report of facilities condition assessment

84
Capitol View Branch Library 5001 Central Avenue, SE Washington, DC 20019 October 21, 2014 Report of Facilities Condition Assessment DRAFT

Upload: others

Post on 28-Feb-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Capitol View Branch Library

5001 Central Avenue, SE Washington, DC 20019

October 21, 2014

Report of Facilities Condition Assessment

DRAFT

2318 MILL ROAD SUITE 1410 ALEXANDRIA VA 22314 PH 703.684.6550 FX 703.684.8590

October 21, 2014 

 

Smoot Construction DC 

5335 Wisconsin Avenue, NW 

Washington, DC 20015    

 

Attention:  Mr. Stu Dziura     Senior Vice President   

 

 Reference:  Proposal for Facilities Condition Assessment   

    Capitol View Branch Library 

    5001 Central Avenue, SE 

    Washington, DC 

    Faithful+Gould Project Number 100036495 

    

Dear Mr. Dziura: 

  

Faithful+Gould, Inc. has completed a report of our Facilities Condition Assessment of the Capitol View 

Branch  Library  located  at  5001  Central  Avenue  in  Southeast Washington  DC  (“the  Property”).  This 

report provides a summary of the project information known to us at the time of the study, the scope 

of work  performed,  an  evaluation  of  the  visually  apparent  condition  of  the  Property,  a  forecast  of 

anticipated  capital  expenditures  required over  the next  ten‐years,  and  a  cost benefit  analysis which 

considers retention versus replacement of the library building and related site systems.  

 

This report was completed in general accordance with the ASTM E2018‐08 Standard Guide for Property 

Condition Assessments: Baseline Property Condition Assessment Process. Please  review  the attached 

report and advise us of any questions or comments. We will  issue a  final report within  three days of 

receipt of comments.   

 

Very Truly Yours, 

                                

 

 

Imran I. Ishaq, MRICS                                            D. Jonathan Bailey, CEM, CCM                                        

Lead Facility Assessor                                  Scope & Technical Compliance Review 

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20015     

Report of Facilities Condition Assessment    F+G Project No. 100036495 

TABLE OF CONTENTS 

INTRODUCTION 

1.0        EXECUTIVE SUMMARY .......................................................................................................... 1 

2.0        OBJECTIVES & SCOPE OF SERVICES ....................................................................................... 9 

 

FACILITY CONDITION ASSESSMENT 

 

SITE FEATURES .............................................................................................................................................. 15 

3.0   SITE SYSTEMS  ................................................................................................................... 15 

BUILDING ELEMENTS  ................................................................................................................................... 18 

4.0  STRUCTURAL SYSTEMS ..................................................................................................... 18 

5.0  ROOFING COMPONENTS .................................................................................................. 20 

6.0  BUILDING EXTERIORS ........................................................................................................ 23 

BUILDING SYSTEMS ...................................................................................................................................... 27 

7.0   MECHANICAL SYSTEMS ..................................................................................................... 27 

8.0   ELECTRICAL SYSTEMS ........................................................................................................ 32 

9.0    PLUMBING SYSTEMS ......................................................................................................... 36 

10.0         FIRE & LIFE SAFETY ........................................................................................................... 38 

11.0         CONVEYANCE SYSTEMS .................................................................................................... 40 

BUILDING INTERIORS & FINISHES ................................................................................................................ 43 

12.0   INTERIOR FINISHES ........................................................................................................... 43 

AMERICANS WITH DISABILITY ACT .............................................................................................................. 45 

13.0   ACCESSIBILITY ................................................................................................................... 45 

Appendices  

Appendix A  ‐  Photographs Appendix B  ‐  Expenditure Forecast by Year Appendix C   ‐  Resumes of Assessment Team Appendix D   ‐  ROM Estimate 

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 1 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

1.0  EXECUTIVE SUMMARY 

 

1.1  Introduction 

 

The Capitol View Library (“the Property”) consists of a two‐story (with basement and a subbasement boiler 

room)  reinforced  concrete‐framed detached  library building  located on an approximately 21,890  square 

foot (0.5 acre) site at 5001 Central Avenue in Southeast Washington DC. The Property contains a reported 

gross floor area of 25,272 square feet, a reported net floor area of 22,240 square feet and was designed by 

Clark  T.  Harmon  in  1962  for  construction  in  1963  and  occupancy  in  early  1964.  The  building  is  of 

Construction  Type  2B  (Un‐Protected  Non‐Combustible)  and  arranged  for  Use  Group  A‐3  (Assembly  ‐ 

Library).  Table 1‐1 and Plan 1‐1 below provides a summary of the building.  

 

        Table 1‐1 – Subject Building   

 

Gross Square Foot 

Floor Area (SF) 

Net Square Foot Floor 

Area (SF) Levels  Construction Date 

25,272  22,240   

Sub Basement, 

Basement, Ground and 

First Floors 

1962 ‐ 1963 

                                                      Plan 1‐1 – Aerial View of Property 

                 

 

 

 

 

 

 

 

 

 

   North 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 2 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

1.2  Scope of Services 

 

On  September  8,  2014,  Mr.  Benjamin  Dutton,  MRICS,  MCIOB  and  Mr.  Imran  Ishaq,  MRICS  of 

Faithful+Gould, Inc. visited the Property to complete a comprehensive facilities condition assessment. The 

objectives of the assessment were as listed on the following page.  

1. Identify the condition of the Property and the timing and cost of expenditures required over the 

next 10 years 

2. Complete  a  cost  benefit  analysis  of  retaining  the  building  and  completing  the  recommended 

capital  expenditures  (hereafter  referred  to  as  “retention”)  or  demolishing  the  building  and 

building a replacement library (hereafter referred to as “demolition / reconstruction”) 

 

In order to meet the above objectives, we evaluated the current condition of the building and utilities and 

projected  future  repair  and  replacement  needs  required  over  the  next  10  years  (study  period)  and 

developed opinions of cost for demolition and reconstruction.  

 

1.3  Cost Benefit Analysis  

 

1.3.1  Cost of Retention & Required Expenditures  

 

1.3.1.1  Expenditures 

 

Over the ten years considered by this report the building will require a series of capital expenditures. These 

relate to expenditures required to address various building defects resulting from poor original design and 

(primarily) systems reaching the end of their effective useful life. The cost table included within Appendix B 

of  this  report  and  the  narrative  included within  the  following  report  sections  provide  details  of  these 

expenditures.  The  listing  below  and  Table  1‐2  on  the  following  pages  provide  a  summary  of  these 

expenditures. All numbers are shown in current (2015) dollar values.  

 

Near‐Term Expenditures (2015 – 2017) 

Resurfacing (mill and overlay) of the asphalt pavements 

Replacement of failed site concrete at building entrance 

Replacement of the built‐up roofing system 

Replacement of lintels and installation of through wall flashings to the external wall system 

Replacement of failed external precast concrete panels 

Replacement of anodized aluminum windows  

Recoating of external precast concrete panels and lintels 

Cleaning of external brickwork 

Replacement of chiller 

Replacement of cooling tower 

Replacement of the boiler  

Replacement of air handling units 

Replacement of electrical switchgear   Mid‐Term Expenditures (2018 – 2021) 

Crack filling, seal coating and re‐striping of asphalt pavements 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 3 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

Replacement of perimeter chain link fence 

Replacement of carpet tiles throughout   Late‐Term Expenditures (2022 – 2024) 

Recoating of external precast concrete panels and lintels 

Cleaning of external brickwork 

 

Table 1‐2 – Summary of Total Expenditures over 10‐year Study Period  

 

Year  Expenditures 

Immediate  $0 

2015  $0 

2016  $756,121 

2017   $0 

2018  $29,025 

2019  $74,805 

2020  $0 

2021  $5,847 

2022  $0 

2023  $0 

2024  $0 

TOTAL  $865,798 

 

1.3.1.2  Facility Condition Index  

 

The Facility Condition Index (FCI or FCNI) provides a relative measure for comparing one building (or group 

of buildings) to another. This index is a calculation, derived by dividing the total accumulated project cost 

for  the 10‐year window covered by  this  report by  the  total Component Replacement Value  (CRV) of  the 

building.  The  index  is  intended  to  show  the  current  and  future  conditions  of  the  building  if  no  capital 

investment is made. Tables 1‐3 provide a summary of the FCI / FCNI condition ranges for the Property.  

 

Table 1‐3 – Facility Condition Index 

 

Accumulated Deferred Maintenance 

Current Replacement Value (CRV) 

Facility Condition Index (FCI) 

$865,798  $12,177,498  0.071 / Fair 

david.saulter
Rectangle
david.saulter
Typewritten Text
david.saulter
Typewritten Text
david.saulter
Typewritten Text
david.saulter
Typewritten Text
david.saulter
Typewritten Text
david.saulter
Rectangle
david.saulter
Typewritten Text
Section Redacted
david.saulter
Typewritten Text
Section Redacted

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 4 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

1.3.2  Cost of Demolition / Reconstruction  

 

In the demolition / reconstruction scenario considered by this report, the Property will be redeveloped for 

the purposes of a branch  library configured for the services of the Washington DC Public Library system, 

with an infrastructure that supports the changing technology of library sciences and the needs of an inner 

city community. We have assumed that this redevelopment will consist of the activities  listed below and 

included within Table 1‐4. 

 

Closing of the existing  library and transfer of all programs to neighboring  libraries  (most  likely a 

combination  of  Anacostia  Library,  Deanwood  Library,  Dorothy  I.  Height/Benning  Library  and 

Francis A. Gregory  Library). Under  our  demolition  /  reconstruction  scenario, we  have  included 

allowances for moving and storage (within a DC DGS warehouse) of existing equipment and books 

and  for  surplus disposal of  furnishings. We have not  included  allowances  for  the  creation of  a 

temporary library facility.  

 

Environmental  remediation of  the  Property.  Pending  the  results of  studies being  completed  in 

conjunction with  this  report, we  have  assumed  that  the  building  contains  asbestos  containing 

insulation around enclosed piping and lead based paint. We have included a lump sum allowance 

for remediation of these items prior to demolition.  

 

Following clearing of the building of all items and environmental contaminants, we have included 

an allowance for complete demolition of the building and clearing of the entire site.   

Retention  of  a  design  team  and  a  General  Contractor  to  design  and  construct  a  replacement 

library. We have assumed that the replacement  library will consist of a two story structure with 

basement  containing  approximately  25,000  gross  square  feet.  The  design  will  incorporate 

sustainable low energy design solutions, and program space for digital reference center, computer 

lab, a 200‐seat community room and cultural center, meeting rooms and seminar rooms, and will 

contain modern furniture, fixtures and equipment.   

Table 1‐4 – Summary of Demolition / Reconstruction Costs 

 

Activity  Cost 

Move & Store Books. Dispose of Furnishings  $30,000 

Environmental Remediation Allowance  $100,000 

Demolish Existing Building & Clear Site  $190,000 

Construct Replacement Building (Exc. FF&E)  $11,267,498 

FF&E  $590,000 

TOTAL  $12,177,498 

 

david.saulter
Rectangle
david.saulter
Typewritten Text
Section Redacted

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 5 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

1.3.3  Cost Comparison 

 

Table 1‐5 on  the  following page provides a comparison between  the cost of  retention and demolition  / 

reconstruction.  

Table 1‐5 – Cost Comparison (Retention Vs. Demolition / Reconstruction) 

 

Year  Retention  Demolition Reconstruction 

Immediate  $0  $0 

2015  $0  $0 

2016  $756,121  $12,177,498 

2017   $0  $0 

2018  $29,025  $0 

2019  $74,805  $0 

2020  $0  $0 

2021  $5,847  $0 

2022  $0  $0 

2023  $0  $0 

2024  $0  $0 

TOTAL  $865,798  $12,177,498 

 

1.3.4  Cost Benefit Analysis of Retention and Demolition / Reconstruction Options  

 

All real properties require maintenance and implementation of capital expenditure projects to prolong the 

life of  systems and  replace  items  that have  reached  the end of  their effective useful  life. The goal  is  to 

maintain  the  tangible  value of  the underlying asset. The  cost of expenditures outlined within Table 1‐2 

represent the  level of capital expenditure necessary to maintain the underlying value of the 1962  library 

facility.  The type of cost expenditures outlined do not address the more salient question of the functional 

adequacy  of  space  configuration,  infrastructure,  energy  efficiency,  security,  handicapped  accessibility, 

image  and  branding,  parking,  or  community  engagement  needed  to meet  the  needs  of  a  2015  library 

structure. Identifying the feasibility and expense of remodeling the existing structure to meet the needs of 

a  contemporary  library  is  outside  the  goal  of  this  report.  However,  by  comparative  analysis  of 

contemporary library projects completed or under construction within the past 5 years we can discern the 

projected  probable  cost  for  the  demolition  /  reconstruction  of  a new  building  on  the  current  site  that 

designed  to meet  contemporary  library  standards.  Similarly,  the  value  of  induced  benefit  from  energy 

savings  through new  construction  can be  identified  for  the 10‐year  study period.   Assuming design and 

david.saulter
Rectangle
david.saulter
Typewritten Text
Section Redacted

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 6 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

construction  is  completed  in 3 years  the  remaining 7 years  in  the  study period  could experience a 15% 

reduction in energy costs.   

 

The long term benefits of retaining or replacing the existing structure extends beyond the capital expense 

of  the  physical  property  presented  in  this  report.   We  recommend  conducting  further  evaluation  and 

analysis of outcomes measurement in public libraries such as the research and grant studies conducted by 

Dr. Glen Holt, executive director, Saint Louis Public Library  and Prof. Donald Elliott, professor of economics 

and business, Southern Illinois University at Edwardsville, Illinois. 

