M25 DBFO LUS SECTION 5
PCF 053 Safety Plan
JOB NUMBER: 5108945 DOCUMENT REF : 5108945-ATK-1204-S5-DOC-X-0024
B For PCF sign-off PW JPD SM SM 20/7/12
A For DNCS Review PW JPD SM SM 14/5/12
- For final PSCRG agreement PW JPD SM SM 30/4/12
Originated Checked Reviewed Authorised Date
Revision Purpose Description
Distribution Record
Copy No. Copy Holder Document Revision
A B C D E
01 Business Collaborator * *
02 Atkins File Copy * *
Note: This Document will be distributed via Business Collaborator. Details of distribution can be obtained from that system
Please note that Section 2.1 of the attached Product provide the introduction and background to the project. The text has been approved by the Highways Agency Project Leader for inclusion in all the PCF Products for this project. These sections have been included for information purposes only, and will be common across the whole suit of PCF Products for the project. You do not need to review and comment on these Sections as a PCF consultee.
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 1
Contents
Section Page
PCF Product Sign Off Sheet 2
1. Executive Summary 5
1.1 Overview 5
1.2 Details 5
2. Introduction 7
2.1 Scheme Background 7
2.2 Report Scope and Objective 8
2.3 Document Scope, History and Future Development 9
3. Safety Management System Selection 10
3.1 Process of Selecting a Safety Management System 10
3.2 Reviewing the Project Scope 10
3.3 Categorisation of Project Features 12
3.4 Implications for the Project Safety Management System 16
4. SAFETY LIFECYCLE ACTIVITIES 17
4.2 Safety Acceptance and Approvals Process 17
4.3 Defining the Safety Baseline 19
4.4 Setting the Safety Objectives for Road Users 19
4.5 Setting the Safety Objective for Road Workers 21
4.6 Risk Assessment Activities 22
4.7 Hazard Log Production 23
4.8 Achievement of Safety Objectives 24
4.9 Safety Report 25
5. Programme Management and Control 26
5.1 Management of Sub-Consultants 26
5.2 Main PCF Product Interfaces (Safety) 26
5.3 Configuration Control 26
6. Key Project Safety Roles 28
6.1 Individuals 28
6.2 Organisation 29
7. Conclusions & Recommendations 30
7.1 Conclusions 30
7.2 Recommendations 30
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 2
Glossary
AMI Advanced Motorway Indicator
AQMA Air Quality Management Area
AST Appraisal Summary Table
ATC Automatic Traffic Count
ATM Active Traffic Management
Auxiliary Lane An additional lane at the side of the mainline carriageway to provide increased merge or diverge opportunity or additional space for weaving traffic
BAS Biodiversity Alert Site
SBB Skanska Balfour Beatty Joint Venture
BT British Telecom
ALR All Lane Running
CDM Regulations Construction (Design and Management) Regulations
Central Reserve The area that separates the carriageways of a dual carriageway / motorway exclusive of any hard strips
CM Controlled Motorway
COBA Cost Benefit Analysis
CSR Client Scheme Requirements
CWS Country Wildlife Site
D3M Dual three lane motorway
D4M Dual four lane motorway
DHS Dynamic Use of the Hard Shoulder
DfT Department for Transport
DMRB Design Manual for Roads and Bridges
DROBB Double Rail Open Box Beam (safety barrier)
EAR Environmental Assessment Report
EcAR Economic Appraisal Report
EIA Environmental Impact Assessment
EMMR1TAM East Midlands M1 Traffic Assessment Model
EMMR Existing Motorway Minimum Requirements
ERA Emergency Refuge Area
ERT Emergency Roadside Telephone
ES Environmental Statement
ESS Entry Stop Signal
EU European Union
Ghost Island An area of the carriageway suitably marked to separate lanes of traffic travelling in the same direction on both merge and diverge layouts.
HA Highways Agency
Headroom The minimum distance between the surface of the highway cross-section and the deflected structure
HGV Heavy Goods Vehicle
HVCB Higher Vertical Concrete Barrier
IAN Interim Advice Note
INCA INcident Cost-benefit Assessment – economics tools for calculating delays and travel time variability costs
ITR Indirect Tax Revenue
JTDB Journey Time Database
LBS Lane Below Signal; refer to terminology at the end of this list
LMVR Local Model Validation Report
LGV Light Goods Vehicle
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 3
LWS Local Wildlife Sites
MAC Managing Agent Contractor
Mainline The carriageway carrying the main flow of traffic (generally traffic passing straight through a junction or interchange)
Maintained Headroom The minimum value of Headroom that must be preserved at all times
MHS Maintenance Hard Standing
MCDHW Manual of Contract Documents for Highway Work
MIDAS Motorway Incident and Automated Signals
MM Managed Motorway(s)
MM-ALR Managed Motorways All Lanes Running
MMDO Managed Motorways Delivery Office
MMSG Managed Motorways Steering Group
MSA Motorway Service Area
NDD HA Network Delivery and Development Directorate
NetServ HA Network Services Directorate
North facing slip roads The merge and diverge on the north side of a junction
Nose A paved area, approximately triangular in shape, between the connector road and the mainline at a merge or diverge
NRTS National Roads Telecommunications Services
NSCRG National Safety & Control Review Group
NTEM National Trip End Model
OBB Open Box Beam (safety barrier)
Overbridge A bridge that spans the road under consideration
Parallel Merge / Diverge
A layout where an auxiliary lane is provided alongside the mainline carriageway
PCF Project Control Framework
PIA Personal Injury Accident
PIE Public Information Exhibition
P4L Permanent Four Lanes
PL Project Leader
POP Police Observation Platforms
POPE Post Opening Project Evaluation
PSSR Preliminary Sources Study Report
PSCRG Project Safety & Control Review Group
PTJR Permanent Through Junction Running
PTZ Pan Tilt Zoom (CCTV)
QUADRO QUeues And Delays at ROadworks – economics programme to evaluate delay impacts during construction
Ramp Metering The control of vehicles joining the main carriageway from slip roads by the means of traffic lights or similar
RCC Regional Control Centre
RPI Retail Price Index
SAR Scheme Assessment Report
SBI Site of Biological Importance
SGAR Stage Gate Assessment Reviews
SoS Secretary of State
South facing slip roads The merge and diverge on the south side of the junction
SoW Start of Works
SPZ Source Protection Zone
SRO Senior Responsible Owner (Highways Agency)
SSD Stopping Site Distance
SSSI Site of Special Scientific Interest
Taper Merge / Diverge A layout where merging or diverging traffic joins or leaves the mainline carriageway through an area forming a funnel to or flare from the mainline carriageway
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 4
TCB Tensioned Corrugated Beam (safety barrier)
TIS Traffic Impact Study
TERN Trans European Road Network
TFR Traffic Forecasting Report
TJR Through Junction Running
TOS Traffic Officer Service
TPI Targeted Programme of Improvements
TRADS HA Traffic Information Data base, containing traffic flows for motorways and major trunk roads in England
TM Traffic Management
TMD HA Traffic Management Directorate
TUBA Transport Users Benefit Appraisal
Underbridge A bridge that carries the road under consideration
VCB Vertical Concrete Barrier
Verge Any nominally flat area between the edge of the paved width and either the start of an adjacent side or slope, in the absence of a side slope, the highway boundary or bridge parapet
VMS Variable Message Signs
VMSL Variable Mandatory Speed Limit
VOC Vehicle Operating Costs
VPH Vehicles per Hour
VRS Vehicle Restraint System
Weaving Section The length of the carriageway between a successive merge or lane gain and diverge or lane drop
WebTAG Website for Transport Analysis Guidance
Terminology Used in this PCF Product
The above terminology is in use throughout the suite of PCF Products/Reports that have been prepared for the scheme. Additionally, terminology used in this PCF Product is as follows: FWI
Fatal and Weighted Injury
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 5
1. Executive Summary
1.1 Overview
1.1.1 This document is the Safety Plan for the M25 LUS Managed Motorway (MM) Section 5. The
document:
Describes the Safety Management System (SMS) and corresponding safety activities that
will be undertaken in order to achieve safety objectives, including a description of the
activities that have been carried out to date.
