Part 1- SOTR Program Overview

Part 2- Standard of Conduct

Part 3- Acquisition Planning

Part 4- Formulating Technical Requirements

Part 5- The Solicitation Process

Part 6- Subcontract Management & Oversight

Open Book Test

SOTR Training Agenda

Page 3: SOTR Training

SOTR’s Top Priority

Training Objectives

Benefits of a Trained SOTR

Prerequisites for SOTR Certification

When is a Certified SOTR Required?

SOTR Responsibilities

The Acquisition Process

Subcontracting Officer Role and Authority

Part 1 SOTR Overview

Page 4: SOTR Training

Make Safety Your Top Priority!

4

“Jefferson Lab has a commitment to provide the safest, most

efficient operations possible to achieve a high level of

performance. No schedule or milestone is so important that

safety, health or environmental responsibility can be

compromised.”

- Stuart Henderson

Jefferson Lab Director

Page 5: SOTR Training

ESH&Q Requirements Cannot Be

Compromised

5

Important ESH&Q Manual References for Acquisitions 3210 Hazard Identification and Characterization

3410 Aspects of Procurements

4200 Developing Job-Specific Training

5200 Incident/Notable Event/Injury/Investigation and Causal

Analysis

6122 Welding, Cutting, Brazing, and Grinding

6150 Compressed, Liquefied, and Solidified Gas Program

6151 Pressure Systems

6750 Environmentally Harmful Materials

CONTACT YOUR ESH&Q PROFESSIONAL FOR ASSISTANCE

Page 6: SOTR Training

Training Objectives

6

Understand important ethical and legal issues

governing acquisition of supplies and services

Understand essential requirements for soliciting

goods and services

Understand the essential elements of Subcontract

administration, ensuring safety, quality, and

timeliness

Page 7: SOTR Training

Benefits of a Trained SOTR

7

Safer work processes and environmental awareness

Better planned and executed acquisitions

Informed decision-making that enhances efficiency,

saves dollars, and mitigates risks

Better quality of product and services

Enhanced relationships that serve the best interests

of JLab, Government, and our business community

Compliance with our DOE Contract

Page 8: SOTR Training

Prerequisites for SOTR Certification

8

SOTR’s will be “Certified” after

Completing this SOTR training, and completion of.. GEN101 Standards of Conduct Training

GEN035 Suspect/Counterfeit Parts Awareness training

Passing a 20-question “open book” test

Individuals must complete above training

requirements to be assigned as SOTR.

A list of “Certified” SOTR’s is maintained on

Procurement Dept website

Page 9: SOTR Training

When is a Certified SOTR Required?

9

Construction, installation, or fabrication work on site

Services performed at JLab with unmitigated Risk

Code 2 or higher

Procurements estimated >$150K using JLab

specifications

When deemed necessary by the Subcontracting

Officer (SO)

Page 10: SOTR Training

The Acquisition Process

10

PRE-SOLICITATION

Develop Technical Requirements

-Coordinate with ESH&Q

-Obtain Vendor Information

-Develop Cost Estimate

-Issue Purchase Requisition

Develop Solicitation

-Develop Approach

-Develop Source List

-Develop Specific Source Selection Plan

ADMINISTRATION

Manage Subcontractor Performance

-Pre performance Briefing

-Issue Notice to Proceed

-Review & Approve Submittals

-Process Changes Through Procurement

-Evaluate Vendor Claims

-Inspect & Accept Work

-Complete Vendor Survey

-Administer Warranties

Subcontract Closeout

-Complete pricing audit

-Approve final invoice

-Complete vendor survey

Page 11: SOTR Training

General SOTR Responsibilities

11

Oversees technical aspects of the acquisition process Serves as SO’s technical lead to process the solicitation

Generates all pre-solicitation technical and funding documents

Assists Subcontracting Officer with Site Visit Guides technical processes through subcontract award

Provides technical oversight of the subcontract Ensures ES&H requirements are met (e.g., ES&H 6150) Reviews and approves submittals and subcontractor changes Performs inspections and tests Accepts final work products and services

Page 12: SOTR Training

Subcontracting Officer (SO) Role and Authority

12

JLab’s business point of contact

Leads solicitation process and vendor negotiations Issues notice of subcontract award

Point of contact for subcontract business issues and

changes Directs and negotiates subcontract changes

Directs and notifies subcontractor to mitigate and/or correct

performance issues

Communicates acceptance to subcontractor

Enforces warranty and termination provisions

Page 13: SOTR Training

Part 2 Applies to All JLab Staff

JLab’s Code of Ethics and Standard of Conduct

Conflict of Interest

Organizational Conflict of Interest (OCI)

