safety report (pre-opening) - highways...
TRANSCRIPT
MAJOR PROJECTS DIRECTORATE
PCF Quality Control M25 LUS Section 5
Page 1 of 84
M25 DBFO LUS SECTION 5
Safety Report (Pre-opening)
JOB NUMBER: 5108945 DOCUMENT REF: 5108945-ATK-1204-S5-DOC-X-0130
F Final P.Whitfield J.P Doherty J.P Doherty S.Moore 13/02/14
E PCF Stage 6 sign-off P.Whitfield J.P Doherty J.P Doherty S.Moore 5/12/13
D PCF Stage 6 update P.Whitfield J.P Doherty J.P Doherty S.Moore 18/10/13
C For PCF Stage 3 sign-off P.Whitfield J.P Doherty R.Thorn S.Moore 30/4/13
B For PCF Stage 3 sign-off P.Whitfield J.P Doherty R.Thorn S.Moore 25/3/13
A HA Review P.Whitfield J.P Doherty R.Thorn S.Moore 25/08/12
Originated Checked Reviewed Authorised Date
Revision Purpose Description
Distribution Record
Copy No. Copy Holder Document Revision
C D E F G
01 Business Collaborator * * * *
02 Atkins File Copy * * * *
Note: This Document will be distributed via Business Collaborator. Details of distribution can be obtained from that system
Please note that Section 2.2 of the attached Product provides the introduction and background to the project. The text has been approved by the Highways Agency Project Leader for inclusion in all the PCF Products for this project. These sections have been included for information purposes only, and will be common across the whole suit of PCF Products for the project. You do not need to review and comment on these Sections as a PCF consultee.
M25 LUS Section 5 Safety Report (pre-opening)
Page 1
Contents
Section Page
PCF Product Sign Off Sheet 2
1. Executive Summary 6
1.1 Purpose of this Document 6
1.2 Safety Objectives 6
1.3 Hazard Log and Risk Assessment Activity 6
1.4 Safety Plan Activities 7
1.5 Safety Conclusions 7
1.6 Outstanding Key Actions 7
2. Introduction 8
2.1 Scheme Background 8
2.2 Project Description 8
2.3 Report Scope and Objectives 9
2.4 Document Status, History and Future Development 10
2.5 Contents of this Report 11
3. Scenario Appraisal 12
3.1 Typical MM-ALR Scheme 12
3.2 Scheme Data and Assumptions 13
4. Safety Objectives 14
4.1 Safety Objectives for Road Users and Road Workers 14
4.2 Safety Baseline 14
4.3 Methodology for Achieving Safety Objectives 14
4.4 Evidence that Safety Objectives have been/will be achieved 15
4.5 Future Validation of Safety Objectives 15
4.6 Post Opening Project Evaluation (POPE) 16
4.7 Additional HA centralised monitoring 17
4.8 Monitoring Required at Scheme Level 18
5. Safety Management System: Evidence a Robust System Followed 19
5.2 Robust Project Safety Management Process in Place 20
5.3 Robust Approval Process in Place 20
5.4 Road Safety Audits 21
5.5 Project Safety Control Review Group (PSCRG) 22
6. Hazard Log Scoring 24
6.1 Initial Population of the Hazard Log 24
6.2 Mitigation and Design Features 25
6.3 Assumptions 25
6.4 Provision of a Controlled Environment 25
6.5 Hazard Log Results 29
6.6 Detailed Analysis 30
6.7 Close-out of Hazard Log Actions 32
6.8 Safety Tasks 33
6.9 Safety Requirements 33
6.10 Compliance with Requirements and impact on the Safety Report 33
6.11 Evidence that Safety Requirements and Restrictions met by Design 34
M25 LUS Section 5 Safety Report (pre-opening)
Page 2
6.12 Verification Reviews 34
7. Project Practice: Methods and Processes been followed during the Project 35
7.1 Design Compatibility with Standards and Regulations 35
7.2 Use of Good Practice during the Project 35
8. Conclusions 36
8.1 General Conclusions 36
8.2 Outstanding Key Actions 36
Appendix A – Hazard Scoring Indices 38
Appendix B – Hazard Log Scores 42
Appendix C – Previously Outstanding Safety Tasks 54
Appendix D – Safety Requirements 59
Appendix E – Safety Requirements Verification 64
M25 LUS Section 5 Safety Report (pre-opening)
Page 3
Glossary
Acronym/Term Meaning/Explanation
AMI Advanced Motorway Indicator
AQMA Air Quality Management Area
AST Appraisal Summary Table
ATC Automatic Traffic Count
ATM Active Traffic Management
Auxiliary Lane An additional lane at the side of the mainline carriageway to provide increased merge or diverge opportunity or additional space for weaving traffic
BAS Biodiversity Alert Site
SBB Skanska Balfour Beatty Joint Venture
BT British Telecom
ALR All Lane Running
CDM Regulations Construction (Design and Management) Regulations
Central Reserve The area that separates the carriageways of a dual carriageway / motorway exclusive of any hard strips
CM Controlled Motorway
COBA Cost Benefit Analysis
CSR Client Scheme Requirements
CWS Country Wildlife Site
D3M Dual three lane motorway
D4M Dual four lane motorway
DHS Dynamic Use of the Hard Shoulder
DfT Department for Transport
DMRB Design Manual for Roads and Bridges
DROBB Double Rail Open Box Beam (safety barrier)
EAR Environmental Assessment Report
EcAR Economic Appraisal Report
EIA Environmental Impact Assessment
EMMR1TAM East Midlands M1 Traffic Assessment Model
EMMR Existing Motorway Minimum Requirements
ERA Emergency Refuge Area
ERT Emergency Roadside Telephone
ES Environmental Statement
ESS Entry Stop Signal
EU European Union
Ghost Island An area of the carriageway suitably marked to separate lanes of traffic travelling in the same direction on both merge and diverge layouts.
HA Highways Agency
Headroom The minimum distance between the surface of the highway cross-section and the deflected structure
HGV Heavy Goods Vehicle
HVCB Higher Vertical Concrete Barrier
IAN Interim Advice Note
INCA INcident Cost-benefit Assessment – economics tools for calculating delays and travel time variability costs
ITR Indirect Tax Revenue
JTDB Journey Time Database
LBS Lane Below Signal; refer to terminology at the end of this list
LMVR Local Model Validation Report
M25 LUS Section 5 Safety Report (pre-opening)
Page 4
Acronym/Term Meaning/Explanation
LGV Light Goods Vehicle
LWS Local Wildlife Sites
MAC Managing Agent Contractor
Mainline The carriageway carrying the main flow of traffic (generally traffic passing straight through a junction or interchange)
Maintained Headroom The minimum value of Headroom that must be preserved at all times
MHS Maintenance Hard Standing
MCDHW Manual of Contract Documents for Highway Work
MIDAS Motorway Incident and Automated Signals
MM Managed Motorway(s)
MM-ALR Managed Motorways All Lanes Running
MMDO Managed Motorways Delivery Office
MMSG Managed Motorways Steering Group
MRSS Maintenance and Repair Strategy Statement
MSA Motorway Service Area
NDD HA Network Delivery and Development Directorate
NetServ HA Network Services Directorate
North facing slip roads The merge and diverge on the north side of a junction
Nose A paved area, approximately triangular in shape, between the connector road and the mainline at a merge or diverge
NRTS National Roads Telecommunications Services
NSCRG National Safety & Control Review Group
NTEM National Trip End Model
OBB Open Box Beam (safety barrier)
Overbridge A bridge that spans the road under consideration
Parallel Merge / Diverge
A layout where an auxiliary lane is provided alongside the mainline carriageway
PCF Project Control Framework
PIA Personal Injury Accident
PIE Public Information Exhibition
P4L Permanent Four Lanes
PL Project Leader
POP Police Observation Platforms
POPE Post Opening Project Evaluation
PSSR Preliminary Sources Study Report
PSCRG Project Safety & Control Review Group
PTJR Permanent Through Junction Running
PTZ Pan Tilt Zoom (CCTV)
QUADRO QUeues And Delays at ROadworks – economics programme to evaluate delay impacts during construction
Ramp Metering The control of vehicles joining the main carriageway from slip roads by the means of traffic lights or similar
RCC Regional Control Centre
RPI Retail Price Index
SAR Scheme Assessment Report
SBI Site of Biological Importance
SGAR Stage Gate Assessment Reviews
SoS Secretary of State
South facing slip roads The merge and diverge on the south side of the junction
SoW Start of Works
SPZ Source Protection Zone
SRO Senior Responsible Owner (Highways Agency)
SSD Stopping Site Distance
SSSI Site of Special Scientific Interest
M25 LUS Section 5 Safety Report (pre-opening)
Page 5
Acronym/Term Meaning/Explanation
Taper Merge / Diverge A layout where merging or diverging traffic joins or leaves the mainline carriageway through an area forming a funnel to or flare from the mainline carriageway
TCB Tensioned Corrugated Beam (safety barrier)
TIS Traffic Impact Study
TERN Trans European Road Network
TFR Traffic Forecasting Report
TJR Through Junction Running
TOS Traffic Officer Service
TPI Targeted Programme of Improvements
TRADS HA Traffic Information Data base, containing traffic flows for motorways and major trunk roads in England
TM Traffic Management
TMD HA Traffic Management Directorate
TUBA Transport Users Benefit Appraisal
Underbridge A bridge that carries the road under consideration
VCB Vertical Concrete Barrier
Verge Any nominally flat area between the edge of the paved width and either the start of an adjacent side or slope, in the absence of a side slope, the highway boundary or bridge parapet
VMS Variable Message Signs
VMSL Variable Mandatory Speed Limit
VOC Vehicle Operating Costs
VPH Vehicles per Hour
VRS Vehicle Restraint System
Weaving Section The length of the carriageway between a successive merge or lane gain and diverge or lane drop
WebTAG Website for Transport Analysis Guidance
M25 LUS Section 5 Safety Report (pre-opening)
Page 6
1. Executive Summary
1.1 Purpose of this Document
This Safety Report (Pre-opening version) has been produced towards the end of the construction
stage of Section 5A of the M25 LUS Section 5 scheme. At this stage the Safety Report contains a
summary of the safety activities, identified in the Safety Plan, that have taken place to date and
describes the available evidence that demonstrates that the scheme Safety Objectives will be
achieved.
Different phased opening dates are planned for J23-J25 (Section 5A) and J25-J27 (Section 5B). Section 5A will open first and the document is presented for approval for Section 5A only. An update will be provided in early 2014 to support the opening of Section 5B.
A further version of the document at PCF stage 7 will report on the safety performance of the fully
operational scheme.
1.2 Safety Objectives
Before a Managed Motorway is implemented it has to be demonstrated in advance that the
scheme Safety Objectives are likely to be met. The PCF Product for the Safety Plan describes the
Safety Objectives as follows:
Road Users:
The safety impact of the project will be measured by comparing the “before” and “after” casualty numbers and severities using 3 year before data (the safety baseline) and 3 year after data. The project will meet its Safety Objective for road users if it is demonstrated for a period of three years after becoming fully operational that:
the average number of Fatal and Weighted Injuries (FWI) casualties per year is no more than the safety baseline, and
the rate of FWIs per billion vehicle miles per annum is no more than the safety baseline, and
no population (e.g. car drivers, pedestrians, HGV drivers and motorcyclists) is adversely affected in terms of safety.
Road Workers:
There will be no specific numerical safety objective set for road workers. These risks will be
managed to be “So Far As Is Reasonably Practicable.
1.3 Hazard Log and Risk Assessment Activity
The risk assessment work, through the application of the Hazard Log process, provides a method
for identifying the potential barriers to the good safety performance of the scheme. Following
identification of high scoring hazards, the design of the key features were scrutinised. Individual
design disciplines undertook a number of risk assessments via Hazard Log Safety Tasks, the
results of which contributed to the formation of a list of Safety Requirements for the scheme.
These Safety Requirements identify key features, working methods or actions which are
considered necessary for the safe functioning of the scheme.
M25 LUS Section 5 Safety Report (pre-opening)
Page 7
1.4 Safety Plan Activities
The Safety Team1 has had an opportunity to review and contribute to a number of PCF
deliverables which will have an impact on the safe operation of the scheme. This involvement has
insured that the safety challenges identified in the Safety Plan and throughout the Hazard Log
process have been properly addressed.
A Project Safety Control Review Group (PSCRG) has been set up and has provided an
opportunity for key design decisions to be challenged by a range of stakeholders.
1.5 Safety Conclusions
The results of the quantitative assessment indicate that the risk after Managed
Motorway implementation is likely to be lower for all populations of road users,
including road workers.
Therefore the evidence available at this time suggests that the Safety Objectives are achievable
for both road users and road workers. The evidence is provided by:
The work done to complete the safety activities outlined in the scheme Safety Plan.
The results of the scheme Hazard Log Risk Assessment activity.
The results of the generic programme level Hazard Log Risk Assessment activity, including
driver simulation.
Verification of Safety Requirements
1.6 Outstanding Key Actions
A Stage 3 (pre-opening) Road Safety Audit Report will be required in accordance with DMRB HD19; the process can be phased to suit incremental go-live dates for different links.
There is one2 outstanding Departure from Standard; confirmation of approval should be
ascertained.
The Scheme Safety Requirements have been subject to a verification assessment, seeking
evidence of compliance. The results of this exercise are listed at Appendix E.
Appendix E shows a number of Safety Requirements that cannot be verified at this time and
therefore these should be re-checked later. These are further sub-divided into two categories:
Those that should be fully verified before any decision to “go-live” for ALR operating
regime is taken
Those that could be closed-out shortly after ALR “go-live”
Both types of un-verified Safety Requirements must be added to a single central action tracker to ensure they are kept under regular review before “go live”. The necessary action is for the SRO to satisfy himself that these outstanding Safety Requirements are all closed out before the ALR phase of the scheme opens.
1 The Safety Team is currently an Atkins Team. The term is included throughout the document in recognition that as the project
progresses responsibility may changes, but regardless of any changes in project resourcing arrangements it is envisaged that a team
with sufficient competence in matters of safety will be retained. The Safety Plan set out the agreed arrangements and any changes
would require client authorisation through a revised Safety Plan.
2 Webdas ref 69708
M25 LUS Section 5 Safety Report (pre-opening)
Page 8
2. Introduction
2.1 Scheme Background
2.1.1 In 2002, the M25 London Orbit Multi-Modal Study (ORBIT MMS) recommended the provision of additional capacity on the M25 Junctions 5 to 7 (Section 2) and on the M25 Junctions 23 to 27 (Section 5), generally in the form of one additional lane in each direction. Subsequently, the Advanced Motorway Signalling and Traffic Management Feasibility Study (Department for Transport (DfT), 2008) concluded that Hard Shoulder Running (HSR) could provide a large proportion of the benefits of widening at significantly lower cost.
2.1.2 A scheme was developed for an option called HSR and the environmental effects of this proposal were reported in the Stage 2 Environmental Assessment Report (2010). This scheme was further refined as part of the Stage 3 commission but the scheme was then put on hold in the autumn of 2010 pending the government’s Comprehensive Spending Review (CSR). In the spring of 2011 the schemes to upgrade the M25 in Section 2 and Section 5 were included in the government’s plans for transport improvements for this parliamentary session and approval for work on the project to recommence was given.
2.1.3 In December 2011 it was announced that new guidance (IAN 161/12) should be followed whereby Managed Motorway Controlled All Lanes Running (MM-ALR) would replace Dynamic Hard Shoulder Running with reduced number of signs, gantries and Emergency Refuge Areas (ERAs).
2.1.4 In March 2012 the Interim Advice Note IAN 161/12 was published entitled ‘Managed motorways All lanes running’, which set out the design parameters and the associated infrastructure and technology requirements.
