quarterly project tracking report - spp.org 2020 spp quarterly project tracki… · this report...
TRANSCRIPT
QUARTERLY PROJECT TRACKING REPORT
Q2 2020
April 2020
Southwest Power Pool, Inc.
REVISION HISTORY
DATE OR VERSION
NUMBER
AUTHOR CHANGE
DESCRIPTION
COMMENTS
4/4/2020 SPP Staff Initial Draft
Southwest Power Pool, Inc.
CONTENTS
REVISION HISTORY .......................................................................................................................................................... I
EXECUTIVE SUMMARY .................................................................................................................................................. 1
NTC PROJECT SUMMARY ............................................................................................................................................ 2
COMPLETED UPGRADES .............................................................................................................................................. 2
NTCS ISSUED .................................................................................................................................................................... 4
PORTFOLIO SUMMARY................................................................................................................................................. 8
PROJECT STATUS SUMMARY .................................................................................................................................. 12
OUT-OF-BANDWIDTH PROJECTS .......................................................................................................................... 13
RESPONSIVENESS REPORT ....................................................................................................................................... 14
ITP20 UPGRADES .......................................................................................................................................................... 16
MORGAN TRANSFORMER PROJECT ..................................................................................................................... 17
APPENDIX 1 .................................................................................................................................................................... 18
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 1
EXECUTIVE SUMMARY
SPP actively monitors and supports the progress of transmission expansion projects, emphasizing the
importance of maintaining accountability for areas such as regional grid reliability standards, firm
transmission commitments, and SPP Open Access Transmission Tariff (OATT) cost recovery.
SPP staff solicits quarterly feedback from the project owners to determine the progress of each approved
transmission project. This quarterly report charts the progress of all SPP transmission projects approved
by the SPP Board of Directors (Board) or through a FERC-filed service agreement under the OATT.
Projects in the current portfolio include all Network Upgrades for which construction activities are
ongoing or those for which construction has completed but not all close-out requirements have been
fulfilled in accordance with Section 13 in Business Practice 70601.
1 SPP OATT Business Practices
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 2
NTC PROJECT SUMMARY
In adherence with the OATT and Business Practice 7060, SPP issues NTCs to Designated Transmission
Owners (DTOs) to begin work on Network Upgrades that have been approved or endorsed by the Board
to meet the construction needs of the OATT or Regional Transmission Organization (RTO).
COMPLETED UPGRADES
Figure 1: Completed Upgrades
NTC ID IN SERVICE
DATE UID OWNER UPGRADE NAME SOURCE STUDY
COST
ESTIMATE
200365 12/20/2019 51406 SPS
Cunningham -
Monument Tap 115 kV
Ckt 1 Rebuild
SPP-2014-AG1-AFS-6 $4,965,782