Gratuities

Kickbacks

Ratifications

General Ethical Do’s and Don’ts

Part 2 Ethics and Standard of Conduct

Page 14: SOTR Training

JLab Code of Ethics and Standard of Conduct

14

Jefferson Lab’s fundamental ethical principles:

Each of us is responsible for the propriety and

consequences of our actions

Each of us must conduct all aspects of JLab business in

an ethical and lawful manner

Each of us must hold ourselves to high standards of

honesty, integrity and fairness in relationship to others

Page 15: SOTR Training

Conflict of Interest (CI)

15

A CI (or apparent CI) occurs when you have

personal/business interests that may adversely

affect JSA’s/DOE‘s mission

Avoid situations that might involve a conflict of interest

or even the appearance of a conflict of interest

Disclose any apparent/actual conflict of interest!

JLab Policy (Admin Manual Section 208.03) covers

full details and guidance on CI

Page 16: SOTR Training

Conflict of Interest (CI) – Discussion over Lunch – I have

a requisition for maintenance of the plants at JLAB!! 16

Page 17: SOTR Training

Organizational Conflict of Interest (OCI)

17

Be vigilant to avoid OCI situations

OCI may exist when:

1. There are conflicting roles that might bias a

subcontractor's judgment in relation to its work Can occur when a fiduciary relationship exists between a company

responsible for construction of a building & another inspecting the work

2. The subcontractor is given an unfair competitive

advantage based on the performance of the

subcontract Can occur when subcontractors responsible for developing specifications

are also bidding on the work package

Page 18: SOTR Training

18

A gift, meal, or entertainment offered to obtain a

subcontract or favored treatment under a subcontract Do not accept a gratuity from vendors or other interested parties

Do not offer a gratuity to a Government official

See JLab Administration Manual Section 208.03 C6/ for

limitations and exclusions to Policy, e.g.,

Individual gift, meal etc. <$25 is considered de minimis and

acceptable under JLab policy ($50 yearly aggregate)

Gratuities

Page 19: SOTR Training

Kickbacks

19

Federal Law (Anti-Kickback Act) prohibits persons

from— 1. Providing or attempting to provide or offering to provide

any kickback;

2. Soliciting, accepting, or attempting to accept any

kickback; or

3. Including, directly or indirectly, the amount of any

kickback in the subcontract price charged by a prime

Contractor to the United States or in the contract price

charged by a subcontractor to a prime contractor or

higher tier subcontractor

Page 20: SOTR Training

Gratuities/Kickbacks – Paid to Coalition Provisional

Authorities (CPA) in Iraq by Phil Bloom 20

Page 21: SOTR Training

Ratifications

21

Ratification – the act of approving unauthorized

agreements (purchase commitments) with vendors (or other

parties) made by JSA personnel without delegated

authority to make such agreements/commitments.

The JLab Procurement Manager (or designee) is the only JLab

individual with authority to ratify actions.

Page 22: SOTR Training

Ratifications

22

Ratification of an unauthorized action may only be exercised when:

Supplies or services have been provided to and accepted by JSA, or JSA

otherwise has obtained or will obtain a benefit resulting from performance of

the unauthorized commitment;

The resulting subcontract would otherwise have been proper if made by an

appropriate buyer/subcontracting officer;

The buyer/subcontracting officer reviewing the unauthorized commitment

determines the price to be fair and reasonable;

The buyer/subcontracting officer recommends payment for the supplies or

services rendered;

Funds are available and were available at the time the unauthorized

commitment was made; and

The ratification is in accordance with any other limitations prescribed under

JSA policy and procedures

Page 23: SOTR Training

Ratifications - Continued

23

Buyer/ subcontracting officers shall determine whether the unauthorized procurement can be ratified.

Complete Procurement form PD 29 Ratification Form and forward it to the person that committed the unauthorized procurement.

Provide a final determination to either ratify or not ratify to the Procurement Manager.

Only the Procurement Manager or his/her designee is authorized to ratify actions under this subsection.

The Procurement Manager will maintain a file of all ratified (and unratified) actions that will be reviewed at least annually to determine if further corrective action(s) are needed based on a trend of ratified actions or other observed variance from JLab policy (e.g., repeat offenders will be brought to the attention of senior management).

