resettlement monitoring report · prepared by the water resources department, public works...
TRANSCRIPT
![Page 1: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/1.jpg)
Resettlement Monitoring Report
#11 Quarterly Progress Report For the period January to March 2019 Project Number: 44429-013 May 2019
IND: Climate Adaptation in Vennar Subbasin in
Cauvery Delta Project
Prepared by the Water Resources Department, Public Works Department, Government of Tamil
Nadu for the Government of India and the Asian Development Bank.
This resettlement monitoring report is a document of the borrower. The views expressed herein
do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may
be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation
of or reference to a particular territory or geographic area in this document, the Asian
Development Bank does not intend to make any judgments as to the legal or other status of any
territory or area.
![Page 2: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/2.jpg)
Loan 3394-IND: Climate Adaptation in Vennar Sub basin in Cauvery Delta Project
Implementation of Resettlement Plan Quarterly Progress Report
January - March 2019
PMU Trichy
Water Resources Organization PWD, Government of Tamil Nadu-India
![Page 3: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/3.jpg)
Abbreviations
ADB Asian Development Bank AEE Assistant Executive Engineer AP Affected Person AH Affected Household CoI Corridor of Impact (toe-to-toe of construction area) DP Displaced Persons DRO District Revenue Officer EE Executive Engineer GoTN Government of Tamil Nadu Ha Hectares NGO Non Governmental Organisation PAFs Project Affected Families PAP Project Affected Person PIU Project Implementation PMS Project Management Specialist PMAY Prime Minister Awas Yojana PMU Project Management Unit PSC Project Steering Committee PWD Public Works Department RDO Revenue Divisional Officer RoW Right of Way RP Resettlement Plan SDS Social Development Specialist SPS Safeguard Policy Statement Sq.ft Square Feet Sq.mt Square meter VAO Village Administrative Officer WRD Water Resources Department
![Page 4: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/4.jpg)
3
L-3394-IND –CAVSCD PROJECT
Quarterly Progress Report on Implementation of Resettlement Plan, Social
Safeguards and Construction monitoring
January to March 2019
1. Resettlement Sites Construction Activities
Since the last reporting period, the number of required houses has been reduced
from 1135 to 1128 total houses (from 41 sites to 40 sites). Initially the construction of 1135
housing units were planned in 41 sites and currently, all 6 PAFs opted house of Erayangudi
hamlet (Pandavaiyar, Nagapattinam District) have changed their options for cash. Hence
the construction of resettlement houses will be taking place in 40 sites. In addition, another
Project Affected Household, Mr. Karunanidhi at Umbalacheri village in Nagapattinam
district, had opted for house to be constructed in her Mother's Patta land however her
mother has since applied and been granted a house under the Prime Minister's housing
scheme. Hence, construction of one additional house was deducted from the CAVSCDP
total house requirement and the PAP will be provided cash in lieu of house. The payment
to the PAP will be disbursed by 15 June 2019 to enable the PAP complete the construction
of house expeditiously. As of March 2019, the number of houses to be constructed under
CAVSCDP is 1128 (Attachment 3).
Construction progress on the 1128 houses is as follows: 278 houses are at
basement level,98 at lintel level, 100 at roof level, finishing works are going on in 152 houses
and sub works are progressing in Pinna vasal (56 houses).There are 101 houses nearing
to basement level. Foundation works are going on in 61 houses and preliminary works are
in progress in 134 house sites.
Issue: The works has been held up at Adhangudi, Thiruvidaivasal,
Vengramperaiyur and Punavasal due to few problems created by the local nearby habitants
and the issue will be resolved with the assistance of Revenue Department after the
Parliamentary Election is over.
![Page 5: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/5.jpg)
4
PAPs of Kunniyur village did not agree to allot houses to the PAPs of neighboring
village in the site given in Kunniyur. The peace meetings were organized by the
Resettlement Officer among PAPs in the village and at the Office of Tahsildar with the help
of Tahsildar and Revenue Officials and AE of PWD Buildings and the dispute was solved
by detailed mutual discussions. PAPs have agreed to accommodate the PAPs of
neighboring villages.
2. Status in Grievance Redressal
A total of 493 valid petitions were received as of 31.03.2019 of which, 455 petitions
were verified and resolved. Among verified petitions 249 were considered in favour of
petitioners and 206 grievances were rejected because they were outside the project scope.
The remaining38 petitions are to be jointly verified in the field by project staff and the
resettlement NGO. Verification of 100% of the outstanding petitions will be completed in the
month of April 2019 (Attachment 4).
Issues: one hundred and five petitions have been received repeatedlyalong with
eleven general petitions. Expecting the favorable reply from GRC, people submit petitions
reatedly, though their petitions were not considered for any compensation or any other
grounds.
Disputes in enter upon resettlement sites will be resolved with the help of Officials
of Revenue Department PWD WRD and Buildings, Resettlement Officer and Social
Development Specialist.
3. Valuation of structures and cash payouts
Since the last reporting period, the number of affected households (AHs) opting for
cash reduced from 855 to 809; 53 structures were identified as located beyond the RoW
(abutting RoW) and will not be displaced for the project. Six AH also changed their
preference from a house to cash. And one has started constructing houses with PMAY .
