 or IS equivalent

Radio Frequency Emission Test

15. IEC 60571-12.2.11 or IS equivalent

Salt Mist Test At firm’s

premises/NABL Labs

Pass/Fail

16. IEC 60571-12.2.13 or IS equivalent

Water Tightness Test At firm’s

premises/NABL Labs

Pass/Fail

17. IEC 60571-12.2.14 or IS equivalent

Equipment Stress Screening Test

At firm’s

premises/NABL Labs

Pass/Fail

18. IEC 60571-12.2.15 or IS equivalent

Low temperature storage test

At firm’s

premises/NABL Labs

Pass/Fail

Page 24: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued 01/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 21 of 28

1. Visual Inspection as per clause 12.2.2 of IEC 60571

a. Physical Dimensional Check

The Physical dimensions are to be measured and recorded as per the RDSO approved drawing.

b. Equipment Number plate verification:

Equipment number plate is to be verified.

c. Power ON check:

This check is to ensure that the system is working normal when the rated input voltage is

connected to the system.

2. Insulation Measurement test as per clause 12.2.10.2 of IEC 60571

All the Input / Output pins of the unit are to be shorted together. All the Cards are removed from the respective enclosures.

The Insulation Resistance is to be measured with a 500V DC Megger between the body of unit and above pins.

The value should be >100 Mega ohm.

3. Voltage Withstand (Di-Electric) Test as per clause 12.2.10.3 of IEC 60571

All the Input / Output pins of the unit are to be shorted together.

A test voltage of 1000V ac is to be applied by gradually increasing the voltage amplitude to set limit and is to be maintained at that level for 1 min.

Observations

No disruptive discharge or flash over should occur. The system should work satisfactorily.

IR Test after Dielectric Test

Repeat the “Insulation Resistance Test” after the Dielectric test once again and record the Insulation Resistance Values. Values of insulation resistance should not be less than 100 M ohm.

4. Reversal of Polarity as per clause 7.2.6 of IEC 60571

The equipment is to be connected with 72V DC in Reverse Polarity at the Power Supply input terminals and is to be kept in that condition for one minute.

The equipment is then to be connected with normal polarity of 72V DC and status LEDs are to be verified

Observations

There should be no damage to the equipment because of reverse polarity.

Page 25: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued 01/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 22 of 28

The equipment is to be working normally after reverse polarity test.

5. Effect of Voltage Variation Test as per clause 5.1.1.2 of IEC 60571

The equipment is to be connected to a variable DC source with normal polarity and the voltage is to be set to 50V DC, (0.7 times of the rated voltage 72V DC).

Status LEDs are to be verified.

Then the voltage is to be slowly increased and set at 90V DC (1.25 times of the rated voltage 72V DC).

Status LEDs are again to be verified

Finally the voltage is to be set to rated voltage of 72V DC.

Status LEDs are to be verified.

There should be no damage to the equipment or malfunctioning because of voltage variations.

The equipment should work satisfactorily in all above conditions.

6. Performance Test as per clause 12.2.3 of IEC 60571

Performance test or functionality of the system as per clause 4 to clause 10 of this

specification is to be checked by RDSO on Simulator/test bed at the firm’s premises.

7. Damp Heat test as per clause 12.2.6 of IEC 60571

Test to be carried out as per IEC 60068-2-30, Test db. With +55°C as upper temperature limit and 2 cycles of 24 hours.

The equipment is to be placed in the test chamber without powering ON.

A functional performance test is to be carried out at the beginning of second cycle.

After test is completed, equipment is to be allowed to recover to ambient conditions.

An Insulation Measurement and Di-electric Test is to be carried out.

Observations

There should be no damage to the equipment or malfunctioning because of Damp Heat.

The equipment is to work satisfactorily during Damp Heat Test.

The Insulation Resistance is to be measured and value should be >100 M Ohms.

There is to be no disruptive discharge or flash over in the Di-electric test.

8. Cooling start Test as per clause 12.2.4 of IEC 60571

This test is to be carried out in accordance with IEC 60068-2-1

Page 26: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued 01/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 23 of 28

The equipment is to be placed in a cold chamber without any voltage applied condition.

The temperature is to be lowered from ambient to -0±2°C gradually.