Page 24: SOTR Training

General Ethical Do’s and Don’ts

Report suspected violations

of the Anti-Kickback Act

Report all instances of Fraud,

Waste, and/or Abuse

Be vigilant to mitigate

and/or avoid conflict of

interest or OCI situations

Be fair and impartial in all

business transactions

Discuss offers of employment

when involved in a procurement

involving the subcontractor, or

encourage subcontractor

employees to join JLab

Disclose “privileged” information

Make commitments with regard

to price, quantity, quality, or

delivery without delegated

authority from Procurement

24

Don’ts Do’s

Page 25: SOTR Training

BREAK

PLEASE RETURN

PROMPTLY

25

Page 26: SOTR Training

When You Need to Plan

Consequences of Poor Planning

Planning Considerations

Primary Types of Subcontracts Used by JLab

Part 3 Acquisition Planning

Page 27: SOTR Training

When is Planning Needed?

27

Most non-standard requirements >$150K, e.g.,

When using “Best Value” to select a subcontractor

When DOE approval is required or procurement will

involve a foreign source

Time critical (e.g., items on the critical path)

Formal Advanced Procurement Plan required for

complex requirements >$1,000,000, $500K for

LCLS II and 12 GeV

When in doubt contact the Procurement Dept.

Page 28: SOTR Training

Consequences of Poor Planning

28

Common failures resulting from poor

(or no) planning: Inferior quality or performance deficiencies

Rework

Late delivery and missed milestones

Higher prices

Missed opportunities

Increased claims from vendors

Negative impact on vendor relationships

Reduced participation of small business firms

Page 29: SOTR Training

Personal Consequence of Poor Planning

29

Project Mgr. taking corrective

action with the responsible

Control Account Mgr. (CAM)

%#@*&#

!

Schedule

Co

st

Over Cost

Behind Schedule

Under Cost

Behind Schedule

Under Cost

Ahead of Schedule

Over Cost

Ahead of Schedule

Cost/Schedule Performance Index

Today

Page 30: SOTR Training

Types of Subcontracts Used by JLab

30

Fixed Price (FP) places greatest risk on vendor

Cost Type “Best Efforts”- No performance guarantee

Time-and-materials uses burdened labor rates and actual material cost as basis of billing

Labor hour for personal services

Memorandum PO (MPO)/Inter-entity Work Order (IWO) used with other DOE Labs- (Cash transfer not a subcontract)

Page 31: SOTR Training

Planning Considerations- Technical Requirements

31

Develop Understanding of Technical Requirements Technical specifications must be complete prior to

issuing the requirement for bid/proposals Specifications involving work with unmitigated risk level >2,

or fabrication work requiring Class A or B welding or brazing requires QA review/concurrence to proceed

Statement of Work must be included with PR for risk level >2 for ESH&Q to properly evaluate

Contact Procurement if vendor information is needed to complete technical requirements Vendor budgetary quotes or price estimates cannot be used

as the basis for awarding subcontracts

Page 32: SOTR Training

Planning Considerations- Develop Sources

32

“Competition” requires at least two sources that can meet stated requirements Exempted $3.5K-supplies, $2K-construction, $2.5K-services

Ideal number of sources depends on the nature of requirement.

Develop sources through- JLab Vendor Portal (new and past vendors) https://misportal.jlab.org/bidderportal/ Sources Sought or Expression of Interest notices

JLab Solicitation Board and/or Fed Biz Ops Direct mailing to known industry contacts Advertising in trade papers, magazines, etc.

Page 33: SOTR Training

Planning Considerations- Vendor Information

33

Involve industry to assist planning

Draft Request for Proposal (RFP) or Request for

Information (RFI’s) can help clarify/define requirements Determine vendor capability and availability

Identify design flaws and inconsistencies

Responses can be used to support JLab cost estimate

Include as much information on project that is known Draft specifications/statements of work

Planned quantities and delivery requirements

Released data must be available to all interested parties

Page 34: SOTR Training

Planning Considerations- Small Business Sources

34

Procurement may establish Small Business (SB) Set-

aside when there are “adequate” number of SB to

provide the requirement

Mandatory Set-asides

Supplies and services <$150K

Construction <$3M

Optional set-asides to Disabled Vets and Hub Zone

<$5M Manufacturing, <$3M Non-Manufacturing Must have two available sources to set-aside

Page 35: SOTR Training

Planning Considerations- Buy American

35

Fed Law gives preference to Domestic End Products 1. Article must be manufactured in the U.S., and 2. Total cost of the domestic components must exceed 50% of the

finished item

Foreign purchase acceptable when: Domestic item not available (requires Procurement/DOE Approval) Domestic price is unreasonable

>6% if large business or >12% if small business

SOTR’s must be vigilant to ensure received materials comply with Buy American Act Contact SO if received items are suspected of violating Buy

American Act requirements

Page 36: SOTR Training

Planning Considerations- Sole Source

36

A sole source means no other source will reasonably

satisfy the Lab’s requirements, i.e., Unusual and compelling urgency

Urgency does not cover events that could have been

avoided with proper planning

Unique attribute/capability Price is not a basis for sole source (we can compete)

We can sole source to a Small Business for <$150K

if no other small business firms are available

Page 37: SOTR Training

Planning Considerations- Acquisition Cycle Time

37

Allow reasonable time to process the solicitation

Processing time is based on complete documentation in

Procurement, does not include RFI’s, sources sought, etc.

