retaining walls: stability analysis and construction

79
USE OF TIRE BALES IN BUILDING EARTH RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION GUIDELINES by MOHAMMAD SADIQUE HOSSAIN, B.S.C.E. A THESIS IN CIVIL ENGINEERING Submitted to the Graduate Faculty of Texas Tech University in Partial Fulfillment of the Requirements for the Degree of MASTER OF SCIENCE IN CIVIL ENGINEERING Appnbved Accepted December, 2000

Upload: others

Post on 07-Dec-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

USE OF TIRE BALES IN BUILDING EARTH

RETAINING WALLS: STABILITY ANALYSIS

AND CONSTRUCTION GUIDELINES

by

MOHAMMAD SADIQUE HOSSAIN, B.S.C.E.

A THESIS

IN

CIVIL ENGINEERING

Submitted to the Graduate Faculty of Texas Tech University in

Partial Fulfillment of the Requirements for

the Degree of

MASTER OF SCIENCE

IN

CIVIL ENGINEERING

Appnbved

Accepted

December, 2000

Page 2: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

ACKNOWLEDGEMENTS

I would like to express my gratitude to Dr. Priyantha W. Jayawickrama for

chairing my thesis committee. I greatly appreciate his guidance and support throughout

the research project. I would also like to thank him for all the knowledge and skills that I

learned from his geotechnical engineering classes. I am also thankful to Dr. Mujahid H.

Akram for being on my thesis committee.

I would like to express my eternal gratitude to my parents for their affection,

guidance, support and sacrifice for me. I am also thankful to my wife whose love and

support made me accomplish my task.

11

Page 3: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

TABLE OF CONTENTS

ACKNOWLEDGEMENTS ii

ABSTRACT vi

LIST OF TABLES vii

LIST OF FIGURES viii

CHAPTER

I. INTRODUCTION 1

1.1 Overview 1

1.2 Significance of Used Tire Problem 1

1.3 Current Applications of Scrap Tires 2

1.3.1 Energy Recovery 2

1.3.2 Tire Pyrolysis 2

1.3.3 Retreading 3

1.3.4 Scrap Tires in Civil Engineering Applications 3

1.3.4.1 Wet Poured Layers 3

1.3.4.2 Rubber Modified Asphalt 3

1.3.4.3 Marine Reefs and Shoreline protection 4

1.3.4.4 Earth Retaining and Erosion Control Structures 4

1.4 Objective and Scope of the Research Project 4

II. LITERATURE REVIEW 6

2.1 Overview 6

2.2 Eco-Bloc in the construction of Retaining Walls 6

2.2.1 Eco-Bloc 6

2.2.2 Different Types of Eco-Bloc 8

2.2.2.1 Bulkhead/Erosion Control 8

2.2.2.2 Perimeter Wall 8

2.2.3 Design Criteria 8

2.2.3.1 Design of the Unit 10

2.2.4 Different Applications of Eco-Bloc 14

2.2.5 Features and Benefits of Using Eco-Bloc in Retaining Walls.. 14

iii

Page 4: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

2.2.6 Economics of Construction by Eco-Bloc 16

2.3 Encore Tire Bales in the Construction of Retaining Walls 16

2.3.1 Encore Baler 16

2.3.2 Summary of Test Results on Encore Tire Bale 19

2.3.3 Benefits ofUsing Baled Whole Tires 19

2.3.4 Costs of Baler 19

2.3.5 Different Applications of Baled Tires 20

2.3.5.1 ABrief Description of Carlsbad, NM Project 21

III. STABILITY ANALYSIS AND DESIGN OF RETAINING WALL 25

3.1 Overview 25

3.2 Eco-Bloc Tire Retaining Walls 25

3.2.1 Modes of Failure 25

3.2.1.1 External Stability 28

3.2.1.2 Internal Stability 30

3.2.2 Stability Analysis and Design of Retaining Wall 32

3.3 Encore Tire Bale Retaining Walls 42

3.3.1. Modes of Failure 42

3.3.2 Stability Analysis 42

IV. DESIGN CHARTS AND SPECIFICATIONS 43

4.1 Overview 43

4.2 Selection of Design parameters 43

4.2.1 Wall Configurations 43

4.2.2 Site and Loading Conditions 44

4.2.3 Earth Reinforcement Systems 44

4.2.4 Soil Parameters 45

4.3 Design Charts 45

4.3.1 Design Charts for Eco-Bloc Retaining Wall 46

4.3.2 Design Charts for Encore Bale Retaining Wall 46

4.4 Construction Costs for Tire Retaining Walls 61

4.5 Construcfion Techniques for tire retaining walls 63

IV

Page 5: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

V. CONCLUSIONS AND RECOMMENDATIONS 66

5.1 Conclusions 66

5.2 Recommendations 66

BIBLIOGRAPHY 68

Page 6: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

ABSTRACT

In the United States, about 270 million automobile and truck tires are sold each

year, with most of those tires eventually making a trip to the landfill, adding to the

existing inventory of about 400 million. This thesis presentation focuses on the possible

use of tire bales for building retaining walls. Tire bales are scrap tires compressed to a

reduced volume. Two types of tire bales that have been used for different purposes were

identified in the literature review. They are Eco-Bloc and En-Core Tire Bales. The tire

bales can be used for building mechanically stabilized earth and gravity retaining walls.

Detailed stability analysis and design was done for these two types of retaining walls.

The stability analyses investigated both external and internal failure modes. Repeated

analysis was done for different site and loading conditions, different wall configurations

and different soil parameters. After all the design combinations were put into design, the

designs were combined to form design charts. These charts may be used in projects that

match the site and loading descriptions provided in the charts. Some construction

guidelines are provided to assist in constructing the retaining walls. It is recommended

that full-scale test walls of both mechanically stabilized and gravity retaining wall be test-

built before their commercial use. The fiill-scale tests should enable the constructability

review, economic analysis and environmental impact analysis to be done.

VI

Page 7: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

LIST OF TABLES

2.1 Engineering Properties of Single Unit -Steel Reinforced 11

2.2 Engineering Properties of Single Unit -Plain Concrete 11

4.1 Mechanically Stabilized Earth Wall for Soil Fricfion Angle of 25^ to 30^ (Reinforcement Type: Metal Strip) 47

4.2 Mechanically Stabilized Earth Wall for Soil Friction Angle of 30^ to 35^ (Reinforcement Type: Metal Strip) 48

4.3 Mechanically Stabilized Earth Wall for Soil Fricfion Angle of 25^ to 30^ (Reinforcement Type: Geotextile/Geogrid) 52

4.4 Mechanically Stabilized Earth Wall for Soil Fricfion Angle of 30^ to 35^ (Reinforcement Type: Geotextile/Geogrid) 53

4.5 Gravity Retaining Wall for Soil Fricfion Angle of 25^0 35^ 57

Vll

Page 8: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

LIST OF FIGURES

2.1 Compressed Tires 7

2.2 Interlocking Design of Eco-Bloc™ 7

2.3 Oblique View of Eco-Bloc™ Unit 9

2.4 Eco-Bloc™ Reinforcing using Welded Wire Fabric 12

2.5 Eco-Bloc™ Reinforcing using No. 3 Rebar 12

2.6 Eco-Bloc ^ using Plain Concrete 13

2.7 Walls using Eco-Bloc Units 15

2.8 River Wing dam Built using Eco-Blocs 15

2.9 Tires being loaded in the Baler 17

2.10 Tires Being Compressed in the Baler 18

2.11 Finished Bale being Ejected from the Baler 18

2.12 Tire Bales as Subgrade Lightweight Fill for Road Construction 21

2.13 Erosion in Lake Carlsbad 22

2.14 Tire Bales on Top of Concrete Foundation 23

2.15 Encapsulation of Bales in Concrete 23

2.16 Block Retaining Wall on Top of Bales 24

3.1 Typical MSE Wall Construcfion using Eco-Bloc™ Units 26

3.2 Gravity Retaining Walls of Different Shape 27

3.3 External Stability Failure Mechanisms of MSE Retaining Walls 29

3.4 Internal Stability Failure Mechanisms of MSE Retaining Walls 31

3.5 Coulomb's Active Earth Pressure 35

3.6 Tensile Forces in the Reinforcements and Schematic Maximum 37 Tensile Force Lines: (b) inextensible reinforcements, (c) Extensible reinforcements

4.1 MSE Wall using metal strips with Horizontal Backfill and no Surcharge 49

4.2 MSE Wall using metal strips with Horizontal Backfill and 500 Ib/ft Surcharge 50

Vlll

Page 9: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

4.3 MSE Wall using metal strips with 15^ Sloping Backfill and no Surcharge 51

4.4 MSE Wall using geosynthetics with Horizontal Backfill and no Surcharge 54

4.5 MSE Wall using geosynthefics with Horizontal Backfill and 500 Ib/fl Surcharge 55

4.6 MSE Wall using geosynthefics with 15^ Sloping Backfill and no Surcharge 56

4.7 Gravity Walls of Different Shape with Horizontal Backfill and no Surcharge 58

and 500 Ib/ft Surcharge 59 4.8 Gravity Walls of Different Shape with Horizontal Backfill

rg'

4.9 Gravity Walls of Different Shape with 15^ Sloping Backfill and no Surcharge 60

IX

Page 10: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

CHAPTER I

INTRODUCTION

1.1 Overview

Throughout the United States, millions of waste tires are being generated each

year. These huge dumps of waste tires represent an enormous depot of lost energy,

materials, and money. Moreover, waste fires present a number of environmental, health

and safety hazards to the public and represent a serious public nuisance. While scrap fires

represent only 1.8% of the total solid waste stream in industrialized countries (1),

problems associated with scrap fires get a disproportionate amount of attention. The

hazards most commonly posed by the unsafe disposal or scrap tires are fire hazard and

mosquito breeding.

1.2 Significance of Used Tire Problem

According to the Rubber Manufacturers Associafion, in 1998, 270 million tires

were generated in the United States. Approximately 66 percent of these scrap tires were

productively used or recycled. Another 12 percent were placed in landfill or monofill.

Estimates also indicate that the current stockpile of scrap tires in the US is around 400

million. Scrap tires create unique problems in landfill disposal; not only because of their

large numbers but also because of the nature and properties of their chief component,

rubber. Rubber tires are difficult to compact in landfills because they tend to rise and

even pop through the groundcover as other waste materials compact around them. Their

buoyancy causes them to rise to the surface after rainfall leaving behind empty spaces

that damages the landfill's stable, carefully layered composition. In addition, the hollow

shape of the tires fills with decomposition gases creating a serious fire hazard. Experience

has shown that large tire fires can bum for weeks causing the rubber to decompose into

oil, which may pollute ground and surface water, as well as gas and carbon black.

Moreover, the tire rubber is a dense, durable and elastic material that does not undergo

natural decomposition in landfill environment easily. Rainwater accumulates in tire piles

creafing an ideal environment for mosquitoes, which are known to transmit disease to

1

Page 11: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

humans. Because of all these reasons, many landfills do not accept large quantities of

discarded tires, while others charge a high tipping fee for their disposal. Consequently,

scrap tires are frequently placed in dedicated stockpiles or in illegal tire dumps.

1.3 Current Applications of Scrap Tires

Presently, approximately 66 percent of scrap tires are being used in retreading,

recycling, and energy recovery applications or in Civil Engineering applications (1).

