s1p2 curtiss fox clemson university

Upload: greyllom9791

Post on 07-Jul-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    1/21

    Introduction to the

    15 MVA Grid Simulator:Challenges in Fault Ride-Through Testing

    Energy Systems Innovation Center

    Workshop11/20/2013

    J. Curtiss Fox – [email protected]

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    2/21

    • new technologies that must play a significant role in power system stability.• the ability to replicate a complex dynamic system like the electrical grid for testing

     purposes.

    • extensive testing of hardware and software to meet safety and quality assurance

    requirements through ‘fully integrated’ system testing.

    •  parallel model verification and validation of physical hardware to ensure higher

    reliability and stability once deployed on the electrical grid.

    Development Demonstration Verification

    Advanced Testing Lowers the Risks and Costs of

    New Technology Introduction into the Market

    Deployment RisksTime to MarketTotal Costs

    Transforming the electrical grid into

    an energy efficient network requires:

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    3/21

    Grid Integration Evaluations• Power Set Points

    • Voltage and Frequency Variations

    • Controls Evaluation

    Steady State and Envelope

    Evaluations

    • Voltage Flicker

    • Harmonic Evaluations

    • Anti-Islanding (Software)Power Quality Evaluations

    •Frequency Response

    • Active Volt-VAR Control

    • Active Frequency RegulationAncillary Services

    • Low Voltage Ride-Through (LVRT)

    • Unsymmetrical Fault Ride-Through

    • High Voltage Ride-Through (HVRT)

    Grid FaultRide-Through Testing

    • Recreation of field events withcaptured waveform dataOpen Loop Testing

    • Simulated dynamic behavior andinteraction between grid and thedevice under test

    Hardware-In-the-Loop

    Testing

     I   n c  r  e a s  i   n

     g l   e v  e l   o f   d  i   f   f   i   c  u l   t   y 

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    4/21

    Energy Systems Innovation Center

    23.9 kV Utility Bus

    7.5MW Test Stand

    15MW Test Stand

    Graduate Education Center

    500 kW Solar Array

    23.9 kV 20 MVA Test Bus

    Experimental Bay #1Experimental Bay #2Experimental Bay #3

    15 MVA HIL

    Grid Simulator

    Up to three independent

    grid integration tests can run

    simultaneously in each of

    the three experimental bay’s

    4.16 kV 5 MVA Test Bus

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    5/21

    Energy Systems Innovation Center

    MV Single Line Diagram

     Variable 23.9 kV (50/60 Hz) 5

    Main Facility Electrical Bus (23.9 kV)

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    6/21

    Electrical Capabilities

    Overall Electrical Capabilities

    Main Test Bay

    Nominal Voltage 24 kV (50/60 Hz)

    Nominal Power 15 MVA (7.5 MVA)

    Frequency Range 45 to 65 Hz

    Sequence Capabilities 3 and 4 wire operation

    Overvoltage capabilities 133% Continuous Overvoltage

    Fault Simulation Yes (includes Reactive Divider)Hardware-In-the-Loop Yes

    Small Test Bay 1

    Nominal Voltage 4160 V (50/60 Hz)

    Nominal Power 3.75 MVA (3 MW @ 0.8 PF)

    Frequency Range 0 to 800 Hz

    Sequence Capabilities 3 and 4 wire operation

    Overvoltage capabilities 133% Continuous Overvoltage

    Fault Simulation Limited to Converter Only

    Hardware-In-the-Loop YesSmall Test Bay 2

    Nominal Voltage 4160 V (50/60 Hz)

    Nominal Power 3.75 MVA (3 MW @ 0.8 PF)

    Frequency Range 0 to 800 Hz

    Sequence Capabilities 3 and 4 wire operation

    Overvoltage capabilities 133% Continuous Overvoltage

    Fault Simulation Limited to Converter Only

    Hardware-In-the-Loop Yes

    Three Independent Test Bays

    6

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    7/21

    Series Connected H-Bridge (SCHB) Topology

    V A

    VB

    VC

    N

    TECO Westinghouse Motor

    Company: Power Amplifier

    Power Amplifier Specs Installed Power 20 MVA (15 MW @ 0.8 PF)

    Rated Power 15 MVA (12 MW @ 0.8 PF)

    Cabinet Power Split 4 x 3.75 MVA or 2 x 7.5 MVA

    Rated Voltage 0 - 4160 V

    Overvoltage 133 % Rated Output Voltage

    Multilevel Operation 7 - Levels (9 - Levels Overvoltage)

    Frequency Range 3 - 66 Hz

    Overload Capability 110% for 60 s (10 min duty cycle)

    7

    Full Power Amplif ier Diagram wi th 8 parallel SCHBs

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    8/21

    • Phase Shifted Carrier PWM –  High degree of harmonic cancelationdue to multilevel architecture

     –  Increased reference sampling fidelity

    • Sampling fidelity is further increasedby using asymmetrical sampling of

    each individual carrier

    8

    First noise mode is at 8 times

    the switching frequency

    Reference resolution also at12 kHz using asymmetrical

    sampling

    Total Harmonic Distortion:

    0.15% THD (0 – 50th)

    0.24% THD (0 – 100th)

    0.30% THD (0 – 150th)

    0.34% THD (0 – 200th)

    Synchronous Sampling up to 12 kHz

    TECO Westinghouse Motor

    Company: Power Amplifier

    Power Amplif ier Output Harmonic Spectrum (Fs = 2 kHz)

    ~260th 

    Harmonic

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    9/21

    Fault-Ride Through (FRT)

    Testing Methods and Requirements

    9

    •ABB Factory Testing (2009)

    •FGH Test Systems Field Testing (2006)

    Reactive Divider Network Method 

    •GE Power Conversion (Fr. Converteam)

    •Vestas V164 Test Bench (2013)

    •NAREC 15 MW Test Bench (Hybrid?) (2014?)