200366 12/20/2019 51408 SPS Eddy Co. 230 kV Bus Tie SPP-2013-AG3-AFS-6 $19,732,223
200386 12/18/2019 51558 AEP Army Ammo - McAlester
69 kV Ckt 1 Rebuild 2016 ITPNT $11,805,970
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 3
NTC ID IN SERVICE
DATE UID OWNER UPGRADE NAME SOURCE STUDY
COST
ESTIMATE
200395 11/20/2019 51453 SPS
Artesia Country Club -
Artesia Country Club Tap
115 kV Ckt 1 New Line
2016 ITPNT $2,105,492
200446 12/20/2019 61858 AEP Tulsa Southeast - E.61st
138 kV Rebuild 2017 ITPNT $7,238,795
200450 12/30/2019 71938 EREC Roberts County - Sisseton
69 kV New Line 2017 ITPNT $622,432
200457 11/15/2019 51819 SPS
Hockley County
Interchange 115 kV
Terminal Upgrades
SPP-2016-AG1-AFS-3 $195,294
200462 12/19/2019 61894 CPEC East Ruthville - SW Minot
115 kV New Line 2017 ITPNT $13,837,385
200462 12/19/2019 61895 CPEC
East Ruthville - SW Minot
115 kV line Terminal
Upgrades
2017 ITPNT $528,350
200483 1/27/2020 72004 OPPD S1255 - S1260 161 kV Ckt
1 New Line DPA-2017-May-746 $9,435,262
210487 12/11/2019 72005 CPEC North Bismarck 115 kV
Terminal Upgrades SUS-002 $0
210494 1/29/2020 82124 EREC Lakeview 69 kV Capacitor
Bank 2018 ITPNT $1,740,000
210495 12/1/2019 72049 KCPL Olathe - Switzer 161kV
Ckt1 2018 ITPNT $957,000
210496 11/13/2019 61850 SPS
Terry County - LG
Clauene 115 kV Terminal
Upgrades
2018 ITPNT $344,598
210542 11/4/2019 112396 WR Getty East - Skelly 69kV
Ckt 1 Terminal Upgrades 2019 ITP $122,788
11/5/2019 82116 WR
Emporia Energy Center
345 kV Substation GEN-
2015-073 Interconnection
(TOIF)
Generation
Interconnection $1,179,325
11/5/2019 82117 WR
Emporia Energy Center
345 kV Substation GEN-
2015-073 Interconnection
(NU)
Generation
Interconnection $1,037,608
1/20/2020 112300 SEPC Mingo 115kV Substation
GEN-2015-064 (TOIF)
Generation
Interconnection $911,033
1/20/2020 112301 SEPC Mingo 115kV Substation
GEN-2015-064 (NU)
Generation
Interconnection $4,517,777
19 Upgrade(s) Completed $81,277,115
Table 1: Completed Upgrades2
2 In accordance with Section 3.4 of SPP BP 7060, SPP only issues NTC for GI upgrades to affected
Transmission Owners who are not a party to the Generation Interconnection Agreement (GIA).
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 4
NTCS ISSUED
Figure 2: NTCs Issued
NTC
ID
NTC
ISSUE
DATE
UID OWNER UPGRADE NAME SOURCE
STUDY
COST
ESTIMATE
OF NEW
UPGRADES
COST
ESTIMATE
OF
PREVIOUSLY
APPROVED
UPGRADES
210525 11/1/19 112180 OPPD
GEN-2016-115
Interconnection Costs (NU)
(OPPD)
DISIS-2016-
002 $7,553 $0
210538 11/18/19 112403 NPPD Firth Cap Bank 115kV Ckt 1 2019 ITP $570,000 $0
210538 11/18/19 112404 NPPD Firth Substation Expansion 2019 ITP $2,800,000 $0
210538 11/18/19 112366 NPPD Canaday 115 kV Breakers 2019 ITP $2,600,000 $0
210538 11/18/19 112367 NPPD Hastings 115 kV Breakers 2019 ITP $550,000 $0
210538 11/18/19 112368 NPPD Moore 13.8 kV Breaker 2019 ITP $510,000 $0
210539 11/18/19 112369 KCPL Craig 161 kV Breaker 2019 ITP $254,000 $0
210539 11/18/19 112370 KCPL Leeds 161 kV Breakers 2019 ITP $440,000 $0
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 5
NTC
ID
NTC
ISSUE
DATE
UID OWNER UPGRADE NAME SOURCE
STUDY
COST
ESTIMATE
OF NEW
UPGRADES
COST
ESTIMATE
OF
PREVIOUSLY
APPROVED
UPGRADES
210539 11/18/19 112371 KCPL Midtown 161 kV Breakers 2019 ITP $440,000 $0
210539 11/18/19 112372 KCPL Southtown 161 kV Breakers 2019 ITP $880,000 $0
210540 11/18/19 112358 OGE Westmoore 138 kV Breakers 2019 ITP $271,289 $0
210540 11/18/19 112359 OGE Santa Fe 138 kV Breakers 2019 ITP $406,935 $0
210540 11/18/19 112402 OGE
Cleo Corner - Cleo Junction
69kV Ckt 1 Terminal
Upgrades
2019 ITP $16,602 $0
210540 11/18/19 112449 OGE Cimarron - Northwest 345kV
Ckt 1 Terminal Upgrades 2019 ITP $166,504 $0
210540 11/18/19 112450 OGE Northwest - Mathewson 345
kV Terminal Upgrades 2019 ITP $369,869 $0
210541 11/18/19 112433 SPS Hansford - Spearman 115 kV
Rebuild 2019 ITP $828,359 $0
