revised lcce case
TRANSCRIPT
-
8/10/2019 Revised LCCE Case
1/16
REHABILITATION OF LOWER CHENAB CANAL EASTERN:
CHALLENGES IN PROJECT PERFORMANCE MANAGEMENT
On 9th September, 2004, Mr. Khalid Ahmed Khan, Head of the Project Management Unit
Planning and Development Department, Government of Punjab, was preparing for the
meeting of the Provincial Steering Committee for Project Management. This Committee
comprised of five Secretaries1of different departments. This meeting was planned the next
day, to review the progress of the Lower Chenab Canal Eastern (LCCE) project. At the time
of its initiation, the project was expected to be completed by 31stJanuary, 2005. In a recent
meeting (which was held on 5th August, 2004 to review the status of the LCCE project),
Major (Retd.) Javed Majid, Secretary, Irrigation and Power (I&P) department, had indicated
that the project would be completed on time. However, in Khalids opinion, the project
would not be completed before the canal closure in October 2005.
Khalid had made a presentation to the Chief Minister (CM) of Punjab, Ch. Pervaiz Ellahi, in
June 2003 on the benefits of implementing the Earned Value for monitoring projects. The
t ti h d b t d b th CM t k d i f Kh lid i i
-
8/10/2019 Revised LCCE Case
2/16
t ti h d b t d b th CM t k d i f Kh lid i i
[Type text] [Type text] 03-851-2013-1
As Khalid took a final look on his numbers, he recollected what he had learned during his
experiences with the public sector, on the pressures on the bearer of bad news. For example,
these were mistakes and delays on part of the government in finalizing and awarding
contracts; while there were contractors who based on their connections were too hot for
any corrective action. In fact one of the contractors, who had been awarded the contract for
two of the sectors on this project, was known to have close relationships with the President;
who in turn was politically aligned with the CM himself. But, Khalid wondered, if theproject was heading for delays, and no decisions are taken, who will lose eventually. Could
project monitoring data be used for a win-win situation for the different stakeholders.
MANAGEMENT OF PUBLIC SECTOR PROJECTS IN PUNJAB
Punjab was Pakistans largest province with a population of 72 million. The public sectordevelopment budget for Punjab was approximately $ 4 billion (US) in 20032. The major
development sector areas included civil infrastructure, irrigation system, education and
health. The Planning and Development Department, Government of Punjab, was the
custodian of all the public sector projects in Punjab. Public spending in Punjab had increased
by almost 30%, since 2002. This increase in public spending was challenging the present
capacity of the government to effectively plan and execute over 1200 projects in the public
sector portfolio. Keeping these challenges in mind, a review of existing project management
practices was carried out by the government of Punjab in July 2003. This exercise was
-
8/10/2019 Revised LCCE Case
3/16
[Type text] [Type text] 03-851-2013-1
Provincial Steering Committee for Project Management (PSCPM)
This was planned to be the principal policy-making forum to guide the
implementation of new project management in the provincial government. This body
was headed by the Chief Secretary, Government of the Punjab, who was the senior
most bureaucrat of the province.
Project Management Unit (PMU)
This unit was planned to be the execution body. It was responsible for turning thepolicy guidelines issued by the PSCPM into tangible deliverables (templates,
guidelines, best practices, trainings, etc.). The PMU was to be headed by a project
management professional who had hands on experience of managing projects. This
unit was incorporated into the Planning and Development Department.
Capacity building efforts by individual departments were guided by the PSCPM and PMU.The physical implementation of the guidelines in terms of hiring of manpower, acquisition of
project management tools, and the development of the Project Management Offices was the
responsibility of the line departments. Internationally recognized PMI standards were used as
the base standard for project management. This was in line with the PSCPM policy of the
adoption of these standards.
Mr. Khalid Ahmed Khan joined PMU in November 2003, as its first head. He had worked on
projects in IT (National Database and Registration Authoritys Computerized National
-
8/10/2019 Revised LCCE Case
4/16
[Type text] [Type text] 03-851-2013-1
According to the Asian Development Bank (ADB)3review in 2002, cost overruns and project
implementation delays were a common feature of project portfolio management in Pakistan.
The data from the Monitoring and Evaluation (M&E) department, Government of the Punjab
verified this trend. The data suggested that on average, each large scale project was
completed at 155% of its planned cost (Exhibit 1). The data further suggested that against
the planned completion time of 30 months, an average large scale project took about 38
months to be completed, a delay of about 27% (Exhibit 2). Cost and schedule variance in
public sector projects resulted in several failed projects. According to the M&E departmentsdata, only 19% of the completed projects were characterized as successful projects, whereas
the rest of the 81% of the projects were declared as partially successful or failed projects
(Exhibit 3). This was not just true for a certain class of projects, but could be seen across the
board from major projects like Islamabad-Peshawar Motor Way (36 months behind
schedule), Ghazi Brotha Hydro Project (36 months behind schedule and Rs. 10 billion 4over
budget), Lahore International Airport (12 months behind schedule) all the way down to smallprojects like primary schools and health units.