2.1.5 In September 2013 a further revision of Interim Advice Note IAN 161/12 was issued in the form of IAN 161/13. As the standards cut off date for this contract is 1st January 2012, the revised IAN is not to be implemented on this scheme, unless specifically instructed by the Highways Agency via a Departments Works Change (DWC). No DWC to implement this standard or any part of it has been received to date.
2.1.6 Construction Works for Section 5 commenced in January 2013.
2.2 Project Description
2.2.1 Section 5 of the Project is within the counties of Hertfordshire, Essex and the Greater London Authority and located in the northern segment of the M25 starting at Junction 23 (A1(M)) and finishing at Junction 27 (M11). This Section will incorporate an existing climbing lane and recent improvements to two tunnels (Holmesdale and Bell Common), so as to provide a traditional hard shoulder with four running lanes at the tunnels and portals.
2.2.2 Construction is being undertaken to two phases, 5A from J23 to J25 (Ch 37+000 to 53+000) and S5B from J25 to J27 (Ch 53+000 to 63+300), with Section 5A being expected to be completed in early January 2014, at which time it is intended to open and operate this section as a MM-ALR scheme, whilst construction works in S5B commences.
2.2.3 MM-ALR makes use of the existing hard shoulder to provide the additional lane capacity. This is achieved by using a system of gantry mounted electronic signs and signals. Safe refuges are provided in accordance with IAN 161/12, approximately every 2.5km where topography and road layout permits. Outside of that required for effective operation of MM-ALR, this Project only includes the minimum improvements to the road infrastructure (e.g. surfacing, vehicle restraint systems, environmental mitigation and drainage improvements), that would be required to achieve safe and legal operation of MM-ALR. A general upgrade to full standards has not been undertaken.
2.2.4 New low noise surfacing has been used to replace life expired surface course in the hard shoulder
with replacement of the main running lanes and hard shoulder with a low noise surface taking
M25 LUS Section 5 Safety Report (pre-opening)
Page 9
place only when the maintaining authority (DBFO) have programmed resurfacing works e.g.
where the surfacing is not fit for purpose. Concrete surface repairs have also taken place.
2.2.5 The drainage arrangements for the Project have been assessed as part of the detailed design, in
order to meet the requirements of IAN161/12, with respect to ‘flow path’ of the water in the road
edge. This comprises additional gullies & kerbs, V Channel or Slot Drains, as identified in the
Detailed Design. The drainage of the ERAs will collect the water into manholes and discharge to
the existing networks where it is attenuated using flow controls and therefore no alteration to the
drainage system was required.
2.2.6 Overall, the proposed drainage system comprises a combination of:
Kerbs and gullies, slot drains and open channels where appropriate.
The existing carrier drain system kept in place for the whole length of the section, taking the
discharge from the collection drain arrangement.
2.2.7 In addition to the implementation of the MM-ALR requirements where appropriate and as agreed
with the Highways Agency, elements of planned maintenance / lifecycle renewal works have been
incorporated into the overall Project scope, including the installation of vertical concrete barriers
and the hardening of the central reserve including any consequential amendments to the drainage
system required as part of these works.
The Overseeing Organisation
2.2.8 The Highways Agency is an Executive Agency of the DfT and is responsible for operating, maintaining and improving the strategic road network in England on behalf of the Secretary of State for Transport. The contact details for the Highways Agency are:
Highways Agency
Federated House
London Road
Dorking
Surrey
RH4 1SZ
The DBFO Co
2.2.9 The DBFO Co is responsible for the delivery of all M25 Projects and maintenance of the M25 for a 30 year period. Connect Plus was appointed in 2009 by the Secretary of State (SoS) for Transport. The contact details are:
Connect Plus
Connect Plus House
St Albans Road
South Mimms
Potters Bar
Hertfordshire
EN6 3NP
2.3 Report Scope and Objectives 2.3.1 This document is the Safety Report (Pre-opening) for the M25 LUS MM – Section 5.
2.3.2 Different phased opening dates are planned for J23-J25 (Section 5A) and J25-J27(Section 5B). Section 5A will open first and the document is presented for approval for Section 5A only. An updated document will be provided in 2014 to support the opening of Section 5B.
2.3.3 This document considers future road user and road worker safety of the completed operational project.
2.3.4 The objectives of this version of the Safety Report are:
M25 LUS Section 5 Safety Report (pre-opening)
Page 10
To describe the safety related activities that have taken place since the production of the
Safety Plan3.
To summarise the contents of the Hazard Log4 for the scheme including the Safety
Requirements defined within it.
To define the main scheme assumptions and thereby by definition benchmark the changes to
the design or operation that would subsequently necessitate consideration of updated safety
reviews in the future.
To define the process which needs to be followed if a significant change in the design or
operation of the scheme is planned or if a defined Safety Requirement cannot be met.
To summarise the evidence in relation to demonstrating achievement of the Safety Objectives.
To provide evidence of compliance with the requirements of the Highways Agency Project
Safety Risk Management System (PSRMS).
2.3.5 This report also describes the relationship between the scheme and the HA’s generic hazard log for a typical MM-ALR scheme and focuses only on the principal differences between the two. It is not necessary to reprise the generic programme level safety work which is separately reported.
2.3.6 The HA has adopted an approach to asset management decisions for the MM-ALR programme that utilises the principle that a MM scheme should include only work that is essential to the safe and efficient implementation, operation and maintenance of the range of operating regimes being implemented. Non-essential maintenance, upgrading and replacement are generally not within the scope of Managed Motorways projects. The risk assessment work described in this report has been guided by these principles.
2.3.7 A glossary of terms has been included after the document sign off sheet.
2.4 Document Status, History and Future Development 2.4.1 This Safety Report (Pre-opening) is issued at the end of the construction phase (PCF Stage 6) of
the scheme prior to the commencement of operation.
2.4.2 This document has been informed by a number of other PCF products, including the following:
Safety Plan
Hazard Log Report
Maintenance and Repair Strategy Statement (MRSS)
Operating Regime, Compliance Strategy, Implications on Core Responders (Combined
Product)
2.4.3 A further version of the document, at PCF stage 7, will report on the safety performance of the fully operational scheme.
3 See document 5108945-ATK-1204-S5-DOC-X-0024
4 See document 5108945-ATK-1204-S5-DOC-X-0090
M25 LUS Section 5 Safety Report (pre-opening)
Page 11
2.5 Contents of this Report
2.5.1 This document is split into a number of sections as described below.
3.0 Scenario Appraisal: describes the typical features of a managed motorway and compares
this to the measures being implemented on the scheme. Also considers the combined safety
impact of the different operating regimes.
4.0 Safety Objectives: summarises the Safety Objectives for the scheme. Further background
and analysis of the existing motorway safety performance can be found in the scheme Safety
Plan.
5.0 Safety Management System: describes how the appropriate Safety Management system
was chosen, how the project safety risk management work instructions were applied and the
approvals process used throughout the safety work.
6.0 Hazard Log: describes how the risk assessment process was utilised on this scheme and
describes how the hazard log provides evidence to support the achievement of the safety
objectives. Further background and a detailed description of how the hazard log was used on
the scheme can be found in the Hazard Log Report.
7.0 Project Practice: discusses how the use of standards and quality control has been managed
on the project to ensure the appropriate level of safety performance is achieved.
8.0 Conclusions: summarises the evidence provided in this version of the Safety Report to
determine whether the scheme is likely to meet its Safety Objectives.
2.5.2 The following Appendices are also included:
Appendix A - Hazard Log Scoring Indices
Appendix B - Hazard Log Scores
Appendix C – Previously Outstanding Safety Tasks
Appendix D - Safety Requirements
Appendix E - Safety Requirements Verification
M25 LUS Section 5 Safety Report (pre-opening)
Page 12
3. Scenario Appraisal
3.1 Typical MM-ALR Scheme
3.1.1 A typical MM-ALR scheme is shown below in Figure 1 (extracted from IAN 161/13).
Figure 1 – Typical MM-ALR Scheme Layout
3.1.2 Two key documents have been produced at programme level to support safety assessment:
Managed Motorways – All Lanes Running Demonstration of Meeting Safety
Objective Report5
5 Highways Agency August 2013 – see: http://www.highways.gov.uk/knowledge/publications/managed-motorways-all-lane-running-
documents/
M25 LUS Section 5 Safety Report (pre-opening)
Page 13
Managed Motorways – All Lanes Running Generic Safety Report6
3.1.3 The above documents are also supported by a Concept of Operations document7.
3.1.4 A substantial amount of data is included in the generic Hazard Log, principally from previous studies undertaken as part of the MM programme. Further data requirements were considered during the initial data population exercise where the existing data was insufficient and the hazard was likely to be high scoring or the M25 schemes were likely to differ from a typical motorway. The values suggested in the generic Hazard Log were typically found to be appropriate and a lean approach was adopted such that additional data (see Section 3.2 below) was only sourced where it was likely to be of material value in understanding risks.
3.2 Scheme Data and Assumptions
3.2.1 The current list of principal scheme features, and associated data values, that are assumed to be part of the final design are:
The scheme does not currently have a complete MIDAS system that includes sufficient overhead signals. The assumed scheme proportion of existing MIDAS by total vehicle kilometres travelled is 27%.
The hard shoulder will be retained, for emergency use, on approximately 23% of the scheme in terms of total vehicle kilometres travelled.
In line with the advice provided in IAN161 suitable safe haven stopping places are provided at maximum 2500m spacing
8.
Off-slips with hard shoulders are considered as safe havens.
Verge barrier will be provided in accordance with DMRB standards but as a result of applying standards it will not be a continuous barrier.
Central reserve concrete barrier will be installed throughout except for small sections at a small number of structures.
The hard shoulder will be resurfaced and strengthened if required.
The ‘before’ and ‘after’ lighting provision will be as per PSCRG Technical Note 6.
Permanent remote controlled (secret) signs in the verge and central reserve will be installed in pairs linked to fixed taper positions; these signs will be blank in their normal state and will show standard TSRGD legends when needed for roadworks.
The set-up and take-down of cones will be mitigated by use of overhead lane closure and Variable Mandatory Speed Limits during the service life of the opened road
6 Highways Agency August 2013 – see: http://www.highways.gov.uk/knowledge/publications/managed-motorways-all-lane-running-
documents/
7 Highways Agency August 2013 – see http://www.dft.gov.uk/ha/standards/tech_info/files/MM-ALR_Concept_of_Operations_v2_0.pdf
8 This is typically achieved but in a few cases marginal increases above 2500m are provided. The risk has been assessed as low via
PSCRG TN11. In other cases spacings of less than 2500m are provided.
M25 LUS Section 5 Safety Report (pre-opening)
Page 14
4. Safety Objectives
4.1 Safety Objectives for Road Users and Road Workers
4.1.1 Before a Managed Motorway is implemented it has to be demonstrated in advance that the scheme Safety Objectives are likely to be met. The PCF Product for the Safety Plan describes the Safety Objectives as follows:
Road Users:
The safety impact of the project will be measured by comparing the “before” and “after” casualty numbers and severities using 3 year before data (the safety baseline) and 3 year after data. The project will meet its Safety Objective for road users if it is demonstrated for a period of three years after becoming fully operational that:
the average number of Fatal and Weighted Injuries (FWI)9 casualties per year is no
more than the safety baseline, and
the rate of FWIs per billion vehicle miles per annum is no more than the safety
baseline, and
no population (e.g. car drivers, pedestrians, HGV drivers and motorcyclists) is
adversely affected in terms of safety.
Road Workers:
There will be no specific numerical safety objective set for road workers. These risks will be
managed to be “So Far As Is Reasonably Practicable.
4.2 Safety Baseline
4.2.1 In accordance with the Managed Motorways Generic Safety Review, the Safety Baseline identifies the level of safety against which the Safety Objectives will be measured (i.e. in safety terms, what the scheme will be compared to).
4.2.2 Section 4.7 describes the role played by the Post Opening Project Evaluation (POPE) process, as part of this process the baseline should be defined using the most up to date accident/casualty data available at that time.
4.2.3 The Safety Baseline will be the 3 year accident/casualty data calculated back from the scheme start of works date, defined as when a speed limit was put in force to allow major works to begin.
4.3 Methodology for Achieving Safety Objectives
4.3.1 The method adopted for achieving the Safety Objectives is the application of the Project Safety Management System. This specifies the process to proactively manage the safety risk using a number of different techniques. The Safety Plan listed the activities that collectively will help ensure that the Safety Objectives for the scheme are met. This method is multi-faceted and utilises a mixture of innovative and long established safety approaches which are applied at various project stages to manage the risk for the different user groups.
9 This indicator is defined in the Safety Plan and places the highest significance of fatal casualties, a high significance on serious
casualties and lowest significance on slight casualties.
M25 LUS Section 5 Safety Report (pre-opening)
Page 15
4.3.2 The principle tool for ensuring the Safety Objectives are met has been the completion of risk assessment activities documented in the Hazard Log application. The development of the Operating Regime and Maintenance and Repair Strategy Statement has also provided opportunities to influence the scheme design for the purposes of safety. The management of these hazards and the development of scheme specific mitigation measures provide a system for reducing the risk to both main targeted groups. Hazards related to Road Users and Road Workers can be treated separately with the different Safety Objectives applied.
4.4 Evidence that Safety Objectives have been/will be achieved
4.4.1 At the time of preparation of this version of the Safety Report there is no direct performance data from the scheme or another MM-ALR scheme. Post-opening, Version 3 of this Safety Report will be able to report on accident/casualty data from the operation of the scheme, therefore demonstrating its performance.
4.4.2 The risk assessment work done to date, through the application of the Hazard Log process, provides a method of identifying the potential barriers to the good safety performance of the scheme. Further details of the Hazard Log methodology are included in Section 6 and the Hazard Log Report.
4.4.3 The methodology behind the Hazard Log makes it possible to combine mathematically the risk assessments for individual hazards to produce a global risk score for both the Managed Motorway and the baseline (existing motorway) and to compare these scores.
4.4.4 The generic Hazard Log is the chosen method of hazard analysis and risk assessment. The Hazard Log is in effect a ‘risk model’ which predicts the impact of introducing Managed Motorway features on a baseline motorway. Risk Score changes can be equated to potential changes in actual FWI.
4.4.5 The generic Hazard Log has been developed using the experience of developing hazard assessments for other forms of Managed Motorway scheme types with additional comparison to all purpose trunk roads without hard shoulders.
4.4.6 The Hazard Log represents an excellent tool to understand how design decisions affect risk quantum and prioritisation. Validation against real schemes can only be fully achieved once more schemes are built and operated successfully. Care must be taken not to assume that the numbers generated represent a higher degree of precision than is actually possible given the finite accuracy and availability of input data.
4.4.7 The Hazard Log process provides the opportunity to focus the safety work on the elements of the scheme that pose the greatest risk to increase confidence that the Safety Objectives will be achieved.
4.5 Future Validation of Safety Objectives
4.5.1 Validation of the Safety Objectives will be possible once sufficient performance data is available. As there is a time lag to collect validated and unvalidated casualty information, it is important to consider if monitoring is required.
4.5.2 It is expected that in the first days and weeks of opening the scheme, RCC/TOS staff will feed back early experiences. This is not considered to be formal monitoring but will nevertheless be useful.
4.5.3 The possible sources of monitoring data are:
Post Opening Project Evaluation (POPE)
Additional HA required centralised monitoring
M25 LUS Section 5 Safety Report (pre-opening)
Page 16
Monitoring Required at Scheme Level
Incident reporting
These different sources of monitoring information are considered in the following sections.
4.6 Post Opening Project Evaluation (POPE)
4.6.1 The Highways Agency will collect casualty data using consultants responsible for the Post Opening Project Evaluation (POPE) project. The data to be collected relevant to safety comprises traffic data, RCC command and control logs, casualty data and incident data. The main purpose of POPE is to:
Identify the degree to which major schemes have offered good value for money by addressing
each of the New Approach to Appraisal (NATA) objectives;
Ascertain the extent to which forecasts of scheme costs and benefits are accurate;
Identify the main factors affecting the accuracy of forecasting; and
Make recommendations regarding how scheme appraisal methods could be improved to help
offer greater accuracy, and therefore ensure that the HA continue to make good investment
decisions.