210541 11/18/19 112425 SPS Amoco - Sundown 115kV
Terminal Upgrades 2019 ITP $358,281 $0
210541 11/18/19 112364 SPS Denver City Interchange
North 115 kV Breakers 2019 ITP $3,316,008 $0
210541 11/18/19 112365 SPS Denver City Interchange
South 115 kV Breakers 2019 ITP $2,210,672 $0
210542 11/18/19 112381 WR Bailey - Seneca 115kV Ckt 1 2019 ITP $6,178,207 $0
210542 11/18/19 112382 WR Bailey - Smittyville 115kV
Ckt 1 2019 ITP $8,839,308 $0
210542 11/18/19 112383 WR Marshallville - Smittyville
115kV Ckt 1 2019 ITP $2,618,506 $0
210542 11/18/19 112428 WR
Lawrence Energy Center -
Midland 115 kV Terminal
Upgrades
2019 ITP $30,939 $0
210542 11/18/19 112396 WR Getty East - Skelly 69kV Ckt
1 Terminal Upgrades 2019 ITP $114,821 $0
210543 11/18/19 112451 SEPC Arnold - Ransom 115kV
Terminal Upgrades 2019 ITP $462,000 $0
210543 11/18/19 112452 SEPC Pile - Scott City 115kV
Terminal Upgrades 2019 ITP $1,633,500 $0
210543 11/18/19 112453 SEPC Scott City - Setab 115kV
Terminal Upgrades 2019 ITP $1,556,500 $0
210544 11/18/19 112460 AEP
Sand Springs - Sheffield
Steel 138kV Terminal
Upgrades
2019 ITP $733,520 $0
210544 11/18/19 112488 AEP Pryor Junction 138/115 kV
Transformer 2019 ITP $9,155,167 $0
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 6
NTC
ID
NTC
ISSUE
DATE
UID OWNER UPGRADE NAME SOURCE
STUDY
COST
ESTIMATE
OF NEW
UPGRADES
COST
ESTIMATE
OF
PREVIOUSLY
APPROVED
UPGRADES
210544 11/18/19 112502 AEP Sooner - Wekiwa 345kV
Terminal Upgrades (AEP) 2019 ITP $5,383,105 $0
210544 11/18/19 112389 AEP Tulsa SE - S Hudson 138kV
Ckt 1 Rebuild 2019 ITP $6,724,237 $0
210544 11/18/19 112393 AEP Tulsa SE - 21 St Tap 138kV
Ckt 1 2019 ITP $1,307,802 $0
210544 11/18/19 112360 AEP Riverside Station 138 kV
Breakers 2019 ITP $16,288,000 $0
210544 11/18/19 112361 AEP Southwestern Station 138 kV
Breakers 2019 ITP $4,421,345 $0
210545 11/18/19 112377 WFEC Anadarko 138 kV Breakers 2019 ITP $228,500 $0
210545 11/18/19 112378 WFEC Washita 69 kV Breaker 2019 ITP $52,400 $0
210545 11/18/19 112379 WFEC Mooreland 138 kV Breakers
#2 2019 ITP $822,500 $0
210545 11/18/19 112380 WFEC Mooreland 69 kV Breakers
#2 2019 ITP $128,300 $0
210545 11/18/19 112395 WFEC Gypsum Cap Bank 69kV 2019 ITP $400,000 $0
210545 11/18/19 112435 WFEC East Kingfisher - Kingfisher
138 kV Rebuild 2019 ITP $1,000,000 $0
210545 11/18/19 122577 WFEC Anadarko - Gracemont
138kV Ckt 1 Rebuild 2019 ITP $2,850,000 $0
210545 11/18/19 122597 WFEC Marietta - Rocky Point 69 kV 2019 ITP $5,908,198 $0
210548 12/13/19 112357 OPPD S1260 161/69 kV
Transformer (69 kV)
DPA-2018-
February-841 $1,799,221 $0
210548 12/13/19 102159 OPPD S3761 345 kV Substation DPA-2018-
February-841 $4,610,067 $0
210548 12/13/19 102160 OPPD S3761 - S3455 345 kV New
Line
DPA-2018-
February-841 $17,036,209 $0
210548 12/13/19 102161 OPPD S1361 161 kV Substation
and 345/161 kV Transformer
DPA-2018-
February-841 $9,707,827 $0
210548 12/13/19 102162 OPPD S1260 161/69 kV
Transformer (161 kV)
DPA-2018-
February-841 $1,105,064 $0
210548 12/13/19 102163 OPPD S1209 - S1231 Ckt 2 161 kV
Reconductor
DPA-2018-
February-841 $3,647,471 $0
210548 12/13/19 102165 OPPD S1259 - S1260 161 kV
Rebuild
DPA-2018-
February-841 $2,107,486 $0
210548 12/13/19 102166 OPPD S1255 161 kV Terminal
Upgrades (new breakers)
DPA-2018-
February-841 $654,180 $0
210549 12/13/19 112456 EDE Neosho - Riverton 161kV
Rebuild (EDE)
SPP-2019-
AG1-AFS-2 $28,410,000 $0
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 7
NTC
ID
NTC
ISSUE
DATE
UID OWNER UPGRADE NAME SOURCE
STUDY
COST
ESTIMATE
OF NEW
UPGRADES
COST
ESTIMATE
OF
PREVIOUSLY
APPROVED
UPGRADES
210550 12/13/19 112457 WR Neosho - Riverton 161kV
Rebuild (WR)
SPP-2019-
AG1-AFS-2 $4,046,162 $0
210551 12/31/19 122650 WR Sub - Neosho - Caney River
345 kV Terminal Upgrades SUS-013 $419,116 $0
53 Upgrade(s) Issued
$167,375,730 $0
Table 2: NTCs Issued
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 8