 

1.4  System & Condition Summaries  

 

Site  features at  the property  include asphalt paved parking areas, cast‐in‐place concrete  sidewalks, curbs 

and  gutters,  raised  planters,  chain  link  perimeter  fencing,  landscaping  and  storm  water  management 

features.  Site  systems  are  generally  in  fair  but worn  condition with  some  localized  defects  noted.  The 

asphalt pavements require near‐term resurfacing and mid‐term seal coating, failed concrete adjacent to the 

front entrance should be replaced near‐term and the perimeter fence should be replaced mid‐term.    

 

The building comprises of a reinforced concrete superstructure (columns, concrete joists, concrete beams) 

supporting  a  concrete  roof  deck  and  a  non‐load  bearing  exterior  wall  system.    The  superstructure  is 

supported  on  isolated  and  continuous  cast  in  place  concrete  footings  varying  in  size  and  depth.  The 

structural  systems  appeared  to  be  in  good  condition  with  no  observed  evidence  of  settlement, 

deterioration, or other distress noted. Assuming correction of defective conditions at the exterior systems, 

we do not anticipate a requirement to complete significant expenditures relative to the structural systems.  

 

The building is enclosed horizontally with a low‐slope roof covered with an asphaltic based built‐up roofing 

(BUR)  system.  The  roof  was  installed  in  1991  and  is  in  fair  to  poor  condition  with  large  blisters, 

missing/detached flashings, active  leaks and failure of the surface coating noted. We have recommended 

budgeting for near‐term replacement of the roof system. 

 

The exterior wall system consists of brickwork cladding with steel lintels, precast concrete cladding panels, 

anodized  aluminum  framed  windows  containing  single‐glazed  glazing  units  and  (at  the  ground  floor) 

painted steel security grills, glazed front entrance and sealants at control  joints and the perimeter of the 

openings. The exterior wall systems are in fair to poor condition. Of significant concern was the condition 

of the precast concrete panels and corroded steel lintels. Several concrete panels have spalled/cracked and 

near‐term  replacement of a number of panels  is  recommended. The corroding steel  lintels  (caused by a 

lack of through‐wall flashing)  is causing separation within the mortar applied at  joints  in a  linear pattern 

above the windows at each level. The defective mortar will permit ongoing water entry which may lead to 

further  corrosion, water  ingress,  damp  and  the  development  of mold  growth. We  have  recommended 

budgeting for the near‐term installation of through wall flashing, and replacement of failed lintels, mortar, 

bricks and concrete cladding panels.  

 

The  majority  of  the  single  glazed,  anodized  aluminum  windows  date  from  the  original  construction, 

however,  some  units  have  been  replaced  to  the  rear  of  the  reception  desk.  The windows  are  in  fair 

condition due to their age/general wear and tear and are no  longer considered to be energy efficient.  In 

some  instances  the windows are warped and permit air  infiltration, which will be affecting heating and 

david.saulter
Rectangle

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 7 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

cooling  performances.  We  have  recommended  near‐term  replacement  of  the  existing  windows  with 

anodized aluminum, double glazed units.   

 

Hot water for heating purposes for is generated by one natural gas fired cast iron boiler manufactured by 

Smith in 1991 with a rated capacity of approximately 1,137‐MBH.  Heating hot water is circulated through 

the two pipe distribution system via two circulation pumps operated in a duty and standby configuration. 

Chilled water  for  cooling  generated  by  one water  cooled  chilled manufactured  by  Carrier with  a  rated 

capacity of approximately 50‐tons.  Condenser water for the chiller is generated by one single cell cooling 

tower located at the southeast corner of the site.  The cooling tower was manufacture by Baltimore Air Coil 

in 1991 with an approximate capacity of 50‐tons.  Condenser water is distributed via one distribution pump 

with a rated capacity of 170‐gpm.  Conditioned air is provided by single‐ and multi‐zone air‐handling units 

equipped with  a  two  pipe  chilled water/hot water  coil.    Conditioned  air  from  the  air‐handling  units  is 

ducted throughout each  floor to the respective zones and/or areas served. Supplemental cooling  for the 

elevator equipment room  is provided by a split system air conditioning unit with the remote condensing 

unit  being mounted  on  the  east  side  of  the  building.    The  split  system  air  conditioning  unit  has  an 

approximate  cooling  capacity  of  1.5‐tons  and  was  manufactured  by  Carrier.  The  HVAC  systems  are 

controlled via a direct digital control system.   

 

The gas‐fired boiler appeared  to be  in  fair condition. Replacement should be anticipated near‐term. The 

chiller appeared to be  in fair condition but due to  its age it will  likely become maintenance  intensive and 

less efficient as it continues to age.  Based on the age of the chiller and advances in chiller efficiencies, we 

recommend budgeting  for  its  replacement near‐term.   The cooling  tower was  in a  similar condition and 

should be replaced in conjunction with the chiller.  The air handling units appeared to be in fair condition 

with sheet metal and interior deterioration noted. Replacement of the air handling units is recommended 

near‐term.  

 

Secondary  electrical  service  is  supplied  at  208‐volts,  3‐phase  from  a  PEPCO  pole mounted  transformer 

located along 50th Street SE. Conductors from the transformer are then routed to a 1,500‐amp main C/T 

cabinet  in the basement mechanical room.   Service from the main switchboard  is then routed to various 

breaker panels,  fuse boxes, and  fused disconnects  to  serve  the electrical  loads  throughout  the building. 

Lighting  throughout  the  building  is  typically  2’  x  4’  recessed  fluorescent  fixtures  with  T8  lamps  and 

electronic  ballasts.    Emergency  lighting  is  provided  by  fixtures  with  battery  backup  units  and  the 

emergency power circuit.  Security systems within the building consist of various security cameras located 

throughout the building which are monitored by a digital video recorder and an electronic theft detection 

system  located at the main  library entrance.   The electrical  installations appeared to be  in  fair condition 

with most of the equipment and components dating to the 1960’s.  Based on the age and type of some of 

the electrical  components  it  is  likely  that  these  components will  reach  the end of  their  service  life and 

become  increasingly unreliable  throughout  the  study period.   We  recommend budgeting  for a electrical 

system upgrade near‐term to ensure the electrical systems continue to provide reliable service. 

 

Plumbing systems  include the cast  iron and galvanized sanitary and storm sewer piping, copper domestic 

hot and  cold water piping,  sewer ejector pumps,  sump pumps, and natural gas domestic water heater.  

Plumbing systems appeared to be fair condition with no major issues note or reported to us.  The domestic 

water heater was  in  fair  to good condition and should not require replacement within  the study period.  

The sump and sewer ejector pumps appeared to be in fair condition and will likely be repaired or replaced 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 8 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

on  an  as needed basis during  routine maintenance  activities  as  an operational  expense.    The domestic 

water and sanitary sewer piping appeared to be  in fair condition. Replacement of the sanitary sewer and 

domestic water distribution piping should be considered for replacement should the library every undergo 

an extensive renovation. 

Fire and  life safety elements observed audible  fire alarm and detection system  (fire alarm / annunciator 

panels, duct detectors, strobes, pull stations, emergency and exit  lights), handheld fire extinguishers, and 

fire‐rated means of egress. The fire and life safety elements were in generally good condition and installed 

in  accordance with  the  code  in  effect  at  the  time  of  construction  and  last  renovation.    The  fire  alarm 

control panel was replaced in 2010 and should remain serviceable throughout the study period. 

 

Conveying systems within the building consist of one hydraulic elevator with a capacity of 2,500‐lbs and a 

speed of 150  feet per minute.   The elevator components appeared  to be  in good condition having been 

subject  to  large‐scale  modernization  in  2007.  Future  modernization  or  capital  replacement  is  not 

anticipated within the study period.  

 

Interior  finishes  consisted of  carpet  tiles, 2’  x  2’  suspended  acoustical  ceiling  tiles  and painted  gypsum 

board  or  concrete masonry  unit walls.  Finishes were  in  generally  good  condition with  the majority  of 

finishes (flooring, walls, ceiling tiles) replaced  in 2006. We have recommended budgeting for mid to  late‐

term replacement of carpet tiles.  

 

The building generally complied with the 2010 edition of the Americans with Disability Act.  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 9 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

2.0      OBJECTIVES & SCOPE OF SERVICES 

 

2.1  Report Objectives 

 

The objective of this report  is to produce an advanced facilities assessment and capital planning process, 

utilizing all current data from a complete condition assessment of the Property, to result  in a strong and 

well‐developed  plan  to  support  strategic  capital  investment,  identify  and  reduce  risk  and  through  the 

completion  of  a  cost  benefit  recommend  either  retention  or  demolition/reconstruction  of  the  existing 

Property  .  In short – the objective  is to assess the condition of all  included building and site systems and 

develop a prioritized  forecast of anticipated capital expenditures over  the 10 year period between 2015 

and 2024  and  to determine  the best build  alternative  for  the Property.   This will  inform  the  long  term 

investment  plan  for  the  building  by  developing  an  array  of  projects,  architectural  and 

mechanical/electrical/plumbing  systems  that  can  be  inputted  into  a  planning model  from which  sound 

management decisions can be made to best utilize funding resources. Specific objectives of this study are 

listed below.  

 

Identification and documentation of the present condition and risks of the building  

Recommendation of corrections for all deficiencies  

Provision of cost estimates for such corrections 

Cost of demolition and reconstruction  

Forecasting of  future  facility  renewal costs based on documented methodology, of  the  facilities and 

equipment in the building 

Obtaining a Facilities Condition Index (FCI) to illustrate the relative condition of the subject building 

 

In order  to meet  these objectives we completed a visual evaluation of  installed systems at  the property 

(i.e.  site  systems,  structural,  roofing,  exterior, mechanical,  electrical,  plumbing,  fire  protection  and  life 

safety, and interiors) and produced this report of Facilities Condition Assessment. This report represents a 

comprehensive evaluation of the building systems and major components including criteria for assessment, 

expected  useful  life,  remaining  useful  life,  year  to  be  replaced,  project  priority  and  plan  type,  existing 

condition, estimated replacement date, and estimated replacement cost standards.  

 

2.2  Key Issues  

 

Faithful+Gould  was  requested  to  complete  a  Facilities  Condition  Assessment  of  the  site  and  site 

improvements.  The  key  issues  to  be  addressed  by  the  Facilities  Condition  Assessment  include  the 

following: 

 

1. Identification  of  the  visually  apparent  condition,  installation  date,  remaining  useful  life  and 

deficiencies at  the Property  to  include all  systems and elements detailed  in  the  following  “Strategy 

Employed to Meet the Key Issues” section 

2. Through the completion of a cost benefit analysis determine the best build alternative  

3. Recommendations and opinions of cost for capital projects over a 10 year period from and  including 

2015. Projects are to be categorized using two priority tools and one set of deficiency categories 

4. The replacement value of the component or system 

5. Proposed projects and timelines for when the system/component should replaced  

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 10 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

6. Proposed execution strategies for the identified projects that minimizes cost and disruption 

 

2.3  Strategy Employed to Meet Key Issues 

 

The  strategy  employed  to meet  the  key  issues  detailed  above  (i.e.  our  scope  of  services)  consisted  of 

performing a visual assessment of the  interior, exterior and site components of the subject building. The 

scope of  services was  governed by  Faithful+Gould’s proposal  for  Facility Condition Assessment  services 

dated July 14, 2014 

 

The primary purpose of the Facilities Condition Assessment was to identify visually apparent deficiencies in 

the  building  and  site.  The  evaluation  included  site  visits  to  observe  the  building  and  site  systems, 

interviewing  building  management  and  maintenance  personnel,  and  reviewing  available  maintenance 

systems,  design  and  construction  documents  and  plans.  This  Facilities  Condition  Assessment  has  been 

conducted  in  general  accordance  with  industry  standards  and  the  American  Society  for  Testing  and 

Materials  (ASTM)  Standard  E  2018‐08  Standard  Guide  for  Property  Condition  Assessment:  Baseline 

Property Condition Assessment Process.  

 

We performed a visual non‐destructive assessment of  the  interior, exterior and  site  components of  the 

building, including the following major components and systems: 

 

Site Systems. We visually observed the site systems for the removal of storm water and evidence of 

poor  drainage  and  /  or  erosion  potential. We  also  reviewed  (where  applicable)  the  condition  of 

pavements, site concrete, retaining walls, fencing, landscaping, site grading, and storm water drainage 

features.  

 

Structural  System. We  observed  the  structures  for  visible  signs  of  distress  and  have  reported  our 

findings. We  also  reviewed  available  structural  drawings  for  information  regarding  the  design  load 

criteria of the existing structures and the building codes to which the structures were designed. We did 

not complete a seismic probable‐maximum‐loss (PML) evaluation of the Property. 

 

Roof System. We visually evaluated the condition of accessible roof systems, accessories, and details. 

In addition, where applicable we discussed existing roof warranties.  

 

Building Exterior Elements. We visually observed the exterior wall system, window and door systems 

for visible evidence of deficiencies, continuity of seals, and other types of distress and have reported 

our findings. We reviewed available flashing and connection details for drainage design and observed 

the  condition  and  placement  of  expansion  joints.  Our  visual  observations  were  based  on  those 

conditions  that  can  be  observed  from  ground  level,  roof  level  terraces  and  through  the  use  of 

binoculars. 

 

Mechanical / HVAC, Electrical, Plumbing (MEP) Systems. We observed the age and condition of the 

MEP and related building systems and have commented on their condition and visible deficiencies.  