Of 809 AHs, valuation for 472 structures is completed, 180 structures (belonging to 178
AHs) were compensated following valuation amount derived by the PWD-Buildings and as
![Page 6: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/6.jpg)
5
per the entitlement matrix of CAVSCDP. PWD-Buildings are in the process of valuing 294
structures as per the entitlement matrix. Valuations and compensation is expected to be
paid in May 2019. The process has been delayed due to the Election Code of Conduct. The
remaining 337 affected structures will be valued in the months of June and July 2019 with
help of PWD - Buildings, PWD-WRD and NGO personnel (Attachment 5).
Issues–During the aftermath of 'Gaja' cyclone many AHs are in dilemma and
frequently switch in choosing houses instead of cash, however, the list of AHs were
finalized. Few AHs have refused to sign the acknowledgement, as they request/demand
more compensation for the affected structures.
4. Resettlement Site Plans - Progress on planning implementation
Out of 40 sites allotted for resettling AHs, detailed Resettlement site plans have
been prepared for 6 resettlement sites where construction of houses are likely to be
completed in near future: Thittanimuttam, Pinnavasal - Mavur, Kankoduthavanitham,
Kadandethi, Korukkai, Thalaikadu.. For remaining 34 sites, draft resettlement site plans
were prepared with available data. Maps showing amenities and infrastructure available in
the vicinity are also under preparation. The final layout plans are required to complete
resettlement site plan; PWD Buildings are yet to provide these layouts. Resettlement site
plans for six sites are attached as annexure 1. Resettlement plan implementation schedule
is given in Attachment 2.
Revenue officials including Tahsildar of Kothanallur and Taluk Surveyor, Village
administrative Offcer (VAO) of Koothanallur Taluk were requested to demarcate the enter
upon lands given by the District Administration to enable the PWD buildings to initiate
construction activities. Requested Revenue Officials to prepare proposals to change lands
classification by the Tahsildars of respective Taluks for the enter upon lands.
Templates for House allotment letter to PAFs who have opted for houses as
compensation and Assignment of Permanent Houses to the PAFs were prepared by Mr.
Pranay Kumar, ADB, Social Safeguard Specialist, Mr. Vaithiyanathan, Resettlement
Officer, CAVSCDP, Dr. R. Rajkumar, Social Development Specialist, CAVSCDP. The
templates are attached as Annexure - II &III.
![Page 7: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/7.jpg)
6
5. Micro plans (compensation and livelihood plans) - Progress on planning
implementation
Among cash opted affected households, 178 PAPs (with 180 structures) were
compensated and for them Micro-plans were completed. Details of all information of AHs
such as -compensation details, bank information, Aadhaar card, copy of notice issued to
AHs mentioning the valuation amount, acknowledgement for receipt of compensation
amount and bank statement after credit of compensation - were collected and filed in
separate folders along with the copy of the completed baseline questionnaire. For the
remaining AHs who opted for cash, micro-plans will be prepared once compensation
payments are completed. Micro-plans for all the house opted AHs are being prepared,
details of AHs like bank, photo copies of bank passbook and other relevant copies of
documents have been collected from all 1128 AHs who opted for houses.
For the promotion of livelihoods of AHs to be resettled, semi-structured interview
schedule in Tamil language was approved by the EE, PMU (Annexure IV). The schedule
will be used to collect information regarding existing micro enterprises and skill-sets with
AHs, which could be promoted. Avenues for alternative livelihoods would also be planned
along with providing skill training to one eligible person in the vulnerable PAF, who lose
livelihoods due to the project as mentioned in the entitlement matrix of CAVSCDP.
. Stakeholder communications
The NGO is carrying out consultations with AHs continuously. The NGO staff are
also sharing information regarding resettlement timeline, compensation, valuation of
structures, getting acknowledgement for the compensation disbursed to the AHs opted for
cash. AHs were consulted in connection with relocation site identified and where the
construction would be initiated for the respective settlements. Individual AHs are being met
to collect bank and other details from all AHs for completing micro-plans and providing
compensation (as per the matrix).
![Page 8: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/8.jpg)
7
Interview schedule for collecting data on training needs assessment for livelihoods
promotion among AHs has been finalized and the same would be consulted with all AHs in
forthcoming months.
Engineers of PWD - Buildings were consulted for resolving disputes emanated by
the encroachers in the enter upon sites such as Adhangudi, Thiruvidaivasal,
Vengramperaiyur and Punavasal located in Thiruvarur District. Resettlement Officer and
Social Development Specialist, CAVSCDP have visited all the sites along with Engineers
of PWD - Buildings and discussed with the persons and groups objecting construction of
housing units in the enter upon sites and given the suggestions to the PWD Engineers as
well as the persons involved in opposing construction. Further efforts such as peace
meeting would be arranged with the help of Revenue Department, wherever it requires after
the Parliamentary and State Election processes are concluded.
6. Overall Civil Works Progress for the Project
In CW1 Harichandranathi,50% of works have been completed against the targeted
physical progress of 65%. An achievement of 42% has been made as financial achievement
against the targeted 65%.Scheduled time elapsed is 80%.Out of 104 structures,37
completed and 67 in progress. Embankment work is in progress for 17KM out of total length
on both sides 78KM.The encroached length of reaches have been arrived at 6km instead
of 13km on left bank and 11km instead of 17km on right bank and the total length of
encroached reaches arrived at 17 km instead of 30km after recent assessment.