PORTFOLIO SUMMARY
SPP staff solicits quarterly feedback from the project owners to determine the progress of each approved
transmission project. This quarterly report charts the progress of projects approved by the SPP Board or
through a FERC filed service agreement under the SPP OATT. Projects included in the portfolio are:
1. Upgrades required to satisfy requests for transmission service (TS)
2. Upgrades required to satisfy requests for generator interconnection (GI)
3. Approved projects from the Integrated Transmission Planning Assessment (ITP)
4. Upgrades within approved Balanced Portfolios3 (BP)
5. Approved high priority upgrades (HP)
6. Endorsed Sponsored Upgrades (SP)
7. Approved Interregional Projects2 (IR)
8. Approved projects from the 20-Year Assessment (ITP20)
This report will document changes over the previous quarter to report on projects captured in the
Quarterly Project Tracking Portfolio as well as new projects added from various processes listed above. A
summary of the project portfolio is also included.
Figure 3: Total Active Portfolio (Millions)
3 There are currently no Balanced Portfolio or Interregional projects included in Quarterly Project Tracking
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 9
Figure 4: Upgrade by Type Cost Summary4
4 Line mileage not available for all upgrade categories
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 10
Figure 5: Estimated Cost for All Upgrades by In-Service Year
Figure 6: Estimated Cost of Upgrades Completed in Past 4 Quarters5
5 Figures 7 and 8 include Network Upgrades not yet confirmed as completed. Note that the previous
quarter’s updated results are listed as the Transmission Owners may make adjustments to final costs and
status of projects completed during the year.
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 11
Figure
7: Number of Upgrades Completed in Past Four Quarters
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 12
PROJECT STATUS SUMMARY
SPP assigns a project status to all Network Upgrades based on the projected in-service dates provided by
the DTOs relative to the Need Date determined for the project. Project status definitions are provided
below:
Closed Out: Upgrade is operation, all project activities are complete, & all close-out requirements
fulfilled in accordance with Business Practice 7060. These upgrades will not appear in future
Quarterly Project Tracking reports
Complete: Upgrade is operation and all project activities are complete
Delayed: Projected In-Service Date beyond Need Date; interim mitigation provided or project
may change but time permits the implementation of project
Identified: Upgrade identified and included in Board approved study results
In Service: Upgrade is operational, but not all project activities are complete
On Schedule < 4: On Schedule within 4-year horizon
On Schedule > 4: On Schedule beyond 4-year horizon
Re-evaluation: Project active; pending re-evaluation
Suspended: Project suspended; pending re-evaluation
NTC Commitment Window: NTC/NTC-C issued, still within the 90-day written commitment to
construct window and no commitment received
NTC-C Project Estimate Window: Within the NTC-C Project Estimate (CPE) window
Figure 8: Portfolio Project Status (Millions)
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 13
OUT-OF-BANDWIDTH PROJECTS
In adherence to the Business Practice 7060, SPP reports projects that have updated cost values that
exceed their established baseline values based upon a ±20% bandwidth. Variances are determined by
total project cost. The following projects with a cost estimate greater than $5 million were identified as
having exceeded the ±20% bandwidth requirement during the reporting period. Tables below provide
summary information and lists cost detail for out-of-bandwidth projects identified during the reporting
quarter.
