revised lcce case

Upload: zara-ramis

Post on 02-Jun-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 Revised LCCE Case

    1/16

    REHABILITATION OF LOWER CHENAB CANAL EASTERN:

    CHALLENGES IN PROJECT PERFORMANCE MANAGEMENT

    On 9th September, 2004, Mr. Khalid Ahmed Khan, Head of the Project Management Unit

    Planning and Development Department, Government of Punjab, was preparing for the

    meeting of the Provincial Steering Committee for Project Management. This Committee

    comprised of five Secretaries1of different departments. This meeting was planned the next

    day, to review the progress of the Lower Chenab Canal Eastern (LCCE) project. At the time

    of its initiation, the project was expected to be completed by 31stJanuary, 2005. In a recent

    meeting (which was held on 5th August, 2004 to review the status of the LCCE project),

    Major (Retd.) Javed Majid, Secretary, Irrigation and Power (I&P) department, had indicated

    that the project would be completed on time. However, in Khalids opinion, the project

    would not be completed before the canal closure in October 2005.

    Khalid had made a presentation to the Chief Minister (CM) of Punjab, Ch. Pervaiz Ellahi, in

    June 2003 on the benefits of implementing the Earned Value for monitoring projects. The

    t ti h d b t d b th CM t k d i f Kh lid i i

  • 8/10/2019 Revised LCCE Case

    2/16

    t ti h d b t d b th CM t k d i f Kh lid i i

    [Type text] [Type text] 03-851-2013-1

    As Khalid took a final look on his numbers, he recollected what he had learned during his

    experiences with the public sector, on the pressures on the bearer of bad news. For example,

    these were mistakes and delays on part of the government in finalizing and awarding

    contracts; while there were contractors who based on their connections were too hot for

    any corrective action. In fact one of the contractors, who had been awarded the contract for

    two of the sectors on this project, was known to have close relationships with the President;

    who in turn was politically aligned with the CM himself. But, Khalid wondered, if theproject was heading for delays, and no decisions are taken, who will lose eventually. Could

    project monitoring data be used for a win-win situation for the different stakeholders.

    MANAGEMENT OF PUBLIC SECTOR PROJECTS IN PUNJAB

    Punjab was Pakistans largest province with a population of 72 million. The public sectordevelopment budget for Punjab was approximately $ 4 billion (US) in 20032. The major

    development sector areas included civil infrastructure, irrigation system, education and

    health. The Planning and Development Department, Government of Punjab, was the

    custodian of all the public sector projects in Punjab. Public spending in Punjab had increased

    by almost 30%, since 2002. This increase in public spending was challenging the present

    capacity of the government to effectively plan and execute over 1200 projects in the public

    sector portfolio. Keeping these challenges in mind, a review of existing project management

    practices was carried out by the government of Punjab in July 2003. This exercise was

  • 8/10/2019 Revised LCCE Case

    3/16

    [Type text] [Type text] 03-851-2013-1

    Provincial Steering Committee for Project Management (PSCPM)

    This was planned to be the principal policy-making forum to guide the

    implementation of new project management in the provincial government. This body

    was headed by the Chief Secretary, Government of the Punjab, who was the senior

    most bureaucrat of the province.

    Project Management Unit (PMU)

    This unit was planned to be the execution body. It was responsible for turning thepolicy guidelines issued by the PSCPM into tangible deliverables (templates,

    guidelines, best practices, trainings, etc.). The PMU was to be headed by a project

    management professional who had hands on experience of managing projects. This

    unit was incorporated into the Planning and Development Department.

    Capacity building efforts by individual departments were guided by the PSCPM and PMU.The physical implementation of the guidelines in terms of hiring of manpower, acquisition of

    project management tools, and the development of the Project Management Offices was the

    responsibility of the line departments. Internationally recognized PMI standards were used as

    the base standard for project management. This was in line with the PSCPM policy of the

    adoption of these standards.