In CW2 Adappar River, 43% of works have been completed against the targeted
physical progress of 80%. An achievement of 31% has been made as financial achievement
against the targeted 80%.Scheduled time elapsed is 80%. Out of 56 structures,32
completed and 24 in progress. Embankment work is in progress for 48.9KM out of total
length on both sides 85.6KM.Macadam inspection road to a length of 2.1km is in progress.
In CW3 Vellaiyar River, 43% of works have been completed against the targeted
physical progress of 100%. An achievement of 43% has been made as financial
achievement against the targeted 100%.Exrention of Time (E.O.T) has been given upto
June 2020.Scheduled time elapsed is 100%. Out of 74 structures,63 completed and 11 in
![Page 9: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/9.jpg)
8
progress. Embankment work is completed in 20KM and in progress for 22KM out of total
length on both sides 84KM
In CW4 Pandavaiyar River, 92% of works have been completed against the targeted
physicalprogress of 100%. An achievement of 91% has been made as financial
achievement against the targeted 100%.Exrention of Time (E.O.T) has been given upto
March 2020. Scheduled time elapsed is 100%. All the 69 structures have been completed.
Embankment work is completed in 68KM out of total length on both sides 76KM.The
remaining portion will be taken up after resettlement of PAPs. Road work is in progress in
8KM.
In CW5 Valavanar River, 80% of works have been completed against the targeted
physical progress of 62%. An achievement of 79% has been made as financial achievement
against the targeted 62%.Scheduled time elapsed is 80%. Out of 32 structures,27
completed and 5 in progress. Embankment work is completed in 29.7KM out of total length
on both sides 38.6KM
In CW6Vedharaniyam Canal,86% of works have been completed against the
targeted physical progress of 90%. An achievement of 80% has been made as financial
achievement against the targeted 90%.Scheduled time elapsed is 75%. All the 11 structures
have been completed. Embankment work is in progress to a length of 18.3KM.
In 13 Pumping Schemes,93% of works have been completed against the targeted
physicalprogress of 95%. An achievement of 87% has been made as financial achievement
against the targeted 95%.Scheduled time elapsed is 155% (E.O.T). All the mechanical and
electrical works have been completed and canal lining work is being taken up and
completed to a length of 0.51km out of total 3.27km
Issues:At present, all the forest trees have been removed. The TANGEDCO is being
continuously insisted for speedy removal of EB poles and transformers. The EB poles and
transformers located in the encroachment reaches are likely to be removed after
![Page 10: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/10.jpg)
9
resettlement of PAPs. The contractors are persuaded to complete the civil works in the
reaches free from any encumbrances.
7. Action Plan
Priority actions to be completed over the next reporting period (April – June 2019) include:
a. Valuation of at least 150 structures opted for cash compensation and preparation of
Microplan for the valued structures and remaining structures in the following months.
b. Distribution of compensation to cash opted 292 PAPs
c. Relocation notice will be issued to 292 PAPs
d.Resettlement Site Plans, Micro plans and PMU proceedings of approval of Resettlement
Site Plan for 18 sites
e. Allotment of House to 136 PAFs
f. PMU will obtain remaining resettlement site layouts from PWD - Buildings
Attachment 1: River wise Summary of AH,s - March 2019
River
Total No. Of PAPs Before reassessmen
t and exclusion of
PAPs
Structures beyond
RoW (abutting the RoW)
- Excluded
No of AHs after Re-
assessment and
excluding AHs
abutting RoW
AHs who have opted for alternate
House in Resettlement Site (as on March 2019)
Cash Opted AHs (as on
March
2019)
Pandavaiyar 376 19 357 202* 155
Vellaiyar 599 21 578 377 201
Harichandranadhi
719 8 711 341 370
Adappar 295 5 290 207 83
Valavanar 1 0 1 1 0
TOTAL 1990 53 1937 1128 809
![Page 11: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/11.jpg)
10
* 6 PAHs from Erayangudi hamlet have opted for cash instead of house opted initially and
one PAP has initiated construction on her own using Prime Minister Awas Yojana Scheme
at Umbalacheri in Adappar
![Page 12: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/12.jpg)
11
Attachment 2: Resettlement Plan Implementation Schedule
Project Activities
2019 2020
Up to
Jan
Feb Mar April May June July Aug Sept Oct Nov Dec Jan Feb
A. Cash Compensation – 809 Project Affected Households
Identification and verification of PAHs (inventory) 472 150 187
Issue ID card Compl
eted
Preparation of Micro Plan 472 337
PMU Approval of Micro plan 180 292 150 100 87
Proceeding issued to PAHs 180 120 172 150 100 87
PMU Disbursement of funds to PAHs 60 120 292 150 100 87
Relocation Notice Issued and Relocation 472 150 100 87
PMU/NGO to verify that land is encumbrance free – handed to
contractors
![Page 13: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/13.jpg)
12
B. Common Property Resources (CPR) – 67 CPR
Identification and verification 67
Public consultation
Assessment and valuation by PWD- Building 67
Micro Plan 67
Disbursement (Cash) 67
Relocation (If applicable)
PMU/NGO to verify that land is encumbrance free – handed to
contractors
C. Relocation and Resettlement -1128 Project Affected Households; 40 Relocation sites
Resettlement Preparations
Resettlement Site Layout Finalized 40
Update Records of PAHs * *
Preparation of Resettlement Site Plans 6 12 12 10
Preparation of Micro Plans 72 64 190 245 246 245 66
PMU proceedings of approval of Resettlement Site Plan 6 12 12 10
Allotment of House 136 190 245 246 245 66
Relocation- 41 sites
Site visit by PAHs 6 10 15 10
Notice of allotment 6 10 15 09
Allotment letter 6 10 15 09
![Page 14: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/14.jpg)
13
Shifting notice 6 10 15 09
Disbursement of resettlement allowances (shifting/transition) 6 10 15 09
Certification of NGO on readiness to move (Checklist) 6 10 24
Occupation of house 6 10 24
PMU/NGO to verify that land is encumbrance free – handed to
contractors
Rehabilitation - 41 sites
Formation of society/association (including registration) 6 10 24
Logistics support to PAHs: Residential certificate, change of
address, PDS etc.
