shippensburg university site telecommunications system
TRANSCRIPT
Shippensburg University
Site Telecommunications System Upgrade
SU 2014/3
HFL File No. 2014-0377.01
December 1, 2014
SITE TELECOMMUNICATIONS SYSTEM UPGRADE
SHIPPENSBURG UNIVERSITY
T A B L E O F C O N T E N T S
Section
Executive Summary 1
Proposed Recommendations
Cabling and Conduit Systems
Building Head-end Equipment
Manholes
Construction Phasing
System Management Software System
2
APPENDICES
Tab
Construction Cost Estimate 1
Site Plans 2
SITE TELECOMMUNICATIONS SYSTEM UPGRADE
SHIPPENSBURG UNIVERSITY
EXECUTIVE SUMMARY
The existing underground cabling system at Shippensburg University has been in place for over
twenty years and has served its useful life. The university desires to upgrade and expand upon
the existing system to incorporate new buildings that have already been added, and put itself in
a good position to provide service when additional buildings called for in the facility's master
plan have been constructed.
This report identifies a concept of serving each building from two distinct fiber optic cabling
paths while maintaining a single source of distribution for the copper cabling. The report
identifies the proposed cable quantities and routes that will be required to serve each building
with 24 strands of single mode fiber optic cabling from the existing data center in the MCT
Building, as well as from a future redundant data center in Grove Hall. New conduit routes are
indicated to identify those locations which currently do not have a ductbank installed, or those
which no known spare conduits currently exist.
For the copper cabling portion of the project, there will be new cabling installed that will
replace the existing older deteriorated cable, but not all of the existing copper cabling will be
replaced.
Additionally, various manholes need to be repaired and cleaned; those manholes are indicated in
the written part of the report. It is recommended that prior to the project commencing, the
existing spare conduits should be checked by pulling a mandrel equivalent to the size of the
conduit through the existing conduits to ensure that a clear path for the cable exists. This report
recommends that all of the new cables should be installed, terminated, and tested prior to the
removal of any of the existing cables so as to maintain a continuity of service to the buildings at
all times.
Finally, in order for the university to maintain an updated accounting of the underground
cabling, and provide a comprehensive method for documenting and managing changes to the
physical layer connectivity and assets of the campus, building, data center, or outside plant
network, a cable management software program should be provided. This cable manager
system should be provided as part of the construction contract and not only be provided, but be
SITE TELECOMMUNICATIONS SYSTEM UPGRADE
SHIPPENSBURG UNIVERSITY Page 2 of 5
completely programmed with all of the new cabling and components input into the program to
provide a comprehensive inventory of the newly installed components.
The estimated cost of construction for these upgrades, including a 10% contingency, is
$2,725,467. The breakdown of these costs without the contingency applied is indicated below.
Additionally, during the design process an investigation of the existing ductbanks and manholes
should be performed to confirm that spare pathways exist and are useable. It is estimated that
the cost to perform this work is $50,000.
PROPOSED RECOMMENDATIONS
Cabling and Conduit Systems
The university data center is located within the MCT Building. In order to create a backup to
this facility, the university will be constructing a second data center site within John L. Grove
Hall as a separate project. The fiber optic cabling for the campus distribution will originate in
each of these two locations. In most cases, the distribution will consist of 24 strands of
underground single mode optical fiber run to each building on campus from the MCT and the
Grove Hall data centers. Some of the smaller buildings, or buildings with limited connectivity
requirements, will only require 12 strands of fiber to each data center. Spare capacity will be
built into the cabling for connection to future buildings not yet constructed. The routing of the
cabling will be such that the paths shall be separate and distinct to eliminate the possibility of a
ductbank being cut and severing all communication to a particular run of buildings.
