software development effort estimation using fuzzy … · software development effort estimation...
TRANSCRIPT
International Journal On Advanced Computer Theory And Engineering (IJACTE)
________________________________________________________________________________________________
________________________________________________________________________________________________
ISSN (Print): 2319-2526, Volume -4, Issue -4, 2015
15
Software Development Effort Estimation using Fuzzy Logic
Framework- An Implementation
1Rshma Chawla,
2Deepak Ahlawat
1,2MMICTBM, MMU Mullana
Email: [email protected],
Abstract: Software development effort estimation is very
important and critical task when we have to develop new
or reusable software. The main objective of this research
paper is to provide a technique for software cost estimation
technique that performs better than other techniques on
the accuracy of effort estimation.This study proposed to
extend the Constructive Cost Model (COCOMO) by
incorporating the concept of fuzziness into the
measurements of size, mode of development for projects
and the cost drivers contributing to the overall
development effort. This study explores four fuzzy logic
membership functions: Fuzzy Triangular Membership
Function, GBell Membership Function, Gauss2
Membership Function and Trapezoidal Membership
Function for Software development effort estimation.
Implementation is done by taking estimated effort of
Intermediate COCOMO.
Index Terms:COCOMO Model, Trapezoidal MF, TMF,
GBell MF, Gauss2 MF.
I. INTRODUCTION
1.1. Software Development
Software development is the computer programming,
documenting, testing, and bug fixing involved in
creating and maintaining applications and frameworks
involved in a software release life cycle and resulting in
a software product [32].
Various Phases in Software Development
a. Requirements specification.
b. Planning.
c. Design.
d. Construction.
e. Testing.
f. Debugging.
g. Deployment.
h. Maintenance.
1.2. Software Effort Estimation
Software effort estimation is the prediction of the likely
amount of cost, time, and staffing levels required to
build a software system at an early stage during a
project. It is difficult to obtain the effort estimate during
the preliminary stages, because of the limited resources
available at that time [2].
Need for effort estimation
It would facilitate increased control of time and
overall cost benefit in software development life cycle.
Software development effort estimates are the
basis for project bidding and planning.
Software effort estimation has even been
identified as one of the three most demanding challenges
in software application areas. During the development
process, the cost and time estimates are useful for the
initial rough validation and monitoring of the project’s
completion process. And in addition, these estimates
may be useful for project productivity assessment
phases.
1.3. Size Estimation
The estimation of size is very critical and difficult area
of project planning. It has been recognized a crucial step
from the very beginning. Many Effort estimation models
take size as basic unit for calculating effort.
Methods of Size Estimation:
a. Lines of Code: It is software metric used to
measure the size of a software program by counting the
number of lines in the text of the program’s source code.
A line of code is any line of program text that is not a
comment or a blank line, regardless of the number
ofstatements or fragment of statements on the line. This
specially includes all lines containing program header,
declarations, and executable and non-executable
statements.Unit of measurement is KLOC/ KSLOC/
KDLOC (1000 lines of code).
There are several cost, schedule, and effort estimation
models which use LOC as an input parameter, including
the widely-used Constructive Cost Model (COCOMO)
invented by Barry Boehm [2].
It can be calculated by:
a1. Define the statement of scope.
a2. Historical data.•
a3. Prepare some rough coding(it may be misleading but
have to be done when there is no previous experience).
International Journal On Advanced Computer Theory And Engineering (IJACTE)
________________________________________________________________________________________________
________________________________________________________________________________________________
ISSN (Print): 2319-2526, Volume -4, Issue -4, 2015
16
a4. Automated tools are available.
b. Function Points: A function point is a unit of
measurement to express the amount of business
functionality an information system (as a product)
provides to a user. Function points measure software
size. The cost of a single unit is calculated from past
projects [1].
It can be calculated as:
b1. Internal Logical files (ILF).
b2. External Interface files (EIF).
b3. External Input (EI).
b4. External Output (EO).
b5. External Inquiry (EQ).
II. COCOMO MODEL
The Constructive Cost Model (COCOMO) is an
algorithmic software cost estimation model developed
by Barry W. Boehm.COCOMO was first published in
Boehm’s 1981 book Software Engineering Economics
as a model for estimating effort, cost, and schedule for
software projects [2]. COCOMO is a model that allows
one to estimate the cost, effort, and schedule when
planning a new software development activity.This
model estimates the total effort in terms of “person –
months” of the technical project staff. COCOMO is a
hierarchy of software cost estimation models, which
include basic, intermediate and detailed sub models.
