spp.org 1. status update for reliability and economic assessments stakeholder meeting september 16,...

25
SPP.org 1

Upload: margaretmargaret-wilkerson

Post on 19-Jan-2016

220 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 1

Page 2: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

Status Update for Reliability

and Economic Assessments

Stakeholder Meeting

September 16, 2008

Austin, TX

Page 3: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 3

Activities Completed Since Last Meeting

• Reliability Assessment

Include 69 kV assessment for 2012 Summer Peak case

Sensitivity with Cottonwood connected to ERCOT

Transfer analysis into ETI as a result of reliability projects

• Economic Assessment

Input assumptions into PROMOD IV revised based on stakeholder comments

Status Quo 2012 and Base Case run with reliability upgrades completed

Page 4: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 4

Reliability Assessment

Page 5: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 5

Reliability Study Cases

• Contingency analysis (N-1) for SPP-ETI system

More stringent reliability criteria in Western Region (N-1, G-1)

Monitored 69 kV and above

• Several potential thermal and voltage violations found

• SPP examined a set of reliability upgrades to mitigate these violations

New 500/230 kV Transformers at Orange County and Cypress

Reconductor nine 138 kV lines in ETI area

• High level planning estimate of projects required to meet SPP Criteria is $115 M

COTTONWOOD IN SPP

Projects to meet SPP Criteria

New Orange County 500/230kV Transformer + Substation work ($50 M)

New Cypress 500/230kV Transformer ($10 M)

Planned Known Projects

ETI Proposed Projects for 2012

Local Reliability projects for Western Region

Transmission Reliability projects from the 2007 approved STEP Plan

ETI Transmission Construction Plan

Page 6: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 6

Reliability Study Cases

• Two Step analysis to assess Cottonwood moving to ERCOT

Identified projects to address Cottonwood exiting SPP (Similar STEP plan, this cost is excluded from Cost/Benefit analysis)

Examined additional reliability projects to address SPP Criteria

• Major projects to meet SPP criteria include

New 500/230 kV Transformers at Orange County and Cypress

Reconductor six 138 kV lines in ETI area

• High level planning estimate of projects required to meet SPP Criteria is $90 Million

COTTONWOOD IN ERCOT

Cottonwood Related Projects

Projects to meet SPP Criteria

Planned Known Projects

ETI Proposed Projects for 2012

Local Reliability projects for Western Region

Transmission Reliability projects from the 2007 approved STEP Plan

ETI Transmission Construction Plan

New Webre – Richard 500kV line ($180 M)

New Orange County 500/230kV Transformer + Substation work ($50 M)

New Cypress 500/230kV Transformer ($10 M)

Page 7: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 7

Cost allocation of ETI Reliability projects

• Reliability projects are required solely to integrate ETI into SPP

• SPP policy is to allocate these costs to the local zone

Similar to current discussion with Nebraska entities

Consistent with treatment with Pre Base Plan funding

• SPP analysis will measure benefits on an equivalent basis

Page 8: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 8

Transfer Capability Assessment into ETI

Page 9: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 9

Transfer Capability Assessment into ETI

• Observations based on Market Power Study

No mitigation needed for case with Cottonwood in SPP

Increase transfer capability into ETI by approx 500 MW in the case with Cottonwood in ERCOT

• Transfer Simulated between the rest of the Entergy and SPP combined into ETI

• Reliability Projects identified in Base Case are considered for this assessment

Series Compensation on Mt. Olive- Hartburg line also considered ($10 M)

• Found approx 460 MW transfer capability as a result of all projects above

• No additional projects recommended at this time

Page 10: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 10

Other Activities In Progress

• Tie Back Analysis to evaluate SPP’s Reliability need for ERCOT QPR option

• Stability analysis performed by independent consultant (Powertech) for SPP QPR and ERCOT QPR study

Page 11: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 11

Economic Assessment

Page 12: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 12

Key Market Assumptions – Status Quo Model

• SPP Market Assumptions

SPP modeled as Day 2 Market planned by SPP Cost Benefit Task Force

System wide unit commitment

System wide treatment of spinning reserve requirements

Security Constrained Unit Commitment and Economic Dispatch

SPP operates as a Single Balancing Authority

• Entergy (including ETI) Operating Assumptions

System wide unit commitment

Security Constrained Economic Dispatch

Reserve Requirements set and met on Entergy System wide basis

ETI Must Run Generation modeled via transmission constraints that represent voltage constraints