POPE Traffic Data
Traffic data on traffic counts will be obtained from HA HATRIS. To examine the wider impacts of
the surrounding area there may also be a requirement to examine Local Authority count sites, and
to commission traffic counts on minor roads.
Journey time data will be obtained from:
Journey times from HATRIS; and
Speed data from MIDAS
It is not intended to commission moving observer surveys on the motorway.
POPE Personal Injury Accident (PIA) Data
STATS19 Accident data is requested for five years prior to the start of scheme construction and
the 12 months post full opening (60 months for the five years after). Data is requested for the
PIAs including details of the numbers of casualties and severities and should be obtained for the
same area as covered in the scheme’s appraisal. The local authority is normally the first point of
contact. Agents can also be sources of accident data for HA roads. Records for the motorways
are held by the HA area teams. Accident records are generally not collated very speedily – there
is generally a time lag of two to three months for the data received, hence the need to request the
information at the earliest opportunity.
It should be noted that the accident data obtained for POPE studies has not normally been
validated by the DfT. It is acceptable to use non-validated data if necessary, as long as this is
noted in the report along with: why that decision was made; what the source of the data is; why
that source is deemed appropriate; and, noting the risk that the data may alter when it has been
validated.
POPE collection of Incident Data
In addition to the safety data described above, for the POPE evaluation of MM schemes it is
intended that additional data will be obtained from the record of critical incidents collected by the
National Incident Liaison Officer (NILO) team.
POPE Safety Evaluation
The key areas to be evaluated will be:
Accident numbers
M25 LUS Section 5 Safety Report (pre-opening)
Page 17
(If appropriate and feasible) analysis of accident numbers in the before and after periods by
causation factor
Casualty numbers – by severity
PIA per million vehicle km travelled
The core evaluation of accidents broadly consists of the following elements:
Comparison of before and after accident numbers – This is usually undertaken across the
wider area covered by the appraisal and on a more local area in order to isolate the effects of
the scheme. For this scheme consideration will need to be given to the extending the local
area to include the adjoining links. A consistent approach will need to be taken across the MM
programme.
Comparison of before and after accident severity levels – This covers the same area and will
examine whether the proportion of fatal and serious accidents has changed;
Comparison of before and after casualty numbers – This covers the same area;
Comparison of before and after accident locations - The location of accidents is usually
mapped by severity. This makes it possible to identify any accident ‘hotspots’ in both the
before and after situation;
Analysis of accident causation factors – In order to draw any firm conclusions from this
analysis; it is more practical to undertake this evaluation at the five year after opening stage
when more data is available. This evaluation is particularly relevant if specific types of
accidents have been identified at the appraisal stage;
Comparison of predicted and observed accident numbers – This is key part of the evaluation
as the changes in the number of accidents feed into the evaluation of economic impacts
generated by the scheme. Where there is a difference, further analysis is undertaken to
examine the reasons why this is occurring. This could be related to differences in expected
traffic flows, or could be a specific design issue related to the scheme; and
Statistical tests to determine if accident change can be attributed to the scheme
It must be ensured that the analysis of the accident causation factors considers the impact
that darkness may have on accidents. This will be equally relevant on lit and unlit sections of
the scheme.
4.7 Additional HA centralised monitoring
4.7.1 The HA has agreed that centralised monitoring of early delivery MM-ALR schemes will be undertaken, including M25 Section 5 as one of the earliest opened MM-ALR link across the HA programme.
4.7.2 A consultant commission is expected to be let during December 2013. The specification is known to be comprehensive and commensurate with the type of detailed monitoring undertaken when the first generation of dynamic hard shoulder running schemes were introduced.
4.7.3 Figure 4.1 below provides an indicative set of milestones for centralised monitoring. The diagram shows how a three year monitoring contract period may progress. It shows an interim report based on the first few months of operations. It shows a 1 year report with interim hazard analysis. Figure 4.1 is subject to change and has been directly extracted from a draft specification.
M25 LUS Section 5 Safety Report (pre-opening)
Page 18
Figure 4.1 – Indicative timescales for centralised monitoring
4.8 Monitoring Required at Scheme Level
4.8.1 Any scheme has the opportunity to promote the need for local specific monitoring, particularly during the very early operation. Such work has to be agreed on a case by case basis, recognising that monitoring attracts a cost and the methodology and ownership needs to be robust to make the process worthwhile. The identification of local scheme monitoring requirements would normally come from these main sources:
As a ‘condition’ of a significant departure from standard where some doubt exists as to the
potential safety outcomes.
As a result of the Safety Report and Hazard Log process identifying a key safety challenge
where doubt exists as to the potential safety outcome
4.8.2 It is confirmed that scheme departure from standards approvals for M25 LUS do not include any conditions associated with specific monitoring.
4.8.3 In the early stages of operation it is also recommended that the RCC and Regional Intelligence Unit provide a summary of early experiences. Such observation of network performance is considered to be “business as usual” and no specific additional action is recorded here. Safety Requirement SR-33 (see Appendix D) notes that the RCC should feed back their experiences of dealing with heavy rain events within the first 3 months of opening.
4.8.4 Given the comprehensive nature of the centralised monitoring (see Section 4.7 above), there is no requirement to duplicate such work and therefore no action is recorded here
M25 LUS Section 5 Safety Report (pre-opening)
Page 19
5. Safety Management System: Evidence a
Robust System Followed 5.1.1 The Safety Plan outlined how the PSRMP would be applied to the scheme. The Safety Plan also
described the key features of the PSRMP and this is illustrated in Figure 5.1 below.
Figure 5.1 - PSRMP features defined in the Safety Plan
M25 LUS Section 5 Safety Report (pre-opening)
Page 20
5.2 Robust Project Safety Management Process in Place
5.2.1 PSRM Work Instruction 001 (contained in IAN 139) was applied to the scheme to determine the appropriate Safety Management System (SMS) to use. The process used to select the SMS is described in detail in the scheme Safety Plan and only a summary of the activities are described here. The main steps involved in the SMS selection process and their constituent parts are as follows:
Review of Project Scope – This included a review of the project against comparison norms.
Categorisation of Project Features – This included a review to characterise the scheme in
terms of Stakeholder Interest; Operational Experience, Technology, Standards and
Legislation, Organisational Impact and Project Scale.
Application of SMS – The selection was then completed by determining the appropriate level
of safety management required.
5.2.2 The application of Work Instruction 001 resulted in application of a Type B SMS. Type B requires a moderate level of safety management to be applied with a commitment to produce a Safety Report and an appropriate level of risk assessment. In addition the HA generic safety report for MM-ALR notes that MM ALR schemes would normally make use of a Type B SMS.
5.3 Robust Approval Process in Place
5.3.1 The safety approvals process used on the scheme is in line with the requirements of PSRM Work Instruction 003 (contained in IAN 139) and as required for a Type B SMS. This process is illustrated in Figure 5.2. The phases of Safety Acceptance and Approval and examples of which deliverables have passed through these phases are described in Table 5.1 below:
Phase Purpose Evidence
Verification. The project executor verified that to the best of their knowledge, the work
produced demonstrates that the Project Safety Requirements are fulfilled.
As authors of the Safety Plan, Hazard Log Report and Safety Report the Safety Team has verified these deliverables.
Consultation The project team undertook consultation with HA Directorates
Consultation with internal stakeholders has been mainly via
Project Safety Control Review Group (PSCRG). Consultation
with Network Services has taken place as design (and Departures)
progressed.
Review and Approval
When consultation is complete, the HA’s Major Projects consider the information
provided to them, including both that submitted by the project executor and the appropriate technical approvals provided
by other Directorates. Once Major Projects has confirmed that all necessary issues have been addressed, approval
for the project is granted.
Consultation has been completed for the Safety Plan, Hazard Log
Report and pre-construction Safety Report and approval was
granted.
Table 5.1 - Safety Approval Process and Progress
M25 LUS Section 5 Safety Report (pre-opening)
Page 21
Figure 5.2 - Safety Acceptance and Approvals process
Evidence that the relevant phases of approval have occurred is recorded via signatures on a
standard HA PCF product cover sheet. A further safety approvals cover sheet is included for the
principal safety deliverables, the Safety Plan, Hazard Log Report and this document, the Safety
Report.
5.4 Road Safety Audits
5.4.1 The requirements of HD19 have been followed in the production of Stage 1 and Stage 2 Road Safety Audits.
5.4.2 Stage 3 (pre-opening) road safety audits will take place before any link opens to traffic.
M25 LUS Section 5 Safety Report (pre-opening)
Page 22
Roads Programme Steering Group
National Safety Control Review Group (NSCRG)
Project Safety Control Review Group (PSCRG)
"Hub" Operational Safety and
Maintenance Techncial Advisory Group
5.5 Project Safety Control Review Group (PSCRG)
5.5.1 A Project Safety Control Review Group was first convened for the MM-ALR scheme in January 2012. At the first meeting a proposed remit was circulated
10 and subsequently agreed.
5.5.2 The PSCRG is made up of representatives from several HA directorates (NDD, TMD, NetServ, and MP), the designer, the Main Contractor and the maintenance community. The Highways Agency has produced an easy guide to MM Safety Governance
11 that explains the relationship
between the PSCRG, safety approval processes and other governance functions.
5.5.3 Figure 5.3 is an amended extract from the guide showing the relationship between the different groups.
Figure 5.3 – Safety Governance Hierarchy for the MM Programme
5.5.4 Regular PSCRG meetings have taken place and the scheme has been represented on the Technical Advisory Group for Operations, Safety and Maintenance.
5.5.5 Any tasks that could impact the achievement of the Safety Objectives have been brought to the attention of the PSCRG via a Technical Note. This process has yielded a number of PSCRG technical notes. The relevant technical notes are as follows:
TN2 – Drainage
TN 3 – Gantry Arrangement
TN4 - Temporary Traffic Management
10 Technical note 32 Revision 1
11 Managed Motorways Safety Governance – An Easy Guide: December 2012 – Version 2
M25 LUS Section 5 Safety Report (pre-opening)
Page 23
TN 5 – Initial hazard review and collision data
TN 6 – Lighting
TN 8 – Scoping paper on maintenance access
TN10 - Lane drop / lane gain / TJR
TN 11 - ERT’s and ERAs that are not paired
TN 13 - Hazard Log – Summary
TN 15 - Lane Provision at Holmesdale Tunnel
TN 20 - ERA Provision for section 5
TN21 – J26 Clockwise Merge/Climbing Lane
TN23 – Secret signs (for roadworks)
TN 24 - Lane Provision at Bell Common Tunnel
TN26 – Use of Wavetronics
TN27 - Section 5 Retained Hard shoulders
TN28 - Safety Report Timeline
M25 LUS Section 5 Safety Report (pre-opening)
Page 24
6. Hazard Log Scoring
6.1 Initial Population of the Hazard Log
6.1.1 The initial population of the Hazard Log took place during a series of internal meetings in June and July 2012. Each generic hazard included in the Highways Agency’s generic Hazard Log was discussed in the context of the preliminary scheme proposals.
6.1.2 The risk assessment of each hazard was guided by the information provided in the Highways Agency’s Risk Assessment Support Documents
12. In assessing each hazard the following
fundamental issues were considered:
Is the ‘frequency’ of hazard occurrence on the M25 currently different to that of a typical section of motorway nationally?
Are the default13
values given for hazard ‘frequency’, ‘probability’ and ‘severity’ appropriate for the M25?
How will the features of a Managed Motorway scheme mitigate or worsen the hazard?
How will the proposed features of M25 impact the scores for hazard frequency, probability and severity?
Is there more data needed or is better definition of the scheme features needed to properly assess the hazard?
Is there further mitigation that could be included to reduce the hazard and how should this be progressed?
Is there a key feature, procedure or process that should be mandated as a requirement to control the hazard?
6.1.3 Prior to this, in February 2012, the safety team undertook a desk based review of the initial scheme drawings to make safety observations; background documents relating to the development of the scheme were also reviewed. This initial review resulted in a list of ‘tasks’, effectively safety considerations, for the design team. This task list along with a progress report on these issues is included in Appendix C.
6.1.4 A PCF Hazard Log Report was produced. It is emphasised that although the PCF Hazard Log Report was produced only once, the Hazard Log Assessment is not a one-off event and the Log remains live as the design evolves.
6.1.5 It is also emphasised that the process, whilst numerically based, is not purely numerical in nature – the discipline of reviewing designs against hazard lists is a key process in challenging designs and assumptions, including feedback on programme level advice or guidance documents.
6.1.6 In August 2013 the Highways Agency amended the Generic MM-ALR Safety Report and its embedded risk scoring information. The M25 LUS Hazard Log results were updated to take account of these minor changes. PSCRG endorsed TN28 and a decision was thereby taken to include the results of these changes in the pre-opening Safety Report rather than via a revised Hazard Log Report.
12 These documents were originally produced for the MM-DHSR generic Hazard Log and have not been updated for MM-ALR.
Nonetheless the generic nature of the hazard descriptions means they are still relevant.
13 The term “default” refers to suggested values contained in MM-ALR generic Hazard Log; these can be changed to suit the local
scheme circumstances
M25 LUS Section 5 Safety Report (pre-opening)
Page 25
6.2 Mitigation and Design Features
6.2.1 In order to assess the risk in the ‘after’ scenario it is necessary to recognise the mitigation that will be provided in applying the requirements of IAN161. Any departures from the requirements of IAN161 or the Design Manual for Roads and Bridges (DMRB) are identified in the Design Strategy Report (DSR) and Departures Checklist. The DSR is used to capture all significant design decisions and provides an auditable record of these decisions. In addition IAN161 states that the DSR must be used to demonstrate that the existing accident record and operational and maintenance performance has been considered.
6.2.2 The Highways Agency has recognised that in order to reduce risks to road workers, the assumptions and designs described in IAN161/12 are likely to require enhancement by scheme designers. The scheme has included a number of additional features listed in Section 3.2 and those specifically of assistance for road worker safety are listed in section 6.6.11.
6.3 Assumptions
6.3.1 A substantial amount of data is included in the generic Hazard Log, principally from previous studies undertaken as part of the MM programme. Further data requirements were considered during the initial data population exercise where the existing data was insufficient and the hazard was likely to be high scoring or the M25 schemes were likely to differ from a typical motorway. The values suggested in the Hazard Log Risk Assessment documents were typically found to be appropriate and a lean approach was adopted such that additional data was only to be sourced where it was likely to be of material value in understanding risks.
6.3.2 The length of the proposed scheme was calculated and used to calculate scheme specific Hazard Log frequencies, probabilities and severity indices.
6.4 Provision of a Controlled Environment
6.4.1 Operation of a high speed road in a way that supports reliable journeys, by effective management of congestion and planned, and unplanned incidents, in a safe and sustainable manner depends primarily on appropriate driver behaviour. This behaviour can be achieved through the implementation of an intuitive system / network of roadside signs and signals along with enforcement measures that when combined (a toolkit of measures and mitigations) has become known as the ‘controlled environment’.
6.4.2 A controlled environment provides road users with the right (i.e. relevant and accurate) information at the right location at the right time; thereby promoting the desired driver behaviour (through situational awareness). Driver information is provided through the appropriate provision and effective operation of infrastructure and technology.
6.4.3 There are a number of key measures deployed under a managed motorways scheme that affect the hazards on a high speed road. These can be broken into operations, technology and infrastructure. The appropriate application of infrastructure and technology, along with how the road is operated can lead to the achievement of the desired outcomes. The most significant hazards are listed in Table 6.1 along with the measures which affect those hazards. The majority of the significant hazards are mitigated by more than one measure.
6.4.4 The key measures that make up a controlled environment can be summarised as follows:
Operations
Suitable and relevant information, visible to road users and provided at regular intervals – ‘right place, right time, right message’, This ensures drivers have limited opportunity to forget key information before being reminded of the required behaviour.
