purpose to update the existing master plan to present development options for the airport to create...
TRANSCRIPT
PurposeTo update the existing master planTo present development options for
the airportTo create an airport layout plan to
document current and future airport conditions
To provide information and strategies for obtaining funding
Master Plan Components Inventory Aviation activity forecasts Demand/Capacity assessment Facility Requirements Airport alternatives and development
plan Airport layout plan Financial plan Public Involvement Environmental overview
Public InvolvementOngoing meetings with County staff
and airport representativesStakeholder meetings (5/9 and 5/23)Advisory committee meeting (6/18)Public meeting (7/11)Advisory committee meeting (8/6)Board workshop (11/7)Board action (December/January)
Development OptionsNo buildMake full improvements to existing
airport per the ALPPhased development per the ALPTransfer ownership and management
of airport to TarpineRelocate the airport
Things to Think AboutCurrent airport activityAlmost entire airport is in new FEMA
V-Zone (special flood hazard area)Benefits and costs of airports
No Build Option Not a true “do nothing” option– County would still need to remove runway
safety area intrusions to remain compliant with FDOT standards (trees, building, berms, poles, etc.)
– To remain compliant there would still be land acquisition needed and site modification costs
– Existing drainage issue repair– Would likely lead to temporary closure of the
airport during the time needed to complete the improvements
– Airport must implement recommendation to remain open and operational
Airport Layout Plan
Airport at Full Build OutPaved runwayFuel facilitiesThree T-hangar buildings (30 T-hangars,
one of which is a maintenance facility)Airport office/FBODesignated helipadConservation easement and noise
bufferSecurity fencing, lighting, and gates
Full Development OptionFull development of all recommended
enhancements (estimates):– Runway - $3,400,000– Land acquisition (includes existing T-hangar building) -
$1,000,000– Hangars (two 10 unit hangars) - $1,000,000– Environmental - $120,000 to $200,000– Fuel facility - $80,000– Total Cost: $5,600,000 phased out over
several years
Phased Development OptionSimilar to full development, but phased over time based on performance of the airport
Phase I– Land acquisition– Total cost: $1,000,000
Phase II (income generating)– Fuel facility– T- hangars– Total Cost: $1,080,000
Phase III– Environmental– Design– Construction– Office/FBO– Total Cost: $5,600,000 phased out over several years
Potential Monthly RevenuesAmount Income Assumptions
Fuel (profit/gallon) 4,000 gallons $2,000 assumes $0.50 profit per gallonHangar Rent (including expenses) 20 hangars $3,500 assumes $175.00 monthly rentalLanding Fees 50 Units $2,500 assumes $50.00 monthly feeBusiness Fees Business Development $3,000 assumes $1,500.00 monthly business fee*
Total Monthly Income: $11,000Total Yearly Income: $132,000
* Business fees may change with market conditions
Based on full build-out and values from similar airports
At full build out Fuel price and quantity based on values seen at Quincy Municipal Airport Rent price based on averages seen at similar airports in north Florida Landing fees based on rate discussed with airport manager Business rental fees (Maintenance Facility)
Potential Monthly Expenses
Expenses Cost per MonthUtilities $1,600.00
Part-time Employee (20 hours a week at $25,000 per year) $1,041.67Insurance $1,250.00Maintenance $2,500.00Legal $200.00Office Supplies $1,000.00Random $1,000.00
Monthly Total: $8,591.67Yearly Total: $103,100.00
Based on values from similar airports
Revenue $132,000 – Cost $103,100 = $28,900(at full build-out)
Transfer Airport to Tarpine Option Tarpine, County, and heirs would work out
details of transfer of ownership Airport would become private– Two options:
• Privately Owned, Private-Use Airport• Privately Owned, Public-Use Airport
Approved by FDOT and FAA– Must meet site approval and registration
requirements– Must be in compliance with Chapter 330, F.S. and
Chapter 14-60, F.A.C.– Costs associated with transfer of ownership
Privately Owned, Private-Use Airport Would be owned by the Tarpine
Community There is no requirement for inspection or
licensing (14-60.007, F.A.C.), the airport just needs to be reviewed for site approval and register with FDOT
Tarpine community would be in charge of ownership and maintenance
Tarpine would also pay for costs of improvements
Privately Owned, Public-Use Airport Would be owned by Tarpine, but would
still be open to the public for use Would still need to comply with Florida’s
inspection and licensing requirements (14-60.007, F.A.C.)
Essentially the same a public airport, but the Tarpine community would be in charge of ownership and maintenance
Tarpine would also pay for costs of improvements
Relocation OptionConsists of closing one airport and
opening anotherWould still need to address transfer of
ownership of the old airportCost would be far greater than
proposed developmentAirport would take years to open
Area Airports
Relocate – Airport Comparisons Wakulla County Airport
– 2,572 x 69 foot runway– 12 acres– Revenue $1,320.00 – Cost $3995.38 = (-$2,675.38)– Information received from Greg James, Finance Director, Wakulla County for FY 12/13
Carrabelle– 4,039 x 75 foot runway– 202 acres– Revenue $28,400 – Cost $27,744 = $656.00– Information received from Courtney Dempsey, City Administrator, City of Carrabelle for FY 12/13
Quincy– 2,684 x 75 foot runway– 212 acres– Revenue $236,097.71 – Cost $260,243.48 = (-$24,145.77)– Information received from Janice Watson, Airport Administrator, Quincy-Gadsden Airport Authority
for FY 12/13 through May
Considerations for Relocation Site Selection – 2 years, $200,000 to $300,000
– Tall structures– Schools
Environmental – 3 to 5 years, $1,500,000 Compatible land uses (i.e. residential) Design – 2 years, $2,500,000 Construction – 2 year, $10,000,000
– 3 T-hangars - $1,500,000– 1 maintenance hangar - $500,000– Office - $250,000– Parking - $250,000
Total cost: $16,000,000 +/- over approximately 12 years– These represent planning level cost estimates, values
may change
Options for Board ActionNeed direction for completion of
Master Plan and coordination with FDOT– Do nothing– Make full improvements– Phased development– Wakulla/FDOT assist Tarpine in taking over– Relocate
Next StepsBoard directionSubmit master plan to FAA and FDOTBoard action