Rule of Thumb processing times Commercial Grade Requirements (off-the-shelf)

<$3K 2-5 work days

<$150K 5-15 work days

>$150K 30-45 work days

Non-commercial (JLab-generated specifications) <$150K 30-90 work days

>$150K 75-270 work days (based on selection method)

Allow a minimum of 90 days for Best Value selections

Page 38: SOTR Training

Planning Considerations- Selection Strategy

38

Three approaches to selecting a subcontractor 1. Award based on lowest price (fastest to process) 2. Award based on technical acceptability and price

Lowest priced offer meeting technical standards is selected If low offer(s) determined not acceptable, must document what

made low offer(s) technically unacceptable 3. Award based on Best Value

Predominant method for large complex procurements Provides more flexibility but requires the most time to process Uses tradeoffs of technical factors and price to make selection

decision Biggest advantage: select the best value subcontractor (not

necessarily the lowest price) to perform work

Method of selection affects procurement time

Page 39: SOTR Training

Planning Considerations- Source Selection Plan

39

Source Selection Plan Required for Best Value

Selections

Establishes framework for the selection process Establishes evaluation criteria and rating plan (next slide)

Criteria must be consistent with the RFP

Names Technical Evaluation Team (TET) members Technical Chair coordinates activities of the technical team

Documents events and writes technical evaluation report

SO responsible for evaluation of the business proposal

Source Selection Official (SSO) responsible for overall selection

May include subject matter experts as advisors, e.g., External

technical, QA, Legal, Safety, and others as appropriate

Page 40: SOTR Training

Sample Best Value Rating Plans

LOCAR (Level of Confidence Assessment Rating)- Evaluators assign a number between 0-1 to assess offeror’s evaluated risk of success-failure 0 = No chance of success; 1 = 100% chance of success

Color/Adjectival Ratings

9 - 10 (BLUE – SUPERIOR) Offeror’s proposal demonstrates excellent understanding of requirements, and significantly exceeds JLab’s mini capability and/or performance standards. Proposal has exceptional strengths that provide a high degree of benefit to JLab and/or considerably less than average risk.

7 - 8 (GREEN - NOTABLY ABOVE AVERAGE) Offeror’s proposal demonstrates good understanding of requirements, and exceeds JLab’s min capability and/or performance standards. Proposal has one or more strengths that provide some degree of benefit to JLab; and there are few, if any, minor deficiencies that result in less than average risk.

5 - 6 (WHITE – AVERAGE) Offeror’s proposal demonstrates acceptable understanding of requirements, and meets JLab’s min capability and/or performance standards. The proposal provides few or no strengths; and may have minor deficiencies that result in an average risk to satisfactory performance.

3 - 4 (YELLOW – MARGINAL) Offeror’s proposal demonstrates shallow understanding of requirements, and only marginally meets capability and/or performance standards. Proposal has a number of minor deficiencies, or one or more major deficiencies that could impact offeror’s capability to provide acceptable performance, and cause JLab to undertake considerable risk.

0 - 2 (RED – POOR) Offeror’s proposal fails to meet capability and/or performance standards. Proposal has a gross deficiency (ies) or numerous other deficiencies which causes the Offeror’s proposal to be non-compliant in one or more area(s) and could cause JLab to undertake unreasonably high risks.

40

Page 41: SOTR Training

BREAK

PLEASE RETURN

PROMPTLY

41

Page 42: SOTR Training

Creating the Statement of Work

Type of Specification Affects Risk

Specification Cost Drivers

Determine Need for Warranty Protection

Furnishing Government Equipment/Property

Inspection and Acceptance Requirements

Purchasing Quality Significant Items

Applicable Industry Codes

Important ESH&Q References

Part 4 Formulating Technical Requirements

Page 43: SOTR Training

Creating the Statement of Work (SOW)/Specification

43

SOW is the foundation of the procurement action

Page 44: SOTR Training

The Type of the Specification Affects Risk

44

Design Specification- Prescriptive, has precise measurements and materials

JLab has liability for errors, omissions, and results

Subcontractor can recover damages for additional costs

incurred

Performance Specification- Describes work in terms of final outcomes-

output/function/operation

Allows subcontractor to exercise discretion to achieve results

We must be careful not to direct “means” and/or “methods”