Describes how the SMS has been selected
Defines how the project Safety Objectives will be achieved
Explains how the project Safety Baseline will be defined to allow future measurement of
performance against the Safety Baseline
Provides an overview of the current highway network safety performance to assist with
the selection of Safety Objectives
Describes the project organisation, how responsibility for safety activities has been
devolved and the associated programme management and control processes
1.1.2 The application of this document will produce evidence to demonstrate that the completed project
is capable of being operated in an acceptably safe manner.
1.2 Details
1.2.1 This document defines the project as a “Type B” project for the purposes of selecting a Safety
Management System. See section 3.3 for details.
1.2.2 Taking account of the existing accident history, the likely interventions included within the project
remit and also performance of other MM projects, the Safety Objectives have been set as follows:
The safety impact of the project will be measured by comparing the “before” and “after” casualty
numbers and severities using 3 year before data (the safety baseline) and 3 year after data. The
project will meet its Safety Objective for road users if it is demonstrated for a period of three years
after becoming fully operational that:
- the average number of Fatal and Weighted Injuries (FWI) casualties per year is no more than
the safety baseline, and
- the rate of FWIs per billion vehicle miles per annum is no more than the safety baseline, and
- no population (e.g. car drivers, pedestrians, HGV drivers and motorcyclists) is adversely
affected in terms of safety.
There will be no specific numerical safety target set for road workers. The risk will be managed
using the test of “So Far As Is Reasonably Practical.”
1.2.3 The Safety Baseline will be defined as a “before” period measured back from the Start of Works
date and will consist of averaged 3 years of data.
1.2.4 The “after” period will be 3 years after full project opening (all links open), with annual data
checks performed to monitor indications of success in meeting the project‟s Safety Objectives.
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 6
These annual interim data checks will include consideration of any links opened early as this may
influence the need for any remedial action elsewhere on the project.
1.2.5 During the development of this project, safety concerns will be addressed by the following
processes identified in this Safety Plan, including:
Hazard Identification
Risk Assessment
Development of a Hazard Log database
Verification and validation reports
Road Safety Audit
The use of a Project Safety Control and Review Group (PSCRG)
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 7
2. Introduction
2.1 Scheme Background
2.1.1 In 2002, the M25 London Orbit Multi-Modal Study (ORBIT MMS) recommended the provision of
additional capacity on the M25 Junctions 5 to 7 (Section 2) and on the M25 Junctions 23 to 27
(Section 5), generally in the form of one additional lane in each direction. Subsequently, the
Advanced Motorway Signalling and Traffic Management Feasibility Study (Department for
Transport (DfT), 2008) concluded that Hard Shoulder Running (HSR) could provide a large
proportion of the benefits of widening at significantly lower cost. .
2.1.2 A scheme was developed for an option called HSR and the environmental effects of this proposal
were reported in the Stage 2 Environmental Assessment Report (2010). This scheme was further
refined as part of the Stage 3 commission but the scheme was then put on hold in the autumn of
2010 pending the government‟s Comprehensive Spending Review (CSR). In the spring of 2011
the schemes to upgrade the M25 in Section 2 and Section 5 were included in the government‟s
plans for transport improvements for this parliamentary session and approval for work on the
project to recommence was given.
2.1.3 In December 2011 it was announced that new guidance (subsequently issued as IAN 161/12)
should be followed whereby Managed Motorway Controlled All Lanes Running (MM-ALR) would
replace Dynamic Hard Shoulder Running with reduced number of signs, gantries and Emergency
Refuge Areas (ERAs).
2.1.4 In March 2012 the Interim Advice Note IAN 161/12 was published entitled „Managed motorways
All lanes running‟, which set out the design parameters and the associated infrastructure and
technology requirements.
Project Description
2.1.5 Section 5 of the Project is within the counties of Hertfordshire, Essex and the Greater London
Authority and located in the northern segment of the M25 starting at Junction 23 (A1(M)) and
finishing at Junction 27 (M11). This Section will incorporate existing climbing lanes and recent
improvements to two tunnels (Holmesdale and Bell Common), retaining a traditional hard shoulder
with four running lanes through the tunnels and portals.
2.1.6 The scheme being carried forward as part of this Preliminary Design assessment will be MM-ALR.
An assessment of the minimum improvements needed to deliver safe operation of hard shoulder
running, including through junction running, will provide the core element of the proposed scheme.
2.1.7 MM-ALR makes use of the existing hardshoulder to provide the additional lane capacity. This is
achieved by using a system of gantry mounted electronic signs and signals. Refuge areas1 are
provided in accordance with IAN 161/12, approximately every 2.5km where topography and road
layout permits. Outside of that required for effective operation of MM-ALR, this Project only
includes the minimum improvements to the road infrastructure (e.g. surfacing, vehicle restraint
systems, environmental mitigation and drainage improvements), that would be required to achieve
safe and legal operation of MM-ALR. A general upgrade to full standards is therefore not
envisaged.
2.1.8 New low noise surfacing will be used to replace life expired surface course in the hard shoulder
with replacement of the main running lanes and hard shoulder with a low noise surface taking
1 Refuge areas include hardened Emergency Refuge Areas, Off-Slips with hardshoulders and intra junction
hard shoulders where these are retained
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 8
place only when the maintaining authority (DBFO) have programmed resurfacing works e.g.
where the surfacing is not fit for purpose.
