WELCOME
To
The Presentation
On
Project Control - Overview
25 March 2014
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
2/19
AGENDA
Introduction
Basic ConceptsProject
Control SystemProject Control Systems
Current Situation in SNC
Action Plan
Conclusion
2
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
3/19
Basic Concepts
Project
Control System
Project Control System
3
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
4/19
Basic Concepts - Project
Project is UniqueNon-repetitive
It is Temporary EndeavourHave Definite Start & Finish
Consume Resources:Manpower
Materials
Machineries & Plant
Money
5 Project Life Cycle StagesInitiation - Starting
Planning - Preparing
Execution - Doing
Monitoring & Control
Close Out
4
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
5/19
Basic ConceptsProject (contd.)
9 Project Management Knowledge AreasIntegration
Scope
TimeSchedule
Cost
Quality
Human Resources
Communication
RiskProcurement
5
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
6/19
6
Source: PMIs PMBoK4 e Project Management Process Groups (42)
Knowledge Area (42) Initiating (2) Planning (20) Executing (8) Monitoring & Controlling(10) Closing (2)
Project Integration
Management (6)
Develop
Project Charter
Develop Project Management Plan Direct & Manage
Project Execution
Monitor & Control Project Work
Perform Integrated Change Control
Close Project or
Phase
Project Scope
Management (5)
Collect Requirements
Define Scope
Create WBS
Verify Scope
Control Scope
Project Time
Management (6)
Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
Develop Schedule
Control Schedule
Project Cost
Management (3)
Estimate Costs
Determine Budget
Control Costs
Project QualityManagement (3)
Plan Quality Perform QualityAssurance
Perform Quality Control
Project Human
Resources
Management (4)
Develop Human Resource Plan Acquire Project Team
Develop Project Team
Manage Project Team
Project
Communication
Management (5)
Identify
Stakeholders
Plan Communications Distribute
Information
Manage Stakeholders
Expectations
Report Performance
Project Risk
Management (6)
Plan Risk Management
Identify RisksPerform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Responses
Monitor & Control risks
Project Procurement
Management (4)
Plan Procurements Conduct
Procurements
Administer Procurements Close
Procurements
Project Management Process Groups and Knowledge Areas Mapping
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
7/19
Project Management
Processes & Major
Activities
7Rehan HamidProject Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
8/19
Basic ConceptsControl System
8
InputsOperations -
Processing
Outputs &
Forecasts
Desired requirements Budget, Time, Profits etc
Comparison
Feedback, Changes & Corrective Actions
Deliverables
Objective of Integrated Control System is to integrate various
processes & stages with main focus on minimize negative
variances and improve positive performances
Measure
Variances
Integrated Control System
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
9/19
Basic ConceptsControl System(contd.)
Control is one of the managerial functions like planning, organizing, staffing and directing. It helps tocheck the errors and to take the corrective action so that deviation from standards are minimized andstated goals of the organization are achieved in desired manner.
Control in Management means:Setting performance standardslike Budget, Productivity Norms, etc.
Measurement of actual performance.
Comparing actual performance with standards.Analysing deviations.
Correcting deviations.
Characteristics of Control :Control is a continuous process
Control is a management process
Control is embedded in each level of organizational hierarchy
Control is forward lookingControl is closely linked with planning
Control is a tool for achieving organizational activities, Objectives & Performance
9
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
10/19
Basic Concepts
Project Control SystemsWhat is Project Control System?
System to control & Improve overall Project performance.
Project Control System keep balance of constraints ofScope
Time or Schedule.
Cost .Quality.
Risk
Resources
Any Change in one of the above constraint will result onchange on atleast one other constraints which affect theequilibrium. Hence, while evaluating any change overall
balanced view should be taken before approving thechange
There is Need for integrated controls
10
Time
Scope
QualityRisk
Project Constraints
CostIntegrated
Controls
Resources
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
11/19
Basic Concepts
Project Control Systems Contd.
Project Control Systems applies atvarious Stages of Project:
Initiation Stage (Tendering)
Mobilisation Stage (On awardManpower, Equipments /Issue ofLOIs/LPOs/WOs)
Execution Stage (periodic progressMPRs, Receipts & Payments, TechnicalSubmissions)
Close out stage (Handing OverFinalAccounts)
11
Time
Benef
its
Benefit diminishes over time
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
12/19
Basic Concepts
Project Control Systems Contd.Initiation Stage (Tendering)Review Tender Documents (details of BOQ, Tender documents, & Tender drawings, Addendums issued by Client during tendering process. Suggestedthat Tender dept shall provide copy of such documents immediately on receipt to PMC Dept at HO.