1.3.1 Energy Recoverv

Tires can be burnt for energy recovery. Tires are burned for fuel in power plants,

tire-manufacturing plants, cement kilns, pulp and paper plants and small steam generators

utilizing a combustion technology similar to that for coal. In the U.S., approximately 114

million scrap tires were used as fuel supplement in power plants, cement kilns, industrial

boilers, etc., in 1998 (1). Tire Derived Fuel (TDF) is currently the most widely used

disposal method for scrap tires. TDF is defined as a scrap tire that is shredded and

processed into a rubber chip with a range in size and metal content. Size normally varies

in a range of 2 inches to 4 inches and metal content ranges from wire free, to relatively

wire free, to only bead wire removed, to no wire removed (1). Depending on the amount

of wire removed, the TDF has an energy content ranging from 14000 Btu/lb. to 15000

Btu/lb (2). Combustion efficiency for TDF is generally understood to be in the 80% range

(3). Hence, the re-use of scrap tires as tire derived fuel is generally considered to be one

of the more promising approaches to solve the scrap tire disposal problem.

1.3.2 Tire Pvrolvsis

Pyrolysis is the thermal decomposition of an organic material under the exclusion

of ambient oxygen. The typical products of scrap tire pyrolysis are: hydrocarbon gases

and oils, low-grade carbon black and steel. Pyrolysis plays only a marginal role in the

scrap tire industry because the oil and gas produced in this method needs to compete with

the low prices of conventional fuel.

Page 12: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

1.3.3 Retreading

One form of tire recycling that has been in use for many years consists of tire

retreading. But available data indicates that retreading of old tires for reuse has steadily

declined in the US, particularly in the recent years. The decline in retreaded tire market

has been partly attributed to the complex technologies used in the production of modem,

high quality tires. As a result, the retreading of tires with new designs has become a less

profitable business.

1.3.4 Scrap Tires in Civil Engineering Applications

Scrap tires are used in different ways in Civil Engineering Applications. Civil

Engineering projects utilizing scrap tires typically involve replacing conventional

construction material (e.g., road fill, gravel, sand or dirt) with whole scrap tires or tire

chips. In their whole form, tires are used in crash barriers, reef, and shore protection and

in retaining walls. Whole tires are now being used to prevent soil erosion. Tires are also

used as fill. Cmmb mbber is being used in highway applications including the

improvement of asphalt.

1.3.4.1 Wet Poured Layers

Playgrounds and athletic surfaces are frequently covered with a layer of mbber

granules in order to help prevent injuries. Many high schools throughout the U.S. use

mnning tracks that consist of recycled material. Most commonly, a moisture-curing

urethane is mixed with ground tire mbber (GTR) and applied in a similar way as other

poured pavements. These layers are usually softer than molded mats and the top layer can

be colored.

1.3.4.2 Rubber Modified Asphalt (RMA)

Adding recycled tire mbber to the hot asphalt mix is a very economical way of

meeting, or exceeding, the new SHRP specifications that require certain physical

properties that rarely can be met by conventional (unmodified) asphalt cements. RMA

can significantly widen the temperature span of asphalt pavements when compared to

Page 13: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

conventional asphalt binders. Increased resistances to mtting, reflective and thermal

cracking are the main benefits of RMA. Other advantages include better de-icing

properties, reduced traffic noise and, most importantly, a significantly increased service

life and thus a lower life cycle cost.

1.3.4.3 Marine Reefs and Shoreline Protection

Artificial reefs are used in the marine environment to duplicate conditions that

cause concentrations of fish and invertebrate on natural reefs. Scrap tires have been used

for shoreline protection since the 1970's. Breakwaters are offshore barriers that protect a

harbor or shore fi-om the strong impact of waves. Scrap tires for breakwaters and floats

are filled with material, usually foam, which displaces of water.

1.3.4.4 Earth Retaining and Erosion Control Stmctures

Whole scrap tires have been used in a variety of earth retaining and erosion

control stmctures across the world. Some of these stmctures have used whole tires filled

with soil or gravel as the basic building unit. Some others have used baled tires that are

produced by compressing a large number of tires and binding them together. One

example of such earth retaining stmctures includes retaining walls for erosion control

using Eco-Bloc units made by Ecological Building Systems. Another instance of tire bale

use is erosion control and dam constmction using En-Core baler, a tire baler produced by

ENCORE SYSTEMS, inc. Some examples of earth retaining stmctures using whole

scrap tires include: (a) ECOFLEX tire retaining wall system developed by SULCAL

Constmction Pvt. Ltd., in Australia; (b) USD A tire-faced reinforced earth retaining wall;

(c) ECO WALL highway noise barrier in Vienna, Austria; and (d) Santa Barbara Public

Works Department's earth retaining stmcture.

1.4 Objectives and Scope of the Research Project

Although earth retaining stmctures have been built using discarded tires by a

number of agencies as isolated constmction projects, general design guidelines applicable

for a wide range of wall heights, wall configurations and backfill material types are not

Page 14: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

available at the present time. The primary objective of this research project is to develop

such guidelines so that used tires can be utilized in routine retaining wall constmction

projects by the transportation industry. Such retaining walls should be capable of

withstanding lateral earth pressures from the soil backfill as well as any surcharge loads

that is typically found in an urban setting. It is equally important that the wall, once

completed, has an aesthetically pleasing appearance.

The general research approach used to accomplish the research objectives stated

above consisted of the following steps:

• Collect information from previous/on-going tire retaining wall projects. This

information will include tire retaining wall configurations, designs, equipment

requirements and any specific problems encountered.

• Review and analyze the information collected and hence come up with a number

of tentative designs that will meet TxDOT (sponsor agency of the research

project) needs.

• Perform necessary stability analysis to ensure that the selected tire wall designs

have adequate factor of safety against potential modes of failure. Such analysis

examined intemal stability criteria such as mpture and pullout of backfill

reinforcement and then external stability conditions such as overtuming, sliding

and bearing capacity failure.

• Perform repetitive design calculations for walls with varying configurations,

heights and backfill material properties and loading conditions and hence develop

design charts. The design charts should enable someone to readily select wall

configurafion without going through detailed experiments and calculations.

Page 15: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

CHAPTER n

LITERATURE REVIEW

2.1 Overview

This project involved a survey of different Civil Engineering applications of

waste tires throughout the world. The survey included a comprehensive library search, a

telephone survey and an Intemet search. The primary purpose of the search was to

identify some suitable techniques to build retaining walls utilizing tire bales. Retaining

walls and River Wing dams have been built utilizing compressed tire bales named Eco-

Bloc. Retaining walls for erosion control have been built using tire bales produced by

Encore Systems, Inc. The findings about the Eco-Bloc and Encore Baler are presented in

this chapter. The other aspect of the project was the use of whole tires for building

retaining walls. That issue has been addressed in a separate task.

2.2 Eco-Bloc'^^ in the Constmction of Retaining Walls

2.2.1 Eco-Bloc™

Eco-Bloc is a trademark of Ecological Building Systems (EBS), which is

headquartered in Cypress, Texas. EBS has developed a patented process for using a bale

of compressed scrap tires as a core for a stmctural concrete building product called the

Eco-Bloc."^^ It has been designed and manufactured for Civil Engineering applications

like erosion control, retaining walls, border walls, prison walls, river wing dams, etc.

Eco-Bloc' ' is an integration of baled compressed tires with concrete and reinforcement

steel to form a sealed concrete unit. The compressed tires are encapsulated with the

concrete to form the central core of the blocks. Figure 2.1 shows the core of the block

made by the compression of tires. It is designed with an external interlocking system to

enhance stmctural wall strength and to simplify and reduce the installation time. The

external interlocking design of Eco-Bloc'^^ is shown in Figure 2.2.

Page 16: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

:^-<^^t\'%\'r«^j5^^ : < ^ '>• < s \

Figure 2.1: Compressed Tires (4)

Figure 2.2: Interlocking Design of Eco-Bloc™ (4)

7

Page 17: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

2.2.2 Different Types of Eco-Bloc (4^

2.2.2.1 Bulkhead/Erosion Control

The bulkhead/erosion control Eco-Bloc™ dimensions are 4'x4'x8', weighs

approximately 5.5 tons, and has the equivalent stmctural integrity as a solid concrete

block. Figure 2.3 shows the oblique view of a 4'x4'x8' Eco-Bloc unit. The economic as

well as environmental advantage of building with the Eco-Bloc™ is that it contains 120

scrap tires (1 ton of waste material), which displaces approximately 52% of the concrete

cost. EBS makes the Eco-Bloc"^^ flexible as the size, shape and stmctural integrity to

meet project specifications and it can be manufactured at the constmction site. This

product can be used for building retaining walls.

2.2.2.2 Perimeter Wall

The tilt wall style Eco-Bloc^^ can be used for walls, barriers, security enclosures,

etc. It is 2'x8'x10' in size and can be installed in the horizontal or the vertical position.

EBS makes available over 30 standard architectural patterns for the exposed surface of the

block.

2.2.3 Design Criteria (5)

The Eco-Bloc"^^ design is based on the engineering concept of weight combined

with a tongue and groove system for lateral resistance. The tongue in the concrete block

provides automatic alignment of the blocks, which in most cases, eliminates the need for

mortar. Each segmental stmctural unit serves as a gravity stmctural element for walls,

stmctures, and a permanent erosion control unit. The basic unit has a minimum wall

thickness of 6 inches with a central core of recycled tires.

The overall design configurations include:

• Unit geometry,

• Loading,

• Location (dry/wet).

8

Page 18: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

8"{typ)

6"(typrZ

I />•* 4'-0

4'-0

Figure 2.3: Oblique View of Eco-Bloc™ Unit (5)

Page 19: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

Two units are available: a steel reinforced unit for stmctural applications and a

plain concrete unit for non-stmctural applications. The basic unit is manufactured using

3000-psi concrete and has a minimum wall thickness of 6 inches with a central core of

recycled tires.

Table 2.1 is presented to provide basic engineering data for a single containment

unit, meeting minimum reinforcing requirements of the American Concrete Institute

(ACI), ACI 318-89 (revised 1992) specifications. The use of this data will allow an

engineer to design a wall system for site-specific conditions. A qualified engineer should

review any proposed application to be certain that the actual site conditions and the

proposed dimensions meet with standard engineering practice.

Table 2.2 provides engineering data for a single containment unit consisting of

plain concrete. This unit shall not be used in stmctural applications.

2.2.3.1 Design of the Unit

Three alternative designs of Eco-Bloc™ are presented based on the use of 3000

psi concrete. Altematives one and two meet the minimum reinforcing requirements of the

American Concrete Institute (ACI), ACI 318-89 (revised 1992) specifications. These

altematives are suitable for stmctural applications and the engineering properties of a

single unit (for either alternative one or two) are given in Table 2.1. Figure 2.4 shows the

first alternative, which consists primarily of welded wire fabric reinforcing. The second

alternative, shown in Figure 2.5, consists of number three steel reinforcing bars. The third

alternative is a plain concrete unit with comer reinforcing only and it is shown in Figure

2.6. It does not meet ACI code requirements and is not applicable for stmctural

applications requiring code conformance. The engineering properties of this alternative

are given Table 2.2. This alternative may be subject to shrinkage and/or thermal induced

cracking.