2.1.9 The proposed drainage arrangements for the Project will be assessed as part of the detailed
design, in order to meet the requirements of IAN161/12, with respect to „flow path‟ of the water in
the road edge. This could comprise additional gullies & kerbs, V Channel or Slot Drains, as
identified in the Detailed Design. There may be no additional surfacing to the back of the hard
shoulder. The drainage of the ERAs will collect the water into manholes and discharge to the
existing networks where it would be attenuated using flow controls and therefore no alteration to
the drainage system would be required. However, some additional attenuation storage may be
required to accommodate additional flows from additional paved areas. All the outfalls to the
streams and rivers will remain as existing.
2.1.10 Overall, the proposed drainage system would comprise a combination of:
Kerbs and gullies, slot drains and open channels where appropriate.
The existing carrier drain system would be kept in place for the whole length of the
section, and would take the discharge from the collection drain arrangement.
2.1.11 In addition to the implementation of the MM-ALR requirements where appropriate and agreed with
the Highways Agency, an element of planned maintenance / lifecycle renewal works may be
incorporated into the overall Project scope, this will include the installation of vertical concrete
barriers and the hardening of the central reserve including any consequential amendments to the
drainage system required as part of these works.
The Overseeing Organisation
2.1.12 The Highways Agency is an Executive Agency of the DfT and is responsible for operating,
maintaining and improving the strategic road network in England on behalf of the Secretary of
State for Transport. The contact details for the Highways Agency are:
Highways Agency
Federated House
London Road
Dorking
Surrey
RH4 1SZ
The DBFO Co
2.1.13 The DBFO Co is responsible for the delivery of all M25 Projects and maintenance of the M25 for a
30 year period. Connect Plus was appointed in 2009 by the Secretary of State (SoS) for
Transport.The contact details for the Contractor are:
Connect Plus
Connect Plus House
St Albans Road
South Mimms
Potters Bar
Hertfordshire
EN6 3NP
2.2 Report Scope and Objective
2.2.1 This document is the Safety Plan for the M25 LUS MM Section 5. The document:
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 9
Describes the Safety Management System (SMS) and corresponding safety activities that will
be undertaken in order to achieve safety objectives, including a description of the activities
that have been carried out to date.
Describes how the SMS has been selected
Defines how the project Safety Objectives will be achieved
Explains how the project Safety Baseline will be defined to allow future measurement of
performance against the Safety Baseline
Provides an overview of the current highway network safety performance to assist with the
selection of Safety Objectives
Describes the project organisation, how responsibility for safety activities has been devolved
and the associated programme management and control processes
2.2.2 The application of this document will produce evidence to demonstrate that the completed project
is capable of being operated in an acceptably safe manner.
To simplify the reading and future review of this document portions of text that are most important
to the safety performance of the scheme and require action in the future PCF stages, are
highlighted in a shaded text box.
2.3 Document Scope, History and Future Development
2.3.1 Previously consultants developing dynamic hardshoulder options produced early drafts of a
Safety Plan. These documents were not signed off and are redundant due to the change of
highway intervention now planned
2.3.2 This current version reflects the new scheme design developed based on the contents of IAN
161/12.
2.3.3 This document is a forward looking planning document and is applicable to all of the project
lifecycle stages including operations and decommissioning.
2.3.4 Similar to a number of PCF Products, the need to consider updating this Product to reflect design
changes is an ongoing activity. However in general terms modest changes to the scheme design
will not require continuous updating of this document. A Project Safety Control Review Group
(PSCRG)2
will assist and advise on such matters, but in general terms it is assumed that only a
fundamental change to the scheme design or Operating Regimes would necessitate a re-issue of
this document.
2.3.5 This document considers both road user and road worker safety of the completed project, but its
scope does not include safety aspects during construction periods.
2.3.6 A glossary of terms has been included after the document sign off sheet.
2 This group is made up of representatives from the design team (including safety specialists) and key
stakeholders, notably HA operating directorates and Network Services.
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 10
3. Safety Management System Selection
3.1 Process of Selecting a Safety Management System
3.1.1 This section contains an assessment of the project safety management system based on the
guidance in Work Instruction WI001 contained in IAN 139/11 “Managed Motorways Project Safety
Risk Work Instructions.”
3.1.2 WI001 describes the process to be followed in order to identify the Safety Management System
(SMS) requirements that are applicable to a given project and addresses when such
requirements shall be established during the project lifecycle. The main steps involved in the
SMS selection process are as followed:
Review of the Project Scope
Categorisation of Project Features
Application of the SMS Selection Rules
3.1.3 The following sections in this chapter document the results of the SMS selection process for the
project.
3.2 Reviewing the Project Scope
3.2.1 Section 2 provides an overview of the project. It is necessary to describe in more detail here the
aspects that have the potential to have a bearing on the future risk assessments. This information
is contained in Table 3.1. This table contains information that it is specific to this scheme and
does not necessarily contain generic information that is applicable to the design of a typical MM
project or the whole MM programme.
3.2.2 Typically a MM-ALR project, incorporating permanent hard shoulder running, as set out in IAN
161 comprises or may comprise:
Advanced Direction Signs (in verge or overhead)
Gantry mounted Advanced Motorway Indicators (AMI) at gateway gantries at the scheme
start and downstream of all Entry Datum Points.
Variable message signs version 4 (MS4) and associated communications equipment
where lane signalling is provided
Pan tilt zoom CCTV coverage for the full carriageway area
MIDAS Loops
Verge cabling in a fully ducted network and cross-carriageway connections
Communications and power supply cabinets
Emergency Refuge Areas (ERAs)
Relocated carriageway markings and road studs
Limited amounts of resurfacing as required
Highways Agency‟s Digital Enforcement Cameras (HADECS)
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 11
Table 3-1 - Local issues relevant to safety
Local Issue Notes
Junction capacity
and improvements
The Project Brief excludes works at junctions with local roads. Merge and diverge layouts can be amended within current pavement
extents although some minor increases in paved extents may be possible.
Existing assets Assets that are fit for purpose will not be replaced solely for the purpose of meeting current standards. Only if the state of the asset
would likely affect the achievability of the Safety Objectives for the project or is beyond economic repair will it be considered for
replacement.
Works in central
reserve
Such works will be avoided as far as possible to minimise future risks to road workers, to reduce costs and to bring forward
construction completion. However it is likely that a slipformed concrete barrier will be required to allow re-allocation of highway space to
avoid extensive drainage works in both verges.
Designing for
maintenance
It is the intention to provide permanent infrastructure to facilitate future lane closures e.g. remote controlled shuttered signs in verges and central reserve for MM-ALR sections. As required by the PCF process a Maintenance and Repair Strategy will be produced; this will include details of how the projects assists the HA‟s Aiming for Zero initiative for road worker safety.
Through Junction
Running (TJR)
Through junction running is required at some junctions, subject to future analysis. There is limited experience of this operational regime
but the hazards associated with it are understood and adequately covered by the generic Hazard Log.
