Project Update
April 8, 2013
Utility Projects
City of Houston Interconnect
Alice Street Water Plant • GST demolition completed • Punch list completed • Closing out contracts
• Completed installation and training for disk filters, currently in testing period
• Clarifier equipment delivered • Project will be substantially complete in
June
Longwood WWTP Rehabilitation
• Thickener sludge removed • Cost issue with sludge removal • Thickener bridge and equipment installed • New centrifuge is nearly complete • Installation of thickener mechanism at Tank
1 & 2 complete • Substantial Completion by the end of April
Barry Rose WWTP Rehabilitation
• Engineer preparing 100% PS&E submittal for signature
• Monitored utility relocations • Finalized segment alternatives due to cost
increases • Submitted plans for BDD4 approval • Construction manager completed constructability
review
Hatfield Basin Trunk Sewer
• Initial lift station start up and testing performed • Started service connections along Bishopton
Circle
Twin Creek Regional Lift Station
Far Northwest Wastewater Treatment Plant Improvements
• Notice to Proceed issued February 18th • Engineer reviewing submittals • Preliminary electrical work started • Public Works requested that the sand filter be added
to project • Sand filter materials ordered and added to
construction project
Old Alvin 20” Waterline
• All parcels/easements acquired • Consultant continued plan revisions and utility
coordination reviews • Constructability review complete • Issue with radio tower at Public Works Service
Center identified
• Engineer modified Drainage Report based on BDD4 comments
• Construction cost estimate being revised for the waterline and roadway
• Draft Geotechnical Report being prepared for review
• Staff reviewing the Waterline Plan and Profile sheets
McHard Road 16” Water Line & Roadway PER
Drainage Projects
Diversion Ditch • Excavation activities continued for diversion channel • Phase II slope paving activities continue
Cowart Creek Diversion
Pump Station • Electricity installed • All weather access installed • Start up in 1-2 weeks Re-grading of Roadside Ditches • Consultant working on plan revisions
Cowart Creek Diversion (cont’d)
• TxDOT approved permit • BDD4 has approved • Currently out for bids
Westchester Sidewalk and Drainage
• PER 95% complete and gravity pond option selected
• Consultant must re-run storm water models with gravity pond to complete PER
Cullen Regional Detention
Facility Projects
• Project is substantially complete • Approximately 1 month ahead of schedule • Furniture/shelving installation underway
Westside Library
• Demolition is complete • Framing complete • Sheetrock is 95% complete and electrical is 75%
complete • Roof repair is 75% complete, plumbing is 50%
complete and ductwork is 25% complete • Relocated Fire & EMS personnel to complete the
renovations
Old PD Renovations
• Programming & Schematic nearing completion • Working on site restrictions • Programming has resulted in a station slightly
larger than 10,000 SF
Fire & EMS Station #3
Parks
• Contractor increased resources to accelerate Pond excavation and fill placement
• Initiated construction of the Pond weir and outfall slope paving
• Completed water line along Hughes Ranch Rd • Completed roadway connection at Stone Road • Initiated concrete pavement placement for Hughes Ranch
Rd • Staff completed review of 90% Sports Complex PS&E
package
Hickory Slough Detention at Max Road & Max Road Sports Complex, Phase I
• Funding requested for geotechnical investigations • Obtained geotechnical investigation proposal for
borings needed for boardwalk foundations • Consultant preparing 90% plans • Legal, Parks, & Projects working with County on
agreement for available CIAP grant funding
Trails at JHEC
• Southgate grand opening held on February 23rd • Substantial and final punch list complete • ADA inspection complete
South Gate & Cypress Village Parks
• Consultant presented preliminary site layout • Site has significant floodway and floodplain
challenges • Staff is reviewing and providing comments on
the site layout
Shadow Creek Ranch Park
Roadway Projects
Thoroughfare Plan Update
• Workshop in April 22nd • Adoption in May
• Jamison Middle School – New driveway installed
• Rustic Oaks Elementary School – Plan in place – City fulfilled our obligation – PISD & Brazoria County working out details &
Interlocal for the work
PISD School Issues
• Carleston Elementary School – PW working on plan to enclose ditch and provide
additional paving – Scheduling work for this summer
PISD School Issues
• Engineer submitted 90% plans • TxDOT reviewing Categorical Exclusion (CE)
documents, drainage report and 90% plans • Environmental documents scheduled to be
completed in early April • Staff attended meeting at TxDOT regarding
schedule of the project, work to complete and estimated letting date
Pearland Parkway
• Main project submittal have not been approved • Siemens has not addressed controller issues • Contractor to submit alternate controller
ITS Project
• Kickoff meeting held with TxDOT • Initial meeting with TxDOT environmental to plan
public meeting
Max Road
• TxDOT reviewing design contract
Fite Road
• Bridge is complete and contractor is pouring the outside lane curb and median curbs
• Subcontractor installed the street light poles and electrical services along east side and performing final grading in those areas
• Switch to new lanes this month
Cullen Parkway – Phase II
• Acquisition negations/proceedings continued • Clearing and Grubbing contract awarded to W. M.