The existing Performance Management Framework was based on the financial progress of
projects against the annual budget allocations. The Management Information Systems (MIS)
were either non-existent or too weak to provide the quantum or quality of information
required for efficient decision-making. A table taken from the Government of Punjabs
Annual Development Program 2000 report, issued by the Planning and Development Board,
exemplified the practical outcome of the Project Performance Management approach (see
-
8/10/2019 Revised LCCE Case
5/16
[Type text] [Type text] 03-851-2013-1
Table 1
Calculation Method for Physical Progress of Projects
Parameter Calculation
Estimate Cost Col 7 + Col 8
Expenditure up to June 1999 Col 9 + Col 10
Physical progress up to June 1999 Expenditure up to June 1999/Estimated cost
Provision for 1999- 2000 Col 11 + Col 12
Physical progress expected during 1999-2000 Provision for 1999-2000/ Estimated Cost
Source: Project Management Office, Planning & Development Department.
THE LOWER CHENAB CANAL EASTERN (LCCE) PROJECT
The Lower Chenab Canal Eastern (LCCE) project was one of the main projects that was
under taken after the creation of the PMU, in November 2003. Thus, this project was
considered critical in terms of measuring the performance of the PMUsteam and held a lot
of importance for Khalid. Previously Khalid had worked as a consultant for some of the
public sector projects (such as NADRA Electoral Roles project), but this was his first major
assignment as a civil service officer and the head of PMU. He was enthusiastic about
improving the performance management systems for large scale projects in the public sector.
The rehabilitation of the LCCE project consisted of 12 sectors A through L Of these 10
-
8/10/2019 Revised LCCE Case
6/16
[Type text] [Type text] 03-851-2013-1
ample availability of water in the rivers, i.e. summer season and could not be managed
without implementing a "Rotational Program"7. The LCCE complex was constructed in 1968
for the conveyance, regulation and control of 14,500 cusec in Qadirabad - Balloki Link canal
and 12,000 cusec in Lower Chenab Canal Upper, and for a diversion of 4,100 cusec through
the Lower Chenab Canal Feeder. It was expected that due to the rehabilitation of the LCCE
system, the water losses due to seepage and other wastages would reduce significantly. Water
losses resulted in lesser water availability along with irregularity in supply of irrigated water,
causing an estimated loss in yields of ten percent. Given the entire irrigated area of 3.03million acres under the LCCE complex, the total improvement in agricultural yield due to the
project, had an estimated value of Rs 12 billion per year8.
Types of Work
The project objectives were expected to be achieved by implementing the following physical
works:1. Raising and Strengthening of the Canals Banks
2. Construction and Repair of Head Regulators (mechanism to control the height of
water flow)
3. Stone Lining of the Banks of the Canals in the Segments of Friable Soil
4. Constructing Spurs (water channels) in Abnormally Widened Parts of the Canal
5. Renovation of the Gates and Gearing System (mechanism to stop/regulate water
flow)
6. Streamlining Flow at Existing Bridges
-
8/10/2019 Revised LCCE Case
7/16
[Type text] [Type text] 03-851-2013-1
10. Rehabilitation / Replacement of Century Old Hydraulic Structures
THE LCCE PROJECT PERFORMANCE MANAGEMENT
The primary objective of the PMU in the LCCE project was to assist the Irrigation and Power
(I&P) department in developing their in-house project management capacity. A weekly
reporting format was introduced by the PMU to keep Mr Javed Majid, the Secretary I&P and
Mr Salman Ghani, the Chairman Planning and Development (P&D) departments, updated onthe status of the project. In addition to the data collected from the LCCE project team, the
PMU team had conducted eight onsite visits to various project locations to monitor the
progress of the project.
At the time of initiation, the LCCE project was expected to be completed by 31st January,
2005 (1st
base line). However, progress on the project was behind schedule from the start dueto delays in design and mobilization of the contractors. The LCCE Project had 12 sectors
with an approximate value of Rs 1.73 billion. The original plan called for the project to be
started on 10thJanuary 2004 and completed by 31stJanuary, 2005. Out of 12 sectors, 10 were
initially awarded after a delay of about two months from the initial schedule. Two packages
(A&E) were reported to have been awarded on 3rd July 2004 with a delay of almost six
months. Current and projected delays had created the risk of claims9by the contractors. It
was not known if the claims had already been filed or were likely to be filed. Additionally,
there was no assessment of the possible cost escalation due to project delays.