Key issues to develop through PSCRG are:
Consideration of vehicular breakdowns in intra-junction location
Safely accommodating merging traffic where there is limited space for “overrun” at the end of a merge taper, particularly where
there is limited verge space immediately downstream of a merge.
As required by IAN161, PSCRG must endorse non-TJR options (lane gain/lane drop)
Departures from
Standard
The project will make use of IAN 161/12 and also Existing Motorway Minimum Requirements Interim Advice Note 149/11 covering changes to TD9, TD22, TD27, TD46 and IAN87. This will reduce the need to apply for Departures from Standard but will require the
designer to complete a Design Strategy Record (DSR). The PSCRG will review key issues captured on DSRs.
Lighting In line with current HA policy a strong evidence-based case for additional investment for any new lighting or replacement/relocation of
existing lighting would be required.
Existing Accident
History
An analysis of 3 year data (2008-2010) shows that Section 5 has overall lower accident rates (measured by traffic volume) than the HA
national average for motorways. An initial assessment has indicated where further investigation is warranted.
Tunnels Although the scheme extents include two tunnels, no substantive work is envisaged in the tunnels which will retain hard shoulders.
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 12
3.3 Categorisation of Project Features
3.3.1 This section categorises the project features which helps to determine the most appropriate
Safety Management System (SMS). Table 3.2 below explains the implications of the six project
features on the selection of SMS and is used to inform Table 3.3 (the template for which comes
from IAN139/11).
3.3.2 The three possible categorisations for the overall project are set out below (and are given in IAN
139/11):
Type A: Basic safety management needs to be applied. This will be satisfied by the
application of existing standards and safety management processes, plus a brief Safety
Report will be needed.
Type B: A moderate level of safety management needs to be applied. This will include the
application of existing standards and safety management processes, where they exist.
However it will also require some additional risk assessment, plus a more detailed Safety
Report.
Type C: Rigorous safety management shall be applied. Where they exist, existing standards
and safety management processes will still be applied, but by definition, much of the project
will fall outside of existing experience. Therefore, records shall be kept of all activities
undertaken, all decisions and their justifications shall be recorded and extensive risk
assessment shall be carried out. A comprehensive Safety Report will be required.
3.3.3 It is noted that the PSCRG will in time review the designer‟s assessments of:
Any issues that are locally relevant or novel in comparison to a typical MM scheme
Design Strategy Records (DSRs)
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 13
Table 3-2 - Feature Categorisation Summary
Feature Implications for the Project
Stakeholder
interest
The project strategy is to inform affected stakeholders rather than formally consult as the
works are within the HA boundary, therefore stakeholder impact on the project is of a more
limited nature.
Stakeholders for safety issues include:
HA Network Delivery and Development Directorate– a significant amount of liaison is
required to ensure that the scheme can be safely constructed and maintained. HA
Network Services also has a significant role in agreeing designs that do not comply
with DMRB.
Regional Control Centre/Traffic Officer Service (TOS)/Traffic Management
Directorate: the role of the regional control centres and traffic officers could change
but in a similar fashion to other areas with Managed Motorways.
Maintenance contractors who will have more equipment to maintain and reduced
access to a hardshoulder to carry out maintenance
Emergency responders who will not have access to a hardshoulder for large
proportion of the scheme length – this is a “national issue” and the scheme will
respond accordingly
Tunnel operators at Bell Common and Holmesdale unaffected as hardshoulder
retained
Local authorities whose junctions lie on the scheme length, however as no
intervention works are planned at junctions, there are no direct safety implications
envisaged
Assessed as: Type B.
Operational
experience
There is a growing UK experience of Managed Motorways on M42 and M6 in the Midlands
plus assessment of pre-opening issues on a wider programme of other “Early Delivery”
schemes.
Early experience of longer link lengths, Motorway Services operation, unlit operation,
Through Junction Running and Emergency Refuge Areas at 70mph will emerge from a
combination of M1 J10-13 and M62 J25-30 in 2013 in time for learning points to be
incorporated in operations of M25 LUS.
Controlled Motorway (VMSL) operation is now familiar on other parts of HA network
including significant portions of M25.
Permanent use of the hardshoulder and also sections without a usable width hardshoulder
occurs on small portions of the HA network, but not always with the benefits of MIDAS and
VMSL that will be in place on M25 LUS e.g. the HA sample includes M4 elevated sections,
Sections 1,3, 4 of M25 widening and M60 Birch services to J18 westbound.
The design is not dissimilar to all-purpose trunk road layouts but with the benefits of better
junction layouts, wider junction spacing, some lighting, Emergency Refuge Areas, MIDAS,
CCTV and mandatory variable speed limits.
National operating procedures already exist for roads without usable hardshoulders.
Tunnel operation at Bell Common and Holmesdale not negatively affected as hardshoulder retained at tunnels.
Assessed as: Type B.
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 14
Feature Implications for the Project
Technology The technology proposed for the project has been used on a significant number of
Managed Motorway projects.
Early experience of unlit operation with low light CCTV will emerge from M1 J10-13 and
M62 J25-30 in time for learning points to be incorporated.
The potential use of MS4s to show speed roundels and other driver information messages
is subject to a HA off road trial to understand driver comprehension.
There is no effect on technology design of MS4s.
HADECS speed camera version 3.0 is expected to be used if Home Office approval for the
new camera type is achieved.
Assessed as: Type A.
Standards and
legislation
The standards (including departures agreed) used on other Managed Motorway projects
should be broadly applicable to this project. New HA guidance (IAN161 and IAN 149) will
reduce the number of formal departures required from other MM schemes.
No new legislation is required; with only non-onerous amendments required to amend the
“model” Statutory Instruments prepared for other MM projects.
Non-standard issues will be scrutinised as required by the PSCRG and if necessary the
National Safety Control Review Group (NSCRG).
Assessed as: Type B.
Impact on
Organisation
No responsibility transfer as part of the project.
Assessed as: Type A.
Project Scale This 25km scheme is to be installed at an important location on the motorway network with
extremely busy surrounding trunk road and local highway networks. This is a major scheme
that is part of a national tranche for a “lighter” MM design that also makes use of 24/7
running for LBS1. Although a number of similar HA schemes are being prepared in parallel
(e.g. M1 J28-31) there is a possibility that M25 may be the first to be operational.
Nevertheless the concept has already been analysed by HA centrally, including safety data
review and driver simulation studies.
Assessed as: Type B/C.