6 10 24
Skill assessment
Identification of training institute(s)
Training
D. Monitoring & Evaluation
Monthly Resettlement Report 5th 5th 5th 5th 5th 5th 5th 5th 5th 5th
Quarterly Monitoring Report 5th 5th 5th 5th
Impact Evaluation
![Page 15: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/15.jpg)
14
Attachment 3: River wise Progress in House Construction
PUBLIC WORKS DEPARTMENT
PROGRESS REPORT FOR RESETTLEMENT HOUSES
Sl.No PROJECT PLACE Estimate
Cost NO OF
HOUSES
STAGE OF WORKS PROBABLE DATE OF
COMPLETION
Current Stage achieved On Schedule?
(Y/N)
Basement Level
Lintel Level
Roof Level
Finishing
1 2 3 5 6 7 8 9 10
1 Kadanthethi 2276.00 190
90 100 --------- 15.07.2019
2 Vadakkupanaiyur 228.10 28 28 --------- --------- --------- 31.07.2019
3 Thirukkuvalai 430.00 36 28 8 --------- --------- 31.07.2019
4 Maharajapuram 355.00 28 14 --------- --------- --------- 31.07.2019
5 Palakurichi 176.00 13 15.03.2019 15.04.2019 31.05.2019 31.08.2019 31.08.2019
Not Achieved Grade beam level
6 PR puram 271.00 24 8 15.04.2019 31.05.2019 31.08.2019 31.08.2019
8 blocks Grade beam level
7 Thulasapuram 141.00 10 15.03.2019 15.04.2019 31.05.2019 31.07.2019 31.07.2019
Not Achieved Grade beam level
8 Naluvedhapathy 101.00 10 15.03.2019 15.04.2019 31.05.2019 31.07.2019 31.07.2019
Not Achieved Grade beam level
9 Umbalachery 461.00 30(31) 15.03.2019 15.04.2019 31.05.2019 31.07.2019 31.08.2019 Not Achieved Grade beam level. 1 individual
house being constructed under PM scheme deleted from this scheme.
Now we construct 30 individual houses only.
Total 4439.10 369 (370)
1 Kankoduthavanitham 96.00 16 --------- --------- --------- 16 30.04.2019
2 Pinnavasal 325.00 56 --------- --------- ---------
Work Completed
15.04.2019 Sub works are in Progress.
3 Thittanimuttam-I 510.00 72 --------- --------- 72 31.05.2019
4 Korkkai 321.00 36 --------- --------- 36 15.03.2019
5 Korkkai 308.00 28 --------- 28 01.04.2019
6 Punavasal-I 88.00 8 15.03.2019 15.04.2019 31.05.2019 31.07.2019 31.07.2019 Not Achieved Grade beam level
7 Punnavasal-II 145.00 14 15.03.2019 15.04.2019 31.05.2019 31.07.2019 31.07.2019 Site Dispute
![Page 16: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/16.jpg)
15
8 Aathangudi 384.00 40 15.03.2019 15.04.2019 31.05.2019 31.08.2019 31.08.2019
Site Dispute
9 Aathangudi 269.00 28 15.03.2019 15.04.2019 31.05.2019 31.08.2019 31.08.2019
Site Dispute
10 Aathangudi 160.00 16 15.03.2019 15.04.2019 31.05.2019 31.07.2019 31.07.2019
Site Dispute
11 Athangudi 161.25 16 15.03.2019 15.04.2019 31.05.2019 31.07.2019 31.07.2019
Site Dispute
12 Arichandrapuram 65.00 6 6 15.04.2019 31.05.2019 31.07.2019 31.07.2019 Achieved Y
13 Vengramperiyar 235.00 24 24 15.04.2019 31.05.2019 31.08.2019 31.08.2019 Achieved Y
14 Vengramperiyar 51.00 4 15.03.2019 15.04.2019 31.05.2019 31.07.2019 31.07.2019 Site Dispute
15 Vengramperiyar 154.00 14 14 15.04.2019 31.05.2019 31.07.2019 31.07.2019 Achieved Y
16 Thittanimuttam-II 770.00 82 40 15.04.2019 31.05.2019 30.09.2019 30.09.2019 For other 42houses, Preliminary work is in progress.
17 Thiruvidaivasal 43.50 4 2 15.04.2019 31.05.2019 31.07.2019 31.07.2019 For other 2houses Foundation work is in progress.