Manholes & Manhole Upgrades $411,723.90
Conduit Ductbanks $1,364,389.55
Cable: Copper and Optical Fiber $518,584.17
OSP Cable Management System $183,000.00
Total Construction Cost $2,477,697.62
Additional Costs
Contingency – 10% $247,769.76
Ductbank and Manhole Investigation (Performed during design process) $50,000.00
SITE TELECOMMUNICATIONS SYSTEM UPGRADE
SHIPPENSBURG UNIVERSITY Page 3 of 5
The existing underground ductbank system varies in age and condition. In order to ensure that
conduits which appear to be spare are truly useable, as part of the design services, each of the
conduits should have a mandrel pulled through them to clear the ducts and confirm that they are
in fact useable ducts. At the same time, a pull string should be installed and tagged for future
use. In order to perform this conduit testing, the manholes will likely need to have the water
pumped from them prior to entering them.
Drawing TS01C is provided as an attachment to this report. It shows the anticipated new
locations of ductbank that will be required for the installation of the copper and optical fiber
cabling. It also indicates the quantity of 4" conduits that will be installed in a concrete encased
ductbank and the number of conduits that require (3) 1¼" innerducts installed.
Drawing TS01OF indicates the quantity and starting and ending points of each optical fiber
cable that will pass through each section of ductbank. It also indicates the amount of fiber
required for each building and the quantity of total fibers in the ductbank.
Drawing TS01CC indicates the routing and quantities of copper cabling to be installed. The
copper cabling distribution will originate out of the Reed Annex Building which is currently the
demarcation point for the copper cabling on campus. The existing distribution from Reed
Annex is through the Reed Operations Center and will need to be rerouted to enable Reed
Operations Center to be demolished in the future. Not all of the existing copper cabling will be
replaced, only that which is indicated on the drawing. There will need to be locations where the
new copper is spliced into the existing system in existing manholes. These locations are
indicated on the drawing.
Building Head-end Equipment
Due to the change in the amount of fiber optic and copper cabling entering the buildings, there
will be some modifications required to the building head-end equipment as part of this project.
These modifications may include the addition of fiber patch panels and racks or cabinets to
house this equipment. A detailed survey of each building's MDF was not included as part of
this study to be able to indicate precisely which buildings will be affected, but during the design
process, this investigation will need to occur and modifications made during construction.
SITE TELECOMMUNICATIONS SYSTEM UPGRADE
SHIPPENSBURG UNIVERSITY Page 4 of 5
Manholes
Of the 70+ manholes currently installed as part of the telecommunications system, a number of
them need to have some upgrades performed on them. As a result of the new ductbank being
installed, there is a need for an additional number of manholes as well. In all, there will be a
need for 25 new manholes to be installed as part of the project. Also, it is recommended that
the manholes with extreme water infiltration have permanent electric sump pumps installed in
them. Additionally, it should be assumed that all manholes have some level of debris and
abandoned cabling installed in them that should be removed as part of this project. The
manholes which need some action taken on them are identified below.
MANHOLE NUMBER ACTION REQUIRED
2, 4, 8, 9, 13, 15, 16, 18, 21, 24, 29, 30, 32, 37a, 46, 49, 50, 51, 54, 55, 56, 60, 61
Install permanent sump pump/seal manholes
22, 23, 35, 37A, 42 Manholes will need to be increased in size to handle additional future cabling
3, 4, 6, 15, 17, 22, 23, 29, 32, 37A, 41, 46, 47, 52, 53, 54, 55, 56, 59, 62
Patching of concrete and sealing of conduits
Construction Phasing
Since the campus is in operation year-round, only minimal disruption of service to the
telecommunication system can be tolerated. Therefore, it should not be assumed that existing
conduits with existing cabling that will be demolished as part of the project, can be removed and
used for the installation of new cabling. In order to accomplish a seamless transition between
the new and old cabling, the new ductbank and cabling systems must be installed prior to
removal of any of the existing cabling. Cutover of cabling can occur at each individual building
then without loss of service. The length of the construction period should be approximately
12 months.