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 15
Table 3.3 - Feature Categorisation Summary
Features Type A Type B
Type C
1. Stakeholder Interest
– Stakeholders
– Influence Single or few
Limited
Several
Limited
or Single or few
Significant
Many
Limited
or
Key
Significant
or Several
Major/critical
2. Operational Experience
– Extent
– Where Widespread
UK
Limited
UK
or
Some
Overseas
only
None
Neither UK nor overseas
3. Technology
– Technology experience (consider degree of innovation and criticality of
application)
Widespread Used in different
application
or Applied in part
Not previously applied
– Safety risk implications Low Medium High
4. Standards and Legislation
– Design covered by existing
standards
– Departures from standards
– Changes to legislation
All
None
None
Mostly
Some
None
No
Many
None
or
New standard
Critical departures
Yes
– HA Guidance Existing/not applicable
Relevant new guidance available Major development in relevant guidance
5. Impact on Organisation
(consider structure, responsibility,
competency, whole life impact)
No changes
Minor changes/responsibility transfer
Significant change or responsibility transfer
6. Project Scale
– Infrastructure affected
– Potential for wider roll-out Single/small
location
None/minimal
Major location/implications
Moderate
Widespread/national implications
National potential
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 16
3.4 Implications for the Project Safety Management
System
3.4.1 Considering the results of the Project Feature Classification (see Tables 3.2 and 3.3), the M25
LUS project (Section 5) should be categorised as Type B. Of the categories two are ranked as
“A”, 3 as “B” and with one a mixture of “B” and C”, the latter only by virtue of the scheme being
self-evidently already part of a national programme that may expand if it is successful. Overall a
categorisation of Type B is appropriate.
3.4.2 The relevant advice and requirements in IAN 139/11 will be followed for a Type B project. IAN
139/11 is a comprehensive document and it is not necessary or appropriate to repeat its contents
in full here, but the main aspects are that the project will be risk assessed with the support of a
Hazard Log tool and all safety related activities will be assisted by the input and review of a
PSCRG.
3.4.3 Where the project wishes to introduce a novel design or novel operating regime the PSCRG
would need to determine if the endorsement of such proposals is within its remit or whether the
National Safety Control and Review Group should be consulted.
3.4.4 Further summary information of how the project will meet the requirements of IAN 139/11 is given
in Chapter 4.
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 17
4. SAFETY LIFECYCLE ACTIVITIES 4.1.1 This Chapter provides a description of the safety management activities that are to be
undertaken. IAN 139/11 Work Instruction 003 guides the activities for a Type B project..
4.2 Safety Acceptance and Approvals Process Figure 4-1 – Safety Management Process
4.2.1 The safety management process for Type B projects is shown in Figure 4.1. The Safety
acceptance and approvals (see Figure 4.2) will take place in four steps as follows:
(1) Verification. The Project Executor verifies that to the best of their knowledge, the safety work demonstrates that the Project‟s safety requirements are fulfilled.
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 18
(2) Consultation. The project undertakes consultation with identified consultees including
NetServ and operational directorates,
(3) Review and (4) Approval. Once consultation is complete, Major Projects reviews the work
done, including both that submitted by the project and the appropriate approvals provided by NetServ and operational directorates. Once Major Projects has confirmed that all necessary issues have been addressed, Approval for the project is granted.
Figure 4-2 – Safety Acceptance and Approvals Process3
3 Note: this graphic is extracted from IAN 139/11.
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 19
4.3 Defining the Safety Baseline
4.3.1 The Safety Baseline identifies the level of safety against which the Safety Objective will be
measured (i.e. in safety terms, what the completed project will be compared to). To objectively
set an appropriate Safety Objective it is necessary to have an understanding of the safety record
of the existing motorway.
4.3.2 The Safety Baseline will be defined as a “before” period measured back from the Start of Works
date and will consist of averaged 3 years of data. The separate post opening project evaluation
(POPE) process will source the accident data to define the Safety Baseline taking account of the
latest validated accident data at that time.
4.3.3 The HA has advised that for projects on networks that already contain MIDAS (for more than 50%
of their length) such projects should “factor up” the “before” casualty data by 10% to account for
the already realised benefits. M25 LUS Section 5 has limited MIDAS. For this reason the safety
baseline data will not include for a 10% factoring up of “before” casualty data.
4.3.4 An initial analysis of the latest available 3 year data period (2008-2010) of casualties/accidents
has shown that the M25 Section 5 has a lower than average accident rate. More detailed analysis
of any road often yields individual areas of concern and the PSCRG will be informed of any such
findings as they emerge.
4.4 Setting the Safety Objectives for Road Users
National Objectives
4.4.1 In 2011 the Government announced a national road safety framework4 that did not include
numerical objectives (targets). The Highways Agency has published its own safety framework5 for
road users and the general approach of investing in a range of interventions will continue. This
investment is envisaged to be developed to support a downward accident trend broadly similar to
the rate of accident reductions achieved between 2000 and 2010.
MM Programme Issues
4.4.2 Each MM project is a component part of the MM programme. Although the programme is
primarily aimed at reducing traffic congestion, it is anticipated that the projects will offer a
contribution to the reduction in the number of fatalities and seriously injured casualties on
motorways. The scale of the potential accident reduction is dependent on the intervention
planned.
4.4.3 A weighted index (known as Fatal and Weighted Injury (FWI) Index) that takes account of
accident severity will be used when setting the safety objective. FWI is defined as:
(Number of fatalities) + 0.1 x (number of serious casualties) + 0.01 x (number of slight casualties)
This definition reflects the approximate ratios between the monetarised costs of fatal, serious and slight casualties given in DfT‟s WebTAG (Unit 3.4.1).
4.4.4 The two key numerical indicators to be measured (before and after the scheme opens) now
suggested by the Highways Agency are:
Number of Fatal and Weighted Injury (FWI) casualties, and
Rate of FWI casualties per billion vehicle miles.
4 http://assets.dft.gov.uk/publications/strategic-framework-for-road-safety/strategicframework.pdf
5 http://www.highways.gov.uk/knowledge/documents/N110040_-
_Safety_Framework_for_the_Strategic_Road_Network_2011.pdf
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 20
If both numbers reduce 3 years after opening in comparison to the 3 years before construction
begins, then the scheme will have delivered safety benefits.
Importance of Safety Objective
4.4.5 The selection of the Safety Objective is important as it informs the safety measurement of
strategic scheme options via the Hazard Log. The Safety Objective forms a framework for
decisions around safety risk, especially for members of the PSCRG.
Data from other relevant projects
4.4.6 It is also important to understand what level of safety performance may be realistically achievable
from this type of intervention. Although not directly comparable for the design concept set out in
IAN 161/12, the currently available robust information for use of a hardshoulder is the 3 year post
opening data from the M42 ATM pilot6.
Comparing 3 Lane (3L) VMSL and 4 Lane (4L) VMSL, the
average number of PIAs has dropped from 3.17 to 2.25 per month. Overall these figures indicate
a reduction in the number of PIAs by 29% from no-VMSL to 3L VMSL and a 56% reduction from
no-VMSL to 4L VMSL. There is a 42% reduction in accidents during the peak period (when HSR
is operational) and a 62% reduction in accidents during the off-peak (when HSR is not
operational).