 

Fire Protection  and  Life  Safety. We observed  the  age  and  condition of  the  fire protection  and  life 

safety elements and have commented on  their condition and any visible deficiencies. The elements 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 11 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

surveyed  included  structural  fire  protection,  means  of  egress,  fire  suppression  systems,  and  fire 

detection and alarm systems.  

Conveyance. We visually observed the conveyance systems and have reported their general condition.  

Interior  Finishes. We  visually  observed  the  interior  areas  of  the  Property  and  have  reported  their 

general condition.  

Disabled Access. We visually identified barriers to disabled access based upon the 2010 edition of the 

Americans with Disability Act.  

 

The scope of services under which the Facilities Condition Assessment was completed was visual in nature 

and not intended to be destructive to the Property to gain access to hidden conditions. We did not perform 

any destructive  testing or uncover or expose any  system members. We have documented  the  type and 

extent of visually apparent defects in the systems in order to perform the condition assessment. 

 

The scope of services under which the Facilities Condition Assessment was completed includes only those 

items specifically  indicated. The evaluation does not  include any environmental services such as (without 

limitation) sampling, testing, or evaluation of asbestos, lead‐based paint, lead‐in‐water, indoor air quality, 

PCB’s, radon, mold, or any other potentially hazard materials, air‐borne toxins or issues not outlined in the 

previous  scope  of  services.  In  addition,  the  assessment  does  not  include  identification  of  underground 

soils, identification or quantification of underground contaminants. 

 

2.4  Personnel 

 

On September 8, 2014, Mr. Benjamin Dutton and Mr. Imran Ishaq from Faithful+Gould visited the Property 

to observe and document  the  condition of  the building and  site  components. During  the  course of our 

assessment, Faithful+Gould interviewed the personnel detailed in Table 2‐1. 

 

Table 2‐1 – DC Public Library Personnel Interviewed by Faithful+Gould Team 

 

Name  Title  Tenure at Property 

Darrell Gray   Building Engineer  Since 1990 

 

2.5  Document Review 

 

In  addition  to  interviewing  Management  representatives  listed  in  Table  2‐2,  we  also  reviewed 

documentation as listed below: 

 

Air  conditioning  program  prepared  by  Lutz,  Schiebla  &  Fulford  –  Engineers  dated  9/21/1967. 

Drawing sheets 11‐23‐67 (ME4, ME5).  

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 12 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

Project Drawings  prepared  by  Clark  T Harmon  of  the Government  of  the District  of  Columbia 

dated 12/27/1962. Architectural: A‐1 to A‐12, Structural: S‐1 to S‐4, Mechanical: E‐1 to E‐3. P‐1. 

M‐1 to M‐2. 

 

Roof replacement drawings prepared by Government of the District of Columbia (Department of 

Public Works). Drawing sheet 612101 – CS‐1. Drawing dated May 1, 1991.  

 

2.6  Assessment Methodology 

 

Each member  of  the  assessment  team  has  a minimum  of  10  years  of  experience  completing  similar 

projects. We used this experience coupled with our review of the requested scope of services, objectives 

and discussions with the parties  listed  in Table 2‐1 to develop a specific assessment methodology for DC 

Public Library (DCPL). This methodology focused upon risk mitigation and standard capital renewal.  

 

Our  methodology  commenced  with  reviewing  available  drawings,  specifications  and  other  relevant 

information for each system. Following review of documentation, we met with DCPL and reported subject 

matter  experts  for  each  system.  Subject matter  experts  typically  consisted  of  facility  or management 

personnel with experience operating or managing the systems to be assessed. Information reported by the 

subject matter experts was considered to be  for  information purposes only, with all  information verified 

(where possible) by our assessment team.  

 

Following review of documents and interview with subject matter experts, we evaluated each system. Our 

evaluation  consisted  of  a  visual  non‐destructive  assessment  completed  in  general  accordance with  the 

ASTM 2018‐08  Standard Guide  for Property Condition Assessments. A  copy of  this  standard  is  included 

within the appendix of this report section. For each system and component of that system we noted the 

visually apparent condition noted for system / component specific modes of failure, noted the age of the 

system / component and made a determination of required repairs / replacements and the timing of those 

actions. We also quantified any system / components  that we  judged would require replacement within 

the 10 year study period. Upon completion of the physical evaluation, we generated this report.  

 

2.7  Development of Estimated Useful Life / Remaining Useful Life 

 

A fundamental part of any capital planning process is the development of the Estimated Useful Life (EUL) 

and  Remaining  Useful  Life  (RUL)  for  each  piece  of  equipment.  EUL  considers  the  life  of  a  system  or 

component of that system (i.e. a roof may have a 15 year life). RUL considers what is the remaining life of 

that system (i.e. a roof may have a RUL of 10 years – therefore replacement will occur in 10 years).  

 

We developed our EUL and RUL based upon  the determined condition of a system, our experience with 

that specific  installation (i.e. roof membranes  installed by a manufacturer such as Carlyle may  last  longer 

than a comparable  system  installed by Firestone) and  the  impact of  that  system’s  failure.   For  instance, 

batteries for an Uninterruptable Power Supply system may typically last 5 to 7 years. However, as they may 

be a critical part of the electrical supply to a process machine, we would consider a RUL of 4 years under 

the assumption that one replaces prior to failure and prior to when the likelihood of failure increases to an 

unacceptable risk level.  

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 13 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

The EUL and RUL can be further modified by the quality / type of existing installation and the quality / type 

of the replacement installation. For instance, if we noted that a system that typically achieves a 10 year life 

was  not  installed  correctly  and  as  a  result  will  require  replacement  at  a  7  year  life,  we  will  show 

replacement after 7 years. However, assuming that a replacement system is installed correctly, it will last 

10 years, we then show a cycle 1 replacement after 7 years, and a cycle 2 replacement 10 years after the 

cycle 1 replacement.  

 

2.8  Opinion of Cost 

 

Our opinions of cost included within this report are based upon our experience with similar buildings and 

systems, industry‐standard cost data, local cost data and the knowledge of Faithful+Gould’s in‐house cost 

estimators.  We  have  considered  that  any  expenditure  below  $1,000  will  be  funded  as  a  Routine 

Maintenance (“operational”) expense and therefore will not be included within this study. However, where 

similar projects with values  less than $1,000 are anticipated, we have grouped these projects to create a 

combined capital project with a value above the cost threshold. We have followed a four phase approach 

when developing our opinions of cost:  

 

1. Identify project scope and complexities during assessment phase 

2. Identify DCPL specific factors that may increase project cost above typical market conditions (i.e. 

work completed in off hours, procurement, union, insurance requirements, prevailing wage etc.) 

3. Utilize the District of Columbia prevailing wage  

4. Included for General Conditions and Architectural / Engineering fees (where applicable) 

5. Utilize our Cost Estimators to develop opinions of cost considering various  factors  including 1, 2 

and 3 above and as detailed below 

 

It should be understood that costs provided are for planning purposes only. Actual project costs may vary 

significantly to those projected based upon  inflationary factors, weather and time of season, unforeseen 

economic circumstances and market trends, contractor schedules, unusual owner requirements, and other 

factors beyond our control. 

 

2.9  Terminology & Limitations 

 

This report and the attached expenditure forecast generally identify the Expected Useful Life (EUL) and the 

Remaining Useful Life (RUL) of observed systems and components. EUL is projected based upon industry‐

standard guidelines and our experience with similar systems. RUL is projected based upon our assessment 

of  age,  condition  and maintenance  /  repair history. The  timing of  the projected expenditures  and  their 

associated  costs  represent our opinion  considering  the  aforementioned  factors. Alternative methods of 

managing  the  existing  equipment or  systems may be  feasible over  the 10  year  study period. However, 

these alternative methods will depend upon actual management practices,  financing  requirements, and 

the ability of the engineering staff to perform some of the repairs in‐house. Alternative scenarios that have 

not been presented to Faithful+Gould have not been considered within this report.  

 

This  report  has  been  presented  based  upon  our  on‐site  observations,  information  provided  to  us, 

discussion with building management and maintenance staff, our review of available documentation (see 

scope  of  services  and  document  review  section)  and  our  experience  with  similar  systems.  If  any 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 14 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

information becomes available that is not consistent with the observations or conclusions expressed within 

this report, we request that this  information be  immediately  forwarded to us. The evaluation of existing 

structures  requires  that  certain assumptions be made  regarding existing conditions. This evaluation was 

based upon our visual non‐destructive evaluation of accessible conditions of  the Property. Furthermore, 

this  evaluation was  limited  in  time  on‐site,  fee,  and  scope  and was  not  based  upon  a  comprehensive 

engineering evaluation.        

 

 

 

 

 

 

         

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 15 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

SITE FEATURES 

 

3.0           SITE SYSTEMS  

 

Site features at the Property include an asphalt paved parking lot, cast‐in‐place concrete sidewalks and curb 

and  gutter,  a  raised  planter,  chain  link  perimeter  fencing,  landscaping  and  storm  water  management 

features (reference Photographs 14, 15 & 17 in Appendix A).   

 

3.1          Description 

 

The  Property  contains  a  continuous  asphalt‐paved  parking  lot  located  to  the  east  and  south 

elevations.  The pavement  is  accessed  via  entrances  / exits off Central Avenue  Southeast  to  the 

North and 50th Street Southeast to the West.  The lot contains 19 spaces plus one additional space 

assigned  for  bus  use.  Standard  spaces  measured  19’  x  9’.  Site  development  plans  were  not 

reviewed, however  the pavement has an asphaltic surface course and  it  is assumed  that  there  is 

also  an  asphaltic  base,  aggregate  base  and  compacted  subgrade.  Plan  3‐1  provides  a  graphical 

overview of the site areas considered by this report. 

 Plan 3‐1 – Aerial View of Property 

                  

Cast‐in‐place  concrete  sidewalks provide pedestrian  access  to  the building  from Central Avenue 

Southeast.  Sidewalks  are  laid  in  approximately  5’  x  4’  sections  and  laid  to  drain  to  the  City 

maintained stormwater systems. The parking areas are accented with cast‐in‐place concrete curb 

and gutter sections. All concrete was assumed to be cast over compacted subgrade.  

 

  The extents of the parking lot are enclosed with dwarf height (approximately 2’ 6”) concrete wall. A 

6’ tall steel chain link fence is mounted upon the perimeter concrete dwarf wall. There is a pair of 

gates to the entrance of 50th Street Southeast which were  locked at the time of the assessment. 

Tables 3‐1 and 3‐2 on the following page summaries the site areas. 

 

   North 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 16 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

Table 3‐1 – Parking Spaces Counted  

 

Standard  Bus Parking  ADA  Drop Off  TOTAL 

19  1  0  0  20 

 

Table 3‐2 – Site Areas Measured   

 

Asphalt Pavement  Sidewalks  Curb & Gutter 

1,063 SY   736 SF   32 LF 

   

There are  landscaping features present to the the front of the Property. These consist of a raised 

planter  area  contained  within  a  brick  enclosure,  flagpole,  cycle  racks  and  grass  lawn  area. 

Stormwater  is  collected  within  brick  culverts  which  expel  to  the  City  maintained  stormwater 

management system.  

3.2         Condition  

The asphalt parking areas are generally in fair condition with considerable areas of longitudinal and 

transverse cracks through the pavement wearing surface, unsealed construction joints and general 

failure of surface markings noted. In addition, a section (approximately 26’ x 16’) of the pavement 

has  settled  following  the  removal  of  an  underground  oil  tank.  This  has  caused  ponding  of  the 

surface water.  In  addition,  vegetation  growth  has  also  penetrated  through  the wearing  course 

which is causing further deterioration in various locations.  

 

To extend the life of the pavements, we recommend the implementation of a structured approach 

to on‐going maintenance and repair. This should commence with resurfacing the asphalt pavement 

wearing course in the near term. We recommend that the pavement wearing surface (the top 1” to 

1 ½”) be edge milled and overlaid. Replacement of the asphalt pavement wearing course should be 

followed by the mid‐term application of a two‐coat asphaltic based seal coat and the re‐application 

of  surface markings  to prolong  the  life expectancy of  the  surface. This will  reduce water  ingress 

(and resulting deterioration) of the pavement sub‐base and subgrade, increase the flexibility of the 

pavement wearing surface (allowing it to accommodate movement) and maintain the appearance 

of the pavements until the end of the study period.  

 

  Sidewalks were in generally good condition. However, the sidewalks adjacent to the front entrance 

are  in poor condition, with numerous areas of  longitudinal cracks and surface spalls noted. Based 

upon the public location of the sidewalks and the potential that tripping hazards will be caused by 

the cracked concrete; we recommend budgeting for near‐term replacement of the failed sidewalk 

panels.  We have also included an allowance for mid‐ and late‐term replacement of sidewalk panels 

in anticipation of future failed sections.  

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 17 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

  Concrete  curb  and  gutter  sections,  landscaping  and  storm  water  management  features  are 

considered to be fair condition. We do not anticipate budgeting for capital repair or replacement of 

these elements within this study period.  

 

  The chain‐link fence  is  in  fair condition with areas of surface corrosion. The posts and panels are 

still  in a  functioning  condition and have not  yet  reached  the end of  their effective  life.  In  some 

isolated areas, vegetation has started  to grow  through  the  fence  from  the neighboring property.  

We have allowed for mid‐replacement of the chain link fence.  

  

3.3         Projected Capital Expenditures  

  Required: 

 

1. We recommend budgeting for edge milling and overlay (resurfacing) of the pavements in 2016. 

Our opinion of cost for this work is $23,386 ($22 per square yard). This includes an allowance 

for localized full depth replacement of the pavement (at areas of alligator cracking) and for the 

installation of a geotextile fabric to help retard reflective cracking.  