Once the temperature in the chamber is stabilized at -0±2°C, the equipment is to be retained in the chamber about 2 hours at that temperature.

The equipment is to be then powered up after approx 5 to 10 minutes.

There should not be any damage to the equipment.

Status LEDs are to be verified.

Observations:

There should be no damage to the equipment because of Cooling start test.

The equipment is to work satisfactorily.

9. Dry Heat test as per clause 12.2.5 of IEC 60571

This test is to be carried out in accordance with IEC60068-2-2,

The equipment is to be connected with 72V DC in normal polarity and placed in a hot chamber.

The temperature is to be raised from ambient to 70±2°C.

Equipment is to be kept in this condition for 6 hours, after stabilization of temperature.

There should not be any damages to the equipment after the test.

Observations:

There should be no damage to the equipment because of Dry Heat Test.

The equipment is to work satisfactorily after the test.

10. Surge Voltage test as per clause 12.2.8.1 of IEC 60571

The surge waveform shall be generated and tested using the generator and waveform as specified in IEC 62236-3-2:2008

Surge Voltage is to be applied at BP and BN pins of working equipment.

Status LEDs are to be verified after the test.

There should not be any damage to the equipment.

Observations:

There should be no damage observed to the equipment because of Surge Voltage Test.

The equipment is to work satisfactorily after the test.

11. Vibration, Shock and bump test as per clause 12.2.12 of IEC 60571

Page 27: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued 01/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 24 of 28

The complete cubicle with its mounting arrangements shall be subjected to the tests indicated in IEC 61373.

There should not be any damages to the equipment after the test.

Observations:

There should be no damage to the equipment because of test.

The equipment is to work satisfactorily after the test.

12. Transient Burst Susceptibility test as per 12.2.8.3 of IEC 60571

Test voltage of 2KV, 5/50 nS, 5KHz as per IEC 62236-3-2:2008 is to be used for testing.

The test is to be carried out in working condition of equipment as per procedure of IEC 61000-4-4.

Observations:

13. There should be no damage to the equipment because of test.

14. The equipment is to work satisfactorily after the test.

15. Radio Frequency Interference Immunity test as per 12.2.9.1 of IEC 60571

Radiated Radio Frequency Interference test and performance with 10V/m (r.m.s) severity as per IEC IEC61000-4-6

The equipment is to be kept energized during the test.

Observations:

For conducted disturbances induced by radio frequencies fields, refer to IEC 62236-3-2:2008 (Table 7 and Table 8).

For radiated disturbances induced by radio frequencies fields, refer to IEC 62236-3-2:2008 (Table 9).

16. Radio Frequency Interference Emission test as per 12.2.9.2 of IEC 60571

Radio Frequency Interference emission test and performance as per IEC IEC62236-3-2:2008

The equipments is to be kept energized during the test.

The test shall be carried out at ETDC/NABL Lab.

Observations:

The equipment shall be tested to the requirements as specified in IEC 62236-3-2:2008 (Table 3,

Table 4, Table 5, and Table 6).

Page 28: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued 01/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 25 of 28

17. Salt Mist Test as per IEC 60571-12.2.11

Salt solution

The solution for producing the salt mist shall be prepared by dissolving (50 ± 1) g sodium chloride (NaCl) analytical reagent quality, in distilled or demineralised water to make up(1 ± 0,02) l of final solution at 20 °C; if the pH does not lie between 6,5 and 7,2, the solution shall be rejected.

Test procedure

During the test, the temperature in the test chamber shall be maintained at (35 ± 2) °C.

The solution and the air used to produce the salt mist shall have a temperature equal to that of the test chamber.

The equipment should be tested in the manner in which they are expected to be used, i.e. protective covers should be in position and the equipment arranged, as nearly as possible, in the position it would occupy in actual use.

The test chamber shall be kept closed and spraying of the salt solution shall continue without interruption during the whole conditioning period.

The period shall be:

– for class ST2: 16 h;

At the end of the test, the equipment shall be washed in running tap water for 5 min, rinsed in distilled or demineralised water, then dried to remove droplets of water and stored under standard atmospheric conditions of the testing area for not less than 1 h, no more than 2 h.