    Mr. Khalid Ahmed Khan joined PMU in November 2003, as its first head. He had worked on

    projects in IT (National Database and Registration Authoritys Computerized National

  • 8/10/2019 Revised LCCE Case

    4/16

    [Type text] [Type text] 03-851-2013-1

    According to the Asian Development Bank (ADB)3review in 2002, cost overruns and project

    implementation delays were a common feature of project portfolio management in Pakistan.

    The data from the Monitoring and Evaluation (M&E) department, Government of the Punjab

    verified this trend. The data suggested that on average, each large scale project was

    completed at 155% of its planned cost (Exhibit 1). The data further suggested that against

    the planned completion time of 30 months, an average large scale project took about 38

    months to be completed, a delay of about 27% (Exhibit 2). Cost and schedule variance in

    public sector projects resulted in several failed projects. According to the M&E departmentsdata, only 19% of the completed projects were characterized as successful projects, whereas

    the rest of the 81% of the projects were declared as partially successful or failed projects

    (Exhibit 3). This was not just true for a certain class of projects, but could be seen across the

    board from major projects like Islamabad-Peshawar Motor Way (36 months behind

    schedule), Ghazi Brotha Hydro Project (36 months behind schedule and Rs. 10 billion 4over

    budget), Lahore International Airport (12 months behind schedule) all the way down to smallprojects like primary schools and health units.

    The existing Performance Management Framework was based on the financial progress of

    projects against the annual budget allocations. The Management Information Systems (MIS)

    were either non-existent or too weak to provide the quantum or quality of information

    required for efficient decision-making. A table taken from the Government of Punjabs

    Annual Development Program 2000 report, issued by the Planning and Development Board,

    exemplified the practical outcome of the Project Performance Management approach (see

  • 8/10/2019 Revised LCCE Case

    5/16

    [Type text] [Type text] 03-851-2013-1

    Table 1

    Calculation Method for Physical Progress of Projects

    Parameter Calculation

    Estimate Cost Col 7 + Col 8

    Expenditure up to June 1999 Col 9 + Col 10

    Physical progress up to June 1999 Expenditure up to June 1999/Estimated cost

    Provision for 1999- 2000 Col 11 + Col 12

    Physical progress expected during 1999-2000 Provision for 1999-2000/ Estimated Cost

    Source: Project Management Office, Planning & Development Department.

    THE LOWER CHENAB CANAL EASTERN (LCCE) PROJECT

    The Lower Chenab Canal Eastern (LCCE) project was one of the main projects that was

    under taken after the creation of the PMU, in November 2003. Thus, this project was

    considered critical in terms of measuring the performance of the PMUsteam and held a lot

    of importance for Khalid. Previously Khalid had worked as a consultant for some of the

    public sector projects (such as NADRA Electoral Roles project), but this was his first major

    assignment as a civil service officer and the head of PMU. He was enthusiastic about

    improving the performance management systems for large scale projects in the public sector.

    The rehabilitation of the LCCE project consisted of 12 sectors A through L Of these 10

  • 8/10/2019 Revised LCCE Case

    6/16

    [Type text] [Type text] 03-851-2013-1

    ample availability of water in the rivers, i.e. summer season and could not be managed

    without implementing a "Rotational Program"7. The LCCE complex was constructed in 1968

    for the conveyance, regulation and control of 14,500 cusec in Qadirabad - Balloki Link canal

    and 12,000 cusec in Lower Chenab Canal Upper, and for a diversion of 4,100 cusec through

    the Lower Chenab Canal Feeder. It was expected that due to the rehabilitation of the LCCE

    system, the water losses due to seepage and other wastages would reduce significantly. Water

    losses resulted in lesser water availability along with irregularity in supply of irrigated water,

    causing an estimated loss in yields of ten percent. Given the entire irrigated area of 3.03million acres under the LCCE complex, the total improvement in agricultural yield due to the

    project, had an estimated value of Rs 12 billion per year8.