 

2. We recommend budgeting for the application of a two‐coat asphaltic‐based seal coating over 

the asphaltic pavement, the re‐application of surface markings and filling of surface cracks. Our 

opinion of cost for this work is $5,847 ($5.50 per square yard) in 2021.  

 

3. We recommend budgeting for replacement of failed sidewalk panels contained at the front of 

the building. Our opinion of cost for this work is $2,940 ($15 per square foot) in 2016. 

 

4. We recommend budgeting for mid‐term replacement of the chain link fencing. Our opinion of 

cost for this work is $9,025 ($25.00 per linear foot) in 2018.  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

david.saulter
Rectangle
david.saulter
Rectangle
david.saulter
Rectangle
david.saulter
Rectangle

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 18 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

BUILDING ELEMENTS 

 

4.0  STRUCTURAL SYSTEMS 

 

The description of  the respective structural systems  is based upon our review of available drawings  (see 

document  review  section),  and  our  observation  of  exposed  portions  of  the  building  structure  at  the 

mechanical  room,  at  exposed  columns,  wall  and  floor  assemblies,  and  at  support  rooms  (reference 

Photograph 46 in Appendix A). 

 

4.1        Description 

 

The structural system consists of a  reinforced concrete superstructure  (columns, concrete  joists 

and concrete beams) supporting the concrete floor and roof decks. The building is supported on a 

combination of isolated and continuous cast in place footings varying in size and depth.  

 

Concrete Strength 

 

We were not provided with details in regard to concrete strength.  

 

Foundations 

 

Supporting columns were to be founded on  isolated and continuous cast  in place footings which 

vary in size. The footings are recorded as having high strength reinforcing steel with intermediate 

grade ties and stirrups. Major walls are supported on continuous footings.  

 

Lowest Floor Level 

 

The ground  floor  slabs  comprises of  reinforced concrete with a vapor barrier and a  compacted 

granular fill.  

 

Superstructure 

 

The structural system consists of a  reinforced concrete superstructure  (columns, concrete  joists 

and concrete beams) supporting the concrete floor and roof decks. The concrete beam schedule 

indicates that the beams vary between 8” and 16” deep and 10” and 48” wide.  

 

Internal Walls  

 

Interior walls consist of 5/8” type X gypsum wallboard supported on either steel studs or 8” thick 

concrete masonry units. 

 

 

 

 

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 19 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

Ceilings 

 

Common  area  ceiling  systems  consist  of  a  combination  of  painted  gypsum wallboard  coffered 

ceilings  supported on a  suspended  ceiling grid, 2’  x 2’  suspended acoustical  ceiling  tiles placed 

within a prefinished steel grid or the exposed underside of the roof structure. 

 

Exterior Walls  

 

The  external walls  are non‐load bearing  and primarily  consist of  clay brick  veneer  and precast 

concrete panels between  the brickwork at horizontal and vertical  interfaces. The exterior walls 

also  incorporate embedded steel  lintels which are  installed as  through wall continuous  flashing. 

We  could  not  ascertain  the  size  of  the  lintels  from  the  drawings  and  no  opening  up  of  the 

structure was undertaken during the assessment.  

 

Roof Structure 

 

The  roof  structure  consists of a 5½”  thick  reinforced concrete  slab. The  canopy  roof also has a 

concrete roof deck which is 4” thick and also has an additional 3” of concrete on top of the roof 

deck underneath the built up roof.   

 

4.2   Condition 

 

The structural systems for the building appeared to be  in good condition and should not require 

repair or replacement within the study period.  However, we noted stepped cracks at the exterior 

wall  system which  serves  the  single  level  storage building  located  at  the  rear of  the  Property. 

Based  upon  the  minimal  size  of  the  building,  we  have  anticipated  that  repair  or  localized 

reconstruction of the building can be funded as an operational expense.  

 

4.3         Projected Capital Expenditures 

 

Required: 

 

No Expenditures are anticipated. 

             

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 20 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

5.0  ROOFING COMPONENTS 

 

The entire building  is enclosed horizontally by a  low‐slope roof covered with an asphalt built‐up 

roofing (BUR) system installed in 1991 (reference Photographs 4 through 8 in Appendix A).  

5.1  Description 

 

The  building  is  enclosed  by  a  two  level  (main  and  canopy)  low‐slope  roof.  Each  roof  level  is 

covered with  an  internally‐drained  asphaltic based  four‐ply built‐up  roofing  system  installed  in 

1991.  The  sectional  detail  of  the  roof  consists  of  the  structural  concrete  deck,  a  base  sheet, 

tapered  rigid  insulation,  the  four‐ply  asphaltic  membrane  and  a  field‐applied  solar  reflective 

acrylic coating. Plan 5‐1 below indicates roof areas covered by the built‐up system. 

 

Plan 5‐1 – Built‐Up Roofing Areas 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The roof was enclosed by 3" to 8” tall parapet walls which consisted of an extension of the main 

wall  system  to  the outer  face and an extension of  the  field membrane  to  the  inner  face. Base 

flashings consist of a two‐ply modified bitumen membrane covered with the acrylic field coating 

and applied over 4” wood cant strips. Cap flashings consist of standing seam steel caps attached 

to 2” x 4” and 2” x 8” wood nailing blocks. Counter flashing consisted of stainless steel units. The 

built‐up roofing areas are internally drained through 5” internal drainage outlets. Table 5‐1 on the 

following page provides a summary of the built‐up roofing areas.  

 

 

 

 

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 21 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

Table 5‐1 ‐ Summary of Roof Construction (BUR) 

 

Roof Component  Built‐Up Roof 

Installation Date  1991 (Coating Applied 2009) 

Roof Area  

(SF / total / approx.) 9,351 

Application/ Membrane  4‐Ply Built‐Up Roofing System 

Manufacturer / Model  Unknown 

Surface  Acrylic Coating  

Deck Type  Cast in Place Concrete 

Insulation  Rigid Tapered Insulation 

Cover Board  None 

Drainage  5” Roof Drains 

Overflow Scuppers  4" External  

Base Flashings  Modified Bitumen 

Cap Flashings  Steel Caps 

Perimeter Enclosure  Variable Height Parapet Wall 

Warranty (Manufacturer)  None 

Warranty (Contractor)  None 

 

5.2   Condition 

 

The built‐up  roofing system was  in generally  fair  to poor condition.  Installed  in 1991, we noted 

numerous areas of blistering and general softness across the roof field (both indicative of trapped 

moisture within the roof system), areas of poorly completed patch repairs, at the surface coating 

areas of debonding and delamination, open and split base  flashings, and areas of water  ingress 

through  the  roof  system.  Parapet  walls  were  also  generally  in  poor  condition.  A  number  of 

sections  have  been  damaged  and  aluminum  parapet  capping  sections  are  missing,  exposing 

underlying wood blocking which are being  subjected  to water  saturation.  If not  rectified,  these 

elements will deteriorate  further,  resulting  in aesthetic and possibly structural  failure. Costs  for 

the replacement of parapet covering have been included within the roof replacement cost. Based 

upon  the  extent  of  deterioration  noted,  we  have  recommended  budgeting  for  near‐term 

replacement of the roof. 

 

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 22 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

5.3   Projected Capital Expenditures 

  Required: 

 

1. We recommend budgeting for replacement of the built‐up roofing system in 2016. Our opinion 

of cost is $130,914 ($14 per square foot). This opinion of cost assumes removal of the existing 

roof  (including all  flashings)  to  the  structural deck and  the  installation of a 60‐mil  single‐ply 

thermoplastic polyolefin roof membrane over tapered insulation.   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

david.saulter
Rectangle

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 23 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

6.0  BUILDING EXTERIORS 

 

The exterior wall systems consist of an anchored brick veneer, steel lintels, architectural precast concrete 

cladding panels, anodized aluminum windows with painted metal security grills (ground floor only), glazed 

storefront  entrance  doors  and  sealants  at  control  joints  and  the  perimeter  of  the  openings  (reference 

Photographs 1, 2, 9 – 13, 18 and 19 in Appendix A).  

 

6.1  Description 

 

  Brick Veneer 

 

The  primary  exterior  wall  system  consists  of  a  clay  brick  veneer.  The  veneer  is  provided  at 

approximately 50%  to 60% of each elevation with  the sectional detail consisting of  the 4”  to 5” 

clay  face  brick  laid  in  stretching  bond,  supported  on  a  steel  shelf  angle  and  placed  against  a 

concrete masonry unit back‐up.  

 

  Precast Concrete Cladding Panels 

   

Architectural precast  concrete  cladding panels make up approximately 25% of  the wall area of 

each elevation. The concrete masonry panels have a painted surface, are typically 3” to 4” thick 

and form infill panels between the brickwork and the window units. The precast concrete panels 

typically measure approximately 2’6” x 4’6” at each section with flush joints between each panel. 

The brickwork is dowelled to the vertical concrete sections adjacent to each section of brickwork. 

The  concrete masonry  panels  are  separated  from  the  brickwork  by  vertical  concrete  sections 

which protrude from the outer face of the elevation walls by approximately 4”. The precast panels 

are interconnected using steel masonry ties.   

Doors and Windows 

 

The front entranceway includes glazed storefront doors consisting of anodized aluminum framing 

members with single pane glazing. Doors are operable by the use of proximity sensors with level 

access  is afforded  from street  level. The current doors are not original and have been replaced. 

Painted steel panel doors are located as secondary access / egress points at the sides and rear of 

the building.  

 

Windows at each elevation consist of operable, single glazed anodized aluminum framed hopper 

style units. Glazing units are ¼” thick. The windows are fitted to the ground and first floors and the 

ground  floor windows  are  fitted with  security  grills  for  added  security. With  the  exception  of 

replacement  double  glazed  anodized  aluminum  windows  installed  at  the  rear  of  the  main 

reception desk, windows date from original construction.  

 

 

 

 

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 24 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

Other Exterior Elements 

 

A canopy  is  located along the north and west elevations over the main entrance to the building. 

The canopy consists of a cantilevered assembly covered by a low‐slope roof.  

 

6.2  Condition  

   

Brick Veneer 

 

The  brickwork  is  currently  suffering  from  expansion 

within  the  mortar  joints  due  to  corroding  of  the 

embedded  steel  shelf  angles. Resulting  from  a  lack of 

through‐wall flashing, corrosion of the shelf angles has 

caused separation which is approximately up to an inch 

wide  in a  continuous  linear pattern. The gap  is  visible 

above  the  windows  at  each  level  around  the  entire 

perimeter  and  is  separated  only  by  the windows  and 

concrete  panels.  The  open  gaps  in  the mortar  joints 

allows water  penetration  leading  to  further  corrosion 

and potentially damp and mold growth internally, if not 

rectified.  

 

We recommend scaffolding of the building, removing of three courses of brick above each shelf 

angle,  removing and  replacing  the  shelf angle,  installing a  through‐wall  flashing and  reinstalling 

(where possible) the removed brick.  

 

In addition to concerns with the shelf angles, we noted stains on the brickwork, particularly to the 

front elevation. While this is not considered to major issue, from an appearance point of view the 

staining  is particularly unsightly when viewed at street  level. On  this basis, we have allowed  for 

two terms of brick cleaning to be undertaken  in the near and  late terms of this study period for 

approximately 15% of the external wall area.  

 

Precast Concrete Cladding Panels 

 

The  condition of  the precast  concrete  cladding panels  ranges  from  fair  to  good with numerous 

areas of surface and minor sectional cracks noted at the panels.  We have recommended that the 

defective panels be replaced in conjunction with correction of the previously cited shelf lintel issue.  

In conjunction with this replacement work, we have also recommended that an allowance be made 

for recoating of the cladding panels and replacement of sealants installed between the panels and 

brick veneer.  

 

Doors and Windows 

 

Doors  appeared  to  be  in  good  condition.  Assuming  the  completion  of  on‐going maintenance 

replacement or capital expenditure should not be required within the study period.  

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 25 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

Windows are  in fair to poor condition due to their age/general wear and tear and are no  longer 

considered  to be energy efficient. During our assessment we  identified  that daylight was visible 

between the operable casement sections of the windows indicating that the frames have warped 

over time which  is exacerbated by the absence of seals. Gaps  in the windows have a significant 

affect upon the heating and cooling equipment, resulting in overuse, increased maintenance plus 

unnecessary  expenditure on  fuel  costs. We  recommend  that windows be  replaced  in  the near 

term with  anodized  aluminum  framed double  glazed units.    This work  should be  completed  in 

conjunction with the previously discussed brick and precast work.  

 

Other Exterior Elements 

 

The entrance canopy appeared to be in good condition. However, we noted general failure of the 

roof cover provided at the canopy and we have allowed for this to be replaced  in the near‐term 

along with the main roof.  

 

The condition of sealants  installed at the connection between the  joints of the precast concrete 

panels and the surrounding horizontal and vertical sections varied. Approximately 15 ‐ 20% of the 

sealants were missing creating gaps between the sections. We have recommended budgeting for 

near‐term  replacement  of  currently  failed  sealant  and  replacement  of  all  remaining  sealant 

towards the end of the study period.  

 

6.3  Projected Capital Expenditures 

 

Required: 

 

Based  upon  the  extent  of  the  exterior  defects  noted  and  interconnected  nature  of  the  trades 

involved  in  correction  of  those  defects, we  recommend  budgeting  for  a multi  faceted  exterior 

renovation project. Completed  in a single phase / mobilization,  the project should consist of  the 

items below. 

 

Mobilization / Design 

 

1. Prior  to  the  commencement  of  any work, we  recommend  retaining  a  District  of  Columbia 

registered architect to design, specify and monitor the replacement and repair work detailed 

below. Our opinion of cost for this work is $30,408 in 2016. 