Education and Encouragement enable an understanding (driver comprehension) of the information and the reasons why and this will change a driver’s behaviour.
M25 LUS Section 5 Safety Report (pre-opening)
Page 26
Enforcement - The perception that motorists will be prosecuted for non-compliance with the signs and signals on display also helps to create a controlled environment.
Traffic Officer procedures and RCC monitoring results in a scheme which is operated to improve network performance and thus engender driver ‘confidence’ in the scheme.
A high level of compliance can be achieved with the implementation of a well designed signalling regime which promotes compliant driver behaviour together with driver education, demonstrating the benefits of obeying the verge and overhead signals displaying the varying speed limits. In order to achieve compliant driver behaviour it only requires a small percentage of drivers on a congested section of road to comply with the information displayed and drivers following the compliant driver will be ‘forced’ to comply .
Infrastructure
Advanced Direction Signs which are visible and display clear information ensure that motorists move into the right lane at an appropriate time.
The use of overhead signals to display information provides a different environment for motorists that will change behaviour.
The permanent removal of the hard shoulder (for most of the scheme length) and its use as a running lane.
The provision of Emergency Refuge Areas (ERAs) with Emergency Roadside Telephones (ERTs). The ERAs will help to provide motorists with an area for safe refuge should they need to stop immediately in an emergency, such as a breakdown
Fixed traffic enforcement signs provide a warning to motorists and encourage compliant driver behaviour.
Lining and studs provide clear information so that drivers understand the status of the carriageway.
Technology
Various means of displaying key appropriate information to road users including Variable Message Signs (VMS) which can display appropriate messages, lane closure information, or display an appropriate speed limit. These are supported by a network/system of data gathering of the traffic flow characteristics which form part of the MIDAS system.
Advanced Motorway Indicator (AMI) on gantries which will display appropriate speeds or lane closure information.
The provision of enforcement cameras along with mock/dummy cameras will help to obtain compliance with speed limits on display.
A CCTV system with full coverage will help provide the perception to motorists that they face prosecution should they commit an offence. This also enables reactive and efficient incident management. In unlit areas the CCTV will be enhanced with infra-red emitters to improve the image quality.
M25 LUS Section 5 Safety Report (pre-opening)
Page 27
Table 6.1 - Measures to enable a Controlled Environment
Hazard (Approximate % of overall scheme risk)
Operational Infrastructure Technology
Driver fatigued – unable to perceive hazards effectively (24%)
- Information displayed in timely manner - Well designed signalling regime
- Lining and stud provision - Signals on verge mounted MS4s and overhead gantries
Individual vehicle is driven too fast (14%)
- Education – driver understanding of information - Encouragement – changing behaviour on the road - Suitable and relevant information - Information displayed in timely manner - Customer perception - Visibility of information - Perceived enforcement (surveillance / ‘being watched’) - Well designed signalling regime
- Gantries - Cantilevers - Enforcement signs
- Signals on verge mounted MS4s and overhead gantries - Full CCTV - Enforcement cameras - Inductive loops and radar (MIDAS)
Vehicle stops in running lane – (off peak in MM-ALR) (8%)
- Suitable and relevant information - Traffic Officer procedures and RCC ability to monitor
- Additional lane (no hard shoulder) - Gaps in nearside safety barrier - Gantries Enforcement signs
- Signals on verge mounted MS4s and overhead gantries - Full CCTV - Inductive loops and radar (MIDAS)
Pedestrian in running lane – live traffic (6%)
- Suitable and relevant information - Traffic Officer and RCC ability to monitor
- ERAs with ERTs - Signals on verge mounted MS4s and overhead gantries - Full CCTV
Rapid change of general vehicle speed (4%)
- Education - driver understanding of information - Suitable and relevant information - Information displayed in timely manner - Visibility of information - Perceived enforcement (surveillance / ‘being watched’) - Traffic Officer procedures and RCC ability to monitor - Well designed signalling regime
- Gantries - Cantilevers - Additional lane (no hard shoulder) - Enforcement signs
- Signals on verge mounted - MS4s and overhead gantries - Enforcement cameras - Inductive loops and radar (MIDAS)
Tailgating (4%)
- Education - driver understanding of information - Encouragement – changing behaviour on the road - Suitable and relevant information - Customer perception - Perceived enforcement (surveillance / ‘being watched’) - Well designed signalling regime
- Additional lane (no hard shoulder)
- Signals on verge mounted MS4s and overhead gantries - Full CCTV - Enforcement cameras - Inductive loops and radar (MIDAS)
Vehicle stops in running lane - Peak (4%)
- Education - driver understanding of information - Encouragement – changing behaviour on the road - Suitable and relevant information - Information displayed in timely manner - Visibility of information - Well designed signalling regime
- Gaps in nearside safety barrier - Gantries - Enforcement signs
- Signals on verge mounted MS4s and overhead gantries - Full CCTV - Inductive loops and radar (MIDAS)
Vehicle drifts off carriageway (2%)
- Encouragement – changing behaviour on the road - Suitable and relevant information - Information displayed in timely manner
- Gantries - Cantilevers - Lining and stud provision - Safety barriers
- Signals on verge mounted MS4s and overhead gantries
Sudden weaving at exit point (2%)
- Suitable and relevant information - Information displayed in timely manner - Visibility of information - Well designed signalling regime
- Advanced Direction Signs - Lining and stud provision
- Full CCTV - Inductive loops and radar (MIDAS)
M25 LUS Section 5 Safety Report (pre-opening)
Page 28
Hazard (Approximate % of overall scheme risk)
Operational Infrastructure Technology
Motorcycles filter through traffic (2%)
- Education – driver understanding of information - Encouragement – changing behaviour on the road - Suitable and relevant information - Information displayed in timely manner - Perceived enforcement (surveillance / ‘being watched’)
- Gantries - Additional lane (no hard shoulder)
- Signals on verge mounted MS4s and overhead gantries - Full CCTV - Enforcement cameras
Driver loses control of vehicle (2%)
- Education - driver understanding of information - Encouragement – changing behaviour on the road - Suitable and relevant information - Information displayed in timely manner - Visibility of information - Well designed signalling regime
- Gantries - Additional lane (no hard shoulder) - Enforcement signs - Lining and stud provision - Safety barriers
- Signals on verge mounted MS4s and overhead gantries
Vehicle rejoins running lane (2%)
- Visibility of information - Well designed signalling regime
- ERAs with ERTs - Additional lane (no hard shoulder)
- Signals on verge mounted MS4s and overhead gantries
Vehicle reversing along exit slip (2%)
- Visibility of information - Perceived enforcement (surveillance / ‘being watched’)
- Enforcement signs - Lining and stud provision
- Signals on verge mounted MS4s and overhead gantries - Full CCTV - Enforcement cameras
Unsafe lane changing (2%)
- Education – driver understanding of information - Information displayed in timely manner - Customer perception - Perceived enforcement (surveillance / ‘being watched’) - Well designed signalling regime
- Advanced Direction Signs - Additional lane (no hard shoulder) - Lining and stud provision
- Signals on verge mounted MS4s and overhead gantries - Full CCTV - Enforcement cameras - Inductive loops and radar (MIDAS)
Vehicle enters main carriageway unsafely (2%)
- Education – driver understanding of information - Suitable and relevant information - Visibility of information - Well designed signalling regime
- Enforcement signs - Lining and stud provision
- Signals on verge mounted MS4s and overhead gantries - Full CCTV - Enforcement cameras
Driver ignores closed lane(s) signals that are protecting an incident (2%)
- Suitable and relevant information - Customer perception - Visibility of information - Well designed signalling regime
- Gantries - Cantilevers - Enforcement signs
- Signals on verge mounted MS4s and overhead gantries - Full CCTV - Enforcement cameras
Vehicle recovered from ERA (2%)
- Traffic Officer procedures and RCC ability to monitor
- ERAs with ERTs - Full CCTV - Signals on verge mounted MS4s and overhead gantries
M25 LUS Section 5 Safety Report (pre-opening)
Page 29
6.5 Hazard Log Results
6.5.1 Before a Managed Motorway is implemented it has to be demonstrated in advance that the scheme Safety Objective is likely to be met.
6.5.2 The methodology behind the Hazard Log makes it possible to combine mathematically the risk assessments for individual hazards to produce a global risk score for both the Managed Motorway and the baseline (existing motorway) and to compare these scores. However, care must be taken not to assume that the numbers generated represent a higher degree of precision than is actually possible given the finite accuracy and availability of input data. To avoid such misinterpretation, this document merely quotes the numerical calculations as a tool for guiding the construction of a qualitative argument to compare the safety of the project with the baseline existing motorway. The reader is required to judge for themselves whether they find the qualitative argument convincing, . In outline, the reasoning is as follows:
Managed Motorways reduce the risk of a large number of existing motorway hazards.
Managed Motorways introduce a number of new hazards to the operation of the motorway.
However, various mitigating measures are to be adopted to reduce the risk of these hazards.
Real-world experience on the other forms of Managed Motorway scheme has produced real
world accident reductions.
Driver simulation of MM-ALR has been carried out
The generic risk assessment work on MM-ALR has been produced with a high degree of
rigour, challenge and governance and is based on comparisons of similar scenarios, such as
all-purpose dual carriageways (with no hard shoulders)
The risk assessment process is deliberately pessimistic in its assumptions for individual
hazards.
The risk identification process tends to concentrate on new features (ERAs etc) and may
therefore overestimate the quantum of risk that these contribute to the total.
6.5.3 Additionally it is noted that the current Hazard Log has been generated against a baseline of a Managed Motorway design contained within IAN161 and as such there is no existing scheme to validate the results, in the same way a traffic model might be validated. However the Hazard Log represents an excellent tool to understand how design decisions affect risk quantum and prioritisation and has been developed from other Hazard Logs that now have some real-world level of validation. Validation against MM-ALR real schemes can only be fully achieved once schemes are built and operated successfully.
6.5.4 The scoring of hazards has been considered against the background of the HA’s Generic Hazard Log
14. The generic Hazard Log contains around 100 hazards which are relevant to the operating
regime of the M25 Section 5 scheme. This considers the safety impact of a generic MM-ALR scheme on the following specific user groups whilst ensuring that the scheme does not seek to improve safety for one user group at the expense of another:
Pedestrians
Motorcyclists
HGV Drivers
On road resources
Maintenance workers
14 This was distributed via email in Excel format by Hub OMS TAG in May 2012
M25 LUS Section 5 Safety Report (pre-opening)
Page 30
6.5.5 In scoring the hazards for the M25 LUS Section 5, the generic score were taken as a starting point and then each hazard was considered against the scheme design with scores amended to reflect the scheme features.
6.5.6 The scoring exercise and the Hazard Log structure enabled the safety team to target further safety appraisal at those issues that pose the greatest safety risk and where further action will likely have the greatest safety impact.
6.5.7 The key hazard groupings are considered to be:
High scoring hazards i.e. those with a ‘before’ or ‘after’ risk score of 8 or more; or
Those associated with maintenance activities
Those associated with the different populations listed in 6.5.4 above.
6.5.8 A list of all the Hazards with descriptions is presented in Appendix B.
6.6 Detailed Analysis
6.6.1 The generic Hazard Log structure is designed to include hazards that exist on all motorways and those that are specific to a Managed Motorway. The new hazards that are specific to a Managed Motorway within the log are only scored for the ‘after’ scenario and as such these represent a substantial proportion of the total ‘after’ risk score as the ‘before’ score for these items is zero.
6.6.2 The generic hazard log reports a risk reduction of around 18% for implementation of an IAN 161 compliant MM-ALR scheme. The M25 LUS Section 5 scheme specific risk assessments indicate that the scheme will meet the road user safety objective. In principal the small difference between the generic and M25 LUS Section 5 assessment is due to the following assumptions in the generic HA log for a “typical MM-ALR” scheme:
No MIDAS.
Each junction has through junction running and so no hard shoulder is retained intra-junction
There are no Controlled Motorway (CM) sections i.e. where the hard shoulder is retained.
6.6.3 The results of the hazard log risk assessment are summarised in Table 6.2 below.
Table 6.2 - Hazard Log Results Summary
All hazards
Before Risk 4,562,503,985
After Risk 3,920,966,518
Expected Change on scheme implementation -14.06%
6.6.4 The overall risk reduction estimated by the Hazard Log should not normally be quoted in external documentation as this may incorrectly infer that this is a numerical “target” to be achieved; the agreed Safety Objectives do not contain such a target. The potential quantum of risk reductions simply provide a level of confidence the scheme Safety Objectives will be met.
6.6.5 The overall predicated scheme risk reduction of c.14% is within the same order of magnitude predicted by the HA’s generic work, which in summary predicts that a typical MM-ALR scheme may be able to generate around 18% accident savings.
M25 LUS Section 5 Safety Report (pre-opening)
Page 31
High Scoring Hazards
6.6.6 The HA’s ‘Demonstration of meeting the safety Objective’ report classifies a high scoring hazard as one with a before or after score of 8.0 or more and this classification has been adopted for the M25. Looking at the high scoring hazards in isolation is particularly useful as these 19 hazards account for 86.89% of the global risk on the scheme.
6.6.7 A summary of the impact the scheme has on these high scoring hazards is included in Table 6.3 below and the high scoring hazards are shown in Appendix B.
6.6.8 Table 6.3 shows that the M25 LUS Section 5 scheme shows a significant reduction in the risk score of the High Scoring Hazards. It is however noted that risk score of the following high scoring hazards increases:
H135 - Vehicle Stops in running lane - Off Peak
H155 - Vehicle stops in running lane - Peak
Table 6.3 - High scoring hazards summary
High Scoring Hazards
No. Hazards 19
Before Risk 4,127,642,423
After Risk 3,406,838,367
% of global after risk 86.89%
Expected Change on scheme implementation
-17.46%
6.6.9 The order of magnitude of hazards H155 and H135 is similar to the generic HA Hazard Log. The programme level safety work considered that individual increases in risk for these high scoring hazards was acceptable due to the reductions in other high ranking hazards.
Maintenance Hazards
6.6.10 There are eight maintenance hazards within the generic hazard log that are relevant to the M25 LUS scheme. The analysis undertaken is summarised in Table 6.4 below. Taking these hazards in isolation shows a reduction in risk from the ‘before’ to ‘after’ for both maintenance and on road resources (traffic officers/incident support staff). The combined result of scoring this small number of hazards is very sensitive to small changes and the scores selected have been based on the recommendations of a number of concurrent activities:
The Eliminate Reduce Isolate Combine (ERIC) assessment developed for the scheme
PSCRG TN 4 – Temporary Traffic Management
PSCRG TN 8 – Maintenance Access
The Maintenance and Repair Strategy Statement PCF product.
6.6.11 The relevant provisions for road workers are:
Inclusion of rigid concrete barrier, thereby reducing interventions for barrier repairs
Elimination of on foot carriageway crossings to set-out signing; permanent signs (remotely
operated “secret signs”) included within the central reserve and also verge.
M25 LUS Section 5 Safety Report (pre-opening)
Page 32
Use of overhead signals to show red X closures aspect and Variable Mandatory Speed Limits
whilst traffic cones are placed and removed
Remote diagnostics and re-boot of the majority of motorway communications (i.e. AMI and
MS4) equipment
Minimising equipment, particularly in the central reserve (e.g. removal of sections of lighting)
Use of upstream signals to reduce speeds and close lanes ahead of road users reaching an
incident scene where workers may be present
6.6.12 One Maintenance hazard has been shown to increase in risk, H34 - Incident management - rolling block, but none of the maintenance hazards are classed as High Scoring hazards due to the relatively low frequency of maintenance compared to other scheme risks.
6.6.13 The maintenance risk in the hazard log takes account of only the risk to operatives from working on the highway i.e. the risk of being involved in a Road Traffic Collision. Further information on control of non-traffic related risks is contained in the Maintenance and Repair Strategy Statement and the CDM risk register.