10

Page 20: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

Table 2.1: Engineering Properties of Single Unit-Steel Reinforced (5)

Property

Weight

Allowable Surcharge Capacity Allowable Punching Shear on Side Wall

6"X6" area 9"X9" area 12"X12" area Allowable Lateral Load Capacity of Tongue

Allowable Bending Capacity of Single Unit with Simply Supported Ends (uniform load)

Units

lbs

kips

lbs lbs lbs kips/ft

kips/ft

Value

13,900

200

9,000 11,900 14,900 19.0

18.8

Table 2.2: Engineering Properties of Single Unit-Plain Concrete (5)

Property

Weight

Allowable Surcharge Capacity Allowable Punching Shear on Side Wall

6"X6" area 9"X9" area 12"X12" area Allowable Lateral Load Capacity of Tongue

Allowable Bending Capacity of Single Unit with Simply Supported Ends (uniform load)

Units

lbs

kips

lbs lbs lbs kips/ft

kips/ft

Value

13,900

200

9,000 11,900 14,900 19.0

6.0

11

Page 21: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

W4.3 wire or W6.5 wire (typ)

Use WWF 4x4 or WWF 6x6 -

- W6 X W4.3 W9 X W6.5

W6 wire or W9 wire (typ)

6 #3 bars x 7'-8" O corners

(typ.)

Figure 2.4: Eco-Bloc™ Reinforcing Using Welded Wire Fabric (5)

6"

—3" cover (typ.)

20 / 3 bars x 7*-6" & 10" spacing

Z.

10 ^3 bars x 3'-6" 9 1 0 spacing Near and Far

-10 #3 bars x 3'-6" @ 10" spacing Top and Bottom

Figure 2.5: Eco-Bloc™ Reinforcing Using No. 3 Rebar (5)

12

Page 22: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

6"

I 3" cover (typ.)

— 6"

6 #3 bars x 7'-6"

Figure 2.6: Eco-Bloc™ Using Plain Concrete (5)

13

Page 23: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

2.2.4 Different Applications of Eco-Bloc™

Eco-Blocs can be used in different Civil Engineering applications. Some of the

typical usage of Eco-Blocs are in erosion control, wetland reclamation, traffic diversion,

building dikes or dams, sound barriers, warehouses, retaining walls, equipment bams,

parking lot levelers, retaining walls for bulk material, river wing dams, border walls,

prison walls and energy efficient homes. Figure 2.7 shows a retaining wall and Figure 2.8

shows a river wing dam built using Eco-Bloc™ units.

2.2.5 Features and Benefits of Using Eco-Bloc™ in Retaining Walls

Following are some of the features of Eco-Bloc™ units, which have beneficial

effects on constructing retaining walls.

a. Standard block has a 32 square foot base, which allows it to act as a foundation

unit eliminating the need for extra foundations.

b. Eco-Bloc's interlocking system makes the installation simple and cost-effective.

This interlocking also resists lateral movement.

c. Each block contains about 1 ton of waste material, which recycles waste from

environment. This also reduces concrete cost by approximately half, which

significantly reduces the cost and weight of the block.

d. The blocks can be manufactured at/near construction site, which reduces

overhead, and transportation cost.

e. The blocks can easily be reinstalled at another job site, as these are portable,

f The simplicity in manufacturing and installation minimizes the need for

technically skilled manpower,

g. This program can establish a community resource conservation program.

14

Page 24: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

Figure 2.7: Walls Using Eco-Bloc Units (4)

Figure 2.8: River Wing Dam Built Using Eco-Blocs (4)

15

Page 25: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

2.2.6 Economics of Construction bv Eco-Bloc™

Each Eco-Bloc' M unit contains about 1 ton of waste material, which reduces

concrete cost by approximately half, which significantly reduces the cost and weight of

the block. Standard block has a 32 square foot base (4'x8'), which allows it to act as a

foundation unit eliminating the need for extra foundations. The blocks can be

manufactured at/near construction site, which reduces overhead, and transportation cost.

The production price of each Eco-Bloc unit is currently approximately US $ 175/unit (4).

2.3 En-Core Tire Bales in the Construction of Retaining Walls

2.3.1 The En-Core Tire Baler (6)

The En-Core baler is manufactured by ENCORE SYSTEMS, inc., headquartered

in Cohasset, Minnesota. The En-Core baler is a vertical down stroke portable baler which

compresses approximately 100 whole passenger and light truck tires into a block

measuring 30 " x 50 " x 60 ". The baler has a chamber of about 5'x4'x2.5' which needs to

be filled three to five times before enough tires are compressed to complete the bale. The

baling process is shown in Figures 2.10-2.12. It takes about 15 minutes to produce a bale

depending upon the speed of the hydraulic system and the type of supportive equipment

used. Average production is 400 tires per hour. The weight of the completed block is

approximately one ton. This is a volume reduction of 5 to 1. The bales are secured with 5

strands of 9-gauge wire. The wires are 12 feet long, 2300-pound tensile strength, made of

carbon steel, galvanized or stainless steel with a "Square Loc" connecting knot.

In some cases, the bales are painted or coated with soil, shot-crete, plastic, foam,

or rubber compounds. Coating the bales improves the aesthetics and creates a barrier to

extend the integrity of the wire almost indefinitely.

The baler and two men are capable of making from four to six bales an hour on a

steady basis. The completed bales are ejected automatically. The completed bales can be

handled with a forklift, front-end loader, logger's clam or grappler. According to the

manufacturers, because of the uniformity of the bales, they can be easily stacked.

16

Page 26: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

Figure 2.9: Tires Being Loaded in the Baler (6)

17

Page 27: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

Figure 2.10: Tires being Compressed in the Baler (6)

Figure 2.11: Finished Bale Being Ejected From the Baler (6)

18

Page 28: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

2.3.2 Summary of Test Results on Tire Bale ^7)

Stork Twin City Testing Corporation in St. Paul, Minnesota performed a creep

test and a load deflection test on a tire bale submitted by the Encore Systems of Cohasset,

Minnesota. In the creep test, the average ultimate deflection after 72 hours was 8.06

inches under a load of 88,000 lb. In the load deflection test, the average ultimate

deflection was 11.45 inches under the maximum load of 338,850 lbs.

2.3.3 Benefits of Using Baled Whole Tires (6)

ENCORE SYSTEMS, inc. claims that the baler is relatively inexpensive, has

virtually no down time, and has very low maintenance costs.

Tires in baled form do not hold water; therefore, pose no threat to public health

due to mosquitoes. Because of the density of the bale, the decreased surface area, and

lack of air, the fire hazard is greatly reduced. The volume reduction of 5 to 1 makes the

storage and transportation of tires more convenient. The uniformity of the bales makes

them a feasible product to be used in Civil Engineering applications.

The comprehensive advantage to this method of scrap tire processing is the

potential use as an end product. Increasing disposal costs and state laws make the option

of baling whole tires an attractive and cost-effective alternative.

2.3.4 Costs of Baler. (6)

The operating and maintenance costs, as given by the ENCORE SYSTEMS, inc.

are given below:

1. Hvdraulic Maintenance Costs

Based on 48 H.P. Kubota diesel engine baling 1,000 bales @ 4 bales/hour

Assuming $10/hour labor costs, 1 hour labor @ $10.00/hour = $ 10.00

Filters/Parts — $ 27.85

Hydraulic Maintenance Costs To Bale 1,000 Bales = $ 37.65

19

Page 29: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

2. Engine Maintenance (Kubota^ Costs

1 hour labor @ $10.00 per hour = $10.00

parts (filters, oil change) = $15.00

Engine Maintenance Costs = $ 35.00

3. Fuel Consumption Costs

48 H.P. Kubota diesel engine - 1.25 gallons/hour.

1,000 bales @ 4 bales per hour = 250 hours

@$1 .25/gallon = $ 250.00

4. Labor Costs

3 men @ $10.00/man per hour baling 1,000 bales in 250 hours = $ 7,500.00

5. Wire Costs

5 galvanized wires per bale

1,000 bales = 5,000 wires @ $.45/wire — $ 2,250.00

6. Total Cost to Bale 1000 Bales/100,000 Tires

= $10,072.65/$.10 per tire.

2.3.5 Different Applications of Baled Tires

Many successful projects have already been completed using the bales. Some of

these projects include impact barriers, erosion control, land reclamation, equine training

arenas, fences, and dam construction. Tire bales were used in erosion control projects like

that in Carlsbad, New Mexico; Manitou Springs, Colorado and Cohasset, Minnesota. Tire

bales have been used as Subgrade Lightweight Fill for Road Construction in Chautauqua

County, New York and also in Pueblo, Colorado. Figure 2.12 shows the bales being used

as Subgrade Lighwight Fill for Road construcfion. Entrance walls and Equipment

buildings have been built ufilizing the bales in Pueblo, Colorado. Over 5,000 bales have

been used to elevate 4 acres of soil for using as a parking lot. Over 50,000 bales have

been used to build a dam in Mountain Home, Arkansas. They were used as fill material

on both the upper and lower sides of the dam.

20

Page 30: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

Figure 2.12: Tire Bales as Subgrade Lightweight Fill for Road Construcfion (6)

2.3.5.1 A Brief Description of Carlsbad, NM Project (6)

This project began in September of 1997, and used approximately 700,000

recycled scrap fires in the form of one-ton bales to stabilize 4,400 feet of the East bank of

the Pecos River in Lake Carlsbad.

Figure 2.13 shows the extent of erosion near the Carlsbad Country Club. The

erosion was being caused by wave action of pleasure watercraft. The river was drained to

allow for construction of the erosion control project.

The first step was to dig a three to four foot deep trench along the river's edge.

This was lined with a concrete foundation, and set with steel reinforcing bars. Then, one-

ton bales produced by Encore's Baler were set on top of the concrete and secured in

place. Figure 2.14 shows the bales on top of concrete foundation. The next step involved

encapsulating the tire bales in concrete. The encapsulation process is shown in Figure

2.15. The encasement in concrete enabled the tire bales to serve as a foundafion for a

concrete block wall, and prepared them for the application of a layer of facing stone,

which was laminated to the front of the bales. A block retaining wall was then

21

Page 31: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

constructed on top of the bales and backfill was applied behind the wall. Figure 2.16

shows the block retaining wall on top of the bales.

Figure 2.13: Erosion in Lake Carlsbad (6)

22

Page 32: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

Figure 2.14: Tire Bales on top of Concrete Foundafion (6)

Figure 2.15: Encapsulafion of Bales in Concrete (6)

23

Page 33: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

Figure 2.16: Block Retaining Wall on Top of Bales (6)

24

Page 34: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

CHAPTER in

STABILITY ANALYSIS AND DESIGN OF RETAINING WALL

3.1 Overview

From the research project's comprehensive literature review, two types of

retaining wall were chosen for further review and analysis. One was a Mechanically

Stabilized Earth retaining wall utilizing Eco-Bloc units and the other was Gravity

retaining wall using Encore Tire Bales. In the mechanically stabilized earth (MSE)

retaining wall, the earth mass is reinforced with a series of strips, which are attached to a

facing material. The facing resists the lateral thrust induced by the active earth pressure,

through the anchorage provided by the strips. The strips derive their tensile capacity fi-om

the friction developed between the strips and the earth. Figure 3.1 shows a typical MSE

wall construction using Eco-Bloc units. Gravity retaining walls depend solely on their

weight for stability. Different shapes of gravity retaining wall are shown in Figure 3.2.

This chapter presents detailed stability analysis for each type of wall.