  

2. Once designs are complete, bid and contractor(s) selected, scaffolding should be  installed at 

each elevation. Our opinion of cost for this work assuming a three month project schedule  is 

$29,200 in 2016. 

 

Correct Deficiencies  

 

3. We  recommend  removing  of  three  courses  of  brick  above  each  shelf  angle,  removing  and 

replacing the shelf angle, installing a through‐wall flashing and reinstalling (where possible) the 

removed brick. Our opinion of cost for this work is $75,950 in 2016.  

david.saulter
Rectangle
david.saulter
Rectangle
david.saulter
Rectangle

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 26 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

4. We recommend budgeting for replacement of cracked precast concrete cladding panels. Our 

opinion of cost for this work is $41,800 in 2016.   

5. We recommend budgeting for recoating of the cladding panels and replacement of associated 

sealants. Our opinion of cost for this work is $15,400 in 2016.  

6. We recommend budgeting for cleaning of stains at the building exterior. Our opinion of cost 

for this work is $9,243 in 2016.   

7. We  recommend  that  the  existing windows  are  replaced with  anodized  aluminum windows. 

Our opinion of the cost for replacement of the 4’3” x 2’1” windows is $57,750 in 2016.  

8. We  recommend  that  the  existing windows  are  replaced with  anodized  aluminum windows. 

Our opinion of the cost for replacement of the 2’4” x 2’ windows is $18,960 in 2016.  

9. We  recommend  that  the  existing windows  are  replaced with  anodized  aluminum windows. 

Our opinion of the cost for replacement of the single 0.91’ x 1’3” window is $620 in 2016. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

david.saulter
Rectangle
david.saulter
Rectangle
david.saulter
Rectangle
david.saulter
Rectangle
david.saulter
Rectangle
david.saulter
Rectangle

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 27 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

BUILDING SYSTEMS 

 

7.0  MECHANICAL SYSTEMS 

 

The following information was obtained through our visual observations of the building systems, review of 

available documents, and discussions with building maintenance personnel. The heating, ventilation and 

air conditioning systems consist of the constant volume system which incorporates the natural gas boiler, 

chiller,  cooling  tower,  three air‐handling units, exhaust  fans and  the direct digital  control (DDC)  system  

(reference Photographs 16, 33, 34, 38 – 41 & 43 in Appendix A). 

 

7.1  Heating Systems 

 

Description 

 

Heating hot water is generated by one natural heating boiler manufactured by Smith in 1991 with 

a capacity of approximately 1,137‐MBH.  Heating hot water is circulated to the multi‐ and single‐

zone  air  handling  units,  radiant  heaters  through  the  two  pipe  distribution  system  via  two 

circulation pumps operated in a duty and standby configuration.   

 

System Capacity 

 

Based  upon  discussions  with  maintenance  personnel  and  our  review  of  the  equipment  and 

documentation, the heating load on the building is minimal and the system has adequate capacity 

to meet comfort conditions. 

 

Condition 

 

The heating hot water distribution boiler and pumps appeared  to be  in  fair  condition with  the 

boiler being serviced at  the  time of our assessment, and with  the pumps having been  replaced 

within the last five years. The boiler should be programmed for replacement near‐term. Assuming 

the  completion  of  on‐going  repair  and maintenance,  we  do  not  anticipate  a  requirement  to 

replace the pumps within the study period.  

 

Projected Capital Expenditures 

 

Required: 

 

1. We recommend budgeting for replacement of the boiler in 2016. Our opinion of cost for this 

work is $22,000. 

 

 

 

 

 

 

david.saulter
Rectangle

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 28 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

7.2  Cooling Systems 

 

Description 

 

Chilled water that  is circulated within the air handling unit coils  is produced by one fluid‐cooled 

reciprocating  liquid  chiller.  The  chiller  is  located  within  the  basement  level  boiler  room  and 

consists  of  a  50  ton  capacity  unit manufactured  by  Carrier®  and  installed  in  1991.  The  chiller 

utilizes R‐22 refrigerant. Chilled water is distributed to the various air‐handling units via two 120‐

gpm pumps.   

 

Condenser water for the chiller  is generated by one cooling tower  located at‐grade at the south 

east corner of the Property.   The cooling tower was manufactured by Baltimore Air Coil  in 1991 

and had a capacity of approximately 50‐tons.  Condenser water is distributed via two approximate 

150‐gpm  pumps with  two  horsepower motors.  Pumps  for  the  cooling  tower  contained  three 

horsepower motors and were rated with a flow capacity of 170‐gpm.  

 

Supplemental  cooling  for  the  elevator  equipment  room  is  provided  by  a  split  system  air 

conditioning unit with the remote condensing unit being mounted on the east side of the building.  

The  split  system  air  conditioning  unit  has  an  approximate  cooling  capacity  of  2‐tons  and was 

manufactured by Carrier.   

 

System Capacity 

 

Based  upon  discussions  with  maintenance  personnel  and  our  review  of  the  equipment  and 

documentation,  the  chilled  water  and  the  condenser  water  systems  are  adequate  for  the 

building’s cooling needs.  

 

Condition 

 

The  chiller  and  the  cooling  tower  appeared  to  be  in  fair  condition  having  been  in  service  for 

almost 25  years.   Based on  the  age of each unit,  it  is  likely  that  replacement  components will 

become  increasingly  difficult  to  procure  or  become  obsolete  altogether.    In  addition, 

advancements  in  technology have  increased  the energy efficiency of chillers and cooling  towers 

drastically  since  the  existing  units  were  installed.    Based  on  these  factors,  we  recommend 

budgeting  for  the  replacement of  the chiller and cooling  tower near‐term.   When  replacing  the 

existing units, it is possible that the existing pumps may require replacement based up on the new 

capacity  of  the  chiller,  so  the  associated  cost  of  replacing  the  distribution  pumps  have  been 

included within the chiller replacement cost. 

 

The  supplemental  cooling  unit  appeared  to  be  in  good  condition  and  should  not  require 

replacement within the study period.  

 

 

 

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 29 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

Projected Capital Expenditures 

 

Required: 

 

2. We recommend budgeting for replacement of the chiller in 2016. Our opinion of cost for this 

work is $75,000. 

  

3. We recommend budgeting for replacement of the cooling tower in 2016. Our opinion of cost 

for this work is $30,000.  

 

7.3  Air Distribution Systems 

 

Description 

 

Conditioned  air  is  provided  by  two  single‐zone  and  one  multi‐zone  air‐handling  units 

manufactured  by ACME  and  equipped with  hydronic  coils.    Conditioned  air  is  then distributed 

throughout each floor of the building via sheet metal ducts. Table 7‐1 provides a summary of the 

air handling units. 

 

 Table 7‐1 – Air Handling Units   

 

AHU #  Location Served  Capacity   Installation Date 

1 (Multi Zone) Principal Areas of the 

Building 

632,000 BTU/Hr 

15,650 CFM 1962/3 

2 (Single Zone) Meeting Room in 

Basement 

77,900 BTU/Hr 

3,180 CFM 1962/3 

3 (Single Zone)  Hallways at 1st Floor  Not Accessible  1962/3 

 

System Capacity 

 

Based  upon  discussions  with  maintenance  personnel  and  our  review  of  the  equipment  and 

documentation, the air‐handling systems have the capacity to maintain comfort conditions within 

the building. 

 

Condition 

 

The modular air‐handling units appeared  to be  in  fair condition with coils replaced  in 2007. We 

noted widespread deterioration of the sheet metal housings and condensate pans noted.  Based 

upon the age of the units and the extent of housing and pan failure, we recommend budgeting for 

replacement of the units near‐term.  

 

 

 

david.saulter
Rectangle
david.saulter
Rectangle

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 30 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

Projected Capital Expenditures 

 

Required: 

 

4. We recommend budgeting for replacement of AHU # 1  in 2016. Our opinion of cost for this 

work is $65,000.  

 

5. We recommend budgeting for replacement of AHU # 2  in 2016. Our opinion of cost for this 

work is $25,000.   

6. We recommend budgeting for replacement of AHU # 3  in 2016. Our opinion of cost for this 

work is $25,000. 

 

7.4  Ventilation and Exhaust Systems 

 

Description 

 

Ventilation Air 

 

Outside air  for  ventilation  is  supplied  to  the air‐handling units  via  various outside air  fans. The 

outside air fans are typical mounted within each of the mechanical rooms on the vertical outside 

air duct.  The individual outside air fans are typically rated at 1,200‐cfm.   

 

Exhaust Systems 

 

General building exhaust systems  include exhaust  fans  for  the  restrooms and boiler  room.   The 

various exhaust fans have rated capacities ranging from 580‐ to 9,840‐cfm.    

 

System Capacity 

 

In  general  the  supply  and  exhaust  systems  for  the  building  appear  appropriate  for  the 

applications.  However, it is possible that the existing air‐handling units are not capable of meeting 

new outside air ventilation rates.   

 

Condition 

 

The various supply and exhaust systems  for  the building appeared  to be  in good condition. The 

estimated useful  life  for  the  types of  fans used  is 20  to 30 years. Based on  the minimal cost of 

replacement, we anticipate that the exhaust or ventilation fans will be replaced upon failure as a 

routine maintenance expense.   

 

 

 

 

 

david.saulter
Rectangle
david.saulter
Rectangle
david.saulter
Rectangle

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 31 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

Projected Capital Expenditures 

 

Required: 

 

No expenditures are anticipated at this time. 

 

 

7.5  Temperature Control Systems 

 

Description 

 

Control  of  the  air  handling  units  and  other  equipment  was  via  a  digital  control  system 

manufactured by Johnson Controls. 

 

Condition 

 

The digital control system appeared to be in good condition having been installed in 2010. Based 

upon obsolescence, we have  recommended budgeting  for mid‐term upgrade of  the  supporting 

software. 

 

Projected Capital Expenditures 

 

Required: 

 

7. We  recommend budgeting  for upgrade of  the building management  software  in 2018. Our 

opinion of cost for this work is $5,000.  

 

 

 

 

 

    

david.saulter
Rectangle

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 32 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

8.0  ELECTRICAL SYSTEMS 

 

The  following  information was  obtained  through  our  visual  observations  of  the  building  systems,  and 

discussion with  building maintenance  personnel.  The  electrical  systems  include  the  incoming  electrical 

service,  service  switchgear  and  electrical  distribution  equipment,  lighting  systems,  communications 

systems, and security systems (reference Photographs28, 30, 36 & 37 in Appendix A). 

 

8.1  Electrical Service and Distribution Equipment 

 

Description  

 

Electrical Service Equipment 

 

Secondary  electrical  service  is  supplied  at  208‐volts,  3‐phase  from  a  PEPCO  pole  mounted 

transformer  located along 50th Street SE. Conductors from the transformer are then routed to a 

400‐amp main  C/T  cabinet  located  in  the  basement  boiler  room.    Service  from  the main  C/T 

cabinet  is then routed to various breaker panels, fuse boxes, and fused disconnects to serve the 

electrical loads throughout the building.  

 

Power Distribution 

 

Voltages 

 

Large motors in the buildings (e.g. chillers and motors driving the HVAC system pumps, supply and 

exhaust  fans,  and  the  boiler)  are  supplied  at  208‐volts.  Building  fluorescent  and  interior  and 

exterior lighting fixtures, small motors, and miscellaneous power branch circuits are also supplied 

from the 208/120‐volt system panels. 

 

Wire and Conduit 

 

Typical power distribution for feeders and branch circuits  is accomplished using wire  in conduit. 

Observed  wiring  consists  of  copper  with  thermoplastic  insulation.  No  aluminum  wiring  was 

observed. 

 

Conduit types varied in the buildings based on area and usage. Rigid metal conduit is used in areas 

subject  to  constant moisture  and  physical  damage.  Electrical metallic  tubing  (EMT)  is  used  in 

interior spaces. Limited amounts of flexible metal conduit and Type MC cable are used.  

 

Panelboards 

 

Panel boards throughout the building range in capacity from 100‐amps up to 250‐amps.  All panels 

utilize either circuit breakers or plug type fuses for overcurrent and short circuit protection.  

 

 

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 33 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

Condition 

 

The  electrical  installations  appeared  to  be  in  fair  condition  with most  of  the  equipment  and 

components dating to the 1960’s.   Based on the age and type of the electrical components,  it  is 

likely  that  these  components will  reach  the  end  of  their  service  life  and  become  increasingly 

unreliable  towards  the  end  of  the  study  period.   We  recommend  budgeting  for  an  electrical 

system upgrade near  to mid‐term  to ensure  the electrical  systems  continue  to provide  reliable 

service. 

 

System Capacity 

 

The  building  is  equipped  an  electrical  service  rated  for  540‐kVA.   Using  a net building  area  of 

22,240 square feet (SF) yields a unit load factor of 41.1‐VA/SF. Based on industry design standards, 

the demand load for this building should be on the order of 8‐ to 10‐VA/SF. The building electrical 

capacity appears to be more than adequate for the anticipated needs of this building. 

 

Projected Capital Expenditures 

 

Required: 

 

1. We recommend budgeting for upgrading the main electrical system.  Our opinion of cost for 

this work is $75,000 in 2016. 

 

 

8.2  Lighting Systems 

 

Description 

 

General  office  area  lighting  consists  of  nominal  2’  x  4’  lensed,  lay‐in  fluorescent  fixtures. 

Equipment  areas  are  illuminated  using  fluorescent  strip  lighting.  Linear  fluorescent  lamps  are 

F32T8 type. Fluorescent ballasts are energy saving electronic style. Most downlights in offices and 

conference  rooms  utilize  compact  fluorescent  lamps  and  electronic  ballasts.  Surface mounted 

fixtures with metal halide lamps are used in the exterior.  