ETI and Entergy IPP output consistent with current operations

• Hurdle rates between SPP / other Regions and Entergy / other Regions

Dispatch hurdle 7 $/MWh

Commitment hurdle 25 $/MWh

Page 13: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 13

Key Market Assumptions – Base Model

• SPP Market Assumptions same as Status Quo model

• ETI is a Member of SPP

• ETI Local Area Operating Assumptions same as Status Quo case

• Hurdle rates same as Status Quo except no hurdle rate between SPP and ETI

Page 14: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 14

Benefit Metric – ETI Adjusted Production Cost

• Same Benefit metric being used by the SPP Cost Benefit Task Force in the Future Market Design Study

• Adjusted Production Cost for ETI

Generation Total Variable Cost

+ Purchase Cost at ETI Load-Hub Rate

– Sales Revenue at ETI Generation-Hub Rate

Page 15: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 15

Entergy-TX Hub Prices On-Peak 2012 ($/MWh)

2012 Average On-Peak ETI Load Hub Prices (with Cottonwood in EIC)

80.0090.00

100.00110.00120.00130.00140.00150.00160.00

$/M

WH

Base Case

Status Quo

2012 Average ETI Load Hub Prices With Cottonwood in ERCOT

90.00

100.00

110.00

120.00

130.00

140.00

1 2 3 4 5 6 7 8 9 10 11 12

$/M

WH

Base Case

Status Quo

Page 16: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 16

Transmission Congestion Impact on ETI Load Hub

• Status Quo – impact on $/MWH

Inland – Hartburg line under contingency

24.05 (Cottonwood in ETI) and 12.89 (Cottonwood in ERCOT)

Mt. Olive – Hartburg line under contingency

5.07 (Cottonwood in ETI) and 10.81 (Cottonwood in ERCOT)

Mabel line under contingency

-1.74 (Cottonwood in ETI) and -1.60 (Cottonwood in ERCOT)

Page 17: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 17

Transmission Congestion Impact on ETI Load Hub

• Base Case – impact on $/MWH

Inland – Hartburg line under contingency

4.11 (Cottonwood in ETI)

Mt. Olive – Hartburg line under contingency

6.96 (Cottonwood in ETI) and 6.84 (Cottonwood in ERCOT)

Wyatt – Parnell under contingency

6.80 (Cottonwood in ERCOT)

McAdam line under contingency

4.05 (Cottonwood in ETI)

Page 18: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 18

2012 Benefits to ETI

Millions of $

Benefit to ETI of joining SPP

Base Case with Cottonwood in

ERCOT

Status Quo with Cottonwood in

ERCOT

Base Case with

Cottonwood in Eastern

Interconnect

Status Quo with Cottonwood in

Eastern Interconnection

Benefit with Cottonwood in

ERCOT

Benefit with Cottonwood in

Eastern Interconnection

2012 2,454.65 2,621.93 2,355.08 2,491.43 167.28 136.35

Jan 197.35 216.41 193.66 206.57 19.06 12.91 Feb 159.27 176.49 161.74 173.51 17.22 11.77 Mar 159.88 186.48 168.26 178.67 26.59 10.42 Apr 159.37 181.61 157.93 173.32 22.24 15.39 May 203.91 212.83 192.56 205.54 8.92 12.98 Jun 240.24 243.55 219.39 228.25 3.31 8.87 Jul 277.66 276.01 251.32 257.23 (1.66) 5.90 Aug 287.17 287.03 254.50 266.61 (0.14) 12.12 Sep 217.72 228.79 204.00 216.44 11.08 12.44 Oct 178.59 198.32 177.69 192.74 19.74 15.05 Nov 173.07 192.92 173.18 185.31 19.85 12.13 Dec 200.43 221.49 200.85 207.23 21.06 6.38

Millions of $

Page 19: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 19

SPP Load Hub Prices On-Peak 2012 ($/MWh)