Product description- (“brand name or equal”) “Or equal” must describe salient characteristics/features

High

Low

Page 45: SOTR Training

SOW Must Be Sufficiently Detailed

45

Details must be sufficient to ensure a “meeting of

the minds” of the contractual parties Include sufficient narrative to describe the requirement

Include applicable industry standards to ensure quality

Include standards to measure progress and results

Include criteria to create measurable acceptance

Lack of required details increases risk to JLab

May not be able to compete on a fixed price basis

Gives greater latitude to the subcontractor Greater likelihood for a dispute

Greater potential for increased cost

Page 46: SOTR Training

Specification Cost Drivers

46

Minimize subcontractor’s risk to reduce cost, i.e.,

Avoid unrealistic or over-restrictive requirements

Avoid/mitigate volatile market conditions

Structure requirements around industry practice Specify “Commercial Grade” items when possible

Align funding availability with normal work processes

Limit use of liquidated damages to critical situations

Evaluate need for warranty based on risk/cost to Lab

Specify minimum needs only

Unnecessary extras increase cost

Page 47: SOTR Training

Determine Need for Warranty Protection

47

Use of a JLab warranty provision is not mandatory

The SO and SOTR should jointly decide the

appropriate use of warranty provisions The decision should be based on the nature, use, complexity

and cost of item vs. the risk to JLab/Government to self-

insure

We use vendor warranty for commercial grade (off-

the-shelf) items

Page 48: SOTR Training

Furnishing Gov’t Equip./Property (GFE/GFP)

48

Determine if GFE/GFP Will Be Provided

Must be identified in the procurement documents

Must be coordinated with JLab’s Property Office

subcontractor may have responsibility for loss/damage

Pro’s

May lower cost and expedite schedule

JLab has greater control over quality

Con’s

JLab liable for defects and late delivery of GFE/GFP

Administrative burden to maintain accountability

Page 49: SOTR Training

Inspection and Acceptance Requirements

49

Standard inspection clause included in RFP and

Subcontract Award language Gives us right to inspect and test work in process

Add other inspection requirements as needed

Include acceptance criteria in specification

Shall be conclusive, excepting latent defects, fraud,

gross mistakes amounting to fraud A latent defect is a fault in the goods that could not have

been discovered by inspection before acceptance

Page 50: SOTR Training

Purchasing Quality Significant Items (QSI)

50

Coordinate QSI/high-risk requirements with ESH&Q

prior to being issued to Procurement Hazardous or environmentally harmful materials

Critical use items with potential for counterfeiting (S/CI)

Pressure systems and structural systems (involving Class

A & B welding/brazing)

Custom electronic devices not listed by a nationally

recognized testing lab

Work performed at the Jefferson Lab site

Page 51: SOTR Training

Industrial Codes Affecting QSI Work

51

Utilize applicable industry codes when specifying

QSI related work American Society of Mechanical Engineers (ASME)

ASME Section III for Pressure Vessels

ASME B31.3 for Pressure Vessel Piping

ASME B31.9 for Building Utilities

American Welding Society (AWS) AWS D.1.1 & D.1.6 for Structural Welding

Page 52: SOTR Training

Applicable Construction Spec Requirements

52

Specifications for Construction and Architect/Engineering may

require flow down language from the DOE General Design

Manual for construction and Architect-Engineer Subcontracts e.g., Independent Estimates. A detailed, independent estimate of

costs shall be prepared for all construction work to be subcontracted.

e.g., Specifications. Specifications for construction shall be prepared

in accordance with the DOE publication entitled “General Design

Criteria Manual.”

SOTR shall notify SO if non-conforming material has been

supplied.

Page 53: SOTR Training

Forming the Request for Proposals

Issuing the Request for Proposals

Evaluating Proposals

Awarding the SubContract

Part 5 The Solicitation Process

Page 54: SOTR Training

Forming the Request for Proposals (RFP)

54

The RFP establishes the basis for selection of a subcontractor and award of the subsequent subcontract The SOTR provides all required technical and funding

documentation to evaluate and award the subcontract Establishes the criteria needed to select the subcontractor

Must be consistent with the Source Selection Plan

Establishes the technical requirements of the subcontract Provides Purchase Requisition (PR) based on cost estimate

Utilize MAXIMO System to issue PR May issue no fund PR if reasonable expectation funds will be

available at the time of award Issue Letter of Increase to add funds to PR before award