 

Emergency  egress  lighting  is  provided  by  fixtures  powered  by  the  emergency  power  system. 

Illuminated exit signs are installed at exit doors and along the path of egress. Exit signs styles vary 

somewhat, but most are edge‐lit.  Lighting  is  controlled by a  combination of  local  switches and 

sensors.  

 

Condition 

 

Fixtures generally appeared to be in good condition and appropriate for the applications.  Most of 

the fixtures have been replaced within the last ten years.  We did note that some T12 fluorescent 

fixtures are still installed in the main mechanical rooms. 

 

david.saulter
Rectangle

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 34 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

Projected Capital Expenditures 

 

Required: 

 

No expenditures are required at this time.   

 

 

8.3  Communication and Data Systems 

 

Description 

 

Telephone service enters the building at the basement level in the boiler room. Trunk cables are 

then  routed up  through  floor  telephone  closets  to  serve  the main  and  second  floor.  Incoming 

service cables belong to the telephone companies.  

 

Condition 

 

The data and telephone  infrastructure appeared to be  in good condition and should not require 

significant repair or replacement within the ten‐year study period. 

 

Projected Capital Expenditures 

 

Required: 

 

No expenditures are required at this time.   

 

 

8.4  Security Systems 

 

Description 

 

The building is protected by electronic security systems.  A closed circuit television (CCTV) system 

is installed throughout the building. A digital video recorder (DVR) manufactured by GE is installed 

at  the main entrance desk.    In addition, an electronic anti  theft  system  is  installed at  the main 

library entrance.  

 

Condition 

 

The  security  systems appeared  to be  in good condition with  the CCTV and DVR  systems having 

been  upgraded within  the  last  four  years.  The  estimated  useful  life  of  the  cameras  and DVRs 

equipment is typically 8 to 10 years due to advances in technology and systems obsolescence. We 

recommend  budgeting  for  the  general  replacement  and  upgrade  of  the  security  systems mid‐

term.  

 

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 35 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

Projected Capital Expenditures 

 

Required:  

 

1. We recommend budgeting for the as needed replacement of the security cameras and DVRs 

late‐term.  Our opinion of cost for this work is $15,000 in 2018. 

    

david.saulter
Rectangle

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 36 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

9.0  PLUMBING SYSTEMS 

 

The  following  information  was  obtained  through  our  visual  observations  of  the  building  systems  and 

discussions with building maintenance personnel. The plumbing systems  include the domestic cold water 

system, domestic hot water system, sanitary waste and vent system, and storm water collection system 

(reference Photograph 42 in Appendix A). 

 

9.1  Domestic Water Systems 

 

Description 

 

Domestic Cold Water 

 

Domestic cold water service, consisting of a 2” diameter water main, enters  the building at  the 

west side of the building in the boiler room.   Shut‐off valves are installed shortly after the service 

enters  the building. The metered  service  is  routed  through a double check‐valve  type backflow 

prevention device, and  then  to  the  respective areas of  the building and site. Water distribution 

relies on the pressure from the service main at around 55‐ to 60‐psi. 

 

Domestic Hot Water 

 

Domestic hot water is generated by one natural gas fired water heater located in the boiler room 

in  the  basement.    The  water  heater  has  a  storage  capacity  of  approximately  60‐gallons  and 

appears to have been installed in 2010.   

 

System Evaluation 

 

The  capacity and  configuration of  the water  service  to and  through  the building appears  to be 

appropriate. No problems were reported or noted concerning water distribution. 

 

Condition 

 

The domestic water systems appear to be in good condition. No leaks or restricted flow was noted 

or reported within the piping systems. The domestic water heater was  in good condition having 

been installed in 2010. Future replacement should not be required within the study period.  

  

Projected Capital Expenditures 

 

Required: 

 

No expenditures are required at this time.   

 

 

 

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 37 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

9.2        Sanitary Waste and Storm Drainage Systems 

 

Description 

 

Sanitary Waste Systems 

 

Sanitary waste is collected from multiple riser stacks and routed to the municipal sanitary system 

via  a  duplex  sanitary  booster  pump  system  contained within  the  basement  level  boiler  room.  

Visible portions of the sanitary piping were of cast iron construction with some PVC repairs.  

 

Storm Water Systems 

 

Storm  drainage  from  the  low‐slope  roof  areas  is  via  roof  drains  and  internal  leaders  and 

downspouts.  Storm water  is  drained  via  gravity  lines  to  site  lines  that  discharge  into  the  City 

maintained system.  Visible portions of the storm water piping were of cast iron construction with 

some modifications being completed with PVC piping.  

 

System Evaluation 

 

The  capacity  and  configuration  of  the  sanitary  and  storm  water  collection  systems  for  both 

buildings appear to be appropriate for the current occupancy.  

 

Condition 

 

The  sanitary  and  storm  drainage  systems  appeared  to  be  in  fair  to  good  condition  with  no 

significant  leaks or other areas of deterioration noted or reported to us. We do not anticipate a 

requirement to complete significant repair or replacement of the sanitary systems within the ten‐

year  study period.   We do anticipate  that one or both of  the  sump pumps and  sewage ejector 

pumps will  need  to  be  replaced  during  the  study  period.    However,  based  upon  the minimal 

replacement cost of the pump and/or motor, we anticipate that they will be replaced upon failure 

as a routine maintenance expense.   

 

Projected Capital Expenditures 

 

Required: 

 

No expenditures are required at this time.   

 

    

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 38 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

10.0  FIRE AND LIFE SAFETY SYSTEMS 

 

Fire and  life safety elements observed audible  fire alarm and detection system  (fire alarm / annunciator 

panels, duct detectors, strobes, pull stations, emergency and exit  lights), handheld fire extinguishers, and 

fire‐rated means of egress (reference Photographs 23 – 25, 29, 32 & 45 in Appendix A).  

 

10.1  Code References 

 

The building was designed  in  1962  for  construction  and occupancy  in  1963.    The building was 

constructed under the 1961 edition of the District of Columbia Building Code.  

 

10.2  Structural Fire Protection 

 

Description 

 

The structure consisted of  reinforced concrete columns and  floors, some structural steel beams 

and columns, concrete masonry unit (CMU) walls, and drywall partitions. Exit stairs are generally 

enclosed, with  the  rated  assemblies  created  using  rated partitions.  Shaft  enclosures  consist  of 

CMU  walls  with  protected  openings  and  penetrations.  These  elements  have  two  hour  fire 

resistance  rating  construction.  Fire  rating  labels  at doors  typically  indicated  a 1, 1 ½ or 2 hour 

rating.  

 

Condition 

 

We noted the condition and adequacy of the structural fire protection systems at the mechanical, 

electrical and telecommunication rooms, in the corridors and exit stairs, and above select ceiling 

tiles. The  structural  fire protection appeared  to be  in good  condition and generally  installed  in 

accordance with industry accepted practice and the codes enforced at the time of construction.  

 

Projected Capital Expenditures 

 

Required: 

 

No expenditures are required at this time.   

 

10.3  Means of Egress 

 

Description 

 

Primary exit stairwells are contained at the east and west of the building. Both exits expel to the 

building exterior.  Exit doors had a clear opening width of 33” per leaf. Exit signs are provided at 

each exit and at appropriate  locations along  the path of egress. Emergency  lighting  serving  the 

egress  paths  and  the  interior  of  exit  stairs  is  provided  by  selected  ceiling  mounted  fixtures 

powered by the emergency circuit and battery backups. 

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 39 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

Condition 

 

Means of egress comply with the fire codes enforced at the time of construction with regard to 

exit discharge, travel distances and other factors. We do not anticipate a requirement to upgrade 

the means of egress components during the study period.  

  

Projected Capital Expenditures 

 

Required: 

 

No expenditures are required at this time.     

10.4       Fire Detection and Alarm Systems 

 

Description 

 

The building is protected by a Simplex 4100 addressable fire alarm system. The fire alarm control 

panel (FACP) is located in the elevator control room.  An annunciator panel is located at the main 

library entrance near the service desk.   

 

The  fire  alarm  system  monitors  manual  pull  stations  and  smoke  detectors  throughout  the 

building. Duct detectors are provided  in air‐handling units  rated  for more  than 2,000 cubic  feet 

per minute (cfm) of airflow. Pull stations are provided at exits.   Alarm notification  is provided by 

horn/strobe signals and strobe‐only signals located throughout the building.  

 

Elevator recall  is accomplished via an  interface with  the  fire alarm system. Upon activation of a 

smoke detector  associated with  an elevator  lobby, machine  room, or hoistway,  the elevator  is 

recalled to the main access floor (or the alternate floor), the doors open, and the elevator is taken 

out‐of‐service until re‐activated by emergency personnel.  

 

Condition 

 

The fire alarm system was upgraded in 2010 and appears to be in good condition. Replacement of 

the existing system  is not required as  long as  it continues  to  function. However, historically  the 

main  fire  alarm  control panels often become obsolete  after  10  to  15  years  and must undergo 

replacement to remain current and fully functional. This timing is beyond the 10 years considered 

by this study.  

 

Projected Capital Expenditures 

 

Required:  

   

No expenditures are required at this time.   

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 40 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

11.0  CONVEYANCE SYSTEMS 

 

11.1  Description 

 

The  building  contains  one  passenger  elevator  (reference  Photograph  31  in  Appendix  A).  The 

elevator consists of a direct plunger basement hydraulic unit which serves the basement, 1st floor 

and 2nd floor.  The elevator consists of a wall‐mounted non proprietary solid state microprocessor 

controller, a hydraulic oil tank with integral pump, the car and car guide rails, car doors and door 

operator,  travelling cables,  the  in‐ground double wall hydraulic cylinder, plunger and associated 

PVC wrapping and stop ring, and the  landing  indicator,  landing push buttons,  landing doors, and 

the car buttons and finishes. Omni Elevator Company is the current maintenance provider. Table 

11‐1 provides a summary of the elevator systems. 

 

Table 11‐1 ‐ Summary of Elevators 

 

Elevator 

Designation 

Floor Levels 

Served Type 

Capacity 

(LBS) 

Speed 

(FPM 1) 

Passenger or 

Freight 

1  B, 1, 2  Hydraulic  2,500  150  Passenger 

 

1. FPM indicates feet per minute 

Machine Room Equipment 

 

The machine room for the elevator is located adjacent to the elevator shaft at the lower level. The 

machine room consists of a purpose built dedicated room and contains the microprocessor solid 

state  controller which  is wall‐mounted  adjacent  to  the pump unit.  The  controller  consists of  a 

V3MH model non‐proprietary unit manufactured by Virginia Controllers and installed in 2007.  

 

Pits & Hoistway 

 

The elevator pit contains the major pieces of equipment listed in Table 12‐2.  

 

Table 12‐2 ‐ Summary of Pit & Hoistway Equipment 

   

Limit Switches  Door Operating Equipment 

Hoistway Wiring and Conduit   Door Operators 

Panels and Frames  Car Operating Station 

Fascias and Dust Covers  Leveling Equipment 

Spring Buffers  PVC lined Double Walled Hydraulic 

Jack Assembly 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 41 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

Cab 

 

The elevator cab consists of a  steel enclosure with decorative  finishes. A car‐operating panel  is 

provided within the cab. Raised numbers and Braille tags are provided at the operating panel. A 

hands  free  communication  system  is  provided  within  the  cab.  The  cab  is  provided  with  side 

opening single‐stage doors with infrared sensors.  Cab finishes consist of 12” x 12” vinyl floor tiles, 

wood laminate wall panels and an acrylic ceiling system.  

  

Lobbies  

 

Hall  call  risers  are  provided  at  each  lobby  serving  the  elevator.  Hall  buttons  provided  at  the 

passenger  elevators  are  newer  style  and  comply  with  the  Americans  with  Disability  Act 

Accessibility Guidelines  (ADAAG). Arrival  lanterns and Braille  floor designations are provided on 

the hoistway entrances.   

 

11.2  Condition 

 

The elevator appeared to be in good condition with records reviewed detailing that the hydraulic 

pump  jack assembly  is not  loosing oil. Routine maintenance  is completed by  the Omni Elevator 

Company. Based upon observed conditions and documents reviewed, it appears that the elevator 

system was subject to large‐scale modernization in 2007. Modernization was generally completed 

using non proprietary components and appeared to consist of the following general scope: 

 

 Machine Room  

Replacement of the original relay logic controller with a with microprocessor controller 

and new VVVF AC drive  

Replacement of wiring 

Replacement of hydraulic pump unit 

Installation of a 1.5 ton capacity split system air conditioning unit  

 

Fixtures  

New main applied panel car station   

New flushmount hall stations 

New hall lantern inserts with LED lights and electronic gongs  

Reuse of the jamb Braille  

New lobby fire panel with required devices  

Replacement of car finishes  

 

Door Equipment  

Installation of a closed loop door operator 

Refurbishment of the car door tracks and hanger assemblies  

Refurbishment of the existing hoistway door equipment (replace rollers, gibbs, closers, 

interlocks as necessary)  

Installation of new hoistway door astragals  

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 42 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

Hoistway Equipment  

New wiring throughout (traveling cable, hoistway wiring, etc.)  

New landing system (position transducer and limit switch package)  

New load weighing devices  

Refurbishment of the existing car and counterweight guides (replace rollers as necessary)  

New cartop exit switch  

Installation of bevel ledges through hoistway  

 

Pit Equipment  

New pit stop switch  

New pit ladder as necessary to meet code requirements  

Replacement of the hydraulic jack assembly  

 

Based upon observed conditions, the use of  long‐life non propriety equipment and the extent of 

the  2007  modernization  project,  repeat  cycle  modernization  of  the  elevator  should  not  be 

required  until  the  existing  components  reach  a  20  year  age  in  circa  2027.  This  is  beyond  the 

timeframe considered by this study.  