-
8/10/2019 Revised LCCE Case
8/16
[Type text] [Type text] 03-851-2013-1
date for project completion was around October, 2005. Achieving that completion would
require the LCCE team to achieve very high productivity during closure. In the closure
period the supply of water to the canal and cultivated lands was stopped temporarily in order
to complete a few works that could not be performed during the water supply period. The
duration for this closure could not be prolonged for more than the specified period of time, as
any further delay in the closure period would cause tremendous loss to the farmers of the
region.
After the project alert, issued on 31stJuly 2004 by PMU, a meeting of the Provincial Steering
Committee for Project Management (PSCPM) was called by Mr. Kamran Rasool, the Chief
Secretary, Punjab. This meeting was held on 5thAugust, 2004.
AUGUST REVIEW MEETING
During the meeting on 5th August, Chief Secretary Kamran had enquired about the design
issues, financial progress and the overall scope of the project accomplished till that date.
Kamran: Can you (Javed) please update us on the performance and the physical
progress of the LCCE project. We would also like to know about the steps taken by
the department to resolve the design issue, given the impact of this issue on the
project. I fail to see why we started the project without completing the design; in fact,
all I can say is that it is plainly, either bad planning or over ambitious planning.
-
8/10/2019 Revised LCCE Case
9/16
[Type text] [Type text] 03-851-2013-1
progress achieved so far in terms of budgeted cost, actual cost and percentage
completion of work is shown on this sheet (Javed passes copies of Table 2 to the
Committee).
Table 2
Data I&P August 2004
Sectors Budgeted CostBC (Rs)
Actual CostAC (Rs)
% ageCompletion
A 173,256,140 31,460,401 18%
B 145,315,150 32,191,709 22%
C 128,625,820 33,974,036 26%
D 163,301,830 15,455,149 9%
E 146,555,360 19,611,663 13%
F 152,951,830 49,018,210 32%
G 151,738,500 47,838,965 32%
H 77,111,960 16,852,744 22%
I 147,718,380 21,650,797 15%
J 135,336,820 21,366,667 16%
K 122,521,140 10,749,246 9%
186 630 310 34 091 762 18%
-
8/10/2019 Revised LCCE Case
10/16
[Type text] [Type text] 03-851-2013-1
included). Although the I&P department had achieved a load of Rs 300 million /
week on a previous project, considering the project specifications of the LCCE
project, they could go upto a work load of Rs 75 million per week. I assure you that
the project would be completed on time with this estimated work load.
Khalid: The progress of the project till August 2004, shows that the project has been
in suspension for the last seven months. The biggest mistake in my opinion, that led
to many other problems was that Sector A was handed over to the contractors without
finalizing the design issues. We do this just too often in the public sector to start
getting the project related financial incentives. I also have concerns regarding the
work load estimates. Keeping in view the previous performance and the potential
problems (such as contractors claims and design issues)with the project, a target of
above Rs. 50 million per week would be unrealistic. I would suggest that we start
working on making a revision in the estimated cost and duration of the projectwithout further delay.
Both Kamran and Javed, however, disagreed suggesting that it would be too early for such an
exercise, and that instead of making revisions, they should try to complete the project within
the estimated time and cost. They decided to meet again at the start of next month.
EARNED VALUE
-
8/10/2019 Revised LCCE Case
11/16
[Type text] [Type text] 03-851-2013-1
was termed as EV. This system enabled project managers to calculate both the cost and
schedule variance of an ongoing project10.
Khalid and his team spent the next two weeks in digging up the planning documents of the
project, to identify the tasks that should have been completed till date. They also identified
the tasks that were actually completed. Khalid, along with some of his team members also
visited the project site to assess the physical progress of the project. This extra work enabled
them to calculate the planned value (the planned cost of work that should have been
completed by then) and the EV (the planned cost of work that was actually completed by
then) for each sector of the project. The actual cost data was already available to him (the
data that Javed had shared in the meeting).
Khalid looked at the data collected (see Table 3), and wondered how to present it to the
senior Secretaries in PSCPM the next day, to convince them that he was right; and withoutstepping on too many toes, to motivate them to take appropriate corrective action.
-
8/10/2019 Revised LCCE Case
12/16
[Type text] [Type text] 03-851-2013-1
Table 3
The Planned Value, Actual Spending and Earned Value, as on 4th
August, 2004
Sectors Total Budgeted
CostPlanned Value Actual Cost Earned Value
B.C (Rs.) PV (Rs.) A.C (Rs.) EV (Rs.)