    Types of Work

    The project objectives were expected to be achieved by implementing the following physical

    works:1. Raising and Strengthening of the Canals Banks

    2. Construction and Repair of Head Regulators (mechanism to control the height of

    water flow)

    3. Stone Lining of the Banks of the Canals in the Segments of Friable Soil

    4. Constructing Spurs (water channels) in Abnormally Widened Parts of the Canal

    5. Renovation of the Gates and Gearing System (mechanism to stop/regulate water

    flow)

    6. Streamlining Flow at Existing Bridges

  • 8/10/2019 Revised LCCE Case

    7/16

    [Type text] [Type text] 03-851-2013-1

    10. Rehabilitation / Replacement of Century Old Hydraulic Structures

    THE LCCE PROJECT PERFORMANCE MANAGEMENT

    The primary objective of the PMU in the LCCE project was to assist the Irrigation and Power

    (I&P) department in developing their in-house project management capacity. A weekly

    reporting format was introduced by the PMU to keep Mr Javed Majid, the Secretary I&P and

    Mr Salman Ghani, the Chairman Planning and Development (P&D) departments, updated onthe status of the project. In addition to the data collected from the LCCE project team, the

    PMU team had conducted eight onsite visits to various project locations to monitor the

    progress of the project.

    At the time of initiation, the LCCE project was expected to be completed by 31st January,

    2005 (1st

    base line). However, progress on the project was behind schedule from the start dueto delays in design and mobilization of the contractors. The LCCE Project had 12 sectors

    with an approximate value of Rs 1.73 billion. The original plan called for the project to be

    started on 10thJanuary 2004 and completed by 31stJanuary, 2005. Out of 12 sectors, 10 were

    initially awarded after a delay of about two months from the initial schedule. Two packages

    (A&E) were reported to have been awarded on 3rd July 2004 with a delay of almost six

    months. Current and projected delays had created the risk of claims9by the contractors. It

    was not known if the claims had already been filed or were likely to be filed. Additionally,

    there was no assessment of the possible cost escalation due to project delays.

  • 8/10/2019 Revised LCCE Case

    8/16

    [Type text] [Type text] 03-851-2013-1

    date for project completion was around October, 2005. Achieving that completion would

    require the LCCE team to achieve very high productivity during closure. In the closure

    period the supply of water to the canal and cultivated lands was stopped temporarily in order

    to complete a few works that could not be performed during the water supply period. The

    duration for this closure could not be prolonged for more than the specified period of time, as

    any further delay in the closure period would cause tremendous loss to the farmers of the

    region.

    After the project alert, issued on 31stJuly 2004 by PMU, a meeting of the Provincial Steering

    Committee for Project Management (PSCPM) was called by Mr. Kamran Rasool, the Chief

    Secretary, Punjab. This meeting was held on 5thAugust, 2004.

    AUGUST REVIEW MEETING

    During the meeting on 5th August, Chief Secretary Kamran had enquired about the design

    issues, financial progress and the overall scope of the project accomplished till that date.

    Kamran: Can you (Javed) please update us on the performance and the physical

    progress of the LCCE project. We would also like to know about the steps taken by

    the department to resolve the design issue, given the impact of this issue on the

    project. I fail to see why we started the project without completing the design; in fact,

    all I can say is that it is plainly, either bad planning or over ambitious planning.

  • 8/10/2019 Revised LCCE Case

    9/16

    [Type text] [Type text] 03-851-2013-1

    progress achieved so far in terms of budgeted cost, actual cost and percentage

    completion of work is shown on this sheet (Javed passes copies of Table 2 to the

    Committee).