3.2 Eco-Bloc Tire Retaining Walls

Eco-Blocs unit, patented by Ecological Building Systems, was used as the main

element to analyze and design mechanically stabilized earth retaining walls. The walls

were designed considering all possible modes of failure.

3.2.1 Modes of Failure

MSE walls shall be designed for external stability of the wall system as well as

intemal stability of the reinforced soil mass behind the facing. Both the external and

intemal stability failure problems were addressed in the design procedure.

25

Page 35: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

Tire Containment

Unit

Surface Water Collection/Diversion

(optional) \

Drainage Tile (as Req'd)

''Leveling Pad

"" Foundation Soil

Groundwater Drainage System (if Req'd)

Figure 3.1: Typical MSE Wall Constmcfion using Eco-Bloc™ Units (5)

26

Page 36: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

30"X50"X60"

6" concrete ' • = d 3 r

± 12" thick • concrete base

^ ^ 1 > ^ ( »( 1 Backfill \-; ^^Draimge 1 II 1 •^> Fill

__jz]aa 1 ^ ^ • a a a %

18'

• • • • • 1 /Drainage

^ •3^< „ M , ^ r »

— J o wiue concrete ba se

(a) Pyramid-Shaped Gravity wall

30"X50"X60"<--tire bale

C 6" concreie [ ] [

II II 11

- 1 II II II 11 II 11 II 11 II

^ ^

1 s -s%

Ai

^8K ^ ^ Drainage

* ^ Fill

Backfill 18'

^xCrainage ^ ^ Pipe ^

12" thick -concrete base

36' wide concrete base

(b) Front-Stepped Gravity wall

^ -

30"X50"X60",,;;--;^^ 1 tire bale ~~~ ^ f

6" concrete -'^^^^^^^^-—^

12" thick • concrete base

II 11 II II 11 II I II

1 11 II II

Backfill

1

M

\

1 1

i

^,,---Drainage * ^ Fill

^....-^rainage ^ ^ Pipe 1

36' wide cone

k

W

rete b

(c) Rear-Stepped Gravity wall

Figure 3.2: Gravity Walls of Different Shape

27

Page 37: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

3.2.1.1 External Stability

Stability computations shall be made by assuming the reinforced soil mass and

facing to be a rigid body. The external stability of an earth wall depends on the ability of

the reinforced soil mass to withstand external loads, including the horizontal earth

pressure from the soil being retained behind the wall and loads applied to the top of the

wall, without failure by one of the failure mechanisms: (l)sliding of the reinforced

volume along the base of the wall or along any plane above the base, (2) overtuming

about the toe of the wall and (3) bearing capacity failure or loss of serviceability because

of excessive settlement of the foundation soil.

1. Sliding Failure: It represents the ability of the reinforced structure to overcome

the horizontal force of the soil immediately behind it. The sliding failure

mechanism is shown in Figure 3.3 (a). The factor of safety of an earth wall

against sliding is typically taken as 1.5.

2. Overtuming Failure: this model the ability of the stmcture to overcome the

overtuming moment created by the soil pressures acting behind it. Figure 3.3 (b)

shows the overtuming failure mechanism. Design engineers have generally

accepted that reinforced soil walls should have a factor of safety of at least 2.0

with respect to overtuming.

3. Bearing Capacity Failure: The bearing capacity of the foundation soil must be

checked to ensure that the vertical load exerted from the weight of the wall and

surcharge is not excessive. Figure 3.3 (c) is an example of bearing capacity

failure. The generally accepted minimum factor of safety against this type of

failure for reinforced soil walls is 2.0.

28

Page 38: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

J J . . . /

(a) Sliding

i - •• • ' •

(b) Overtuming

iiJ ±.J^ ^ - ^

- » - - • I »^

• . ^ I i © Bearing Capacity (d) Global Failure

Figure 3.3: Extemal Stability Failure Mechanisms of MSE Retaining Walls

Source: Allan Block Design Manual

29

Page 39: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

3.2.1.2 Intemal Stability

Intemal stability requires that the reinforced soil stmcture be coherent and self-

supporting under the action of its own weight and any extemally applied forces.

Reinforcement loads calculated for intemal stability design are dependent on the soil

reinforcement extensibility and material type. In general, inextensible reinforcements

consist of metallic strips, bar mats, or welded wire mats, whereas extensible

reinforcements consist of geotextiles or geogrids. Intemal stability failure modes include

soil reinforcement mpture and soil reinforcement pullout. For a reinforced soil stmcture

to be intemally stable, the reinforcements must be able to carry the tensile stresses

transferred to them by the soil without mpture . In addition, there must be sufficient bond

between the reinforcements and the soil in the resisting zone that reinforcements do not

pull out under the load that they are required to carry. The basis for the intemal design is

to evaluate the required spacing and lengths of reinforcements so as to satisfy the mpture

and pullout criteria. Intemal stability is determined by equating the tensile load applied to

the reinforcement to the allowable tension for reinforcement, the allowable tension being

govemed by reinforcement mpture and pullout. Figure 3.4 shows the failure mechanism

of a mechanically stabilized retaining wall due to lack of intemal stability.

The load in the reinforcement is determined at two critical locations, i.e., at the

zone of maximum stress and at the connection with the wall face, to assess the intemal

stability of the wall system. Potential for reinforcement mpture and pullout are evaluated

at the zone of maximum stress. The zone of maximum stress is assumed to be located at

the boundary between the acfive zone and resistant zone. Potential for reinforcement

mpture and pullout are also evaluated at the connecfion of the reinforcement to the wall

facing.

A very important addifional intemal design considerafion concems loss of

reinforcement durability over time. Reinforcement deteriorafion can result from

corrosion, creep, and chemical and biological attack of the different reinforcement

materials. Current practices in design to prevent failure as a result of reinforcement

deteriorafion include use of additional reinforcement cross secfion to allow for corrosion

30

Page 40: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

(a) Breakage

i 4 . I * •

f | l 1 . - . . . • J

^^•*dada*da**ak

(b) Pullout

© Bulging

Figure 3.4: Intemal Stability Failure Mechanisms of MSE Retaining Walls

Source: Allan Block Design Manual

31

Page 41: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

loss, epoxy coating of metallic reinforcements, protection of geotextiles from exposure to

ultraviolet light, and design at reduced stress levels to minimize creep in plastic grids and

geotextiles.

3.2.2 Stability Analysis and Design of Retaining Wall

The present concept of systematic analysis and design of reinforced earth

stmctures was developed by a French Engineer, H. Vidal (1966). The mechanically

stabilized earth (MSE) retaining wall uses the principle of introducing reinforcing into a

granular backfill via mechanical means such as metal strips and rods, geotextile strips and

sheets, or wire grids.

The three basic components of MSE retaining walls are:

1. Earth fill - usually granular material with less than 15% passing #200 sieve.

2. Reinforcement - strips or rods of metal, strips or sheets of geotextiles or wire

gridding fastened to the facing unit and extending into the backfill some

distance.

3. Facing unit - not necessary but used to maintain appearance and to avoid soil

erosion between reinforcements. It may be curved or flat metal plates or

precast concrete strips or plates. In our case, Eco-Bloc units serve as the

facing unit.

MSE walls derive their lateral resistance through the dead weight of the

reinforced soil mass behind the facing. The current design procedures for reinforced earth

retaining stmctures consider the intemal and extemal stability analyses separately. MSE

walls shall be dimensioned to ensure that the minimum factors of safety required for both

intemal and extemal stability are satisfied. Different wall dimensions were analyzed for

different loading condifions, soil backfill properties and different types of reinforcement.

Both inextensible (metallic strips) and extensible (geotextile and geogrid) types of

reinforcement were considered in the design procedure. Diversified soil backfill

properties (fricfion angle varying from 25° to 35°) were considered. Different site settings

(horizontal backslope and sloping backslope) were analyzed in the design. Dissimilar

loading conditions (surcharge and non-surcharge) were analyzed.

32

Page 42: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

General Design Procedure for MSE Walls: The following general procedure was

followed for the design of MSE walls.

1. Establish wall profile and design loadings.

Establish wall profile from the grading plan of the wall site and verify the

following design assumpfions:

• The wall face is vertical or nearly vertical;

• The backfill is granular and free draining;

• The wall is constmcted over a firm foundafion or stabilized, improved soils;

• The live loads are vertical.

If any of the design assumpfions are not safisfied, the design method must be modified.

2. Determine the properties of backfill soil, foundafion soil and retained soil.

Well-graded and fi-ee-draining granular material should be used as backfill of

mechanically stabilized earth reinforced walls. The fHction angle, (|), of the soil can be

estimated conservatively by a soil engineer or determined by performing appropriate

direct shear or triaxial tests. Diversified fricfion angle ranging from 25° to 35°was

considered in the analysis. The unit weight, y, can be determined in a moisture density

test. Generally, the unit weight at 95% Standard Proctor relative compaction is specified.

A unit weight of 115 Ib/ft was assumed in the analysis of the wall. Obtain the shear

strength and allowable bearing capacity of the foundafion soil. Determine soil-tie fricfion

angle, ^u-

3. Establish design factors of safety.

Suggested values of safety factors used in the stability analysis are as follows:

I. Extemal Stability

a. Sliding, Fs>=l.5,

b. Overtuming, Fo>=2.0,

c. Bearing Capacity, Fb>=2.0.

n. Intemal Stability

a. Breakage Strength, FB>=2.5,

b. Pullout resistance, Fp>=2.5.

33

Page 43: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

4. Determine preliminary wall dimensions.

Determine the height of the wall; H. Heights extending fi-om 4' to 16' were

analyzed for the mechanically stabilized earth retaining wall. The heights were

incremented at an interval of 4', since the depth of the Eco-Bloc units are 4'. The heights

for gravity retaining walls ranged from 3' to 18'. Their height interval was 3' as the depth

of the EnCore Bale is 3'. An embedment depth, D is usually required for reinforced earth

stmctures to avoid bearing failure of the foundafion soil. Embedment is also required

because of risk of local failure in the vicinity of the spacing, depth of frost and risk of

scour or erosion-induced local damage. In any case, an embedment depth of 0.1 H is

usually used, H being the height of the wall.

5. Select reinforcement type and strength.

Both inextensible (metallic strips) and extensible (geotextile and geogrid) types of

reinforcement were considered in the design procedure.

Metallic strips of 1.6 by 0.2 inch with an ultimate tensile strength of 36 ksi were

considered in the analysis. Both the geotextile and geogrid were assumed to have

allowable tensile capacity of 100 lb/inch (17.5 kN/m). This is a conservative value.

6. Determine actions of lateral earth pressure due to overburden pressure and live

loads.

Active Earth Pressure Coefficient,

K,= ^'"^f^^^ (3.1)

y sin(0 - o)sin(^ + p)

where

0= back face of the retaining wall, (0=0 for vertical back face of the wall),

(t)= angle of intemal friction of backfill soil,

5= fricfion angle between back face of the wall and soil backfill,

p= slope of backfill.

The parameters of the above equation are shown in Figure 3.5.

34

Page 44: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

A ' K A X H

Figure 3.5: Coulomb's Active Earth Pressure (12)

Both sloping and non-sloping conditions were analyzed in the design procedure.

A typical, modest slope of 15° was analyzed to represent a sloping back slope.