18 Thiruvidaivasal 114.50 10 15.03.2019 15.04.2019 31.05.2019 31.07.2019 31.07.2019 Site Dispute
19 Thiruvidaivasal 158.00 16 15.03.2019 15.04.2019 31.05.2019 31.07.2019 31.07.2019 Site Dispute
20 Thiruvidaivasal 45.50 4 15.03.2019 15.04.2019 31.05.2019 31.07.2019 31.07.2019 Site Dispute
21 Radhanallur 340.00 31 8 15.04.2019 31.05.2019 31.08.2019 31.08.2019 For other 23houses Foundation work is in progress.
22 Kunniyur 290.00 26 15.03.2019 15.04.2019 31.05.2019 31.08.2019 31.08.2019 Preliminary work is in progress
23 Pallivarthi 43.00 4 15.03.2019 15.04.2019 31.05.2019 31.07.2019 31.07.2019 Preliminary work is in progress
24 Pallivarthi 112.00 8 15.03.2019 15.04.2019 31.05.2019 31.07.2019 31.07.2019 Preliminary work is in progress
25 Vikkirapandiam 453.00 40 15.03.2019 15.04.2019 31.05.2019 31.08.2019 31.08.2019 Preliminary work is in progress
26 Kokkaladi 267.00 20 20 15.04.2019 31.05.2019 31.08.2019 31.08.2019 Achieved Y
27 Puluthikudi 221.00 18 18 15.04.2019 31.05.2019 31.08.2019 31.08.2019 Achieved Y
28 Aalivalam 710.00 66 30 15.04.2019 31.05.2019 31.08.2019 31.08.2019 For other 36houses Foundation
work is in progress
29 Aalathur 335.00 30 30 15.04.2019 31.05.2019 31.08.2019 31.08.2019 Achieved Y
30 Velur - Manali 110.00 8 8 15.04.2019 31.05.2019 31.07.2019 31.07.2019 Achieved Y
31 Palayangudi 151.00 14 15.03.2019 15.04.2019 31.05.2019 31.07.2019 31.07.2019 Preliminary work is in progress
Total 7435.75 759
Net Total 11874.85 1128
![Page 17: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/17.jpg)
16
Attachment 4 Status of Grievance Redressal as on March2019
Sl.No River
No. of
Valid
Grievance
received
Verified
at field
Reply sent to APs
Pending
verification Decided in
favour of AP Rejected Total
1 Pandavaiyar 60 56 31 25 56 4
2 Vellaiyar 140 135 67 68 135 5
3 Harichandranathi 220 203 114 89 203 17
4 Adappar 73 61 37 24 61 12
5 Valavanar 0 0 0 0 0 0
TOTAL 493 455 249 206 455 38
Attachment 5-Status of Valuation of Cash optioned structures as onMarch 2019
River No. of cash optioned
structures
Valuation Completed
No of Structure Valuation reports
completed
Date to complete remaining
Compensation settled to AHs
No. of structures removed
Compensation to be completed (date)
Date for removal of structures
Pandavaiyar 155 55 0 0
Vellaiyar 201 71 20 1
Harichandranadhi 370 291 145 (+2)* 9
Adappar 83 55 13 0
TOTAL 809 472** 178
(180Structures)
10
* Two AHs own two structures
** 21 Structures beyond RoW, previously affected structures were 493
![Page 18: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/18.jpg)
17
Attachment 6: Civil Works Progress up to March 2019
Contract Scheduled completion
Encroachment km
Planned Physical Progress
%
Achieved Physical Progress
%
Planned Financial progress
%
Achieved Financial Progress
%
Time Elapsed %
1 Harichandranathi 03 Nov 2019 17 65 50 65 42 80
2 Adappar 03 Nov 2019 11.5 80 43 80 31 80
3 Vellaiyar* 26.02.2019 / 30.06.2020
( E.O.T) 17.4 100 43 100 43 100 (E.O.T)
4 Pandavaiyar 27.02.2019 / 31.03.2020
( E.O.T) 12.0 100 92 100 91 100 (E.O.T)
5 Valavanar Drain 25 Oct 2019 0 62 80 62 79 80
6 Vedaranyam canal
18 Jan 2020 0 90 86 90 80 75
Pumping (and supply channels)
31 March 2019 - 95 93 95 87 155 (E.O.T)
*1. Concrete blocks along channel prism for 2km not yet placed but many have been precast ready to install
![Page 19: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/19.jpg)
18
Contract Scheduled completio
n
Structures, No L&R Bunds, km Macadam Inspection Roads,
km
Total
Complete
In progres
s
Completion date
To Strengthe
n
Complete
Progress
Completion date Scop
e Progres
s
Completion date
1 Harichandranathi
27 Oct 2019
104 37 67 78.0 17 33.0
2 Adappar 27 Oct 2019
56 32 24 85.6 48.9 7.6 2.1
3 Vellaiyar* 8 Feb 2019 74 63 11 84.0*1 20 22 54.0
4 Pandavaiyar 10 Feb 2019
69 69 76.0 68 26.0 8
5 Valavanar Drain 27 Oct 2019
32 27 5 38.6 29.7 13.8
6 Vedaranyam canal
27 Oct 2019
11 11 18.3 18.3 0
Pumping (and supply channels)
22 March 2019
13 13
Lining work 3.270
0.510 2.76
![Page 20: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/20.jpg)
Annexure I
SITE 1. Profile of PAFs - Pinnavasal - Mavur (Survey No. 135)
Name of the Settlement to be relocated
No. of PAP