PID Project Name Owner NTC
Source Study
Upgrade Type
In-Service Date
31031
Multi - Kummer Ridge - Roundup 345 kV
New Line and Patent Gate and Roundup
345/115 kV Substations
BEPC 2016
ITPNT
Regional
Reliability 9/1/2016
41223 Line - New East Ruthville - SW Minot 115 kV
New Line CPEC
2017
ITPNT
Regional
Reliability 12/19/2019
1036 Line - Soncy convert load to 115 kV SPS 2010
STEP
Regional
Reliability 12/31/2018
1144 XFR - Hitchland 230/115 kV Ckt 2 SPS Ag
Studies
Regional
Reliability 3/29/2017
30875 Line - PCA Interchange - Quahada 115 kV
Ckt 1 Rebuild SPS
2015
ITPNT
Regional
Reliability 2/25/2017
41209
Line - Line -– Republic East – Republic Hines
Street – Republic North – Nichols 69 kV
Reconductor
EDE 2017
ITPNT
Regional
Reliability 4/13/2018
30410 Line - Bowers - Canadian 69 kV Rebuild SPS DPA
Studies
Regional
Reliability 7/1/2015
Table 3: Out-of-Bandwidth Project Summary
PID Baseline Cost
Estimate Baseline Cost Estimate Year
Baseline Cost Estimate
with Escalation
Latest Estimate or Final Cost
$ Variance Variance %
31031 $69,884,000 2016 $69,884,000 $41,871,332 ($28,012,668) -40%
41223 $21,781,000 2017 $22,883,663 $14,365,735 ($8,517,928) -37%
1036 $929,500 2014 $1,025,994 $6,411,523 $5,385,529 524%
1144 $4,087,144 2014 $4,401,407 $7,012,238 $2,610,831 59%
30875 $7,264,308 2015 $7,632,064 $11,174,333 $3,542,270 46%
41209 $6,300,000 2017 $6,457,500 $10,343,040 $3,885,540 60%
30410 $34,999,584 2013 $36,771,438 $28,931,563 ($7,839,875) -21%
Table 4: Out-of-Bandwidth Cost Detail
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 14
RESPONSIVENESS REPORT
The table and figures below provide insight into the responsiveness of DTOs constructing Network
Upgrades within SPP in the Quarterly Project Tracking Report. Note: Network Upgrades with statuses of
“Suspended”, “Re-evaluation”, “Within NTC Commitment Window”, “Within NTC-C Project Estimate
Window”, and “Within RFP Response Window” were excluded from this analysis.
Project Owner
Number of Upgrades
Number of Upgrades Reviewed
Reviewed % In-Service
Date Changes ISD Change % Cost Changes
Cost Change %
AECC 1 0 0% 0 0.00% 0 0%
AEP 57 56 98% 6 10.53% 2 4%
BEPC 23 8 35% 0 0.00% 7 30%
CBPC 1 0 0% 0 0.00% 0 0%
CPEC 3 3 100% 3 100.00% 2 67%
CUS 2 2 100% 0 0.00% 0 0%
EDE 3 0 0% 0 0.00% 0 0%
EREC 3 3 100% 1 33.33% 1 33%
GHP 1 0 0% 0 0.00% 0 0%
GMO 2 1 50% 0 0.00% 0 0%
GRDA 3 1 33% 0 0.00% 1 33%
KCPL 9 8 89% 2 22.22% 2 22%
KPP 1 0 0% 0 0.00% 0 0%
MIDW 5 5 100% 0 0.00% 0 0%
NIPCO 2 0 0% 0 0.00% 0 0%
NPPD 38 0 0% 0 0.00% 2 5%
NWE 2 0 0% 0 0.00% 0 0%
OGE 29 8 28% 6 20.69% 2 7%
OPPD 13 13 100% 0 0.00% 0 0%
SEPC 8 7 88% 2 25.00% 1 13%
SPS 173 173 100% 57 32.95% 70 40%
TBD 10 0 0% 0 0.00% 0 0%
TSMO 2 2 100% 0 0.00% 0 0%
WAPA 10 0 0% 0 0.00% 0 0%
WFEC 35 0 0% 0 0.00% 0 0%
WR 28 25 89% 1 3.57% 5 18%
Total 464 315 67.89% 78 16.81% 95 20.47%
Table 5: Responsiveness Summary
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 15
Figure 9: In-Service Date Changes
Figure 10: Cost Changes
0
20
40