For a non-sloping backfill, the above formula simplifies to the simplest form of

Rankine equation,

K^ = t an ' (45 -^ /2 ) (3.2)

7. Calculate horizontal tensile stress at each reinforcement level:

Maximum vertical pressure on nth layer, QV = Yz + q,

Maximum horizontal pressure on nth layer, CTH = Ka (ay),

where

y = unit weight of backfill,

z = depth of reinforcement,

Ka = active earth pressure coefficient,

q = surcharge.

A surcharge value of 500 Ib/ft spanning over 25 ft was analyzed in the design.

35

Page 45: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

Maximum tensile stress at nth layer,

T= (active earth pressure at depth z) x (area of the wall to be supported by the tie)

=(crh) X (s vxs h) (3.3)

where

Gh= horizontal pressure on reinforcement,

Sv= vertical spacing between reinforcements,

Sh= horizontal spacing between reinforcements.

Figure 3.6 shows the schemafic tensile force lines for both inextensible and

extensible reinforcements.

For metallic strips, values of horizontal and vertical spacing were assumed.

For geotexfile or geogrid, the vertical spacing of fabric layers (Sy) is calculated fi-om:

S . = ^ (3.4)

where

Taii= allowable fabric long-term tensile force per unit width,

ah= total lateral earth pressure for the layer,

FB= factor of safety against mpture.

The design specifications assume that the wall facing combined with reinforced

backfill acts as a coherent unit to form a gravity retaining stmcture. The effect of

relatively large vertical spacing of reinforcement on this assumption is not well known,

and a vertical spacing greater than 0.8 m (31 inches) shall not be used without full scale

wall data (e.g., reinforcement loads and strains, and overall deflections) which supports

the acceptability of larger vertical spacing.

36

Page 46: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

OJH.

^ • ^ A - j , C

w Mion ( ' / 4 - « / 2 )

t-m ' II I

P)

Figure 3.6: Tensile Forces in the Reinforcements and Schematic Maximum Tensile Force Lines: (b) inextensible reinforcements, (c) extensible reinforcements

Source: James K. Mitchell and Barry R. Christopher, "Design and Performance of Earth

Retaining Stmctures", North American Practice in Reinforced Soil Systems,

Geotechnical Special Publicafion No. 25, 1990.

37

Page 47: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

8. Check intemal stability:

Reinforcement loads calculated for intemal stability design are dependent on the

soil reinforcement extensibility and material type. Maximum reinforcement load is

obtained by multiplying a lateral earth pressure coefficient by the vertical pressure at the

reinforcement, and applying the resulting lateral pressure to the tributary area for the

reinforcement. The applied load to the reinforcement shall be calculated on a load per

unit of wall width basis.

Check against reinforcement mpture for each layer n.

For metallic strips,

T<L„ = '-^ (3.5) FB

where

T= developed tensile force in the reinforcement,

Taii= allowable tensile stress of the reinforcing material,

Ts= ultimate tensile stress of the reinforcing material,

FB = Factor of Safety against mpture,

w = width of each tie,

t = thickness of each tie.

For geotexfiles or geogrids,

T<T^„~ (3-6)

where

RF= RFIDXRFCRXRFD,

Tall = long-term tensile strength required to prevent mpture,

Tuit = ulfimate tensile strength of the reinforcement,

RF = combined reducfion factor to account for potenfial long-term degradation

due to installation damage, creep, and chemical aging,

38

Page 48: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

RFiD = strength reducfion factor to account for installation damage to the

reinforcement,

RFcR = strength reduction factor to prevent long term creep mpture of the

reinforcement,

RFD = strength reducfion factor to prevent mpture of the reinforcement due to

chemical and biological degradafion.

9. Determine length of reinforcements:

Total length of fies at any depth is L = L r + Lg (3.7)

where

L r = length within the Rankine /Coulomb failure zone,

Le = Effective length of reinforcements.

The effective length of ties along which the fricfional resistance is developed may be

conservatively taken as the length that extends beyond the limits of the Rankine active

failure zone.

At any depth z.

I , = ^ - ^ (3.8) ' tan(45 + ^/2)

where

h= height of wall,

z= depth of reinforcement,

([)= angle of intemal fiiction of backfill soil.

Check against reinforcement pullout for each layer n.

Pullout occurs when the reinforcement is pulled out of the soil by the intemal forces of

soil causing the wall to experience bulging or even worse, falling apart. Adequate length

of reinforcement prevents pullout. The reinforcement pullout resistance shall be checked

at each level against pullout failure for intemal stability. A factor of safety of about 2.5-3

is generally recommended for fies at all levels.

39

Page 49: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

For a given factor of safety against reinforcement pullout, Ff

j ^ , W A (3 2>vcr„ tan^^

For sheets of geotexfile, the values of w and Sh are meaningless. So, the equafion becomes

Le = -If^^^^ (3.10) 2cr., tan kO

where

Fp = factor of safety against pullout,

aa= lateral earth pressure at depth z,

ay = vertical earth pressure at a depth z,

Sy = vertical spacing of reinforcement,

Sh = horizontal spacing of reinforcement,

w= width of reinforcing ties,

k(|)= soil-tie friction angle (can be conservatively assumed to be 2/3 of intemal

friction angle of backfill, (|)).

Find fabric wrapped embedment length for geotextile.

The length of fabric-wrapped embedment, Lo is calculated by dividing the lateral

pressure-induced tension in the fabric by the fricfion mobilized between the soil and

fabric over its overlap length. The required fabric overlap length is calculated from:

A(7^ tan(A: )

So, a minimum fabric embedment length of 3 ft should be used.

40

Page 50: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

10. Check the extemal stability of the wall:

Check for overtuming, sliding and bearing capacity failure needs to be done to

ensure the extemal stability of the MSE wall,

i. Check for overtuming.

The factor of safety against overtuming is defined as the ratio of the sum of

stabilizing moment to the sum of overtuming moment. The moments are calculated by

taking moments about the toe of the footing.

Fo = Resisfing Moment, MR/Overtuming Moment, Mo

MR = (Weight of soil, Ws)x(distance of Ws from front face of wall)+

(Weight of block, W b)x(distance of W b from front face of wall)+

(Weight of surcharge q, Wq)x(distance of Wq from front face of wall) (3.12)

Mo = Total soil thmst, PaX distance of Pa from base of wall

= l/2KayH^xH/3+KaqHxH/2 (3.13)

ii. Check for Sliding.

The factor of safety against sliding is defined as the ratio of the sum of horizontal

resistance forces to the sum of horizontal disturbing forces.

Fs = Horizontal resisting forces/ Horizontal driving forces

= (Ws +W b +W q)(tan k,|,)/( 1 /2 Kay H^+KaqH) (3.14)

where k(|) = friction angle at geotextile-soil interface = 2/3 (|).

iii. Check for Bearing Capacity Failure.

Since allowable bearing capacity depends on site conditions and these walls may

be used in a variety of condifions, a conservative approach was followed to check against

bearing capacity failure. Allowable bearing capacity of 3000 Ib/ft was assumed in the

design. Actual bearing pressure coming to the base was then calculated. The maximum

pressure usually occurs beneath the toe. This value must not exceed the allowable bearing

capacity of the soil, otherwise setfiement or vertical yielding may occur. Factor of safety

against bearing capacity failure was then determined by dividing allowable bearing

capacity (3000 Ib/ft ) by the actual bearing pressure, hi some cases, the reinforcement

length had to be increased to safisfy this criterion. Equations 3.15 and 3.16 were used to

obtain the actual bearing pressure coming to the foundafion soil.

41

Page 51: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

Eccentricity,e='-''''''''^'"'^^^''''<^'^^ (3.15) Ws + Wb-vqL

n • Ws + Wb + qL , . . ,, Bearing pressure,cr = — (3.16)

L-2e

3.3 Encore Tire Bale Retaining Walls

Encore tire bales, produced by Encore Systems, inc., were used as the building

block for analyzing constmcfion of gravity walls. Different wall dimensions were

analyzed for different loading conditions and different soil backfill properties.

3.3.1 Modes of Failure

A gravity wall is typically intemally stable. The failure mechanisms of a gravity

wall are the same as those for the extemal stability of a mechanically stabilized earth

retaining wall. For the purpose of checking extemal stability, a gravity wall is treated as a

rigid monolith (i.e., no intemal yielding or distortion).

3.3.2 Stability Analysis

The same principles applied to ensure the extemal stability of the MSE wall was

applied to check the extemal stability of the gravity wall.

42

Page 52: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

CHAPTER IV

DESIGN CHARTS AND SPECIFICATIONS

4.1 Overview

This chapter presents details of design charts and constmction specifications of

the mechanically stabilized earth retaining walls and gravity retaining walls. The

development of design charts involved repeated analysis for different site condifions,

different loading conditions, different wall configurafions and different natural properties.

After all the design combinafions are put into design, the designs are combined to form

design charts. After the design charts are completed, constmcfion detailing needs to be

determined. These details should include the stacking arrangement of fire bales,

connecting tire bales together and placing and compacting the backfill.

4.2 Selection of Design Parameters

Different wall dimensions were analyzed for different loading conditions, soil

backfill properties and different types of reinforcement. Both inextensible (metallic

strips) and extensible (geotextile and geogrid) types of reinforcement were considered in

the design procedure. Reasonable values were assumed for their tensile strength. The soil

parameters were selected based on commonly used soil backfill materials. Ranges of soil

backfill properties (friction angle varying from 25° to 35°) were considered. Different site

settings (horizontal backslope and sloping backslope) were analyzed in the design.

Dissimilar loading conditions (surcharge and non-surcharge) were also analyzed.

4.2.1 Wall Configurafions

Two types of retaining walls were considered in the analyses. They are the

mechanically stabilized earth retaining wall and gravity retaining wall. One configuration

of mechanically stabilized earth retaining wall was analyzed with different kinds of

reinforcement. Three types of gravity retaining wall were reviewed. These are pyramid

shaped, front-stepped and rear-stepped. These configurations are shown in Figure 3.2.

43

Page 53: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

4.2.2 Site and Loading Condifions

Each configuration of both the mechanically stabilized earth retaining wall and

gravity retaining wall was designed for different extemal environment. Both horizontal

and sloping backslope were examined in the design. A modest slope of 15° was used to

represent a sloping backslope. Dissimilar loading environments were analyzed in the

design. One was with surcharge and the other was without surcharge loading. The

surcharge loading considered in these analyses included a uniformly distributed load of

500 Ib/ft spanning over 25 ft into the backfill.

4.2.3 Earth Reinforcement Systems

With strip reinforcement methods, a coherent reinforced soil material is created

by the interaction of longitudinal, linear reinforcing strips and the soil backfill. The strips

are normally placed in horizontal planes between successive lifts of soil backfill. For

concrete panel facings, the reinforcement strips are made of mild galvanized steel, with a

cross-secfion of 1.6 by 0.2 inch or 2.4 by 0.2 inch (40 by 5 mm, or 60 by 5 mm) or of

high strength steel with a cross-secfion of 2.0 by 0.16 inch (50 by 4 mm). Metallic strips

of 1.6 by 0.2 inch with an ulfimate tensile strength of 36-kip/sq inch were considered in

the analysis. Their surface is ribbed to improve the apparent soil-reinforcement friction.