System Management Software System In order for the university to have ready access to the cabling, manholes, building head-end
equipment etc., the project should include the procurement of a management software system
that will organize all of this information into one readily accessible database as part of the
SITE TELECOMMUNICATIONS SYSTEM UPGRADE
SHIPPENSBURG UNIVERSITY Page 5 of 5
construction contract. One manufacturer of such a tool is Patch Manager. This software
system gives clear insight into the purpose and usage of every cable, device, and network
location. It is equipped with realistic modeling that maps one-to-one with the actual
infrastructure. Additionally, the program shall be fully populated indicating the quantity, type,
and location of the newly installed equipment as part of the construction contract so that at the
completion of the project, the university has a fully functioning and updated database of the
system.
I:\PROJECTS\2014\140300\140377X01\REPORTS\REVISED FINAL REPORT\14_1201_FINAL REVISED REPORT W TOC.DOCX
Appendix 1
Construction Cost Estimate
SITE TELECOMMUNICATIONS SYSTEM UPGRADE
SHIPPENSBURG UNIVERSITY
COST ESTIMATE
A Construction Cost Estimate is provided as part of this report. The estimate is compiled
in 2014 dollars and includes a breakdown of all of the anticipated equipment to be installed
as part of the upgrade project. The duct investigation should be performed as part of the
professional's Scope of Services and is therefore not covered in the construction cost.
JOB NAME: SHIPPENSBURG CAPITAL TELECOM STUDY
JOB #:
ITEM: CONDUIT / COPPER CABLE / DATE:
OPTICAL FIBER CABLE ESTIMATOR: PPH
SHEET 1 OF 2
MATERIAL COST LABOR COST LINE
ITEM DESCRIPTION QTY UNIT PER UNIT TOTAL PER UNIT TOTAL TOTAL
1 6'X8'X7' Manhole complete &
installed 25 EA 7,500.00 187,500.00 187,500.00
2 Remove debris / abandoned cables
within manholes 1 LOT 6,875.00 6,875.00 6,875.00
3 Remove abandoned OF cables
within conduit 1 LOT 9,860.00 9,860.00 9,860.00
4 Remove abandoned copper cables
within conduit 1 LOT 19,512.00 19,512.00 19,512.00
5 Manholes with water iinfilltration -
install sump pump 1 LOT 103,684.00 103,684.00 25,921.00 25,921.00 129,605.00
6 Concrete patch manholes 1 LOT 3,381.00 3,381.00 7,889.00 7,889.00 11,270.00
7 2-way ductbank, complete/installed 1,075 LF 66.00 70,950.00 44.00 47,300.00 118,250.00
8 4-way ductbank, complete/installed 6955 LF 75.00 521,625.00 50.00 347,750.00 869,375.00
9 6-way ductbank, complete/installed 750 LF 93.00 69,750.00 62.00 46,500.00 116,250.00
10 576 strand SM OF cable (UG) 2420 FT 5.24 12,680.80 0.90 2,178.00 14,858.80
11 360 strand SM OF cable (UG) 1950 FT 4.62 9,009.00 0.90 1,755.00 10,764.00
12 288 strand SM OF cable (UG) 2275 FT 2.86 6,506.50 0.90 2,047.50 8,554.00
13 216 strand SM OF cable (UG) 260 FT 2.70 702.00 0.90 234.00 936.00
14 192 strand SM OF cable (UG) 1125 FT 2.64 2,970.00 0.90 1,012.50 3,982.50
15 156 strand SM OF cable (UG) 1525 FT 1.95 2,973.75 0.90 1,372.50 4,346.25