60
80
100
120
140
160
180
200
AEC
C
AEP
BEP
C
CB
PC
CP
EC
CU
S
EDE
EREC
GH
P
GM
O
GR
DA
KC
PL
KP
P
MID
W
NIP
CO
NP
PD
NW
E
OG
E
OP
PD
SEP
C
SPS
TBD
TSM
O
WA
PA
WFE
C
WR
In-Service Date Changes No In-Service Date Change
0
20
40
60
80
100
120
140
160
180
200
AEC
C
AEP
BEP
C
CB
PC
CP
EC
CU
S
EDE
EREC
GH
P
GM
O
GR
DA
KC
PL
KP
P
MID
W
NIP
CO
NP
PD
NW
E
OG
E
OP
PD
SEP
C
SPS
TBD
TSM
O
WA
PA
WFE
C
WR
Cost Changes No Cost Change
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 16
ITP20 UPGRADES
ITP20 assessments were performed in 2010 and 2013. While the projects proposed by those studies are
incorporated into the STEP Project List, they were not included in SPP’s project tracking effort as part of
the Quarterly Tracking Report prior to Q1 2019. A list of active ITP20 projects will be maintained in the
STEP Report and Quarterly Project Tracking Report lists going forward. The current ITP20 projects are
listed in the table below.
Project ID Upgrade
ID Owner Upgrade Name
RTO Determined
Need Date
Latest Cost
Estimate
30401 50492 TBD Cass Co. - S.W. Omaha (aka S3454)
345 kV Ckt1 1/1/2033 $33,126,800
30402 50493 OPPD S3459 345/161 kV Transformer Ckt 2 1/1/2033 $12,600,000
30599 50769 AEP South Fayetteville 345/161 kV
Transformer Ckt1 1/1/2033 $12,600,000
30599 50770 TBD Chamber Springs - South Fayetteville
345 kV Ckt1 1/1/2033 $21,295,800
30600 50771 GMO Maryville 345/161 kV Transformer
Ckt1 1/1/2033 $12,600,000
30601 50772 KCPL Nashua 345/161 kV Transformer
Upgrade Ckt11 1/1/2033 $12,600,000
30602 50773 TBD Keystone - Red Willow 345 kV Ckt1 1/1/2033 $130,141,000
30603 50774 TBD Tolk - Tuco 345 kV Ckt1 1/1/2033 $75,718,400
30604 50775 SEPC Holcomb 345/115 kV Transformer
Ckt2 1/1/2033 $12,600,000
30605 50776 TBD Neosho - Wolf Creek 345 kV Ckt1 1/1/2033 $117,126,900
30606 50777 TBD Clinton - Truman 161 kV Ckt1
Reconductor 1/1/2033 $15,701,325
30606 50778 TBD North Warsaw - Truman 161 kV Ckt1
Reconductor 1/1/2033 $1,082,850
30608 50779 WR Auburn 345/115 kV Transformer Ckt2 1/1/2033 $12,600,000
30608 50780 TBD Auburn - Swissvale 345 kV Ckt1
Voltage Conversion 1/1/2033 $20,112,700
30608 50781 TBD Auburn - Jeffrey EC 345 kV Ckt1
Voltage Conversion 1/1/2033 $35,493,000
30607 50782 OGE Muskogee/Pecan Creek 345 kV
Terminal Upgrades 1/1/2033 $34,605,675
Table 6: ITP20 Upgrades
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 17
MORGAN TRANSFORMER PROJECT
Pursuant to a Joint Operating Agreement and resulting Joint Coordinated System Planning Process
between AECI and SPP, SPP and AECI have agreed to share cost associated with the Morgan Transformer
Project.
Project ID Upgrade
ID Owner Upgrade Name
Projected In-
Service Date
Latest Cost
Estimate
31132 51740 AECI Morgan 345/161kV Transformer 10/31/2020 $6,700,000
31132 51832 AECI Morgan Line Uprate 10/31/2020 $7,050,000
Table 7: Morgan Upgrades
Southwest Power Pool, Inc.
Q2 2020 Quarterly Project Tracking Report 18
APPENDIX 1
(See accompanying list of Quarterly Project Tracking Projects)