SC BC MBC ST Hindu Christian
Ogaiperaiyur 31 29 0 0 2 31 0
Attur 5 4 0 1 0 4 1
Kalimangalam 10 10 0 0 0 10 0
Kunniyur 3 0 3 0 0 3 0
Mavur 1 0 1 0 0 1 0
Neermangalam 2 1 1 0 0 2 0
Pinnavasal 1 1 0 0 0 1 0
Ramanujamanali 2 2 0 0 0 2 0
Vadakattalai 1 1 0 0 0 1 0
Total 56 48 5 1 2 55 1
PAFs required Ground Floor
Type of PAPs Numbers of PAPs
Differently abled 0
Senior citizen 7
Senior citizen / Women headed household
1
Total 08
![Page 21: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/21.jpg)
Annexure I
SITE 2 Profile of PAFs - Thittanimuttam (Survey No 39/1)
River
Name of the Settlement to be relocated
No. of PAP
SC BC Hindu Christian Muslim
Vellaiyar Pothagudi 72 5 67 5 67
TOTAL 72 5 67 5 67
PAFs required Ground Floor
Type of PAPs Numbers of PAPs
Differently abled 1
Senior citizen 10
Women headed household 4
Total 15
![Page 22: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/22.jpg)
Annexure I
SITE 3 Profile of PAFs Kankoduthavanitham (Survey No. 116/9)
River
Name of the Settlement to be relocated
No. of PAP
SC Hindu
Pandavaiyar Ilangarkudi 4 4 4
Pandavaiyar Kankoduthavanitham 11 11 11
Pandavaiyar Nadutheru 1 1 1
TOTAL 16 16 16
PAFs required Ground Floor
Type of PAPs Numbers of PAPs
Differently abled 1
Senior citizen 2
Women headed household 0 Total 3
![Page 23: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/23.jpg)
Annexure I
SITE-4 Social Profile of PAFs - Kadandethi (S.No. 110)
River
Name of the Settlement to be relocated
No. of PAP
SC BC MBC Hindu Muslim
Pandavaiyar Aatrangarai Street 1 1 1
Pandavaiyar Kadalakudi 2 2 2
Pandavaiyar Killukudi 9 9 9
Pandavaiyar Thirupanjanam 4 4 4
Pandavaiyar Thulasiyapuram 1 1 1
Harichandranadhi Alangudi 13 8 5 13
Harichandranadhi Amarakoonmoolai 1 1 1
Harichandranadhi Egarajapuram 19 19 19
Harichandranadhi Kadandethi 16 16 16
Harichandranadhi Karapidagai 1 1 1
Harichandranadhi Kothangudi 10 5 4 1 10
Harichandranadhi Manakudi 2 2 2
Harichandranadhi Mudaliyappankandi 1 1 1
Harichandranadhi Pazhzya Aatrangarai 7 5 2 7
Harichandranadhi Pirinjimoolai 40 5 5 30 40
Harichandranadhi Sadayankadu 4 2 2 4
Harichandranadhi Thalaignayiru 47 28 11 8 46 1
Harichandranadhi Thirumalam 3 2 1 3
Harichandranadhi Vettaikaraniruppu 9 6 3 9
Total 190 106 34 50 189 1
PAFs required Ground Floor
Type of PAPs Numbers of PAPs
Differently abled 2
Senior citizen 17 Women headed household 1
Total 20
![Page 24: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/24.jpg)
Annexure I
SITE - 5 Social Profile of PAFs - Korukkai
River
Name of the Settlement to be relocated
No. of PAP
SC BC MBC ST Hindu Christian Muslim
Adappar Dhesingarajapuram 1 1 1
Adappar Korukkai 1 1 1
Adappar Pamani 20 20 20
Adappar Salakadai 12 6 5 1 12
Adappar Thalaikadu 2 1 1 2
Total 36 29 6 1 36
PAFs required Ground Floor
Type of PAPs Numbers of PAPs
Differently abled 1
Senior citizen 5 ( 1 Expired)
Women headed household 0
Total 6
![Page 25: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/25.jpg)
Annexure I
SITE. 6 Social Profile of PAFs - Thalaikadu (Survey No. 487/21A)
River
Name of the Settlement to be relocated
No. of PAP
SC BC Hindu
Adappar Thalaikadu 28 25 3 28
Total 28 25 3 28
PAFs required Ground Floor
Type of PAPs Numbers of PAPs
Differently abled 0
Senior citizen 3
Women headed household 0
Total 3
![Page 26: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/26.jpg)
Annexure II
Government of Tamil Nadu
Permanent Residential/House Allotment Order for the Project affected families of
Climate Adaptation in Vennar Sub-Basin in Cauvery Delta Project (CAVSCDP)
Water Resources Department
1 Name
2 Name of Father / Husband
3 Residential Address before
resettlement
4 Aadhaar /Ration card Number
5 Block Number - House / Unit
Number allotted in the
resettlement site
6 Place
Tahsildar
Name of the Taluk
![Page 27: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/27.jpg)
Annexure II
Letter of Undertaking
1. Undertaking of Thiru ________ S/o or D/0_______________ residing in ________ Village
_________ Taluk, ______ District.
2. As per the G.O. Ms. 172 / (Miscellaneous)/ dated ____________ subject to the conditions
prescribed, I receive the allotment letter along with key of the allotted house on ___________.