16 144 strand SM OF cable (UG) 3500 FT 2.16 7,560.00 0.90 3,150.00 10,710.00
17 120 strand SM OF cable (UG) 220 FT 1.74 382.80 0.90 198.00 580.80
18 108 strand SM OF cable (UG) 865 FT 1.62 1,401.30 0.90 778.50 2,179.80
19 96 strand SM OF cable (UG) 1565 FT 1.33 2,081.45 0.90 1,408.50 3,489.95
20 72 strand SM OF cable (UG) 4300 FT 0.81 3,483.00 0.90 3,870.00 7,353.00
21 60 strand SM OF cable (UG) 1525 FT 0.90 1,372.50 0.90 1,372.50 2,745.00
22 48 strand SM OF cable (UG) 8,110 FT 0.59 4,784.90 0.90 7,299.00 12,083.90
23 24 strand SM OF cable (UG) 3225 FT 0.41 1,322.25 0.90 2,902.50 4,224.75
24 1800 pr, 24 ga OSP copper Ca 690 FT 48.08 33,175.20 3.60 2,484.00 35,659.20
25 900 pr, 24 ga OSP copper Ca 2120 FT 22.74 48,208.80 3.00 6,360.00 54,568.80
26 600 pr, 24 ga OSP copper Ca 600 FT 14.94 8,964.00 3.00 1,800.00 10,764.00
27 400 pr, 24 ga OSP copper Ca 545 FT 11.50 6,267.50 2.10 1,144.50 7,412.00
28 300 pr, 24 ga OSP copper Ca 2,665 FT 8.37 22,306.05 2.10 5,596.50 27,902.55
28 100 pr, 24 ga OSP copper Ca 1185 FT 5.58 6,612.30 1.20 1,422.00 8,034.30
30 Copper Splice Case 8 EA 261.30 2,090.40 60.00 480.00 2,570.40
31 Building Ent Term e/w GT Protect 8 EA 648.24 5,185.92 120.00 960.00 6,145.92
32 Copper Cable splicing / Testing 405 HR 60.00 24,300.00 24,300.00
33 (1)-19" rack e/w vert wire managers 2 EA 494.63 989.26 240.00 480.00 1,469.26
34 PCHO4U conn housing fully equip
for 2 buildings 6 EA 1,791.52 10,749.12 120.00 720.00 11,469.12
35 Optical Fiber Splice Case 35 EA 480.73 16,825.55 120.00 4,200.00 21,025.55
36 PCHO1U conn housing fully equip
with (1) SM-LC connector panels 16 EA 469.43 7,510.88 240.00 3,840.00 11,350.88
37 PCHO1U conn housing fully equip
with (2) SM-LC connector panels 31 EA 651.09 20,183.79 240.00 7,440.00 27,623.79
38 Pigtails LC-SM factory (12) 142 EA 191.06 27,130.52 27,130.52
39 Optical Fiber Splicing / testing Labor 300 HR 60.00 18,000.00 18,000.00
Subtotal 1,230,319.54 620,412.50 1,850,732.04
2014-0377.01
12/1/2014
SubmissionCONSTRUCTION COST ESTIMATE
HFLCCEST.XLT Revised: 12/1/2014
JOB NAME: SHIPPENSBURG CAPITAL TELECOM STUDY
JOB #:
ITEM: CONDUIT / COPPER CABLE / DATE:
OPTICAL FIBER CABLE ESTIMATOR: PPH
SHEET 2 OF 2
MATERIAL COST LABOR COST LINE
ITEM DESCRIPTION QTY UNIT PER UNIT TOTAL PER UNIT TOTAL TOTAL
Subtotal Sheet 1 1,230,319.54 620,412.50 1,850,732.04
40 OSP Cable Management Software 1 EA 50,000.00 50,000.00 100,000.00 100,000.00 150,000.00
Subtotal 1,280,319.54 720,412.50 2,000,732.04
Overhead - 10% 200,073.20
Subtotal 2,200,805.24
Profit - 10% 200,073.20
Subtotal 2,400,878.45
Tax On Material 76,819.17
Subtotal 2,477,697.62
Contingency - 10% 247,769.76
TOTAL 2,725,467.38
1
2
3
4 OSP Cable Management System
$518,584.17
CONSTRUCTION COST ESTIMATE Submission
2014-0377.01
12/1/2014
TELECOMMUNICATIONS RENOVATION COST OPINION
TOTAL $2,477,697.62
$183,000.00
Construction Services
Manholes & Manhole Upgrades
Conduit Ductbanks
Cable : Copper and Optical Fiber
$411,723.90
$1,364,389.55
HFLCCEST.XLT Revised: 12/1/2014
Appendix 2
Site Plans