2 - 7% increase if ETI joins

SPP Load Hub Prices

60.00

70.00

80.00

90.00

100.00

110.00

$/M

WH

Status Quo:Cottonwood in SPP

Status Quo:Cottonwood in ERCOT

Base: Cottonwood inSPP

Base: Cottonwood inERCOT

Page 20: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 20

2012 SPP Generation Impact of ETI Joining SPP (Cottonwood in Eastern Interconnection)

Benefit to SPP of ETI joining if Cottonwood stays in Eastern Interconnection

Base Case Status QuoGeneration

Change Base Case Status QuoGeneration

Cost Change

2012 184,534.44 184,428.67 (105.77) 7,050.91 7,224.31 173.40

Jan 15,207.31 15,132.07 (75.25) 481.56 490.49 8.93 Feb 12,872.04 12,698.48 (173.55) 393.60 393.16 (0.44) Mar 13,420.91 13,205.33 (215.59) 481.70 474.84 (6.85) Apr 12,865.27 12,789.34 (75.92) 414.21 423.84 9.64 May 15,002.93 14,963.97 (38.96) 526.40 543.88 17.48 Jun 16,833.63 17,040.57 206.94 724.18 757.52 33.35 Jul 19,753.94 20,039.96 286.02 938.64 980.28 41.64 Aug 20,411.53 20,622.01 210.48 957.40 989.44 32.04 Sep 16,654.22 16,774.30 120.07 620.45 646.43 25.98 Oct 13,938.54 13,749.18 (189.36) 508.40 507.57 (0.83) Nov 13,069.52 12,962.54 (106.99) 514.96 514.09 (0.88) Dec 14,504.60 14,450.92 (53.67) 489.42 502.76 13.34

Generation (GWH) Generation Costs(millions $)

Page 21: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 21

2012 Benefits to SPP of ETI Joining SPP

Benefit to SPP of ETI joining SPP

Base Case with Cottonwood in

ERCOT

Status Quo with Cottonwood in

ERCOT

Base Case with

Cottonwood in Eastern

Interconnect

Status Quo with Cottonwood in

Eastern Interconnection

Benefit with Cottonwood in

ERCOT

Benefit with Cottonwood in

Eastern Interconnection

2012 7,652.40 8,432.43 7,750.26 8,309.27 780.03 559.01

Jan 478.57 562.43 500.11 552.51 83.86 52.40 Feb 417.61 487.13 432.00 484.37 69.52 52.36 Mar 478.75 549.39 495.98 542.56 70.64 46.57 Apr 411.08 490.88 422.25 483.35 79.79 61.10 May 541.51 623.02 560.00 615.95 81.51 55.95 Jun 825.12 877.14 824.83 861.09 52.02 36.26 Jul 1,090.72 1,131.42 1,079.13 1,114.35 40.71 35.22 Aug 1,092.75 1,132.41 1,077.42 1,114.74 39.67 37.31 Sep 666.21 731.06 672.30 718.64 64.85 46.33 Oct 541.00 605.18 551.61 600.77 64.18 49.16 Nov 581.59 634.05 593.04 625.96 52.46 32.92 Dec 527.49 608.31 541.57 594.98 80.82 53.41

Millions of $

Page 22: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 22

Discussion of Findings - ETI• Summary of Production Cost Analysis

$136.3 million in lower annual production costs to ETI area with Cottonwood in SPP

$167.3 million in lower annual production costs to ETI area with Cottonwood in ERCOT

Lower production costs driven by decline in ETI generation as ETI purchases more from SPP

Production Cost benefit greater in non-summer months due to lower seasonal demand allowing SPP lower cost generation to serve more ETI load

Major transmission congestion in Mt. Olive/Hartburg/Inland area and around Wyatt/Parnell had major impact on ETI hub prices

• Entergy – TX hub prices for load decline with inclusion of ETI into SPP about 12 - 20%

• Cottonwood reduces Entergy – TX load hub prices but lowest Entergy – TX load hub prices occur with ETI in SPP and Cottonwood in SPP

Page 23: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 23

Discussion of Findings – SPP• SPP/ETI generation increases but overall variable generation

costs are lower by $173.4 million (if Cottonwood in EIC) due to more efficient commitment and dispatch

• SPP benefits due mostly to changes in load and generation hub prices which drive the cost of purchases and sales revenues

• SPP benefits more if Cottonwood is not included

$559.0 benefit with Cottonwood in SPP

$780.3 million benefit with Cottonwood in ERCOT

• SPP Load hub prices increase slightly with inclusion of ETI in SPP, about 2 - 7%

Page 24: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 24

Questions?

Page 25: SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX

SPP.org 25

Mak NagleManager, Technical Studies & Modeling(501)[email protected]