Jones at the February 11th City Council meeting
Bailey Road
• Drainage installation is approximately 98% complete • Paving operations to begin this week
Business Center Drive
• Paving activities continue to progress towards the north
• Contractor working on driveways and sidewalks on the northbound side of road between FM518 and Orange St.
• Bridge piers were poured at the Hickory Slough bridge and contractor has begun working on bents and abutments
SH35 – BW8 to FM518
• TxDOT Area Office has approved the City’s plans for modifications to the Crossing for the Quiet Zone
• Project advertised on April 3rd, scheduled Bid Opening on April 25th
Quiet Zone Railroad Crossing
2013-2016 TIP Call for Projects • What is a TIP? • Schedule • Process • Federal Funding Availability • Eligibility, Rankings, & Selection • Funding Scenarios
Transportation Improvement Program
What is a TIP? • Transportation Improvement Program • 4 year program of transportation projects for the 8
County H-GAC Area • Assigns federal, state & local funding to projects • Implementation device for long range plan (RTP) • Multimodal, multijurisdictional • Approved by Transportation Policy Council
2013-2016 TIP Call for Projects
• Schedule: – 5/30/12 HGAC TIP Workshop – 6/5/12 Meeting with HGAC Staff – 7/23/12 Council Resolution supporting the projects – 8/1/12 Project Submittal due to HGAC – 12/21/12TPC Approval of 2013-2016 TIP Projects
(Original Date) – 4/26/13 TPC Approval of 2013-2016 TIP Projects
2013-2016 TIP Call for Projects
• Eligible Projects – In the 2035 RTP – Air Quality Conformity Year must be 2019 or earlier – Be able to meet the ‘readiness’ schedule for the funding
year – Environmental, ROW, Design, Utilities, local commitment
• Project sponsors required to ‘Self Evaluate’ projects
• Staff evaluated all Pearland projects that are in the 2035 RTP for AQ Conformity and Readiness
2013-2016 TIP Call for Projects
2013-2016 TIP Call for Projects Submittal Project Name
Limits Funding Year
Total Project Cost
City Contribution
TxDOT Contribution
Smith Ranch Rd/CR94
Hughes Ranch to Broadway
2015 $4,984,489 $996,898 $3,987,591
Bailey Rd Veterans Dr to FM 1128 2015 $27,664,720 $5,532,944 $22,131,775
Mykawa Rd BW8 to FM 518 2016 $22,225,000 $4,445,000 $17,780,000
McHard Rd Ext
Cullen to Mykawa 2016 $41,155,664 $8,231,133 $32,924,531
CR 403 CR94 to Cullen 2014 $21,928,000 $4,385,600 $17,542,400
CR 48/ Kingsley
BW8 to Clear Creek 2016 $11,362,000 $2,727,400 $9,089,600
Max Rd Ext Future McHard Road to Hughes Ranch
2016 $7,589,907 $1,517,981 $6,071,926
Shadowcreek Ranch Trail
East of Kingsley to Kirby Dr
2016 $1,935,458 $387,091 $1,548,366
Green Tee Terrace Trail
FM 518 along Clear Creek to Barry Rose Rd
2016 $4,173,938 $834,787 $3,339,150
• Projects Ranked on: – Readiness
• Preliminary Design • ROW • Environmental • Utility Adjustments • Local Commitment of Funds (Council Resolution)
– Planning Factors • Congestion Relief • Regional Impact • Mobility & Air Quality • Safety & Security • Access Management
– Benefit/Cost Analysis
2013-2016 TIP Call for Projects
• H-GAC provided a list based on the rankings with projects in three tiers: 1st Tier: Funding Recommendation Likely 2nd Tier: Funding Recommendation Possible 3rd Tier: Funding Recommendation Unlikely
• Final recommendations will consider the availability of
funds, project eligibility for funding, and input gained during public involvement.