Other Populations
6.6.14 Table 6.4 summarise the results of the Hazard Log Assessment in terms of all individual populations.
6.6.15 The results indicate that all populations have a reduced risk score. It is noted that the risks from collisions involving HGVs are captured within “general” risks within the Hazard Log because incidents involving both cars and HGVs have an effect on both user types. The Hazard Log does identify a particular risk for large vehicles : “H141: HGV-LGV-Bus exits ERA”. This is a generic ALR issue that is controlled by:
Verge signs that require users to make contact with the RCC before leaving an ERA
Traffic Officer procedures to set signals to assist exits from ERA
Table 6.4 – All populations summary
Before After
Population No. Hazards
Risk % of global Risk % of global % Change
General +HGV
combined
70 3,837,557,458 84.11% 3,346,076,464 85.34%
-13%
Maintenance 8 90,670,109 1.99% 58,308,029 1.49% -36%
Motorcyclist 6 114,478,506 2.51% 90,751,949 2.31% -21%
Pedestrian 7 361,012,823 7.91% 300,274,563 7.66% -16.8%
Worker 9 158,785,054 3.48% 125,555,478 3.20% -21%
None 35 35 0.00% 35 0.00% 0%
Total
135
4562503985
3920966518 100% -14%
6.7 Close-out of Hazard Log Actions
6.7.1 The Hazard Log is a semi-quantitative assessment tool used to understand the main safety challenges posed by the scheme. The focus of the assessment work was to better understand how the scheme can most effectively reduce risk for the different user groups, resulting in consideration of minor changes to the design or operation of the scheme (whilst remaining within the Concept of Operations philosophy). To ensure that the Hazard Log assessment was output
M25 LUS Section 5 Safety Report (pre-opening)
Page 33
based the Safety Team has produced a list of both safety tasks and safety requirements that will need to be proactively managed by all those involved in the scheme.
6.7.2 The principal advantage of applying the Hazard Log process to the scheme has been to prioritise the importance of each hazard and as a result it has been possible to focus the safety effort on the areas that have the greatest potential to affect safety impacts of the scheme.
6.7.3 Sections 6.8 and 6.9 provide information of close-out of issues.
6.8 Safety Tasks
6.8.1 The initial population of the Hazard Log for the scheme resulted in a number of instances where further investigation of the hazard, or associated control measures was required. A full list of these ‘Safety Tasks’ was included in Appendix C of the pre-construction version of this report. This is now updated to report close-out of previously open actions. No actions remain.
6.8.2 Any significant tasks whose outcome could impact the achievement of the Safety Objectives were brought to the attention of the PSCRG via a Technical Note.
6.9 Safety Requirements
6.9.1 The population of the Hazard Log for the Section 5 scheme has also resulted in the identification of a number of safety crucial features which are either part of the design or operation process or need to be included (as a result of the analysis). These are deemed as Safety Requirements. A Safety Requirement is a mandatory instruction, such as the need for a certain feature or process, that must be included as part of the scheme to aid the achievement of the Safety Objectives. The full definition of a Safety Requirement is:
“Those features, operational procedures, working methods or actions which are considered necessary for the safe functioning of the Managed Motorway scheme.”
6.9.2 Appendix D includes a full list of the Safety Requirements. The existing list takes account of the Hazard Log findings, PSCRG Technical Notes and a generic list of Safety Requirements produced by the Highways Agency.
6.9.3 Appendix E reports on the Verification of Safety Requirements.
6.10 Compliance with Requirements and impact on the Safety Report
6.10.1 Because the Safety Report creates an important audit trail, with signatures, on project safety related decisions any scheme changes that potentially affect the Safety Report must be carefully assessed. This statement applies for the life of the road.
6.10.2 Although it is not anticipated that the Safety Requirements will be varied between now and road opening , where a post-opening proposal to amend the design or operation of the scheme is planned it is expected that the proposer would identify the potential impact on the Safety Requirements and scheme Hazard Log. These impacts must be reported in writing and the conclusions accepted by the Highways Agency before the design or operation is varied. The proposer must also report changes that they consider would have no impact on the Safety Requirements so that this can be verified.
6.10.3 Where a proposal to vary a Safety Requirement is put forward the potential outcomes are:
Not accepted: the proposal is refused on grounds of safety or for other reasons
M25 LUS Section 5 Safety Report (pre-opening)
Page 34
Accepted minor change: the wording of the Safety Requirements is amended after
confirmation that there is no affect on the safety assessment of the scheme. The Safety
Report is not re-issued for approval, but changes to Safety Requirements are logged. This
may be as a result of an emerging national procedure or revision of an existing guidance
document.
Accepted non-minor change: the Safety Requirements are amended. Safety Report re-
issued for approval containing explanation of changes and affects on the safety assessment.
6.11 Evidence that Safety Requirements and Restrictions met by Design
6.11.1 Each individual Safety Requirement requires verification to minimise the risk that the scheme safety performance will not be compromised by failure to follow a requirement.
6.12 Verification Reviews
6.12.1 A summary of the categorisation that was available to use during the Verification process is provided in Table 6.5 below.
Categorisation Description
Verified These requirements are verified
Allowable Non-
Compliance
These requirements have not been met, or have only been met in part.
This non compliance will not impact the achievement of the safety
objective and has been endorsed by the Safety Team and the PSCRG.
Revisit later in
current stage
This category is used where the requirement needs to be revisited once
further work has taken place.
Await evidence This category is used where the requirement needs to be revisited as
insufficient evidence was presented to the review team.
Retired These requirements are no longer relevant to the scheme.
Non Compliance The scheme design was not initially shown to comply with these
requirements.
Table 6.5 - Verification Categorisation
6.12.2 There are a number of Safety Requirements with the status “Revisit later in current stage”. These are identified in Appendix E. The majority of these are associated with the fact that M25 LUS is the first ALR scheme to “go-live” and associated operational procedures are still being finalised. Additionally this Safety Report has been requested to be produced in advance of when these Safety Requirements would normally be closed-out.
6.12.3 The necessary action is for the SRO to satisfy himself that these outstanding Safety Requirements are all closed out before the ALR phase of the scheme opens.
M25 LUS Section 5 Safety Report (pre-opening)
Page 35
7. Project Practice: Methods and Processes
been followed during the Project
7.1 Design Compatibility with Standards and Regulations
7.1.1 The design of the scheme has been carried out in accordance with the guidance contained in IAN 161/12. Where the design is not in compliance with IAN 161/12 or another standard within the Design Manual for Roads and Bridges (DMRB) a departure from standard has been produced and submitted to the HA for approval. Each departure produced has taken proper account of the potential safety benefits and disbenefits, the impact of which has been included within the risk assessment activities.
7.1.2 Each departure produced has taken proper account of the potential safety benefits and disbenefits, the impact of which has been included within the risk assessment activities. The authors of the Hazard Log have been included in the internal check and review process for Departures.
7.1.3 In addition to the departures from standard process a Design Strategy Record has been produced for the scheme. IAN 161/12 contains clauses that depart from other standards within the DMRB and as such removes the need for a departure to be approved. The Design Strategy Record identifies where and how each mandatory clause has been applied on the scheme and carefully records the cumulative effect of their application. This report demonstrates that the combined effect and interaction of these decisions will not negatively affect the achievement of the Safety Objectives.
7.1.4 The “Departures from Standard Checklist” PCF product describes the scheme Departures in detail.
7.1.5 No Departures were classed as high risk requiring National Safety & Control Review Group (NSCRG) review.
7.1.6 For Section 5A, one Departure from Standard is outstanding due to approval being awaited from HA Netserv.
7.2 Use of Good Practice during the Project
7.2.1 The scheme has been developed in line with the requirements of Atkins Business Management System (BMS). At project inception a quality plan was drafted detailing the communication, change control, programme, document storage and Health and Safety arrangements for staff working on the project. This document also established the project controls in terms of the checking, review and authorisation of scheme drawings and reports.
7.2.2 In order to manage communication and facilitate the efficient development of the scheme across the different disciplines a dedicated collaboration site was established.
7.2.3 Atkins staff from across the design disciplines contributed to the HA’s Technical Advisory Groups ensuring that best practice identified elsewhere within the managed motorway programme could be disseminated.
7.2.4 The Safety Team selected had experience gained on the other Managed Motorway schemes and were able to apply this to the scheme.
7.2.5 Full use has been made of the PSCRG forum. Key issues have been discussed and included in a series of Technical Notes.
M25 LUS Section 5 Safety Report (pre-opening)
Page 36
7.2.6 PSCRG has also inputted to formal PCF safety products before sign-off processes have been initiated.
8. Conclusions
8.1 General Conclusions
8.1.1 This Safety Report has summarised the safety work that has taken place to date on the M25 LUS Section 5 Managed Motorway scheme. The details of the principal safety challenges, the decisions made, including their justification and the actions taken to date have also been recorded.
8.1.2 The evidence available at this time suggests that the Safety Objectives are achievable for both road users and road workers. At the current project stage there is no performance data to demonstrate the achievement of the Safety Objectives. The evidence that the Safety Objectives are achievable is provided by:
The results of the scheme Hazard Log Risk Assessment activity.
The results of the generic programme level Hazard Log Risk Assessment activity, including
driver simulation.
The work done to complete the safety activities outlined in the scheme Safety Plan.
Verification of Safety Requirements
8.2 Outstanding Key Actions
8.2.1 A Stage 3 (pre-opening) Road Safety Audit Report will be required in accordance with DMRB HD19; the process can be phased to suit incremental go-live dates for different links.
8.2.2 There is one15
outstanding Departure from Standard for Section 5A; confirmation of approval should be ascertained. Non-approval of any departures requires the validity of Safety Report to be re-confirmed.
8.2.3 The Scheme Safety Requirements have been subject to a verification assessment, seeking evidence of compliance. The results of this exercise are listed at Appendix E.
8.2.4 Appendix E shows a number of Safety Requirements that cannot be verified at this time and therefore these should be re-checked later. These are further sub-divided into two categories:
Those that should be fully verified before any decision to “go-live” for ALR operating regime is
taken
Those that could be closed-out shortly after ALR “go-live”
8.2.5 Both types of un-verified Safety Requirements must be added to a single central action tracker to ensure they are kept under regular review before “go live”. The necessary action is for the SRO to satisfy himself that these outstanding Safety Requirements are all closed out before the ALR phase of the scheme opens.
15 Webdas ref 69708
M25 LUS Section 5 Safety Report (pre-opening)
Page 37
8.2.6 Longer term actions are as follows:
Highways Agency and Connect Plus to ensure that a safety review takes place for any future
changes to the scheme that could impact safety. Owner: Highways Agency and Connect
Plus, Timescale: Throughout PCF Stage 7.
The assessment of safety performance data when available. Owner: Highways Agency,
Timescale: PCF Stage 7.
M25 LUS Section 5 Safety Report (pre-opening)
Page 38
Appendix A – Hazard Scoring Indices
M25 LUS Section 5 Safety Report (pre-opening)
Page 39
Table A1 - Frequency table for hazardous events
Frequency Classification
Nominal Value: Occurrences/
year/mile
Occurrences/ year/entire
scheme
Frequency of occurrences (for the entire scheme)
Index Value
Very frequent 1,000 26060 Three times an hour 6.0
316 8235 Once an hour 5.5
Frequent 100 2606 Once every 2 hours 5.0
31.6 823 Twice per day 4.5
Probable 10 261 Once per day 4.0
3.16 82 Twice a week 3.5
Occasional 1 26 Twice a month 3.0
0.316 8 Once every 2 months 2.5
Remote 0.1 2.6 3 times a year 2.0
0.0316 0.82 Once per year 1.5
Improbable 0.01 0.26 Once every 2 years 1.0
0.00316 0.082 Once every 10 years 0.5
Incredible 0.001 0.026 Once every 50 years 0.0
Table A2 - Frequency table for hazardous states
Likelihood Classification
Interpretation (for the entire scheme) Nominal Value per
mile of motorway
Expected no. of
occurrences on scheme
Index Value
Very frequent 26 or more occurrences at any one time 1 26 6.0
8 occurrences at any one time 0.316 8 5.5
Frequent 3 occurrences at any one time 0.1 2.6 5.0
10 months a year 0.0316 0.82 4.5
Probable 3 months a year 0.01 0.26 4.0
30 days a year 0.00316 0.082 3.5
Occasional 10 days per year 0.001 0.026 3.0
3 days per year 0.000316 0.0082 2.5
Remote 1 day a year 0.0001 0.0026 2.0
7 hours per year 0.0000316 0.00082 1.5
Improbable 2 hours per year 0.00001 0.00026 1.0
1 hour year 0.0000031 0.000082 0.5
Incredible 15 or less minutes a year 0.000001 2.6E-05 0.0
Table A3 - Hazardous Events/State Probability/Rate Classifications
M25 LUS Section 5 Safety Report (pre-opening)
Page 40
Classification Interpretation Index value
Certain It is certain that this hazard, if it occurs, will cause an accident 4
Probable It is probable that this hazard, if it occurs, will cause an accident
3
Occasional This hazard, if it occurs, will occasionally cause an accident 2
Remote There is a remote chance that this hazard, if it occurs, will cause an accident
1
Improbable It is improbable that this hazard, if it occurs, will cause an accident
0
Table A4 - Hazardous Events/State Severity Classifications
Severity Classification
Interpretation Index Value
Person outside of
vehicle
Stationary Vehicle
Motorcycle Car Large Vehicle
(LHV, HGV, Bus)
Severe The proportion of collisions that are fatal is expected to be higher than average by at least a factor of 10
2.0 Involved Involved Involved Speed differential approx 60 mph
Speed differential approx 50 mph
Higher than average
The proportion of fatal collisions is expected to be higher than average by a factor between 3 and 10
1.5 No involvement
No involvement
No involvement
Speed differential approx 50 mph
Speed differential approx 40 mph
Average The distribution of collisions (i.e. ratio of damage-only to fatal) is expected to be similar to the motorway average
1.0 No involvement
No involvement
No involvement
Speed differential approx 40 mph
Speed differential approx 30 mph
Lower than average
The proportion of fatal collisions is expected to be lower than average by a factor between 3 and 10
0.5 No involvement
No involvement
No involvement
Speed differential approx 30 mph
Speed differential approx 20 mph
Minor The proportion of collisions that are fatal is expected to be lower than average by at least a factor of 10
0.0 No involvement
No involvement
No involvement
Speed differential < 20 mph
Speed differential < 10 mph
Table A5 – Measuring before and after risk changes using finer scale
M25 LUS Section 5 Safety Report (pre-opening)
Page 41
Change in risk score (logarithmic) Absolute change in risk
0.5 216% increase in risk
0.4 150% increase in risk
0.3 100% increase in risk (i.e. doubling of risk)
0.2 60% increase in risk
0.1 25% increase in risk
0.0 No change in risk
-0.1 20% decrease in risk
-0.2 35% decrease in risk
-0.3 50% decrease in risk (i.e. risk is halved)
-0.4 60% decrease in risk
-0.5 70% decrease in risk
M25 LUS Section 5 Safety Report (pre-opening)
Page 42
Appendix B – Hazard Log Scores
M25 LUS Section 5 Safety Report (pre-opening)
Page 43
Hazard ID
Description Further Information Status Population E/S Before Risk
After Risk
1 Abnormal loads -
escortable
If it encroaches into other lanes or changes lanes likely to send a shockwave through
traffic or irregular flow Existing General Event 6.00 5.80
2 Abnormal loads -
notifiable
If it encroaches into other lanes or changes lanes likely to send a shockwave through
traffic or irregular flow Existing General Event 7.00 6.90
3 Aborting or pausing
LBS1 sequence half way Removed None 0.00 0.00
4
Blanking of one gantry when LBS1 open to
traffic indicates sudden local closure of LBS1
Removed None 0.00 0.00
5
Closing sequence overtakes vehicles in
LBS1, requiring them to move out of LBS1
unnecessarily
Removed None 0.00 0.00
7 Conflicting signs and
signals set
Vehicles may collide in the running lane as different drivers respond differently to the
information they have been presented with. Existing General State 5.00 5.10
9 Driver changes mind about entering ERA
New General Event 0.00 5.40
11 Driver ignores closed
lane(s) signals that are protecting an incident
To avoid the incident a driver might make a late manoeuvre causing a collision with other
vehicles in the adjacent lanes Existing General Event 8.00 7.80
12 Driver ignores traffic
management protecting a maintenance site
Not Scored for Hazard Log Comparison (Used to score other Hazards)
To avoid the incident a driver might make a late manoeuvre causing a collision with other
vehicles in the adjacent lanes
Retired for M25
None Event 0.00 0.00
13 Driver loses control of
vehicle Due to the loss of control the vehicle may
collide with other vehicles or infrastructure. Existing General Event 8.00 7.90
14 Driver mistakes ERA for
exit slip New General Event 0.00 5.90
15 Driver observance of red
X changes on rest of network
Removed None Event 0.00 0.00
M25 LUS Section 5 Safety Report (pre-opening)
Page 44
16 Driver on LBS1 fails to exit and continues on LBS1 through junction
New General Event 0.00 8.00
17 Driver stays on LBS1
when it is closing Removed None Event 0.00 0.00
18 Drivers assume that
LBS1 is open immediately after section
Removed None Event 0.00 0.00
19 Drivers assume they can
use LBS1 on rest of network
This hazard has been removed from the analysis. Drivers already encounter Multi-
lane roads without a Hard Shoulder Removed None Event 0.00 0.00
20 Drivers enter LBS1 too early when LBS1 being
opened Removed None Event 0.00 0.00
21
Emergency services driving at speed down
the hard shoulder (LBS1)
Not Scored for Hazard Log Comparison (Used to score other Hazards)
Retired for M25
None Event 0.00 0.00
22 Emergency staff -TO etc
on foot at scene of an incident
TO might be hit by vehicles. Existing Worker State 6.00 6.00
23 Escorted convoys
Long convoys travelling at lower speeds might slow down traffic and result in irregular
flow. Vehicles might also collide in the running lane if trying to overtake or avoid the
lane taken up by convoy
Existing General State 5.00 4.80
25 Excessive lane merging required when lanes are
closed Vehicles collide when merging Existing General State 6.00 5.90
26 Excessive opening and
closing of LBS1 Removed None Event 0.00 0.00
28 Extreme weather
conditions lead to a pile-up
An incident has already happened, and because of poor visibility, e.g. fog, vehicles fail to stop and plough into the back of the
queue of stationary traffic
Existing General Event 6.00 5.90
29 Generic underlying causes for hazards
Retired for M25
None Event 0.00 0.00
30 Group of vehicles drive too fast (in relation to
set/not set speed limit)
Vehicles might collide in the running lane or the vehicle could collide with infrastructure or veer off road (Inappropriate speeds generally
increase the chance of collision)
Existing General State 7.00 6.70
M25 LUS Section 5 Safety Report (pre-opening)
Page 45
31
HADECS flash unit misaligned affecting drivers on opposite
carriageway
The flashing might distract drivers in the opposite carriageway or cause them to brake suddenly in order to reduce speed and avoid
being caught for speed
New General State 0.00 3.50
32 Health deterioration of
vehicle occupant
With all lane running emergency vehicles might take longer to reach the occupant and health might deteriorate more. Vehicle might
collide with other vehicle if the health condition affects occupant's driving.