Grid reinforcement systems consist of metallic or polymeric tensile resistant

elements arranged in rectangular grids placed in horizontal planes in the backfill to resist

outward movement of the reinforced soil mass. Geogrid reinforcements are produced and

marketed under the trade name "Tensar" by Netlon Limited in the United States, United

Kingdom, and elsewhere. Tensar geogrids are manufactured from high strength grades of

high-density polyethylene or polypropylene using a stretching procedure. Geogrids

generally are of two types: (a) uniaxial geogrids and (b) biaxial geogrids. Moderate

strength geogrids suitable for design lives between 1 year and 120 years have tensile

capacity of 100 lb/inch (17.5 kN/m). Facings can be formed for geogrids by looping

reinforcements at the face or by attachment of the reinforcement grids to concrete panels.

Continuous sheets of geotexfiles laid down altemately with horizontal layers of

soil form a composite reinforced soil material with the mechanism of stress transfer

44

Page 54: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

between soil and sheet reinforcement being predominantly fricfion. The majority of

geotexfile fabrics used in soil reinforcement are made of either polyester or

polypropylene fibers. Woven, nonwoven needle-punched, nonwoven heat-bonded, and

resin-bonded fabrics are available as well as materials made by other processes. Moderate

strength geotextiles suitable for design lives between 1 year and 120 years have tensile

capacity of 100 lb/inch (17.5 kN/m). The durability of geosynthefic reinforcements is

influenced by environmental factors such as fime, temperature, mechanical damage,

stress levels and chemical exposure. Facing elements are commonly constmcted by

wrapping the geotextile around the exposed soil at the face and covering the exposed

fabric by gunite, asphalt emulsion or concrete. Altematively, stmctural elements such as

concrete panels or gabions can be used. Connecfion between the geotexfile sheet and

stmctural wall elements can be provided by casfing the geotexfile into the concrete,

fricfion, nailing, overlapping or other bonding methods.

4.2.4 Soil Parameters

The soil parameters selected in the design procedure represent the range of backfill

soils that are commonly used in retaining wall constmction. The soil parameters that were

assumed are soil friction angle and unit weight of soil. Soil friction angles ranging from

25° to 35°were considered in the analysis. A moderate unit weight of 115 lb/ft for soil

backfill was assumed in the analysis of the wall.

4.3 Design Charts

The design charts provided herein fumish an accurate esfimate of reinforcement

spacing and lengths for different configurafions of the walls. To use the charts, one has to

verify that the site and loading condifions match the given site condifions of the chart.

The following secfions provide the design charts of retaining walls for soil friction angle

varying from 25° to 35°. These charts may be used in projects that match the site and

loading descripfions provided in the charts.

45

Page 55: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

4.3.1 Design Charts for Eco-Bloc Retaining Walls

Tables 4.1 through 4.4 fumish design charts for mechanically stabilized earth

retaining wall ufilizing Eco-Bloc units. Tables 4.1 and 4.2 are the design charts for MSE

walls to be built with metal strips as the reinforcement. Table 4.1 can be used for MSE

walls with backfill soil fricfion angle varying from 25° to 30°. Table 4.2 corresponds to

MSE walls with backfill soil fricfion angle varying from 30° to 35°. Tables 4.3 and 4.4

are the design charts for MSE walls to be built with geotexfile / geogrid as the

reinforcement. Table 4.3 can be used for MSE walls with backfill soil fiiction angle

varying from 25° to 35°. Table 4.4 corresponds to MSE walls with backfill soil fricfion

angle varying from 30° to 35°. These tables provide the height and width of retaining

walls along with the lengths of reinforcement. The diagrams corresponding to the tables

are shown in Figures 4.1 through 4.6.

4.3.2 Design Charts for Encore Bale Retaining Walls

Tables 4.5 fumishes design chart for gravity retaining wall ufilizing Encore fire

bales as the building block. The table corresponds to a pyramid-shaped gravity retaining

wall or a front-stepped gravity retaining wall or a rear-stepped gravity retaining wall

(Figures 4.7- 4.9). The table can be used for soils with fricfion angle varying from 25° to

35°. The table corresponds to gravity walls with or without surcharge and also for both

horizontal and sloping backfill. The table provides the height and width of retaining walls

along with the number of bales and the number of rows of bales.

46

Page 56: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

o O CO

O • 4 - *

o m CN t M

o (U

**^ 00

^

c o

• * - »

o •c PtH

Soil

l-l

,o <+H

all

43 t : cd

W TS Q) N

• » - ^ '—'

00 > .

^ • ^

c« o • t-H

C «J

X ! o u s

^

' ^ (D

1 " * ^

X5 cd

H

a

Stri

m •»-> (U

S

ype:

H • * - >

c <l> B (U CJ ; - l

nfo

w ft^

Len

gths

of m

etal

str

ips

|

(ft)

1

Num

ber

of b

lock

s

PQ

ffi

(ft)

(ft)

Con

ditio

n

abov

e w

all

S

h-1

1—1

i n

o

-

-

^

oo

<N

-

0 0

•n

»n

o

o

ro

(N

(N

O CO

O

o

o

"«t

' ^

(N

»o

Figu

re 4

.1

u-i

o

-

-

- ^

o

CM

-

0 0

»n

0 0

0 0 CO

CO

CN

( N

O

o

0 0

0 0

m

(N

(N - *

'=t

(N

VO

Figu

re 4

.2

O

CO cn

-

-

' ^

0 0 CN

CN

-

OO

m m

CO

o

o

CO

CN

CN

CO

O CO

0 0 CO

0 0 CO

CN

CN

' ^

CN

VO

Figu

re 4

.3

47

Page 57: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

o in CO

o • » - »

o

o CO <•*->

o u (30 c

<

c o

• • - <

o •c tin • ^ M

O C/D Vi

cS • — 1

t: c« w T3

N

• 1-N

X) «J -4->

C/3 >.

all

o • 1 — c

G e« ^ o (U s CN ^ (U

^ • ^

^ c« H

O-•c •<-J

(/)

cd • * - >

(L>

fe H +->

e (U f > i-l

,o U-i

a (D c^

Len

gths

of m

etal

str

ips

| N

umbe

r

m

K

(ft)

1 of

blo

cks

(ft)

(f

t)

Con

ditio

n

abov

e w

all

3 CO

CN

2

o

o CN

-

-

't

o

CN

CN

CN

-

00

CN

«n CN

00 CN

00 CN

CO

CN

CN f-H

CN CN

CS CN

CN

CN

o ro

o ro

^

CN

VO

Figu

re 4

.1

o

o CN

-

-

^

o CN

CN

CN

CN

-

00

in CN

m CN

00 CN

00 CN

ro

CN

CN

O CN

O CN

00 CN

OO CN

CN ro

CN ro

'^

CN

VO

Figu

re 4

.2

in

CN CN

-

-

Tj-

00

CN CN

in CN

CN

-

00

CN CN

(N CN

in CN

in CN

ro

CN

CN

CN CN

CN CN

CN

CN

CM CO

CN CO

^

CN

VO

Figu

re 4

.3

48

Page 58: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

T

B=rembedmer 5 L2

^

2.5'

2.5'

H=4' high MSE retaining wall T

B= r embedment

1 I i

Ll

L2 tJ^

L3

^ 4?

•0 H=8' high MSE retaining wall

/ Drainage Fill

%/ Ll v.-

L2 1 L3

4v Drainage Fill

L4

/

#

Drain Pipe

H=12' high MSE retaining wall

2.5' vertical spacing

2' vertical spacing

B= T embedment

Ll

I L2

L3

L4

B

L5

L6

.O"

/ ^

^

H=16' high MSE retaining wall

Figure 4.1: MSE wall using metal strips with horizontal backfill and no surcharge

49

Page 59: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

500 Ib/ft surcharge for 25'

2' r

B=l' embedme • i

&

Ll L2

i>" J^ 0 H=4' high MSE retaining wall

2.5'

2.5'

T

B= r embedment

500 Ib/ft surcharge for 25'

i i

Ll ^

L2

L3 7 s^ 0'

H=8' high MSE retaining wall

2.5' vertical spacing

B=2' embedment

500 Ib/ft surcharge for 25'

.v/

I 5

Drainage Fill

Ll

I L2

5

L3

L4

Drainage Fill

Drain Pipe

H=12' high MSE retaining wall

2.5' vertical spacing

2' vertical spacing

B= 2' embedment

i00 Ib/ft surcharge for 25',

' . Ll ISL I

I L2 /

tft-

L3 1 ^ .

L4

1 ^ . L5

J L6

I I

.^^ a H=16' high MSE retaining wall

Figure 4.2: MSE wall using metal strips with horizontal backfill and 500 Ib/ft surcharge

50

Page 60: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

T V

B=r embedm( I Ll L2 ^

0-(%'

H=4' high MSE retaining wall

2.5'

2.5'

2'

B= r embedment t)

Ll

L2

L3 T M c

H=8' high MSE retaining wall

15° slope

2.5' vertical spacing

B=2' embedment

1^ iCr

Drainage Fill Ll

I \

If

L2 1^' ^

L3 V?

Drainage Fill

L4

Drain Pipe Pfpe

H=12' high MSE retaining wall

2.5' vertical spacing

2' vertical spacing

15 slope

V

B=2' embedment

Ll

, •

, •

>

L2

L3

L4

L5

_,•

L6

IID

/? #

1l»

^

- 0 /

.0 H=16' high MSE retaining wall

Figure 4.3: MSE wall using metal strips with 15' sloping backfill and no surcharge

51

Page 61: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

o O CO

O •(->

o »n CN tM

o (L>

^ • ^

bO

1 C o • 1-H

o •c PH

• f^

o C/) 1-1

4: 1

» 'H

rth

CO

73 q> N ^^ JO

00

ally

O • H

C «J

xi o (U s ro -*

u ^•^H

X) «J H

TJ

• & o o ''*'*»,^ (L>

" 1-N

+-> X!

o <1)

O

ype

c OJ

S (i> o LH

nfo

Rei

,£3

ti) c (U ^

lap

i-H (U >

O

TD

• &

/geo

xt

ile

geot

e hs

of

^

c

/—N

w

(ft)

-^ ^

B -5 § - •7 tM

CQ

ffi

^

£

(ft)

|

a ^

Con

ditio

ab

ove

wa

' ^ ^-H

hJ

m ^^

J CN 1—H

^

^ l-H

hJ

0 1—H

00

h-1

3

CN

hJ

m

'^

Tf

,—1

'"'

"^

^

-^

1 Fi

gure

ro

ro

^

m

00

CN

• " ^

00

ro

•n

u-

»o

VO

00

0 ""

»n t-H

ro

CN

CN

ro

ro

ro

"^

^

•r

u

0

0

0 CN

0 CN

UO CN

u-i CN

»n CN

^

CN

^

ro

»ri

u

1—1

1-H

'^

m '^

1 Fi

gure

ro

"^

tn

in

VO

0

^

CN

""

00

ro

«n

>o

00

00

0 ""

0 ""

0 CN

0 CN

ro

CN

CN

ro

0 ^ H

0 r—l

0 1-H

0 »-H

0 CN

0 CN

0 CN

0 CN

CN

yn CN

•T) fN|

^n CN

u- ro

•n ro

^

CN

VO

ro

m

»n

-—I

•^

VO

^

1 Fi

gure

ro

yn

•T)