Review the basic working made by Estimation Dept for quantities of major work items planned to be executed in-hose - especially breaking down to variousbuildings / phases / floor wise / heights variances upto 3.5 mt , 3.5 to 4.5 m, 4,5 to 6 mtrs, 6.0 to 9.0 m, 9.0 to 12.0 mt & above 12.0 mtrs clear height floor areas, surfaceareas, perimeters, volumes to be calculated and co-related
Review Overall construction Strategy worked out for project executions alongwith workings of Estimation Dept for Overall resources requirementschedule for:
Materials
Consumables
ManpowerSubcontractors
Formwork requirements
Equipments
Staff
Mobilization
Local Authority Approvals requirements
Other site requirements
Review the Risk analysis performedespecially issues relating to Design Requirements, Consultant, Client, Local Authorities requirements, ProjectDuration requirements, Contract conditions for variations, escalations, various responsibilities, Site Conditions and similar other special requirements.
Have a site visit alongwith the Tender Department person during tendering.
Provide feedback to Tendering Dept for any special attentions / queries to be raised to be clarified from the Client / Consultant.
Participate in final negotiation process before accepting the Contract award
12
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
13/19
Basic Concepts
Project Control Systems Contd.Mobilisation Stage (On awardManpower, Equipments /Issue of LOIs/LPOs/WOs)Collect Final Contract Documents - details of BOQ, Tender documents, & Tender drawings,working of quantities, rate analysis & pricing basis considered by the estimation dept. while finalization of the Tenderproposal & control.
work out Construction BOQ based on construction drawings and make variance analysis.
work out the Overall resources requirement schedulefor:Materials
Manpower
Subcontractors
Equipments
Staff
Mobilization
Other site requirements
Work out the Master Budgetfor all resources item wise with Quantities, Rate & Amount.
Proceed for Resources Mobilisation-Manpower, Equipments, Issue of LOI/LPO/WOs in line withapproved master budgetMobilisation
13
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
14/19
Basic Concepts
Project Control Systems Contd.Execution Stage (periodic progressMPRs, Receipts & Payments, Technical Submissions)Data Collection from project sites:
Construction Drawings & Material take-off
Receipt of materials
Consumption of materials Reconciliations with requirements/usage
Manpower utilization
Equipment utilization
Subcontract works and Reconciliation with Billed to Client Work progress
Revise drawings/Site instruction issued by the consultant
Other relevant details
Review valuations, variation/claims analysis & Contractual Correspondences & Technical Submissions.
Monitor & update the resources schedules as the work progress based on actual quantities, rates etc. and
Prepare cost reports and variance report on monthly basis.
Arrange project review meetings
Report to the Management on monthly basis for review of the following: Project wise Profitability
Cash flow
Cost report
Variance analysis
Suggestions for Improvement
14
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
15/19
Basic Concepts
Project Control Systems Contd.Close out stage (Handing OverFinal Accounts)
Review Final Handing over documentations requirements
Prepare & Review Final Statement of Account for Client
Review Final Statement of Accounts for Sub-Contractors
Review As-Built Drawings
Review Arrangements & requirements for Maintenance Periods
Support for Final Handing Over sign off
15
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
16/19
Current Situation in SNC
Following Points Hinder Effective Project Control at Sites:
Lack of Awareness about Project Control requirements
Lack of formal process for Project Control
Lack of Clarity of RolesJob Description & Integration with others
Lack of Effective Decision Making
Lack of proper Planning for Resources & Utilization
Lack of Proper Communication & Flow of Information
Lack of Competent Manpower
Lack of Proper Documentation for Project Controls required for various Stages
However, the plus point - there is Management Commitment to
Implement and Support Project Control Systems
16
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
17/19
Action Plan
However, Following Actions will help us move in proper direction:
Formal Training for Project Management & Controls
Formalized process for Project Control
Clarity of RolesJob Description to be finalised & Issued to Staff
Decentralization of Common Services for Project
Higher Authority & Accountability system for Project leaders
Establishing System for Conflict resolutionCost, Time, quality & Risk
Transparency in Decision Making
Improving Communication & Flow of Information
Keeping Proper Documentation
Efforts for Continuous Improvement of Productivity & Resource Utilization
Performance Linked Incentive Scheme
17
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
18/19
Conclusion
We have a Long Way to go for Effective Project Control at Sites,
But, with Support from the Management and Project Teams,
we can improve our performance on a sustainable basis for All
Projects that we Execute & Deliver within Agreed Time & Budget.
18
Rehan Hamid
Project Engineering Lead-T&D
-
8/12/2019 rev01projectcostcontrolpresentationtafseer-12955241348714-phpapp02
19/19
THANK YOU
Q & A.