After that, the equipment is to be subjected to a visual examination.

Observations:

There should be no major damage

A performance check shall not show any failure or damage nor any results which are beyond the specified tolerances.

18. Water tightness test as per IEC 60571-12.2.13

As electronic equipment is generally mounted either inside the body of the vehicle or in boxes outside, there is no need to carry out water tightness tests, apart from exceptional cases which is to be defined between user and manufacturer.

19. Equipment stress screening test as per IEC 60571-12.2.14

A screening procedure to be applied to completed equipment or a part of it, for the purpose of eliminating dormant manufacturing or component defects.

Burn-in test

Page 29: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued 01/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 26 of 28

After mounting of components, the populated PCB cards kept in proper chassis in energized

condition shall be burnt in for minimum 45 hrs at +70 deg. C and - 25 deg C as per the cycle at

figure above, wherever specified in the main specification. The PCBs will be tested for

functionality to the extent possible during the burn-in test. This will be mutually decided.

20. Low temperature storage test as per IEC 60571-12.2.15

This test shall be in accordance with IEC 60068-2-1.

The temperature value for the test shall be –40 °C and the time period shall be 16 h minimum.

After recovery, a performance check shall be carried out at ambient temperature.

Observations:

No damage shall occur,

The functional check should not show any failure or any results beyond the specified tolerances.

(ii) Functional test:

These tests will be carried out under simulated conditions at supplier’s premises to establish that the governor is functioning as per the specification. The detailed functional test plan may vary from vendor to vendor based on their design. Hence, vendor shall submit the detailed functional test plan as per their design meeting the functional requirement of the specification for approval by RDSO before prototype test. RDSO Document no. MP-TP-15 may be referred for

Page 30: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued 01/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 27 of 28

guidance. On satisfactory completion of environmental and functional tests, the prototypes will be subjected to Loco Validation tests.

(iii) Loco Validation test

After successful prototype test as given above, the prototype shall be subjected to loco validation test which includes load box test, checking of functional test, Route run trials, MU Test, etc. Functional test of the MCBG should be carried out to verify the functional requirements of the specification stated at Clause 4 to 10. The detailed functional test plan may vary from vendor to vendor based on their design. Hence, vendor shall submit the detailed functional test plan as per their design meeting the functional requirement of the specification for approval by RDSO before prototype test. Loco validation test will consist of following:

The maximum instantaneous variation in engine speed expressed as percentage of rated speed, after sudden variation of load from the rated value to zero must not exceed 10% of the rated speed.

Possible faults will be created to test the fail safe features of the governor (to be listed out by the supplier and got approved by RDSO).

On satisfactory completion of the performance tests, the MCBG will be cleared by the inspecting

authority for field trials.

B. Acceptance Test Plan

This test is to be conducted for the system other than prototype for purchase inspection. This is the subset of type test mentioned above. Following test is required to be conducted for Acceptance test plan. The sampling plan as per IS: 2500, Pt.I, General Inspection Level-II should be adopted for selecting the samples against the lot and determining the acceptance/rejection of lot based on Acceptance test result.

S. No Standard Test Name Test Location Test Result/Re

marks

1. IEC 60571 - 12.2.2 or IS equivalent

Visual Inspection At firm’s premises/NABL Labs

Pass/Fail

2. IEC 60571 - 12.2.10.2 or IS equivalent

Insulation Measurement Test

At firm’s

premises/NABL Labs

Pass/Fail

3. IEC 60571 - 12.2.10.3 or IS equivalent

Voltage Withstand Test At firm’s

premises/NABL Labs

Pass/Fail

4. IEC 60571 - 7.2.6 or IS equivalent

Reverse Polarity Test At firm’s

premises/NABL Labs

Pass/Fail

Page 31: Specification for Revision - Indian Railways

Document No: MP.0.1700.04 Revision No: 01-Draft Date Issued 01/10/2020

Specification Title: Micro Controller Based Governor (MCBG) for application on Microprocessor Controlled ALCo/DLW 6 Cylinder 251 Series WDS6 D-E locomotives

INDIAN RAILWAYS, RESEARCH DESIGNS & STANDARDS ORGANIZATION

Page 28 of 28

S. No Standard Test Name Test Location Test Result/Re

marks

5. IEC 60571 - 5.1.1.2 or IS equivalent

Voltage Variation Test At firm’s

premises/NABL Labs

Pass/Fail

6. IEC 60571 - 12.2.3 or IS equivalent

Performance Test with Simulator

At firm’s

premises/NABL Labs

Pass/Fail

Note: The Test plan given above is the minimum requirement and strictly governed by IEC 60571. The latest edition of IEC 60571 shall apply mutatis mutandis to this Test plan. The test other than above as specified may also be considered with mutual agreement between vendor and Vendor approving authority, if desired so.

