sgt5-8000h scc5-8000h 1s experience of commercial...
TRANSCRIPT
SGT5-8000HSCC5-8000H 1S
Experience of Commercial
Energy Sector
© Siemens AG 2012
Experience of Commercial Operation at Irsching 4
ANIMP-ATI, Sesto San Giovanni
26 June 2012
Massimo Gianfreda
8000H Overview
Validation Status
Summary
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 2
Summary
Energy Sector
© Siemens AG 2012
SGT6 2000E
SGT5 2000E
SGT6 4000F
SGT6 5000F
SGT5 4000F 292
200
187
168
113
375SGT5 8000H
Siemens Large Scale Gas Turbines:Product Portfolio for 50 Hz and 60 Hz
SGT6 8000H 274
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 3
SGT6 2000E
Output in MW @ ISO conditions
113
8000H Program Overview
Irsch
ing
4
Program Launch – Concept Phase 01 Oct 2000
Gate 1: Product Strategy Release 21 Mar 2001
Gate 2: Start GT/CC Basic Design 05 Nov 2001
Gate 3: Product Release 17 Aug 2004
1st 50Hz engine ex Works Berlin 30 Apr 2007
1st Fire 20 Dec 2007
1st Synchronization to grid 07 Mar 2008
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 4
Irsch
ing
4B
TF
1st Synchronization to grid 07 Mar 2008
1st Base Load 24 Apr 2008
End of 50Hz GT Test & Validation Phase 28 Aug 2009
Gate 4: Series Release 22 Jun 2010
Combined Cycle Commissioning & Testing Jan – Jul 2011
1st 60 Hz engine es works Berlin Jan 2011
1st fire 60Hz engine (Berlin Test Facility - BTF) Sept 2011
End of 60Hz Test & Validation Phase Jul 2012
SGT-8000H engine conceptbased on harmonization and new technology
Siemens V Design Siemens W Design
Turbine cylinder
Turbine vane carrier
Front hollow shaft
Bearings
Turbine features
Turbine diffuser
Single tie bolt
Compr. stat. design
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 5
Turbine vane carrier
Exit housing
Bearings
Compressor cylinder
Turbine diffuserCompr. stat. design
Secondary Air System
ULN can-annular combustion systemHarmonized
Compressor
The SGT-8000H concept uses proven features from Siemens and
(former) Westinghouse engines and introduces new technology
> 60% combined
cycle efficiency
SGT5-8000HEfficient & Flexible
4 stages of fast acting variable-
pitch guide vanes (VGV) allowing
for improved part load efficiency and high load transients
Proven rotor design
(Hirth serration,
central tie rod, internal
Evolutionary 3D blading
3D Four stage turbine with
Advanced Can Annular
combustion system
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 6
Designed for >60% efficiency in combined cycleand best in class operational flexibility
central tie rod, internal
cooling air passages)
for world class fast (cold) start and hot restart capability
High cycling capability due
to fully internally air cooled
turbine section
3D Four stage turbine with
advanced materials and
thermal barrier coating
HCO for reduced
clearance losses
Transient protection of clearances
for reduced degradation with
hydraulic clearance optimization (HCO) active clearance control
Performance features
Flexibility features
TVC roll out/roll in capability
Roll out/in capability of the turbine vane carrier enables exchange of stationary turbine hardware without rotor lift
Sequence and tooling successfully tested during final assembly and prototype test
Removable turbine blades and vanes
SGT5-8000HDesigned for serviceability
Rollout-Rollin of TVC w/o rotor lift Blade 1 removal
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 7
Removable compressor blades
All rotating blades replaceable without rotor de-stack or lift.
All blades removable w/o rotor lift
Vane 1 and blade 1 removable w/o cover lift (access through combustion chamber)
Blade 4 removable w/o cover lift(towards the exhaust end)
Removable turbine blades and vanes
Serviceability – a key design factor to assureoptimized outage time and high availability
Combustor Handling Tool for safety and efficiency
Rollout-Rollin of TVC w/o rotor lift Blade 1 removal
Possible heat extraction per GT Typein large CHP-CCPPs (Examples)
SCC5-2000E (1x1)
SCC5-4000F 1S
SCC5-8000H 1S 570MW
430MW
230MW
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 8
SGT5-2000E SGT5-4000F SGT5-8000H
50 100 150 200 250 300 3500 400
possible heat extraction [MWth]
SGT5-8000H / SCC5-8000HSignificant Increase of CC Efficiency
Placeholder for picture,
size 13 x 14,68 cm
■ Increased PR + 0,2 %
■ Increased TIT combined
with cooling air reduction + 0,8 %
■ Improved component
efficiencies + 0,2 %
■ Fuel Preheating of 215°C + 0,1 %
Eff
icie
nc
y, %
10
16
12
14
1820222630
1100
1150
1200
1250
1300
550
600
650
Turbine Inlet Temperature
(acc. to ISO 2314)
Compressor
Pressure Ratio
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 9
Siemens 8000H significantly increases efficiency by up to 1,7%-pts. in
combined cycle.
Without compromising plant flexibility!