 

11.3  Projected Capital Expenditures  

   

Required: 

 

No required expenditures are anticipated at this time. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 43 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

BUILDING INTERIORS AND FINISHES 

 

12.0        INTERIOR FINISHES  

 

The interior areas of the building can be divided into 1) the public areas, 2) meeting rooms and 3) 

staff areas (reference Photographs 22 & 26 in Appendix A). 

 

12.1  Description 

 

The interior areas of the building can be divided into three principal areas (reference Photographs 

xx through xx in Appendix A). These consist of 1) the public areas, 2) meeting rooms and 3) staff 

areas.  The  public  areas  account  for  the majority  of  the  building  and  consist  of  the  entrance 

vestibule and  lobby, reception and the main  library area on the ground floor. The first floor has 

limited books and is primarily used as a meeting space.  

 

Finishes within  communal  areas,  such  as  library  spaces  typically  have  a  carpet  tiles. However, 

finishes within communal staircases consist of resilient vinyl floor tiling and some lobby areas have 

ceramic floor tiles. Wall finishes generally consist of painted gypsum board, however some areas 

have concrete masonry units (CMU) with a painted finish.  

 

Floor  finishes within  restrooms  consist  of  ceramic mosaic  tiling  to  the  floors. Walls  consist  of 

gypsum  board  and  are  a  partially  clad with  ceramic  tiling  to  a  height  of  around  five  feet,  the 

remainder of the wall has a painted finish.  

 

Ceiling finishes throughout consist of a suspended ceiling grid with 2x4' composite infill tiles.  

12.2  Condition  

 

Floor finishes throughout are in fair condition. Areas of carpeting were showing signs of wear and 

had localized stains, it is therefore recommended that carpet tiles are replaced in the mid‐term. It 

is  assumed  that  all other  floor  finishes will be  replaced during  the next  internal  refurbishment 

project. Wall finishes are  in fair condition,  it  is however recommended that cyclical redecoration 

works  are  undertaken  ever  5‐7  years,  however  such  costs  have  been  excluded  from  this 

assessment. 

 

The condition of the  interior finishes varied from fair (where original) to good (where replaced). 

Replacement  finishes consisted of carpet tiles and paint  in the public areas and meeting rooms. 

These finishes were replaced in 2012. We have included an allowance for periodic replacement of 

interior finishes based upon observed conditions, discussion with management personal and our 

experience with similar facilities.  

The ceiling finishes are in fair condition and should not require any significant capital expenditures 

during this study period. 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 44 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

12.3  Projected Capital Expenditures 

 

Required: 

 

1. We recommend budgeting for replacement of carpet tiles in 2019. Our opinion of cost for this 

work is $74,805. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

david.saulter
Rectangle

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 45 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

AMERICANS WITH DISABILITY ACT (ADA) 

 

13.0   ACCESSIBILITY 

 

13.1  The Guidelines 

 

As  a  publically  accessible  office  facility,  the  building  should  seek  compliance  with  the  1991 

Americans  with  Disability  Act  (ADA)  Accessibility  Guideline.  This  report  section  compares  the 

requirements of  the ADA with as‐built conditions, and where applicable, recommends upgrades 

required to achieve compliance. Specifically, two areas of the ADA have significant effect on the 

physical aspects of the Property. 

 

Title  I  deals  with  employment  discrimination,  and  requires  that  employers  not  discriminate 

against a disabled person in hiring or employment. This can impact the configuration and features 

of buildings and those employers are expected to make “reasonable accommodation”,  including 

making facilities readily accessible to disabled employees. 

 

Title III requires that public accommodation provide goods and services to disabled patrons on an 

equal  basis with  the  non‐disabled  patrons.  This  title  is  the  part  of  the  ADA with  perhaps  the 

greatest impact on buildings, which provide public accommodations, including libraries.  

 

The ADA has provided a benchmark for measuring accessibility, primarily orientated towards new 

construction. It also provides guidance for modification of existing facilities to eliminate barriers to 

access. This benchmark  is the ADA Accessibility Guidelines  (ADAAG). The ADAAG was written by 

the Architectural and Transportation Barriers Compliance Board, and  first  issued  in  final  form  in 

July 1991. The stated purpose of the guidelines is to ensure that newly constructed facilities and 

altered  portions  of  existing  facilities  covered  by  the  ADA  are  readily  accessible  to  disabled 

persons.  

 

The ADA  in  its  purest  form  relates  only  to  facilities  first  occupied  or  significantly  altered  after 

March 13, 1991. For facilities with Certificates of Occupancy  issued prior to March 13, 1991 and 

not  significantly  altered  after  this  date,  the  ADA  is  seen  as  a  “good  practice  guide”  with  a 

requirement to complete accessibility upgrades typically made by civil suit and employee / user 

request.   

 

Regulatory  implementation of  the ADA  includes  the  following prioritizes  for barrier  removal  in 

existing facilities: 

 

Accessible  Entrances.    Providing  access  from  public  sidewalks,  parking  or  public 

transportation that enables disabled individuals to enter the facility. 

 

Access  to Goods and Services. Providing access  to areas where goods and services are 

made available to the public. 

 

Usability of Restrooms. Providing access to restroom facilities. 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 46 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

 

Removal  of  Remaining  Barriers.  Providing  access  to  the  goods,  services,  facilities, 

privileges, advantages, or accommodations. 

 

13.2  Applicability 

 

The ADA relates primarily to facilities occupied or significantly altered after March 13, 1991.  For 

facilities  with  Certificates  of  Occupancy  issued  prior  to March  13,  1991  and  not  significantly 

altered after this date, the ADA is seen as a “good practice guide” with a requirement to complete 

accessibility upgrades typically made by civil suit and employee / user request.  The building was 

first occupied  in circa 1963.   Therefore, compliance with the ADAAG  is not necessarily required, 

but compliance of the Property has been considered to be needed as a good practice.   

  

13.3  Accessible Entrances 

 

The  first  consideration  relates  to  measures  that  will  enable  individuals  with  disabilities  to 

physically approach and enter a place of public accommodation. The priority of “getting through 

the  door”  recognizes  that  providing  actual  physical  access  to  a  facility  from  public  sidewalks, 

public transportation, or parking, is generally preferable to any alternative arrangement in terms 

of both business efficiency and the dignity of individuals with disabilities. 

 

Persons travelling to the building via public transportation are likely to access the site from a small 

section of private sidewalk which is accessed via public sidewalks located on either 50th Street SE 

or Central Avenue SW. The sidewalks at the perimeter of the site are provided with curb ramps 

where required and are generally accessible. 

 

The building provides  combined access  for visitors and  for employees.   All parties entering  the 

building via public  transport or  from  the parking  stalls on  site  can enter via  the main entrance 

located at the corner of 50th Street SE and Central Avenue SW. Access vie the main entrance  is 

provided  through  a  pair  of  glazed  double  doors  with  an  adjacent  vestibule  and  with  power‐

assisted automatic opening devices.  The entrance doors’ configuration is generally compliant with 

the ADAAG. However, it should be noted that no accessible parking is provided at present and the 

route from the parking lot to the main entrance is via a paved roadway. 

 

The  entrance  doors’  configuration  is  generally  compliant with  the  ADAAG.   Once  through  the 

elevator  lobby entrance doors, access  to  the  second  floor’s main  lobby and  the upper  floors  is 

unrestricted  via  an  elevator.    Door  widths  and  hardware  are  compliant  with  the  applicable 

sections of the ADAAG.   

 

An  item to address as an operational expense  is provision of directional signage at the entrance 

drive and along the sidewalk  indicating the accessible route to parking and the entrance at  first 

floor level. 

 

 

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 47 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

13.4  Accessible Drop‐Off and Pick‐Up Areas 

 

If passenger drop‐off areas are provided,  they must be accessible and an accessible  route must 

connect  each  accessible  drop‐off  area  with  the  accessible  entrance(s).    Curb  ramps must  be 

provided  if  the drop‐off area  is next  to a curb and raised sidewalk. The building  is not provided 

with a drop off area.  

 

13.5  Route of Travel 

 

Disabled persons wishing to access the Property are able to gain suitable means of entry via the 

main entrance located at the corner of 50th Street SE and Central Avenue SW. This route of travel 

utilized public and private sidewalks and is generally in compliance with ADAAG. 

 

The  route of  travel,  from  the parking  lot  is partially  restricted as access  is provided via a paved 

access road, which has locked gate outside of business hours. 

 

13.6  Horizontal and Vertical Circulation 

 

The building is served by a single passenger elevators that generally comply with the requirements 

of  Section  4.10  (Elevators)  of  the  ADAAG,  including  hall  call  buttons,  hall  lanterns,  raised  and 

Braille characters on hoistway entrances, and car controls.   

 

Horizontal circulation throughout the building  is  in corridors or open areas with  level  floors and 

typically of adequate width and configuration. 

 

13.7  Door Widths and Signage 

 

Section 4.13  (Doors) of  the ADAAG  states  that doorways and gates,  including  security entrance 

gates, shall have a minimum clear opening of 32‐inches. The doorways met this requirement with 

a typical clear opening width of 33‐ to 34‐inches.  The threshold at doorways is to not exceed ½‐

inches in height, and the door hardware (handles, pulls, latches, locks etc.) on accessible doors are 

to have a  shape  that  is easy  to grasp with one hand and does not  require  tight grasping,  tight 

pinching, or twisting of the wrist to operate. The doorways at the Property were compliant with 

these requirements. 

 

The ADAAG states that signs that identify permanent rooms and spaces such as those identifying 

restrooms and exits or providing room numbers must have Braille and raised letters or numbers to 

allow them be read visually or tactilely.  The ADAAG also states that signs must also meet specific 

requirements  for mounting  location,  color  contrast,  and  non‐glare  surface.    Signs  that  provide 

direction  to,  or  information  about,  functional  spaces must  only  comply with  requirements  for 

character proportion, character height, and finish and with contrast between the characters and 

background.  

 

Signs used  to  identify offices and other permanent  rooms and spaces within  the Property meet 

these requirements.  

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 48 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

13.8  Space Allowance and Reach Ranges 

 

Section 4.2  (Space Allowance and Reach Ranges) of  the ADAAG  requires  that a minimum  clear 

width for single wheelchair passage shall be 32‐inches, the minimum width for two wheelchairs to 

pass is 60‐inches, the space required for a wheelchair to make a 180‐degree turn is a clear space 

of 60‐inches, and  the minimum  clear  floor or ground  space  required  to accommodate a  single, 

stationary wheelchair occupant is 30‐inches by 48‐inches.  

 

The Property generally complies with these requirements. 

 

13.9  Protruding Objects 

 

Section 4.4  (Protruding Objects) of  the ADAAG  requires  that objects projecting  from walls  (e.g. 

drinking fountains) with their leading edges between 27‐inches and 80‐inches above the finished 

floor  shall  protrude  no more  than  4‐inches  into walks,  halls,  corridors,  passageways,  or  aisles. 

Objects mounted with  their  leading  edges  at or below  27‐inches  above  the  finished  floor may 

protrude any amount. Free‐standing objects mounted on posts or pylons may overhang 12‐inches 

maximum from 27‐inches to 80‐inches above the ground or finished floor. Protruding objects shall 

not reduce the clear width of an accessible route or maneuvering space. 

 

The section also states that walks, halls, corridors, passageways, aisles, or other circulation spaces 

shall have a minimum clear head room of 80‐inches. If a vertical clearance of an area adjoining an 

accessible route is reduced to less than 80‐inches (nominal dimension), a barrier to warn blind or 

visually‐impaired persons shall be provided.   

 

The Property’s interior spaces generally comply with these requirements.   

 

13.10  Ground and Floor Surfaces  

 

Section 4.5  (Ground and Floor  Surfaces) of  the ADAAG  requires  that ground and  floor  surfaces 

along accessible routes and in accessible rooms and spaces, including floors, walks, ramps, stairs, 

and curb ramps, be stable, firm, and slip‐resistant.  

 

Flooring within the Property generally complied with this requirement. 

 

This section also requires that changes  in  level between ¼‐inches to ½‐inches be beveled with a 

slope no greater  than 1:2, and  that changes  in  level greater  than ½‐inches be accomplished by 

means of  a  ramp.  The  section  also  states  that  carpet or  carpet  tile used on  a  ground or  floor 

surface be securely attached; have a firm cushion, pad, or backing or no cushion or pad; and have 

a  level  loop,  textured  loop,  level  cut  pile,  or  level  cut/uncut  pile  texture. Where  gratings  are 

located on walking  surfaces,  then  they  shall have  spaces no greater  than ½‐inches wide  in one 

direction.  

 

Ground and floor surfaces for the Property were generally compliant.  

 

Capitol View Branch Library 5001 Central Avenue, SE    October 21, 2014 Washington, DC 20019    Page 49 of 49 

Report of Facilities Condition Assessment    F+G Project No. F09936511 

13.11  Ramps 

 

Section  4.8  (Ramps)  of  the  ADAAG  requires  that  any  part  of  an  accessible  route with  a  slope 

greater than 1:20 shall be considered a ramp. The Property does not contain ramps.   

 

13.12  Accessible Amenities 

 

ADAAG requires that the controls and operating mechanisms of vending machines in restaurants 

and cafeterias comply with all of 4.27 (Controls and Operating Mechanisms) of the ADAAG.  

 

Common area vending machines were not noted at the Property. 