Existing General Event 7.00 7.05
34 Incident management -
rolling block
Vehicles might collide with ORR vehicles or brake suddenly when forced to slow down by
the rolling block. Existing Maintenance Event 5.00 5.20
35
Incident occurs in opened section of LBS1
during opening sequence
Removed None Event 0.00 0.00
36
Incidents or congestion caused in other lanes or
carriageway due to rubber necking
Driver distracted by incidents and congestion may lead to vehicles slowing down which in
turn leads to incidents Existing General State 7.00 6.90
37 Individual vehicle is
driven too fast
Vehicles might collide in the running lane or the vehicle could collide with infrastructure or
veer off road (In appropriate speeds generally increase the chance of collision)
Existing General State 9.00 8.87
38 Infrastructure collapse Infrastructure falling may hit vehicle, or
vehicles might collide if trying to avoid the falling object.
Existing General Event 4.00 4.00
39 Infrastructure collapse
due to additional load on LBS1
New General State 0.00 4.80
40
Lane closure signals are set in wrong lane
following an incident due to operator error
Vehicles may collide with unprotected incident or collision may result with drivers
swerving to avoid the incident Existing General State 5.00 5.00
41 Lane diverts into lane with incident due to
technical failure
Vehicles may collide if forced to stop/brake suddenly in a live lane in response to the
lane diversion. TO attending incident might be hit by a vehicle that has been diverted into
the wrong lane
Existing General Event 5.00 5.10
M25 LUS Section 5 Safety Report (pre-opening)
Page 46
42 Lane(s) closed, but
driver unable to leave lane and stops
Vehicle travelling behind stopped vehicle might be unable to stop in time and the two
vehicles might collide. A vehicle trying to avoid the stopped vehicle might collide with
others in the adjacent lanes.
Existing General Event 7.00 7.10
44 LBS1 closed too early Removed None State 0.00 0.00
45 LBS1 closed too late Removed None State 0.00 0.00
46 LBS1 opened before
required Removed None State 0.00 0.00
47 LBS1 opened too late (after traffic flow has
broken down) Removed None State 0.00 0.00
48 Legal-illegal
pedestrian(s) in path of vehicles in ERA
New Pedestrian Event 0.00 6.40
49
LGVs, HGVs or other wide vehicles avoid using LBS1 due to
narrowing effect of red studs
Removed None Event 0.00 0.00
50 Limping vehicles in LBS1 (when open)
Removed None State 0.00 0.00
51 Maintenance workers in
carriageway Maintenance workers might be hit by vehicles
in other lanes. Existing Maintenance Event 6.00 6.00
52 Maintenance workers setting up and taking
down work site
Maintenance workers might be hit by vehicles in other lanes.
Existing Maintenance State 7.00 6.90
53 MIDAS queue protection does not operate for a
significant queue
Vehicles might collide in running lane if appropriate speeds are not advised.
Existing General Event 6.50 7.00
54 Motorcycles filter
through traffic
Motorcyclist might collide with vehicles if he/she loses control whilst weaving through
traffic. Vehicles might collide if they swerve or change path in order to avoid the motorcyclist
Existing Motorcyclist Event 8.00 7.91
56 Motorcycle stopped on LBS1 as LBS1 opens
Removed None Event 0.00 0.00
58 Motorcyclist cross wind
buffering Existing Motorcyclist State 6.50 6.50
59 Motorcyclist falls off
crossing line on entry to ERA
New Motorcyclist Event 0.00 6.40
M25 LUS Section 5 Safety Report (pre-opening)
Page 47
61
Object in LBS1 causes impediment to traffic - causes drivers to take avoiding action when
opening
Removed None Event 0.00 0.00
62 On-road resources work
unprotected ORR might be hit by a vehicle Existing Worker State 7.50 7.40
63 Opening sequence is faster than the traffic
Removed None Event 0.00 0.00
64
Operator closes LBS1 following an incident on
main carriageway, diverting traffic toward
incident
Removed None State 0.00 0.00
65 Operator fails to remove signals after an incident
If signal setting includes lane closures, additional unnecessary lane changing will
occur Existing General Event 4.00 3.90
66 Operator fails to set
signals to protect incident in timely manner
If signal setting includes lane closures, additional unnecessary lane changing will
occur Existing General State 5.50 5.40
67 Pedestrian in running
lane - live traffic
For some reason, possibly trying to reach an ERT on the opposite side of the carriageway
someone is on the live carriageway. Pedestrian might be hit by traffic. Vehicles
might collide whilst trying to avoid the pedestrian. For MM2 includes pedestrians walking along the carriageway to seek help
(as opposed to walking along verge see H73).
Existing Pedestrian Event 8.50 8.40
68 Pedestrian on slip road Pedestrian might be hit by traffic. Vehicles
might collide whilst trying to avoid the pedestrian.
Existing Pedestrian State 7.00 7.00
69 Pedestrians in a running
lane - stationary-slow moving traffic
After a major incident occurs and the motorway comes to a complete standstill,
people leave their vehicles and walk about. Pedestrian might be hit by traffic. Vehicles
might collide whilst trying to avoid the pedestrian. For MM2 includes pedestrians walking along the carriageway to seek help
(as opposed to walking along verge).
Existing Pedestrian State 7.50 7.40
M25 LUS Section 5 Safety Report (pre-opening)
Page 48
70
Pedestrians on hard shoulder adjacent to a parked vehicle (D3M = Hard Shoulder) (MM2 =
verge).
Only used to inform other hazards Retired for M25
None State 0.00 0.00
71 Pedestrians on LBS1 while opening LBS1
Removed None Event 0.00 0.00
74 Person on off-side of
vehicle in ERA New Pedestrian State 0.00 6.40
75
Power failure of several/all gantries
during LBS1 running effectively indicates
sudden closure of LBS1
Removed None Event 0.00 0.00
76 Rapid change of general
vehicle speed
Approaching vehicles are unlikely to be able to manoeuvre safely around the group of
vehicles that has decelerated (the lanes will be occupied) and therefore must rely on
being able to brake safely to avoid a collision. Approaching vehicles may also collide while changing or merging lanes in an attempt to
avoid the slower-moving vehicles ahead
Existing General Event 8.40 8.06
77 Reduced visibility due to
weather conditions The reduction in stopping and decision sight
distances may lead to a collision Existing General State 7.00 6.80
78
Road Traffic Collision in live lane pushes one or
more vehicles into a maintenance site
Vehicle collides with maintenance site / vehicle - only required to inform other
hazards
Retired for M25
None Event 0.00 0.00
79 Roadworks - long term
static Vehicle collides with maintenance site /
vehicle or pedestrian worker Existing Maintenance State 7.50 7.50
80 Roadworks - short term
static Vehicle collides with maintenance site /
vehicle or pedestrian worker Existing Maintenance State 6.50 6.50
82 Short duration stops /
debris removal by TO / maintenance workers
Vehicle collides with maintenance site / vehicle or pedestrian worker. Includes visits
to equipment cabinets - if they exist. Existing Maintenance State 7.00 6.50
83 Signals change while
TO/ emergency services are still on motorway
Vehicle collides with maintenance site / vehicle or pedestrian worker
Existing Worker Event 6.00 5.90
84 Signals set in wrong
place (i.e. are not protecting the incident)
Vehicles are likely to collide if forced to stop suddenly in a live lane in response to the
signal set. Existing General State 4.00 3.90
M25 LUS Section 5 Safety Report (pre-opening)
Page 49
85 Significant incursion of
passing vehicle into ERA New General Event 0.00 5.90
86 Slow traffic in LBS2
passed by faster traffic on LBS1
Removed None State 0.00 0.00
87
Speed differential between emergency services and general
traffic
Existing General Event 6.50 6.50
88 Stationary traffic backed up onto motorway at exit
Irregular traffic flow. Vehicles approaching the exit might misjudge the traffic conditions
and approach at an inappropriate speed, resulting in a collision between vehicles
Existing General State 6.00 5.90
89 Sudden weaving at exit
point Vehicles might brake suddenly resulting in a
collision with vehicles behind Existing General Event 8.00 7.93
90
System failure - signs or signals incorrectly
indicate that lanes with static roadworks are
open
Vehicles might change lanes or swerve suddenly to avoid roadworks resulting in a collision with other vehicles in the live lane
Retired for M25
None State 0.00 0.00
91 Tail gating
Any braking or sudden lane change by vehicle in front is likely to result in a collision. Space between the vehicles does not allow sufficient reaction time for driver/s behind
Existing General State 8.50 8.20
92 Terrorism of system A significant number of casualties might
result depending on the nature of the attack e.g. a bomb
Existing General Event 5.00 5.00
93 The driver loses control
and enters the maintenance site
Vehicle might collide with maintenance site/workers
Retired for M25
None Event 0.00 0.00
94 TO arrives, but has
difficulty containing the scene
TO might be hit by vehicles in adjacent lane. Existing Worker Event 7.00 6.90
95 TO/ISUO in running lane TO might be hit by vehicles Existing Worker Event 8.00 7.90
96 TOs behave
hazardously at an incident
TO might be hit by vehicles Existing Worker Event 6.50 6.50
97 TOs/ emergency
services go to wrong location (incident)
Delay in attending incident might leave the original incident exposed to live traffic
Existing Worker Event 6.00 5.90
M25 LUS Section 5 Safety Report (pre-opening)
Page 50
98 TOs/emergency services despatched but cannot
reach scene
Delay in attending incident might leave the original incident exposed to live traffic
Existing Worker Event 6.00 6.00
99 TOs/emergency services
not despatched in a timely manner
Delay in attending incident might leave the original incident exposed to live traffic
Existing Worker Event 7.00 6.80
100 Unable to remove settings of signs or
signals after incidents
Irregular traffic flow. Vehicles might collide while changing lanes
Existing General Event 4.00 4.10
101 Unable to set signs and
signals to protect incidents
Secondary incident might occur of initial incident is left exposed to live traffic
Existing General State 6.10 6.50
102 Undertaking Vehicles collide when merging or changing
lanes Existing General Event 7.00 6.80
103 Unsafe lane changing Vehicles collide when merging or changing
lanes Existing General Event 8.00 7.80
104 Unsafe lane changing in
the slip road (both off and on slips)
Vehicles collide when merging or changing lanes
Existing General Event 7.00 6.86
105 Vandalism of equipment Cost implications are likely to arias from the
vandalism of equipment Existing General Event 3.00 3.00
106
Vandalism or sabotage directed at injuring
members of the public or Managed Motorway staff
Casualties/death are likely to result from being hit by an object or equipment.
Existing General Event 5.00 5.00
107 Vehicle accelerates into LBS1 immediately after
last red X Removed None Event 0.00 0.00
108 Vehicle decelerates
suddenly in response to signals
Vehicles are likely to collide in running lane if drivers behind do not react in time
Existing General Event 4.50 4.40
110 Vehicle drifts out of lane Vehicle might collide with infrastructure or
with vehicles in adjacent running lane. Existing General Event 7.50 7.43
111 Vehicle drives down LBS1 when closed
Vehicle might collide with other vehicles stopped on the hard shoulder
Retired for M25
None Event 0.00 0.00
112 Vehicle enters main
carriageway unsafely Vehicles collide in the running lane Existing General Event 8.00 7.80
113 Vehicle exits ERA when LBS1 is open to traffic
New General Event 0.00 7.40
M25 LUS Section 5 Safety Report (pre-opening)
Page 51
115
Vehicle in lane adjacent to hard shoulder (LBS1) straddles hard shoulder
(LBS1)
Vehicle might collide with other vehicles stopped on the hard shoulder
Retired for M25
None Event 0.00 0.00
116 Vehicle misjudges entry
to ERA New General Event 0.00 7.00
118 Vehicle on the main
carriageway decelerates suddenly
Vehicles might collide in the running lane Existing General Event 7.00 6.80
120 Vehicle rejoins running
lane
The vehicle may emerge directly into the path of a passing vehicle, resulting in a collision
between the emerging vehicle and an oncoming vehicle in the nearside lane.