Boehm proposed 3 modes of projects:
1. Organic mode – simple projects that engage small
teams working in known and stable environments.
2. Semi-detached mode– projects that engage teams with
a mixture of experience. It is in between organic and
embedded modes.
3. Embedded mode– complex projects that are
developed under tight constraints with changing
requirements.
BASIC MODEL:
Equation for effort calculation
DE= a * (SIZE)b
Where, DE is development effort.
Constants a and b are dependent upon the mode of the
project.
INTERMEDIATE MODEL:
Ei= a * (SIZE)b
Where, Ei = Estimated effort
Table 2.1 gives the value of a and b for different modes
[29].
Table 2.1: Intermediate COCOMO nominal effort
estimating equations
Development Mode Nominal Effort Equation Ei
Organic
Semi-Detached
Embedded
(MM)NOM = 3.2(KDLOC)1.05
(MM)NOM = 3.0(KDLOC)1.12
(MM)NOM = 2.8(KDLOC)1.20
Development Effort = EAF * Ei
EAF is effort adjustment factor, which can be calculated
from 15 different factors or cost drivers.
Table 2.2: Effort multipliers for different cost drivers
S. no Cost Driver Symbol Very Low Low Nominal High Very High Extra High
1 RELY 0.75 0.88 1.00 1.15 1.40 -
2 DATA - 0.94 1.00 1.08 1.16 -
3 CPLX 0.70 0.85 1.00 1.15 1.30 1.65
4 TIME - - 1.00 1.11 1.30 1.66
5 STOR - - 1.00 1.06 1.21 1.56
6 VIRT - 0.87 1.00 1.15 1.30 -
7 TURN - 0.87 1.00 1.07 1.15 -
8 ACAP - 0.87 1.00 1.07 1.15 -
9 AEXP 1.29 1.13 1.00 0.91 0.82 -
10 PCAP 1.42 1.17 1.00 0.86 0.70 -
11 VEXP 1.21 1.10 1.00 0.90 - -
12 LEXP 1.14 1.07 1.00 0.95 - -
13 MODP 1.24 1.10 1.00 0.91 0.82 -
14 TOOL 1.24 1.10 1.00 0.91 0.83 -
15 SCED 1.23 1.08 1.00 1.04 1.10 -
III. FUZZY LOGIC
Four basic concepts [17], [18], [21]:
a) Fuzzy Sets – sets with smooth boundaries. “Jane is
old” [0,1]
b) Linguistic variables – consider the sentence “The
amount of trading is heavy” uses a fuzzy set “Heavy” to
describe the quantity of the stock market trading in one
day. More formally, this can be expressed as
Trading Quantity is Heavy.
Here Trading Quantity is linguistic variable.
International Journal On Advanced Computer Theory And Engineering (IJACTE)
________________________________________________________________________________________________
________________________________________________________________________________________________
ISSN (Print): 2319-2526, Volume -4, Issue -4, 2015
17
c) Possibility distribution – constraints on the value of
a linguistic variable imposed by assigning it a fuzzy set.
Age (suspect) = [20, 30].
d) Fuzzy if-then rules – a knowledge representation
scheme for describing a functional mapping or a logic
formula that generalizes an implication in two-valued
logic.
Figure 3.1: Fuzzy System
3.1. Fuzzy Inference Process
i) Fuzzification:
Membership Functions
A membership function (MF) is a curve that defines how
each point in the input space is mapped to a membership
value (or degree of membership) between 0 and 1. The
input space is sometimes referred to as the universe of
discourse, a fancy name for a simple concept.
ii) Logical Operators and if-then Rules:
Fuzzy sets and fuzzy operators are the subjects and
verbs of fuzzy logic. These if-then rule statements are
used to formulate the conditional statements that
comprise fuzzy logic. A single fuzzy if-then rule
assumes the form
if x is A then y is B
Where A and B are linguistic values defined by fuzzy
sets on the ranges (universes of discourse) X and Y,
respectively. The if-part of the rule “x is A” is called the
antecedent or premise, while the then-part of the rule “y
is B” is called the consequent or conclusion.
iii) Defuzzification: We can implement two types of
fuzzy inference systems in the toolbox: Mamdani-type
and Sugeno-type.
Mamdani’s fuzzy inference method is the most
commonly seen fuzzy methodology. Mamdani-type
inference, as defined for the toolbox, expects the output
membership functions to be fuzzy sets. After the
aggregation process, there is a fuzzy set for each output
variable that needs defuzzification. Mamdani method
finds the centroid of a two-dimensional function [25],
[26], [27].