    Table 2

    Data I&P August 2004

    Sectors Budgeted CostBC (Rs)

    Actual CostAC (Rs)

    % ageCompletion

    A 173,256,140 31,460,401 18%

    B 145,315,150 32,191,709 22%

    C 128,625,820 33,974,036 26%

    D 163,301,830 15,455,149 9%

    E 146,555,360 19,611,663 13%

    F 152,951,830 49,018,210 32%

    G 151,738,500 47,838,965 32%

    H 77,111,960 16,852,744 22%

    I 147,718,380 21,650,797 15%

    J 135,336,820 21,366,667 16%

    K 122,521,140 10,749,246 9%

    186 630 310 34 091 762 18%

  • 8/10/2019 Revised LCCE Case

    10/16

    [Type text] [Type text] 03-851-2013-1

    included). Although the I&P department had achieved a load of Rs 300 million /

    week on a previous project, considering the project specifications of the LCCE

    project, they could go upto a work load of Rs 75 million per week. I assure you that

    the project would be completed on time with this estimated work load.

    Khalid: The progress of the project till August 2004, shows that the project has been

    in suspension for the last seven months. The biggest mistake in my opinion, that led

    to many other problems was that Sector A was handed over to the contractors without

    finalizing the design issues. We do this just too often in the public sector to start

    getting the project related financial incentives. I also have concerns regarding the

    work load estimates. Keeping in view the previous performance and the potential

    problems (such as contractors claims and design issues)with the project, a target of

    above Rs. 50 million per week would be unrealistic. I would suggest that we start

    working on making a revision in the estimated cost and duration of the projectwithout further delay.

    Both Kamran and Javed, however, disagreed suggesting that it would be too early for such an

    exercise, and that instead of making revisions, they should try to complete the project within

    the estimated time and cost. They decided to meet again at the start of next month.

    EARNED VALUE

  • 8/10/2019 Revised LCCE Case

    11/16

    [Type text] [Type text] 03-851-2013-1

    was termed as EV. This system enabled project managers to calculate both the cost and

    schedule variance of an ongoing project10.

    Khalid and his team spent the next two weeks in digging up the planning documents of the

    project, to identify the tasks that should have been completed till date. They also identified

    the tasks that were actually completed. Khalid, along with some of his team members also

    visited the project site to assess the physical progress of the project. This extra work enabled

    them to calculate the planned value (the planned cost of work that should have been

    completed by then) and the EV (the planned cost of work that was actually completed by

    then) for each sector of the project. The actual cost data was already available to him (the

    data that Javed had shared in the meeting).

    Khalid looked at the data collected (see Table 3), and wondered how to present it to the

    senior Secretaries in PSCPM the next day, to convince them that he was right; and withoutstepping on too many toes, to motivate them to take appropriate corrective action.

  • 8/10/2019 Revised LCCE Case

    12/16

    [Type text] [Type text] 03-851-2013-1

    Table 3

    The Planned Value, Actual Spending and Earned Value, as on 4th

    August, 2004

    Sectors Total Budgeted

    CostPlanned Value Actual Cost Earned Value

    B.C (Rs.) PV (Rs.) A.C (Rs.) EV (Rs.)

    A 173,256,140 37,064,340 31,460,401 17,875,614

    B 145,315,150 33,380,370 32,191,709 25,253,576

    C 128,625,820 33,266,450 33,974,036 26,275,164

    D 163,301,830 17,394,690 15,455,149 13,614,146

    E 146,555,360 39,663,380 19,611,663 13,739,982

    F 152,951,830 50,384,680 49,018,210 32,669,884

    G 151,738,500 41,785,820 47,838,965 33,932,470

    H 77,111,960 18,478,150 16,852,744 12,116,794

    I 147,718,380 21,039,960 21,650,797 16,799,022

    J 135,336,820 20,699,440 21,366,667 15,437,050

    K 122,521,140 13,192,700 10,749,246 9,126,480

    L 186,630,310 49,666,210 34,091,762 24,811,940

    Total 1,731,063,240 376,016,190 334,261,346 241,652,123

  • 8/10/2019 Revised LCCE Case

    13/16

    [Type text] [Type text] 03-851-2013-1

    Exhibit 1

    REHABILITATION OF LOWER CHENAB CANAL EASTERN:

    CHALLENGES IN PROJECT PERFORMANCE MANAGEMENT

    Public Sector Project Performance 1998

    Sr # Name of Project Approved

    Cost

    Revised

    Cost

    %

    Increase

    1 Third KV Jamshoro- Multan Second 500 KV Multan-Lahore Gilgit

    Transmission Line

    9806 18,727 91%

    2 Left Bank Outfall Drain (LBOD) Stage-1 8594 31,040 261%

    3 Bulk Water Supply From Khanpur Dam To Islamabad/Rawalpindi 3606 6,819 89%

    4 Balochistan Primary Education Project 3010 4,460 48%

    5 3 x 30 MW EB.Clakhra 2651 5,730 116%

    6 Additional 415 MW Combined Cycle Power Unit At Guddu 2586 7324 183%

    7 On-Farm Water Management Project 2016 3327 65%

    8 Chashma Right Bank Irrigation Projects 1570 13870 783%

    9 Development Of Sector I-16 Islamabad 1188 2212 86%

    10 132 KV Transmission Lines And Grid Station In Makran Area

    Phase- 2

    781 879 13%

    11 Construction of Parliament Lodges at Islamabad 700 1157 65%

    12 Family Health Project NWFP 684 843 23%

    13 Tarbell Watershed And Management Project (Phase- 2) 574 753 31%

    14 Second SCARP Transition Project Punjab 531 696 31%

  • 8/10/2019 Revised LCCE Case

    14/16

  • 8/10/2019 Revised LCCE Case

    15/16

    [Type text] [Type text] 03-851-2013-1

    Exhibit 3

    REHABILITATION OF LOWER CHENAB CANAL EASTERN:

    CHALLENGES IN PROJECT PERFORMANCE MANAGEMENT

    The Evaluation of Public Sector Projects

  • 8/10/2019 Revised LCCE Case

    16/16

    [Type text] [Type text] 03-851-2013-1

    -16-

    Source: Punjab ADB 2000 Report

    Exhibit 4

    REHABILITATION OF LOWER CHENAB CANAL EASTERN:

    CHALLENGES IN PROJECT PERFORMANCE MANAGEMENT

    Public Sector Project Monitoring and Evaluation Framework

    Name of the schemeLocation of the

    SchemeStatus of

    the SchemeEstimated cost

    Expenditureup to 1998-

    1999

    Revisedallocationfor 1998-

    1999

    Provision for 1999-2000

    ForeignAid for1999-2000with

    source

    Physical ProgressPercent

    Column 3 4 5 6 7 8 9 10 11 12 13 14 15 16

    District TehsilForeign

    ExchangeComponent

    TotalCost

    Capital Revenue TotalUptoJune1999

    Expectedduring 1999-

    2000

    ON-GOING SCHEMES MEDICAL EDUCATION

    Replacement of damagedroof of patiala Block in the

    Department of Pathology,KEMC, Lahore

    Lahore Lahore Approved 5.98 5.60 0.98 0.98 94 110

    Establishment of AllamaIqbal Medical College,Lahore

    Lahore Lahore Approved993.9433.0580.9

    867.6350.7517.1

    0.950

    0.961 1 87 88

    Construction of Admin.Block in FJMC, Lahore

    Lahore Lahore Approved 1.50 0.59 1.01 1.01 40 107

    Construction of 70-students Hostel at 1- Road,FJMC

    Lahore Lahore Approved 6.795 7.35 0.28 0.28 108 111

    ROADS & BRIDGES ON GOING SCHEMES

    W/I of Attock Pindi Gheb

    road (Tarbela- Hattian-Talagang road) L= 76.00KM

    AttockFatehJang

    Approved 99.1 19.39 15.34 2 2 35 37

    W/I of Attock Fateh Jang toJang Bhater Brehma roadL= 18.50 KM

    AttockH.Abdal/

    FatehJang

    Approved 40.15 17.21 5.30 3.69 3.69 56 65

    Const. of high level bridgeover river Harro NearSanjwal

    Attock Attock Approved 19.93 15.63 4.18 0.11 0.11 99 100