Existing General Event 8.00 7.70
121 Vehicle reversing along
exit slip Vehicles might collide on or around slip roads Existing General Event 8.00 7.90
122 Vehicle reversing back
to exit slip Vehicles might collide on or around slip roads Existing General Event 7.00 7.00
123 Vehicle reversing up
entry slip Vehicles might collide on or around slip roads Existing General Event 7.00 6.90
125 Vehicle stopped on
LBS1 as LBS1 opens Removed None Event 0.00 0.00
126 Vehicle stopped on slip
road (off or on slip) Vehicles might collide on or around slip roads Existing General Event 7.00 7.20
128 Vehicle stops in LBS1
when LBS1 open
Collisions may occur on LBS1, if a vehicle runs into the back of the queue, or in LBS2, if
a vehicle pulls out to avoid the queue. Removed None Event 0.00 0.00
130 Vehicle stops/attempts to stop on the central
reserve
If the vehicle encroaches onto the running a collision might result with vehicles in adjacent running lane. Vehicles swerving to avoid the
stopped vehicle might collide
Existing General Event 6.50 6.60
131 Vehicle suddenly
decelerates at end of on slip road
Vehicles might collide on or around slip roads Existing General Event 7.10 7.00
132 Vehicle suddenly
decelerates while on off-slip
Vehicles might collide on or around slip roads Existing General Event 4.50 4.50
133 Vehicle travelling in
wrong direction Vehicle collides with vehicles travelling in the
opposite direction Existing General State 5.50 5.40
134 Vehicles with trailer /
caravans travelling too fast
Vehicles might collide in the running lane or when swerving/changing lanes to avoid the
articulated vehicles. Existing General Event 6.50 6.40
M25 LUS Section 5 Safety Report (pre-opening)
Page 52
135 Vehicle Stops in
Running Lane - Off Peak (Event)
A vehicles stopping might send a shockwave through traffic resulting in irregular flow. Other vehicles might also collide with the
stopped vehicles or if they swerve to avoid the stopped vehicle
Existing General Event 7.81 8.21
136 Collision with workers doing maintenance on
verge
Defines such activities as grass-cutting, collection of litter from the verge, working on
Cabinets etc. Existing Maintenance State 6.50 6.10
137 Debris in running lane (being hit or causing unsafe manoeuvre)
Vehicles might hit debris or collide with other vehicles when trying to avoid debris in
running lane Existing General State 7.50 7.43
138 Driver Fatigued - unable
to perceive hazards effectively
Driver/rider was so tired that they could not drive effectively or were unable to perceive
hazards. Vehicle may be involved in collisions with
other vehicles/infrastructure or may lead to other vehicles taking evasive action
Existing General Event 9.00 8.99
139 Excessive lane changing caused by availability of
an additional lane New General Event 0.00 2.90
140 Excessively slow moving vehicle in running lane
A collision might result if drivers swerve to avoid the vehicle or if this slow moving
vehicle tries to change lane to avoid vehicles moving at higher speeds.
Existing General State 4.50 4.60
141 HGV-LGV-Bus exits
ERA Note: H120 covers other types of rejoining
carriageway New HGV Event 0.00 7.40
142
Large vehicle does not completely clear the running lane when stopping on Hard
Shoulder (D3M) or Verge (MM-ALR)
Assume that in some cases the driver will attempt to move the vehicle off the main carriageway and onto verge (MM2 only)
Existing HGV State 4.50 4.30
143
Motorcycle stopped next to running lanes (D3M = Hard Shoulder, MM-ALR
= verge)
Motorcyclist at risk from other vehicles travelling on the hard shoulder. For dynamic
use of LBS1, only applies when LBS1 is closed
Existing Motorcyclist State 7.00 6.50
144
Motorcycle uses hard shoulder to pass slow moving or stationary
traffic
Motorcyclists might collide with vehicles already on the hard shoulder
Existing Motorcyclist State 6.00 5.50
M25 LUS Section 5 Safety Report (pre-opening)
Page 53
145 Motorcyclists crosses
rumble strips
Motorcyclist might fall off bike. Secondary incident likely to occur if he falls onto the live
lane Motorcyclist Event 5.50 5.50
146 Pedestrians walking
along the hard shoulder (Applies to D3M only)
If there is any rubber necking a vehicle might veer off lane and hit the pedestrian on the
verge/LBS1 Existing Pedestrian State 6.50 6.00
147 Pedestrians walking in lane 1 (applies to MM-
ALR only) New Pedestrian State 0.00 6.90
148 Roadworks - short term static on hard shoulder
Vehicle collides with maintenance site / vehicle or pedestrian worker
Existing Maintenance State 7.50 7.00
149
Vehicle drifts off carriageway (i.e. leaving
the carriageway as a result of Road Environment)
Vehicle might collide with infrastructure. HGV etc might go through barriers
Existing General Event 8.00 8.00
150 Vehicle in ERA (or
verge_ obtrudes into Lane 1 (MM-ALR only)
New General State 0.00 7.00
151
Vehicle not fully in control when trying to stop on Hard Shoulder (D3M) or Verge (MM-
ALR)
Vehicle collides with infrastructure, pedestrians or runs off road.
Existing General Event 6.00 5.90
152 Vehicle recovered from
ERA New General Event 0.00 7.90
153 Vehicle reversing up
Hard shoulder (D3M) or Lane 1 (MM-ALR)
Vehicle collides with vehicles travelling in the opposite direction
Existing General Event 7.00 6.50
154 Vehicle stopped on Hard Shoulder (D3M) or verge
(MM-ALR) Existing General State 8.00 7.50
155 Vehicle stops in running
lane - Peak
A vehicles stopping might send a shockwave through traffic resulting in irregular flow. Other vehicles might also collide with the
stopped vehicles or if they swerve to avoid the stopped vehicle
Existing General Event 7.90 8.10
M25 LUS Section 5 Safety Report (pre-opening)
Page 54
Appendix C – Previously Outstanding Safety Tasks
M25 LUS Section 5 Safety Report (pre-opening)
Page 55
Task Ref
Task Title Task Description Update as of October
2013 Task Status Owner
T6 Maintenance
Depots
Merge/Diverge Layouts - There is limited carriageway space to provide compliant layouts for the maintenance depots. Safe Haven - The area around the merge and diverge may appear to be a safe haven for motorists who are breaking down - consider measures to reduce this risk.
Gregory’s Lane access to be hatched to extent described in PSCRG TN27
Now closed
Atkins
T9 Height of
verge signs
Ensure height of underside of sign plate allows for maintainers to walk under. Extent and final routing of pathways is a long term task, so possibly assume all signs are higher until Value Engineering can take place. Also remember that public may try and use whole verge length during emergency so case for all signs (within say 3.0m of road) to be high regardless of pathway presence. Carefully consider if any flapped verge signs then become too high to reach to open/close.
Standard mounting heights to be used as no interaction with pathways. No flapped signs in existing or proposed situation
Now closed Atkins
T10 Removal of white lines
Previous lane markings often remain visible following changes to the layout and this can confuse drivers, especially in bad light and poor weather conditions. A long debate took place on MM-DHSR schemes – ghosting may best be avoided by hydro removal methods but this introduces higher risk of stone loss and joint opening. Consider trial of one or more methods.
The method of removal was tasked to SBB and the work has concluded successfully where lining has been removed already.
Now closed SBB
T12 Hard
shoulder breakdowns
Consider hatching hard shoulder at residual lengths Hatching only provided where stopping may be unsafe due to length/width. Extent described in PSCG TN27
Now closed Atkins
T15
Fixed Central
Reserve TM signing
It is anticipated that the majority of maintenance will be undertaken using Lane 1 closures. The need for operatives to cross the carriageway to install 'wicket ' signs would be reduced by the installation of fixed Central Reserve remote controlled signs.
The scheme approach is explained in PSCRG TN 4 and in PSCRG TN 23. The scheme Maintenance and Repair Strategy
Now closed Atkins/CPS
M25 LUS Section 5 Safety Report (pre-opening)
Page 56
Task Ref
Task Title Task Description Update as of October
2013 Task Status Owner
Statement summarises this issue – paired signs will be provided in verge and centre.
T16 MS4 Signs -
Criticality
Failure of an individual MS4 could result in a section of around 2km with no facility for incident or speed management. Options for carrying a stock of spare MS4s should be considered.
The HA has issued a draft contract change that defines response times for restoring signals. Service Providers will be able to decide how they can best achieve the contract requirements.
Now closed Atkins/CPS
T20 Diversion
routes
It is accepted that substantive change to diversion strategy is outside scope of scheme, but it is necessary to understand how existing strategy can be operated
It is confirmed that no flap signs are in use in the existing scenario
Now closed Atkins
T22 Slip road
ERT visibility Ensure slip road ERTs are not visible to a stranded motorist at a Intra junction location.
TJR junctions checked and no physical screening
is required . Lane drop junctions unaffected as
existing situation
Now closed Atkins
M25 LUS Section 5 Safety Report (pre-opening)
Page 57
M25 LUS Section 5 Safety Report (pre-opening)
Page 58
M25 LUS Section 5 Safety Report (pre-opening)
Page 59
Appendix D – Safety Requirements
M25 LUS Section 5 Safety Report (pre-opening)
Page 60
Ref Responsible Source Safety Requirement
SR-01 HA/Designer Generic Safety
Report
Signal sequencing rules must facilitate the required signalling outcomes in response to manual or automatic primary signal settings, and be appropriate for the signal / message sign spacing and operating speed.
SR-02 Designer Generic Safety
Report
Instruction on which lane(s) to use- For the prevailing traffic conditions, motorists shall be given clear instruction on which lane(s) to use. These instructions must facilitate vehicle movements (from lane to lane) in a controlled and safe manner.
SR-03 Designer Generic Safety
Report Variable mandatory speed control must be provided
SR-04 Designer Generic Safety
Report
An automatic queue protection system (e.g. MIDAS) to alert both operators and road users of changes in traffic conditions must be provided.
SR-05 Designer/Oper
ator Generic Safety
Report An enforcement strategy must be implemented to ensure creation and maintenance of a 'controlled' environment.
SR-06 Highways Agency
Generic Safety Report
A monitoring strategy must be in place to enable the creation and maintenance of the required network and safety performance data
SR-07 Highways Agency
Generic Safety Report
Stakeholder engagement must be designed to facilitate and support effective education and encouragement of road users
SR-08 Designer Generic Safety
Report
All equipment must be designed to eliminate or minimise the need for maintenance and reduce the exposure for road workers SFAIRP (So Far As Reasonably Practicable).
SR-09 Designer Generic Safety
Report
Roadside equipment requiring maintenance should, where practicable, be clustered and an appropriate access strategy put in place minimising the need for temporary traffic management in live lanes.
SR-10 Maintainer Generic Safety
Report Maintenance contractors must be trained and competent in the appropriate maintenance procedures.
SR-11 Maintainer Generic Safety
Report Winter treatment must include all designated refuge areas.
SR-12 HA/Designer Generic Safety
Report
Faults that impact on the safe and efficient operation of the system shall be defined and response / repair times incorporated into relevant contracts in accordance with their impact.
SR-13 Maintainer Generic Safety
Report Sightlines must be effectively maintained to signs and signals
SR-14 Operator Generic Safety
Report Procedures and guidance must be appropriate and effective for safe operation
M25 LUS Section 5 Safety Report (pre-opening)
Page 61
Ref Responsible Source Safety Requirement
SR-15 Operator Generic Safety
Report
Traffic Officers must be trained and competent to work in accordance with the latest National Procedures and the Operational Procedures and Guidance provided within the MM Manual Operators must be trained in the MM-ALR scheme procedures. They must also be competent in carrying out the Procedures and guidance.D23
SR-16 Operator Generic Safety
Report Operators must have instantaneous access to the current Procedures and Guidance at all relevant workstations.
SR-17 Operator Generic Safety
Report The interfaces with Emergency Services must be effective and must allow them to carry out their functions
SR-18 Operator Generic Safety
Report Procedures shall use a consistent lane referencing system across a scheme.
SR-19 Operator/Maint
ainer Generic Safety
Report A system must be established to operationally manage the access and actions of maintenance personnel.
SR-20 Designer Generic Safety
Report Software/hardware must be in accordance with Highways Agency standards
SR-21 Designer Generic Safety
Report Software development procedures and testing must be in accordance with Highways Agency standard
SR-22 Designer Generic Safety
Report All site and system data must be maintained under strict version control.
SR-23 Maintainer Generic Safety
Report
After maintenance activity has been carried out on the technology system and / or equipment, tests shall be carried out to re-commission them to the ‘as-built’ / as-commissioned.
SR-24 Designer Generic Safety
Report
Full CCTV camera coverage must be provided of the carriageway (including refuge areas). The coverage must be such that an operator can interpret correctly the nature of each incident within the designed viewing range at all times of day and night, and in all ambient lighting levels whether the carriageway is lit or not, as they will be used to confirm the location of incidents on the main carriageway. To achieve this, at the extreme of the required coverage and maximum zoom, a 1.75m target should represent a minimum of 5% of screen
SR-25 Designer Generic Safety
Report
Fixed signage must be provided directing motorists to ERTs (not including signage for pedestrians on marker posts which will not be provided on MM-ALR schemes).
SR-26 Not Used
M25 LUS Section 5 Safety Report (pre-opening)
Page 62
Ref Responsible Source Safety Requirement
SR-27 Designer Generic Safety
Report Safety barrier must only be installed where necessary, i.e. gaps should not be necessarily closed.
SR-28 Maintainer Scheme Hazard
Log Roadworkers shall not cross the mainline carriageway on foot
SR-29 Designer Scheme Hazard
Log A means of displaying roadworks wicket signs shall be included in the permanent works for each MM-ALR link
SR-30 Maintainer Scheme Hazard
Log ERAs will not be used by service providers whilst Lane 1 is trafficked
SR-31 Maintainer/ Operator
Scheme Hazard Log
VMSL will be displayed upstream of cone-laying and cone-removal plant
SR- 32 Relevant to M25 LUS Section 2 only; not used for Section 5
SR-33 Operator PSCRG TN2 RCC should be tasked with feeding back their experiences of dealing with heavy rain events within the first 3 months of opening
SR-34 Designer PSCRG TN2 The Edge of Carriageway Rib line should have drainage gaps as per SHW
SR-35 Designer PSCRG TN2 Chamber covers in flexible pavement should be orientated to reduce trafficking and re-located as close to the centre of the new Lane 1 as far as is reasonably practicable
SR-36 Maintainer MRSS
(Prior to opening) CPS to develop amended risk assessment for VRS to determine priority of response and any necessary control measures to manage risks after any impact damage reported on MM-ALR sections of scheme.
SR-37 Relevant to M25 LUS Section 2 only; not used for Section 5
SR-38 Designer PSCRG TN6 White-webbs footbridge staircase to be amended to reduce risk to pedestrian users
SR-39 Designer PSCRG TN6
It is recommended that a profiled lane line marking meeting the reflectivity requirements of SHW clause 1212.5 (commonly known as “rainline”) is used to assist with lane delineation on the concrete pavement. This line type may also assist in daytime on the predominantly east-west route. (J24-25)
SR-40 Designer Scheme Hazard
Log Speed camera sign to be provided on all types of signal gantry i.e. Portal and cantilever.
SR-41 Designer Scheme Hazard
Log Rigid concrete barrier to be provided in the central reserve where possible.
The following Safety Requirements have been added since the pre-construction Safety Report was produced
SR-42 Designer PSCRG TN 15
and 24
Holmesdale and Bell Common Tunnels to retain a usable hard shoulder; the hard shoulder is also to extend upstream and downstream of a tunnel to permit a stricken HGV to park at an Emergency Telephone outside of tunnel
SR-43 Maintainer MRSS and
PSCRG TN23
Maintainer to develop protocol for deployment of remotely operated temporary traffic management signs, including visual confirmation of correct deployment.
M25 LUS Section 5 Safety Report (pre-opening)
Page 63
Ref Responsible Source Safety Requirement
SR-44 HA MRSS
Technology response times to be amended contractually to be suitable for MM-ALR so that technology outages are limited in number and duration by adherence to the contract requirements.
SR-45 Maintainer MRSS
To dissuade public comfort stops, the ALR verge shall not be hardened where traffic could mount the verge after leaving the hard strip. A 1.0m verge strip nearest to paved edge of ALR nearside shall be maintained such that the grass length shall be limited to an average not exceeding 350mm, so as to permit emergency public access to the verge.