We use Mamdani-Type inference system.
IV. FUZZY LOGIC FOR SOFTWARE
DEVELOPMENT EFFORT ESTIMATION
Available data in the initial stages of project is often
incomplete, inconsistent, uncertain and unclear [8], [34].
A fuzzy model is more apt when the systems are not
suitable for analysis by conventional approach or when
the available data is uncertain, inaccurate or vague [35],
[36], [37]. The major difference between our work and
previous works is that four fuzzy logic functions will be
used for software development effort estimation on
COCOMO model and then it’s validated with gathered
data. The advantages of fuzzy logic are combined and
learning ability and good generalization are obtained.
The main benefit of this approach is it has good
interpretability by using the fuzzy rules. The effort
predicted using four fuzzy logic functions will be
compared with Intermediate COCOMO.
V. DEVELOPMENT TOOLS AND
TECHNIQUES
MATLAB 7.5
MATLAB is a high-performance language for technical
computing. It integrates computation, visualization, and
programming in an easy-to-use environment where
problems and solutions are expressed in familiar
mathematical notation. Typical uses include
• Math and computation
• Algorithm development
• Data acquisition
• Modeling, simulation, and prototyping
• Data analysis, exploration, and visualization
• Scientific and engineering graphics
• Application development, including graphical user
interface building.
The Matlab System:
→ Development Environment.
→ The MATLAB Mathematical Function Library.
→ The MATLAB Language.
→ Graphics.
→ The MATLAB Application Program Interface
(API).
Fuzzy Logic Toolbox
Figure 5.1: GUI Tools of Fuzzy LogicToolbox
International Journal On Advanced Computer Theory And Engineering (IJACTE)
________________________________________________________________________________________________
________________________________________________________________________________________________
ISSN (Print): 2319-2526, Volume -4, Issue -4, 2015
18
VI. IMPLEMENTATION
1. This research will implement Constructive Cost
Model (COCOMO) using Mamdani Fuzzy
Inference System (FIS).
2. Fuzzy Triangular membership (trimf) function,
Trapezoidal membership function (trapmf),
generalized bell (Gaussian Bell) membership
function (gbellmf) and two-sided gaussian curve
built in membership function (gauss2mf) are used
with NASA63 dataset for software effort
estimation.
3. The results were analyzed using the criterion –
MMRE (Mean Magnitude of Relative Error).
4. Less MMRE means the result is more accurate [5,
6].
6.1. Research Methodology Used
1. Select a particular type of Fuzzy Inference System
(Mamdani).
2. Define the input variables and output variable.
3. Set the type of the membership functions for input
variables.
4. Set the type of the membership function for output
variable.
5. Write the rules in Rule Editor.
6. The data is now translated into a set of if–then
rules written in Rule editor.
7. A certain model structure is created, and
parameters of input and output variables can be
tuned to get the desired output.
6.2. Fuzzy rules applied[6]
• If MODE is Organic and SIZE is S1 then EFFORT
is EF1
• If MODE is Semidetached and SIZE is S1 then
EFFORT is EF2
• If MODE is Embedded and SIZE is S1 then
EFFORT is EF3
• If MODE is Organic and SIZE is S2 then EFFORT
is EF4
• If MODE is Semidetached and SIZE is S2 then
EFFORT is EF5
• If MODE is Embedded and SIZE is S3 then
EFFORT is EF5
• If MODE is Embedded and SIZE is S4 then
EFFORT is EF3
• If MODE is Organic and SIZE is S3 then EFFORT
is EF4
• If MODE is Embedded and SIZE is S5 then
EFFORT is EF6
• If MODE is Organic and SIZE is S4 then EFFORT
is EF4
6.3. Fuzzy Framework Used
Figure 6.1: Fuzzy Framework
6.4. Experimental Results
1. Trapezoidal Membership Function
Figure 6.2: Output 1
Calculated Fuzzy Effort for Trap MF = Fuzzy Nominal
Effort * EAF
= 768 * 2.72
= 2088.96 = 2089
2. Triangular Membership Function
Figure 6.3: Output 2
Calculated Fuzzy effort for TMF = 2.72 * 763 = 2075
3. GBell Membership Funtion
Figure 6.4: Output 3
Calculated Fuzzy Effort for Gbell MF = 715 * 2.72 =
1945
4. Gauss2 Membership Function
Figure 6.5: Output 4
Calculated Fuzzy Effort for Gauss2 MF = 718 * 2.72=
1956
International Journal On Advanced Computer Theory And Engineering (IJACTE)
________________________________________________________________________________________________
________________________________________________________________________________________________
ISSN (Print): 2319-2526, Volume -4, Issue -4, 2015
19
Table 6.1: Developmental Effort Estimate using various Techniques
S.