2013-2016 TIP Call for Projects
2013-2016 TIP Ranking/Scoring Project Name Current
Rank Federal Funds Requested
“Ready” Fiscal Year
Planning Factor Score
B/C Score
Total Score
McHard Rd Ext
#9 “Likely”
$32,924,531 2016 76 75 76
Smith Ranch Rd/CR94
#13 “Likely”
$3,987,591 2016 79 60 70
Mykawa Rd #22 “Possible”
$21,683,536 2016 72 53 63
Bailey Rd #23 “Possible”
$18,926,465 2015 71 51 61
CR 403 NA $17,542,400 Not Ready
CR 48/ Kingsley
NA
$7,968,800 Not Ready
Max Rd Ext NA $6,396,424 Not Ready
Shadowcreek Ranch Trail
#16 “Possible”
$1,299,804 2016 69 46 66
Green Tee Terrace Trail
#17 “Possible”
$2,656,253 2016 65 43 60
• Funding Recommendation Factors: – Project Evaluation (Scores) – Input from Public Comment Period – Closed April 5th – Availability of Funds
• Project readiness (Timing) • Eligibility of project activities
2013-2016 TIP Call for Projects
Scenarios: 1. McHard, Smith Ranch, SCR Trail receive
funding – Matching funds required: $9,615,122 2. Mykawa also receives funding – Matching funds
required: $14,060,122 3. Bailey also receives funding – Matching funds
required: $19,593,066
2013-2016 TIP Call for Projects
Scenario 1: McHard, Smith Ranch & SCR Trail
2013-2016 TIP Call for Projects
Matching Funds Required
Fiscal Year 2014 2015 2016 2017 TOTAL
Matching Funds 369,747 265,020 1,719,762 7,260,593 9,615,122
GO Bonds Scheduled & Available in 2013-2017 CIP by Fiscal Year
Project 2013 & 2014 2015 2016 2017 Total
McHard Road - - - - -
Smith Ranch Road 4,984,490 - - - 4,984,490
SCR Trail - - - - -
Hughes Ranch/CR403 - 1,065,000 4,172,600 - 5,237,600
Total 4,984,490 1,065,000 4,172,600 - 10,222,090
Scenario 2: McHard, Smith Ranch, SCR Trail & Mykawa
2013-2016 TIP Call for Projects
Matching Funds Required
Fiscal Year 2014 2015 2016 2017 TOTAL
Grand Total 732,171 265,020 2,269,638 10,793,294 14,060,122
GO Bonds Scheduled & Available in 2013-2017 CIP by Fiscal Year
Project 2013 & 2014 2015 2016 2017 Total
McHard Road - - - - -
Smith Ranch Road 4,984,490 - - - 4,984,490
SCR Trail - - - - -
Mykawa Road 2,707,318 10,262,032 643,650 13,613,000
Hughes Ranch/CR403 - 1,065,000 4,172,600 - 5,237,600
Total 4,984,490 3,772,318 14,434,632 643,650 23,835,090
Scenario 3: McHard, Smith Ranch, SCR Trail, Mykawa &Bailey
2013-2016 TIP Call for Projects
Matching Funds Required
Fiscal Year 2014 2015 2016 2017 TOTAL
Grand Total 816,246 782,662 7,200,865 10,793,294 19,593,066
GO Bonds Scheduled & Available in 2013-2017 CIP by Fiscal Year
Project 2013 & 2014 2015 2016 2017 Total
McHard Road - - - - -
Smith Ranch Road 4,984,490 - - - 4,984,490
SCR Trail - - - - -
Mykawa Road 2,707,318 10,262,032 643,650 13,613,000
Bailey Road 5,159,632 10,393,000 5,800,423 21,353,055
Hughes Ranch/CR403 - 1,065,000 4,172,600 - 5,237,600
Total 4,984,490 8,931,950 24,827,632 6,444,073 45,188,145
Funding Conclusions: • Existing CIP funds will cover matching
funds • No additional debt service rate increase
beyond existing projections • Opportunity to sell less debt or reallocate
2013-2016 TIP Call for Projects
Project Update
Questions/Comments
April 8, 2013