sandy point sewage treatment plant upgrade: pievc … · vulnerabilty assessement david trudel,...
TRANSCRIPT
SANDY POINT SEWAGE TREATMENT PLANT UPGRADE: PIEVC CLIMATE CHANGE VULNERABILTY ASSESSEMENT
David Trudel, P.Eng. CBCL Limited
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
Environment
PIEVC IN A SMALL COMMUNITY: PRE-DESIGN
Presentation Outline:
• Community Profile
• Description of Existing System
• Design Criteria
• PIEVC
• PIEVC at Pre-Design Stage
• Recommendations for PIEVC in Small Communities
• Ideas for Implementation
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
MUNICIPALITY OF THE DISTRICT OF SHELBURNE, NS
Community Profile:
• Population – 4,408
• Rural, coastal community in southwest NS (1,808.5 km2)
• Declining population, low population density dispersed along coast
• Established in 1885, one of five municipal units in Shelburne County
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
MUNICIPALITY OF THE DISTRICT OF SHELBURNE, NS
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
DESCRIPTION OF EXISTING SYSTEM
Extended Aeration STP:
• Constructed in 1969
• 30,000 USgpd Capacity
• Overloaded, not in compliance with NSE discharge criteria
• Wet weather flows affecting plant performance
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
DESIGN CRITERIA
Sewage Treatment Plant Upgrade:
• Expansion of Industrial Park (add’l 29 acres)
• 5,000 Usgpd
• Average Daily Flow – 100,000 USgpd
• Maximum Daily Flow – 350,000 USgpd
• Secondary Treatment
• Modular Growth
• Industrial Park / Sandy Point Road
• Option of Receipt of Septage
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
PIEVC
Public Infrastructure Engineering
Vulnerability Committee (PIEVC):
• Created August 2005
• Co-funded by NRCan & Engineers Canada
• Committee developed the PIEVC Protocol, a formalized process to assess climate risks to infrastructure
• Goal - ensure that decision makers always consider climate change as an integral part of planning, designing, constructing, operating, maintaining and rehabilitating infrastructure
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
PIEVC
Project Lifecycle:
• Pre-Design
• Design Criteria
• Site Selection
• Technology Selection
• PIEVC
• Detailed Design
• Tendering
• Construction
• Operations
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
• PIEVC
• Project Definition
• Data Gathering & Sufficiency
• Risk Assessment
• Engineering Analysis
• Conclusions & Recommendations
DATA GATHERING & SUFFICIENCY
Temperature and Precipitation:
• For current climate (1961 to 1990) the greatest three (3) day total rainfall is 87mm
• For projected climate (2071 to 2100) the greatest three (3) day total rainfall is projected to increase to 116mm
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
DATA GATHERING & SUFFICIENCY
Storms, Storm Surges & Sea Level Rise:
• Ultimately, high water levels result from a combination high tides, sea level rise, storm surge, sinking land, and possibly wave run-up
• Sea Level Elevation:
• 40 – 132 cm average sea level rise globally
• Crustal subsidence (sinking land) 10 – 15 cm in 100 years
• Frost and Freeze/Thaw cycling predicted to decrease
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
DATA GATHERING & SUFFICIENCY
Storm Surge (40 year return) - Atlantic Canada
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
DATA GATHERING & SUFFICIENCY
Extreme Rainfall Statistics – Atlantic Canada
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
VULNERABILITY (RISK) ASSESSMENT
Climate – Infrastructure Interactions
• Total of 45 infrastructure components identified
• Total of 24 Climate events identified
• Of 1080 possible interactions, 404 were identified as having potential consequences
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
VULNERABILITY (RISK) ASSESSMENT
Methodology:
• Engineering team conducted pre-assessment of risk using matrix
• Limited resources for workshop:
• Modified workshop process to prioritize interactions discussed and to rank interactions as High/Medium/Low risk
• 14/404 interactions were High Risk
• 111/404 interactions were Medium Risk
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
R = P x S
R: Risk
P: Probability
S: Severity
VULNERABILITY (RISK) ASSESSMENT
Workshop:
• Participants identified opportunities for mitigation & adaptive capacity for high risk interactions: • The majority of interactions related to power supply,
communications & access to infrastructure during extreme climate events
• SCADA complete with UPS and backup power system requirements identified
• Shut-off for existing pumping station when seawater ingress experienced
• Planned increases in maintenance due to climate events
• Installation of weather station at the plant site
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
ENGINEERING (INDICATOR) ANALYSIS
Methodology:
• Calculate the projected total load/capacity of the infrastructure:
• Definitions
• Direct Measurements
• Engineering Calculations
• Assumptions based on Professional Judgement
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
ENGINEERING (INDICATOR) ANALYSIS
• Much of the data required for the Engineering Analysis did not exist or was difficult to obtain
• Pre-design stage
• Limited climate data available
• Professional judgment and experience were used where data was not available
• For the thirty-five (35) components for which potential vulnerabilities were identified
• 21 remedial engineering actions recommended
• 4 management actions being recommended
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
RECOMMENDATIONS
Summary:
• Reduce I&I into the collection system
• Install stand-by power at pumping stations
• Ensure process building meets code for hurricane resistance
• Install radio communications system at the pumping stations and process building
• Install high level pump shutoffs at the existing pumping station
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
RECOMMENDATIONS
Summary:
• Install a bypass on the grit removal system
• Implement a policy to protect staff from hurricanes, storm surges and ice storms
• Discuss safe conditions for deliveries from septage hauling companies
• Adjust scheduling to accommodate required maintenance
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
CONSTRUCTION
New STP Constructed 2011-12
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
CONSTRUCTION
Elevation Above Chart Datum
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
PIEVC PROCESS AT PRE-DESIGN STAGE
Summary:
• Project was small - PIEVC implemented at the Pre-Design stage:
• Protocol as presented was a useful complement to the Pre-Design process and assisted in site selection, technology selection and design of components
• Difficult to assess the detailed system components at such an early stage in the design process
• Protocol is currently ‘one-size-fits-all’ but it was flexible enough to adapt to fit project
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
PROJECT UPDATE
• Implemented stand-by power & dialer system for high level alarms at PS’
• Inspected collection system - identified I&I issues to be addressed
• Industrial Park servicing completed 2013-14
• New 80-unit seniors housing complex connected to STP
• SRS installed & commissioned in August 2013 (Volumes < 1% of plant throughput)
• New STP is much more resilient to heavy precipitation events and power outages
• PIEVC results used to supplement MCCAP
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB
QUESTIONS?
Climate Change Adaptation and Infrastructure 2016 – Moncton, NB