remote handling design progress for the collimation upgrade project keith kershaw en-he 6 june 2011

Download Remote Handling design progress for the Collimation Upgrade project Keith Kershaw EN-HE 6 June 2011

If you can't read please download the document

Upload: cory-benson

Post on 23-Dec-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

  • Slide 1
  • Remote Handling design progress for the Collimation Upgrade project Keith Kershaw EN-HE 6 June 2011
  • Slide 2
  • Contents Introduction refresher (on-going process) Four areas of work as proposed and agreed in 2010 2 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 3
  • First mock up tests remote handling of collimator Collimation Working Group 6 June 2011 Keith Kershaw EN-HE 3 Dummy collimator installed on base using modified truck loader crane fitted with hoist and spreader rotation. Operation with only camera viewing and remote controls
  • Slide 4
  • 4 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 5
  • Reserved space for collimator handling LHCHMUMC_0001 Implications for infrastructure Implications for collimator dimensions It was necessary to modify water pipes 5 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 6
  • Installation using specially designed trailer crane 6 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 7
  • Plug ins: Careful guidance during LHC installation (not ideal for the future) 7 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 8
  • Plug-in behaviour tests 2010 Practical investigations in LHC tunnel mock- up by EN-STI, EN- MME and EN-HE. 8 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 9
  • Water plug - ins 9 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 10
  • Infrastructure P7 (need to pass via TZ76) Collimation Working Group 6 June 2011 Keith Kershaw EN-HE 10
  • Slide 11
  • Passage at point 7 - Improvement of entry to UJ 76. Need to move grille Shorter push-pull bar and push attachment point on Palfinger 11 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 12
  • Palfinger 1000kg trailer - crane Stability tests at 125% Safety checks at the factory Custom design for collimator handling Increased capacity (2x previous) Better control with radio control Flat loading surface (pump underneath) Operation zone at rearend of trailer Asymmetric stabilizers to reduce width 12 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE Spreader beam load test
  • Slide 13
  • EN-HE radioactive collimator handling equipment development work 2010 onwards 1.Optimisation of collimator transfer etc 2.Remote collimator exchange crane vehicle 3.Vacuum disconnection mobile robot 4.Remote Survey (HE part - see Patrick Bestmanns presentation) 13 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 14
  • 1) Optimisation of collimator transfer Improve remote controls on the two existing 500 kg trailer cranes. Compact shielded tractor units to tow the trailer cranes Partially shielded trailers for transporting the collimators (weight of shielding restricted by LHC point 7 lift capacity of 1 tonne) Additional 1000kg capacity trailer crane Minor infrastructure modifications to improve passage. 14 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 15
  • 2) Remote collimator exchange crane vehicle Two remote control vehicles fitted with 1 tonne crane (One + option) Camera viewing system Accessories, mock up tests, infrastructure preparation 15 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 16
  • Collimator remote crane design features 1000kg crane load capacity Support platform for collimator transfer Dimensions compatible with LSS7 Remote control of all movements Powered rotation of spreader Powered extension of stabilisers Powered traction Powered steering Supports to add shielding Manoeuvrability compatible with chicanes at point 7 Powered from monorail in tunnel (MAFI-type trolley) Possible to tow out in event of breakdown 16 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 17
  • Power from monorail Notes : New trolley design needed to allow mounting on continuous monorail Use trolley for overview camera mounting LHC Cryomagnet transport vehicle power trolley and push-pull bar. 17 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 18
  • Collimator remote crane - status Market survey currently with specification committee out this week Conceptual design for specification in progress Specification based on previous trailer cranes Aim for December 2011 Finance committee (1 + option is borderline for FC threshold) Delivery end 2012 18 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 19
  • 3) Vacuum disconnection mobile robot Main items in cost estimate Test equipment and trials Robot with force reflecting master arm Vehicle Cable handling and accessories Plan is based on studies and tests in 2011- 1012 then major purchases of equipment in 2013-2014 19 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 20
  • Collimator connections Turn nuts to release unstructured environment 20 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 21
  • Bellows compressor 21 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 22
  • Vacuum disconnection mobile robot CEA pictures from: Overview of remote handling technologies developed for inspection and maintenance of spent fuel management facilities in France: Philippe DESBATS (CEA-LIST), Grard PIOLAIN (COGEMA-HAG/DMCO), Basic idea for cost estimation: Industrial robot controlled using force-reflecting master arm mounted on remote control vehicle CEA LIST Master arm used with Staubli robot Remote control vehicle (Kuka shown) 22 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 23
  • Collimator remote disconnection development issues Determine level of remote handling sophistication and viewing necessary for task Determine geometrical requirements Navigation and communication issues Review radiation dose implications, risks etc 23 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 24
  • Determine level of remote handling sophistication necessary for task Practical mock-up tests with different remote handling techniques: e.g. master slave force reflecting manipulator, joystick control 24 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 25
  • Determine geometrical requirements Inventory of collimators, 3D models, photos. (eg alignment of flange release nuts) Collect details of tooling Define geometrical restrictions and check against commercial manipulator /robot arms Catia studies 25 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 26
  • Solve mobile platform navigation and communication issues We have obtained EU Marie Curie funding to look into mobile platform issues specific to CERNs radiation environment We are currently designing and will build a mobile test platform for this It will be possible to equip the mobile platform with an arm 26 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 27
  • Disconnection review radiation dose implications, risks etc We have a joint project with RP and have obtained EU Marie Curie funding to look into radiation dose implications of handling scenarios. The collimator exchange will be a major case for this work. Report at end of 2011 bringing together test and study outcomes with intermediate conclusions and way ahead. 27 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 28
  • Remote Survey (HE part) Please see Patrick Bestmanns presentation) 28 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 29
  • Any Questions? 29 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 30
  • Extra slides 30 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 31
  • 31 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE
  • Slide 32
  • 32 Collimation Working Group 6 June 2011 Keith Kershaw EN-HE