I agree to vacate all the encroached area and the structure located in the land belong to the
PWD - WRD Right of Way (RoW) where I have resided earlier. I declare that, I shall not claim any
rights abiding all the conditions as per the above Government Order.
3. I take full charge of the house allotted to me by Government of Tamil Nadu under Climate
Adaptation in Vennar Sub-Basin in Cauvery Delta Project - CAVSCDP
4. I declare that all particulars / documents provided by me are true to the best of my knowledge.
I agree to abide the rules and regulations of the Government to take legal action, if any of the
documents/particulars found irrelevant.
Signature of the Allottee
Date:
Place:
![Page 28: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/28.jpg)
Annexure III
Order of the Assignment of House site Patta along with Permanent House
The house of Thiru___________ S/o or W/o ________________ residing in ________
Village_________ Taluk, ______ District is affected by the Climate Adaptation in Vennar Sub-Basin in
Cauvery Delta Project - (CAVSCDP), as per the entitlement matrix, his/her family is eligible for getting a
permanent house and assignment of Pattaland underResettlement Plan Implementation. The house
allotted to him bearing the number ---------, the four boundaries are _____ in North _____ East, ______
South ______ West. The _______ Sq. Mts of permanent house and the _______ Hectares of undivided
share of total land allocated for four houses in one block having Ground and first floor is allotted as per
Revenue Standing Order under Article 21 of part (ii) in Para No. 7
Allotted Unit / House No
Block Number Survey Number Area of the House site allotted (in Hectares)
Allotment Criteria - Order of Allotment
1) Thepatta/allotment letter will be given jointly in the name of Wife and Husband. The land and house
transferred to any of the spouse or Head of the family will not be permitted legally
2) The allottee should not sell the house, lease out or rent out the allotted house for 10 years, .
Violation will result in cancellation of the allotment
3) The respective departments having the right to assess and tax the property and land allotted and
subject to change time to time by the Government
4) The assignee should not entertain any business, commercial activity or enterprises in any part of
the house or land allotted
5) If the assigneedo not occupy the allotted house on the date of deadline i.e 60 days from the
allotment for taking possession, the allotment will be deemed to be cancelled.
6) The assignee has to vacate all the encroached area and the structure located in the land belong to
the PWD - WRD Right of Way (RoW) where he/she as resided earlier. He/She has no claim any
rights and would not encroach again.
7) The assignee is permitted to mortgage the house for self employmentloan and agricultural loan
from Cooperative Society or Nationalized Banks.
8) No allottee can, under any circumstances, use more than one tenement. If any allottee due to
misrepresentation or otherwise is found to be in possession of more than one house and that if
s/he does not report the fact of such possession, the allotment will be cancelled.
9) Whenever the particulars / documents provided by the assignee are found incorrect or fraudulent,
stringent action will be taken by the Tahsildar / Appropriate Authority throughdetailed enquiry. The
assignment of land along with house will be cancelled without any compensation even for any other
modifications done in the allotted house, if found guilty.
It is certified that I ___________ , Tahsildar, ________ Taluk, is signed an authorized officer on behalf of
the Governor of Tamil Nadu and by the Order of Honb'le Governor of Tamil Nadu on _________ date,
________, Month, _____ Year.
![Page 29: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/29.jpg)
Annexure III
Note:
1. House allotment letter is issued with house site assignment order
2. The following category of vulnerable PAFs, such as families with differently abled person, families
with senior citizen, women headed families, will be allotted Ground Floor tenements through lottery
method in G+1 tenements. If the numbers of such vulnerable PAFs exceed the number of available
ground floor units, preference in allotment will be given to families with differently abled person,
families with senior citizen, women headed families respectively.
3. Families with blood relations assigned to a resettlement site and who would like to reside adjacent
to each other, may submit their request to the District Administration within one week of receiving
the notice of allotment. Such request may be considered subject to availability of units. Such
allotments, if made, will be through lottery method.
Tahsildar
______ Taluk, _______ District
![Page 30: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/30.jpg)
1
jkpH;ehL muR
fhBthp bly;lhtpy; cs;s btz;zhu; cgtoepyj;ij jl;g btg;g epiy
khWghLfSf;Bfw;g Bkk;gLj;Jk; jpl;lk; - CAVSCDP
kPsFoBaw;w jpl;lj;jpd; fPH; Bjh;t[ bra;ag;gl;l jFjp tha;e;j FLk;g
cWg;gpdh;fSf;F thH;thjhu jpwd; Bkk;ghl;L gapw;rp BjitfSf;fhd tpdh gl;oay;
I.FLk;g tptuk;: Bjjp:
1. Mw;wpd; bgau;
2. Mf;fpukpg;g[ brhj;jpd; milahs vz; rhjp:
3. nlJ / tyJ kjk;:
4. FoapUg;gpd; bgau;
5. fpuhk Cuhl;rp
6. tl;lk;
7. khtl;lk;
8. FLk;g jiythpd; bgau;
9. miyBgrp vz;
10. FLk;gj;jpy; 18 taJ Kjy; 45 taJ tiu vj;jid cWg;gpdh;fs; cs;shu;?
11. FLk;g cWg;gpdh;fs; gw;wpa tptuk;:
t.vz;.