 

13.13  Usability of Restrooms 

 

Sections 4.16 through 4.21 of the ADA detail those measures needed to provide  individuals with 

disabilities  with  access  to  restroom  facilities.    These  include  the  height  of  fixtures,  size  and 

arrangement of toilet stalls, location and height of grab bars and accessories, and floor and reach 

range  clearances.  In  general,  the  restrooms  fixtures,  stall  configurations,  dimensions  and 

accessories,  the  floor clearances and  reach ranges  to  fixtures and accessories appear  to comply 

with the ADAAG.   

 

13.14  Drinking Fountains 

 

Bi‐level drinking fountains are provided on each floor  level.   Section 4.15.2 (Spout Height) of the 

ADA requires that the spout height of drinking fountains no exceed 36”. The spout height of one 

of the drinking fountains one each floor was compliant at 32”.   

 

Drinking fountains were compliant with this section of the ADAAG. 

 

13.15  Parking 

 

An  insufficient  number  of  accessible  parking  spaces  were  provided  for  the  building.  ADA 

requirements  state  that  for  a  building which  contains  20  spaces,  one  ADA  compliant  parking 

spaces  is  required under Section 208.2, Parking Spaces  ‐ Minimum Number, of  the ADAAG and 

only one was provided. No of accessible  spaces are provided  to  the building,  therefore parking 

requirements are non‐compliant. 

 

We recommend that an ADA compliant parking space  is provided. This should be  located at the 

nearest point to the main building entrance. These works will likely be undertaken during the re‐

striping of the parking lot and have therefore been excluded from this assessment. 

 

Projected Capital Expenditures  

 

Required: 

No required expenditures are anticipated at this time. 

Appendix A Photographs

Photograph 01 Library sign at front entrance

Photograph 02 Front elevation

Photograph 03 Main roof covering in poor condition

Photograph 04 Peeling surface coating and evidence of ponding

Photograph 05 Missing capping and exposed timbers to roof perimeter

Photograph 06 Split and detached roof capping sheet

Photograph 07 Roof covering to canopy on the front elevation

Photograph 08 Missing roof covering and exposed timber decking to storage area (Rear elevation)

Photograph 09 Aluminum windows and security grills to lower level (Rear elevation)

Photograph 10 Precast concrete panels between brick work

Photograph 11 Damaged brickwork and corroding embedded steel lintel

Photograph 12 Efflorescence stained brickwork

Photograph 13 Corroded and detached rainwater pipe

Photograph 14

Patched and worn parking lot pavement with vegetation growth

Photograph 15 Cracking to parking pavement

Photograph No.01 Southeast Corner of the Property

Photograph 16 Cooling tower located in parking lot

Photograph 17 Main parking lot entrance and ponding water to pavement

Photograph 18 Debris build up on interior of aluminum windows

Photograph 19 Glazing obscured by etched effect to the surface

Photograph 20 Typical ceiling mounted CCTV camera

Photograph 21 ADA compliant water fountains

Photograph 22 First floor finishes

Photograph 23 Ceiling mounted smoke detection and strobe light

Photograph 24 Fire exit door from first floor

Photograph 25 Stair well and fire escape

Photograph 26 Typical rest room finishes

Photograph 27 Typical door furniture (Non ADA Compliant)

Photograph 28 Main electrical circuit breakers

Photograph 29 Fire alarm annunciator panel in reception

Photograph No.01 Southeast Corner of the Property

Photograph 30 Security barriers adjacent to exit doors

Photograph 31 Lift control circuitry

Photograph 32 Addressable fire alarm control panel

Photograph 33 Chiller

Photograph 34 Chiller

Photograph 35 Sewage ejector pumps

Photograph 36 Main electrical panels

Photograph 37 Main electrical panels

Photograph 38 Prime and stand-by pump

Photograph 39 Main air handling unit

Photograph 40 Secondary air handling unit

Photograph 41 Boiler

Photograph 42 Domestic water heater

Photograph 43 Interior view of boiler

Photograph 44 Sump pump

Photograph 45 Fire control panel

Photograph 46 Floor structure

Appendix B Expenditure Forecast By Year

Component No. ComponentEstimated Useful

Life or Replacement Cycle (Yrs)

Remaining Useful Life (Yrs)

QuantityUnit of

MeasurementUnit Cost Immediate 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024

Req

uire

d

Year 0 1 2 3 4 5 6 7 8 9 10

Site Systems

Ten Year Capital Expenditure Forecast Capitol View Branch Library

5001 Central Avenue, SEWashington, DC

RequiredRequired

1 Resurface (Mill & Overlay) Asphalt Pavements 20 2 1,063 SY $22.00 $23,386 $23,386

2 Crack Fill, Seal Coat & Re-Stripe Asphalt Pavements 5 N/A 1,063 SY $5.50 $5,847 $5,847

3 Replace Failed Concrete at Building Entrance 20 1 196 SF $15.00 $2,940 $2,940

4 Allowance For Replacement of Perimeter Chain Link Fence 15 4 361 LF $25.00 $9,025 $9,025

Structural Systems

Roofing Systems

1 Replace Built-Up Roof System 20 1 9,351 SF $14.00 $130,914 $130,914

Exterior Elements

1 A/E Fees Relating to Recommendations 3 - 9 N/A 1 15 % $219,723.00 $32,958 $32,958

2 Scaffolding for Recommendations 3 - 9 N/A 1 1 LS $29,200.00 $29,200 $29,200

3 Refurbish or Replace Lintels and Install Through Wall Flashings 60 1 434 LF $175.00 $75,950 $75,950

4 Replace Failed Precast Concrete Panels 60 1 19 EA $2,200.00 $41,800 $41,800

5 Recoat Precast Concrete Panels and Apply Sealants 8 1 280 SF $55.00 $15,400 $15,400

6 Clean External Brickwork 15 1 1027 SF $9.00 $9,243 $9,243

7 Replace Windows (4'3" tall x 2'1" long) 35 1 55 EA $1,050.00 $57,750 $57,750

8 Replace Windows (2'4" tall x 2' long) 35 1 24 EA $790.00 $18,960 $18,960

9 Replace Windows (0.91' tall x 1'3" long) 35 1 1 EA $620.00 $620 $620

Mechanical

1 Replace Boiler 20 2 1 EA $22,000.00 $22,000 $22,000

2 Replace Chiller 20 2 50 Ton $1,500.00 $75,000 $75,000

3 Replace Cooling Tower 20 2 50 Ton $600.00 $30,000 $30,000

4 Replace AHU # 1 20 2 1 LS $55,000.00 $65,000 $65,000

5 Replace AHU # 2 20 2 1 LS $25,000.00 $25,000 $25,000

6 Replace AHU # 3 20 2 1 LS $25,000.00 $25,000 $25,000

7 Upgrade Software at Building Automation System 8 4 1 LS $5,000.00 $5,000 $5,000

Required

Required

Required

No Expenditures Required at This Time

Required

Component No. ComponentEstimated Useful

Life or Replacement Cycle (Yrs)

Remaining Useful Life (Yrs)

QuantityUnit of

MeasurementUnit Cost Immediate 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024

Req

uire

d

Year 0 1 2 3 4 5 6 7 8 9 10

Ten Year Capital Expenditure Forecast Capitol View Branch Library

5001 Central Avenue, SEWashington, DC

Electrical

1 Replace Electrical Switchgear 30 2 1 LS $75,000.00 $75,000 $75,000

2 Replace CCTV & Proximity Sensor Systems 8 4 1 LS $15,000.00 $15,000 $15,000

Plumbing

Fire & Life Safety

Interiors

1 Replace Carpet Tiles 8 5 14,961 SF $5.00 $74,805 $74,805

$0 $0 $756,121 $0 $29,025 $74,805 $0 $5,847 $0 $0 $0 $865,798

$0 $0 $778,805 $0 $31,716 $84,194 $0 $6,981 $0 $0 $0 $901,696Cost (Inflated @ 3% Per Yr.)

Required Cost (Present Worth)

Required

Required

No Expenditures Required at This Time

Required

Required

No Expenditures Required at This Time

Appendix C Resumes of Assessment Team

Imran Ishaq , MRICS, CSCS Senior Facility Assessor Imran is a Chartered Building Surveyor with considerable experience in the Healthcare and Social Housing sector. He graduated from DeMontfort University, Leicester in 1999, started his career in London and returned to the North in June 2003 to commence employment with Faithful+Gould. Imran has undertaken projects from inception to completion and is familiar with contract procedures under JCT and NEC Forms of Contract. SELECTED PROJECT EXPERIENCE Sheffield City Council: Building fabric assessments using Apple iPad’s and Technology Forge IT platform to identify building pathology defects and estimated 5 year maintenance liability of municipal buildings including libraries, cemeteries and schools. Included the survey of Grade I Listed – Sheffield Town Hall. Lovell: Sheffield Family Courts – Condition assessment of building fabric and M&E installations to establish 20 year maintenance liability. Lovell: Fabric & M&E Condition assessments of 74nr residential properties using iPad technology and Kykloud Survey system. South Yorkshire Police: Condition assessment of building fabric and M&E installations to 72nr police properties including stations and other ancillary buildings. Anchor Housing Trust: Condition assessment of building fabric and M&E installations to 134 residential sites located in the Midlands, Yorkshire, Lancashire and North East. Development of specification documents and implementation of construction works. Halifax Plc: Project involved the survey and alteration of the building fabric and M&E to 1100 nationwide properties in accordance with Equality Act 2010. Doncaster Metropolitan Borough Council: Building fabric surveys to implement roof refurbishments to the Grade 1 & 2 Listed Buildings – Mansion House, Priory Place and Cusworth Hall.

Education B.S., Building Surveying,

University of West England, 2000

Certifications Professional Member of The

Royal Institute of Chartered Surveyors (MRICS)

Bachelor of Science Degree with Honours in Building Surveying

Achieved certification with the Construction Skills Certification scheme (CSCS)

NEBOSH general certificate in Health and Safety and NEBOSH fire safety and risk assessments

Years of Experience 16

Benjamin Dutton, FFB, MCIOB, MRICS Project Executive Benjamin Dutton is the director of Faithful+Gould’s facility condition assessment practice for North America. With more than 15 years of experience in facility assessments, Benjamin has worked in all sectors of the industry, from both municipal and federal governmental facilities to airports and resorts. Since 2005, Benjamin has grown Faithful+Gould’s condition assessment practice and built strong relationships with clients such as the District of Columbia Department of Real Estate Services (DRES), District of Columbia Public Schools, Archon Group and the U.S. General Services Administration. Benjamin’s driven nature and technical knowledge are assets as he spearheads Faithful+Gould’s condition assessment service across the United States and provides strategic facility information creating value for our clients. SELECTED PROJECT EXPERIENCE Archon Group Portfolio; Nationwide: Partnered with Archon Group on the condition assessment of more than 20 million square feet of office, hotel and related buildings under acquisition. National Institutes of Health (NIH); Bethesda, MD: Completed a comprehensive facility condition assessments on NIH’s 120-acre, 49-building campus to help them better understand the condition of its properties and develop a better maintenance system. Comerica Bank Portfolio; Various Locations, CA: Provided ongoing on-call due diligence engineering evaluations for various Comerica Bank properties varying in size of 5,000 square feet to 100,000 square feet. District of Columbia Department of General Services, City-wide Facility Assessment Portfolio; Washington, DC: Acted as project executive overseeing the comprehensive facility condition assessment of several different facility types for DRES such as office and administrative buildings, police stations, fire stations, the DC hospital, parks and recreation facilities, detentions facilities and much more. City of Milwaukie, City-wide Facility Assessment Property Portfolio; Milwaukie, OR: Provided executive oversight for the asset inventory, 10-year life cycle expenditure forecast and facility condition, energy and sustainability assessment consisting of the site systems, exterior and interior building systems, MEP systems and health/fire/life safety systems.

Education B.S., Building Surveying,

University of West England, 2000

Certifications Member of Royal Institution

of Chartered Surveyors (MRICS)

Member, Chartered Institute of Building (MCIOB)

Fellow, Faculty of Building (FFB)

Member, Society for the Protection of Ancient Buildings

Certified Reserved Specialist Faculty of Building CoreNet Global RICS, Royal Institution of

Chartered Surveyors, UK The Society for the Protection

of Ancient Buildings (SPAB)

Chartered Institute of Building (CIOB)

Years of Experience 15

Appendix D ROM Estimate

Capitol View Branch LibraryNew BuildingWashington, D.C.D.C. Public Library Area:Rough Order of Magnitude Date:

Summary

DESCRIPTION TOTAL $/SF %

02 Sitework $998,244 $39.50 11.2%03 Concrete $612,846 $24.25 6.9%04 Masonry $884,520 $35.00 10.0%05 Metals $688,662 $27.25 7.8%06 Woods & Plastics $181,958 $7.20 2.0%07 Thermal & Moisture Protection $866,830 $34.30 9.8%08 Doors & Windows $574,938 $22.75 6.5%09 Finishes $796,068 $31.50 9.0%10 Specialties $214,812 $8.50 2.4%11 Equipment $353,808 $14.00 4.0%12 Furnishings $151,632 $6.00 1.7%13 Special Construction $189,540 $7.50 2.1%14 Conveying Systems $151,632 $6.00 1.7%15 Mechanical $1,405,123 $55.60 15.8%16 Electrical $808,704 $32.00 9.1%

Estimated Direct Construction Cost $8,879,317 $351.35 100.0%

Estimating & Design Contingency 10.0% $887,932

General Conditions & Overhead 12.0% $1,172,070Fee 3.0% $328,180

25,272 gsfOctober 20, 2014

Estimated Construction Cost Award (ECCA) $11,267,498 $445.85

Summary Page 1 of 1

david.saulter
Rectangle