0

^

0

CN

00

ro

U-)

wo

00

00

vo '^

<:>

^

vo

ro

CN

CN

p-|

ro

-^

^

U-)

in

0

0

0

0

0

0 • " ^

0 CN

0 CN

0 CN

^

CN

VO

52

Page 62: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

o »n ro

o O ro +H

o (U

^ • ^

bO

1 c o

Fric

t

• ^ o i- l

,o t M ^ «J

^

J 3

art

w

lized

-9 c« • 4 - >

C/3

>% j ;5 C3 O

• wM

C a ^ o (U s

^ ' ' ^ (U

1 — H

^ c« H

-o

o o (U

- 4 . ^

X (U

o o o oi & H c B o ; - i

<2 c <u

Cci

Vi J3

U C <u J

lap

l-H (U >

O

-n • &

o bO

D

-4-J

X U

O bO

o

Len

gt

^-^ w

«

^ "si -^ ^

:^ ^

CQ

ffi

£ g

c ^

ondi

tio

ove

wa

U -^

^

3 ro

HJ

CN I -H

H-1

^ H

2 o » - H

0 ^ I - )

0 0 I - l

vo h-1

3 ro

CN

^^

J

ro

^

' ^

1 - H

-

^

ro

ro

^

r

o

CN

-

0 0

ro

'si-

' ^

«n

»n

0 0

o

m

ro

CN

CN

ro

ro

ro

VO

VO

O '"'

o , - H

•n

m

o CN

O CN

VO CN

VO CN

VO CN

' ' t

CN

VO

"^

I H

fe

ro

m

yn

1—1

-

^

ro

T f

uo

•n

VO

o

CN

-

0 0

ro

»n

•n

0 0

oo

o

o

o CN

O CN

ro

CN

CN

ro

i n

»n

»n

IT)

o

o ^^

o

o

o CN

o CN

o CN

O

o ro

O ro

' ^

CN

VO

>n

[in

ro

m

•n

" — I

-

^

ro

m

«n

o

o ^^

CN

-

0 0

ro

m

»n

0 0

0 0

0 0

0 0

0 0 '"'

ro

CN

CN

ro

T t

•^

m

»n

o ^^

o

o

m

m

<n

CN CN

CN CN

CN CN

"^

CN

VO

VO

(U >H

[JH

53

Page 63: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

2'

r B=r embedmei § 6 '

H=4' high MSE retaining wall

Spacing @ 2'

_L1

B=r embedment

1 ^ .

5: . iS i -

1 ^

^

0 >v

• ^

Dram Pipe

H=12' high MSE retaining wall

H=8' high MSE retaining wall

Drainage Fill

Spacing between Ll and L2 @2'

Spacing between L3 and L4 @1.5'

Spacing between L5 to L9 @r

Spacing between LIO to [email protected]'

B=2' embedment

•J".

•i

'A

t • • I I 5

1 V5?

If

a H=16' high MSE retaining wall

Figure 4.4: MSE wall using geosynthefics with horizontal backfill and no surcharge

54

Page 64: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

2'

T B=l' embedme

500 Ib/ft surcharge for 25'

t3^ a Spacing @ 2'

H=4' high MSE retaining wall Spacing® r

B= r embedment

500 Ib/ft surcharge for 25'

5 / ^

Ci. Id".

I i?

Spacing

Spacing

@2'

500 Ib/ft surcharge for 25'

@1'

1^ Drainage Fill

I i •J".

^ ^.s^

B=2' embedment

vf

\ ^

••A

Drain Pipe

H=12' high MSE retaining wall

Spacing between Ll and L2 @2'

Spacing between L3 to LIO @r

Spacing between Ll 1 to [email protected]' J

& ' .0' H=8' high MSE retaining wall

Drainage Fill

500 Ib/ft surcharge for 25'

l i i i i U i

I 0 i H | JJ-

' ^

«•."'

i s '

if.

-f l ^ •

f.

^ L ^

3?

0 B= 2' embedment

H= 16' high MSE retaining wall ^

Figure 4.5: MSE wall usmg geosynthetics with horizontal backfill and 500 lb/ft

surcharge

55

Page 65: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

2' _LL

B=l'embedment

15° slope

' 5

H=4' highMSEretaining wall 0- Spacing @ 2'

r b=r ernbedment

: ^

^' >r

-M^

•0 H=8' high MSE retaining wall

-vv' Drainage Fill

B=2' embedment

Drain Pipe

H=12' high MSE retaining wall

Spacing between Ll and L3 @2'

Spacing between L4 to L9 @r

Spacing between LIO to [email protected]'

M

i.-tf

B= 2' embedment

t

15° slope

# ys^

#

^ '

A» ^

• A

..^"

H=16' high retaining wall

Figure 4.6: MSE wall using geosynthetics with 15° sloping backfill and no surcharge

56

Page 66: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

o ro

I o »0 CN (+H

o

c o

' • ^

O • 1-H tH

O 00

I H

bO G C

> >H

o

H

Num

ber

of

row

s of

bal

es

Num

ber

of b

ales

m g

ffi g

Con

ditio

n ab

ove

wal

l

-

-

VO

ro

CN

ro

CN 1-H

VO

ro

VO

00

as

^

o

CN

CN

»n

«n

o ro

«o

VO

CN

VO ro

00

Figu

re 4

.7

-

-

VO

ro

CN

ro

CN

VO

ro

VO

00

OS

^

o

cs

(N

yn

«o

o ro

W-)

VO

CN

VO ro

00

Figu

re 4

.8

-

-

VO

ro

CN

ro

CN

VO

ro

VO

OO

ON

'i^

o

CN

CN I — 1

u-^

u-

o ro

»o

VO

CN

VO ro

oo

Figu

re 4

.9

57

Page 67: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

30"X50"X60" tire bale

6" concrete

Horizontal Backfill with

1 no surcharge

12" thick concrete base

Drainage Fill

H=18'

Drainage Pipe

B=36' wide concrete base

(a) Pyramid-Shaped Gravity wall

CZIT 30"X50"X60" tire bale

•a Dan

6" concrete

12" thick -concrete base

•aaa aaaaaI laaiaaarS

Drainage Fill

Horizontal backfill with no surcharge

Drainage Pipe

H=18'

B=36' wide concrete base

(b) Front-Stepped Gravity wall

30"X50"X60" tire bale

^ ^

1 ac

6" concrete

12" thick concrete base'

a Horizontal backfill with no surcharge

Drainage Fll

B=36' wide concrete base

(c) Rear-Stepped Gravity wall

Figure 4.7: Gravity Walls of Different Shape with no Surcharge

58

Page 68: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

30"X50"X60" tire bale

6" concrete

12" thick concrete base

, 500 Ib/ft surcharge for 25'

I II 1 rJ ^ ^ D h i n a g e 1 II I 'if^ Fill

I 11 ] I I Horizontal ^ - — ^ ' — " - — - * backfill with 500

I ) ( Z Z ) I Z Z ) ( Z Z ] ^^^^' surcharge

aaaaa I i rnai~ir~i k

(a) Pyramid-Shaped Gravity wall

H=18'

I "rainage Fipe

B=36' wide concrete base

30"X50"X60" tire bale

6" concrete

12" thick -concrete base

30"X50"X60" tire bale

6" concrete

12" thick -concrete base

500 Ih/ft surcharge for 25'

aaac I

Horizontal backfill with 500 Ib/ft surcharge

Drainage Fill

Drainage Pipe

H=18'

(b) Front-Stepped Gravity wall

B=36' wide concrete base

500 Ib/ft surcharge for 25'

Horizontal backfil with 500 Ib/ft surcharge

I

1 Drainage Fill

Drainaj ;e Pipe

H=18'

(c) Rear-Stepped Gravity wall

B=36' wide concrete base

Figure 4.8: Gravity Walls of Different Shape with 500 Ib/ft Surcharge

59

Page 69: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

30"X50"X60" tire bale

15° slope

•iT.

6" concrete

^ 15 sloping JI I backfill with

- ( >. no surcharge I

12" thick concrete base

nage

H=18'

Drainage pe

(a) Pyramid-Shaped Gravity wall

B=36' wide concrete base

15° slope

30"X50"X60"<-tire bale

L 6" concreie i [

^ — ' ^ — ar 12" thick ^ concrete base

)l

11

- 1 II II II II II II II II II

—' 15° sloping ty^ 1 backfill with no [i.

surcharge r

J %

^ ^

•^ h>—-5o wide concrete base

. Drai nage Fill

H=

Drai nage Pipe^

(b) Front-Stepped Gravity wall

30"X50"X60' tire bale

6" concrete

12" thick -concrete base

15° slope

15° sloping backfill with no surcharge

Da inn

(c) Rear-Stepped Gravity wall

Drainage Fill

Drainagt Pipe

H=18'

B=36' wide concrete base

Figure 4.9: Gravity walls of Different Shape with 15' Sloping Backfill

60

Page 70: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

4.4 Construction Costs of the Tire Retaining Walls

The total cost of earth retaining walls is composed of materials, construction and

backfill soil costs, and any special project features. Special project features might include

a special wall facing treatment or restricted site access. Usually, a reinforced retaining

structure may be 20 to50 percent less expensive than conventional altematives. This is

because the materials cost less, and the simple construction procedures result in lower

installation costs. An earth-reinforced wall may be especially cost effective where its use

permits the use of on-site soil as backfill material. The primary advantage gained from

the use of reinforced soil may be the improved idealization, which the concept permits;

thus structural forms that normally would have been difficult become feasible.

Reinforced soil structures will not always prove economical when compared with other

structural forms, but in many conventional situations where circumstances are favorable,

savings in cost may be realized. Cost comparisons are more difficult for slope and

embankment reinforcement because each situation is likely to be unique, and there may

be several options for each situation.

The derivation of cost estimates for a project is one of the significant elements in

the project. The total cost of a reinforced soil structure is made up of the following cost

estimates:

i. Excavation,

ii. Backfill,

iii. Reinforcing connection elements and their installation,

iv. Facing elements,

V. Labor for transport and construction,

vi. Transport of materials,

vii. Drainage construction.

The above elements are interrelated and the minimum total cost of a structure may be

produced by a combination of the most compatible elements in any particular situation.

Accurate expense for the retaining walls could not be estimated as no retaining

walls of these types have ever been built. However, both the MSE wall and gravity

61

Page 71: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

retaining wall should cost less than their conventional altematives because of lower

material cost.

The cost of excavation is less in the case of MSE walls built with Eco-Bloc units,

as they do not need any extra foundation. Standard block has a 32 square foot base

(4'x8'), which allows it to act as a foundation unit eliminating the need for extra

foundations. Gravity retaining walls made of Encore Tire Bales require concrete

foundation, the thickness of which is equal to the height of wall in inches (e.g., 12" thick

concrete foundation for a 12' high wall). The cost of fill materials is dependent upon local

availability and haulage rates. Reinforcement materials have different properties and

costs vary. MSE walls built of Eco-Bloc units require less reinforcement because of the

magnitude of the blocks. Gravity retaining walls are more economical than MSE walls as

they do not require any reinforcements. Both the Eco-Bloc units and encore Tire Bales

can be manufactured at/near the construction site, which reduces overhead and

transportation cost. The cost of drainage construction should not vary much for different

types of retaining wall, with site conditions determining the cost of drainage.