Page 55: SOTR Training

Issuing the RFP

55

Allow 30-90 days for submission of offers

Can require oral presentations to minimize paperwork

Post solicitation on Jlab website and notify vendors

Hold a site visit if necessary to show potential

offerors the site of work

Issue amendments to incorporate changes

Proposals are distributed to Technical Evaluation

Team for review and evaluation

Page 56: SOTR Training

Site Visits

56

The Subcontracting Officer will establish a site visit if required

The Subcontracting Officer shall use a PD Form 101A for the Site Visit to ensure Safety is invited, the SOTR, and other required personnel

All site visits will be coordinated with the SOTR

SOTR’s are responsible to assist the Subcontracting Officer in showing the area of work

The SOTR shall alert any potential bidders of site conditions and where the work will be accomplished

During the Site visit if in the accelerator area or other areas that contain ODH hazards or Radiation, the SOTR shall be responsible to know current status of these areas

The SOTR shall coordinate obtaining the proper dosimetry for any of the visitors/JLAB personnel at the site visit and shall coordinate with Subcontracting Officer that proper actions have taken place

Page 57: SOTR Training

Evaluating Proposals- Low Price

57

SO has lead responsibility for determining that

proposals are complete Requests clarifications from bidders to correct

omissions/errors in business proposal

SOTR is lead technical representative

Provides technical guidance/documentation to SO

Page 58: SOTR Training

Evaluating Proposals- Best Value

58

Proposals evaluated in accordance with SSP Technical and business parts evaluated separately

We can request clarifications as needed to complete eval Selection committee develops “Competitive Range” (CR) Can award on initial offers or conduct “discussions”

Discussions requires Final Proposal Revisions ( previously BAFO) from all offerors in CR

SO has lead responsibility for the selection process Leads negotiations and written/oral discussions Evaluates terms & conditions, & prepares price analysis

SOTR is lead technical representative

Source Selection Official (SSO) makes source selection decision based on guidance from TET & SO

Page 59: SOTR Training

Awarding the Subcontract

59

Prior to award SO must satisfy that the:

1. Offeror is “Responsive” to the solicitation,

2. Offeror is “Responsible” to complete the work,

3. The final price is “Fair and Reasonable”, and

4. The award is consistent with the solicitation

Successful Offeror notified of award decision

Unsuccessful Offerors notified and given opportunity for

debriefing

SO and SOTR provide post-award debriefing upon request

Advise strengths/weaknesses of offeror’s proposal only

Page 60: SOTR Training

BREAK

PLEASE RETURN

PROMPTLY

60

Page 61: SOTR Training

Starting Subcontractor Performance

Subcontract Administration

S/CI

Making Changes to the Subcontract

Constructive Changes

Request for Equitable Adjustment

Subcontractor Claims

Final Acceptance

Issues Affecting Final Acceptance

Closing the Subcontract

Enforcing the Warranty

Terminating Subcontractor Performance

Your Approach is Critical to Success

Part 6

Subcontract Management & Oversight

Common Environments for S/CI

Protect Against Intrusion of S/CI

Example of S/CI at JLab

Corrective and Preventative Measures

Page 62: SOTR Training

Starting Subcontractor Performance

62

Conduct pre-performance “kick-off” meeting to

identify and clarify requirements, i.e., Assign & communicate subcontract roles & responsibilities

Achieve a clear & mutual understanding of the subcontract

requirements, e.g., Subcontractor access to the work site and training requirements

Communication process for submittals, status reports & payments

Permits, safety, and environmental issues requiring coordination

Inspection, testing and hold points

Delivery and milestone schedules

Other?...

Page 63: SOTR Training

Subcontract Administration

63

Ensure subcontract requirements are being met Monitor performance, inspections, and witness tests

Document performance deficiencies & address with SO Intervene if you observe unsafe work practices and stop work for

imminent danger! Be vigilant to avoid suspect/counterfeit items (S/CI) Coordinate inspections by subject matter experts Accept work and services consistent with subcontract

Approve and process invoices (including earned value)

SOTR’s records and supporting documentation are important to ensure a satisfactory outcome

For on-site work Ensure subcontractor has appropriate signage, i.e., safety notices,

DOL Notices including Wage Determinations (service and construction), contact information, and e-verify notices

Page 64: SOTR Training

Subcontract Administration – Vendor Communication

64

Vendor

Collaborators

Prime Contractor (Purchaser)

Ultimate Customer Government

Third Parties

Logistics Partners

Page 65: SOTR Training

SO/SOTR

Subcontract Administration – Vendor Communication

65

Users

Customer

Industry Experts

Partner A

Government

Partner

B

Vendor

Page 66: SOTR Training

Subcontract Administration

66

Vendor Communications:

Protocol established by the SO/SOTR Other lab participants have no privy of contract

Subcontractors are instructed to only listen/take direction

from the assigned SO/SOTR for the subcontract awarded

by the issuing Lab.