11.1 FLk;gcWg;gpdhpd;bgau;
11.2 FLk;gjiytUlkhdcwt[ Kiw
11.3ghypdk;
11.4taJ
11.5fy;tpjFjp
11.6jpUkzepiy
11.7Mz;LtUkhdk;
![Page 31: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/31.jpg)
2
12. eypt[w;w FLk;g tifapy; ve;jg; gphpit rhu;e;jth;
1. bgz;jiyik 2. khw;W jpuhdhsp 3. 60 taJk; mjw;FBkYk;
4. kw;wtu;fs; - tpthpf;ft[k;
II.thH;thjhu jpwd; Bkk;ghL gw;wpa tptuA;fs;
2. cA;fs; gFjpapy; eilbgw;W tUk; Kf;fpa bjhHpy;fs; vd;dbd;d?
2.1 jw;BghJ eilbgw;W tUk; bjhHpy;fs; }yk; Bghjpa mst[ Btiy tha;g;g[fs;
fpilf;fpd;wjh ? Mk; / ny;iy
2.2 Mk; vdpy; nj;jifa bjhHpy;fs; }yk; Bghjpa mst[ tUkhdk; fpilf;fpd;wjh?
1. Mk; / 2. ny;iy
2.3 gapw;rpapd; fhyk; vd;d?
2.4 gapw;rpapd; epiwtpy; VBjDk; rhd;wpjH; tHA;fg;gl;ljh?
2.5 nj;jifa gapw;rpapy; cA;fs; bjhHpy; jpwid Bkk;gLj;jf; Toa tifapy;
mike;Js;sjh?
2.6 nj;jifa bjhHpy;fis ePA;fs; bjhlA;Ftjw;Fk;, bjhlh;e;J bra;at[k; tA;fpapd;
}yk; fld; trjp fpilj;jjh?
2.7 bjhlA;fpa bjhHpiy bjhlh;e;J bra;J tUfpwPh;fsh?
2.8 ePA;fs; Vw;fdBt bgw;w gapw;rpapd; mog;gilapy; bjhlh; gapw;rp VBjDk;
Bjitg;gLfpd;wjh? Mk; / ny;iy
2.9 Mk; vdpy; ve;j tifahd bjhHpy; gapw;rpfs; Bjit?
2.10 bjhHpw;gapw;rp bgw 10 Kjy; 30 ehl;fs; tiu jhA;fs; Beuk; bryt[ bra;a
Koakh?
![Page 32: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/32.jpg)
3
2.11 nytr gapw;rpfs; jpUth\h; / ehfg;gl;odjjpy; ele;jhy; jhA;fs; te;J bry;y
Koakh?
2.12 ePA;fs; Ra cjtp FGf;fspy; cWg;gpduhf nUe;Js;sPu;fs;? my;yJ ng;bghGJk;
nUf;fpd;wPh;fs;?
2.13 ePA;fs; trpf;Fk; nlj;jpy; vd;d tifahd bjhHpy; bra;jhy; yhgfukhf
nUf;Fk;?
2.14 Vw;fdBt ePA;fs; bra;J te;j cw;gj;jp bghUspy; kjpg;g[f; Tl;ly; bra;jhy;
yhgfukhf nUf;Fk; vd fUJfpd;wPh;fsh?
2.15 Vw;fdBt jhA;fs; bra;J tUk; bjhHpypy; cw;gj;jp bghUl;fSf;fhd
re;ijg;gLj;j cjtp Bjitg;gLfpd;wjh?
2.16 jhA;fs; bjhHpy; bjhlA;f / elj;j tA;fpf;fld; bgw;W jpUk;g brYj;jp
tpl;lh;fsh?
2.17 jdp egh; bjhHpy; / FGj; bjhHpy;, ntw;wpy; ve;j bjhHpy; bra;jhy; rpwg;ghf
nUf;Fk; vd fUJfpwhh;fs;?
2.18 g[jpjhf kPs; FoBaWk; nlj;jpy; mA;Fs;stu;fSld; Ra cjtp FGf;fshf
nize;J bjhHpy; bjhlA;f Mu;tkhf nUf;fpd;wPh;fsh?
2.19 nisqh;fSf;F vd;d tifahd bjhHpy;fs; Vw;wjhf mika[k;?
1. 2. 3.
2.20 Bkw;Twpa bjhHpy;fSf;F vd;d tifahd gapw;rpfs; Bjit?
![Page 33: Resettlement Monitoring Report · Prepared by the Water Resources Department, Public Works Department, Government of Tamil Nadu for the Government of India and the Asian Development](https://reader033.vdocuments.mx/reader033/viewer/2022042112/5e8d74908bcbf936c20e9f9b/html5/thumbnails/33.jpg)
4
III.fhy;eilfs; gw;wpa tptuA;fs;
3. vd;d tifahd fhy;eil itj;Js;sPfs;? vj;jid itj;Js;sPf;fs;?
t.vz; fhy;eilfs; vz;zpf;if1 khL2 fhis khL3 ML4 brk;kwp ML5 BfhHp
3.1 fhy;eilfs; %yk; khjk; vt;tst[ tUkhdk; fpilf;fpwJ?
3.2 fhy;eilfis ve;j epyj;jpy; Bka;r;rYf;fhf tpLfpwPh;fs;? fhy;eilfis
Bka;f;Fk; FLk;g cWg;gpdh;fs; ahh;?
3.3 fhy;eilfis vA;F fl;o itf;fpwPh;fs;?
3.4 fhy;eilfis fl;Ltjw;F vt;tst[ nlk; Bjitg;gLk;?