    •ABB Test Systems

    •NWTC at NREL (4Q-2013)

    Voltage Source Converter Method

    •Clemson University (1Q-2014)

    A Hybrid Method

    World Wide FRT Withstand Curves

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    10/21

    Reactive Divider Network Method• Faults created at the PCC to allow fortrue zero voltage faults

    • Real inductances provide a worst casescenario for line connected machinery

    • Operates at the fixed frequency ofutility connection

    • Requires a sufficient fault duty fromthe utility for voltage regulation

    Advantages and Challenges

    with Existing FRT Technologies

    Voltage Source Converter Method

    • Faults created behind a step-up transformer

    limit true zero voltage faults• Voltage regulation is straight forward given

    close electrical coupling with the DUT

    • Step-up transformer flux management limitssharp voltage transitions

    • Power electronics must handle the fault

    current delivered by the DUT 10

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    11/21

    Why a Hybrid Method?Increased flexibility and accuracy of FRT evaluations

     –  Faulted at the point of common coupling (PCC) –  True zero voltage faults (ZVRT)

     –  Magnetic flux decoupling between transformers

     –  Real inductive loading for transient time constant analysis

     –  Backwards compatible with existing methods

     –  Power electronic switching for point-in-wave studies

    11

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    12/21

    The Hybrid Method:

    Operation Cycle

    The Operation Cycle1. Open Series

    Bypass Switch

    2. Close Shunt

    Fault Switch3. Open Shunt

    Fault Switch

    4. Close Series

    Bypass Switch

    There are only three unique

    system states in the operation

    cycle.

    State 2

    State 1 State 3

    State 2

    12

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    13/21

    The Time-Variant

    Thevenin Equivalent Model

    The three unique states of the single phase systemmodel can be compressed into a time-variant

    Thevenin equivalent model.

    The time-variant Thevenin equivalent model is then

    only dependent upon the state of each switch.

    The time-variant Thevenin equivalent model is:

    where:

    and

    13

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    14/21

    Development of the Control

    Strategy

    The basis of control is built using the Internal ModelPrinciple to control at the Point of Common Coupling

    The voltage control signals are derived from twocomponents:

    1.) The feed-forward, open-circuit voltage reference, K2.) The feedback, closed-circuit voltage compensation, G

    K is only dependent on the state of SF

    G is only dependent on the state of SB

    14

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    15/21

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    16/21

    16

    Fixed Switch

    Positions

    Shunt Fixed

    (mH)

    Series Fixed

    (mH)

    Total

    Shunt (mH)

    Total

    Series (mH)

    1-1-1-0 0 25 0-25 25-50

    1-1-0-0 0 50 0-25 50-75

    1-0-0-0 0 75 0-25 75-100

    0-1-1-1 25 0 25-50 0-25

    0-1-1-0 25 25 25-50 25-50

    0-1-0-0 25 50 25-50 50-75

    0-0-1-1 50 0 50-75 0-25

    0-0-1-0 50 25 50-75 25-50

    0-0-0-1 75 0 75-100 0-25

    Table of Fixed Reactance Combinations

    Reactive Divider Network• Safety Considerations

     –  Access controlled room

     –  Automatic grounding system when not in service

    • Voltage Isolation –  35 kV insulation system

     –  2500 A (100 MVA) DUT fault duty

    • Performance and Flexibility –  Remote control of all elements allows for setup and

    operation without the need for room access –  Individual phase operation allows for thousands of three

    phase impedance combinations

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    17/21

    Table of Fixed Reactance Combinations

    17

    Fixed Switch

    Positions

    Shunt Fixed

    (mH)

    Series Fixed

    (mH)

    Total

    Shunt (mH)

    Total

    Series (mH)

    1-1-1-0 0 25 0-25 25-50

    1-1-0-0 0 50 0-25 50-75

    1-0-0-0 0 75 0-25 75-100

    0-1-1-1 25 0 25-50 0-25

    0-1-1-0 25 25 25-50 25-50

    0-1-0-0 25 50 25-50 50-75

    0-0-1-1 50 0 50-75 0-25

    0-0-1-0 50 25 50-75 25-50

    0-0-0-1 75 0 75-100 0-25

    Reactive Divider Network• Safety Considerations

     –  Access controlled room

     –  Automatic grounding system when not in service

    • Voltage Isolation –  35 kV insulation system

     –  2500 A (100 MVA) DUT fault duty

    • Performance and Flexibility –  Remote control of all elements allows for setup and

    operation without the need for room access –  Individual phase operation allows for thousands of three

    phase impedance combinations

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    18/21

    Controller Design Validation with

    Controller Hardware-In-the-Loop Experiments

    18

    National Instruments

    Interface Controller Real Time Power

    System Simulator

    RTDS®

    • Controller Hardware-In-the-Loop (CHIL) experiments are designed to evaluate the

    controllability and stability of performing fault ride-through evaluations with the HybridMethod

    • The RTDS system simulates the Grid Simulator physical system model and the DUT models

    • A scale version of the Interface Controller is used to validate the control algorithms

    Block Diagram of the CHIL experiments for the Hybrid Method 

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    19/21

    Example CHIL Results10 MVA Synchronous Generator:Three Phase Fault – 0% Remaining Voltage

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    20/21

    Magnetic Flux Decoupling During the FaultElectrical distance created by the series impedance decouples the magnetic

    flux between the two transformers.

    The magnetic flux of the power amplifier step-up transformer is passivelycontrolled by the hybrid method vector controller.

    20

    10 MVA Sync. Gen – 3PF – 0%

  • 8/19/2019 S1P2 Curtiss Fox Clemson University

    21/21

     

    Th k Y