No.
Project
id
MODE SIZE EAF Actual
Effort
Intermediate
COCOMO
Nominal
Effort
Intermediate
COCOMO
Est. Effort
Est. Effort
using Trap
MF
Est.
Effort
using
TMF
Est.
Effort
using
GBell
MF
Est.
Effort
using
Gauss2
MF
1 1 1.2 E 113 2.72 2040 814.4 2215.24 2089 2075 1945 1956
2 10 1.2 E 18 2.38 321 89.9 213.83 201.6 200.4 187.8 188.73
3 13 1.2 E 24 0.85 79 127 107.85 102 101.15 94.35 95.2
4 19 1.2 E 966 0.73 6600 10694 7806.45 7373 7329.2 6854.7 6891.2
5 22 1.2 E 109 0.94 724 780 733.16 690.9 687.14 643.9 646.72
6 43 1.05 O 28 0.96 83 105.8 101.61 95.71 95.14 89.2 89.6
7 49 1.12 SD 91 0.36 156 469 168.87 159.12 158.04 148.32 149
8 63 1.2 E 10 0.39 15 44.36 17.3 16.3 16.22 15.17 15.25
Table 6.1 shows Estimated Effort for fuzzy logic
functions, four membership functions namely
Trapezoidal Membership Function (Trapmf), Triangular
Membership Function (TMF), Guass Bell Membership
Function (GBellMF), Gauss2mf - Gaussian curve built-
in Membership Function. These are obtained in Fuzzy
logic Toolbox by selecting the appropriate MF. Inputs to
the FIS are MODE and SIZE. Range of MODE should
be selected among 1.05, 1.12, 1.2. Range of SIZE can be
noted from examining the project id. Fuzzy rules are
applied and then select the Nominal Effort of COCOMO
as the range of Fuzzy Nominal Effort.
Estimated Fuzzy Effort = Fuzzy Nominal Effort * EAF.
6.5. Comparison
The main parameter for the evaluation of cost estimation
models is the Magnitude of Relative Error (MRE) which
is defined as follows
MRE: Mean Relative Error,
MRE =│Actual Effort – Estimated Effort │
Actual Effort ……. (1)
The MRE value is calculated for each observation i
whose effort is predicted.
Table 6.2: Comparison of MRE
S.
No
MRE
using
Inter.
COCOMO
Model
MRE
using
TRAP
MF
MRE
using
TMF
MRE
using
GBell
MF
MRE
using
Gauss2
MF
1 0.0859 0.0240 0.0171 0.0465 0.0411
2 0.3339 0.3719 0.3757 0.4149 0.4120
3 0.3651 0.2911 0.2803 0.1943 0.2050
4 0.1828 0.1171 0.1105 0.0385 0.0386
5 0.0126 0.0457 0.0509 0.1106 0.1067
6 0.2242 0.1531 0.1462 0.0746 0.0795
7 0.0825 0.0200 0.0130 0.0492 0.0448
8 0.1533 0.0866 0.0813 0.0113 0.0166
Σ 1.4403 1.0638 1.0750 0.9399 0.9444
Table 6.3: Computation of MMRE
Estimation Technique MMRE
Intermediate COCOMO 0.1800
FL Trapezoidal MF 0.1329
FL Triangular MF 0.1344
FL GBell MF 0.1175
FL Gauss2 MF 0.1180
Figure 6.6: Comparison of MMRE
VII. CONCLUSION
We can conclude that the introduction of fuzzy logic in
the process of Software Development Effort Estimation
yields more accurate results than the previous Empirical
Model Approach. Trapezoidal Membership function
gives more accurate estimate of Effort as compare to
Triangular Membership Function. GBell MF gives more
accurate result than Gauss2 MF. Gaussian Curve MF’s
are more accurate than the simple straight line
Membership functions. Between five techniques that we
used in our research GBell MF has the lowest value of
MMRE. So, it has highest accuracy.