4.4.7 The severity index has also reduced, 4L VMSL has a severity index of 0.07, with the no-VMSL
and 3L VMSL modes of operation resulting in an index of 0.16. Over the five year period in which
no-VMSL mode data was collected, a monthly average of 0.12 fatal accidents was recorded, in
the 42months of data collection for 3L-VMSL and 4L-VMSL there have been no fatal accidents.
4.4.8 Controlled Motorway (VMSL)7 installed where MIDAS/High Occupancy Algorithm is already in
place delivers an estimated further 15% reduction in the safety risk over Triple Package. In
developing the dynamic MM programme generic safety work8 it was concluded that a realistic
goal was to deliver between 20% and 30% accident reductions for the type of interventions
planned on this project, but that figure includes the assumption that Triple Package would be
added at the same time.
4.4.9 A generic safety assessment9 for a typical MM2 scheme has recently been produced by the
Highways Agency. The expected safety benefit for a typical MM2 scheme will be in the order of
15% if no MIDAS is currently in place and 5% if MIDAS is already in place. The scheme Hazard
Log, based on the HA generic Hazard Log will allow the designers to compare the scheme
against these typically expected safety benefits.
6 M42 MM Monitoring and Evaluation, Three Year Safety Review, 292(308)MOTT, January 2011
7 TRL Ltd: Safety Benefits of the M25 Controlled Motorway: 1990 to 2006 Data.
8 Managed Motorways – Generic safety review HRG Report 718471/DOC/201 Issue B March 2009
9 MM-ALR Generic Safety Report (Final 23-03-12)
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 21
Conclusions
4.4.10 Bearing in mind the HA advice at programme level the Road User Safety Objective will
therefore be defined as follows:
The safety impact of the project will be measured by comparing the “before” and “after” casualty numbers and severities using 3 year before data (the safety baseline) and 3 year after data. The project will meet its Safety Objective for road users if it is demonstrated for a period of three years after becoming fully operational that:
- the average number of Fatal and Weighted Injuries (FWI) casualties per year is no more than the safety baseline, and
- the rate of FWIs per billion vehicle miles per annum is no more than the safety baseline, and
- no population (e.g. car drivers, pedestrians, HGV drivers and motorcyclists) is adversely affected in terms of safety.
Residual Actions
4.4.11 For the purposes of setting the Safety Baseline it is important that accident/casualty data is
updated to allow the numerical input to be made for the Safety Baseline. Whilst this Safety Plan
sets out the form of the Safety Baseline and explains how this relates to the Safety Objective, the
actual declared value of “FWI” will need to be based on casualty and traffic volumes related to
the Start of Works date – this will be done via the Post Opening Project Evaluation (POPE)
process.
4.5 Setting the Safety Objective for Road Workers
4.5.1 The Highways Agency recognises that people who work on the network are a particularly
vulnerable group. The HA have a policy initiative “Aiming for Zero” which sets out a number of
strategic actions to reduce the frequency of exposure of this vulnerable group to live traffic
situations and also to reduce risks where exposure is unavoidable. The policy recognises that
responsibilities are shared between the Highways Agency as network operator, design
organisations and employers of road workers.
4.5.2 Managing risks so that they are reduced So Far As Is Reasonably Practicable (SFAIRP) is a legal
requirement10
of the Health and Safety at Work Act and so must be used as the underpinning
Safety Objective for operatives and others who work on the network .
4.5.3 In common with other MM projects setting numerical objectives in addition to abiding by the
SFAIRP principle is not appropriate because road worker accidents are reported on an area and
company basis and not by individual motorway link lengths. In any case any absolute numbers or
accident rates, expressed by hours of work/exposure are extremely small, meaning that
numerical targets would not be of assistance in prioritising solutions. Additionally “Aiming for
Zero” in itself does not set a numerical target across the HA network. This position is re-affirmed
in “Managed Motorways – All Lanes Running Demonstration of Meeting Safety Objective Report”
dated 23 March 2012.
There will be no specific numerical safety target set for road workers. The risk will be managed
using the test of “So Far As Is Reasonably Practical.”
10 It is not possible to define a singular test to demonstrate reasonableness. However the scheme will
produce a CDM risk register and also a PCF Maintenance and Repair Strategy which must be agreed before
construction commences
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 22
4.6 Risk Assessment Activities
4.6.1 The activities will include the identification / review of the following issues:
The main safety hazards and risks for different parties affected by the project
The main assumptions underpinning the risk assessment
The main decisions made about how the project design controls safety risk and the basis for
these decisions
The main residual risks associated with the project and justification for the tolerability of
these risks
Key parameters/safety risk controls to be monitored into the future.
4.6.2 The outcome of risk assessment activities will be documented within the Safety Report. The
Safety Report will summarise all safety activities reported elsewhere, following the template set
out in the PCF framework.
4.6.3 The risk assessments will consider safety hazards and risks to road users,
construction/maintenance operatives, Traffic Officers and 3rd parties. Details of the hazards, risks
and associated controls identified as part of this hazard identification and risk assessment activity
will be recorded in a Hazard Log. The PSCRG will be informed of key risk assessment activities,
including key Departures from Standard (or equivalent when using IAN 149/11 methodology).
4.6.4 For each hazard the following shall be included in the Hazard Log:
A full description of the hazard
The frequency at which the hazard will occur (frequency)
How likely it is that the hazard will lead to a collision (likelihood)
The consequences of the collision(s) that arise(s) from the hazard, including a link to the
collision(s)
Who the hazard could affect (road users, road workers or 3rd parties)
A risk assessment (using frequency/ likelihood/ consequence) with appropriate supporting
arguments and data
The assumptions underlying the risk assessments
The mitigation measures for the hazard, including any project Safety Requirements.
4.6.5 A number of other activities are defined in the PCF matrix produced by the Highways Agency.
Subsequent paragraphs below highlight those that most directly relate to in-use safety of the
improved road.
CDM Designer’s Risk Assessment
4.6.6 At each stage of the design process, designers from all disciplines can make a significant
contribution by identifying and eliminating hazards, and reducing likely risks from hazards where
elimination is not possible. Designers‟ earliest decisions fundamentally affect the health and
safety of construction work and future maintenance activities therefore it is vital to address health
and safety from the very start.
4.6.7 The identification of hazards and mitigating measures is recorded on the Designer‟s Risk
Register. The designer identifies the hazard and the measures taken by the design to eliminate or
reduce the risks to road users, operatives, and Traffic Officers and 3rd parties. It also identifies at
which stage in the project the hazard is likely to be realised i.e. construction, operation,
maintenance or decommission. The assessment identifies whether there is a significant residual
risk and how this will be communicated to the Contractor.
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 23
4.6.8 In November 2008 Atkins adopted the 'design out risk' approach which makes use of Red,
Amber, Green lists to easily identify significant risks.