.

Acceptance Criteria for functional test

Ability to maintain desired engine speed at each notch within specified tolerance of ± 3rpm with or without load. Yes/No

Ability to maintain desired engine speed without speed fluctuations i.e. free from hunting at each notch with or without load. Yes/No

Ability to maintain constant engine power output at each notch. Yes/No

Ability to actuate the fuel control mechanism for rack movement in either direction to regulate fuel supply. Yes/No

Ability to maintain temporary speed change within 10% of the rated speed after sudden removal of rated load. Yes/No

Ability to regulate fuel supply as a function of air manifold pressure (i.e, proper functioning of air manifold pressure bias fuel limiting feature) for optimum combustion. This will be judged from the opacity/colour of the exhaust smoke during rapid notching up of engine speed at the time of load box testing. Yes/No

Proper functioning of safety devices. Yes/No Note : Functional tests will be carried out under simulated conditions at supplier’s premises to establish that the governor is functioning as per the specification. The detailed functional test plan may vary from vendor to vendor based on their design. Hence, vendor shall submit the detailed functional test plan as per their design meeting the functional requirement of the specification for approval by RDSO. RDSO Document no. MP-TP-15 may be referred for guidance.

Page 32: Specification for Revision - Indian Railways

(for official use only) (dsoy ljdkjh iz;ksx gsrq)

Hkkjr ljdkj jsy ea=ky;

GOVERNMENT OF INDIA MINISTRY OF RAILWAYS

PERFORMANCE TEST PROCEDURE AND ACCEPTANCE CRITERIA

FOR MICRO CONTROLLER BASED GOVERNOR ( WDM2, WDM2C, WDG2, WDP2 )

No. MP. TP-15

SEPTEMBER 2000 (REVISION- 0.00)

.

vuqla/kku vfHkdYi ,oa ekud laxBu ekud uxj] y[kuÅ - 226 011

RESEARCH DESIGNS & STANDARDS ORGANISATION MANAK NAGAR, LUCKNOW-226 011

PERFORMANCE TEST PROCEDURE FOR MICROCONTROLLER BASED GOVERNOR

Page 33: Specification for Revision - Indian Railways

The performance of the microcontroller based governor shall be checked at DLW/DCW in two stages (i) Engine test stage (ii) Loco test stage. I. ENGINE TEST STAGE: To ascertain and evaluate the performance of the micro controller based governor, various parameters shall be checked and recorded as under: 1. Dry Run Test :

Rack travel: ----------------- mm

2. Cranking Test:

Time for starting the engine from stationary condition to idle rpm: ------------------ sec

Max. rack travel during cranking: ----------------- mm

3. Normal shutdown Test: Shuts down/not 4. Notch Speed /Stability (No load):

Engine rpm Nominal Actual

Hunting + rpm

Rack LCR Notch

WDM2 WDM2C WDG2 WDP2

IDLE 350 350 1 350 350 2 443 450 3 536 550 4 629 650 5 722 750 6 815 850 7 908 950 8 1000 1050

5. Over Speed Trip Test:

(i) Over speed trip setting of mechanical device

WDM2 (Nominal 1130+20rpm. Aim at 1130 rpm)

WDM2C/WDG2/WDP2 (Nominal 1180 + 20rpm. Aim at 1180 rpm) ------------------ rpm

(ii) Over speed trip setting of built in feature of the micro

1 controller based governor

Page 34: Specification for Revision - Indian Railways

(10 rpm below mechanical OST setting) -------------------rpm

Note : For testing the over speed trip setting, there shall be provision for freezing the maximum rpm attained during the test on the digital display unit of the governor

6. Engine Performance Test (Load test): Ambient temperature: _________°C

Engine rpm

Nominal Actual

Hunt ing

+ rpm

Rack LCR LOP BAP Water temp.