00.020.040.060.08
0.10.120.140.160.18
0.2
MM
RE
Estimation Technique
Comparison of MMRE
International Journal On Advanced Computer Theory And Engineering (IJACTE)
________________________________________________________________________________________________
________________________________________________________________________________________________
ISSN (Print): 2319-2526, Volume -4, Issue -4, 2015
20
VIII. FUTURE WORK
The above research work can be easily employed in the
software industries.By applying some more effort there
is the possibility to develop other customized
membership functions, which represents inputs more
closely to tolerate uncertainty and imprecision in inputs,
and hence restricting the same to be propagated to the
outputs. Today various softwares are available in the
market to make use of COCOMO model; the above
research can be deployed on COCOMO II, with experts
on the subject providing required information for
developing fuzzy sets and appropriate rules. This work
can be extended by integrating with neural networks to
take the advantage of its features, such as learning
ability and good interpretability. Thus, a promising line
of future work is to extend to the neuro-fuzzy approach
that allows the integration of numerical data and expert
knowledge.
REFERENCES
[1] Albrecht A.J., and J.E. Gaffney, “Software
function, source lines of code, and development
effort prediction: a software science validation,”
IEEE Transactions on Software Engineering, pp.
639-648, November1983.
[2] B. W. Boehm, “Software Engineering
Economics”, Englewood Cliffs, NJ, Prentice
Hall, 1981.
[3] B. W. Boehm, C. Abts and S.Chulani, “Software
Development Cost Estimation Approaches- A
Survey”, Technical Reports, University of
Southern California Centre for Software
Engineering, usccse 2000-505.
[4] Boetticher, G.D., “An assessment of metric
contribution in the construction of a neural
network-based effort estimator”, Proceedings of
Second International Workshop on Soft
Computing Applied to Software Engineering,
2001.
[5] Ch. Satyananda Reddy, KvsvnRaju, “Improving
the Accuracy of Effort Estimation through Fuzzy
Set Combination of Size and Cost Drivers”,
Wseas Transactions on Computers, ISSN: 1109-
2750, Vol. 8, No. 6, June 2009.
[6] Ch. Satyananda Reddy, KVSVN Raju.,“An
Improved Fuzzy Approach for COCOMO’s
Effort Estimation using Gaussian Membership
Function”, Journal of Software, Vol. 4, No. 5,
July 2009.
[7] Exforsys, “Software Project Planning”, Dec
2005.
[8] GeetikaBatra and MahimaTrivedi, “A Fuzzy
Approach for Software Effort Estimation”,
International Journal on Cybernetics &
Informatics (IJCI), Vol.2, No.1, pp. 9-15,
February 2013.
[9] ImanAttarzadeh and Siew Hock Ow, “Software
Development Effort Estimation based on a New
Fuzzy Logic Model”, International Journal of
Computer Theory and Engineering, Vol. 1, No. 4,
October 2009.
[10] ImanAttarzadeh and Siew Hock Ow, “A Novel
Algorithmic Cost Estimation Model Based on
Soft Computing Technique”, Journal of
Computer Science 6 (2): ISSN 1549-3636 ©
2010 Science Publications, pp. 117-125, 2010.
[11] Jones C., “Software Estimating Rules of Thumb”,
Computers, pp. 116-118, March 1996.
[12] Jones C., “Programming Productivity”, McGraw-
Hill, 1986.
[13] Jones C., “Applied Software Measurement”,
McGraw-Hill, 1991.
[14] Jones C., “Estimating Software Costs”, McGraw-
Hill, 1998.
[15] Krishanmoorthy Srinivasan and Douglas Fisher,
“Machine Learning Approaches to Estimating
Software Development Effort”, IEEE
Transactions on Software Engineering, Volume
21, No. 2, pp. 126-137, February 1995.
[16] L. H. Putnam, “A general empirical solution to
the macro software sizing and estimating
problem”. IEEE Transactions on Software
Engineering, SE-4(4), pp. 345-361, 1978.
[17] Lotfi A. Zadeh, “Fuzzy sets”,Information and
Control, Vol. 8, pp. 338–353, 1965.
[18] Lotfi A. Zadeh, “Fuzzy Algorithms”,Information
and Control, Vol. 12, pp. 94-102, 1968.
[19] Lotfi A. Zadeh, “A fuzzy-set-theoretical
interpretation of linguistic hedges”, Journal of
Cybernetics, Vol. 2, pp. 4–34, 1972.
[20] Lotfi A. Zadeh, “Outline of a new approach to
the analysis of complex systems and decision
processes”, IEEE Trans. Systems, Man and
Cybernetics, Vol. 3, No. 1, pp. 28–44, 1973.
[21] Lotfi A. Zadeh, “Making Computers Think like
People”, IEEE Spectrum, 8, pp. 26- 32, 1984.