4.6.9 The CDM Risk Register is updated regularly throughout the project as the design develops.
Road Restraint Risk Assessment Process (RRRAP)
4.6.10 The RRRAP and the associated standard TD 19/06 „Requirements for Road Restraint Systems‟
describe the procedures to be followed in the design and provision of road restraint systems. The
standard introduces a risk based framework to support designers in making optimal design
choices at specific sites to minimise the risk to errant vehicles leaving the highway.
4.6.11 The RRRAP software has two main elements: risk analysis, and risk assessment. Risk analysis
enables the designer to enter information about a particular site (such as: location and hazard;
traffic speed; alignment), and the risk that each hazard may pose, to be presented in terms of the
probability of an accident/year/km and benefit/cost ratio. The software then enables various
control measures to be reviewed and their effect on the risk level and relative benefit/cost
assessed, e.g. redesign or relocation of the hazard; protection with a VRS; no protection.
4.6.12 The RRRAP will be undertaken within the detailed design stage of the project and will be subject
to the same design check and approval as other elements of the design. The output of the
RRRAP will be the selection of road restraint systems that reduce the risk to errant vehicles to an
acceptable level.
Road Safety Audit
4.6.13 Road Safety Audits will be undertaken at four stages during the project and ensure that the
project will deliver a certain level of safety performance. The Audit comprises four stages as set
out in DMRB HD19/03:
Stage 1: Completion of preliminary design
Stage 2: Completion of detailed design
Stage 3: Completion of construction
Stage 4: Monitoring
4.6.14 At each stage an Audit Report will be prepared by the Lead Auditor and if required the design
team will prepare any Exceptions Reports for HA approval.
4.6.15 A Stage 1 RSA is likely to be undertaken in Summer 2012 for the current design.
4.7 Hazard Log Production
4.7.1 A Hazard Log will be produced to record all safety hazards associated with the project and to
track all hazards that are identified in a project through to their successful resolution. Resolution
is regarded as demonstrating that necessary mitigation has been identified and subsequently
applied to the hazard.
4.7.2 A hazard log application for MM projects designed to IAN111/09 has been developed by
Highways Agency Network Services. A revised version is expected in Spring 2012 to support the
design concept of IAN 161/12. Together with project specific assessment, the generic Log will
revert to a Project Hazard Log. This Log will be regularly reviewed and updated throughout the
project life cycle. The HA‟s supporting documents explain the rationale for the „probability‟ and
„severity‟ scores that have been pre-populated in the application.
4.7.3 We have considered how the Hazard Log will be reported and communicated. The list of design
and operation requirements that underpin the hazard scores will be circulated across the project
team. For high scoring risks, documented reviews will be required to ensure that risks have been
reduced to an appropriate level. This process will be extended to include risks to on-road staff
and maintainers.
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 24
4.7.4 The PSCRG will be invited to take part in a Hazard Log workshop once initial population of the
database is complete. This process will examine the initial Hazard Log findings and test the
robustness of the results and assumptions. Similar workshops will be reconvened as the need
arises.
4.7.5 The PSCRG will be informed of any material changes to the Log.
4.7.6 We have considered the required staff that will input to the Hazard Log. The Safety Team will
feed information to the Hazard Log from the design team as it is produced. In general it is only
“exceptions” that will be informed to the Safety Team as in the absence of information to the
contrary, the assumptions of IAN 161/09 and IAN112/08 will be used to quantify risk.
4.7.7 Although non-PSCRG stakeholders will have important views on safety, it is not considered
appropriate to invite stakeholders to hazard scoring events. Instead information will be gathered
as liaison meetings take place and information of relevance will be passed through to the safety
team. Issues that are local to the scheme will be addressed in an appropriate manner e.g.
emergency routes and parking/enforcement facilities. In liaising with stakeholders Atkins staff will
be aware that in some circumstances the requests of stakeholders could lead to the creation of
the need to manage new risks e.g. for layouts or operating procedures not set down in published
guidance.
4.7.8 Information from the Hazard log will inform the project design and feed into the verification and
validation exercise reported via the Safety Report.
4.7.9 Following the Hazard Log workshop, a report will be produced that documents the population of
the Hazard Log and describes the assumptions and design requirements. Where these design
requirements differ from HA standards and guidance these will be specifically flagged.
4.7.10 It is suggested that the post–workshop report is recognised as “The Hazard Log Report”. This will
record how the Hazard Log has been populated and verified by stakeholder input. As the Hazard
Log will continue to be updated and the scoring changed to represent the scheme design any
report would only provide a snapshot of the progress and understanding at the point of
production. The proposed „Hazard Log Report‟ will be circulated to consultees and signed-off on
this basis. The Safety Report is to be used to provide an update of any substantive changes.
4.8 Achievement of Safety Objectives
4.8.1 There will be a „verification and validation‟ section within the Safety Report, summarising the
details of any verification or validation exercise undertaken and the associated findings.
4.8.2 Verification will be carried out by making sure that the project is delivered in accordance with the
Safety Plan and by demonstrating that all the hazards in the hazard log have been mitigated to
an appropriate level.
4.8.3 Atkins (Safety Team) will review the actual project activities against the Safety Plan. If this
identifies that any activities from the Safety Plan have not been completed, or have been
completed but not in accordance with the plan, then this situation will be reported back to the HA
Project Leader and addressed as soon as practicable. In addition, any implications of non-
compliance to date will be identified and addressed through revisions to the Safety Plan or project
design as required.
4.8.4 Validation will determine whether the safety benefits anticipated by the project are being achieved
in practice and whether assumptions made within the risk assessments are correct. This will be
undertaken after an appropriate period of operation and covered through POPE activities. The
findings will also be fed back into the Safety Objectives, Safety Plan, design and/or construction
process, as appropriate.
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 25
4.9 Safety Report
4.9.1 The Safety Report aims to summarise the evidence demonstrating that the project Safety
Objectives have been met by summarising all of the safety work that has been done in
association with the project and in doing so facilitating the safety approval of the project.
4.9.2 Typically, there will be three versions of the Safety Report, although the exact number will vary
according to the requirements of individual projects. The versions are:
Design – produced after detailed design prior to constructing the project. Confirms that the
design is capable of meeting the project Safety Objectives
As–built – updated after project is completed prior to handover into operation and
maintenance.
Final – produced after a significant period of operational experience (e.g. 1 year)11
to
demonstrate if the scheme has met its Safety Objectives
4.9.3 Further versions of the Safety Report may also be needed if:
An additional hazard is identified that needs mitigation
Other changes are made to the project to which the Safety Report relates e.g. a change in
operational regime
11 Assuming the POPE activity continues to be funded, a three year “after” POPE assessment will also be
produced
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 26
5. Programme Management and Control
5.1 Management of Sub-Consultants
5.1.1 There are no sub-consultants engaged on safety activities for this project.
5.2 Main PCF Product Interfaces (Safety)
5.2.1 Table 5.1 describes the main PCF safety products together with indicative dates for completion.
Table 5-1 - PCF safety related products.