Vx I GHP Notch

WDM2

WDM2C WDG2 WDP2

IDLE 350 350 1 350 350 2 443 450 3 536 550 4 629 650 5 722 750 6 815 850 7 908 950 8 1000 1050

7. Lube oil pressure during sudden notching down from full load to idle with water at 90 °C:

Min. pressure ---------------kg/cm² Min. engine rpm -----------------rpm Stabilised pressure --------------kg/cm²

8. Exhaust Appearance:

During rapid notching up: Clear/Hazy/Black 9. Temporary speed change test:

The maximum instantaneous variation in engine speed expressed as percentage of rated speed, after sudden variation of load from the rated value to zero:

Max. Speed - Rated speed

Temporary speed change = ------------------------------------ x 100 Rated speed

In order to measure the temporary speed change of engine under the control the governor, the variation of speed after sudden removal of rated load is measured, the engine having previously attained steady operating condition. At rated speed and for the sudden removal of the rated load this temporary speed change must not exceed 10% of the rated speed.

Temporary speed change: --------------rpm

----------------%

2

Page 35: Specification for Revision - Indian Railways

10. Fail Safe Features test:

Possible faults will be created to test the fail safe features of the governor (to be listed out by the supplier and got approved by RDSO).

11. Specific Fuel Consumption (SFC): --------------gm/GHP hr II. LOCO TEST STAGE: At loco test stage also, all the above parameters with the exception of sfc shall be measured and recorded as under: 1. Dry Run Test:

Rack travel: --------------mm 2. Cranking Test:

Time for starting the engine from stationary condition to idle rpm: --------------sec

Max rack travel during cranking -------------mm 3. Shutdown Test:

(i) With STOP push button: Shuts down/not

(ii)With MUSD switch: Shuts down/not 4. Notch Speed/Stability:

Engine rpm Nominal Actual

Hunting + rpm

Rack LCR Notch

WDM2 WDM2C WDG2 WDP2

IDLE 350 350 1 350 350 2 443 450 3 536 550 4 629 650 5 722 750 6 815 850 7 908 950 8 1000 1050

5. Over Speed Trip Test:

(i) Over speed trip setting of mechanical device

3

Page 36: Specification for Revision - Indian Railways

WDM2 (Nominal 1130+20rpm. Aim at 1130 rpm)

WDM2C/WDG2/WDP2 (Nominal 1180 + 20rpm. Aim at 1180 rpm) ------------------ rpm

(ii) Over speed trip setting of built in feature of the micro

controller based governor (10 rpm below mechanical OST setting) -------------------rpm

(iii)Check operation of reset switch for OST. ok/not

Note : For testing the over speed trip setting, there shall be provision for freezing the maximum

rpm attained during the test on the digital display unit of the governor. 6. Governor Response:

Check time taken for speed adjustment from: (i) Idle to Full speed

(Nominal 15-20 sec) -----------------sec

(ii) Full to Idle speed (Nominal 8-12 Sec) -----------------sec 7. Load Control Rheostat (LCR): 7.1 LCR operation: Operate the engine at 8th notch with full load, and full rack stop nut adjusted to

hold the rack position around 21-22 mm. The LCR must operate to reduce excitation. LCR Operates/not 7.2 Check load control timing from:

(i) Max. to min. field position: (Nominal 8.5-11 sec) ------------------sec

(ii) Min. to max. Field position: (Nominal.25-30 sec) ------------------sec

8. Engine Performance Test :

Ambient temperature:---------------º C

Notch Engine rpm Hunt Rack LCR LOP BAP Water Vx I GHP

4

Page 37: Specification for Revision - Indian Railways

Nominal Actual ing +

rpm

temp.