■ Fuel Preheating of 215°C + 0,1 %
■ Advanced water/steam cycle (600°C & 171 bar) + 0,4 %
Specific Power Output, kW/(kg/s)
1000
1050
450
500 Turbine Exhaust Temperature
SGT-8000HDirect scaling approach
Speed x 1.2
÷÷÷÷
50Hz to 60Hz
Scaling rules
SGT5-8000H
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 10
Harmonized design features allow validation experiencetransfer from 50 to 60 Hz
SGT6-8000H
Dimensions ÷÷÷÷ 1.2
Power, Mass Flow
÷÷÷÷ 1.44
Stresses & Temperatures
x 1.0
Efficiency x ~1.0
Configuration and Performance Overview
50 Hz 60 Hz
SGT-PAC 8000H 375 MW 274 MW
40 % 40 %
SCC-PAC 8000H 1S
SGT5/6-8000H
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 11
SCC-PAC 8000H 1S 570 MW 410 MW
60 % 60 %
SCC-PAC 8000H 2x1 1.145 MW 824 MW
60 % 60 %
SCC-PAC 8000H 3x1 - - 1.236 MW
- - 60 %
at ISO conditions
SCC5/6-8000H 1S
SCC5/6-8000H 2x1
8000H Overview
Validation Status
Summary
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 12
Summary
Energy Sector
© Siemens AG 2012
Sales PreparationStrategic Product Planning Design Design Implementation Validation
Product StrategyTechn. Acquisition,
Product,Technology & Developm. Planning
Conceptual
DesignBasic
Design
Commerciali-
zation Planning
Manufacturing &
Assembly
Erection, Installation,Commissioning and
Trial Operation
Product Monitoring
Performance & Reliability Validation
Final Design &
Procurement
Parts tests
• Casting blades & vanes
• Materials, coatings
• Manufacturing trials etc.
• Stress / Strain verification
50Hz Prototype GT field validation
8000H Program includesComprehensive Validation and Testing Concept
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 13
Component tests
• Combustion system rig test
• Cover plate rig test
• Mock up
Systems tests
• Compressor test &
• Combustion system test
at test bed Berlin
Prototype CC field operation
13
Siemens carried out the most comprehensive test program in the industry
60Hz Prototype Validation
Irsching 4, Project Overview
Overall schedule from Contract to Combined Cycle extension and Commercial Operation (PAC)
Open Cycle
Validation 8000H
Phase 1SGT5-8000H
open cycle
Field ValidationSGT5-8000H
2011201020092008200720062005Q4Q3Q2Q1Q4Q3Q3Q2Q1Q4Q3Q2Q1Q4Q3Q2Q1 Q2Q1Q4Q3Q2Q1Q4Q3Q2Q1Q4
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 14
Validation 8000H
Reference PlantSCC5-8000H 1S
Phase 2Combined Cycle
extension
SGT5-8000H
18 months
Irsching 4 Reference
Power PlantSCC5-4000F
experiance
Combined Cycle
PAC
SCC5-8000H 1S Single Shaft Power Train
Irsching 4, Phase II, Combined Cycle ExtensionInstallation Completed on Schedule
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 15
Plant in commercial operation since July 2011
Plant View, June 2011 Power Train View, June 2011
SGT5-8000H ValidationExample: Simple Cycle Start-up
Increased loading & acceleration rate reduces startup time
Standard Loading: 25 Minutes to 375MW
Fast Loading: 10 Minutes to 350 MW
Startup w/ fast loading
Lo
ad
ing
Normal Startup
60%
80%
100%
Ou
tpu
t (%
Lo
ad
)
350 MW
in 10 minutes
375 MW
in 25 min.
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 16
Accele
rati
on
Lo
ad
ing
0%
20%
40%
60%
Ou
tpu
t (%
Lo
ad
)
0
500
1000
1500
2000
2500
3000
0 200 400 600 800 1000 1200 1400 1600 1800
Time (seconds)
Sp
eed
(R
PM
)
6 minutes to
accelerate and sync.
Proven: GT Fast start-up capability due to internal air cooling concept
SGT5-8000H ValidationExample: Performance/Emissions
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 17
387,1 MW
Fuel preheat onEmissions met
5-8000H Validation:Serviceability
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 18
Rollout-Rollin of TVC w/o rotor liftBlade 1 removal
Rotor liftRotor de-
stackingBlade 1 removal
Excellent serviceability proven on customer site boundaries
Reality Check:World Class Flexibility (Plant Hot Start)
GT speed ST speed Plant Load
30min
Hot start capability:
540 MW in 30 min.
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 19
Promised and Delivered !
> ½ GW in ½ hour
Load increase64 MW (12%) in 10 s
CC load
Load decrease250 MW (45%) in 6 s
Reality Check:World Class Flexibility (Grid Code Compliance)
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 20
Promised and Delivered !
Frequency simulation -500mHz
Most stringent frequency response target overachieved
Island Operation target achieved.
We are prepared for the upcoming ENTSO-
E network code
Reality Check:World Class Performance
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 21
Promised and Delivered !
SCC5-8000H 1S Irsching 4Typical weekly load profile (summer)
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 22
SGT5-8000H / Irsching 4Operational Status
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 23
Phase I Phase IIGT Testing CC Extension
Starts 85 >295EOH 4365 >11.000
status 2012-05-31
more than 380 starts & 15.500 EOH’s so far
SGT-8000H References
1x 5-8000H, Germany
>15.500 EOH
6x 6-8000H, USA
status June 2012
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 24
3x PAC 2013, 3x PAC2014
1x 6-8000H, South Korea
PAC 2013
SGT-8000H References
1x 6-8000H, South Korea
PAC 2014
2x 6-8000H, South Korea
status June 2012
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 25
PAC 2014
1x 5-8000H, Germany
PAC 2015
8000H Overview
Validation Status
Summary
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 26
Summary
Energy Sector
© Siemens AG 2012
Siemens has spent >10 years with significant R&D investment to
create a robust product and confirmed both integrity & performance
to ensure highest customer value at lowest customer risk.
The SGT-8000H / SCC-8000H
has proven:
H Class Performance >60%
8000HSummary
© Siemens AG 2012Energy SectorANIMP-ATI, Sesto San Giovanni, 26 June 2012Fig. 27
The SCC-8000H plants promise World Class Power, Efficiency
and Operational Flexibility
H Class Performance >60%
beyond
F Class Flexibility