PCF Product Description Indicative Dates
Safety Plan Defines how the project will achieve its
stated Safety Objectives [this document]
To be signed off in May 2012.
Hazard Log
To provide a record of all hazard related
information and track all hazards that are
identified in a project through to their
successful resolution, by demonstrating that
necessary mitigation has been identified
and subsequently applied to the hazard.
Report to be signed off before 30th
November 2012 with further review
continuing until Start of Works
Safety Report
To demonstrate that the scheme will be
acceptably safe at its introduction and that
this level of safety can be maintained
through the life of the scheme. Specifically
it provides documentary evidence and an
audit trial to all stakeholders that the
solution will/has meet/met its Safety
Objectives.
Version 1 to be signed off before
construction commences
5.3 Configuration Control
5.3.1 The project safety documentation will be the Safety Report and its supporting documents. The
first production of these documents will take place in parallel with the development of the design.
As the design develops document checkers and authorisers are required to consider the possible
impact changes may have on the risk assessment and the Hazard Log score. The Project
Manager will determine if a revised document or drawing warrants a change in the scope of
safety activity or invalidates previously made safety assumptions. If new documentation is
thought to have any material impact on the hazard scores the Project Manager should make the
revised version available and directly inform the project safety leader. For example:
Relocation of ERAs or removal of an ERA from the scheme.
Changes to the operation of the motorway.
Changes to the type of camera enforcement system used.
5.3.2 Access to the Hazard Log will be controlled. The consultant Project Manager will decide who to
give read access to and who to give write access to.
5.3.3 Mitigation and risk control measures introduced by the Risk Assessment will be recorded via the
Hazard Log software. „Tasks‟ will then be created in the hazard log and allocated to the
appropriate design team for consideration and incorporation into the design. The measures
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 27
introduced, as well as reasons for not introducing suggested mitigation, will be recorded in the
safety documentation.
5.3.4 Changes to the scheme during the design, construction and operation phases may all have an
impact on the risk assessment. There will be a requirement to keep the safety documents under
continual review. In particular, if any new hazards are identified after the project becomes
operational, or if the mode of operation changes in a way that affects any known hazards or risks,
then the risk assessment and Hazard Log will be updated to reflect these changes and any
corresponding changes to risk controls that will be introduced. Attention will also need to be paid
to any design activities undertaken by the contractor.
5.3.5 With respect to MM projects, the long-term responsibility for maintaining all such documents will
reside with HA Network Delivery and Development (NDD) who will be the owner of the project
once it commences operation.
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 28
6. Key Project Safety Roles
6.1 Individuals
6.1.1 The individual staff responsible for review and approval of this PCF Product are listed on the
cover sheet. Key staff responsible for developing safety related PCF Products are given in Table
6.1. The experience of key individuals is appropriate for this project and has been compared
against the Highways Agency‟s requirements set out in IAN139/11 and on the HA Suppliers
Portal12.
Table 6-1 - Key staff
Role Named Individual
Qualification and
competency
1 Safety Team Leader and chair of PSCRG
Peter Whitfield
Chartered Civil Engineer with 21 years experience of road safety engineering, standards and policy. Experience of role on the M1 J28-31, M62 J25-30 and M4M5 Managed Motorway schemes, plus past member of HA Subject Matters Expert Group on Operational Safety. Peter will also represent the scheme at the HA Hub at
regular meetings.
2 Road Safety Audit Team Leader
Neil Hutchings Meeting the requirements of HD19/03, independent of the Design/Safety Team and experience of auditing the
M25 widened sections.
4 On-road and RCC operations including Maintenance and
Repair Strategy
John Paul Doherty Chartered Civil Engineer and with 10 years experience of highway engineering, standards and policy. Qualified as a road safety auditor. Experience of Safety Plan, Hazard Log and Safety Report role on the M1 J28-31, M62 J25-30 and M4M5 Managed Motorway schemes, plus responsible for Operational PCF products on M62 J25-30. This role will be supported by representatives of the DBFO
Co and it‟s maintainer.
12 Managed Motorway Schemes - NSCRG and PSCRG Remit for Organisation and Governance. Annex 2. By HRG August 2010 Issue D.
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 29
6.2 Organisation
6.2.1 The Safety Team will be a component part of the design team. This arrangement recognises the
important role that the Hazard Log and risk assessment has as an iterative process to challenge
and inform the design and operational regimes.
6.2.2 The Road Safety Audit aspects will be performed in accordance with HD19/03 retaining
independence between the design team and audit team.
6.2.3 The PSCRG had its remit and composition formally agreed at the inaugural meeting on 20th
January 2012, with these aspects based on the advice in IAN139/11.
M25 DBFO LUS Section 5 PCF 053 Safety Plan
Page 30
7. Conclusions & Recommendations
7.1 Conclusions
7.1.1 This document defines the project as a “Type B” project for the purposes of selecting a Safety
Management System.
7.1.2 Taking account of the existing accident history, the likely interventions included within the project
remit and also performance of other MM projects, the Safety Objectives have been set as follows:
The safety impact of the project will be measured by comparing the “before” and “after” casualty
numbers and severities using 3 year before data (the safety baseline) and 3 year after data. The
project will meet its Safety Objective for road users if it is demonstrated for a period of three years
after becoming fully operational that:
- the average number of Fatal and Weighted Injuries (FWI) casualties per year is no more than
the safety baseline, and
- the rate of FWIs per billion vehicle miles per annum is no more than the safety baseline, and
- no population (e.g. car drivers, pedestrians, HGV drivers and motorcyclists) is adversely
affected in terms of safety.
There will be no specific numerical safety target set for road workers. The risk will be managed
using the test of “So Far As Is Reasonably Practical.”
7.1.3 The Safety Baseline will be defined as a “before” period measured back from the Start of Works
date and will consist of averaged 3 years of data.
7.1.4 The “after” period will be 3 years after full project opening (all links open), with annual data
checks performed to monitor indications of success in meeting the project‟s Safety Objectives.
These annual interim data checks will include consideration of any links opened early as this may
influence the need for any remedial action elsewhere on the project.
7.1.5 During the development of this project, safety concerns will be addressed by the following
processes identified in this Safety Plan, including:
Hazard Identification
Risk Assessment
Development of a Hazard Log database
Verification and validation reports
Road Safety Audit
The use of a Project Safety Control and Review Group (PSCRG)
7.2 Recommendations
7.2.1 This Safety Plan should be referred to when undertaking risk assessments, including completion
of the Hazard Log and the Safety Report.
7.2.2 As a key safety document, this product will be reviewed by the PSCRG before moving to sign-off
stage.