A 173,256,140 37,064,340 31,460,401 17,875,614
B 145,315,150 33,380,370 32,191,709 25,253,576
C 128,625,820 33,266,450 33,974,036 26,275,164
D 163,301,830 17,394,690 15,455,149 13,614,146
E 146,555,360 39,663,380 19,611,663 13,739,982
F 152,951,830 50,384,680 49,018,210 32,669,884
G 151,738,500 41,785,820 47,838,965 33,932,470
H 77,111,960 18,478,150 16,852,744 12,116,794
I 147,718,380 21,039,960 21,650,797 16,799,022
J 135,336,820 20,699,440 21,366,667 15,437,050
K 122,521,140 13,192,700 10,749,246 9,126,480
L 186,630,310 49,666,210 34,091,762 24,811,940
Total 1,731,063,240 376,016,190 334,261,346 241,652,123
-
8/10/2019 Revised LCCE Case
13/16
[Type text] [Type text] 03-851-2013-1
Exhibit 1
REHABILITATION OF LOWER CHENAB CANAL EASTERN:
CHALLENGES IN PROJECT PERFORMANCE MANAGEMENT
Public Sector Project Performance 1998
Sr # Name of Project Approved
Cost
Revised
Cost
%
Increase
1 Third KV Jamshoro- Multan Second 500 KV Multan-Lahore Gilgit
Transmission Line
9806 18,727 91%
2 Left Bank Outfall Drain (LBOD) Stage-1 8594 31,040 261%
3 Bulk Water Supply From Khanpur Dam To Islamabad/Rawalpindi 3606 6,819 89%
4 Balochistan Primary Education Project 3010 4,460 48%
5 3 x 30 MW EB.Clakhra 2651 5,730 116%
6 Additional 415 MW Combined Cycle Power Unit At Guddu 2586 7324 183%
7 On-Farm Water Management Project 2016 3327 65%
8 Chashma Right Bank Irrigation Projects 1570 13870 783%
9 Development Of Sector I-16 Islamabad 1188 2212 86%
10 132 KV Transmission Lines And Grid Station In Makran Area
Phase- 2
781 879 13%
11 Construction of Parliament Lodges at Islamabad 700 1157 65%
12 Family Health Project NWFP 684 843 23%
13 Tarbell Watershed And Management Project (Phase- 2) 574 753 31%
14 Second SCARP Transition Project Punjab 531 696 31%
-
8/10/2019 Revised LCCE Case
14/16
-
8/10/2019 Revised LCCE Case
15/16
[Type text] [Type text] 03-851-2013-1
Exhibit 3
REHABILITATION OF LOWER CHENAB CANAL EASTERN:
CHALLENGES IN PROJECT PERFORMANCE MANAGEMENT
The Evaluation of Public Sector Projects
-
8/10/2019 Revised LCCE Case
16/16
[Type text] [Type text] 03-851-2013-1
-16-
Source: Punjab ADB 2000 Report
Exhibit 4
REHABILITATION OF LOWER CHENAB CANAL EASTERN:
CHALLENGES IN PROJECT PERFORMANCE MANAGEMENT
Public Sector Project Monitoring and Evaluation Framework
Name of the schemeLocation of the
SchemeStatus of
the SchemeEstimated cost
Expenditureup to 1998-
1999
Revisedallocationfor 1998-
1999
Provision for 1999-2000
ForeignAid for1999-2000with
source
Physical ProgressPercent
Column 3 4 5 6 7 8 9 10 11 12 13 14 15 16
District TehsilForeign
ExchangeComponent
TotalCost
Capital Revenue TotalUptoJune1999
Expectedduring 1999-
2000
ON-GOING SCHEMES MEDICAL EDUCATION
Replacement of damagedroof of patiala Block in the
Department of Pathology,KEMC, Lahore
Lahore Lahore Approved 5.98 5.60 0.98 0.98 94 110
Establishment of AllamaIqbal Medical College,Lahore
Lahore Lahore Approved993.9433.0580.9
867.6350.7517.1
0.950
0.961 1 87 88
Construction of Admin.Block in FJMC, Lahore
Lahore Lahore Approved 1.50 0.59 1.01 1.01 40 107
Construction of 70-students Hostel at 1- Road,FJMC
Lahore Lahore Approved 6.795 7.35 0.28 0.28 108 111
ROADS & BRIDGES ON GOING SCHEMES
W/I of Attock Pindi Gheb
road (Tarbela- Hattian-Talagang road) L= 76.00KM
AttockFatehJang
Approved 99.1 19.39 15.34 2 2 35 37
W/I of Attock Fateh Jang toJang Bhater Brehma roadL= 18.50 KM
AttockH.Abdal/
FatehJang
Approved 40.15 17.21 5.30 3.69 3.69 56 65
Const. of high level bridgeover river Harro NearSanjwal
Attock Attock Approved 19.93 15.63 4.18 0.11 0.11 99 100