M25 LUS Section 5 Safety Report (pre-opening)
Page 64
Appendix E – Safety Requirements Verification
M25 LUS Section 5 Safety Report (pre-opening)
Page 65
Ref Responsible Source Safety Requirement Verification Commentary Verification Status
SR-01
HA/Designer Generic Safety Report
Signal sequencing rules must facilitate the required signalling outcomes in response to manual or automatic primary signal settings, and be appropriate for the signal / message sign spacing and operating speed.
HA has confirmed that Version 3.2 of the Managed Motorways – All Lanes Running (MM-ALR) Driver Information Requirements Specification, will be issued in Autumn 2013. “Site data” work can only be finalised once rules fully published.
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
SR-02
Designer Generic Safety Report
Instruction on which lane(s) to use- For the prevailing traffic conditions, motorists shall be given clear instruction on which lane(s) to use. These instructions must facilitate vehicle movements (from lane to lane) in a controlled and safe manner.
Scheme follows IAN 161 requirements
Verified
SR-03
Designer Generic Safety Report
Variable mandatory speed control must be provided
Scheme follows IAN 161 requirements
Verified
SR-04
Designer Generic Safety Report
An automatic queue protection system (e.g. MIDAS) to alert both operators and road users of changes in traffic conditions must be provided.
Scheme follows IAN 161 requirements
Verified
SR-05
Designer/ Operator
Generic Safety Report
An enforcement strategy must be implemented to ensure creation and maintenance of a 'controlled' environment.
Scheme follows IAN 161 requirements, but HADECS enforcement system version 3 is still awaiting Home Office Type Approval and this approval is needed before camera enforcement can occur.
Revisit later in current stage This requirement is a key issue before ALR can operate.
M25 LUS Section 5 Safety Report (pre-opening)
Page 66
Ref Responsible Source Safety Requirement Verification Commentary Verification Status
SR-06
Highways Agency
Generic Safety Report
A monitoring strategy must be in place to enable the creation and maintenance of the required network and safety performance data
The scheme will be the subject of a consultancy commission managed by HA Netserv. This work will involve detailed investigations of M25 and other early ALR schemes within the HA’s national programme. The HA POPE (post opening project evaluation) process will also be made use of.
Revisit later in current stage A clear plan is in place. This requirement is not considered essential for a decision to operate ALR, but must be verified shortly after go-live.
SR-07
Highway Agency
Generic Safety Report
Stakeholder engagement must be designed to facilitate and support effective education and encouragement of road users
The HA has a detailed and timed programme of activity. This is based on delivery of MM-ALR generic programme level key messages to influence behaviours. On a local basis for LUS, HA will seek local media opportunities giving LUS scheme context; programme tied to opening dates.
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
SR-08
Designer Generic Safety Report
All equipment must be designed to eliminate or minimise the need for maintenance and reduce the exposure for road workers SFAIRP (So Far As Reasonably Practicable).
A maintenance and repair strategy has been prepared to verify this requirement.
Verified
SR-09
Designer Generic Safety Report
Roadside equipment requiring maintenance should, where practicable, be clustered and an appropriate access strategy put in place minimising the need for temporary traffic management in live lanes.
A maintenance and repair strategy has been prepared to verify this requirement.
Verified
SR-10
Maintainer Generic Safety Report
Maintenance contractors must be trained and competent in the appropriate maintenance procedures.
Contractors will be required to update their Risk Assessments and Method Statements and carry out any training necessary. The MRSS has been circulated to contractors and a meeting held to discuss.
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
M25 LUS Section 5 Safety Report (pre-opening)
Page 67
Ref Responsible Source Safety Requirement Verification Commentary Verification Status
SR-11
Maintainer Generic Safety Report
Winter treatment must include all designated refuge areas.
Refuge areas and retained hard shoulders will be included in winter treatment with the same priority as hard shoulders on D3M. Updated Winter Service Plan is imminent.
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
SR-12
HA/Designer Generic Safety Report
Faults that impact on the safe and efficient operation of the system shall be defined and response / repair times incorporated into relevant contracts in accordance with their impact.
MM Programme Board paper entitled “MMALR and Technology Maintenance Requirements” [HA Author: Antony Atkins Dated: 25 July 2013] provides the details to be put in place via amended contracts
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
SR-13
Maintainer Generic Safety Report
Sightlines must be effectively maintained to signs and signals
New and relocated signs will be uploaded to signs inventory and passed to O&M team for sightline maintenance. Sightlines will be maintained as necessary.
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
SR-14
Operator Generic Safety Report
Procedures and guidance must be appropriate and effective for safe operation
Scheme is consistent with national ALR Concept of Operations Version 2 (August 2013). Final drafting of national TOS/RCC procedures is nearing completion and will be informed by a detailed risk assessment that is currently being assessed by a core team of TMD Staff. Following successful completion of the risk assessment, HA TMD will either be in a position to publish the final procedures.
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
M25 LUS Section 5 Safety Report (pre-opening)
Page 68
Ref Responsible Source Safety Requirement Verification Commentary Verification Status
SR-15
Operator Generic Safety Report
Traffic Officers must be trained and competent to work in accordance with the latest National Procedures and the Operational Procedures and Guidance provided within the MM Manual Operators must be trained in the MM-ALR scheme procedures. They must also be competent in carrying out the Procedures and guidance.D23
The Resource and Capability Group are currently designing training for both On and Off Road staff; however this training will not be rolled out until the Risk Assessments have been completed (see SR14) and the procedures released.
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
SR-16
Operator Generic Safety Report
Operators must have instantaneous access to the current Procedures and Guidance at all relevant workstations.
Upon publication of Procedures and Guidance, they will be made available on the HA Way We Work portal as per other HA TMD Procedural Instructions
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
SR-17
Operator Generic Safety Report
The interfaces with Emergency Services must be effective and must allow them to carry out their functions
HA TMD Traffic Officer Procedures will detail formal operating interfaces during incident management. The local police forces are updating their own processes and procedures and this effort is being informed by national level Task and Finish Groups. Once the local emergency services have finished their work, a local meeting will take place to agree a MoU or joint protocols with HA TOS and service providers. It is anticipated that local joint tabletop exercises will be used to test all parties’ procedures.
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
M25 LUS Section 5 Safety Report (pre-opening)
Page 69
Ref Responsible Source Safety Requirement Verification Commentary Verification Status
SR-18
Operator Generic Safety Report
Procedures shall use a consistent lane referencing system across a scheme.
This will form part of the National TOS Procedures once complete.
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
SR-19
Operator/Maintainer
Generic Safety Report
A system must be established to operationally manage the access and actions of maintenance personnel.
Permit to Enter process will be included in CPS roadspace procedures for ALR sections
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
SR-20
Designer Generic Safety Report
Software/hardware must be in accordance with Highways Agency standards
All software/hardware provided for the scheme is compliant with relevant Highways Agency specifications.
Verified
SR-21
Designer Generic Safety Report
Software development procedures and testing must be in accordance with Highways Agency standard
No software development took place Verified
SR-22
Designer Generic Safety Report
All site and system data must be maintained under strict version control.
Site data and system data will be maintained as defined in the relevant Highways Agency specifications.
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
M25 LUS Section 5 Safety Report (pre-opening)
Page 70
Ref Responsible Source Safety Requirement Verification Commentary Verification Status
SR-23
Maintainer Generic Safety Report
After maintenance activity has been carried out on the technology system and / or equipment, tests shall be carried out to re-commission them to the ‘as-built’ / as-commissioned.
The TechMAC has advised that the technology system will be maintained in accordance with the relevant Highways Agency Specification unless otherwise stated in Maintenance and Repair Strategy Statement documentation/Health and Safety Handover File, including MCH 1349, which will be incorporated into TechMAC maintenance procedures. MCH 1349 specifies the requirements for installation standards, spares, documentation, routine maintenance schedules, specialist test equipment, handover into maintenance and warranty.
Revisit later in current stage A clear plan is in place. This requirement is not considered essential for a decision to operate ALR, but must be verified shortly after go-live.
SR-24
Designer Generic Safety Report
Full CCTV camera coverage must be provided of the carriageway (including refuge areas). The coverage must be such that an operator can interpret correctly the nature of each incident within the designed viewing range at all times of day and night, and in all ambient lighting levels whether the carriageway is lit or not, as they will be used to confirm the location of incidents on the main carriageway. To achieve this, at the extreme of the required coverage and maximum zoom, a 1.75m target should represent a minimum of 5% of screen
CCTV Coverage Reports produced. Verified CCTV Coverage Report for Section 5: 5108945-ATK-0715-S5-DOC-X-0143 details 99.5% coverage
M25 LUS Section 5 Safety Report (pre-opening)
Page 71
Ref Responsible Source Safety Requirement Verification Commentary Verification Status
SR-25
Designer Generic Safety Report
Fixed signage must be provided directing motorists to ERTs (not including signage for pedestrians on marker posts which will not be provided on MM-ALR schemes).
Scheme follows IAN 161 requirements
Verified Advanced signing of ERA/ERT(SoS) provided Marker posts are only used within extents of hard shoulders to direct ex-vehicle pedestrians to ERTs. Specified in marker post schedule below: Section 5: 5108945-ATK-0712-S5-CH-X-0218 And 5108945_ATK_0712_S5_SCH_X_0534
SR-26
Designer Not used
SR-27
Designer Generic Safety Report
Safety barrier must only be installed where necessary, i.e. gaps should not be necessarily closed.
RRRAP used and barrier only provided where risk of non-provision is unacceptably high
Verified Where a gap between different sets of safety barrier is less than 20m it is infilled to remove the need for terminal sections. The 20m gap is stated in the IAN 161/12 paragraph 5.12. Report ref: Section 5 5108945-ATK-0704-S5-DIS-X-0022
M25 LUS Section 5 Safety Report (pre-opening)
Page 72
Ref Responsible Source Safety Requirement Verification Commentary Verification Status
SR-28
Maintainer Scheme Hazard
Log
Roadworkers shall not cross the mainline carriageway on foot
Secret signs at fixed taper positions are provided as set out in the MRSS for ALR sections. These signs will negate the need to cross the main carriageway on foot to place temporary signs
Verified
SR-29
Designer Scheme Hazard
Log
A means of displaying roadworks wicket signs shall be included in the permanent works for each MM-ALR link
Secret signs at fixed taper positions are provided as set out in the MRSS for ALR sections. These signs will negate the need to cross the main carriageway on foot to place temporary signs
Verified
SR-30
Maintainer Scheme Hazard
Log
ERAs will not be used by service providers whilst Lane 1 is trafficked
Requirement stated in MRSS. CPS procedure is in draft and will prohibit use of ERAs and also prohibit retained hard shoulders for maintenance purposes. Any exceptions will be subject to dynamic risk assessment.
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
SR-31
Maintainer/ Operator
Scheme Hazard
Log
VMSL will be displayed upstream of cone-laying and cone-removal plant
HA document “Generic Safe Method for placing TTM on MM-ALR” confirms existing policy allows RCC to make use of VMSL. CPS O&M manual (currently being drafted) will include TM “launch” procedure and linkage to RCC procedure
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
SR-32
Relevant to M25 LUS Section 2 only; not used for Section 5
M25 LUS Section 5 Safety Report (pre-opening)
Page 73
Ref Responsible Source Safety Requirement Verification Commentary Verification Status
SR-33
Operator PSCRG
TN2
RCC should be tasked with feeding back their experiences of dealing with heavy rain events within the first 3 months of opening
HA TMD has noted that as this will be the first MM-ALR (Smart) motorway to be opened a time table of review meetings will be set for each month with the RCC & On Road managers to feedback best practice and issues that may have encountered. Heavy rain events can be included in the agenda as a standing item
Revisit later in current stage A clear plan is in place. This requirement is not considered essential for a decision to operate ALR, but must be verified shortly after go-live.
SR-34
Designer PSCRG
TN2 The Edge of Carriageway Rib line should have drainage gaps as per SHW
Specified in Appendix 12/3.
Verified Specified in Appendix 12/3. Section 5: 5108945-ATK-0712-S5-SPEX-0215
SR-35
Designer PSCRG
TN2
Chamber covers in flexible pavement should be orientated to reduce trafficking and re-located as close to the centre of the new Lane 1 as far as is reasonably practicable
Covers have been upgraded to E600 and have a minimum skid resistance, PSRV value of 60 to make them suitable for traffic loading. Where possible, the chamber cover slab has been rotated to move the cover out of the wheel track zone.
Verified
SR-36
Maintainer MRSS
(Prior to opening) CPS to develop amended risk assessment for VRS to determine priority of response and any necessary control measures to manage risks after any impact damage reported on MM-ALR sections of scheme.
CPS will ensure this is carried out for VRS in their maintenance.
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
SR-37
Relevant to M25 LUS Section 2 only; not used for Section 5
M25 LUS Section 5 Safety Report (pre-opening)
Page 74
Ref Responsible Source Safety Requirement Verification Commentary Verification Status
SR-38
Designer Scheme Hazard
Log
White-webbs footbridge staircase to be amended to reduce risk to pedestrian users
New structural steel stair flights on concrete pad foundations were designed to move access provision away from the live carriageway.
Verified
Refer to drawings 5108945-ATK-0717-S518-DRG-X-011 to -016
SR-39
Designer PSCRG
TN6
It is recommended that a profiled lane line marking meeting the reflectivity requirements of SHW clause 1212.5 (commonly known as “rainline”) is used to assist with lane delineation on the concrete pavement. This line type may also assist in daytime on the predominantly east-west route. (J24-25)
Lane lines and raised rib edge lines on concrete pavements in areas without street lighting are to comply with Cl.1212.5. Specified in Appendix 12/3
Verified Specified in Appendix 12/3.
SR-40
Designer Scheme Hazard
Log
Speed camera sign to be provided on all types of signal gantry i.e. Portal and cantilever.
Prescribed enforcement signs are provided
Verified Signs are provided as per drawings; Section 5: 5108945-ATK-0712-S5-DRG-X-001 to 026
SR-41
Designer Scheme Hazard
Log
Rigid concrete barrier to be provided in the central reserve where possible.
Limited exceptions as noted. Verified Provided throughout scheme extents except at S527 River Lee UB using a Steel Step Barrier (with Departure for Standard) and emergency crossing locations using a steel gate.
SR-42
Designer PSCRG TN 15 and 24
Holmesdale and Bell Common Tunnels to retain a usable hard shoulder; the hard shoulder is also to extend upstream and downstream of a tunnel to permit a stricken HGV to park at an Emergency Telephone outside of tunnel
Provision agreed with TDSCG as per TN15 and TN24 such that both ends of both tunnels have hard shoulder and emergency phone
Verified
M25 LUS Section 5 Safety Report (pre-opening)
Page 75
Ref Responsible Source Safety Requirement Verification Commentary Verification Status
SR-43
Maintainer
MRSS and
PSCRG TN23
Maintainer to develop protocol for deployment of remotely operated temporary traffic management signs, including visual confirmation of correct deployment.
CPS O&M manual (currently being drafted) will include TM “launch” procedure and linkage to RCC procedure
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
SR-44
HA MRSS
Technology response times to be amended contractually to be suitable for MM-ALR so that technology outages are limited in number and duration by adherence to the contract requirements.
A contract change has been drafted and proposed by HA and this will be incorporated before road opens.
Revisit later in current stage A clear plan is in place. This requirement is a key issue before ALR can operate.
SR-45
Maintainer MRSS
To dissuade public comfort stops, the verge shall not be hardened where traffic could mount the verge after leaving the hard strip. A 1.0m verge strip nearest to paved edge of nearside shall be maintained such that the grass length shall be limited to an average not exceeding 350mm, so as to permit emergency public access to the verge.
The design does not contain any hardened pull-off areas, other than ERAs. CPS has confirmed that the existing regime of spraying and cutting to limit grass growth accords with this requirement.
Verified