[22] Lotfi A. Zadeh, “Fuzzy Logic, Neural Networks
and Soft Computing”, Communication of ACM
37(3): pp. 77-84, 1994.
[23] Lofti A. Zadeh, “The Future of Soft Computing”,
In Joint 9th IFSA World Congress and 20th
NAFIPS International Conference, Vancouver,
Canada,2001.
[24] Lofti A. Zadeh, “Knowledge representation in
fuzzy logic,” IEEE Transactions on Knowledge
and Data Engineering, Vol. 1, pp. 89-100, 1989.
[25] Mamdani, E.H. and S. Assilian, “An experiment
in linguistic synthesis with a fuzzy logic
International Journal On Advanced Computer Theory And Engineering (IJACTE)
________________________________________________________________________________________________
________________________________________________________________________________________________
ISSN (Print): 2319-2526, Volume -4, Issue -4, 2015
21
controller”, International Journal of Man-
Machine Studies, Vol. 7, No. 1, pp. 1-13, 1975.
[26] Mamdani, E.H., “Advances in the linguistic
synthesis of fuzzy controllers,” International
Journal of Man-Machine Studies, Vol. 8, pp. 669-
678, 1976.
[27] Mamdani, E.H., “Applications of fuzzy logic to
approximate reasoning using linguistic
synthesis,” IEEE Transactions on Computers,
Vol. 26, No. 12, pp. 1182-1191, 1977.
[28] Moon Ting Su, TeckChaw Ling,
KeatKeongPhang, Chee Sun Liew, Peck Yen
Man, “Enhanced Software Development Effort
And Cost Estimation Using Fuzzy Logic Model”,
Malaysian Journal of Computer Science, Vol. 20,
No. 2, 2007.
[29] PankajJalote, “An Integrated Approach to
Software Engineering”, Third Edition, Narosa
Publishing House, 2006.
[30] Parvinder S. Sandhu, PorushBassi, and
Amanpreet Singh Brar, “Software Effort
Estimation Using Soft Computing Techniques”,
World Academy of Science, Engineering and
Technology, 46, 2008.
[31] RshmaChawla, Deepak Ahlawat, “Improved
Software Development Effort Estimation Based
on Four Fuzzy Logic Functions”, International
Journal on Advanced Computer Theory and
Engineering (IJACTE), IRD India, ISSN (Print):
2319-2526, Vol. 4, No. 2, pp. 9-13, March 2015.
[32] Roger S Pressman, “Software Engineering-A
Practitioner’s Approach”, Tata McGraw-Hill
Edition 2010.
[33] RoheetBhatnagar, Vandana Bhattacharjee, Mrinal
Kanti Ghose, “ A Proposed Novel Framework for
Early Effort Estimation using Fuzzy Logic
Techniques”, Vol. 10, No. 14 (Ver. 1.0), pp. 66,
November 2010.
[34] Rahul Kumar Yadav,Dr. S. Niranjan , “Software
Effort Estimation Using Fuzzy Logic: A
Review”, International Journal of Engineering
Research & Technology (IJERT) Vol. 2, No. 5,
ISSN: 2278-0181, pp. 1377-1384, May 2013.
[35] RoheetBhatnagar, MrinalKanti Ghose, Vandana
Bhattacharjee, “Predicting the Early Stage
Software Development Effort using Mamdani
FIS”, Roheet Bhatnagar et al, (IJCSIT)
International Journal of Computer Science and
Information Technologies, Vol. 2, No. 4, pp.
1675-1678, ISSN:0975 – 9646, 2011.
[36] S.G MacDonell, and A.R Gray, “A comparison
of modelling techniques for software
development effort prediction”, Proceedings of
the International Conference on Neural
Information Processing and Intelligent
Information Systems, Dunedin, New Zealand,
Springer-Verlag, pp. 869–872, 1997.
[37] S.G MacDonell, and A.R Gray, “Fuzzy Logic for
Software Metric Models throughout the
Development Life-Cycle”, The Information
Science Discussion Paper Series, Number 99/20,
ISSN 1172-6024, September 1999.
[38] Xu, Z., Khoshgoftaar, T.M., “Identification of
fuzzy models of software cost estimation”,
Elsevier Fuzzy Sets and Systems 145 (1), pp.
141–163, 2004.
[39] Zikmund, Babin, Carr, Adhikari, and Griffin,
“Business Research Methods”, 8e, CENGAGE
Learning, 2013.