WDM2 WDM2CWDG2 WDP2

IDLE 350 350 1 350 350 2 443 450 3 536 550 4 629 650 5 722 750 6 815 850 7 908 950 8 1000 1050

9. Lube oil pressure during sudden notching down from full load to idle with water at 90 º C: Min. pressure -------------kg/cm2

Min. engine rpm ----------------rpm Stabilised pressure -------------kg/cm2

10. Exhaust Appearance: During rapid notching up: Clear / Hazy / Black 11. Dynamic Braking Test :

(i) With ECS at “run”, throttle at “idle” and reverser handle in “forward” or “reverse” position, movement of selector handle to big “B” position should raise the engine speed to 4th notch rpm.

Confirm: Yes / No

(ii) Engine should shutdown through stop push button both in motoring or in dynamic braking

modes.

Confirm: Yes / No

12. Temporary Speed Change Test:

The maximum instantaneous variation in engine speed expressed as percentage of rated speed, after sudden variation of load from the rated value to zero:

Max. Speed - Rated speed

Temporary speed change = ------------------------------------ x 100 Rated speed

5

Page 38: Specification for Revision - Indian Railways

Temporary speed change: ----------------rpm ------------------% 13. Safety Devices Operation Test: Test operation of the safely devices provided on the locomotive shall be checked at loco test

stage as under:

(i) Low water alarm (LWA) switch : Actuation of LWA switch should cause shut down of the engine. Confirm: Yes / No

(ii) Ground Relay: Manual actuation of ground relay (GR) should cause power cut off and bring the engine to

idle. Confirm: Yes / No (iii) Hot Engine Alarm: Actuation of this device should bring the engine to idle speed . Confirm: Yes / No (iv) Low Oil Pressure Shutdown Settings:

(To be checked if feasible)

Actuation of this feature should cause engine shutdown in case the lube oil pressure falls below the specified limits.

Function of this device will be checked in the following manner :

During notch up-

Notch LOPS setting Time delay in loco shut down Idle/1 1.1-1.3 kg/cm2 40-45 sec

Idle/1 to notch X

Proportionate value at notch X

10 sec + time taken by the reference speed to reach

notch X rpm

During notch down:

Notch LOPS setting Time delay in loco shut down

Idle/1 1.1-1.3 kg/cm2 40-45 sec Idle/1 to notch

X Proportionate value at

notch X Instantaneous

LOPS values will be as follows:

6

Page 39: Specification for Revision - Indian Railways

LOPS value (kg/cm2 ) Loco type Idle/Notch 1 Notch 8

WDM2 1.1-1.3 1.1-1.3 WDM22C/WDG2/WDP2 3.9-4.1 4.1-4.4

Check operation of LOPS reset button: Working/not 14. Fail Safe Feature Test : Possible faults shall be created to test the fail safe feature of the governor (to be listed out by

the supplier and got approved by RDSO). 15. Multiple Unit (MU) Operation Test :

Multiple unit operation test shall be carried out as per procedure listed below:

(i) Couple one WDM2/WDG2/WDP2 locomotive having GE or WW or micro controller based governor in MU with the locomotive equipped with micro controller based governor .

(ii) Crank and start both the locomotive engines one by one. (iii) Check notch wise engine rpm of both the locomotives by ascending and descending of

throttle notch positions. (iv) Check for dynamic braking setup of both the locomotives. It should be able to give response

simultaneously. (v) Check MU stop operation : while the engines of the locomotives under MU test are running

at any notch, operate the MUSD switch on the control stand. Both the engines should shutdown.

III. ACCEPTANCE CRITERIA: 1. Ability to maintain desired engine speed at each notch within specified tolerance of +3 rpm with

or without load. 2. Ability to maintain desired engine speed without speed fluctuations i.e. free from hunting at each

notch with and without load. 3. Ability to maintain constant engine power output at each notch. 4. Ability to actuate the fuel control mechanism for rack movement in either direction to regulate

fuel supply. 5.Ability to maintain temporary speed change within 10% of the rated speed after sudden removal

of rated load. 6. Ability to regulate fuel supply as a function of air manifold pressure (i.e. proper functioning of

air manifold pressure bias fuel limiting feature) for optimum combustion. This will be judged from the opacity/colour of the exhaust smoke during rapid notching up of engine speed at the time of load box testing.

7. Suitability to work in Multiple Unit (MU) operation with locos provided with either same /similar or Woodward or GE/EDC type or micro controller based governors.

8. Proper functioning of safety devices. -----------------

7