Changes in cost, schedule, terms can only be directed by the

SO for a particular subcontract.

Directions from other than the SO/SOTR causes

communication issues leading to potential delays and claims

Page 67: SOTR Training

Subcontract Administration

67

Meeting Protocols:

Meetings are the responsibility of the SO/SOTR for the

subcontract let by a particular lab There should be no arguments/disagreements during meetings

with a subcontractor

If a partner lab has a question or comment please send to

SO/SOTR before or during the meeting. If in the meeting ask SO

for a discussion and then decide the course of action while the call

is muted.

Personnel outside the Lab managing the subcontract should only

discuss issues with the subcontractor when asked to by SO/SOTR

Written communications to a subcontractor can be accomplished

when approved by the SO/SOTR

Page 68: SOTR Training

4 Guidelines for Effective Vendor Communication

68

1. Maintain a single funnel/filter for all vendor communication. • Involve the SO & SOTR in every email or phone call with the vendors.

• Do not contact the vendor without guidance from the SOTR &/or SO.

2. Never argue in front of the vendor. • If on call, ask to press "mute".

• If in person, wait for a break. If urgent, ask for a break & discuss offline.

• If you have a question that may be controversial, run it by the SOTR first (if

technical) & the SO (if of a business nature).

3. Avoid using: "You should...", "You need to..", "You will..." (Unless you are the SO or have the SO’s concurrence).

• The direction may be considered a “directed change” and increase

subcontract scope.

Page 69: SOTR Training

69

4. Don’t lay all of your cards on the table. Do not discuss the project (P6) schedule.

• If there is float, keep it to yourself or your float will soon disappear.

• The vendor is accountable to the subcontract schedule, not P6.

Never agree to changes, impacts to cost or schedule

without consideration. • If the vendor suggests possible cost increases, or schedule

extension……ask “What is the impact?”

• Take the discussion offline with SO, CAM, STL for final decision

4 Guidelines for Effective Vendor Communication

Page 70: SOTR Training

Subcontract Administration – 30 K Tank for CHL Area

70

Page 71: SOTR Training

What Constitutes an Improper Payment

Improper Payments Elimination and Recovery Act of

2010 (IPERA)

OMB A-123 Appendix C parts I and II

JSA, LLC Jefferson Lab determined to be a reporting

site started Oct 1, 2012 (FY2013)

Page 72: SOTR Training

Improper Payment Definitions

Payment – any transfer or commitment for future transfer of Federal funds such as cash, securities, loans, loan guarantees and insurance subsidies to any non-Federal person or entity that is made by a Federal contractor administering a Federal program or activity.

Improper Payment – any payment that should not have been made or that was made in an incorrect amount (including overpayments or underpayments) under statutory, contractual, administrative, or other legally applicable requirements. Includes insufficient or lack of documentation to justify payment.

Page 73: SOTR Training

Improper Payments

Examples include:

Invoices authorized for payment for services not rendered

Incomplete quantities of material or equipment authorized for payment

Leased equipment not received

Incorrect labor rates

Incorrect material cost

Invalid backup documentation (e.g. signature not obtained for services, backup missing for T&M contracts, pricing on invoice does not match the pricing structure in the contract)

Payment outside of PO terms (milestones not met)

Page 74: SOTR Training

Lesson: ensure mfg.’s markings are clearly

indicated

Example of “suspect” part used by a JLab subcontractor 74

Page 75: SOTR Training

Common Environments for S/CI

75

Locations where S/CI may reside

at the workplace- Lifting & Rigging hardware & material

Valves and compressors

Temperature or high-pressure steam or fluid systems

Systems that support safe operation or shutdown of a

facility or process

Electrical panels and circuits

Other? …

Page 76: SOTR Training

Protect Against Intrusion of S/CI

76

Common types of S/CI found at DOE facilities

Fasteners (bolts and brackets)

Rigging components

Ratchet straps/tie down straps

Refurbished molded-case circuit breakers

Transformers, fuses, resistors, switch gear

Metal struts

Pipe components, fittings, flanges, valves

Material and testing certification

Page 77: SOTR Training

Corrective and Preventative S/CI Measures

77

Corrective and preventive actions are institutionalized within JLab S/CI guidance and policy can be found at:

JLab’s Assurance Program Description JLab’s QA Plan S/CI Program Description S/CI Policy S/CI Identification Procedure S/CI Documentation and Notification Procedure S/CI Segregation and Disposal Procedure There is the online training, including images, at http://

www.jlab.org/div_dept/train/online_courses/GEN035/. Additional images can be found at http://www.jlab.org/div_dept

/train/Knowledge_Docs/KD0005.pdf

Page 78: SOTR Training

Directing Changes to the Subcontract

78

The “Changes” clause allows JLab to unilaterally

direct changes within the scope of the subcontract Subcontractor must proceed with the changed work

JLab may negotiate the cost of the change prior to

authorizing the performance of the work

Changes outside the scope require a sole source action

The change must be coordinated with, and

authorized by, the Subcontracting Officer

SOTR must provide a Purchase Requisition (PR) to

support the requested change

Page 79: SOTR Training

Constructive Changes (CC)

79

A CC can occur when we fail to act in a reasonable and

prudent manner, e.g., when we… Provide specifications that are defective, ambiguous, or

create an impossibility of performance

Don’t address or correct obvious errors, e.g., submittals

Don’t extend the schedule for an excusable delay

Provide defective or late GFE/GFP

Direct subcontractor’s means or methods of performance

Withhold critical information affecting performance

May also result when the subcontractor encounters

“differing site conditions”

Page 80: SOTR Training

Request for Equitable Adjustment (REA)

80

Purpose of a REA is to make the subcontractor whole for directed or constructive changes to the subcontract

The subcontractor may submit a REA for damages if he can demonstrate he has been harmed, The adjustment amount is reasonable (quantum), and The connection between the circumstances and

amount(s) to subcontract (entitlement)

Subcontract price may also be reduced for changes that reduce subcontractor’s cost of performance

Page 81: SOTR Training

Subcontractor Claims

81

A Claim is any open dispute or REA that cannot be

settled directly with the subcontractor without 3rd

party intervention

An unsettled claim can be resolved in two ways: 1. Alternative Dispute Resolution (ADR)-

Includes mediation and arbitration

2. Litigation in Federal Court

Page 82: SOTR Training

Terminating Subcontractor Performance

82

Two ways to formally terminate “Termination for Convenience”

JLab can terminate subcontract without cause Subcontractor recovers all costs + associated profit

“Termination for Default” Subcontractor responsible for all re-procurement costs Termination for Default requires accurate/thorough records

to protect our interest

Both parties may mutually agree to “walk away” and end subcontract relationship without fault/liability

Page 83: SOTR Training

Issues Affecting Final Acceptance

83

Beneficial occupancy allows JLab to take possession

of the project (or portion of) prior to final

acceptance

Construction subcontractor works on a “punch list” of

outstanding construction and installation issues

May negate subcontractor’s liability for further

liquidated damages

System commissioning identifies issues that need to

be resolved prior to project completion and final

acceptance

Page 84: SOTR Training

Final Acceptance

84

Final acceptance establishes the point in time that title

passes to the Government (not JLab) Nonconforming items must be communicated to the SO

Correct defective/nonconforming work before acceptance

May accept non-conforming items in return for consideration

Non-conforming QSI must be coordinated with JLab’s QA

Department

Acceptance of services/construction is on a monthly basis Approval of subcontractor’s invoice indicates acceptance

Receive Release of Claims prior to final payment

Acceptance may be implied when JLab uses the item, or

time for acceptance expires without comment

Page 85: SOTR Training

Closing the Subcontract

85

Retrieve all subcontractor badges

Ensure satisfactory return of all GFE/GFP Coordinate with Procurement and JLab Property Office

Ensure received items are properly stored

Complete and return the subcontractor performance

evaluation form to Procurement (actions >$150K)

Document subcontractor’s performance

(strengths/weaknesses)

Document “lessons learned”

Page 86: SOTR Training

Enforcing the Warranty

86

Problems encountered after acceptance should be

addressed through the subcontract’s warranty

provision

Procurement maintains the warranty provisions in the

subcontract file

Enforce subcontract warranty provisions in a timely

manner

Coordinate vendor compliance issues with SO

Recovery for latent defects or fraud (including gross

mistakes) are not constrained by warranty clause

Page 87: SOTR Training

Your Approach Is Critical to Success

87

Cultivate a positive work relationship with the

subcontractor Convey realistic expectations- the subcontractor is only

accountable for what’s in the subcontract

Ensure technical oversight does not interfere with

subcontractor’s ability to perform work

Maintain open communications with all parties- and

seek “win-win” outcomes, and

Demonstrate integrity in all relationships

Page 88: SOTR Training

Questions