The tire bales make the big economic distinction. Producing tire bales is a far

better economic alternative than paying for the disposal of scrap tires. Each Eco-Block

unit contains 120 scrap tires (about 1 ton of waste material), which displaces

approximately 52 percent of concrete. This reduces the cost and weight of the block to

about half Moreover, each Eco-Bloc removes 120 scrap tires form the environment,

which would otherwise have to be disposed off in a landfill paying for their disposal costs

also. The disposal costs of tires vary from state to state. However, on average, their

disposal cost is around $ 1-1.5 per tire. Consequently, each block saves the state

approximately $ 150 in disposal fees. The price for each Eco-Bloc unit is approximately

US $ 175/unit. Producing the same volume of concrete of an Eco-Bloc unit (4'x4'x8')

would cost about US $ 250. The Encore tire bales contain 100 scrap tires. According to

the manufacturers, the production price of each bale is about US $15. hi addition to this,

each tire bale saves the state approximately $ 125 in tire disposal fees. The size of each

bale is 30"x50"x60"(1.93 cubic yard). Consequently, each tire bale displaces about 1.93

cubic yard of concrete from a gravity retaining wall.

62

Page 72: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

4.5 Construction Technignpc for Tire Ret.inin^ w.iic

The topography, drainage pattems, soil conditions and local building codes and

regulations have to be considered for the construction of retaining wall. Construction of

reinforced soil structures must be consistent with the assumed idealization and analysis.

Speed of construction is essential to achieve economy and is detemiined by the rate of

placing and compacting the fill. Economy may be achieved by the simplicity of the

construction technique. Care must be taken that building units and reinforcements are not

damaged during construction. The following several factors have to be considered for

constructing retaining wall using tire bales.

When installing walls more than 4 feet high, particularly with surcharge loads, a

qualified engineer should be consulted, as recommended by the manufacturer's of the

Eco-Bloc units.

Foundation soil should be examined by the engineer to ensure that the actual

foundation soil strength meets or exceeds the assumed design strength. Site preparation

consists of excavating the area where construction is to take place to the limits shown in

the plans. Foundation soil should be excavated to a depth recommended by a qualified

engineer. The excavation width at any depth should be equal to or exceed the length of

the reinforcement layer planned for that elevation. Foundation preparation includes

removal of unsuitable materials or regrading the bottom of the excavation. Unsuitable

foundation materials may need to be replaced with compacted backfill prior to

construction of the MSE wall.

The first course of the concrete blocks shall be placed on the prepared base (no

extra foundation is necessary). The tire containment unit should be checked for levelness

and alignment. Units should be placed end to end for frill length of the desired structure.

Alignment could be done by using a string line or any other technique that is approved by

the engineer. The top of the unit should be cleaned before installing the next one on top

of it. The second course of tire containment units should be positioned upon the preceding

one, straddling two lower units, and staggering the vertical joints (no mortar or

interlocking pins are required). It is important that the Eco-Bloc units are not damaged

63

Page 73: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

during handling. The stability of the facing panels during the backfilling operation can be

ensured by temporary struds placed on the extemal side of the wall.

For building gravity walls made of Encore Tire Bales, extra foundation needs to

be built. The thickness of the concrete foundation should be equal to the height of the

wall in inches, with a minimum of 6 inches. The first course of the tire bales shall be

placed on the foundation. There should be a gap of 6 inches between tire bales in both

vertical and horizontal direction. The bales need to be tied to one another in some

fashion. They can be tied with # 3 rebars running both vertically and horizontally. The

front of the wall should be painted or coated with soil, shot-crete, plastic, foam, or rubber

compounds. Coating the bales improves the aesthetics and creates a barrier to extend the

integrity of the wire almost indefinitely.

A well draining granular soil should be used as backfill behind the wall. Organic

topsoil should not be used. Clay soils or similar material should not be used as fill.

Compaction of the fill in a reinforced soil structure is desirable as it has a beneficial

influence on behavior and increases the efficiency of the structure. Proper compaction of

the backfill soil is required to minimize subsequent settlements and to ensure good soil-

reinforcement stress transfer. Each fill layer must be leveled after compaction to ensure

that all the reinforcements are in contact with the soil over their enfire bottom surface.

This may require some manual filling and tamping, particularly near the connection of

the reinforcements to the facing and in zones of difficult access.

The reinforcements should be laid flat on the compacted backfill and fixed to the

fie-strips protruding from the panels. All the reinforcements should be bolted to the tie-

strips, and corrosive protecfion should be applied to the bolts. Care should be taken to

ensure that the reinforcing strips are properly aligned after dumping the backfill.

A typical geotexfile-reinforced wall is constructed by placing horizontal layers of

geotextile in an earth fill (backfill), with the front edge of each geotextile layer wrapped

around the overiying layer of backfill to forni the wall face. The geotextile should be

unrolled in the direction specified in the design (machine or cross-machine direction).

Backfill is progressively dumped and spread toward the wall face. During backfilling

operations, no construction equipment should be pennitted to roll directly over the

64

Page 74: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

installed geotextile, and a minimum backfill thickness of 6 in. should be maintained

Reinforcement layers and backfill are placed altemately as the wall height increases.

Materials used in the construction of a geotextile-wrapped wall face may be asphalt,

gunite, structural material or soil. Placement of either asphalt or gunite is usually by

spraying in one or several coats directly onto the geotexfile-wrapped face.

Geogrid reinforcement should be laid directly on the surface of a layer of

compacted fill and covered with the next layer of fill. Care should be taken to control the

timing and rate of placing of fill material to ensure that grids are not damaged by

compaction of site vehicles. Vehicles should not travel directly on the exposed

reinforcement. Uniaxial grids-Tensar SR2 are generally adopted as the main

reinforcement. When positioning the grids, particular attenfion should be given to ensure

that they are placed in the correct direcfions. The reinforcement is generally laid

horizontally in continuous strips of the required length.

Proper drainage of retaining soil structures is essential. Accumulation of water in

the backfill soil could cause a reduction in the effective vertical stress between soil and

reinforcement that would lower the pullout capacity of the reinforcement, resulting in

wall movements. The drainage of each structure or condition should be considered

separately on its merits. Proper drainage construction will control the flow and volume of

water around the retaining wall, hi the case of walls where the backfill material is poorly

draining, it is necessary to collect and remove the water by providing drainage blanket at

the back and beneath the reinforced structure, as shown in Figures 4.1 though 4.9.

65

Page 75: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

CHAPTER V

CONCLUSIONS AND RECOMMENDATIONS

5.1 Conclusions

The tire rubber is a dense, durable and elastic material that does not undergo

natural decomposition easily. However, tires in baled fomi do not hold water; therefore,

pose no threat to public health due to mosquitoes. Because of the density of the bale, the

decreased surface area, and lack of air, the fire hazard is greatly reduced. Utilizing this

property, tire bales can be used in many applications whereas scrap tires pose a number

of environmental and monetary hazards, hicreasing disposal costs and state laws make

the option of baling whole tires an attractive and cost-effective altemative. The global

advantage to this method of scrap tire processing is the potential use of an unproductive

material that had to be dispose off to a landfill with some disposal costs. The project's

literature search reveals that the tire bales are a potential product for Civil Engineering

applications like erosion control, wetland reclamation, construction of dam, retaining

wall, etc. Each tire bale contains about 1 ton of waste material, which recycles waste

from environment. This also reduces concrete cost by approximately half, which

significantly reduces the cost and weight of the block. Mechanically stabilized earth and

gravity walls utilizing tire bales appear to be two practical solutions to the disposal

problem of scrap tires. Both of them appear to be cost-effective as well as environment-

fiiendly.

5.2 Recommendations

No test wall could be built because of lack of fiinds in the project. A test wall

needs to be built to complement the stability analysis. Both the mechanically stabilized

earth retaining wall and three types of gravity retaining wall need to be test-built before

their implementation. A frill-scale test should enable the constructability review,

economic analysis and environmental impact analysis to be done. Constructability review

addresses different issues such as material availability, speed of construction and other

aspects of construction. Economic analysis is necessary to find the actual cost of wall

66

Page 76: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

construction in terms of life cycle costs. It can be anticipated that tires in baled form and

encapsulated in concrete should pose no threat to environment. Still an environmental

impact analysis needs to be done before their public use. The Eco-Bloc units should have

to have some connection mechanisms to connect the reinforcements because connection

mechanisms at every half-foot of the block was assumed in the design.

67

Page 77: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

BIBLIOGRAPHY

1. Rubber Manufacturers Association homepage, http://wvm. rma.org.

2. Proximity and Ultimate Analysis of TDF Waste Recovery, Inc., Hazen Labs, 1997.

3- Efficiency Resuhs of Multi-Fuel Firinp ABB Combustion Engineering Services Inc., Waste Recovery Inc., 1993.

4. Ecological Building Systems homepage, http://www.comwerx.net/biz/ecobloc.

5. Avent, R, Richard and Alawaddy, Mohamed, Analysis and Design of Concrete Tire Containment Unit, Ecological Building Systems, April 1995.

6. Encore Systems, Inc. homepage, http://www.tirebaler.com.

7 Stork Twin City Testing Corporation, Project: MNDOT Test of Tire Bale, Project No:03066, Date: March 24, 2000.

8. 1997 Interim Revisions to the Standard Specifications for Highway Bridges, 16 ^ Edition, 1996, American Association of State Highway and Transportation Officials.

9. Reinforcement of Earth Slopes and Embankments, National Cooperative highway Research Program Report 290, Transportation Research Board, Washington, D.C., June 1987.

10. Design and Performance of Earth Retaining Structures, Geotechnical Special Publication No. 25, American Society of Civil Engineers, 1990.

11. Design Manual, Allan Block Retaining Wall Systems, http://www.allanblock.com.

12. Das, Braja M, Principles of Foundation Engineering, 3''* Edition, PWS Publishing Company, Boston, Massachusetts, 1995.

13. Bowles, Joseph E., Foundation Analysis and Design, 4'*' Edition, McGraw-Hill, Inc., 1988.

14. Day, Robert W.. Geotechnical and Foundation Engineering, McGraw-Hill, Inc., 1999.

15. Liu, Cheng and Evett, Jack B., Soils and Foundations, 4* Edition, Prentice Hall, Englewood Cliffs, New Jersey, 1990.

16. Jones, Colin J FP, Farth Reinforcement andjoijjtructures, Butterworths, Stoneham.

Massachusetts, 1985.

68

Page 78: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

17. Koemer, R.B., Design with Geosynthetics, 2"^ Edition, Prentice Hall, Englewood Cliffs, New Jersey, 1990.

18. Whitlow, R., Basic Soil Mechanics, 3"* Edition, Longman Scientific and Technical. Chicago, 1995.

19. Cemica, John N., Geotechnical Engineering: Foundation Design, John Wiley & Sons, Inc., New York, 1995.

20. Brown, Robert Wade, Practical Foundation Engineering Handbook, McGraw-Hill, New York, 1996.

69

Page 79: RETAINING WALLS: STABILITY ANALYSIS AND CONSTRUCTION

PERMISSION TO COPY

In presenting this thesis in partial ftilfillment of the requirements for a master's

degree at Texas Tech University or Texas Tech University Health Sciences Center, I

agree that the Library and my major department shall make it freely available for

research purposes. Permission to copy this thesis for scholarly purposes may be

granted by the Director of the Library or my major professor. It is understood that

any copying or publication of this thesis for financial gain shaU not be allowed

without my further written permission and that any user may be liable for copyright

infringement.

Agree (Permission is granted.)

Student Signature Date

Disagree (Permission is not granted.)

Date Student Signature